AF2-068 Final System Impact Study (Retool 2) Report

v2.00 released 2026-05-14 11:48

Jay 138 kV

90.0 MW Capacity / 150.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Leeward Renewable Energy Development, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.

The AF2-068 Final System Impact Study (Retool 1) Report is available for download here.

Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed a Solar generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Blackford County, Indiana. The installed facilities will have a total capability of 150.0 MW with 90.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-068
Project Name:
Jay 138 kV
Project Developer Name:
Leeward Renewable Energy Development, LLC
State:
Indiana
County:
Blackford
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
150.0
MWE:
150.0
MWC:
90.0
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF2-068 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system at the Jay 138 kV substation.

 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AF2-068 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AF2-068Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$1,750,487$1,750,487
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$1,483,556$1,483,556
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0
AFS - Non-PJM Violations$0 **$0 **
Total$3,234,043$3,234,043

* Contributes to calculation for Security. See Security Requirement Section of this report for additional detail.

** This value reflects the results at the time of the report posting and it is subject to change. AFS – Non-PJM Violations are not subject to Security. For latest AFS – Non-PJM Violations, please refer to the latest Affected System Study Report for your project.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF2-068

Security has been calculated for the AF2-068 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF2-068
Project(s): AF2-068
Final Agreement Security (A): $3,234,043
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $3,234,043
Security on Hand with PJM (D): $3,234,043
Additional Security Due at Agreement Execution (E): C D = $0
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

AF2-068 will interconnect with the AEP transmission system via a direct connection to the Jay 138 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements..

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9564.0

Jay 138 kV Substation: • Extend the north Bus #1 to the east. • Install one (1) new circuit breaker string with two (2) new 3000 A 138 kV 40 kA circuit breakers with associated control relaying. • Install four (4) new 4000 A circuit breaker disconnect switches. • Expand and extend the southeast corner of the Jay Substation by 170 ft. x 75 ft. to accommodate the relocated capacitor bank and associated equipment. • Relocate capacitor bank AA, circuit breaker AA, and associated equipment to the south side of the Jay 138 kV Bus #2. • Install associated and additional buswork, bus supports, jumpers, insulators, grounding, ground grid extension, Supervisory Control and Data Acquisition ("SCADA") connectivity, fiber-optic relaying connectivity & equipment, cables, pull boxes, and foundations. • Review and revise the protective relay settings for the remainder of the Jay 138 kV Substation to account for the addition of the new circuit breakers and the AF2-068 generation source.

$886,855$490,908$68,098$37,695$1,483,556$1,483,556
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• Install one (1) new 130 ft. custom steel single circuit, single pole dead end structure on a concrete foundation with an anchor bolt cage. • Install one (1) span of aluminum conductor steel-reinforced ("ACSR") 795 26/7 (Drake) transmission line conductor with 7 #8 Alumoweld and optical ground wire ("OPGW") shield wire for the generation lead circuit extending from the Jay 138 kV Substation to the PCO. • Install one (1) 138 kV revenue metering package, including one (1) drop in control module ("DICM")-installed metering panel with Primary and Backup meters, three (3) 1-phase current transformers ("CTs"), three (3) 1-phase voltage transformers ("VTs"), three (3) 1-phase surge arresters, and associated structures, foundations, grounding, and telecommunications connectivity at the Jay 138 kV Substation for the proposed AF2-068 generation lead circuit. • Install one (1) new H-Frame take off structure for the generation lead termination. • Install three (3) single-phase capacitor coupled voltage transformers ("CCVTs") on the generation lead to the proposed AF2-068 collector station. • Install dual direct fiber current differential relays for the protection scheme for the proposed AF2-068 generation lead. • Extend the two (2) fiber-optic cables via underground, transmission-supported all dielectric self-supporting ("ADSS") and OPGW with ADSS and OPGW entrances via diverse paths from the Jay 138 kV Substation control house to fiber demarcation splice boxes. The fiber-optic cable runs will support direct fiber relaying between the Jay 138 kV Substation and the Project Developer's collector station.

$1,006,852$496,738$162,638$84,259$1,750,487$1,750,487

Based on the scope of work for the Interconnection Facilities, it is expected to take 26 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

Transmission Owner Identified Network Impacts

There were no network impacts to Distribution facilities identified by the Transmission Owner.

The Transmission Owner identified network impacts to Sub-Regional facilities as follows:

Transmission Owner Identified System Reinforcements on Sub-Regional Facilities
Overloaded ElementContingencyRating [MVA]Final Cycle Loading %Contribution [MW]
243334 05MAGLEY 138.0 - 246250 05MAGLEY 69.0 CKT 1 AEP_P4_#7522_05ALLEN 138_J_SRT-A
CONTINGENCY 'AEP_P4_#7522_05ALLEN 138_J_SRT-A'
 OPEN BRANCH FROM BUS 243211 TO BUS 243242 CKT 2   /*05ALLEN      345.0 - 05ALLEN      138.0
 OPEN BRANCH FROM BUS 243242 TO BUS 243334 CKT 1   /*05ALLEN      138.0 - 05MAGLEY     138.0
END
93.0114.43 %8.5
243334 05MAGLEY 138.0 - 246250 05MAGLEY 69.0 CKT 1 AEP_P7-1_#11020___SRT-A
CONTINGENCY 'AEP_P7-1_#11020___SRT-A'
 OPEN BRANCH FROM BUS 243242 TO BUS 243334 CKT 1   /*05ALLEN      138.0 - 05MAGLEY     138.0
 OPEN BRANCH FROM BUS 243242 TO BUS 243391 CKT 1   /*05ALLEN      138.0 - 05WAYNET     138.0
 OPEN BRANCH FROM BUS 243309 TO BUS 243391 CKT 1   /*05HILLCR     138.0 - 05WAYNET     138.0
END
93.0113.04 %8.5
Transmission Owner Identified System Reinforcements
AF2-068 Transmission Owner Identified System Reinforcements Cost Breakdown:
TORTEP ID / TO IDCategoryTitleMW ImpactPercent AllocationAllocated Cost ($USD)Facilities Study
Grand Total:$0

System Reinforcement: n9286.0
TO
AEP
RTEP ID / TO ID
n9286.0 / n9286
Category
SubRegional
Title
Replace existing 138/69 kV TR1 transformer with a 130 MVA transformer.
Description
Replace existing 138/69 kV TR1 transformer with a 130 MVA transformer. This replacement is required due to a criteria violation not considered under the PJM studies. AEP performs a separate study that monitors non-PJM monitored (sub-transmission) utility equipment. Move the primary station service with the new transformer. Replace the TR1 transformer low side jumpers to reach the box bay structure.
Total Cost
$2,501,173
Note: Based on PJM cost allocation criteria, AF2-068 currently does not receive cost allocation towards this upgrade. As changes to the PJM queue process occur (such as prior queued projects withdrawing from the queue, reducing in size, etc.) AF2-068 could receive cost allocation. Although Queue Project AF2-068 may not presently have cost responsibility for this upgrade, Queue Project AF2-068 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AF2-068 comes into service prior to completion of the upgrade, Queue Project AF2-068 will need an interim study.

System Reinforcement: n9285.0
TO
AEP
RTEP ID / TO ID
n9285.0 / n9285
Category
SubRegional
Title
Remove Magley TR1 Transformer
Description
Remove the existing 138/69 kV TR1 transformer. Remove the existing dual 2000KCM Strain Bus Assembly on the 138 kV side.
Total Cost
$288,821
Note: Based on PJM cost allocation criteria, AF2-068 currently does not receive cost allocation towards this upgrade. As changes to the PJM queue process occur (such as prior queued projects withdrawing from the queue, reducing in size, etc.) AF2-068 could receive cost allocation. Although Queue Project AF2-068 may not presently have cost responsibility for this upgrade, Queue Project AF2-068 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AF2-068 comes into service prior to completion of the upgrade, Queue Project AF2-068 will need an interim study.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AF2-068 was evaluated as a 150.0 MW (90.0 MW Capacity) injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1OVEC
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
DEOK_P2-3_1403_MIAMI FORT_SRT-A
BreakerAC100.86 %971.0B979.389.19
GD1OVEC
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
DEOK_P2-3_1401_MIAMI FORT_SRT-A
BreakerAC100.35 %971.0B974.439.2

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1403_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.86 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:979.38
MW Contribution:9.19
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.59 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:976.75
MW Contribution:9.18
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.13882352941176470.118
961762AG1-017 E
Adder
0.63647058823529420.541
962031AG1-047 C
Adder
3.67647058823529443.125
962032AG1-047 E
Adder
2.45058823529411772.083
965651AG1-433 C
Adder
1.281.088
965652AG1-433 E
Adder
5.9905882352941175.092
24726405LAWG1A
50/50
6.86.8
24726505LAWG1B
50/50
6.86.8
24726605LAWG1S
50/50
10.86110.861
24726705LAWG2A
50/50
6.86.8
24726805LAWG2B
50/50
6.3116.311
24726905LAWG2S
50/50
10.86110.861
247543V3-007 C
50/50
0.4930.493
247929S-071 E
Adder
5.8552941176470594.977
247935V3-007 E
50/50
20.20920.209
24795805WLD G2 E
Adder
12.55764705882352810.674
24796305HDWTR1G E
50/50
20.20920.209
934962AD1-128 E
Adder
7.3717647058823536.266
936561AD2-071 C
Adder
4.7094117647058834.003
936562AD2-071 E
Adder
2.321.972
942081AE2-220 C
50/50
6.0976.097
942082AE2-220 E
50/50
8.428.42
944031AF1-071 C
Adder
0.47411764705882360.403
944032AF1-071 E
Adder
0.77411764705882360.658
958711AF2-162 C
Adder
2.18117647058823531.854
958712AF2-162 E
Adder
1.09058823529411760.927
960971AF2-388 C
Adder
2.55882352941176452.175
960972AF2-388 E
Adder
11.98117647058823510.184
24379505HDWTR1G C
50/50
0.4930.493
25194708EBND2
50/50
16.23816.238
932681AC2-090 C
50/50
0.720.72
932682AC2-090 E
50/50
7.2017.201
939761AE1-207 C
Adder
4.4658823529411763.796
939762AE1-207 E
Adder
6.1682352941176485.243
939771AE1-208 C
Adder
3.9588235294117653.365
939772AE1-208 E
Adder
5.3988235294117654.589
942071AE2-219 C
Adder
2.56941176470588272.184
942072AE2-219 E
Adder
3.5482352941176473.016
247968Z2-115 E
Adder
0.070588235294117650.06
926874AC1-174 E
50/50
7.2017.201
926881AC1-175 E
50/50
7.2017.201
270209AC1-174 C
50/50
0.7210.721
270210AC1-175 C
50/50
0.7210.721
270222AC2-111 C
Adder
2.1082352941176471.792
932844AC2-111 E
Adder
3.40588235294117642.895
933596AC2-176 E
Adder
6.9294117647058825.89
942221AE2-234 C
Adder
1.2988235294117651.104
942222AE2-234 E
Adder
0.58705882352941170.499
942791AE2-297 C O1
50/50
1.5831.583
942792AE2-297 E O1
50/50
6.6276.627
944531AF1-118 C
Adder
16.3613.906
944532AF1-118 E
Adder
4.9341176470588244.194
944541AF1-119 C
Adder
10.1788235294117648.652
944542AF1-119 E
Adder
4.36235294117647053.708
945371AF1-202 C
Adder
2.61411764705882372.222
945372AF1-202 E
Adder
12.76352941176470610.849
945581AF1-223 C
Adder
6.925.882
945582AF1-223 E
Adder
4.61294117647058853.921
946032AF1-268 E
Adder
2.04470588235294141.738
958861AF2-177 C
Adder
1.9470588235294121.655
958862AF2-177 E
Adder
13.03176470588235211.077
961171AF2-408 C
Adder
6.4976470588235295.523
939781AE1-209 C
Adder
1.21.02
939782AE1-209 E
Adder
8.0282352941176466.824
939791AE1-210 C
Adder
1.21.02
939792AE1-210 E
Adder
8.0282352941176466.824
946031AF1-268 C
Adder
4.5082352941176473.832
964611AG1-324 C
Adder
1.8117647058823531.54
964612AG1-324 E
Adder
0.72117647058823530.613
940981AE2-089 C
Adder
4.99529411764705964.246
940982AE2-089 E
Adder
3.33058823529411762.831
941691AE2-169 C
Adder
2.3752941176470592.019
941721AE2-172 C
Adder
2.65882352941176462.26
957741AF2-068 C
Adder
5.5141176470588244.687
957742AF2-068 E
Adder
3.67647058823529443.125
965461AG1-414 C
Adder
2.7552941176470592.342
965462AG1-414 E
Adder
1.8364705882352941.561
CBM West 1LTFEXP_CBM-W1->PJM
CBM
36.45236.452
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.19914.199
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.9220.922
NYPJM->LTFIMP_NY
CLTF
0.4740.474
LGEELTFEXP_LGEE->PJM
CLTF
0.6180.618
WECLTFEXP_WEC->PJM
CLTF
0.8430.843
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.2640.264
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1350.135
TVALTFEXP_TVA->PJM
CLTF
1.3261.326
MECLTFEXP_MEC->PJM
CLTF
3.7733.773
LAGNLTFEXP_LAGN->PJM
CLTF
2.092.09
SIGELTFEXP_SIGE->PJM
CLTF
0.320.32
O66PJM->LTFIMP_O-066
CMTX_NF
5.9075.907
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.3980.398

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1401_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.35 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:974.43
MW Contribution:9.2
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.08 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:971.74
MW Contribution:9.18
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.13882352941176470.118
961762AG1-017 E
Adder
0.63647058823529420.541
962031AG1-047 C
Adder
3.67764705882352953.126
962032AG1-047 E
Adder
2.45176470588235332.084
965651AG1-433 C
Adder
1.281.088
965652AG1-433 E
Adder
5.9929411764705885.094
24726405LAWG1A
50/50
6.8016.801
24726505LAWG1B
50/50
6.8016.801
24726605LAWG1S
50/50
10.86210.862
24726705LAWG2A
50/50
6.8016.801
24726805LAWG2B
50/50
6.3126.312
24726905LAWG2S
50/50
10.86210.862
247543V3-007 C
50/50
0.4940.494
247929S-071 E
Adder
5.8588235294117654.98
247935V3-007 E
50/50
20.21420.214
24795805WLD G2 E
Adder
12.56117647058823510.677
24796305HDWTR1G E
50/50
20.21420.214
934962AD1-128 E
Adder
7.37529411764705946.269
936561AD2-071 C
Adder
4.7105882352941174.004
936562AD2-071 E
Adder
2.321.972
942081AE2-220 C
50/50
6.0996.099
942082AE2-220 E
50/50
8.4228.422
944031AF1-071 C
Adder
0.475294117647058870.404
944032AF1-071 E
Adder
0.77411764705882360.658
958711AF2-162 C
Adder
2.1823529411764711.855
958712AF2-162 E
Adder
1.09058823529411760.927
960971AF2-388 C
Adder
2.562.176
960972AF2-388 E
Adder
11.98588235294117710.188
24379505HDWTR1G C
50/50
0.4940.494
25194708EBND2
50/50
16.24416.244
932681AC2-090 C
50/50
0.720.72
932682AC2-090 E
50/50
7.2037.203
939761AE1-207 C
Adder
4.46823529411764753.798
939762AE1-207 E
Adder
6.1694117647058825.244
939771AE1-208 C
Adder
3.96117647058823553.367
939772AE1-208 E
Adder
5.40117647058823554.591
942071AE2-219 C
Adder
2.5705882352941182.185
942072AE2-219 E
Adder
3.55058823529411743.018
247968Z2-115 E
Adder
0.070588235294117650.06
926874AC1-174 E
50/50
7.2037.203
926881AC1-175 E
50/50
7.2037.203
270209AC1-174 C
50/50
0.7210.721
270210AC1-175 C
50/50
0.7210.721
270222AC2-111 C
Adder
2.1105882352941181.794
932844AC2-111 E
Adder
3.4082352941176472.897
933596AC2-176 E
Adder
6.9329411764705885.893
942221AE2-234 C
Adder
1.31.105
942222AE2-234 E
Adder
0.58823529411764710.5
942791AE2-297 C O1
50/50
1.5831.583
942792AE2-297 E O1
50/50
6.6286.628
944531AF1-118 C
Adder
16.36705882352941213.912
944532AF1-118 E
Adder
4.9364705882352944.196
944541AF1-119 C
Adder
10.182352941176478.655
944542AF1-119 E
Adder
4.3635294117647063.709
945371AF1-202 C
Adder
2.61529411764705882.223
945372AF1-202 E
Adder
12.76823529411764610.853
945581AF1-223 C
Adder
6.9223529411764715.884
945582AF1-223 E
Adder
4.6152941176470593.923
946032AF1-268 E
Adder
2.04588235294117651.739
958861AF2-177 C
Adder
1.9482352941176471.656
958862AF2-177 E
Adder
13.03647058823529511.081
961171AF2-408 C
Adder
6.4976470588235295.523
939781AE1-209 C
Adder
1.21.02
939782AE1-209 E
Adder
8.0305882352941186.826
939791AE1-210 C
Adder
1.21.02
939792AE1-210 E
Adder
8.0305882352941186.826
946031AF1-268 C
Adder
4.5105882352941183.834
964611AG1-324 C
Adder
1.8117647058823531.54
964612AG1-324 E
Adder
0.72117647058823530.613
940981AE2-089 C
Adder
4.9988235294117644.249
940982AE2-089 E
Adder
3.33294117647058872.833
941691AE2-169 C
Adder
2.3764705882352942.02
941721AE2-172 C
Adder
2.662.261
957741AF2-068 C
Adder
5.517647058823534.69
957742AF2-068 E
Adder
3.67764705882352953.126
965461AG1-414 C
Adder
2.7552941176470592.342
965462AG1-414 E
Adder
1.83764705882352961.562
CBM West 1LTFEXP_CBM-W1->PJM
CBM
36.49436.494
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.20814.208
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.9180.918
NYPJM->LTFIMP_NY
CLTF
0.4720.472
LGEELTFEXP_LGEE->PJM
CLTF
0.6160.616
WECLTFEXP_WEC->PJM
CLTF
0.8440.844
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.2620.262
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1340.134
TVALTFEXP_TVA->PJM
CLTF
1.3281.328
MECLTFEXP_MEC->PJM
CLTF
3.7763.776
LAGNLTFEXP_LAGN->PJM
CLTF
2.0932.093
SIGELTFEXP_SIGE->PJM
CLTF
0.320.32
O66PJM->LTFIMP_O-066
CMTX_NF
5.8835.883
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.3960.396
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7   /*08M.FORT     345.0 - 08M.FRT7      22.0
END
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9   /*08M.FORT     345.0 - 08M.FORT     138.0
END
248001 to 248013 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
AEP_P1-2_#8702_2543_SRT-A-C
OPAC111.57 %897.0B1000.7916.26

Details for AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line l/o AEP_P1-2_#8702_2543_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:111.57 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1000.79
MW Contribution:16.26
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:112.91 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1012.81
MW Contribution:16.31
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
50/50
0.2450.245
961762AG1-017 E
50/50
1.1251.125
962031AG1-047 C
50/50
6.5036.503
962032AG1-047 E
50/50
4.3364.336
965651AG1-433 C
50/50
8.2918.291
965652AG1-433 E
50/50
38.81938.819
24699105WLD G1 C
50/50
0.2420.242
24725505WLD G2 C
50/50
0.2350.235
24728505AND G1
50/50
0.5880.588
24728605AND G2
50/50
0.5880.588
24728705AND G3
50/50
1.231.23
24728805RICHG1
50/50
0.6040.604
24728905RICHG2
50/50
0.6040.604
24753605BLUFF P WF
50/50
0.4130.413
247543V3-007 C
50/50
0.9250.925
247929S-071 E
50/50
10.110.1
247935V3-007 E
50/50
37.89937.899
24795805WLD G2 E
50/50
19.56819.568
24796305HDWTR1G E
50/50
37.89937.899
934961AD1-128 C
50/50
1.4761.476
934962AD1-128 E
50/50
15.74415.744
936561AD2-071 C
50/50
7.2167.216
936562AD2-071 E
50/50
3.5543.554
942081AE2-220 C
50/50
11.43511.435
942082AE2-220 E
50/50
15.79115.791
944031AF1-071 C
Adder
0.64588235294117660.549
944032AF1-071 E
Adder
1.05411764705882360.896
958711AF2-162 C
50/50
14.13314.133
958712AF2-162 E
50/50
7.0677.067
960971AF2-388 C
50/50
16.58316.583
960972AF2-388 E
50/50
77.63877.638
24341505WWVSTA
50/50
1.6751.675
24379505HDWTR1G C
50/50
0.9250.925
932681AC2-090 C
50/50
1.3511.351
932682AC2-090 E
50/50
13.50413.504
939761AE1-207 C
50/50
7.9447.944
939762AE1-207 E
50/50
10.9710.97
939771AE1-208 C
50/50
6.3866.386
939772AE1-208 E
50/50
8.7088.708
942071AE2-219 C
50/50
4.4324.432
942072AE2-219 E
50/50
6.1216.121
926874AC1-174 E
50/50
13.50413.504
926881AC1-175 E
50/50
13.50413.504
270201AC2-176 GEN
50/50
0.2990.299
270209AC1-174 C
50/50
1.3531.353
270210AC1-175 C
50/50
1.3531.353
270222AC2-111 C
Adder
2.86941176470588262.439
932844AC2-111 E
Adder
4.6352941176470593.94
933596AC2-176 E
50/50
12.25912.259
942791AE2-297 C O1
50/50
1.8541.854
942792AE2-297 E O1
50/50
7.767.76
944531AF1-118 C
50/50
65.88465.884
944532AF1-118 E
50/50
19.87119.871
944541AF1-119 C
50/50
65.95565.955
944542AF1-119 E
50/50
28.26628.266
945371AF1-202 C
50/50
14.37414.374
945372AF1-202 E
50/50
70.17970.179
945581AF1-223 C
50/50
38.04938.049
945582AF1-223 E
50/50
25.36625.366
946032AF1-268 E
50/50
4.5994.599
958861AF2-177 C
50/50
6.3726.372
958862AF2-177 E
50/50
42.64542.645
961171AF2-408 C
50/50
11.20711.207
24336205RANDOLPH1
50/50
0.0690.069
939781AE1-209 C
50/50
3.1873.187
939782AE1-209 E
50/50
21.3321.33
939791AE1-210 C
50/50
3.1873.187
939792AE1-210 E
50/50
21.3321.33
946031AF1-268 C
50/50
10.13810.138
964611AG1-324 C
50/50
3.4223.422
964612AG1-324 E
50/50
1.3621.362
941691AE2-169 C
50/50
3.8323.832
941721AE2-172 C
50/50
4.7294.729
957741AF2-068 C
50/50
9.7559.755
957742AF2-068 E
50/50
6.5036.503
965461AG1-414 C
Adder
4.2541176470588233.616
965462AG1-414 E
Adder
2.8364705882352942.411
955152J993 G
External Queue
18.25959396362304718.259593963623047
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.73313.733
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
10.80710.807
G-007ALTFEXP_G-007A->PJM
CMTX
0.1370.137
VTFLTFEXP_VFT->PJM
CMTX
0.3560.356
NYPJM->LTFIMP_NY
CLTF
0.0070.007
LGEELTFEXP_LGEE->PJM
CLTF
2.4272.427
CPLELTFEXP_CPLE->PJM
CLTF
0.8360.836
TVALTFEXP_TVA->PJM
CLTF
2.5252.525
LAGNLTFEXP_LAGN->PJM
CLTF
2.5582.558
SIGELTFEXP_SIGE->PJM
CLTF
0.4430.443
MDUPJM->LTFIMP_MDU
CLTF
0.0440.044
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.4110.411
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
944540 to 243225 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AF2-068 was evaluated as a 150.0 MW injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 60 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 60 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 60 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 60 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 60 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 125 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 60 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 60 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-068 meet the 0.95 leading and lagging PF requirement.

 

AF2-068 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement upon request.

 

The AG1-047 unit tripped by undervoltage relay for one contingency (P5.01). The P5.01 contingency involved a single-phase fault at 80% of line from Jay (AF2-068/AG1-017/AG1-047 POI) 138 kV on AG1-324 POI circuit with delayed (Zone 2) clearing in 60 cycles. As per NERC Standard PRC-024 requirements, the contingency was found to meet the corresponding NERC PRC-024 LVRT criteria. We solved the tripping by updating the relay instance 96203408 from 0.3 second to 1.01 seconds. Additionally, this tripping event was observed in the pre-project study and therefore is not attributed to AF2-068.

 

For P1.06 contingency AE2-318, AE2-318, AD2-163, AD2-163, AC2-195, AC1-102, AC1-074 and 08HLCRT unit have been tripped for over voltage relay settings where clearing time was 0 second for all those relay settings. Added one cycle to original pick up to prevent fictious post-fault overvoltage tripping. It should be noted that generic dynamic models for inverter-based generators tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception or clearing. These spikes can be ignored in most cases as they do not represent the performance of the actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.

 

The IPCMD and IQCMD states in the REGCAU model of AF2-068 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The CSCR results are summarized in Table 3 through Table 8 and revealed a minimum and maximum CSCR values of 1.99 for P4.32 and 4.14 for P1.02, respectively. 57 contingencies out of 125 contingencies have values less than 3. The lowest value is 1.99 for contingencies P1.12, P1.13, P4.24, P4.25, P4.32 and P5.05.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 60 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

60

AF2-068

Solar

AEP

150

150

90

Jay 138 kV

 

 

Reactive Power Analysis

The reactive power capability of AF2-068 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AC1-174Losantville 345kVIn Service
AC1-175Losantville 345kVIn Service
AC2-090Losantville 345kVIn Service
AC2-111College Corner 138kVEngineering & Procurement
AC2-176Jay 138 kVIn Service
AD1-128Modoc-Delaware 138 kVIn Service
AD2-071Strawton-Deer Creek 138 kVSuspended
AE1-207Mississinewa-Gaston 138 kVSuspended
AE1-208Delaware-Van Buren 138 kVSuspended
AE1-209Desoto 345 kVSuspended
AE1-210Desoto 345 kVSuspended
AE2-089Pennville-Adams 138 kVSuspended
AE2-169Delaware-Van Buren 138 kVSuspended
AE2-172Mississinewa-Gaston 138 kVSuspended
AE2-219Bluff Point-Randolph 138 kVSuspended
AE2-220Losantville 345 kVEngineering & Procurement
AE2-234Liberty Center-Buckeye Tap 69 kVEngineering & Procurement
AE2-297Madison-Tanners Creek 138 kVIn Service
AF1-071College Corner 138 kVEngineering & Procurement
AF1-118Sorenson-Desoto 345 kVWithdrawn
AF1-119Keystone-Desoto 345 kVEngineering & Procurement
AF1-202Keystone-Desoto 345 kVUnder Construction
AF1-223Keystone-Desoto 345 kVUnder Construction
AF1-268Desoto-Jay 138 kVEngineering & Procurement
AF2-162Keystone-Desoto 345 kVEngineering & Procurement
AF2-177Sorenson-DeSoto #2 345 kVEngineering & Procurement
AF2-388Keystone-Desoto 345 kVEngineering & Procurement
AF2-408Fall Creek 138 kVEngineering & Procurement
AG1-017Jay 138 kVIn Service
AG1-047Jay 138 kVEngineering & Procurement
AG1-324Jay-Desoto 138 kVEngineering & Procurement
AG1-414Mississinewa 138 kVEngineering & Procurement
AG1-433Keystone-DeSoto 345 kVEngineering & Procurement
V3-007Desoto-Tanners Creek #1 345kVIn Service
Z2-115Deer Creek 12.47kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In coordination with other Affected System Operators, PJM has determined that the Affected System Operator for this project that requires an Affected System Study. For the latest Affected System Study results pertaining this project, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM lists any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Final System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9680.0
Type
Load Flow
TO
OVEC
RTEP ID / TO ID
n9680.0 / OVEC0001a
Title
Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F
Description
•Remove and replace sixteen (16) existing double circuit towers with taller double circuit custom steel poles. (Towers 11, 14, 45, 47, 52, 57, 59, 61, 63, 66, 67, 71, 77, 84, 91, and 96) •Remove and replace two (2) existing river crossing lattice towers with taller lattice structures. (Towers 2 and 140)
Total Cost ($USD)
$24,006,000
Discounted Total Cost ($USD)
$24,006,000
Allocated Cost ($USD)
$0
Time Estimate
38 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-068 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-068 could receive cost allocation. Although AF2-068 may not presently have cost responsibility for this upgrade, AF2-068 is a potential Aggregate Pool Contributor.

FacilityContingency
06DEARB1-06PIERCE 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)B1165.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-068


AF2-068 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AF2-068 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AF2-068 One Line Diagram

AF2-068 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.