AG2-447 Phase II System Impact Study Report
v1.00 released 2026-06-03 18:51
Cedar Creek 138 kV VII
12.0 MW Capacity / 20.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Freepoint Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Delmarva Power and Light Company.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Delmarva Power and Light Company zone — New Castle County, Delaware. This project is an increase to the developer’s AC1-091/AC1-092/AC1-093/AC1-094/AC2-184/AC2-185 project(s), which will share the same Point of Interconnection. The AG2-447 project is a 20.0 MW uprate (12.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 134.25 MW with 55.3 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
A Physical Interconnection Facilities Study is not required for this project.
Point of Interconnection
AG2-447 will interconnect with the Delmarva Power and Light Company transmission system at the Cedar Creek 138 kV Substation.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AG2-447 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG2-447 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 | $0 |
| Other Scope | $0 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | $0 |
| Network Upgrades | $0 | $0 | $0 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $15,000,000 | $15,000,000 | $15,000,000 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $15,000,000 | $15,000,000 | $15,000,000 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AG2-447
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AG2-447
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
No TO Interconnection Facilities or Physical Network Upgrades are required for this project.
Transmission Owner Analysis
No impacts identified by Transmission Owner.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. DPL interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AG2-447 was evaluated as a 20.0 MW (12.0 MW Capacity) injection in the DPL area.
AG2-447 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 134.25 MW (20.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | DP&L | BRIDGEVL-TAYLOR 69.0 kV Ckt 1 line | DPL_P4_2_DP51_SRT-A | Breaker | AC | 108.94 % | 64.0 | B | 69.72 | 0.65 | |
| GD2 | DP&L/PECO | CLAY_230-LINWOOD84 230.0 kV Ckt 1 line | PECO_P1-2_220-85_SRT-A/* $ DELCO $ PECO_P1-2_220-85 $ L | Single | AC | 108.56 % | 800.0 | B | 868.48 | 1.47 | |
| GD2 | AE/PECO | DELCOTAP-MCKLTON 230.0 kV Ckt 1 line | PECO_P4_CHICH045_SRT-A/* $ DELCO $ PECO_P4_CHICH045 $ STBK | Breaker | AC | 125.54 % | 637.0 | B | 799.67 | 1.0 | |
| GD2 | AE/PECO | DELCOTAP-MCKLTON 230.0 kV Ckt 1 line | PECO_P2-2_CHI230B1_SRT-A/* $ DELCO $ PECO_P2-2_CHI230B1 $ B | Bus | AC | 125.54 % | 637.0 | B | 799.66 | 1.0 | |
| GD2 | AE/PECO | DELCOTAP-MCKLTON 230.0 kV Ckt 1 line | PECO_P4_CHICH195_SRT-A/* $ DELCO $ PECO_P4_CHICH195 $ STBK | Breaker | AC | 125.54 % | 637.0 | B | 799.66 | 1.0 | |
| GD2 | AE/PECO | DELCOTAP-MCKLTON 230.0 kV Ckt 1 line | PECO_P4_CHICH435_SRT-A/* $ DELCO $ PECO_P4_CHICH435 $ STBK | Breaker | AC | 125.49 % | 637.0 | B | 799.38 | 1.0 | |
| GD2 | DP&L | EDGEMR 5-CLAY_230 230.0 kV Ckt 1 line | PECO_P1-2_220-85_SRT-A/* $ DELCO $ PECO_P1-2_220-85 $ L | Single | AC | 104.67 % | 800.0 | B | 837.36 | 1.29 | |
| GD2 | DP&L/PECO | EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line | DPL_P4_2_DPEM231_SRT-A | Breaker | AC | 105.87 % | 809.0 | B | 856.45 | 1.66 | |
| GD2 | DP&L/PECO | EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line | PECO_P1-2_220-84_SRT-A/* $ DELCO $ PECO_P1-2_220-84 $ L | Single | AC | 103.6 % | 809.0 | B | 838.11 | 1.41 | |
| GD2 | DP&L/PECO | EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line | PECO_P4_LINWO115_SRT-A/* $ DELCO $ PECO_P4_LINWO115 $ STBK | Breaker | AC | 103.25 % | 809.0 | B | 835.32 | 1.95 | |
| GD2 | DP&L/PECO | EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line | DPL_P1_2_CKT 23015_SRT-A | Single | AC | 102.59 % | 809.0 | B | 829.93 | 1.29 | |
| GD2 | PECO | RICHMOND35-WANEETA3 230.0 kV Ckt 1 line | PECO_P4_CHICH045_SRT-A/* $ DELCO $ PECO_P4_CHICH045 $ STBK | Breaker | AC | 102.49 % | 1180.0 | B | 1209.36 | 1.71 | |
| GD2 | PECO | RICHMOND35-WANEETA3 230.0 kV Ckt 1 line | PECO_P2-2_CHI230B1_SRT-A/* $ DELCO $ PECO_P2-2_CHI230B1 $ B | Bus | AC | 102.48 % | 1180.0 | B | 1209.3 | 1.71 | |
| GD2 | PECO | RICHMOND35-WANEETA3 230.0 kV Ckt 1 line | PECO_P4_CHICH195_SRT-A/* $ DELCO $ PECO_P4_CHICH195 $ STBK | Breaker | AC | 102.48 % | 1180.0 | B | 1209.29 | 1.71 | |
| GD2 | PECO | RICHMOND35-WANEETA3 230.0 kV Ckt 1 line | PECO_P4_CHICH435_SRT-A/* $ DELCO $ PECO_P4_CHICH435 $ STBK | Breaker | AC | 102.48 % | 1180.0 | B | 1209.25 | 1.71 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AP/PJM | CHAN-01DOUBS 500.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 105.04 % | 4150.0 | B | 4359.2 | 4.68 | |
| GD2 | AP/PJM | CHAN-01DOUBS 500.0 kV Ckt 1 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 105.01 % | 4150.0 | B | 4357.8 | 4.68 | |
| GD2 | AP/PJM | CHAN-01DOUBS 500.0 kV Ckt 1 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 104.99 % | 4150.0 | B | 4357.18 | 4.68 | |
| GD2 | AP/PJM | CHAN-01DOUBS 500.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 104.65 % | 4150.0 | B | 4342.89 | 4.7 | |
| GD2 | PECO | CHIREACT_39-CHICHST2 230.0 kV Ckt 1 line | PECO_CBO_CHIC435_SRT-A/* $ DELCO $ PECO_CBO_CHIC435 $ K | Bus | AC | 101.34 % | 1622.0 | B | 1643.73 | 2.17 | |
| GD2 | PECO | CHIREACT_43-CHICHST1 230.0 kV Ckt 1 line | PECO_P4_POST475_SRT-A/* $ DELCO $ PECO_P4_POST475 $ STBK | Breaker | AC | 101.18 % | 1770.0 | B | 1790.82 | 2.18 | |
| GD2 | PECO | CHIREACT_43-CHICHST1 230.0 kV Ckt 1 line | PECO_P4_POST785_SRT-A/* $ DELCO $ PECO_P4_POST785 $ STBK | Breaker | AC | 101.17 % | 1770.0 | B | 1790.79 | 2.18 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019E_SRT-SL | Breaker | AC | 127.16 % | 3098.0 | B | 3939.34 | 3.49 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | AP_P1-2_PE-500-3835T_SRT-A | Single | AC | 116.99 % | 3098.0 | B | 3624.44 | 2.43 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019B_SRT-A | Breaker | AC | 111.62 % | 3098.0 | B | 3458.01 | 2.84 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | PECO_P4_PEACH025_SRT-A/* $ CHESCO $ PECO_P4_PEACH025 $ STBK | Breaker | AC | 103.85 % | 3098.0 | B | 3217.41 | 3.31 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | BG_P7_CNSTN_NWEST2_SRT-A | Tower | AC | 102.61 % | 3098.0 | B | 3178.71 | 2.63 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | PECO_P4_PEACH035_SRT-A/* $ CHESCO $ PECO_P4_PEACH035 $ STBK | Breaker | AC | 101.69 % | 3098.0 | B | 3150.34 | 3.3 | |
| GD2 | BGE/PECO | COOPER-GRACETON 230.0 kV Ckt 1 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 109.26 % | 578.0 | B | 631.55 | 1.24 | |
| GD2 | BGE/PECO | COOPER-GRACETON 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 109.24 % | 578.0 | B | 631.4 | 1.24 | |
| GD2 | BGE/PECO | COOPER-GRACETON 230.0 kV Ckt 1 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 109.22 % | 578.0 | B | 631.31 | 1.24 | |
| GD2 | BGE/PECO | COOPER-GRACETON 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 108.49 % | 578.0 | B | 627.1 | 1.22 | |
| GD2 | BGE/PECO | COOPER-GRACETON 230.0 kV Ckt 1 line | PECO_P4_PEACH245_SRT-A/* $ CHESCO $ PECO_P4_PEACH245 $ STBK | Breaker | AC | 102.86 % | 578.0 | B | 594.52 | 1.25 | |
| GD2 | DP&L/PECO | EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line | DPL_P4_2_DPEM237_SRT-A | Breaker | AC | 103.9 % | 809.0 | B | 840.56 | 1.88 | |
| GD2 | PECO | LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | PECO_P4_POST475_SRT-A/* $ DELCO $ PECO_P4_POST475 $ STBK | Breaker | AC | 101.18 % | 1770.0 | B | 1790.82 | 2.18 | |
| GD2 | PECO | LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | PECO_P4_POST785_SRT-A/* $ DELCO $ PECO_P4_POST785 $ STBK | Breaker | AC | 101.17 % | 1770.0 | B | 1790.79 | 2.18 | |
| GD2 | PECO | LINWOOD97-POST97 230.0 kV Ckt 1 line | PECO_CBO_CHIC435_SRT-A/* $ DELCO $ PECO_CBO_CHIC435 $ K | Bus | AC | 101.44 % | 1770.0 | B | 1795.44 | 2.17 | |
| GD2 | PECO | NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 117.62 % | 578.0 | B | 679.82 | 1.24 | |
| GD2 | PECO | NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 117.49 % | 578.0 | B | 679.08 | 1.24 | |
| GD2 | PECO | NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 117.45 % | 578.0 | B | 678.84 | 1.24 | |
| GD2 | PECO | NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 116.79 % | 578.0 | B | 675.02 | 1.22 | |
| GD2 | PECO | NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | PECO_P4_PEACH245_SRT-A/* $ CHESCO $ PECO_P4_PEACH245 $ STBK | Breaker | AC | 111.0 % | 578.0 | B | 641.56 | 1.25 | |
| GD2 | PECO | NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | PECO_P1-2_5012_SRT-A | Single | AC | 104.49 % | 578.0 | B | 603.92 | 0.86 | |
| GD2 | PECO | NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 117.62 % | 578.0 | B | 679.82 | 1.24 | |
| GD2 | PECO | NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 117.49 % | 578.0 | B | 679.08 | 1.24 | |
| GD2 | PECO | NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 117.45 % | 578.0 | B | 678.84 | 1.24 | |
| GD2 | PECO | NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 116.79 % | 578.0 | B | 675.02 | 1.22 | |
| GD2 | PECO | NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | PECO_P4_PEACH245_SRT-A/* $ CHESCO $ PECO_P4_PEACH245 $ STBK | Breaker | AC | 111.0 % | 578.0 | B | 641.56 | 1.25 | |
| GD2 | PECO | NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | PECO_P1-2_5012_SRT-A | Single | AC | 104.49 % | 578.0 | B | 603.92 | 0.86 | |
| GD2 | PJM | PCHBTM1N-CHAN 500.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 133.22 % | 3486.0 | B | 4644.1 | 6.76 | |
| GD2 | PJM | PCHBTM1N-CHAN 500.0 kV Ckt 1 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 133.22 % | 3486.0 | B | 4644.06 | 6.76 | |
| GD2 | PJM | PCHBTM1N-CHAN 500.0 kV Ckt 1 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 133.16 % | 3486.0 | B | 4641.99 | 6.76 | |
| GD2 | PJM | PCHBTM1N-CHAN 500.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 133.05 % | 3486.0 | B | 4638.14 | 6.78 | |
| GD2 | PJM | PCHBTM1N-CHAN 500.0 kV Ckt 1 line | PECO_P1-2_5012_SRT-A | Single | AC | 120.33 % | 3486.0 | B | 4194.82 | 4.72 | |
| GD2 | PJM | PCHBTM1N-CHAN 500.0 kV Ckt 1 line | PECO_P4_PEACH245_SRT-A/* $ CHESCO $ PECO_P4_PEACH245 $ STBK | Breaker | AC | 111.17 % | 3486.0 | B | 3875.5 | 6.84 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019E_SRT-SL | Breaker | AC | 150.91 % | 3620.0 | B | 5462.93 | 6.24 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019B_SRT-A | Breaker | AC | 145.49 % | 3620.0 | B | 5266.8 | 5.89 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PECO_P4_PEACH025_SRT-A/* $ CHESCO $ PECO_P4_PEACH025 $ STBK | Breaker | AC | 140.01 % | 3620.0 | B | 5068.35 | 6.69 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | AP_P1-2_PE-500-3835T_SRT-A | Single | AC | 136.68 % | 3620.0 | B | 4947.73 | 4.35 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PECO_P4_PEACH035_SRT-A/* $ CHESCO $ PECO_P4_PEACH035 $ STBK | Breaker | AC | 134.7 % | 3620.0 | B | 4876.15 | 6.65 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PECO_P1-2_5007_SRT-A/* $ CHESCO $ PECO_P1-2_5007 $ L | Single | AC | 126.49 % | 3620.0 | B | 4579.06 | 4.67 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_M_SRT-A | Breaker | AC | 116.54 % | 3620.0 | B | 4218.81 | 3.96 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | Base Case | Single | AC | 113.37 % | 2920.0 | A | 3310.31 | 3.23 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PECO_P2-2_NOTT230B_SRT-A/* $ CHESCO $ PECO_P2-2_NOTT230B $ B | Bus | AC | 107.12 % | 3620.0 | B | 3877.79 | 5.03 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PL_04_P71_001014_SRT-A | Tower | AC | 105.23 % | 3620.0 | B | 3809.42 | 4.69 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PL_05_P71_000906_SRT-A | Tower | AC | 104.19 % | 3620.0 | B | 3771.64 | 4.66 | |
| GD2 | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PL_04_P22_102290_SRT-A | Bus | AC | 103.6 % | 3620.0 | B | 3750.31 | 4.66 | |
| GD2 | PJM | PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 133.98 % | 2860.0 | B | 3831.94 | 7.0 | |
| GD2 | PJM | PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 133.98 % | 2860.0 | B | 3831.93 | 7.0 | |
| GD2 | PJM | PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 133.84 % | 2860.0 | B | 3827.78 | 6.99 | |
| GD2 | PJM | PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 133.82 % | 2860.0 | B | 3827.22 | 7.01 | |
| GD2 | PJM | PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | PECO_P1-2_5012_SRT-A | Single | AC | 121.88 % | 2860.0 | B | 3485.9 | 4.88 | |
| GD2 | PJM | PCHBTM2S-PCHBTM1S 500.0 kV Ckt Z1 line | PECO_P4_PEACH255_SRT-A/* $ CHESCO $ PECO_P4_PEACH255 $ STBK | Breaker | AC | 117.7 % | 2860.0 | B | 3366.11 | 6.59 | |
| GD2 | PECO | PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_C_SRT-A | Breaker | AC | 115.07 % | 578.0 | B | 665.09 | 1.24 | |
| GD2 | PECO | PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | PECO_P4_PEACH235_SRT-A/* $ CHESCO $ PECO_P4_PEACH235 $ STBK | Breaker | AC | 114.97 % | 578.0 | B | 664.51 | 1.24 | |
| GD2 | PECO | PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | BGE_P4_GRACETON_51_SRT-A | Breaker | AC | 114.92 % | 578.0 | B | 664.26 | 1.24 | |
| GD2 | PECO | PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | PJM_500_BG_P4_5_CNSTN_B_SRT-A | Breaker | AC | 114.26 % | 578.0 | B | 660.41 | 1.22 | |
| GD2 | PECO | PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | PECO_P4_PEACH245_SRT-A/* $ CHESCO $ PECO_P4_PEACH245 $ STBK | Breaker | AC | 108.46 % | 578.0 | B | 626.91 | 1.25 | |
| GD2 | PECO | PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | PECO_P1-2_5012_SRT-A | Single | AC | 101.97 % | 578.0 | B | 589.37 | 0.86 | |
| GD2 | PECO | POST39-CHIREACT_39 230.0 kV Ckt 1 line | PECO_CBO_CHIC435_SRT-A/* $ DELCO $ PECO_CBO_CHIC435 $ K | Bus | AC | 101.34 % | 1622.0 | B | 1643.73 | 2.17 |
Winter Peak Analysis
The New Service Request AG2-447 was evaluated as a 20.0 MW (12.0 MW Capacity) injection in the DPL area.
AG2-447 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 134.25 MW (20.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | AP_P1-2_PE-500-3835T_SRT-A | Single | AC | 128.38 % | 3507.0 | B | 4502.35 | 0.2 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019E_SRT-W | Breaker | AC | 128.11 % | 3507.0 | B | 4492.66 | 0.2 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019B_SRT-A | Breaker | AC | 111.87 % | 3507.0 | B | 3923.45 | 0.16 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | PECO_P1-2_5007_SRT-A/* $ CHESCO $ PECO_P1-2_5007 $ L | Single | AC | 108.79 % | 3507.0 | B | 3815.35 | 0.19 | |
| GD2 | PJM | CNASTONE-BRIGHTON 500.0 kV Ckt 1 line | BG_P7_CNSTN_NWEST2_SRT-A | Tower | AC | 101.98 % | 3507.0 | B | 3576.36 | 0.15 |
Light Load Analysis
The New Service Request AG2-447 was evaluated as a 20.0 MW injection
AG2-447 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 134.25 MW (20.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
New Service Requests (projects) in PJM Transition Cycle 2, Cluster 86 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 86 projects.
This analysis is effectively a screening study to determine whether the addition of the cluster 86 projects will meet the dynamics requirements of the NERC, DPL and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 86 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.
Cluster 86 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period. Studied faults included:
- Steady-state operation (20 second run);
- Three-phase faults with normal clearing time;
- Single-phase bus faults with normal clearing time;
- Single-phase faults with stuck breaker;
- Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
No relevant tower faults or single-phase bus faults were identified for this study.
For generator interconnection studies, Category P3 and P6 contingencies will be evaluated on an as-needed basis.
Prior outage scenarios will not be considered for this study.
Stations at which the faults listed above will be applied are:
- Carville 138 kV (AG2-380/AF1-036/AE2-112/AD2-076 POI)
- Wye Mills 138 kV
- Pondtown 138 kV (AB2-032/AB2-153 POI)
- Cedar Creek 138 kV (AG2-447/AC1-091/AC1-092/AC1-093/AC1-094/AC2 184/AC2-185 POI)
- Cedar Creek 230 kV
- Clayton 138 kV (W1-062 POI)
- Farmview 138 kV (AH1-672 POI)
- Milford 138 kV
- South Harrington 138 kV
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2028 peak load case:
- Cluster 86 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
- The system with Cluster 86 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes,
- Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus),
- No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AG2-380, AG2-447, and AH1-672 meet the 0.95 leading and lagging PF requirement.
High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e., fault where spike is observed]). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”
No mitigations were found to be required.
Table 1: TC2 Cluster 86 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
86 | AG2-380 | Storage | DPL | 106.00 | 20.00 | 20.00 | Carville 138 kV IV Substation |
AG2-447 | Solar | DPL | 134.25 | 20.00 | 12.00 | Cedar Creek 138 kV VII Substation | |
AH1-672 | Solar | DPL | 75.00 | 75.00 | 48.90 | Farmview 138 kV Substation |
Reactive Power Analysis
Analysis Complete - No Issues
The reactive power capability of AG2-447 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Not Required
A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA2-184 | Atlantic-Red Bank 34kV | In Service |
| AB1-001 | Absecon 12 kV | In Service |
| AB1-138 | Navy 34.5kV | In Service |
| AB1-139 | Metuchen 26kV | In Service |
| AB1-141 | Church-Wye Mills 138 kV I | In Service |
| AB1-142 | Church-Wye Mills 138 kV II | In Service |
| AB1-176 | Price 25kV II | Engineering & Procurement |
| AB2-032 | Church-Wye Mills 138 kV | In Service |
| AB2-036 | Church - Oil City 138kV | Suspended |
| AB2-037 | Keeney-Steele 230kV | Partially in Service - Under Construction |
| AB2-049 | Gloucester Township 12kV | In Service |
| AB2-057 | Brunswick 26kV | In Service |
| AB2-133 | Chestertown 69kV | Under Construction |
| AB2-135 | Church-Kent 69kV | In Service |
| AB2-136 | Cambridge-West Cambridge 69kV | In Service |
| AB2-153 | Church-Wye Mills 138 kV | In Service |
| AB2-172 | Todd 69kV | In Service |
| AB2-179 | Townsend 138kV | In Service |
| AC1-010 | Gloucester 26kV | Partially in Service - Under Construction |
| AC1-017 | Levittown 13 kV | In Service |
| AC1-030 | Cinnaminson 13kV | In Service |
| AC1-091 | Cedar Creek 138kV I | Suspended |
| AC1-092 | Cedar Creek 138kV II | Suspended |
| AC1-093 | Cedar Creek 138kV III | Suspended |
| AC1-094 | Cedar Creek 138kV IV | Suspended |
| AC1-190 | East New Market 69kV | Suspended |
| AC2-009 | Pennington 13 kV | In Service |
| AC2-023 | Hebron 69kV | Suspended |
| AC2-185 | Cedar Creek 138kV II | Suspended |
| AC2-186 | Harrington 25kV | Under Construction |
| AC2-187 | Harrington 69kV | Under Construction |
| AC2-188 | Harrington 69 kV | Under Construction |
| AD2-027 | Camden Switch 26 kV | In Service |
| AD2-042 | Camden Switch 26 kV II | In Service |
| AD2-065 | Atco 12 kV | In Service |
| AD2-076 | Carville 138 kV | Withdrawn |
| AD2-135 | Williamstown 12kV | Partially in Service - Under Construction |
| AE1-041 | Edison 4kV | In Service |
| AE1-104 | BL England 138 kV | Suspended |
| AE1-142 | Manitou-Pleasant Plains 34.5 kV | In Service |
| AE1-229 | Deepwater-Upper Pittsgrove 138 kV | Suspended |
| AE2-112 | Carville 138 kV II | Withdrawn |
| AF1-007 | Indian River 230 kV I | Suspended |
| AF1-036 | Carville 138 kV III | Withdrawn |
| AF1-262 | Upper Pittsgrove 12 kV | In Service |
| AF1-264 | Runnemede 13 kV | In Service |
| AF2-060 | Wattsville 12 kV | Suspended |
| AF2-247 | Bustleton 13.2 kV | In Service |
| AF2-250 | Edgewood 12 kV III | In Service |
| AF2-254 | Cookstown-New Lisbon 34.5 kV | Withdrawn |
| AF2-325 | Jacktown 12 kV | Engineering & Procurement |
| AF2-378 | Cambridge 12 kV | Engineering & Procurement |
| AF2-379 | Princess Anne 25 kV | Under Construction |
| AG1-130 | Burlington 26 kV | Engineering & Procurement |
| AG1-188 | Manitou-Oyster Creek 34.5 kV | Engineering & Procurement |
| AG1-189 | Oyster Creek-Bamber Lake 34.5 | Engineering & Procurement |
| AG1-223 | Larrabee-Allaire 34.5 kV | Under Construction |
| AG1-254 | Salem-Woodstown 69 kV | Engineering & Procurement |
| AG1-499 | Lambs 12.47 kV | Under Construction |
| AG2-016 | Oyster Creek-Whitings 34.5 kV | Active |
| AG2-297 | Cumberland 230 kV | Active |
| AG2-380 | Carville 138 kV IV | Active |
| AG2-616 | Churchtown - Upper Pittsgrove 138 kV | Active |
| AH1-054 | Upton-Whitings 34.5 kV | Active |
| AH1-057 | Edgewood 12.47 kV | Active |
| AH1-258 | Belford - Keansburg 34.5 kV | Active |
| AH1-260 | New Freedom - Monroe 230 kV | Active |
| AH1-334 | Lakehurst - Whitings 34.5 kV | Active |
| AH1-641 | Churchtown - Upper Pittsgrove 138kV | Active |
| AH1-672 | Farmview 138 kV | Active |
| AH1-701 | Valero 69 kV | Active |
| AH1-710 | Salem 500kV | Active |
| V1-021 | Cape May County 12kV | In Service |
| V2-041 | Clayville 12kV | In Service |
| V2-046 | Pilesgrove Township 12kV | In Service |
| V4-054 | Fairfield Township 12kV | In Service |
| V4-067 | Cates Road Egg Harbor Township 12kV | Deactivated |
| W1-003 | Oak Hall | In Service |
| W1-004 | Oak Hall | In Service |
| W1-005 | Oak Hall | In Service |
| W1-006 | Oak Hall | In Service |
| W1-130 | Vine Road 12kV | In Service |
| W2-030 | Egg Harbor Township | In Service |
| X2-083 | Newark 12kV | In Service |
| X3-008 | Todd 69kV | In Service |
| X3-066 | Church Hill 69kV | In Service |
| Y1-079 | Wye Mills 69kV | In Service |
| Y1-080 | Dorchester 12kV | In Service |
| Y2-105 | Eagle Point 230kV | In Service |
| Y3-058 | Rockawalkin 69kV | In Service |
| Z2-076 | Worcester South 25kV | In Service |
| Z2-077 | Worcester North 25kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| DPL | n9774.0 | Rebuild BRIDGEVL 69.0 kV to TAYLOR 69.0 kV ckt 1 to achieve 70 MVA minimum | Cost Allocated | $15,000,000 | N/A |
| Grand Total: | $15,000,000 | ||||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n9774.0
- Type
- Load Flow
- TO
- DPL
- RTEP ID / TO ID
- n9774.0 / (Pending)
- Title
- Rebuild BRIDGEVL 69.0 kV to TAYLOR 69.0 kV ckt 1 to achieve 70 MVA minimum
- Description
- Rebuild line with new conductor
- Total Cost ($USD)
- $15,000,000
- Discounted Total Cost ($USD)
- $15,000,000
- Allocated Cost ($USD)
- $15,000,000
- Time Estimate
- 36 to 60 Months
Aggregate Contributor
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| BRIDGEVL-TAYLOR 69.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-447 | 0.7 MW | 100.0% | $15,000,000 |
System Reinforcement: b3780.7
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.7
- Title
- Build new Batavia Road substation (Projected ISD 12/31/2028)
- Description
- Build Batavia Road substation. Add 4 x 230kV breaker bays
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.8
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.8
- Title
- Graceton 500 kV substation expansion (Projected ISD 12/31/2028)
- Description
- Add 3x 500 kV breaker bays, 2x 500/230 kV auto transformer, 1x 500 kV caps
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.9
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.9
- Title
- Graceton to Batavia Road 230 kV double circuit pole line (Projected ISD 12/31/2028)
- Description
- Graceton to Batavia Road 230 kV double circuit pole line New rating: 1331 MVA SN/ 1594 MVA SE
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.5
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.5
- Title
- Build Solley Road substation + Statcom (Projected ISD 12/31/2028)
- Description
- Build Solley Road substation + Statcom. New STATCOM rating: 350 MVAR Add 4x 230 kV breakers bays.
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.13
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.13
- Title
- Batavia Road to Riverside 230 kV reconductor
- Description
- Batavia Road to Riverside 230 kV reconductor New rating: 1941 MVA SN / 2181 MVA SE
- Cost Information
- Time Estimate
- Dec 31 2027
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.11
- Type
- Load Flow
- TO
- PEPCO
- RTEP ID / TO ID
- b3780.11
- Title
- Brighton Statcom and Capacitor (Projected ISD 12/31/2028)
- Description
- Brighton Statcom and capacitor New STATCOM rating: 350 MVAR New capacitor rating: 350 MVAR
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.15
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.15
- Title
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub
- Description
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV substation by rebuilding 5012 between new terminal at Peach Bottom South and North Delta on single circuit structures and terminating at North Delta.
- Cost Information
- Time Estimate
- Apr 10 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.17
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.17
- Title
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub (Transource)
- Description
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV substation by rebuilding 5012 between new terminal at Peach Bottom South and North Delta on single circuit structures and terminating at North Delta (Transource Scope).
- Cost Information
- Time Estimate
- May 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.1
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.1
- Title
- Peach Bottom North upgrades – substation work (Projected ISD 12/31/2028)
- Description
- Add 3x 500 kV breakers to form a breaker-and-a-half bay.
- Cost Information
- Time Estimate
- Oct 15 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.14
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.14
- Title
- Reconfigure Cooper transmission feeds by establishing new Cooper-North Delta 230 kV line and rerouting existing transmissions lines by Cooper.
- Description
- None
- Cost Information
- Time Estimate
- Oct 23 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.16
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.16
- Title
- Terminate new Cooper-North Delta 230 kV line (Transource Scope) at North Delta 230 kV
- Description
- None
- Cost Information
- Time Estimate
- Oct 15 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.6
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.6
- Title
- Build Granite substation + Statcom (Projected ISD 12/31/2028)
- Description
- Build Granite substation + Statcom. New STATCOM rating: 350 MVAR. Add 4x 230 kV breaker bays.
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.37
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.37
- Title
- Replace terminal equipment limitations at Conastone 500 kV - on the (existing Peach Bottom-Conastone) or (new Graceton-Conastone) 500 kV line (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.34
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.34
- Title
- Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV and cut into North Delta 500kV (Projected ISD 12/31/2030)
- Description
- Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.35
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.35
- Title
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV (Projected ISD 12/1/2030)
- Description
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
- Cost Information
- Time Estimate
- Apr 10 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.36
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.36
- Title
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV (Projected ISD 12/31/2030)
- Description
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.52
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.52
- Title
- Reconfigure Peach Bottom North and South 500 kV yards (Projected ISD 12/1/2030)
- Description
- Reconfigure Peach Bottom North and South yards to allow for termination of 500 kV lines from Peach Bottom to North Delta. North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line.
- Cost Information
- Time Estimate
- Dec 01 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.45
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.45
- Title
- North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (PECO work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- Jan 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.50
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.50
- Title
- North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (Transource work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- Jan 23 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.46
- Type
- Load Flow
- TO
- PEPCO
- RTEP ID / TO ID
- b3800.46
- Title
- North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (PECO work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- Dec 11 2029
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.48
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.48
- Title
- North Delta termination for the North Delta-High Ridge 500 line (Transource work).
- Description
- None
- Cost Information
- Time Estimate
- Dec 15 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.51
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.51
- Title
- North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (Transource work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- May 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.44
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.44
- Title
- North Delta termination for the North Delta-High Ridge 500 line (PECO work).
- Description
- None
- Cost Information
- Time Estimate
- Dec 15 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.31
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.31
- Title
- Build new North Delta-High Ridge 500 kV line - PECO Portion (Projected ISD 12/1/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 15 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.29
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.29
- Title
- High Ridge termination for the North Delta-High Ridge 500 kV line (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.27
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.27
- Title
- High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) - Waugh Chapel side (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.28
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.28
- Title
- High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) -Brighton side (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.26
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.26
- Title
- Build High Ridge 500 kV substation - Three bay breaker and half configuration (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.32
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.32
- Title
- Build new North Delta-High Ridge 500 kV line - BGE Portion (Projected ISD 12/31/2030)
- Description
- Build new North Delta-High Ridge 500 kV line. (~59 miles)
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.30
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.30
- Title
- High Ridge - Install two 500/230 kV transformers (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.47
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.47
- Title
- Build new Peach Bottom South-North Delta 500 kV line (Projected ISD 12/1/2030)
- Description
- Build new Peach Bottom South-North Delta 500 kV line – cut in to Peach Bottom tie No. 1 and extending line to North Delta (~1.25 miles new ROW).
- Cost Information
- Time Estimate
- Jan 14 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.42
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.42
- Title
- Peach Bottom 500kV North bus upgrade (Projected ISD 12/1/2030)
- Description
- Peach Bottom 500kV North bus upgrade - Replace 11 – Instances of strain bus conductor used for breaker drops or CT drops, 7 – 500 kV disconnect switches, 7 – Free Standing CTs, 1 – 500 kV breaker, 2 – Breaker relays or meters.
- Cost Information
- Time Estimate
- Dec 01 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.49
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.49
- Title
- North Delta 500 kV termination for the Calpine generator (Calpine/Transource work).
- Description
- None
- Cost Information
- Time Estimate
- Oct 06 2027
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3737.47
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3737.47
- Title
- Build New North Delta 500 kV substation (Four bay breaker and half configuration)
- Description
- Build New North Delta 500 kV substation (four bay breaker and half configuration) - the substation will include 12 - 500kV breakers and one 500/230 kV transformer, will allow the termination of six - 500 kV lines
- Cost Information
- Time Estimate
- Oct 06 2027
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3800.33
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.33
- Title
- Replace terminal equipment limitations at Brighton 500 kV - on the existing Brighton-Waugh Chapel 500 kV (5053) or new Brighton-High Ridge 500 kV.
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.2
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.2
- Title
- Peach Bottom to Graceton (PECO Portion) – New 500kV Line
- Description
- Peach Bottom to Graceton (PECO Portion) – New 500kV Line. New rating: 4503 MVA SN/ 5022 MVA SE. This is a baseline identified for the announced Brandon Shores deactivation.
- Cost Information
- Time Estimate
- Oct 23 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3780.4
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.4
- Title
- Peach Bottom to Graceton (BGE Portion) – New 500kV Line
- Description
- New rating: 4503 MVA SN/ 5022 MVA SE. This is a baseline identified for the announced Brandon Shores deactivation.
- Cost Information
- Time Estimate
- Dec 31 2028
Not ContingentTopology Changing Note 1: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| CHICHST1-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHICHST2-CHIREACT_39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| LINWOOD43-CHIREACT_43 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| POST97-LINWOOD97 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CHIREACT_39-POST39 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTNGHM-NOTTREAC 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| NOTTREAC-PCHBTMTP 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| BRIGHTON-CNASTONE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PCHBTM2S 500.0 kV Ckt Z1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1S-PBN_EXP_BAY 500.0 kV Ckt 2 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTM1N-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| PCHBTMTP-COOPER2 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| COOPER-GRACETON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 01DOUBS-CHAN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3867.1
- Type
- Load Flow
- TO
- AEC
- RTEP ID / TO ID
- b3867.1
- Title
- Upgrade a circuit switcher at Mickleton substation.
- Description
- Upgrade a circuit switcher at Mickleton substation.
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| DELCOTAP-MCKLTON 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- (Pending) / New Ratings
- Title
- Line rating higher on PECO side: 830/925/923/1052 MVA SN/SE/WN/WE.
- Description
- PECO ratings for this facility, which include from the Delco Tap to the NJ state line are: 830/925/923/1052 MVA SN/SE/WN/WE. Relay and Communication upgrades may require new fiber optic installation. The cost and scope will be further evaluated during the Phase 2 Interconnection Facilities Study.
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- TBD
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| DELCOTAP-MCKLTON 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- (Pending)
- Title
- PECO Ratings: 731/885 MVA (SN/SE)
- Description
- PECO Ratings: 731/885 MVA (SN/SE)
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- 0 to 1 Months
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| LINWOOD84-CLAY_230 230.0 kV Ckt 1 line | (Any) |
| ||||||||||
| LINWOOD85-EDGEMR 5 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4004.1
- Type
- Load Flow
- TO
- DPL
- RTEP ID / TO ID
- b4004.1
- Title
- Upgrade terminal equipment at Claymont substation
- Description
- Upgrade existing 1590 ACSR stranded bus at Claymont substation to increase the rating on the Claymont – Linwood 230 kV circuit SUM: 654/809/900 // WP: 753/911/1017 // LL: 659/809/919
- Cost Information
- Time Estimate
- May 31 2030
Not Contingent Note: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| LINWOOD84-CLAY_230 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- DPL
- RTEP ID / TO ID
- (Pending) / PE-2025-008 (Supplemental)
- Title
- DPL 230 kV Supplemental Upgrades
- Description
- Rebuild the entire 7.1 miles of the 23015 Claymont-Edgemoor 230kV line and the DPL sections of the 220-84 Claymont-Linwood 230kV line (1 mile) and 220-85 Edgemoor-Linwood 230kV line (8.1 miles). Replace breakers, disconnects, relays and bus sections at Claymont and Edgemoor substations. Note: Developer is responsible for costs if supplemental upgrades are cancelled.
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- 60 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-447 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-447 could receive cost allocation. Although AG2-447 may not presently have cost responsibility for this upgrade, AG2-447 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| LINWOOD84-CLAY_230 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||
| LINWOOD85-EDGEMR 5 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||
| CLAY_230-EDGEMR 5 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3907.2
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3907.2
- Title
- Rebuild Richmond - Waneeta 230 kV line
- Description
- Richmond to Waneeta 230kV Line: Rebuild entire 0.95 miles of existing UGT, and rebuild entire 2.23 miles of existing OHT
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AG2-447 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-447 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| WANEETA3-RICHMOND35 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9787.0
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- n9787.0 / PECO_TC2_PH2_Chichester
- Title
- New bus tie at Chichester
- Description
- At Chichester, create a new bus tie facility through the installation of two new 230kV circuit breakers and associated disconnects /relaying on the 230kV Chichester #1 bus, splitting the bus in two. One bus will connect to the 220-43 Chichester – Linwood line, the 220-04 Chichester – Foulk line, and the #3 distribution transformer. The other bus will connect to the 220-36 Chichester – Eddystone line, the 230/138kV 9A/9B transformers, and to the existing bus tie / #2 bus. Perform bus relaying upgrades.
- Total Cost ($USD)
- $3,500,000
- Discounted Total Cost ($USD)
- $3,500,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 36 to 48 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AG2-447 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-447 could receive cost allocation. Although AG2-447 may not presently have cost responsibility for this upgrade, AG2-447 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||
|---|---|---|---|
| (Any) | PECO_P2-2_CHI230B1_SRT-A/* $ DELCO $ PECO_P2-2_CHI230B1 $ B | No new ratings for this Flowgate. | |
| (Any) | PECO_P4_CHICH045_SRT-A/* $ DELCO $ PECO_P4_CHICH045 $ STBK | No new ratings for this Flowgate. | |
| (Any) | PECO_P4_CHICH195_SRT-A/* $ DELCO $ PECO_P4_CHICH195 $ STBK | No new ratings for this Flowgate. | |
| (Any) | PECO_P4_CHICH435_SRT-A/* $ DELCO $ PECO_P4_CHICH435 $ STBK | No new ratings for this Flowgate. |