AH1-680 Phase II System Impact Study Report

v1.00 released 2026-06-04 08:30

Sammis - South Canton 345 kV

1300.0 MW Capacity / 1300.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Chestnut Run Energy LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $28,517,041 $27,079,653 = 1.05 AND ( $28,517,041 - $27,079,653 ) 1300.0 = $1,106 per MW

General

The Project Developer has proposed a Natural Gas generating facility located in the American Transmission Systems, Incorporated zone — Carroll County, Ohio. The installed facilities will have a total capability of 1300.0 MW with 1300.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-680
Project Name:
Sammis - South Canton 345 kV
Project Developer Name:
Chestnut Run Energy LLC
State:
Ohio
County:
Carroll
Transmission Owner:
American Transmission Systems, Incorporated
MFO:
1300.0
MWE:
1300.0
MWC:
1300.0
Fuel Type:
Natural Gas
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AH1-680 will interconnect on the American Transmission Systems, Incorporated  transmission system by tapping the Sammis - South Canton 345 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-680 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-680Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$2,128,099$0$0
Other Scope$680,115$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$19,561,445$19,561,445$19,561,445
Network Upgrades$7,955,596$7,955,596$7,955,596
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$1,000,000$1,000,000$1,000,000
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$0$0$0
Total$31,325,255$28,517,041$28,517,041

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AH1-680

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AH1-680
Project ID: AH1-680
20% of cost allocation for Phase II Network Upgrades:(A) $5,703,408
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $5,200,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $503,408
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Cut the existing 345kV line and Loop in the new interconnection substation.

$3,484,832$3,106,732$145,230$95,530$6,832,324$6,832,324
(Pending)

Install (2) wave traps, (2) line tuner units , (4) carrier sets (radio transceivers/receiver units), (4) carrier monitors, (4) hybrids and update relay settings at Sammis Substation.

$651,977$192,766$27,171$3,894$875,808$875,808
(Pending)

Review and update relay settings at Star substation.

$49,161$0$2,049$0$51,210$51,210
(Pending)

Review and update relay settings at Wellsville substation.

$49,161$0$2,049$0$51,210$51,210
(Pending)

Reveiw and update relay settings at Toronto substation.

$50,191$0$2,092$0$52,283$52,283
(Pending)

Review and revise (as needed) the protective relay settings at the South Canton 345 kV substation.

$44,758$12,003$28,387$7,613$92,761$92,761
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install 345 kV revenue metering within new interconnection substation.

$343,153$316,272$14,301$6,389$680,115$680,115
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Construct a new 345 kV 3-breaker ring bus interconnection substation.

$11,434,955$5,647,127$476,552$136,958$17,695,592$17,695,592
(Pending)

Install/Test approximately 0.19 miles of new 48F/SM ADSS cable from AH1-680 substation control house to STR 420 on the existing Knox-Nottingham 138kV OPGW. Underground ADSS will be utilized for this entire run to Structure 420 on the Knox-Nottingham 138kV OPGW line.

$792,279$312,364$33,018$6,310$1,143,971$1,143,971
(Pending)

Estimated (2) in-sub fiber builds for relaying protection from interconneciton substation control house to the Point of Change in Ownership.

$54,006$2,655$2,251$54$58,966$58,966
(Pending)

Estimated design, installation, and testing/commissioning for MPLS equipment for SCADA transport at interconnection substation.

$613,735$23,137$25,577$467$662,916$662,916
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Integrate Interconnection Facilities protection and controls to the Transmission Owner system.

$49,161$0$2,049$0$51,210$51,210
(Pending)

Install line terminal equipment within the AH1-680 Interconnection substation. Install one span from AH1-680 Interconnection Substation to the Project Developer-owned dead-end structure outside of FE substation fence.

$1,335,311$663,999$55,649$21,930$2,076,889$2,076,889
Developer Build Option

Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.

If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Cut the existing 345kV line and Loop in the new interconnection substation.

$3,484,832$3,106,732$145,230$95,530$6,832,324$6,832,324
(Pending)

Install (2) wave traps, (2) line tuner units , (4) carrier sets (radio transceivers/receiver units), (4) carrier monitors, (4) hybrids and update relay settings at Sammis Substation.

$651,977$192,766$27,171$3,894$875,808$875,808
(Pending)

Review and update relay settings at Star substation.

$49,161$0$2,049$0$51,210$51,210
(Pending)

Review and update relay settings at Wellsville substation.

$49,161$0$2,049$0$51,210$51,210
(Pending)

Reveiw and update relay settings at Toronto substation.

$50,191$0$2,092$0$52,283$52,283
(Pending)

Review and revise (as needed) the protective relay settings at the South Canton 345 kV substation.

$44,758$12,003$28,387$7,613$92,761$92,761
Option to Build Oversight
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Transmission Owner oversight of developer design and construction of new interconnection substation.

$1,042,337$0$43,439$0$1,085,776$1,085,776
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install 345 kV revenue metering within new interconnection substation.

$343,153$316,272$14,301$6,389$680,115$680,115
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install/Test approximately 0.19 miles of new 48F/SM ADSS cable from AH1-680 substation control house to STR 420 on the existing Knox-Nottingham 138kV OPGW. Underground ADSS will be utilized for this entire run to Structure 420 on the Knox-Nottingham 138kV OPGW line.

$792,279$312,364$33,018$6,310$1,143,971$1,143,971
(Pending)

Install (1) security system and camera system, (1) indoor security AC cabinet, (1) network fiber termination rack and program SCADA RTU.

$1,911,001$349,062$79,641$7,051$2,346,755$2,346,755
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Integrate Interconnection Facilities protection and controls to the Transmission Owner system.

$49,161$0$2,049$0$51,210$51,210
Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$30,325,255$30,325,255
Developer Build Option$13,263,423$13,263,423

Based on the scope of work for the Interconnection Facilities, it is expected to take 60 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Remote end work required on a Facility owned by a PJM Transmission Owner other than the interconnected Transmission Owner:

 

Please note that your project interconnects directly to an ATSI (interconnected Transmission Owner) facility which shares a tie line with  AEP Ohio Transmission Company Inc. The Transmission Owner Scope of Work above outlines the physical interconnection upgrades required on the ATSI facilities and the remote end work at the AEP Ohio Transmission Company Inc. facility (South Canton 345 kV) . 

Transmission Owner Analysis

FE performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AH1-680 did not contribute to any overloads on the FE transmission <100 kV system.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-680 was evaluated as a 1300.0 MW (1300.0 MW Capacity) injection in the ATSI area.

AH1-680 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1300.0 MW (1300.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2DLCO
15BI-15ARSENL 345.0 kV Ckt 1 line
DLC_P24_BI-2-3-345_SRT-A
BreakerAC109.39 %523.0B572.12
33.03
GD2DLCO
15BI-15ARSENL 345.0 kV Ckt 2 line
DLC_P24_BI-1-3-345_SRT-A
BreakerAC125.71 %523.0B657.47
28.21

Details for 15BI-15ARSENL 345.0 kV Ckt 1 line l/o DLC_P24_BI-2-3-345_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:DLCO
Facility Description:
15BI-15ARSENL 345.0 kV Ckt 1 line
Contingency Name:
DLC_P24_BI-2-3-345_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:109.39 %
Rating:523.0 MVA
Rating Type:B
MVA to Mitigate:572.12
MW Contribution:
33.03
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:DLCO
Facility Description:
15BI-15ARSENL 345.0 kV Ckt 1 line
Contingency Name:
DLC_P24_BI-2-3-345_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:117.56 %
Rating:523.0 MVA
Rating Type:B
MVA to Mitigate:614.83
MW Contribution:
33.65
Bus #Bus NameTypeMW Contribution
237043AE2-125 C
Solar/Wind Helper
0.081
972191AH1-680 GEN
Adder
33.03
NYPJM->LTFIMP_NY
CLTF
0.539
LGEELTFEXP_LGEE->PJM
CLTF
0.308
WECLTFEXP_WEC->PJM
CLTF
0.209
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.004
LAGNLTFEXP_LAGN->PJM
CLTF
0.64
CBM West 1LTFEXP_CBM-W1->PJM
CBM
9.655
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.255
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.218
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.117
TVALTFEXP_TVA->PJM
CLTF
0.297
MECLTFEXP_MEC->PJM
CLTF
0.828
SIGELTFEXP_SIGE->PJM
CLTF
0.024

Details for 15BI-15ARSENL 345.0 kV Ckt 2 line l/o DLC_P24_BI-1-3-345_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:DLCO
Facility Description:
15BI-15ARSENL 345.0 kV Ckt 2 line
Contingency Name:
DLC_P24_BI-1-3-345_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:125.71 %
Rating:523.0 MVA
Rating Type:B
MVA to Mitigate:657.47
MW Contribution:
28.21
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:DLCO
Facility Description:
15BI-15ARSENL 345.0 kV Ckt 2 line
Contingency Name:
DLC_P24_BI-1-3-345_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:137.61 %
Rating:523.0 MVA
Rating Type:B
MVA to Mitigate:719.7
MW Contribution:
29.2
Bus #Bus NameTypeMW Contribution
23652301WDPWR_K20
Solar/Wind Helper
0.068
237043AE2-125 C
Solar/Wind Helper
0.095
237046AF1-021 C
Solar/Wind Helper
0.141
972191AH1-680 GEN
Adder
28.212
NYPJM->LTFIMP_NY
CLTF
0.739
LGEELTFEXP_LGEE->PJM
CLTF
0.497
WECLTFEXP_WEC->PJM
CLTF
0.305
CPLELTFEXP_CPLE->PJM
CLTF
0.113
LAGNLTFEXP_LAGN->PJM
CLTF
1.109
CBM West 1LTFEXP_CBM-W1->PJM
CBM
12.601
CBM West 2LTFEXP_CBM-W2->PJM
CBM
8.541
CBM South 1LTFEXP_CBM-S1->PJM
CBM
2.128
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.64
TVALTFEXP_TVA->PJM
CLTF
0.532
MECLTFEXP_MEC->PJM
CLTF
1.246
SIGELTFEXP_SIGE->PJM
CLTF
0.038
CONTINGENCY 'DLC_P24_BI-2-3-345_SRT-A'
 OPEN BRANCH FROM BUS 253965 TO BUS 253975 CKT 1   /*15COLLIE     345.0 - 15BI         345.0
 OPEN BRANCH FROM BUS 253975 TO BUS 253990 CKT 1   /*15BI         345.0 - 15CARSON     345.0
 OPEN BRANCH FROM BUS 253975 TO BUS 253999 CKT 2   /*15BI         345.0 - 15ARSENL     345.0
 OPEN BUS 253992                                   /*15CARSNR     345.0
END
CONTINGENCY 'DLC_P24_BI-1-3-345_SRT-A'
 OPEN BRANCH FROM BUS 253963 TO BUS 253975 CKT 1   /*15COLLRT     345.0 - 15BI         345.0
 OPEN BRANCH FROM BUS 253975 TO BUS 253976 CKT 1   /*15BI         345.0 - 15BI_12      138.0
 OPEN BRANCH FROM BUS 253975 TO BUS 253990 CKT 1   /*15BI         345.0 - 15CARSON     345.0
 OPEN BRANCH FROM BUS 253975 TO BUS 253999 CKT 1   /*15BI         345.0 - 15ARSENL     345.0
 OPEN BUS 253992                                   /*15CARSNR     345.0
END
253975 to 253999 ckt 1
253975 to 253999 ckt 2

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2NYISO/PENELEC
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
PN_P1-1_PN-230-018_SRT-A
SingleAC121.66 %128.0B155.73
6.66
GD2NYISO/PENELEC
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
PN_P1-1_PN-230-017_SRT-A
SingleAC121.66 %128.0B155.73
6.66
GD2NYISO/PENELEC
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
PN_P2-3_PN-115-84A1_SRT-A
BreakerAC104.69 %128.0B134.0
7.97
GD2NYISO/PENELEC
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
PN_P2-3_PN-115-84D1_SRT-A
BreakerAC104.69 %128.0B134.0
7.97
GD2NYISO/PENELEC
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
PN_P2-2_PN-345-1154-W_SRT-A
BusAC104.14 %128.0B133.29
7.47

Details for N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line l/o PN_P1-1_PN-230-018_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:NYISO/PENELEC
Facility Description:
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
Contingency Name:
PN_P1-1_PN-230-018_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:121.66 %
Rating:128.0 MVA
Rating Type:B
MVA to Mitigate:155.73
MW Contribution:
6.66
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20083726HOMER C1
Adder
9.087
20083826HOMER C2
Adder
14.498
20083926HOMER C3
Adder
15.349
203859AF2-294 C
Solar/Wind Harmer
0.513
970935AG2-582 GEN
Adder
6.784
200917MEHOOPANY_G
Solar/Wind Helper
1.991
941421AE2-139 GEN
Solar/Wind Helper
2.971
972191AH1-680 GEN
Adder
6.656
LGEELTFEXP_LGEE->PJM
CLTF
0.234
WECLTFEXP_WEC->PJM
CLTF
0.134
CPLELTFEXP_CPLE->PJM
CLTF
0.233
LAGNLTFEXP_LAGN->PJM
CLTF
0.624
CBM NorthLTFEXP_CBM-N->PJM
CBM
17.816
CBM West 1LTFEXP_CBM-W1->PJM
CBM
5.356
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.354
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.182
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.727
TVALTFEXP_TVA->PJM
CLTF
0.309
MECLTFEXP_MEC->PJM
CLTF
0.575
SIGELTFEXP_SIGE->PJM
CLTF
0.018

Details for N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line l/o PN_P1-1_PN-230-017_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:NYISO/PENELEC
Facility Description:
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
Contingency Name:
PN_P1-1_PN-230-017_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:121.66 %
Rating:128.0 MVA
Rating Type:B
MVA to Mitigate:155.73
MW Contribution:
6.66
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20083726HOMER C1
Adder
9.087
20083826HOMER C2
Adder
14.498
20083926HOMER C3
Adder
15.349
203859AF2-294 C
Solar/Wind Harmer
0.513
970935AG2-582 GEN
Adder
6.784
200917MEHOOPANY_G
Solar/Wind Helper
1.991
941421AE2-139 GEN
Solar/Wind Helper
2.971
972191AH1-680 GEN
Adder
6.656
LGEELTFEXP_LGEE->PJM
CLTF
0.234
WECLTFEXP_WEC->PJM
CLTF
0.134
CPLELTFEXP_CPLE->PJM
CLTF
0.233
LAGNLTFEXP_LAGN->PJM
CLTF
0.624
CBM NorthLTFEXP_CBM-N->PJM
CBM
17.816
CBM West 1LTFEXP_CBM-W1->PJM
CBM
5.356
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.354
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.182
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.727
TVALTFEXP_TVA->PJM
CLTF
0.309
MECLTFEXP_MEC->PJM
CLTF
0.575
SIGELTFEXP_SIGE->PJM
CLTF
0.018

Details for N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line l/o PN_P2-3_PN-115-84A1_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:NYISO/PENELEC
Facility Description:
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
Contingency Name:
PN_P2-3_PN-115-84A1_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:104.69 %
Rating:128.0 MVA
Rating Type:B
MVA to Mitigate:134.0
MW Contribution:
7.97
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20083726HOMER C1
Adder
11.181
20083826HOMER C2
Adder
17.856
20083926HOMER C3
Adder
18.903
203859AF2-294 C
Solar/Wind Harmer
0.75
970935AG2-582 GEN
Adder
8.182
200917MEHOOPANY_G
Solar/Wind Helper
2.406
20398826ARMNA MT
Solar/Wind Helper
2.272
941421AE2-139 GEN
Solar/Wind Helper
3.566
972191AH1-680 GEN
Adder
7.967
LGEELTFEXP_LGEE->PJM
CLTF
0.281
WECLTFEXP_WEC->PJM
CLTF
0.161
CPLELTFEXP_CPLE->PJM
CLTF
0.281
LAGNLTFEXP_LAGN->PJM
CLTF
0.749
CBM NorthLTFEXP_CBM-N->PJM
CBM
19.554
CBM West 1LTFEXP_CBM-W1->PJM
CBM
6.415
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.226
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.419
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.875
TVALTFEXP_TVA->PJM
CLTF
0.371
MECLTFEXP_MEC->PJM
CLTF
0.689
SIGELTFEXP_SIGE->PJM
CLTF
0.021

Details for N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line l/o PN_P2-3_PN-115-84D1_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:NYISO/PENELEC
Facility Description:
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
Contingency Name:
PN_P2-3_PN-115-84D1_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:104.69 %
Rating:128.0 MVA
Rating Type:B
MVA to Mitigate:134.0
MW Contribution:
7.97
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20083726HOMER C1
Adder
11.181
20083826HOMER C2
Adder
17.856
20083926HOMER C3
Adder
18.903
203859AF2-294 C
Solar/Wind Harmer
0.75
970935AG2-582 GEN
Adder
8.182
200917MEHOOPANY_G
Solar/Wind Helper
2.406
20398826ARMNA MT
Solar/Wind Helper
2.272
941421AE2-139 GEN
Solar/Wind Helper
3.566
972191AH1-680 GEN
Adder
7.967
LGEELTFEXP_LGEE->PJM
CLTF
0.281
WECLTFEXP_WEC->PJM
CLTF
0.161
CPLELTFEXP_CPLE->PJM
CLTF
0.281
LAGNLTFEXP_LAGN->PJM
CLTF
0.749
CBM NorthLTFEXP_CBM-N->PJM
CBM
19.554
CBM West 1LTFEXP_CBM-W1->PJM
CBM
6.415
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.226
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.419
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.875
TVALTFEXP_TVA->PJM
CLTF
0.371
MECLTFEXP_MEC->PJM
CLTF
0.689
SIGELTFEXP_SIGE->PJM
CLTF
0.021

Details for N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line l/o PN_P2-2_PN-345-1154-W_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:NYISO/PENELEC
Facility Description:
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line
Contingency Name:
PN_P2-2_PN-345-1154-W_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:104.14 %
Rating:128.0 MVA
Rating Type:B
MVA to Mitigate:133.29
MW Contribution:
7.47
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20083726HOMER C1
Adder
10.621
20083826HOMER C2
Adder
17.014
20083926HOMER C3
Adder
18.011
203859AF2-294 C
Solar/Wind Harmer
0.816
970935AG2-582 GEN
Adder
7.698
200917MEHOOPANY_G
Solar/Wind Helper
2.229
20398826ARMNA MT
Solar/Wind Helper
1.624
941421AE2-139 GEN
Solar/Wind Helper
3.345
972191AH1-680 GEN
Adder
7.471
LGEELTFEXP_LGEE->PJM
CLTF
0.264
WECLTFEXP_WEC->PJM
CLTF
0.151
CPLELTFEXP_CPLE->PJM
CLTF
0.265
LAGNLTFEXP_LAGN->PJM
CLTF
0.704
CBM NorthLTFEXP_CBM-N->PJM
CBM
19.942
CBM West 1LTFEXP_CBM-W1->PJM
CBM
6.02
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.908
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.333
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.823
TVALTFEXP_TVA->PJM
CLTF
0.349
MECLTFEXP_MEC->PJM
CLTF
0.647
SIGELTFEXP_SIGE->PJM
CLTF
0.02
CONTINGENCY 'PN_P1-1_PN-230-018_SRT-A'
 REMOVE MACHINE 1 FROM BUS 203923   /*AA1-082 G2    23.0
END
CONTINGENCY 'PN_P1-1_PN-230-017_SRT-A'
 REMOVE MACHINE 1 FROM BUS 203922   /*AA1-082 G1    23.0
END
CONTINGENCY 'PN_P2-3_PN-115-84A1_SRT-A'
 DISCONNECT BRANCH FROM BUS 200929 TO BUS 200672 CKT 1   /*26MAINESBURG 115.0 - 26MANSFIEL   115.0
 DISCONNECT BRANCH FROM BUS 200930 TO BUS 200929 CKT 1   /*26MAINESBURG 345.0 - 26MAINESBURG 115.0
END
CONTINGENCY 'PN_P2-3_PN-115-84D1_SRT-A'
 DISCONNECT BRANCH FROM BUS 200929 TO BUS 200885 CKT 1   /*26MAINESBURG 115.0 - 26EVERT DR   115.0
 DISCONNECT BRANCH FROM BUS 200930 TO BUS 200929 CKT 1   /*26MAINESBURG 345.0 - 26MAINESBURG 115.0
END
CONTINGENCY 'PN_P2-2_PN-345-1154-W_SRT-A'
 DISCONNECT BRANCH FROM BUS 200930 TO BUS 200929 CKT 1   /*26MAINESBURG 345.0 - 26MAINESBURG 115.0
 REMOVE SWSHUNT FROM BUS 200930 BLOCK 1 STEP 1           /*26MAINESBURG 345.0
 REMOVE SWSHUNT FROM BUS 200930 BLOCK 2 STEP 1           /*26MAINESBURG 345.0
END
130836 to 200676 ckt 1

Winter Peak Analysis

The New Service Request AH1-680 was evaluated as a 1300.0 MW (1300.0 MW Capacity) injection in the ATSI area.

AH1-680 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1300.0 MW (1300.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-680 was evaluated as a 1300.0 MW injection

AH1-680 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1300.0 MW (1300.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Short Circuit Analysis is complete and requires a cost allocation for this project. TC2 project AH1-680 is contributing to the overduty in 05TORREY1 138.kV, which exceeds the >1% threshold per PJM Manual 14H 4.2.3.1.

Below is the duty impact analysis.

Bus Name

Bus Number

Project ID

Breaker Overdutied

Breaker Capacity (Amps)

Duty Percent With TC2 (%)

Duty Amps With TC2 (Amps)

Full Amps Contribution (Amps)

Reinforcement ID

Reinforcement Project Description

05TORREY1 138.kV

243132

AH1-680

AF

40000

107.01%

42802.7

1363.7

n9689.0

Replace with a 138 kV 63 kA 3000A.

 

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

 

 

 

 

Stability Analysis

Analysis Complete - No Issues

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 43 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 43 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 43 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the 2028 light load case, modified to include applicable projects. Cluster 43 projects have been dispatched online at maximum power output, with approximately unity power factors at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

Cluster 43 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 53 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
  5. Single-phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 43 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For 53 out of 53 fault contingencies tested on the 2028 light load case:

  1. Cluster 43 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 43 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

 

Table 1: TC2 Cluster 43 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

43

AH1-680

Natural Gas

FirstEnergy (FE) transmission system,

ATSI zone

1300 MW

1300 MW

1300 MW

Sammis – South Canton 345 kV

 

Reactive Power Analysis

 The reactive power capability of AH1-680 meets the 0.9 lagging and 0.95 leading PF requirement at the generator terminals.

Steady-State Voltage Analysis

Not Required

A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AE2-125Stahlstown-Ligonier 25 kVIn Service
AF1-021Bethelboro-Connellsville #1 25 kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)Identified Impacts

No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.


System Reinforcement
Type
Load Flow
TO
NYISO
RTEP ID / TO ID
(Pending) / NYISO_CY17_13387
Title
East Sayre-North Waverly 115kV line upgrade - NYSEG (NYISO CY17 driven upgrade)
Description
North Waverly terminal equipment upgrades and a line reconductor of the NYSEG portion of the East Sayre – North Waverly 115kV line. (Install approximately twenty-six (26) new steel pole structures, one (1) 795 kcmil (26/7) ACSR conductor, and 36 Fiber OPGW). Final expected SUM ratings with both NYSEG & Penelec work complete = 218/251 MVA SN/SE. NYSEG uses LTE for Rate B, not STE like FirstEnergy. The projected in-service date for this project is in late 2026, but that timeframe may shift to complete the terminal equipment work at North Waverly. The final trip setting for the line will be updated during engineering and construction, but it must meet at least 176 MVA. Note: NYISO customers Q387, Q421, Q505 require an upgrade on the East Sayre-North Waverly 115 kV line as part of the CY17 study. NYSEG will complete work at North Waverly substation and the line reconductor/rebuild. FirstEnergy will complete work at East Sayre substation. Per NYISO, the rating that must be achieved for CY17 is 176/176/176 MVA Summer Normal/LTE/STE. NYSEG confirmed the new line ratings for the NYISO side (218/251/282 MVA Summer Normal/LTE/STE; 265/291/318 MVA Winter Normal/LTE/STE), but the East Sayre terminal needs to be upgraded since it is limiting. NYSEG uses LTE for Rate B, not STE like FirstEnergy.
Total Cost ($USD)
$10,525,000
Allocated Cost ($USD)
$0
Time Estimate
32 Months

Info

Note: AH1-680 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.

FacilityContingency
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line(Any)

Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AH1-680 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
AEPn9689.0Replace 05TORREY1 breaker with a 138 kV 63 kA 3000ACost Allocated$1,000,000N/A
PENELECn8471East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade)Contingent$0N/A
Grand Total:$1,000,000

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9689.0
Type
Short Circuit
TO
AEP
RTEP ID / TO ID
n9689.0
Title
Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A
Description
Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A
Total Cost ($USD)
$1,000,000
Discounted Total Cost ($USD)
$1,000,000
Allocated Cost ($USD)
$1,000,000
Time Estimate
Jun 01 2028

Contributor

Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AH1-680100.00%$1,000,000

System Reinforcement
Type
Load Flow
TO
DL
RTEP ID / TO ID
(Pending)
Title
A forced cooling system is installed on the DLC underground Arsenal-Brunot Island 345 kV circuits 305 & 306 (PSSE Bus Nos. 253975-253999 Ckt. 1&2)
Description
A forced cooling system is installed on the DLC underground Arsenal-Brunot Island 345 kV circuits 305 & 306 (PSSE Bus Nos. 253975-253999 Ckt. 1&2). For contingencies involving one of the parallel circuits, the emergency rating of the remaining circuit can be increased to 837 MVA.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
15BI-15ARSENL 345.0 kV Ckt 2 lineDLC_P24_BI-1-3-345_SRT-A
Rating SetRating TypeRating Value
(All)B837.0 MVA
15BI-15ARSENL 345.0 kV Ckt 1 lineDLC_P24_BI-2-3-345_SRT-A
Rating SetRating TypeRating Value
(All)B837.0 MVA

System Reinforcement: n8471
Type
Load Flow
TO
PENELEC
RTEP ID / TO ID
n8471
Title
East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade)
Description
East Sayre Substation: Replace one (1) 115 kV circuit breaker on North Waverly (NYSEG) terminal at East Sayre. Revise wiring for the North Waverly 115kV PR and BU line protection relays to utilize the redundant CT’s and trip coils on the new breaker. East Sayre – North Waverly 115kV line: Replace 3 pole wood Structure 141 due to NYSEG reconductor of East Sayre-North Waverly 115kV line. Enable load encroachment such that all protection elements will achieve the required loadability of 221/263/263/301 MVA (SN/SE/WN/WE) Note: NYISO customers Q387, Q421, Q505 require an upgrade on the East Sayre-North Waverly 115 kV line as part of the CY17 study. NYSEG will complete work at North Waverly substation and the line reconductor/rebuild. FirstEnergy will complete work at East Sayre substation. Per NYISO, the rating that must be achieved for CY17 is 176/176/176 MVA Summer Normal/LTE/STE. NYSEG confirmed the new line ratings for the NYISO side (218/251/282 MVA Summer Normal/LTE/STE; 265/291/318 MVA Winter Normal/LTE/STE), but the East Sayre terminal is still limiting. Once the scope of work and ratings at East Sayre are finalized, the expected line ratings will be updated. NYSEG uses LTE for Rate B, not STE like FirstEnergy.
Total Cost ($USD)
$1,417,388
Discounted Total Cost ($USD)
$1,417,388
Allocated Cost ($USD)
$0
Time Estimate
Nov 01 2027

Contingent

Note: Based on PJM cost allocation criteria, AH1-680 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-680 could receive cost allocation. Although AH1-680 may not presently have cost responsibility for this upgrade, AH1-680 may need this upgrade in-service to be deliverable to the PJM system. If AH1-680 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A218.0 MVA
(All)B251.0 MVA
(All)C276.0 MVA
WINA263.0 MVA
WINB291.0 MVA
WINC312.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-680


AH1-680 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-680 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-680 One Line Diagram

AH1-680 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.