AH1-744 Phase I Study Report

v1.00 released 2025-10-29 20:47

Cheltenham 500 kV

48.285 MW Capacity / 53.5 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Parkway Generation Operating LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Potomac Electric Power Company.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed a Natural Gas generating facility located in the Potomac Electric Power Company zone — Prince George's County, Maryland. The installed facilities will have a total capability of 853.5 MW with 48.285 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-744
Project Name:
Cheltenham 500 kV
Project Developer Name:
Parkway Generation Operating LLC
State:
Maryland
County:
Prince George's
Transmission Owner:
Potomac Electric Power Company
MFO:
853.5
MWE:
53.5
MWC:
48.285
Fuel Type:
Natural Gas
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AH1-744 will interconnect on the Potomac Electric Power Company transmission system by tapping X4-035/Z1-052 tap 500 kV. 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AH1-744 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-744Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$0$0
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$0$0

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AH1-744

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AH1-744 Project due at DP1
ABA - B
AH1-744$0$216,000$0

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

No additional equipment, facilities, or construction are required for this project, as it involves a MW uprate of the existing base project. However, relay settings will need to be reviewed during Phase 2 to determine if a new relay is necessary.

 



Transmission Owner Analysis

No impacts identified by Transmission Owner.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. PEPCO interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-744 was evaluated as a 53.5 MW (48.285 MW Capacity) injection in the PEPCO area.

AH1-744 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 853.5 MW (53.5 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Winter Peak Analysis

The New Service Request AH1-744 was evaluated as a 53.5 MW (48.285 MW Capacity) injection in the PEPCO area.

AH1-744 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 853.5 MW (53.5 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Light Load Analysis

The New Service Request AH1-744 was evaluated as a 53.5 MW injection

AH1-744 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 853.5 MW (53.5 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage analysis is not performed as part of the Phase I System Impact Study. Steady State Voltage analysis will commence in the Phase II System Impact Study.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.

Attachments

AH1-744 One Line Diagram

AH1-744 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.