Designated Entity Design Standards

For Greenfield projects that are designated as a result of the competitive process, the Designated Entity may follow design standards that differ from those of the zonal transmission owner. Questions were raised at Planning Committee, Transmission Expansion Advisory Committee and Lessons Learned regarding the potential for introducing a weak point in the system or reducing the reliability by lest robust solutions. Feedback provided by stakeholders consisted of the following items:
  • Ensure new project does not reduce the performance
  • Consideration of physical geography and environment
  • Consideration of other local requirements or codes
  • Well integrated protection  
  • Robustness of physical construction
  • Emergency Restoration
  • Future considerations
  • Proposed Timeline

    Issue initiated: 7.9.2015
    Work begins: 8.13.2015
    Target Completion: TBD
    Actual Completion: TBD

    Issue Details

    Stakeholder Body Designated Entity Design Standards Subcommittee
    Facilitator Glatz, Suzanne E.
    Subject Matter Expert Herman, Michael
    Issue Catalyst FERC Order 1000
    Issue Status Closed
    Manual Changes Yes
    • Stakeholder Process Step

    • Completed Approved
    • Completed Education
    • Completed Interest
    • Completed Design
    • Completed Options
    • Completed Packages
    • Completed Consensus
    • Completed Review
    • Completed Completed