AH1-699 Phase II System Impact Study Report

v1.00 released 2026-06-03 18:23

Wellsville 345 kV

69.0 MW Capacity / 58.0 MW Energy

Introduction

AH1-699 meets the criteria for acceleration at Decision Point II (DP2) .

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is South Field Energy LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Final Agreement Requirements

This New Service Request meets the criteria for acceleration at Decision Point II (DP2).

Please note that additional requirements apply to accelerated projects at DP2 per PJM Tariff Part VII, Subpart D, section 311. Failure to meet the requirements by the close of DP2 will result in withdrawal.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $143,106 $49,000 = 2.92 AND ( $143,106 - $49,000 ) 69.0 = $1,364 per MW

General

The Project Developer has proposed an uprate to a planned/existing Natural Gas facility located in the American Transmission Systems, Incorporated zone — Columbiana County, Ohio. This project is an increase to the developer’s AA1-123 project(s), which will share the same Point of Interconnection. The AH1-699 project is a 58.0 MW uprate (69.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 1210.0 MW with 1174.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-699
Project Name:
Wellsville 345 kV
Project Developer Name:
South Field Energy LLC
State:
Ohio
County:
Columbiana
Transmission Owner:
American Transmission Systems, Incorporated
MFO:
1210.0
MWE:
58.0
MWC:
69.0
Fuel Type:
Natural Gas
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AH1-699 will interconnect on the American Transmission Systems, Incorporated transmission system at the Wellsville 345 kV substation as an uprate to AA1-123. 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-699 project has the following allocation of costs for interconnection.

Cost Summary
DescriptionCost Allocated to AH1-699Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$57,092$57,092
Other Scope$4,971$4,971
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$143,106$143,106
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0
AFS - Non-PJM Violations$0$0
Total$205,169$205,169
Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Security Requirement

A summary of this New Service Requests costs are summarized in the Cost Summary section, herein. Final security will be shown in the Generation Interconnection Agreement (GIA).

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9693.0

Revise relay settings at Wellsville substation as required.

$45,792$0$1,910$0$47,702$47,702
n9703.0

Revise relay settings at Lordstown substation as required.

$45,792$0$1,910$0$47,702$47,702
n9704.0

Revise relay settings at Sammis substation as required.

$45,792$0$1,910$0$47,702$47,702
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Support for existing revenue metering coordination.

$3,653$0$1,318$0$4,971$4,971
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Integrate Interconnection Facilities protection and controls to the Transmission Owner system.

$54,596$0$2,496$0$57,092$57,092
Developer Build Option

(No Developer Build Option for this project.)

Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$205,169$205,169
Developer Build Option(No Developer Build Option)

Based on the scope of work for the Interconnection Facilities, it is expected to take 9 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Transmission Owner Analysis

FE performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AH1-699 did not contribute to any overloads on the FE transmission <100 kV system.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-699 was evaluated as a 58.0 MW (69.0 MW Capacity) injection in the ATSI area.

AH1-699 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1210.0 MW (58.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AP
01HARRSN-01PRNTY 500.0 kV Ckt 1 line
AP_P2-3_WP-500-DRT6_SRT-SL
BreakerAC104.91 %3792.0B3978.38
6.97
GD2AP
01HARRSN-01PRNTY 500.0 kV Ckt 1 line
AP_P2-3_WP-500-DRT9_SRT-SL
BreakerAC104.68 %3792.0B3969.31
7.02
GD2AP
01HARRSN-01PRNTY 500.0 kV Ckt 1 line
AP_P1-2_MP-500-022_SRT-A
SingleAC104.34 %3792.0B3956.52
6.97

Details for 01HARRSN-01PRNTY 500.0 kV Ckt 1 line l/o AP_P2-3_WP-500-DRT6_SRT-SL


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AP
Facility Description:
01HARRSN-01PRNTY 500.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_WP-500-DRT6_SRT-SL
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:104.91 %
Rating:3792.0 MVA
Rating Type:B
MVA to Mitigate:3978.38
MW Contribution:
6.97
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
23546401DTGZ2-030
Solar/Wind Helper
0.09
23585401KL_K28_T16
Solar/Wind Helper
1.429
23750701CROSSCHOOL
Solar/Wind Helper
1.321
23751201ROTHROCK
Solar/Wind Helper
0.827
23562501BACKB
Solar/Wind Helper
1.011
23777901MDS_W4-102
Solar/Wind Helper
0.149
23908902SAMMG5
Adder
20.994
23909002SAMMG6
Adder
26.243
23909102SAMMG7
Adder
26.243
3141426STAFORD
Solar/Wind Helper
0.05
235020AA1-095 C
Solar/Wind Helper
0.045
23558501HARRN1
50/50
18.426
23558601HARRN2
50/50
18.426
23558701HARRN3
50/50
18.426
23559001PLEAS1
50/50
7.032
23559101PLEAS2
50/50
7.032
23684101S70BUS1
50/50
0.191
23684201S70BUS2
50/50
0.195
237038AE2-054 C
Solar/Wind Helper
0.226
3141196NOKESVL
Solar/Wind Helper
0.972
316411AF1-147_GEN1
Solar/Wind Helper
0.818
316415AF1-147_GEN2
Solar/Wind Helper
0.818
23751101LEADS_P59
Solar/Wind Helper
2.386
235062AE1-101 C1
Solar/Wind Helper
1.369
3132123MT JACKSON
Solar/Wind Helper
0.75
3132273ORANGE
Solar/Wind Helper
0.045
238185AF2-356 C
Solar/Wind Helper
2.426
237080AD1-060 GEN
Solar/Wind Helper
0.285
235067AD1-061 GEN
Solar/Wind Helper
0.37
237001AB1-127_GEN
Solar/Wind Helper
0.364
237002AB1-128_GEN
Solar/Wind Helper
0.366
238175AF1-290_GEN
Solar/Wind Helper
0.141
238221AF1-254 C O1
Solar/Wind Helper
0.23
238120AE2-309 GEN
Solar/Wind Helper
0.474
238169AE2-226 GEN1
Solar/Wind Helper
0.655
238170AE2-226 GEN2
Solar/Wind Helper
0.655
238108AE1-109 GEN1
Solar/Wind Helper
0.102
238109AE1-109 GEN2
Solar/Wind Helper
0.102
238110AE1-109 GEN3
Solar/Wind Helper
0.102
237085AD2-009_GEN
Solar/Wind Helper
1.368
235054AD2-180 GEN
Solar/Wind Helper
1.916
315651AD1-115 GEN
Solar/Wind Helper
0.779
237061AD1-155 GEN
Solar/Wind Helper
1.799
235531U2-073 GEN
Solar/Wind Helper
2.963
23583801GRNGAP
Solar/Wind Helper
6.248
316447AC1-158 HLD
Solar/Wind Helper
2.81
316044AC1-158 PL1
Solar/Wind Helper
1.277
316045AC1-158 PL2
Solar/Wind Helper
4.086
316450AC1-158 RIC
Solar/Wind Helper
0.34
226929AD2-058 GEN
Solar/Wind Helper
0.087
238127S14_GEN_2
Solar/Wind Helper
0.741
238126S14_GEN_1
Solar/Wind Helper
0.741
238117U2-030
Solar/Wind Helper
0.306
238118U2-030_1
Solar/Wind Helper
0.306
241859AE2-194_GEN
Solar/Wind Harmer
13.402
316006AB2-029 C
Solar/Wind Helper
0.114
316164AC1-076 GEN
Solar/Wind Helper
1.091
3138216PACIFIC
Solar/Wind Helper
0.04
316095T157 G97
Solar/Wind Helper
1.648
316097T157 G90
Solar/Wind Helper
1.648
970935AG2-582 GEN
50/50
814.391
964991AG1-363 GEN
Solar/Wind Helper
3.939
972001AH1-545 GEN
Solar/Wind Harmer
19.9
972229AH1-699 GEN
Adder
6.968
238147AE2-230_GEN1
Solar/Wind Helper
0.499
238148AE2-230_GEN2
Solar/Wind Helper
0.499
238149AF1-291A_GEN
Solar/Wind Helper
0.143
238152AF2-075_GEN
Solar/Wind Helper
0.713
235063AE1-101 C2
Solar/Wind Helper
1.369
CBM West 1LTFEXP_CBM-W1->PJM
CBM
76.53
CBM West 2LTFEXP_CBM-W2->PJM
CBM
51.788
CBM South 1LTFEXP_CBM-S1->PJM
CBM
12.571
NYPJM->LTFIMP_NY
CLTF
2.523
LGEELTFEXP_LGEE->PJM
CLTF
3.372
WECLTFEXP_WEC->PJM
CLTF
1.937
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.856
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.074
TVALTFEXP_TVA->PJM
CLTF
3.004
MECLTFEXP_MEC->PJM
CLTF
7.827
LAGNLTFEXP_LAGN->PJM
CLTF
6.196
SIGELTFEXP_SIGE->PJM
CLTF
0.25
AG2-052LTFEXP_AG2-052->PJM
LTF
0.123
AH1-155LTFEXP_AH1-155->PJM
LTF
0.185

Details for 01HARRSN-01PRNTY 500.0 kV Ckt 1 line l/o AP_P2-3_WP-500-DRT9_SRT-SL


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AP
Facility Description:
01HARRSN-01PRNTY 500.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_WP-500-DRT9_SRT-SL
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:104.68 %
Rating:3792.0 MVA
Rating Type:B
MVA to Mitigate:3969.31
MW Contribution:
7.02
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
23546401DTGZ2-030
Solar/Wind Helper
0.09
23585401KL_K28_T16
Solar/Wind Helper
1.387
23750701CROSSCHOOL
Solar/Wind Helper
1.3
23751201ROTHROCK
Solar/Wind Helper
0.799
23562501BACKB
Solar/Wind Helper
0.978
23777901MDS_W4-102
Solar/Wind Helper
0.15
23908902SAMMG5
Adder
21.14
23909002SAMMG6
Adder
26.425
23909102SAMMG7
Adder
26.425
3141426STAFORD
Solar/Wind Helper
0.05
235020AA1-095 C
Solar/Wind Helper
0.045
23558501HARRN1
50/50
18.441
23558601HARRN2
50/50
18.441
23558701HARRN3
50/50
18.441
23559001PLEAS1
50/50
7.048
23559101PLEAS2
50/50
7.048
23684101S70BUS1
50/50
0.192
23684201S70BUS2
50/50
0.196
3147983MERCK5
Solar/Wind Helper
0.089
237038AE2-054 C
Solar/Wind Helper
0.227
3141196NOKESVL
Solar/Wind Helper
0.977
316411AF1-147_GEN1
Solar/Wind Helper
0.822
316415AF1-147_GEN2
Solar/Wind Helper
0.822
23751101LEADS_P59
Solar/Wind Helper
2.329
235062AE1-101 C1
Solar/Wind Helper
1.371
3132123MT JACKSON
Solar/Wind Helper
0.753
3132273ORANGE
Solar/Wind Helper
0.045
238185AF2-356 C
Solar/Wind Helper
2.372
237080AD1-060 GEN
Solar/Wind Helper
0.286
235067AD1-061 GEN
Solar/Wind Helper
0.371
237001AB1-127_GEN
Solar/Wind Helper
0.365
237002AB1-128_GEN
Solar/Wind Helper
0.367
238175AF1-290_GEN
Solar/Wind Helper
0.142
238221AF1-254 C O1
Solar/Wind Helper
0.23
238120AE2-309 GEN
Solar/Wind Helper
0.464
238169AE2-226 GEN1
Solar/Wind Helper
0.658
238170AE2-226 GEN2
Solar/Wind Helper
0.658
238108AE1-109 GEN1
Solar/Wind Helper
0.101
238109AE1-109 GEN2
Solar/Wind Helper
0.101
238110AE1-109 GEN3
Solar/Wind Helper
0.101
237085AD2-009_GEN
Solar/Wind Helper
1.37
235054AD2-180 GEN
Solar/Wind Helper
1.867
315651AD1-115 GEN
Solar/Wind Helper
0.783
237061AD1-155 GEN
Solar/Wind Helper
1.806
235531U2-073 GEN
Solar/Wind Helper
2.885
23583801GRNGAP
Solar/Wind Helper
6.278
316447AC1-158 HLD
Solar/Wind Helper
2.824
316044AC1-158 PL1
Solar/Wind Helper
1.284
316045AC1-158 PL2
Solar/Wind Helper
4.107
316450AC1-158 RIC
Solar/Wind Helper
0.342
226929AD2-058 GEN
Solar/Wind Helper
0.088
238127S14_GEN_2
Solar/Wind Helper
0.725
238126S14_GEN_1
Solar/Wind Helper
0.725
238117U2-030
Solar/Wind Helper
0.297
238118U2-030_1
Solar/Wind Helper
0.297
241859AE2-194_GEN
Solar/Wind Harmer
13.49
316006AB2-029 C
Solar/Wind Helper
0.115
316164AC1-076 GEN
Solar/Wind Helper
1.096
3138216PACIFIC
Solar/Wind Helper
0.041
316095T157 G97
Solar/Wind Helper
1.656
316097T157 G90
Solar/Wind Helper
1.656
970935AG2-582 GEN
50/50
815.661
227287AC2-120 GEN
Solar/Wind Helper
0.303
964991AG1-363 GEN
Solar/Wind Helper
3.958
972001AH1-545 GEN
Solar/Wind Harmer
20.03
972229AH1-699 GEN
Adder
7.018
238147AE2-230_GEN1
Solar/Wind Helper
0.501
238148AE2-230_GEN2
Solar/Wind Helper
0.501
238149AF1-291A_GEN
Solar/Wind Helper
0.143
238152AF2-075_GEN
Solar/Wind Helper
0.715
235063AE1-101 C2
Solar/Wind Helper
1.371
CBM West 1LTFEXP_CBM-W1->PJM
CBM
76.746
CBM West 2LTFEXP_CBM-W2->PJM
CBM
51.882
CBM South 1LTFEXP_CBM-S1->PJM
CBM
12.59
NYPJM->LTFIMP_NY
CLTF
2.521
LGEELTFEXP_LGEE->PJM
CLTF
3.379
WECLTFEXP_WEC->PJM
CLTF
1.942
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.865
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.078
TVALTFEXP_TVA->PJM
CLTF
3.008
MECLTFEXP_MEC->PJM
CLTF
7.845
LAGNLTFEXP_LAGN->PJM
CLTF
6.204
SIGELTFEXP_SIGE->PJM
CLTF
0.25
AG2-052LTFEXP_AG2-052->PJM
LTF
0.124
AH1-155LTFEXP_AH1-155->PJM
LTF
0.185

Details for 01HARRSN-01PRNTY 500.0 kV Ckt 1 line l/o AP_P1-2_MP-500-022_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AP
Facility Description:
01HARRSN-01PRNTY 500.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_MP-500-022_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.34 %
Rating:3792.0 MVA
Rating Type:B
MVA to Mitigate:3956.52
MW Contribution:
6.97
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
23546401DTGZ2-030
Solar/Wind Helper
0.09
23585401KL_K28_T16
Solar/Wind Helper
1.429
23750701CROSSCHOOL
Solar/Wind Helper
1.321
23751201ROTHROCK
Solar/Wind Helper
0.827
23562501BACKB
Solar/Wind Helper
1.011
23777901MDS_W4-102
Solar/Wind Helper
0.149
23908902SAMMG5
Adder
20.994
23909002SAMMG6
Adder
26.243
23909102SAMMG7
Adder
26.243
3141426STAFORD
Solar/Wind Helper
0.05
235020AA1-095 C
Solar/Wind Helper
0.045
23558501HARRN1
50/50
18.426
23558601HARRN2
50/50
18.426
23558701HARRN3
50/50
18.426
23559001PLEAS1
50/50
7.032
23559101PLEAS2
50/50
7.032
23684101S70BUS1
50/50
0.191
23684201S70BUS2
50/50
0.195
237038AE2-054 C
Solar/Wind Helper
0.226
3141196NOKESVL
Solar/Wind Helper
0.972
316411AF1-147_GEN1
Solar/Wind Helper
0.818
316415AF1-147_GEN2
Solar/Wind Helper
0.818
23751101LEADS_P59
Solar/Wind Helper
2.386
235062AE1-101 C1
Solar/Wind Helper
1.369
3132123MT JACKSON
Solar/Wind Helper
0.75
3132273ORANGE
Solar/Wind Helper
0.045
238185AF2-356 C
Solar/Wind Helper
2.426
237080AD1-060 GEN
Solar/Wind Helper
0.285
235067AD1-061 GEN
Solar/Wind Helper
0.37
237001AB1-127_GEN
Solar/Wind Helper
0.364
237002AB1-128_GEN
Solar/Wind Helper
0.366
238175AF1-290_GEN
Solar/Wind Helper
0.141
238221AF1-254 C O1
Solar/Wind Helper
0.23
238120AE2-309 GEN
Solar/Wind Helper
0.474
238169AE2-226 GEN1
Solar/Wind Helper
0.655
238170AE2-226 GEN2
Solar/Wind Helper
0.655
238108AE1-109 GEN1
Solar/Wind Helper
0.102
238109AE1-109 GEN2
Solar/Wind Helper
0.102
238110AE1-109 GEN3
Solar/Wind Helper
0.102
237085AD2-009_GEN
Solar/Wind Helper
1.368
235054AD2-180 GEN
Solar/Wind Helper
1.916
315651AD1-115 GEN
Solar/Wind Helper
0.779
237061AD1-155 GEN
Solar/Wind Helper
1.799
235531U2-073 GEN
Solar/Wind Helper
2.963
23583801GRNGAP
Solar/Wind Helper
6.248
316447AC1-158 HLD
Solar/Wind Helper
2.81
316044AC1-158 PL1
Solar/Wind Helper
1.277
316045AC1-158 PL2
Solar/Wind Helper
4.086
316450AC1-158 RIC
Solar/Wind Helper
0.34
226929AD2-058 GEN
Solar/Wind Helper
0.087
238127S14_GEN_2
Solar/Wind Helper
0.741
238126S14_GEN_1
Solar/Wind Helper
0.741
238117U2-030
Solar/Wind Helper
0.306
238118U2-030_1
Solar/Wind Helper
0.306
241859AE2-194_GEN
Solar/Wind Harmer
9.028
316006AB2-029 C
Solar/Wind Helper
0.114
316164AC1-076 GEN
Solar/Wind Helper
1.091
3138216PACIFIC
Solar/Wind Helper
0.04
316095T157 G97
Solar/Wind Helper
1.648
316097T157 G90
Solar/Wind Helper
1.648
970935AG2-582 GEN
50/50
814.391
964991AG1-363 GEN
Solar/Wind Helper
3.939
972001AH1-545 GEN
Solar/Wind Harmer
2.314
972229AH1-699 GEN
Adder
6.968
238147AE2-230_GEN1
Solar/Wind Helper
0.499
238148AE2-230_GEN2
Solar/Wind Helper
0.499
238149AF1-291A_GEN
Solar/Wind Helper
0.143
238152AF2-075_GEN
Solar/Wind Helper
0.713
235063AE1-101 C2
Solar/Wind Helper
1.369
CBM West 1LTFEXP_CBM-W1->PJM
CBM
76.53
CBM West 2LTFEXP_CBM-W2->PJM
CBM
51.788
CBM South 1LTFEXP_CBM-S1->PJM
CBM
12.571
NYPJM->LTFIMP_NY
CLTF
2.523
LGEELTFEXP_LGEE->PJM
CLTF
3.372
WECLTFEXP_WEC->PJM
CLTF
1.937
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.856
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.074
TVALTFEXP_TVA->PJM
CLTF
3.004
MECLTFEXP_MEC->PJM
CLTF
7.827
LAGNLTFEXP_LAGN->PJM
CLTF
6.196
SIGELTFEXP_SIGE->PJM
CLTF
0.25
AG2-052LTFEXP_AG2-052->PJM
LTF
0.123
AH1-155LTFEXP_AH1-155->PJM
LTF
0.185
CONTINGENCY 'AP_P2-3_WP-500-DRT6_SRT-SL'
 OPEN BRANCH FROM BUS 235111 TO BUS 235107 CKT 1                /*01 502 J     500.0 - 01HARRSN     500.0
 SET POSTCONTRATING 4289 BRANCH FROM BUS 235111 TO BUS 314917 CKT 1 /*01 502 J     500.0 - 8MT STM      500.0
 SET PRECONTRATING 3546 BRANCH FROM BUS 235111 TO BUS 314917 CKT 1 /*01 502 J     500.0 - 8MT STM      500.0
 SET PRECONTRATING 3753 BRANCH FROM BUS 235111 TO BUS 235098 CKT 1 /*01 502 J     500.0 - WOODSIDE     500.0
END
CONTINGENCY 'AP_P2-3_WP-500-DRT9_SRT-SL'
 OPEN BRANCH FROM BUS 235111 TO BUS 235107 CKT 1                /*01 502 J     500.0 - 01HARRSN     500.0
 OPEN BRANCH FROM BUS 235111 TO BUS 235113 CKT 2                /*01 502 J     500.0 - 01 502JCT    138.0
 SET POSTCONTRATING 4289 BRANCH FROM BUS 235111 TO BUS 314917 CKT 1 /*01 502 J     500.0 - 8MT STM      500.0
 SET PRECONTRATING 3546 BRANCH FROM BUS 235111 TO BUS 314917 CKT 1 /*01 502 J     500.0 - 8MT STM      500.0
 SET PRECONTRATING 3753 BRANCH FROM BUS 235111 TO BUS 235098 CKT 1 /*01 502 J     500.0 - WOODSIDE     500.0
END
CONTINGENCY 'AP_P1-2_MP-500-022_SRT-A'
 DISCONNECT BRANCH FROM BUS 235107 TO BUS 235111 CKT 1   /*01HARRSN     500.0 - 01 502 J     500.0
END
235107 to 235112 ckt 1

Winter Peak Analysis

The New Service Request AH1-699 was evaluated as a 58.0 MW (69.0 MW Capacity) injection in the ATSI area.

AH1-699 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1210.0 MW (58.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-699 was evaluated as a 58.0 MW injection

AH1-699 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1210.0 MW (58.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 44 are listed in Table 1 below. This report will cover the dynamic analysis of the Cluster 44 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 44 projects will meet the dynamics requirements of the NERC, FE, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 44 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00-1.03 pu voltage at the generator terminals, and 1.00-1.02 pu voltage at the POI buses.

Cluster 44 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 241 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 44 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 44 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 44 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

The AG2-621 voltage relay (VTGTPAT 97100306, TP = 0.3 s) tripped during several P4 stuck-breaker contingencies (P4_1B1.73–90) with 20-cycle backup clearing. A timer setting of at least 0.35 s would be required to ride through the 20-cycle backup clearing. Based on documentation for the inverter type, the relay timer pickup was adjusted to 1.2 s. No further trips were observed after this adjustment.

The existing AE2-285 overvoltage relay (VTGTPAT 24196701, TP = 0.01 s) tripped during the P1.34 contingency (7-cycle clearing of the Maysville 138/69 kV transformer) at t = 1.129 s in both the pre-project and post-project cases. The overvoltage spike is brief and settles quickly, suggesting the trip may be a numerical simulation artifact rather than a sustained overvoltage condition. Adding 8 ms to the relay timer pickup (TP = 0.018 s) was sufficient to ride through the transient and resolve the trip.

 

Table 1: TC2 Cluster 44 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

44

AG2-236

Solar

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

60.0

20.0

2.0

Potter-Harlan 69 kV

AG2-621

Storage

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

150.0

150.0

150.0

Hoytdale 138 kV

AH1-699

Natural Gas

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

1210.0

58.0

69.0

Wellsville 345 kV

AH1-706

Natural Gas

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

970.453

30.453

23.823

Lordstown 345 kV

 

 

Reactive Power Analysis

The reactive power capability of AH1-699 meets the 0.9 lagging and 0.95 leading PF requirement at the generator terminal.

Steady-State Voltage Analysis

Not Required

A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: s3191.1
Type
Load Flow
TO
APS
RTEP ID / TO ID
s3191.1 / APS-2023-056
Title
Harrison – Pruntytown 500 kV Misoperation Relays (Projected ISD by end of 2025)
Description
- Replace wave trap, line metering and relaying at Harrison Substation- - Replace wave trap, line metering and relaying at Pruntytown Substation
Cost Information
Time Estimate
Dec 31 2024

Not Contingent

Note: AH1-699 contributes to the loading of an overloaded facility that is being mitigated by a planned supplemental project. AH1-699 is not contingent on this supplemental project as it is already in-service.

FacilityContingency
01HARRSN-01PRNTY 500.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A3573.0 MVA
(All)B4379.0 MVA
(All)C4973.0 MVA
WINA4050.0 MVA
WINB5194.0 MVA
WINC5640.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-699


AH1-699 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-699 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-699 One Line Diagram

AH1-699 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.