Unit types not Addressed by Manual 15

This issue concerns Lack of cost development guidelines for non-fossil steam units (biomass or solid waste), run-of-river hydroelectric units, wind units, solar units or energy storage units. There is no adequate basis currently to evaluate the cost based offers of these units. A process to clearly delineate the actual components of cost for these unit types needs to be developed.

Proposed Timeline

Issue initiated: 2.23.2011
Work begins: TBD
Target Completion: 4.1.2013
Actual Completion: TBD

Issue Details

Stakeholder Body Markets and Reliability Committee
Issue Catalyst Manual 15 rewrite/ IMM
Issue Status Closed
Manual Changes No
  • Stakeholder Process Step

  • Not Started Approved
  • Not Started Education
  • Not Started Interest
  • Not Started Design
  • Not Started Options
  • Not Started Packages
  • Not Started Consensus
  • Not Started Review
  • Not Started Completed