Manual 3 - Transmission Operations pdfPDF
Revision 38
Effective Date: 04.27.2011
Revision 38 (04/27/2011):
Throughout – Formatting changes to tables to meet with current PJM style set.
Throughout – Replaced references to “Conectiv” with “PHI – Pepco Holdings, Inc.” or “AE-PHI” where appropriate.
Throughout – Replaced references to “Orange” with “Maliszewski” wherever the reference was to the former “Orange” 765/138kV substation within AEP.
Section 1.3 – Note added regarding TO requirements for real-time network analysis within Transmission Operations Guidelines.
Section 2.1 – Revised wording for Note1 from “may operator” to “may operate” within Thermal Operating Criteria section.
Section 2, end – Revised wording for Exhibit 1 PJM Actual Overload Thermal Operating Policy table from a Guideline to a Policy and revised text within said table to correspond with Load Shed Determination Procedure.
Section 3.2 – Revised section title from Voltage Operating Criteria & Guidelines to Voltage Operating Criteria & Policy and relevant wording within section from “Guideline” to “Policy”.
Section 3.3.3 – Clarified the Voltage Schedule and Bandwidth rows as being ‘kV’ values within the Generator Voltage Schedules table.
Section 3.8 – Reformatted the Interface line definitions for clarity within the Transfer Limits section. Added the future Mt Storm – Meadowbrook 500kV line to the AP South definition, and added the CLVLND reactive interface both with an effective date of 6/1/2011.
Section 3.9 – Revised UGI’s 69kV voltage limits within Exhibit 5: Bus and Zone Specific Variations to PJM Base Line Voltage Limits to appropriate voltage limits for their 66kV network. Added entries for ATSI and CPP for upcoming integration, effective 6/1/2011.
Section 4.2 – Inserted subsection 4.2.6 Peak Period Outage Scheduling Guidelines. To accommodate, former subsections 4.2.6 through 4.2.12 all advanced by one and are now 4.2.7 through 4.2.13.
Section 4.2.9 – Revised wording from ‘ … may loose its priority … ‘ to ‘may lose its priority’ within the Rescheduling Outages subsection.
Section 4.5 – Updated the Transmission Outage Acceleration Process to provide clarifications, aligning manual with tariff language.
Section 5 – Revised all Single Breaker Derate tables to utilize standardized ‘NL’, ‘EM’, ‘LT’, ‘ST’ and/or ‘LD’ limit titles where appropriate within the Operating Procedures for all Transmission Zones with applicable Single Breaker Derate tables.
Section 5 – Added Load Shed Determination Procedure and Load Shed Directive within the Operating Procedures for the PJM RTO and applicable index tables.
Section 5 – Corrected wording in reference to the “J” and “K” lines in the PSEG/ConEd Wheel within the Operating Procedure for the PJM RTO.
Section 5 – Revised NL & EL voltage limits for the Dresden units 2 & 3 in Voltage Control at Nuclear Stations within the Operating Procedures for the PJM RTO. Added Davis-Besse and Perry in same section effective upon ATSI integration, 6/1/2011.
Section 5 – Added a Directional Ratings procedure within the Operating Procedures for the AE Transmission Zone and applicable index tables.
Section 5 – Added AEP Single Breaker Derates within the Operating Procedures for the AEP Transmission Zone and applicable index tables.
Section 5 – Updated the Smith Mountain 138kV Station Stability procedure within the Operating Procedures for the AEP Transmission Zone.
Section 5 – Updated to classify Fast Valving and Emergency Unit Tripping as part of the overall SPS at Rockport in the Rockport Operating Guide within the Operating Procedures for the AEP Transmission Zone.
Section 5 – Revised the Twin Branch – Argenta (Conservative Operations) procedure to clearly identify the potential IROL limits within the Operating Procedures for the AEP Transmission Zone.
Section 5 – Renamed/Revised the Pleasants and Oak Grove Operating Restrictions to the Belmont SPS within the Operating Procedures for the AP Transmission Zone and applicable index tables to reflect the redundancy added to the preexisting relay scheme.
Section 5 – Added Bus Voltage Exceptions within the Operating Procedures for the AP Transmission Zone and applicable index tables.
Section 5 – Added/Revised rating sets for Bedington, Belmont, Black Oak, Cabot, Doubs, Ft Martin, Harrison, Hatfield, Meadowbrook, Pruntytown, South Bend, Wylie Ridge & Yukon 500kV CBs in the Breaker Derate Table within the Operating Procedures for the AP Transmission Zone.
Section 5 – Revised the ratings with one breaker in service for the Waugh Chapel – Calvert Cliffs ‘5052’ 500kV line in the Breaker Derate Table within the Operating Procedures for the BC Transmission Zone.
Section 5 – Added a DPL Transmission Zone section within the Operating Procedures and applicable index tables.
Section 5 – Added a Directional Ratings procedure within the Operating Procedures for the DPL Transmission Zone and applicable index tables.
Section 5 – Added Note, explaining limitation of one pump per GSU for a duel pump trip, to Bath County SPS procedure within the Operating Procedures for the DOM Transmission Zone.
Section 5 – Added an FE-ATSI Transmission Zone section within the Operating Procedures with an Effective Date of the PJM-ATSI/CPP Integration, 6/1/2011. Added to all applicable index tables.
Section 5 – Added Mansfield Unit Stability Restrictions and Richland Substation SPS within the Operating Procedures for the FE-ATSI Transmission Zone and applicable index tables.
Section 5 – Removed TMI Voltage Notification Procedures, as the limits for 1 Auxiliary Transformer and 2 Auxiliary Transformers are now the same, within the Operating Procedures for the FE Transmission Zone[h1] and applicable index tables.
Section 5 – Renamed/Reordered Operating Procedures and associated index tables for FE Transmission Zones.
Section 5 – Added the Homer City Stability Limits within the Operating Procedures for the FE Transmission Zone and applicable index tables.
Section 5 – Revised the table and procedure based upon most recent study results in the Conemaugh/Hunterstown Stability Limits within the Operating Procedures for the FE Transmission Zone.
Section 5 – Revised wording from “500 Conemaugh – Keystone 500kV line” to “5003 Conemaugh – Keystone 500kV line” in the Conemaugh #2 Stability Trip within the Operating Procedures for the FE Transmission Zone.
Section 5 – Clarified control modes for the 138kV Capacitor Banks for the Elmhurst SVC within the Operating Procedures for the ComEd Transmission Zone.
Section 5 – Removed reference to retired SPOGs 1-3-I-1 and 1-8 within the Operating Procedures for the ComEd Transmission Zone.
Section 5 – Removed reference to retired SPOG 1-3-C-1 from Quad Cities and Cordova Stability Limitations [SPS] within the Operating Procedures for the ComEd Transmission Zone.
Section 5 – Removed retired SPOG 3-21 107_Dixon ‘L15621’ 138 kV CB Operation within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Added Wolfs TR81 [SPS] within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Revised and renamed the former Sandwich 138kV Bus Tie Circuit Breaker [SPS] to Wolfs Crossing-Sandwich 138kV 14302 line [SPS] due to changes associated with the SPS and the applicable ComEd SPOG 3-31 within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Added Electric Junction – North Aurora 138kV 11106 line [SPS] due to changes associated with SPOG 3-27 within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Added Highland Park Transfer Trip [SPS] within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Added Zion Generation Stability Trip [SPS] within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Added Camp Grove Islanding within the Operating Procedures for the ComEd Transmission Zone and applicable index tables.
Section 5 – Removed the Elrama 138/69kV Auto Transformer Operation procedure within the Operating Procedures for the DLCO Transmission Zone and applicable index tables due to transformer replacement.
Section 5 – Revised the Common Trench Cable Ratings within the Operating Procedures for the PEPCO Transmission Zone.
Section 5 – Revised status to normally ‘Disabled; And, Enabled as needed’ for the Peach Bottom ‘45’ 500kV CB SPS and the Peach Bottom ‘35’ 500kV CB SPS within the Operating Procedures for the PE Transmission Zone[h2] .
Section 5 – Removed 2 lines pertaining to North & South bus outage restrictions and applicable Note from the Montour Stability Restrictions within the Operating Procedures for the PL Transmission Zone.
Section 5 – Removed the Hosensack – Buxmont 230kV Line Contingency procedure within the Operating Procedures for the PL Transmission Zone and applicable index tables as the scheme is no longer required and has been disabled.
Section 5 – Associated the PSE&G Artificial Island Stability procedure with the A.I. (Salem) Cross Trip Scheme and designated it as an [SPS] within the Operating Procedures for the PS Transmission Zone.
Section 5 – Removed the 500kV ‘3-4’ & ‘4-4A’ CBs @ Branchburg, the New Freedom 500kV ‘2-6’, ‘2-8’ & ‘9-10’ CB, the 138kV ‘4-5’ & ‘5-6’ CB @ Trenton and the 230kV ‘1-5’ & ‘5-6’ CBs @ Linden; Added the 500kV ‘2-6’ & ‘5-6’ CBs @ Deans; Revised the 500kV ‘1-3’ CB @ Hope Creek; All within the Breaker Derate Table for the PS Transmission Zone.
Section 5 – Revised to reflect area upgrades the Operation of 23030 Tie at Mountain and UGI/PL 66kV Tie Line Operation procedures within the Operating Procedures for the UGI Transmission Zone. Removed the Hunlock Outlet Overloads procedure from same.
Section 5 – Properly identified the Clover Generation Shed Scheme as an “[SPS]” within the Operating Procedures for the VP Transmission Zone.
Attachment B – Open Circuit Terminal Voltage Control table updated to reflect present PJM EHV lines.
Attachment E – Added Automatic Sectionalizing Schemes for the PPL & UGI Transmission Zone which are effective as of March 1, 2011. Removed three Automatic Sectionalizing Schemes related to the Matt Funk 345kV for the AEP Transmission Zone due to upgrades.
Exhibits – Added wording to indicate the Juniata PLC trip for high voltage is currently off within Exhibit 4: Capacitor Installations with PLCs.
|