AF1-176 Final System Impact Study (Retool 1) Report

v1.00 released 2025-12-08 18:16

Corey 138 kV

155.682 MW Capacity / 300.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Three Lakes Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed a Solar/Storage generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — St. Joseph County, Michigan. The installed facilities will have a total capability of 300.0 MW with 155.682 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF1-176
Project Name:
Corey 138 kV
Project Developer Name:
Three Lakes Solar LLC
State:
Michigan
County:
St. Joseph
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
300.0
MWE:
300.0
MWC:
155.682
Battery Storage Specification:
486.32 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Solar/Storage
Basecase Study Year:
2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF1-176 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system at the Corey 138 kV substation.

 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AF1-176 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AF1-176Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$1,095,657$1,095,657
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$1,996,401$1,996,401
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$838,835$838,835
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$372,089$0
AFS - Non-PJM Violations$1,496,302$0
Total$5,799,283$3,930,893

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF1-176

Security has been calculated for the AF1-176 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF1-176
Project(s): AF1-176
Final Agreement Security (A): $3,930,893
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $3,930,893
Security on Hand with PJM (D): $26,774,654
Additional Security Due at Agreement Execution (E): C D = $0
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

AF1-176 will interconnect with the AEP transmission system via a direct connection to the Corey 138 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9614.0

Corey 138 kV Station: Re-terminate Kenzie Creek - Corey 138 kV line. • Remove one (1) steel dead-end structure and associated conductor and shield wire along the Kenzie Creek – Corey 138 kV Circuit. • Install one (1) new 100’ steel, single-circuit, single-pole dead-end structure on a concrete foundation with an anchor bolt cage and two spans of aluminum conductor steel-reinforced 1033.5 (Curlew) transmission line conductor with 7#8 Alumoweld shield wire.

$372,152$129,068$66,941$23,216$591,377$591,377
n9613.0

Corey 138 kV Station: • Installation of one (1) new 3000A 40 kA 138 kV circuit breaker with associated control relaying. • Installation of one (1) three-phase 3000A circuit breaker disconnect switch. • Installation of one (1) three-phase coupling capacitor voltage transformer and associated structures for the line exit to the Hydramatic 138 kV Station. • Installation of one (1) H-frame dead-end structure for the line exit to the Hydramatic 138 kV Station. • Installation of associated and additional buswork, bus supports, jumpers, insulators, grounding, and foundations.

$471,817$278,029$34,084$20,085$804,015$804,015
n9612.0

Corey 1385 kV Station: Re-terminate the Hydramatic - Corey 138 kV circuit. • Remove two (2) steel tangent structures, one (1) steel dead-end structure, and associated conductor and shield wire along the existing Corey – Hydramatic 138 kV circuit. • Install one (1) new 90’ steel, single-circuit, single-pole, running corner direct embedded structure. • Install one (1) new 90’ steel, single-circuit, single-pole dead-end structure on a concrete foundation with an anchor bolt cage. • Install two (2) spans of aluminum conductor steel-reinforced 1033.5 (Curlew) transmission line conductor with 7#8 Alumoweld shield wire.

$312,808$149,666$93,702$44,833$601,009$601,009
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• Installation of a dual, direct fiber-based current differential relaying protection scheme for the generation lead circuit. • Extension of two (2) underground all dielectric loose tube fiber optic cables from the Corey 138 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the Corey 138 kV and Project Developer's collector stations. • Installation of a standard revenue metering package, including three (3) single-phase current transformers (CT), three (3) single-phase voltage transformers (VT), associated structures and foundations, one (1) ethernet switch, and one (1) drop-in control module (DICM)-installed metering panel, for the generation lead circuit at the Corey 138 kV station. • Review and revision of the protective relay settings for the remainder of the Corey 138 kV Station.

$632,240$310,507$103,733$49,177$1,095,657$1,095,657

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 25 to 26 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AF1-176 was evaluated as a 300.0 MW (155.68 MW Capacity) injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
05SORENS-05MARYSV 765.0 kV Ckt 1 line
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
BreakerAC102.72 %4142.0B4254.8576.12
GD1ATSI/METC
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
ATSI_P7-1_TE-345-022T_SRT-A-1_SENS
TowerAC111.87 %1793.0B2005.8634.33

Details for 05SORENS-05MARYSV 765.0 kV Ckt 1 line l/o AEP_P4_#7334_05JEFRSO 765_A2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05SORENS-05MARYSV 765.0 kV Ckt 1 line
Contingency Name:
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.72 %
Rating:4142.0 MVA
Rating Type:B
MVA to Mitigate:4254.85
MW Contribution:76.12
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP
Facility Description:
05SORENS-05MARYSV 765.0 kV Ckt 1 line
Contingency Name:
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:103.54 %
Rating:4142.0 MVA
Rating Type:B
MVA to Mitigate:4288.77
MW Contribution:76.31
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24335305OLIVE
50/50
0.2120.212
965681AG1-436 C
Adder
18.9305882352941216.091
965682AG1-436 E
Adder
12.62117647058823510.728
966091AG1-478 C
Adder
3.88000000000000033.298
966092AG1-478 E
Adder
0.97647058823529410.83
966441AG1-513 C
Adder
0.96823529411764710.823
966442AG1-513 E
Adder
1.45294117647058841.235
24642205MAYFLWER
50/50
0.2440.244
24643105BUCHANAN
50/50
0.0840.084
247643Z2-116 C
50/50
0.0550.055
24796605WTRV SLR E
Adder
0.57647058823529410.49
24796705OLIV SLR E
50/50
0.6480.648
247969Z2-116 E
50/50
0.3340.334
910542X3-005 E
Adder
1.39411764705882371.185
918052AA1-018 E OP
Adder
31.17294117647058726.497
934722AD1-100 E
Adder
172.2376470588235146.402
943001AE2-323 C
Adder
16.5152941176470614.038
943002AE2-323 E
Adder
8.097647058823536.883
943021AE2-325 C
50/50
7.9467.946
943022AE2-325 E
50/50
5.2975.297
944161AF1-084 C
Adder
13.66941176470588311.619
944162AF1-084 E
Adder
7.80823529411764656.637
944961AF1-161 C
50/50
6.3426.342
958481AF2-142 C
Adder
21.49882352941176618.274
958482AF2-142 E
Adder
14.3329411764705912.183
959351AF2-226 C
Adder
4.7847058823529424.067
959352AF2-226 E
Adder
7.17647058823529356.1
960281AF2-319 C
Adder
4.7847058823529424.067
960282AF2-319 E
Adder
7.17647058823529356.1
960681AF2-359 C
Adder
18.9305882352941216.091
960682AF2-359 E
Adder
12.62117647058823510.728
24307105BERRINSP G
50/50
0.1370.137
24344005CKG1
50/50
43.40443.404
24344105CKG2
50/50
55.8555.85
24441505OLIV SLR C
50/50
0.1060.106
270142AA2-116_CT1
50/50
15.92315.923
270143AA2-116_CT2
50/50
15.92315.923
270144AA2-116_ST
50/50
14.10214.102
274675JOLIET 29;7U
Adder
134.57764705882354114.391
274676JOLIET 29;8U
Adder
134.5764705882353114.39
274682WAUKEGAN ;7U
Adder
78.4505882352941366.683
274683WAUKEGAN ;8U
Adder
84.6588235294117671.96
274687WILL CNTY;4U
Adder
124.97176470588235106.226
274771LINCOLN ;2U
50/50
3.1893.189
274772LINCOLN ;3U
50/50
3.1893.189
274773LINCOLN ;4U
50/50
3.1893.189
274776LINCOLN ;7U
50/50
3.1893.189
274777LINCOLN ;8U
50/50
3.1893.189
274788SE CHICAG;5U
Adder
9.2541176470588237.866
274789SE CHICAG;6U
Adder
9.2541176470588237.866
274790SE CHICAG;7U
Adder
9.2541176470588237.866
274791SE CHICAG;8U
Adder
9.2541176470588237.866
274792SE CHICAG;9U
Adder
9.2541176470588237.866
274793SE CHICAG;0U
Adder
9.2541176470588237.866
274794SE CHICAG;1U
Adder
9.2541176470588237.866
274795SE CHICAG;2U
Adder
9.2541176470588237.866
276591L-013 2
Adder
6.9894117647058825.941
293061N-015 E
Adder
29.2470588235294124.86
293644O22 E1
Adder
27.48823529411764723.365
293645O22 E2
Adder
31.48352941176470726.761
294392P-010 E
Adder
37.143529411764731.572
933411AC2-154 C
Adder
4.6870588235294123.984
933412AC2-154 E
Adder
7.6482352941176476.501
274674JOLIET 9 ;6U
Adder
68.6729411764705958.372
934101AD2-000 1
Adder
11.2117647058823529.53
934111AD2-000 2
Adder
11.2741176470588259.583
24335205NTRDAM
50/50
2.4332.433
24641605TWIN BRNCH
50/50
0.0710.071
24647605NILES
50/50
0.0550.055
24647705NILES
50/50
0.0550.055
270100AB1-080 CT1
50/50
9.9719.971
270101AB1-080 CT2
50/50
9.9719.971
270102AB1-080 ST
50/50
10.78910.789
270216AD2-079_C O1
50/50
0.5020.502
275149KELLYCK ;1E
Adder
34.53882352941176529.358
293519PILOT HIL;1E
Adder
34.53882352941176529.358
936632AD2-079 E O1
50/50
2.0472.047
936141AD2-020 C
50/50
15.70315.703
936371AD2-047 C
Adder
8.3882352941176477.13
936372AD2-047 E
Adder
40.95294117647059634.81
936461AD2-060 C
Adder
4.9341176470588244.194
942241AE2-236 C
Adder
9.7541176470588238.291
942242AE2-236 E
Adder
4.183.553
943121AE2-341 C
Adder
24.38470588235294320.727
943122AE2-341 E
Adder
11.97411764705882410.178
943591AF1-030 C
Adder
16.21647058823529613.784
943592AF1-030 E
Adder
8.0235294117647066.82
944241AF1-092 C
Adder
28.98705882352941324.639
944242AF1-092 E
Adder
8.822352941176477.499
944931AF1-158 C
50/50
3.7133.713
944932AF1-158 E
50/50
15.54815.548
945111AF1-176 C
50/50
39.50439.504
945112AF1-176 E
50/50
36.6236.62
945421AF1-207 C
Adder
8.1811764705882366.954
945422AF1-207 E
Adder
35.13176470588235429.862
945502AF1-215 E
Adder
30.13647058823529425.616
959141AF2-205 C
Adder
29.48588235294117525.063
959142AF2-205 E
Adder
19.65764705882352816.709
960591AF2-350 C
Adder
14.80235294117647312.582
960592AF2-350 E
Adder
9.8682352941176488.388
961051AF2-396 C
50/50
50.74150.741
961501AF2-441 C
Adder
19.95058823529411616.958
961502AF2-441 E
Adder
29.9258823529411825.437
939351AE1-166 C
Adder
19.19176470588235316.313
939352AE1-166 E
Adder
17.7152941176470615.058
939391AE1-170 C
50/50
16.1416.14
939392AE1-170 E
50/50
22.28822.288
939402AE1-172 E
Adder
25.43999999999999821.624
940581AE2-045 C
Adder
20.59882352941176717.509
940582AE2-045 E
Adder
28.28352941176470724.041
962601AG1-109 C
50/50
6.3426.342
964401AG1-302 C
Adder
44.7047058823529537.999
964402AG1-302 E
Adder
29.80235294117647325.332
936142AD2-020 E
50/50
9.6669.666
941551AE2-152 C
Adder
22.1447058823529418.823
941552AE2-152 E
Adder
14.76352941176470612.549
957371AF2-031 C
Adder
2.01.7
957372AF2-031 E
Adder
3.02.55
957841AF2-078 C
Adder
28.8752941176470624.544
957842AF2-078 E
Adder
19.25058823529411716.363
957891AF2-083 C
50/50
25.55625.556
957892AF2-083 E
50/50
12.77812.778
958011AF2-095 C
Adder
21.31529411764705618.118
958012AF2-095 E
Adder
14.21058823529411812.079
958381AF2-132 C
Adder
44.7047058823529537.999
958382AF2-132 E
Adder
29.80235294117647325.332
958391AF2-133 C
Adder
44.3929411764705937.734
958392AF2-133 E
Adder
29.59529411764705725.156
958402AF2-134 E
Adder
10.0458823529411768.539
964861AG1-349 C
Adder
38.6632.861
964862AG1-349 E
Adder
25.7729411764705921.907
965791AG1-447 C
Adder
13.88235294117647111.8
274770LINCOLN ;1U
50/50
3.1893.189
276675AE2-062 E
Adder
0.287058823529411760.244
CBM West 1LTFEXP_CBM-W1->PJM
CBM
319.618319.618
CBM West 2LTFEXP_CBM-W2->PJM
CBM
75.36775.367
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
6.9886.988
NYPJM->LTFIMP_NY
CLTF
3.633.63
LGEELTFEXP_LGEE->PJM
CLTF
3.8433.843
WECLTFEXP_WEC->PJM
CLTF
7.6087.608
HAMLETPJM->LTFIMP_HAMLET
CLTF
1.531.53
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.7280.728
TVALTFEXP_TVA->PJM
CLTF
8.198.19
MECLTFEXP_MEC->PJM
CLTF
30.0930.09
LAGNLTFEXP_LAGN->PJM
CLTF
13.77113.771
SIGELTFEXP_SIGE->PJM
CLTF
1.2341.234
O66PJM->LTFIMP_O-066
CMTX_NF
44.79244.792
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
2.3872.387

Details for 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-022T_SRT-A-1_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:ATSI/METC
Facility Description:
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
Contingency Name:
ATSI_P7-1_TE-345-022T_SRT-A-1_SENS
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:111.87 %
Rating:1793.0 MVA
Rating Type:B
MVA to Mitigate:2005.86
MW Contribution:34.33
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24335305OLIVE
50/50
0.0820.082
965681AG1-436 C
Adder
6.5623529411764715.578
965682AG1-436 E
Adder
4.3752941176470593.719
24639705ELKHART HY
50/50
0.0320.032
24642205MAYFLWER
50/50
0.1020.102
24643105BUCHANAN
50/50
0.0350.035
24752805COVRT1
50/50
5.4595.459
24752905COVRT2
50/50
5.4595.459
24753005COVRT3
50/50
5.4595.459
24753105COVRT4
50/50
3.2833.283
24753205COVRT5
50/50
3.2593.259
24753305COVRT6
50/50
2.6732.673
247620Y3-023
50/50
0.0770.077
247643Z2-116 C
50/50
0.0220.022
24796605WTRV SLR E
50/50
0.290.29
24796705OLIV SLR E
50/50
0.2510.251
247969Z2-116 E
50/50
0.1370.137
943001AE2-323 C
Adder
5.824.947
943002AE2-323 E
Adder
2.8541176470588242.426
943021AE2-325 C
50/50
3.6953.695
943022AE2-325 E
50/50
2.4632.463
944161AF1-084 C
50/50
6.5136.513
944162AF1-084 E
50/50
3.723.72
944961AF1-161 C
50/50
2.952.95
945641AF1-229 C
Adder
-8.618823529411765-7.326
960681AF2-359 C
Adder
6.5623529411764715.578
960682AF2-359 E
Adder
4.3752941176470593.719
960841AF2-375 C
Adder
-9.301176470588235-7.906
24307105BERRINSP G
50/50
0.0630.063
24344005CKG1
50/50
18.67318.673
24441205WTRV SLR C
50/50
0.0470.047
24441505OLIV SLR C
50/50
0.0410.041
270142AA2-116_CT1
50/50
6.8386.838
270143AA2-116_CT2
50/50
6.8386.838
270144AA2-116_ST
50/50
6.0566.056
274788SE CHICAG;5U
Adder
3.09058823529411742.627
274789SE CHICAG;6U
Adder
3.09058823529411742.627
274790SE CHICAG;7U
Adder
3.09058823529411742.627
274791SE CHICAG;8U
Adder
3.09058823529411742.627
274792SE CHICAG;9U
Adder
3.09411764705882362.63
274793SE CHICAG;0U
Adder
3.09411764705882362.63
274794SE CHICAG;1U
Adder
3.09411764705882362.63
274795SE CHICAG;2U
Adder
3.09411764705882362.63
941781AE2-181 C
Adder
-7.374117647058823-6.268
24335205NTRDAM
50/50
0.9730.973
24641605TWIN BRNCH
50/50
0.0290.029
24647605NILES
50/50
0.0230.023
24647705NILES
50/50
0.0230.023
24653605MOTTVILLE
50/50
0.0090.009
247604X1-042
50/50
0.0810.081
270216AD2-079_C O1
50/50
0.2080.208
936632AD2-079 E O1
50/50
0.8480.848
936141AD2-020 C
50/50
7.3037.303
944931AF1-158 C
50/50
1.451.45
944932AF1-158 E
50/50
6.0726.072
945111AF1-176 C
50/50
17.81417.814
945112AF1-176 E
50/50
16.51416.514
945502AF1-215 E
Adder
10.5917647058823539.003
959141AF2-205 C
Adder
10.1647058823529428.64
959142AF2-205 E
Adder
6.7764705882352945.76
961051AF2-396 C
50/50
23.33323.333
939391AE1-170 C
50/50
7.1597.159
939392AE1-170 E
50/50
9.8869.886
940581AE2-045 C
Adder
7.0670588235294116.007
940582AE2-045 E
Adder
9.7035294117647068.248
962601AG1-109 C
50/50
2.952.95
964401AG1-302 C
Adder
15.55882352941176413.225
964402AG1-302 E
Adder
10.3729411764705888.817
936142AD2-020 E
50/50
4.4954.495
957371AF2-031 C
Adder
0.66705882352941170.567
957372AF2-031 E
Adder
1.00117647058823530.851
957891AF2-083 C
50/50
11.29411.294
957892AF2-083 E
50/50
5.6475.647
958381AF2-132 C
Adder
15.55882352941176413.225
958382AF2-132 E
Adder
10.3729411764705888.817
958391AF2-133 C
Adder
15.35529411764705913.052
958392AF2-133 E
Adder
10.2364705882352968.701
958402AF2-134 E
Adder
3.5305882352941183.001
964861AG1-349 C
Adder
13.4294117647058811.415
964862AG1-349 E
Adder
8.9529411764705887.61
965791AG1-447 C
Adder
4.8117647058823534.09
939161AE1-146 C
Adder
-9.078823529411764-7.717
943961AF1-064 C
Adder
-7.631764705882353-6.487
991182J1586 G
External Queue
63.33609008789062563.336090087890625
990527J1329 G
External Queue
5.52491998672485355.5249199867248535
955182J996 G
External Queue
27.58028030395507827.580280303955078
990142J1224 G
External Queue
46.72817993164062546.728179931640625
990152J1226
External Queue
85.5240020751953185.52400207519531
991177J1571 G
External Queue
66.2298431396484466.22984313964844
991227J1663 G
External Queue
17.13986778259277317.139867782592773
955782J1062 G
External Queue
59.26379013061523459.263790130615234
CBM West 1LTFEXP_CBM-W1->PJM
CBM
233.141233.141
CBM West 2LTFEXP_CBM-W2->PJM
CBM
27.95127.951
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
9.2539.253
G-007PJM->LTFIMP_G-007
CMTX_NF
2.2922.292
NYPJM->LTFIMP_NY
CLTF
1.4091.409
LGEELTFEXP_LGEE->PJM
CLTF
1.9271.927
WECLTFEXP_WEC->PJM
CLTF
2.4822.482
CPLELTFEXP_CPLE->PJM
CLTF
0.4250.425
TVALTFEXP_TVA->PJM
CLTF
4.1424.142
MECLTFEXP_MEC->PJM
CLTF
10.07210.072
LAGNLTFEXP_LAGN->PJM
CLTF
6.0326.032
SIGELTFEXP_SIGE->PJM
CLTF
0.4440.444
O66PJM->LTFIMP_O-066
CMTX_NF
14.78614.786
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.2120.212
CONTINGENCY 'AEP_P4_#7334_05JEFRSO 765_A2_SRT-A'
 OPEN BRANCH FROM BUS 242865 TO BUS 243208 CKT 2    /*05JEFRSO     345.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 242865 TO BUS 248000 CKT Z1   /*05JEFRSO     345.0 - 06CLIFTY     345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1    /*05HANG R     765.0 - 05JEFRSO     765.0
END
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-1_SENS'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 264594 CKT 1   /*02LEMOYN     345.0 - 19LULU       345.0
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
END
246999 to 242928 ckt 1
256583 to 238530 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1ATSI/METC
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
ATSI_P7-1_TE-345-022T_SRT-A-1
TowerAC111.24 %1793.0B1994.5133.36
GD1ATSI/METC
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
ATSI_P7-1_TE-345-022T_SRT-A-2
TowerAC108.8 %1793.0B1950.8133.36

Details for 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-022T_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:ATSI/METC
Facility Description:
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
Contingency Name:
ATSI_P7-1_TE-345-022T_SRT-A-1
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:111.24 %
Rating:1793.0 MVA
Rating Type:B
MVA to Mitigate:1994.51
MW Contribution:33.36
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
965681AG1-436 C
Adder
6.8894117647058835.856
965682AG1-436 E
Adder
4.5929411764705883.904
24639705ELKHART HY
50/50
0.0310.031
24642205MAYFLWER
50/50
0.0990.099
24643105BUCHANAN
50/50
0.0340.034
24752805COVRT1
50/50
5.2795.279
24752905COVRT2
50/50
5.2795.279
24753005COVRT3
50/50
5.2795.279
24753105COVRT4
50/50
3.1753.175
24753205COVRT5
50/50
3.1513.151
24753305COVRT6
50/50
2.5822.582
247620Y3-023
50/50
0.0740.074
247643Z2-116 C
50/50
0.0220.022
24796605WTRV SLR E
50/50
0.2820.282
24796705OLIV SLR E
Adder
0.243529411764705880.207
247969Z2-116 E
50/50
0.1330.133
943001AE2-323 C
Adder
5.6729411764705884.822
943002AE2-323 E
Adder
2.78117647058823542.364
943021AE2-325 C
50/50
3.5913.591
943022AE2-325 E
50/50
2.3942.394
944161AF1-084 C
50/50
6.3286.328
944162AF1-084 E
50/50
3.6143.614
944961AF1-161 C
50/50
2.8662.866
945641AF1-229 C
Adder
-8.249411764705883-7.012
960681AF2-359 C
Adder
6.8894117647058835.856
960682AF2-359 E
Adder
4.5929411764705883.904
960841AF2-375 C
Adder
-8.9-7.565
24307105BERRINSP G
50/50
0.0610.061
24344005CKG1
50/50
18.08718.087
24441205WTRV SLR C
50/50
0.0460.046
270142AA2-116_CT1
50/50
6.6246.624
270143AA2-116_CT2
50/50
6.6246.624
270144AA2-116_ST
50/50
5.8665.866
274788SE CHICAG;5U
Adder
3.01764705882352932.565
274789SE CHICAG;6U
Adder
3.01764705882352932.565
274790SE CHICAG;7U
Adder
3.01764705882352932.565
274791SE CHICAG;8U
Adder
3.01764705882352932.565
274792SE CHICAG;9U
Adder
3.02235294117647072.569
274793SE CHICAG;0U
Adder
3.02235294117647072.569
274794SE CHICAG;1U
Adder
3.02235294117647072.569
274795SE CHICAG;2U
Adder
3.02235294117647072.569
941781AE2-181 C
Adder
-7.069411764705883-6.009
24335205NTRDAM
50/50
0.9430.943
24641605TWIN BRNCH
50/50
0.0280.028
24647605NILES
50/50
0.0220.022
24647705NILES
50/50
0.0220.022
24653605MOTTVILLE
50/50
0.0090.009
247604X1-042
50/50
0.0780.078
270216AD2-079_C O1
50/50
0.2010.201
936632AD2-079 E O1
50/50
0.8250.825
936141AD2-020 C
50/50
7.0977.097
944932AF1-158 E
Adder
5.9082352941176485.022
945111AF1-176 C
50/50
17.31417.314
945112AF1-176 E
50/50
16.0516.05
945502AF1-215 E
Adder
10.3188235294117668.771
959141AF2-205 C
Adder
9.912941176470598.426
959142AF2-205 E
Adder
6.6082352941176475.617
961051AF2-396 C
50/50
22.67522.675
939391AE1-170 C
50/50
6.9596.959
939392AE1-170 E
50/50
9.6099.609
940581AE2-045 C
Adder
6.8929411764705895.859
940582AE2-045 E
Adder
9.4647058823529418.045
962601AG1-109 C
50/50
2.8662.866
964401AG1-302 C
Adder
15.16588235294117712.891
964402AG1-302 E
Adder
10.1105882352941178.594
936142AD2-020 E
50/50
4.3684.368
957371AF2-031 C
Adder
0.6517647058823530.554
957372AF2-031 E
Adder
0.97764705882352940.831
957891AF2-083 C
50/50
10.97810.978
957892AF2-083 E
50/50
5.4895.489
958381AF2-132 C
Adder
15.16588235294117712.891
958382AF2-132 E
Adder
10.1105882352941178.594
958391AF2-133 C
Adder
14.97058823529411812.725
958392AF2-133 E
Adder
9.9811764705882358.484
958402AF2-134 E
Adder
3.442.924
964861AG1-349 C
Adder
13.09058823529411911.127
964862AG1-349 E
Adder
8.7270588235294117.418
965791AG1-447 C
Adder
5.0517647058823534.294
939161AE1-146 C
Adder
-8.681176470588236-7.379
943961AF1-064 C
Adder
-7.32-6.222
991182J1586 G
External Queue
60.0508537292480560.05085372924805
990527J1329 G
External Queue
5.49665594100952155.4966559410095215
955182J996 G
External Queue
28.6180343627929728.61803436279297
990142J1224 G
External Queue
46.4891281127929746.48912811279297
990152J1226
External Queue
89.7095184326171989.70951843261719
991177J1571 G
External Queue
68.5579071044921968.55790710449219
991227J1663 G
External Queue
16.31785583496093816.317855834960938
955782J1062 G
External Queue
43.4495162963867243.44951629638672
CBM West 1LTFEXP_CBM-W1->PJM
CBM
229.18229.18
CBM West 2LTFEXP_CBM-W2->PJM
CBM
27.68127.681
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
10.13610.136
G-007PJM->LTFIMP_G-007
CMTX_NF
2.3062.306
NYPJM->LTFIMP_NY
CLTF
1.41.4
LGEELTFEXP_LGEE->PJM
CLTF
1.9231.923
WECLTFEXP_WEC->PJM
CLTF
2.4232.423
CPLELTFEXP_CPLE->PJM
CLTF
0.4980.498
TVALTFEXP_TVA->PJM
CLTF
4.1694.169
MECLTFEXP_MEC->PJM
CLTF
9.8669.866
LAGNLTFEXP_LAGN->PJM
CLTF
6.0236.023
SIGELTFEXP_SIGE->PJM
CLTF
0.440.44
O66PJM->LTFIMP_O-066
CMTX_NF
14.86514.865
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.2470.247

Details for 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-022T_SRT-A-2


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:ATSI/METC
Facility Description:
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
Contingency Name:
ATSI_P7-1_TE-345-022T_SRT-A-2
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:108.8 %
Rating:1793.0 MVA
Rating Type:B
MVA to Mitigate:1950.81
MW Contribution:33.36
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
965681AG1-436 C
Adder
6.8894117647058835.856
965682AG1-436 E
Adder
4.5929411764705883.904
24639705ELKHART HY
50/50
0.0310.031
24642205MAYFLWER
50/50
0.0990.099
24643105BUCHANAN
50/50
0.0340.034
24752805COVRT1
50/50
5.2795.279
24752905COVRT2
50/50
5.2795.279
24753005COVRT3
50/50
5.2795.279
24753105COVRT4
50/50
3.1753.175
24753205COVRT5
50/50
3.1513.151
24753305COVRT6
50/50
2.5822.582
247620Y3-023
50/50
0.0740.074
247643Z2-116 C
50/50
0.0220.022
24796605WTRV SLR E
50/50
0.2820.282
24796705OLIV SLR E
Adder
0.243529411764705880.207
247969Z2-116 E
50/50
0.1330.133
943001AE2-323 C
Adder
5.6729411764705884.822
943002AE2-323 E
Adder
2.78117647058823542.364
943021AE2-325 C
50/50
3.5913.591
943022AE2-325 E
50/50
2.3942.394
944161AF1-084 C
50/50
6.3286.328
944162AF1-084 E
50/50
3.6143.614
944961AF1-161 C
50/50
2.8662.866
945641AF1-229 C
Adder
-8.249411764705883-7.012
960681AF2-359 C
Adder
6.8894117647058835.856
960682AF2-359 E
Adder
4.5929411764705883.904
960841AF2-375 C
Adder
-8.9-7.565
24307105BERRINSP G
50/50
0.0610.061
24344005CKG1
50/50
18.08718.087
24441205WTRV SLR C
50/50
0.0460.046
270142AA2-116_CT1
50/50
6.6246.624
270143AA2-116_CT2
50/50
6.6246.624
270144AA2-116_ST
50/50
5.8665.866
274788SE CHICAG;5U
Adder
3.01764705882352932.565
274789SE CHICAG;6U
Adder
3.01764705882352932.565
274790SE CHICAG;7U
Adder
3.01764705882352932.565
274791SE CHICAG;8U
Adder
3.01764705882352932.565
274792SE CHICAG;9U
Adder
3.02235294117647072.569
274793SE CHICAG;0U
Adder
3.02235294117647072.569
274794SE CHICAG;1U
Adder
3.02235294117647072.569
274795SE CHICAG;2U
Adder
3.02235294117647072.569
941781AE2-181 C
Adder
-7.069411764705883-6.009
24335205NTRDAM
50/50
0.9430.943
24641605TWIN BRNCH
50/50
0.0280.028
24647605NILES
50/50
0.0220.022
24647705NILES
50/50
0.0220.022
24653605MOTTVILLE
50/50
0.0090.009
247604X1-042
50/50
0.0780.078
270216AD2-079_C O1
50/50
0.2010.201
936632AD2-079 E O1
50/50
0.8250.825
936141AD2-020 C
50/50
7.0977.097
944932AF1-158 E
Adder
5.9082352941176485.022
945111AF1-176 C
50/50
17.31417.314
945112AF1-176 E
50/50
16.0516.05
945502AF1-215 E
Adder
10.3188235294117668.771
959141AF2-205 C
Adder
9.912941176470598.426
959142AF2-205 E
Adder
6.6082352941176475.617
961051AF2-396 C
50/50
22.67522.675
939391AE1-170 C
50/50
6.9596.959
939392AE1-170 E
50/50
9.6099.609
940581AE2-045 C
Adder
6.8929411764705895.859
940582AE2-045 E
Adder
9.4647058823529418.045
962601AG1-109 C
50/50
2.8662.866
964401AG1-302 C
Adder
15.16588235294117712.891
964402AG1-302 E
Adder
10.1105882352941178.594
936142AD2-020 E
50/50
4.3684.368
957371AF2-031 C
Adder
0.6517647058823530.554
957372AF2-031 E
Adder
0.97764705882352940.831
957891AF2-083 C
50/50
10.97810.978
957892AF2-083 E
50/50
5.4895.489
958381AF2-132 C
Adder
15.16588235294117712.891
958382AF2-132 E
Adder
10.1105882352941178.594
958391AF2-133 C
Adder
14.97058823529411812.725
958392AF2-133 E
Adder
9.9811764705882358.484
958402AF2-134 E
Adder
3.442.924
964861AG1-349 C
Adder
13.09058823529411911.127
964862AG1-349 E
Adder
8.7270588235294117.418
965791AG1-447 C
Adder
5.0517647058823534.294
939161AE1-146 C
Adder
-8.681176470588236-7.379
943961AF1-064 C
Adder
-7.32-6.222
991182J1586 G
External Queue
60.0508537292480560.05085372924805
990527J1329 G
External Queue
5.49665594100952155.4966559410095215
955182J996 G
External Queue
28.6180343627929728.61803436279297
990142J1224 G
External Queue
46.4891281127929746.48912811279297
990152J1226
External Queue
89.7095184326171989.70951843261719
991177J1571 G
External Queue
68.5579071044921968.55790710449219
991227J1663 G
External Queue
16.31785583496093816.317855834960938
CBM West 1LTFEXP_CBM-W1->PJM
CBM
229.18229.18
CBM West 2LTFEXP_CBM-W2->PJM
CBM
27.68127.681
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
10.13610.136
G-007PJM->LTFIMP_G-007
CMTX_NF
2.3062.306
NYPJM->LTFIMP_NY
CLTF
1.41.4
LGEELTFEXP_LGEE->PJM
CLTF
1.9231.923
WECLTFEXP_WEC->PJM
CLTF
2.4232.423
CPLELTFEXP_CPLE->PJM
CLTF
0.4980.498
TVALTFEXP_TVA->PJM
CLTF
4.1694.169
MECLTFEXP_MEC->PJM
CLTF
9.8669.866
LAGNLTFEXP_LAGN->PJM
CLTF
6.0236.023
SIGELTFEXP_SIGE->PJM
CLTF
0.440.44
O66PJM->LTFIMP_O-066
CMTX_NF
14.86514.865
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.2470.247
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-1'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 955780 CKT 1   /*02LEMOYN     345.0 - J1062 POI    345.0
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
END
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-2'
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
 DISCONNECT BRANCH FROM BUS 264599 TO BUS 955780 CKT 1   /*19MAJTC      345.0 - J1062 POI    345.0
END
256583 to 238530 ckt 1

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line
Base Case
OPAC100.54 %296.0A297.5836.16

Details for AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:100.54 %
Rating:296.0 MVA
Rating Type:A
MVA to Mitigate:297.58
MW Contribution:36.16
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:100.41 %
Rating:296.0 MVA
Rating Type:A
MVA to Mitigate:297.22
MW Contribution:36.16
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24796605WTRV SLR E
50/50
0.4360.436
943021AE2-325 C
50/50
14.48814.488
943022AE2-325 E
50/50
9.6599.659
944161AF1-084 C
50/50
18.44618.446
944162AF1-084 E
50/50
10.53610.536
944961AF1-161 C
50/50
11.56511.565
24441205WTRV SLR C
50/50
0.0710.071
936141AD2-020 C
50/50
28.63428.634
945111AF1-176 C
50/50
18.76818.768
945112AF1-176 E
50/50
17.39817.398
961051AF2-396 C
50/50
66.6766.67
939391AE1-170 C
50/50
59.29259.292
939392AE1-170 E
50/50
81.8881.88
962601AG1-109 C
50/50
11.56511.565
936142AD2-020 E
50/50
17.62417.624
CBM NorthLTFEXP_CBM-N->PJM
CBM
0.0160.016
CBM West 1LTFEXP_CBM-W1->PJM
CBM
0.8730.873
G-007ALTFEXP_G-007A->PJM
CMTX
0.0240.024
VTFLTFEXP_VFT->PJM
CMTX
0.0660.066
COTTONWOODPJM->LTFIMP_COTTONWOOD
CLTF
0.0430.043
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.0030.003
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.0020.002
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
0.0740.074
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.010.01
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.0310.031
MDUPJM->LTFIMP_MDU
CLTF
0.0040.004
LTFEXP_AC1-056LTFEXP_AC1-056->LTFIMP_AC1-056
CLTF
0.0320.032
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.0030.003
939390 to 243322 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AF1-176 was evaluated as a 121.5 MW injection and 121.58 MW withdrawal in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 55 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 55 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 55 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 55 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.

 

Cluster 55 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)       Steady-state operation (Category P0);

b)       Three-phase faults with normal clearing time (Category P1);

c)       Single-phase faults with stuck breaker (Category P4);

d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e)       Three-phase faults with normal clearing for common structure (Category P7).

 

Multiple-circuit tower line faults were identified for this study.

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 55 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 55 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 55 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-325, AF1-161, AF1-176, AF2-396 and AG1-109 meet the 0.95 leading and lagging PF requirement.

 

Please note that AE2-325 meets its own requested MFO of the uprate portion. However, AE2-325 combined with AD2-020 does not meet the total requested MFO of 152.2 MW. There are about 1.5 MW deficiencies due to the prior queue project AD2-020.

 

AE1-170, AE2-325 and AF2-396 were tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

 

No other mitigations were found to be required for TC1 Cluster 55.

 

Table 1: TC1 Cluster 55 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

55

AE2-325

Storage

American Electric Power (AEP)

52.2 MW

52.2

MW

31.32

MW

Valley 138 kV substation

AF1-161

Storage

American Electric Power (AEP)

50

MW

50 MW

25 MW

Valley 138 kV

substation

AF1-176

Solar + Storage

American Electric Power (AEP)

300

MW

300 MW

155.684

MW

Corey 138 kV

substation

AF2-396

Solar + Storage

American Electric Power (AEP)

200

MW

200 MW

200 MW

Stinger 138 kV

substation

 

 

Reactive Power Analysis

The reactive power capability of AF1-176 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis complete, no voltage issues found.

 

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AA1-018Powerton-Goodings GroveIn Service
AA2-116Cook-East Elkhart 345kVIn Service
AB1-006Meadow Lake 345kVIn Service
AB1-080Dumont-Olive 345kVIn Service
AC2-154Davis Creek 138kVEngineering & Procurement
AD1-100Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVUnder Construction
AD2-020Valley 138 kVEngineering & Procurement
AD2-047Davis Creek 138 kVSuspended
AD2-060Davis Creek 138kVEngineering & Procurement
AD2-079Capitol Ave 34.5kVIn Service
AE1-146Ebersole #2-Fostoria Central 138 kVUnder Construction
AE1-166Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE1-170Kenzie Creek-Colby 138 kVSuspended
AE1-172Loretto-Wilton CenterActive
AE2-045Olive-Reynolds 345 kVEngineering & Procurement
AE2-062Romeoville 12 kVIn Service
AE2-152Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE2-181Snyder 69kVPartially in Service - Under Construction
AE2-236Columbia-Northeast 138 kVSuspended
AE2-323Twin Branch-Guardian 138 kVPartially in Service - Under Construction
AE2-325Valley 138 kVActive
AE2-341Sandwich-Plano 138 kVActive
AF1-030Sandwich-Plano 138 kVActive
AF1-064Weston 69 kVUnder Construction
AF1-084Hartford-Almena 69 kVEngineering & Procurement
AF1-092Huntington Jct. 138 kVSuspended
AF1-158Edison-Gravel Pit 138 kVIn Service
AF1-161Valley 138 kVActive
AF1-207Reynolds-Olive #1 345 kVEngineering & Procurement
AF1-215Olive-Reynolds 345 kVIn Service
AF1-229Galion-South Berwick 345 kVEngineering & Procurement
AF1-322Meadow Lake 345 kVEngineering & Procurement
AF2-031CalumetEngineering & Procurement
AF2-078Reynolds-Olive #1 345 kVEngineering & Procurement
AF2-083Kenzie Creek-Stone Lake 69 kVUnder Construction
AF2-095Davis Creek 138 kVActive
AF2-132Reynolds-Olive #1 345 kVUnder Construction
AF2-133Reynolds-Olive #2 345 kVUnder Construction
AF2-134Olive-Reynolds #2 345 kVIn Service
AF2-142Nevada 345 kVActive
AF2-205Olive-Reynolds #2 345 kVEngineering & Procurement
AF2-226Katydid Road 345 kVActive
AF2-319Katydid Road 345 kVActive
AF2-350Kensington 138 kVActive
AF2-359Olive-University Park 345 kVEngineering & Procurement
AF2-375Ebersole-Fostoria 138 kVEngineering & Procurement
AF2-396Stinger 138 kVActive
AF2-441Burnham 138kVActive
AG1-109Valley 138 kVActive
AG1-302Olive-Reynolds #1 345 kVUnder Construction
AG1-349Olive-Reynolds #2 345 kVEngineering & Procurement
AG1-436Olive-University Park 345 kVActive
AG1-447Olive-University Park 345 kVActive
AG1-478Wilmington 34.5 kVEngineering & Procurement
AG1-513Aurora 138 kVSuspended
X1-042WatervlietIn Service
X3-005Wildwood 12kVIn Service
Y3-023Country Side 12kVIn Service
Z2-116Twin Branch 12.47kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts
AF1-176 System Reinforcements:
TOTrans Owner IDTitleCategoryAllocated Cost ($USD)
METCMETC_TC1_16078Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1861/2124 MVA.Cost Allocated$372,089
ITCTITCT_TC1_13866MTEP24#25223 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027)Contingent$0
Grand Total:$372,089

System Reinforcement
Type
Load Flow
TO
METC
RTEP ID / TO ID
(Pending) / METC_TC1_16078
Title
Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1861/2124 MVA.
Description
Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1861/2124 MVA.
Total Cost ($USD)
$625,000
Allocated Cost ($USD)
$372,089
Time Estimate
18 Months

Contributor

FacilityContingency
02ALLEN-18MOROCCO 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)B2124.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AF1-17634.3 MW59.5%$372,089
AF2-39623.3 MW40.5%$252,911

System Reinforcement
Type
Load Flow
TO
ITCT
RTEP ID / TO ID
(Pending) / ITCT_TC1_13866
Title
MTEP24#25223 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027)
Description
Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station. This project is a DPP 2020 Network Upgrade associated with the J1516, J1525, J1526, J1527, J1550, J1553, J1557, J1571, J1586, J1587, J1603, J1614, J1635, J1658, J1659, J1663, and J1664 projects. Projected In-Service 6/1/2027
Total Cost ($USD)
$29,916,928
Allocated Cost ($USD)
$0
Time Estimate
TBD

Contingent

Note: Based on PJM cost allocation criteria, AF1-176 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF1-176 could receive cost allocation. Although AF1-176 may not presently have cost responsibility for this upgrade, AF1-176 may need this upgrade in-service to be deliverable to the PJM system. If AF1-176 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
02ALLEN-18MOROCCO 345.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: Please communicate with the Affected System Operator regarding the status of the Affected System Study for your project.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AF1-176Scenarios
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
DEI DEI: Rebuild 1 mile of Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$1,500,000$115,254
  • NIPSCO LPC
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS NIPSCO: Rebuild line (.3miles)Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$0$0
  • NIPSCO LPC
  • Argos 69.0 - Plymouth 69.0 CKT 1
NIPS Rebuild Argos - Plymouth 69 kV line
Rebuild line, approx 10 miles
$12,654,948$947,149
  • NIPSCO LPC
  • Argos 69.0 - Rochester TP 69.0 CKT 1
NIPS Rebuild Argos - Rochester TP 69 kV
Rebuild line, approx 3.2 miles
$4,049,583$311,154
  • NIPSCO LPC
  • CAP BANK 230.0 - Gallagher 230.0 CKT 0
DEI Install 144 MVAR cap bank at Gallagher sub.
Install 144 MVAR cap bank at Gallagher sub.
$3,000,000$50,139
  • MISO Voltage
  • CAP BANK 138.0 - Shoals 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Shoals sub
Install 28.8 MVAR cap bank at Shoals sub
$3,000,000$44,304
  • MISO Voltage
  • CAP BANK 138.0 - Avon East 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Avon East sub
Install 28.8 MVAR cap bank at Avon East sub
$3,000,000$28,302
  • MISO Voltage
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF1-176 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
ATSIn9322.0Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction.Cost Allocated$838,835
AEPn3985Upgrade three Marysville Wavetraps ( 3000A)Contingent$0N/A
Grand Total:$838,835

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9322.0
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
n9322.0 / TE-AG1-S-0012a
Title
Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction.
Description
Replace (4) disconnect switches at Allen Junction Replace (4) breaker leads at Allen Junction Reconductor (2) TL Drops at Allen Junction Replace (1) meter at Allen Junction New FE Ratings 1868 / 2249 / 2586 MVA SN/SE/SLD
Total Cost ($USD)
$1,408,997
Discounted Total Cost ($USD)
$1,408,997
Allocated Cost ($USD)
$838,835
Time Estimate
38 Months

Contributor

FacilityContingency
02ALLEN-18MOROCCO 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A1868.0 MVA
(All)B2249.0 MVA
(All)C2586.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AF1-17634.3 MW59.5%$838,835
AF2-39623.3 MW40.5%$570,162

System Reinforcement: n3985
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n3985 / AEPO0036a
Title
Upgrade three Marysville Wavetraps ( 3000A)
Description
Replace 3 Marysville 765 kV wave traps. Costs updated to $705,368 from Facility Study
Total Cost ($USD)
$900,000
Discounted Total Cost ($USD)
$900,000
Allocated Cost ($USD)
$0
Time Estimate
18 to 24 Months

Contingent

Note: Based on PJM cost allocation criteria, AF1-176 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle. Although AF1-176 may not have cost responsibility for this upgrade, AF1-176 may need this upgrade in-service to be deliverable for the reliability to the PJM system. If AF1-176 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05MARYSV-05SORENS 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A5075.0 MVA
(All)B5075.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF1-176


AF1-176 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AF1-176 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AF1-176 One Line Diagram

AF1-176 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.