AE2-283 Final System Impact Study (Retool 1) Report
v1.00 released 2025-12-08 18:15
Gladys-Stone Mill 69 kV
28.0 MW Capacity / 53.0 MW Energy
Introduction
This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Gladys Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).
Preface
The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:
- Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
- Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
- Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:
In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:
- PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
- The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):
If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:
- PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
- The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.
General
The Project Developer has proposed a Solar generating facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Campbell County, Virginia. The installed facilities will have a total capability of 53.0 MW with 28.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AE2-283 “Gladys-Stone Mill 69 kV” will interconnect with the Dominion’s transmission system through a new single breaker 69 kV switching station tapped off the Gladys to Stone Mill 69 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).
Based on the Final SIS results, the AE2-283 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AE2-283 | Cost Subject to Security* | |
| Transmission Owner Interconnection Facilities (TOIF) | $8,300,735 | $8,300,735 | |
| Other Scope | $0 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | |
| Network Upgrades | $3,617,755 | $3,617,755 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $0 | $0 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violatons | $0 | $0 | |
| AFS - Non-PJM Violations | $0 | $0 | |
| Total | $11,918,490 | $11,918,490 | |
* Contributes to calculation for Security. See Security Section of this report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Security Requirement
Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).
Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.
Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Security Due for AE2-283
Security has been calculated for the AE2-283 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.
Security Due for AE2-283
In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.
Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.
If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.
Transmission Owner Scope of Work
The New Service Request Project will interconnect with the Dominion transmission system by tapping the Gladys-Stone Mill 69 kV Line 35. The required work for the interconnection of the New Service Request Project to the Dominion Transmission System is detailed in the following tables.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Scope
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9429.0 | Re-arrange line #35 to loop into and out of the new AE2-283 single breaker 69 kV tap | $2,095,134 | $1,088,327 | $201,664 | $136,420 | $3,521,545 | $3,521,545 |
| n9323.0 | Remote Relay at Stone Mill Substation. | $144,634 | $99,161 | $27,348 | $17,487 | $288,630 | $96,210 (See Note 1) |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Build a new 69 kV single breaker tap located along VEPCO’s existing 69 kV #35 line from Gladys DP to Stone Mill Substation and terminate generator lead line. | $4,163,093 | $2,829,319 | $1,037,413 | $270,910 | $8,300,735 | $8,300,735 |
Based on the scope of work for the Interconnection Facilities, it is expected to take 39 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.
Transmission Owner Analysis
PJM performed a power flow analysis of the transmission system using a 2027 load flow model and the results were verified by Dominion.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AE2-283 was evaluated as a 53.0 MW (28.0 MW Capacity) injection in the Dominion area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | AEP | 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line | AEP_P1-2_#3174_6_SRT-A | Single | AC | 126.48 % | 245.0 | B | 309.89 | 9.53 | |
| GD1 | AEP | 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line | Base Case | Single | AC | 123.38 % | 167.0 | A | 206.05 | 9.71 | |
| GD1 | AEP | 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line | AEP_P1-2_#311_5_SRT-A | Single | AC | 107.23 % | 245.0 | B | 262.72 | 9.59 | |
| GD1 | AEP | 05OTTER-05JOHNMT 138.0 kV Ckt 1 line | AEP_P1-2_#3174_6_SRT-A | Single | AC | 127.99 % | 245.0 | B | 313.58 | 9.53 | |
| GD1 | AEP | 05OTTER-05JOHNMT 138.0 kV Ckt 1 line | Base Case | Single | AC | 125.51 % | 167.0 | A | 209.59 | 9.71 | |
| GD1 | AEP | 05OTTER-05JOHNMT 138.0 kV Ckt 1 line | AEP_P1-2_#311_5_SRT-A | Single | AC | 108.71 % | 245.0 | B | 266.35 | 9.59 | |
| GD1 | AEP/DVP | 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line | AEP_P1-2_#3174_6_SRT-A | Single | AC | 128.95 % | 245.0 | B | 315.94 | 9.53 | |
| GD1 | AEP/DVP | 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line | Base Case | Single | AC | 126.83 % | 167.0 | A | 211.8 | 9.71 | |
| GD1 | AEP/DVP | 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line | AEP_P1-2_#311_5_SRT-A | Single | AC | 109.65 % | 245.0 | B | 268.64 | 9.59 | |
| GD1 | DVP | 6BUCKING-6BREMO 230.0 kV Ckt 1 line | DVP_P1-2: LN 556_SRT-S-3 | Single | AC | 113.03 % | 571.52 | B | 645.99 | 1.52 | |
| GD1 | DVP | 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line | DVP_P1-2: LN 556_SRT-S-3 | Single | AC | 114.05 % | 559.3 | B | 637.86 | 1.52 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | DVP | 8RAWLINGS-8CARSON 500.0 kV Ckt 1 line | DVP_P1-2: LN 585_SRT-A-1 | Single | AC | 106.7 % | 4070.2 | B | 4342.97 | 3.73 | |
| GD1 | DVP | 8RAWLINGS-8CARSON 500.0 kV Ckt 1 line | DVP_P1-2: LN 585_SRT-A-2 | Single | AC | 102.59 % | 4070.2 | B | 4175.62 | 3.73 | |
| GD1 | AEP/DVP | AE1-108 TP-4BREMO 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-A | Breaker | AC | 148.6 % | 167.0 | B | 248.16 | 2.71 | |
| GD1 | AEP/DVP | AE1-108 TP-4BREMO 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 147.33 % | 167.0 | B | 246.03 | 2.71 | |
| GD1 | AEP/DVP | AE1-108 TP-4BREMO 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 118.01 % | 167.0 | B | 197.07 | 1.43 | |
| GD1 | DVP | AE2-094 TP-8CARSON 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S | Single | AC | 104.04 % | 4070.2 | B | 4234.7 | 3.4 |
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | AEP | 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line | Base Case | OP | AC | 149.29 % | 167.0 | A | 249.31 | 18.39 | |
| GD1 | AEP | 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line | AEP_P1-2_#3174_6_SRT-A | OP | AC | 144.76 % | 245.0 | B | 354.66 | 18.03 | |
| GD1 | AEP | 05OTTER-05JOHNMT 138.0 kV Ckt 1 line | Base Case | OP | AC | 151.42 % | 167.0 | A | 252.87 | 18.39 | |
| GD1 | AEP | 05OTTER-05JOHNMT 138.0 kV Ckt 1 line | AEP_P1-2_#3174_6_SRT-A | OP | AC | 146.26 % | 245.0 | B | 358.35 | 18.03 | |
| GD1 | DVP | 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer | DVP_P1-2: LN 173_SRT-A | OP | AC | 134.39 % | 134.04 | B | 180.13 | 52.99 | |
| GD1 | DVP | 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer | Base Case | OP | AC | 123.76 % | 128.78 | A | 159.38 | 52.99 | |
| GD1 | DVP | 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line | DVP_P1-2: LN 173_SRT-A | OP | AC | 165.64 % | 101.52 | B | 168.15 | 52.99 | |
| GD1 | DVP | 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line | Base Case | OP | AC | 148.09 % | 101.52 | A | 150.34 | 52.99 | |
| GD1 | DVP | 3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line | DVP_P1-2: LN 35_SRT-A-3 | OP | AC | 172.9 % | 66.74 | B | 115.39 | 53.0 | |
| GD1 | DVP | 3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line | Base Case | OP | AC | 166.5 % | 66.74 | A | 111.12 | 53.0 | |
| GD1 | AEP/DVP | 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line | Base Case | OP | AC | 152.76 % | 167.0 | A | 255.1 | 18.39 | |
| GD1 | AEP/DVP | 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line | AEP_P1-2_#3174_6_SRT-A | OP | AC | 147.23 % | 245.0 | B | 360.72 | 18.03 | |
| GD1 | DVP | AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line | DVP_P1-2: LN 35_SRT-A-3 | OP | AC | 172.99 % | 66.74 | B | 115.45 | 53.0 | |
| GD1 | DVP | AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line | Base Case | OP | AC | 166.59 % | 66.74 | A | 111.18 | 53.0 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | DVP | 3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line | AEP_P1-2_#5366_42_SRT-A-1 | OP | AC | 100.93 % | 285.76 | B | 288.41 | 11.8 | |
| GD1 | DVP | AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line | AEP_P1-2_#5366_42_SRT-A-1 | OP | AC | 101.1 % | 285.76 | B | 288.91 | 11.8 |
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Light Load Analysis
The New Service Request AE2-283 was evaluated as a 53.0 MW injection in the Dominion area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
(No impacts were found for this analysis)
Light Load Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
(No impacts were found for this analysis)
Short Circuit Analysis
Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Stability Analysis
Analysis Complete - No Issues
Executive Summary for Dynamic Stability Analysis Using PSSE
New Service Requests (projects) in PJM Transition Cycle 1 Cluster 35 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 35 projects.
Table 1: Transition Cycle 1 Cluster 35 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO (MW) | MWE (MW) | MWC (MW) | Point of Interconnection |
35 | AE2-185 | Solar | Dominion | 60 | 60 | 36 | Gladys DP – Stonemill 69 kV |
AF2-404 | Battery | Dominion | 0 | 0 | |||
AE2-283 | Solar | Dominion | 53 | 53 | 28 |
This analysis is effectively a screening study to determine whether the addition of the Cluster 35 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.
The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 35 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 35 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 35 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.
For Cluster 35 the dispatch of the study units was based on two scenarios.
- Scenario 1: MFO met with solar generation and energy storage offline (solar output = 61.9 MW and storage is offline)
- Scenario 3: MFO met with the solar generation and energy storage dispatched proportionally to their power capability (solar output = 47.44 MW and storage output = 14.56 MW)
Cluster 35 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 75 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:
- Steady-state operation
- Three-phase faults with normal clearing time
- Single-phase bus faults with normal clearing time
- Single-phase faults with stuck breaker
- Single-phase faults with delayed clearing at remote end
- Three-phase faults with loss of multiple-circuit tower line.
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the RTEP 2027 summer peak case:
- Cluster 35 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
- The system with Cluster 35 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
- Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy and AEP’s transmission planning criteria.
- Dominion Energy:
- P1 Category Contingencies:
- 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.01 to 1.096 p.u. for 500 kV facilities
- P2, P4, P5, and P7 Category Contingencies:
- 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.00 to 1.096 p.u. for 500 kV facilities
- AEP:
- 0.92 p.u. to 1.05 p.u. for all voltage levels for each NERC Category Contingency
- No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
The results of the analysis indicated all evaluation criteria were met. The following observations were made.
The initial results showed that Cluster 35 generators units exhibited slow reactive power recovery for several contingencies, Power Plant Controller (PPC) freezing, divergence and low frequency controller oscillations. These issues did not cause instability, and the generating units were tuned to achieve a faster recovery with better response.
The following adjustments were required for the respective queue projects based on the analysis results:
- For AE2-187 the following adjustments were made:
- The REECA1 Vup (p.u.) (CON J+1) parameter was set to 1.15 p.u to mitigate PPC freezing
- Generator tripped for overvoltage protection model for voltage above 1.21 p.u and the time delay setting was updated from 0.16 to 0.3 seconds to allow generator to ride through the fault
- For AE2-283 the following adjustments were made:
- The REGCA1 Accel (CON J+13) parameter was set to 0.5 to improve PSS/E network solution calculations
- For AC1-122 the following adjustments were made:
- The REPCA Ki (CON J+2) parameter was changed from 0 to 10 to improve reactive power recovery
During phase 3 analysis all generations near Cluster 35 (AC1-042, AC1-145, AE2-185, AE2-187, and AF2-404) have their REGCA1 Accel set to 0.7. This was implemented as part of a phase 2 observation. It should be noted that this parameter does not affect the performance or recovery of the renewable model, but is used to smooth the voltage and angle calculations within PSS/E.
Voltages above 1.05 p.u. were observed at Altavista 69 kV. This is due to Altavista 138-69 kV load tap changer operating at 1.10 p.u. to maintain the Altavista 69 kV scheduled voltage. A significant voltage drop was observed between Altavista, Gladys Tap, Altavista DP, and Mt Airy Tap due to the amount of generation served within the Altavista 69 kV system. To ensure that the post contingency voltage is below 1.05 p.u., the Altavista 138/69 kV load tap changing transformer would need to operate at 1.0375 p.u. tap and under System Normal (P0) conditions, would produce a 0.968 p.u. voltage on the Altavista 69 kV bus, which is within Dominion Energy’s P0 voltage levels. A voltage coordination study is recommended in the future to determine an acceptable voltage schedule for the Altavista 138/69 kV load tap changing transformer to coordinate with the generations served in the Altavista 69 kV system.
AE2-185, AF2-404, AE2-283, AC1-042 and AE2-187 were observed to have controller oscillations for a few faults such as P415. This is not a concern, and IC can tune their model to eliminate this behavior.
AD1-131, and AF2-107’s reactive power was observed to not settle within the 30 second simulation window for various faults. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement.
Low-frequency oscillations were observed for AE1-250 that were positively damped and settled in less than 15 seconds. This issue did not cause instability in the system.
The AE2-185 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.
The AE2-185 and AF2-404 BESS queue projects combined met the 0.95 lagging and leading power factor measured at the high side of main transformer.
The AE2-283 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.
A voltage coordination study and Electromagnetic Transients (EMT) study around Altavista is recommended due to the findings of this analysis. Additionally, any future projects connecting near Altavista should provide EMT models for their facility.
No mitigations were found to be required
Executive Summary for Dynamic Stability Analysis Using PSCAD/EMT
Model Quality Testing Report
PSCAD model for Queue project AE2-185/AF2-404 and AE2-283 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.
Table 2. MQT Result for each project
Test | Status |
Flat Start Test | Pass |
Voltage Step-Down | Pass |
Voltage Step-Up | Pass |
Frequency Step-Down, No Headroom | Pass |
Frequency Step-Down, Headroom | Pass |
Frequency Step-Up, Headroom | Pass |
HVRT Leading | Pass |
HVRT Lagging | Pass |
LVRT Leading | Pass |
LVRT Lagging | Pass |
System Strength Test | Pass |
Voltage Ride Through | Pass |
Phase Angle Step-Down | Pass |
Phase Angle Step-Up | Pass |
Weak Grid Assessment
This Weak Grid Assessment evaluates three projects from PJM Transition Cycle 1 (TC1) Cluster 35 for risk of voltage instability due to weak grid conditions in an EMT simulation environment. The three projects, AE2-185, AF2-404, and AE2-283, were identified in the Cluster Study as having potential risk of weak grid instability during contingency conditions after dynamic simulation analysis in PSS/E. System reinforcement was found to not be required, although evaluation using detailed models in an EMT simulation was recommended.
This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability due to low short circuit ratio as identified in the Cluster Study, using detailed models in an EMT simulation. A summary description of each project can be found below:
Table 3. Summary Description of TC1 Cluster 35 Projects
Project Name | Project Type | Project Size (MW) | POI | POI Bus Number |
AE2-185 / AF2-404 Pigeon Run Solar and BESS | PV + BESS | 60 | Gladys DP – Stonemill 69 kV | 941800 |
AE2-283 Gladys Solar | PV | 53 | Gladys DP – Stonemill 69 kV | 942670 |
Individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test process, model updates being made where needed. INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model.
Two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. For Cluster 35, the following contingency cases were chosen (all projects operating at rated power pre-fault).
- Fault ID: P1.01: Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35
- Fault ID: P1.18: Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13
Simulation results in PSCAD are summarized below. It can be observed that in case P1.01 the islanded condition results in the projects tripping, similar to the Cluster Study. Overall system recovery as observed from the remaining 138kV network is stable. In P1.18, stable recovery is observed in PSCAD and is consistent with the results of the Cluster Study.
Table 4. Summary of cases tested in PSCAD system study
Fault ID | Fault Description | Cluster Study Result | PSCAD Study Result |
P1.01 | Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35. Islanded condition in the 69 kV subnetwork. Cluster projects expected to trip. | System Stable, | System Stable, |
P1.18 | Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13 | Stable | Stable |
The results of this weak grid assessment using PSCAD show overall stable system recovery in the two worst-case contingencies and supports the conclusion from the Cluster Study that mitigation's are not required.
Reactive Power Analysis
The reactive power capability of AE2-283 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA2-057 | Hornertown-Whitakers 115kV | In Service |
| AB1-081 | Anaconda-Mayo Dunbar 115kV | In Service |
| AB1-132 | Thelma 230kV | In Service |
| AB1-173 | Brink-Trego 115kV | In Service |
| AB2-040 | Brink 115kV | In Service |
| AB2-043 | Chase City 115kV | In Service |
| AB2-045 | Buckingham 34.5kV | In Service |
| AB2-059 | Benson-Dunbar 115kV | In Service |
| AB2-060 | Chase City-Lunenburg 115kV | In Service |
| AB2-077 | Buggs Island-Chase City 115kV | In Service |
| AB2-078 | Buggs Island-Chase City 115kV | In Service |
| AB2-079 | Buggs Island-Chase City 115kV | In Service |
| AB2-174 | Emporia-Trego 115kV | In Service |
| AC1-034 | Heartsease DP - Mayo Dunbar 115kV | Suspended |
| AC1-036 | Twittys Creek 34.5kV | In Service |
| AC1-042 | Altavista-Mt. Airy 69kV | In Service |
| AC1-054 | Kerr Dam–Eatons Ferry 115 kV | In Service |
| AC1-075 | Perth-Hickory Grove 115kV | In Service |
| AC1-080 | Perth-Hickory Grove 115kV | In Service |
| AC1-083 | Smith Mountain-Bearskin 138kV | In Service |
| AC1-086 | Thelma 230kV | Suspended |
| AC1-098 | Dawson-South Justice 115kV | Partially in Service - Under Construction |
| AC1-099 | Dawson-South Justice 115kV | Partially in Service - Under Construction |
| AC1-105 | Halifax-Mt. Laurel 115kV | In Service |
| AC1-145 | Gretna DP 69 kV | In Service |
| AC1-208 | Cox-Whitakers 115kV | Under Construction |
| AC1-221 | Halifax-Person 230kV | In Service |
| AC1-222 | Crystal Hill-Halifax 115kV | In Service |
| AC2-084 | Dawson-South Justice 115kV | Partially in Service - Under Construction |
| AC2-100 | Halifax-Person 230kV | In Service |
| AC2-165 | Bremo-Powhatan 230kV | Suspended |
| AD1-056 | Hornertown-Hathaway 230 kV | Suspended |
| AD1-057 | Hornertown-Hathaway 230 kV | Suspended |
| AD1-087 | Clover-Sedge Hill 230 kV | In Service |
| AD1-088 | Briery-Clover 230 kV | Suspended |
| AD1-152 | Clover-Sedge Hill 230 kV | In Service |
| AD2-022 | East Danville - Roxborough 230 kV | Engineering & Procurement |
| AD2-023 | East Danville - Roxborough 230 kV | Engineering & Procurement |
| AD2-033 | Chase City-Lunenburg 115 kV | Under Construction |
| AD2-202 | Clover-Sedge Hill 230kV | In Service |
| AE1-108 | Bremo-Scottsville 138 kV | Engineering & Procurement |
| AE1-250 | Smith Mountain-E. Danville 138 kV | Engineering & Procurement |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-185 | Gladys DP-Stonemill Switching Station 69 kV | Active |
| AE2-259 | Curdsville-Willis Mtn 115 kV | Engineering & Procurement |
| AE2-291 | Grit DP-Perth 115 kV | Active |
| AF1-058 | Welco 34.5 kV | In Service |
| AF1-292 | Fields 34.5kV | Engineering & Procurement |
| AF1-294 | Jetersville-Ponton 115 kV | Active |
| AF2-042 | Clover-Rawlings 500 kV | Active |
| AF2-115 | Jetersville-Ponton 115 kV | Active |
| AF2-222 | Madisonville DP-Twitty's Creek 115 kV | Active |
| AF2-299 | Fields 34.5 kV | Active |
| AG1-021 | Jetersville-Ponton 115 kV | Active |
| AG1-105 | Mount Laurel-Barnes Junction 115 kV | Active |
| AG1-106 | Thelma 230 kV | Active |
| AG1-285 | Chase City-Central 115 kV | Active |
| AG1-342 | Dryburg 115 kV | Active |
| AG1-532 | Fields 34.5 kV | Engineering & Procurement |
| Z2-044 | Whitakers 34.5kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.
If your project required an Affected System Study, the results are shown below from the Affected System Operator.
For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.
System Reinforcements
Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| Dominion | n8492.2 | Expand Yadkin Substation to accommodate the new 500 kV line. | Contingent | $0 | N/A |
| Dominion | n9259.0 | Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation. | Contingent | $0 | N/A |
| Dominion | n9267.0 | Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. | Contingent | $0 | N/A |
| Dominion | n9630.0 | Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. | Contingent | $0 | N/A |
| Dominion | b4000.357 | Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. | Contingent | $0 | N/A |
| Dominion | b4000.352 | Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. | Contingent | $0 | N/A |
| Dominion | b4000.351 | Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. | Contingent | $0 | N/A |
| Dominion | b4000.350 | Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. | Contingent | $0 | N/A |
| Dominion | b4000.349 | Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. | Contingent | $0 | N/A |
| Dominion | b4000.348 | Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. | Contingent | $0 | N/A |
| Dominion | b4000.346 | Cut-in 500kV line from Kraken substation into Yeat substation | Contingent | $0 | N/A |
| Dominion | b4000.345 | Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. | Contingent | $0 | N/A |
| Dominion | b4000.344 | Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. | Contingent | $0 | N/A |
| Dominion | b4000.325 | Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. | Contingent | $0 | N/A |
| Dominion | b4000.326 | At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. | Contingent | $0 | N/A |
| Dominion | b4000.327 | Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. | Contingent | $0 | N/A |
| Dominion | s3047.2 | Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. | Contingent | $0 | N/A |
| Dominion | b3800.312 | Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. | Contingent | $0 | N/A |
| Dominion | b3800.313 | Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. | Contingent | $0 | N/A |
| Dominion | b3800.356 | Build a new 500 kV line from Vint Hill to Wishing Star. | Contingent | $0 | N/A |
| Dominion | b3800.357 | Build a new 500 kV line from Morrisville to Vint Hill. | Contingent | $0 | N/A |
| Dominion | b3800.354 | Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. | Contingent | $0 | N/A |
| Dominion | n8492 | Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. | Contingent | $0 | N/A |
| Dominion | n8492.1 | Two Breaker Additions at Fentress Substation. | Contingent | $0 | N/A |
| AEP | b4000.211 | Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line | Contingent | $0 | N/A |
| AEP | b4000.210 | Rebuild 7 miles of Otter - Johnson Mountain 138 kV line. | Contingent | $0 | N/A |
| AEP | n5613 | Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line. | Contingent | $0 | N/A |
| Grand Total: | $0 | ||||
PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b4000.211
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.211
- Title
- Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line
- Description
- Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line Projected In Service Date: 06/01/2029
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4000.210
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.210
- Title
- Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
- Description
- Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOHNMT-05OTTER 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n5613
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n5613 / AEPA0014a
- Title
- Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
- Description
- Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
- Total Cost ($USD)
- $2,740,849
- Discounted Total Cost ($USD)
- $2,740,849
- Allocated Cost ($USD)
- $0
- Time Estimate
- Nov 21 2027
Contingent Note: Based on PJM cost allocation criteria, AE2-283 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle. Although AE2-283 may not have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable for the reliability to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05OTTER-4ALTVSTA 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending)
- Title
- Most limiting rating on the Dominion side is the Wave Trap and Lead at Altavista: 363 / 382 /420 MVA.
- Description
- Most limiting rating on the Dominion side is the Wave Trap and Lead at Altavista: 363 / 382 /420 MVA.
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- 99 Months
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05OTTER-4ALTVSTA 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending) / dom-397
- Title
- ELIMINATED FOR TC1: Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
- Description
- Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C.
- Total Cost ($USD)
- $23,887,052
- Discounted Total Cost ($USD)
- $23,887,052
- Allocated Cost ($USD)
- $0
- Time Estimate
- 43 to 44 Months
ContingentEliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 4BREMO-AE1-108 TP 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending) / AEPAPRJV007
- Title
- ELIMINATED FOR TC1: Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.
- Description
- •Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design. •Replace 3 structures and 1 floating dead ends along the Reusens – Scottsville – Bremo Bluff line determined in preliminary engineering study.
- Total Cost ($USD)
- $4,759,000
- Discounted Total Cost ($USD)
- $4,759,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 29 Months
ContingentEliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 4BREMO-AE1-108 TP 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending) / AEPAPRJV008
- Title
- ELIMINATED FOR TC1: Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.
- Description
- "•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design. •Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line by installing one floating deadend and replacing one structure"
- Total Cost ($USD)
- $1,245,000
- Discounted Total Cost ($USD)
- $1,245,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 15 Months
ContingentEliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 4BREMO-AE1-108 TP 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9220.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9220.0 / TC1-PH2-DOM-033
- Title
- Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
- Description
- Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
- Total Cost ($USD)
- $44,465,922
- Discounted Total Cost ($USD)
- $44,465,922
- Allocated Cost ($USD)
- $0
- Time Estimate
- 42 to 48 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BUCKING-6BREMO 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9217.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9217.0 / TC1-PH2-DOM-028
- Title
- Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
- Description
- Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
- Total Cost ($USD)
- $40,414,822
- Discounted Total Cost ($USD)
- $40,414,822
- Allocated Cost ($USD)
- $0
- Time Estimate
- 45 to 46 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BUCKING-6FARMVIL 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9138.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9138.0 / TC1-PH1-DOM-070
- Title
- ELIM TC1: Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
- Description
- Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
- Total Cost ($USD)
- $111,130,292
- Discounted Total Cost ($USD)
- $111,130,292
- Allocated Cost ($USD)
- $0
- Time Estimate
- 60 to 61 Months
Potential Aggregate ContributorEliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | ||
|---|---|---|---|
| 8CARSON-8RAWLINGS 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S-C | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S-A | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P4-2: 51192_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P4-2: 51172_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P4-2: 511T544_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: n9250.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9250.0 / TC1-PH2-DOM-044
- Title
- ELIM TC1: Construct a new 22.59 mile line between Carson and Rawlings Substations.
- Description
- Construct a new 22.59 mile line between Carson and Rawlings Substations.
- Total Cost ($USD)
- $108,728,086
- Discounted Total Cost ($USD)
- $108,728,086
- Allocated Cost ($USD)
- $0
- Time Estimate
- 60 to 61 Months
Potential Aggregate ContributorEliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | ||
|---|---|---|---|
| 8CARSON-8RAWLINGS 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S-C | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S-A | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P1-2: LN 511_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P4-2: 51192_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P4-2: 51172_SRT-S | No new ratings for this Flowgate. | |
| 8CARSON-AE2-094 TP 500.0 kV Ckt 1 line | DVP_P4-2: 511T544_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: n8492.2
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n8492.2
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n8492.2
- Title
- Expand Yadkin Substation to accommodate the new 500 kV line.
- Description
- Expansion of yadkins 500 kV switchyard to accommodate the new 500 kV line which includes addition of 5000 amp GIS breakers and relocation of the existing suffolk -yadkin 500 kV line#565
- Total Cost ($USD)
- $16,207,123
- Allocated Cost ($USD)
- $0
- Time Estimate
- 15 to 16 Months
- Cost Alloc Type
- Contingent
System Reinforcement: n9259.0
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n9259.0
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n9259.0
- Title
- Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.
- Description
- Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.
- Total Cost ($USD)
- $25,304,902
- Allocated Cost ($USD)
- $0
- Time Estimate
- 38 to 39 Months
- Cost Alloc Type
- Contingent
System Reinforcement: n9267.0
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n9267.0
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n9267.0 / TC1-PH2-DOM-067
- Title
- Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
- Description
- Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner substations with single (1) 768.2 ACSS/TW “Maumee” at 250 degrees C. This new line will be on separate transmission towers from the existing Northern Neck and Moon Corner line 1059. Station expansion is required at Northern Neck and Moon Corner to accommodate the new line.
- Total Cost ($USD)
- $45,730,074
- Allocated Cost ($USD)
- $0
- Time Estimate
- 45 to 46 Months
- Cost Alloc Type
- Contingent
System Reinforcement: n9630.0
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n9630.0
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n9630.0 / TC1-PH3-DOM-013
- Title
- Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
- Description
- n9630.0 addresses both stability and load flow violations. Construct a new 230 kV Line from the AG1-285 substation to the 230 kV Finneywood substation following the Line 1012 ROW for approximately 1.0 miles, then following the Line 556 ROW for approximately 3.5 miles to terminate at Finneywood. Expand the AG1-285 115 kV substation to accommodate two (2) new 115/230 kV transformers. Build a 230 kV substation at AG1-285 to connect the 115/230 kV transformers and the new 230 kV line to Finneywood. Expand the Finneywood 230 kV substation to accommodate the new line. The existing 1.0 miles of 115 kV from AG1-285 to Chase City does not need to be rebuilt to accommodate a new structure in the same right of way and therefore will be unchanged. The existing 3.5 miles of 500 kV towers from Structure 556/46 to Finneywood substation will need to be rebuilt as a double circuit tower to accommodate the new 230 kV line.
- Total Cost ($USD)
- $71,697,833
- Allocated Cost ($USD)
- $0
- Time Estimate
- Dec 31 2029
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.357
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.352
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.351
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.351
System Reinforcement: b4000.350
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.349
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.348
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.346
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.345
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.344
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.325
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.325
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.325
- Title
- Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
- Description
- Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.326
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.326
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.326
- Title
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Description
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b4000.327
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.327
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.327
- Title
- Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
- Description
- Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: s3047.2
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: s3047.2
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- s3047.2
- Title
- Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
- Description
- Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV line #535 Loudoun – Meadowbrook and #569 Loudoun - Morrisville as the 500 kV sources into the proposed 500 kV ring bus Vint Hill Substation will be expanded to the north of the existing site to accommodate the 500 kV ring required for the addition of the new transformers Existing terminations for 230 kV line #2174 Wheeler – Vint Hill, line #2101 Bristers – Vint Hill, and line #2163 Liberty – Vint Hill will be rearranged to terminate into the expanded Vint Hill Substation 230 kV line #2114 Remington CT – Rollins Ford will also be cut and looped into the expanded Vint Hill Substation due to spatial constraints along the existing right-of-way.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b3800.312
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.312
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.312
- Title
- Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
- Description
- Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b3800.313
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.313
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.313
- Title
- Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
- Description
- Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b3800.356
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.356
- Title
- Build a new 500 kV line from Vint Hill to Wishing Star.
- Description
- Build a new 500kV line from Vint Hill to Wishing Star. The line will be supported on single circuit monopoles. New conductor to have a summer rating of 4357 MVA. Line length is approximately 16.59 miles
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b3800.357
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.357
- Title
- Build a new 500 kV line from Morrisville to Vint Hill.
- Description
- Build a new 500kV line from Morrisville to Vint Hill. New conductor to have a summer rating of 4357 MVA. Line length is approximately 19.71 miles.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: b3800.354
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.354
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.354
- Title
- Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
- Description
- Install terminal equipment at Wishing Star substation to support a 5000A line to Vint Hill. Update relay settings for 500kV Lines #546 and #590.
- Cost Information
- Cost Alloc Type
- Contingent
System Reinforcement: n8492
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n8492
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n8492
- Title
- Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
- Description
- Wreck and rebuild one (1) overhead 500kV transmission line that will start at the existing Fentress 500 kV Substation and terminate at the existing Yadkin 500 kV Substation, located approximately 13.5 miles away.
- Total Cost ($USD)
- $80,172,278
- Allocated Cost ($USD)
- $0
- Time Estimate
- 26 to 27 Months
- Cost Alloc Type
- Contingent
System Reinforcement: n8492.1
AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n8492.1
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n8492.1
- Title
- Two Breaker Additions at Fentress Substation.
- Description
- Install Two 5000 amp GIS Breakers at Fentress Substation to connect the new 500 kV line 5005.
- Total Cost ($USD)
- $19,945,879
- Allocated Cost ($USD)
- $0
- Time Estimate
- 30 to 36 Months
- Cost Alloc Type
- Contingent