External Capacity Performance Enhancements

Since the November 18, 2015 Joint and Common Markets (JCM) committee meeting, PJM has discussed various internal (PJM) and external (MISO and other external entities) operational, markets and planning challenges associated with the integration of external Capacity Performance (CP) resources into PJM. In an attempt to reconcile these challenges, PJM believes there is a need to implement enhancements to its external CP resource evaluation construct.   Specifically, the Task Force will explore a comprehensive solution to address external CP resource complications regarding: 1) Operational, reliability and compliance risks associated with network model expansion;  2) Congestion management challenges and compliance risks resulting from the delivery of external capacity and energy;  3) Transmission service evaluation process and planning requirements for external resources; and 4) Operational impacts on neighboring systems resulting from an external entity committing and dispatching resources in their footprint.

Proposed Timeline

Issue initiated: 5.26.2016
Work begins: 6.2.2016
Target Completion: TBD
Actual Completion: TBD

Issue Details

Stakeholder Body Underperformance Risk Management Senior Task Force
Subject Matter Expert Perera, Asanga
Issue Catalyst PJM
Issue Status Closed
Manual Changes Yes
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed
3.9.2017 -Filing-
Docket No. ER17-1138-000  PDF
5.26.2017 -Filing-
Docket No. ER17-1138-000  PDF