AF1-204 Final System Impact Study (Retool 1) Report

v1.00 released 2025-12-08 18:16

Eugene 345 kV

63.75 MW Capacity / 255.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Vermilion Grove Wind, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed a Wind generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Vermillion County, Indiana. The installed facilities will have a total capability of 255.0 MW with 63.75 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF1-204
Project Name:
Eugene 345 kV
Project Developer Name:
Vermilion Grove Wind, LLC
State:
Indiana
County:
Vermillion
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
255.0
MWE:
255.0
MWC:
63.75
Fuel Type:
Wind
Basecase Study Year:
2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF1-204 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system via a direct connection to the Eugene 345 kV substation.

 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AF1-204 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AF1-204Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$2,204,630$2,204,630
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$391,163$391,163
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$3,615,699$0
AFS - Non-PJM Violations$69,943$0
Total$6,281,435$2,595,793

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF1-204

Security has been calculated for the AF1-204 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF1-204
Project(s): AF1-204
Final Agreement Security (A): $2,595,793
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $2,595,793
Security on Hand with PJM (D): $7,241,988
Additional Security Due at Agreement Execution (E): C D = $0
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

AF1-204 will interconnect with the AEP transmission system via a direct connection to the Eugene 345 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9599.0

Eugene 345 kV Station: Expansion. • Installation of one (1) terminal riser for the line exit to the AF1-204 generation lead circuit. • Review and revise the protective relay settings for the remainder of the Eugene 345 kV Station.

$257,613$45,707$75,299$12,544$391,163$391,163
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage. • Installation of one (1) new span of aluminum conductor steel-reinforced ("ACSR") 2-bundled 954 54/7 (Cardinal) transmission line conductor with Guinea 159 ACSR 12-7 shield wire for the generation lead circuit exiting the Eugene 345 kV Station. • Installation of a standard revenue metering package, including three (3) single phase current transformers ("CTs"), three (3) single phase coupling capacitor voltage transformers ("CCVTs"), associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module ("DICM")-installed metering panel, for the generation lead circuit at the Eugene 345 kV Station. • Extension of two (2) underground all dielectric loose tube ("ADLT") fiber optic cables from the Eugene 345 kV Station control house to fiber demarcation splice boxes to support direct fiber relaying between the Eugene 345 kV and Project Developer's collector stations. • Installation of a dual, direct-fiber, current differential protection scheme for the generation lead circuit.

$1,198,864$642,862$242,087$120,817$2,204,630$2,204,630

Based on the scope of work for the Interconnection Facilities, it is expected to take 31 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The wind generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Wind speed (meters/second) - (Required)
  • Wind direction (decimal degrees from true north) - (Required)
  • Ambient air temperature (Fahrenheit) - (Required)
  • Air Pressure (Hectopascals) - (Required)
  • Humidity (Percent) - (Accepted, not required)
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AF1-204 was evaluated as a 255.0 MW (63.75 MW Capacity) injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP/DEI
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
AEP_P7-1_#11014___SRT-A-1
TowerAC106.03 %1374.0B1456.88135.47
GD1AEP/DEI
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
AEP_P7-1_#11042___SRT-A
TowerAC104.37 %1374.0B1434.0119.03

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
Contingency Name:
AEP_P7-1_#11014___SRT-A-1
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:106.03 %
Rating:1374.0 MVA
Rating Type:B
MVA to Mitigate:1456.88
MW Contribution:135.47
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
Contingency Name:
AEP_P7-1_#11014___SRT-A-1
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:106.52 %
Rating:1374.0 MVA
Rating Type:B
MVA to Mitigate:1463.53
MW Contribution:135.49
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
965091AG1-374 C
Adder
14.06117647058823611.952
965092AG1-374 E
Adder
9.3741176470588247.968
965911AG1-460 C
Adder
1.05647058823529430.898
965912AG1-460 E
Adder
1.58470588235294121.347
290261S-027 E
Adder
12.74941176470588310.837
290265S-028 E
Adder
12.67058823529411710.77
936771AD2-100 C
Adder
11.0211764705882369.368
936772AD2-100 E
Adder
7.3470588235294126.245
936971AD2-131 C
Adder
0.72588235294117650.617
936972AD2-131 E
Adder
3.6470588235294123.1
942111AE2-223 C
Adder
1.4764705882352941.255
942112AE2-223 E
Adder
9.8788235294117658.397
942481AE2-261 C
Adder
15.78941176470588213.421
942482AE2-261 E
Adder
10.5258823529411768.947
959341AF2-225 C
Adder
4.76941176470588254.054
959342AF2-225 E
Adder
6.58588235294117655.598
959611AF2-252 C
Adder
1.56235294117647071.328
959612AF2-252 E
Adder
2.3435294117647061.992
960611AF2-352 C
Adder
1.56235294117647071.328
960612AF2-352 E
Adder
2.3435294117647061.992
276615W2-048 GEN
Adder
5.00470588235294044.254
276621X2-022 GEN
Adder
17.1305882352941214.561
917502Z2-087 E
Adder
13.17176470588235311.196
957381AF2-032 C
Adder
1.21.02
957382AF2-032 E
Adder
0.56470588235294120.48
274890CAYUG;1U E
Adder
6.3117647058823545.365
274891CAYUG;2U E
Adder
6.3117647058823545.365
925772AC1-053 E
Adder
16.4529411764705913.985
933441AC2-157 C
50/50
9.5729.572
933442AC2-157 E
50/50
15.61715.617
276174W4-005 E
Adder
25.1282352941176521.359
924048AB2-047 E1
Adder
8.1670588235294136.942
924049AB2-047 E2
Adder
8.2964705882352947.052
924266AB2-070 E
Adder
15.03529411764705912.78
942601AE2-276 C
50/50
6.2976.297
945391AF1-204 C
50/50
33.86833.868
945392AF1-204 E
50/50
101.603101.603
960141AF2-305_AG1-
Adder
0.87882352941176480.747
930461AB1-087 C
50/50
11.00811.008
930462AB1-087 E
50/50
3.1493.149
930471AB1-088 C
50/50
10.83910.839
930472AB1-088 E
50/50
3.1493.149
939741AE1-205 C
Adder
6.3588235294117655.405
939742AE1-205 E
Adder
8.7811764705882357.464
963741AG1-226 C
50/50
75.42975.429
963742AG1-226 E
50/50
163.607163.607
963841AG1-237 C
50/50
13.81113.811
963842AG1-237 E
50/50
92.42492.424
944221AF1-090 C
Adder
3.0235294117647062.57
944222AF1-090 E
Adder
14.15411764705882512.031
990057J1201
External Queue
2.866802692413332.86680269241333
990272J1263 G
External Queue
34.43985748291015634.439857482910156
990672J1360
External Queue
49.1416740417480549.14167404174805
992572J1022
External Queue
23.22961235046386723.229612350463867
954822J955
External Queue
78.4833374023437578.48333740234375
956282J1115 C
External Queue
3.1526603698730473.152660369873047
956283J1115 E
External Queue
17.0567016601562517.05670166015625
956452J1139
External Queue
34.86825561523437534.868255615234375
990353J1289 C
External Queue
1.89602851867675781.8960285186767578
990354J1289 E
External Queue
10.25800037384033210.258000373840332
991037J1464 G
External Queue
40.3800201416015640.38002014160156
991082J1475 G
External Queue
7.5343327522277837.534332752227783
991192J1610 G
External Queue
7.13355541229248057.1335554122924805
991197J1626
External Queue
9.9642887115478529.964288711547852
991217J1653
External Queue
8.5655527114868168.565552711486816
991267J1714
External Queue
6.642859458923346.64285945892334
991278J1725 C
External Queue
0.89081752300262450.8908175230026245
991279J1725 E
External Queue
4.819550991058354.81955099105835
CBM West 1LTFEXP_CBM-W1->PJM
CBM
29.38929.389
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.0794.079
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.6960.696
NYPJM->LTFIMP_NY
CLTF
0.3780.378
WECLTFEXP_WEC->PJM
CLTF
1.0231.023
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.0860.086
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.0330.033
TVALTFEXP_TVA->PJM
CLTF
1.1281.128
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.8660.866
MECLTFEXP_MEC->PJM
CLTF
5.8845.884
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.8452.845
LAGNLTFEXP_LAGN->PJM
CLTF
2.632.63
O66PJM->LTFIMP_O-066
CMTX_NF
4.4694.469
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.1550.155

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11042___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
Contingency Name:
AEP_P7-1_#11042___SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:104.37 %
Rating:1374.0 MVA
Rating Type:B
MVA to Mitigate:1434.0
MW Contribution:119.03
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
Contingency Name:
AEP_P7-1_#11042___SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:104.68 %
Rating:1374.0 MVA
Rating Type:B
MVA to Mitigate:1438.32
MW Contribution:119.04
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
966841AG1-555 C
50/50
24.49324.493
966842AG1-555 E
50/50
8.7558.755
965091AG1-374 C
Adder
12.3810.523
965092AG1-374 E
Adder
8.2529411764705877.015
965911AG1-460 C
Adder
0.90.765
965912AG1-460 E
Adder
1.34941176470588231.147
24790005FR-11G E
50/50
23.68923.689
24790105FR-12G E
50/50
23.32923.329
24790205FR-21G E
50/50
24.79824.798
24790305FR-22G E
50/50
23.82823.828
24790405FR-3G E
50/50
46.21546.215
24790505FR-4G E
50/50
36.62836.628
24790605MDL-1G E
50/50
48.7948.79
24790705MDL-2G E
50/50
23.49423.494
24791205MDL-3G E
50/50
23.46723.467
24791305MDL-4G E
50/50
24.43624.436
290261S-027 E
Adder
11.2247058823529419.541
290265S-028 E
Adder
11.1552941176470589.482
936771AD2-100 C
Adder
9.3588235294117657.955
936772AD2-100 E
Adder
6.2388235294117655.303
936971AD2-131 C
Adder
0.61647058823529410.524
936972AD2-131 E
Adder
3.09764705882352942.633
942111AE2-223 C
Adder
1.30941176470588231.113
942112AE2-223 E
Adder
8.7623529411764727.448
942481AE2-261 C
Adder
13.44941176470588411.432
942482AE2-261 E
Adder
8.9658823529411777.621
959341AF2-225 C
Adder
4.23058823529411753.596
959342AF2-225 E
Adder
5.8423529411764714.966
959611AF2-252 C
Adder
1.3752941176470591.169
959612AF2-252 E
Adder
2.0635294117647061.754
960611AF2-352 C
Adder
1.3752941176470591.169
960612AF2-352 E
Adder
2.0635294117647061.754
24385905FR-11G C
50/50
1.1631.163
24386205FR-12G C
50/50
0.5660.566
24386405FR-21G C
50/50
0.5890.589
24386605FR-22G C
50/50
0.5890.589
24387005FR-3G C
50/50
0.5660.566
24387305FR-4G C
50/50
1.3181.318
276615W2-048 GEN
Adder
4.3141176470588243.667
276621X2-022 GEN
Adder
14.76705882352941212.552
917502Z2-087 E
Adder
11.6835294117647069.931
946581AF1-322 C
50/50
23.27323.273
946582AF1-322 E
50/50
32.13932.139
957381AF2-032 C
Adder
1.02352941176470580.87
957382AF2-032 E
Adder
0.481176470588235260.409
24690905MDL-1G C
50/50
1.1731.173
24691005MDL-2G C
50/50
0.6880.688
24697605MDL-3G C
50/50
0.6930.693
24697905MDL-4G C
50/50
0.5340.534
925772AC1-053 E
Adder
14.23647058823529612.101
933441AC2-157 C
50/50
9.1999.199
933442AC2-157 E
50/50
15.00915.009
276174W4-005 E
Adder
21.75294117647058618.49
924048AB2-047 E1
Adder
7.24470588235294166.158
924049AB2-047 E2
Adder
7.3588235294117656.255
24755605MDL-5G
50/50
0.9150.915
247943T-127 E
50/50
22.10922.109
930041AB1-006 E1
50/50
42.18242.182
930042AB1-006 E2
50/50
6.0266.026
270180AB1-006 W1
50/50
1.031.03
270181AB1-006 W2
50/50
0.1470.147
924266AB2-070 E
Adder
13.03176470588235211.077
942601AE2-276 C
50/50
6.0526.052
945391AF1-204 C
50/50
29.75729.757
945392AF1-204 E
50/50
89.27189.271
960141AF2-305_AG1-
Adder
0.76117647058823530.647
930461AB1-087 C
50/50
10.5810.58
930462AB1-087 E
50/50
3.0263.026
930471AB1-088 C
50/50
10.41710.417
930472AB1-088 E
50/50
3.0263.026
939741AE1-205 C
Adder
5.644.794
939742AE1-205 E
Adder
7.7894117647058836.621
963741AG1-226 C
50/50
49.45349.453
963742AG1-226 E
50/50
107.265107.265
963841AG1-237 C
50/50
8.1778.177
963842AG1-237 E
50/50
54.72654.726
944221AF1-090 C
Adder
2.54235294117647072.161
944222AF1-090 E
Adder
11.90588235294117510.12
990272J1263 G
External Queue
28.79624176025390628.796241760253906
990672J1360
External Queue
43.5486869812011743.54868698120117
992572J1022
External Queue
20.7162399291992220.71623992919922
954822J955
External Queue
70.3054656982421970.30546569824219
956282J1115 C
External Queue
2.83346652984619142.8334665298461914
956283J1115 E
External Queue
15.32977962493896515.329779624938965
956452J1139
External Queue
30.61046218872070330.610462188720703
991037J1464 G
External Queue
36.4587554931640636.45875549316406
991082J1475 G
External Queue
7.1702566146850597.170256614685059
991192J1610 G
External Queue
6.4510741233825686.451074123382568
CBM West 1LTFEXP_CBM-W1->PJM
CBM
28.12128.121
G-007PJM->LTFIMP_G-007
CMTX_NF
0.7110.711
NYPJM->LTFIMP_NY
CLTF
0.3810.381
WECLTFEXP_WEC->PJM
CLTF
0.9720.972
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.210.21
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1160.116
TVALTFEXP_TVA->PJM
CLTF
0.3420.342
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
1.1131.113
MECLTFEXP_MEC->PJM
CLTF
5.0675.067
BlueGrassPJM->LTFIMP_BlueG
CLTF
3.6773.677
LAGNLTFEXP_LAGN->PJM
CLTF
1.6091.609
O66PJM->LTFIMP_O-066
CMTX_NF
4.5614.561
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.2990.299
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
243221 to 249504 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP/NIPS
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
AEP_P1-2_#8807_SRT-A
OPAC130.68 %1868.0B2441.1455.93
GD1AEP/NIPS
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
AEP_P1-2_#8695_SRT-A
OPAC130.68 %1868.0B2441.1455.93

Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line l/o AEP_P1-2_#8807_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8807_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:130.68 %
Rating:1868.0 MVA
Rating Type:B
MVA to Mitigate:2441.14
MW Contribution:55.93
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8807_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:131.46 %
Rating:1868.0 MVA
Rating Type:B
MVA to Mitigate:2455.69
MW Contribution:56.0
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
966841AG1-555 C
50/50
51.16851.168
966842AG1-555 E
50/50
18.29118.291
24790005FR-11G E
50/50
49.48949.489
24790105FR-12G E
50/50
48.73748.737
24790205FR-21G E
50/50
51.80551.805
24790305FR-22G E
50/50
49.77949.779
24790405FR-3G E
50/50
96.54896.548
24790505FR-4G E
50/50
76.52176.521
24790605MDL-1G E
50/50
120.794120.794
24790705MDL-2G E
50/50
58.16858.168
24791205MDL-3G E
50/50
58.09958.099
24791305MDL-4G E
50/50
60.560.5
24385905FR-11G C
50/50
2.432.43
24386205FR-12G C
50/50
1.1831.183
24386405FR-21G C
50/50
1.231.23
24386605FR-22G C
50/50
1.231.23
24387005FR-3G C
50/50
1.1831.183
24387305FR-4G C
50/50
2.7532.753
946581AF1-322 C
50/50
57.61957.619
946582AF1-322 E
50/50
79.56979.569
24690905MDL-1G C
50/50
2.9032.903
24691005MDL-2G C
50/50
1.7041.704
24697605MDL-3G C
50/50
1.7151.715
24697905MDL-4G C
50/50
1.3231.323
933441AC2-157 C
50/50
10.93510.935
933442AC2-157 E
50/50
17.84217.842
24755605MDL-5G
50/50
2.2642.264
247943T-127 E
50/50
54.73854.738
930041AB1-006 E1
50/50
104.434104.434
930042AB1-006 E2
50/50
14.91914.919
270180AB1-006 W1
50/50
2.552.55
270181AB1-006 W2
50/50
0.3640.364
942601AE2-276 C
50/50
7.1947.194
945391AF1-204 C
50/50
13.98213.982
945392AF1-204 E
50/50
41.94741.947
930461AB1-087 C
50/50
12.57712.577
930462AB1-087 E
50/50
3.5973.597
930471AB1-088 C
50/50
12.38312.383
930472AB1-088 E
50/50
3.5973.597
963741AG1-226 C
50/50
63.03663.036
963742AG1-226 E
50/50
136.726136.726
963841AG1-237 C
50/50
13.20413.204
963842AG1-237 E
50/50
88.36888.368
958391AF2-133 C
Adder
-32.38470588235295-27.527
956452J1139
External Queue
17.7291660308837917.72916603088379
991082J1475 G
External Queue
8.5628738403320318.562873840332031
991162J1518
External Queue
26.29820823669433626.298208236694336
CBM West 2LTFEXP_CBM-W2->PJM
CBM
36.35336.353
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
16.85316.853
G-007ALTFEXP_G-007A->PJM
CMTX
0.0120.012
VTFLTFEXP_VFT->PJM
CMTX
0.0160.016
NYPJM->LTFIMP_NY
CLTF
0.0430.043
LGEELTFEXP_LGEE->PJM
CLTF
2.2532.253
CPLELTFEXP_CPLE->PJM
CLTF
1.231.23
TVALTFEXP_TVA->PJM
CLTF
5.1395.139
MECLTFEXP_MEC->PJM
CLTF
2.8472.847
LAGNLTFEXP_LAGN->PJM
CLTF
6.2716.271
SIGELTFEXP_SIGE->PJM
CLTF
0.7630.763
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.5930.593

Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line l/o AEP_P1-2_#8695_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
Contingency Name:
AEP_P1-2_#8695_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:130.68 %
Rating:1868.0 MVA
Rating Type:B
MVA to Mitigate:2441.14
MW Contribution:55.93
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
Contingency Name:
AEP_P1-2_#8695_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:131.46 %
Rating:1868.0 MVA
Rating Type:B
MVA to Mitigate:2455.69
MW Contribution:56.0
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
966841AG1-555 C
50/50
51.16851.168
966842AG1-555 E
50/50
18.29118.291
24790005FR-11G E
50/50
49.48949.489
24790105FR-12G E
50/50
48.73748.737
24790205FR-21G E
50/50
51.80551.805
24790305FR-22G E
50/50
49.77949.779
24790405FR-3G E
50/50
96.54896.548
24790505FR-4G E
50/50
76.52176.521
24790605MDL-1G E
50/50
120.794120.794
24790705MDL-2G E
50/50
58.16858.168
24791205MDL-3G E
50/50
58.09958.099
24791305MDL-4G E
50/50
60.560.5
24385905FR-11G C
50/50
2.432.43
24386205FR-12G C
50/50
1.1831.183
24386405FR-21G C
50/50
1.231.23
24386605FR-22G C
50/50
1.231.23
24387005FR-3G C
50/50
1.1831.183
24387305FR-4G C
50/50
2.7532.753
946581AF1-322 C
50/50
57.61957.619
946582AF1-322 E
50/50
79.56979.569
24690905MDL-1G C
50/50
2.9032.903
24691005MDL-2G C
50/50
1.7041.704
24697605MDL-3G C
50/50
1.7151.715
24697905MDL-4G C
50/50
1.3231.323
933441AC2-157 C
50/50
10.93510.935
933442AC2-157 E
50/50
17.84217.842
24755605MDL-5G
50/50
2.2642.264
247943T-127 E
50/50
54.73854.738
930041AB1-006 E1
50/50
104.434104.434
930042AB1-006 E2
50/50
14.91914.919
270180AB1-006 W1
50/50
2.552.55
270181AB1-006 W2
50/50
0.3640.364
942601AE2-276 C
50/50
7.1947.194
945391AF1-204 C
50/50
13.98213.982
945392AF1-204 E
50/50
41.94741.947
930461AB1-087 C
50/50
12.57712.577
930462AB1-087 E
50/50
3.5973.597
930471AB1-088 C
50/50
12.38312.383
930472AB1-088 E
50/50
3.5973.597
963741AG1-226 C
50/50
63.03663.036
963742AG1-226 E
50/50
136.726136.726
963841AG1-237 C
50/50
13.20413.204
963842AG1-237 E
50/50
88.36888.368
958391AF2-133 C
Adder
-32.38470588235295-27.527
956452J1139
External Queue
17.7291660308837917.72916603088379
991082J1475 G
External Queue
8.5628738403320318.562873840332031
991162J1518
External Queue
26.29820823669433626.298208236694336
CBM West 2LTFEXP_CBM-W2->PJM
CBM
36.35336.353
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
16.85316.853
G-007ALTFEXP_G-007A->PJM
CMTX
0.0120.012
VTFLTFEXP_VFT->PJM
CMTX
0.0160.016
NYPJM->LTFIMP_NY
CLTF
0.0430.043
LGEELTFEXP_LGEE->PJM
CLTF
2.2532.253
CPLELTFEXP_CPLE->PJM
CLTF
1.231.23
TVALTFEXP_TVA->PJM
CLTF
5.1395.139
MECLTFEXP_MEC->PJM
CLTF
2.8472.847
LAGNLTFEXP_LAGN->PJM
CLTF
6.2716.271
SIGELTFEXP_SIGE->PJM
CLTF
0.7630.763
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.5930.593
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
243878 to 255205 ckt 1
243878 to 255205 ckt 2

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AF1-204 was evaluated as a 255.0 MW injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP/OVEC
06KYGER-05SPORN 345.0 kV Ckt 1 line
AEP_P1-2_#7441_100545_SRT-A
SingleDC101.06 %1204.0B1216.7212.69

Details for 06KYGER-05SPORN 345.0 kV Ckt 1 line l/o AEP_P1-2_#7441_100545_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
Contingency Type:Single
DC|AC:DC
Final Cycle Loading:101.06 %
Rating:1204.0 MVA
Rating Type:B
MVA to Mitigate:1216.72
MW Contribution:12.69
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24725505WLD G2 C
80/20
0.2270.227
24385905FR-11G C
80/20
0.3740.374
24386205FR-12G C
80/20
0.1820.182
24386405FR-21G C
80/20
0.1890.189
24386605FR-22G C
80/20
0.1890.189
24387005FR-3G C
80/20
0.1820.182
24387305FR-4G C
80/20
0.4240.424
24790105FR-12G E
80/20
1.2271.227
24790205FR-21G E
80/20
1.3041.304
24790405FR-3G E
80/20
2.432.43
24790505FR-4G E
80/20
1.9261.926
24790605MDL-1G E
80/20
2.5232.523
24790705MDL-2G E
80/20
1.2151.215
24791205MDL-3G E
80/20
1.2141.214
24791305MDL-4G E
80/20
1.2641.264
24795805WLD G2 E
80/20
3.0893.089
274847GR RIDGE ;BU
80/20
0.3660.366
274848CAMPGROVE;RU
80/20
0.1730.173
274849CRESCENT ;1U
80/20
0.1290.129
274851PROVIDENC;RU
80/20
0.1370.137
274853TWINGROVE;U1
80/20
0.4790.479
274854TWINGROVE;U2
80/20
0.4920.492
274861TOP CROP ;1U
80/20
0.2450.245
274862TOP CROP ;2U
80/20
0.4680.468
274863CAYUGA RI;1U
80/20
0.3050.305
274864CAYUGA RI;2U
80/20
0.3050.305
274871GR RIDGE ;2U
80/20
0.1360.136
274877BISHOP HL;1U
80/20
0.2660.266
274878BISHOP HL;2U
80/20
0.2660.266
274879MINONK ;1U
80/20
0.5330.533
274880RADFORD R;1U
80/20
0.6340.634
274887PILOT HIL;1U
80/20
0.4670.467
274888KELLY CRK;1U
80/20
0.4670.467
276615W2-048 GEN
80/20
0.9020.902
276621X2-022 GEN
80/20
2.5692.569
290021O50 E
80/20
2.1322.132
290261S-027 E
80/20
2.2452.245
290265S-028 E
80/20
2.2322.232
293061N-015 E
80/20
1.6031.603
293644O22 E1
80/20
1.5311.531
293645O22 E2
80/20
1.7541.754
293771O-035 E
80/20
0.8490.849
294392P-010 E
80/20
2.0362.036
294401BSHIL;1U E
80/20
1.0641.064
294410BSHIL;2U E
80/20
1.0641.064
917502Z2-087 E
80/20
2.3892.389
918052AA1-018 E OP
80/20
1.7391.739
925581AC1-033 C
80/20
0.2790.279
925582AC1-033 E
80/20
1.8681.868
934721AD1-100 C
80/20
1.9291.929
934722AD1-100 E
80/20
30.0130.01
942111AE2-223 C
80/20
0.8570.857
942112AE2-223 E
80/20
5.7335.733
959351AF2-226 C
80/20
1.0661.066
959352AF2-226 E
80/20
1.5991.599
959611AF2-252 C
80/20
1.1011.101
959612AF2-252 E
80/20
1.6511.651
960281AF2-319 C
80/20
1.0661.066
960282AF2-319 E
80/20
1.5991.599
960611AF2-352 C
80/20
1.1011.101
960612AF2-352 E
80/20
1.6511.651
960971AF2-388 C
80/20
1.8951.895
960972AF2-388 E
80/20
8.8738.873
965651AG1-433 C
80/20
0.9480.948
965652AG1-433 E
80/20
4.4364.436
966091AG1-478 C
80/20
0.2130.213
966092AG1-478 E
80/20
0.320.32
966842AG1-555 E
80/20
5.1515.151
24344305RKG2
80/20
49.81949.819
24379505HDWTR1G C
80/20
0.5180.518
24699105WLD G1 C
80/20
0.2340.234
24753605BLUFF P WF
80/20
0.4330.433
247543V3-007 C
80/20
0.5180.518
247929S-071 E
80/20
1.7341.734
247935V3-007 E
80/20
3.4643.464
24796305HDWTR1G E
80/20
3.4643.464
274674JOLIET 9 ;6U
80/20
6.7426.742
274675JOLIET 29;7U
80/20
17.57617.576
274676JOLIET 29;8U
80/20
17.57617.576
274687WILL CNTY;4U
80/20
16.29816.298
943771AF1-045 C
80/20
3.7493.749
943772AF1-045 E
80/20
2.5032.503
945382AF1-203 E
80/20
1.0781.078
961761AG1-017 C
80/20
0.1560.156
961762AG1-017 E
80/20
0.7170.717
24690905MDL-1G C
80/20
0.3710.371
24691005MDL-2G C
80/20
0.2180.218
24697605MDL-3G C
80/20
0.2190.219
24697905MDL-4G C
80/20
0.1690.169
274890CAYUG;1U E
80/20
1.6261.626
274891CAYUG;2U E
80/20
1.6261.626
925771AC1-053 C
80/20
0.5780.578
925772AC1-053 E
80/20
3.8683.868
938851AE1-113 C
80/20
2.8142.814
938852AE1-113 E
80/20
9.9789.978
24790005FR-11G E
80/20
1.2461.246
24790305FR-22G E
80/20
1.2531.253
939401AE1-172 C
80/20
1.941.94
939402AE1-172 E
80/20
9.0819.081
942651AE2-281 C
80/20
0.2980.298
942652AE2-281 E
80/20
1.8341.834
939781AE1-209 C
80/20
0.7710.771
939782AE1-209 E
80/20
5.1615.161
957382AF2-032 E
80/20
0.1110.111
964782AG1-341 E
80/20
5.6895.689
24755605MDL-5G
80/20
0.2890.289
247943T-127 E
80/20
1.1431.143
251828CLNTESP1
80/20
1.0531.053
25196808ZIMRHP
80/20
48.79548.795
270180AB1-006 W1
80/20
0.3260.326
270181AB1-006 W2
80/20
0.0470.047
270681BRIGHTSTK; R
80/20
0.3570.357
270839OTTER CRK; R
80/20
0.260.26
275149KELLYCK ;1E
80/20
1.8691.869
276174W4-005 E
80/20
3.6233.623
276645AC1-214 C1
80/20
0.1130.113
276646AC1-214 C2
80/20
0.1130.113
276655AB2-047 C1
80/20
0.2230.223
276656AB2-047 C2
80/20
0.2230.223
276668AB2-070 C
80/20
0.3610.361
276675AE2-062 E
80/20
0.0530.053
293519PILOT HIL;1E
80/20
1.8691.869
916212CRESCENT ;1U
80/20
0.5970.597
924048AB2-047 E1
80/20
1.4811.481
924049AB2-047 E2
80/20
1.5041.504
924266AB2-070 E
80/20
2.1882.188
926821AC1-168 C
80/20
0.4360.436
926822AC1-168 E
80/20
2.9272.927
927208AC1-214 E1
80/20
0.4030.403
927209AC1-214 E2
80/20
0.4030.403
930041AB1-006 E1
80/20
2.1822.182
930042AB1-006 E2
80/20
0.3120.312
935141AD1-148 C
80/20
0.8070.807
936371AD2-047 C
80/20
1.4531.453
936372AD2-047 E
80/20
7.0937.093
939321AE1-163 C
80/20
2.092.09
939322AE1-163 E
80/20
12.83712.837
939791AE1-210 C
80/20
0.7710.771
939792AE1-210 E
80/20
5.1615.161
941721AE2-172 C
80/20
2.7562.756
942421AE2-255 C
80/20
1.0661.066
942422AE2-255 E
80/20
3.1983.198
942601AE2-276 C
80/20
3.1363.136
944221AF1-090 C
80/20
1.5711.571
944222AF1-090 E
80/20
7.3577.357
944242AF1-092 E
80/20
6.476.47
944532AF1-118 E
80/20
22.09922.099
944542AF1-119 E
80/20
13.12313.123
945371AF1-202 C
80/20
1.871.87
945372AF1-202 E
80/20
9.1319.131
945391AF1-204 C
80/20
3.1723.172
945392AF1-204 E
80/20
9.5179.517
957372AF2-031 E
80/20
0.6380.638
957842AF2-078 E
80/20
1.1371.137
958861AF2-177 C
80/20
1.4161.416
958862AF2-177 E
80/20
9.4749.474
960261AF2-317 C
80/20
0.3490.349
961161AF2-407 C
80/20
22.20322.203
961171AF2-408 C
80/20
5.9915.991
961501AF2-441 C
80/20
4.2584.258
961502AF2-441 E
80/20
6.3886.388
963581AG1-207 C
80/20
6.7246.724
963841AG1-237 C
80/20
1.2281.228
963842AG1-237 E
80/20
8.2188.218
964611AG1-324 C
80/20
0.3140.314
964612AG1-324 E
80/20
0.4710.471
965331AG1-398 C
80/20
0.1630.163
965462AG1-414 E
80/20
1.6981.698
990901L-005 E
80/20
1.5991.599
270201AC2-176 GEN
80/20
0.2920.292
933596AC2-176 E
80/20
1.9521.952
25016408BKJDB1
80/20
0.2670.267
251827WILLYESP
80/20
0.6880.688
965913AG1-460 BT
80/20
0.0060.006
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
248005 to 242528 ckt 1

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1CE
AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line
COMED_P1-2_345-L8014__R-S_SRT-A
OPAC117.32 %1528.0B1792.6613.1
GD1CE
LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line
COMED_P1-2_345-L8014__R-S_SRT-A
OPAC107.62 %1528.0B1644.3913.1

Details for AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L8014__R-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:117.32 %
Rating:1528.0 MVA
Rating Type:B
MVA to Mitigate:1792.66
MW Contribution:13.1
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:117.14 %
Rating:1528.0 MVA
Rating Type:B
MVA to Mitigate:1789.94
MW Contribution:13.15
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
274853TWINGROVE;U1
50/50
3.5773.577
274854TWINGROVE;U2
50/50
3.6793.679
274863CAYUGA RI;1U
50/50
3.4783.478
274864CAYUGA RI;2U
50/50
3.4783.478
274880RADFORD R;1U
50/50
3.2763.276
276615W2-048 GEN
50/50
3.9753.975
276621X2-022 GEN
50/50
11.31211.312
290261S-027 E
50/50
16.77316.773
290265S-028 E
50/50
16.67116.671
917502Z2-087 E
50/50
19.24919.249
942111AE2-223 C
50/50
6.9036.903
942112AE2-223 E
50/50
46.19846.198
959611AF2-252 C
50/50
8.2228.222
959612AF2-252 E
50/50
12.33312.333
960611AF2-352 C
50/50
8.2228.222
960612AF2-352 E
50/50
12.33312.333
966091AG1-478 C
Adder
-0.37411764705882355-0.318
274674JOLIET 9 ;6U
Adder
-10.927058823529412-9.288
274675JOLIET 29;7U
Adder
-26.610588235294117-22.619
274890CAYUG;1U E
50/50
18.54818.548
274891CAYUG;2U E
50/50
18.54818.548
925771AC1-053 C
50/50
2.7412.741
925772AC1-053 E
50/50
18.34518.345
939401AE1-172 C
50/50
24.45324.453
939402AE1-172 E
50/50
114.484114.484
957382AF2-032 E
50/50
0.4060.406
270681BRIGHTSTK; R
50/50
2.8762.876
276174W4-005 E
50/50
18.7118.71
276655AB2-047 C1
50/50
1.7981.798
276656AB2-047 C2
50/50
1.7981.798
276668AB2-070 C
50/50
1.7711.771
924048AB2-047 E1
50/50
11.93711.937
924049AB2-047 E2
50/50
12.12512.125
924266AB2-070 E
50/50
10.72810.728
935141AD1-148 C
50/50
3.5553.555
942601AE2-276 C
Adder
2.66588235294117662.266
944221AF1-090 C
50/50
4.9244.924
944222AF1-090 E
50/50
23.05323.053
945391AF1-204 C
Adder
3.27529411764705852.784
945392AF1-204 E
Adder
9.8258823529411778.352
960141AF2-305_AG1-
50/50
1.0041.004
960261AF2-317 C
50/50
1.5361.536
965331AG1-398 C
50/50
0.80.8
965913AG1-460 BT
50/50
0.020.02
956282J1115 G
External Queue
47.51847.518
990057J1201
External Queue
1.20651.2065
990272J1263 G
External Queue
10.002810.0028
990352J1289
External Queue
23.13823.138
990672J1360
External Queue
55.9555.95
992572J1022
External Queue
29.761529.7615

Details for LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L8014__R-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:107.62 %
Rating:1528.0 MVA
Rating Type:B
MVA to Mitigate:1644.39
MW Contribution:13.1
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:107.48 %
Rating:1528.0 MVA
Rating Type:B
MVA to Mitigate:1642.37
MW Contribution:13.15
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
274853TWINGROVE;U1
50/50
3.5773.577
274854TWINGROVE;U2
50/50
3.6793.679
274863CAYUGA RI;1U
50/50
3.4783.478
274864CAYUGA RI;2U
50/50
3.4783.478
274880RADFORD R;1U
50/50
3.2763.276
276615W2-048 GEN
50/50
3.9753.975
276621X2-022 GEN
50/50
11.31211.312
290261S-027 E
50/50
16.77316.773
290265S-028 E
50/50
16.67116.671
917502Z2-087 E
50/50
19.24919.249
942111AE2-223 C
50/50
6.9036.903
942112AE2-223 E
50/50
46.19846.198
959611AF2-252 C
50/50
8.2228.222
959612AF2-252 E
50/50
12.33312.333
960611AF2-352 C
50/50
8.2228.222
960612AF2-352 E
50/50
12.33312.333
966091AG1-478 C
Adder
-0.37411764705882355-0.318
274674JOLIET 9 ;6U
Adder
-10.927058823529412-9.288
274675JOLIET 29;7U
Adder
-26.610588235294117-22.619
274890CAYUG;1U E
50/50
18.54818.548
274891CAYUG;2U E
50/50
18.54818.548
925771AC1-053 C
50/50
2.7412.741
925772AC1-053 E
50/50
18.34518.345
957382AF2-032 E
50/50
0.4060.406
270681BRIGHTSTK; R
50/50
2.8762.876
276174W4-005 E
50/50
18.7118.71
276655AB2-047 C1
50/50
1.7981.798
276656AB2-047 C2
50/50
1.7981.798
276668AB2-070 C
50/50
1.7711.771
924048AB2-047 E1
50/50
11.93711.937
924049AB2-047 E2
50/50
12.12512.125
924266AB2-070 E
50/50
10.72810.728
935141AD1-148 C
50/50
3.5553.555
942601AE2-276 C
Adder
2.66588235294117662.266
944221AF1-090 C
50/50
4.9244.924
944222AF1-090 E
50/50
23.05323.053
945391AF1-204 C
Adder
3.27529411764705852.784
945392AF1-204 E
Adder
9.8258823529411778.352
960141AF2-305_AG1-
50/50
1.0041.004
960261AF2-317 C
50/50
1.5361.536
965331AG1-398 C
50/50
0.80.8
965913AG1-460 BT
50/50
0.020.02
956282J1115 G
External Queue
47.51847.518
990057J1201
External Queue
1.20651.2065
990272J1263 G
External Queue
10.002810.0028
990352J1289
External Queue
23.13823.138
990672J1360
External Queue
55.9555.95
992572J1022
External Queue
29.761529.7615
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
939400 to 934720 ckt 1
270704 to 939400 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests AF1-204 and AG1-226 in PJM Transition Cycle 1, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 131 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breakers,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-204 and AG1-226 meet the 0.95 leading and lagging PF requirement.

 

AG1-237 exhibited slow reactive power recovery for P7.04 contingency. This issue did not cause instability in the system and the models can be tuned if required to achieve a faster reactive power output settlement.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 64 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

64

AF1-204

Wind

AEP

255

255

63.75

Eugene 345 kV

AG1-226

Solar

AEP

450

450

142

Eugene-Dequine 345 kV

 

 

Reactive Power Analysis

The reactive power capability of AF1-204 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AB1-006Meadow Lake 345kVIn Service
AB1-080Dumont-Olive 345kVIn Service
AB1-087Sullivan 345kV #1Under Construction
AB1-088Sullivan 345kV #2Engineering & Procurement
AB2-047Brokaw-Pontiac MidpointIn Service
AB2-070Mt. Pulaski-BrokawIn Service
AC1-053Lanesville-BrokawPartially in Service - Under Construction
AC1-168Kewanee-StreatorSuspended
AC2-154Davis Creek 138kVEngineering & Procurement
AC2-157Sullivan 345 kVUnder Construction
AD1-100Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVUnder Construction
AD2-047Davis Creek 138 kVSuspended
AD2-060Davis Creek 138kVEngineering & Procurement
AD2-066Mazon-Crescent Ridge 138 kVUnder Construction
AD2-100Kincaid-Pana 345 kVSuspended
AD2-131Kincaid-Pana 345kVSuspended
AE1-113Mole Creek 345 kVEngineering & Procurement
AE1-163Powerton-Nevada 345 kVEngineering & Procurement
AE1-166Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE1-170Kenzie Creek-Colby 138 kVSuspended
AE1-172Loretto-Wilton CenterActive
AE1-205McLean 345 kVEngineering & Procurement
AE2-045Olive-Reynolds 345 kVEngineering & Procurement
AE2-152Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE2-223McLean 345 kVActive
AE2-255Molecreek 345 kVEngineering & Procurement
AE2-261Kincaid-Pana 345 kVActive
AE2-267Woodsdale 345 kVEngineering & Procurement
AE2-276Sullivan 345kVEngineering & Procurement
AE2-281Powerton-Nevada 345 kVEngineering & Procurement
AE2-341Sandwich-Plano 138 kVActive
AF1-030Sandwich-Plano 138 kVActive
AF1-090Kincaid-PanaEngineering & Procurement
AF1-158Edison-Gravel Pit 138 kVIn Service
AF1-207Reynolds-Olive #1 345 kVEngineering & Procurement
AF1-215Olive-Reynolds 345 kVIn Service
AF1-322Meadow Lake 345 kVEngineering & Procurement
AF2-027Zion Energy Center 345 kVEngineering & Procurement
AF2-031CalumetEngineering & Procurement
AF2-032Kincaid 345 kVEngineering & Procurement
AF2-078Reynolds-Olive #1 345 kVEngineering & Procurement
AF2-083Kenzie Creek-Stone Lake 69 kVUnder Construction
AF2-095Davis Creek 138 kVActive
AF2-132Reynolds-Olive #1 345 kVUnder Construction
AF2-133Reynolds-Olive #2 345 kVUnder Construction
AF2-134Olive-Reynolds #2 345 kVIn Service
AF2-142Nevada 345 kVActive
AF2-143Powerton-Nevada 345 kVActive
AF2-205Olive-Reynolds #2 345 kVEngineering & Procurement
AF2-225McLean 345 kVActive
AF2-226Katydid Road 345 kVActive
AF2-252Blue Mound 345 kVEngineering & Procurement
AF2-305Brokaw-Lanesville 345 kVIn Service
AF2-319Katydid Road 345 kVActive
AF2-350Kensington 138 kVActive
AF2-352Blue Mound 345 kVEngineering & Procurement
AF2-359Olive-University Park 345 kVEngineering & Procurement
AF2-366Crego Rd 138 kVEngineering & Procurement
AF2-441Burnham 138kVActive
AG1-118Sugar Grove-Waterman 138kVActive
AG1-127Crego Rd 138 kVActive
AG1-226Dequine-Eugene 345 kVActive
AG1-237Dequine-Eugene 345 kVEngineering & Procurement
AG1-302Olive-Reynolds #1 345 kVUnder Construction
AG1-349Olive-Reynolds #2 345 kVEngineering & Procurement
AG1-374Blue Mound 345 kVActive
AG1-436Olive-University Park 345 kVActive
AG1-447Olive-University Park 345 kVActive
AG1-460Kincaid-Pana 345 kVActive
AG1-478Wilmington 34.5 kVEngineering & Procurement
AG1-513Aurora 138 kVSuspended
AG1-555Dequine 345 kVEngineering & Procurement
W2-048Brokaw-LanesvilleIn Service
W4-005Blue Mound-LathamIn Service
X2-022Brokaw-LanesvilleIn Service
X3-005Wildwood 12kVIn Service
Y1-054Rochelle 138kVIn Service
Z2-087Pontiac MidPoint-Brokaw 345kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts
AF1-204 System Reinforcements:
TOTrans Owner IDTitleCategoryAllocated Cost ($USD)
DEIDEI_TC1_16079Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. New rating 2430 MVA.Cost Allocated$3,615,699
Grand Total:$3,615,699

System Reinforcement
Type
Load Flow
TO
DEI
RTEP ID / TO ID
(Pending) / DEI_TC1_16079
Title
Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. New rating 2430 MVA.
Description
Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. New rating 2430 MVA.
Total Cost ($USD)
$12,000,000
Allocated Cost ($USD)
$3,615,699
Time Estimate
8 Months

Contributor

FacilityContingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)B2430.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AE2-223 McLean 345kV (ComEd): This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.4 MW2.5%$303,039
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
26.3 MW5.9%$702,348
AF1-204135.5 MW30.1%$3,615,699
AF2-225 McLean 345kV (ComEd): This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.4 MW2.5%$303,039
AG1-226239.0 MW53.2%$6,379,906
AG1-37423.4 MW5.2%$625,508
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.6 MW0.6%$70,462

New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: Please communicate with the Affected System Operator regarding the status of the Affected System Study for your project.

 

Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AF1-204Scenarios
  • Argos 69.0 - Plymouth 69.0 CKT 1
NIPS Rebuild Argos - Plymouth 69 kV line
Rebuild line, approx 10 miles
$12,654,948$3,244
  • NIPSCO LPC
  • CAP BANK 230.0 - Gallagher 230.0 CKT 0
DEI Install 144 MVAR cap bank at Gallagher sub.
Install 144 MVAR cap bank at Gallagher sub.
$3,000,000$25,070
  • MISO Voltage
  • CAP BANK 138.0 - Shoals 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Shoals sub
Install 28.8 MVAR cap bank at Shoals sub
$3,000,000$18,987
  • MISO Voltage
  • CAP BANK 138.0 - Avon East 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Avon East sub
Install 28.8 MVAR cap bank at Avon East sub
$3,000,000$22,642
  • MISO Voltage
  • Cayuga 345.0 - Nucor 345.0 CKT 1
DEI MTEP Proj ID 50718: Cayuga Gen Yard to Nucor
MTEP Proj ID 50718: Rebuild with 954 ZTACSR @ 200C
from
Cayuga Gen Yard to Nucor. Upgrade terminal
equipment
accordingly.
$0$0
  • Contingent
  • Morrison Ditch 345.0 - Reynolds 345.0 CKT 1
NIPS LRTP-16: Morrison Ditch – Reynolds – Burr Oak
Install single circuit 345kV transmission line
from the existing Morrison Ditch
Substation, to the existing Reynolds Substation,
to the existing Burr Oak
Substation, to the existing Leesburg Substation,
to the existing Hiple Substation.
$0$0
  • Contingent
  • Greentown 765.0 - Sorenson 765.0 CKT 1
ITCT LRTP-33: Greentown - Sorenson - Lulu
Install single circuit 765kV transmission line
from the existing Greentown
Substation to the existing Sorenson Substation, to
the existing Lulu Substation.
$0$0
  • Contingent
  • Petersburg 345.0 - Pike County 345.0 CKT 1
DEI LRTP-35: Southwest Indiana-Kentucky
Install double circuit 345kV transmission line
from the existing Petersburg
Substation to the new Pike County Substation.
Install single circuit 345kV
transmission line from the new Pike County
Substation to the existing Duff
Substation, to the existing Culley Substation, to
the existing Reid EHV Substation.
$0$0
  • Contingent
  • Madison County 345.0 - Greensboro 345.0 CKT 1
DEI LRTP-36: Southeast Indiana
Install single circuit 345kV transmission line
from the new Madison County
Substation to the existing Greensboro Substation.
Install single circuit 138kV
transmission line from the existing Decatur County
Substation to the existing
Greensburg Substation. Install double circuit
138kV transmission line from the existing
Batesville Substation to the existing Hubbell
Substation, to the existing Greendale Substation,
to the existing Miami Fort Substation.
$0$0
  • Contingent
  • Maywood 345.0 - Belleau 345.0 CKT 1
AMIL LRTP-37: Maywood - Belleau - MRPD - Sioux - Bugle
Install single circuit 345kV transmission line
from the existing Maywood Substation to the
existing Belleau Substation, to the new MRPD
Substation, to the existing Sioux Substation, from
the new MRPD Substation to the existing Bugle
Substation.
$0$0
  • Contingent
  • Burr Oak 345.0 - Schahfer 345.0 CKT 1
NIPS LRTP-42: Burr Oak - Schahfer
Install single circuit 345kV transmission line
from the existing Burr Oak Substation to the
existing Schahfer Substation.
$0$0
  • Contingent
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF1-204 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
Grand Total:$0

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement
Type
Load Flow
TO
AEP
RTEP ID / TO ID
(Pending) / AEP_TC1_13727
Title
AEP SE rating is 1868 MVA
Description
AEP SE rating is 1868 MVA
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
0 to 1 Months

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)B1868.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF1-204


AF1-204 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AF1-204 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AF1-204 One Line Diagram

AF1-204 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.