AH1-563 Phase I Study Report

v1.00 released 2025-10-29 20:49

Aurora E.C. 138kV

150.0 MW Capacity / 150.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Aurora Generation, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed an uprate to a planned/existing Natural Gas/Storage facility located in the Commonwealth Edison Company zone — Illinois. This project is an increase to the developer’s AC1-109/AC1-110/AC1-111/AG1-513 project(s), which will share the same Point of Interconnection. The AH1-563 project is a 150.0 MW uprate (150.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 1206.0 MW with 250.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-563
Project Name:
Aurora E.C. 138kV
Project Developer Name:
Aurora Generation, LLC
State:
Illinois
County:
Undetermined
Transmission Owner:
Commonwealth Edison Company
MFO:
1206.0
MWE:
150.0
MWC:
150.0
Battery Storage Specification:
600.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AH1-563 will interconnect on the Commonwealth Edison Company  transmission system at the Aurora 138 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AH1-563 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-563Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$0$0
Other Scope$350,000$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$2,600,000$2,600,000
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$2,950,000$2,600,000

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AH1-563

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AH1-563 Project due at DP1
ABA - B
AH1-563$260,000$600,000$0

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project, unless the Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or applicable Network Upgrades have been securitized in an ISA/GIA. 

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Physical Interconnection
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)SCADA, Relay and Comm' review/updates.$350,000 $350,000

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 12 to 15 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

Notes on Cost Estimate:

  1. These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
  2. There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
  3. These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
  4. The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.

 

 

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-563 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.

AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDCE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC112.02 %404.0STE452.56149.87
GD2CE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC110.66 %404.0STE447.06149.87
GD2CE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P4_111-45-L16703__SRT-A
BreakerAC107.33 %404.0STE433.62112.17
GD2CE
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Base Case
SingleAC106.4 %1201.0A1277.879.01
GD2CE
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
COMED_P4-6_111-345-R______SRT-A
BreakerAC106.31 %1568.0STE1666.9818.82

Details for [AH1-563] AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:112.02 %
Rating:404.0 MVA
Rating Type:STE
MVA to Mitigate:452.56
MW Contribution:149.87
IPD Plant:AH1-563
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
149.872

Details for AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:110.66 %
Rating:404.0 MVA
Rating Type:STE
MVA to Mitigate:447.06
MW Contribution:149.87
Bus #Bus NameTypeMW Contribution
276890AG1-513 C
50/50
3.997
274741AC1-111 GEN5
50/50
2.787
274742AC1-111 GEN6
50/50
2.787
274743AC1-111 GEN7
50/50
2.787
274744AC1-111 GEN8
50/50
50.956
274745AC1-111 GEN9
50/50
50.956
274746AC1-111 G10
50/50
50.956
972029AH1-563 GEN
50/50
149.872
NYPJM->LTFIMP_NY
CLTF
0.047
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.049
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.03
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
0.221
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.048
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.148
MDUPJM->LTFIMP_MDU
CLTF
0

Details for AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P4_111-45-L16703__SRT-A


Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P4_111-45-L16703__SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:107.33 %
Rating:404.0 MVA
Rating Type:STE
MVA to Mitigate:433.62
MW Contribution:112.17
Bus #Bus NameTypeMW Contribution
274693ROCKY RD ;1P
Adder
7.402
274695ROCKY RD ;2P
Adder
7.476
274696ROCKY RD ;4P
Adder
7.584
274697ROCKY RD ;3P
Adder
2.031
276890AG1-513 C
50/50
2.991
274741AC1-111 GEN5
50/50
2.086
274742AC1-111 GEN6
50/50
2.086
274743AC1-111 GEN7
50/50
2.086
274744AC1-111 GEN8
50/50
38.138
274745AC1-111 GEN9
50/50
38.138
274746AC1-111 G10
50/50
38.138
972029AH1-563 GEN
50/50
112.172
CBM West 1LTFEXP_CBM-W1->PJM
CBM
8.711
CBM West 2LTFEXP_CBM-W2->PJM
CBM
0.967
NYPJM->LTFIMP_NY
CLTF
0.093
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
0.52
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.057
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.032
TVALTFEXP_TVA->PJM
CLTF
0.02
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.08
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
1.392
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.242
LAGNLTFEXP_LAGN->PJM
CLTF
0.249

Details for ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line l/o Base Case


Base Case Flowgate

Area:CE
Facility Description:
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:106.4 %
Rating:1201.0 MVA
Rating Type:A
MVA to Mitigate:1277.87
MW Contribution:9.01
Bus #Bus NameTypeMW Contribution
274693ROCKY RD ;1P
Adder
5.275
274695ROCKY RD ;2P
Adder
5.327
274696ROCKY RD ;4P
Adder
5.428
274697ROCKY RD ;3P
Adder
1.447
274738AURORA EC;3P
50/50
1.4
274740AURORA EC;4P
50/50
1.4
274822ROCKFORD ;11
Adder
8.519
274823ROCKFORD ;21
Adder
8.46
274855GSG-6 ;RU
Solar/Wind Harmer
0.19
274856ECOGROVE ;U1
Solar/Wind Harmer
0.078
274760LEE CO EC;1U
Adder
5.499
276602WESTBROOK C
Solar/Wind Harmer
0
276603SUBLETTE C
Solar/Wind Harmer
0
274850MENDOTA H;RU
Solar/Wind Harmer
0.061
274761LEE CO EC;2U
Adder
5.499
274762LEE CO EC;3U
Adder
5.499
274763LEE CO EC;4U
Adder
5.447
274764LEE CO EC;5U
Adder
5.512
274765LEE CO EC;6U
Adder
5.512
274766LEE CO EC;7U
Adder
5.434
274767LEE CO EC;8U
Adder
5.434
274872LEEDK;1U
Solar/Wind Harmer
0.202
274872LEEDK;1U
Solar/Wind Harmer
0.003
276611AD2-172 GEN
Solar/Wind Harmer
0.001
276612AE2-035 GEN
Solar/Wind Harmer
0.001
276799AD1-013 GEN
Solar/Wind Harmer
0.001
276890AG1-513 C
50/50
0.24
274741AC1-111 GEN5
50/50
0.167
274742AC1-111 GEN6
50/50
0.167
274743AC1-111 GEN7
50/50
0.167
274744AC1-111 GEN8
50/50
3.062
274745AC1-111 GEN9
50/50
3.062
274746AC1-111 G10
50/50
3.062
276861AD2-134 GEN
Solar/Wind Harmer
0.093
276863AD2-134 GEN
Solar/Wind Harmer
0.093
274857EASY ROAD;U1
Solar/Wind Harmer
0.001
274858EASY ROAD;U2
Solar/Wind Harmer
0.001
938861AE1-114 GEN
Solar/Wind Harmer
2.141
943121AE2-341 GEN
Solar/Wind Harmer
8.952
946321AF1-296 GEN
Solar/Wind Harmer
1.865
946671AF1-331 GEN
Solar/Wind Harmer
0.555
959081AF2-199 GEN
Solar/Wind Harmer
8.365
959091AF2-200 GEN
Solar/Wind Harmer
16.73
961011AF2-392 GEN
Solar/Wind Harmer
2.541
962691AG1-118 GEN
Solar/Wind Harmer
17.758
962781AG1-127 GEN
Solar/Wind Harmer
5.247
970819AG2-516 GEN
Solar/Wind Harmer
3.637
970921AG2-575 GEN
Solar/Wind Harmer
5.514
970921AG2-575 GEN
Solar/Wind Harmer
1.838
971067AG2-660 GEN
Solar/Wind Harmer
2.788
971171AH1-044 GEN
Solar/Wind Harmer
16.73
971333AH1-146 GEN
Solar/Wind Harmer
7.632
971335AH1-147 GEN
Solar/Wind Harmer
7.632
971341AH1-150 GEN
Solar/Wind Harmer
16.73
971343AH1-151 GEN
Solar/Wind Harmer
16.73
971573AH1-285 GEN
Solar/Wind Harmer
1.008
971675AH1-338 GEN
Solar/Wind Harmer
2.025
971681AH1-341 GEN
Solar/Wind Harmer
6.413
276157O29GEN1
Solar/Wind Harmer
0.598
276158O29GEN2
Solar/Wind Harmer
0
276708O09 GEN2
Solar/Wind Harmer
0.132
276741O09 GEN1
Solar/Wind Harmer
0.132
957471AF2-041 GEN
Solar/Wind Harmer
25.095
965931AG1-462 GEN
Solar/Wind Harmer
8.404
972235AH1-702 GEN1
Adder
1.232
972236AH1-702 GEN2
Adder
1.068
972267AH1-718 GEN
Adder
2.741
943591AF1-030 GEN
Solar/Wind Harmer
5.953
972029AH1-563 GEN
50/50
9.006
CBM West 1LTFEXP_CBM-W1->PJM
CBM
8.633
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.757
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.535
NYPJM->LTFIMP_NY
CLTF
0.151
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.05
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.023
TVALTFEXP_TVA->PJM
CLTF
0.206
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.109
MECLTFEXP_MEC->PJM
CLTF
3.632
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.321
LAGNLTFEXP_LAGN->PJM
CLTF
0.91

Details for ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line l/o COMED_P4-6_111-345-R______SRT-A


Base Case Flowgate

Area:CE
Facility Description:
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_111-345-R______SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:106.31 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1666.98
MW Contribution:18.82
Bus #Bus NameTypeMW Contribution
274693ROCKY RD ;1P
Adder
7.7
274695ROCKY RD ;2P
Adder
7.776
274696ROCKY RD ;4P
Adder
7.923
274697ROCKY RD ;3P
Adder
2.112
274738AURORA EC;3P
50/50
1.619
274740AURORA EC;4P
50/50
1.619
274822ROCKFORD ;11
Adder
11.046
274823ROCKFORD ;21
Adder
10.969
274855GSG-6 ;RU
Solar/Wind Harmer
3.312
274856ECOGROVE ;U1
Solar/Wind Harmer
2
274760LEE CO EC;1U
Adder
6.572
276602WESTBROOK C
Solar/Wind Harmer
1.907
276603SUBLETTE C
Solar/Wind Harmer
0.756
274850MENDOTA H;RU
Solar/Wind Harmer
2.303
274761LEE CO EC;2U
Adder
6.572
274762LEE CO EC;3U
Adder
6.572
274763LEE CO EC;4U
Adder
6.51
274764LEE CO EC;5U
Adder
6.587
274765LEE CO EC;6U
Adder
6.587
274766LEE CO EC;7U
Adder
6.494
274767LEE CO EC;8U
Adder
6.494
274872LEEDK;1U
Solar/Wind Harmer
0.246
274872LEEDK;1U
Solar/Wind Harmer
7.885
276611AD2-172 GEN
Solar/Wind Harmer
1.518
276612AE2-035 GEN
Solar/Wind Harmer
1.518
276799AD1-013 GEN
Solar/Wind Harmer
1.994
276890AG1-513 C
50/50
0.502
274737AURORA EC;1P
50/50
1.024
274739AURORA EC;2P
50/50
1.024
274741AC1-111 GEN5
50/50
0.35
274742AC1-111 GEN6
50/50
0.35
274743AC1-111 GEN7
50/50
0.35
274744AC1-111 GEN8
50/50
6.398
274745AC1-111 GEN9
50/50
6.398
274746AC1-111 G10
50/50
6.398
276861AD2-134 GEN
Solar/Wind Harmer
1.602
276863AD2-134 GEN
Solar/Wind Harmer
1.602
274857EASY ROAD;U1
Solar/Wind Harmer
3.385
274858EASY ROAD;U2
Solar/Wind Harmer
3.385
938861AE1-114 GEN
Solar/Wind Harmer
5.367
942991AE2-321 GEN
Solar/Wind Harmer
5.137
943121AE2-341 GEN
Solar/Wind Harmer
14.555
946321AF1-296 GEN
Solar/Wind Harmer
5.753
946671AF1-331 GEN
Solar/Wind Harmer
0.378
959081AF2-199 GEN
Solar/Wind Harmer
13.151
959091AF2-200 GEN
Solar/Wind Harmer
26.301
960751AF2-366 GEN
Solar/Wind Harmer
2.767
961011AF2-392 GEN
Solar/Wind Harmer
7.849
962691AG1-118 GEN
Solar/Wind Harmer
30.866
962781AG1-127 GEN
Solar/Wind Harmer
9.173
970819AG2-516 GEN
Solar/Wind Harmer
6.653
970921AG2-575 GEN
Solar/Wind Harmer
9.646
970921AG2-575 GEN
Solar/Wind Harmer
2.243
971067AG2-660 GEN
Solar/Wind Harmer
3.058
971171AH1-044 GEN
Solar/Wind Harmer
26.301
971177AH1-047 GEN
Solar/Wind Harmer
3.083
971333AH1-146 GEN
Solar/Wind Harmer
14.63
971335AH1-147 GEN
Solar/Wind Harmer
14.63
971341AH1-150 GEN
Solar/Wind Harmer
26.301
971343AH1-151 GEN
Solar/Wind Harmer
26.301
971411AH1-196 GEN
Solar/Wind Harmer
7.549
971475AH1-234 GEN
Solar/Wind Harmer
10.987
971573AH1-285 GEN
Solar/Wind Harmer
8.369
971675AH1-338 GEN
Solar/Wind Harmer
16.183
971681AH1-341 GEN
Solar/Wind Harmer
10.29
276157O29GEN1
Solar/Wind Harmer
2.326
276158O29GEN2
Solar/Wind Harmer
3.058
276708O09 GEN2
Solar/Wind Harmer
2.185
276741O09 GEN1
Solar/Wind Harmer
2.185
957471AF2-041 GEN
Solar/Wind Harmer
39.452
965931AG1-462 GEN
Solar/Wind Harmer
13.862
972235AH1-702 GEN1
Adder
1.582
972236AH1-702 GEN2
Adder
1.372
972267AH1-718 GEN
Adder
3.157
943591AF1-030 GEN
Solar/Wind Harmer
9.703
970707AG2-453 GEN
Solar/Wind Harmer
15.509
972029AH1-563 GEN
50/50
18.818
CBM West 1LTFEXP_CBM-W1->PJM
CBM
10.908
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.761
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.478
NYPJM->LTFIMP_NY
CLTF
0.185
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.074
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.036
TVALTFEXP_TVA->PJM
CLTF
0.199
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.145
MECLTFEXP_MEC->PJM
CLTF
4.217
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.434
LAGNLTFEXP_LAGN->PJM
CLTF
0.979
CONTINGENCY 'COMED_P1-2_138-L14403_R-N_SRT-A'
 CLOSE LINE FROM BUS 271070 TO BUS 271071 CKT Z1   /*ESS W503 ; B 138.0 - ESS W503 ; R 138.0
 CLOSE LINE FROM BUS 272754 TO BUS 272755 CKT Z1   /*W CHICAGO; B 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 271069 CKT 1   /*BATAVIA  ;RT 138.0 - ESS W502 ; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 272755 CKT 1   /*BATAVIA  ;RT 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 272755 TO BUS 272741 CKT 1   /*W CHICAGO; R 138.0 - WAYNE    ; R 138.0
 TRIP BRANCH FROM BUS 274747 TO BUS 271067 CKT 1   /*AURORA EC;RP 138.0 - BATAVIA  ;RT 138.0
END
CONTINGENCY 'COMED_P4_111-45-L16703__SRT-A'
 DISCONNECT BUS 270731                             /*ELECT JCT;4R 345.0
 DISCONNECT BUS 275184                             /*ELECT JCT;4M 138.0
 TRIP BRANCH FROM BUS 270846 TO BUS 270847 CKT 1   /*PLANO    ; B 345.0 - PLANO    ; R 345.0
 TRIP BRANCH FROM BUS 270847 TO BUS 270733 CKT 1   /*PLANO    ; R 345.0 - ELECT JCT;3R 345.0
END
CONTINGENCY 'COMED_P4-6_111-345-R______SRT-A'
 DISCONNECT BUS 270731   /*ELECT JCT;4R 345.0
 DISCONNECT BUS 270733   /*ELECT JCT;3R 345.0
 DISCONNECT BUS 275183   /*ELECT JCT;3M 138.0
 DISCONNECT BUS 275184   /*ELECT JCT;4M 138.0
END
274747 to 271391 ckt 1
270732 to 270814 ckt 1

Winter Peak Analysis

The New Service Request AH1-563 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.

AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDCE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC105.72 %467.0STE493.7150.0
GD2CE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC104.46 %467.0STE487.85150.0

Details for [AH1-563] AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:105.72 %
Rating:467.0 MVA
Rating Type:STE
MVA to Mitigate:493.7
MW Contribution:150.0
IPD Plant:AH1-563
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
150

Details for AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.46 %
Rating:467.0 MVA
Rating Type:STE
MVA to Mitigate:487.85
MW Contribution:150.0
Bus #Bus NameTypeMW Contribution
276890AG1-513 C
50/50
4
274741AC1-111 GEN5
50/50
58.26
274742AC1-111 GEN6
50/50
58.26
274743AC1-111 GEN7
50/50
58.26
274744AC1-111 GEN8
50/50
58.26
274745AC1-111 GEN9
50/50
58.26
274746AC1-111 G10
50/50
58.26
972029AH1-563 GEN
50/50
150
CONTINGENCY 'COMED_P1-2_138-L14403_R-N_SRT-A'
 CLOSE LINE FROM BUS 271070 TO BUS 271071 CKT Z1   /*ESS W503 ; B 138.0 - ESS W503 ; R 138.0
 CLOSE LINE FROM BUS 272754 TO BUS 272755 CKT Z1   /*W CHICAGO; B 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 271069 CKT 1   /*BATAVIA  ;RT 138.0 - ESS W502 ; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 272755 CKT 1   /*BATAVIA  ;RT 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 272755 TO BUS 272741 CKT 1   /*W CHICAGO; R 138.0 - WAYNE    ; R 138.0
 TRIP BRANCH FROM BUS 274747 TO BUS 271067 CKT 1   /*AURORA EC;RP 138.0 - BATAVIA  ;RT 138.0
END
274747 to 271391 ckt 1

Light Load Analysis

The New Service Request AH1-563 was evaluated as a 150.0 MW injection and 150.0 MW withdrawal in the ComEd area.

AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage analysis is not performed as part of the Phase I System Impact Study. Steady State Voltage analysis will commence in the Phase II System Impact Study.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AC1-111Aurora 138kVIn Service
AD1-013Twombly Road 138kVEngineering & Procurement
AD2-134Shady OaksPartially in Service - Under Construction
AD2-172Lena 138kVIn Service
AE1-114Maryland-Lancaster 138 kVActive
AE2-035Lena 138 kVIn Service
AE2-321Belvidere-Marengo 138 kVActive
AE2-341Sandwich-Plano 138 kVActive
AF1-030Sandwich-Plano 138 kVActive
AF1-296Garden Plain 138 kVActive
AF1-331Twombley RoadEngineering & Procurement
AF2-041Nelson-Electric Junction 345 kVActive
AF2-199Nelson-Electric Junction 345 kVActive
AF2-200Nelson-Electric Junction 345 kVActive
AF2-366Crego Rd 138 kVEngineering & Procurement
AF2-392Nelson-Dixon 138 kVActive
AG1-118Sugar Grove-Waterman 138kVActive
AG1-127Crego Rd 138 kVActive
AG1-462Cordova 345 kVActive
AG1-513Aurora 138 kVSuspended
AG2-453Lasalle - Plano 345 kVActive
AG2-516Pecatonica 138kVActive
AG2-575Crego Rd. 138 kVActive
AG2-660Nelson-Electric Junction 345 kVActive
AH1-044Nelson - Electric Junction 345 kVActive
AH1-047Marengo - Belvidere 138 kVActive
AH1-146White Rock - Wayne 345 kVActive
AH1-147White Rock - Wayne 345 kVActive
AH1-150Nelson-Electric Junction 345 kVActive
AH1-151Nelson-Electric Junction 345 kVActive
AH1-196Prairie 345 kVActive
AH1-234Wempletown - Paddock 345 kVActive
AH1-285Sandwich 138 kVActive
AH1-338McGirr Rd - Ritchie Road 138kVActive
AH1-341Stillman - Dixon 138KVActive
AH1-702Byron 345 kVActive
AH1-718Nelson 345 kVActive

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Study Pending
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Phase I analysis results, this project may have a cost responsibility for the following System Reinforcements:

AH1-563 System Reinforcements:
TORTEP IDTitleAllocated Cost ($USD)
ComEd(Pending) / CE_NUN_L11103_1TC2 NETWORK UPGRADE - 138KV L11103$2,600,000
Grand Total:$2,600,000

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
(Pending) / CE_NUN_L11103_1
Title
TC2 NETWORK UPGRADE - 138KV L11103
Description
STATION CONDUCTOR UPGRADES AT BOTH LINE TERMINALS. RECONDUCTOR L11103, POTENTIAL TRANSMISSION TOWER REPLACEMENT REQUIRED. THIS WILL BE DETERMINED DURING PJM PHASE III FACILITY STUDY. TEH ESTIMTAE PROVIDED DOES NOT INCLUDE THAT COST/TIMELINE.
Total Cost ($USD)
$2,600,000
Allocated Cost ($USD)
$2,600,000
Time Estimate
24 to 30 Months

Contributor

FacilityContingency
ELECT JCT;3R-AURORA EC;RP 138.0 kV Ckt 1 line(Any)
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AH1-563
150.0 MW100.0%$2,600,000

System Reinforcement: n7023.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n7023.1 / CE_NUN_L11124.1
Title
Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades.
Description
• Upgrade 13.5 Miles of 345kV transmission line 11124 from TSS 111 Electric Junction to TSS 120 Lombard • Upgrade relay & protection at 345kV substation TSS 111 Electric Junction & TSS 120 Lombard to support upgrade of 345kV transmission line, L1124
Total Cost ($USD)
$38,797,273
Allocated Cost ($USD)
$0
Time Estimate
36 Months

Contingent

Note: Based on PJM cost allocation criteria, AH1-563 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-563 could receive cost allocation. Although AH1-563 may not presently have cost responsibility for this upgrade, AH1-563 may need this upgrade in-service to be deliverable to the PJM system. If AH1-563 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line(Any)

Attachments

AH1-563 One Line Diagram

AH1-563 One Line Diagram.png
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.