Make Whole Payment Cost Allocation for Resources Committed for Reliability in the Day Ahead Market

This is the fast tracked temporary fix to better allocate DA operating reserves for units called on for reliability. This issue also includes in it the OATT and manual language for the issue: “Compensation of Make Whole Payments to Automatic Load Rejection (ALR) Black Start Units”

Proposed Timeline

Issue initiated: 11.27.2012
Work begins: TBD
Target Completion: 2.1.2012
Actual Completion: TBD

Issue Details

Stakeholder Body Members Committee
Issue Catalyst PJM
Issue Status Closed
Manual Changes No
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Not Started Approved
  • Not Started Education
  • Not Started Interest
  • Not Started Design
  • Not Started Options
  • Not Started Packages
  • Not Started Consensus
  • Not Started Review
  • Not Started Completed