AH1-713 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:57

Mt. Storm 500kV

14.0 MW Capacity / 0.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia), and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $0 $0 = AND ( $0 - $0 ) 14.0 = $0 per MW

General

The Project Developer has proposed a Coal generating facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Grant County, West Virginia. The installed facilities will have a total capability of 538.0 MW with 14.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-713
Project Name:
Mt. Storm 500kV
Project Developer Name:
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
State:
West Virginia
County:
Grant
Transmission Owner:
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
MFO:
538.0
MWE:
0.0
MWC:
14.0
Fuel Type:
Coal
Basecase Study Year:
2028

Physical Interconnection Facility Study

Not Required

A Physical Interconnection Facilities Study is not required for this project.

Point of Interconnection

AH1-713 will interconnect on the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) transmission system as an uprate to S74/S76 at the Mt. Storm 500 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-713 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-713Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$0$0$0
Other Scope$0$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0$0
Network Upgrades$0$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$0$0$0
Total$0$0$0

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AH1-713

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AH1-713
Project ID: AH1-713
20% of cost allocation for Phase II Network Upgrades:(A) $0
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $56,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $0
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

AH1-713 is sharing a POI and the TOIF with , so there are no associated interconnection costs for this project. Should the previous project(s) S74/S76 withdraw from the Interconnection Queue, AH1-713 will assume responsibility of the Transmission Owner Interconnection Facilities and Network Upgrades costs identified in the S74/S76 study report(s) for interconnection to the Dominion System.

No TO Interconnection Facilities or Physical Network Upgrades are required for this project.

Transmission Owner Analysis

PJM performed a power flow analysis of the transmission system using a 2028 load flow model and the results were verified by Dominion.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-713 was evaluated as a 0.0 MW (14.0 MW Capacity) injection in the Dominion area.

AH1-713 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 538.0 MW (0.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2DVP/PEPCO
6EDFERRY-DICKH230 230.0 kV Ckt 1 line
AP_P2-3_PE-500-019B_SRT-A
BreakerAC121.4 %1417.0B1720.2
0.7
GD2DVP
8FRONT ROYAL-8MORRSVL 500.0 kV Ckt 1 line
AP_P1-2_PE-500-404T_SRT-A
SingleAC100.67 %3220.44B3241.91
2.05

Details for 6EDFERRY-DICKH230 230.0 kV Ckt 1 line l/o AP_P2-3_PE-500-019B_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:DVP/PEPCO
Facility Description:
6EDFERRY-DICKH230 230.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-500-019B_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:121.4 %
Rating:1417.0 MVA
Rating Type:B
MVA to Mitigate:1720.2
MW Contribution:
0.7
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
3144293JTRSVLE
Adder
0.13
3144293JTRSVLE
Adder
0.164
3144293JTRSVLE
Adder
0.164
3144293JTRSVLE
Adder
0.164
3147043LAWRENC
Solar/Wind Harmer
-0.005
3147043LAWRENC
Adder
0.625
3147133PAMPLIN
Solar/Wind Harmer
-0.024
3147133PAMPLIN
Solar/Wind Harmer
-0.006
3147133PAMPLIN
Solar/Wind Harmer
-0.008
20390526W1-045 C
Solar/Wind Helper
0.226
23544701WINZ1-113
Adder
0.24
20671828STAW2-080
Solar/Wind Helper
0.02
20671928W4-073
Solar/Wind Helper
0.066
20673628F1S_V4-069
Solar/Wind Helper
0.022
20673728F2S_V4-070
Solar/Wind Helper
0.022
20673828FLE_V3-070
Solar/Wind Helper
0.065
20674128FR_U2-059
Solar/Wind Helper
0.003
20674328GAR_V4-001
Solar/Wind Helper
0.017
20674628WNG_W3-110
Solar/Wind Helper
0.066
20674828DL_W4-046
Solar/Wind Helper
0.006
20674928WA_W3-044
Solar/Wind Helper
0.073
20675128HRM_W1-127
Solar/Wind Helper
0.022
20675428EAM_W2-061
Solar/Wind Helper
0.012
20675528CPH_W2-050
Solar/Wind Helper
0.085
20675728RH_W2-091
Solar/Wind Helper
0.06
20675828AU_W4-064
Solar/Wind Helper
0.022
20675928HOL_W4-097
Solar/Wind Helper
0.037
20676128MHD_W3-029
Solar/Wind Helper
0.072
20676228FRD_X1-012
Solar/Wind Helper
0.068
20676328BVR_Y1-020
Solar/Wind Helper
0.02
20676428JCR_X2-075
Solar/Wind Helper
0.051
20676728BRNX1-095
Solar/Wind Helper
0.022
20714528FRN_Y2-051
Solar/Wind Helper
0.043
20714828MDF_W3-079
Solar/Wind Helper
0.099
20714928UPF_X1-085
Solar/Wind Helper
0.004
20715028HAN_X4-015
Solar/Wind Helper
0.044
20715228NPK_W1-113
Solar/Wind Helper
0.059
20715728PEM_W1-119
Solar/Wind Helper
0.073
20715828PEM_W1-120
Solar/Wind Helper
0.073
20716028EGP_W2-019
Solar/Wind Helper
0.014
20716928W4-060COL
Solar/Wind Helper
0.039
20720528MAN_W1-024
Solar/Wind Helper
0.021
20720628TIN_W1-124
Solar/Wind Helper
0.144
20720728JCB_W1-129
Solar/Wind Helper
0.044
20720828JCB_W4-025
Solar/Wind Helper
0.048
207408W3-077 C
Solar/Wind Helper
0.062
207439AE1-081 C O1
Solar/Wind Helper
0.014
214067T20SOLAR
Solar/Wind Helper
0.009
217206BARNGR HS C
Solar/Wind Helper
0.005
217208PARK ELE C
Solar/Wind Helper
0.003
217209CENTRL HS C
Solar/Wind Helper
0.006
217211CAMDEN ST C
Solar/Wind Helper
0.003
217213AMBOY SO C
Solar/Wind Helper
0.022
232404W1-003 C
Solar/Wind Helper
0.401
232408W1-005 C
Solar/Wind Helper
0.401
232410W1-006 C
Solar/Wind Helper
0.401
232417X3-008 C
Solar/Wind Helper
0.184
232426Y1-080 FULL
Solar/Wind Helper
0.031
232428Y3-058 C
Solar/Wind Helper
0.267
23777801MSM_W1-116
Solar/Wind Helper
0.111
3137176SLIGO L2192
Solar/Wind Harmer
-0.033
3141346CRANES
Adder
0.097
3141426STAFORD
Solar/Wind Harmer
-0.002
3141843SHACKLE
Adder
0.389
3141906WESTMOR
Solar/Wind Harmer
-0.003
3142296MT RD221
Adder
0.244
3142366NRTHEST
Adder
0.249
3142416OLDCHRC
Solar/Wind Harmer
-0.022
3142416OLDCHRC
Solar/Wind Harmer
0.866
3142416OLDCHRC
Solar/Wind Harmer
-0.008
3142433PROV 92
Solar/Wind Harmer
-0.034
3142433PROV 92
Adder
0.148
3142433PROV 92
Adder
0.148
3142433PROV 92
Adder
0.148
3142433PROV 92
Adder
0.148
3142433PROV 92
Adder
0.148
3142433PROV 92
Adder
0.148
3142956BIRDNECK
Solar/Wind Harmer
0.445
3143096IRON208
Adder
0.312
3143096IRON208
Adder
0.318
3143096IRON208
Adder
0.318
3143316POE
Solar/Wind Harmer
-0.033
3143336POWHATN
Solar/Wind Harmer
0.99
3143336POWHATN
Solar/Wind Harmer
0.841
3144216WINCHST
Adder
0.282
3144356SAPONY
Solar/Wind Harmer
0.285
3145506HICKORY
Solar/Wind Harmer
-0.033
3145506HICKORY
Solar/Wind Harmer
-0.02
3145506HICKORY
Solar/Wind Harmer
-0.005
3146386ELIZ CT
Solar/Wind Harmer
-0.008
3146396TANGLEW
Solar/Wind Harmer
0.151
3146776BUCKING
Solar/Wind Harmer
-0.032
3146776BUCKING
Solar/Wind Harmer
-0.003
3146776BUCKING
Solar/Wind Harmer
-0.003
3146776BUCKING
Solar/Wind Harmer
-0.003
3150071POSSM 5
Adder
38.706
3150151POSSMC1
Adder
0.847
3150151POSSMC1
Adder
0.847
3150151POSSMC1
Adder
0.847
3150181POSSMC2
Adder
0.847
3150181POSSMC2
Adder
0.847
3150181POSSMC2
Adder
0.854
3150211REMNGT1
Adder
12.461
3150221REMNGT2
Adder
12.544
3150241REMNGT4
Adder
12.627
3150281M RUN A
Adder
13.427
3150291M RUN B
Adder
13.319
3150301M RUN C
Adder
13.419
3150331BIRCHWDA
Adder
13.822
3150341NORNECKC1
Adder
0.801
3150341NORNECKC1
Adder
0.808
3150351NORNECKC2
Adder
0.782
3150351NORNECKC2
Adder
0.769
3150391LDYSMT3
Adder
10.838
3150401LDYSMT4
Adder
10.858
3150411LDYSMT5
Adder
10.892
3150671DARBY 1
Adder
5.457
3150681DARBY 2
Adder
5.463
3150691DARBY 3
Adder
5.482
3150701DARBY 4
Adder
5.469
3150921YORKTN3
Adder
1.882
209027LOR2_Q27
Solar/Wind Helper
0.713
212266LOR1
Solar/Wind Helper
0.208
217081WEATEXAS C
Solar/Wind Helper
0.009
217169METRODIV C
Solar/Wind Helper
0.003
217201HACKENSOLA C
Solar/Wind Helper
0.002
217202FBANKSOLAR C
Solar/Wind Helper
0.002
218428ETC SOLAR C
Solar/Wind Helper
0.004
218438BLK ROCK C
Solar/Wind Helper
0.021
218440SUMMTASSOC C
Solar/Wind Helper
0.012
218660EHAMPSOLAR C
Solar/Wind Helper
0.025
219236SOUTHERNHQ C
Solar/Wind Helper
0.004
219249CENTRALDIV C
Solar/Wind Helper
0.008
219272CLEANLIGHT C
Solar/Wind Helper
0.02
219276PARKLANDSO C
Solar/Wind Helper
0.068
219291REEVESSOUT C
Solar/Wind Helper
0.009
219348LDSOLAR C
Solar/Wind Helper
0.088
219607WPEMNERT C
Solar/Wind Helper
0.062
219612MATRIX C
Solar/Wind Helper
0.018
219615MILLCREEK C
Solar/Wind Helper
0.02
219620RIDERU C
Solar/Wind Helper
0.001
219766PARADISE C
Solar/Wind Helper
0.042
227927V4-067C
Solar/Wind Helper
0.008
3150981CHESPKA
Adder
0.923
3150991CHESPKB
Adder
0.756
3150991CHESPKB
Adder
0.775
3151081ELIZAR1
Adder
6.78
3151091ELIZAR2
Adder
6.662
3151101ELIZAR3
Adder
6.866
3151171GRAVELC
Adder
0.793
3151171GRAVELC
Adder
1.042
3151191GRAVEL3
Adder
5.356
3151201GRAVEL4
Adder
5.424
3151211GRAVEL5
Adder
5.356
3151221GRAVEL6
Adder
5.418
3151731LOISA B
Adder
5.418
3151751LOISA D
Adder
5.418
3151761LOISA E
Adder
11.045
3151861LOWMORA
Adder
0.673
3151861LOWMORA
Adder
0.647
3151881LOWMORC
Adder
0.657
3151881LOWMORC
Adder
0.668
3152111X4-039 GT1
50/50
2.013
3152121X4-039 GT2
50/50
2
3152131X4-039 ST
50/50
3.148
3152541MT STMG
Adder
0.592
316075AC2-137 C
Solar/Wind Harmer
0.23
316077AC2-138 C
Solar/Wind Harmer
0.182
228728W1-130C
Solar/Wind Helper
0.042
228729W2-030 C
Solar/Wind Helper
0.085
3138133OCRAN
Solar/Wind Harmer
-0.003
3138133OCRAN
Solar/Wind Harmer
-0.005
3138283WHITEMARSH
Solar/Wind Harmer
0.013
3141766HARMONY
Solar/Wind Harmer
0.761
3141766HARMONY
Solar/Wind Harmer
-0.002
3141783LANCAST
Solar/Wind Harmer
-0.005
3141783LANCAST
Solar/Wind Harmer
-0.003
3141813NORNECK
Solar/Wind Harmer
-0.009
3141913WHIT STONE
Solar/Wind Harmer
-0.009
3143226MDLTHAN
Solar/Wind Harmer
-0.009
3143873LANEXA
Solar/Wind Harmer
-0.005
3145273HOLLAND
Solar/Wind Harmer
-0.006
3146376EDENTON
Solar/Wind Harmer
-0.008
3146376EDENTON
Solar/Wind Harmer
0.24
3146376EDENTON
Solar/Wind Harmer
0.24
3146456SLIGO L269
Solar/Wind Harmer
0.976
3146456SLIGO L269
Solar/Wind Harmer
-0.008
3146456SLIGO L269
Solar/Wind Harmer
-0.008
3146486SUNBURY
Solar/Wind Harmer
-0.008
3146486SUNBURY
Solar/Wind Harmer
-0.008
3146516WINFALL
Solar/Wind Harmer
-0.008
3146516WINFALL
Solar/Wind Harmer
-0.008
3146516WINFALL
Solar/Wind Harmer
-0.026
3146516WINFALL
Solar/Wind Harmer
-0.008
3146516WINFALL
Solar/Wind Harmer
-0.008
3146516WINFALL
Solar/Wind Harmer
-0.008
3146626S HERTFORD
Solar/Wind Harmer
-0.008
3146626S HERTFORD
Solar/Wind Harmer
-0.008
3146626S HERTFORD
Solar/Wind Harmer
-0.008
3146926FARMVIL
Solar/Wind Harmer
-0.005
3146926FARMVIL
Solar/Wind Harmer
-0.005
3147346CASHSCORNER
Solar/Wind Harmer
0.143
3147666LOUISA
Solar/Wind Harmer
-0.038
3147666LOUISA
Solar/Wind Harmer
-0.022
232406W1-004 FULL
Solar/Wind Helper
0.401
232436AB1-176 C
Solar/Wind Helper
0.035
3141726DUNNSVL
Solar/Wind Harmer
-0.034
3145663CRESWEL
Solar/Wind Harmer
-0.022
316034AC1-036 C
Solar/Wind Harmer
0.142
316036AC1-147 C
Solar/Wind Harmer
0.224
316059AD1-063 C
Solar/Wind Harmer
0.193
316159AE1-175 C
Solar/Wind Harmer
0.226
316240AF1-291 C
Solar/Wind Harmer
0.254
316246AF1-032 C
Solar/Wind Harmer
0.167
316258AE1-075 C
Solar/Wind Harmer
0.202
316305AF2-043 C
Solar/Wind Harmer
0.248
316314AB2-024 C
Solar/Wind Harmer
0.73
316315AB2-025 C
Solar/Wind Harmer
0.22
316316AC1-027 C
Solar/Wind Harmer
0.254
316317KELFORD C
Solar/Wind Harmer
0.359
316336AC2-165 C
Solar/Wind Harmer
5.168
316382AG1-145 C
Solar/Wind Harmer
0.254
316405AF2-144 C
Solar/Wind Harmer
0.213
223402AF1-300 C
Solar/Wind Helper
0.38
230415AB2-049 C
Solar/Wind Helper
0.023
20742028HF_AC1-207
Solar/Wind Helper
0.106
207454AA2-184 E
Solar/Wind Helper
0.234
207459AE1-142 C O1
Solar/Wind Helper
0.221
207471AF2-354 C
Solar/Wind Helper
0.124
208835TUHI V3-051
Solar/Wind Helper
0.019
208835TUHI V3-051
Solar/Wind Helper
0.019
232424Y1-079 C
Solar/Wind Helper
0.092
3150371LDYSMT1
Adder
10.492
3150381LDYSMT2
Adder
10.424
218524CNTRALGAS1 C
Solar/Wind Helper
0.121
218526CNTRALGAS2 C
Solar/Wind Helper
0.121
226910AB2-157 C
Solar/Wind Helper
0.012
233901CHERRYDALE C
Solar/Wind Helper
0.184
233940AF2-379 C
Solar/Wind Helper
0.049
212507AE2-042_GEN
Solar/Wind Helper
1.059
219907AC1-030 C
Solar/Wind Helper
0.026
237025AB1-124 C
Solar/Wind Helper
0.169
237030AB1-096 C
Solar/Wind Helper
0.069
237038AE2-054 C
Solar/Wind Helper
0.12
3130156CHOWAN
Solar/Wind Harmer
-0.008
3130156CHOWAN
Solar/Wind Harmer
-0.008
3130156CHOWAN
Solar/Wind Harmer
-0.008
3145336SMITFLD
Solar/Wind Harmer
-0.033
3145336SMITFLD
Solar/Wind Harmer
-0.003
3141196NOKESVL
Solar/Wind Harmer
-0.049
3141873WAN 176
Solar/Wind Harmer
1.014
3141873WAN 176
Solar/Wind Harmer
-0.002
3143526WINTERP
Solar/Wind Harmer
-0.044
3143526WINTERP
Solar/Wind Harmer
-0.044
316411AF1-147_GEN1
Solar/Wind Harmer
1.196
316415AF1-147_GEN2
Solar/Wind Harmer
1.196
316404AE1-155 C
Solar/Wind Harmer
1.647
316017AA1-139 ULT1
Solar/Wind Harmer
0.667
316018AA1-139 ULT2
Solar/Wind Harmer
0.707
316181AB2-040 GEN
Solar/Wind Harmer
1.085
316033AB2-134 GEN
Solar/Wind Harmer
2.708
228754AB1-001 C
Solar/Wind Helper
0.02
316388AE2-253 GEN
Solar/Wind Harmer
0.556
235062AE1-101 C1
Solar/Wind Helper
0.75
205956AE1-196_GEN
Solar/Wind Helper
0.424
217204WCALDSOLAR C
Solar/Wind Helper
0.002
3145176PASQUOTANK
Solar/Wind Harmer
-0.005
3132273ORANGE
Solar/Wind Harmer
-0.002
3142543TWELFTH
Solar/Wind Harmer
-0.001
3144303KENBRDG
Solar/Wind Harmer
-0.006
237080AD1-060 GEN
Solar/Wind Helper
0.152
235067AD1-061 GEN
Solar/Wind Helper
0.193
237001AB1-127_GEN
Solar/Wind Helper
0.222
237002AB1-128_GEN
Solar/Wind Helper
0.213
238221AF1-254 C O1
Solar/Wind Helper
0.123
316203AE2-005 GEN
Solar/Wind Harmer
3.602
316441AF1-014 GEN
Solar/Wind Harmer
0.576
233944AB2-135 GEN
Solar/Wind Helper
0.467
233946AB2-136 GEN
Solar/Wind Helper
0.45
316426AA2-053 GEN
Solar/Wind Harmer
0.782
316190AA2-174 GEN
Solar/Wind Harmer
0.095
3156081AA2-088 GEN
Solar/Wind Harmer
2.574
233994AC2-023 GEN
Solar/Wind Helper
0.76
315614AA2-178 GEN
Solar/Wind Harmer
0.86
315816AE2-034 GEN
Solar/Wind Harmer
0.645
316312AB1-027
Solar/Wind Harmer
0.289
316011AB1-132 GEN
Solar/Wind Harmer
1.62
316369SG1_INVT
Solar/Wind Harmer
1.5
315651AD1-115 GEN
Solar/Wind Harmer
4.548
316023GEN1_S
Solar/Wind Harmer
0.531
316365GEN2_N
Solar/Wind Harmer
0.531
237006AB1-125 GEN
Solar/Wind Helper
0.127
23779801AA1-109
Solar/Wind Helper
0.182
316463AE2-346 GEN
Solar/Wind Harmer
0.126
315839AE2-212 C
Solar/Wind Harmer
0.253
233982AB2-133 GEN
Solar/Wind Helper
0.284
233915AB1-141 GEN
Solar/Wind Helper
0.398
233918AB1-142 GEN
Solar/Wind Helper
0.398
315821AE2-092 GEN
Solar/Wind Harmer
1.599
315814AE2-033 C
Solar/Wind Harmer
7.588
315671AE2-027_GEN
Solar/Wind Harmer
1.522
315747AE2-019 GEN
50/50
14.046
233930AB2-032 GEN
Solar/Wind Helper
0.302
233987AB2-037 GEN
Solar/Wind Helper
1.854
315662AE1-191 GEN
Solar/Wind Harmer
1.027
315666AE1-190 GEN
Solar/Wind Harmer
0.257
315673AE1-157 GEN
Solar/Wind Harmer
6.743
315813AE1-149 C
Solar/Wind Harmer
5.222
315683AE1-153 C
Solar/Wind Harmer
9.352
315742AE1-103 GEN
Solar/Wind Harmer
1.923
319010AE1-072 C
Solar/Wind Harmer
1.667
316065AD1-022 GEN
Solar/Wind Harmer
3.952
315697AD1-025 GEN
Solar/Wind Harmer
1.697
316185AD1-033 GEN
Solar/Wind Harmer
0.873
233933AB2-153 GEN
Solar/Wind Helper
0.184
315773AC2-141 GEN
Solar/Wind Harmer
3.486
316280AD1-041 GEN
Solar/Wind Harmer
0.642
233935AB2-179 C
Solar/Wind Helper
1.008
315732AD1-074 GEN1
Solar/Wind Harmer
1.599
315733AD1-074 GEN2
Solar/Wind Harmer
1.599
315735AD1-075 GEN1
Solar/Wind Harmer
0.799
315737AD1-076 GEN
Solar/Wind Harmer
1.504
316473AC1-191 GEN
Solar/Wind Harmer
0.93
316478AD1-087 GEN
Solar/Wind Harmer
0.668
316486AD2-202 GEN
Solar/Wind Harmer
0.195
316447AC1-158 HLD
Solar/Wind Harmer
2.175
316044AC1-158 PL1
Solar/Wind Harmer
0.989
316045AC1-158 PL2
Solar/Wind Harmer
3.165
316450AC1-158 RIC
Solar/Wind Harmer
0.264
316468AD1-105 GEN
Solar/Wind Harmer
1.005
316072AD1-144
Solar/Wind Harmer
0.167
315778AD1-151 GEN
Solar/Wind Harmer
7.492
316156AD2-030 GEN
Solar/Wind Harmer
0.227
316337AD2-073 GEN
Solar/Wind Harmer
0.234
234015AF2-250 C
Solar/Wind Helper
0.03
234036AF2-325 C
Solar/Wind Helper
0.033
207484AF2-139 C O1
Solar/Wind Helper
0.062
207510AF2-138 C
Solar/Wind Helper
0.06
207518AF1-320_GEN
Solar/Wind Helper
1.157
207442AE1-156 GEN
Solar/Wind Helper
0.244
226929AD2-058 GEN
Solar/Wind Helper
0.066
207437AD2-070 GEN
Solar/Wind Helper
0.102
209054AE2-059 GEN
Solar/Wind Helper
0.054
313526AB2-022
Solar/Wind Harmer
0.221
316313AB2-026
Solar/Wind Harmer
0.224
207445AB1-138_GEN
Solar/Wind Helper
0.079
209071AE2-133 GEN
Solar/Wind Helper
0.054
209116AE2-175 GEN
Solar/Wind Helper
1.293
3145513AHOSKIE
Solar/Wind Harmer
-0.008
3145513AHOSKIE
Solar/Wind Harmer
0.068
233923SMA
Solar/Wind Helper
0.594
230433AD2-135 GEN
Solar/Wind Helper
0.013
219680HOPEWELLV C1
Solar/Wind Helper
0.002
219686LUMSOLAR_N C
Solar/Wind Helper
0.031
219688LUMSOLAR_S C
Solar/Wind Helper
0.031
219908AB1-139 C
Solar/Wind Helper
0.055
219904AC1-010 C
Solar/Wind Helper
0.047
219906AC1-017 C
Solar/Wind Helper
0.032
219623KINSLEYBEA C
Solar/Wind Helper
0.002
219258KINSLEYDEP C
Solar/Wind Helper
0.059
219304NAMERICA C
Solar/Wind Helper
0.101
219921AF1-264
Solar/Wind Helper
0.039
203975AE1-071-GEN
Solar/Wind Helper
1.568
211065PSPA IPP
Solar/Wind Helper
0.11
211065PSPA IPP
Solar/Wind Helper
0.11
207530AG1-191 GEN
Solar/Wind Helper
0.049
230511AF1-262
Solar/Wind Helper
0.011
205932AD2-116_GEN
Solar/Wind Helper
0.424
205941AD2-115 GEN
Solar/Wind Helper
0.376
205943AE1-185 GEN
Solar/Wind Helper
0.425
205917AD1-020 ES
Solar/Wind Helper
0.323
205916AD1-020 GEN
Solar/Wind Helper
1.501
3147623JAMES R
Solar/Wind Harmer
0.121
209067AE2-060 GEN
Solar/Wind Helper
0.052
209137AF2-361 C
Solar/Wind Helper
0.867
3146206CASHIE
Solar/Wind Harmer
-0.008
3146206CASHIE
Solar/Wind Harmer
-0.008
3146206CASHIE
Solar/Wind Harmer
-0.008
3142666NORTHAMPTON
Solar/Wind Harmer
-0.008
3142666NORTHAMPTON
Solar/Wind Harmer
-0.008
3142666NORTHAMPTON
Solar/Wind Harmer
-0.008
3142666NORTHAMPTON
Solar/Wind Harmer
-0.005
3142666NORTHAMPTON
Solar/Wind Harmer
-0.008
316349AD2-085 GEN
Solar/Wind Harmer
0.734
3156021HOLLOMANSOL
Solar/Wind Harmer
1.054
315652AC1-086 GEN
Solar/Wind Harmer
8.728
313506AB2-031 GEN
Solar/Wind Harmer
0.625
316006AB2-029 C
Solar/Wind Harmer
0.63
316322AB2-045
Solar/Wind Harmer
0.266
316192AB2-158 GEN
Solar/Wind Harmer
1.118
316083AB2-161 GEN
Solar/Wind Harmer
1.35
316174AB2-169 GEN
Solar/Wind Harmer
1.19
316087AB2-174 GEN
Solar/Wind Harmer
1.111
316132AB2-190 GEN1
Solar/Wind Harmer
0.85
316458AB2-190 GEN2
Solar/Wind Harmer
0.85
316254AC1-120 GEN1
Solar/Wind Harmer
3.829
316170AC1-121 GEN2
Solar/Wind Harmer
1.276
316375AC2-012 GEN
Solar/Wind Harmer
2.873
316311AC2-079 GEN
Solar/Wind Harmer
4.173
316339AD2-160 GEN
Solar/Wind Harmer
0.556
316164AC1-076 GEN
Solar/Wind Harmer
0.844
316140AB2-099
Solar/Wind Harmer
0.053
316223AC1-118
Solar/Wind Harmer
0.236
316294AC1-161 GEN
Solar/Wind Harmer
2.694
315975AC1-164 GENB
Solar/Wind Harmer
0.057
315976AC1-164 GENA
Solar/Wind Harmer
1.94
316169AC1-164_GENC
Solar/Wind Harmer
1.676
316381AD1-082 GEN
Solar/Wind Harmer
0.761
316233AE1-074 FULL
Solar/Wind Harmer
0.231
316236AE1-162_GEN
Solar/Wind Harmer
0.251
316093AE2-104_GEN
Solar/Wind Harmer
2.397
315607AA1-063A GEN
Solar/Wind Harmer
0.787
3150851SPRUNCC
Adder
0.35
3150861SPRUNCD
Adder
0.35
230434AG1-499 GEN
Solar/Wind Helper
0.178
233964AF2-378 GEN
Solar/Wind Helper
0.033
3130546PLYMOUTH
Solar/Wind Harmer
-0.008
3145593CAROLNA
Solar/Wind Harmer
0.064
3145593CAROLNA
Solar/Wind Harmer
-0.008
3145593CAROLNA
Solar/Wind Harmer
-0.008
3145683EARLEYS
Solar/Wind Harmer
-0.008
3145683EARLEYS
Solar/Wind Harmer
-0.008
3145683EARLEYS
Solar/Wind Harmer
-0.008
3145683EARLEYS
Solar/Wind Harmer
-0.016
207511W3-106 GEN
Solar/Wind Helper
0.02
208972BECR K09
Solar/Wind Helper
0.228
209029WAYMART-WD
Solar/Wind Helper
0.567
223401AF1-299 GEN
Solar/Wind Helper
0.38
230407AD2-065 C
Solar/Wind Helper
0.031
232432Z2-076 GEN
Solar/Wind Helper
0.053
232434Z2-077 GEN
Solar/Wind Helper
0.1
233996TM1833_GEN
Solar/Wind Helper
0.162
233997TMININ_4.2
Solar/Wind Helper
0.162
233998TM1NIN_3.36
Solar/Wind Helper
0.162
3130086AYDLETT
Solar/Wind Harmer
-0.033
3137643SOCKMAN
Solar/Wind Harmer
-0.031
3138126ROCKLANDING
Solar/Wind Harmer
0.026
3138216PACIFIC
Solar/Wind Harmer
-0.003
3138266HYDRAULIC
Solar/Wind Harmer
0
3138266HYDRAULIC
Solar/Wind Harmer
0
3142946ENON
Solar/Wind Harmer
-0.001
3142946ENON
Solar/Wind Harmer
-0.003
3144536CHRHLND
Solar/Wind Harmer
-0.001
3144873MCLAUGH
Solar/Wind Harmer
0
3145783HORNRTN
Solar/Wind Harmer
-0.008
3145783HORNRTN
Solar/Wind Harmer
0.917
3145783HORNRTN
Solar/Wind Harmer
0.733
3145783HORNRTN
Solar/Wind Harmer
0.229
3145783HORNRTN
Solar/Wind Harmer
0.092
3145796HORNRTN
Solar/Wind Harmer
-0.023
3145796HORNRTN
Solar/Wind Harmer
-0.025
3145796HORNRTN
Solar/Wind Harmer
-0.008
3145796HORNRTN
Solar/Wind Harmer
-0.008
3145796HORNRTN
Solar/Wind Harmer
-0.031
3145796HORNRTN
Solar/Wind Harmer
-0.025
3145796HORNRTN
Solar/Wind Harmer
-0.003
3145823KELFORD
Solar/Wind Harmer
-0.008
3145823KELFORD
Solar/Wind Harmer
-0.008
3145893MURPHYS
Solar/Wind Harmer
0.22
3145893MURPHYS
Solar/Wind Harmer
-0.014
3145893MURPHYS
Solar/Wind Harmer
0.055
3145893MURPHYS
Solar/Wind Harmer
0.234
3145893MURPHYS
Solar/Wind Harmer
-0.008
3145893MURPHYS
Solar/Wind Harmer
-0.031
3145893MURPHYS
Solar/Wind Harmer
-0.008
3145893MURPHYS
Solar/Wind Harmer
-0.021
3145963POPLR C
Solar/Wind Harmer
-0.008
3145963POPLR C
Solar/Wind Harmer
-0.008
3146033SCOT NK
Solar/Wind Harmer
-0.031
3146043SEABORD
Solar/Wind Harmer
-0.008
3146173TUNIS
Solar/Wind Harmer
-0.008
3146173TUNIS
Solar/Wind Harmer
-0.008
3146173TUNIS
Solar/Wind Harmer
-0.008
3146173TUNIS
Solar/Wind Harmer
-0.008
3146263WOODLND
Solar/Wind Harmer
-0.008
3146263WOODLND
Solar/Wind Harmer
-0.008
3146406KITTY HAWK
Solar/Wind Harmer
0.007
315611Z1-036_GEN2
Solar/Wind Harmer
1.999
315800Z1-036_GEN1
Solar/Wind Harmer
1.999
316318V4-068
Solar/Wind Harmer
0.197
316320Y1-086
Solar/Wind Harmer
0.482
316321Z2-027
Solar/Wind Harmer
0.221
942461AE2-259 GEN
Solar/Wind Harmer
1.175
944011AF1-069 GEN
Solar/Wind Harmer
4.79
944491AF1-114 GEN
Solar/Wind Harmer
2.607
944581AF1-123 GEN
Solar/Wind Harmer
37.785
944591AF1-124 GEN
Solar/Wind Harmer
37.921
944601AF1-125 GEN
Solar/Wind Harmer
37.195
944631AF1-128 GEN
Adder
36.103
944641AF1-129 GEN
Adder
35.868
946281AF1-292 GEN
Solar/Wind Harmer
0.175
946301AF1-294 GEN
Solar/Wind Harmer
1.983
946691AF1-333 GEN
Solar/Wind Helper
0.298
946731AF1-337 GEN
Solar/Wind Helper
0.298
946741AF1-338 GEN
Solar/Wind Helper
0.298
946751AF1-339 GEN
Solar/Wind Helper
0.298
959311AF2-222 GEN
Solar/Wind Harmer
8.024
959381AF2-229 GEN
Solar/Wind Helper
0.231
959421AF2-233 GEN
Solar/Wind Helper
0.297
959431AF2-234 GEN
Solar/Wind Helper
0.595
959561AF2-247 GEN
Solar/Wind Helper
0.016
960081AF2-299 GEN
Solar/Wind Harmer
0.881
961261AF2-417 GEN
Solar/Wind Helper
0.309
961301AF2-421 GEN
Solar/Wind Helper
0.31
961331AF2-424 GEN
Solar/Wind Helper
0.303
961341AF2-425 GEN
Solar/Wind Helper
0.303
961421AF2-433 GEN
Solar/Wind Helper
0.302
961431AF2-434 GEN
Solar/Wind Helper
0.302
961611AG1-000B GEN
Solar/Wind Harmer
4.139
961611AG1-000B GEN
Solar/Wind Harmer
1.766
961791AG1-021 GEN
Solar/Wind Harmer
0.967
961941AG1-037 GEN
Solar/Wind Harmer
0.059
961951AG1-038 GEN
Solar/Wind Harmer
1.134
962571AG1-106 GEN
Solar/Wind Harmer
1.115
962861AG1-135 GEN
Solar/Wind Harmer
3.234
963151AG1-164 GEN
Solar/Wind Helper
0.31
963161AG1-165 GEN
Solar/Wind Helper
0.31
966871AG1-558 GEN
Solar/Wind Harmer
0.26
966871AG1-558 GEN
Solar/Wind Harmer
0.089
966881AG1-559 GEN
Solar/Wind Harmer
0.268
966881AG1-559 GEN
Solar/Wind Harmer
0.092
970053AG2-049 GEN
Adder
1.705
970085AG2-068 GEN
Solar/Wind Harmer
4.913
970087AG2-069 GEN
Solar/Wind Harmer
7.37
970099AG2-077 GEN
Solar/Wind Harmer
9.803
970133AG2-095 GEN
Solar/Wind Harmer
0.951
970221AG2-151 GEN
Solar/Wind Harmer
4.898
970257AG2-171 GEN
Solar/Wind Harmer
0.181
970293AG2-193 GEN
Solar/Wind Harmer
1.069
970301AG2-198 GEN
Solar/Wind Harmer
3.93
970323AG2-213 GEN
Solar/Wind Harmer
3.839
970533AG2-339 GEN
Solar/Wind Harmer
5.483
970581AG2-369 GEN
Solar/Wind Harmer
4.225
970601AG2-382 GEN
Solar/Wind Harmer
3.452
970657AG2-426 GEN
Solar/Wind Harmer
1.68
970657AG2-426 GEN
Solar/Wind Harmer
0.524
970673AG2-436 GEN
Solar/Wind Harmer
17.761
970681AG2-440 GEN
Solar/Wind Harmer
3.614
970683AG2-441 GEN
Solar/Wind Harmer
5.445
970685AG2-442 GEN
Solar/Wind Harmer
6.757
970917AG2-570 GEN
Solar/Wind Harmer
19.76
970919AG2-571 GEN
Solar/Wind Harmer
2.501
970933AG2-581 GEN
Solar/Wind Harmer
7.508
970937AG2-583 GEN
Solar/Wind Harmer
5.831
971069AG2-661 GEN
Solar/Wind Harmer
1.332
971153AH1-033 GEN
Solar/Wind Harmer
0.956
971163AH1-040 GEN
Solar/Wind Harmer
7.498
971223AH1-071 GEN
Solar/Wind Harmer
1.073
971281AH1-106 GEN
Solar/Wind Harmer
1.394
971283AH1-107 GEN
Solar/Wind Harmer
1.394
971285AH1-108 GEN
Adder
0.573
971317AH1-138 GEN
Solar/Wind Harmer
1.055
971377AH1-170 GEN
Solar/Wind Harmer
0.98
971445AH1-216 GEN
Solar/Wind Harmer
5.168
971455AH1-223 GEN
Solar/Wind Harmer
2.518
971547AH1-271 GEN
Solar/Wind Harmer
1.973
971563AH1-280 GEN
Solar/Wind Harmer
0.967
971685AH1-345 GEN
Solar/Wind Harmer
0.962
219918AC2-009 C
Solar/Wind Helper
0.001
227287AC2-120 GEN
Solar/Wind Helper
0.268
316431W1029_GEN1
Solar/Wind Harmer
1.483
316433W1029_GEN2
Solar/Wind Harmer
1.483
316435W1029_GEN3
Solar/Wind Harmer
1.483
939411AE1-173 GEN
Solar/Wind Harmer
41.429
940641AE2-051 GEN
Solar/Wind Harmer
7.765
941031AE2-094 GEN
Solar/Wind Harmer
15.288
957481AF2-042 GEN
Solar/Wind Harmer
24.507
957601AF2-054 GEN
Solar/Wind Harmer
0.256
957831AF2-077 GEN
Solar/Wind Harmer
0.255
957871AF2-081 GEN
Solar/Wind Harmer
4.136
957921AF2-086 GEN
Solar/Wind Helper
0.299
957971AF2-091 GEN
Solar/Wind Harmer
0.887
958211AF2-115 GEN
Solar/Wind Harmer
1.209
958261AF2-120 GEN
Solar/Wind Harmer
3.344
963691AG1-221 GEN
Solar/Wind Harmer
2.518
963711AG1-223 GEN
Solar/Wind Helper
0.049
964051AG1-259 GEN
Solar/Wind Helper
0.044
964061AG1-260 GEN
Solar/Wind Helper
0.044
964211AG1-282 GEN
Solar/Wind Harmer
0.26
964851AG1-348 GEN
Solar/Wind Helper
0.046
966001AG1-469 GEN
Solar/Wind Harmer
0.179
966621AG1-532 GEN
Solar/Wind Harmer
0.159
971761AH1-387 GEN
Solar/Wind Harmer
4.557
971777AH1-397 GEN
Solar/Wind Harmer
0.997
971781AH1-399 GEN
Solar/Wind Harmer
0.542
971845AH1-439 GEN
Solar/Wind Harmer
4.206
971967AH1-528 GEN
Solar/Wind Harmer
15.148
972003AH1-546 GEN
Solar/Wind Harmer
3.236
972135AH1-637 GEN
Solar/Wind Harmer
0.886
972185AH1-677 GEN
Adder
4.03
972187AH1-678 GEN
Adder
2.035
972189AH1-679 GEN
Adder
1.303
972193AH1-681 GEN
Adder
1.592
972195AH1-682 GEN
Adder
1.424
972197AH1-683 GEN
Adder
1.696
972199AH1-684 GEN
Adder
1.915
972201AH1-685 GEN
Adder
2.164
972205AH1-687 GEN
Adder
3.031
972213AH1-691 GEN
Adder
1.763
972215AH1-692 GEN
Adder
1.763
972217AH1-693 GEN
Adder
1.665
972219AH1-694 GEN
Adder
1.221
972223AH1-696 GEN
Adder
6.689
972255AH1-712 GEN
Adder
35.633
972257AH1-713 GEN
Adder
0.696
972277AH1-723 GEN
Adder
41.523
233950AC2-186 GEN
Solar/Wind Helper
0.092
233952AC2-187 GEN
Solar/Wind Helper
0.184
233954AC2-188 GEN
Solar/Wind Helper
0.184
315835AF2-110_GEN
Solar/Wind Harmer
1.03
232422X3-066 FULL
Solar/Wind Helper
0.09
315693AD1-088 GEN
Solar/Wind Harmer
3.916
316487AF1-042 GEN
Solar/Wind Harmer
1.134
315833AF1-017_GEN
Solar/Wind Harmer
1.571
316484AD2-074 GEN
Solar/Wind Harmer
2.167
219919AE1-041 FULL
Solar/Wind Helper
0.003
219912AD2-042 GEN
Solar/Wind Helper
0.116
219914AD2-027 C
Solar/Wind Helper
0.089
235063AE1-101 C2
Solar/Wind Helper
0.75
3151721LOISA A
Adder
5.39
CBM West 1LTFEXP_CBM-W1->PJM
CBM
41.692
CBM West 2LTFEXP_CBM-W2->PJM
CBM
43.695
CBM South 1LTFEXP_CBM-S1->PJM
CBM
12.818
CBM South 2LTFEXP_CBM-S2->PJM
CBM
12.759
NYPJM->LTFIMP_NY
CLTF
3.275
LGEELTFEXP_LGEE->PJM
CLTF
2.092
WECLTFEXP_WEC->PJM
CLTF
1.123
CPLELTFEXP_CPLE->PJM
CLTF
5
TVALTFEXP_TVA->PJM
CLTF
3.494
MECLTFEXP_MEC->PJM
CLTF
5.118
LAGNLTFEXP_LAGN->PJM
CLTF
6.94
SIGELTFEXP_SIGE->PJM
CLTF
0.161
AG2-052LTFEXP_AG2-052->PJM
LTF
0.067
AH1-155LTFEXP_AH1-155->PJM
LTF
0.1

Details for 8FRONT ROYAL-8MORRSVL 500.0 kV Ckt 1 line l/o AP_P1-2_PE-500-404T_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:DVP
Facility Description:
8FRONT ROYAL-8MORRSVL 500.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-500-404T_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:100.67 %
Rating:3220.44 MVA
Rating Type:B
MVA to Mitigate:3241.91
MW Contribution:
2.05
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
23503301WHY_Z2-039
50/50
0.009
23503901LHY_Z2-039
50/50
0.005
23544701WINZ1-113
50/50
1.004
23503401SHY_Z2-039
50/50
0.005
23503501NHY_Z2-039
50/50
0.007
3141426STAFORD
Solar/Wind Helper
0.056
3152511MT STM1
50/50
2.142
3152511MT STM1
50/50
2.159
3152521MT STM2
50/50
2.2
3152521MT STM2
50/50
2.21
3152531MT STM3
50/50
4.175
3152541MT STMG
50/50
1.739
3152701WARREN G1
50/50
6.32
3152711WARREN G2
50/50
6.32
3152721WARREN G3
50/50
6.32
3152731WARREN S1
50/50
11.831
3147666LOUISA
Solar/Wind Helper
0.959
3147666LOUISA
Solar/Wind Helper
0.551
3141196NOKESVL
Solar/Wind Helper
1.175
316411AF1-147_GEN1
Solar/Wind Helper
0.812
316415AF1-147_GEN2
Solar/Wind Helper
0.812
3132123MT JACKSON
Solar/Wind Harmer
0.416
3132273ORANGE
Solar/Wind Helper
0.05
238223AG1-045 C
Solar/Wind Harmer
4.626
315651AD1-115 GEN
Solar/Wind Helper
1.013
23583801GRNGAP
Solar/Wind Harmer
0
316447AC1-158 HLD
Solar/Wind Helper
3.972
316044AC1-158 PL1
Solar/Wind Helper
1.805
316045AC1-158 PL2
Solar/Wind Helper
5.776
316450AC1-158 RIC
Solar/Wind Helper
0.481
316006AB2-029 C
Solar/Wind Helper
0.16
316192AB2-158 GEN
Solar/Wind Helper
1.604
316164AC1-076 GEN
Solar/Wind Helper
1.414
3138216PACIFIC
Solar/Wind Helper
0.038
966881AG1-559 GEN
Solar/Wind Helper
0.31
970117AG2-086 GEN
Solar/Wind Harmer
3.188
970117AG2-086 GEN
Solar/Wind Harmer
2.126
970459AG2-300 GEN
50/50
18.964
971513AH1-254 GEN
Solar/Wind Harmer
5.736
971569AH1-283 GEN
Solar/Wind Harmer
15.971
964441AG1-307 GEN
Solar/Wind Harmer
5.813
964441AG1-307 GEN
Solar/Wind Harmer
0.969
965471AG1-415 GEN
Solar/Wind Harmer
4.218
971761AH1-387 GEN
Solar/Wind Harmer
6.622
972257AH1-713 GEN
50/50
2.046
CBM West 1LTFEXP_CBM-W1->PJM
CBM
32.928
CBM West 2LTFEXP_CBM-W2->PJM
CBM
21.031
CBM South 1LTFEXP_CBM-S1->PJM
CBM
4.984
NYPJM->LTFIMP_NY
CLTF
1.24
LGEELTFEXP_LGEE->PJM
CLTF
1.482
WECLTFEXP_WEC->PJM
CLTF
0.842
HAMLETPJM->LTFIMP_HAMLET
CLTF
1.195
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.335
TVALTFEXP_TVA->PJM
CLTF
1.145
MECLTFEXP_MEC->PJM
CLTF
3.343
LAGNLTFEXP_LAGN->PJM
CLTF
2.295
SIGELTFEXP_SIGE->PJM
CLTF
0.108
CONTINGENCY 'AP_P2-3_PE-500-019B_SRT-A'
 DISCONNECT BRANCH FROM BUS 235105 TO BUS 200003 CKT 1   /*01DOUBS      500.0 - BRIGHTON     500.0
 DISCONNECT BRANCH FROM BUS 270095 TO BUS 235105 CKT 1   /*CHAN         500.0 - 01DOUBS      500.0
END
CONTINGENCY 'AP_P1-2_PE-500-404T_SRT-A'
 DISCONNECT BRANCH FROM BUS 235110 TO BUS 313440 CKT 1   /*01MDWBRK     500.0 - 8VINTHIL     500.0
END
314290 to 223938 ckt 1
314929 to 314916 ckt 1

Winter Peak Analysis

The New Service Request AH1-713 was evaluated as a 0.0 MW (14.0 MW Capacity) injection in the Dominion area.

AH1-713 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 538.0 MW (0.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-713 was evaluated as a 0.0 MW injection

AH1-713 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 538.0 MW (0.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

PJM has reviewed this project submission and determined that a stability study is not required as this is a CIR only increase with no changes to equipment/electrical parameters (no change to MFO).

 

Reactive Power Analysis

Not Required

Reactive Power Analysis was not performed. This project is responsible for meeting all applicable power factor requirements based on the project Agreements per PJM’s Tariff, Part IX, Subpart B, App. 2, section 4.6.1.

Steady-State Voltage Analysis

Not Required

A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b4000.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.357
Title
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Description
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.356
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.355
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.355
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.352
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.352
Title
Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
Description
Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.351
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.351
Title
Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
Description
Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.349
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.349
Title
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
Description
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.348
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.348
Title
Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Description
Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Thornburg (formerly Kraken) to accommodate the new 500kV line from North Anna to Thornburg (formerly Kraken).
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.346
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.346
Title
Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
Description
Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.344
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.344
Title
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.341
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.341
Title
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Description
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
Cost Information
Time Estimate
Jul 13 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.342
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.342
Title
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Description
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Cost Information
Time Estimate
Jul 13 2029

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.345
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.345
Title
Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.350
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.350
Title
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
Description
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
8MORRSVL-8FRONT ROYAL 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.11
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.11
Title
Replace Bells Mill T3 XF with new PEPCO standard 260 MVA 230/138 kV transformer.
Description
Replace Bells Mill T3 XF with new PEPCO standard 260 MVA 230/138 kV transformer. (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.10
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.10
Title
Replace one stranded bus conductor, three thermal relays, two disconnect switches at Quince Orchard 230 kV substation.
Description
Replace one stranded bus conductor, three thermal relays, two disconnect switches at Quince Orchard 230 kV substation. (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.9
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.9
Title
Replace two breakers, one bushing CT, one stranded bus conductor, four disconnect switches at Brighton 500 kV substation.
Description
Replace two breakers, one bushing CT, one stranded bus conductor, four disconnect switches at Brighton 500 kV substation.
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.8
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.8
Title
Relocate Dickerson "D"-Quince Orchard 23035 to terminate at Dickerson "H" at Dickerson No. 2 tie location.
Description
Relocate Dickerson "D"-Quince Orchard 23035 to terminate at Dickerson "H" at Dickerson No. 2 tie location. (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.7
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.7
Title
Install 3.2% 230 kV series reactor at Dickerson "H" terminal side of the Edwards Ferry-Dickerson circuit.
Description
Install 3.2% 230 kV series reactor at Dickerson "H" terminal side of the Edwards Ferry-Dickerson circuit. (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.6
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4052.6
Title
Aspen 500 kV remote work for Dickerson (new 500 kV) - Aspen line
Description
Aspen 500 kV remote work for Dickerson (new 500 kV) - Aspen line (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.5
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4052.5
Title
Rocky Point 500 kV remote work for Dickerson (new 500 kV)-Rocky Point line
Description
Rocky Point 500 kV remote work for Dickerson (new 500 kV)-Rocky Point line. (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.1
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.1
Title
New 500/230 kV substation (Dickerson) by cutting into the Aspen-Rocky Point 500 kV line
Description
New 500/230 kV substation (Dickerson) by cutting into the Aspen-Rocky Point 500 kV line. (2025-W1-919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.4
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.4
Title
Aspen-Dickerson (new 500 kV) termination work at Dickerson 500 kV
Description
Aspen-Dickerson (new 500 kV) termination work at Dickerson 500 kV (2025 W1 919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.3
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.3
Title
Rocky Point-Dickerson (new 500 kV) termination work at Dickerson 500 kV
Description
Rocky Point-Dickerson (new 500 kV) termination work at Dickerson 500 kV (2025 W1-919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4052.2
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b4052.2
Title
Install two 500/230 kV transformers connecting a new 500 kV Dickerson station and DIckeson "H" 230 kV station including 230 kV substation work.
Description
Install two 500/230 kV transformers connecting a new 500 kV Dickerson station and DIckeson "H" 230 kV station including 230 kV substation work. (2025 W1-919)
Cost Information
Time Estimate
Jun 01 2032

Not Contingent

Note: AH1-713 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-713 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DICKH230-6EDFERRY 230.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-713


AH1-713 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-713 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-713 One Line Diagram

AH1-713 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.