AH1-563 Phase II System Impact Study Report
v1.00 released 2026-06-03 17:59
Aurora E.C. 138kV
150.0 MW Capacity / 150.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Aurora Generation, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed an uprate to a planned/existing Natural Gas/Storage facility located in the Commonwealth Edison Company zone — Not Specified County, Illinois. This project is an increase to the developer’s AC1-109/AC1-110/AC1-111/AG1-513 project(s), which will share the same Point of Interconnection. The AH1-563 project is a 150.0 MW uprate (150.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 1206.0 MW with 250.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AH1-563 will interconnect on the Commonwealth Edison Company transmission system at the Aurora E.C. 138 kV Substation.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AH1-563 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-563 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 | $0 |
| Other Scope | $0 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | $0 |
| Network Upgrades | $1,420,651 | $1,420,651 | $1,420,651 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $14,807,780 | $14,807,780 | $14,807,780 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $39,781 | $0 | $39,781 |
| Total | $16,268,213 | $16,228,431 | $16,268,213 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AH1-563
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AH1-563
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Relay and communication work at TSS144 | $30,802 | $0 | $11,840 | $0 | $42,642 | $42,642 |
| (Pending) | Relay and communication work at TSS 111 | $30,802 | $0 | $11,840 | $0 | $42,642 | $42,642 |
| (Pending) | Install new AMI AND REVENUE meter at TSS 951 | $670,180 | $381,038 | $257,607 | $26,542 | $1,335,367 | $1,335,367 |
Developer Build Option
(No Developer Build Option for this project.)
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $1,420,651 | $1,420,651 | |||||
| Developer Build Option | (No Developer Build Option) | ||||||
Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 1 to 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Notes on Cost Estimate:
- These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
- There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
- These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
- The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-563 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.
AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | CE | ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line | Base Case | Single | AC | 105.07 % | 1201.0 | A | 1261.88 | 9.1 | |
| GD2 | CE | ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line | COMED_P4-6_111-345-R______SRT-A | Breaker | AC | 102.29 % | 1568.0 | STE | 1603.94 | 18.94 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Winter Peak Analysis
The New Service Request AH1-563 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.
AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| IPD | CE | AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line | COMED_P1-2_138-L14403_R-N_SRT-A | Single | AC | 105.74 % | 467.0 | STE | 493.82 | 150.0 | |
| GD2 | CE | AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line | COMED_P1-2_138-L14403_R-N_SRT-A | Single | AC | 104.5 % | 467.0 | STE | 487.99 | 150.0 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Analysis
The New Service Request AH1-563 was evaluated as a 150.0 MW injection and 150.0 MW withdrawal in the ComEd area.
AH1-563 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1206.0 MW (150.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 104.17 % | 1180.0 | B | 1229.25 | 13.0 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 104.17 % | 1180.0 | B | 1229.25 | 13.0 | |
| IPD | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 104.16 % | 1180.0 | B | 1229.15 | 13.0 | |
| GD2 | CE | AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line | COMED_P1-2_345-L0627__B-R_SRT-A | Single | AC | 109.81 % | 1912.0 | STE | 2099.51 | 7.96 | |
| GD2 | CE | AF2-041 TP-ELECT JCT;1B 345.0 kV Ckt 1 line | COMED_P1-2_345-L15501_B-R_SRT-A-1 | Single | AC | 108.06 % | 1912.0 | STE | 2066.06 | 7.92 | |
| IPD | CE | AURORA EC;RP-ELECT JCT;3R 138.0 kV Ckt 1 line | COMED_P1-2_138-L14403_R-N_SRT-A | Single | AC | 101.3 % | 446.0 | B | 451.8 | 150.0 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
Executive Summary:
- Steady-state operation (20 second run);
- Three-phase faults with normal clearing time;
- Three-phase bus faults with normal clearing time;
- Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
- Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
- Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
- Three-phase faults with loss of multiple-circuit tower line.
For all simulations, the Cluster 57 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2028 peak load and light load cases:
- Cluster 57 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
- The system with Cluster 57 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
- Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
- No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AG2-453, AG2-524, AH1-165, AH1-563, AH1-673, AH1-698 and AH1-714 meets the leading and lagging PF requirement.
Initial simulations identified slow terminal voltage and reactive power control response at AH1-165 due to the absence of reactive power droop in the voltage controller of the power plant controller model (REPCA1). This was resolved by adding a 5% droop to Q/V controller in the REPCA1 model as follows:
REPCA1:
- CON(J+8) = 0.05 (Kc, Reactive current compensation gain (pu))
Contingencies P4.01, P4.02, P4.03, P4.04, P4.05, P4.06, P4.229, P4.230, P4.267, P4.269, P4.270 and P4.279 exhibited oscillations in the POI voltage and generator responses after 17.5s. This behavior is attributed to improperly tuned power system stabilizer model (PSS2C) in AH1-698. This issue was observed only in light load scenario. It is recommended to tune the power system stabilizer to according to the system conditions.
Table 1: TC2 Cluster 57 Projects
Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
AG2-453 | Solar | ComEd | 280 | 280 | 196 | La Salle – Plano 345 kV |
AG2-524 | Storage/Solar | ComEd | 110 | 110 | 110 | La Salle – Mazon 138 kV |
AH1-165 | Storage | ComEd | 72 | 72 | 0 | Will County 138 kV |
AH1-563 | Storage | ComEd | 1,206 | 150 | 150 | Aurora EC 138 kV |
AH1-673 | Storage | ComEd | 85 | 85 | 85 | State Line - River Energy Center 138 kV |
AH1-698 | Nuclear | ComEd | 2,584 | 130 | 57.6 | Braidwood 345 kV |
AH1-714 | Nuclear | ComEd | 1,360 | 169 | 174.1 | La Salle 345 kV |
Reactive Power Analysis
Analysis Complete - No Issues
The reactive power capability of AH1-563 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis complete, no voltage issues identified.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AC1-111 | Aurora 138kV | In Service |
| AD1-013 | Twombly Road 138kV | Engineering & Procurement |
| AD2-134 | Shady Oaks | Partially in Service - Under Construction |
| AD2-172 | Lena 138kV | In Service |
| AE1-114 | Maryland-Lancaster 138 kV | Engineering & Procurement |
| AE2-035 | Lena 138 kV | In Service |
| AE2-341 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-030 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-296 | Garden Plain 138 kV | Engineering & Procurement |
| AF1-331 | Twombley Road | Engineering & Procurement |
| AF2-041 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-199 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-200 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-366 | Crego Rd 138 kV | Engineering & Procurement |
| AG1-118 | Sugar Grove-Waterman 138kV | Engineering & Procurement |
| AG1-127 | Crego Rd 138 kV | Engineering & Procurement |
| AG1-462 | Cordova 345 kV | Engineering & Procurement |
| AG1-513 | Aurora 138 kV | Suspended |
| AG2-453 | Lasalle - Plano 345 kV | Active |
| AG2-516 | Pecatonica 138kV | Active |
| AG2-660 | Nelson-Electric Junction 345 kV | Active |
| AG2-675 | Cordova 345 kV | Active |
| AH1-044 | Nelson - Electric Junction 345 kV | Active |
| AH1-150 | Nelson-Electric Junction 345 kV | Active |
| AH1-151 | Nelson-Electric Junction 345 kV | Active |
| AH1-196 | Silver Lake - Cherry Valley 345 kV | Active |
| AH1-338 | New Sub S2354 138kV | Active |
| AH1-341 | ESS-H445 3B 138kv | Active |
| AH1-702 | Byron 345 kV | Active |
| AH1-718 | Nelson 345 kV | Active |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
| Impacted Facility | Transmission Owner | Reinforcement | Cost | Cost Allocated to AH1-563 | Scenarios |
|---|---|---|---|---|---|
| NIPS | Reynolds-Greentown 765 kV NIPSCO: No mitigation required. Rating Of NIPS- Owned Line Portion: SN/SE=9015 MVA/9015 MVA. AEP: No mitigation required. 8348 MVA SN/SE | $0 | $0 |
|
| NIPS | Wvrich - Rochester TP 69 kV DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @ 100/120C the ratings assume that NIPSCO terminal upgrades would not limit our T-Line rating. $1.5M NIPSCO: DEI mitigations acceptable to remove constraint. $0 | $1,500,000 | $39,781 |
|
System Reinforcements
Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| ComEd | n7023.1 | Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades. | Cost Allocated | $8,307,780 | N/A |
| ComEd | n9784.0 | L11103 Station conductor and line work | Cost Allocated | $6,500,000 | N/A |
| AEP | b4000.251 | Replace the wave trap and upgrade the relay at Cloverdale 765kV substation | Contingent | $0 | N/A |
| AEP | b4000.252 | Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation | Contingent | $0 | N/A |
| Grand Total: | $14,807,780 | ||||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n7023.1
- Type
- Load Flow
- TO
- ComEd
- RTEP ID / TO ID
- n7023.1 / CE_NUN_L11124.1
- Title
- Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades.
- Description
- • Upgrade 13.5 Miles of 345kV transmission line 11124 from TSS 111 Electric Junction to TSS 120 Lombard • Upgrade relay & protection at 345kV substation TSS 111 Electric Junction & TSS 120 Lombard to support upgrade of 345kV transmission line, L1124
- Total Cost ($USD)
- $38,797,273
- Discounted Total Cost ($USD)
- $38,797,273
- Allocated Cost ($USD)
- $8,307,780
- Time Estimate
- 36 Months
Contributor
| Facility | Contingency | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ELECT JCT;1B-LOMBARD ;4B 345.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-660 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG2-660, AH1-044, AH1-150, AH1-151 | 2.8 MW | 3.2% | $1,228,492 |
| AH1-044 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG2-660, AH1-044, AH1-150, AH1-151 | 16.8 MW | 19.0% | $7,370,513 |
| AH1-150 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG2-660, AH1-044, AH1-150, AH1-151 | 16.8 MW | 19.0% | $7,370,513 |
| AH1-151 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AG2-660, AH1-044, AH1-150, AH1-151 | 16.8 MW | 19.0% | $7,370,513 |
| AH1-338 | 16.3 MW | 18.4% | $7,149,463 |
| AH1-563 | 18.9 MW | 21.4% | $8,307,780 |
System Reinforcement: n9784.0
- Type
- Load Flow
- TO
- ComEd
- RTEP ID / TO ID
- n9784.0 / CE_L11103_2
- Title
- L11103 Station conductor and line work
- Description
- Sag mitigation of 1113 ACSR conductor. TSS 111 BUS UPGRADE- REPLACE BUS BAR Upgrade L11103 Bushing CT on CB. (possible CB replacement if unable to replace Bushing CT in existing CB housing). This will be determined during the Facility Study Phase (PH 3).
- Total Cost ($USD)
- $6,500,000
- Discounted Total Cost ($USD)
- $6,500,000
- Allocated Cost ($USD)
- $6,500,000
- Time Estimate
- 24 to 30 Months
Contributor
| Facility | Contingency | ||
|---|---|---|---|
| ELECT JCT;3R-AURORA EC;RP 138.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AH1-563 | 150.0 MW | 100.0% | $6,500,000 |
System Reinforcement: b4000.251
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.251
- Title
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-563 may not presently have cost responsibility for this upgrade, AH1-563 may need this upgrade in-service to be deliverable to the PJM system. If AH1-563 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4000.252
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.252
- Title
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-563 may not presently have cost responsibility for this upgrade, AH1-563 may need this upgrade in-service to be deliverable to the PJM system. If AH1-563 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n6639.2
- Type
- Load Flow
- TO
- ComEd
- RTEP ID / TO ID
- n6639.2 / CE_NUN_L15502_4
- Title
- Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches.
- Description
- • Reconductor 27.2 Miles of 345kV transmission line 93407 from structure 339 to structure 454 • Perform sag mitigation on 13.5 miles of 345kV transmission line 93407 from structure 454 to TSS 111 Electric Junction • Upgrade the existing substation TSS 111 Electric Junction by replacing L.93407 CB motor-operated disconnect switches on both sides of the breaker.
- Total Cost ($USD)
- $146,197,759
- Discounted Total Cost ($USD)
- $146,197,759
- Allocated Cost ($USD)
- $0
- Time Estimate
- Sep 30 2029
Not Contingent Note: AH1-563 contributes to the loading of an overloaded facility that is being mitigated by a network upgrade that was securitized by a prior Queue/Cycle. AH1-563 is not contingent on this network upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ELECT JCT;1B-AF2-041 TP 345.0 kV Ckt 1 line | (Any) |
|