AH1-680 Phase II System Impact Study Report
v1.00 released 2026-06-04 08:30
Sammis - South Canton 345 kV
1300.0 MW Capacity / 1300.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Chestnut Run Energy LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Natural Gas generating facility located in the American Transmission Systems, Incorporated zone — Carroll County, Ohio. The installed facilities will have a total capability of 1300.0 MW with 1300.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AH1-680 will interconnect on the American Transmission Systems, Incorporated transmission system by tapping the Sammis - South Canton 345 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AH1-680 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-680 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $2,128,099 | $0 | $0 |
| Other Scope | $680,115 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $19,561,445 | $19,561,445 | $19,561,445 |
| Network Upgrades | $7,955,596 | $7,955,596 | $7,955,596 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $1,000,000 | $1,000,000 | $1,000,000 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $31,325,255 | $28,517,041 | $28,517,041 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AH1-680
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AH1-680
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Cut the existing 345kV line and Loop in the new interconnection substation. | $3,484,832 | $3,106,732 | $145,230 | $95,530 | $6,832,324 | $6,832,324 |
| (Pending) | Install (2) wave traps, (2) line tuner units , (4) carrier sets (radio transceivers/receiver units), (4) carrier monitors, (4) hybrids and update relay settings at Sammis Substation. | $651,977 | $192,766 | $27,171 | $3,894 | $875,808 | $875,808 |
| (Pending) | Review and update relay settings at Star substation. | $49,161 | $0 | $2,049 | $0 | $51,210 | $51,210 |
| (Pending) | Review and update relay settings at Wellsville substation. | $49,161 | $0 | $2,049 | $0 | $51,210 | $51,210 |
| (Pending) | Reveiw and update relay settings at Toronto substation. | $50,191 | $0 | $2,092 | $0 | $52,283 | $52,283 |
| (Pending) | Review and revise (as needed) the protective relay settings at the South Canton 345 kV substation. | $44,758 | $12,003 | $28,387 | $7,613 | $92,761 | $92,761 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Install 345 kV revenue metering within new interconnection substation. | $343,153 | $316,272 | $14,301 | $6,389 | $680,115 | $680,115 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Construct a new 345 kV 3-breaker ring bus interconnection substation. | $11,434,955 | $5,647,127 | $476,552 | $136,958 | $17,695,592 | $17,695,592 |
| (Pending) | Install/Test approximately 0.19 miles of new 48F/SM ADSS cable from AH1-680 substation control house to STR 420 on the existing Knox-Nottingham 138kV OPGW. Underground ADSS will be utilized for this entire run to Structure 420 on the Knox-Nottingham 138kV OPGW line. | $792,279 | $312,364 | $33,018 | $6,310 | $1,143,971 | $1,143,971 |
| (Pending) | Estimated (2) in-sub fiber builds for relaying protection from interconneciton substation control house to the Point of Change in Ownership. | $54,006 | $2,655 | $2,251 | $54 | $58,966 | $58,966 |
| (Pending) | Estimated design, installation, and testing/commissioning for MPLS equipment for SCADA transport at interconnection substation. | $613,735 | $23,137 | $25,577 | $467 | $662,916 | $662,916 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Integrate Interconnection Facilities protection and controls to the Transmission Owner system. | $49,161 | $0 | $2,049 | $0 | $51,210 | $51,210 |
| (Pending) | Install line terminal equipment within the AH1-680 Interconnection substation. Install one span from AH1-680 Interconnection Substation to the Project Developer-owned dead-end structure outside of FE substation fence. | $1,335,311 | $663,999 | $55,649 | $21,930 | $2,076,889 | $2,076,889 |
Developer Build Option
Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.
If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.
The cost estimates for eligible facilities and Option to Build oversight are highlighted below:
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Cut the existing 345kV line and Loop in the new interconnection substation. | $3,484,832 | $3,106,732 | $145,230 | $95,530 | $6,832,324 | $6,832,324 |
| (Pending) | Install (2) wave traps, (2) line tuner units , (4) carrier sets (radio transceivers/receiver units), (4) carrier monitors, (4) hybrids and update relay settings at Sammis Substation. | $651,977 | $192,766 | $27,171 | $3,894 | $875,808 | $875,808 |
| (Pending) | Review and update relay settings at Star substation. | $49,161 | $0 | $2,049 | $0 | $51,210 | $51,210 |
| (Pending) | Review and update relay settings at Wellsville substation. | $49,161 | $0 | $2,049 | $0 | $51,210 | $51,210 |
| (Pending) | Reveiw and update relay settings at Toronto substation. | $50,191 | $0 | $2,092 | $0 | $52,283 | $52,283 |
| (Pending) | Review and revise (as needed) the protective relay settings at the South Canton 345 kV substation. | $44,758 | $12,003 | $28,387 | $7,613 | $92,761 | $92,761 |
| Option to Build Oversight | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Transmission Owner oversight of developer design and construction of new interconnection substation. | $1,042,337 | $0 | $43,439 | $0 | $1,085,776 | $1,085,776 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Install 345 kV revenue metering within new interconnection substation. | $343,153 | $316,272 | $14,301 | $6,389 | $680,115 | $680,115 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Install/Test approximately 0.19 miles of new 48F/SM ADSS cable from AH1-680 substation control house to STR 420 on the existing Knox-Nottingham 138kV OPGW. Underground ADSS will be utilized for this entire run to Structure 420 on the Knox-Nottingham 138kV OPGW line. | $792,279 | $312,364 | $33,018 | $6,310 | $1,143,971 | $1,143,971 |
| (Pending) | Install (1) security system and camera system, (1) indoor security AC cabinet, (1) network fiber termination rack and program SCADA RTU. | $1,911,001 | $349,062 | $79,641 | $7,051 | $2,346,755 | $2,346,755 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Integrate Interconnection Facilities protection and controls to the Transmission Owner system. | $49,161 | $0 | $2,049 | $0 | $51,210 | $51,210 |
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $30,325,255 | $30,325,255 | |||||
| Developer Build Option | $13,263,423 | $13,263,423 | |||||
Based on the scope of work for the Interconnection Facilities, it is expected to take 60 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Remote end work required on a Facility owned by a PJM Transmission Owner other than the interconnected Transmission Owner:
Please note that your project interconnects directly to an ATSI (interconnected Transmission Owner) facility which shares a tie line with AEP Ohio Transmission Company Inc. The Transmission Owner Scope of Work above outlines the physical interconnection upgrades required on the ATSI facilities and the remote end work at the AEP Ohio Transmission Company Inc. facility (South Canton 345 kV) .
Transmission Owner Analysis
FE performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AH1-680 did not contribute to any overloads on the FE transmission <100 kV system.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-680 was evaluated as a 1300.0 MW (1300.0 MW Capacity) injection in the ATSI area.
AH1-680 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1300.0 MW (1300.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | DLCO | 15BI-15ARSENL 345.0 kV Ckt 1 line | DLC_P24_BI-2-3-345_SRT-A | Breaker | AC | 109.39 % | 523.0 | B | 572.12 | 33.03 | |
| GD2 | DLCO | 15BI-15ARSENL 345.0 kV Ckt 2 line | DLC_P24_BI-1-3-345_SRT-A | Breaker | AC | 125.71 % | 523.0 | B | 657.47 | 28.21 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P1-1_PN-230-018_SRT-A | Single | AC | 121.66 % | 128.0 | B | 155.73 | 6.66 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P1-1_PN-230-017_SRT-A | Single | AC | 121.66 % | 128.0 | B | 155.73 | 6.66 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P2-3_PN-115-84A1_SRT-A | Breaker | AC | 104.69 % | 128.0 | B | 134.0 | 7.97 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P2-3_PN-115-84D1_SRT-A | Breaker | AC | 104.69 % | 128.0 | B | 134.0 | 7.97 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P2-2_PN-345-1154-W_SRT-A | Bus | AC | 104.14 % | 128.0 | B | 133.29 | 7.47 |
Winter Peak Analysis
The New Service Request AH1-680 was evaluated as a 1300.0 MW (1300.0 MW Capacity) injection in the ATSI area.
AH1-680 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1300.0 MW (1300.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Analysis
The New Service Request AH1-680 was evaluated as a 1300.0 MW injection
AH1-680 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1300.0 MW (1300.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Short Circuit Analysis is complete and requires a cost allocation for this project. TC2 project AH1-680 is contributing to the overduty in 05TORREY1 138.kV, which exceeds the >1% threshold per PJM Manual 14H 4.2.3.1.
Below is the duty impact analysis.
Bus Name | Bus Number | Project ID | Breaker Overdutied | Breaker Capacity (Amps) | Duty Percent With TC2 (%) | Duty Amps With TC2 (Amps) | Full Amps Contribution (Amps) | Reinforcement ID | Reinforcement Project Description |
05TORREY1 138.kV | 243132 | AH1-680 | AF | 40000 | 107.01% | 42802.7 | 1363.7 | n9689.0 | Replace with a 138 kV 63 kA 3000A. |
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
- Steady-state operation (Category P0);
- Three-phase faults with normal clearing time (Category P1);
- Single-phase faults with stuck breaker (Category P4);
- Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
- Single-phase to ground faults with normal clearing for common structure (Category P7).
Multiple-circuit tower line faults were identified for this study.
High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 43 projects.
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For 53 out of 53 fault contingencies tested on the 2028 light load case:
- Cluster 43 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
- The system with Cluster 43 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
- Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
- No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
Table 1: TC2 Cluster 43 Projects |
|
|
|
|
|
|
|
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
43 | AH1-680 | Natural Gas | FirstEnergy (FE) transmission system, ATSI zone | 1300 MW | 1300 MW | 1300 MW | Sammis – South Canton 345 kV |
Reactive Power Analysis
The reactive power capability of AH1-680 meets the 0.9 lagging and 0.95 leading PF requirement at the generator terminals.
Steady-State Voltage Analysis
Not Required
A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AE2-125 | Stahlstown-Ligonier 25 kV | In Service |
| AF1-021 | Bethelboro-Connellsville #1 25 kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.
System Reinforcement
- Type
- Load Flow
- TO
- NYISO
- RTEP ID / TO ID
- (Pending) / NYISO_CY17_13387
- Title
- East Sayre-North Waverly 115kV line upgrade - NYSEG (NYISO CY17 driven upgrade)
- Description
- North Waverly terminal equipment upgrades and a line reconductor of the NYSEG portion of the East Sayre – North Waverly 115kV line. (Install approximately twenty-six (26) new steel pole structures, one (1) 795 kcmil (26/7) ACSR conductor, and 36 Fiber OPGW). Final expected SUM ratings with both NYSEG & Penelec work complete = 218/251 MVA SN/SE. NYSEG uses LTE for Rate B, not STE like FirstEnergy. The projected in-service date for this project is in late 2026, but that timeframe may shift to complete the terminal equipment work at North Waverly. The final trip setting for the line will be updated during engineering and construction, but it must meet at least 176 MVA. Note: NYISO customers Q387, Q421, Q505 require an upgrade on the East Sayre-North Waverly 115 kV line as part of the CY17 study. NYSEG will complete work at North Waverly substation and the line reconductor/rebuild. FirstEnergy will complete work at East Sayre substation. Per NYISO, the rating that must be achieved for CY17 is 176/176/176 MVA Summer Normal/LTE/STE. NYSEG confirmed the new line ratings for the NYISO side (218/251/282 MVA Summer Normal/LTE/STE; 265/291/318 MVA Winter Normal/LTE/STE), but the East Sayre terminal needs to be upgraded since it is limiting. NYSEG uses LTE for Rate B, not STE like FirstEnergy.
- Total Cost ($USD)
- $10,525,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 32 Months
Info Note: AH1-680 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.
| Facility | Contingency | |
|---|---|---|
| N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | (Any) |
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| AEP | n9689.0 | Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A | Cost Allocated | $1,000,000 | N/A |
| PENELEC | n8471 | East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade) | Contingent | $0 | N/A |
| Grand Total: | $1,000,000 | ||||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n9689.0
- Type
- Short Circuit
- TO
- AEP
- RTEP ID / TO ID
- n9689.0
- Title
- Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A
- Description
- Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A
- Total Cost ($USD)
- $1,000,000
- Discounted Total Cost ($USD)
- $1,000,000
- Allocated Cost ($USD)
- $1,000,000
- Time Estimate
- Jun 01 2028
Contributor
| Project | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|
| AH1-680 | 100.00% | $1,000,000 |
System Reinforcement
- Type
- Load Flow
- TO
- DL
- RTEP ID / TO ID
- (Pending)
- Title
- A forced cooling system is installed on the DLC underground Arsenal-Brunot Island 345 kV circuits 305 & 306 (PSSE Bus Nos. 253975-253999 Ckt. 1&2)
- Description
- A forced cooling system is installed on the DLC underground Arsenal-Brunot Island 345 kV circuits 305 & 306 (PSSE Bus Nos. 253975-253999 Ckt. 1&2). For contingencies involving one of the parallel circuits, the emergency rating of the remaining circuit can be increased to 837 MVA.
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- TBD
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 15BI-15ARSENL 345.0 kV Ckt 2 line | DLC_P24_BI-1-3-345_SRT-A |
| |||||||
| 15BI-15ARSENL 345.0 kV Ckt 1 line | DLC_P24_BI-2-3-345_SRT-A |
|
System Reinforcement: n8471
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n8471
- Title
- East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade)
- Description
- East Sayre Substation: Replace one (1) 115 kV circuit breaker on North Waverly (NYSEG) terminal at East Sayre. Revise wiring for the North Waverly 115kV PR and BU line protection relays to utilize the redundant CT’s and trip coils on the new breaker. East Sayre – North Waverly 115kV line: Replace 3 pole wood Structure 141 due to NYSEG reconductor of East Sayre-North Waverly 115kV line. Enable load encroachment such that all protection elements will achieve the required loadability of 221/263/263/301 MVA (SN/SE/WN/WE) Note: NYISO customers Q387, Q421, Q505 require an upgrade on the East Sayre-North Waverly 115 kV line as part of the CY17 study. NYSEG will complete work at North Waverly substation and the line reconductor/rebuild. FirstEnergy will complete work at East Sayre substation. Per NYISO, the rating that must be achieved for CY17 is 176/176/176 MVA Summer Normal/LTE/STE. NYSEG confirmed the new line ratings for the NYISO side (218/251/282 MVA Summer Normal/LTE/STE; 265/291/318 MVA Winter Normal/LTE/STE), but the East Sayre terminal is still limiting. Once the scope of work and ratings at East Sayre are finalized, the expected line ratings will be updated. NYSEG uses LTE for Rate B, not STE like FirstEnergy.
- Total Cost ($USD)
- $1,417,388
- Discounted Total Cost ($USD)
- $1,417,388
- Allocated Cost ($USD)
- $0
- Time Estimate
- Nov 01 2027
Contingent Note: Based on PJM cost allocation criteria, AH1-680 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-680 could receive cost allocation. Although AH1-680 may not presently have cost responsibility for this upgrade, AH1-680 may need this upgrade in-service to be deliverable to the PJM system. If AH1-680 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | (Any) |
|