AG1-226 Phase II Study Report

v1.00 released 2024-12-18 14:06

Eugene-Dequine 345 kV

142.0 MW Capacity / 450.0 MW Energy

Introduction

This Phase II System Impact Study Report (PH2) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle #1. The Project Developer/Eligible Customer (developer) is Dolphin Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Electric Power.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
  1. PJM will retool load flow results from Phase I System Impact Study (summer peak, winter peak[1] and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $39,712,012 $27,645,774 = 1.44 AND ( $39,712,012 - $27,645,774 ) 450.0 = $26,814 per MW

General

The Project Developer has proposed a Solar generating facility located in the American Electric Power zone — Fountain County, Indiana. The installed facilities will have a total capability of 450.0 MW with 142.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number AG1-226
Project Name Eugene-Dequine 345 kV
Project Developer Name Dolphin Solar LLC
State Indiana
County Fountain
Transmission Owner American Electric Power
MFO 450.0 MW
MWE 450.0 MW
MWC 142.0 MW
Fuel Type Solar
Basecase Study Year 2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-226 will interconnect on the AEP transmission system tapping the Eugene to Dequine 345 kV line.

 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AG1-226 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
Description Cost Allocated to AG1-226 Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF) $2,930,035 $0
Other Scope $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $25,004,681 $25,004,681
Network Upgrades $8,068,798 $8,068,798
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $6,638,533 $6,638,533
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements $0 $0
Total $42,642,047 $39,712,012

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase 2 SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AG1-226

Readiness Deposit #3 has been calculated for the AG1-226 project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID 20% of cost allocation for Phase II Network Upgrades Sum of Readiness Deposit #1 & Readiness Deposit #2 Received (RD1+RD2) Readiness Deposit #3 (RD3) for AG1-226 Project due at DP2
A B A - B
AG1-226 $7,942,402 $2,764,577 $5,177,825

Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

AG1-226 will interconnect with the AEP transmission system via a new station cut into the Eugene - Dequine 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Work required for the new station tie-in

$3,463,702 $2,538,944 $577,854 $422,162 $7,002,662 $7,002,662
(Pending)

Review and revise (as needed) the protective relay settings at the Eugene 345 kV

$146,060 $31,397 $82,884 $18,728 $279,069 $279,069
(Pending)

Review and revise (as needed) the protective relay settings at the proposed AG1-237 345 kV Station

$134,232 $28,384 $72,890 $16,183 $251,689 $251,689
(Pending)

Review and revise (as needed) the protective relay settings at the Dequine 345 kV

$23,657 $6,026 $19,989 $5,092 $54,764 $54,764
(Pending)

Final Tie in for Fiber installation in New ROW

$331,151 $81,362 $54,669 $13,432 $480,614 $480,614
Stand-Alone Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Construct a new 345 kV breaker and a half station, to be operated as a three (3) circuit breaker ring bus, initially expandable to six (6) circuit breakers

$7,094,103 $7,608,514 $648,995 $700,373 $16,051,985 $16,051,985
(Pending)

Fiber Installation in New ROW

$6,008,977 $1,487,051 $1,177,654 $279,014 $8,952,696 $8,952,696
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Install necessary equipment and associated fiber for the generation lead line, and standard revenue metering package.

$1,602,066 $869,267 $304,726 $153,976 $2,930,035 $2,930,035
Developer Build Option

Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.

If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Work required for the new station tie-in

$3,463,702 $2,538,944 $577,854 $422,162 $7,002,662 $7,002,662
(Pending)

Review and revise (as needed) the protective relay settings at the Eugene 345 kV

$146,060 $31,397 $82,884 $18,728 $279,069 $279,069
(Pending)

Review and revise (as needed) the protective relay settings at the proposed AG1-237 345 kV Station

$134,232 $28,384 $72,890 $16,183 $251,689 $251,689
(Pending)

Review and revise (as needed) the protective relay settings at the Dequine 345 kV

$23,657 $6,026 $19,989 $5,092 $54,764 $54,764
(Pending)

Final Tie in for Fiber installation in New ROW

$331,151 $81,362 $54,669 $13,432 $480,614 $480,614
Other
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

New Interconnection Substation (Oversight)

$224,288 $55,462 $108,244 $26,767 $414,761 $414,761
(Pending)

Fiber Installation in New ROW (Oversight)

$13,201 $1,850 $13,083 $1,833 $29,967 $29,967
Build Option Price Comparison
Build Option Total Cost Allocated Cost
Transmission Owner Build Option $36,003,514 $36,003,514
Developer Build Option $8,513,526 $8,513,526

Based on the scope of work for the Interconnection Facilities, it is expected to take 31 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. The maximum schedule is based off of AEP assumed long lead material ordering not considering allocation of existing material production slots, advanced progress enabled by Engineering and Procurement Agreements, or other schedule expediting methods. AEP may be able to allocate material production slots for long lead time materials to expedite this schedule. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to these agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No violations.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AG1-226 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 450.0 MW (142.0 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Summer Peak Analysis - Eliminated Flowgates
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Tower AC 125.82 1374.0 B 1728.77 239.4
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P1-2_#709_546_SRT-A
CONTINGENCY 'AEP_P1-2_#709_546_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Single AC 118.58 2255.0 B 2673.89 17.11
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-2
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-2'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TP   345.0 - AG1-226 TP   345.0
END
Tower AC 119.86 1374.0 B 1646.83 239.4
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Breaker AC 114.4 1374.0 B 1571.82 236.63
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2 FROM BUS 247249                     /*05HRKG2B      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Breaker AC 137.5 2255.0 B 3100.62 54.08
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 160.8 2255.0 B 3625.96 38.4
AEP 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 117.07 3039.0 B 3557.81 38.4

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Tower AC 125.82 1374.0 B 1728.77 239.4
Elimination
Base Case Details for Eliminated Flowgate 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-1
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 14.23 MW 12.1 MW
965092 AG1-374 E Adder 9.49 MW 8.07 MW
965911 AG1-460 C Adder 1.07 MW 0.91 MW
965912 AG1-460 E Adder 1.6 MW 1.36 MW
966531 AG1-522 C Adder 17.73 MW 15.07 MW
966532 AG1-522 E Adder 11.82 MW 10.05 MW
966541 AG1-523 C Adder 17.73 MW 15.07 MW
966542 AG1-523 E Adder 11.82 MW 10.05 MW
966551 AG1-524 C Adder 17.73 MW 15.07 MW
966552 AG1-524 E Adder 11.82 MW 10.05 MW
966561 AG1-525 C Adder 17.73 MW 15.07 MW
966562 AG1-525 E Adder 11.82 MW 10.05 MW
290261 S-027 E Adder 12.91 MW 10.97 MW
290265 S-028 E Adder 12.83 MW 10.9 MW
936771 AD2-100 C Adder 11.14 MW 9.46 MW
936772 AD2-100 E Adder 7.42 MW 6.31 MW
936971 AD2-131 C Adder 0.73 MW 0.62 MW
936972 AD2-131 E Adder 3.69 MW 3.13 MW
942111 AE2-223 C Adder 1.5 MW 1.27 MW
942112 AE2-223 E Adder 10.0 MW 8.5 MW
942481 AE2-261 C Adder 15.95 MW 13.56 MW
942482 AE2-261 E Adder 10.64 MW 9.04 MW
959341 AF2-225 C Adder 4.83 MW 4.11 MW
959342 AF2-225 E Adder 6.67 MW 5.67 MW
959611 AF2-252 C Adder 1.58 MW 1.34 MW
959612 AF2-252 E Adder 2.37 MW 2.02 MW
960611 AF2-352 C Adder 1.58 MW 1.34 MW
960612 AF2-352 E Adder 2.37 MW 2.02 MW
276615 W2-048 GEN Adder 5.06 MW 4.3 MW
276621 X2-022 GEN Adder 17.3 MW 14.71 MW
917502 Z2-087 E Adder 13.34 MW 11.34 MW
957381 AF2-032 C Adder 1.21 MW 1.03 MW
957382 AF2-032 E Adder 0.57 MW 0.48 MW
274890 CAYUG;1U E Adder 6.43 MW 5.47 MW
274891 CAYUG;2U E Adder 6.43 MW 5.47 MW
925772 AC1-053 E Adder 16.61 MW 14.12 MW
933441 AC2-157 C 50/50 9.63 MW 9.63 MW
933442 AC2-157 E 50/50 15.72 MW 15.72 MW
276174 W4-005 E Adder 25.37 MW 21.57 MW
924048 AB2-047 E1 Adder 8.27 MW 7.03 MW
924049 AB2-047 E2 Adder 8.4 MW 7.14 MW
924266 AB2-070 E Adder 15.18 MW 12.9 MW
942601 AE2-276 C 50/50 6.34 MW 6.34 MW
945391 AF1-204 C 50/50 33.92 MW 33.92 MW
945392 AF1-204 E 50/50 101.76 MW 101.76 MW
960141 AF2-305_AG1- Adder 0.89 MW 0.75 MW
930461 AB1-087 C 50/50 69.71 MW 69.71 MW
930462 AB1-087 E 50/50 3.17 MW 3.17 MW
930471 AB1-088 C 50/50 69.71 MW 69.71 MW
930472 AB1-088 E 50/50 3.17 MW 3.17 MW
939741 AE1-205 C Adder 6.44 MW 5.47 MW
939742 AE1-205 E Adder 8.89 MW 7.56 MW
963741 AG1-226 C 50/50 75.54 MW 75.54 MW
963742 AG1-226 E 50/50 163.85 MW 163.85 MW
963831 AG1-236 C Adder 2.23 MW 1.9 MW
963832 AG1-236 E Adder 14.95 MW 12.71 MW
963841 AG1-237 C 50/50 13.83 MW 13.83 MW
963842 AG1-237 E 50/50 92.56 MW 92.56 MW
941731 AE2-173 C Adder 3.83 MW 3.26 MW
944221 AF1-090 C Adder 3.06 MW 2.6 MW
944222 AF1-090 E Adder 14.3 MW 12.16 MW
957142 AF2-008 NFTI 50/50 63.37 MW 63.37 MW
944201 AF1-088 FTIR 50/50 126.75 MW 126.75 MW
957141 AF2-008 FTIR 50/50 63.37 MW 63.37 MW
956282 J1115 C External Queue 3.15 MW 3.15 MW
956283 J1115 E External Queue 17.07 MW 17.07 MW
956452 J1139 External Queue 34.87 MW 34.87 MW
990672 J1360 External Queue 49.15 MW 49.15 MW
991237 J1676 C External Queue 4.73 MW 4.73 MW
991238 J1676 E External Queue 12.87 MW 12.87 MW
991562 J2178 External Queue -10.88 MW -10.88 MW
991577 J2192 C External Queue 5.2 MW 5.2 MW
991578 J2192 E External Queue 28.14 MW 28.14 MW
991622 J2232 External Queue -10.37 MW -10.37 MW
991627 J2233 G External Queue 33.38 MW 33.38 MW
992572 J1022 External Queue 23.24 MW 23.24 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 30.82 MW 30.82 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.63 MW 4.63 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.1 MW 0.1 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.64 MW 0.64 MW
NY PJM->LTFIMP_NY CLTF 0.34 MW 0.34 MW
WEC LTFEXP_WEC->PJM CLTF 1.06 MW 1.06 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.04 MW 0.04 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
TVA LTFEXP_TVA->PJM CLTF 1.25 MW 1.25 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.82 MW 0.82 MW
MEC LTFEXP_MEC->PJM CLTF 6.04 MW 6.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.71 MW 2.71 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.78 MW 2.78 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.08 MW 4.08 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.1 MW 0.1 MW

Details for 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P1-2_#709_546_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P1-2_#709_546_SRT-A
CONTINGENCY 'AEP_P1-2_#709_546_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Single AC 118.58 2255.0 B 2673.89 17.11
Elimination
Base Case Details for Eliminated Flowgate 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P1-2_#709_546_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243353 05OLIVE 80/20 0.08 MW 0.08 MW
966841 AG1-555 C 80/20 11.53 MW 11.53 MW
965681 AG1-436 C 80/20 7.89 MW 7.89 MW
966431 AG1-512 C Adder 1.61 MW 1.37 MW
966531 AG1-522 C 80/20 41.81 MW 41.81 MW
966541 AG1-523 C 80/20 41.81 MW 41.81 MW
966551 AG1-524 C 80/20 41.81 MW 41.81 MW
966561 AG1-525 C 80/20 41.81 MW 41.81 MW
934721 AD1-100 C Adder 15.04 MW 12.78 MW
960681 AF2-359 C 80/20 7.89 MW 7.89 MW
243441 05CKG2 80/20 19.41 MW 19.41 MW
243442 05RKG1 80/20 62.56 MW 62.56 MW
243443 05RKG2 80/20 61.72 MW 61.72 MW
243859 05FR-11G C 80/20 0.51 MW 0.51 MW
243862 05FR-12G C 80/20 0.25 MW 0.25 MW
243864 05FR-21G C 80/20 0.26 MW 0.26 MW
243866 05FR-22G C 80/20 0.26 MW 0.26 MW
243870 05FR-3G C 80/20 0.25 MW 0.25 MW
243873 05FR-4G C 80/20 0.57 MW 0.57 MW
244415 05OLIV SLR C 80/20 0.04 MW 0.04 MW
274751 CRETE EC ;1U 80/20 1.16 MW 1.16 MW
274752 CRETE EC ;2U 80/20 1.16 MW 1.16 MW
274753 CRETE EC ;3U 80/20 1.16 MW 1.16 MW
274754 CRETE EC ;4U 80/20 1.16 MW 1.16 MW
274770 LINCOLN ;1U 80/20 1.19 MW 1.19 MW
274771 LINCOLN ;2U 80/20 1.19 MW 1.19 MW
274772 LINCOLN ;3U 80/20 1.19 MW 1.19 MW
274773 LINCOLN ;4U 80/20 1.19 MW 1.19 MW
274774 LINCOLN ;5U 80/20 1.19 MW 1.19 MW
274775 LINCOLN ;6U 80/20 1.19 MW 1.19 MW
274776 LINCOLN ;7U 80/20 1.19 MW 1.19 MW
274777 LINCOLN ;8U 80/20 1.19 MW 1.19 MW
274788 SE CHICAG;5U Adder 3.74 MW 3.18 MW
274789 SE CHICAG;6U Adder 3.74 MW 3.18 MW
274790 SE CHICAG;7U Adder 3.74 MW 3.18 MW
274791 SE CHICAG;8U Adder 3.74 MW 3.18 MW
274792 SE CHICAG;9U 80/20 3.75 MW 3.75 MW
274793 SE CHICAG;0U 80/20 3.75 MW 3.75 MW
274794 SE CHICAG;1U 80/20 3.75 MW 3.75 MW
274795 SE CHICAG;2U 80/20 3.75 MW 3.75 MW
933411 AC2-154 C Adder 1.9 MW 1.62 MW
946581 AF1-322 C 80/20 11.2 MW 11.2 MW
958021 AF2-096 C Adder 18.04 MW 15.34 MW
246909 05MDL-1G C 80/20 0.52 MW 0.52 MW
246910 05MDL-2G C 80/20 0.31 MW 0.31 MW
246976 05MDL-3G C 80/20 0.31 MW 0.31 MW
246979 05MDL-4G C 80/20 0.24 MW 0.24 MW
933441 AC2-157 C 80/20 12.9 MW 12.9 MW
270100 AB1-080 CT1 80/20 3.71 MW 3.71 MW
270101 AB1-080 CT2 80/20 3.71 MW 3.71 MW
270102 AB1-080 ST 80/20 4.02 MW 4.02 MW
247556 05MDL-5G 80/20 0.41 MW 0.41 MW
270180 AB1-006 W1 80/20 0.46 MW 0.46 MW
270181 AB1-006 W2 80/20 0.07 MW 0.07 MW
936371 AD2-047 C Adder 3.41 MW 2.9 MW
936461 AD2-060 C Adder 2.0 MW 1.7 MW
942521 AE2-267 C Adder -2.97 MW -2.52 MW
942601 AE2-276 C 80/20 8.48 MW 8.48 MW
945391 AF1-204 C 80/20 6.62 MW 6.62 MW
945421 AF1-207 C 80/20 4.57 MW 4.57 MW
945501 AF1-215 C 80/20 3.09 MW 3.09 MW
959001 AF2-191 C Adder 6.68 MW 5.68 MW
959141 AF2-205 C 80/20 15.32 MW 15.32 MW
960591 AF2-350 C Adder 6.01 MW 5.11 MW
961501 AF2-441 C Adder 8.07 MW 6.86 MW
930461 AB1-087 C 80/20 93.34 MW 93.34 MW
930471 AB1-088 C 80/20 93.34 MW 93.34 MW
939351 AE1-166 C Adder 7.82 MW 6.65 MW
940581 AE2-045 C 80/20 10.9 MW 10.9 MW
963741 AG1-226 C 80/20 17.11 MW 17.11 MW
963841 AG1-237 C 80/20 3.25 MW 3.25 MW
964361 AG1-298 C Adder 50.55 MW 42.97 MW
964401 AG1-302 C 80/20 22.36 MW 22.36 MW
941551 AE2-152 C Adder 9.02 MW 7.67 MW
957371 AF2-031 C Adder 0.81 MW 0.69 MW
957841 AF2-078 C 80/20 16.12 MW 16.12 MW
958011 AF2-095 C Adder 9.62 MW 8.18 MW
958381 AF2-132 C 80/20 22.36 MW 22.36 MW
958391 AF2-133 C 80/20 22.77 MW 22.77 MW
958401 AF2-134 C 80/20 1.03 MW 1.03 MW
964861 AG1-349 C 80/20 19.49 MW 19.49 MW
965791 AG1-447 C 80/20 5.79 MW 5.79 MW
945351 AF1-200 FTIR Adder 238.3 MW 202.55 MW
944201 AF1-088 FTIR 80/20 169.7 MW 169.7 MW
957141 AF2-008 FTIR 80/20 84.85 MW 84.85 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 115.9 MW 115.9 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 18.91 MW 18.91 MW
NY PJM->LTFIMP_NY CLTF 0.98 MW 0.98 MW
WEC LTFEXP_WEC->PJM CLTF 3.06 MW 3.06 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 1.24 MW 1.24 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.75 MW 0.75 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 10.23 MW 10.23 MW
MEC LTFEXP_MEC->PJM CLTF 11.6 MW 11.6 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 29.29 MW 29.29 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.92 MW 1.92 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.63 MW 1.63 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-2


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-2
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-2'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TP   345.0 - AG1-226 TP   345.0
END
Tower AC 119.86 1374.0 B 1646.83 239.4
Elimination
Base Case Details for Eliminated Flowgate 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-2
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 14.23 MW 12.1 MW
965092 AG1-374 E Adder 9.49 MW 8.07 MW
965911 AG1-460 C Adder 1.07 MW 0.91 MW
965912 AG1-460 E Adder 1.6 MW 1.36 MW
966531 AG1-522 C Adder 17.73 MW 15.07 MW
966532 AG1-522 E Adder 11.82 MW 10.05 MW
966541 AG1-523 C Adder 17.73 MW 15.07 MW
966542 AG1-523 E Adder 11.82 MW 10.05 MW
966551 AG1-524 C Adder 17.73 MW 15.07 MW
966552 AG1-524 E Adder 11.82 MW 10.05 MW
966561 AG1-525 C Adder 17.73 MW 15.07 MW
966562 AG1-525 E Adder 11.82 MW 10.05 MW
290261 S-027 E Adder 12.91 MW 10.97 MW
290265 S-028 E Adder 12.83 MW 10.9 MW
936771 AD2-100 C Adder 11.14 MW 9.46 MW
936772 AD2-100 E Adder 7.42 MW 6.31 MW
936971 AD2-131 C Adder 0.73 MW 0.62 MW
936972 AD2-131 E Adder 3.69 MW 3.13 MW
942111 AE2-223 C Adder 1.5 MW 1.27 MW
942112 AE2-223 E Adder 10.0 MW 8.5 MW
942481 AE2-261 C Adder 15.95 MW 13.56 MW
942482 AE2-261 E Adder 10.64 MW 9.04 MW
959341 AF2-225 C Adder 4.83 MW 4.11 MW
959342 AF2-225 E Adder 6.67 MW 5.67 MW
959611 AF2-252 C Adder 1.58 MW 1.34 MW
959612 AF2-252 E Adder 2.37 MW 2.02 MW
960611 AF2-352 C Adder 1.58 MW 1.34 MW
960612 AF2-352 E Adder 2.37 MW 2.02 MW
276615 W2-048 GEN Adder 5.06 MW 4.3 MW
276621 X2-022 GEN Adder 17.3 MW 14.71 MW
917502 Z2-087 E Adder 13.34 MW 11.34 MW
957381 AF2-032 C Adder 1.21 MW 1.03 MW
957382 AF2-032 E Adder 0.57 MW 0.48 MW
274890 CAYUG;1U E Adder 6.43 MW 5.47 MW
274891 CAYUG;2U E Adder 6.43 MW 5.47 MW
925772 AC1-053 E Adder 16.61 MW 14.12 MW
933441 AC2-157 C 50/50 9.63 MW 9.63 MW
933442 AC2-157 E 50/50 15.72 MW 15.72 MW
276174 W4-005 E Adder 25.37 MW 21.57 MW
924048 AB2-047 E1 Adder 8.27 MW 7.03 MW
924049 AB2-047 E2 Adder 8.4 MW 7.14 MW
924266 AB2-070 E Adder 15.18 MW 12.9 MW
942601 AE2-276 C 50/50 6.34 MW 6.34 MW
945391 AF1-204 C 50/50 33.92 MW 33.92 MW
945392 AF1-204 E 50/50 101.76 MW 101.76 MW
960141 AF2-305_AG1- Adder 0.89 MW 0.75 MW
930461 AB1-087 C 50/50 69.71 MW 69.71 MW
930462 AB1-087 E 50/50 3.17 MW 3.17 MW
930471 AB1-088 C 50/50 69.71 MW 69.71 MW
930472 AB1-088 E 50/50 3.17 MW 3.17 MW
939741 AE1-205 C Adder 6.44 MW 5.47 MW
939742 AE1-205 E Adder 8.89 MW 7.56 MW
963741 AG1-226 C 50/50 75.54 MW 75.54 MW
963742 AG1-226 E 50/50 163.85 MW 163.85 MW
963831 AG1-236 C Adder 2.23 MW 1.9 MW
963832 AG1-236 E Adder 14.95 MW 12.71 MW
941731 AE2-173 C Adder 3.83 MW 3.26 MW
944221 AF1-090 C Adder 3.06 MW 2.6 MW
944222 AF1-090 E Adder 14.3 MW 12.16 MW
957142 AF2-008 NFTI 50/50 63.37 MW 63.37 MW
944201 AF1-088 FTIR 50/50 126.75 MW 126.75 MW
957141 AF2-008 FTIR 50/50 63.37 MW 63.37 MW
956282 J1115 C External Queue 3.15 MW 3.15 MW
956283 J1115 E External Queue 17.07 MW 17.07 MW
956452 J1139 External Queue 34.87 MW 34.87 MW
956822 J1180 G External Queue 7.46 MW 7.46 MW
990672 J1360 External Queue 49.15 MW 49.15 MW
991237 J1676 C External Queue 4.73 MW 4.73 MW
991238 J1676 E External Queue 25.56 MW 25.56 MW
991562 J2178 External Queue -10.88 MW -10.88 MW
991577 J2192 C External Queue 5.2 MW 5.2 MW
991578 J2192 E External Queue 28.14 MW 28.14 MW
991622 J2232 External Queue -10.37 MW -10.37 MW
991627 J2233 G External Queue 33.38 MW 33.38 MW
992572 J1022 External Queue 23.24 MW 23.24 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 30.82 MW 30.82 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.63 MW 4.63 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.1 MW 0.1 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.64 MW 0.64 MW
NY PJM->LTFIMP_NY CLTF 0.34 MW 0.34 MW
WEC LTFEXP_WEC->PJM CLTF 1.06 MW 1.06 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.04 MW 0.04 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
TVA LTFEXP_TVA->PJM CLTF 1.25 MW 1.25 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.82 MW 0.82 MW
MEC LTFEXP_MEC->PJM CLTF 6.04 MW 6.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.71 MW 2.71 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.78 MW 2.78 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.08 MW 4.08 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.1 MW 0.1 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P4_#4697_05DEQUIN 345_B_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Breaker AC 114.4 1374.0 B 1571.82 236.63
Elimination
Base Case Details for Eliminated Flowgate 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P4_#4697_05DEQUIN 345_B_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 14.03 MW 11.93 MW
965092 AG1-374 E Adder 9.36 MW 7.95 MW
965911 AG1-460 C Adder 1.03 MW 0.87 MW
965912 AG1-460 E Adder 1.54 MW 1.31 MW
966531 AG1-522 C Adder 15.37 MW 13.07 MW
966532 AG1-522 E Adder 10.25 MW 8.71 MW
966541 AG1-523 C Adder 15.37 MW 13.07 MW
966542 AG1-523 E Adder 10.25 MW 8.71 MW
966551 AG1-524 C Adder 15.37 MW 13.07 MW
966552 AG1-524 E Adder 10.25 MW 8.71 MW
966561 AG1-525 C Adder 15.37 MW 13.07 MW
966562 AG1-525 E Adder 10.25 MW 8.71 MW
290261 S-027 E Adder 12.72 MW 10.82 MW
290265 S-028 E Adder 12.65 MW 10.75 MW
936771 AD2-100 C Adder 10.7 MW 9.1 MW
936772 AD2-100 E Adder 7.14 MW 6.07 MW
936971 AD2-131 C Adder 0.7 MW 0.6 MW
936972 AD2-131 E Adder 3.54 MW 3.01 MW
942111 AE2-223 C Adder 1.48 MW 1.26 MW
942112 AE2-223 E Adder 9.91 MW 8.42 MW
942481 AE2-261 C Adder 15.37 MW 13.07 MW
942482 AE2-261 E Adder 10.25 MW 8.71 MW
959341 AF2-225 C Adder 4.78 MW 4.07 MW
959342 AF2-225 E Adder 6.61 MW 5.62 MW
959611 AF2-252 C Adder 1.56 MW 1.32 MW
959612 AF2-252 E Adder 2.34 MW 1.99 MW
960611 AF2-352 C Adder 1.56 MW 1.32 MW
960612 AF2-352 E Adder 2.34 MW 1.99 MW
276615 W2-048 GEN Adder 4.91 MW 4.18 MW
276621 X2-022 GEN Adder 16.82 MW 14.29 MW
917502 Z2-087 E Adder 13.21 MW 11.23 MW
957381 AF2-032 C Adder 1.17 MW 0.99 MW
957382 AF2-032 E Adder 0.55 MW 0.47 MW
274890 CAYUG;1U E Adder 6.49 MW 5.52 MW
274891 CAYUG;2U E Adder 6.49 MW 5.52 MW
925772 AC1-053 E Adder 16.19 MW 13.76 MW
933441 AC2-157 C 50/50 8.37 MW 8.37 MW
933442 AC2-157 E 50/50 13.66 MW 13.66 MW
276174 W4-005 E Adder 24.76 MW 21.04 MW
924048 AB2-047 E1 Adder 8.19 MW 6.96 MW
924049 AB2-047 E2 Adder 8.32 MW 7.07 MW
924266 AB2-070 E Adder 14.81 MW 12.59 MW
942601 AE2-276 C 50/50 5.51 MW 5.51 MW
945391 AF1-204 C 50/50 33.53 MW 33.53 MW
945392 AF1-204 E 50/50 100.58 MW 100.58 MW
960141 AF2-305_AG1- Adder 0.87 MW 0.74 MW
961651 AG1-005 C Adder 6.01 MW 5.11 MW
961652 AG1-005 E Adder 4.0 MW 3.4 MW
930461 AB1-087 C 50/50 60.57 MW 60.57 MW
930462 AB1-087 E 50/50 2.75 MW 2.75 MW
930471 AB1-088 C 50/50 60.57 MW 60.57 MW
930472 AB1-088 E 50/50 2.75 MW 2.75 MW
939741 AE1-205 C Adder 6.38 MW 5.42 MW
939742 AE1-205 E Adder 8.81 MW 7.49 MW
963741 AG1-226 C 50/50 74.67 MW 74.67 MW
963742 AG1-226 E 50/50 161.96 MW 161.96 MW
963831 AG1-236 C Adder 2.18 MW 1.85 MW
963832 AG1-236 E Adder 14.57 MW 12.39 MW
963841 AG1-237 C 50/50 13.67 MW 13.67 MW
963842 AG1-237 E 50/50 91.49 MW 91.49 MW
941731 AE2-173 C Adder 3.8 MW 3.23 MW
944221 AF1-090 C Adder 2.92 MW 2.48 MW
944222 AF1-090 E Adder 13.65 MW 11.6 MW
957142 AF2-008 NFTI 50/50 55.06 MW 55.06 MW
944201 AF1-088 FTIR 50/50 110.13 MW 110.13 MW
957141 AF2-008 FTIR 50/50 55.06 MW 55.06 MW
956452 J1139 External Queue 34.18 MW 34.18 MW
990672 J1360 External Queue 48.23 MW 48.23 MW
991237 J1676 C External Queue 4.65 MW 4.65 MW
991238 J1676 E External Queue 15.65 MW 15.65 MW
991562 J2178 External Queue -11.32 MW -11.32 MW
991577 J2192 C External Queue 5.12 MW 5.12 MW
991578 J2192 E External Queue 27.72 MW 27.72 MW
991622 J2232 External Queue -10.29 MW -10.29 MW
991627 J2233 G External Queue 32.88 MW 32.88 MW
992572 J1022 External Queue 22.85 MW 22.85 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 32.48 MW 32.48 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.46 MW 2.46 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.65 MW 0.65 MW
NY PJM->LTFIMP_NY CLTF 0.35 MW 0.35 MW
WEC LTFEXP_WEC->PJM CLTF 1.09 MW 1.09 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.11 MW 0.11 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.05 MW 0.05 MW
TVA LTFEXP_TVA->PJM CLTF 0.89 MW 0.89 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.96 MW 0.96 MW
MEC LTFEXP_MEC->PJM CLTF 5.88 MW 5.88 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 3.17 MW 3.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.35 MW 2.35 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.17 MW 4.17 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.17 MW 0.17 MW

Details for 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P4_#6189_05HANG R 765_D1_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2 FROM BUS 247249                     /*05HRKG2B      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Breaker AC 137.5 2255.0 B 3100.62 54.08
Elimination
Base Case Details for Eliminated Flowgate 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P4_#6189_05HANG R 765_D1_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 11.5 MW 11.5 MW
966842 AG1-555 E 50/50 4.11 MW 4.11 MW
965681 AG1-436 C 50/50 7.87 MW 7.87 MW
965682 AG1-436 E 50/50 5.25 MW 5.25 MW
966531 AG1-522 C 50/50 41.76 MW 41.76 MW
966532 AG1-522 E 50/50 27.84 MW 27.84 MW
966541 AG1-523 C 50/50 41.76 MW 41.76 MW
966542 AG1-523 E 50/50 27.84 MW 27.84 MW
966551 AG1-524 C 50/50 41.76 MW 41.76 MW
966552 AG1-524 E 50/50 27.84 MW 27.84 MW
966561 AG1-525 C 50/50 41.76 MW 41.76 MW
966562 AG1-525 E 50/50 27.84 MW 27.84 MW
247900 05FR-11G E 50/50 11.13 MW 11.13 MW
247901 05FR-12G E 50/50 10.96 MW 10.96 MW
247902 05FR-21G E 50/50 11.65 MW 11.65 MW
247903 05FR-22G E 50/50 11.19 MW 11.19 MW
247904 05FR-3G E 50/50 21.71 MW 21.71 MW
247905 05FR-4G E 50/50 17.2 MW 17.2 MW
247906 05MDL-1G E 50/50 23.41 MW 23.41 MW
247907 05MDL-2G E 50/50 11.28 MW 11.28 MW
247912 05MDL-3G E 50/50 11.26 MW 11.26 MW
247913 05MDL-4G E 50/50 11.73 MW 11.73 MW
960681 AF2-359 C 50/50 7.87 MW 7.87 MW
960682 AF2-359 E 50/50 5.25 MW 5.25 MW
243441 05CKG2 50/50 19.36 MW 19.36 MW
243442 05RKG1 50/50 62.5 MW 62.5 MW
243443 05RKG2 50/50 61.66 MW 61.66 MW
243859 05FR-11G C 50/50 0.51 MW 0.51 MW
243862 05FR-12G C 50/50 0.25 MW 0.25 MW
243864 05FR-21G C 50/50 0.26 MW 0.26 MW
243866 05FR-22G C 50/50 0.26 MW 0.26 MW
243870 05FR-3G C 50/50 0.25 MW 0.25 MW
243873 05FR-4G C 50/50 0.57 MW 0.57 MW
274751 CRETE EC ;1U 50/50 1.16 MW 1.16 MW
274752 CRETE EC ;2U 50/50 1.16 MW 1.16 MW
274754 CRETE EC ;4U 50/50 1.16 MW 1.16 MW
946581 AF1-322 C 50/50 11.17 MW 11.17 MW
946582 AF1-322 E 50/50 15.42 MW 15.42 MW
246909 05MDL-1G C 50/50 0.52 MW 0.52 MW
246910 05MDL-2G C 50/50 0.31 MW 0.31 MW
246976 05MDL-3G C 50/50 0.31 MW 0.31 MW
246979 05MDL-4G C 50/50 0.24 MW 0.24 MW
933441 AC2-157 C 50/50 12.87 MW 12.87 MW
933442 AC2-157 E 50/50 21.0 MW 21.0 MW
270100 AB1-080 CT1 50/50 3.7 MW 3.7 MW
270101 AB1-080 CT2 50/50 3.7 MW 3.7 MW
270102 AB1-080 ST 50/50 4.01 MW 4.01 MW
247556 05MDL-5G 50/50 0.41 MW 0.41 MW
247943 T-127 E 50/50 10.61 MW 10.61 MW
930041 AB1-006 E1 50/50 20.24 MW 20.24 MW
930042 AB1-006 E2 50/50 2.89 MW 2.89 MW
270180 AB1-006 W1 50/50 0.46 MW 0.46 MW
270181 AB1-006 W2 50/50 0.07 MW 0.07 MW
942601 AE2-276 C 50/50 8.47 MW 8.47 MW
945391 AF1-204 C 50/50 6.6 MW 6.6 MW
945392 AF1-204 E 50/50 19.81 MW 19.81 MW
945421 AF1-207 C 50/50 4.56 MW 4.56 MW
945422 AF1-207 E 50/50 19.57 MW 19.57 MW
945501 AF1-215 C 50/50 3.08 MW 3.08 MW
945502 AF1-215 E 50/50 14.43 MW 14.43 MW
959141 AF2-205 C 50/50 15.28 MW 15.28 MW
959142 AF2-205 E 50/50 10.19 MW 10.19 MW
930461 AB1-087 C 50/50 93.17 MW 93.17 MW
930462 AB1-087 E 50/50 4.24 MW 4.24 MW
930471 AB1-088 C 50/50 93.17 MW 93.17 MW
930472 AB1-088 E 50/50 4.24 MW 4.24 MW
940581 AE2-045 C 50/50 10.88 MW 10.88 MW
940582 AE2-045 E 50/50 14.94 MW 14.94 MW
963741 AG1-226 C 50/50 17.06 MW 17.06 MW
963742 AG1-226 E 50/50 37.01 MW 37.01 MW
963841 AG1-237 C 50/50 3.25 MW 3.25 MW
963842 AG1-237 E 50/50 21.73 MW 21.73 MW
964401 AG1-302 C 50/50 22.3 MW 22.3 MW
964402 AG1-302 E 50/50 14.87 MW 14.87 MW
957841 AF2-078 C 50/50 16.08 MW 16.08 MW
957842 AF2-078 E 50/50 10.72 MW 10.72 MW
958381 AF2-132 C 50/50 22.3 MW 22.3 MW
958382 AF2-132 E 50/50 14.87 MW 14.87 MW
958391 AF2-133 C 50/50 22.71 MW 22.71 MW
958392 AF2-133 E 50/50 15.14 MW 15.14 MW
958401 AF2-134 C 50/50 1.03 MW 1.03 MW
958402 AF2-134 E 50/50 4.81 MW 4.81 MW
964861 AG1-349 C 50/50 19.44 MW 19.44 MW
964862 AG1-349 E 50/50 12.96 MW 12.96 MW
965791 AG1-447 C 50/50 5.77 MW 5.77 MW
957142 AF2-008 NFTI 50/50 84.7 MW 84.7 MW
944201 AF1-088 FTIR 50/50 169.39 MW 169.39 MW
957141 AF2-008 FTIR 50/50 84.7 MW 84.7 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 115.38 MW 115.38 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 18.71 MW 18.71 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.98 MW 1.98 MW
NY PJM->LTFIMP_NY CLTF 0.99 MW 0.99 MW
WEC LTFEXP_WEC->PJM CLTF 3.04 MW 3.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 1.25 MW 1.25 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.77 MW 0.77 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 10.25 MW 10.25 MW
MEC LTFEXP_MEC->PJM CLTF 11.55 MW 11.55 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 29.34 MW 29.34 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.86 MW 1.86 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 12.64 MW 12.64 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.66 MW 1.66 MW

Details for 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 160.8 2255.0 B 3625.96 38.4
Elimination
Base Case Details for Eliminated Flowgate 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C Adder 6.74 MW 5.73 MW
966842 AG1-555 E Adder 2.41 MW 2.05 MW
965091 AG1-374 C Adder 12.36 MW 10.51 MW
965092 AG1-374 E Adder 8.24 MW 7.0 MW
965911 AG1-460 C Adder 0.98 MW 0.83 MW
965912 AG1-460 E Adder 1.46 MW 1.24 MW
966531 AG1-522 C 50/50 61.12 MW 61.12 MW
966532 AG1-522 E 50/50 40.74 MW 40.74 MW
966541 AG1-523 C 50/50 61.12 MW 61.12 MW
966542 AG1-523 E 50/50 40.74 MW 40.74 MW
966551 AG1-524 C 50/50 61.12 MW 61.12 MW
966552 AG1-524 E 50/50 40.74 MW 40.74 MW
966561 AG1-525 C 50/50 61.12 MW 61.12 MW
966562 AG1-525 E 50/50 40.74 MW 40.74 MW
247900 05FR-11G E Adder 6.52 MW 5.54 MW
247901 05FR-12G E Adder 6.42 MW 5.46 MW
247902 05FR-21G E Adder 6.82 MW 5.8 MW
247903 05FR-22G E Adder 6.56 MW 5.58 MW
247904 05FR-3G E Adder 12.72 MW 10.81 MW
247905 05FR-4G E Adder 10.08 MW 8.57 MW
247906 05MDL-1G E Adder 7.36 MW 6.25 MW
290261 S-027 E Adder 11.21 MW 9.53 MW
290265 S-028 E Adder 11.14 MW 9.47 MW
936771 AD2-100 C Adder 10.39 MW 8.83 MW
936772 AD2-100 E Adder 6.93 MW 5.89 MW
936971 AD2-131 C Adder 0.68 MW 0.58 MW
936972 AD2-131 E Adder 3.44 MW 2.92 MW
942111 AE2-223 C Adder 1.29 MW 1.1 MW
942112 AE2-223 E Adder 8.66 MW 7.36 MW
942481 AE2-261 C Adder 14.58 MW 12.39 MW
942482 AE2-261 E Adder 9.72 MW 8.26 MW
959341 AF2-225 C Adder 4.18 MW 3.56 MW
959342 AF2-225 E Adder 5.78 MW 4.91 MW
959611 AF2-252 C Adder 1.37 MW 1.17 MW
959612 AF2-252 E Adder 2.06 MW 1.75 MW
960611 AF2-352 C Adder 1.37 MW 1.17 MW
960612 AF2-352 E Adder 2.06 MW 1.75 MW
243442 05RKG1 50/50 95.03 MW 95.03 MW
243443 05RKG2 50/50 93.75 MW 93.75 MW
276615 W2-048 GEN Adder 4.21 MW 3.58 MW
276621 X2-022 GEN Adder 14.4 MW 12.24 MW
917502 Z2-087 E Adder 11.55 MW 9.82 MW
957381 AF2-032 C Adder 1.1 MW 0.93 MW
957382 AF2-032 E Adder 0.52 MW 0.44 MW
925772 AC1-053 E Adder 13.37 MW 11.36 MW
933441 AC2-157 C 50/50 17.8 MW 17.8 MW
933442 AC2-157 E 50/50 29.04 MW 29.04 MW
276174 W4-005 E Adder 19.95 MW 16.95 MW
924048 AB2-047 E1 Adder 7.16 MW 6.09 MW
924049 AB2-047 E2 Adder 7.28 MW 6.18 MW
252511 Y1-054 E Adder -1.3 MW -1.1 MW
924266 AB2-070 E Adder 12.02 MW 10.22 MW
942601 AE2-276 C 50/50 11.71 MW 11.71 MW
945391 AF1-204 C 50/50 6.4 MW 6.4 MW
945392 AF1-204 E 50/50 19.21 MW 19.21 MW
960141 AF2-305_AG1- Adder 0.7 MW 0.6 MW
930461 AB1-087 C 50/50 128.82 MW 128.82 MW
930462 AB1-087 E 50/50 5.86 MW 5.86 MW
930471 AB1-088 C 50/50 128.82 MW 128.82 MW
930472 AB1-088 E 50/50 5.86 MW 5.86 MW
939741 AE1-205 C Adder 5.58 MW 4.74 MW
939742 AE1-205 E Adder 7.7 MW 6.55 MW
963741 AG1-226 C Adder 12.12 MW 10.3 MW
963742 AG1-226 E Adder 26.28 MW 22.34 MW
963831 AG1-236 C Adder 1.8 MW 1.53 MW
963832 AG1-236 E Adder 12.03 MW 10.23 MW
963841 AG1-237 C Adder 2.11 MW 1.79 MW
963842 AG1-237 E Adder 14.1 MW 11.98 MW
941731 AE2-173 C Adder 3.32 MW 2.82 MW
944221 AF1-090 C Adder 3.03 MW 2.58 MW
944222 AF1-090 E Adder 14.18 MW 12.05 MW
957142 AF2-008 NFTI 50/50 117.11 MW 117.11 MW
944201 AF1-088 FTIR 50/50 234.22 MW 234.22 MW
957141 AF2-008 FTIR 50/50 117.11 MW 117.11 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 62.53 MW 62.53 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.0 MW 27.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.56 MW 1.56 MW
NY PJM->LTFIMP_NY CLTF 0.81 MW 0.81 MW
WEC LTFEXP_WEC->PJM CLTF 1.68 MW 1.68 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.51 MW 0.51 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.28 MW 0.28 MW
TVA LTFEXP_TVA->PJM CLTF 1.89 MW 1.89 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 5.26 MW 5.26 MW
MEC LTFEXP_MEC->PJM CLTF 8.38 MW 8.38 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 14.7 MW 14.7 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.03 MW 4.03 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.26 MW 0.26 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 9.97 MW 9.97 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.74 MW 0.74 MW

Details for 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 117.07 3039.0 B 3557.81 38.4
Elimination
Base Case Details for Eliminated Flowgate 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C Adder 6.74 MW 5.73 MW
966842 AG1-555 E Adder 2.41 MW 2.05 MW
965091 AG1-374 C Adder 12.36 MW 10.51 MW
965092 AG1-374 E Adder 8.24 MW 7.0 MW
965911 AG1-460 C Adder 0.98 MW 0.83 MW
965912 AG1-460 E Adder 1.46 MW 1.24 MW
966531 AG1-522 C 50/50 61.12 MW 61.12 MW
966532 AG1-522 E 50/50 40.74 MW 40.74 MW
966541 AG1-523 C 50/50 61.12 MW 61.12 MW
966542 AG1-523 E 50/50 40.74 MW 40.74 MW
966551 AG1-524 C 50/50 61.12 MW 61.12 MW
966552 AG1-524 E 50/50 40.74 MW 40.74 MW
966561 AG1-525 C 50/50 61.12 MW 61.12 MW
966562 AG1-525 E 50/50 40.74 MW 40.74 MW
247900 05FR-11G E Adder 6.52 MW 5.54 MW
247901 05FR-12G E Adder 6.42 MW 5.46 MW
247902 05FR-21G E Adder 6.82 MW 5.8 MW
247903 05FR-22G E Adder 6.56 MW 5.58 MW
247904 05FR-3G E Adder 12.72 MW 10.81 MW
247905 05FR-4G E Adder 10.08 MW 8.57 MW
247906 05MDL-1G E Adder 7.36 MW 6.25 MW
290261 S-027 E Adder 11.21 MW 9.53 MW
290265 S-028 E Adder 11.14 MW 9.47 MW
936771 AD2-100 C Adder 10.39 MW 8.83 MW
936772 AD2-100 E Adder 6.93 MW 5.89 MW
936971 AD2-131 C Adder 0.68 MW 0.58 MW
936972 AD2-131 E Adder 3.44 MW 2.92 MW
942111 AE2-223 C Adder 1.29 MW 1.1 MW
942112 AE2-223 E Adder 8.66 MW 7.36 MW
942481 AE2-261 C Adder 14.58 MW 12.39 MW
942482 AE2-261 E Adder 9.72 MW 8.26 MW
959341 AF2-225 C Adder 4.18 MW 3.56 MW
959342 AF2-225 E Adder 5.78 MW 4.91 MW
959611 AF2-252 C Adder 1.37 MW 1.17 MW
959612 AF2-252 E Adder 2.06 MW 1.75 MW
960611 AF2-352 C Adder 1.37 MW 1.17 MW
960612 AF2-352 E Adder 2.06 MW 1.75 MW
243442 05RKG1 50/50 95.03 MW 95.03 MW
243443 05RKG2 50/50 93.75 MW 93.75 MW
276615 W2-048 GEN Adder 4.21 MW 3.58 MW
276621 X2-022 GEN Adder 14.4 MW 12.24 MW
917502 Z2-087 E Adder 11.55 MW 9.82 MW
957381 AF2-032 C Adder 1.1 MW 0.93 MW
957382 AF2-032 E Adder 0.52 MW 0.44 MW
925772 AC1-053 E Adder 13.37 MW 11.36 MW
933441 AC2-157 C 50/50 17.8 MW 17.8 MW
933442 AC2-157 E 50/50 29.04 MW 29.04 MW
276174 W4-005 E Adder 19.95 MW 16.95 MW
924048 AB2-047 E1 Adder 7.16 MW 6.09 MW
924049 AB2-047 E2 Adder 7.28 MW 6.18 MW
252511 Y1-054 E Adder -1.3 MW -1.1 MW
924266 AB2-070 E Adder 12.02 MW 10.22 MW
942601 AE2-276 C 50/50 11.71 MW 11.71 MW
945391 AF1-204 C 50/50 6.4 MW 6.4 MW
945392 AF1-204 E 50/50 19.21 MW 19.21 MW
960141 AF2-305_AG1- Adder 0.7 MW 0.6 MW
930461 AB1-087 C 50/50 128.82 MW 128.82 MW
930462 AB1-087 E 50/50 5.86 MW 5.86 MW
930471 AB1-088 C 50/50 128.82 MW 128.82 MW
930472 AB1-088 E 50/50 5.86 MW 5.86 MW
939741 AE1-205 C Adder 5.58 MW 4.74 MW
939742 AE1-205 E Adder 7.7 MW 6.55 MW
963741 AG1-226 C Adder 12.12 MW 10.3 MW
963742 AG1-226 E Adder 26.28 MW 22.34 MW
963831 AG1-236 C Adder 1.8 MW 1.53 MW
963832 AG1-236 E Adder 12.03 MW 10.23 MW
963841 AG1-237 C Adder 2.11 MW 1.79 MW
963842 AG1-237 E Adder 14.1 MW 11.98 MW
941731 AE2-173 C Adder 3.32 MW 2.82 MW
944221 AF1-090 C Adder 3.03 MW 2.58 MW
944222 AF1-090 E Adder 14.18 MW 12.05 MW
957142 AF2-008 NFTI 50/50 117.11 MW 117.11 MW
944201 AF1-088 FTIR 50/50 234.22 MW 234.22 MW
957141 AF2-008 FTIR 50/50 117.11 MW 117.11 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 62.53 MW 62.53 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.0 MW 27.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.56 MW 1.56 MW
NY PJM->LTFIMP_NY CLTF 0.81 MW 0.81 MW
WEC LTFEXP_WEC->PJM CLTF 1.68 MW 1.68 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.51 MW 0.51 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.28 MW 0.28 MW
TVA LTFEXP_TVA->PJM CLTF 1.89 MW 1.89 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 5.26 MW 5.26 MW
MEC LTFEXP_MEC->PJM CLTF 8.38 MW 8.38 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 14.7 MW 14.7 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.03 MW 4.03 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.26 MW 0.26 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 9.97 MW 9.97 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.74 MW 0.74 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Summer Potential Congestion due to Local Energy Deliverability
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 163.85 1868.0 B 3060.81 199.65
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 163.85 1868.0 B 3060.81 199.65
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 122.71 1506.0 B 1848.03 25.51
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 123.87 1958.0 B 2425.43 189.38
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 122.85 1958.0 B 2405.41 187.79
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Base Case OP AC 119.2 1409.0 A 1679.52 259.08
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
AEP_P1-2_#8905_1697_SRT-A
CONTINGENCY 'AEP_P1-2_#8905_1697_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
END
OP AC 113.64 1868.0 B 2122.85 249.63
AEP AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line
963740 to 963840 ckt 1
Base Case OP AC 111.29 1409.0 A 1568.06 259.08
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P1-2_#8908_5621_SRT-A
CONTINGENCY 'AEP_P1-2_#8908_5621_SRT-A'
 OPEN BRANCH FROM BUS 247712 TO BUS 254529 CKT 1   /*05SULLIVAN   345.0 - 16PETE       345.0
END
OP AC 108.36 4571.0 B 4953.3 45.6
AEP 05FALL C-05DESOTO 345.0 kV Ckt 1 line
243222 to 243218 ckt 1
AEP_P1-2_#534_SRT-A-1
CONTINGENCY 'AEP_P1-2_#534_SRT-A-1'
 OPEN BRANCH FROM BUS 243233 TO BUS 964350 CKT 1   /*05TANNER     345.0 - AG1-297 TP   345.0
END
OP AC 107.34 1160.0 B 1245.09 25.8

Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line l/o AEP_P1-2_#8807_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 163.85 1868.0 B 3060.81 199.65
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 163.42 1868.0 B 3052.69 200.2
Topology Case Flowgate Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line l/o AEP_P1-2_#8807_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 51.22 MW 51.22 MW
966842 AG1-555 E 50/50 18.31 MW 18.31 MW
966531 AG1-522 C 50/50 20.4 MW 20.4 MW
966532 AG1-522 E 50/50 13.6 MW 13.6 MW
966541 AG1-523 C 50/50 20.4 MW 20.4 MW
966542 AG1-523 E 50/50 13.6 MW 13.6 MW
966551 AG1-524 C 50/50 20.4 MW 20.4 MW
966552 AG1-524 E 50/50 13.6 MW 13.6 MW
966561 AG1-525 C 50/50 20.4 MW 20.4 MW
966562 AG1-525 E 50/50 13.6 MW 13.6 MW
247900 05FR-11G E 50/50 49.54 MW 49.54 MW
247901 05FR-12G E 50/50 48.78 MW 48.78 MW
247902 05FR-21G E 50/50 51.85 MW 51.85 MW
247903 05FR-22G E 50/50 49.83 MW 49.83 MW
247904 05FR-3G E 50/50 96.64 MW 96.64 MW
247905 05FR-4G E 50/50 76.59 MW 76.59 MW
247906 05MDL-1G E 50/50 120.93 MW 120.93 MW
247907 05MDL-2G E 50/50 58.23 MW 58.23 MW
247912 05MDL-3G E 50/50 58.16 MW 58.16 MW
247913 05MDL-4G E 50/50 60.57 MW 60.57 MW
243859 05FR-11G C 50/50 2.26 MW 2.26 MW
243862 05FR-12G C 50/50 1.1 MW 1.1 MW
243864 05FR-21G C 50/50 1.14 MW 1.14 MW
243866 05FR-22G C 50/50 1.14 MW 1.14 MW
243870 05FR-3G C 50/50 1.1 MW 1.1 MW
243873 05FR-4G C 50/50 2.56 MW 2.56 MW
946581 AF1-322 C 50/50 57.68 MW 57.68 MW
946582 AF1-322 E 50/50 79.66 MW 79.66 MW
246909 05MDL-1G C 50/50 2.7 MW 2.7 MW
246910 05MDL-2G C 50/50 1.58 MW 1.58 MW
246976 05MDL-3G C 50/50 1.6 MW 1.6 MW
246979 05MDL-4G C 50/50 1.23 MW 1.23 MW
933441 AC2-157 C 50/50 11.01 MW 11.01 MW
933442 AC2-157 E 50/50 17.96 MW 17.96 MW
247556 05MDL-5G 50/50 2.11 MW 2.11 MW
247943 T-127 E 50/50 54.8 MW 54.8 MW
930041 AB1-006 E1 50/50 104.55 MW 104.55 MW
930042 AB1-006 E2 50/50 14.94 MW 14.94 MW
270180 AB1-006 W1 50/50 2.37 MW 2.37 MW
270181 AB1-006 W2 50/50 0.34 MW 0.34 MW
942601 AE2-276 C 50/50 7.24 MW 7.24 MW
945391 AF1-204 C 50/50 13.88 MW 13.88 MW
945392 AF1-204 E 50/50 41.64 MW 41.64 MW
930461 AB1-087 C 50/50 79.64 MW 79.64 MW
930462 AB1-087 E 50/50 3.62 MW 3.62 MW
930471 AB1-088 C 50/50 79.64 MW 79.64 MW
930472 AB1-088 E 50/50 3.62 MW 3.62 MW
963741 AG1-226 C 50/50 63.0 MW 63.0 MW
963742 AG1-226 E 50/50 136.65 MW 136.65 MW
963841 AG1-237 C 50/50 13.21 MW 13.21 MW
963842 AG1-237 E 50/50 88.39 MW 88.39 MW
957142 AF2-008 NFTI 50/50 72.4 MW 72.4 MW
957141 AF2-008 FTIR 50/50 72.4 MW 72.4 MW
944201 AF1-088 FTIR 50/50 144.8 MW 144.8 MW
956452 J1139 External Queue 17.56 MW 17.56 MW
956822 J1180 G External Queue 8.55 MW 8.55 MW
991082 J1475 G External Queue 8.55 MW 8.55 MW
991162 J1518 External Queue 26.71 MW 26.71 MW
991452 J2000 G External Queue 20.21 MW 20.21 MW
991552 J2170 G External Queue 17.1 MW 17.1 MW
991577 J2192 C External Queue 2.3 MW 2.3 MW
991578 J2192 E External Queue 12.43 MW 12.43 MW
991597 J2213 External Queue -27.41 MW -27.41 MW
991627 J2233 G External Queue 14.74 MW 14.74 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 37.09 MW 37.09 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 17.73 MW 17.73 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.18 MW 0.18 MW
VTF LTFEXP_VFT->PJM CMTX 0.47 MW 0.47 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.28 MW 2.28 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.3 MW 1.3 MW
TVA LTFEXP_TVA->PJM CLTF 5.28 MW 5.28 MW
MEC LTFEXP_MEC->PJM CLTF 3.01 MW 3.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.45 MW 6.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.78 MW 0.78 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.62 MW 0.62 MW

Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line l/o AEP_P1-2_#8695_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 163.85 1868.0 B 3060.81 199.65
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 163.42 1868.0 B 3052.69 200.2
Topology Case Flowgate Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line l/o AEP_P1-2_#8695_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 51.22 MW 51.22 MW
966842 AG1-555 E 50/50 18.31 MW 18.31 MW
966531 AG1-522 C 50/50 20.4 MW 20.4 MW
966532 AG1-522 E 50/50 13.6 MW 13.6 MW
966541 AG1-523 C 50/50 20.4 MW 20.4 MW
966542 AG1-523 E 50/50 13.6 MW 13.6 MW
966551 AG1-524 C 50/50 20.4 MW 20.4 MW
966552 AG1-524 E 50/50 13.6 MW 13.6 MW
966561 AG1-525 C 50/50 20.4 MW 20.4 MW
966562 AG1-525 E 50/50 13.6 MW 13.6 MW
247900 05FR-11G E 50/50 49.54 MW 49.54 MW
247901 05FR-12G E 50/50 48.78 MW 48.78 MW
247902 05FR-21G E 50/50 51.85 MW 51.85 MW
247903 05FR-22G E 50/50 49.83 MW 49.83 MW
247904 05FR-3G E 50/50 96.64 MW 96.64 MW
247905 05FR-4G E 50/50 76.59 MW 76.59 MW
247906 05MDL-1G E 50/50 120.93 MW 120.93 MW
247907 05MDL-2G E 50/50 58.23 MW 58.23 MW
247912 05MDL-3G E 50/50 58.16 MW 58.16 MW
247913 05MDL-4G E 50/50 60.57 MW 60.57 MW
243859 05FR-11G C 50/50 2.26 MW 2.26 MW
243862 05FR-12G C 50/50 1.1 MW 1.1 MW
243864 05FR-21G C 50/50 1.14 MW 1.14 MW
243866 05FR-22G C 50/50 1.14 MW 1.14 MW
243870 05FR-3G C 50/50 1.1 MW 1.1 MW
243873 05FR-4G C 50/50 2.56 MW 2.56 MW
946581 AF1-322 C 50/50 57.68 MW 57.68 MW
946582 AF1-322 E 50/50 79.66 MW 79.66 MW
246909 05MDL-1G C 50/50 2.7 MW 2.7 MW
246910 05MDL-2G C 50/50 1.58 MW 1.58 MW
246976 05MDL-3G C 50/50 1.6 MW 1.6 MW
246979 05MDL-4G C 50/50 1.23 MW 1.23 MW
933441 AC2-157 C 50/50 11.01 MW 11.01 MW
933442 AC2-157 E 50/50 17.96 MW 17.96 MW
247556 05MDL-5G 50/50 2.11 MW 2.11 MW
247943 T-127 E 50/50 54.8 MW 54.8 MW
930041 AB1-006 E1 50/50 104.55 MW 104.55 MW
930042 AB1-006 E2 50/50 14.94 MW 14.94 MW
270180 AB1-006 W1 50/50 2.37 MW 2.37 MW
270181 AB1-006 W2 50/50 0.34 MW 0.34 MW
942601 AE2-276 C 50/50 7.24 MW 7.24 MW
945391 AF1-204 C 50/50 13.88 MW 13.88 MW
945392 AF1-204 E 50/50 41.64 MW 41.64 MW
930461 AB1-087 C 50/50 79.64 MW 79.64 MW
930462 AB1-087 E 50/50 3.62 MW 3.62 MW
930471 AB1-088 C 50/50 79.64 MW 79.64 MW
930472 AB1-088 E 50/50 3.62 MW 3.62 MW
963741 AG1-226 C 50/50 63.0 MW 63.0 MW
963742 AG1-226 E 50/50 136.65 MW 136.65 MW
963841 AG1-237 C 50/50 13.21 MW 13.21 MW
963842 AG1-237 E 50/50 88.39 MW 88.39 MW
957142 AF2-008 NFTI 50/50 72.4 MW 72.4 MW
957141 AF2-008 FTIR 50/50 72.4 MW 72.4 MW
944201 AF1-088 FTIR 50/50 144.8 MW 144.8 MW
956452 J1139 External Queue 17.56 MW 17.56 MW
956822 J1180 G External Queue 8.55 MW 8.55 MW
991082 J1475 G External Queue 8.55 MW 8.55 MW
991162 J1518 External Queue 26.71 MW 26.71 MW
991452 J2000 G External Queue 20.21 MW 20.21 MW
991552 J2170 G External Queue 17.1 MW 17.1 MW
991577 J2192 C External Queue 2.3 MW 2.3 MW
991578 J2192 E External Queue 12.43 MW 12.43 MW
991597 J2213 External Queue -27.41 MW -27.41 MW
991627 J2233 G External Queue 14.74 MW 14.74 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 37.09 MW 37.09 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 17.73 MW 17.73 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.18 MW 0.18 MW
VTF LTFEXP_VFT->PJM CMTX 0.47 MW 0.47 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.28 MW 2.28 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.3 MW 1.3 MW
TVA LTFEXP_TVA->PJM CLTF 5.28 MW 5.28 MW
MEC LTFEXP_MEC->PJM CLTF 3.01 MW 3.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.45 MW 6.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.78 MW 0.78 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.62 MW 0.62 MW

Details for 05SULLIVAN-16PETE 345.0 kV Ckt 1 line l/o AEP_P1-2_#10136_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 122.71 1506.0 B 1848.03 25.51
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP/IPL 05SULLIVAN-16PETE 345.0 kV Ckt 1 line
247712 to 254529 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 125.26 1506.0 B 1886.37 26.04
Topology Case Flowgate Details for 05SULLIVAN-16PETE 345.0 kV Ckt 1 line l/o AEP_P1-2_#10136_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C Adder 4.6 MW 3.91 MW
966842 AG1-555 E Adder 1.65 MW 1.4 MW
965911 AG1-460 C Adder 0.63 MW 0.53 MW
965912 AG1-460 E Adder 0.94 MW 0.8 MW
966531 AG1-522 C 50/50 46.58 MW 46.58 MW
966532 AG1-522 E 50/50 31.05 MW 31.05 MW
966541 AG1-523 C 50/50 46.58 MW 46.58 MW
966542 AG1-523 E 50/50 31.05 MW 31.05 MW
966551 AG1-524 C 50/50 46.58 MW 46.58 MW
966552 AG1-524 E 50/50 31.05 MW 31.05 MW
966561 AG1-525 C 50/50 46.58 MW 46.58 MW
966562 AG1-525 E 50/50 31.05 MW 31.05 MW
247900 05FR-11G E Adder 4.45 MW 3.79 MW
247901 05FR-12G E Adder 4.39 MW 3.73 MW
247902 05FR-21G E Adder 4.66 MW 3.96 MW
247903 05FR-22G E Adder 4.48 MW 3.81 MW
247904 05FR-3G E Adder 8.69 MW 7.39 MW
247905 05FR-4G E Adder 6.89 MW 5.85 MW
936771 AD2-100 C Adder 6.72 MW 5.72 MW
936772 AD2-100 E Adder 4.48 MW 3.81 MW
936971 AD2-131 C Adder 0.44 MW 0.38 MW
936972 AD2-131 E Adder 2.23 MW 1.89 MW
942481 AE2-261 C Adder 9.38 MW 7.97 MW
942482 AE2-261 E Adder 6.25 MW 5.31 MW
243442 05RKG1 50/50 51.77 MW 51.77 MW
957381 AF2-032 C Adder 0.7 MW 0.6 MW
957382 AF2-032 E Adder 0.33 MW 0.28 MW
933441 AC2-157 C 50/50 19.67 MW 19.67 MW
933442 AC2-157 E 50/50 32.09 MW 32.09 MW
942601 AE2-276 C 50/50 12.94 MW 12.94 MW
945391 AF1-204 C Adder 4.1 MW 3.48 MW
945392 AF1-204 E Adder 12.3 MW 10.46 MW
930461 AB1-087 C 50/50 142.33 MW 142.33 MW
930462 AB1-087 E 50/50 6.47 MW 6.47 MW
930471 AB1-088 C 50/50 142.33 MW 142.33 MW
930472 AB1-088 E 50/50 6.47 MW 6.47 MW
963741 AG1-226 C Adder 8.05 MW 6.84 MW
963742 AG1-226 E Adder 17.46 MW 14.84 MW
963841 AG1-237 C Adder 1.42 MW 1.21 MW
963842 AG1-237 E Adder 9.48 MW 8.06 MW
944221 AF1-090 C Adder 1.99 MW 1.7 MW
944222 AF1-090 E Adder 9.34 MW 7.94 MW
957142 AF2-008 NFTI 50/50 129.39 MW 129.39 MW
957141 AF2-008 FTIR 50/50 129.39 MW 129.39 MW
944201 AF1-088 FTIR 50/50 258.79 MW 258.79 MW
955132 J991 External Queue 10.86 MW 10.86 MW
956452 J1139 External Queue 8.91 MW 8.91 MW
956822 J1180 G External Queue 13.94 MW 13.94 MW
990057 J1201 External Queue 2.27 MW 2.27 MW
990272 J1263 G External Queue 40.64 MW 40.64 MW
991082 J1475 G External Queue 13.94 MW 13.94 MW
991197 J1626 External Queue 9.16 MW 9.16 MW
991263 J1713 C External Queue 1.21 MW 1.21 MW
991264 J1713 E External Queue 6.56 MW 6.56 MW
991267 J1714 External Queue 6.11 MW 6.11 MW
991462 J2032 External Queue -5.3 MW -5.3 MW
991523 J2115 C External Queue 0.81 MW 0.81 MW
991524 J2115 E External Queue 4.38 MW 4.38 MW
991532 J2123 External Queue -4.84 MW -4.84 MW
991537 J2131 External Queue 12.61 MW 12.61 MW
991552 J2170 G External Queue 27.91 MW 27.91 MW
991577 J2192 C External Queue 0.92 MW 0.92 MW
991578 J2192 E External Queue 4.96 MW 4.96 MW
991582 J2195 External Queue 6.11 MW 6.11 MW
991627 J2233 G External Queue 5.88 MW 5.88 MW
991652 J2254 External Queue -22.82 MW -22.82 MW
991657 J2263 External Queue -8.43 MW -8.43 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 31.07 MW 31.07 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.7 MW 0.7 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
WEC LTFEXP_WEC->PJM CLTF 0.84 MW 0.84 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.47 MW 0.47 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.29 MW 0.29 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 1.82 MW 1.82 MW
MEC LTFEXP_MEC->PJM CLTF 3.84 MW 3.84 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 6.08 MW 6.08 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.0 MW 0.0 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.47 MW 4.47 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.6 MW 0.6 MW

Details for 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line l/o AEP_P1-2_#6490_16000_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 123.87 1958.0 B 2425.43 189.38
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 123.98 1958.0 B 2427.52 189.93
Topology Case Flowgate Details for 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line l/o AEP_P1-2_#6490_16000_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 48.57 MW 48.57 MW
966842 AG1-555 E 50/50 17.36 MW 17.36 MW
966531 AG1-522 C 50/50 19.43 MW 19.43 MW
966532 AG1-522 E 50/50 12.95 MW 12.95 MW
966541 AG1-523 C 50/50 19.43 MW 19.43 MW
966542 AG1-523 E 50/50 12.95 MW 12.95 MW
966551 AG1-524 C 50/50 19.43 MW 19.43 MW
966552 AG1-524 E 50/50 12.95 MW 12.95 MW
966561 AG1-525 C 50/50 19.43 MW 19.43 MW
966562 AG1-525 E 50/50 12.95 MW 12.95 MW
247900 05FR-11G E 50/50 46.98 MW 46.98 MW
247901 05FR-12G E 50/50 46.26 MW 46.26 MW
247902 05FR-21G E 50/50 49.17 MW 49.17 MW
247903 05FR-22G E 50/50 47.25 MW 47.25 MW
247904 05FR-3G E 50/50 91.64 MW 91.64 MW
247905 05FR-4G E 50/50 72.63 MW 72.63 MW
243859 05FR-11G C 50/50 2.14 MW 2.14 MW
243862 05FR-12G C 50/50 1.04 MW 1.04 MW
243864 05FR-21G C 50/50 1.08 MW 1.08 MW
243866 05FR-22G C 50/50 1.08 MW 1.08 MW
243870 05FR-3G C 50/50 1.04 MW 1.04 MW
243873 05FR-4G C 50/50 2.43 MW 2.43 MW
933441 AC2-157 C 50/50 10.47 MW 10.47 MW
933442 AC2-157 E 50/50 17.08 MW 17.08 MW
942601 AE2-276 C 50/50 6.89 MW 6.89 MW
945391 AF1-204 C 50/50 13.19 MW 13.19 MW
945392 AF1-204 E 50/50 39.55 MW 39.55 MW
930461 AB1-087 C 50/50 75.75 MW 75.75 MW
930462 AB1-087 E 50/50 3.44 MW 3.44 MW
930471 AB1-088 C 50/50 75.75 MW 75.75 MW
930472 AB1-088 E 50/50 3.44 MW 3.44 MW
963741 AG1-226 C 50/50 59.76 MW 59.76 MW
963742 AG1-226 E 50/50 129.62 MW 129.62 MW
963841 AG1-237 C 50/50 12.53 MW 12.53 MW
963842 AG1-237 E 50/50 83.83 MW 83.83 MW
957142 AF2-008 NFTI 50/50 68.86 MW 68.86 MW
957141 AF2-008 FTIR 50/50 68.86 MW 68.86 MW
944201 AF1-088 FTIR 50/50 137.73 MW 137.73 MW
956452 J1139 External Queue 16.64 MW 16.64 MW
956822 J1180 G External Queue 8.1 MW 8.1 MW
990272 J1263 G External Queue 40.63 MW 40.63 MW
990647 J1355 External Queue -10.33 MW -10.33 MW
991082 J1475 G External Queue 8.1 MW 8.1 MW
991162 J1518 External Queue 25.3 MW 25.3 MW
991252 J1691 External Queue 19.28 MW 19.28 MW
991432 J1966 C External Queue 3.09 MW 3.09 MW
991433 J1966 E External Queue 16.74 MW 16.74 MW
991452 J2000 G External Queue 19.15 MW 19.15 MW
991537 J2131 External Queue 12.49 MW 12.49 MW
991552 J2170 G External Queue 16.2 MW 16.2 MW
991562 J2178 External Queue 9.65 MW 9.65 MW
991577 J2192 C External Queue 2.18 MW 2.18 MW
991578 J2192 E External Queue 11.77 MW 11.77 MW
991597 J2213 External Queue -25.97 MW -25.97 MW
991617 J2230 External Queue 38.56 MW 38.56 MW
991627 J2233 G External Queue 13.96 MW 13.96 MW
991662 J2270 External Queue 28.92 MW 28.92 MW
991682 J2296 External Queue 9.64 MW 9.64 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.07 MW 0.07 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 35.5 MW 35.5 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 17.36 MW 17.36 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.3 MW 0.3 MW
VTF LTFEXP_VFT->PJM CMTX 0.79 MW 0.79 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.19 MW 2.19 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.28 MW 1.28 MW
TVA LTFEXP_TVA->PJM CLTF 5.08 MW 5.08 MW
MEC LTFEXP_MEC->PJM CLTF 2.94 MW 2.94 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.2 MW 6.2 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.74 MW 0.74 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.62 MW 0.62 MW

Details for 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line l/o AEP_P1-2_#6472_15258_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 122.85 1958.0 B 2405.41 187.79
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 122.96 1958.0 B 2407.58 188.34
Topology Case Flowgate Details for 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line l/o AEP_P1-2_#6472_15258_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 48.16 MW 48.16 MW
966842 AG1-555 E 50/50 17.22 MW 17.22 MW
966531 AG1-522 C 50/50 19.26 MW 19.26 MW
966532 AG1-522 E 50/50 12.84 MW 12.84 MW
966541 AG1-523 C 50/50 19.26 MW 19.26 MW
966542 AG1-523 E 50/50 12.84 MW 12.84 MW
966551 AG1-524 C 50/50 19.26 MW 19.26 MW
966552 AG1-524 E 50/50 12.84 MW 12.84 MW
966561 AG1-525 C 50/50 19.26 MW 19.26 MW
966562 AG1-525 E 50/50 12.84 MW 12.84 MW
247900 05FR-11G E 50/50 46.58 MW 46.58 MW
247901 05FR-12G E 50/50 45.87 MW 45.87 MW
247902 05FR-21G E 50/50 48.76 MW 48.76 MW
247903 05FR-22G E 50/50 46.85 MW 46.85 MW
247904 05FR-3G E 50/50 90.88 MW 90.88 MW
247905 05FR-4G E 50/50 72.02 MW 72.02 MW
243859 05FR-11G C 50/50 2.13 MW 2.13 MW
243862 05FR-12G C 50/50 1.03 MW 1.03 MW
243864 05FR-21G C 50/50 1.08 MW 1.08 MW
243866 05FR-22G C 50/50 1.08 MW 1.08 MW
243870 05FR-3G C 50/50 1.03 MW 1.03 MW
243873 05FR-4G C 50/50 2.41 MW 2.41 MW
933441 AC2-157 C 50/50 10.38 MW 10.38 MW
933442 AC2-157 E 50/50 16.93 MW 16.93 MW
942601 AE2-276 C 50/50 6.83 MW 6.83 MW
945391 AF1-204 C 50/50 13.07 MW 13.07 MW
945392 AF1-204 E 50/50 39.22 MW 39.22 MW
930461 AB1-087 C 50/50 75.11 MW 75.11 MW
930462 AB1-087 E 50/50 3.41 MW 3.41 MW
930471 AB1-088 C 50/50 75.11 MW 75.11 MW
930472 AB1-088 E 50/50 3.41 MW 3.41 MW
963741 AG1-226 C 50/50 59.26 MW 59.26 MW
963742 AG1-226 E 50/50 128.53 MW 128.53 MW
963841 AG1-237 C 50/50 12.42 MW 12.42 MW
963842 AG1-237 E 50/50 83.13 MW 83.13 MW
957142 AF2-008 NFTI 50/50 68.29 MW 68.29 MW
957141 AF2-008 FTIR 50/50 68.29 MW 68.29 MW
944201 AF1-088 FTIR 50/50 136.57 MW 136.57 MW
956452 J1139 External Queue 16.5 MW 16.5 MW
956822 J1180 G External Queue 8.03 MW 8.03 MW
990272 J1263 G External Queue 40.29 MW 40.29 MW
990647 J1355 External Queue -10.25 MW -10.25 MW
991082 J1475 G External Queue 8.03 MW 8.03 MW
991162 J1518 External Queue 25.09 MW 25.09 MW
991252 J1691 External Queue 19.12 MW 19.12 MW
991432 J1966 C External Queue 3.07 MW 3.07 MW
991433 J1966 E External Queue 16.59 MW 16.59 MW
991452 J2000 G External Queue 18.99 MW 18.99 MW
991537 J2131 External Queue 12.38 MW 12.38 MW
991552 J2170 G External Queue 16.07 MW 16.07 MW
991562 J2178 External Queue 9.57 MW 9.57 MW
991577 J2192 C External Queue 2.16 MW 2.16 MW
991578 J2192 E External Queue 11.67 MW 11.67 MW
991597 J2213 External Queue -25.75 MW -25.75 MW
991617 J2230 External Queue 38.24 MW 38.24 MW
991627 J2233 G External Queue 13.85 MW 13.85 MW
991662 J2270 External Queue 28.68 MW 28.68 MW
991682 J2296 External Queue 9.56 MW 9.56 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.06 MW 0.06 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 35.2 MW 35.2 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 17.21 MW 17.21 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.3 MW 0.3 MW
VTF LTFEXP_VFT->PJM CMTX 0.79 MW 0.79 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.17 MW 2.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.27 MW 1.27 MW
TVA LTFEXP_TVA->PJM CLTF 5.04 MW 5.04 MW
MEC LTFEXP_MEC->PJM CLTF 2.91 MW 2.91 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.15 MW 6.15 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.73 MW 0.73 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.61 MW 0.61 MW

Details for AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Base Case OP AC 119.2 1409.0 A 1679.52 259.08
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Base Case OP AC 119.99 1409.0 A 1690.69 259.96
Topology Case Flowgate Details for AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965911 AG1-460 C Adder 0.62 MW 0.53 MW
965912 AG1-460 E Adder 0.94 MW 0.8 MW
936771 AD2-100 C Adder 6.69 MW 5.68 MW
936772 AD2-100 E Adder 4.46 MW 3.79 MW
936971 AD2-131 C Adder 0.44 MW 0.38 MW
936972 AD2-131 E Adder 2.21 MW 1.88 MW
942481 AE2-261 C Adder 9.33 MW 7.93 MW
942482 AE2-261 E Adder 6.22 MW 5.29 MW
957381 AF2-032 C Adder 0.7 MW 0.6 MW
957382 AF2-032 E Adder 0.33 MW 0.28 MW
933441 AC2-157 C Adder 4.32 MW 3.67 MW
933442 AC2-157 E Adder 7.04 MW 5.99 MW
942601 AE2-276 C Adder 2.84 MW 2.41 MW
945391 AF1-204 C 50/50 14.46 MW 14.46 MW
945392 AF1-204 E 50/50 43.38 MW 43.38 MW
930461 AB1-087 C Adder 31.23 MW 26.54 MW
930462 AB1-087 E Adder 1.42 MW 1.21 MW
930471 AB1-088 C Adder 31.23 MW 26.54 MW
930472 AB1-088 E Adder 1.42 MW 1.21 MW
963741 AG1-226 C 50/50 81.75 MW 81.75 MW
963742 AG1-226 E 50/50 177.32 MW 177.32 MW
963841 AG1-237 C 50/50 17.55 MW 17.55 MW
963842 AG1-237 E 50/50 117.46 MW 117.46 MW
944221 AF1-090 C Adder 1.98 MW 1.68 MW
944222 AF1-090 E Adder 9.28 MW 7.88 MW
957142 AF2-008 NFTI Adder 33.4 MW 28.39 MW
957141 AF2-008 FTIR Adder 33.4 MW 28.39 MW
944201 AF1-088 FTIR Adder 66.8 MW 56.78 MW
990497 J1323 External Queue -1.28 MW -1.28 MW
991517 J2100 External Queue -13.15 MW -13.15 MW
955152 J993 G External Queue 11.01 MW 11.01 MW
956452 J1139 External Queue 16.19 MW 16.19 MW
990272 J1263 G External Queue 28.05 MW 28.05 MW
990547 J1333 G External Queue -10.13 MW -10.13 MW
990552 J1334 G External Queue -10.13 MW -10.13 MW
990557 J1335 G External Queue -10.13 MW -10.13 MW
990562 J1336 G External Queue -10.13 MW -10.13 MW
990577 J1339 External Queue -10.89 MW -10.89 MW
990582 J1340 External Queue -10.89 MW -10.89 MW
990647 J1355 External Queue -8.09 MW -8.09 MW
990662 J1358 External Queue -6.4 MW -6.4 MW
990672 J1360 External Queue 21.16 MW 21.16 MW
991162 J1518 External Queue 20.67 MW 20.67 MW
991242 J1678 External Queue -4.31 MW -4.31 MW
991252 J1691 External Queue 15.79 MW 15.79 MW
991377 J1861 G External Queue -2.73 MW -2.73 MW
991432 J1966 C External Queue 2.16 MW 2.16 MW
991433 J1966 E External Queue 11.69 MW 11.69 MW
991452 J2000 G External Queue 15.86 MW 15.86 MW
991472 J2045 External Queue -3.78 MW -3.78 MW
991562 J2178 External Queue 7.9 MW 7.9 MW
991577 J2192 C External Queue 2.25 MW 2.25 MW
991578 J2192 E External Queue 12.19 MW 12.19 MW
991597 J2213 External Queue -18.54 MW -18.54 MW
991617 J2230 External Queue 31.58 MW 31.58 MW
991627 J2233 G External Queue 14.46 MW 14.46 MW
991662 J2270 External Queue 23.68 MW 23.68 MW
991682 J2296 External Queue 7.89 MW 7.89 MW
992572 J1022 External Queue 9.52 MW 9.52 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.76 MW 27.76 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 12.08 MW 12.08 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.11 MW 0.11 MW
VTF LTFEXP_VFT->PJM CMTX 0.28 MW 0.28 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.49 MW 1.49 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.87 MW 0.87 MW
TVA LTFEXP_TVA->PJM CLTF 3.72 MW 3.72 MW
MEC LTFEXP_MEC->PJM CLTF 2.9 MW 2.9 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.67 MW 4.67 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.54 MW 0.54 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.42 MW 0.42 MW

Details for AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line l/o AEP_P1-2_#8905_1697_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
AEP_P1-2_#8905_1697_SRT-A
CONTINGENCY 'AEP_P1-2_#8905_1697_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
END
OP AC 113.64 1868.0 B 2122.85 249.63
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
AEP_P1-2_#8905_1697_SRT-A
CONTINGENCY 'AEP_P1-2_#8905_1697_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
END
OP AC 112.9 1868.0 B 2108.93 250.52
Topology Case Flowgate Details for AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line l/o AEP_P1-2_#8905_1697_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965911 AG1-460 C Adder 0.67 MW 0.57 MW
965912 AG1-460 E Adder 1.01 MW 0.86 MW
966531 AG1-522 C Adder 12.75 MW 10.84 MW
966532 AG1-522 E Adder 8.5 MW 7.22 MW
966541 AG1-523 C Adder 12.75 MW 10.84 MW
966542 AG1-523 E Adder 8.5 MW 7.22 MW
966551 AG1-524 C Adder 12.75 MW 10.84 MW
966552 AG1-524 E Adder 8.5 MW 7.22 MW
966561 AG1-525 C Adder 12.75 MW 10.84 MW
966562 AG1-525 E Adder 8.5 MW 7.22 MW
936771 AD2-100 C Adder 7.25 MW 6.16 MW
936772 AD2-100 E Adder 4.83 MW 4.11 MW
936971 AD2-131 C Adder 0.48 MW 0.41 MW
936972 AD2-131 E Adder 2.4 MW 2.04 MW
942481 AE2-261 C Adder 10.06 MW 8.55 MW
942482 AE2-261 E Adder 6.71 MW 5.7 MW
957381 AF2-032 C Adder 0.76 MW 0.64 MW
957382 AF2-032 E Adder 0.36 MW 0.3 MW
933441 AC2-157 C Adder 6.9 MW 5.87 MW
933442 AC2-157 E Adder 11.27 MW 9.58 MW
942601 AE2-276 C Adder 4.54 MW 3.86 MW
945391 AF1-204 C 50/50 14.46 MW 14.46 MW
945392 AF1-204 E 50/50 43.38 MW 43.38 MW
930461 AB1-087 C Adder 49.97 MW 42.48 MW
930462 AB1-087 E Adder 2.27 MW 1.93 MW
930471 AB1-088 C Adder 49.97 MW 42.48 MW
930472 AB1-088 E Adder 2.27 MW 1.93 MW
963741 AG1-226 C 50/50 78.77 MW 78.77 MW
963742 AG1-226 E 50/50 170.86 MW 170.86 MW
963841 AG1-237 C 50/50 16.85 MW 16.85 MW
963842 AG1-237 E 50/50 112.77 MW 112.77 MW
944221 AF1-090 C Adder 2.17 MW 1.85 MW
944222 AF1-090 E Adder 10.18 MW 8.65 MW
957142 AF2-008 NFTI Adder 53.45 MW 45.43 MW
957141 AF2-008 FTIR Adder 53.45 MW 45.43 MW
944201 AF1-088 FTIR Adder 106.89 MW 90.86 MW
990497 J1323 External Queue -1.45 MW -1.45 MW
991182 J1586 G External Queue -27.49 MW -27.49 MW
991382 J1880 G External Queue -3.43 MW -3.43 MW
991397 J1894 External Queue -11.35 MW -11.35 MW
991442 J1980 External Queue -2.82 MW -2.82 MW
991447 J1984 External Queue -2.84 MW -2.84 MW
991492 J2057 G External Queue -5.55 MW -5.55 MW
991517 J2100 External Queue -14.92 MW -14.92 MW
955132 J991 External Queue 10.98 MW 10.98 MW
955152 J993 G External Queue 11.43 MW 11.43 MW
956452 J1139 External Queue 16.75 MW 16.75 MW
956822 J1180 G External Queue 5.46 MW 5.46 MW
990272 J1263 G External Queue 33.5 MW 33.5 MW
990547 J1333 G External Queue -11.62 MW -11.62 MW
990552 J1334 G External Queue -11.62 MW -11.62 MW
990557 J1335 G External Queue -11.62 MW -11.62 MW
990562 J1336 G External Queue -11.62 MW -11.62 MW
990577 J1339 External Queue -12.49 MW -12.49 MW
990582 J1340 External Queue -12.49 MW -12.49 MW
990647 J1355 External Queue -9.26 MW -9.26 MW
990662 J1358 External Queue -7.32 MW -7.32 MW
990672 J1360 External Queue 21.93 MW 21.93 MW
991082 J1475 G External Queue 5.46 MW 5.46 MW
991162 J1518 External Queue 20.57 MW 20.57 MW
991242 J1678 External Queue -4.98 MW -4.98 MW
991252 J1691 External Queue 16.84 MW 16.84 MW
991377 J1861 G External Queue -3.13 MW -3.13 MW
991432 J1966 C External Queue 2.04 MW 2.04 MW
991433 J1966 E External Queue 11.04 MW 11.04 MW
991452 J2000 G External Queue 15.46 MW 15.46 MW
991472 J2045 External Queue -4.51 MW -4.51 MW
991537 J2131 External Queue 9.62 MW 9.62 MW
991552 J2170 G External Queue 10.93 MW 10.93 MW
991562 J2178 External Queue 8.43 MW 8.43 MW
991577 J2192 C External Queue 2.29 MW 2.29 MW
991578 J2192 E External Queue 12.4 MW 12.4 MW
991597 J2213 External Queue -21.24 MW -21.24 MW
991602 J2215 G External Queue -17.08 MW -17.08 MW
991617 J2230 External Queue 33.69 MW 33.69 MW
991627 J2233 G External Queue 14.71 MW 14.71 MW
991657 J2263 External Queue 5.48 MW 5.48 MW
991662 J2270 External Queue 25.27 MW 25.27 MW
991682 J2296 External Queue 8.42 MW 8.42 MW
992572 J1022 External Queue 9.8 MW 9.8 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.02 MW 0.02 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 30.99 MW 30.99 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 14.26 MW 14.26 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.19 MW 0.19 MW
VTF LTFEXP_VFT->PJM CMTX 0.49 MW 0.49 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.75 MW 1.75 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.04 MW 1.04 MW
TVA LTFEXP_TVA->PJM CLTF 4.29 MW 4.29 MW
MEC LTFEXP_MEC->PJM CLTF 3.06 MW 3.06 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.34 MW 5.34 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.61 MW 0.61 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.5 MW 0.5 MW

Details for AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line
963740 to 963840 ckt 1
Base Case OP AC 111.29 1409.0 A 1568.06 259.08
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line
963740 to 963840 ckt 1
Base Case OP AC 112.02 1409.0 A 1578.31 259.96
Topology Case Flowgate Details for AG1-226 TP-AG1-237 TP 345.0 kV Ckt 1 line l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965911 AG1-460 C Adder 0.62 MW 0.53 MW
965912 AG1-460 E Adder 0.94 MW 0.8 MW
936771 AD2-100 C Adder 6.69 MW 5.68 MW
936772 AD2-100 E Adder 4.46 MW 3.79 MW
936971 AD2-131 C Adder 0.44 MW 0.38 MW
936972 AD2-131 E Adder 2.21 MW 1.88 MW
942481 AE2-261 C Adder 9.33 MW 7.93 MW
942482 AE2-261 E Adder 6.22 MW 5.29 MW
957381 AF2-032 C Adder 0.7 MW 0.6 MW
957382 AF2-032 E Adder 0.33 MW 0.28 MW
933441 AC2-157 C Adder 4.32 MW 3.67 MW
933442 AC2-157 E Adder 7.04 MW 5.99 MW
942601 AE2-276 C Adder 2.84 MW 2.41 MW
945391 AF1-204 C 50/50 14.46 MW 14.46 MW
945392 AF1-204 E 50/50 43.38 MW 43.38 MW
930461 AB1-087 C Adder 31.23 MW 26.54 MW
930462 AB1-087 E Adder 1.42 MW 1.21 MW
930471 AB1-088 C Adder 31.23 MW 26.54 MW
930472 AB1-088 E Adder 1.42 MW 1.21 MW
963741 AG1-226 C 50/50 81.75 MW 81.75 MW
963742 AG1-226 E 50/50 177.32 MW 177.32 MW
944221 AF1-090 C Adder 1.98 MW 1.68 MW
944222 AF1-090 E Adder 9.28 MW 7.88 MW
957142 AF2-008 NFTI Adder 33.4 MW 28.39 MW
957141 AF2-008 FTIR Adder 33.4 MW 28.39 MW
944201 AF1-088 FTIR Adder 66.8 MW 56.78 MW
990497 J1323 External Queue -1.28 MW -1.28 MW
991382 J1880 G External Queue -3.03 MW -3.03 MW
991397 J1894 External Queue -10.02 MW -10.02 MW
991447 J1984 External Queue -2.51 MW -2.51 MW
991517 J2100 External Queue -13.15 MW -13.15 MW
955152 J993 G External Queue 11.01 MW 11.01 MW
956452 J1139 External Queue 16.19 MW 16.19 MW
990272 J1263 G External Queue 28.05 MW 28.05 MW
990547 J1333 G External Queue -10.13 MW -10.13 MW
990552 J1334 G External Queue -10.13 MW -10.13 MW
990557 J1335 G External Queue -10.13 MW -10.13 MW
990562 J1336 G External Queue -10.13 MW -10.13 MW
990577 J1339 External Queue -10.89 MW -10.89 MW
990582 J1340 External Queue -10.89 MW -10.89 MW
990647 J1355 External Queue -8.09 MW -8.09 MW
990662 J1358 External Queue -6.4 MW -6.4 MW
990672 J1360 External Queue 21.16 MW 21.16 MW
991162 J1518 External Queue 20.67 MW 20.67 MW
991242 J1678 External Queue -4.31 MW -4.31 MW
991252 J1691 External Queue 15.79 MW 15.79 MW
991377 J1861 G External Queue -2.73 MW -2.73 MW
991432 J1966 C External Queue 2.16 MW 2.16 MW
991433 J1966 E External Queue 11.69 MW 11.69 MW
991452 J2000 G External Queue 15.86 MW 15.86 MW
991472 J2045 External Queue -3.78 MW -3.78 MW
991537 J2131 External Queue 7.54 MW 7.54 MW
991562 J2178 External Queue 7.9 MW 7.9 MW
991577 J2192 C External Queue 2.25 MW 2.25 MW
991578 J2192 E External Queue 12.19 MW 12.19 MW
991597 J2213 External Queue -18.54 MW -18.54 MW
991617 J2230 External Queue 31.58 MW 31.58 MW
991627 J2233 G External Queue 14.46 MW 14.46 MW
991662 J2270 External Queue 23.68 MW 23.68 MW
991682 J2296 External Queue 7.89 MW 7.89 MW
992572 J1022 External Queue 9.52 MW 9.52 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.76 MW 27.76 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 12.08 MW 12.08 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.11 MW 0.11 MW
VTF LTFEXP_VFT->PJM CMTX 0.28 MW 0.28 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.49 MW 1.49 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.87 MW 0.87 MW
TVA LTFEXP_TVA->PJM CLTF 3.72 MW 3.72 MW
MEC LTFEXP_MEC->PJM CLTF 2.9 MW 2.9 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.67 MW 4.67 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.54 MW 0.54 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.42 MW 0.42 MW

Details for 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line l/o AEP_P1-2_#8908_5621_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P1-2_#8908_5621_SRT-A
CONTINGENCY 'AEP_P1-2_#8908_5621_SRT-A'
 OPEN BRANCH FROM BUS 247712 TO BUS 254529 CKT 1   /*05SULLIVAN   345.0 - 16PETE       345.0
END
OP AC 108.36 4571.0 B 4953.3 45.6
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P1-2_#8908_5621_SRT-A
CONTINGENCY 'AEP_P1-2_#8908_5621_SRT-A'
 OPEN BRANCH FROM BUS 247712 TO BUS 254529 CKT 1   /*05SULLIVAN   345.0 - 16PETE       345.0
END
OP AC 107.78 4571.0 B 4926.73 45.16
Topology Case Flowgate Details for 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line l/o AEP_P1-2_#8908_5621_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965911 AG1-460 C 50/50 1.27 MW 1.27 MW
965912 AG1-460 E 50/50 1.91 MW 1.91 MW
966531 AG1-522 C 50/50 88.26 MW 88.26 MW
966532 AG1-522 E 50/50 58.84 MW 58.84 MW
966541 AG1-523 C 50/50 88.26 MW 88.26 MW
966542 AG1-523 E 50/50 58.84 MW 58.84 MW
966551 AG1-524 C 50/50 88.26 MW 88.26 MW
966552 AG1-524 E 50/50 58.84 MW 58.84 MW
966561 AG1-525 C 50/50 88.26 MW 88.26 MW
966562 AG1-525 E 50/50 58.84 MW 58.84 MW
936771 AD2-100 C 50/50 13.64 MW 13.64 MW
936772 AD2-100 E 50/50 9.09 MW 9.09 MW
936971 AD2-131 C 50/50 0.9 MW 0.9 MW
936972 AD2-131 E 50/50 4.51 MW 4.51 MW
942481 AE2-261 C 50/50 19.01 MW 19.01 MW
942482 AE2-261 E 50/50 12.67 MW 12.67 MW
243442 05RKG1 50/50 130.96 MW 130.96 MW
243443 05RKG2 50/50 129.22 MW 129.22 MW
274650 KINCAID ;1U 50/50 8.88 MW 8.88 MW
274651 KINCAID ;2U 50/50 8.87 MW 8.87 MW
957381 AF2-032 C 50/50 1.43 MW 1.43 MW
957382 AF2-032 E 50/50 0.67 MW 0.67 MW
933441 AC2-157 C 50/50 27.65 MW 27.65 MW
933442 AC2-157 E 50/50 45.11 MW 45.11 MW
942601 AE2-276 C 50/50 18.19 MW 18.19 MW
945391 AF1-204 C 50/50 8.52 MW 8.52 MW
945392 AF1-204 E 50/50 25.57 MW 25.57 MW
930461 AB1-087 C 50/50 200.09 MW 200.09 MW
930462 AB1-087 E 50/50 9.1 MW 9.1 MW
930471 AB1-088 C 50/50 200.09 MW 200.09 MW
930472 AB1-088 E 50/50 9.1 MW 9.1 MW
963741 AG1-226 C 50/50 14.39 MW 14.39 MW
963742 AG1-226 E 50/50 31.21 MW 31.21 MW
944221 AF1-090 C 50/50 4.05 MW 4.05 MW
944222 AF1-090 E 50/50 18.94 MW 18.94 MW
957142 AF2-008 NFTI 50/50 181.9 MW 181.9 MW
957141 AF2-008 FTIR 50/50 181.9 MW 181.9 MW
944201 AF1-088 FTIR 50/50 363.79 MW 363.79 MW
956822 J1180 G External Queue 17.76 MW 17.76 MW
990272 J1263 G External Queue 56.17 MW 56.17 MW
991082 J1475 G External Queue 17.76 MW 17.76 MW
991537 J2131 External Queue 18.67 MW 18.67 MW
991552 J2170 G External Queue 35.54 MW 35.54 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 65.43 MW 65.43 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 36.11 MW 36.11 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.09 MW 2.09 MW
NY PJM->LTFIMP_NY CLTF 1.09 MW 1.09 MW
WEC LTFEXP_WEC->PJM CLTF 1.69 MW 1.69 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.56 MW 0.56 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.28 MW 0.28 MW
TVA LTFEXP_TVA->PJM CLTF 3.5 MW 3.5 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 1.94 MW 1.94 MW
MEC LTFEXP_MEC->PJM CLTF 9.88 MW 9.88 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 5.12 MW 5.12 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.08 MW 6.08 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.36 MW 0.36 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 13.38 MW 13.38 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.86 MW 0.86 MW

Details for 05FALL C-05DESOTO 345.0 kV Ckt 1 line l/o AEP_P1-2_#534_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
AEP 05FALL C-05DESOTO 345.0 kV Ckt 1 line
243222 to 243218 ckt 1
AEP_P1-2_#534_SRT-A-1
CONTINGENCY 'AEP_P1-2_#534_SRT-A-1'
 OPEN BRANCH FROM BUS 243233 TO BUS 964350 CKT 1   /*05TANNER     345.0 - AG1-297 TP   345.0
END
OP AC 107.34 1160.0 B 1245.09 25.8
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
AEP 05FALL C-05DESOTO 345.0 kV Ckt 1 line
243222 to 243218 ckt 1
AEP_P1-2_#534_SRT-A-1
CONTINGENCY 'AEP_P1-2_#534_SRT-A-1'
 OPEN BRANCH FROM BUS 243233 TO BUS 964350 CKT 1   /*05TANNER     345.0 - AG1-297 TP   345.0
END
OP AC 107.7 1160.0 B 1249.34 25.64
Topology Case Flowgate Details for 05FALL C-05DESOTO 345.0 kV Ckt 1 line l/o AEP_P1-2_#534_SRT-A-1
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966531 AG1-522 C Adder 10.03 MW 8.52 MW
966532 AG1-522 E Adder 6.68 MW 5.68 MW
966541 AG1-523 C Adder 10.03 MW 8.52 MW
966542 AG1-523 E Adder 6.68 MW 5.68 MW
966551 AG1-524 C Adder 10.03 MW 8.52 MW
966552 AG1-524 E Adder 6.68 MW 5.68 MW
966561 AG1-525 C Adder 10.03 MW 8.52 MW
966562 AG1-525 E Adder 6.68 MW 5.68 MW
247285 05AND G1 50/50 1.07 MW 1.07 MW
247286 05AND G2 50/50 1.07 MW 1.07 MW
247287 05AND G3 50/50 2.24 MW 2.24 MW
247958 05WLD G2 E Adder 10.09 MW 8.58 MW
934961 AD1-128 C Adder -6.99 MW -5.95 MW
936561 AD2-071 C Adder 3.38 MW 2.87 MW
936562 AD2-071 E Adder 1.66 MW 1.42 MW
959691 AF2-260 C Adder 2.7 MW 2.3 MW
959692 AF2-260 E Adder 1.63 MW 1.39 MW
960181 AF2-309 C Adder 2.15 MW 1.83 MW
960182 AF2-309 E Adder 1.43 MW 1.22 MW
942071 AE2-219 C Adder -3.5 MW -2.98 MW
957961 AF2-090 C Adder 3.9 MW 3.31 MW
957962 AF2-090 E Adder 1.93 MW 1.64 MW
933441 AC2-157 C Adder 5.19 MW 4.41 MW
933442 AC2-157 E Adder 8.46 MW 7.19 MW
934161 AD1-043 C Adder 3.71 MW 3.15 MW
934162 AD1-043 E Adder 6.06 MW 5.15 MW
942601 AE2-276 C Adder 3.41 MW 2.9 MW
942791 AE2-297 C O1 50/50 1.66 MW 1.66 MW
942792 AE2-297 E O1 50/50 7.47 MW 7.47 MW
945391 AF1-204 C Adder 5.62 MW 4.78 MW
945392 AF1-204 E Adder 16.86 MW 14.33 MW
960171 AF2-308 C Adder 1.43 MW 1.22 MW
961001 AF2-391 C Adder 3.73 MW 3.17 MW
961002 AF2-391 E Adder 2.49 MW 2.12 MW
961161 AF2-407 C 50/50 122.45 MW 122.45 MW
961171 AF2-408 C 50/50 20.62 MW 20.62 MW
930461 AB1-087 C Adder 37.53 MW 31.9 MW
930462 AB1-087 E Adder 1.71 MW 1.45 MW
930471 AB1-088 C Adder 37.53 MW 31.9 MW
930472 AB1-088 E Adder 1.71 MW 1.45 MW
939781 AE1-209 C Adder -3.05 MW -2.59 MW
939791 AE1-210 C Adder -3.05 MW -2.59 MW
963741 AG1-226 C Adder 8.14 MW 6.92 MW
963742 AG1-226 E Adder 17.66 MW 15.01 MW
964351 AG1-297 C 50/50 16.86 MW 16.86 MW
964352 AG1-297 E 50/50 50.57 MW 50.57 MW
940981 AE2-089 C Adder -7.76 MW -6.59 MW
944221 AF1-090 C Adder 1.81 MW 1.54 MW
944222 AF1-090 E Adder 8.47 MW 7.2 MW
957142 AF2-008 NFTI Adder 40.14 MW 34.12 MW
957141 AF2-008 FTIR Adder 40.14 MW 34.12 MW
944201 AF1-088 FTIR Adder 80.28 MW 68.24 MW
990497 J1323 External Queue -1.47 MW -1.47 MW
990527 J1329 G External Queue -1.04 MW -1.04 MW
991182 J1586 G External Queue -25.38 MW -25.38 MW
991372 J1860 G External Queue -3.11 MW -3.11 MW
991487 J2056 G External Queue -10.38 MW -10.38 MW
991507 J2064 External Queue -5.11 MW -5.11 MW
955152 J993 G External Queue 40.32 MW 40.32 MW
990427 J1308 G External Queue 16.21 MW 16.21 MW
991162 J1518 External Queue 11.09 MW 11.09 MW
991187 J1593 G External Queue 35.73 MW 35.73 MW
991207 J1637 External Queue 14.46 MW 14.46 MW
991252 J1691 External Queue 13.49 MW 13.49 MW
991462 J2032 External Queue 13.16 MW 13.16 MW
991502 J2063 External Queue 9.64 MW 9.64 MW
991532 J2123 External Queue 2.59 MW 2.59 MW
991547 J2164 External Queue 21.91 MW 21.91 MW
991557 J2177 External Queue 7.6 MW 7.6 MW
991562 J2178 External Queue 6.75 MW 6.75 MW
991617 J2230 External Queue 26.98 MW 26.98 MW
991622 J2232 External Queue 11.35 MW 11.35 MW
991652 J2254 External Queue 8.77 MW 8.77 MW
991657 J2263 External Queue 10.49 MW 10.49 MW
991662 J2270 External Queue 20.23 MW 20.23 MW
991682 J2296 External Queue 6.74 MW 6.74 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 24.18 MW 24.18 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 37.51 MW 37.51 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 13.91 MW 13.91 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.33 MW 0.33 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.55 MW 2.55 MW
WEC LTFEXP_WEC->PJM CLTF 0.67 MW 0.67 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.92 MW 0.92 MW
TVA LTFEXP_TVA->PJM CLTF 5.06 MW 5.06 MW
MEC LTFEXP_MEC->PJM CLTF 5.21 MW 5.21 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.32 MW 6.32 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.94 MW 0.94 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.1 MW 2.1 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.44 MW 0.44 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle #2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle #2.

Light Load Analysis

The New Service Request was evaluated as a 450.0 MW injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

(No impacts were found for this analysis)

Light Load Potential Congestion due to Local Energy Deliverability

(No impacts were found for this analysis)

Short Circuit Analysis

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests AF1-204 and AG1-226 in PJM Transition Cycle 1, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 131 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-204 and AG1-226 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCAU1 models of AF1-204 showed erratic behavior for some contingencies in which AF1-204 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

AG1-226 exhibited slow reactive power recovery for contingencies P4.41,

 

P4.44, P7.01 and P7.04. This issue did not cause instability in the system and the model can be tuned to have faster reactive power output settlement upon request. 

 

No mitigations were found to be required.

 

The stability study results in this report identified system performance issues.  PJM is actively performing simulations to assess the impacts of potential dynamic model parameter changes required to address identified stability issues. Additionally, feedback from the Transmission Owner is being incorporated into the stability study. The study will be finalized at the conclusion of Phase III of Transition Cycle. 

Table 1: TC1 Cluster 64 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

64

AF1-204

Wind

AEP

255

255

63.75

Eugene 345 kV

AG1-226

Solar

AEP

450

450

142

Eugene-Dequine 345 kV

 

Reactive Power Analysis

The reactive power capability of AG1-226 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected Systems

In Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator (MISO) Study Pending
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase II analysis results, this project has potential cost responsibility for the following System Reinforcements:

AG1-226 System Reinforcements Cost Breakdown:
Type TO RTEP ID / TO ID Title MW Impact Percent Allocation Allocated Cost ($USD)
Load Flow AEP n9243 / AEPSERG13 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles 76.8 MW 4.1% $3,330,873
Load Flow DEI n9123 / DEI_TC1_13416 MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP SE rating is 1868 MVA . 239.4 MW 26.5% $2,009,513
Load Flow AEP n9260 / AEP_TC1_16006 AEP end termination of new Eugene - Cayuga 345kV proposed second circuit reinforcement from MISO 239.4 MW 26.5% $913,792
Load Flow AEP n7964 / AEPI0025a Replace 765/345 Transformer 38.4 MW 4.2% $205,573
Load Flow AEP n4106.4 Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. 38.4 MW 4.0% $81,017
Load Flow AEP n7943.2 / AEPI0025b Replace Jefferson 345kV Circuit Breaker (5000A) 38.4 MW 4.2% $41,115
Load Flow AEP n4106.6 / AEPI0045e Replace Jefferson Breaker (5000A) 38.4 MW 4.0% $38,888
Load Flow OVEC n9185 / OVECPJH01 Replace 5" Al Tubing 345 kV bus at Clifty Creek 38.4 MW 4.0% $12,464
Load Flow AEP n4106.5 / AEPI0045c Replace Clifty Bus 5"0 AL Tubular Sch 40 38.4 MW 4.0% $3,241
Load Flow AEP n4106.7 / AEPI0045f An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. 38.4 MW 4.0% $810
Load Flow AEP n9180 / AEPSERG09 Jefferson CT thermal limit 38.4 MW 4.0% $623
Load Flow AEP n9181 / AEPSERG10 Clifty relay thermal limit 38.4 MW 4.0% $623
Grand Total: $6,638,532
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n9243 / AEPSERG13 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles $130,000,000 $3,330,873 36 to 48 Months

ContributorTopology Changing

Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Description: There is no bigger 765/345 kV transformer in the AEP system than the transformer at Jefferson station or a bigger 345 kV breaker than the Jefferson 345 kV breaker to be able to upgrade to a bigger size. Expand 345 kV north of Jefferson station install a second 765/345 kV 750 MVA transformer, install a 345 kV low side breaker and install a second Jefferson - Clifty Creek 345 kV single circuit line ~0.8 miles. Install new 765 kV breaker "B2" at the existing Jefferson station and 765 kV line than ~0.25 miles to connect to the new 765/345 750 MVA transformer. Install a 345 kV circuit breaker at Clifty Creek OVEC station. This reinforcement will reduce loadings on the branch and mitigations for limiting elements due to lower loadings may no longer be required. This reinforcement should reduce loadings such that no further mitigation is needed for TC1 PH2.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line SUM B 3040.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 1.3% $1,053,578
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
468.4 MW 24.9% $20,315,887
AF1-204 25.6 MW 1.4% $1,110,826
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
468.4 MW 24.9% $20,315,887
AG1-226 76.8 MW 4.1% $3,330,873
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.1% $105,692
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
203.7 MW 10.8% $8,835,170
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
203.7 MW 10.8% $8,835,170
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
203.7 MW 10.8% $8,835,170
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
203.7 MW 10.8% $8,835,170
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow DEI n9123 / DEI_TC1_13416 MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP SE rating is 1868 MVA . $12,095,000 $2,009,513 TBD

ContributorTopology Changing

Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Description: AEP SE rating is 1868 MVA . MISO end upgrade: Mitigation would be add a new 345kV Circuit in Parallel of existing 345kV line from Cayuga to Eugene. AEP end cost TBD.

Flowgates Addressed by this Reinforcement
Facility Contingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (All) A 9999.0 MVA
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (All) B 9999.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-223 McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.5 MW 1.3% $96,524
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
26.6 MW 2.9% $223,182
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
126.7 MW 14.0% $1,063,909
AF1-204 135.7 MW 15.0% $1,138,869
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
126.7 MW 14.0% $1,063,909
AF2-225 McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.5 MW 1.3% $96,524
AF2-407 32.7 MW 3.6% $274,403
AG1-226 239.4 MW 26.5% $2,009,513
AG1-236 17.2 MW 1.9% $144,269
AG1-297 31.5 MW 3.5% $264,754
AG1-374 23.7 MW 2.6% $199,133
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.7 MW 0.3% $22,395
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $248,020
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $248,020
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $248,020
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $248,020
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n9260 / AEP_TC1_16006 AEP end termination of new Eugene - Cayuga 345kV proposed second circuit reinforcement from MISO $5,500,000 $913,792 36 Months

ContributorTopology Changing

Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Description: Add a new breaker string with 2 new breakers and associated equipment to the Eugene station. Raise a double circuit tower so that the new second Eugene - Cayuga 345kV can be routed underneath it.

Flowgates Addressed by this Reinforcement
Facility Contingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-223 McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.5 MW 1.3% $43,893
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
26.6 MW 2.9% $101,488
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
126.7 MW 14.0% $483,795
AF1-204 135.7 MW 15.0% $517,882
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
126.7 MW 14.0% $483,795
AF2-225 McLean 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.5 MW 1.3% $43,893
AF2-407 32.7 MW 3.6% $124,780
AG1-226 239.4 MW 26.5% $913,792
AG1-236 17.2 MW 1.9% $65,604
AG1-297 31.5 MW 3.5% $120,392
AG1-374 23.7 MW 2.6% $90,552
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.7 MW 0.3% $10,184
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $112,783
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $112,783
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $112,783
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
29.5 MW 3.3% $112,783
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n7964 / AEPI0025a Replace 765/345 Transformer $7,800,000 $205,573 24 to 36 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: Replace 765/345 Transformer

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3113.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 3113.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 25.6% $1,253,846
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 25.6% $1,253,846
AG1-226 38.4 MW 4.2% $205,573
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $545,285
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $545,285
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $545,285
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $545,285
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n4106.4 Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload. $3,250,000 $81,017 24 to 36 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: Rebuild 0.75 miles of ACSR ~ 2156 ~ 64/19 ~ BLUEBIRD conductor to mitigate the overload.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 2365.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3290.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $51,253
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $494,146
AF1-204 25.6 MW 2.6% $54,037
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $494,146
AG1-226 38.4 MW 4.0% $81,017
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $5,142
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $214,899
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $214,899
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $214,899
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $214,899
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n7943.2 / AEPI0025b Replace Jefferson 345kV Circuit Breaker (5000A) $1,560,000 $41,115 18 to 24 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: Replace Jefferson 345kV Circuit Breaker (5000A)

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) A 3426.0 MVA
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (All) B 3582.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 25.6% $250,769
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 25.6% $250,769
AG1-226 38.4 MW 4.2% $41,115
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $109,057
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $109,057
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $109,057
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 11.1% $109,057
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n4106.6 / AEPI0045e Replace Jefferson Breaker (5000A) $1,560,000 $38,888 18 to 24 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: Replace Jefferson Breaker (5000A)

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 3290.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3290.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $24,601
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $237,190
AF1-204 25.6 MW 2.6% $25,938
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $237,190
AG1-226 38.4 MW 4.0% $38,888
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $2,468
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $103,151
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $103,151
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $103,151
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $103,151
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow OVEC n9185 / OVECPJH01 Replace 5" Al Tubing 345 kV bus at Clifty Creek $500,000 $12,464 18 to 24 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: Replace 5" Al Tubing 345 kV bus at Clifty Creek. Note: From AEP: AEP owns a potion of the is bus as well due to split ownership of the station

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3039.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $7,885
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $76,022
AF1-204 25.6 MW 2.6% $8,313
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $76,022
AG1-226 38.4 MW 4.0% $12,464
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $791
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $33,061
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $33,061
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $33,061
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $33,061
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n4106.5 / AEPI0045c Replace Clifty Bus 5"0 AL Tubular Sch 40 $130,000 $3,241 18 to 24 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: Replace Clifty Bus 5"0 AL Tubular Sch 40

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 2365.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 2831.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $2,050
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $19,766
AF1-204 25.6 MW 2.6% $2,161
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $19,766
AG1-226 38.4 MW 4.0% $3,241
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $206
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $8,596
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $8,596
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $8,596
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $8,596
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n4106.7 / AEPI0045f An engineering study will need to be conducted to determine if the Jefferso [...] l be required if the settings cannot be adjusted. $32,500 $810 12 to 18 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: An engineering study will need to be conducted to determine if the Jefferson Relay Compliance Trip limits 5506 Amps settings can be adjusted to mitigate the overload. New relay packages will be required if the settings cannot be adjusted. Estimated Cost: $600,000.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 3426.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3581.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $513
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $4,941
AF1-204 25.6 MW 2.6% $540
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $4,941
AG1-226 38.4 MW 4.0% $810
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $51
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $2,149
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $2,149
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $2,149
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $2,149
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n9180 / AEPSERG09 Jefferson CT thermal limit $25,000 $623 12 to 18 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: An engineering study will need to be conducted to determine if the Jefferson CT thermal limitsettings can be adjusted to mitigate the overload.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) A 3426.0 MVA
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3736.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $394
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $3,801
AF1-204 25.6 MW 2.6% $416
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $3,801
AG1-226 38.4 MW 4.0% $623
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $40
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow AEP n9181 / AEPSERG10 Clifty relay thermal limit $25,000 $623 12 to 18 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Description: An engineering study will need to be conducted to determine if the Clifty Relay Thermal limits settings can be adjusted to mitigate the overload.

Flowgates Addressed by this Reinforcement
Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (All) B 3426.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
24.3 MW 2.5% $394
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $3,801
AF1-204 25.6 MW 2.6% $416
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008
234.2 MW 24.2% $3,801
AG1-226 38.4 MW 4.0% $623
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.3% $40
AG1-522 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
AG1-523 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
AG1-524 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653
AG1-525 Sullivan - Rockport 765kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-522, AG1-523, AG1-524, AG1-525
101.9 MW 10.5% $1,653

Attachments


[1]Winter load flow analysis will be performed starting in Transition Cycle #2.