AG2-163 Phase II System Impact Study Report
v1.00 released 2026-06-03 18:20
Dequine-Eugene 345 kV
35.0 MW Capacity / 250.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Dolphin Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed an uprate to a planned/existing Solar facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Fountain County, Indiana. This project is an increase to the developer’s AG1-226 project(s), which will share the same Point of Interconnection. The AG2-163 project is a 250.0 MW uprate (35.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 700.0 MW with 177.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AG2-163 will interconnect on the American Electric Power transmission system by tapping the Dequine-Eugene 345 kV Line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AG2-163 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG2-163 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 | $0 |
| Other Scope | $603,891 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $304,936 | $304,936 | $304,936 |
| Network Upgrades | $968,778 | $968,778 | $968,778 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $30,941 | $0 | $30,941 |
| Total | $1,908,546 | $1,273,714 | $1,304,655 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AG2-163
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AG2-163
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | IMTCO will tie the proposed AG2-163 345 kV project into the existing Dequine-Eugene 345 kV station by completing the following construction tasks: - Installation of (3) 345KV RCVTs with (3) single-phase 345KV CCVT structures, foundations, and adapter steel. - AEP Indiana Michigan Transmission Company Inc. will review and revise (as needed) the protective relay settings at the AG1-226 New 345 kV Station. - AEP Indiana Michigan Transmission Company Inc. will install one (1) new 1101 router at the AG1-226 New Station 345 kV Station. | $420,621 | $313,499 | $136,796 | $97,862 | $968,778 | $968,778 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | AEP Indiana Michigan Transmission Company Inc. will install one (1) metering panel with two (2) primary meters and one (1) ethernet switch in the AG2-163 Project Developer's collector Station. | $310,265 | $139,608 | $106,222 | $47,796 | $603,891 | $603,891 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Installation of Power Quality monitoring equipment | $197,501 | $38,273 | $57,935 | $11,227 | $304,936 | $304,936 |
Developer Build Option
(No Developer Build Option for this project.)
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $1,877,605 | $1,877,605 | |||||
| Developer Build Option | (No Developer Build Option) | ||||||
Based on the scope of work for the Interconnection Facilities, it is expected to take 15 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AG2-163 was evaluated as a 250.0 MW (35.0 MW Capacity) injection in the AEP area.
AG2-163 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 700.0 MW (250.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS | Breaker | AC | 103.15 % | 5523.0 | B | 5696.85 | 24.03 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS | Breaker | AC | 103.15 % | 5523.0 | B | 5696.85 | 24.03 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237805-SB6_SRT-SL_SENS | Breaker | AC | 103.14 % | 5523.0 | B | 5696.46 | 24.03 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237805-SB5_SRT-SL_SENS | Breaker | AC | 103.14 % | 5523.0 | B | 5696.46 | 24.03 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237805-SB3_SRT-SL_SENS | Breaker | AC | 103.14 % | 5523.0 | B | 5696.16 | 24.03 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 102.09 % | 5523.0 | B | 5638.63 | 3.91 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 102.08 % | 5523.0 | B | 5637.94 | 3.91 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS | Breaker | AC | 218.92 % | 1180.0 | B | 2583.23 | 19.2 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 218.92 % | 1180.0 | B | 2583.23 | 19.2 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS | Breaker | AC | 218.92 % | 1180.0 | B | 2583.23 | 19.2 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 218.9 % | 1180.0 | B | 2582.97 | 19.2 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2168-555_SRT-A | Tower | AC | 190.44 % | 1180.0 | B | 2247.18 | 16.1 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2114-535_SRT-A_SENS | Tower | AC | 186.74 % | 1180.0 | B | 2203.48 | 15.57 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P2-2: BREMO B1_SRT-A | Bus | AC | 182.69 % | 1180.0 | B | 2155.77 | 15.43 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P2-2: ALTAVISTA 138KV_SRT-A | Bus | AC | 182.37 % | 1180.0 | B | 2151.99 | 15.48 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | Base Case | Single | AC | 178.66 % | 1180.0 | A | 2108.2 | 15.45 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS | Breaker | AC | 124.63 % | 4571.0 | B | 5696.85 | 24.03 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS | Breaker | AC | 124.63 % | 4571.0 | B | 5696.85 | 24.03 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB6_SRT-SL_SENS | Breaker | AC | 124.62 % | 4571.0 | B | 5696.46 | 24.03 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB5_SRT-SL_SENS | Breaker | AC | 124.62 % | 4571.0 | B | 5696.46 | 24.03 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB4_SRT-SL_SENS | Breaker | AC | 124.62 % | 4571.0 | B | 5696.16 | 24.03 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 123.36 % | 4571.0 | B | 5638.63 | 3.91 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 123.34 % | 4571.0 | B | 5637.94 | 3.91 | |
| GD2 | AEP | 05KAMMER_RG-05KAMMER 765.0 kV Ckt Z1 line | AP_P1-3_MP-765-501T_SRT-A | Single | AC | 104.85 % | 4142.0 | B | 4342.78 | 5.16 | |
| GD2 | AEP | 05KAMMER_RG-05KAMMER 765.0 kV Ckt Z1 line | AEP_P1-2_#706_SRT-A | Single | AC | 104.04 % | 4142.0 | B | 4309.27 | 5.69 | |
| GD2 | AEP | 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | AEP_P1-2_#AG1-125-ADKINS_SRT-A_SENS | Single | AC | 101.48 % | 4571.0 | B | 4638.62 | 5.22 | |
| GD2 | AEP | 05MARYSVL_RM-05MALIS 765.0 kV Ckt 1 line | AEP_P1-2_#AG1-125-ADKINS_SRT-A_SENS | Single | AC | 101.94 % | 4571.0 | B | 4659.48 | 5.22 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P1-2_#XXXX_GREENTOWN_TEDDY_SRT-A_SENS | Single | AC | 120.92 % | 4142.0 | B | 5008.41 | 5.72 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P1-2_#9287_1679_SRT-A | Single | AC | 103.12 % | 4142.0 | B | 4271.28 | 3.55 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#3149_05HANG R 765_B_SRT-A | Breaker | AC | 143.94 % | 1540.0 | B | 2216.66 | 12.9 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#1760_05JEFRSO 765_A_SRT-A | Breaker | AC | 123.49 % | 1540.0 | B | 1901.76 | 11.57 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#1558_05BAKER 765_Q_SRT-A | Breaker | AC | 121.58 % | 1540.0 | B | 1872.34 | 11.84 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#309_05HANG R 765_B2_SRT-A | Breaker | AC | 121.32 % | 1540.0 | B | 1868.38 | 11.82 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#1560_05BAKER 765_Q2_SRT-A | Breaker | AC | 121.04 % | 1540.0 | B | 1864.08 | 11.81 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P2-2_#6156_05MARQUI 765_2_SRT-A | Bus | AC | 120.75 % | 1540.0 | B | 1859.53 | 12.52 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 108.24 % | 1540.0 | B | 1666.97 | 11.17 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P2-2_#308_05CULLOD 765_1_SRT-A | Bus | AC | 106.58 % | 1540.0 | B | 1641.32 | 10.78 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AP | 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | AP_P1-2_MP-500-028_SRT-A | Single | AC | 122.65 % | 3792.0 | B | 4650.99 | 3.72 | |
| GD2 | AP | 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | AP_P1-3_MP-765-502T_SRT-A | Single | AC | 122.64 % | 3792.0 | B | 4650.57 | 3.72 | |
| GD2 | AP | 01FLINTRUN-01HARRSN 500.0 kV Ckt 1 line | AP_P1-3_MP-765-502T_SRT-A | Single | AC | 138.45 % | 3792.0 | B | 5250.02 | 3.65 | |
| GD2 | AP | 01FLINTRUN-01HARRSN 500.0 kV Ckt 1 line | AP_P1-2_MP-500-028_SRT-A | Single | AC | 138.41 % | 3792.0 | B | 5248.4 | 3.65 | |
| GD2 | AP | 01KAMMER-01 502 J 500.0 kV Ckt 1 line | AP_P1-2_MP-500-007A_SRT-A | Single | AC | 131.87 % | 3729.0 | B | 4917.49 | 4.12 | |
| GD2 | AP | 01KAMMER-01 502 J 500.0 kV Ckt 1 line | AP_P1-2_MP-500-008A_SRT-SL | Single | AC | 124.24 % | 3729.0 | B | 4632.89 | 3.98 | |
| GD2 | ATSI | 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P1-2_TE-345-602_SRT-A | Single | AC | 113.4 % | 1683.0 | B | 1908.5 | 1.97 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 110.65 % | 1737.0 | B | 1922.03 | 2.67 | |
| GD2 | AEP/AP | 05BELMON-01BELMNT 765.0/500.0 kV Ckt 5 transformer | AP_P1-2_MP-500-028_SRT-A | Single | AC | 100.79 % | 4000.0 | B | 4031.79 | 3.9 | |
| GD2 | AEP/AP | 05BELMON-01BELMNT 765.0/500.0 kV Ckt 5 transformer | AP_P1-3_MP-765-502T_SRT-A | Single | AC | 100.79 % | 4000.0 | B | 4031.62 | 3.9 | |
| GD2 | AEP | 05CLOV17_XFL-05CLOVRD 345.0 kV Ckt 17 line | AEP_P4_#7421_05CLOVRD 765_BB2_SRT-A | Breaker | AC | 107.18 % | 2320.0 | B | 2486.65 | 11.68 | |
| GD2 | AEP | 05CLOV17_XFL-05CLOVRD 345.0 kV Ckt 17 line | AEP_P1-3_#7421_05CLOVRD 765_14_SRT-A | Single | AC | 104.78 % | 2320.0 | B | 2430.97 | 1.9 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AP_P1-3_MP-765-501T_SRT-A | Single | AC | 118.13 % | 3393.4 | B | 4008.49 | 3.65 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AP_P2-3_MP-500-020_SRT-SL | Breaker | AC | 115.66 % | 3610.0 | B | 4175.28 | 22.55 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AP_P2-3_MP-500-021_SRT-SL | Breaker | AC | 115.4 % | 3610.0 | B | 4165.98 | 22.45 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AEP_P4_#37_05MOUNTN 765_B1_SRT-A | Breaker | AC | 115.26 % | 3610.0 | B | 4160.96 | 22.41 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AEP_P4_#2942_05KAMMER 765_PP_SRT-A | Breaker | AC | 114.94 % | 3610.0 | B | 4149.41 | 22.42 | |
| GD2 | AEP | 05ELDERBERRY-05DUMONT 345.0 kV Ckt 1 line | AEP_P4_#2978_05DUMONT 765_B_SRT-A | Breaker | AC | 115.16 % | 1868.0 | B | 2151.12 | 15.88 | |
| GD2 | AEP | 05ELDERBERRY-05DUMONT 345.0 kV Ckt 1 line | AEP_P4_#671_05COOK 345_M2_SRT-A | Breaker | AC | 104.8 % | 1868.0 | B | 1957.75 | 16.6 | |
| GD2 | AEP | 05ELDERBERRY-05DUMONT 345.0 kV Ckt 1 line | AEP_P4_#6560_05COOK 345_M_SRT-A | Breaker | AC | 104.7 % | 1868.0 | B | 1955.71 | 16.6 | |
| GD2 | AEP | 05ELDERBERRY-05DUMONT 345.0 kV Ckt 1 line | AEP_P7-1_#10997___SRT-A | Tower | AC | 104.69 % | 1868.0 | B | 1955.69 | 16.6 | |
| GD2 | AEP | 05HANGRCK_RJ-05HANG R 765.0 kV Ckt Z1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 104.71 % | 4571.0 | B | 4786.33 | 40.1 | |
| GD2 | AEP | 05HANGRCK_RJ-05HANG R 765.0 kV Ckt Z1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 103.97 % | 4571.0 | B | 4752.25 | 39.55 | |
| GD2 | AEP | 05HANGRCK_RJ-05HANG R 765.0 kV Ckt Z1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 100.43 % | 4571.0 | B | 4590.88 | 39.73 | |
| GD2 | AEP | 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer | AEP_P4_#6189_05HANG R 765_D1_SRT-A | Breaker | AC | 117.08 % | 3039.0 | B | 3557.92 | 25.83 | |
| GD2 | AEP | 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer | AEP_P4_#709_05HANG R 765_D2_SRT-A | Breaker | AC | 115.5 % | 3039.0 | B | 3509.91 | 25.9 | |
| GD2 | AEP | 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer | AEP_P1-2_#709_546_SRT-A | Single | AC | 105.58 % | 3039.0 | B | 3208.68 | 4.22 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P4_#6189_05HANG R 765_D1_SRT-A | Breaker | AC | 125.58 % | 2826.0 | B | 3548.99 | 25.83 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P4_#709_05HANG R 765_D2_SRT-A | Breaker | AC | 123.82 % | 2826.0 | B | 3499.07 | 25.9 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P1-2_#709_546_SRT-A | Single | AC | 113.16 % | 2826.0 | B | 3197.84 | 4.22 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P4_#1760_05JEFRSO 765_A_SRT-A | Breaker | AC | 106.84 % | 2826.0 | B | 3019.17 | 18.05 | |
| GD2 | AEP/AP | 05KAMMER-01KAMMER 765.0/500.0 kV Ckt 1 transformer | AP_P1-2_MP-500-007A_SRT-A | Single | AC | 133.22 % | 3792.0 | B | 5051.83 | 4.12 | |
| GD2 | AEP/AP | 05KAMMER-01KAMMER 765.0/500.0 kV Ckt 1 transformer | AP_P1-2_MP-500-008A_SRT-SL | Single | AC | 125.57 % | 3792.0 | B | 4761.71 | 3.98 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 111.91 % | 2246.0 | B | 2513.45 | 2.55 | |
| GD2 | AEP | 05MALIS-05VASSEL 765.0 kV Ckt 1 line | AP_P1-3_MP-765-501T_SRT-A | Single | AC | 127.9 % | 4142.0 | B | 5297.56 | 4.65 | |
| GD2 | AEP | 05MALIS-05VASSEL 765.0 kV Ckt 1 line | AEP_P1-2_#706_SRT-A | Single | AC | 108.0 % | 4142.0 | B | 4473.55 | 4.65 | |
| GD2 | AEP | 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | AP_P1-3_MP-765-501T_SRT-A | Single | AC | 126.31 % | 4571.0 | B | 5773.71 | 4.6 | |
| GD2 | AEP | 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | AEP_P1-3_#8072_05MARYSV 765_2_SRT-A | Single | AC | 111.01 % | 4571.0 | B | 5074.41 | 3.68 | |
| GD2 | AEP | 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | Base Case | Single | AC | 110.62 % | 4047.0 | A | 4476.89 | 3.67 | |
| GD2 | AEP | 05MARYSVL_RM-05MALIS 765.0 kV Ckt 1 line | AP_P1-3_MP-765-501T_SRT-A | Single | AC | 126.34 % | 4571.0 | B | 5774.92 | 4.6 | |
| GD2 | AEP | 05MARYSVL_RM-05MALIS 765.0 kV Ckt 1 line | AEP_P1-3_#8072_05MARYSV 765_2_SRT-A | Single | AC | 111.24 % | 4571.0 | B | 5084.88 | 3.68 | |
| GD2 | AEP | 05MARYSVL_RM-05MALIS 765.0 kV Ckt 1 line | Base Case | Single | AC | 110.76 % | 4047.0 | A | 4482.29 | 3.67 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | Base Case | Single | AC | 120.76 % | 4047.0 | A | 4887.22 | 5.72 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 119.32 % | 5523.0 | B | 6590.12 | 30.67 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#8980_05KAMMER 765_QQ2_SRT-A | Breaker | AC | 117.27 % | 5523.0 | B | 6477.04 | 33.73 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P1-2_#17217_SRT-A | Single | AC | 116.4 % | 5523.0 | B | 6428.58 | 5.49 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#17219_05GUERNSEY 765_A_SRT-A | Breaker | AC | 112.72 % | 5523.0 | B | 6225.55 | 34.08 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 111.96 % | 5523.0 | B | 6183.32 | 23.9 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | Base Case | Single | AC | 109.18 % | 4558.0 | A | 4976.63 | 3.89 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 108.41 % | 5523.0 | B | 5987.66 | 28.8 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P2-2_#7222_05MALIS 765_1_SRT-A | Bus | AC | 107.46 % | 5523.0 | B | 5935.05 | 28.85 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 106.76 % | 5523.0 | B | 5896.19 | 4.69 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P7-1_#10944___SRT-A | Tower | AC | 105.86 % | 5523.0 | B | 5846.6 | 25.44 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P7-1_#10856___SRT-A | Tower | AC | 101.88 % | 5523.0 | B | 5626.94 | 25.75 | |
| GD2 | AEP | 05OLIVE-05COOK 345.0 kV Ckt 1 line | AEP_P4_#8817_05DUMONT 345_G2_SRT-A | Breaker | AC | 110.17 % | 1409.0 | B | 1552.23 | 14.21 | |
| GD2 | AEP | 05OLIVE-05COOK 345.0 kV Ckt 1 line | AEP_P2-2_#15388_05ELDERBERRY 345_1_SRT-A | Bus | AC | 110.16 % | 1409.0 | B | 1552.19 | 14.21 | |
| GD2 | AEP | 05OLIVE-05COOK 345.0 kV Ckt 1 line | AEP_P4_#14455_05DUMONT 345_G_SRT-A | Breaker | AC | 109.74 % | 1409.0 | B | 1546.27 | 14.18 | |
| GD2 | AEP | 05OLIVE-05COOK 345.0 kV Ckt 1 line | AEP_P7-1_#11000___SRT-A | Tower | AC | 109.74 % | 1409.0 | B | 1546.26 | 14.18 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 122.25 % | 1868.0 | B | 2283.58 | 2.58 | |
| GD2 | AEP | 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | AEP_P1-2_#7442_200545_SRT-A | Single | AC | 103.01 % | 3097.0 | B | 3190.2 | 3.95 | |
| GD2 | AEP | 05SORENS-05SORENSN_RM 765.0 kV Ckt Z1 line | AEP_P1-2_#709_546_SRT-A | Single | AC | 101.53 % | 5523.0 | B | 5607.44 | 6.86 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 123.9 % | 2317.0 | B | 2870.85 | 13.96 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 121.45 % | 2317.0 | B | 2813.9 | 14.01 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 121.4 % | 2317.0 | B | 2812.93 | 13.86 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#9456_06DEARB1 345_DC_SRT-A | Breaker | AC | 121.23 % | 2317.0 | B | 2808.9 | 14.8 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P2-2_#9456_06DEARB1 345_1_SRT-A | Bus | AC | 121.23 % | 2317.0 | B | 2808.8 | 14.8 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 112.63 % | 2317.0 | B | 2609.67 | 2.28 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | DEOK_P_4519BUFFCLIFTYPIERCEDEAR1OVEC_SRT-A | Tower | AC | 106.66 % | 2317.0 | B | 2471.36 | 13.63 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P7-1_#485___SRT-A | Tower | AC | 106.66 % | 2317.0 | B | 2471.23 | 13.63 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | DEOK_P4_1579_EASTBEND_SRT-A | Breaker | AC | 104.35 % | 2317.0 | B | 2417.88 | 12.39 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 153.59 % | 1540.0 | B | 2365.35 | 14.46 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 141.94 % | 1540.0 | B | 2185.8 | 2.29 | |
| GD2 | AEP/OVEC | 06KYGER-05SPORN 345.0 kV Ckt 1 line | AEP_P1-2_#309_15_SRT-A | Single | AC | 133.27 % | 1540.0 | B | 2052.4 | 2.17 | |
| GD2 | AEP/OVEC | 06PIERCE-05MARQUI 345.0 kV Ckt 1 line | AEP_P4_#6189_05HANG R 765_D1_SRT-A | Breaker | AC | 107.31 % | 1540.0 | B | 1652.5 | 14.0 | |
| GD2 | AEP/OVEC | 06PIERCE-05MARQUI 345.0 kV Ckt 1 line | AEP_P4_#709_05HANG R 765_D2_SRT-A | Breaker | AC | 102.96 % | 1540.0 | B | 1585.6 | 14.11 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 128.82 % | 1868.0 | B | 2406.35 | 2.58 |
Winter Peak Analysis
The New Service Request AG2-163 was evaluated as a 250.0 MW (35.0 MW Capacity) injection in the AEP area.
AG2-163 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 700.0 MW (250.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P1-2: LN 553_SRT-A_SENS | Single | AC | 191.58 % | 1180.0 | B | 2260.65 | 16.35 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 542T553_SRT-W_SENS | Breaker | AC | 189.19 % | 1180.0 | B | 2232.49 | 16.4 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 553T564_SRT-W_SENS | Breaker | AC | 188.15 % | 1180.0 | B | 2220.13 | 16.42 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 183.3 % | 1180.0 | B | 2162.99 | 19.8 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2168-555_SRT-A | Tower | AC | 163.75 % | 1180.0 | B | 1932.27 | 16.54 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2114-535_SRT-A_SENS | Tower | AC | 161.68 % | 1180.0 | B | 1907.79 | 15.98 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P2-2: BREMO B1_SRT-A | Bus | AC | 157.63 % | 1180.0 | B | 1860.08 | 15.85 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P2-2_#10265_05LEESVI 138_1_SRT-A | Bus | AC | 157.29 % | 1180.0 | B | 1856.06 | 15.95 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | Base Case | Single | AC | 152.98 % | 1180.0 | A | 1805.12 | 15.88 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 120.49 % | 1737.0 | B | 2092.95 | 0.91 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 118.4 % | 1737.0 | B | 2056.53 | 0.92 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 116.41 % | 1737.0 | B | 2022.06 | 0.92 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 115.97 % | 1737.0 | B | 2014.34 | 0.88 | |
| GD2 | AEP | 05DUMONT-05DUMONT_RS 765.0 kV Ckt Z1 line | AEP_P4_#7334_05JEFRSO 765_A2_SRT-A | Breaker | AC | 108.18 % | 5133.0 | B | 5552.88 | 2.2 | |
| GD2 | AEP | 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer | AEP_P4_#6189_05HANG R 765_D1_SRT-A | Breaker | AC | 103.35 % | 3276.0 | B | 3385.78 | 1.47 | |
| GD2 | AEP | 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer | AEP_P1-2_#709_546_SRT-A | Single | AC | 101.76 % | 3276.0 | B | 3333.77 | 1.48 | |
| GD2 | AEP | 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer | AEP_P4_#709_05HANG R 765_D2_SRT-A | Breaker | AC | 101.76 % | 3276.0 | B | 3333.74 | 1.48 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P4_#6189_05HANG R 765_D1_SRT-A | Breaker | AC | 111.9 % | 2991.0 | B | 3346.96 | 1.47 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P1-2_#709_546_SRT-A | Single | AC | 110.0 % | 2991.0 | B | 3290.17 | 1.48 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P4_#709_05HANG R 765_D2_SRT-A | Breaker | AC | 110.0 % | 2991.0 | B | 3290.12 | 1.48 | |
| GD2 | AEP/OVEC | 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | AEP_P4_#1760_05JEFRSO 765_A_SRT-A | Breaker | AC | 105.8 % | 2991.0 | B | 3164.42 | 1.02 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P4_#7334_05JEFRSO 765_A2_SRT-A | Breaker | AC | 113.19 % | 4961.0 | B | 5615.13 | 2.7 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P4_#6189_05HANG R 765_D1_SRT-A | Breaker | AC | 103.69 % | 4961.0 | B | 5144.06 | 2.42 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P4_#1760_05JEFRSO 765_A_SRT-A | Breaker | AC | 103.1 % | 4961.0 | B | 5114.58 | 2.55 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P1-2_#709_546_SRT-A | Single | AC | 102.1 % | 4961.0 | B | 5065.25 | 2.43 | |
| GD2 | AEP | 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line | AEP_P4_#709_05HANG R 765_D2_SRT-A | Breaker | AC | 102.1 % | 4961.0 | B | 5065.17 | 2.43 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 103.66 % | 2219.0 | B | 2300.12 | 0.91 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 101.06 % | 2219.0 | B | 2242.58 | 0.92 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 100.53 % | 2219.0 | B | 2230.82 | 0.92 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 100.04 % | 2219.0 | B | 2219.82 | 0.88 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 108.89 % | 2317.0 | B | 2523.04 | 0.79 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 107.9 % | 2317.0 | B | 2499.98 | 0.8 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 107.01 % | 2317.0 | B | 2479.49 | 0.8 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 107.01 % | 2317.0 | B | 2479.4 | 0.79 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P2-2_#9456_06DEARB1 345_1_SRT-A | Bus | AC | 106.64 % | 2317.0 | B | 2470.96 | 0.84 | |
| GD2 | AEP/DEO&K | 05TANNER-08M.FORT 345.0 kV Ckt 1 line | AEP_P4_#9456_06DEARB1 345_DC_SRT-A | Breaker | AC | 106.64 % | 2317.0 | B | 2470.93 | 0.84 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 106.03 % | 2219.0 | B | 2352.88 | 0.91 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 103.21 % | 2219.0 | B | 2290.26 | 0.92 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 102.89 % | 2219.0 | B | 2283.06 | 0.92 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 102.36 % | 2219.0 | B | 2271.47 | 0.88 |
Light Load Analysis
The New Service Request AG2-163 was evaluated as a 250.0 MW injection
AG2-163 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 700.0 MW (250.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 100.99 % | 1180.0 | B | 1191.7 | 22.06 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 100.99 % | 1180.0 | B | 1191.7 | 22.06 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 100.98 % | 1180.0 | B | 1191.6 | 22.06 | |
| GD2 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P1-2_#672_1713_SRT-A-1 | Single | AC | 107.94 % | 1374.0 | B | 1483.12 | 71.82 | |
| GD2 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | EXT_P12:345:AMIL-DEI:KANSAS:SUGARCREEK:1_SRT-L | Single | AC | 107.0 % | 1374.0 | B | 1470.21 | 28.69 | |
| GD2 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P7-1_#11014___SRT-A-1 | Tower | AC | 104.95 % | 1374.0 | B | 1442.04 | 72.73 | |
| GD2 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P4_#8648_05JEFRSO 765_B_SRT-A | Breaker | AC | 104.63 % | 1374.0 | B | 1437.55 | 31.74 | |
| GD2 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P4_#4700_05DEQUIN 345_B2_SRT-A | Breaker | AC | 103.67 % | 1374.0 | B | 1424.38 | 71.82 | |
| GD2 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P7-1_#11042___SRT-A | Tower | AC | 100.59 % | 1374.0 | B | 1382.09 | 47.41 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests AG2-014, AG2-126, AG2-163, AG2-343, AG2-345, AG2-491, AG2-492 and AH1-482 in PJM Transition Cycle 2, Cluster 37 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 37 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 37 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.
Cluster 37 projects were dispatched for stability analysis according to the following scenarios:
a) Scenario 1: AG2-126 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.
b) Scenario 2: AG2-126 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.
c) Scenario 3: AG2-126 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.
d) Scenario 4: AG2-126 dispatched to full capacity with PV and BESS MW injection maxed out.
This report describes a dynamic simulation analysis of TC2 Cluster 37 for dispatch Scenario 3 as part of the overall system impact study.
The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 37 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.
Transition Cycle 2 Cluster 37 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:
a) Steady-state operation (Category P0);
b) Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);
c) Single-phase bus faults with normal clearing time (Category P2);
d) Single-phase faults with stuck breaker (Category P4);
e) Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).
High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 cluster 37 projects.
There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV Nearby Queue Projects transmission system.
Prior outage scenarios will not be considered for this study.
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all the fault contingencies tested on the 2028 peak load case:
a) Cluster 37 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 37 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip because of that fault.
In several contingencies, it was observed that multiple units excluding Cluster 37 projects trip due to unrealistic high terminal voltages during the fault and post-fault. Upon further analysis and observing the similar issues in the bench case with Cluster 37 projects offline, we were able to resolve the tripping instances by g-netting the following units in MISO area:
• 17XRD2 (J968),
• 17XRD(J1069),
• 17HOOSIER_WF,
• 17INXR(J913),
• 17INXRD_J838,
• 17CVY(J1067).
It may be required to coordinate with MISO to obtain an updated dynamic model for the facility—preferably a user-defined PSS®E model—for validation in TC2 Phase 3 studies.
Under some P1, P4, and P7 contingencies, it was observed that AF2-078 units trip as a result of the high voltage spikes following fault clearance and no further stability issues were observed. It is known that voltage spikes are a modeling limitation of WECC generic renewable models . Consequently, the pickup timer of corresponding relay instances (i.e., 9578464 and 9578484) has been increased to 0.0333 seconds.
Fictitious frequency response at AF1-204 generator bus tripped the queue project due to the action of instantaneous under-frequency relay under some P1 and P7 contingencies. Therefore, the relay pickup times for frequency relay instance was set to 20 seconds to avoid fictitious frequency tripping of the unit.
The IPCMD and IQCMD states in the REGCA1 models of AG2-014 showed erratic behavior for some contingencies in which AG2-014 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AG2-126 showed erratic behavior for some contingencies in which AG2-126 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AG2-163 showed erratic behavior for some contingencies in which AG2-163 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AG2-343 showed erratic behavior for some contingencies in which AG2-343 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AG2-345 showed erratic behavior for some contingencies in which AG2-345 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AG2-491 showed erratic behavior for some contingencies in which AG2-491 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AG2-492 showed erratic behavior for some contingencies in which AG2-492 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 models of AH1-482 showed erratic behavior for some contingencies in which AH1-482 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
No mitigations were found to be required.
Table 1: Transition Cycle 2 Cluster 37 Projects |
|
|
|
|
Project | Fuel Type | Transmission Owner | MFO (MW) | Point of Interconnection |
AG2-014 | Battery | AEP | 50 | Meadow Lake substation 345 kV |
AG2-126 | Solar/Battery | AEP | 150 | Eugene substation 345 kV |
AG2-163 | Solar | AEP | 250 | Dequine – Eugene 345 kV |
AG2-343 | Battery | AEP | 100 | Dequine – Eugene 345 kV |
AG2-345 | Battery | AEP | 50 | Dequine – Eugene 345 kV |
AG2-491 | Solar | AEP | 100 | Meadow Lake substation 345kV |
AG2-492 | Battery | AEP | 50 | Meadow Lake substation 345kV |
AH1-482 | Battery | AEP | 78 | Olive – Reynolds CKT #2 345kV |
Reactive Power Analysis
Analysis Complete - No Issues
The reactive power capability of AG2-163 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Not Required
A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-018 | Powerton-Goodings Grove | In Service |
| AA1-038 | Lexington-Low Moor 230kV | Under Construction |
| AB1-006 | Meadow Lake 345kV | In Service |
| AB1-027 | Old Church 34.5 KV | In Service |
| AB1-150 | Grassy Falls 138kV | In Service |
| AB2-026 | Powhatan 34.5kV | In Service |
| AB2-029 | Remington 34.5kV | In Service |
| AB2-045 | Buckingham 34.5kV | In Service |
| AB2-067 | Kammer-Vassell 765kV | In Service |
| AB2-070 | Mt. Pulaski-Brokaw | In Service |
| AB2-134 | Hopewell-Surry 230kV | In Service |
| AB2-157 | Prince George's County 12kV | In Service |
| AB2-158 | Louisa-South Anna 230kV | In Service |
| AB2-170 | East Lima-Marysville 345kV | In Service |
| AB2-190 | Hopewell-Surry 230kV | In Service |
| AC1-001 | Delano 138kV | In Service |
| AC1-027 | Pendleton 34.5kV | In Service |
| AC1-033 | Kewanee 138 kV | In Service |
| AC1-042 | Altavista-Mt. Airy 69kV | In Service |
| AC1-044 | Kammer-Vassell 765kV | In Service |
| AC1-053 | Lanesville-Brokaw | In Service |
| AC1-068 | Atlanta 69kV I | In Service |
| AC1-069 | Atlanta 69kV II | In Service |
| AC1-074 | Jacksonville-Renaker 138kV I | In Service |
| AC1-075 | Perth-Hickory Grove 115kV | In Service |
| AC1-076 | Locust Grove-Paytes 115kV | In Service |
| AC1-078 | Beatty-London 138kV | In Service |
| AC1-082 | Ravenswood-Hemlock 69kV | Partially in Service - Under Construction |
| AC1-085 | Stuart-Clinton 345kV | In Service |
| AC1-089 | Hillsboro-Wildcat 138kV | In Service |
| AC1-101 | Johns Creek-Excel 138kV I | Engineering & Procurement |
| AC1-102 | Johns Creek-Excel 138kV II | Engineering & Procurement |
| AC1-111 | Aurora 138kV | In Service |
| AC1-118 | Westmoreland 34.5kV | In Service |
| AC1-122 | Smith Mountain-Candler's Mountain 138kV | In Service |
| AC1-141 | Cook-East Elkhart 345kV | In Service |
| AC1-147 | Grassfield 34.5kV | In Service |
| AC1-158 | Spotsylvania 500kV | In Service |
| AC1-161 | Septa 500kV | In Service |
| AC1-164 | Chickahominy 230kV | Partially in Service - Under Construction |
| AC1-165 | Atlanta 69kV III | In Service |
| AC1-166 | Atlanta 69kV IV | In Service |
| AC1-168 | Kewanee-Streator | Suspended |
| AC1-174 | Losantville 345kV | In Service |
| AC1-175 | Losantville 345kV | In Service |
| AC1-188 | Rio-Lick 138kV | Engineering & Procurement |
| AC1-191 | Elmont 115kV | Engineering & Procurement |
| AC1-194 | Elk 138kV | Engineering & Procurement |
| AC1-214 | Crescent Ridge | In Service |
| AC2-012 | Grassfield-Great Bridge 115kV | In Service |
| AC2-029 | Circleville 138kV | Suspended |
| AC2-044 | Maddox Creek 345kV | Suspended |
| AC2-059 | Biers Run-Circleville 138kV | In Service |
| AC2-060 | Buckskin 69kV | In Service |
| AC2-061 | Hillsboro-Clinton 138kV | In Service |
| AC2-067 | Camden-Crystal I 69kV | Engineering & Procurement |
| AC2-068 | Camden-Crystal II 69kV | Engineering & Procurement |
| AC2-075 | Jacksonville-Renaker 138 kV | In Service |
| AC2-088 | S. Bethel-Brown 69kV | In Service |
| AC2-090 | Losantville 345kV | In Service |
| AC2-111 | College Corner 138kV | Engineering & Procurement |
| AC2-120 | Ripley 69kV | In Service |
| AC2-123 | Jacksons Ferry 138kV | In Service |
| AC2-137 | Elko 34.5kV | In Service |
| AC2-138 | Northern Neck 34.5kV | In Service |
| AC2-141 | Septa 500kV | Engineering & Procurement |
| AC2-154 | Davis Creek 138kV | Engineering & Procurement |
| AC2-157 | Sullivan 345 kV | Partially in Service - Under Construction |
| AC2-168 | Clinton 23kV | In Service |
| AC2-176 | Jay 138 kV | In Service |
| AD1-013 | Twombly Road 138kV | Engineering & Procurement |
| AD1-025 | Hopewell-Surry 230 kV | In Service |
| AD1-033 | Fentress-Landstown 230 kV | In Service |
| AD1-041 | Harmony Village-Shackleford 115 kV | In Service |
| AD1-063 | Harmony Village 34.5 kV | In Service |
| AD1-082 | Bakers Pond-Ivor 115kV | In Service |
| AD1-100 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Under Construction |
| AD1-105 | Kings Dominion DP 115 kV | Under Construction |
| AD1-106 | North Waldo-Wild Creek 138 kV | Withdrawn |
| AD1-115 | Mountain Run-Mitchell 115 kV | Withdrawn |
| AD1-128 | Modoc-Delaware 138 kV | In Service |
| AD1-130 | Hardin Switch 345 kV | In Service |
| AD1-136 | South Bethel-Brown 69 kV | In Service |
| AD1-140 | Greene-Clark 138 kV | Engineering & Procurement |
| AD1-144 | Kings Fork 34.5 kV | In Service |
| AD1-155 | Meadow Brook-Strasburg 138 kV | In Service |
| AD2-016 | Biers Run-Circleville 138 kV | In Service |
| AD2-020 | Valley 138 kV | Engineering & Procurement |
| AD2-030 | Wan 34.5 kV | In Service |
| AD2-031 | Martinsville-Wilmington 69 kV | In Service |
| AD2-038 | Powerton-Nevada 345 kV | Under Construction |
| AD2-047 | Davis Creek 138 kV | Suspended |
| AD2-048 | Cynthia-Headquarters 69 kV | Under Construction |
| AD2-058 | St. Barnabas 13 kV | In Service |
| AD2-060 | Davis Creek 138kV | Engineering & Procurement |
| AD2-066 | Mazon-Crescent Ridge 138 kV | Under Construction |
| AD2-067 | Centerburg 138kV | Engineering & Procurement |
| AD2-071 | Strawton-Deer Creek 138 kV | Suspended |
| AD2-073 | Sanders DP 230 kV | In Service |
| AD2-074 | Garner DP-Lancaster 115 kV | Under Construction |
| AD2-079 | Capitol Ave 34.5kV | In Service |
| AD2-086 | Hardin Switch 345 kV | In Service |
| AD2-091 | Hardin Tap 345kV | Suspended |
| AD2-092 | Marysville 345kV | Withdrawn |
| AD2-093 | Marysville 345kV | Partially in Service - Under Construction |
| AD2-096 | Marysville 345kV | Suspended |
| AD2-100 | Kincaid-Pana 345 kV | Suspended |
| AD2-131 | Kincaid-Pana 345kV | Suspended |
| AD2-133 | Eagle Valley 115kV | In Service |
| AD2-134 | Shady Oaks | Partially in Service - Under Construction |
| AD2-163 | Broadview-Tangy 138 kV | In Service |
| AD2-172 | Lena 138kV | In Service |
| AD2-180 | Elk Garden-Parr Run 138kV | In Service |
| AE1-040 | Greenfield 69 kV | In Service |
| AE1-074 | Winterpock 34.5 kV | Under Construction |
| AE1-075 | Powhatan 34.5 kV | In Service |
| AE1-079 | Maysville-Sharon 69 kV | Under Construction |
| AE1-091 | West Newton-Lynn 138 kV | Suspended |
| AE1-092 | Blue Jacket-Kirby 138 kV | Engineering & Procurement |
| AE1-100 | Axton 138 kV | In Service |
| AE1-102 | Maddox Creek 345 kV | Suspended |
| AE1-108 | Bremo-Scottsville 138 kV | Under Construction |
| AE1-113 | Mole Creek 345 kV | Under Construction |
| AE1-114 | Maryland-Lancaster 138 kV | Engineering & Procurement |
| AE1-143 | Marion County 161 kV | Under Construction |
| AE1-155 | Garner-Northern Neck 115 kV | In Service |
| AE1-162 | Smithfield 34.5 kV | In Service |
| AE1-163 | Powerton-Nevada 345 kV | Under Construction |
| AE1-166 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE1-170 | Kenzie Creek-Colby 138 kV | Suspended |
| AE1-172 | Loretto-Wilton Center | Withdrawn |
| AE1-175 | Light Foot 34.5 kV | In Service |
| AE1-183 | Maysville-McDowell 69 kV | Under Construction |
| AE1-190 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-191 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-205 | McLean 345 kV | Engineering & Procurement |
| AE1-207 | Mississinewa-Gaston 138 kV | Suspended |
| AE1-208 | Delaware-Van Buren 138 kV | Suspended |
| AE1-209 | Desoto 345 kV | Suspended |
| AE1-210 | Desoto 345 kV | Suspended |
| AE1-237 | Andover (Maysville) 69kV I | Under Construction |
| AE1-245 | Haviland 138 kV | Partially in Service - Under Construction |
| AE2-027 | Harrowgate-Locks 115kV | Suspended |
| AE2-029 | Grottoes-Merck 115kV | Under Construction |
| AE2-035 | Lena 138 kV | In Service |
| AE2-045 | Olive-Reynolds 345 kV | Engineering & Procurement |
| AE2-071 | Patton Rd-Summer Shade 69 kV | In Service |
| AE2-072 | East Leipsic-Richland 138 kV | In Service |
| AE2-074 | Potter 46 kV | Under Construction |
| AE2-089 | Pennville-Adams 138 kV | Suspended |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-113 | Farmers Valley-Ridgeway 115 kV | Under Construction |
| AE2-114 | Midland 23 kV I | In Service |
| AE2-115 | Midland 23 kV II | In Service |
| AE2-125 | Stahlstown-Ligonier 25 kV | In Service |
| AE2-126 | Dubois-Curwensville 34.5 kV | In Service |
| AE2-129 | Philipsburg-Clarence 34.5 kV | In Service |
| AE2-131 | Philipsburg-Karthaus 34.5 | Under Construction |
| AE2-139 | East Towanda-Grover 230 kV | Engineering & Procurement |
| AE2-140 | Axton-Danville 138 kV | Suspended |
| AE2-148 | Beatty-Greene 345 kV | In Service |
| AE2-152 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE2-166 | Stockton 138 kV | Suspended |
| AE2-169 | Delaware-Van Buren 138 kV | Suspended |
| AE2-172 | Mississinewa-Gaston 138 kV | Suspended |
| AE2-206 | East Sidney-Quincy 138 kV | In Service |
| AE2-212 | Harrowgate 34 kV | Engineering & Procurement |
| AE2-214 | Cole 345 kV | Under Construction |
| AE2-216 | Hardin Switch 345 kV | Suspended |
| AE2-217 | East Springfield-London 138 kV | Engineering & Procurement |
| AE2-219 | Bluff Point-Randolph 138 kV | Suspended |
| AE2-220 | Losantville 345 kV | Engineering & Procurement |
| AE2-221 | Clinton-Stuart 345 kV | Under Construction |
| AE2-223 | McLean 345 kV | Engineering & Procurement |
| AE2-224 | Bear Rock-Johnstown 230 kV | In Service |
| AE2-226 | Millville-Old Chapel 138 kV | Engineering & Procurement |
| AE2-230 | Bartonsville-Meadow Brook 138 kV | In Service |
| AE2-234 | Liberty Center-Buckeye Tap 69 kV | Engineering & Procurement |
| AE2-236 | Columbia-Northeast 138 kV | Suspended |
| AE2-254 | Garrard County-Tommy-Gooch 69 kV | In Service |
| AE2-255 | Molecreek 345 kV | Under Construction |
| AE2-261 | Kincaid-Pana 345 kV | Engineering & Procurement |
| AE2-267 | Woodsdale 345 kV | Engineering & Procurement |
| AE2-276 | Sullivan 345kV | Engineering & Procurement |
| AE2-281 | Powerton-Nevada 345 kV | Under Construction |
| AE2-285 | Maysville 69 kV | Under Construction |
| AE2-297 | Madison-Tanners Creek 138 kV | In Service |
| AE2-305 | Givens-Mechanicsburg 138 kV | Withdrawn |
| AE2-308 | Three Forks-Dale 138 kV | Engineering & Procurement |
| AE2-309 | Carlos Junction-Lonaconing 34.5 kV | In Service |
| AE2-315 | Yankee Tap 69 kV | In Service |
| AE2-318 | Ford-Cedarville 138 kV | Suspended |
| AE2-323 | Twin Branch-Guardian 138 kV | Partially in Service - Under Construction |
| AE2-325 | Valley 138 kV | Withdrawn |
| AE2-326 | Jacksons Ferry 138 kV | Engineering & Procurement |
| AE2-339 | Avon 138 kV | Under Construction |
| AE2-341 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AE2-342 | Woodstock 69 kV | Suspended |
| AE2-343 | Andover (Maysville) 69 kV II | Under Construction |
| AF1-006 | Fairview East 34.5 kV | In Service |
| AF1-021 | Bethelboro-Connellsville #1 25 kV | In Service |
| AF1-022 | Lake Lynn-Uniontown 25 kV | In Service |
| AF1-030 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-038 | Sewellton Jct-Webbs Crossroads 69 kV | Under Construction |
| AF1-039 | Listonburg-Highpoint 24.9 kV | In Service |
| AF1-042 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AF1-045 | Cedarville-Ford 138 kV | Suspended |
| AF1-049 | Berry Hill 138 kV | Under Construction |
| AF1-050 | Summer Shade - Green County 161 kV | Engineering & Procurement |
| AF1-053 | Givens-Mechanicsburg 138 kV | Withdrawn |
| AF1-054 | Givens-Mechanicsburg 138 kV | Withdrawn |
| AF1-062 | Jug Street 138 kV | Engineering & Procurement |
| AF1-071 | College Corner 138 kV | Engineering & Procurement |
| AF1-078 | East Sidney-Quincy 138 kV | In Service |
| AF1-083 | Green County-Saloma 161 kV | Engineering & Procurement |
| AF1-086 | Madera-Westover South 115 kV | Partially in Service - Under Construction |
| AF1-090 | Kincaid-Pana | Engineering & Procurement |
| AF1-091 | Varner - Sowers 138 kV | Engineering & Procurement |
| AF1-092 | Huntington Jct. 138 kV | Withdrawn |
| AF1-093 | Henderson-Stoneboro 69 kV | Under Construction |
| AF1-094 | Union City-Cambridge Springs 34.5 kV | Engineering & Procurement |
| AF1-098 | Four Mile Jct-Corry East 115 kV | Suspended |
| AF1-118 | Sorenson-Desoto 345 kV | Withdrawn |
| AF1-119 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF1-122 | Cardington-Liberty 69 kV | Suspended |
| AF1-130 | Inez 138 kV | Suspended |
| AF1-134 | Philipsburg-Madera 34.5 kV | Under Construction |
| AF1-140 | Claysburg 23 kV | Engineering & Procurement |
| AF1-147 | Poland Rd-Runway DP 230kV | Partially in Service - Under Construction |
| AF1-158 | Edison-Gravel Pit 138 kV | In Service |
| AF1-161 | Valley 138 kV | Engineering & Procurement |
| AF1-162 | Inez 138 kV | Engineering & Procurement |
| AF1-176 | Corey 138 kV | Engineering & Procurement |
| AF1-202 | Keystone-Desoto 345 kV | Under Construction |
| AF1-203 | Patton Rd-Summer Shade 69 kV | In Service |
| AF1-204 | Eugene 345 kV | Engineering & Procurement |
| AF1-207 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF1-215 | Olive-Reynolds 345 kV | In Service |
| AF1-223 | Keystone-Desoto 345 kV | Under Construction |
| AF1-227 | Marysville – Gunn Road 345 kV | In Service |
| AF1-228 | Beatty-Greene 345 kV | Under Construction |
| AF1-233 | Flemingsburg – Spurlock 138kV | Engineering & Procurement |
| AF1-249 | Nickel 12.47 kV | In Service |
| AF1-268 | Desoto-Jay 138 kV | Engineering & Procurement |
| AF1-272 | Lucerne 115 kV | Engineering & Procurement |
| AF1-275 | Cole 345 kV | Under Construction |
| AF1-282 | Stuart-Clinton 345 kV | Engineering & Procurement |
| AF1-283 | Stuart-Clinton 345 kV | Engineering & Procurement |
| AF1-285 | Gunn Road 345 kV | Under Construction |
| AF1-291 | Tyler 34.5 kV | Engineering & Procurement |
| AF1-291A | Bartonsville-Meadow Brook 138 kV | In Service |
| AF1-296 | Garden Plain 138 kV | Engineering & Procurement |
| AF1-302 | Brookville-Squab Hollow 138 kV | Under Construction |
| AF1-322 | Meadow Lake 345 kV | Under Construction |
| AF1-331 | Twombley Road | Engineering & Procurement |
| AF2-014 | Maddox Creek 345 kV | Under Construction |
| AF2-018 | Inez 138 kV | Engineering & Procurement |
| AF2-032 | Kincaid 345 kV | Withdrawn |
| AF2-039 | Shawville-Clearfield 34.5 kV | Under Construction |
| AF2-041 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-048 | Rio-Lick 138 kV | Engineering & Procurement |
| AF2-054 | Wan 34.5 kV | In Service |
| AF2-068 | Jay 138 kV | Engineering & Procurement |
| AF2-075 | Bartonsville-Meadow Brook 138 kV III | In Service |
| AF2-077 | White Marsh 34.5 kV | In Service |
| AF2-078 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF2-083 | Kenzie Creek-Stone Lake 69 kV | Under Construction |
| AF2-088 | Shawville-Clearfield 34.5 kV II | Under Construction |
| AF2-095 | Davis Creek 138 kV | Engineering & Procurement |
| AF2-111 | North Clark-Spurlock 345 kV | Engineering & Procurement |
| AF2-122 | Kirk 138 kV | Partially in Service - Under Construction |
| AF2-130 | Cobalt Corners 34.5 kV | In Service |
| AF2-132 | Reynolds-Olive #1 345 kV | Under Construction |
| AF2-133 | Reynolds-Olive #2 345 kV | Under Construction |
| AF2-134 | Olive-Reynolds #2 345 kV | In Service |
| AF2-142 | Nevada 345 kV | Engineering & Procurement |
| AF2-143 | Powerton-Nevada 345 kV | Engineering & Procurement |
| AF2-144 | Powhatan 34.5 kV | In Service |
| AF2-162 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-177 | Sorenson-DeSoto #2 345 kV | Engineering & Procurement |
| AF2-199 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-200 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-205 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AF2-224 | Allen 345 kV | Engineering & Procurement |
| AF2-225 | McLean 345 kV | Engineering & Procurement |
| AF2-252 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-291 | Sporn South-Leon 138 kV | Engineering & Procurement |
| AF2-298 | Crown-New Lebanon 69 kV | Engineering & Procurement |
| AF2-350 | Kensington 138 kV | Engineering & Procurement |
| AF2-352 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-356 | Albright-Mt. Zion 138 kV | Partially in Service - Under Construction |
| AF2-359 | Olive-University Park 345 kV | Engineering & Procurement |
| AF2-366 | Crego Rd 138 kV | Engineering & Procurement |
| AF2-371 | Harrison-Good Hope 138 kV | Engineering & Procurement |
| AF2-382 | Hurley 69 kV | Engineering & Procurement |
| AF2-388 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-396 | Stinger 138 kV | Engineering & Procurement |
| AF2-407 | Fall Creek 345 kV | Withdrawn |
| AF2-408 | Fall Creek 138 kV | Engineering & Procurement |
| AF2-440 | Hillsboro-Middleboro 138 kV | Under Construction |
| AG1-017 | Jay 138 kV | In Service |
| AG1-024 | Centerburg 138 kV | Engineering & Procurement |
| AG1-034 | Centerburg 138 kV | Engineering & Procurement |
| AG1-040 | Morgan Street-Mount Hope 34.5 kV | Engineering & Procurement |
| AG1-047 | Jay 138 kV | Engineering & Procurement |
| AG1-054 | Potter-Harlan 69 kV | Engineering & Procurement |
| AG1-066 | Bonnyman 69 kV | Engineering & Procurement |
| AG1-100 | Venango-Saegertown 34.5 kV | Engineering & Procurement |
| AG1-107 | Hillsboro-Middleboro 138 kV | Under Construction |
| AG1-109 | Valley 138 kV | Engineering & Procurement |
| AG1-118 | Sugar Grove-Waterman 138kV | Engineering & Procurement |
| AG1-125 | Marysville-Flatlick 765 kV | Engineering & Procurement |
| AG1-126 | Marysville-Flatlick 765 kV | Engineering & Procurement |
| AG1-127 | Crego Rd 138 kV | Engineering & Procurement |
| AG1-145 | Lightfoot 34.5 kV | In Service |
| AG1-198 | Union City 34.5 kV | In Service |
| AG1-226 | Dequine-Eugene 345 kV | Engineering & Procurement |
| AG1-232 | Magley 138 kV | Engineering & Procurement |
| AG1-237 | Dequine-Eugene 345 kV | Engineering & Procurement |
| AG1-281 | Claysburg-HCR Tap 46 kV | Engineering & Procurement |
| AG1-282 | Dunnsville 34.5 kV | Withdrawn |
| AG1-302 | Olive-Reynolds #1 345 kV | Under Construction |
| AG1-320 | Hodgenville-Stephensburg 69 kV | Engineering & Procurement |
| AG1-324 | Jay-Desoto 138 kV | Engineering & Procurement |
| AG1-341 | Summer Shade 161 kV | Engineering & Procurement |
| AG1-349 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AG1-351 | Harrison-Good Hope 138 kV | Engineering & Procurement |
| AG1-354 | Summershade-Green County 161 kV | Engineering & Procurement |
| AG1-363 | Black Oak-Hatfield 500 kV | Engineering & Procurement |
| AG1-365 | Allen 345 kV | Engineering & Procurement |
| AG1-366 | Allen 345 kV | Engineering & Procurement |
| AG1-368 | Tillman 138 kV | Engineering & Procurement |
| AG1-369 | Logtown 138 kV | Engineering & Procurement |
| AG1-374 | Blue Mound 345 kV | Engineering & Procurement |
| AG1-386 | Smith-Francis Junction 25 kV | In Service |
| AG1-410 | Maddox Creek-RP Mone 345 kV | Engineering & Procurement |
| AG1-414 | Mississinewa 138 kV | Engineering & Procurement |
| AG1-433 | Keystone-DeSoto 345 kV | Engineering & Procurement |
| AG1-436 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-447 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-460 | Kincaid-Pana 345 kV | Engineering & Procurement |
| AG1-462 | Cordova 345 kV | Engineering & Procurement |
| AG1-469 | Gordonsville 34.5 kV | Withdrawn |
| AG1-471 | Up Church-Wayne County 69 kV | Engineering & Procurement |
| AG1-478 | Wilmington 34.5 kV | Engineering & Procurement |
| AG1-508 | Point Lookout 69 kV | Withdrawn |
| AG1-555 | Dequine 345 kV | Engineering & Procurement |
| AG1-558 | Buckner 34.5 kV | Withdrawn |
| AG1-559 | Caroline Pines 22 kV | Withdrawn |
| AG2-014 | Meadow Lake 345 kV | Active |
| AG2-029 | Forest G. Hipple-Dunton Lake 345 kV | Active |
| AG2-057 | Cardington-Liberty 69 kV II | Active |
| AG2-061 | Dana 345 kV | Active |
| AG2-072 | Rockport 765 kV | Active |
| AG2-073 | Crooksville 69 kV | Active |
| AG2-081 | Avon - Renaker 138 kV | Active |
| AG2-104 | Marysville-Flatlick 765 kV | Active |
| AG2-106 | Marysville-Flatlick 765 kV | Active |
| AG2-107 | Marysville-Flatlick 765 kV | Active |
| AG2-114 | Dresden-Pontiac Midpoint 345 kV | Active |
| AG2-119 | Galion-Roberts South 138 kV II | Active |
| AG2-125 | Camden-Crystal 69 kV | Active |
| AG2-126 | Eugene 345 kV | Active |
| AG2-184 | Harbert Metering 138 kV | Active |
| AG2-191 | Mississinewa 138 kV | Active |
| AG2-192 | Mississinewa 138 kV | Active |
| AG2-216 | East Sidney-Quincy 138 kV | Active |
| AG2-230 | Dumont 345 kV | Active |
| AG2-245 | Olive - Reynolds #1 345 kV | Active |
| AG2-298 | Sulphur Creek-Loretto 69 kV | Active |
| AG2-332 | East Elkhart - Elcona Tap 138 kV | Active |
| AG2-343 | Eugene - Dequine 345 kV | Active |
| AG2-345 | Eugene - Dequine 345 kV | Active |
| AG2-360 | Broadford 138 kV | Active |
| AG2-363 | Powerton 345 kV | Active |
| AG2-364 | Powerton 345 kV | Active |
| AG2-401 | Losantville 345 kV | Active |
| AG2-405 | Continental 69 kV | Active |
| AG2-406 | Payne 69 kV | Active |
| AG2-424 | Summersville - Magnolia 69 kV | Active |
| AG2-453 | Lasalle - Plano 345 kV | Active |
| AG2-487 | Madison - Tanners Creek 138 kV | Active |
| AG2-491 | Meadow Lake 345 kV | Active |
| AG2-492 | Meadow Lake 345 kV | Active |
| AG2-516 | Pecatonica 138kV | Active |
| AG2-519 | Royerton - Desoto 138 kV | Active |
| AG2-524 | LaSalle Station - Mazon 138 kV | Active |
| AG2-548 | Corwin - Elk 138 kV | Active |
| AG2-550 | Bluff Point - Randolph 138 kV | Active |
| AG2-551 | Bluff Point - Randolph 138 kV | Active |
| AG2-562 | Elderberry 345 kV | Active |
| AG2-568 | Stink Run - Sundial 138 kV | Active |
| AG2-585 | Kensignton 138kV | Active |
| AG2-637 | Randolph - Hodgin 138 kV | Active |
| AG2-660 | Nelson-Electric Junction 345 kV | Active |
| AG2-665 | Corwin - Elk 138 kV | Active |
| AG2-675 | Cordova 345 kV | Active |
| AH1-004 | Avon - Renaker 138 kV | Active |
| AH1-044 | Nelson - Electric Junction 345 kV | Active |
| AH1-055 | Kyger Creek - Don Marquis 345 kV | Active |
| AH1-059 | Sharp Road 69 kV | Active |
| AH1-060 | Cardington-Liberty 69 kV III | Active |
| AH1-072 | Red Onion - VC5 69 kV | Active |
| AH1-073 | Red Onion - VC5 69 kV | Active |
| AH1-098 | Wolf Glade-West Carroll 138 kV | Active |
| AH1-133 | Saltville - Tazewell 138 kV | Active |
| AH1-150 | Nelson-Electric Junction 345 kV | Active |
| AH1-151 | Nelson-Electric Junction 345 kV | Active |
| AH1-153 | Dumont 345 kV | Active |
| AH1-188 | Pigeon Creek 138 kV | Active |
| AH1-196 | Silver Lake - Cherry Valley 345 kV | Active |
| AH1-227 | Flemming - Fremont 69 kV | Active |
| AH1-239 | Upchurch - Zula 69 kV | Active |
| AH1-272 | Argenta - Twin Branch 345 kV | Active |
| AH1-292 | Sullivan 345 kV | Active |
| AH1-302 | Olive - Reynolds 345 kV | Active |
| AH1-304 | Delaware-Van Buren 138 kV | Active |
| AH1-305 | Olive - Reynolds 345 kV | Active |
| AH1-306 | Mississinewa-Gaston 138 kV | Active |
| AH1-327 | Hardin Switch 345 kV | Active |
| AH1-328 | Blue Jacket - Kirby 138 kV | Active |
| AH1-338 | New Sub S2354 138kV | Active |
| AH1-341 | ESS-H445 3B 138kv | Active |
| AH1-348 | Pound 34.5 kV | Active |
| AH1-392 | Gravel Pit-Kankakee 138 kV | Active |
| AH1-482 | Olive - Reynolds #2 345 kV | Active |
| AH1-535 | Nagel - Cane River 230 kV | Active |
| AH1-537 | Pierce - Kyger Creek 345 kV | Active |
| AH1-541 | Chestnut 345 kV | Active |
| AH1-542 | Crissinger-Delaware Business Park 138kV | Active |
| AH1-543 | Mulberry - Tazewell 345 kV | Active |
| AH1-567 | University Park 138 kV | Active |
| AH1-570 | Millersburg 69 kV | Active |
| AH1-571 | Millersburg 69 kV | Active |
| AH1-617 | Harbert Metering 138 kV | Active |
| AH1-661 | Cannelville 12.47 kV | Active |
| AH1-664 | Goddard-Plumville 138 kV | Active |
| AH1-665 | Goddard-Plumsville 138 kV II | Active |
| AH1-666 | Flemingsburg - Spurlock 138 kV | Active |
| AH1-686 | Hanging Rock 765 kV | Active |
| AH1-698 | Braidwood 345 kV | Active |
| AH1-702 | Byron 345 kV | Active |
| AH1-714 | Lasalle 345 kV | Active |
| AH1-718 | Nelson 345 kV | Active |
| AH1-721 | Laurel-Cooper 161 kV | Active |
| U2-030 | Four Mile Ridge Wind 138kV | In Service |
| U2-073 | Frostburg 138kV II | In Service |
| V1-011 | Haviland 138kV | In Service |
| V3-007 | Desoto-Tanners Creek #1 345kV | In Service |
| V4-073 | Yankee 12.5kV | In Service |
| W2-048 | Brokaw-Lanesville | In Service |
| W4-005 | Blue Mound-Latham | In Service |
| X1-042 | Watervliet | In Service |
| X2-022 | Brokaw-Lanesville | In Service |
| X2-052 | Dumont-Olive 345kV | In Service |
| X3-005 | Wildwood 12kV | In Service |
| Y1-033 | Penn Mar-Rock Wood 115kV | In Service |
| Y3-023 | Country Side 12kV | In Service |
| Y3-024 | Bluff Point 12kV | In Service |
| Z2-087 | Pontiac MidPoint-Brokaw 345kV | In Service |
| Z2-115 | Deer Creek 12.47kV | In Service |
| Z2-116 | Twin Branch 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.
System Reinforcement
- Type
- Load Flow
- TO
- DEI
- RTEP ID / TO ID
- (Pending) / DEI_TC1_16079
- Title
- Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor.
- Description
- Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. Projected in-service date is 6/1/2030.
- Total Cost ($USD)
- $23,213,515
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 Months
Contingent Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (Any) |
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
| Impacted Facility | Transmission Owner | Reinforcement | Cost | Cost Allocated to AG2-163 | Scenarios |
|---|---|---|---|---|---|
| NIPS | Reynolds-Greentown 765 kV NIPSCO: No mitigation required. Rating Of NIPS- Owned Line Portion: SN/SE=9015 MVA/9015 MVA. AEP: No mitigation required. 8348 MVA SN/SE | $0 | $0 |
|
| NIPS | Wvrich - Rochester TP 69 kV DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @ 100/120C the ratings assume that NIPSCO terminal upgrades would not limit our T-Line rating. $1.5M NIPSCO: DEI mitigations acceptable to remove constraint. $0 | $1,500,000 | $30,941 |
|
| DEI | Cayuga-Nucor 345 kV MTEP Proj ID 50718: Rebuild with 954 ZTACSR @ 200C from Cayuga Gen Yard to Nucor. Upgrade terminal equipment accordingly. | $0 | $0 |
|
System Reinforcements
Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| AEP | b4068.1 | b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570 | Contingent | $0 | N/A |
| AEP | b3919.1 | Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard | Contingent | $0 | N/A |
| AEP | b4000.252 | Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation | Contingent | $0 | N/A |
| AEP | b4000.251 | Replace the wave trap and upgrade the relay at Cloverdale 765kV substation | Contingent | $0 | N/A |
| AEP | s3588.1 | Construct new Larrison Drive 345 kV substation | Contingent | $0 | N/A |
| AEP | s3588.2 | Construct new New Prairie 345 kV substation | Contingent | $0 | N/A |
| Grand Total: | $0 | ||||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b4000.11
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.11
- Title
- Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)
- Description
- Expand Black Oak Substation to accommodate the connection of the 502 Jct-Woodside 500 kV line and loop the 502 Jct-Woodside 500 kV line into the Black Oak substation by constructing ~0.85 miles of new 500 kV line into and out of Black Oak 500 kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.1
- Title
- Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.2
- Title
- Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.3
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.3
- Title
- Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.4
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.4
- Title
- Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.5
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.5
- Title
- Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.6
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.6
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.7
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.7
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.8
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.8
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.9
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.9
- Title
- Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029)
- Description
- Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard. Loop in the Doubs-Goose Creek 500 kV line, the Doubs-Aspen 500 kV line, and the Woodside-Goose Creek 500 kV line. Install two 765/500 kV transformer at Rocky Point substation. 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.10
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.10
- Title
- Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 01BELMNT-05BELMON 500.0/765.0 kV Ckt 5 transformer | (Any) | No new ratings for this Flowgate. | |
| 01 502 J-01KAMMER 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01BELMNT-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01HARRSN-01FLINTRUN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. | |
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4068.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4068.1 / AEP-TC2-18693
- Title
- b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570
- Description
- b4068.1 through b4068.49: Affected Transmission Owners: AEP / Dayton / ATSI The objective of this project is to construct multiple transmission lines to address Ohio area violations. The total distance covered by the lines is approximately 359.54 miles. The first transmission line ranges from the existing Greentown Substation in Howard County, Indiana to the new Teddy Substation in Clark County, Ohio, the line then branches north towards the existing Marysville Substation in Union County, Ohio, and east to the existing Beatty Substation in Franklin County, Ohio, and then extends to the existing Cole Substation in Franklin County, Ohio. The second transmission line extends from the existing Adkins Substation in Pickaway County, Ohio, to the new West Millersport Substation in Fairfield County, Ohio, then continues to the existing Conesville Substation in Coshocton County, Ohio before finally extending to the existing Guernsey Substation in Guernsey County, Ohio. There is a total of five transmission lines that extend between unnamed substations (Hayden - Cole 345 kV, Hyatt - Maliszewski 345 kV [double circuit], Roberts - Kenny 138 kV, Wilson - 5th Avenue 138 kV, West Millersport-Kirk 345 kV). This project will traverse 4 counties (Howard, Grant, Blackford, Jay) in Indiana, and 13 counties (Darke, Shelby, Champaign, Clark, Madison, Franklin, Delaware, Pickaway, Fairfield, Licking, Muskingum, Coshocton, Guernsey) in Ohio. This proposal has a total of 38 components, including 16 substation upgrade components, two greenfield substation components, eight greenfield transmission line components covering approximately 336.2 miles, and 12 transmission line upgrade components covering approximately 23.34 miles. b4068.28/b4068.49 is dependent on b3919.1 Baseline completion.
- Cost Information
- Time Estimate
- Jun 01 2030
ContingentTopology Changing Note 1: Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05COOK-05OLIVE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05TANNER-08M.FORT 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05E LIMA-05MADDOX 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05SPORN-06KYGER 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05HANG R-05HANGRCK_RJ 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05MALIS-05VASSEL 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05MALIS-05MARYSVL_RM 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05MARYSV-05MARYSVL_RS 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05MARQUI-06PIERCE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05DUMONT-05DUMONT_RS 765.0 kV Ckt Z1 line | (Any) |
| ||||||||||
| 05SORENS-05SORENSN_RM 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3919.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3919.1
- Title
- Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard
- Description
- Reconfigure Maliszewski 765 kV station from 2 breakers to a 6 breaker ring bus. Install a new 765/345 kV transformer. Establish new 345 kV breaker yard with 3 string breaker and a half to include a line exit to Hyatt and a line exit to Corridor. Loop the existing Hyatt - West Millersport 345 kV line into the new established 345 kV yard at the Maliszewski station.
- Cost Information
- Time Estimate
- Jun 01 2029
ContingentTopology Changing Note 1: Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05COOK-05OLIVE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05TANNER-08M.FORT 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer | (Any) | No new ratings for this Flowgate. | |
| 05E LIMA-05MADDOX 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05SPORN-06KYGER 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05JEFRSO-06CLIFTY 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05HANG R-05HANGRCK_RJ 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| 05MALIS-05VASSEL 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MALIS-05MARYSVL_RM 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MARYSV-05MARYSVL_RS 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| 05MARQUI-06PIERCE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05DUMONT-05DUMONT_RS 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| 05SORENS-05SORENSN_RM 765.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.356
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.355
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.355
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.13
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.13
- Title
- Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat.
- Description
- Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat. Develop two 765 kV line terminal positions and three 500 kV line terminal positions. Install one 765/500 kV transformer, with provisions for a future second transformer.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.14
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.14
- Title
- Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.
- Description
- Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.15
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.15
- Title
- Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.
- Description
- Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.16
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.16
- Title
- Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.
- Description
- Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.28
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.28
- Title
- Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.
- Description
- Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Thornburg (formerly Kraken) to accommodate the new 500kV line from North Anna to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.346
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.346
- Title
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Description
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.342
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.342
- Title
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Description
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Cost Information
- Time Estimate
- Jul 13 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.341
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.341
- Title
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Description
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Cost Information
- Time Estimate
- Jul 13 2029
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: n9769.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9769.0 / AEP-TC2-19070
- Title
- 05CLOVRD_RJA 765.0 kV to 05CLOVRD 765.0 kV ckt Z1 - Upgrade/replace CBs
- Description
- Upgrade/replace Cloverdale 765 kV, 4000 A CBs "CC" and "CC2" to 5000 A
- Total Cost ($USD)
- $25,000,000
- Discounted Total Cost ($USD)
- $25,000,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 54 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05CLOVRD-05CLOVRD_RJA 765.0 kV Ckt Z1 line | (Any) |
|
System Reinforcement: b4000.252
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.252
- Title
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4000.251
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.251
- Title
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: s3588.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- s3588.1 / (Pending)
- Title
- Construct new Larrison Drive 345 kV substation
- Description
- Construct a new station in a breaker and a half configuration consisting of sixteen (16) 345kV 5000A 63kA breakers, six (6) 345kV meters, and station fiber cable. Construct six (6) 345kV bus ties from AEP’s Larrison Drive 345kV station to the customer station. Cut in the Elderberry-Dumont and Dumont-Olive Bypass 345 kV line into the new station.
- Cost Information
- Time Estimate
- Dec 15 2026
ContingentTopology Changing Note 1: Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05COOK-05OLIVE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05DUMONT-05ELDERBERRY 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: s3588.2
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- s3588.2 / (Pending)
- Title
- Construct new New Prairie 345 kV substation
- Description
- New station to be constructed in a breaker and a half configuration consisting of sixteen (16) 345kV 5000A 63kA breakers, six (6) 345kV meters, and station fiber cable. Construct six (6) bus ties from AEP’s New Prairie 345kV station to the customer station. Cut in the Elderberry-Dumont and Dumont-Olive Bypass 345 kV line into the new station.
- Cost Information
- Time Estimate
- Dec 15 2026
ContingentTopology Changing Note 1: Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 may need this upgrade in-service to be deliverable to the PJM system. If AG2-163 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05COOK-05OLIVE 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05DUMONT-05ELDERBERRY 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP_TC1_13727
- Title
- AEP SE rating is 1868 MVA
- Description
- AEP SE rating is 1868 MVA
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- 0 to 1 Months
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9763.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9763.0 / AEP-TC2-19060
- Title
- 05J.FERR 765.0 kV to 05CLOVRD_RJA 765.0 kV ckt 1 - Replace Wavetraps
- Description
- Replace wave trap on 765 kV Cloverdale line. Replace/upgrade CB's B and B2 with 5000A CBs.
- Total Cost ($USD)
- $3,300,000
- Discounted Total Cost ($USD)
- $3,300,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 54 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9767.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9767.0 / AEP-TC2-19068
- Title
- 05KAMMER_RG 765.0 kV to 05KAMMER 765.0 kV ckt Z1 - Replace Wavetraps
- Description
- Replace the existing 3000A wave trap at Kammer 765 station towards Guernsey with a 5000A wave trap. Additionally, replace the 3000A circuit breaker QQ1 with a 5000A circuit breaker. Disconnect switches and a relays will be upgraded as well.
- Total Cost ($USD)
- $4,500,000
- Discounted Total Cost ($USD)
- $4,500,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 54 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05KAMMER-05KAMMER_RG 765.0 kV Ckt Z1 line | (Any) |
|
System Reinforcement: b3851.2
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3851.2
- Title
- Rebuild R.P. Mone – Maddox Creek 345kV line (9.4 miles).
- Description
- Rebuild R.P. Mone – Maddox Creek 345kV line (9.4 miles).
- Cost Information
- Time Estimate
- Jun 01 2027
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MADDOX-AG1-410 TP 345.0 kV Ckt 1 line | (Any) |
| |||||||||||||
| 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9786.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9786.0 / AEP-TC2-19161
- Title
- 05MARYSVL_RM 765.0 kV to 05MALIS 765.0 kV ckt 1 - Replace Wave Traps
- Description
- Replace wave tap at Maliszewski towards Marysville
- Total Cost ($USD)
- $3,000,000
- Discounted Total Cost ($USD)
- $3,000,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 24 to 36 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MALIS-05MARYSVL_RM 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9766.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9766.0 / AEP-TC2_19067
- Title
- 05MARYSV 765.0 kV to 05MARYSVL_RM 765.0 kV ckt Z1 - Replace Wavetrap
- Description
- Replace 4000A Wavetrap towards Maliszewski with 5000A equivalent
- Total Cost ($USD)
- $1,100,000
- Discounted Total Cost ($USD)
- $1,100,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 36 to 48 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MARYSV-05MARYSVL_RM 765.0 kV Ckt Z1 line | (Any) |
|
System Reinforcement: b3878.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3878.1
- Title
- Upgrade 765 kV circuit breakers 'B' and 'B2' to 5000A 50kA breakers at Marysville Station
- Description
- Upgrade 765 kV circuit breakers 'B' and 'B2' to 5000A 50kA breakers at Marysville Station. In addition, the project will upgrade the existing wavetrap towards Sorenson.
- Cost Information
- Time Estimate
- Nov 12 2027
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MARYSV-05MARYSVL_RS 765.0 kV Ckt Z1 line | (Any) |
|
System Reinforcement: b3851.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3851.1 / B3851.1
- Title
- Rebuild Allen-RP Mone 345kV
- Description
- Rebuild Allen –R.P. Mone 345kV line (18.6 miles).
- Cost Information
- Time Estimate
- Jun 01 2027
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05RPMONE-05ALLEN 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9759.0
- Type
- Load Flow
- TO
- OVEC
- RTEP ID / TO ID
- n9759.0 / OVEC-TC2-19030
- Title
- 06KYGER 345.0 kV to 05SPORN 345.0 kV ckt 1 - Replace Equipment
- Description
- Sag study Sporn - Kyger Creek line and replace section #25 OVEC element conductor 12.51 Miles At Sporn replace the following equipment: 2 - 2000 KCM AAC, 91-Str., AA1S1, AA1S2, AAS1, AAS2, KYGER CREEK #1 - PH A, KYGER CREEK #1 - PH B At Kyger Creek Replace the following equipment: 2156.0 KCM ACSR (84/19), 3000A Switch, CB-BB
- Total Cost ($USD)
- $38,180,000
- Discounted Total Cost ($USD)
- $38,180,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 60 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05SPORN-06KYGER 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9753.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9753.0 / AEP-TC2-18751
- Title
- 05KYGER 345kV to 05SPORN 345kV ckt 1 - Replace Equipment and Sag Study
- Description
- Sag study Sporn - Kyger Creek line and at Kyger Creek Replace the following equipment: 2156.0 KCM ACSR (84/19), 3000A Switch, CB-BB, 2870 MCM ACSR (Bus), GCB AA, Wave Trap, Line Relay/CT, Meters, Switch 104, and Switch 10
- Total Cost ($USD)
- $5,052,000
- Discounted Total Cost ($USD)
- $5,052,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 60 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-163 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-163 could receive cost allocation. Although AG2-163 may not presently have cost responsibility for this upgrade, AG2-163 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05SPORN-06KYGER 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3788.2
- Type
- Load Flow
- TO
- OVEC
- RTEP ID / TO ID
- b3788.2 / B3788.2
- Title
- Replace limiting station elements at Kyger Creek
- Description
- Upgrade existing 345 kV terminal equipment at Kyger Creek on the Kyger Creek-Sporn 345 kV line. Projected in-service date 6/1/2028 Replace OVEC-owned breaker AA risers, bus work, and breaker AA disconnect switches at OVEC-owned Kyger Creek station.
- Cost Information
- Time Estimate
- Jun 01 2028
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 05SPORN-06KYGER 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3788.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3788.1 / B3788.1
- Title
- Replace limiting station elements at Kyger Creek
- Description
- Upgrade existing 345 kV terminal equipment at Kyger Creek on the Kyger Creek-Sporn 345 kV line. Projected in-service date 6/1/2028 Replace AEP-owned station takeoff riser and breaker BB risers at OVEC-owned Kyger Creek station.
- Cost Information
- Time Estimate
- Apr 03 2028
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 05SPORN-06KYGER 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b2831.2
- Type
- Load Flow
- TO
- DEOK
- RTEP ID / TO ID
- b2831.2
- Title
- Rebuild the Tanner Creek – Miami Fort 345kV line (DEOK portion), Actual In-service date 5/14/2021
- Description
- Rebuild the Tanner Creek – Miami Fort 345kV line (DEOK portion) Actual In-service date 5/14/2021
- Cost Information
- Time Estimate
- May 14 2021
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it is already in-service.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05TANNER-08M.FORT 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: s2019
- Type
- Load Flow
- TO
- DEOK
- RTEP ID / TO ID
- s2019 / AEP Project Resolves Overload
- Title
- AEP Project s2019 Resolves DEOK Overload
- Description
- Install two (2) new 345 kV breakers and move the existing M2 breaker into the new N string at Tanners Creek station. Terminate the Dearborn line and the transformer into the new N string. Install a new 345 kV breaker “T” to complete the T string. Projected in-service date 5/23/2023.
- Cost Information
- Time Estimate
- May 26 2021
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned supplemental project. AG2-163 is not contingent on this supplemental project as it is already in-service.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05TANNER-08M.FORT 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b2968
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b2968
- Title
- Upgrade existing 345kV terminal equipment at Tanners Creek station on Tanners Creek - Miami Fort 345kV line, Actual In-Service Date 12/22/2020
- Description
- Upgrade existing 345kV terminal equipment at Tanners Creek station on Tanners Creek - Miami Fort 345kV line, Actual In-Service Date 12/22/2020
- Cost Information
- Time Estimate
- Dec 22 2020
Not Contingent Note: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it is already in-service.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05TANNER-08M.FORT 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4053.3
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.3
- Title
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW.
- Description
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. The HVDC link, approximately 185 miles in length, will be fully routed underground between the two new proposed converter stations, one at Heritage and one at Mosby.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.4
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.4
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.5
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.5
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.11
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.11
- Title
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Description
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.12
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.12
- Title
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement.
- Description
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement. Upgrade existing terminal equipment to 500 kV, 5000A 63 kAIC standards including breaker (XT590), disconnect switches (59078, X74), leads and bus work.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AG2-163 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-163 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |