Committees & Groups

Issue Details

Multi-Driver Approach for Planning

Multi-Driver Project is a transmission enhancement or expansion that addresses more than one of the following: reliability violations, economic constraints, or Public Policy Requirements.  The multi-driver approach principles provide PJM planning methods to develop multi-driver project combinations as part of annual RTEP.  Tariff and OA revisions include adding Multi-driver project definition and new MDA section 1.5.10 (Schedule 6 of OA)

Proposed Timeline

Issue initiated: 2.1.2011
Work begins: 2.14.2013
Target Completion: TBD
Actual Completion: 11.12.2014

Issue Details

Stakeholder Body Regional Planning Process Task Force
Facilitator Sims, Mark
Subject Matter Expert Barrett, Fran S.
Issue Status Closed
Manual Changes Yes
Agreement Changes Open Access Transmission Tariff, Operating Agreement
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed