Print Email
E-mail This Page

Please wait... loading

Jacks Mountain

Jacks Mountain
Click to enlarge

PenElec and PPL assigned baseline project with PJM id:

  • PenElec b0284.1, b0284.3, b0369 and b0370
  • PPL b0284.2, b0284.4

Scope:

  • Build a new 500kV substation (Jacks Mountain) by tapping the existing Conemaugh – Juniata and Keystone – Juniata 500kV circuits. The circuits will be connected with a breaker and a half scheme and a total of 1000MVARs of capacitors
  • Replace wave trap and upgrade a bus section at Keystone 500kV.
  • Replace two wave traps at Juniata 500kV
  • Relay changes at Juniata 500 kV sub

Need: Based on the PJM analysis of 2013, the Jack’s Mountain project is required to resolve voltage problems for load deliverability reliability criteria violations starting June 1, 2013

Permits:

  • NPDES individual permit – Approved
  • Environmental and Sediment Control permit – Approved

Energization: PJM required in service: 06.01.2014

Land Acquisition: PenElec purchased the property for the project in Oct 2008

Engineering / Design:

  • Site grading and storm-water management design has been revised and all drawings were reissued for permitting in January 2011. Permits approved on January 26, 2011.
  • Transmission line engineering is in process to support Spring 2014 outages.
  • Detailed Substation engineering has been postponed until Summer of 2013.

Equipment Procurement / Delivery:

  • Transmission and Substation Dead-end Structures have been designed and are ready to be procured when needed to support Spring 2014 outages.
  • Transmission line hardware procurement has been delayed until mid 2013 for delivery in 2014.
  • Substation procurement has been delayed until mid 2013 for delivery in 2014.
  • 500kV Breakers are on order and delivery scheduled for October 2014 & January 2015.
  • 500kV Cap Banks are on order and delivery scheduled for January 2015.
  • 500kV Disconnect Switches are on order and delivery scheduled for October 2014.

Construction:

  • Phase 1 Site Grading - Summer 2013
  • Transmission Line Construction - Foundations in Fall 2013, Outages in early Spring of 2014
  • Phase 2 Site Grading - Late Spring 2014
  • Substation Construction - Summer 2014 to June 1, 2015


Outages:

    GPU (PenElec)
  • 373926 - Conemaugh - Juniata (5005) – Fall 2013 foundation installation
  • 373928 - Keystone - Juniata (5004) - Fall 2013 foundation installation
  • 373929 - Conemaugh - Juniata (5005) - Spring 2014 demo and structure installation
  • 373930 - Keystone - Juniata (5004) – Spring 2014 demo and structure installation
  • TBD - Keystone - Juniata (5004) - Spring 2014 Substation Tie-in
  • TBD - Conemaugh - Juniata (5005) - Spring 2015 Substation Tie-in PPL
  • 306813 – replace wavetrap at Juniata on Keystone – Juniata line, complete
  • 351635 - replace wavetrap at Juniata on Conemaugh – Juniata line, complete
  • TBD – outages for relay work at Juniata sub