AG1-226 Phase II Study Report
v1.00 released 2024-12-18 14:06
Eugene-Dequine 345 kV
142.0 MW Capacity / 450.0 MW Energy
Introduction
This Phase II System Impact Study Report (PH2) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle #1. The Project Developer/Eligible Customer (developer) is Dolphin Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Electric Power.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from Phase I System Impact Study (summer peak, winter peak[1] and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Solar generating facility located in the American Electric Power zone — Fountain County, Indiana. The installed facilities will have a total capability of 450.0 MW with 142.0 MW of this output being recognized by PJM as Capacity.
| Project Information | |
|---|---|
| New Service Request Number | AG1-226 |
| Project Name | Eugene-Dequine 345 kV |
| Project Developer Name | Dolphin Solar LLC |
| State | Indiana |
| County | Fountain |
| Transmission Owner | American Electric Power |
| MFO | 450.0 MW |
| MWE | 450.0 MW |
| MWC | 142.0 MW |
| Fuel Type | Solar |
| Basecase Study Year | 2027 |
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AG1-226 will interconnect on the AEP transmission system tapping the Eugene to Dequine 345 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AG1-226 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG1-226 | Cost Subject to Readiness* | |
| Transmission Owner Interconnection Facilities (TOIF) | $2,930,035 | $0 | |
| Other Scope | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $25,004,681 | $25,004,681 | |
| Network Upgrades | $8,068,798 | $8,068,798 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $6,638,533 | $6,638,533 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | |
| Distribution | $0 | $0 | |
| Affected System Study Reinforcements | $0 | $0 | |
| Total | $42,642,047 | $39,712,012 | |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase 2 SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AG1-226
Readiness Deposit #3 has been calculated for the AG1-226 project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
| Readiness Deposit | |||
|---|---|---|---|
| Project ID | 20% of cost allocation for Phase II Network Upgrades | Sum of Readiness Deposit #1 & Readiness Deposit #2 Received (RD1+RD2) | Readiness Deposit #3 (RD3) for AG1-226 Project due at DP2 |
| A | B | A - B | |
| AG1-226 | $7,942,402 | $2,764,577 | $5,177,825 |
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
AG1-226 will interconnect with the AEP transmission system via a new station cut into the Eugene - Dequine 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) |
Work required for the new station tie-in |
$3,463,702 | $2,538,944 | $577,854 | $422,162 | $7,002,662 | $7,002,662 |
| (Pending) |
Review and revise (as needed) the protective relay settings at the Eugene 345 kV |
$146,060 | $31,397 | $82,884 | $18,728 | $279,069 | $279,069 |
| (Pending) |
Review and revise (as needed) the protective relay settings at the proposed AG1-237 345 kV Station |
$134,232 | $28,384 | $72,890 | $16,183 | $251,689 | $251,689 |
| (Pending) |
Review and revise (as needed) the protective relay settings at the Dequine 345 kV |
$23,657 | $6,026 | $19,989 | $5,092 | $54,764 | $54,764 |
| (Pending) |
Final Tie in for Fiber installation in New ROW |
$331,151 | $81,362 | $54,669 | $13,432 | $480,614 | $480,614 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) |
Construct a new 345 kV breaker and a half station, to be operated as a three (3) circuit breaker ring bus, initially expandable to six (6) circuit breakers |
$7,094,103 | $7,608,514 | $648,995 | $700,373 | $16,051,985 | $16,051,985 |
| (Pending) |
Fiber Installation in New ROW |
$6,008,977 | $1,487,051 | $1,177,654 | $279,014 | $8,952,696 | $8,952,696 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) |
Install necessary equipment and associated fiber for the generation lead line, and standard revenue metering package. |
$1,602,066 | $869,267 | $304,726 | $153,976 | $2,930,035 | $2,930,035 |
Developer Build Option
Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.
If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.
The cost estimates for eligible facilities and Option to Build oversight are highlighted below:
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) |
Work required for the new station tie-in |
$3,463,702 | $2,538,944 | $577,854 | $422,162 | $7,002,662 | $7,002,662 |
| (Pending) |
Review and revise (as needed) the protective relay settings at the Eugene 345 kV |
$146,060 | $31,397 | $82,884 | $18,728 | $279,069 | $279,069 |
| (Pending) |
Review and revise (as needed) the protective relay settings at the proposed AG1-237 345 kV Station |
$134,232 | $28,384 | $72,890 | $16,183 | $251,689 | $251,689 |
| (Pending) |
Review and revise (as needed) the protective relay settings at the Dequine 345 kV |
$23,657 | $6,026 | $19,989 | $5,092 | $54,764 | $54,764 |
| (Pending) |
Final Tie in for Fiber installation in New ROW |
$331,151 | $81,362 | $54,669 | $13,432 | $480,614 | $480,614 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) |
New Interconnection Substation (Oversight) |
$224,288 | $55,462 | $108,244 | $26,767 | $414,761 | $414,761 |
| (Pending) |
Fiber Installation in New ROW (Oversight) |
$13,201 | $1,850 | $13,083 | $1,833 | $29,967 | $29,967 |
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $36,003,514 | $36,003,514 | |||||
| Developer Build Option | $8,513,526 | $8,513,526 | |||||
Based on the scope of work for the Interconnection Facilities, it is expected to take 31 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.
The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. The maximum schedule is based off of AEP assumed long lead material ordering not considering allocation of existing material production slots, advanced progress enabled by Engineering and Procurement Agreements, or other schedule expediting methods. AEP may be able to allocate material production slots for long lead time materials to expedite this schedule. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to these agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.
Transmission Owner Analysis
No violations.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AG1-226 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.
Summer Peak Analysis
The New Service Request was evaluated as a 450.0 MW (142.0 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Summer Peak Analysis - Eliminated Flowgates | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | ||
| AEP/DEI |
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1 |
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1' OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1 /*05DEQUIN 345.0 - 05SULLIVAN 345.0 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1 /*05DEQUIN 345.0 - AG1-237 TP 345.0 END |
Tower | AC | 125.82 | 1374.0 | B | 1728.77 | 239.4 | ||
| AEP/OVEC |
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1 |
AEP_P1-2_#709_546_SRT-A
CONTINGENCY 'AEP_P1-2_#709_546_SRT-A' OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1 /*05HANG R 765.0 - 05JEFRSO 765.0 END |
Single | AC | 118.58 | 2255.0 | B | 2673.89 | 17.11 | ||
| AEP/DEI |
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1 |
AEP_P7-1_#11014___SRT-A-2
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-2' OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1 /*05DEQUIN 345.0 - 05SULLIVAN 345.0 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1 /*AG1-237 TP 345.0 - AG1-226 TP 345.0 END |
Tower | AC | 119.86 | 1374.0 | B | 1646.83 | 239.4 | ||
| AEP/DEI |
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1 |
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A' OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1 /*05DEQUIN 345.0 - 05MEADOW 345.0 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1 /*05DEQUIN 345.0 - AG1-237 TP 345.0 END |
Breaker | AC | 114.4 | 1374.0 | B | 1571.82 | 236.63 | ||
| AEP/OVEC |
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1 |
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A' OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1 /*05CORNU 765.0 - 05HANG R 765.0 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1 /*05CORNU 765.0 - 05CORNU 345.0 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1 /*05HANG R 765.0 - 05JEFRSO 765.0 REMOVE UNIT 1A FROM BUS 247245 /*05HRKG1A 18.0 REMOVE UNIT 1B FROM BUS 247246 /*05HRKG1B 18.0 REMOVE UNIT 1S FROM BUS 247247 /*05HRKG1S 18.0 REMOVE UNIT 2 FROM BUS 247249 /*05HRKG2B 18.0 REMOVE UNIT 2A FROM BUS 247248 /*05HRKG2A 18.0 REMOVE UNIT 2S FROM BUS 247250 /*05HRKG2S 18.0 END |
Breaker | AC | 137.5 | 2255.0 | B | 3100.62 | 54.08 | ||
| AEP/OVEC |
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1 |
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A' OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1 /*05HANG R 765.0 - 05JEFRSO 765.0 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1 /*05GRNTWN 765.0 - 05JEFRSO 765.0 END |
Breaker | AC | 160.8 | 2255.0 | B | 3625.96 | 38.4 | ||
| AEP |
05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2 |
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A' OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1 /*05HANG R 765.0 - 05JEFRSO 765.0 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1 /*05GRNTWN 765.0 - 05JEFRSO 765.0 END |
Breaker | AC | 117.07 | 3039.0 | B | 3557.81 | 38.4 | ||
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Summer Potential Congestion due to Local Energy Deliverability | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | ||
| AEP/NIPS |
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1 |
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A' OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2 /*05MEADOW 345.0 - 17REYNOLDS 345.0 END |
OP | AC | 163.85 | 1868.0 | B | 3060.81 | 199.65 | ||
| AEP/NIPS |
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2 |
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A' OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1 /*05MEADOW 345.0 - 17REYNOLDS 345.0 END |
OP | AC | 163.85 | 1868.0 | B | 3060.81 | 199.65 | ||
| AEP/IPL |
05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1 |
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A' OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1 /*05JEFRSO 765.0 - 05ROCKPT 765.0 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2 /*05ROCKPT 765.0 - 05RKG2 26.0 REMOVE UNIT 2H FROM BUS 243443 /*05RKG2 26.0 REMOVE UNIT 2L FROM BUS 243443 /*05RKG2 26.0 END |
OP | AC | 122.71 | 1506.0 | B | 1848.03 | 25.51 | ||
| AEP |
05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1 |
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A' OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2 /*05DEQUIN 345.0 - 05MEADOW 345.0 END |
OP | AC | 123.87 | 1958.0 | B | 2425.43 | 189.38 | ||
| AEP |
05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2 |
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A' OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1 /*05DEQUIN 345.0 - 05MEADOW 345.0 END |
OP | AC | 122.85 | 1958.0 | B | 2405.41 | 187.79 | ||
| AEP |
AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1 |
Base Case | OP | AC | 119.2 | 1409.0 | A | 1679.52 | 259.08 | ||
| AEP |
AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1 |
AEP_P1-2_#8905_1697_SRT-A
CONTINGENCY 'AEP_P1-2_#8905_1697_SRT-A' OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1 /*05DEQUIN 345.0 - 05SULLIVAN 345.0 END |
OP | AC | 113.64 | 1868.0 | B | 2122.85 | 249.63 | ||
| AEP |
AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line
963740 to 963840 ckt 1 |
Base Case | OP | AC | 111.29 | 1409.0 | A | 1568.06 | 259.08 | ||
| AEP |
05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1 |
AEP_P1-2_#8908_5621_SRT-A
CONTINGENCY 'AEP_P1-2_#8908_5621_SRT-A' OPEN BRANCH FROM BUS 247712 TO BUS 254529 CKT 1 /*05SULLIVAN 345.0 - 16PETE 345.0 END |
OP | AC | 108.36 | 4571.0 | B | 4953.3 | 45.6 | ||
| AEP |
05FALL C-05DESOTO 345.0 kV Ckt 1 line
243222 to 243218 ckt 1 |
AEP_P1-2_#534_SRT-A-1
CONTINGENCY 'AEP_P1-2_#534_SRT-A-1' OPEN BRANCH FROM BUS 243233 TO BUS 964350 CKT 1 /*05TANNER 345.0 - AG1-297 TP 345.0 END |
OP | AC | 107.34 | 1160.0 | B | 1245.09 | 25.8 | ||
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle #2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle #2.
Light Load Analysis
The New Service Request was evaluated as a 450.0 MW injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:
(No impacts were found for this analysis)
Light Load Potential Congestion due to Local Energy Deliverability
(No impacts were found for this analysis)
Short Circuit Analysis
Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests AF1-204 and AG1-226 in PJM Transition Cycle 1, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.
Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 131 contingencies were studied, each with a 20 second simulation time period. Studied faults included:
a) Steady-state operation (20 second run),
a) Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),
b) Single-phase bus faults with normal clearing time,
c) Single-phase faults with stuck breaker,
d) Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).
There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2027 peak load case:
a) Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AF1-204 and AG1-226 meet the 0.95 leading and lagging PF requirement.
The IPCMD and IQCMD states in the REGCAU1 models of AF1-204 showed erratic behavior for some contingencies in which AF1-204 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
AG1-226 exhibited slow reactive power recovery for contingencies P4.41,
P4.44, P7.01 and P7.04. This issue did not cause instability in the system and the model can be tuned to have faster reactive power output settlement upon request.
No mitigations were found to be required.
The stability study results in this report identified system performance issues. PJM is actively performing simulations to assess the impacts of potential dynamic model parameter changes required to address identified stability issues. Additionally, feedback from the Transmission Owner is being incorporated into the stability study. The study will be finalized at the conclusion of Phase III of Transition Cycle.
Table 1: TC1 Cluster 64 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
64 | AF1-204 | Wind | AEP | 255 | 255 | 63.75 | Eugene 345 kV |
AG1-226 | Solar | AEP | 450 | 450 | 142 | Eugene-Dequine 345 kV |
Reactive Power Analysis
The reactive power capability of AG1-226 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
(No dependencies were identified)
Affected Systems
In Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
Based on the Phase II analysis results, this project has potential cost responsibility for the following System Reinforcements:
| AG1-226 System Reinforcements Cost Breakdown: | Type | TO | RTEP ID / TO ID | Title | MW Impact | Percent Allocation | Allocated Cost ($USD) | |||
|---|---|---|---|---|---|---|---|---|---|---|
| Load Flow | AEP | n9243 / AEPSERG13 | Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles | 76.8 MW | 4.1% | $3,330,873 | ||||
| Load Flow | DEI | n9123 / DEI_TC1_13416 | MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP SE rating is 1868 MVA . | 239.4 MW | 26.5% | $2,009,513 | ||||
| Load Flow | AEP | n9260 / AEP_TC1_16006 | AEP end termination of new Eugene - Cayuga 345kV proposed second circuit reinforcement from MISO | 239.4 MW | 26.5% | $913,792 | ||||
| Load Flow | AEP | n7964 / AEPI0025a | Replace 765/345 Transformer | 38.4 MW | 4.2% | $205,573 | ||||
| Load Flow | AEP | n4106.4 | Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. | 38.4 MW | 4.0% | $81,017 | ||||
| Load Flow | AEP | n7943.2 / AEPI0025b | Replace Jefferson 345kV Circuit Breaker (5000A) | 38.4 MW | 4.2% | $41,115 | ||||
| Load Flow | AEP | n4106.6 / AEPI0045e | Replace Jefferson Breaker (5000A) | 38.4 MW | 4.0% | $38,888 | ||||
| Load Flow | OVEC | n9185 / OVECPJH01 | Replace 5" Al Tubing 345 kV bus at Clifty Creek | 38.4 MW | 4.0% | $12,464 | ||||
| Load Flow | AEP | n4106.5 / AEPI0045c | Replace Clifty Bus 5"0 AL Tubular Sch 40 | 38.4 MW | 4.0% | $3,241 | ||||
| Load Flow | AEP | n4106.7 / AEPI0045f | An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. | 38.4 MW | 4.0% | $810 | ||||
| Load Flow | AEP | n9180 / AEPSERG09 | Jefferson CT thermal limit | 38.4 MW | 4.0% | $623 | ||||
| Load Flow | AEP | n9181 / AEPSERG10 | Clifty relay thermal limit | 38.4 MW | 4.0% | $623 | ||||
| Grand Total: | $6,638,532 | |||||||||
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n9243 / AEPSERG13 | Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles | $130,000,000 | $3,330,873 | 36 to 48 Months | |||
ContributorTopology Changing Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.
Description: There is no bigger 765/345 kV transformer in the AEP system than the transformer at Jefferson station or a bigger 345 kV breaker than the Jefferson 345 kV breaker to be able to upgrade to a bigger size. Expand 345 kV north of Jefferson station install a second 765/345 kV 750 MVA transformer, install a 345 kV low side breaker and install a second Jefferson - Clifty Creek 345 kV single circuit line ~0.8 miles. Install new 765 kV breaker "B2" at the existing Jefferson station and 765 kV line than ~0.25 miles to connect to the new 765/345 750 MVA transformer. Install a 345 kV circuit breaker at Clifty Creek OVEC station. This reinforcement will reduce loadings on the branch and mitigations for limiting elements due to lower loadings may no longer be required. This reinforcement should reduce loadings such that no further mitigation is needed for TC1 PH2.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | SUM | B | 3040.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 1.3% | $1,053,578 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
468.4 MW | 24.9% | $20,315,887 |
| AF1-204 | 25.6 MW | 1.4% | $1,110,826 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
468.4 MW | 24.9% | $20,315,887 |
| AG1-226 | 76.8 MW | 4.1% | $3,330,873 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.1% | $105,692 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
203.7 MW | 10.8% | $8,835,170 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
203.7 MW | 10.8% | $8,835,170 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
203.7 MW | 10.8% | $8,835,170 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
203.7 MW | 10.8% | $8,835,170 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | DEI | n9123 / DEI_TC1_13416 | MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP SE rating is 1868 MVA . | $12,095,000 | $2,009,513 | TBD | |||
ContributorTopology Changing Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.
Description: AEP SE rating is 1868 MVA . MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP end cost TBD.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (All) | A | 9999.0 MVA |
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (All) | B | 9999.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-223
⧉
McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-223, AF2-225 |
11.5 MW | 1.3% | $96,524 |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
26.6 MW | 2.9% | $223,182 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
126.7 MW | 14.0% | $1,063,909 |
| AF1-204 | 135.7 MW | 15.0% | $1,138,869 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
126.7 MW | 14.0% | $1,063,909 |
|
AF2-225
⧉
McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-223, AF2-225 |
11.5 MW | 1.3% | $96,524 |
| AF2-407 | 32.7 MW | 3.6% | $274,403 |
| AG1-226 | 239.4 MW | 26.5% | $2,009,513 |
| AG1-236 | 17.2 MW | 1.9% | $144,269 |
| AG1-297 | 31.5 MW | 3.5% | $264,754 |
| AG1-374 | 23.7 MW | 2.6% | $199,133 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.7 MW | 0.3% | $22,395 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $248,020 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $248,020 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $248,020 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $248,020 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n9260 / AEP_TC1_16006 | AEP end termination of new Eugene - Cayuga 345kV proposed second circuit reinforcement from MISO | $5,500,000 | $913,792 | 36 Months | |||
ContributorTopology Changing Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.
Description: Add a new breaker string with 2 new breakers and associated equipment to the Eugene station. Raise a double circuit tower so that the new second Eugene - Cayuga 345kV can be routed underneath it.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (Any) |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-223
⧉
McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-223, AF2-225 |
11.5 MW | 1.3% | $43,893 |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
26.6 MW | 2.9% | $101,488 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
126.7 MW | 14.0% | $483,795 |
| AF1-204 | 135.7 MW | 15.0% | $517,882 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
126.7 MW | 14.0% | $483,795 |
|
AF2-225
⧉
McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-223, AF2-225 |
11.5 MW | 1.3% | $43,893 |
| AF2-407 | 32.7 MW | 3.6% | $124,780 |
| AG1-226 | 239.4 MW | 26.5% | $913,792 |
| AG1-236 | 17.2 MW | 1.9% | $65,604 |
| AG1-297 | 31.5 MW | 3.5% | $120,392 |
| AG1-374 | 23.7 MW | 2.6% | $90,552 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.7 MW | 0.3% | $10,184 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $112,783 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $112,783 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $112,783 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
29.5 MW | 3.3% | $112,783 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n7964 / AEPI0025a | Replace 765/345 Transformer | $7,800,000 | $205,573 | 24 to 36 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: Replace 765/345 Transformer
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (All) | A | 3113.0 MVA |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (All) | B | 3113.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 25.6% | $1,253,846 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 25.6% | $1,253,846 |
| AG1-226 | 38.4 MW | 4.2% | $205,573 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $545,285 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $545,285 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $545,285 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $545,285 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n4106.4 | Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. | $3,250,000 | $81,017 | 24 to 36 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | A | 2365.0 MVA |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 3290.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $51,253 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $494,146 |
| AF1-204 | 25.6 MW | 2.6% | $54,037 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $494,146 |
| AG1-226 | 38.4 MW | 4.0% | $81,017 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $5,142 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $214,899 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $214,899 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $214,899 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $214,899 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n7943.2 / AEPI0025b | Replace Jefferson 345kV Circuit Breaker (5000A) | $1,560,000 | $41,115 | 18 to 24 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: Replace Jefferson 345kV Circuit Breaker (5000A)
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (All) | A | 3426.0 MVA |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (All) | B | 3582.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 25.6% | $250,769 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 25.6% | $250,769 |
| AG1-226 | 38.4 MW | 4.2% | $41,115 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $109,057 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $109,057 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $109,057 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 11.1% | $109,057 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n4106.6 / AEPI0045e | Replace Jefferson Breaker (5000A) | $1,560,000 | $38,888 | 18 to 24 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: Replace Jefferson Breaker (5000A)
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | A | 3290.0 MVA |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 3290.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $24,601 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $237,190 |
| AF1-204 | 25.6 MW | 2.6% | $25,938 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $237,190 |
| AG1-226 | 38.4 MW | 4.0% | $38,888 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $2,468 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $103,151 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $103,151 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $103,151 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $103,151 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | OVEC | n9185 / OVECPJH01 | Replace 5" Al Tubing 345 kV bus at Clifty Creek | $500,000 | $12,464 | 18 to 24 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: Replace 5" Al Tubing 345 kV bus at Clifty Creek. Note: From AEP: AEP owns a potion of the is bus as well due to split ownership of the station
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 3039.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $7,885 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $76,022 |
| AF1-204 | 25.6 MW | 2.6% | $8,313 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $76,022 |
| AG1-226 | 38.4 MW | 4.0% | $12,464 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $791 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $33,061 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $33,061 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $33,061 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $33,061 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n4106.5 / AEPI0045c | Replace Clifty Bus 5"0 AL Tubular Sch 40 | $130,000 | $3,241 | 18 to 24 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: Replace Clifty Bus 5"0 AL Tubular Sch 40
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | A | 2365.0 MVA |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 2831.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $2,050 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $19,766 |
| AF1-204 | 25.6 MW | 2.6% | $2,161 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $19,766 |
| AG1-226 | 38.4 MW | 4.0% | $3,241 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $206 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $8,596 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $8,596 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $8,596 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $8,596 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n4106.7 / AEPI0045f | An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. | $32,500 | $810 | 12 to 18 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: An engineering study will need to be conducted to determine if the Jefferson Relay Compliance Trip limits 5506 Amps settings can be adjusted to mitigate the overload. New relay packages will be required if the settings cannot be adjusted. Estimated Cost: $600,000.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | A | 3426.0 MVA |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 3581.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $513 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $4,941 |
| AF1-204 | 25.6 MW | 2.6% | $540 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $4,941 |
| AG1-226 | 38.4 MW | 4.0% | $810 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $51 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $2,149 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $2,149 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $2,149 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $2,149 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n9180 / AEPSERG09 | Jefferson CT thermal limit | $25,000 | $623 | 12 to 18 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: An engineering study will need to be conducted to determine if the Jefferson CT thermal limitsettings can be adjusted to mitigate the overload.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | A | 3426.0 MVA |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 3736.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $394 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $3,801 |
| AF1-204 | 25.6 MW | 2.6% | $416 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $3,801 |
| AG1-226 | 38.4 MW | 4.0% | $623 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $40 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
| System Reinforcement | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| Type | TO | RTEP ID / TO ID | Title | Total Cost ($USD) | Allocated Cost ($USD) | Time Estimate | |||
| Load Flow | AEP | n9181 / AEPSERG10 | Clifty relay thermal limit | $25,000 | $623 | 12 to 18 Months | |||
ContributorEliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report. Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Description: An engineering study will need to be conducted to determine if the Clifty Relay Thermal limits settings can be adjusted to mitigate the overload.
| Flowgates Addressed by this Reinforcement | |
|---|---|
| Facility | Contingency |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (Any) |
| New Ratings | |||
|---|---|---|---|
| Facility | Rating Set | Rating Type | Rating Value |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line | (All) | B | 3426.0 MVA |
| Cost Allocation | |||
|---|---|---|---|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|
AE2-261
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
24.3 MW | 2.5% | $394 |
|
AF1-088
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $3,801 |
| AF1-204 | 25.6 MW | 2.6% | $416 |
|
AF2-008
⧉
Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF1-088, AF2-008 |
234.2 MW | 24.2% | $3,801 |
| AG1-226 | 38.4 MW | 4.0% | $623 |
|
AG1-460
⧉
Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 |
2.4 MW | 0.3% | $40 |
|
AG1-522
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
|
AG1-523
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
|
AG1-524
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
|
AG1-525
⧉
Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG1-522, AG1-523, AG1-524, AG1-525 |
101.9 MW | 10.5% | $1,653 |
Attachments
[1]Winter load flow analysis will be performed starting in Transition Cycle #2.