AF1-161 Final System Impact Study (Retool 2) Report
v2.00 released 2026-05-14 11:46
Valley 138 kV
25.0 MW Capacity / 50.0 MW Energy
Introduction
This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Decatur Storage LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..
Preface
The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:
- Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
- Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
- Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:
In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:
- PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
- The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
The AF1-161 Final System Impact Study (Retool 1) Report is available for download here.
Retool 2 (if needed):
If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:
- PJM will perform Retool 2 (if necessary) considering only the removal of projects from the model which chose not to execute their agreements after Retool 1.
- The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.
General
The Project Developer has proposed a Storage facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Van Buren County, Michigan. The installed facilities will have a total capability of 50.0 MW with 25.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AF1-161 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system at the Valley 138kV substation.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).
Based on the Final SIS results, the AF1-161 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AF1-161 | Cost Subject to Security* | |
| Transmission Owner Interconnection Facilities (TOIF) | $503,836 | $503,836 | |
| Other Scope | $0 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | |
| Network Upgrades | $1,371,722 | $1,371,722 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $0 | $0 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $16,136 | $16,136 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | |
| AFS - Non-PJM Violations | $250,855 ** | $0 ** | |
| Total | $2,142,549 | $1,891,694 | |
* Contributes to calculation for Security. See Security Requirement Section of this report for additional detail.
** This value reflects the results at the time of the report posting and it is subject to change. AFS – Non-PJM Violations are not subject to Security. For latest AFS – Non-PJM Violations, please refer to the latest Affected System Study Report for your project.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Security Requirement
Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).
Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.
Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Security Due for AF1-161/AG1-109
Security has been calculated for the AF1-161/AG1-109 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.
Security Due for AF1-161/AG1-109
In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.
Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.
If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.
Transmission Owner Scope of Work
AF1-161 will interconnect with the AEP transmission system via a direct connection to the Valley 138 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Scope
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9557.0 | Valley 138 kV Station: Expansion of Station. • One (1) new 3000 A 138 kV 40 kA circuit breaker (breaker “Q”) with breaker control relaying for the Stinger Circuit relocation. • Two (2) new 3-phase 3000 A circuit breaker disconnect switches. • Three (3) single phase capacitor coupled voltage transformers and associated structures for the Stinger Circuit relocation. • Three (3) single phase Arresters and associated structures for the Stinger Circuit relocation. • One 16 ft. x 18 ft. DICM expansion to the existing Valley 138 kV Station DICM control house. • Dual fiber-based integrated communications optical network multiplexor current differential relays for the protection scheme for the re-terminated Stinger Circuit. • Expansion of a 132' section of the Valley 138 kV Station fence by 20' to the East, across from the east side of the middle box bay. • Associated jumpers, insulators, grounding, fiber-optic relaying connectivity & equipment, cables, pull boxes and foundations. • Protection and control settings review for the existing relays at the Valley 138 kV Station and adjustment as needed. | $934,627 | $938,428 | $136,800 | $156,635 | $2,166,490 | $1,083,245 (See Note 1) |
| n9556.0 | Valley 138 kV Station: Re-termination of the Stinger Circuit in the Valley 138 kV Station. • Remove the existing Stinger - Valley 138 kV Circuit connection to the Valley 138 kV Station by removing one (1) existing 65 ft. wood pole structure (#285) and one (1) span of line conductor with shield wire. • Install one (1) new custom 80 ft. steel, single circuit, single pole dead end structure on a concrete foundation with an anchor bolt cage. • Install one (1) span of ACSR 1033.5 54/7 (Curlew) transmission line conductor with 7#8 Alumoweld shield wire for the new Stinger line exit. | $292,715 | $159,811 | $80,485 | $43,942 | $576,953 | $288,476 (See Note 1) |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | • Installation of one (1) new custom 80 ft. steel, single circuit, single pole dead end structure on a concrete foundation with an anchor bolt cage and • Extension of one (1) span of aluminum conductor steel-reinforced (ACSR) 1033.5 54/7 (Curlew) transmission line conductor to the east with 7#8 Alumoweld shield wire for the generation lead circuit connecting to the Valley 138 kV Station. • The proposed generation lead circuit will be protected by the existing Circuit Breaker “M” relays using a dual direct fiber current differential protection scheme. • Installation of a 138 kV revenue metering package, including one (1) drop in control module ("DICM")-installed metering panel with Primary and Backup meters, three (3) 1-phase current transformers ("CT"s), three (3) 1-phase voltage transformers ("VT"s), three (3) 1-phase surge arresters, and associated structures, foundations, grounding, and telecommunications connectivity at the Valley 138 kV Station for the proposed AF1-161 generation lead circuit. • Extension of two (2) underground all dielectric loose tube fiber optic cables with all dielectric self-supporting entrances via diverse paths from the Valley 138 kV Station control house to fiber demarcation splice boxes to support direct fiber relaying between the Valley 138 kV Station and the Project Developer's collector station. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station. | $547,448 | $296,949 | $106,664 | $56,611 | $1,007,672 | $503,836 (See Note 1) |
Based on the scope of work for the Interconnection Facilities, it is expected to take 25 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.
Transmission Owner Analysis
There were no network impacts to Distribution facilities identified by the Transmission Owner.
The Transmission Owner identified network impacts to Sub-Regional facilities as follows:
| Overloaded Element | Contingency | Rating [MVA] | Final Cycle Loading % | Contribution [MW] |
|---|---|---|---|---|
| 246535 05MOORE PK 69.0 - 246553 05WHEELR S 69.0 CKT 1 | AEP_P4_#5620_05COREY 138_K_SRT-A CONTINGENCY 'AEP_P4_#5620_05COREY 138_K_SRT-A' OPEN BRANCH FROM BUS 243265 TO BUS 243299 CKT 1 /*05COREY 138.0 - 05HYDRAMATIC 138.0 OPEN BRANCH FROM BUS 243265 TO BUS 245259 CKT 1 /*05COREY 138.0 - 05EDLOWE 138.0 OPEN BRANCH FROM BUS 243322 TO BUS 245259 CKT 1 /*05KENZIE 138.0 - 05EDLOWE 138.0 END | 92.0 | 109.84 % | 3.04 |
System Reinforcement: n9107.0
- TO
- AEP
- RTEP ID / TO ID
- n9107.0 / AEP_TC1_89
- Category
- SubRegional
- Title
- Replace 69 kV riser at the Moore Park Station.
- Description
- Replace 477 KCM 69 kV riser at Moore Park. 246535 05MOORE PK 69.0 - 246553 05WHEELR S 69.0 CKT 1
- Total Cost
- $262,000
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF1-161 | 3.0 MW | 6.2% | $16,136 |
| AF2-396 | 43.3 MW | 87.7% | $229,728 |
| AG1-109 | 3.0 MW | 6.2% | $16,136 |
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AF1-161 was evaluated as a 25.0 MW (25.0 MW Capacity) injection in the AEP area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | AEP | 05SORENS-05MARYSV 765.0 kV Ckt 1 line | AEP_P4_#7334_05JEFRSO 765_A2_SRT-A | Breaker | AC | 102.72 % | 4142.0 | B | 4254.71 | 6.34 | |
| GD1 | ATSI/METC | 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-022T_SRT-A-1_SENS | Tower | AC | 111.53 % | 1793.0 | B | 1999.7 | 2.95 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | ATSI/METC | 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-022T_SRT-A-1 | Tower | AC | 111.69 % | 1793.0 | B | 2002.62 | 2.87 | |
| GD1 | ATSI/METC | 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-022T_SRT-A-2 | Tower | AC | 109.25 % | 1793.0 | B | 1958.92 | 2.87 | |
| GD1 | ATSI/ITCT | 19MON12-02LALLENDORF 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-025T_SRT-A-1 | Tower | AC | 114.15 % | 1660.0 | B | 1894.94 | 2.54 | |
| GD1 | ATSI/ITCT | J1062 POI-02LEMOYN 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-032T_SRT-A-1 | Tower | AC | 103.43 % | 852.0 | B | 881.21 | 1.69 |
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Light Load Analysis
The New Service Request AF1-161 was evaluated as a 25.0 MW injection and 50.0 MW withdrawal in the AEP area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests (projects) in PJM Transition Cycle 1, Cluster 55 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 55 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 55 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 55 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.
Cluster 55 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:
a) Steady-state operation (Category P0);
b) Three-phase faults with normal clearing time (Category P1);
c) Single-phase faults with stuck breaker (Category P4);
d) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).
e) Three-phase faults with normal clearing for common structure (Category P7).
Multiple-circuit tower line faults were identified for this study.
High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 55 projects.
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2027 peak load case:
a) Cluster 55 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 55 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AE2-325, AF1-161, AF1-176, AF2-396 and AG1-109 meet the 0.95 leading and lagging PF requirement.
Please note that AE2-325 meets its own requested MFO of the uprate portion. However, AE2-325 combined with AD2-020 does not meet the total requested MFO of 152.2 MW. There are about 1.5 MW deficiencies due to the prior queue project AD2-020.
AE1-170, AE2-325 and AF2-396 were tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.
No other mitigations were found to be required for TC1 Cluster 55.
Table 1: TC1 Cluster 55 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
55 | AE2-325 | Storage | American Electric Power (AEP) | 52.2 MW | 52.2 MW | 31.32 MW | Valley 138 kV substation |
AF1-161 | Storage | American Electric Power (AEP) | 50 MW | 50 MW | 25 MW | Valley 138 kV substation | |
AF1-176 | Solar + Storage | American Electric Power (AEP) | 300 MW | 300 MW | 155.684 MW | Corey 138 kV substation | |
AF2-396 | Solar + Storage | American Electric Power (AEP) | 200 MW | 200 MW | 200 MW | Stinger 138 kV substation |
Reactive Power Analysis
The reactive power capability of AF1-161 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-018 | Powerton-Goodings Grove | In Service |
| AA2-116 | Cook-East Elkhart 345kV | In Service |
| AB1-006 | Meadow Lake 345kV | In Service |
| AB1-080 | Dumont-Olive 345kV | In Service |
| AC2-154 | Davis Creek 138kV | Engineering & Procurement |
| AD1-100 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Under Construction |
| AD2-020 | Valley 138 kV | Engineering & Procurement |
| AD2-047 | Davis Creek 138 kV | Suspended |
| AD2-060 | Davis Creek 138kV | Engineering & Procurement |
| AD2-079 | Capitol Ave 34.5kV | In Service |
| AE1-146 | Ebersole #2-Fostoria Central 138 kV | Under Construction |
| AE1-166 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE1-170 | Kenzie Creek-Colby 138 kV | Suspended |
| AE2-045 | Olive-Reynolds 345 kV | Engineering & Procurement |
| AE2-062 | Romeoville 12 kV | In Service |
| AE2-152 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE2-181 | Snyder 69kV | In Service |
| AE2-236 | Columbia-Northeast 138 kV | Suspended |
| AE2-323 | Twin Branch-Guardian 138 kV | Partially in Service - Under Construction |
| AE2-341 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-030 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-064 | Weston 69 kV | Under Construction |
| AF1-084 | Hartford-Almena 69 kV | Under Construction |
| AF1-092 | Huntington Jct. 138 kV | Withdrawn |
| AF1-158 | Edison-Gravel Pit 138 kV | In Service |
| AF1-176 | Corey 138 kV | Engineering & Procurement |
| AF1-207 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF1-215 | Olive-Reynolds 345 kV | In Service |
| AF1-229 | Galion-South Berwick 345 kV | Under Construction |
| AF1-322 | Meadow Lake 345 kV | Engineering & Procurement |
| AF2-027 | Zion Energy Center 345 kV | Engineering & Procurement |
| AF2-031 | Calumet | Engineering & Procurement |
| AF2-078 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF2-083 | Kenzie Creek-Stone Lake 69 kV | Under Construction |
| AF2-095 | Davis Creek 138 kV | Engineering & Procurement |
| AF2-132 | Reynolds-Olive #1 345 kV | Under Construction |
| AF2-133 | Reynolds-Olive #2 345 kV | Under Construction |
| AF2-134 | Olive-Reynolds #2 345 kV | In Service |
| AF2-142 | Nevada 345 kV | Engineering & Procurement |
| AF2-205 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AF2-226 | Katydid Road 345 kV | Engineering & Procurement |
| AF2-319 | Katydid Road 345 kV | Engineering & Procurement |
| AF2-350 | Kensington 138 kV | Engineering & Procurement |
| AF2-359 | Olive-University Park 345 kV | Engineering & Procurement |
| AF2-375 | Ebersole-Fostoria 138 kV | Engineering & Procurement |
| AF2-396 | Stinger 138 kV | Engineering & Procurement |
| AF2-441 | Burnham 138kV | Engineering & Procurement |
| AG1-109 | Valley 138 kV | Engineering & Procurement |
| AG1-118 | Sugar Grove-Waterman 138kV | Engineering & Procurement |
| AG1-302 | Olive-Reynolds #1 345 kV | Under Construction |
| AG1-349 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AG1-436 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-447 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-478 | Wilmington 34.5 kV | Engineering & Procurement |
| AG1-513 | Aurora 138 kV | Suspended |
| X1-042 | Watervliet | In Service |
| X3-005 | Wildwood 12kV | In Service |
| Y3-023 | Country Side 12kV | In Service |
| Z1-108 | McHenry 34kV | In Service |
| Z2-116 | Twin Branch 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
| AF1-161 System Reinforcements: | TO | Trans Owner ID | Title | Category | Allocated Cost ($USD) | |||||
|---|---|---|---|---|---|---|---|---|---|---|
| METC | METC_TC1_16078 | Perform sag mitigation on Allen Junction - Morocco 345kV line | Informational | $0 | ||||||
| ITCT | ITCT_TC1_13866 | MTEP #25223/#25224 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027) | Informational | $0 | ||||||
| Grand Total: | $0 | |||||||||
System Reinforcement
- Type
- Load Flow
- TO
- METC
- RTEP ID / TO ID
- (Pending) / METC_TC1_16078
- Title
- Perform sag mitigation on Allen Junction - Morocco 345kV line
- Description
- Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1776/2040 MVA SN/SE. Upgrades is required along with ATSI-2025-005 (Supplemental) to increase the rating of the tie line between ATSI and MISO.
- Total Cost ($USD)
- $792,500
- Allocated Cost ($USD)
- $0
- Time Estimate
- 18 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF1-161 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF1-161 could receive cost allocation. Although AF1-161 may not presently have cost responsibility for this upgrade, AF1-161 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 02ALLEN-18MOROCCO 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- ITCT
- RTEP ID / TO ID
- (Pending) / ITCT_TC1_13866
- Title
- MTEP #25223/#25224 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027)
- Description
- Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station. This project is a DPP 2020 Network Upgrade associated with the J1516, J1525, J1526, J1527, J1550, J1553, J1557, J1571, J1586, J1587, J1603, J1614, J1635, J1658, J1659, J1663, and J1664 projects. Projected In-Service 6/1/2027
- Total Cost ($USD)
- $29,916,928
- Allocated Cost ($USD)
- $0
- Time Estimate
- TBD
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF1-161 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF1-161 could receive cost allocation. Although AF1-161 may not presently have cost responsibility for this upgrade, AF1-161 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 02ALLEN-18MOROCCO 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 02LALLENDORF-19MON12 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | ||||||||||
| 02LEMOYN-J1062 POI 345.0 kV Ckt 1 line | (Any) |
|
Affected System - Non-PJM Identified Violations
In coordination with other Affected System Operators, PJM has determined that the Affected System Operator for this project that requires an Affected System Study. For the latest Affected System Study results pertaining this project, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM lists any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.
System Reinforcements
No cost allocated system reinforcements were identified for this project in the Final System Impact Study load flow analysis.
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / ATSI-2025-005 (Supplemental)
- Title
- Lallendorf & Allen Jct Substation Upgrades (Projected ISD 6/1/2032) - s3845.1
- Description
- 1) At Lallendorf Substation: Substation: Replace line relaying. Install new seven-mile ADSS fiber line from Lallendorf Substation to Toledo Edison regional services territory boundary. 2) At Allen Junction Substation: replace disconnect switches, breaker leads, metering, and transmission line drops. Cost Est: $7.21 mil Allen Junction – Morocco 345 kV Line ratings: - Before Proposed Solution: 1517 / 1793 / 1759 / 1793 MVA (SN/SE/WN/WE) - After Proposed Solution: 1868 / 2249 / 2340 / 2535 MVA (SN/SE/WN/WE) Laplaissance Creek 345kV sub involves tapping the Lemoyne-Maple (J1062 POI) 345kV line & Lallendorf-Monroe 345kV line https://www.pjm.com/-/media/DotCom/committees-groups/committees/teac/2025/20251208/20251208-item-04---atsi-supplemental-projects.pdf
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- TBD
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF1-161 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF1-161 could receive cost allocation. Although AF1-161 may not presently have cost responsibility for this upgrade, AF1-161 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 02ALLEN-18MOROCCO 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n3985
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n3985 / AEPO0036a
- Title
- Upgrade three Marysville Wavetraps ( 3000A)
- Description
- Replace 3 Marysville 765 kV wave traps. Costs updated to $705,368 from Facility Study
- Total Cost ($USD)
- $900,000
- Discounted Total Cost ($USD)
- $900,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- Jul 16 2026
Not Contingent Note: AF1-161 contributes to the loading of an overloaded facility that is being mitigated by a network upgrade that was securitized by a prior Queue/Cycle. AF1-161 is not contingent on this network upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MARYSV-05SORENS 765.0 kV Ckt 1 line | (Any) |
|