AH1-563 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:59

Aurora E.C. 138kV

150.0 MW Capacity / 150.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Aurora Generation, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $16,268,213 $2,600,000 = 6.26 AND ( $16,268,213 - $2,600,000 ) 150.0 = $91,121 per MW

General

The Project Developer has proposed an uprate to a planned/existing Natural Gas/Storage facility located in the Commonwealth Edison Company zone — Not Specified County, Illinois. This project is an increase to the developer’s AC1-109/AC1-110/AC1-111/AG1-513 project(s), which will share the same Point of Interconnection. The AH1-563 project is a 150.0 MW uprate (150.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 1206.0 MW with 250.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-563
Project Name:
Aurora E.C. 138kV
Project Developer Name:
Aurora Generation, LLC
State:
Illinois
County:
Not Specified
Transmission Owner:
Commonwealth Edison Company
MFO:
1206.0
MWE:
150.0
MWC:
150.0
Battery Storage Specification:
600.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AH1-563 will interconnect on the Commonwealth Edison Company  transmission system at the Aurora E.C. 138 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-563 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-563Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$0$0$0
Other Scope$0$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0$0
Network Upgrades$1,420,651$1,420,651$1,420,651
System Reliability Network Upgrades
Steady State Thermal & Voltage$14,807,780$14,807,780$14,807,780
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$39,781$0$39,781
Total$16,268,213$16,228,431$16,268,213

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AH1-563

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AH1-563
Project ID: AH1-563
20% of cost allocation for Phase II Network Upgrades:(A) $3,245,686
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $600,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $2,645,686
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Relay and communication work at TSS144

$30,802$0$11,840$0$42,642$42,642
(Pending)

Relay and communication work at TSS 111

$30,802$0$11,840$0$42,642$42,642
(Pending)

Install new AMI AND REVENUE meter at TSS 951

$670,180$381,038$257,607$26,542$1,335,367$1,335,367
Developer Build Option

(No Developer Build Option for this project.)

Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$1,420,651$1,420,651
Developer Build Option(No Developer Build Option)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 1 to 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Notes on Cost Estimate:

  1. These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
  2. There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
  3. These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
  4. The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.

 

 

Transmission Owner Analysis

No Transmission Owner impacts identified.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-563 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.

AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2CE
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Base Case
SingleAC105.07 %1201.0A1261.88
9.1
GD2CE
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
COMED_P4-6_111-345-R______SRT-A
BreakerAC102.29 %1568.0STE1603.94
18.94

Details for ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:105.07 %
Rating:1201.0 MVA
Rating Type:A
MVA to Mitigate:1261.88
MW Contribution:
9.1
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.94 %
Rating:1201.0 MVA
Rating Type:A
MVA to Mitigate:1260.39
MW Contribution:
9.0
Bus #Bus NameTypeMW Contribution
274693ROCKY RD ;1P
Adder
5.338
274695ROCKY RD ;2P
Adder
5.391
274696ROCKY RD ;4P
Adder
5.494
274697ROCKY RD ;3P
Adder
1.465
274738AURORA EC;3P
50/50
1.406
274740AURORA EC;4P
50/50
1.406
274822ROCKFORD ;11
Adder
8.628
274823ROCKFORD ;21
Adder
8.568
274855GSG-6 ;RU
Solar/Wind Harmer
0.19
274856ECOGROVE ;U1
Solar/Wind Harmer
0.078
274760LEE CO EC;1U
Adder
5.549
274850MENDOTA H;RU
Solar/Wind Harmer
0.061
274761LEE CO EC;2U
Adder
5.549
274762LEE CO EC;3U
Adder
5.549
274763LEE CO EC;4U
Adder
5.497
274764LEE CO EC;5U
Adder
5.562
274765LEE CO EC;6U
Adder
5.562
274766LEE CO EC;7U
Adder
5.484
274767LEE CO EC;8U
Adder
5.484
274872LEEDK;1U
Solar/Wind Harmer
0
276890AG1-513 C
50/50
0.243
274741AC1-111 GEN5
50/50
0.169
274742AC1-111 GEN6
50/50
0.169
274743AC1-111 GEN7
50/50
0.169
274744AC1-111 GEN8
50/50
3.094
274745AC1-111 GEN9
50/50
3.094
274746AC1-111 G10
50/50
3.094
276861AD2-134 GEN
Solar/Wind Harmer
0.093
276863AD2-134 GEN
Solar/Wind Harmer
0.093
274857EASY ROAD;U1
Solar/Wind Harmer
0
274858EASY ROAD;U2
Solar/Wind Harmer
0
938861AE1-114 GEN
Solar/Wind Harmer
2.162
943121AE2-341 GEN
Solar/Wind Harmer
9.007
946321AF1-296 GEN
Solar/Wind Harmer
1.885
946671AF1-331 GEN
Solar/Wind Harmer
0.559
959081AF2-199 GEN
Solar/Wind Harmer
8.403
959091AF2-200 GEN
Solar/Wind Harmer
16.805
962691AG1-118 GEN
Solar/Wind Harmer
17.869
962781AG1-127 GEN
Solar/Wind Harmer
5.282
970819AG2-516 GEN
Solar/Wind Harmer
3.683
971067AG2-660 GEN
Solar/Wind Harmer
2.801
971171AH1-044 GEN
Solar/Wind Harmer
16.805
971341AH1-150 GEN
Solar/Wind Harmer
16.805
971343AH1-151 GEN
Solar/Wind Harmer
16.805
971675AH1-338 GEN
Solar/Wind Harmer
2.039
971681AH1-341 GEN
Solar/Wind Harmer
6.474
276157O29GEN1
Solar/Wind Harmer
0.603
276158O29GEN2
Solar/Wind Harmer
0
276708O09 GEN2
Solar/Wind Harmer
0.132
276741O09 GEN1
Solar/Wind Harmer
0.132
957471AF2-041 GEN
Solar/Wind Harmer
25.208
965931AG1-462 GEN
Solar/Wind Harmer
8.496
972235AH1-702 GEN1
Adder
1.246
972236AH1-702 GEN2
Adder
1.081
972267AH1-718 GEN
Adder
2.763
943591AF1-030 GEN
Solar/Wind Harmer
5.99
971087AG2-675 GEN
Solar/Wind Harmer
1.777
972029AH1-563 GEN
50/50
9.1
CBM West 1LTFEXP_CBM-W1->PJM
CBM
9.077
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.001
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.56
NYPJM->LTFIMP_NY
CLTF
0.158
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.055
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.025
TVALTFEXP_TVA->PJM
CLTF
0.213
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.108
MECLTFEXP_MEC->PJM
CLTF
3.707
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.318
LAGNLTFEXP_LAGN->PJM
CLTF
0.938

Details for ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line l/o COMED_P4-6_111-345-R______SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_111-345-R______SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.29 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1603.94
MW Contribution:
18.94
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_111-345-R______SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.12 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1601.2
MW Contribution:
18.81
Bus #Bus NameTypeMW Contribution
274693ROCKY RD ;1P
Adder
7.782
274695ROCKY RD ;2P
Adder
7.859
274696ROCKY RD ;4P
Adder
8.008
274697ROCKY RD ;3P
Adder
2.135
274738AURORA EC;3P
50/50
1.627
274740AURORA EC;4P
50/50
1.627
274822ROCKFORD ;11
Adder
11.187
274823ROCKFORD ;21
Adder
11.108
274855GSG-6 ;RU
Solar/Wind Harmer
3.335
274856ECOGROVE ;U1
Solar/Wind Harmer
2.023
274760LEE CO EC;1U
Adder
6.636
276602WESTBROOK C
Solar/Wind Harmer
1.92
276603SUBLETTE C
Solar/Wind Harmer
0.763
274850MENDOTA H;RU
Solar/Wind Harmer
2.319
274761LEE CO EC;2U
Adder
6.636
274762LEE CO EC;3U
Adder
6.636
274763LEE CO EC;4U
Adder
6.573
274764LEE CO EC;5U
Adder
6.651
274765LEE CO EC;6U
Adder
6.651
274766LEE CO EC;7U
Adder
6.557
274767LEE CO EC;8U
Adder
6.557
274872LEEDK;1U
Solar/Wind Harmer
7.934
276611AD2-172 GEN
Solar/Wind Harmer
1.535
276612AE2-035 GEN
Solar/Wind Harmer
1.535
276799AD1-013 GEN
Solar/Wind Harmer
2.007
276890AG1-513 C
50/50
0.505
274737AURORA EC;1P
50/50
1.032
274739AURORA EC;2P
50/50
1.032
274741AC1-111 GEN5
50/50
0.352
274742AC1-111 GEN6
50/50
0.352
274743AC1-111 GEN7
50/50
0.352
274744AC1-111 GEN8
50/50
6.44
274745AC1-111 GEN9
50/50
6.44
274746AC1-111 G10
50/50
6.44
276861AD2-134 GEN
Solar/Wind Harmer
1.613
276863AD2-134 GEN
Solar/Wind Harmer
1.613
274857EASY ROAD;U1
Solar/Wind Harmer
3.417
274858EASY ROAD;U2
Solar/Wind Harmer
3.417
938861AE1-114 GEN
Solar/Wind Harmer
5.424
943121AE2-341 GEN
Solar/Wind Harmer
14.637
946321AF1-296 GEN
Solar/Wind Harmer
5.821
946671AF1-331 GEN
Solar/Wind Harmer
0.38
959081AF2-199 GEN
Solar/Wind Harmer
13.218
959091AF2-200 GEN
Solar/Wind Harmer
26.436
960751AF2-366 GEN
Solar/Wind Harmer
2.786
962691AG1-118 GEN
Solar/Wind Harmer
31.06
962781AG1-127 GEN
Solar/Wind Harmer
9.235
970819AG2-516 GEN
Solar/Wind Harmer
6.739
971067AG2-660 GEN
Solar/Wind Harmer
3.074
971171AH1-044 GEN
Solar/Wind Harmer
26.436
971341AH1-150 GEN
Solar/Wind Harmer
26.436
971343AH1-151 GEN
Solar/Wind Harmer
26.436
971411AH1-196 GEN
Solar/Wind Harmer
7.659
971675AH1-338 GEN
Solar/Wind Harmer
16.301
971681AH1-341 GEN
Solar/Wind Harmer
10.393
276157O29GEN1
Solar/Wind Harmer
2.351
276158O29GEN2
Solar/Wind Harmer
3.092
276708O09 GEN2
Solar/Wind Harmer
2.208
276741O09 GEN1
Solar/Wind Harmer
2.208
957471AF2-041 GEN
Solar/Wind Harmer
39.654
965931AG1-462 GEN
Solar/Wind Harmer
14.028
972235AH1-702 GEN1
Adder
1.599
972236AH1-702 GEN2
Adder
1.388
972267AH1-718 GEN
Adder
3.185
943591AF1-030 GEN
Solar/Wind Harmer
9.758
970707AG2-453 GEN
Solar/Wind Harmer
15.618
971087AG2-675 GEN
Solar/Wind Harmer
2.047
972029AH1-563 GEN
50/50
18.942
CBM West 1LTFEXP_CBM-W1->PJM
CBM
11.469
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.059
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.508
NYPJM->LTFIMP_NY
CLTF
0.193
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.08
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.04
TVALTFEXP_TVA->PJM
CLTF
0.209
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.144
MECLTFEXP_MEC->PJM
CLTF
4.311
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.43
LAGNLTFEXP_LAGN->PJM
CLTF
1.013
CONTINGENCY 'COMED_P4-6_111-345-R______SRT-A'
 DISCONNECT BUS 270731   /*ELECT JCT;4R 345.0
 DISCONNECT BUS 270733   /*ELECT JCT;3R 345.0
 DISCONNECT BUS 275183   /*ELECT JCT;3M 138.0
 DISCONNECT BUS 275184   /*ELECT JCT;4M 138.0
END
270732 to 270814 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

The New Service Request AH1-563 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.

AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDCE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC105.74 %467.0STE493.82
150.0
GD2CE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC104.5 %467.0STE487.99
150.0

Details for [AH1-563] AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:105.74 %
Rating:467.0 MVA
Rating Type:STE
MVA to Mitigate:493.82
MW Contribution:
150.0
IPD Plant:AH1-563
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:105.76 %
Rating:467.0 MVA
Rating Type:STE
MVA to Mitigate:493.9
MW Contribution:
150.0
IPD Plant:AH1-563
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
150

Details for AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.5 %
Rating:467.0 MVA
Rating Type:STE
MVA to Mitigate:487.99
MW Contribution:
150.0
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.51 %
Rating:467.0 MVA
Rating Type:STE
MVA to Mitigate:488.08
MW Contribution:
150.0
Bus #Bus NameTypeMW Contribution
276890AG1-513 C
50/50
4
274741AC1-111 GEN5
50/50
58.26
274742AC1-111 GEN6
50/50
58.26
274743AC1-111 GEN7
50/50
58.26
274744AC1-111 GEN8
50/50
58.26
274745AC1-111 GEN9
50/50
58.26
274746AC1-111 G10
50/50
58.26
972029AH1-563 GEN
50/50
150
CONTINGENCY 'COMED_P1-2_138-L14403_R-N_SRT-A'
 CLOSE LINE FROM BUS 271070 TO BUS 271071 CKT Z1   /*ESS W503 ; B 138.0 - ESS W503 ; R 138.0
 CLOSE LINE FROM BUS 272754 TO BUS 272755 CKT Z1   /*W CHICAGO; B 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 271069 CKT 1   /*BATAVIA  ;RT 138.0 - ESS W502 ; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 272755 CKT 1   /*BATAVIA  ;RT 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 272755 TO BUS 272741 CKT 1   /*W CHICAGO; R 138.0 - WAYNE    ; R 138.0
 TRIP BRANCH FROM BUS 274747 TO BUS 271067 CKT 1   /*AURORA EC;RP 138.0 - BATAVIA  ;RT 138.0
END
274747 to 271391 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-563 was evaluated as a 150.0 MW injection and 150.0 MW withdrawal in the ComEd area.

AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AEP_P1-2_#7422_16_SRT-A
SingleAC104.17 %1180.0B1229.25
13.0
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A
BreakerAC104.17 %1180.0B1229.25
13.0
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P4-2: 56602_SRT-A
BreakerAC104.16 %1180.0B1229.15
13.0
GD2CE
AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line
COMED_P1-2_345-L0627__B-R_SRT-A
SingleAC109.81 %1912.0STE2099.51
7.96
GD2CE
AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line
COMED_P1-2_345-L15501_B-R_SRT-A-1
SingleAC108.06 %1912.0STE2066.06
7.92
IPDCE
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
COMED_P1-2_138-L14403_R-N_SRT-A
SingleAC101.3 %446.0B451.8
150.0

Details for [AH1-563] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.17 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1229.25
MW Contribution:
13.0
IPD Plant:AH1-563
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
13.001

Details for [AH1-563] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:104.17 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1229.25
MW Contribution:
13.0
IPD Plant:AH1-563
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
13.001

Details for [AH1-563] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P4-2: 56602_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P4-2: 56602_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:104.16 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1229.15
MW Contribution:
13.0
IPD Plant:AH1-563
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
13.001

Details for AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L0627__B-R_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L0627__B-R_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:109.81 %
Rating:1912.0 MVA
Rating Type:STE
MVA to Mitigate:2099.51
MW Contribution:
7.96
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L0627__B-R_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:109.48 %
Rating:1912.0 MVA
Rating Type:STE
MVA to Mitigate:2093.17
MW Contribution:
8.06
Bus #Bus NameTypeMW Contribution
276890AG1-513 C
50/50
Charging
0.53
274857EASY ROAD;U1
Solar/Wind Harmer
17.012
274858EASY ROAD;U2
Solar/Wind Harmer
17.012
959081AF2-199 GEN
Solar/Wind Harmer
32.126
959091AF2-200 GEN
Solar/Wind Harmer
64.252
971067AG2-660 GEN
Solar/Wind Harmer
29.205
971171AH1-044 GEN
Solar/Wind Harmer
64.252
971341AH1-150 GEN
Solar/Wind Harmer
64.252
971343AH1-151 GEN
Solar/Wind Harmer
64.252
276157O29GEN1
Solar/Wind Harmer
11.804
276158O29GEN2
Solar/Wind Harmer
11.804
276708O09 GEN2
Solar/Wind Harmer
11.085
276741O09 GEN1
Solar/Wind Harmer
11.085
957471AF2-041 GEN
Solar/Wind Harmer
96.378
965931AG1-462 GEN
Solar/Wind Harmer
18.034
971087AG2-675 GEN
Solar/Wind Harmer
10.287
972029AH1-563 GEN
50/50
Charging
7.957
991092J1477
External Queue
7.49889612197876
CBM West 1LTFEXP_CBM-W1->PJM
CBM
50.47
CBM West 2LTFEXP_CBM-W2->PJM
CBM
24.467
CBM South 1LTFEXP_CBM-S1->PJM
CBM
3.504
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.615
NYPJM->LTFIMP_NY
CLTF
0.373
WECLTFEXP_WEC->PJM
CLTF
0.1
CPLELTFEXP_CPLE->PJM
CLTF
0.026
TVALTFEXP_TVA->PJM
CLTF
1.177
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.177
MECLTFEXP_MEC->PJM
CLTF
14.874
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.478
LAGNLTFEXP_LAGN->PJM
CLTF
4.346
SIGELTFEXP_SIGE->PJM
CLTF
0.011
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
593.19

Details for AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L15501_B-R_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L15501_B-R_SRT-A-1
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:108.06 %
Rating:1912.0 MVA
Rating Type:STE
MVA to Mitigate:2066.06
MW Contribution:
7.92
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L15501_B-R_SRT-A-1
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:107.73 %
Rating:1912.0 MVA
Rating Type:STE
MVA to Mitigate:2059.75
MW Contribution:
8.02
Bus #Bus NameTypeMW Contribution
276602WESTBROOK C
Solar/Wind Harmer
0.491
276603SUBLETTE C
Solar/Wind Harmer
0.636
276890AG1-513 C
50/50
Charging
0.528
959081AF2-199 GEN
Solar/Wind Harmer
32.141
959091AF2-200 GEN
Solar/Wind Harmer
64.283
971067AG2-660 GEN
Solar/Wind Harmer
29.22
971171AH1-044 GEN
Solar/Wind Harmer
64.283
971341AH1-150 GEN
Solar/Wind Harmer
64.283
971343AH1-151 GEN
Solar/Wind Harmer
64.283
276157O29GEN1
Solar/Wind Harmer
11.818
276158O29GEN2
Solar/Wind Harmer
11.818
276708O09 GEN2
Solar/Wind Harmer
11.098
276741O09 GEN1
Solar/Wind Harmer
11.098
957471AF2-041 GEN
Solar/Wind Harmer
96.424
965931AG1-462 GEN
Solar/Wind Harmer
32.601
971087AG2-675 GEN
Solar/Wind Harmer
18.596
972029AH1-563 GEN
50/50
Charging
7.915
991092J1477
External Queue
7.49889612197876
CBM West 1LTFEXP_CBM-W1->PJM
CBM
50.824
CBM West 2LTFEXP_CBM-W2->PJM
CBM
24.795
CBM South 1LTFEXP_CBM-S1->PJM
CBM
3.596
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.688
NYPJM->LTFIMP_NY
CLTF
0.357
WECLTFEXP_WEC->PJM
CLTF
0.109
CPLELTFEXP_CPLE->PJM
CLTF
0.053
TVALTFEXP_TVA->PJM
CLTF
1.202
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.161
MECLTFEXP_MEC->PJM
CLTF
14.914
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.429
LAGNLTFEXP_LAGN->PJM
CLTF
4.396
SIGELTFEXP_SIGE->PJM
CLTF
0.012
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
593.19

Details for [AH1-563] AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line l/o COMED_P1-2_138-L14403_R-N_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:101.3 %
Rating:446.0 MVA
Rating Type:B
MVA to Mitigate:451.8
MW Contribution:
150.0
IPD Plant:AH1-563
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_138-L14403_R-N_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:101.29 %
Rating:446.0 MVA
Rating Type:B
MVA to Mitigate:451.77
MW Contribution:
150.0
IPD Plant:AH1-563
Bus #Bus NameTypeMW Contribution
972029AH1-563 GEN
PJM_IPD_GROUP
150
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'DVP_P4-2: 56602_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314856 TO BUS 314912 CKT 1   /*6LEXNGT2     230.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'COMED_P1-2_345-L0627__B-R_SRT-A'
 TRIP BRANCH FROM BUS 274768 TO BUS 270678 CKT 1   /*LEE CO EC;BP 345.0 - BYRON    ; B 345.0
END
CONTINGENCY 'COMED_P1-2_345-L15501_B-R_SRT-A-1'
 TRIP BRANCH FROM BUS 270828 TO BUS 946150 CKT 1   /*NELSON   ; B 345.0 - AF1-280 TP   345.0
END
CONTINGENCY 'COMED_P1-2_138-L14403_R-N_SRT-A'
 CLOSE LINE FROM BUS 271070 TO BUS 271071 CKT Z1   /*ESS W503 ; B 138.0 - ESS W503 ; R 138.0
 CLOSE LINE FROM BUS 272754 TO BUS 272755 CKT Z1   /*W CHICAGO; B 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 271069 CKT 1   /*BATAVIA  ;RT 138.0 - ESS W502 ; R 138.0
 TRIP BRANCH FROM BUS 271067 TO BUS 272755 CKT 1   /*BATAVIA  ;RT 138.0 - W CHICAGO; R 138.0
 TRIP BRANCH FROM BUS 272755 TO BUS 272741 CKT 1   /*W CHICAGO; R 138.0 - WAYNE    ; R 138.0
 TRIP BRANCH FROM BUS 274747 TO BUS 271067 CKT 1   /*AURORA EC;RP 138.0 - BATAVIA  ;RT 138.0
END
290614 to 242515 ckt 1
957470 to 270732 ckt 1
274747 to 271391 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Analysis Complete - No Issues

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 57 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 57 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 57 projects will meet the dynamics requirements of the NERC, COMED and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load and light load case, modified to include applicable projects. Cluster 57 projects have been dispatched online according to the scenarios, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer for the IBR projects.

Cluster 57 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 632 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  7. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 57 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load and light load cases:

  1. Cluster 57 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 57 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-453, AG2-524, AH1-165, AH1-563, AH1-673, AH1-698 and AH1-714 meets the leading and lagging PF requirement.

Initial simulations identified slow terminal voltage and reactive power control response at AH1-165 due to the absence of reactive power droop in the voltage controller of the power plant controller model (REPCA1). This was resolved by adding a 5% droop to Q/V controller in the REPCA1 model as follows:

REPCA1:

  • CON(J+8) = 0.05 (Kc, Reactive current compensation gain (pu))

Contingencies P4.01, P4.02, P4.03, P4.04, P4.05, P4.06, P4.229, P4.230, P4.267, P4.269, P4.270 and P4.279 exhibited oscillations in the POI voltage and generator responses after 17.5s. This behavior is attributed to improperly tuned power system stabilizer model (PSS2C) in AH1-698. This issue was observed only in light load scenario. It is recommended to tune the power system stabilizer to according to the system conditions.

Table 1: TC2 Cluster 57 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-453

Solar

ComEd

280

280

196

La Salle – Plano 345 kV

AG2-524

Storage/Solar

ComEd

110

110

110

La Salle – Mazon 138 kV

AH1-165

Storage

ComEd

72

72

0

Will County 138 kV

AH1-563

Storage

ComEd

1,206

150

150

Aurora EC 138 kV

AH1-673

Storage

ComEd

85

85

85

State Line - River Energy Center 138 kV

AH1-698

Nuclear

ComEd

2,584

130

57.6

Braidwood 345 kV

AH1-714

Nuclear

ComEd

1,360

169

174.1

La Salle 345 kV

 

 

Reactive Power Analysis

Analysis Complete - No Issues

The reactive power capability of AH1-563 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

 Steady State Voltage Analysis complete, no voltage issues identified.

 

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AC1-111Aurora 138kVIn Service
AD1-013Twombly Road 138kVEngineering & Procurement
AD2-134Shady OaksPartially in Service - Under Construction
AD2-172Lena 138kVIn Service
AE1-114Maryland-Lancaster 138 kVEngineering & Procurement
AE2-035Lena 138 kVIn Service
AE2-341Sandwich-Plano 138 kVEngineering & Procurement
AF1-030Sandwich-Plano 138 kVEngineering & Procurement
AF1-296Garden Plain 138 kVEngineering & Procurement
AF1-331Twombley RoadEngineering & Procurement
AF2-041Nelson-Electric Junction 345 kVEngineering & Procurement
AF2-199Nelson-Electric Junction 345 kVEngineering & Procurement
AF2-200Nelson-Electric Junction 345 kVEngineering & Procurement
AF2-366Crego Rd 138 kVEngineering & Procurement
AG1-118Sugar Grove-Waterman 138kVEngineering & Procurement
AG1-127Crego Rd 138 kVEngineering & Procurement
AG1-462Cordova 345 kVEngineering & Procurement
AG1-513Aurora 138 kVSuspended
AG2-453Lasalle - Plano 345 kVActive
AG2-516Pecatonica 138kVActive
AG2-660Nelson-Electric Junction 345 kVActive
AG2-675Cordova 345 kVActive
AH1-044Nelson - Electric Junction 345 kVActive
AH1-150Nelson-Electric Junction 345 kVActive
AH1-151Nelson-Electric Junction 345 kVActive
AH1-196Silver Lake - Cherry Valley 345 kVActive
AH1-338New Sub S2354 138kVActive
AH1-341ESS-H445 3B 138kvActive
AH1-702Byron 345 kVActive
AH1-718Nelson 345 kVActive

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AH1-563Scenarios
  • 17REYNOLDS 765.0 - 05GRNTWN 765.0 CKT 1
NIPS Reynolds-Greentown 765 kV
NIPSCO: No mitigation required. Rating Of NIPS-
Owned
Line Portion: SN/SE=9015 MVA/9015 MVA.

AEP: No mitigation required. 8348 MVA SN/SE
$0$0
  • NIPSCO
  • Contingent
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M

NIPSCO: DEI mitigations acceptable to remove
constraint. $0
$1,500,000$39,781
  • NIPSCO
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AH1-563 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
ComEdn7023.1Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades.Cost Allocated$8,307,780N/A
ComEdn9784.0L11103 Station conductor and line workCost Allocated$6,500,000N/A
AEPb4000.251Replace the wave trap and upgrade the relay at Cloverdale 765kV substationContingent$0N/A
AEPb4000.252Replace the wave trap and upgrade the relay at Joshua Falls 765kV substationContingent$0N/A
Grand Total:$14,807,780

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n7023.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n7023.1 / CE_NUN_L11124.1
Title
Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades.
Description
• Upgrade 13.5 Miles of 345kV transmission line 11124 from TSS 111 Electric Junction to TSS 120 Lombard • Upgrade relay & protection at 345kV substation TSS 111 Electric Junction & TSS 120 Lombard to support upgrade of 345kV transmission line, L1124
Total Cost ($USD)
$38,797,273
Discounted Total Cost ($USD)
$38,797,273
Allocated Cost ($USD)
$8,307,780
Time Estimate
36 Months

Contributor

FacilityContingency
ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
SUMA1334.0 MVA
SUMB1726.0 MVA
SUMC2084.0 MVA
SUMSTE1837.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-660 Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
2.8 MW3.2%$1,228,492
AH1-044 Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
16.8 MW19.0%$7,370,513
AH1-150 Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
16.8 MW19.0%$7,370,513
AH1-151 Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
16.8 MW19.0%$7,370,513
AH1-33816.3 MW18.4%$7,149,463
AH1-56318.9 MW21.4%$8,307,780

System Reinforcement: n9784.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9784.0 / CE_L11103_2
Title
L11103 Station conductor and line work
Description
Sag mitigation of 1113 ACSR conductor. TSS 111 BUS UPGRADE- REPLACE BUS BAR Upgrade L11103 Bushing CT on CB. (possible CB replacement if unable to replace Bushing CT in existing CB housing). This will be determined during the Facility Study Phase (PH 3).
Total Cost ($USD)
$6,500,000
Discounted Total Cost ($USD)
$6,500,000
Allocated Cost ($USD)
$6,500,000
Time Estimate
24 to 30 Months

Contributor

FacilityContingency
ELECT JCT;3R-AURORA EC;RP 138.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AH1-563150.0 MW100.0%$6,500,000

System Reinforcement: b4000.251
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.251
Title
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Description
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AH1-563 may not presently have cost responsibility for this upgrade, AH1-563 may need this upgrade in-service to be deliverable to the PJM system. If AH1-563 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A4047.0 MVA
(All)B4571.0 MVA

System Reinforcement: b4000.252
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.252
Title
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Description
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AH1-563 may not presently have cost responsibility for this upgrade, AH1-563 may need this upgrade in-service to be deliverable to the PJM system. If AH1-563 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A4047.0 MVA
(All)B4571.0 MVA

System Reinforcement: n6639.2
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n6639.2 / CE_NUN_L15502_4
Title
Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches.
Description
• Reconductor 27.2 Miles of 345kV transmission line 93407 from structure 339 to structure 454 • Perform sag mitigation on 13.5 miles of 345kV transmission line 93407 from structure 454 to TSS 111 Electric Junction • Upgrade the existing substation TSS 111 Electric Junction by replacing L.93407 CB motor-operated disconnect switches on both sides of the breaker.
Total Cost ($USD)
$146,197,759
Discounted Total Cost ($USD)
$146,197,759
Allocated Cost ($USD)
$0
Time Estimate
Sep 30 2029

Not Contingent

Note: AH1-563 contributes to the loading of an overloaded facility that is being mitigated by a network upgrade that was securitized by a prior Queue/Cycle. AH1-563 is not contingent on this network upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
ELECT JCT;1B-AF2-041 TP 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A1872.0 MVA
(All)B2112.0 MVA
(All)C2485.0 MVA
(All)STE2336.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-563


AH1-563 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-563 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-563 One Line Diagram

AH1-563 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.