Feasibility Study Data


If you have any questions, please contact at 866-400-8980.

Feasibility Study Checklist

  1. Feasibility Study Data Sheet
  2. One-line drawing showing:
    1. Generator Unit(s)
    2. GSU (transformers)
    3. Breakers
    4. Proposed Point of Interconnection
  3. Attachment N

 

 

 

 




Data Requirements for PJM RTEP Feasibility Studies

This form is not to be used to submit changes in project MW size or estimated in-service dates. Changes related to project MW size or in-service dates must be officially submitted to the assigned project manager.

This form is not to be used to submit data for existing generator projects. The form listed in Manual 14C known as Generator As Built Data Form is to be used instead.

This form is to submit data for proper modeling of your respective queue project in the Feasibility Study phase.

Feasibility Studies are conducted to identify transmission expansion needed to maintain the system reliability given your generation onto the network.

The data submitted is required to perform the power flow, and short circuit analysis which are necessary for the Feasibility Study phase.

PJM uses the following programs to perform the feasibility analysis:

  1. PSS/E program from PTI, Inc. (power flow)
  2. Aspen from Advanced Systems for Power Engineering, Inc.(short circuit)

Minimum requirement fields are indicated by *. Failure to provide the necessary data prior to the project kick-off meeting will result in withdrawal of the project from the queue.

All data must be provided on an individual unit basis.

For example, a combined cycle plant with two identical Combustion Turbines (CT) and one Steam Turbine (ST) would have two submissions of the data request form. One submission for the CT and one submission for the ST.

When more information is available, the typical model must be replaced with a detailed model based on the actual unit purchased.

If data is still not available and cannot be estimated please indicate by typing:

  • TBD and MM/DD/YY

Note: Please do not include special characters in the fields below (e.g. %, /, *, !, etc).
Unit Capability Data Request Form
  What type of study will this be?
1. Interconnection customer name:*
2. Name of individual completing form:*
3. E-mail:*
(Individual completing the form)
4. Phone:*
(Individual completing the form)
5. Primary fuel type:*
6. Interconnection Customer's proposed location (if known) for Point of Interconnection (POI) to PJM system:*
7. Maximum gross MW output:*
8. Maximum net MW output:*
9. Station service load (MW/MVAR):*  
  MW
  MVAR
10. Is load connected to high side of GSU?
11. Is load connected to low side of GSU?
 
Main Transformer Data
12. Number of machines per GSU:*
13. Generator step-up transformer MVA base:*
14. Generator step-up transformer impedance (R+jX on transformer MVA base):*
R: 
X: 
15. Generator step-up transformer reactance-to-resistance ratio (X/R):
16. Generator Step-up Transformer OA/FA/FA Rating (MVA):
OA: 
FAI: 
FAZ: 
17. Generator step-up transformer low-side voltage (kV):*
18. Generator step-up transformer high-side voltage (kV):*
19. Generator Step-up transformer off-nominal turns ratio:
20. Generator step-up transformer number of taps and step size:
Number: 
Size: 
 
Transmission Line Data
21. Line length from main transformer high-side to interconnection point (mi):
22. Voltage level (kV):
23. Conductor type:
24. Transmission line MVA base:
25. Positive sequence impedance (R+jX per mile on line MVA base):
R: 
X: 
26. Zero sequence impedance (R+jX per mile on line MVA base):
R: 
X: 
27. Positive sequence charging admittance
(in % per mile on line MVA base):
 
Plant Data Non-Wind Generators (Feasibility Study)
1. Generator MVA base (upon which all reactances, resistance and inertia are calculated):*
2. Generator nominal power factor:*
3. Generator terminal voltage (kV):*
4. Generator saturated sub-transient reactance, X"d(v) (on MVA base):*
Please provide site plan (on tax map, USGS topo map, etc.) for interconnection customer's facilities (electronic file if available) and a one-line diagram of the facility electrical arrangement via e-mail attachment to