Transition Cycle 1

v1.00 released 2025-12-08 18:26

New Service Requests

System Impact Study Executive Summary Report

Transition Cycle 1 — Final (Retool 1)

Introduction

This Final System Impact Study executive summary report has been prepared in accordance with the PJM Open Access Transmission Tariff Part VII, Subpart D, section 314 This report presents an executive summary of Final System Impact Study results for New Service Requests (projects) in Transition Cycle 1.

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

New Services Request List

PJM received 87 New Service Requests in Transition Cycle 1, Final System Impact Study with a combined Maximum Facility Output (MFO) of 14,377.2 MW and 6,802.6 MW as Capacity Interconnection Rights (CIRs). All of these New Service Requests are listed in table below.

Project IDProject Name / POI
State
Status
Transmission Owner
Maxiumum Facility Output (MFO in MW)MW Energy (MWE)MW Capacity (MWC)Project TypeResource TypeFacilities Study
AE1-092Blue Jacket-Kirby 138 kVOhioActiveThe Dayton Power and Light Company206.55206.5596.4Generation InterconnectionSolar
AE1-114Maryland-Lancaster 138 kVIllinoisActiveCommonwealth Edison Company150.0150.034.0Generation InterconnectionWind
AE1-172Loretto-Wilton CenterIllinoisActiveCommonwealth Edison Company255.0255.044.88Generation InterconnectionWind
AE2-156Yadkin 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)100.0100.0100.0Generation InterconnectionStorage
AE2-185Gladys DP-Stonemill Switching Station 69 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)60.060.036.0Generation InterconnectionSolar
AE2-223McLean 345 kVIllinoisActiveCommonwealth Edison Company350.0150.019.5Generation InterconnectionWind
AE2-261Kincaid-Pana 345 kVIllinoisActiveCommonwealth Edison Company299.0299.0179.4Generation InterconnectionSolar
AE2-283Gladys-Stone Mill 69 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)53.053.028.0Generation InterconnectionSolar
AE2-291Grit DP-Perth 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)102.0102.061.2Generation InterconnectionSolar
AE2-308Three Forks-Dale 138 kVKentuckyActiveEast Kentucky Power Cooperative, Inc.100.0100.060.0Generation InterconnectionSolar
AE2-325Valley 138 kVMichiganActiveAEP Indiana Michigan Transmission Company, Inc.152.252.231.32Generation InterconnectionStorage
AE2-341Sandwich-Plano 138 kVIllinoisActiveCommonwealth Edison Company150.0150.0100.6Generation InterconnectionSolar
AF1-030Sandwich-Plano 138 kVIllinoisActiveCommonwealth Edison Company250.0100.066.9Generation InterconnectionSolar
AF1-123Harper 230 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)833.0833.0253.2Generation InterconnectionOffshore Wind
AF1-124Harper 230 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)836.0836.0254.1Generation InterconnectionOffshore Wind
AF1-125Harper 230 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)820.0820.0249.3Generation InterconnectionOffshore Wind
AF1-128Chesterfield 230 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)569.0569.0569.0Generation InterconnectionNatural Gas
AF1-161Valley 138 kVMichiganActiveAEP Indiana Michigan Transmission Company, Inc.50.050.025.0Generation InterconnectionStorage
AF1-176Corey 138 kVMichiganActiveAEP Indiana Michigan Transmission Company, Inc.300.0300.0155.682Generation InterconnectionSolar; Storage
AF1-204Eugene 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.255.0255.063.75Generation InterconnectionWind
AF1-233Flemingsburg – Spurlock 138kVKentuckyActiveEast Kentucky Power Cooperative, Inc.188.5188.5113.1Generation InterconnectionSolar
AF1-238Sherman Ave - West Vineland 69 kVNew JerseyActiveAtlantic City Electric50.050.020.0Generation InterconnectionStorageN/A
AF1-280Nelson-Lee CountyIllinoisActiveCommonwealth Edison Company200.0200.00.0Generation InterconnectionSolar
AF1-294Jetersville-Ponton 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)41.041.022.2Generation InterconnectionSolar
AF1-296Garden Plain 138 kVIllinoisActiveCommonwealth Edison Company190.89190.8933.6Generation InterconnectionWind
AF2-010Union City-Titusville 115 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC77.077.046.0Generation InterconnectionSolar
AF2-041Nelson-Electric Junction 345 kVIllinoisActiveCommonwealth Edison Company300.0300.0180.0Generation InterconnectionSolar
AF2-042Clover-Rawlings 500 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)500.0500.0300.0Generation InterconnectionSolar
AF2-050Bear Rock-Johnstown 230 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC150.050.030.0Generation InterconnectionSolar
AF2-068Jay 138 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.150.0150.090.0Generation InterconnectionSolar
AF2-080Chinquapin-Everetts 230 kVNorth CarolinaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)150.070.048.5Generation InterconnectionSolarN/A
AF2-081Moyock 230 kVNorth CarolinaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)80.080.056.0Generation InterconnectionSolar
AF2-095Davis Creek 138 kVIllinoisActiveCommonwealth Edison Company144.0144.086.4Generation InterconnectionSolar
AF2-111North Clark-Spurlock 345 kVKentuckyActiveEast Kentucky Power Cooperative, Inc.250.0250.0150.0Generation InterconnectionSolar
AF2-115Jetersville-Ponton 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)66.025.013.5Generation InterconnectionSolar
AF2-120Garner-Northern Neck 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)62.062.037.2Generation InterconnectionSolar
AF2-126Weston 69 kV IIOhioActiveAmerican Transmission Systems, Incorporated62.012.08.0Generation InterconnectionSolar
AF2-142Nevada 345 kVIllinoisActiveCommonwealth Edison Company150.0150.090.0Generation InterconnectionSolar
AF2-143Powerton-Nevada 345 kVIllinoisActiveCommonwealth Edison Company150.0150.090.0Generation InterconnectionSolar
AF2-177Sorenson-DeSoto #2 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.200.0200.026.0Generation InterconnectionWind
AF2-182Nelson-Lee County 345 kV IIIllinoisActiveCommonwealth Edison Company500.0300.00.0Generation InterconnectionSolar
AF2-199Nelson-Electric Junction 345 kVIllinoisActiveCommonwealth Edison Company400.0100.060.0Generation InterconnectionSolar
AF2-200Nelson-Electric Junction 345 kVIllinoisActiveCommonwealth Edison Company600.0200.0120.0Generation InterconnectionSolar
AF2-222Madisonville DP-Twitty's Creek 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)167.0167.0100.0Generation InterconnectionSolar
AF2-225McLean 345 kVIllinoisActiveCommonwealth Edison Company500.0150.063.0Generation InterconnectionSolar
AF2-226Katydid Road 345 kVIllinoisActiveCommonwealth Edison Company350.050.020.0Generation InterconnectionStorage
AF2-296Madera 34.5 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC20.020.012.0Generation InterconnectionSolarN/A
AF2-299Fields 34.5 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)18.018.010.8Generation InterconnectionSolarN/A
AF2-319Katydid Road 345 kVIllinoisActiveCommonwealth Edison Company400.050.020.0Generation InterconnectionStorage
AF2-349SILVER LAKE- CHERRY VALLEY 345 KVIllinoisActiveCommonwealth Edison Company300.0300.00.0Generation InterconnectionSolar
AF2-350Kensington 138 kVIllinoisActiveCommonwealth Edison Company100.0100.060.0Generation InterconnectionSolar
AF2-376Timber Switch 138 kVOhioActiveOhio Power Company147.050.020.0Generation InterconnectionStorage
AF2-388Keystone-Desoto 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.200.0200.035.2Generation InterconnectionWind
AF2-396Stinger 138 kVMichiganActiveAEP Indiana Michigan Transmission Company, Inc.200.0200.0200.0Generation InterconnectionSolar; Storage
AF2-404Gladys DP-Stonemill 69 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)60.00.00.0Generation InterconnectionStorage
AF2-407Fall Creek 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.300.0300.0300.0Generation InterconnectionStorage
AF2-441Burnham 138kVIllinoisActiveCommonwealth Edison Company200.0200.080.0Generation InterconnectionStorage
AG1-021Jetersville-Ponton 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)86.020.010.8Generation InterconnectionSolar
AG1-090Philipsburg 115 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC95.095.030.0Generation InterconnectionSolar; Storage
AG1-105Mount Laurel-Barnes Junction 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)90.090.054.0Generation InterconnectionSolar
AG1-106Thelma 230 kVNorth CarolinaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)143.023.016.0Generation InterconnectionSolarN/A
AG1-109Valley 138 kVMichiganActiveAEP Indiana Michigan Transmission Company, Inc.50.00.025.0Generation InterconnectionStorage
AG1-118Sugar Grove-Waterman 138kVIllinoisActiveCommonwealth Edison Company300.0300.0180.0Generation InterconnectionSolar
AG1-124Gladstone 138 kVVirginiaActiveAppalachian Power Company90.090.053.01Generation InterconnectionSolar
AG1-127Crego Rd 138 kVIllinoisActiveCommonwealth Edison Company190.095.157.1Generation InterconnectionSolar
AG1-135Garner-Lancaster 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)60.060.036.0Generation InterconnectionSolar
AG1-153Heritage 500 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)75.075.030.0Generation InterconnectionStorage
AG1-226Dequine-Eugene 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.450.0450.0142.0Generation InterconnectionSolar
AG1-285Chase City-Central 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)125.0125.075.0Generation InterconnectionSolar
AG1-320Glendale-Stephensburg 69 kVKentuckyActiveEast Kentucky Power Cooperative, Inc.82.082.054.8Generation InterconnectionSolar
AG1-341Summer Shade 161 kVKentuckyActiveEast Kentucky Power Cooperative, Inc.106.0106.063.6Generation InterconnectionSolar; Storage
AG1-342Dryburg 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)36.036.021.6Generation InterconnectionSolar
AG1-354Summershade-Green County 161 kVKentuckyActiveEast Kentucky Power Cooperative, Inc.150.0150.090.0Generation InterconnectionSolar
AG1-374Blue Mound 345 kVIllinoisActiveCommonwealth Edison Company300.0300.0180.0Generation InterconnectionSolar
AG1-377Philipsburg 115 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC115.020.06.0Generation InterconnectionSolar
AG1-378Philipsburg 115 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC135.020.06.0Generation InterconnectionSolar
AG1-410Maddox Creek-RP Mone 345 kVOhioActiveOhio Power Company300.0300.0180.0Generation InterconnectionSolar
AG1-411Maddox Creek-RP Mone 345 kVOhioActiveOhio Power Company400.0100.0100.0Generation InterconnectionStorage
AG1-433Keystone-DeSoto 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.100.0100.017.6Generation InterconnectionWind
AG1-436Olive-University Park 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.250.0125.075.0Generation InterconnectionSolar
AG1-447Olive-University Park 345 kVIndianaActiveAEP Indiana Michigan Transmission Company, Inc.305.055.055.0Generation InterconnectionStorage
AG1-460Kincaid-Pana 345 kVIllinoisActiveCommonwealth Edison Company329.030.012.0Generation InterconnectionStorage
AG1-462Cordova 345 kVIllinoisActiveCommonwealth Edison Company255.0255.0153.0Generation InterconnectionSolar
AG1-471Up Church-Wayne County 69 kVKentuckyActiveEast Kentucky Power Cooperative, Inc.54.054.032.4Generation InterconnectionSolar
AG1-536Garner-Northern Neck 115 kVVirginiaActiveVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)137.075.032.0Generation InterconnectionStorage
AG1-548Erie South-Union City 115 kVPennsylvaniaActiveMid-Atlantic Interstate Transmission, LLC150.0150.045.0Generation InterconnectionSolar; Storage
AG1-553Cordova 345 kVIllinoisActiveCommonwealth Edison Company260.0260.00.0Generation InterconnectionSolar

Stability Clusters

Stability analysis was performed by grouping New Service Requests into clusters based on their electrical proximity in order to increase the efficiency of the stability study process. A single stability study is performed for all New Service Requests in the cluster and any reinforcement costs shall be cost allocated proportionally to all New Service Requests in the cluster.

Cluster IndexCluster NameNew Service RequestsStatusExecutive Summary
1Cluster 1AE2-341, AF1-030, AG1-118, AG1-127Analysis Complete - No Issues
2Cluster 2AE1-114Analysis Complete - No Issues
3Cluster 3AF2-350Analysis Complete - No Issues
5Cluster 5AF2-226, AF2-319Analysis Complete - No Issues
7Cluster 7AE2-261, AG1-460Analysis Complete - No Issues
8Cluster 8AE1-172, AE2-223, AF2-225Analysis Complete - No Issues
11Cluster 11AF2-441Analysis Complete - No Issues
13Cluster 13AF2-142, AF2-143Analysis Complete - No Issues
14Cluster 14AF2-095Analysis Complete - No Issues
15Cluster 15AF2-041, AF2-199, AF2-200Analysis Complete - No Issues
16Cluster 16AF1-280, AF2-182, AF2-349Analysis Complete - No Issues
17Cluster 17AF1-296, AG1-462, AG1-553Analysis Complete - No Issues
21Cluster 21AG1-374Analysis Complete - No Issues
23Cluster 23AE1-092Analysis Complete - No Issues
24Cluster 24AF1-233Analysis Complete - No Issues
25Cluster 25AG1-354, AG1-471Analysis Complete - No Issues
26Cluster 26AE2-308Analysis Complete - No Issues
27Cluster 27AF2-111Analysis Complete - No Issues
29Cluster 29AF1-123, AF1-124, AF1-125Analysis Complete - Issues Found
30Cluster 30AF1-294, AF2-115, AG1-021Analysis Complete - No Issues
31Cluster 31AF2-222, AG1-285Analysis Complete - Issues Found
32Cluster 32AF2-120, AG1-135, AG1-536Analysis Complete - Issues Found
34Cluster 34AE2-291, AG1-105, AG1-342Analysis Complete - No Issues
35Cluster 35AE2-185, AE2-283, AF2-404Analysis Complete - No Issues
39Cluster 39AF2-080, AG1-106Analysis Complete - No Issues
44Cluster 44AF2-081Analysis Complete - No Issues
45Cluster 45AF2-042Analysis Complete - No Issues
46Cluster 46AE2-156Analysis Complete - No Issues
47Cluster 47AG1-153Analysis Complete - No Issues
48Cluster 48AF1-128Analysis Complete - No Issues
54Cluster 54AG1-124Analysis Complete - No Issues
55Cluster 55AE2-325, AF1-161, AF1-176, AF2-396, AG1-109Analysis Complete - No Issues
56Cluster 56AG1-410, AG1-411Analysis Complete - No Issues
58Cluster 58AG1-436, AG1-447Analysis Complete - No Issues
60Cluster 60AF2-068Analysis Complete - No Issues
62Cluster 62AF2-177, AF2-407Analysis Complete - No Issues
63Cluster 63AF2-388, AG1-433Analysis Complete - No Issues
64Cluster 64AF1-204, AG1-226Analysis Complete - No Issues
69Cluster 69AF2-010, AG1-548Analysis Complete - No Issues
70Cluster 70AF2-050Analysis Complete - No Issues
71Cluster 71AG1-090, AG1-377, AG1-378Analysis Complete - No Issues
72Cluster 72AF1-238Analysis Complete - No Issues
74Cluster 74AF2-126Analysis Complete - No Issues
84Cluster 84AG1-341Analysis Complete - No Issues
85Cluster 85AG1-320Analysis Complete - No Issues
88Cluster 88AF2-376Analysis Complete - No Issues

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 01 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 01 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 01 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 01 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 01 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 140 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

In the original 2027SP base case, it was found that the system becomes unstable for contingencies P1.13, P4.24, P4.29, P5.06, P5.08 and P7.03 since the units in the City of Rochelle and Mendota areas are connected to the bulk power system just through a single branch, McGirr – Dixon, during post-fault configuration. As such, it appears that local voltage collapse occurs in the weak network conditions during post-fault period. Plots from the dynamic simulations for these simulations are provided in Attachment 4.

To mitigate the instability issue, ESS H440 generating unit was turned off, and LEED (Q57), Mendota Hills (AD1-067) and AD1-013 generating units were dispatched at a reduced capacity in “Alternate Base Case” folder to satisfy the Short Term Emergency (STE) ratings of Haumesser – W. Dekalb 138 kV and McGirr Rd – Dixon 138 kV circuits, and thus secure the case for N-0 and N-1 conditions for unstable contingencies.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 01 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 01 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

Cluster 01 projects meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCAU model of AE2-341 GEN, AF1-030 GEN, AG1-118 GEN1, AG1-118 GEN2 and AG1-127 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

Fictitious frequency response at AE2-341 generator bus tripped the queue project due to the action of instantaneous under frequency relays when faults were applied to AF1-030/AE2-341 POI. This issue is mitigated by increasing the relay pickup time for frequency relay instance 94312513 to 20 seconds to avoid fictitious frequency tripping of the unit.

Fictitious frequency response at the AF1-030 generator bus tripped the queue project due to the action of instantaneous over frequency and under frequency relays when faults were applied to AF1-030/AE2-341 POI. This issue is mitigated by increasing the relay pickup time for frequency relay instances 94359509 and 94359511 to 20 seconds to avoid fictitious frequency tripping of the units.

AF1-030 unit tripped due to an overvoltage spike following fault clearing. This was mitigated by adding a small pick-up time of 0.113 seconds to the relay instance 94359501 to resolve the overvoltage tripping.

The AC1-110 unit tripped by angle deviation relays for 3 contingencies (P4.48.3B3, P4.50.3B3 and P4.52.3B3). The AC1-111 unit tripped by angle deviation relays for 4 contingencies (P4.39.3B3, P4.44.3B3, P4.45.3B3 and P4.46.3B3). These tripping events were observed in previous stability analysis studies for AC1-109/110/111 and AF2-363/366 and therefore are not attributed to Cluster 01 stability analysis.

The DVR (Dynamic Voltage Recovery) criteria have been violated under several contingencies due to instability and unit tripping, particularly at the Mendota location, as observed in events P1.13, P4.24, P4.29, P5.06, P5.08, and P7.03. These contingencies have been simulated with reduced dispatch for several units and no DVR violation has been observed. Additional DVR violations occurred under contingencies P4.48.3B3, P4.50.3B3, and P4.52.3B3, where the tripping of the AC1-110 unit led to angle deviations. Notably, DVR violations identified at the AC1-110 generator bus terminals during contingencies P4.42.3B3 and P4.43.3B3 were not mitigated, as generation buses and points-of-interconnection (Aurora) are not valid monitoring points for assessing DVR compliance. Similarly, violations at the Aurora and Batavia buses (P4.42.3B3 and P4.53.3B3) were not addressed, given that the DVR recovery envelope was breached at only two buses per contingency—below the threshold of ten or more applicable buses required for mitigation to be considered.

No mitigations were found to be required.

Table 1: TC1 Cluster 01 Projects

Project

Fuel Type

Transmission Owner

MFO

Point of Interconnection

AE2-341

Solar

ComEd

150

Sandwich – Plano 138 kV circuit 14609

AF1-030

Solar

ComEd

100

Sandwich – Plano 138 kV circuit 14609

AG1-118

Solar

ComEd

300

Sugar Grove – Waterman 138 kV circuit 11106

AG1-127

Solar

ComEd

95.1

Crego Road 138 kV station

 

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 02 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 02 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 02 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 02 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 02 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 45 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies were identified for this study.

There are no three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic).

There are no three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic).

There are no three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic).

Stations at which the faults listed above will be applied are:

  • AE1-114 POI 138 kV
  • Lancaster TSS 119 138 kV
  • Lena TSS 180 138 kV
  • Maryland TSS 124 138 kV

The SPOG 2-51 (TSS 119 Lancaster automatic line 11904 trip schemes prevent islanding of TSS 969 Ecogrove Generation). The following assumptions were made for contingency development:

  1. TSS 969 Ecogrove Generation will be tripped when one of the following conditions are met:
  1. 138 kV line 11904 circuit breaker is open at TSS 119 Lancaster; or,
  2. 138 kV line 17121 circuit breaker is open AND either 138 kV bus tie 5-7 OR 6-7 is open at TSS 119 Lancaster.

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 02 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 02 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE1-114 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA model of AE1-114 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away of Cluster 02. The CSCR results are summarized in Table 4 through Table 9 and revealed a minimum CSCR value of 3.01 for P4.18, P4.15, P4.16 and so on and a maximum CSCR value of 4.444 for P1.08, P1.06, P0.01.

Table 1: TC1 Cluster 02 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

02

AE1-114

Wind

ComED

150

150

34

Maryland - Lancaster 138 kV Line

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 3 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 3 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 3 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 3 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 3 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 166 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 3 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 3 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 3 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-350 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AF2-350 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system these plots are ignored.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 3 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

3

AF2-350

Solar

ComEd

100

100

60

Kensington 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 5 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 5 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 5 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 5 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 5 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 107 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 5 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 5 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 5 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-226 and AF2-319 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 models of AF2-226 GEN and AF2-319 GEN showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

Initial simulations showed AF2-226 and AF2-319 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. The reactive power settling time was decreased by adjusting the PPC Q/V controller PI gains for both projects (Kp = 1 from 0, Ki = 5 from 0.5). The developer confirmed that the updated controller parameters are acceptable.

Simulations showed AF2-142, AF2-143, and AE1-163 getting stuck in high voltage ride through (HVRT) mode for extended periods after fault clearance for several contingencies. This resulted in a 345 kV POI voltage of about 1.1 pu for more than 5 seconds. For AF2-142 and AF2-143, this was resolved by adjusting the HVRT threshold and deadband to 1.15 pu (from 1.1 pu) and 0.15 pu (from 0.1 pu), respectively. These parameter adjustments were confirmed by the respective project developers. For AE1-163, the dynamic model was updated to the Vestas UDM which was submitted for the AE1-163/AE2-281 necessary study as per the developer’s request.

Initial simulations showed poorly damped oscillations in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. Revision 1 of the AC1-111 dynamic model was used in the last iteration of the AC1-111 dynamic analysis, therefore it is assumed that the AC7B model is accurate relative to what is in the field. The updated dynamic model eliminated these oscillations.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 5 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

5

AF2-226

Storage

ComEd

50

50

20

Katydid Road 345 kV

AF2-319

Storage

ComEd

50

50

20

Katydid Road 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 07 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 07 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 07 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 07 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 07 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 110 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run).
  2. Three-phase faults with normal clearing time.
  3. Single-phase faults with stuck breaker.
  4. Three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic).
  5. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic).
  6. Three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic).

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all the fault contingencies tested on the 2027 peak load case:

  1. Cluster 07 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 07 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AE2-261, AG1-236, and AG1-460 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCAU model of AE2-261, and AG1-236 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

AG1-236 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the models have been tuned to achieve a faster reactive power output settlement by updating Kp and Kc from REPCTA1 module in generator AG1-236.

The tripping of AD2-100 was identified in contingencies P4.68, P4.69, and P4.70, as well as during the Cluster 07 pre-project test. Therefore, it has been confirmed that the tripping of AD2-100 is not caused by the TC1 Cluster 07 queue projects. Tripping was avoided for all events by updating the undervoltage protection settings: Relay 93677405 was adjusted to 0.177 seconds (10 cycles, adding one cycle to the original P4 fault clearing time of 9 cycles).

No mitigations were found to be required.

 

Table 1: TC1 Cluster 07 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

07

AE2-261

Solar

ComEd

299

299

179.4

Kincaid-Pana 345 kV

AG1-460

Storage

ComEd

30

30

12

Kincaid-Pana 345 kV

AG1-236

Wind

ComEd

180

180

23.4

Lanesville- Brokaw

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 08 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 08 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 08 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 08 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 08 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 110 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic);
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the ComEd 345 kV transmission system.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 08 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 08 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AE1-172, AE2-173, AE2-223, and AF2-225 meet the 0.95 leading and lagging PF requirement.

The AE1-205 unit tripped by undervoltage relays for 4 contingencies (P4.61, P4.62, P4.63, P4.64). Contingencies P4.61, P4.62, P4.63 and P4.64 involved a three-phase stuck breaker fault at Pontiac Midpoint 345 kV clearing in 13 cycles. As per NERC Standard PRC-024 requirements, these contingencies were found to meet the corresponding NERC PRC-024 LVRT criteria. A similar tripping issue was observed in AF2-252/AF2-352 dynamic study.

AF2-225 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the model is tuned by adjusting the Kc parameter in the plant controller (REPCA1) to 0.1 from 0 to achieve a faster reactive power output settlement. The change has been confirmed by the developer.

The IPCMD and IQCMD states in the REGCAU model of AE2-173 GEN, and AE2-223 GEN, and AF2-225 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

Fictitious post-fault overvoltage tripping at AF2-252 and AF2-352 generator buses tripped the queue projects due to the action of instantaneous over-voltage relays for contingencies P4.62 and P4.63. Therefore, the relay pickup times for voltage relay instances 96061504 and 95961504 were set to 0.0305 seconds from 0.001 to avoid fictitious voltage tripping of the units.

No mitigations were found to be required.

Table 1: TC1 Cluster 08 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

08

AE1-172

Wind

ComEd

255

255

44.88

Loretto-Wilton Center 345 kV

AE2-173

Battery Storage

ComEd

50

50

50

McLean 345 kV

AE2-223

Wind

ComEd

150

150

19.5

McLean 345 kV

AF2-225

Solar

ComEd

150

150

63

McLean 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 11 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 11 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 11 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 11 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 11 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 129 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 11 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 11 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-441 meets the 0.95 leading and lagging PF requirement.

AF2-441 GEN post fault terminal voltage was more than 1.05 p.u. for several contingencies. This issue did not cause instability in the system and the dynamic models were tuned to achieve a post fault terminal voltage less than 1.05 by adjusting Kc parameter in the REPCA1 module of AF2-441 to 0.1.

The IPCMD and IQCMD states in the REGCAU model of AF2-441 GEN, and AG1-298 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 11 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

11

AF2-441

Storage

ComEd

200

200

80

Burnham 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 13 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 13 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 13 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 13 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 13 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 125 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers);
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 13 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 13 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 13 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-142 and AF2-143 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AF2-142 GEN, AF2-143 GEN, AA1-018 GEN1, AA1-018 GEN2, and AD2-038 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

Voltage spikes over 1.2 pu lasting less than one cycle were observed in some contingencies at Nevada 345 kV, AF2-143 POI, and AE2-281 POI. The voltage spikes are a result of the high reactive current injection of inverter-based generation and instantaneous voltage recovery at fault clearance. Note that RMS simulation is not an accurate tool to evaluate temporary over-voltages produced by inverter-based generation.

 

Simulations showed AF2-142, AF2-143, and AE1-163 getting stuck in high voltage ride through (HVRT) mode for extended periods after fault clearance for several contingencies. This resulted in a 345 kV POI voltage of about 1.1 pu for more than 5 seconds. For AF2-142 and AF2-143, this was resolved by adjusting the HVRT threshold and deadband to 1.15 pu (from 1.1 pu) and 0.15 pu (from 0.1 pu), respectively. These parameter adjustments were confirmed by the respective project developers. For AE1-163, the dynamic model was updated to the Vestas UDM which was submitted for the AE1-163/AE2-281 necessary study as per the developer’s request.

Initial simulations showed poorly damped oscillations in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. The updated dynamic model eliminated these oscillations.

Sensitivity studies were conducted on more severe scenarios (P4.19.3B1, P4.21.3B1, P4.53.3B3) for Powerton generator stability in the light load case. Initial simulations resulted in a numerical instability for P4.53.3B3 which was resolved by reducing generation at Elwood E.C. such that the pre-contingent loading on Elwood – Goodings Grove 345 kV circuit 11620 is at 100% of RATE A (1201 MVA). The results are stable for the contingencies studied.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 13 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

13

AF2-142

Solar

ComEd

150

150

90

Nevada 345 kV

AF2-143

Solar

ComEd

150

150

90

Powerton – Nevada 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 14 are listed in              Table 1 below. This report will cover the dynamic analysis of Cluster 14 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 14 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 14 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 14 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 139 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time (and with unsuccessful high speed reclosing);
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line (and with unsuccessful high speed reclosing).

There are no three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic);

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 14 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 14 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-095 meets the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from AF2-095. The CSCR revealed minimum and maximum CSCR values of 3.241 for P2.01 and 5.558 for P1.03, respectively.

Nearby queues AC2-154 and AD2-060, located at the same POI (Davis Creek 138 kV) are GNETTED due to the unavailability of updated user defined models that are compatible with PSS/E 34.

The IPCMD and IQCMD states in the REGCAU models of AF2-095 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system. 

The DVR (Dynamic Voltage Recovery) criteria have been violated under several contingencies (P2.12, P4.33.3B3 and P4.34.3B3)  at the University Park and Wilmington buses were not addressed, given that the DVR recovery envelope was breached at only one bus per contingency — below the threshold of ten or more applicable buses required for mitigation to be considered.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 14 Projects

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

Point of Interconnection

14

AF2-095

Solar

ComEd

144

Davis Creek TSS 86 138 kV Substation

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (AF2-041/AF2-199/AF2-200) in PJM Transition Cycle 1, Cluster 15 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 15 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 15 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 15 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 15 projects were tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. Steady-state condition and 76 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run),
  2. Three-phase faults with normal clearing time,
  3. Three-phase bus faults with normal clearing time,
  4. Three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic),
  5. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic),
  6. Three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic),
  7. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic),
  8. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the ComEd 345 kV transmission system.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 15 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  2. The system with Cluster 15 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-041, AF2-199, and AF2-200 meet the 0.95 leading and lagging PF requirement.

AF2-041 exhibited slow reactive power recovery within the 20-second simulation window for several contingencies. This issue did not result in system instability. The model was tuned to improve reactive power settling time by updating the Kp parameter to 2.0, the Ki parameter to 3.0, and setting the VCFlag to 0 in the REPCA1 module.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied. The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from AF2-041/AF2-199/AF2-500. The CSCR revealed minimum and maximum CSCR values of 3.66 for P1.17 and 5.25 for P0.01, respectively.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 15 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

15

AF2-041

Solar

ComEd

300

300

180

Nelson-Electric Junction 345 kV

AF2-199

Solar

ComEd

100

100

60

Nelson-Electric Junction 345 kV

AF2-200

Solar

ComEd

200

200

120

Nelson-Electric Junction 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 16 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 16 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 16 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 16 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 16 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 112 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers);
  6. Three-phase faults with loss of multiple-circuit tower line;

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 16 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 16 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 16 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF1-280, AF2-182, and AF2-349 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 models of AF1-280 GEN, AF2-182 GEN, AF2-349 GEN1, and AF2-349 GEN2 showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

Voltage response at Brooke wind generator terminal bus (631215) caused the generator terminal voltage to drop below 0.892 pu resulting in the unit being tripped instantaneously by voltage relay instance 63121502. The relay pickup time was extended to 3 seconds (PRC-024-3 compliant) to prevent the plant from tripping.

Initial simulations showed a poorly damped oscillation in voltage/reactive power at the Easy Road Type 3 Wind plant for contingency P1.02 (fault at AF1-280/AF2-182 POI on Lee County EC 345 kV circuit). Tuning the Torque controller in the Type 3 wind plant resolved the oscillation:

WTTQA1:

CON(J+11) = 0.98 (spd3, shaft speed for power p3 (pu)) from 1.2

CON(J+13) = 1.0 (spd4, shaft speed for power p4 (pu)) from 1.2

Initial simulations showed a poorly damped oscillation in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. The updated dynamic model eliminated these oscillations.

No mitigations were found to be required.

Table 1: TC1 Cluster 16 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

16

AF1-280

Solar

ComEd

200

200

0

Nelson – Lee County 345 kV

AF2-182

Solar

ComEd

300

300

0

Nelson – Lee County 345 kV

AF2-349

Solar

ComEd

300

300

0

Silver Lake – Cherry Valley 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests AF1-296, AG1-462 and AG1-553 in PJM Transition Cycle 1, Cluster 17 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 17 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 17 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 17 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus, except AF1-296, which was allowed to have a terminal voltage of 1.027 pu.

Cluster 17 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 197 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic).
  5. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic);
  6. Three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic);
  7. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  8. Single-phase faults with stuck breaker (for MISO substations);
  9. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  10. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (for MISO substations);
  11. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies were identified for this study.

Buses at which the faults listed above were applied are:

  • Cordova E.C. TSS 940 (AG1-553/AG1-462 POI) 345 kV
  • Cordova M.E.C. 345 kV
  • Nelson TSS 155 (AE1-134/AA2-030/AA1-146 POI) 345 kV
  • E. Molin (Barstow SUB. 39 M.E.C.) 345 kV
  • Quad Cities STA. 4 345 kV
  • Garden Plain TSS 132 (AF1-296 POI) 138 kV
  • Nelson TSS 155 138 kV
  • AF2-392 TAP 138 kV
  • Sterling Steel (ESS H71) 138 kV
  • Rock Falls TSS 133 138 kV
  • Albany S.S. 138 kV & 161 kV
  • Beaver Channel 161 kV
  • York 161 kV
  • Savanna 161 kV
  • Rock Creek 161 kV
  • SUB 49 161 kV

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 17 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 17 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-553, AG1-462 and AF1-296 meet the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away of Cluster 17. The CSCR results for AF1-296 are summarized in Table 7 through Table 17 and revealed a minimum and maximum CSCR values of 2.64 for P4.84 & P4.86 and 4.45 for P1.64, respectively. The CSCR results for AG1-553 and AG1-462 revealed a minimum and maximum CSCR values of 3.81 for P4.08 & P4.10 and 7.24 for P1.02 & P4.03, respectively.

Specific findings from the simulations for each of the queue projects of Cluster 17 are indicated below.

AG1-553 and AG1-462

The IPCMD and IQCMD states in the REGCA1 models of AG1-553 GEN 1&2 and AG1-462 GEN 1 showed erratic behavior for some contingencies in which AG1-553 or AG1-462 generators have been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

High voltage spikes on the terminal voltages of AG1-462 and AG1-553, occurred in the simulations immediately after fault clearing for a few of the contingencies studied (i.e. fault where spike is observed). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

AF1-296

For 24 contingencies out of 197, the steady state post-contingency terminal voltage of AF1-296 went slightly above 1.05 pu (Et ≈ 1.056 pu – 14 contingencies, Et ≈ 1.051 pu – 10 contingencies). This is due to the fact that the terminal voltage of AF1-296 pre-contingency is 1.027 pu.

High voltage spikes at the terminals of AF1-296 and its POI, Garden Plain 138 kV, occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e. fault where spike is observed]). As, with the WECC models, these voltage spikes are considered a consequence of the model’s limited bandwidth, integration time step and the way it interfaces with the network solution. Therefore, it is estimated that they do not represent the performance of actual equipment and can be ignored in most cases. The spike at Garden Plain is a consequence of the spike at the terminals of AF1-296.

No mitigations were found to be required. However, it is recommended that the developer of AF1-296 provides an adjusted model that allows specifying the generator’s reactive power output at levels that support initial conditions with a terminal voltage close to 1.0 pu.

 

Table 1: Cluster 17 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

17

AF1-296

Wind

ComEd

190.89

190.89

33.6

Garden Plain 138 kV

AG1-462

Solar

ComEd

255

255

153

Cordova 345 kV

AG1-553

Solar

ComEd

260

260

0

Cordova 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 21 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 21 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 21 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 21 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 21 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 39 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run),
  2. Three-phase faults with normal clearing time,
  3. Three-phase faults with single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic),
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic).

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the ComEd 345 kV transmission system.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 21 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 21 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-374 meets the 0.95 leading and lagging PF requirement.

 

 

 

The AE1-205 unit tripped by undervoltage relays for 4 contingencies (P4.23, P4.24, P4.25, and P4.26). Contingencies P4.23, P4.24, P4.25, and P4.26 involved a three-phase stuck breaker fault at Pontiac Midpoint 345 kV clearing in 13 cycles. As per NERC Standard PRC-024 requirements, these contingencies were found to meet the corresponding NERC PRC-024 LVRT criteria. A similar tripping issue was observed in AF2-252/AF2-352 dynamic study.

 

Fictitious post-fault overvoltage tripping at AF2-252 and AF2-352 generator buses tripped the queue projects due to the action of instantaneous over-voltage relays for contingencies P1.02, P1.03, P4.10, P4.25 and P4.26. Therefore, the relay pickup times for voltage relay instances 96061504 and 95961504 were set to 0.0305 seconds to avoid fictitious voltage tripping of the units. With this updated relay settings only P1.03 was tripping. Both relay instances have been updated to 0.035 seconds to avoid this tripping.

 

The IPCMD and IQCMD states in the REGCAU model of AG1-374 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from Cluster 21. The CSCR results are summarized in Table 8 through Table 11 and revealed a minimum and maximum CSCR values of 3.11 for P4.15, P4.16, P4.19 and P4.20 and 7.02 for P1.04, respectively.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 21 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

21

AG1-374

Solar

ComEd

300

300

180

Blue Mound 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 23 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 23 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 23 projects will meet the dynamics requirements of the NERC, Dayton and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 23 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer. Four dispatch scenarios were considered for AG1-323, which is a hybrid solar/storage project where the aggregate machine capability exceeds MFO. The dispatch scenarios are given in the following table.

 

AG1-323 Dispatch Scenarios

Dispatch Scenario

Description

Solar Pgen (MW)

Storage Pgen (MW)

1

AG1-323 solar dispatched to maximum power output. AG1-323 storage dispatched such that the net active power injected by AG1-323 is equal to MFO at the POI.

37.77

4.63

2

AG1-323 storage dispatched such that the net active power injected by AG1-323 is equal to MFO at the POI. AG1-323 solar offline.

offline

42

3

AG1-323 Solar and Storage dispatched proportionally, prorated to the aggregate inverter MVA, such that the net active power injected by AG1-323 is equal to MFO at the POI.

19.2

22.8

4

AG1-323 Solar and Storage dispatched at maximum power output. Net active power injected by AG1-323 exceeds the requested MFO at the POI.

37.77

44.9

 

 

Cluster 23 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 193 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 23 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 23 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 23 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE1-092 and AG1-323 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA1 models of AE1-092 GEN, AG1-323_GEN1 and AG1-323_GEN2 showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 23 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

23

AE1-092

Solar

Dayton

206.55

206.6

96.4

Blue Jacket – Kirby 138 kV

AG1-323

Solar

Dayton

40

40

40

Blue Jacket 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 24 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 24 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 24 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 24 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 24 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 154 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 24 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 24 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 24 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-233 and AF2-307 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCAU model of AF1-233 GEN and AF2-307 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

Dynamic simulations showed that AF2-307 inverter reactive power output was being limited by the inverter controls (REECA1) below the 0.95 dynamic power factor requirement. The issue was resolved in consultation with the developer  by adjusting the inverter control parameters as follows:

•       REECA1:

o       CON(J+15) = 2 (VMAX (pu), Max. limit for voltage control) from 1.1

o       CON(J+16) = 0 (VMIN (pu), Min. limit for voltage control) from 0.9

 

AF2-111 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 24 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

24

AF1-233

Solar

EKPC

188.5

188.5

113.1

Flemingsburg – Spurlock 138kV

AF2-307

Solar

EKPC

64.2

64.2

39.6

Hope – Blevins Valley Tap 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 25 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 25 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 25 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 25 projects have been dispatched online at maximum power output, and voltage schedules set to achieve near unity power factor at the high side of the main transformer.

 

       Cluster 25 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 133 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 25 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 25 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 25 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-354 and AG1-471 meet the 0.95 leading and lagging PF requirement.

 

AG1-471 generator unit remained at High Voltage Ride Through mode for several  contingencies. As a result, the AG1-471 generator terminal voltage remained at approximately 1.12 pu after fault recovery which exceeds the range of 0.95 pu – 1.05 pu. This issue caused the voltage relay stage set to 1.1 pu for 10 seconds to pick up and trip AG1-471 generating unit. Modifying CON(J+1): Vup to 1.16 pu of the REECA1 model resolved the issue of AG1-471 getting stuck in HVRT mode and resolved the tripping of the unit. The AG1-471 developer confirmed the proposed settings .

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 25 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

25

AG1-354

Solar

EKPC

150.0

150.0

90.0

Summershade - Green County 161 kV

AG1-471

Solar

EKPC

54.0

54.0

32.4

Up Church-Wayne County 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 26 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 26 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 26 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 26 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 26 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 139 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 26 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 26 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 26 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-308 meets the 0.95 leading and lagging PF requirement.

 

ETERM of AE2-308 GEN went outside the range of 0.95 pu - 1.05 pu in post fault for several contingencies. This issue did not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 model of AE2-308 GEN showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

Due to the breaker configuration at the AE2-308 Point of Interconnection (POI), there is a potential risk of an islanding condition in which AE2-308 could become the sole power source for the load at Three Forks if both the Fawkes and Dale circuits are lost. This scenario could occur during a stuck breaker contingency, where the breaker between the Fawkes and Dale circuits fails to operate. The AE2-308 inverter control strategy includes passive anti-islanding protection. Under this strategy, if the facility becomes islanded, the voltage and/or frequency magnitude at the inverter terminals will rapidly reach set protection thresholds, causing the inverters to trip.

 

Poorly damped oscillations in the rotor speeds and active power of the 1HAEFLING units 1 and 2 were observed for most contingencies. Select contingency was studied without TC1 projects dispatched. The oscillations persists without TC1 projects. Therefore, the issue is not a result of the addition of TC1 projects. Note that these units are using a simple GENCLS model, without an exciter or power system stabilizer.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 26 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

26

AE2-308

Solar

EKPC

100

100

60

Three Forks - Dale 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 27 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 27 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 27 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 27 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 27 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 209 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 27 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 27 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 27 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-111 and AG1-526 meet the 0.95 leading and lagging PF requirement.

 

The provided AF2-111 power plant controller model (REPCA1) did not include a reactive power droop on the voltage controller. It is expected to have a reactive power droop to avoid any interactions with the other plants in the AC system. This was resolved in consultation with the AF2-111 developer  by adding a 5% droop to Q/V controller in the plant controller model (REPCA1).

 

The provided AG1-526 power plant controller model (REPCA1) did not include a reactive power droop on the voltage controller. It is expected to have a reactive power droop to avoid any interactions with the other plants in the AC system. This was resolved in consultation with the AG1-526 developer  by adding a 5% droop to Q/V controller in the plant controller model (REPCA1).

 

Poorly damped oscillations in the rotor speeds and active power of the 1HAEFLING units 1 and 2 were observed for most contingencies. It was observed that the oscillations persist without TC1 projects.  Therefore, the issue is not a result of the addition of TC1 projects. Note that these units are using a simple GENCLS model, without an exciter or power system stabilizer.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 27 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

27

AF2-111

Solar

EKPC

250

250

150

North Clark – Spurlock 345 kV

AG1-526

Solar

EKPC

222

222

133.2

West Gerrard 345 kV

 

 

 

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 29 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 29 projects.

 

Table 1: Transition Cycle 1 Cluster 29 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

29

AF1-123

Wind

Dominion

833

833

253.2

Harper 230 kV

AF1-124

Wind

Dominion

836

836

254.1

Harper 230 kV

AF1-125

Wind

Dominion

820

820

249.3

Harper 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 29 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 29 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 29 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 29 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

This analysis currently was performed using the PSSE library models provided the developer.  Dominion Energy Transmission provided the models for the FACT’s devices for the AF1-123, AF1-124, and AF1-125 queue projects.

 

Cluster 29 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 133 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Single-phase faults with loss of multiple-circuit tower line.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Transmission Owner criteria:

  • Cluster 29 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 29 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-123, AF1-124 and AF1-125 met the 0.95 lagging and leading power factor requirements at the point of interconnect (POI) at Harpers 230 kV substation.

 

The results of the analysis identified that the addition of the AF1-123, AF1-124 and AF1-125 queue projects resulted in instability in a majority of contingencies. The following mitigation is required to maintain stability:

  • Add a second 500 kV line from the Updated Fentress to the Yadkin substations
  • Add two 230 kV gas-insulated lines (GILs) from the existing Fentress to the New Fentress substations
  • All 230 kV breakers (212822, 269T2128, 26922, 224022-1, 224022-2, 208722, W22, L122, L322, H22, SC122, SC322, SC422, SV122, and the new breakers G1 and G2 for the gas insulated lines) at Fentress 230 kV Substation require a 14 cycle clearing time
  • Dual pilot protection is required for the Fentress to AD1-033 POI 230 kV line circuit 2240

No voltage or frequency protection trips occurred for AF1-123, AF1-124 and AF1-125 queue projects using the settings provided.

 

The AF1-123, AF1-124 and AF1-125 queue projects exhibited slow active power recovery after the fault cleared and this is recovery was expected based on the model documentation provided for the OEMs’ wind turbine. The WGOWECC controller, clamps the active power at 95% for up to 5 seconds to ensure steady recovery of the system and then releases the active power to 100% to restore full operation.

 

An EMT analysis and stability analysis using a PSS/E user defined model is recommended for AF1-123, AF1-124 and AF1-125 due to the CSCR values being less than 3. A user defined model is under development by the IC and it will be evaluated as a sensitivity once the model initializes properly.

 

AE2-156 reactive power and terminal voltage recovery was not settling to a steady state value during the analysis. However, it was observed that reactive settling doesn’t violate PJM or Dominion’s criteria. The models were tuned to achieve a faster recovery in Cluster 46 Phase 2 Stability Analysis.

 

AE2-051 reactive power and terminal voltage recovery was not settling to a steady state value during the analysis. The models can be tuned to achieve a faster recovery upon request.

 

AB2-169 generator tripped for overvoltage’s above 1.25 p.u. The unit rode through when the pickup timer  was increased from 0.0 seconds to 0.0125 seconds.

 

Executive Summary for Dynamic Stability Analysis using PSCAD/EMT

 

The EMT dynamic performance analysis was revelated with the latest PSCAD models pprovided by CVOW (AF1-123, 124 & 125) generation developer.   A detailed model quality testing was performed. Below are some deficiency and corresponding update that were applied to the plant model.

 

  • CVOW initialization issues were cured by using a stiff voltage source model at POI during the initialization period and disconnected later in the simulation.
  • Pi-circuit equivalents for 66 kV IAC cables were updated to Bergeron models using best available data.
  • Onshore cable section was updated into onshore and HDD sections using best available data.
  • Earthing transformer model was included at the 66 kV delta winding of OSS transformer.
  • OSS LTC transformer taps were set to match values used for TC1 analysis.
  • Harpers STATCOM model was updated to latest OEM model.

 

Preliminary results of CVOW performance for Summer peak and Light Load system conditions for select TPL contingencies indicate the following:

 

  • Instability of the project post-fault was observed for select P1 and P6 contingencies prior to the inclusion of all proposed upgrades.
  • With the inclusion of the proposed upgrades namely the 500 kV Line 5005 between Fentress and Yadkin and two GIL circuits between new and existing Fentress 230 kV, CVOW fully recovers post-fault for a severe P4 contingency.
  • The preliminary results demonstrate the impact of the weak system strength and the improvements provided by the proposed upgrades.
  • Analysis of CVOW performance for severe P6 contingencies with the proposed upgrades is ongoing.
  • Investigation of partial nuisance tripping of CVOW post-fault is also on-going for other contingencies and system conditions.

 

CVOW Flicker

 

Preliminary analysis shows flicker issue induced by CVOW project. Preliminary flicker analysis was conducted using a range of ramp rates in the absence of data on power fluctuation in response to wind speed variation. To assess flicker impact, MEPPI evaluated multiple wind profiles, spanning from conservative scenarios to less conservative ramp rates. Results indicate that the ramp rate significantly influences the flicker observed at the POI and we violate the criteria of 1 Pst for various profiles considered. Flicker analysis was performed in PSCAD using detailed models of the CVOW project and a system equivalent at the POI.  In order to mitigate the flicker issue an addition of 300 MVAR STATCOM will need to be installed at Fentress 230 kV Substation.

 

Note:

 

TC1 Phase 3 Dynamic  Stability analysis has been completed by using library model provided in TC1 Phase 2.  For TC1 Phase 3, a PSSE User Defined Model was requested due to low SCR concerns in the area. The CVOW project developer provided a User Defined Model that did not work properly in the TC1 base case. The CVOW  project development team is actively working on getting an updated User Defined Model for the AF1-123/AF1-124/AF1-125 projects from Siemens Gamesa Renewable Energy (SGRE). This updated model was not ready at the time TC1 Phase 3 studies concluded, and CVOW will need to initiate a Necessary Study request post GIA to have the updated User Defined Model provided to PJM to perform a Dynamic Stability analysis for the AF1-123/AF1-124/AF1-125 projects.

Also, CVOW notified PJM of a change for nineteen (19) of the GSUs that are planned to be installed for the CVOW Project for Queue Position AF1-123 (OSS T1L11). Note that these 19 GSUs – installed in 19 of the 59 wind turbine generators – have been manufactured and have higher impedance values that was in the original design. Following evaluation, it has been determined that these changes in impedances to these 19 units do not affect the MFO/gross output, have very limited changes for the  losses, and the MW output at the POI will be changed, but insubstantially. The other queues AF1-124 & AF1-125 are unchanged/unaffected. This GSU change for AF1-123 will also be evaluated as part of the Necessary Study being requested above.

 

Bellow are some of the item that will be captured during post GIA Necessary study request for CVOW project.

 

  1. The User Defined Model dynamic stability analysis for AF1-123/AF1-124/AF1-125 as well as the GSU change for AF1-123.
  2. The EMT Analysis is based on PSCAD Models provided to PJM & DEV-ET on May 19th, the developers needs to confirm that these models are still valid and if updates to these models need to be made to represent changes made in the UDM please provide updated EMT models.
  3. As identified in the TC1 Phase 2 Reports and the June 2025 “EMT Generation Model Review” Report Nuisance Tripping is still occurring which can result in up to 1600 MW Tripping Off-Line.  This tripping is being initiated by the DC Protection Scheme of the WTGs, the developer needs to provide a solution to PJM & DEV-ET for this deficiency.   This solution will be evaluated in the NSA to determine if it resolves the nuisance tripping issue.  
  4. The developer needs to indicate if margin can be increased in the Over-Voltage Ride Through, Under Voltage Ride Through & Frequency Ride-Through to increase the margins from the PRC-024 & IEEE 2800 Requirements as identified in the TC1 Phase 2 Reports and the June 2025 “EMT Generation Model Review” Report.
  5. Preliminary Study Results indicate that the CVOW Project will result in a Pst Value greater than 1.  This will adversely impact Dominion’s Customers the proposed solution to this flicker issue will be to install a 300 MVAR STATCOM at Fentress Substation on the 230 kV Bus.   The developer can provide updated Ramp Rates  as part of the NSA to determine if mitigation is still required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 30 for Phase 3 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 30 projects.

 

Table 1: Transition Cycle 1 Cluster 30 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

30

AF1-294

Solar

Dominion

41

41

22.2

Jetersville - Ponton 115 kV

AF2-115

Solar

Dominion

25

25

13.5

AG1-021

Solar

Dominion

20

20

10.8

AG1-166

Solar

Dominion

20

20

6

Lone Pine 115 kV

AG1-167

Solar

Dominion

15

15

4.5

AG1-168

Solar

Dominion

15

15

4.5

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 30 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case for Phase 2 was used as a starting point and was updated based on latest Cluster 30 data, recommended transmission changes incorporated based on Dominion Energy Phase 2 feedback, and withdrawn generation removed. Cluster 30 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 30 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 30 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. During the Phase 2 analysis contingencies were examined around the POIs and no violations were observed as a result of Cluster 30 projects interconnecting.  Due to this the Phase 3 analysis for Cluster 30 focused on the contingencies at Chase City that resulted in instability caused by Cluster 31 and Cluster 40 during Phase 2.  The Phase 3 analysis examined, 8 initial contingencies and 24 sensitivity contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Three-phase faults with normal clearing time.
  • Single-phase bus faults with normal clearing time.
  • Single-phase faults with stuck breaker.

 

Instability was observed for contingencies when the Chase City to AG1-285 Tap 115 kV circuit was tripped. This outage resulted in instability due to insufficient export paths for the generation along the Farmville to Chase City 115 kV path through the radial connection.  Additionally, the Farmville to Chase City 115 kV path is prone to controller instability due to weak grid conditions determined by the composite short circuit ratio assessment.  The instability was caused by the Cluster 31 queue projects. 

 

To following mitigation was tested and all maintain stability:

  1. Adding a new 115 kV line from AG1-285 to Butcher’s Creek.
  2. Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood.
  3. Upgrade the new AG1-285 substation to a breaker and a half scheme to accommodate 2 x 230/115 kV transformers and a 230 kV line from AG1-285 to Finneywood .

 

The Transmission Owner has elected to upgrade the new AG1-285 substation to a breaker and a half scheme to accommodate 2 x 230/115 kV transformers and a 230 kV line from AG1-285 to Finneywood as the mitigation to the instability. This mitigation is required due to the interconnection of the Cluster 31 queue projects. Cluster 30 queue projects did not cause the instability. The mitigation was further tested for all Phase 2 contingencies and no violations were observed.

 

Nearby projects were found to trip based on their protection settings. The protection trip times were increased during Phase 2 analysis and maintained during the Phase 3 analysis:

 

  • AE1-056 tripped for frequencies below 55 hz for more than 0.001 seconds and the relay pick-up time was increased to 0.034 seconds
  • AE1-056 tripped for frequencies above 65 hz for more than 0.001 seconds and the relay pick-up time was increased to 0.020834 seconds
  • AF2-222 tripped for voltages above 1.3 p.u. for more than 0.001 seconds and the relay pick-up time was increased to 0.012501 seconds

 

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found:

 

  • Cluster 30 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 30 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation was needed to connect the Cluster 30 queue projects.

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis Using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 31 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 31 projects.

 

 

Table 1: Transition Cycle 1 Cluster 31 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

31

AF2-222

Solar

Dominion

167

167

100

Madisonville DP-Twitty's Creek 115 kV

AG1-285

Solar

Dominion

125

125

75

Chase City-Central 115 kV

 

For the Cluster 31 base run, the latest data from DP3 was used to update the models for the Cluster 31 generation in addition to removing withdrawn generation from the dispatch.

 

Cluster 31 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 136 initial contingencies and 169 sensitivity contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

The results of the analysis identified instability for outages of the Chase City – AG1-285 115 kV circuit as observed in the Phase 3 analysis. The mitigation recommended from the Phase 3 analysis was then tested and resolved the instability. Network upgrade N9630 is still recommended. N9630 updates the new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood.

 

AG1-285 DP3 data included  a 0.84 MVA base for the inverters based on  a 25? PQ curve rating.  A sensitivity was performed to determine the impacts of AG1-285 model with inverter rating 0.81 MVA at 35?. The results of the analysis matched when using the 25? and 35? ratings. The network upgrade is still required.

 

 

The following changes were required during Phase 3 analysis that would still apply for the Restudy results: 

 

The protection settings for AE2-259 regarding frequency above 62.5 Hz for more than 0 seconds and frequencies below 56.5 Hz for more than 0 seconds are commented due to tripping of the generator during the Phase 3 analysis.  

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found:

 

  • Cluster 31 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 31 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Executive Summary for Dynamic Stability Analysis Using  PSCAD/EMT

 

Model Quality Testing Report

PSCAD model for Queue project AF2-222 and AG1-285 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each Project

 

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

 

Weak Grid Assessment

This Weak Grid Assessment evaluates two projects from PJM Transition Cycle 1 (TC1) Cluster 31 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The two projects, AF2-222 and AG1-285, were identified in the Cluster Study as having risk of undamped oscillations during a contingency condition and indicating system instability after dynamic simulation analysis in PSS/E. Three potential network upgrades were considered to resolve this instability, and Network Upgrades 2 and 3 were shown to be effective through sensitivity analysis.

This assessment, completed by INS Engineering, aims to verify the impact of Network Upgrade 2 and 3 identified in the Cluster Study, using detailed models in an EMT simulation.  Summary descriptions of each project and the two network upgrades are listed below:

 

Table 3. Summary Description of TC1 Cluster 31 Projects

 

 

 

 

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AF2-222 Courthouse Solar

PV

167

Madisonville DP-Twitty's Creek 115 kV

959310

AG1-285 Quarter Horse Solar

PV

125

Chase City-Central 115 kV

964240

 

The following network upgrades proposed as mitigation in cluster 31 are evaluated in this weak grid assessment:

  • Network Upgrade 2: Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood
    • Evaluated in the main body of this report
  • Network Upgrade 3: Upgrading the new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood
    • Evaluated in Appendix B
    • This option has been selected by the Transmission Owner

First, the individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test in [2] and [3], with model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

For Network Upgrade 2, two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were simulated in the PSCAD detailed system model. For Cluster 31, the following contingency cases were chosen.

 

  • P=1.0pu, 3LG fault, 150ms, on AF2-171 POI to Farmville 230kV and loss of circuit
  • P=1.0pu, 3LG fault, 150ms, on AG1-427 to Finneywood 230kV and loss of circuit

 

Simulation results in PSCAD are summarized below.  It can be observed that both contingency cases using the detailed PSCAD system model results in a stable recovery, matching the results of the Cluster Study. 

 

Table 4. Summary of cases tested in the PSCAD system study with Network Upgrade 2

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 1.0

P=1.0pu, 3LG fault, 150ms, on AF2-171 POI to Farmville 230kV and loss of circuit

Stable

Stable

Case 2.0

P=1.0pu, 3LG fault, 150ms, on AG1-427 to Finneywood 230kV and loss of circuit

Stable

Stable

 

For Network Upgrade 3, three representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. Simulation results in PSCAD are summarized below.  It can be observed that all three contingency cases using the detailed PSCAD system model results in a stable recovery, matching the results of the Cluster Study. 

 

 

Table 5. Summary of cases tested in the PSCAD system study with Network Upgrade 3

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 3.1
(SP1.01)

P=1.0pu, 3LG fault, 150ms, on AF2-222 115 kV on Pamplin 115 kV circuit 154 and loss of circuit

Stable

Stable

Case 3.2
(SP1.10)

P=1.0pu, 3LG fault, 150ms, on AG1-285 POI switching station 115 kV on Chase City 115 kV circuit 1012 and loss of circuit

Stable

Stable

Case 3.3
(SP1.51)

P=1.0pu, 3LG fault, 150ms, on Finneywood 230 kV on AG1-285 – Finneywood 230 kV circuit and loss of circuit 

Stable

Stable

 

The results of this assessment show stable recovery in worst-case contingencies using either Network Upgrade 2 or 3, and support the conclusion from the Cluster Study that these proposed network upgrades mitigate the identified weak grid instability issues.

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 32 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 32 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 32 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

 

 Table 1: Transition Cycle 1 Cluster 32 Projects 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

32

AF2-120

Solar

Dominion

62

62

37.2

Garner – Northern Neck 115 kV

AG1-135

Solar

Dominion

60

60

36

Garner – Lancaster

115 kV

AG1-536

Battery

Dominion

75

75

32

Garner – Northern Neck 115 kV

 

For the Cluster 32 base run, the latest data from DP3 was used to update the models for the Cluster 32 generation in addition to removing withdrawn generation from the dispatch. Contingencies were updated to account for withdrawn projects.

 

Cluster 32 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 105 initial contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

The results of the analysis identified TO criteria violations for outages of the Northern Neck – AE1-155 Tap 115 kV circuit (P103, P105, P409, P410, P412, P423, P501, P502) as observed in the Phase 3 analysis. The mitigation recommended from the Phase 3 analysis resolved the violations. It is recommended that a new second 115 kV transmission line be constructed from Northern Neck to AE1-155 Tap on a separate tower or structure, not sharing with the existing 115 kV transmission line from Northern Neck to AE1-155 Tap, to mitigate voltage instability. A new 115 kV breakers will be required at Northern Neck to complete a 5-breaker ring bus and AE1-155 to complete a 5-breaker ring bus. The two 115 kV line shall not share a common breaker such that a breaker failure or breaker stuck event could take out the two 115 kV lines from Northern Neck to AE1-155 Tap.

 

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found:

 

  • Cluster 32 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 32 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

 

Protection trips for AF1-114 and AF2-091 were observed for some contingencies (P109, P110, P111, P112, P113, P115, P116) in both the pre and post network upgrade analysis. These protection trips were not investigated further for this analysis to determine if the network upgrade was still required after DP3 data changes.

Executive Summary for Dynamic Stability Analysis using PSCAD/EMT

 

Model Quality Testing Report

 

PSCAD model for Queue project AF2-120, AG1-135, AG1-146/147 and AG1-536 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each project

 

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

 

Weak Grid Assessment

 

This Weak Grid Assessment evaluates five projects from PJM Transition Cycle 1 (TC1) Cluster 32 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The five projects, AF2-120, AG1-135, AG1-146, AG1-147, and AG1-536, were identified in the Cluster Study as having risk of undamped oscillations in multiple contingency cases, indicating system instability after dynamic simulation analysis in PSS/E. A network upgrade, a new second 115 kV transmission line from Northern Neck to AE1-155 Tap, was recommended along with evaluation using detailed models in an EMT simulation.

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability and verify the effectiveness of the recommended network upgrade in EMT simulation.  A summary description of each project is listed below:

 

 

Table 3. Summary Description of TC1 Cluster 32 Projects

 

 

 

 

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AF2-120 Cerulean Solar

PV

62

Garner – Northern Neck 115 kV

939240

AG1-135 Moon Corner

PV

60

Garner – Lancaster

115 kV

962860

AG1-146/AG1-147 Merry Point 1 and 2 Solar

PV

100

Garner – Lancaster

115 kV

962970

AG1-536 Mulberry

BESS

75

Garner – Northern Neck 115 kV

939240

 

First, the individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Tests process, model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual project models were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

A representative contingency case from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, was then simulated in the PSCAD detailed system model. For Cluster 32, the following contingency case was chosen.

 

  • Fault ID P1.03: Fault at AE1-155 Tap 115 kV on AE1-155 Tap – Northern Neck 115 kV circuit #1059. Fault cleared with loss of Northen Neck 115/34.5 kV Transformer #1

 

Simulation results in PSCAD are summarized below.  In Case 1a with the PSCAD detailed system model, weak grid oscillations and unstable recovery are observed without the network upgrade. With the network upgrade added in Case 1b, stable recovery is observed due to sufficient grid strength. These results are consistent with the results in the Cluster Study.

 

Table 4. Summary of cases tested in PSCAD system study

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 1a

P1.03, without network upgrade

Unstable

Unstable

Case 1b

P1.03, with network upgrade

Stable

Stable

Case 2a

P1.03, without network upgrade, modified PPC tuning

-

Stable*

* Details in Appendix B. Although a stable response was observed in this case, a detailed tuning evaluation over multiple operating conditions would be needed to verify robustness of the modified tuning.

 

As a potential alternative solution, PPC parameter were tuned to be more appropriate for weak grid conditions and this configuration was evaluated in base case P1.03, without the network upgrade – Case 2a. A stable response was observed in Case 2a, however, a detailed tuning evaluation over multiple operating conditions would be needed to verify robustness of this modified tuning.  As such, the modified tuning results in Appendix B should be considered for information only.

Based on the simulation results described above, the results of this assessment show stable recovery in the worst-case contingency when the network upgrade is included.  These results support the conclusion from the Cluster Study that the proposed network upgrade mitigates potential weak grid instability issues.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 34 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 34 projects.

 

Table 1: Transition Cycle 1 Cluster 34 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

34

AE1-148

Solar

Dominion

90

90

54

Kerr Dam-Ridge Rd

115 kV

AE2-291

Solar

Dominion

102

102

61.2

Grit DP-Perth 115 kV

AF2-297

Solar

Dominion

80

80

48

Sedge Hill 115 kV

AG1-105

Solar

Dominion

90

90

54

Mount Laurel-Barnes Junction 115 kV

AG1-342

Solar

Dominion

36

36

21.6

Dryburg 115 kV

 

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 34 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case for Phase 2 was used as a starting point and was updated based on latest Cluster 34 data, recommended transmission changes incorporated based on Dominion Energy Phase 2 feedback, and withdrawn generation removed. Cluster 34 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 34 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.  

 

Cluster 34 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. During the Phase 2 analysis contingencies were examined around the POIs and no violations were observed as a result of Cluster 34 projects interconnecting.  Due to this the Phase 3 analysis for Cluster 34 focused on the contingencies at Chase City that resulted in instability caused by Cluster 31 and Cluster 40 during Phase 2.  The Phase 3 analysis examined 217 sensitivity contingencies, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line

 

Instability was observed for contingencies when the Chase City to AG1-285 Tap 115 kV circuit was tripped. This outage resulted in instability due to insufficient export paths for the generation along the Farmville to Chase City 115 kV path through the radial connection.  Additionally, the Farmville to Chase City 115 kV path is prone to controller instability due to weak grid conditions determined by the composite short circuit ratio assessment.  The instability was caused by the Cluster 31 queue projects. 

  

To following mitigation was tested and all maintain stability: 

  1. Adding a new 115 kV line from AG1-285 to Butcher’s Creek. 
  2. Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood. 
  3. Updating the new AG1-285 230 kV substation to breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood. 

 

The Transmission Owner selected the 3rd mitigation option, which updated the new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood. to maintain stability. This mitigation is required due to the interconnection of the Cluster 31 queue projects. Cluster 34 queue projects did not cause instability.

 

The REGCA1 Accel (CON J+13) parameter was set to 0.7 to improve PSS/E network solution calculations for all IBRs located in dispatch area.

 

Voltage oscillations were observed at Altavista 69 kV. It is determined that Smith Mountain, AEP generator, is the source of this oscillation. Gnetting the Smith Mountain generators improved PSS/E network solution calculations. It is recommended for Smith Mountain dynamic model to be revised.

 

Nearby projects were found to trip based on their protection settings. The protection trip times were increased during Phase 2 analysis and maintained during the Phase 3 analysis:

  • AD2-033 tripped for overvoltage protection model for voltage above 1.4 p.u. and the time delay setting was update from 0.001 to 0.0208 seconds.
  • AE2-185 tripped for overvoltage protection model for voltage above 1.2 p.u. and the time delay setting was update from 0.001 to 0.0542 seconds.
  • AE2-187 tripped for overvoltage protection model for voltage above 1.175 p.u. and the time delay setting was update from 0.21 to 0.4042 seconds.
  • AE2-187 tripped for overvoltage protection model for voltage above 1.2 p.u. and the time delay setting was update from 0.001 to 0.3875 seconds.
  • AE2-283 tripped for underfrequency protection model for frequency below 55 Hz and the time delay settings was updated from 0.01 to 0.0167 seconds.
  • AF2-404 tripped for underfrequency protection model for frequency below 55 Hz and the time delay settings was updated from 0.01 to 0.0167 seconds.  

 

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found: 

 

  • Cluster 34 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 34 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes in Dominion area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds,  except where protective action isolates that bus.
  • For Dominion area, the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

It is recommended that future model submissions be validated with the settings proposed in this study. If model data and settings differ, then a transient stability study is recommended to validate the new model data and settings.

 

No mitigation was needed to connect the Cluster 34 queue projects. 

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis Using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 35 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 35 projects.

 

Table 1: Transition Cycle 1 Cluster 35 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

35

AE2-185

Solar

Dominion

60

60

36

Gladys DP – Stonemill 69 kV

AF2-404

Battery

Dominion

0

0

AE2-283

Solar

Dominion

53

53

28

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 35 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 35 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 35 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 35 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

For Cluster 35 the dispatch of the study units was based on two scenarios.

  • Scenario 1: MFO met with solar generation and energy storage offline (solar output = 61.9 MW and storage is offline)
  • Scenario 3: MFO met with the solar generation and energy storage dispatched proportionally to their power capability (solar output = 47.44 MW and storage output = 14.56 MW)

 

Cluster 35 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 75 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 35 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 35 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy and AEP’s transmission planning criteria.
    • Dominion Energy:
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
    • AEP:
      • 0.92 p.u. to 1.05 p.u. for all voltage levels for each NERC Category Contingency
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The results of the analysis indicated all evaluation criteria were met. The following observations were made.

 

The initial results showed that Cluster 35 generators units exhibited slow reactive power recovery for several contingencies, Power Plant Controller (PPC) freezing, divergence and low frequency controller oscillations. These issues did not cause instability, and the generating units were tuned to achieve a faster recovery with better response.

The following adjustments were required for the respective queue projects based on the analysis results:

 

  • For AE2-187 the following adjustments were made:
    • The REECA1 Vup (p.u.) (CON J+1) parameter was set to 1.15 p.u to mitigate PPC freezing
    • Generator tripped for overvoltage protection model for voltage above 1.21 p.u and the time delay setting was updated from 0.16 to 0.3 seconds to allow generator to ride through the fault

 

  • For AE2-283 the following adjustments were made:
    • The REGCA1 Accel (CON J+13) parameter was set to 0.5 to improve PSS/E network solution calculations

 

  • For AC1-122 the following adjustments were made:
    • The REPCA Ki (CON J+2) parameter was changed from 0 to 10 to improve reactive power recovery

 

During phase 3 analysis all generations near Cluster 35 (AC1-042, AC1-145, AE2-185, AE2-187, and AF2-404) have their REGCA1 Accel set to 0.7. This was implemented as part of a phase 2 observation.  It should be noted that this parameter does not affect the performance or recovery of the renewable model, but is used to smooth the voltage and angle calculations within PSS/E.

 

Voltages above 1.05 p.u. were observed at Altavista 69 kV. This is due to Altavista 138-69 kV load tap changer operating at 1.10 p.u. to maintain the Altavista 69 kV scheduled voltage. A significant voltage drop was observed between Altavista, Gladys Tap, Altavista DP, and Mt Airy Tap due to the amount of generation served within the Altavista 69 kV system. To ensure that the post contingency voltage is below 1.05 p.u., the Altavista 138/69 kV load tap changing transformer would need to operate at 1.0375 p.u. tap and under System Normal (P0) conditions, would produce a 0.968 p.u. voltage on the Altavista 69 kV bus, which is within Dominion Energy’s P0 voltage levels. A voltage coordination study is recommended in the future to determine an acceptable voltage schedule for the Altavista 138/69 kV load tap changing transformer to coordinate with the generations served in the Altavista 69 kV system.

 

AE2-185, AF2-404, AE2-283, AC1-042 and AE2-187 were observed to have controller oscillations for a few faults such as P415. This is not a concern, and IC can tune their model to eliminate this behavior.

 

AD1-131, and AF2-107’s reactive power was observed to not settle within the 30 second simulation window for various faults. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement.

 

Low-frequency oscillations were observed for AE1-250 that were positively damped and settled in less than 15 seconds.  This issue did not cause instability in the system.

 

The AE2-185 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

The AE2-185 and AF2-404 BESS queue projects combined met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

The AE2-283 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

A voltage coordination study and Electromagnetic Transients (EMT) study around Altavista is recommended due to the findings of this analysis.  Additionally, any future projects connecting near Altavista should provide EMT models for their facility.

 

No mitigations were found to be required

 

Executive Summary for Dynamic Stability Analysis Using  PSCAD/EMT

 

Model Quality Testing Report

 

PSCAD model for Queue project AE2-185/AF2-404 and AE2-283 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each project

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

Weak Grid Assessment

 

This Weak Grid Assessment evaluates three projects from PJM Transition Cycle 1 (TC1) Cluster 35 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The three projects, AE2-185, AF2-404, and AE2-283, were identified in the Cluster Study as having potential risk of weak grid instability during contingency conditions after dynamic simulation analysis in PSS/E. System reinforcement was found to not be required, although evaluation using detailed models in an EMT simulation was recommended.

 

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability due to low short circuit ratio as identified in the Cluster Study, using detailed models in an EMT simulation.  A summary description of each project can be found below:

Table 3. Summary Description of TC1 Cluster 35 Projects

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AE2-185 / AF2-404 Pigeon Run Solar and BESS

PV + BESS

60

Gladys DP – Stonemill 69 kV

941800

AE2-283 Gladys Solar

PV

53

Gladys DP – Stonemill 69 kV

942670

 

Individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test process,  model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

Two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. For Cluster 35, the following contingency cases were chosen (all projects operating at rated power pre-fault).

 

  • Fault ID: P1.01: Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35
  • Fault ID: P1.18: Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

 

Simulation results in PSCAD are summarized below.  It can be observed that in case P1.01 the islanded condition results in the projects tripping, similar to the Cluster Study.  Overall system recovery as observed from the remaining 138kV network is stable.  In P1.18, stable recovery is observed in PSCAD and is consistent with the results of the Cluster Study. 

 

Table 4. Summary of cases tested in PSCAD system study

Fault ID

Fault Description

Cluster Study Result

PSCAD Study Result

P1.01

Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35. Islanded condition in the 69 kV subnetwork. Cluster projects expected to trip.

System Stable,
Projects on 69kV trip

System Stable,
Projects on 69kV trip

P1.18

Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

Stable

Stable

 

The results of this weak grid assessment using PSCAD show overall stable system recovery in the two worst-case contingencies and supports the conclusion from the Cluster Study that mitigation's are not required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 39 are listed in Table 1 below. This report will cover the TC1 Phase 3 dynamic analysis of Cluster 39 projects.

 

 

Table 1: Transition Cycle 1 Cluster 39 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

39

AF2-080

Solar

Dominion

150

70

48.5

Chinquapin - Everetts 230 kV

AG1-106

Solar

Dominion

323

23

16

Thelma 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 39 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 39 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 39 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 39 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 39 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 211 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 39 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 39 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Oscillations were observed at the Gaston units for contingencies P4.43, P4.48, P4.52, P4.57, and P4.58. These oscillations did not met Dominion’s 4% damping criteria for local area and were observed to be pre-existing but was exacerbated by dispatched generation at Thelma.  The damping angle with changes to the generation dispatched at Thelma. The results indicate that reducing generation in the surrounding area leads to improved damping performance at Gaston and it is concluded that the oscillations at Gaston were not caused by the TC1 Cluster 39 projects.

 

The Transmission Owner has elected to upgrade the Hathaway 115 kV substation by splitting the existing 115 kV bus into two separate buses with a 115 kV line on each bus and the tie switch between line 55 and 80 was closed. Additionally, Line #1001 was opened at Battleboro, resulting in it becoming a radial line from Chestnut Substation. Contingency definitions at the Hathaway 115 kV substation were updated based on topology change, and the analysis was performed. Oscillations at Gaston continue to persist and were unaffected by the topology changes. No other violations occurred.

 

AF2-080 queue project did not meet the 0.95 lagging power factor measured at high side of the main transformer. When the facility was tested at its maximum lagging reactive capability, voltages above 1.10 p.u. were observed at the inverter terminal. To ensure that the facility can provide its lagging power factor without high voltages at the inverter terminal, it is recommended that the tap on the high side of the main transformer be adjusted from 1.0 to 1.025. An additional 5.42 Mvar is required to meet the 0.95 lagging power factor. The AF2-080 queue project met the 0.95 leading power factor measured at high side of the main transformer.

 

AG1-106 is an uprate of AB1-132 and AC1-086. The measurement point for the power factor requirements per the Interconnection Service Agreement (ISA) is at the generator terminals for AB1-132 and AC1-086.  AG1-106’s power factor requirements is measured at the high side of the station transformer.  Due to this three power factor assessments were included to bound the lagging deficiencies observed.  The following lagging deficiencies were observed for AG1-106 depending on the measurement’s points enforced for each test.

 

  • With AG1-106 online, and AB1-132 and AC1-086 offline to ensure the losses created by the AB1-132 and AC1-086 generators are not counted against AG1-106. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer.
  • With AG1-106 and AB1-132 online, AC1-086 offline to consider the shared high side of main station transformer. AB1-132’s measurement point in the ISA is not enforced in this test. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer. However, voltage violation were observed at the generator terminals with the voltage of 1.196 p.u. at AB1-132 and 1.147 p.u. at AG1-106.
  • AG1-106, AB1-132, and AC1-086 online to consider the shared high side of main station transformer. AB1-132 and AC1-086 measurement point in the ISA are not enforced in this test. The lagging power factor deficiency is 49.38 Mvar.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 44 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 44 projects.

 

Table 1: Transition Cycle 1 Cluster 44 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

44

AF2-081

Solar

Dominion

80

80

56

Moyock 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 44 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 44 data, Dominion Energy recommended transmission changes, and withdrawn generation. Projects in vicinity of Cluster 44 has been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for the Cluster 44 project was updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 44 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 123 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

The contingencies were updated based on latest breaker topology at Moyock 230 kV substation, as provided by the Transmission Owner during the Phase 2 final review and generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

  • Cluster 44 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 44 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-081 met the 0.95 lagging and leading power factor requirements by adjusting Main Power Transformer Tap setting to 0.9 p.u for lagging test and 1.05 p.u. for leading test. Interconnection Customer confirmed per “AF2-081 Equivalent Model V34.7 - Dynamic Model Report - 02-13-25. Docx” that transformer is equipped with Load Tap changer.

 

No mitigations were found to be required.

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 45 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 45 projects.

Table 1: Transition Cycle 1 Cluster 45 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

45

AF2-042

Solar

Dominion

500

500

300

Clover-Finneywood 500 kV

AG1-098

Solar

Dominion

107

107

64.2

Briery-Finneywood 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 45 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2027 summer peak case, modified to include applicable projects. Cluster 45 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 45 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 104 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 45 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 45 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The results of the analysis indicated all evaluation criteria were met.

 

The following observations were made:

 

AF2-042’s reactive power took longer than 20 seconds to settle to a steady state value  While this is not a criteria violations the model could be tuned to decrease the settling time.

Contingencies P123, P124 and P125 diverged due to the AG1-098 queue project.  This issue was resolved by updating the PSS/E Dynamic Simulation Acceleration factor from 0.5 and 0.25.

Controller oscillations were observed for AG1-098 Generators 1 & 2 during the fault on selected P4 contingencies. After the fault is cleared, no controller oscillations were observed. This did not cause instability and is not a concern.

 

AD2-202 tripped due to the overvoltage protection (1.12 p.u. in 5 seconds). When the protection model was disabled the units reached terminal voltages above 1.12 p.u. with its reactive power reaching its upper limit.  To resolve the tripping the transformer tap on the high side of the AD1-087 and AD2-202 main station transformers was changed to 1.05 p.u and by changing the two projects to control the POI voltage in the power flow case.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 46 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 46 project.

 

 

Table 1: TC1 Cluster 46 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

46

AE2-156

Battery

Dominion

100

100

100

Yadkin 115 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 46 projects will meet the dynamics requirements of the NERC, Dominion Energy and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak case, modified to include applicable projects. Cluster 46 projects have been dispatched online at maximum power output. The reactive power output for cluster 46 projects will be set near unity power factor at the high side of the station transformer before beginning the analysis

Cluster 46 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 299 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 summer peak case:

  • Cluster 46 projects are able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 46 projects included is transiently stable and post-contingency oscillations should be positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  • The final voltages are within the steady-state voltage ranges below per the TOs transmission Planning Criteria:
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 138, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element trips, other than those either directly connected or designed to trip as a consequence of that fault.

During the model assumptions the following changes were made to the data provided by the developer.

  • REPCAU1 ICON(M) (Bus number for voltage control) to 314513
  • REPCAU1 ICON(M+1) (Monitored branch ‘FROM’)  to 941590
  • REPCAU1 ICON(M+2) (Monitored branch ‘TO’) to 314513
  • REPCAU1 CON(J+13) QMAX to 0.4764
  • REPCAU1 CON(J+14) QMIN to -0.4764
  • REPCAU1 CON(J+22) PMAX to 0.8759
  • REPCAU1 CON(J+26) droop for under-frequency to 20

 

The results of the analysis met the evaluation criteria for all contingencies.

AE2-156 exhibited the reactive power not recovering to a steady-state value, terminal voltages outside of 0.95 to 1.05 p.u. and decreasing active power for several contingencies. Although no criteria was violated, the transient stability analysis recommends modifications to AE2-156 to improve recovery and settling time. The following modifications for AE2-156 are recommended and improved recovery.

  • REECAU1 ICON M+3 (QFLAG) to 0
  • REPCAU1 ICON (M) to POI (314513)
  • REPCAU1 ICON M+4 (VC Flag) to 0

 

It is recommended that future model submissions be validated with the settings proposed in this study. If model data and settings differ, then a transient stability study is recommended to validate the new model data and settings

AD1-033’s reactive power recovery was not settling to a steady state value during the analysis.

 

AE1-072 exhibited low frequency oscillations for 0.5 seconds on selected P4 contingencies during the fault. These oscillations settled and did not cause any instability. This is not a concern.

 

AB2-169 generator tripped for overvoltage protection model1  for voltage above 1.25 p.u. for P1.21 and P1.22 contingencies the time delay settings was updated from 0.00 to 0.0125.

 

AE2-156 was turned off and the issues remained therefore it’s pre-existing. However, it was observed that reactive settling doesn’t violate any PJM or Dominion criteria and settles within a 60 second simulation. The project is currently working on an as built model submittal that can be reviewed for this behavior at a later date. 

 

No mitigations were found to be required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 47 are listed in Table 1 below. This report will cover the TC1 Phase 3 dynamic analysis of Cluster 47 projects.

 

Table 1: Transition Cycle 1 Cluster 47 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

47

AG1-153

Battery

Dominion

75

75

30

Heritage 500 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 47 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 47 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 47 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 42 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 47 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 97 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

 

AG1-153 queue project did not meet the power factor 0.95 lagging measured at the high side of the transformer and it is deficient by 3.85 MVAR. AG1-153 queue project met the 0.95 leading power factor requirements.

 

The result of the analysis for Cluster 47 projects met all evaluation criteria for all the contingencies. No mitigation was required. There were minor reactive drift from AG1-153 that could be tuned by developer to improve performance.

 

AE1-173:

AE1-173, a nearby generator tripped for under voltage protection for voltages under 0.64 p.u for 0.31 seconds. The unit rode through all contingencies when pickup time was increased to 0.4375 seconds. The generator owner should be contacted to confirm if the revised setting is within plants capability and/or tune the model’s recovery.

 

AB2-169:

AB2-169, nearby generator, tripped for over voltage protection for voltages over 1.25 p.u. for 0.0 seconds. The unit rode through all contingencies when pickup time was increased to 0.0125 seconds.  The generator owner should be contacted to confirm if the revised setting is within plants capability and/or tune the model’s recovery.

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 48 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 48 project.

 

Table 1: Transition Cycle 1 Cluster 48 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

48

AF1-128

Natural Gas

Dominion

569

569

569

Chesterfield 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 48 project will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2027 light load case, modified to include applicable projects. Projects in vicinity of Cluster 48 have been dispatched online at maximum power output with electrically close generators dispatched near 50% of the respective units minimum reactive power output.

 

Cluster 48 were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 126 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 light load case:

 

  • Cluster 48 was able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 48 included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes in Dominion area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus)
  • For Dominion area, the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The transmission system being studied met the evaluation criteria. Below are some notable results.

 

AD2-074 was observed to trip on overvoltage (1.11 p.u. for 1 second and 1.2 p.u. for 0.001 second) for a number of P1 contingencies. Terminal voltage plots showed that the controller for this unit was freezing and not absorbing reactive power within the studied 20 second simulation. After reviewing the dynamic model, it was found that the REGCA model for this unit had reactive power ramp rate parameters Iqrmax and Iqrmin set to 0.02 and -0.02 p.u. respectively. These values are typically set much higher to allow the unit to respond to voltage variations quicker. Therefore, these values were increased to 100 and -100 p.u.. AD2-074 was then able to reduce the voltage post fault which prevented the unit from tripping on the 1.1 p.u. setpoint. The unit was still tripping for the 1.2 p.u. setpoint because of the low time delay (0.001 second). This time delay was increased slightly to 0.0167s. These changes enabled the unit to ride through all faults.

 

Surry units reactive response took over 20 seconds to settle for some contingencies. A longer 40 second test simulation was conducted which demonstrated that the unit settled shortly after 20 seconds shown in Figure 1 below. Slow settling is not a criteria violation and will not affect the results of the study.

 

AD1-151 reactive power was found to have some oscillations post fault that are positively damped with adequate damping ratio. This is not a criteria violation.

 

AB2-134 unit reactive power was found to not settle during the 20 second simulation. The following adjustments were made:

 

  • REPCA CON (J+1) Kp was adjusted to 1
  • REPCA CON (J+2) Ki was adjusted to 5

 

After these adjustments, the reactive power settlement improved but it did not settle within 20 seconds for some contingencies. This is not criteria violation. The developer should be requested to tune the dynamic model.

AB2-190 units reactive power was found to not settle during the 20 second simulation. The following adjustments were made:

  • PLNTBU1 CON (J+1) Kp was adjusted to 1
  • PLNTBU1 CON (J+2) Ki was adjusted to 5
  • PLNTBU1 CON (J+8) Kc was adjusted to 0.04

 

After these adjustments, the reactive power settlement improved but it did not settle within 20 seconds for some contingencies. This is not criteria violation. The developer should be requested to tune the dynamic model.

 

AG1-154 reactive power was observed to not settle during the 20 second simulation. The following adjustments were made:

 

  • REPCA CON (J+8) Kc was adjusted to 0.04

 

This adjustment improved the reactive power settlement for all contingencies.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG1-124 and AG1-494 in PJM Transition Cycle 1, Cluster 54 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 54 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 54 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 54 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 54 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 111 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 54 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 54 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-124 and AG1-494 meet the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed forinverter-based renewable generation units which are within one (1) substation away AG1-124 and AG1-494. CSCR results are summarized in Table 4 to Table 9 and revealed a minimum and maximum CSCR values of 3.99 for P1.16 and 6.08 for P4.21 & P4.22, respectively.

 

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e. fault where spike is observed]). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.” 

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-494 GEN, and AG1-124 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

Non-queue project AE1-108:

 

In the previous phase (phase 2) of the dynamic simulation analysis for Cluster 54, the relay pick-up time of AE1-108, instance 93882501 (VTGTPAT) was adjusted to 0.25 seconds to prevent tripping under one contingency. For this phase of the study (phase 3) the relay pick-up time for 93882501 (VTGTPAT) of AE1-108 was restored to original setting 0.0 seconds. No trippings of this unit were observed in this study.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 54 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

54

AG1-124

Solar

AEP

90

90

53.01

Gladstone 138 kV

AG1-494

Battery

AEP

50

50

20

Boxwood-Amherst 138 kV

 

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 55 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 55 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 55 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 55 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.

 

Cluster 55 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)       Steady-state operation (Category P0);

b)       Three-phase faults with normal clearing time (Category P1);

c)       Single-phase faults with stuck breaker (Category P4);

d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e)       Three-phase faults with normal clearing for common structure (Category P7).

 

Multiple-circuit tower line faults were identified for this study.

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 55 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 55 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 55 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-325, AF1-161, AF1-176, AF2-396 and AG1-109 meet the 0.95 leading and lagging PF requirement.

 

Please note that AE2-325 meets its own requested MFO of the uprate portion. However, AE2-325 combined with AD2-020 does not meet the total requested MFO of 152.2 MW. There are about 1.5 MW deficiencies due to the prior queue project AD2-020.

 

AE1-170, AE2-325 and AF2-396 were tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

 

No other mitigations were found to be required for TC1 Cluster 55.

 

Table 1: TC1 Cluster 55 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

55

AE2-325

Storage

American Electric Power (AEP)

52.2 MW

52.2

MW

31.32

MW

Valley 138 kV substation

AF1-161

Storage

American Electric Power (AEP)

50

MW

50 MW

25 MW

Valley 138 kV

substation

AF1-176

Solar + Storage

American Electric Power (AEP)

300

MW

300 MW

155.684

MW

Corey 138 kV

substation

AF2-396

Solar + Storage

American Electric Power (AEP)

200

MW

200 MW

200 MW

Stinger 138 kV

substation

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 56 are listed in Table 1 below . This report will cover the dynamic analysis of Cluster 56 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 56 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 56 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 56 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 34 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

       

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 56 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 56 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-410 and AG1-411 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA model of AG1-410 GEN, and AG1-411 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The AG1-411 generator terminal voltage settles beyond the acceptable voltage limits after fault clearance during 17 contingencies (P1.02, P1.03, P1.04, P1.08, P1.10, P4.07, P4.08, P4.09, P4.12, P4.13, P4.14, P4.15, P4.16, P4.17, P4.18, P4.19, and P4.20). This violation has been mitigated by adjusting the following parameters in the plant controller (REPCA1) for both AG1-410 and AG1-411: Kc (the reactive current compensation gain) to 0.1 (originally set to 0.0) and VC Flag (droop flag) to 0 (originally set to 1). These changes have been confirmed by the developer and updated in the latest data package received.

 

Fictitious frequency response at AG1-410 generator bus tripped the queue project due to the action of instantaneous over-frequency relay for several contingencies. Therefore, the relay pickup time for frequency relay instance 96542509 was set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

Voltage tripping was observed at the terminals of the AG1-410 generating unit after fault clearing during contingency P1.03. This issue was mitigated by adjusting Ki (Reactive power PI control integral gain) to 1.0 (originally set to 3.0) for AG1-410 in the plant controller REPCA1. The change was confirmed through correspondence with the developer.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 56 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

56

AG1-410

Solar

AEP

300

300

180

Maddox Creek-RP Mone 345 kV

AG1-411

Storage

AEP

100

100

100

Maddox Creek-RP Mone 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (AG1-436, and AG1-447) in PJM Transition Cycle 1, Cluster 58 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 58 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 58 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 58 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 58 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 56 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 58 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 58 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-447 and AG1-436 meet the 0.95 leading and lagging PF requirement.

 

AG1-436 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue was mitigated by increasing Kc value in REPCA1 dynamic model from 0 to 0.1. This change has been confirmed by the developer and included in the latest data submission.

 

AG1-447 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. ETERM of AG1-447 GEN went outside the range of 0.95 pu ~1.05 pu in post fault for several contingencies. These issues were mitigated by changing VCFlag from 1 to 0, increasing Kc from 0 to 0.08, and Ki from 0.5 to 3.5 in the REPCA1 model. These changes have been confirmed by the developer in correspondence.

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-447 GEN, and AG1-436 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 58 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

58

AG1-436

Solar

AEP

125

125

75

Olive-University Park 345 kV

AG1-447

Battery

AEP

55

55

55

Olive-University Park 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 60 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 60 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 60 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 60 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 60 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 125 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 60 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 60 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-068 meet the 0.95 leading and lagging PF requirement.

 

AF2-068 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement upon request.

 

The AG1-047 unit tripped by undervoltage relay for one contingency (P5.01). The P5.01 contingency involved a single-phase fault at 80% of line from Jay (AF2-068/AG1-017/AG1-047 POI) 138 kV on AG1-324 POI circuit with delayed (Zone 2) clearing in 60 cycles. As per NERC Standard PRC-024 requirements, the contingency was found to meet the corresponding NERC PRC-024 LVRT criteria. We solved the tripping by updating the relay instance 96203408 from 0.3 second to 1.01 seconds. Additionally, this tripping event was observed in the pre-project study and therefore is not attributed to AF2-068.

 

For P1.06 contingency AE2-318, AE2-318, AD2-163, AD2-163, AC2-195, AC1-102, AC1-074 and 08HLCRT unit have been tripped for over voltage relay settings where clearing time was 0 second for all those relay settings. Added one cycle to original pick up to prevent fictious post-fault overvoltage tripping. It should be noted that generic dynamic models for inverter-based generators tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception or clearing. These spikes can be ignored in most cases as they do not represent the performance of the actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.

 

The IPCMD and IQCMD states in the REGCAU model of AF2-068 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The CSCR results are summarized in Table 3 through Table 8 and revealed a minimum and maximum CSCR values of 1.99 for P4.32 and 4.14 for P1.02, respectively. 57 contingencies out of 125 contingencies have values less than 3. The lowest value is 1.99 for contingencies P1.12, P1.13, P4.24, P4.25, P4.32 and P5.05.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 60 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

60

AF2-068

Solar

AEP

150

150

90

Jay 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 62 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 199 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-173, AF2-177, AF2-407, AG1-367 and AG1-375 meet the 0.95 leading and lagging PF requirement.

 

AF2-173 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-173, setting Ki to 0.15 from its original value of 0.5.

 

AF2-177 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-177, setting Ki to 0.15 from its original value of 0.5.

 

AG1-367 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-367, setting Kc to 0.1 from its original value of 0.

 

AG1-375 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-375, setting Kc to 0.1 from its original value of 0.

 

AF2-407 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc, Ki and Kp parameters in the plant controller (REPCA1) for AF2-407, setting Kc to 0.15 from its original value of 0.04, setting Ki to 2 from its original value of 0.5, and setting Kp to 0.5 from its original value of 0.

 

Fictitious frequency response at AF2-407 generator bus tripped the queue project due to the action of instantaneous under-frequency and over-frequency relays when faults were applied at Fall Creek 345 kV (AF2-407 POI). Therefore, the relay pickup times for frequency relay instances 96116513 and 96116516 were set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 62 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

62

AF2-173

Solar

AEP

140

140

84

Desoto 345 kV Substation

AF2-177

Wind

AEP

200

200

26

Sorenson – Desoto #2 345 kV Line

AF2-407

Battery Storage

AEP

300

300

300

Fall Creek 345 kV Substation

AG1-367

Solar

AEP

100

100

60

DeSoto 345 kV Substation

AG1-375

Solar

AEP

100

100

100

Sorenson – Desoto #2 345 kV Line

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 63 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 63 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 63 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 63 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 63 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 102 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

a)       Steady-state operation (20 second run),

b)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

c)       Single-phase bus faults with normal clearing time,

d)       Single-phase faults with stuck breakers,

e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 63 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 63 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-433 and AF2-388 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCAU model of AG1-433 GEN, and AF2-388 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

It was observed that the terminal voltage of the AF1-119 and AF2-162 generating units after fault clearing for several contingency goes beyond the limits. This can be eliminated by adjusting the following for both AF1-119 and AF2-162 in the REPCA1 model: Kc to 0.1 (originally set to 0), Ki to 8 (originally set to 50), and Kp to 2 (originally set to 1).

 

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from Cluster 63. The CSCR results are summarized in Table 4 through Table 8 and revealed a minimum and maximum CSCR values of 3.17 for P7.13, and 4.99 for P1.09, respectively.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 63 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

63

AF2-388

Wind

AEP

200 MW

200

35.2

Keystone-Desoto 345 kV

AG1-433

Wind

AEP

100 MW

100

17.6

Keystone-Desoto 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AF1-204 and AG1-226 in PJM Transition Cycle 1, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 131 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breakers,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-204 and AG1-226 meet the 0.95 leading and lagging PF requirement.

 

AG1-237 exhibited slow reactive power recovery for P7.04 contingency. This issue did not cause instability in the system and the models can be tuned if required to achieve a faster reactive power output settlement.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 64 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

64

AF1-204

Wind

AEP

255

255

63.75

Eugene 345 kV

AG1-226

Solar

AEP

450

450

142

Eugene-Dequine 345 kV

 

 

Executive Summary for Stability Cluster

PSSE Dynamic Study Analysis

 

Executive Summary

 

New Service Request projects in PJM Transition Cycle 1, Cluster 69 are listed in Table 1 below. The report covers the dynamic analysis of Cluster 69 projects.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 69 projects will meet the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 69 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.01 pu voltage at the AF2-010 POI bus, and 1.01 pu voltage at the AG1-548 POI bus.

 

Cluster 69 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 81 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)  Steady-state operation (Category P0);

b)  Three-phase faults with normal clearing time (Category P1);

c)  Single-phase faults with stuck breaker (Category P4);

d)  Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 69 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For 75 out of 81 fault contingencies tested on the 2027 peak load case:

a)  Cluster 69 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)  The system with Cluster 69 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter-area modes and 4% for local modes.

c)  Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)  No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-010 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AF2-010 was observed.

 

For P1.27, P4.12, P4.13, P4.14, P4.15, and P5.13, after losing 115 kV circuit from Erie South to AG1-548 POI, the results show undamped oscillations indicating system instability. The CSCR assessment shows under these fault contingencies, the CSCR values would be below 1.5 which could be considered very weak grid conditions. The PSSE dynamic analysis initially shows that system reinforcement is needed to resolve the undamped oscillations. However, after an electromagnetic transient (PSCAD) study was performed, the PPC setting were tuned. Further PSSE simulation shows that system is stable with adjusted PPC setting and no reinforcement is required.   

 

PSCAD Electromagnetic Study Analysis

 

Executive Summary

 

Electromagnetic transient model quality tests were performed for the 150 MW French Creek Solar and Storage project and the Union Solar project. PSCAD models were used to perform testing and analysis to ensure compliance with PJM requirements.

 

The French Creek Solar and Storage project located in Erie County, Pennsylvania was modeled with forty-two (42) Sungrow SG4400UD-US inverters and forty-two (42) step-up transformers for the photovoltaic generation portion; eight (8) Sungrow SC4400UD-US inverters and eight (8) step-up transformers for the battery energy storage system (BESS) portion; two (2) collection systems; one (1) main power transformer; and a 1-mile (5280 ft) transmission line connected to a 115 kV tap on the Erie South to Union City transmission line.

 

The Union Solar project located in Erie County, Pennsylvania was modeled with nineteen (19) SMA SC 4600-UP inverters and nineteen (19) step-up transformers, one (1) collection system, one (1) main power transformer, and a 0.02-mile transmission line connected to the 115 kV tap on Union City to Titusville transmission line.

 

Model quality tests for the French Creek Solar and Storage project, and the Union Solar project were performed for the following scenarios:

 

•  Flat Start Test Voltage Step-Down

•  Voltage Step-Up

•  Frequency Step-Down, No Headroom

•  Frequency Step-Up/Down, Headroom (@ 80% Pmax)

•  HVRT Leading (Legacy Curve)

•  HVRT Lagging (Legacy Curve)

•  LVRT Leading (Legacy Curve)

•  LVRT Lagging (Legacy Curve)

•  Voltage Ride Through (VRT)

•  Phase Angle Step-Down

•  Phase Angle Step-Up

•  System Strength Test

 

The French Creek Solar and Storage project PSCAD model, and the Union Solar project PSCAD model, with fine tuning, both passed all the model quality tests. The undamped oscillations identified in the PSSE dynamic study are not observed in the PSCAD study with a more detailed model. It is therefore concluded that undamped oscillations under P1.27, P4.12, P4.13, P4.14, P4.15, and P5.13 can be resolved with fine tuning of the plant.

 

Table 1: TC1 Cluster 69 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

69

AF2-010

Solar

FirstEnergy (Mid-Atlantic Interstate Transmission, LLC - Penelec Zone)

77 MW

77 MW

46 MW

Union City –Titusville 115 kV

69

AG1-548

Solar + Storage

FirstEnergy (Mid-Atlantic Interstate Transmission, LLC - Penelec Zone)

150 MW

150 MW

45 MW

Erie South -Union City 115 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request project in PJM Transition Cycle 1, Cluster 70 is listed in Table 1 below. The report covers the dynamic analysis of the Cluster 70 project.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 70 project meets the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include the applicable project. The Cluster 70 project was dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.02 pu voltage at the POI buses.

The Cluster 70 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 60 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e) Single phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of the TC1 Cluster 70 project.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For 158 out of 160 fault contingencies tested on the 2027 peak load case:

a) The Cluster 70 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with the Cluster 70 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter-area modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required for the TC1 Cluster 70 project.

Table 1: TC1 Cluster 70 Project

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

70

AF2-050

Solar

FirstEnergy (FE) transmission system, Pennsylvania Electric Co (PENELEC) zone

150

50

30

Johnstown –Bear Rock 230 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request projects in PJM Transition Cycle 1, Cluster 71 are listed in Table 1 below. The report covers the dynamic analysis of the Cluster 71 projects.

The analysis is effectively a screening study to determine whether the addition of the Cluster 71 projects meet the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 71 projects were dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.02 pu voltage at the POI bus for AG1-090, AG1-377, and AG1-378.

 

Cluster 71 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 101 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 71 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For all of the fault contingencies tested on the 2027 peak load case:

a) Cluster 71 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with Cluster 71 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required for TC1 Cluster 71. 

 

 Table 1: TC1 Cluster 71 Projects 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

71

AG1-090

Solar + Storage

FirstEnergy (FE) Transmission System, Pennsylvania Electric Company (PENELEC) zone

95 MW

95

MW

30

MW

Philipsburg 115 kV Substation

AG1-377

Solar

FirstEnergy (FE) Transmission System, Pennsylvania Electric Company (PENELEC) zone

20

MW

20 MW

6

MW

Philipsburg 115 kV Substation

AG1-378

Solar

FirstEnergy (FE) Transmission System, Pennsylvania Electric Company (PENELEC) zone

20

MW

20 MW

6

MW

Philipsburg 115 kV Substation

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 72 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 72 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 72 projects will meet the dynamics requirements of the NERC, Atlantic City Electric Company (AEC), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 72 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, 1.03 pu voltage at the POI bus for AF1-238, and 1.04 pu voltage at the POI bus for AF2-025.

Cluster 72 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 136 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)       Steady-state operation (Category P0);

b)       Three-phase faults with normal clearing time (Category P1);

c)       Single-phase faults with stuck breaker (Category P4);

d)       Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e)       Single phase to ground faults with normal clearing for common structure (Category P7).

No High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 72 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 72 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 72 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF1-238 and AF2-025 meet the 0.95 leading and lagging PF requirement.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied. The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution. (source: https://www.esig.energy/wiki-main-page/dynamic-simulation-of-pv-plants/)

No mitigations were found to be required for TC1 Cluster 72.

Table 1: TC1 Cluster 72 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

72

AF1-238

Storage

Atlantic City Electric Company (AEC)

50 MW

50 MW

20 MW

Sherman Ave - West Vineland 69 kV

AF2-025

Storage

Atlantic City Electric Company (AEC)

20 MW

20 MW

8

MW

Ontario 69 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

The New Service Request project in PJM Transition Cycle 1, Cluster 74 is listed in Table 1 below. The report covers the dynamic analysis of the Cluster 74 project.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 74 project meets the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include the applicable project. The Cluster 74 project was dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

 

The Cluster 74 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 87 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e) Single phase faults with normal clearing on common structure (Category P7)

High Speed Reclosing (HSR) facilities were found in the vicinity of the TC1 Cluster 74 project.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

a) The Cluster 74 project is able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with the Cluster 74 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-126 was tripped during the fault application close to the POI as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

No mitigation is required for TC1 Cluster 74.

 

Table 1: TC1 Cluster 74 Project 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

74

AF2-126

Solar

FirstEnergy (FE) transmission system, West Penn Power (“WPP” in ATSI) zone

62 MW

12 MW

8 MW

Weston substation

69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request (project) AG1-341 in PJM Transition Cycle 1 is listed in Table 1 below. This report will cover the dynamic analysis of AG1-341.

 

This analysis is effectively a screening study to determine whether the addition of the AG1-341 will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-341 have been dispatched online at maximum output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

AG1-341 was tested for compliance with NERC, EKPC, PJM, and other applicable criteria. Steady-state condition and 233 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Three-phase bus faults with normal clearing time;

       d)       Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker;

       e)       Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Three-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the AG1-341 project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       AG1-341 project was able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with AG1-341 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-341 meets the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-341 GEN, AF1-050 GEN and AE2-071 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system these plots are ignored.

 

AG1-341, AF1-050 and AE2-071 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 AG1-341 Project

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-341

Solar/Storage

EKPC

106

106

63.6

Summer Shade 161 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Request (project) AG1-320 in PJM Transition Cycle 1 is listed in Table 1 below. This report will cover the dynamic analysis of AG1-320.

This analysis is effectively a screening study to determine whether the addition of AG1-320 will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-320 has been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

AG1-320 was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 132 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, AG1-320 along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AG1-320 was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AG1-320 included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-320 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AG1-320 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

AF1-050 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

No mitigations were found to be required.

 

Table 1: TC1 AG1-320 Project

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-320

Solar

EKPC

82

82

54.8

Glendale – Stephensburg 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request (project) in PJM Transition Cycle 1, AF2-376 is listed in Table 1 below. This report will cover the dynamic analysis of AF2-376 project.

 

This analysis is effectively a screening study to determine whether the addition of the AF2-376 project will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AF2-376 project has been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

AF2-376 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 92 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time,

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       f)       Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       AF2-376 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with AF2-376 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-376 meet the 0.95 leading and lagging PF requirement.

 

The AE2-298 unit tripped by an undervoltage relay for one contingency (P1.09). Contingency P1.09 involved a three-phase fault at Haviland 345 kV clearing in 6 cycles. As per NERC Standard PRC-024 requirements, this relay settings were found to meet the corresponding NERC PRC-024 LVRT. Additionally, this tripping event was observed in the AE2-298 Dynamic Study and with the pre-AF2-376 scenario, therefore is not attributed to AF2-376.

 

For contingencies P5.01, P5.02 and P5.04, it was observed that active power of Timber switch unit was not recovered to pre fault value. This will not cause any instability in the system and can be mitigated upon request.

 

The IPCMD and IQCMD states in the REGCAU model of AF2-376 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The CSCR results are summarized in Table 4 through Table 9 and revealed a minimum and maximum CSCR values of 1.85  for P4.25 and 4.91 for P1.04, respectively.

 

No mitigations were found to be required.

 

Table 1: TC1 AF2-376 Project

Queue

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AF2-376

AF2-376

BESS

AEP

50.0 MW

50.0 MW

20.0

MW

Timber Switch 138 kV

 

 

Shared POIs

At PJM's discretion, New Service Requests in a Cycle at the same Point of Interconnection may be aggregated for the purposes of System Impact Studies, in accordance with PJM Open Access Transmission Tariff, Part VIII, Subpart C, section 404.2.a.iii.

Shared POI NameNew Service Requests Aggregated
AE1-155 115 kV - DominionAF2-120, AG1-536
AE2-185 69 kV - DominionAE2-185, AF2-404
AF1-294 115 kV - DominionAF1-294, AF2-115, AG1-021
CVOW Harpers 230 kV - DominionAF1-123, AF1-124, AF1-125
Cordova 345 kV (ComEd)AG1-462, AG1-553
Katydid Road 345kV (ComEd)AF2-226, AF2-319
Keystone - Desoto 345kV - AEPAF2-388, AG1-433
Kincaid Pana Tap - ComEdAE2-261, AG1-460
Maddox Creek - RP Mone 345kV - AEPAG1-410, AG1-411
McLean 345kV (ComEd)AE2-223, AF2-225
Nelson - Lee County 345kV - ComEdAF1-280, AF2-182
Nelson-Electric Junction 345kV - ComEdAF2-041, AF2-199, AF2-200
Olive - University Park 345kV - AEPAG1-436, AG1-447
Philipsburg 115kV yard - PenelecAG1-090, AG1-377, AG1-378
Sandwich - Plano 138kV - ComEdAE2-341, AF1-030
Sorenson - Desoto 345kV - AEPAF2-177
Valley 138kV - AEPAF1-161, AG1-109

CIR Claims From Deactivated Generators

The following Transition Cycle 1 projects intend to claim and transfer CIRs from deactivated capacity generation resources. PJM performed a reliability analysis of the impacts to the system capability for the proposed transfers of CIRs from the deactivated generation resources.

ProjectStatusCIR ClaimedPOI TransferDetails
AF1-128Active569.0Yes
Unit NameStatusCIR ClaimedPOI Transfer
Chesterfield 3Deactivated Generator100.0Yes
Chesterfield 4Deactivated Generator119.0Yes
Chesterfield 5Deactivated Generator350.0No

Cost Summary

Table below shows a summary of the total planning level cost estimates for each individual New Service Request received by PJM and studied in Transition Cycle 1 Final System Impact Study. These network upgrade costs are subject to change as a result of a facility study performed by the Interconnected Transmission Owner during the Final System Impact Study.

Project IDTransmission Owner Interconnection Facilities (TOIF)Physical Interconnection Network UpgradesSystem Reliability Network UpgradesAffected System Study ReinforcementsAdditional ChargesTotal CostCost Details
AE1-092$796,612$14,467,553$0$0$0$15,264,165
AE1-114$0$11,422,206$4,677,511$82,193$1,237,828$17,419,738
AE1-172$0$28,485,236$10,024,572$136,518$2,005,307$40,651,633
AE2-156$3,487,508$8,024,437$1,907,381$0$0$13,419,326
AE2-185$0$724,989$0$0$939,177$1,664,166
AE2-223$0$32,602$3,751,843$376,799$1,321,269$5,482,513
AE2-261$0$5,449,938$17,510,143$1,436,014$997,871$25,393,967
AE2-283$8,300,735$3,617,755$0$0$0$11,918,490
AE2-291$1,091,112$15,672,692$3,255,793$0$0$20,019,597
AE2-308$960,000$16,084,000$0$0$0$17,044,000
AE2-325$193,802$60,764$29,905$249,654$0$534,125
AE2-341$392,212$20,659,366$0$567,614$0$21,619,192
AF1-030$392,212$20,659,366$0$375,625$0$21,427,203
AF1-123$7,308,561$250,069,522$263,650,733$0$0$521,028,816
AF1-124$7,308,561$250,069,522$264,594,367$0$0$521,972,451
AF1-125$7,308,561$250,069,522$259,555,062$0$0$516,933,145
AF1-128$853,497$2,182,499$0$0$0$3,035,996
AF1-161$503,836$1,371,722$14,294$239,991$0$2,129,843
AF1-176$1,095,657$1,996,401$838,835$1,868,391$0$5,799,283
AF1-204$2,204,630$391,163$0$3,685,642$0$6,281,435
AF1-233$1,090,000$17,924,352$0$3,511,290$0$22,525,642
AF1-238$0$0$0$0$0$0
AF1-280$0$12,467,942$14,292,703$681,511$970,966$28,413,122
AF1-294$0$1,370,721$5,054,676$0$956,979$7,382,376
AF1-296$717,375$11,672,026$9,366,298$95,169$0$21,850,868
AF2-010$52,291$4,938,510$7,287,728$0$962,458$13,240,987
AF2-041$0$5,286,342$36,686,940$1,062,418$698,350$43,734,050
AF2-042$2,167,703$36,291,713$312,504,638$0$0$350,964,054
AF2-050$49,831$153,052$9,867,043$0$0$10,069,926
AF2-068$1,750,487$1,483,556$0$8,357$0$3,242,400
AF2-080$0$0$35,148,396$3,726,000$0$38,874,396
AF2-081$4,133,798$3,663,047$1,771,488$0$0$9,568,333
AF2-095$5,112,467$1,166,794$3,452,545$597,954$0$10,329,760
AF2-111$0$8,479,000$0$81,383$1,416,000$9,976,383
AF2-115$0$1,370,721$3,082,125$0$956,979$5,409,826
AF2-120$1,219,290$1,219,184$28,157,299$0$0$30,595,772
AF2-126$58,252$233,066$0$2,025$0$293,343
AF2-142$0$0$1,881,556$589,248$256,082$2,726,886
AF2-143$0$0$1,881,471$575,326$256,082$2,712,879
AF2-177$2,399,061$20,794,488$5,909,187$0$0$29,102,736
AF2-182$0$12,467,942$21,438,948$1,018,422$970,966$35,896,278
AF2-199$0$5,286,342$12,228,959$350,908$698,350$18,564,559
AF2-200$0$5,286,342$27,175,429$710,842$698,350$33,870,963
AF2-222$1,080,391$16,075,015$41,639,056$0$0$58,794,462
AF2-225$0$32,602$3,751,843$767,196$1,321,269$5,872,910
AF2-226$0$0$627,185$204,661$256,082$1,087,928
AF2-296$0$0$0$0$0$0
AF2-299$0$0$0$515,000$0$515,000
AF2-319$0$0$627,185$204,661$256,082$1,087,928
AF2-349$0$17,122,339$0$1,094,363$2,000,162$20,216,864
AF2-350$793,922$29,405,140$0$419,501$0$30,618,563
AF2-376$193,802$60,764$0$0$0$254,566
AF2-388$982,483$691,462$5,736,003$19,678$0$7,429,626
AF2-396$2,531,657$2,169,205$773,668$1,226,374$0$6,700,905
AF2-404$0$724,989$0$0$939,177$1,664,166
AF2-407$2,435,538$3,325,190$9,492,808$235,944$0$15,489,480
AF2-441$787,345$7,072,041$0$910,924$0$8,770,310
AG1-021$0$1,370,721$2,465,771$0$956,979$4,793,471
AG1-090$84,934$1,099,479$12,461,472$0$1,658$13,647,543
AG1-105$993,766$14,284,645$5,665,432$0$0$20,943,843
AG1-106$0$0$15,012,381$1,018,000$0$16,030,381
AG1-109$503,836$1,432,486$14,294$0$0$1,950,616
AG1-118$0$8,216,337$3,283,718$1,111,779$1,810,470$14,422,304
AG1-124$1,838,092$10,076,477$7,818,051$0$0$19,732,620
AG1-127$0$0$0$346,850$256,082$602,932
AG1-135$1,085,295$17,406,305$24,820,562$0$0$43,312,162
AG1-153$4,822,863$1,958,524$1,759,557$0$0$8,540,944
AG1-226$2,930,035$33,073,479$0$7,603,912$0$43,607,426
AG1-285$1,077,358$18,954,196$30,130,203$0$0$50,161,757
AG1-320$0$2,214,000$0$4,334,526$1,591,000$8,139,526
AG1-341$1,683,000$6,002,000$0$7,562,355$0$15,247,355
AG1-342$0$1,957,245$2,214,755$0$2,945,911$7,117,911
AG1-354$0$1,333,000$0$13,379,640$1,337,000$16,049,640
AG1-374$2,382,120$19,794,599$7,034,968$1,520,708$0$30,732,395
AG1-377$84,934$1,099,479$2,623,735$0$1,658$3,809,806
AG1-378$84,934$1,099,479$2,623,735$0$1,658$3,809,806
AG1-410$1,279,780$10,446,603$0$23,042$0$11,749,425
AG1-411$1,279,780$10,507,367$0$0$193,802$11,980,949
AG1-433$982,483$752,226$2,868,001$0$193,802$4,796,513
AG1-436$138,247$60,764$0$652,242$0$851,253
AG1-447$138,247$60,764$0$291,870$0$490,881
AG1-460$0$5,449,938$1,756,880$143,028$1,253,952$8,603,798
AG1-462$2,663,655$16,617,794$12,912,297$798,388$0$32,992,135
AG1-471$718,000$13,187,000$0$5,352,864$0$19,257,864
AG1-536$1,219,290$1,219,184$29,458,570$0$0$31,897,044
AG1-548$54,570$6,698,199$14,089,682$0$951,097$21,793,548
AG1-553$2,167,424$16,617,794$13,165,446$816,076$0$32,766,740

System Reinforcements

As part of Transition Cycle 1 Final System Impact Study, PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements.

Regional Discount Factors for Topology Changing Upgrades
RegionTopology UpgradesEliminated UpgradesDiscount FactorDetails
Dominion$259,058,089$731,408,60426.155154%
Mid-Atlantic Area Council$0$0100.000000%
PJM West$0$0100.000000%

Details for Dominion Region


The following topology changing reinforcements within the Dominion region were modeled to mitigate the impacts driven by the new service requests in Transition Cycle 1 Final Agreements:

Table 3: Dominion Topology Changing Reinforcement(s) Modeled for Transition Cycle 1 Final Agreements
TORTEP ID / TO IDTitleTime EstimateTotal Cost Estimate ($)
Dominions3047.2

Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.

Jun 30 2029$0
Dominionb3800.312

Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.

Jun 30 2030$0
Dominionb3800.313

Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.

Jun 30 2030$0
Dominionb3800.356

Build a new 500 kV line from Vint Hill to Wishing Star.

Jun 30 2030$0
Dominionb3800.357

Build a new 500 kV line from Morrisville to Vint Hill.

Jun 30 2030$0
Dominionb3800.354

Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.

Jun 30 2030$0
Dominionn8492

Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.

26 to 27 Months$80,172,278
Dominionn8492.1

Two Breaker Additions at Fentress Substation.

30 to 36 Months$19,945,879
Dominionn8492.2

Expand Yadkin Substation to accommodate the new 500 kV line.

15 to 16 Months$16,207,123
Dominionn9259.0

Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.

38 to 39 Months$25,304,902
Dominionn9267.0 / TC1-PH2-DOM-067

Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.

45 to 46 Months$45,730,074
Dominionb4000.357

Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.

Jun 01 2029$0
Dominionb4000.356

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).

Jun 01 2029$0
Dominionb4000.355

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).

Jun 01 2029$0
Dominionb4000.352

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.

Sep 16 2030$0
Dominionb4000.351

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.

Sep 16 2030$0
Dominionb4000.350

Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.

Sep 16 2030$0
Dominionb4000.349

Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.

Sep 16 2030$0
Dominionb4000.348

Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.

Jun 01 2029$0
Dominionb4000.346

Cut-in 500kV line from Kraken substation into Yeat substation

Jun 01 2029$0
Dominionb4000.345

Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030$0
Dominionb4000.344

Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030$0
Dominionb4000.342

Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.

Jul 13 2029$0
Dominionb4000.341

Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.

Jul 13 2029$0
Dominionb4000.325

Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.

Feb 24 2029$0
Dominionb4000.326

At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.

Feb 24 2029$0
Dominionb4000.327

Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.

Feb 24 2029$0
Dominionn9630.0 / TC1-PH3-DOM-013

Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.

Dec 31 2029$71,697,833
Grand Total:$259,058,089

The following reinforcements in the Dominion region were eliminated as a result of modeling the above topology reinforcements in Transition Cycle 1 Final Agreements.

Table 4: Dominion Eliminated Reinforcement(s) Identified for Transition Cycle 1 Final Agreements
TORTEP ID / TO IDTitleTime EstimateTotal Cost Estimate ($)
Dominionn6161 / dom-039

ELIMINATED FOR TC1: Replace 500 kV circuit breaker H1T561 at Clifton with a higher rated device (Clifton - Ox).

Dec 31 2029$2,634,901
Dominion(Pending) / dom-281

ELIMINATED FOR TC1 - Rebuild 7.91 miles of 230 kV Line 2083 from Birchwood to Fines with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor 250 degrees C.

43 to 44 Months$35,735,843
Dominion(Pending) / dom-286

ELIMINATED FOR TC1: Rebuild 6.46 mi miles of 2-545.6 ACAR (15/7) 90 MOT 230 kV Line 2083 from Fredericksburg to Fines with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C.

43 to 44 Months$33,559,690
Dominion(Pending) / dom-369

ELIM FOR TC1: Wreck and rebuild 6.47 miles of 230 kV transmission line 2028 between Charlottesville and Mt. Eagle with (2) 768.2 ACSS/TW (20/7) "Maumee" @ 250C and replace line lead at Mt. Eagle.

43 to 44 Months$36,802,018
Dominion(Pending) / dom-461

ELIMINATED FOR TC1: Reconductor 3.53 miles of 115 kV Line 65 from AD2-074 Tap to AG1-146 Tap with (1) 768.2 ACSS/TW (20/70) "Maumee" conductor @ 250 degrees C

43 to 44 Months$16,493,251
Dominion(Pending) / dom-397

ELIMINATED FOR TC1: Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

43 to 44 Months$23,887,052
Dominion(Pending) / dom-490

ELIMINATED FOR TC1: Upgrade a 3.78 mile segment of 230kV transmission line 2028 between Mt. Eagle and Grape Vine Substations at structure 2080/73.

43 to 44 Months$13,360,242
Dominionn9138.0 / TC1-PH1-DOM-070

ELIM TC1: Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.

60 to 61 Months$111,130,292
Dominionn9146.0 / TC1-PH1-DOM-004

ELIMINATED FOR TC1: Wreck and rebuild 1.51 miles of 115 kV Line No. 5 between Bremo and Fork Union with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees Celsius. Replace line lead at Bremo.

42 to 43 Months$7,535,533
Dominion(Pending) / AEPAPRJV007

ELIMINATED FOR TC1: Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.

29 Months$4,759,000
Dominion(Pending) / AEPAPRJV008

ELIMINATED FOR TC1: Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.

15 Months$1,245,000
Dominion(Pending) / TC1-PH2-DOM-008

ELIMINATED FOR TC1: Wreck and rebuild 10.74 miles of line 2028 between Fork Union and Cunningham (Grape Vine) with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C.

45 to 46 Months$29,539,973
Dominion(Pending) / TC1-PH2-DOM-030

ELIMINATED FOR TC1: Reconductor 6.01 miles of 115 kV Line 65 from AG1-146 Tap to Lancaster with (1) 768.2 ACSS/TW (20/70 "Maumee" conductor @ 250 degrees C.

43 to 44 Months$27,984,346
Dominion(Pending) / TC1-PH2-DOM-040

ELIM TC1: Wreck and rebuild 18.75 miles of Line 594 btwn Morrisville and Spotsylvania with (3) 1351.5 ACSR (45/7) Dipper at 110 degrees C and assoc substation work (new rating: 4356/4356/5009 MVA)

60 to 61 Months$128,018,212
Dominionn9247.0 / TC1-PH2-DOM-041

ELIM TC1: Wreck and rebuild 14.02 miles of Line 573 btwn Spotsylvania and North Anna with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and assoc substation work (new rating: 4356/4356/5009 MVA)

48 Months$99,636,684
Dominionn9250.0 / TC1-PH2-DOM-044

ELIM TC1: Construct a new 22.59 mile line between Carson and Rawlings Substations.

60 to 61 Months$108,728,086
Dominion(Pending) / TC1-PH2-DOM-061

ELIMINATED FOR TC1: Replace wave trap 256WT at Four River 230 kV station (Four River - St. John).

14 to 15 Months$514,454
Dominion(Pending) / TC1-PH2-DOM-062

ELIMINATED FOR TC1: Wreck and Rebuild 14.83 miles of 230 kV line 256 with (2) 768.2 ACSS/TW (20/7) ""Maumee"" conductor @ 250 degrees C.

46 to 47 Months$41,037,004
Dominion(Pending) / TC1-PH3-DOM-006

ELIM FOR TC1: Upgrade a 2.73 mile segment of 230kV transmission line 2028 between Mt. Eagle and Grape Vine. This segment runs from Grape Vine substation to structure 2080/73.

42 to 43 Months$8,415,380
Dominion(Pending) / TC1-PH3-DOM-009

ELIMINATED FOR TC1: Replace 795 AAC 37 line lead at Farmville 115 kV.

12 to 13 Months$391,643
Grand Total:$731,408,604

Impacted New Service Requests have a cost responsibility into the eliminated reinforcements, but these reinforcements will not be constructed. A discount factor of 26.155154% has been applied to all projects which contribute to a topology changing or eliminated reinforcement in the Dominion region.

Details for Mid-Atlantic Area Council Region


There were no eliminated reinforcements identified in the Mid-Atlantic Area Council region. Therefore, no reinforcements in the Mid-Atlantic Area Council region have been discounted.

Details for PJM West Region


There were no eliminated reinforcements identified in the PJM West region. Therefore, no reinforcements in the PJM West region have been discounted.

Steady State Thermal & Voltage Reinforcements

PJM performed generator deliverability load flow analysis for the New Service Requests in Transition Cycle 1 Final System Impact Study. Load flow analysis was performed to simulate Summer Peak, and Light Load conditions. The table below shows all the system reinforcements identified from generator deliverability load flow analysis.

TORTEP ID / TO IDTitleTime EstimateTotal Cost Estimate ($)Projects with Cost AllocationContingent ProjectsFacilities Study
AEPb3775.10

Perform sag study mitigation work on Olive – University Park

Dec 01 2026
Contingent

AE1-114, AE1-172, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-441, AG1-118, AG1-127

N/A
AEPb3775.11 / b3775.7a

Upgrade the wavetrap at Dumont substation to increase the rating of the Stillwell-Dumont 345 kV line to match conductor rating.

Dec 01 2026
Contingent

AF2-041, AF2-441, AG1-118, AG1-374

N/A
AEPb3775.6

Perform sag study mitigation work on the Dumont-Stillwell 345 kV line

Nov 20 2026
Contingent

AF2-041, AF2-441, AG1-118, AG1-374

N/A
AEPb3775.7 / b3775.7b

Upgrade breakers at Dumont substation on the Stillwell-Dumont 345 kV line.

Dec 01 2026
Contingent

AF2-041, AF2-441, AG1-118, AG1-374

N/A
AEPb4000.210

Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.

Jun 01 2029
Contingent

AE2-185, AE2-283, AE2-291, AG1-105

N/A
AEPb4000.211

Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line

Jun 01 2029
Contingent

AE2-185, AE2-283, AE2-291

N/A
AEPn3985 / AEPO0036a

Upgrade three Marysville Wavetraps ( 3000A)

18 to 24 Months
Contingent

AE1-172, AF1-176, AF2-396, AF2-441

N/A
AEPn5613 / AEPA0014a

Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.

Nov 21 2027
Contingent

AE2-185, AE2-283, AE2-291, AG1-105

N/A
AEPn7679 / AEPI0040a

Replace 1272 AAC Jumper at Allen station

18 to 24 Months
Contingent

AF2-376

N/A
AEPs2793.5 / s2793

Rebuild the T-line from West Van Wert to Roller Creek

Jul 18 2025
Contingent

AF2-376

N/A
AEPs3442.26

Dumont 765 kV: Replace 3000 A circuit breaker at Dumont

Dec 01 2026
Contingent

AE1-172, AF2-349, AF2-441, AG1-118

N/A
ATSIn9322.0 / TE-AG1-S-0012a

Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction.

38 Months
$1,408,997

AF1-176, AF2-396

ComEdb3775.1

Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line

Mar 30 2027
Contingent

AF1-280, AF2-041, AF2-182, AF2-200, AF2-349, AG1-118, AG1-374, AG1-436, AG1-462

N/A
ComEdb3775.3

Rebuild ComEd’s section of 345 kV double circuit in IL from St. John to Crete

Dec 01 2026
Contingent

AF1-280, AF2-041, AF2-182, AF2-200, AF2-349, AG1-118, AG1-374, AG1-462

N/A
ComEdb3775.4 / CE_B3775.4

Rebuild 345 kV double circuit extending from Crete to E. Frankfort.

Dec 01 2026
Contingent

AF2-041, AF2-200, AF2-349, AG1-118, AG1-374, AG1-462

N/A
ComEdb3775.5

Replace E. Frankfort 345 kV circuit breaker “9-14” with 3150A SF6 circuit breaker.

TBD
Contingent

AE1-172, AE2-341, AF2-041, AF2-095, AF2-142, AF2-143, AF2-200, AF2-349, AF2-441, AG1-118

N/A
ComEdb3811.1 / CE_PJM B3811_L11323

Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.

Dec 01 2028
Contingent

AE1-114

N/A
ComEdb3811.2 / CE_PJM B3811_L11323

Additional Circuit Breaker at ESS H452

Dec 01 2028
Contingent

AE1-114

N/A
ComEdb3811.3 / CE_PJM B3811_L11323

Rebuild 3 miles of 138 kV line 11323 from Haumesser Road to the H-452 tap

Dec 01 2028
Contingent

AE1-114

N/A
ComEdn5145

Reconfigure Wilton 765kV bus

Dec 31 2025
Contingent

AE1-172, AE2-341, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-200, AF2-349, AF2-441, AG1-118

N/A
ComEdn6639.2 / CE_NUN_L15502_4

Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches.

42 Months
$146,197,759

AE1-114, AF1-280, AF1-296, AF2-041, AF2-182, AF2-199, AF2-200, AG1-462, AG1-553

ComEdn6840 / CE_NUN_Sta. 12 Dresden

Install a new 345kV bus tie circuit breaker at Station 12 Dresden

Dec 18 2024
Contingent

AE1-172

N/A
ComEdn9101.0 / CE_NUN_L18806

Mitigate sag on the Brokaw to TSS 909 Deer Creek 345 kV line L90907.

36 Months
$14,966,004

AE2-261, AG1-460

ComEdn9195.0 / CE_NUN_STA12_345 NEW CB

Install a new 345 kV circuit breaker at Station 12 Dresden.

45 Months
$3,357,627

AE1-172, AE2-223, AE2-261, AF2-225, AG1-374, AG1-460

ComEdn9269.0 / CE_NUN_L11212.5

Reconductorthe L11212 345 kV line.

42 Months
$37,989,655

AE1-172, AE2-223, AE2-261, AF2-041, AF2-095, AF2-199, AF2-200, AF2-225, AG1-118, AG1-374, AG1-460

ComEdn9682.0 / CE_NUN_0304.1

Perform sag mitigation on the Powerton - Tazewell 345 kV Line and replace disconnect switches at Powerton substation.

1 to 36 Months
$5,017,397

AF2-142, AF2-143, AF2-226, AF2-319

ComEds3011 / CE_S3011

Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.

Dec 31 2028
Contingent

AF2-182, AF2-349, AG1-374

N/A
Daytonb3904.1

Rebuild and reconductor 7.7 miles of 69kV line.

Jun 01 2029
Contingent

AF2-376

N/A
Dominionb3692

Rebuild approximately 27.7-miles of 500 kV transmission line from Elmont to Chickahominy.

Jun 01 2026
Contingent

AF1-123, AF1-124, AF1-125, AF1-128

N/A
Dominionb3694.8

Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1047 MVA.

May 03 2025
Contingent

AF2-042

N/A
Dominionb3800.312

Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.

Jun 30 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb3800.313

Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.

Jun 30 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb3800.354

Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.

Jun 30 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb3800.356

Build a new 500 kV line from Vint Hill to Wishing Star.

Jun 30 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb3800.357

Build a new 500 kV line from Morrisville to Vint Hill.

Jun 30 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb3800.373

Wreck and rebuild approximately 7.14 miles of 230kV line #256 from St. Johns to structure 256/108 to achieve a summer rating of 1573 MVA. Line switch 25666 at St. Johns to be upgraded to 4000A.

Jun 15 2027
Contingent

AF1-123, AF1-124, AF1-125

N/A
Dominionb3800.374

Reconductor approximately 5.30 miles of 230kV line #256 from Ladysmith CT to structure 256/107 to achieve a summer rating of 1573 MVA.

Jun 15 2027
Contingent

AF1-123, AF1-124, AF1-125

N/A
Dominionb4000.315

Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.

Apr 22 2030
Contingent

AF2-042, AG1-153, AG1-285

N/A
Dominionb4000.325

Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.

Feb 24 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.326

At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.

Feb 24 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.327

Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.

Feb 24 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.344

Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.345

Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.346

Cut-in 500kV line from Kraken substation into Yeat substation

Jun 01 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.348

Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.

Jun 01 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.349

Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.

Sep 16 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.350

Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.

Sep 16 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.351

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.

Sep 16 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.352

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.

Sep 16 2030
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionb4000.357

Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.

Jun 01 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominionn6605 / dom-101

Wreck and rebuild 0.99 miles of line 271 between Pocaty and Landstown with (2)-768 ACSS (20/7) “MAUMEE” conductor @ 250 degrees C. Replace the line lead at Landstown.

Dec 31 2026
$6,555,756

AF1-123, AF1-124, AF1-125, AF2-081

Dominionn6872 / dom-047

Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C.

Dec 31 2029
$59,572,939

AF2-042, AF2-080, AF2-222, AG1-106, AG1-285

Dominionn7553 / dom-427

Replace Northern Neck 115/230 kV transformer #6 with a 224 MVA (260/271/295 MVA).

59 to 60 Months
$7,242,347

AF2-120, AG1-135, AG1-536

Dominionn9112.0 / TC1-PH2-DOM-063

Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield.

46 to 47 Months
$87,030,447

AF1-123, AF1-124, AF1-125, AF2-042

Dominionn9139.0 / TC1-PH1-DOM-073

Wreck and rebuild 37.41 miles of 500kV line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" and associated substation work.

69 to 70 Months
$245,455,768

AF1-123, AF1-124, AF1-125, AF2-042

Dominionn9153.0 / TC1-PH1-DOM-043

Wreck and rebuild 5.9 miles of 230 kV line 2128 between Fentress and Thrasher with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Fentress.

43 to 44 Months
$33,297,247

AE2-156, AF1-123, AF1-124, AF1-125, AF2-081

Dominionn9191.0 / TC1-PH1-DOM-090

Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor and associated substation work.

74 to 75 Months
$256,706,175

AF1-123, AF1-124, AF1-125, AF2-042

Dominionn9199.0 / TC1-PH2-DOM-004

Wreck and rebuild 1.63 miles of line 2193 between Fork Union and Bremo with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C and replace line lead at Bremo.

42 to 43 Months
$7,947,612

AF1-123, AF1-124, AF1-125

Dominionn9200.0 / TC1-PH2-DOM-005

Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductors.

45 to 46 Months
$38,691,326

AF2-042, AF2-080, AF2-222, AG1-106, AG1-285

Dominionn9201.0 / TC1-PH2-DOM-006

Replace wave trap at Carson 230 kV (Carson - Sapony).

14 to 15 Months
$521,941

AF2-042, AF2-080, AF2-222, AG1-106, AG1-285

Dominionn9204.0 / TC1-PH2-DOM-014

Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

42 to 43 Months
$6,764,273

AF2-042, AF2-080, AF2-222, AG1-106, AG1-285

Dominionn9207.0 / TC1-PH2-DOM-018

Replace 6ELMONT 230 kV to 8ELMONT 500 kV circuit 1 with larger transformer (3-480 MVA single phase transformer).

59 to 60 Months
$38,254,469

AE2-156, AF1-123, AF1-124, AF1-125, AF2-081, AF2-120, AG1-536

Dominionn9217.0 / TC1-PH2-DOM-028

Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.

45 to 46 Months
$40,414,822

AE2-291, AF1-294, AF2-042, AF2-115, AF2-222, AG1-021, AG1-105, AG1-285, AG1-342

Dominionn9220.0 / TC1-PH2-DOM-033

Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

42 to 48 Months
$44,465,922

AE2-291, AF1-294, AF2-042, AF2-115, AF2-222, AG1-021, AG1-105, AG1-285, AG1-342

Dominionn9252.0 / TC1-PH2-DOM-047

Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor.

15 to 16 Months
$12,801,638

AF2-080

Dominionn9264.0 / TC1-PH1-DOM-080

Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1.

12 to 13 Months
$582,006

AF1-123, AF1-124, AF1-125, AF2-042

Dominionn9265.0 / TC1-PH2-DOM-064

Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B).

14 to 15 Months
$396,021

AF1-123, AF1-124, AF1-125, AF2-042

Dominionn9378.0 / TC1-PH3-DOM-010

Replace existing 230/500 kV Carson transformer 2 with (4)-480 MVA single phase transformers.

Dec 31 2029
$37,801,301

AF1-123, AF1-124, AF1-125, AF2-042, AF2-222, AG1-153

Dominionn9379.0 / TC1-PH3-DOM-011

Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase transformers.

Dec 31 2029
$37,836,293

AF1-123, AF1-124, AF1-125, AF2-042

Dominionn9380.0 / TC1-PH3-DOM-012

Replace existing Ladysmith 230/500 kV transformer 1 with four (4) 480 MVA single phase transformers.

Dec 31 2029
$37,587,605

AF1-123, AF1-124, AF1-125, AF2-120, AG1-536

Dominionn9651.0 / TC1-PH2-DOM-009

Wreck and rebuild 10.05 miles of Line 1059 between Northern Neck and Moon Corner with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C and replace line lead at Moon Corner (AE1-155).

Mar 31 2029
$28,476,954

AF2-120, AG1-135, AG1-536

Dominionn9681.0

Upgrade 1.04 Miles of 230kV transmission line 249 from 249/86 to 249/93

20 to 21 Months
$3,042,004

AF2-042, AF2-222, AG1-285

Dominions2824

Rebuild 230 kV Line #2056 from Hornertown to Hathaway.

Dec 31 2026
Contingent

AG1-106

N/A
Dominions3047.2

Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.

Jun 30 2029
Contingent

AE2-185, AE2-283, AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

N/A
Dominions3222.1

Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA.

Dec 31 2028
Contingent

AF2-080

N/A
NextErab3775.2

Reconductor NEET’s section of Crete(IN/IL border)-St. John 345 kV line (6.95 miles).

May 09 2023
Contingent

AF1-280, AF2-041, AF2-182, AF2-200, AF2-349, AG1-118, AG1-374, AG1-462

N/A
OVECn9680.0 / OVEC0001a

Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F

38 Months
$24,006,000

AF2-177, AF2-388, AF2-407, AG1-433

PENELECn9116.0 / TC1-PN-001.d

Rebuild approximately 11 miles of the Homer City-Shelocta 230 kV line with double bundled 795 kcmil 26/7 ACSS conductor

31 Months
$39,312,233

AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548

PENELECn9119.0 / TC1-PN-003.b

Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor

23 Months
$9,533,592

AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548

PENELECn9225.0 / TC1-PN-001.e

Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal

13 Months
$107,569

AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548

PENELECs3334.1 / PN-2023-030

Replace the existing Shawville 1A Transformer

Dec 31 2026
Contingent

AF2-296, AG1-090, AG1-377, AG1-378

N/A
PENELECs3335.1 / PN-2024-007

Replace Homer City South 345/230-23kV Transformer

Jun 01 2027
Contingent

AF2-010, AG1-548

N/A

Cost Allocation details for n9322.0 / TE-AG1-S-0012a


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-17659.53%$838,835
AF2-39640.47%$570,162

Cost Allocation details for n6639.2 / CE_NUN_L15502_4


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE1-1143.20%$4,677,511
AF1-2809.78%$14,292,703
AF1-2966.41%$9,366,298
AF2-04123.20%$33,916,212
AF2-18214.66%$21,438,948
AF2-1997.73%$11,305,333
AF2-20017.18%$25,123,010
AG1-4628.83%$12,912,297
AG1-5539.01%$13,165,446

Cost Allocation details for n9101.0 / CE_NUN_L18806


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE2-26190.88%$13,601,297
AG1-4609.12%$1,364,707

Cost Allocation details for n9195.0 / CE_NUN_STA12_345 NEW CB


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE1-17221.20%$711,694
AE2-22316.23%$545,043
AE2-26114.70%$493,549
AF2-22516.23%$545,043
AG1-37430.16%$1,012,774
AG1-4601.47%$49,523

Cost Allocation details for n9269.0 / CE_NUN_L11212.5


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE1-17224.51%$9,312,878
AE2-2238.44%$3,206,800
AE2-2618.99%$3,415,297
AF2-0417.29%$2,770,727
AF2-0959.09%$3,452,545
AF2-1992.43%$923,626
AF2-2005.40%$2,052,419
AF2-2258.44%$3,206,800
AG1-1188.64%$3,283,718
AG1-37415.85%$6,022,194
AG1-4600.90%$342,650

Cost Allocation details for n9682.0 / CE_NUN_0304.1


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-14237.50%$1,881,556
AF2-14337.50%$1,881,471
AF2-22612.50%$627,185
AF2-31912.50%$627,185

Cost Allocation details for n6605 / dom-101


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12332.55%$2,134,014
AF1-12432.67%$2,141,702
AF1-12532.04%$2,100,719
AF2-0812.74%$179,321

Cost Allocation details for n6872 / dom-047


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-04240.19%$23,940,647
AF2-08021.41%$12,754,165
AF2-22212.49%$7,438,616
AG1-10614.34%$8,545,448
AG1-28511.57%$6,894,063

Cost Allocation details for n7553 / dom-427


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-12035.86%$2,597,162
AG1-13533.29%$2,411,008
AG1-53630.85%$2,234,177

Cost Allocation details for n9112.0 / TC1-PH2-DOM-063


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12327.02%$23,513,865
AF1-12427.12%$23,598,622
AF1-12526.60%$23,146,929
AF2-04219.27%$16,771,032

Cost Allocation details for n9139.0 / TC1-PH1-DOM-073


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12327.55%$67,622,418
AF1-12427.65%$67,865,939
AF1-12527.12%$66,566,940
AF2-04217.68%$43,400,471

Cost Allocation details for n9153.0 / TC1-PH1-DOM-043


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE2-1561.60%$532,288
AF1-12332.41%$10,791,585
AF1-12432.53%$10,830,603
AF1-12531.90%$10,623,269
AF2-0811.56%$519,501

Cost Allocation details for n9191.0 / TC1-PH1-DOM-090


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12324.08%$61,806,471
AF1-12424.16%$62,026,005
AF1-12523.71%$60,854,858
AF2-04228.05%$72,018,840

Cost Allocation details for n9199.0 / TC1-PH2-DOM-004


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12333.47%$2,659,940
AF1-12433.59%$2,669,367
AF1-12532.94%$2,618,305

Cost Allocation details for n9200.0 / TC1-PH2-DOM-005


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-04239.33%$15,216,675
AF2-08020.96%$8,110,757
AF2-22213.97%$5,405,710
AG1-10614.05%$5,435,780
AG1-28511.69%$4,522,403

Cost Allocation details for n9201.0 / TC1-PH2-DOM-006


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-04243.63%$227,742
AF2-08012.31%$64,253
AF2-22215.50%$80,905
AG1-10615.59%$81,355
AG1-28512.97%$67,685

Cost Allocation details for n9204.0 / TC1-PH2-DOM-014


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-04239.34%$2,660,923
AF2-08020.96%$1,417,583
AF2-22213.97%$945,201
AG1-10614.04%$949,798
AG1-28511.69%$790,769

Cost Allocation details for n9207.0 / TC1-PH2-DOM-018


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE2-1563.59%$1,375,093
AF1-12329.47%$11,275,111
AF1-12429.58%$11,315,765
AF1-12529.01%$11,099,228
AF2-0812.80%$1,072,666
AF2-1202.50%$957,860
AG1-5363.03%$1,158,746

Cost Allocation details for n9217.0 / TC1-PH2-DOM-028


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE2-2913.84%$1,550,409
AF1-2945.01%$2,026,247
AF2-04246.18%$18,661,737
AF2-1153.06%$1,235,466
AF2-22218.35%$7,415,536
AG1-0212.45%$988,419
AG1-1056.67%$2,697,555
AG1-28511.84%$4,784,850
AG1-3422.61%$1,054,602

Cost Allocation details for n9220.0 / TC1-PH2-DOM-033


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AE2-2913.84%$1,705,384
AF1-2945.01%$2,229,393
AF2-04246.18%$20,532,412
AF2-1153.06%$1,359,435
AF2-22218.35%$8,159,120
AG1-0212.45%$1,087,573
AG1-1056.67%$2,967,877
AG1-28511.84%$5,264,576
AG1-3422.61%$1,160,153

Cost Allocation details for n9252.0 / TC1-PH2-DOM-047


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-080100.00%$12,801,638

Cost Allocation details for n9264.0 / TC1-PH1-DOM-080


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12329.59%$172,233
AF1-12429.70%$172,853
AF1-12529.13%$169,545
AF2-04211.58%$67,376

Cost Allocation details for n9265.0 / TC1-PH2-DOM-064


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12324.48%$96,938
AF1-12424.56%$97,278
AF1-12524.10%$95,442
AF2-04226.86%$106,363

Cost Allocation details for n9378.0 / TC1-PH3-DOM-010


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12322.37%$8,456,365
AF1-12422.45%$8,486,733
AF1-12522.02%$8,324,368
AF2-04223.67%$8,947,219
AF2-2224.83%$1,827,058
AG1-1534.65%$1,759,557

Cost Allocation details for n9379.0 / TC1-PH3-DOM-011


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12322.37%$8,463,643
AF1-12422.45%$8,493,744
AF1-12522.03%$8,333,502
AF2-04233.16%$12,545,404

Cost Allocation details for n9380.0 / TC1-PH3-DOM-012


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12330.90%$11,614,950
AF1-12431.01%$11,656,754
AF1-12530.42%$11,433,686
AF2-1203.47%$1,304,375
AG1-5364.20%$1,577,841

Cost Allocation details for n9651.0 / TC1-PH2-DOM-009


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-12031.47%$8,962,270
AG1-13530.46%$8,673,193
AG1-53638.07%$10,841,491

Cost Allocation details for n9681.0


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-04267.33%$2,048,312
AF2-22217.81%$541,856
AG1-28514.85%$451,836

Cost Allocation details for n9680.0 / OVEC0001a


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-17724.62%$5,909,187
AF2-38823.89%$5,736,003
AF2-40739.54%$9,492,808
AG1-43311.95%$2,868,001

Cost Allocation details for n9116.0 / TC1-PN-001.d


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-01014.90%$5,856,981
AF2-05020.44%$8,035,979
AG1-09025.20%$9,906,974
AG1-3775.31%$2,085,995
AG1-3785.31%$2,085,995
AG1-54828.85%$11,340,309

Cost Allocation details for n9119.0 / TC1-PN-003.b


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-01014.84%$1,414,721
AF2-05018.98%$1,809,075
AG1-09026.51%$2,527,390
AG1-3775.58%$532,032
AG1-3785.58%$532,032
AG1-54828.51%$2,718,342

Cost Allocation details for n9225.0 / TC1-PN-001.e


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF2-01014.90%$16,026
AF2-05020.44%$21,989
AG1-09025.20%$27,108
AG1-3775.31%$5,708
AG1-3785.31%$5,708
AG1-54828.85%$31,030

Short Circuit Reinforcements

PJM performed short circuit analysis for the New Service Requests in Transition Cycle 1 Final System Impact Study. The table below shows all the system reinforcements identified from short circuit analysis.

(None)

Stability Reinforcements

PJM performed stability analysis for the New Service Requests in Transition Cycle 1 Final System Impact Study. The table below shows all the system reinforcements identified from stability analysis.

TORTEP ID / TO IDTitleTime EstimateTotal Cost Estimate ($)Projects with Cost AllocationContingent ProjectsFacilities Study
Dominionn8492

Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.

26 to 27 Months
$80,172,278

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

AE2-185, AE2-283

Dominionn8492.1

Two Breaker Additions at Fentress Substation.

30 to 36 Months
$19,945,879

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

AE2-185, AE2-283

Dominionn8492.2

Expand Yadkin Substation to accommodate the new 500 kV line.

15 to 16 Months
$16,207,123

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

AE2-185, AE2-283

Dominionn9259.0

Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.

38 to 39 Months
$25,304,902

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

AE2-185, AE2-283

Dominionn9267.0 / TC1-PH2-DOM-067

Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.

45 to 46 Months
$45,730,074

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

AE2-185, AE2-283

Dominionn9630.0 / TC1-PH3-DOM-013

Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.

Dec 31 2029
$71,697,833

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-120, AF2-222, AG1-021, AG1-124, AG1-135, AG1-285, AG1-536

AE2-185, AE2-283

Dominionn9647.0

Install a 300 MVAR STATCOM at Fentress Substation.

Mar 31 2029
$49,163,341

AF1-123, AF1-124, AF1-125

Cost Allocation details for n8492


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12314.90%$11,942,531
AF1-12414.95%$11,984,782
AF1-12514.67%$11,757,413
AF1-2940.31%$247,251
AF2-04229.09%$23,321,932
AF2-1150.19%$150,804
AF2-1205.53%$4,436,569
AF2-2223.79%$3,040,611
AG1-0210.15%$120,659
AG1-1243.02%$2,419,517
AG1-1355.30%$4,251,051
AG1-2852.84%$2,275,928
AG1-5365.27%$4,223,231

Cost Allocation details for n8492.1


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12314.90%$2,971,155
AF1-12414.95%$2,981,667
AF1-12514.67%$2,925,100
AF1-2940.31%$61,513
AF2-04229.09%$5,802,211
AF2-1150.19%$37,518
AF2-1205.53%$1,103,764
AF2-2223.79%$756,467
AG1-0210.15%$30,019
AG1-1243.02%$601,946
AG1-1355.30%$1,057,609
AG1-2852.84%$566,223
AG1-5365.27%$1,050,688

Cost Allocation details for n8492.2


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12314.90%$2,414,227
AF1-12414.95%$2,422,768
AF1-12514.67%$2,376,805
AF1-2940.31%$49,983
AF2-04229.09%$4,714,615
AF2-1150.19%$30,486
AF2-1205.53%$896,869
AF2-2223.79%$614,671
AG1-0210.15%$24,392
AG1-1243.02%$489,114
AG1-1355.30%$859,366
AG1-2852.84%$460,087
AG1-5365.27%$853,742

Cost Allocation details for n9259.0


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12314.90%$3,769,440
AF1-12414.95%$3,782,775
AF1-12514.67%$3,711,011
AF1-2940.31%$78,040
AF2-04229.09%$7,361,138
AF2-1150.19%$47,598
AF2-1205.53%$1,400,321
AF2-2223.79%$959,713
AG1-0210.15%$38,084
AG1-1243.02%$763,676
AG1-1355.30%$1,341,766
AG1-2852.84%$718,355
AG1-5365.27%$1,332,985

Cost Allocation details for n9267.0 / TC1-PH2-DOM-067


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12314.90%$6,811,991
AF1-12414.95%$6,836,090
AF1-12514.67%$6,706,400
AF1-2940.31%$141,031
AF2-04229.09%$13,302,774
AF2-1150.19%$86,018
AF2-1205.53%$2,530,608
AF2-2223.79%$1,734,357
AG1-0210.15%$68,824
AG1-1243.02%$1,380,087
AG1-1355.30%$2,424,789
AG1-2852.84%$1,298,184
AG1-5365.27%$2,408,921

Cost Allocation details for n9630.0 / TC1-PH3-DOM-013


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12314.90%$10,680,170
AF1-12414.95%$10,717,955
AF1-12514.67%$10,514,620
AF1-2940.31%$221,116
AF2-04229.09%$20,856,735
AF2-1150.19%$134,863
AF2-1205.53%$3,967,611
AF2-2223.79%$2,719,209
AG1-0210.15%$107,905
AG1-1243.02%$2,163,767
AG1-1355.30%$3,801,702
AG1-2852.84%$2,035,356
AG1-5365.27%$3,776,823

Cost Allocation details for n9647.0


Cost Allocation
ProjectPercent AllocationAllocated Cost ($USD)
AF1-12333.47%$16,453,621
AF1-12433.59%$16,512,878
AF1-12532.94%$16,196,842
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.

Note: Additional detail can be found in each of the individual TC1 New Service Request System Impact Study reports also available on PJM.com.