Committees & Groups

Issue Details

Enhancements to Deactivation Rules

Given the anticipated volume of generation resource retirements expected in the coming years, this issue will evaluate the general deactivation process and the provisions of Part V of the Tariff, including a focus on compensation, the deactivation notification timeline and transparency.

Proposed Timeline

Issue initiated: 9.20.2023
Work begins: 10.12.2023
Target Completion: 5.17.2024
Actual Completion: TBD

Issue Details

Stakeholder Body Deactivation Enhancements Senior Task Force
Facilitator Hendrzak, Chantal Aimee N.
Subject Matter Expert Zhang, Michael
Problem Statement/
Issue Charge First Read
7.26.2023
Issue Catalyst PJM and IMM
Issue Status Solution Alternatives Proposed
Manual Changes No
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • In Progress Options
  • Not Started Packages
  • Not Started Consensus
  • Not Started Review
  • Not Started Completed