Eugene-Dequine 345 kV

331.5 MW Capacity / 450.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle #1. The Project Developer/Eligible Customer (developer) is Dolphin Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Electric Power.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak[1] and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The developer has proposed a Solar generating facility located in the American Electric Power zone — Fountain County, Indiana. The installed facilities will have a total capability of 450.0 MW with 331.5 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number AG1-226
Project Name Eugene-Dequine 345 kV
Developer Name Dolphin Solar LLC
State Indiana
County Fountain
Transmission Owner American Electric Power
MFO 450.0 MW
MWE 450.0 MW
MWC 331.5 MW
Fuel Type Solar
Basecase Study Year 2027

Point of Interconnection

AG1-226 will interconnect on the AEP transmission system tapping the Eugene to Dequine 345 kV line.

 

Cost Summary

The table below shows a summary of the total planning level cost estimates for this New Service Request project. These network upgrade costs are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AG1-226 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
Description Cost Allocated to AG1-226 Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF) $2,730,000 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $17,900,000 $17,900,000
Network Upgrades $3,570,000 $3,570,000
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $6,175,774 $6,175,774
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements $0 $0
Total $30,375,774 $27,645,774

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below and not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AG1-226

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID 10% of cost allocation for Phase I Network Upgrades Readiness Deposit #1 Received (RD1) Readiness Deposit #2 (RD2) for AG1-226 Project due at DP1
A B A - B
AG1-226 $2,764,577 $1,800,000 $964,577

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

AG1-226 will interconnect with the AEP transmission system via a new station cut into the Eugene - Dequine 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements. In addition, Stability analysis will be completed during the Phase 2 study. It is possible that a need for additional upgrades could be identified by these studies.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Interconnection Facilities
RTEP ID Description Total Cost ($USD) Allocated Cost ($USD)
(Pending) AEP will install one (1) new steel, single circuit, single pole dead end structure with associated conductor and shield wire for the generation lead circuit extending from the proposed 345 kV station. $1,610,000 $1,610,000
(Pending) AEP will install a standard revenue metering package for the generation lead circuit at the proposed 345 kV station. $810,000 $810,000
(Pending)
Extension of two (2) fiber optic cables from the proposed 345 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the proposed 345 kV and Project Developer's collector stations. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station.
$310,000 $310,000
Stand-Alone Network Upgrades
RTEP ID Description Total Cost ($USD) Allocated Cost ($USD)
(Pending)
AEP will construct a new 345 kV ring bus station; initially populated with three (3) circuit breakers, expandable to four (4) breakers.
$17,900,000 $17,900,000
Network Upgrades
RTEP ID Description Total Cost ($USD) Allocated Cost ($USD)
(Pending)
AEP will install two (2) new, double circuit, single-pole dead-end structures, one (1) new double circuit, single pole, tangent structure, and associated spans of conductor and shield wire in the existing Eugene - Dequine 345 kV Right of Way, cutting in the proposed 345 kV station in an in-and-out arrangement. The additional tangent structure will be installed to prevent blowout from the conductor on the far side of the double circuit tower line into the new dead end structures being installed to accommodate this interconnection.
$2,660,000 $2,660,000
(Pending)
AEP will replace the remote end protective relays at the Eugene and Dequine 345 kV Stations.
$910,000 $910,000

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 24 to 36 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to c, including remote end work, considering the Project Developer selection of the Option To Build, allocating the long lead material ordering as part of the Project Developer scope. The maximum schedule is based off of AEP assumed long lead material ordering not considering allocation of existing material production slots, advanced progress enabled by Engineering and Procurement Agreements, or other schedule expediting methods. AEP may be able to allocate material production slots for long lead time materials to expedite this schedule. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to these agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No violations.

 

Developer Requirements

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

AEP posts the latest versions of the "Connection Requirements for the AEP Transmission System", and associated documentation at: https://www.aep.com/requiredpostings/AEPTransmissionStudies

Revenue Metering and SCADA Requirements

PJM Requirements    

 

The Project Developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manuals M-01 and M14D, and PJM Tariff Part IX, Subpart B, Appendix 2, Section 8.

 

Meteorological Data Reporting Requirement             

The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:

 

    • Temperature (degrees Fahrenheit)
    • Atmospheric Pressure (hectopascals)
    • Irradiance
    • Forced outage data                


Interconnection Transmission Owner Requirements        

The details of applicable metering requirements are provided in the "Connection Requirements for the AEP Transmission System" document, found at: https://www.aep.com/requiredpostings/AEPTransmissionStudies  The primary metering will be installed on the Transmission Owner side of the Point of Change in Ownership and will be owned and maintained by the Transmission Owner. Any additional generation proposed behind an originating project POC that differs in either type or corporate entity from the originating project will require the installation of additional submetering for both the originating project and the uprate for the purpose of settlement. Submetering will require additional space within the originating project facilities. The meters, routers, Ethernet to fiber converters, and telecom switch will be procured and owned by AEP. The revenue quality instrument transformers, fiber cable connecting the submeters, and any other additional hardware for the required submetering will be procured, installed, owned, and maintained by the Project Developer.

Summer Peak Analysis

The New Service Request project was evaluated as a 450.0 MW (Capacity 331.5 MW) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of New Service Requests are evaluated for single or N-1 contingencies. The full energy output of New Service Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P1-2_#709_546_SRT-A
CONTINGENCY 'AEP_P1-2_#709_546_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Single AC 124.38 % 2255.0 B 2804.73 39.38
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
Single AC 111.8 % 1409.0 B 1575.28 18.48
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#10135_SRT-A
CONTINGENCY 'AEP_P1-2_#10135_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243442 CKT 1   /*05ROCKPT     765.0 - 05RKG1        26.0
 REMOVE UNIT 1H FROM BUS 243442                    /*05RKG1        26.0
 REMOVE UNIT 1L FROM BUS 243442                    /*05RKG1        26.0
END
Single AC 111.46 % 1409.0 B 1570.54 18.49
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Single AC 102.53 % 1868.0 B 1915.3 144.66
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Single AC 102.53 % 1868.0 B 1915.3 144.66
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 177.18 % 2255.0 B 3995.34 38.2
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2 FROM BUS 247249                     /*05HRKG2B      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Breaker AC 154.14 % 2255.0 B 3475.82 53.31
AEP 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 126.19 % 3039.0 B 3834.89 38.2
AEP 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2 FROM BUS 247249                     /*05HRKG2B      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Breaker AC 107.21 % 3039.0 B 3258.2 53.31
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Breaker AC 105.16 % 1374.0 B 1444.84 238.01
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Tower AC 116.3 % 1374.0 B 1598.01 240.76
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Tower AC 110.74 % 1374.0 B 1521.63 160.06

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

Summer Potential Congestion due to Local Energy Deliverability
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 169.91 % 1868.0 B 3173.97 196.38
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 169.91 % 1868.0 B 3173.97 196.38
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP DC 144.26 % 1409.0 B 2032.66 25.09
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 124.28 % 1958.0 B 2433.45 186.3
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 123.18 % 1958.0 B 2411.82 184.74
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Base Case OP AC 122.9 % 1409.0 A 1731.63 254.41
AEP AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line
963740 to 963840 ckt 1
Base Case OP AC 113.28 % 1409.0 A 1596.12 254.41
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345/69XFR_SRT-S
CONTINGENCY 'EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345
 CLOSE BRANCH FROM BUS 250595 TO BUS 250896 CKT 1   /*08INLNDC      69.0 - 08WROWJ       69.0
 OPEN BRANCH FROM BUS 249504 TO BUS 249505 CKT 1    /*08CAYSUB     345.0 - 08CAYUGA     345.0
 OPEN BRANCH FROM BUS 249504 TO BUS 250340 CKT 1    /*08CAYSUB     345.0 - 08CAYSUB      69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250341 CKT 1    /*08CAYSUB      69.0 - 08CAY69       69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250595 CKT 1    /*08CAYSUB      69.0 - 08INLNDC      69.0
END
OP AC 109.99 % 1868.0 B 2054.64 290.24
AEP AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line
963740 to 963840 ckt 1
992070 J2664 POI 345 249516 08NUCOR 345 1_SRT-A
CONTINGENCY '992070 J2664 POI 345 249516 08NUCOR 345 1_SRT-A'
 OPEN BRANCH FROM BUS 992070 TO BUS 249516 CKT 1   /*J2664 POI    345.0 - 08NUCOR      345.0
END
OP AC 101.04 % 1959.0 B 1979.32 262.65
AEP 05FALL C-05DESOTO 345.0 kV Ckt 1 line
243222 to 243218 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 102.42 % 1195.0 B 1223.97 24.41

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle #2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle #2.

Light Load Analysis

At this time light load analysis not required for this project.

Light Load Potential Congestion due to Local Energy Deliverability

At this time light load analysis not required for this project.

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage analysis is not performed as part of the Phase I System Impact Study. Steady State Voltage analysis will commence in the Phase II System Impact Study.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AB1-006 Meadow Lake 345kV In Service
AB1-080 Dumont-Olive 345kV In Service
AB1-087 Sullivan 345kV #1 Suspended
AB1-088 Sullivan 345kV #2 Suspended
AB2-047 Brokaw-Pontiac Midpoint In Service
AB2-070 Mt. Pulaski-Brokaw In Service
AC1-053 Lanesville-Brokaw Under Construction
AC2-154 Davis Creek 138kV Suspended
AC2-157 Sullivan 345 kV Engineering & Procurement
AD1-100 Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV Engineering & Procurement
AD1-148 Brokaw-Lanesville In Service
AD2-047 Davis Creek 138 kV Engineering & Procurement
AD2-060 Davis Creek 138kV Suspended
AD2-100 Kincaid-Pana 345 kV Engineering & Procurement
AD2-131 Kincaid-Pana 345kV Engineering & Procurement
AE1-166 Loretto-Wilton & Braidwood-Davis Creek Active
AE1-205 McLean 345 kV Active
AE2-045 Olive-Reynolds 345 kV Active
AE2-130 Rockport 765 kV Active
AE2-152 Loretto-Wilton & Braidwood-Davis Creek Active
AE2-173 McLean 345 kV Active
AE2-223 McLean 345 kV Active
AE2-261 Kincaid-Pana 345 kV Active
AE2-267 Woodsdale 345 kV Engineering & Procurement
AE2-276 Sullivan 345kV Active
AF1-088 Sullivan 345 kV Active
AF1-090 Kincaid-Pana Active
AF1-158 Edison-Gravel Pit 138 kV Under Construction
AF1-200 Plano 345 kV Active
AF1-204 Eugene 345 kV Active
AF1-207 Reynolds–Olive #1 345 kV Active
AF1-215 Reynolds-Olive 345 kV Under Construction
AF1-249 Nickel 12.47 kV Under Construction
AF1-252 Kincaid-Pana Active
AF1-253 Kincaid-Pana Active
AF1-322 Meadow Lake 345 kV Active
AF2-008 Sullivan 345 kV Active
AF2-031 Calumet Active
AF2-032 Kincaid 345 kV Active
AF2-078 Reynolds-Olive #1 345 kV Active
AF2-095 Davis Creek 138 kV Active
AF2-096 Braidwood-East Frankfort 345 kV Active
AF2-132 Reynolds-Olive #1 345 kV Active
AF2-133 Reynolds-Olive #2 345 kV Active
AF2-134 Reynolds-Olive #2 345 kV Under Construction
AF2-191 New Carlisle 138 kV Active
AF2-205 Olive-Reynolds #2 345 kV Active
AF2-225 McLean 345 kV Active
AF2-252 Blue Mound 345 kV Active
AF2-305 Brokaw-Lanesville 345 kV In Service
AF2-317 Hill Topper 345 kV In Service
AF2-350 Kensington 138 kV Active
AF2-351 Kensington 138 kV Active
AF2-352 Blue Mound 345 kV Active
AF2-359 Olive-University Park 345 kV Active
AF2-441 Burnham 138kV Active
AG1-236 Lanesville-Brokaw 345 kV Active
AG1-237 Dequine-Eugene 345 kV Active
AG1-297 Hanna-Tanners Creek 345 kV Active
AG1-298 Calumet-Burnham 345 kV Active
AG1-302 Olive-Reynolds #1 345 kV Active
AG1-349 Olive-Reynolds #2 345 kV Active
AG1-374 Blue Mound 345 kV Active
AG1-398 Brokaw-Lanesville 345 kV In Service
AG1-399 Blue Mound-Chestnut 345 kV Active
AG1-400 Blue Mound-Chestnut 345 kV Active
AG1-402 Blue Mound-Chestnut 345 kV Active
AG1-404 Blue Mound-Chestnut 345 kV Active
AG1-436 Olive-University Park 345 kV Active
AG1-447 Olive-University Park 345 kV Active
AG1-460 Kincaid-Pana 345 kV Active
AG1-512 University Park North 345 kV Active
AG1-522 Sullivan-Rockport 765 kV Active
AG1-523 Sullivan-Rockport 765 kV Active
AG1-524 Sullivan-Rockport 765 kV Active
AG1-525 Sullivan-Rockport 765 kV Active
AG1-535 State Line-S. Chicago Properties 138 kV Active
AG1-555 Dequine 345 kV Active
W2-048 Brokaw-Lanesville In Service
W4-005 Blue Mound-Latham In Service
X2-022 Brokaw-Lanesville In Service
Z2-087 Pontiac MidPoint-Brokaw 345kV In Service

Affected Systems

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator (MISO) Study Pending
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase I analysis results, this project has potential cost responsibility for the following System Reinforcements:

AG1-226 System Reinforcements Cost Breakdown:
TO RTEP ID / TO ID Title MW Impact Percent Allocation Allocated Cost ($USD)
AEP (Pending) / AEP_TC1_15474 Replace 345kV CB A1 and Tie CB A at Meadow Lake 144.7 MW 30.4% $1,973,842
AEP n7618 / AEPI0081a Replace two Meadowlake CBs (3000A) 144.7 MW 30.4% $1,973,842
AEP (Pending) / AEPSERG13 At Jefferson station install a second 765/345 kV 750 MVA transformer to connect to the Jefferson 765 kV bus #1 and a second Jefferson - Clifty 345 kV line to connect to the Jefferson 345 kV bus 1 38.2 MW 3.0% $1,033,537
IPL (Pending) / IPL_TC1_15157 Reconductor this line to meet at minimum rating of 1624 MVA. 18.5 MW 2.6% $377,998
AEP n7964 / AEPI0025a Replace 765/345 Transformer 38.2 MW 3.0% $230,331
AEP n7943.4 / AEPI0025d Replace 9 Jefferson 5000 A switches 38.2 MW 3.0% $172,748
AEP (Pending) / AEPSERG11 Jefferson - Clifty OVEC conductor - line rebuild 38.2 MW 2.8% $96,142
AEP n4106.4 Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. 38.2 MW 2.8% $92,444
AEP (Pending) / AEPSERG12 Replace (3) Jefferson 345 kV 5000 A switches 38.2 MW 2.8% $55,467
AEP n7943.2 / AEPI0025b Replace Jefferson 345kV Circuit Breaker (5000A) 38.2 MW 3.0% $46,066
AEP n4106.6 / AEPI0045e Replace Jefferson Breaker (5000A) 38.2 MW 2.8% $44,373
AEP (Pending) / AEPSERG17 Upgrade Jefferson 345kV 3-2500 AAC risers 38.2 MW 3.0% $20,154
AEP (Pending) / AEPSERG08 Replace Jefferson risers 3-2500 kCM AAC 91-Str 38.2 MW 2.8% $19,413
IPL (Pending) / IPL_TC1_15158 Replace substation terminal equipment to meet at minimum rating of 1624 MVA 18.5 MW 2.6% $12,945
OVEC (Pending) / OVECPJH01 Replace 5" Al Tubing 345 kV bus at Clifty Creek 38.2 MW 2.4% $11,788
AEP n7943.5 / AEPI0025e Replace 2 Jefferson (Sub cond 3-2500 kcm AAC 91 Str) 38.2 MW 3.0% $7,678
AEP n4106.5 / AEPI0045c Replace Clifty Bus 5"0 AL Tubular Sch 40 38.2 MW 2.8% $3,698
AEP n7943.3 / AEPI0025c An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. 38.2 MW 3.0% $960
AEP n4106.7 / AEPI0045f An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. 38.2 MW 2.8% $924
AEP (Pending) / AEPSERG09 Jefferson CT thermal limit 38.2 MW 2.8% $711
AEP (Pending) / AEPSERG10 Clifty relay thermal limit 38.2 MW 2.8% $711
NIPS (Pending) / NIPS_TC1_15149 NIPSCO rating: 2133/2577 SN/SE 144.7 MW 30.4% $0
NIPS (Pending) / NIPS_TC1_15150 NIPSCO rating: 2133/2577 SN/SE 144.7 MW 30.4% $0
AEP (Pending) / AEP_TC1_15492 AEP SE rating is 1749 MVA. 18.5 MW 2.6% $0
Grand Total: $6,175,772
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEP_TC1_15474 Replace 345kV CB A1 and Tie CB A at Meadow Lake $6,500,000 $1,973,842 18 to 24 Months

Contributor

Description: Replace 345kV CB A1 and Tie CB A at Meadow Lake

Flowgates Addressed by this Reinforcement
Facility Contingency
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (All) A 1916.0 MVA
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (All) B 2246.0 MVA
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (All) C 2387.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 34.3 MW 7.2% $467,901
AF1-088 144.3 MW 30.3% $1,968,357
AF2-008 72.1 MW 15.1% $984,172
AG1-226 144.7 MW 30.4% $1,973,842
AG1-522 20.3 MW 4.3% $276,432
AG1-523 20.3 MW 4.3% $276,432
AG1-524 20.3 MW 4.3% $276,432
AG1-525 20.3 MW 4.3% $276,432
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n7618 / AEPI0081a Replace two Meadowlake CBs (3000A) $6,500,000 $1,973,842 Dec 31 2024

Contributor

Description: Replace two Meadowlake CBs (3000A). MISO-end SE rating is 2577 MVA SE.

Flowgates Addressed by this Reinforcement
Facility Contingency
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line (All) A 1916.0 MVA
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line (All) B 2246.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 34.3 MW 7.2% $467,901
AF1-088 144.3 MW 30.3% $1,968,357
AF2-008 72.1 MW 15.1% $984,172
AG1-226 144.7 MW 30.4% $1,973,842
AG1-522 20.3 MW 4.3% $276,432
AG1-523 20.3 MW 4.3% $276,432
AG1-524 20.3 MW 4.3% $276,432
AG1-525 20.3 MW 4.3% $276,432
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG13 At Jefferson station install a second 765/345 kV 750 MVA transformer to connect to the Jefferson 765 kV bus #1 and a second Jefferson - Clifty 345 kV line to connect to the Jefferson 345 kV bus 1 $35,000,000 $1,033,537 36 to 48 Months

Contributor

Description: There is no bigger 765/345 kV transformer in the AEP system than the transformer at Jefferson station or a bigger 345 kV breaker than the Jefferson 345 kV breaker to be able to upgrade to a bigger size. At Jefferson station install a second 765/345 kV 750 MVA transformer to connect to the Jefferson 765 kV bus #1 and a second Jefferson - Clifty 345 kV line to connect to the Jefferson 345 kV bus 1

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $10,301,036
AF1-088 233.8 MW 18.1% $6,325,819
AF2-008 233.8 MW 18.1% $6,325,819
AG1-226 38.2 MW 3.0% $1,033,537
AG1-522 101.8 MW 7.9% $2,753,447
AG1-523 101.8 MW 7.9% $2,753,447
AG1-524 101.8 MW 7.9% $2,753,447
AG1-525 101.8 MW 7.9% $2,753,447
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
IPL (Pending) / IPL_TC1_15157 Reconductor this line to meet at minimum rating of 1624 MVA. $14,600,000 $377,998 TBD

Contributor

Description: Reconductor this line to meet at minimum rating of 1624 MVA.

Flowgates Addressed by this Reinforcement
Facility Contingency
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (All) A 1624.0 MVA
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (All) B 1624.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 123.6 MW 17.3% $2,527,916
AF1-088 257.6 MW 36.1% $5,267,806
AF2-008 128.8 MW 18.0% $2,633,903
AG1-226 18.5 MW 2.6% $377,998
AG1-522 46.4 MW 6.5% $948,094
AG1-523 46.4 MW 6.5% $948,094
AG1-524 46.4 MW 6.5% $948,094
AG1-525 46.4 MW 6.5% $948,094
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n7964 / AEPI0025a Replace 765/345 Transformer $7,800,000 $230,331 24 to 36 Months

Contributor

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3113.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 3113.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $2,295,659
AF1-088 233.8 MW 18.1% $1,409,754
AF2-008 233.8 MW 18.1% $1,409,754
AG1-226 38.2 MW 3.0% $230,331
AG1-522 101.8 MW 7.9% $613,625
AG1-523 101.8 MW 7.9% $613,625
AG1-524 101.8 MW 7.9% $613,625
AG1-525 101.8 MW 7.9% $613,625
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n7943.4 / AEPI0025d Replace 9 Jefferson 5000 A switches $5,850,000 $172,748 18 to 24 Months

Contributor

Description: Replace 9 Jefferson 5000 A switches

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3582.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 3813.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $1,721,745
AF1-088 233.8 MW 18.1% $1,057,315
AF2-008 233.8 MW 18.1% $1,057,315
AG1-226 38.2 MW 3.0% $172,748
AG1-522 101.8 MW 7.9% $460,219
AG1-523 101.8 MW 7.9% $460,219
AG1-524 101.8 MW 7.9% $460,219
AG1-525 101.8 MW 7.9% $460,219
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG11 Jefferson - Clifty OVEC conductor - line rebuild $3,380,000 $96,142 18 to 24 Months

Contributor

Description: Jefferson - Clifty OVEC conductor - line rebuild

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM A 2568.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM B 3040.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $958,228
AE2-261 24.1 MW 1.8% $60,591
AF1-088 233.8 MW 17.4% $588,443
AF1-204 25.3 MW 1.9% $63,622
AF2-008 233.8 MW 17.4% $588,443
AG1-226 38.2 MW 2.8% $96,142
AG1-522 101.8 MW 7.6% $256,133
AG1-523 101.8 MW 7.6% $256,133
AG1-524 101.8 MW 7.6% $256,133
AG1-525 101.8 MW 7.6% $256,133
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n4106.4 Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. $3,250,000 $92,444 24 to 36 Months

Contributor

Description: Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 2365.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 2826.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $921,373
AE2-261 24.1 MW 1.8% $58,261
AF1-088 233.8 MW 17.4% $565,811
AF1-204 25.3 MW 1.9% $61,175
AF2-008 233.8 MW 17.4% $565,811
AG1-226 38.2 MW 2.8% $92,444
AG1-522 101.8 MW 7.6% $246,281
AG1-523 101.8 MW 7.6% $246,281
AG1-524 101.8 MW 7.6% $246,281
AG1-525 101.8 MW 7.6% $246,281
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG12 Replace (3) Jefferson 345 kV 5000 A switches $1,950,000 $55,467 24 to 30 Months

Contributor

Description: Replace (3) Jefferson 345 kV 5000 A switches

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM A 3241.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM B 3813.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $552,824
AE2-261 24.1 MW 1.8% $34,957
AF1-088 233.8 MW 17.4% $339,487
AF1-204 25.3 MW 1.9% $36,705
AF2-008 233.8 MW 17.4% $339,487
AG1-226 38.2 MW 2.8% $55,467
AG1-522 101.8 MW 7.6% $147,769
AG1-523 101.8 MW 7.6% $147,769
AG1-524 101.8 MW 7.6% $147,769
AG1-525 101.8 MW 7.6% $147,769
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n7943.2 / AEPI0025b Replace Jefferson 345kV Circuit Breaker (5000A) $1,560,000 $46,066 18 to 24 Months

Contributor

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3426.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 3582.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $459,132
AF1-088 233.8 MW 18.1% $281,951
AF2-008 233.8 MW 18.1% $281,951
AG1-226 38.2 MW 3.0% $46,066
AG1-522 101.8 MW 7.9% $122,725
AG1-523 101.8 MW 7.9% $122,725
AG1-524 101.8 MW 7.9% $122,725
AG1-525 101.8 MW 7.9% $122,725
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n4106.6 / AEPI0045e Replace Jefferson Breaker (5000A) $1,560,000 $44,373 18 to 24 Months

Contributor

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 3290.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3290.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $442,259
AE2-261 24.1 MW 1.8% $27,965
AF1-088 233.8 MW 17.4% $271,589
AF1-204 25.3 MW 1.9% $29,364
AF2-008 233.8 MW 17.4% $271,589
AG1-226 38.2 MW 2.8% $44,373
AG1-522 101.8 MW 7.6% $118,215
AG1-523 101.8 MW 7.6% $118,215
AG1-524 101.8 MW 7.6% $118,215
AG1-525 101.8 MW 7.6% $118,215
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG17 Upgrade Jefferson 345kV 3-2500 AAC risers $682,500 $20,154 18 to 24 Months

Contributor

Description: Upgrade Jefferson 345kV 3-2500 AAC risers

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer SUM B 4132.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $200,870
AF1-088 233.8 MW 18.1% $123,353
AF2-008 233.8 MW 18.1% $123,353
AG1-226 38.2 MW 3.0% $20,154
AG1-522 101.8 MW 7.9% $53,692
AG1-523 101.8 MW 7.9% $53,692
AG1-524 101.8 MW 7.9% $53,692
AG1-525 101.8 MW 7.9% $53,692
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG08 Replace Jefferson risers 3-2500 kCM AAC 91-Str $682,500 $19,413 18 to 24 Months

Contributor

Description: Replace Jefferson risers 3-2500 kCM AAC 91-Str

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM A 3444.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM B 4132.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $193,488
AE2-261 24.1 MW 1.8% $12,235
AF1-088 233.8 MW 17.4% $118,820
AF1-204 25.3 MW 1.9% $12,847
AF2-008 233.8 MW 17.4% $118,820
AG1-226 38.2 MW 2.8% $19,413
AG1-522 101.8 MW 7.6% $51,719
AG1-523 101.8 MW 7.6% $51,719
AG1-524 101.8 MW 7.6% $51,719
AG1-525 101.8 MW 7.6% $51,719
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
IPL (Pending) / IPL_TC1_15158 Replace substation terminal equipment to meet at minimum rating of 1624 MVA $500,000 $12,945 TBD

Contributor

Description: Replace substation terminal equipment to meet at minimum rating of 1624 MVA

Flowgates Addressed by this Reinforcement
Facility Contingency
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (All) A 1624.0 MVA
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (All) B 1624.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 123.6 MW 17.3% $86,572
AF1-088 257.6 MW 36.1% $180,404
AF2-008 128.8 MW 18.0% $90,202
AG1-226 18.5 MW 2.6% $12,945
AG1-522 46.4 MW 6.5% $32,469
AG1-523 46.4 MW 6.5% $32,469
AG1-524 46.4 MW 6.5% $32,469
AG1-525 46.4 MW 6.5% $32,469
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
OVEC (Pending) / OVECPJH01 Replace 5" Al Tubing 345 kV bus at Clifty Creek $500,000 $11,788 18 to 24 Months

Contributor

Description: Replace 5" Al Tubing 345 kV bus at Clifty Creek

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3040.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 23.5% $117,485
AE2-261 24.1 MW 1.5% $7,429
AF1-088 233.8 MW 14.4% $72,147
AF1-200 201.6 MW 12.4% $62,218
AF1-204 25.3 MW 1.6% $7,800
AF2-008 233.8 MW 14.4% $72,147
AF2-096 25.4 MW 1.6% $7,849
AG1-226 38.2 MW 2.4% $11,788
AG1-298 50.3 MW 3.1% $15,523
AG1-522 101.8 MW 6.3% $31,404
AG1-523 101.8 MW 6.3% $31,404
AG1-524 101.8 MW 6.3% $31,404
AG1-525 101.8 MW 6.3% $31,404
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n7943.5 / AEPI0025e Replace 2 Jefferson (Sub cond 3-2500 kcm AAC 91 Str) $260,000 $7,678 18 to 24 Months

Contributor

Description: Replace 2 Jefferson (Sub cond 3-2500 kcm AAC 91 Str)

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3444.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 4132.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $76,522
AF1-088 233.8 MW 18.1% $46,992
AF2-008 233.8 MW 18.1% $46,992
AG1-226 38.2 MW 3.0% $7,678
AG1-522 101.8 MW 7.9% $20,454
AG1-523 101.8 MW 7.9% $20,454
AG1-524 101.8 MW 7.9% $20,454
AG1-525 101.8 MW 7.9% $20,454
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n4106.5 / AEPI0045c Replace Clifty Bus 5"0 AL Tubular Sch 40 $130,000 $3,698 18 to 24 Months

Contributor

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 2365.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 2831.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $36,855
AE2-261 24.1 MW 1.8% $2,330
AF1-088 233.8 MW 17.4% $22,632
AF1-204 25.3 MW 1.9% $2,447
AF2-008 233.8 MW 17.4% $22,632
AG1-226 38.2 MW 2.8% $3,698
AG1-522 101.8 MW 7.6% $9,851
AG1-523 101.8 MW 7.6% $9,851
AG1-524 101.8 MW 7.6% $9,851
AG1-525 101.8 MW 7.6% $9,851
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n7943.3 / AEPI0025c An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. $32,500 $960 12 to 18 Months

Contributor

Description: An engineering study will need to be conducted to determine if the Jefferson CT thermal Trip limits 2703 Amps settings can be adjusted to mitigate the overload, Estimated Cost $25,000. New relay packages will be required if the settings cannot be adjusted. Estimated Cost: $600,000.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3582.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 3759.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 29.4% $9,565
AF1-088 233.8 MW 18.1% $5,874
AF2-008 233.8 MW 18.1% $5,874
AG1-226 38.2 MW 3.0% $960
AG1-522 101.8 MW 7.9% $2,557
AG1-523 101.8 MW 7.9% $2,557
AG1-524 101.8 MW 7.9% $2,557
AG1-525 101.8 MW 7.9% $2,557
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n4106.7 / AEPI0045f An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. Estimated Cost: $600,000. $32,500 $924 12 to 18 Months

Contributor

Description: An engineering study will need to be conducted to determine if the Jefferson Relay Compliance Trip limits 5506 Amps settings can be adjusted to mitigate the overload, Estimated Cost $25,000. New relay packages will be required if the settings cannot be adjusted. Estimated Cost: $600,000.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 3426.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3581.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $9,214
AE2-261 24.1 MW 1.8% $583
AF1-088 233.8 MW 17.4% $5,658
AF1-204 25.3 MW 1.9% $612
AF2-008 233.8 MW 17.4% $5,658
AG1-226 38.2 MW 2.8% $924
AG1-522 101.8 MW 7.6% $2,463
AG1-523 101.8 MW 7.6% $2,463
AG1-524 101.8 MW 7.6% $2,463
AG1-525 101.8 MW 7.6% $2,463
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG09 Jefferson CT thermal limit $25,000 $711 12 to 18 Months

Contributor

Description: An engineering study will need to be conducted to determine if the Jefferson CT thermal limitsettings can be adjusted to mitigate the overload.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM A 3426.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM B 3736.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $7,087
AE2-261 24.1 MW 1.8% $448
AF1-088 233.8 MW 17.4% $4,352
AF1-204 25.3 MW 1.9% $471
AF2-008 233.8 MW 17.4% $4,352
AG1-226 38.2 MW 2.8% $711
AG1-522 101.8 MW 7.6% $1,894
AG1-523 101.8 MW 7.6% $1,894
AG1-524 101.8 MW 7.6% $1,894
AG1-525 101.8 MW 7.6% $1,894
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEPSERG10 Clifty relay thermal limit $25,000 $711 12 to 18 Months

Contributor

Description: An engineering study will need to be conducted to determine if the Clifty Relay Thermal limits settings can be adjusted to mitigate the overload.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM B 3426.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-130 380.7 MW 28.3% $7,087
AE2-261 24.1 MW 1.8% $448
AF1-088 233.8 MW 17.4% $4,352
AF1-204 25.3 MW 1.9% $471
AF2-008 233.8 MW 17.4% $4,352
AG1-226 38.2 MW 2.8% $711
AG1-522 101.8 MW 7.6% $1,894
AG1-523 101.8 MW 7.6% $1,894
AG1-524 101.8 MW 7.6% $1,894
AG1-525 101.8 MW 7.6% $1,894
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEP_TC1_13727 AEP SE rating is 1868 MVA $0 $0 TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Description: AEP SE rating is 1868 MVA

Flowgates Addressed by this Reinforcement
Facility Contingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (All) B 1868.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
DEI (Pending) / DEI_TC1_13416 MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP SE rating is 1868 MVA . $12,095,000 $0 TBD

Contingent

Note: Based on PJM cost allocation criteria, AG1-226 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-226 could receive cost allocation. Although AG1-226 may not presently have cost responsibility for this upgrade, AG1-226 may need this upgrade in-service to be deliverable to the PJM system. If AG1-226 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: AEP SE rating is 1868 MVA . MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP end cost TBD.

Flowgates Addressed by this Reinforcement
Facility Contingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (All) A 9999.0 MVA
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (All) B 9999.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP n4106.3 Extend One (1) Tower on the Jefferson - Clifty Creek (IKEC) 345 kV Circuit $409,714 $0 12 to 18 Months

Contingent

Note: Based on PJM cost allocation criteria, AG1-226 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-226 could receive cost allocation. Although AG1-226 may not presently have cost responsibility for this upgrade, AG1-226 may need this upgrade in-service to be deliverable to the PJM system. If AG1-226 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: A sag check will be required for the ACSR ~ 2156 ~ 84/19 ~ BLUEBIRD Conductor Section 1 to determine if the line section can be operated above its emergency rating. Z1-070 LTF Facilities Study sag study results: Jefferson Clifty Creek 345 kV line work will include one location of grading to remediate clearance location of concern in span 1 to 2. From latest Facility Study for AF1-215: Extend One (1) Tower on the Jefferson - Clifty Creek (IKEC) 345 kV Circuit

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 2826.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP b3748 Replace four Clifty Creek 345 kV 3000A switches with 5000 A 345 kV switches $850,000 $0 Jun 28 2024

Contingent

Note: Although AG1-226 may not presently have cost responsibility for this upgrade, AG1-226 may need this upgrade in-service to be deliverable to the PJM system. If AG1-226 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: Replace four Clifty Creek 345 kV 3000A switches with 5000 A 345 kV switches. Projected IS 6/2023 Replaces project n4106.1

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 2354.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
OVEC n4106 / N4106 Replace Two (2) Switches at the Clifty Creek 345 kV Station $536,791 $0 18 to 24 Months

Contingent

Note: Based on PJM cost allocation criteria, AG1-226 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-226 could receive cost allocation. Although AG1-226 may not presently have cost responsibility for this upgrade, AG1-226 may need this upgrade in-service to be deliverable to the PJM system. If AG1-226 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: Replace Two (2) Switches at the Clifty Creek 345 kV Station

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 2354.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP s2832.1 / s2832 Replace (2) Clifty Creek 345 kV breakers $7,150,000 $0 Jun 07 2024

Contingent

Note: Although AG1-226 may not presently have cost responsibility for this upgrade, AG1-226 may need this upgrade in-service to be deliverable to the PJM system. If AG1-226 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: Replace (2) Clifty Creek 345 kV breakers

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
NIPS (Pending) / NIPS_TC1_15149 NIPSCO rating: 2133/2577 SN/SE $0 $0 TBD

Contributor

Description: NIPSCO rating: 2133/2577 SN/SE

Flowgates Addressed by this Reinforcement
Facility Contingency
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (All) A 2133.0 MVA
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line (All) B 2577.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
NIPS (Pending) / NIPS_TC1_15150 NIPSCO rating: 2133/2577 SN/SE $0 $0 TBD

Contributor

Description: NIPSCO rating: 2133/2577 SN/SE

Flowgates Addressed by this Reinforcement
Facility Contingency
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line (All) A 2133.0 MVA
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line (All) B 2577.0 MVA
System Reinforcement
TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
AEP (Pending) / AEP_TC1_15492 AEP SE rating is 1749 MVA. $0 $0 TBD

Contributor

Description: AEP SE rating is 1749 MVA.

Flowgates Addressed by this Reinforcement
Facility Contingency
05SULLIVAN-16PETE 345.0 kV Ckt 1 line (Any)

Attachments


[1]Winter load flow analysis will be performed starting in Transition Cycle #2.