Performance Impact of multi-schedule model in Market Clearing Engine (MCE) in nGEM Enhanced Combined Cycle (ECC) and Energy Storage Resource (ESR) models

Addressing the performance impact due to multi-schedule model in the MCE with nGEM ECC and ESR model and make necessary changes to reduce the impact.

Proposed Timeline

Issue initiated: 3.8.2023
Work begins: 3.30.2023
Target Completion: 8.1.2023
Actual Completion: 10.25.2023

Issue Details

Stakeholder Body Market Implementation Committee
Facilitator Militello, Nikki
MIC Approval Date 10.25.2023
MRC Approval Date 11.15.2023
Problem Statement/
Issue Charge First Read
12.7.2022
Issue Catalyst PJM
Issue Status Awaiting Implementation & FERC Approval
Manual Changes No
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed