AF2-080 Final System Impact Study (Retool 1) Report
v1.00 released 2025-12-08 18:18
Chinquapin-Everetts 230 kV
48.5 MW Capacity / 70.0 MW Energy
Introduction
This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Pitt Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).
Preface
The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:
- Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
- Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
- Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:
In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:
- PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
- The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):
If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:
- PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
- The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.
General
The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Pitt County, North Carolina. This project is an increase to the developer’s AC1-189 project(s), which will share the same Point of Interconnection. The AF2-080 project is a 70.0 MW uprate (48.5 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 150.0 MW with 101.9 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
A Physical Interconnection Facilities Study is not required for this project.
Point of Interconnection
AF2-080 will interconnect with the Dominion on transmission system as an uprate to AC1-189 which is tapping the Chinquapin to Everetts 230 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).
Based on the Final SIS results, the AF2-080 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AF2-080 | Cost Subject to Security* | |
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 | |
| Other Scope | $0 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | |
| Network Upgrades | $0 | $0 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $35,148,396 | $35,148,396 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violatons | $0 | $0 | |
| AFS - Non-PJM Violations | $3,726,000 | $0 | |
| Total | $38,874,396 | $35,148,396 | |
* Contributes to calculation for Security. See Security Section of this report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Security Requirement
Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).
Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.
Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Security Due for AC1-189/AF2-080
Security has been calculated for the AC1-189/AF2-080 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.
Security Due for AC1-189/AF2-080
In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.
Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.
If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.
Transmission Owner Scope of Work
No TO Interconnection Facilities or Physical Network Upgrades are required for this project.
AF2-080 is sharing the POI and Transmission Owner Interconnection Facilities with AC1-189, there are no associated interconnection costs for this project. Should AC1-189 withdraw the Interconnection Request, AF2-080 will assume the Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and applicable Network Upgrade costs identified in the AC1-189 study report for connection to the Dominion system.
Transmission Owner Analysis
PJM performed a power flow analysis of the transmission system using a 2027 load flow model and the results were verified by Dominion.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AF2-080 was evaluated as a 70.0 MW (48.5 MW Capacity) injection in the Dominion area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | CPLE/DVP | 3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line | DVP_P7-1: LN 2058-2181_SRT-A | Tower | AC | 119.41 % | 313.0 | B | 373.75 | 7.9 | |
| GD1 | DVP | 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | Breaker | AC | 110.49 % | 1204.0 | C | 1330.34 | 6.0 | |
| GD1 | DVP | 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | Breaker | AC | 108.7 % | 1204.0 | C | 1308.78 | 6.0 | |
| GD1 | DVP | 6CHESTF B-6BASIN 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | Breaker | AC | 142.63 % | 812.0 | C | 1158.14 | 4.21 | |
| GD1 | DVP | 6CHESTF B-6BASIN 230.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | Single | AC | 133.85 % | 663.64 | B | 888.27 | 2.8 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | DVP_P4-2: 246T247_SRT-A | Breaker | AC | 112.58 % | 830.0 | C | 934.43 | 12.95 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | DVP_P4-2: 24642_SRT-A | Breaker | AC | 107.8 % | 830.0 | C | 894.71 | 12.53 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | DVP_P4-2: 24662_SRT-A | Breaker | AC | 107.79 % | 830.0 | C | 894.66 | 12.49 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | DVP_P1-2: LN 556_SRT-S-3 | Single | AC | 100.22 % | 678.68 | B | 680.18 | 6.86 | |
| GD1 | DVP | 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line | DVP_P1-2: LN 2092_SRT-A | Single | AC | 118.32 % | 571.52 | B | 676.24 | 10.44 | |
| GD1 | DVP | 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line | DVP_P1-2: LN 2131_SRT-A | Single | AC | 116.14 % | 571.52 | B | 663.74 | 10.45 | |
| GD1 | DVP | 6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line | DVP_P4-2: 246T247_SRT-A | Breaker | AC | 119.67 % | 699.0 | C | 836.51 | 9.45 | |
| GD1 | DVP | 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line | DVP_P1-2: LN 2092_SRT-A | Single | AC | 113.42 % | 571.52 | B | 648.23 | 10.44 | |
| GD1 | DVP | 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line | DVP_P1-2: LN 2131_SRT-A | Single | AC | 111.23 % | 571.52 | B | 635.73 | 10.45 | |
| GD1 | DVP | 6POE-6TYLER1 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | Breaker | AC | 104.13 % | 541.0 | C | 563.34 | 3.54 | |
| GD1 | DVP | 6SAPONY-6CARSON 230.0 kV Ckt 1 line | DVP_P4-2: 246T247_SRT-A | Breaker | AC | 123.57 % | 830.0 | C | 1025.65 | 12.95 | |
| GD1 | DVP | 6SAPONY-6CARSON 230.0 kV Ckt 1 line | DVP_P1-2: LN 556_SRT-S-3 | Single | AC | 112.21 % | 678.68 | B | 761.57 | 6.85 | |
| GD1 | DVP | 6SAPONY-6CARSON 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | Single | AC | 111.1 % | 678.68 | B | 753.98 | 8.65 | |
| GD1 | DVP | 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | DVP_P4-2: 557T574_SRT-S | Breaker | AC | 106.16 % | 3940.0 | C | 4182.74 | 15.76 | |
| GD1 | DVP | 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | DVP_P7-1: ELMONT-LADYSMITH_500_230_SRT-A | Tower | AC | 104.22 % | 3940.0 | C | 4106.12 | 14.88 | |
| GD1 | DVP | 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | DVP_P4-2: H1T567_SRT-A | Breaker | AC | 103.44 % | 3940.0 | C | 4075.55 | 15.7 | |
| GD1 | DVP | 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-A | Single | AC | 100.39 % | 1058.16 | B | 1062.25 | 3.33 | |
| GD1 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P1-2: LN 574_SRT-S_SENS | Single | AC | 102.07 % | 3220.44 | B | 3287.01 | 10.36 | |
| GD1 | DVP | 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line | DVP_P4-2: 56372_SRT-S | Breaker | AC | 102.59 % | 3144.0 | C | 3225.32 | 12.79 | |
| GD1 | DVP | 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A | Breaker | AC | 102.48 % | 3144.0 | C | 3221.97 | 13.14 | |
| GD1 | DVP | 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S | Breaker | AC | 102.48 % | 3144.0 | C | 3221.97 | 13.14 | |
| GD1 | DVP | 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line | DVP_P4-2: 563T576_SRT-S | Breaker | AC | 102.48 % | 3144.0 | C | 3221.81 | 13.14 | |
| GD1 | DVP | AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line | DVP_P4-2: 246T247_SRT-A | Breaker | AC | 123.02 % | 830.0 | C | 1021.04 | 12.95 | |
| GD1 | DVP | AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line | DVP_P1-2: LN 556_SRT-S-3 | Single | AC | 109.42 % | 678.68 | B | 742.63 | 6.86 | |
| GD1 | DVP | AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | Single | AC | 108.28 % | 678.68 | B | 734.84 | 8.66 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | DVP | 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | Single | AC | 100.89 % | 984.18 | B | 992.94 | 3.77 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | Single | AC | 108.46 % | 678.68 | B | 736.13 | 8.7 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | DVP_P1-2: LN 570_SRT-A | Single | AC | 104.8 % | 678.68 | B | 711.27 | 7.28 | |
| GD1 | DVP | 6SAPONY-6CARSON 230.0 kV Ckt 1 line | Base Case | Single | AC | 102.72 % | 678.68 | A | 697.11 | 6.82 | |
| GD1 | DVP | 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | DVP_P4-2: H2T574_SRT-S | Breaker | AC | 113.38 % | 3940.0 | C | 4467.2 | 14.76 | |
| GD1 | DVP | 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | DVP_P1-2: LN 574_SRT-S | Single | AC | 103.8 % | 3220.44 | B | 3342.68 | 10.17 | |
| GD1 | DVP | 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-A | Single | AC | 111.92 % | 4070.2 | B | 4555.56 | 11.93 | |
| GD1 | DVP | 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | Single | AC | 101.04 % | 4070.2 | B | 4112.5 | 10.12 | |
| GD1 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P1-2: LN 574_SRT-S | Single | AC | 119.82 % | 3220.44 | B | 3858.59 | 11.03 | |
| GD1 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | Single | AC | 111.38 % | 3220.44 | B | 3586.78 | 5.65 | |
| GD1 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-A | Single | AC | 111.09 % | 3220.44 | B | 3577.61 | 5.97 | |
| GD1 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: SPOTS H1T594_SRT-S | Breaker | AC | 110.41 % | 3940.0 | C | 4350.17 | 8.55 | |
| GD1 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: H1T594_SRT-S | Breaker | AC | 106.75 % | 3940.0 | C | 4205.81 | 8.17 | |
| GD1 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P1-2: LN 575_SRT-S | Single | AC | 116.97 % | 3220.44 | B | 3767.03 | 6.76 | |
| GD1 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P1-2: LN 581_SRT-S | Single | AC | 114.22 % | 3220.44 | B | 3678.49 | 7.81 | |
| GD1 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P1-2: LN 575_SRT-S | Single | AC | 121.18 % | 3220.44 | B | 3902.62 | 6.57 | |
| GD1 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P1-2: LN 552_SRT-S | Single | AC | 120.07 % | 3220.44 | B | 3866.79 | 7.65 |
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | DVP | 6CHARCTY-6LAKESIDE 230.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | OP | AC | 100.11 % | 984.18 | B | 985.29 | 3.9 | |
| GD1 | DVP | 6CHESTF B-6VARINA 230.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | OP | AC | 103.74 % | 984.18 | B | 1020.96 | 3.9 | |
| GD1 | DVP | 6CHOWAN-6PEMBROKE 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | OP | AC | 102.05 % | 733.2 | B | 748.25 | 11.05 | |
| GD1 | DVP | 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | Base Case | OP | AC | 109.02 % | 678.68 | A | 739.92 | 9.82 | |
| GD1 | DVP | 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line | DVP_P1-2: LN 2092_SRT-A | OP | AC | 166.69 % | 571.52 | B | 952.64 | 15.07 | |
| GD1 | DVP | 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line | Base Case | OP | AC | 111.43 % | 571.52 | A | 636.85 | 11.79 | |
| GD1 | CPLE/DVP | 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line | RKYMT-WILS230_&_RKYMT-SHARPB115_SRT-S | OP | AC | 106.07 % | 478.0 | B | 507.02 | 18.6 | |
| GD1 | DVP | 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | OP | AC | 102.75 % | 733.2 | B | 753.4 | 11.05 | |
| GD1 | DVP | 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line | DVP_P1-2: LN 2092_SRT-A | OP | AC | 161.64 % | 571.52 | B | 923.83 | 15.07 | |
| GD1 | DVP | 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line | Base Case | OP | AC | 106.53 % | 571.52 | A | 608.85 | 11.79 | |
| GD1 | DVP | 6PEMBROKE-6WALBMRL 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | OP | AC | 118.52 % | 733.2 | B | 868.96 | 11.04 | |
| GD1 | DVP | 6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | OP | AC | 116.77 % | 733.2 | B | 856.13 | 11.04 | |
| GD1 | DVP | 6SAPONY-6CARSON 230.0 kV Ckt 1 line | Base Case | OP | AC | 127.47 % | 678.68 | A | 865.08 | 9.81 | |
| GD1 | DVP | 6VARINA-6CHARCTY 230.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | OP | AC | 103.68 % | 984.18 | B | 1020.42 | 3.9 | |
| GD1 | DVP | 6WALBMRL-6S HERTFORD 230.0 kV Ckt 1 line | DVP_P1-2: LN 246_SRT-A | OP | AC | 117.19 % | 733.2 | B | 859.24 | 11.04 | |
| GD1 | DVP | 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | Base Case | OP | AC | 104.12 % | 3220.44 | A | 3352.99 | 12.44 | |
| GD1 | DVP | 8CHCKAHM-8ELMONT 500.0 kV Ckt 1 line | DVP_P1-2: LN 2083_SRT-S | OP | AC | 104.87 % | 2442.12 | B | 2561.02 | 11.12 | |
| GD1 | DVP | 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-A | OP | AC | 126.88 % | 1058.16 | B | 1342.55 | 4.8 | |
| GD1 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | AEP_P1-2_242515_248184_SRT-A | OP | AC | 101.34 % | 3220.44 | B | 3263.62 | 8.4 | |
| GD1 | DVP | 8SEPTA-8SURRY 500.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S-1 | OP | AC | 106.42 % | 2442.12 | B | 2598.93 | 8.57 | |
| GD1 | DVP | AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line | Base Case | OP | AC | 124.4 % | 678.68 | A | 844.26 | 9.82 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | DVP | 8CHCKAHM-8ELMONT 500.0 kV Ckt 1 line | Base Case | OP | AC | 104.11 % | 2442.12 | A | 2542.46 | 10.79 |
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Light Load Analysis
The New Service Request AF2-080 was evaluated as a 70.0 MW injection in the Dominion area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
(No impacts were found for this analysis)
Light Load Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
(No impacts were found for this analysis)
Short Circuit Analysis
Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Stability Analysis
Analysis Complete - No Issues
|
|
|
|
|
|
| |
- Steady-state operation (30 seconds)
- Three-phase faults with normal clearing time
- Single-phase bus faults with normal clearing time
- Single-phase faults with stuck breaker
- Single-phase faults with delayed clearing at remote end
- Three-phase faults with loss of multiple-circuit tower line.
The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the RTEP 2027 summer peak case:
- Cluster 39 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
- The system with Cluster 39 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
- Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
- P1 Category Contingencies:
- 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.01 to 1.096 p.u. for 500 kV facilities
- P2, P4, P5, and P7 Category Contingencies:
- 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.00 to 1.096 p.u. for 500 kV facilities
- No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
Oscillations were observed at the Gaston units for contingencies P4.43, P4.48, P4.52, P4.57, and P4.58. These oscillations did not met Dominion’s 4% damping criteria for local area and were observed to be pre-existing but was exacerbated by dispatched generation at Thelma. The damping angle with changes to the generation dispatched at Thelma. The results indicate that reducing generation in the surrounding area leads to improved damping performance at Gaston and it is concluded that the oscillations at Gaston were not caused by the TC1 Cluster 39 projects.
The Transmission Owner has elected to upgrade the Hathaway 115 kV substation by splitting the existing 115 kV bus into two separate buses with a 115 kV line on each bus and the tie switch between line 55 and 80 was closed. Additionally, Line #1001 was opened at Battleboro, resulting in it becoming a radial line from Chestnut Substation. Contingency definitions at the Hathaway 115 kV substation were updated based on topology change, and the analysis was performed. Oscillations at Gaston continue to persist and were unaffected by the topology changes. No other violations occurred.
AF2-080 queue project did not meet the 0.95 lagging power factor measured at high side of the main transformer. When the facility was tested at its maximum lagging reactive capability, voltages above 1.10 p.u. were observed at the inverter terminal. To ensure that the facility can provide its lagging power factor without high voltages at the inverter terminal, it is recommended that the tap on the high side of the main transformer be adjusted from 1.0 to 1.025. An additional 5.42 Mvar is required to meet the 0.95 lagging power factor. The AF2-080 queue project met the 0.95 leading power factor measured at high side of the main transformer.
AG1-106 is an uprate of AB1-132 and AC1-086. The measurement point for the power factor requirements per the Interconnection Service Agreement (ISA) is at the generator terminals for AB1-132 and AC1-086. AG1-106’s power factor requirements is measured at the high side of the station transformer. Due to this three power factor assessments were included to bound the lagging deficiencies observed. The following lagging deficiencies were observed for AG1-106 depending on the measurement’s points enforced for each test.
- With AG1-106 online, and AB1-132 and AC1-086 offline to ensure the losses created by the AB1-132 and AC1-086 generators are not counted against AG1-106. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer.
- With AG1-106 and AB1-132 online, AC1-086 offline to consider the shared high side of main station transformer. AB1-132’s measurement point in the ISA is not enforced in this test. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer. However, voltage violation were observed at the generator terminals with the voltage of 1.196 p.u. at AB1-132 and 1.147 p.u. at AG1-106.
- AG1-106, AB1-132, and AC1-086 online to consider the shared high side of main station transformer. AB1-132 and AC1-086 measurement point in the ISA are not enforced in this test. The lagging power factor deficiency is 49.38 Mvar.
No mitigation was required.
Reactive Power Analysis
The reactive power capability of AF2-080 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-063A | Carolina–Seaboard 115kV | In Service |
| AA1-065 | Earleys 230kV | In Service |
| AA1-067 | Everetts 34.5kV | In Service |
| AA1-139 | Hickory-Shawboro 230kV | In Service |
| AA2-053 | Carolina-Jackson 115kV | In Service |
| AA2-057 | Hornertown-Whitakers 115kV | In Service |
| AA2-088 | Boykins-Handsome 115kV | In Service |
| AA2-178 | Mackeys 230kV | In Service |
| AB1-081 | Anaconda-Mayo Dunbar 115kV | In Service |
| AB1-132 | Thelma 230kV | In Service |
| AB1-173 | Brink-Trego 115kV | In Service |
| AB2-022 | Elizabeth City 34.5kV | In Service |
| AB2-025 | Sapony 34.5kV | In Service |
| AB2-026 | Powhatan 34.5kV | In Service |
| AB2-040 | Brink 115kV | In Service |
| AB2-043 | Chase City 115kV | In Service |
| AB2-059 | Benson-Dunbar 115kV | In Service |
| AB2-060 | Chase City-Lunenburg 115kV | In Service |
| AB2-077 | Buggs Island-Chase City 115kV | In Service |
| AB2-078 | Buggs Island-Chase City 115kV | In Service |
| AB2-079 | Buggs Island-Chase City 115kV | In Service |
| AB2-099 | Ahoskie 34.5kV | In Service |
| AB2-100 | Clubhouse-Lakeview 230kV | In Service |
| AB2-134 | Hopewell-Surry 230kV | In Service |
| AB2-161 | Waverly #2 DP 115kV | In Service |
| AB2-169 | Pantago-Five Points 115kV | In Service |
| AB2-174 | Emporia-Trego 115kV | In Service |
| AB2-190 | Hopewell-Surry 230kV | In Service |
| AC1-027 | Pendleton 34.5kV | In Service |
| AC1-034 | Heartsease DP - Mayo Dunbar 115kV | Suspended |
| AC1-036 | Twittys Creek 34.5kV | In Service |
| AC1-054 | Kerr Dam–Eatons Ferry 115 kV | In Service |
| AC1-075 | Perth-Hickory Grove 115kV | In Service |
| AC1-080 | Perth-Hickory Grove 115kV | In Service |
| AC1-086 | Thelma 230kV | Suspended |
| AC1-098 | Dawson-South Justice 115kV | Partially in Service - Under Construction |
| AC1-099 | Dawson-South Justice 115kV | Partially in Service - Under Construction |
| AC1-105 | Halifax-Mt. Laurel 115kV | In Service |
| AC1-147 | Grassfield 34.5kV | In Service |
| AC1-161 | Septa 500kV | In Service |
| AC1-164 | Chickahominy 230kV | Partially in Service - Under Construction |
| AC1-189 | Chinquapin-Everetts 230kV | Under Construction |
| AC1-208 | Cox-Whitakers 115kV | Under Construction |
| AC1-216 | Hopewell-Surry 230kV | In Service |
| AC1-221 | Halifax-Person 230kV | In Service |
| AC1-222 | Crystal Hill-Halifax 115kV | In Service |
| AC2-012 | Grassfield-Great Bridge 115kV | In Service |
| AC2-079 | Ivor-Oak Ridge 115kV | Suspended |
| AC2-084 | Dawson-South Justice 115kV | Partially in Service - Under Construction |
| AC2-100 | Halifax-Person 230kV | In Service |
| AC2-141 | Septa 500kV | Engineering & Procurement |
| AC2-165 | Bremo-Powhatan 230kV | Suspended |
| AD1-022 | Cashie-Trowbridge 230 kV | Engineering & Procurement |
| AD1-025 | Hopewell-Surry 230 kV | Partially in Service - Under Construction |
| AD1-033 | Fentress-Landstown 230 kV | In Service |
| AD1-056 | Hornertown-Hathaway 230 kV | Suspended |
| AD1-057 | Hornertown-Hathaway 230 kV | Suspended |
| AD1-074 | Trowbridge 230 kV | Engineering & Procurement |
| AD1-075 | Trowbridge 230 kV | Engineering & Procurement |
| AD1-076 | Trowbridge 230 kV | Engineering & Procurement |
| AD1-082 | Bakers Pond-Ivor 115kV | In Service |
| AD1-087 | Clover-Sedge Hill 230 kV | In Service |
| AD1-088 | Briery-Clover 230 kV | Suspended |
| AD1-144 | Kings Fork 34.5 kV | In Service |
| AD1-151 | Hopewell-Surry 230 kV | Suspended |
| AD1-152 | Clover-Sedge Hill 230 kV | In Service |
| AD2-022 | East Danville - Roxborough 230 kV | Engineering & Procurement |
| AD2-023 | East Danville - Roxborough 230 kV | Engineering & Procurement |
| AD2-033 | Chase City-Lunenburg 115 kV | Under Construction |
| AD2-074 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AD2-085 | Myrtle-Windsor DP 115kV | Engineering & Procurement |
| AD2-202 | Clover-Sedge Hill 230kV | In Service |
| AE1-072 | Shawboro-Sligo 230 kV | Under Construction |
| AE1-074 | Winterpock 34.5 kV | Under Construction |
| AE1-075 | Powhatan 34.5 kV | In Service |
| AE1-103 | Holland-Union Camp 115 kV | Suspended |
| AE1-108 | Bremo-Scottsville 138 kV | Engineering & Procurement |
| AE1-149 | Disputanta-Poe 115 kV | Suspended |
| AE1-162 | Smithfield 34.5 kV | In Service |
| AE1-173 | Carson-Suffolk 500 kV | Under Construction |
| AE1-175 | Light Foot 34.5 kV | In Service |
| AE2-027 | Harrowgate-Locks 115kV | Under Construction |
| AE2-033 | Clubhouse-Sapony 230 kV | Suspended |
| AE2-034 | Mackeys 230 kV | Partially in Service - Under Construction |
| AE2-040 | Sapony 34.5 kV | Partially in Service - Under Construction |
| AE2-041 | Harmony Village 230 kV | Engineering & Procurement |
| AE2-051 | Carson-Septa 500 kV | Engineering & Procurement |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-094 | Carson-Rogers Road 500 kV | Engineering & Procurement |
| AE2-104 | Suffolk 115 kV | Suspended |
| AE2-156 | Yadkin 115 kV | Active |
| AE2-212 | Harrowgate 34 kV | Engineering & Procurement |
| AE2-247 | Myrtle-Windsor 115 kV | Engineering & Procurement |
| AE2-253 | Hickory-Moyock 230 kV | In Service |
| AE2-259 | Curdsville-Willis Mtn 115 kV | Engineering & Procurement |
| AE2-346 | Ahoskie 34.5 kV | In Service |
| AF1-017 | Myrtle-Windsor 115 kV | Engineering & Procurement |
| AF1-018 | Harmony Village 230 kV | Engineering & Procurement |
| AF1-032 | Suffolk 34.5 kV | In Service |
| AF1-042 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AF1-058 | Welco 34.5 kV | In Service |
| AF1-069 | Carson-Rogers Rd 500 kV | Engineering & Procurement |
| AF1-123 | Harper 230 kV | Active |
| AF1-124 | Harper 230 kV | Active |
| AF1-125 | Harper 230 kV | Active |
| AF1-128 | Chesterfield 230 kV | Active |
| AF1-129 | Chesterfield 230 kV | Engineering & Procurement |
| AF1-291 | Tyler 34.5 kV | Engineering & Procurement |
| AF1-292 | Fields 34.5kV | Engineering & Procurement |
| AF1-294 | Jetersville-Ponton 115 kV | Active |
| AF2-042 | Clover-Rawlings 500 kV | Active |
| AF2-043 | Suffolk 34.5 kV | In Service |
| AF2-054 | Wan 34.5 kV | In Service |
| AF2-077 | White Marsh 34.5 kV | In Service |
| AF2-081 | Moyock 230 kV | Active |
| AF2-085 | Midlothian 34.5 kV | In Service |
| AF2-110 | Suffolk 115 kV | Suspended |
| AF2-115 | Jetersville-Ponton 115 kV | Active |
| AF2-144 | Powhatan 34.5 kV | In Service |
| AF2-222 | Madisonville DP-Twitty's Creek 115 kV | Active |
| AF2-299 | Fields 34.5 kV | Active |
| AG1-007 | Tar River 12.5 kV | Engineering & Procurement |
| AG1-021 | Jetersville-Ponton 115 kV | Active |
| AG1-037 | Ahoskie 34.5 kV | Engineering & Procurement |
| AG1-038 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AG1-105 | Mount Laurel-Barnes Junction 115 kV | Active |
| AG1-106 | Thelma 230 kV | Active |
| AG1-145 | Lightfoot 34.5 kV | In Service |
| AG1-153 | Heritage 500 kV | Active |
| AG1-285 | Chase City-Central 115 kV | Active |
| AG1-342 | Dryburg 115 kV | Active |
| AG1-532 | Fields 34.5 kV | Engineering & Procurement |
| V4-068 | Murphy's 34.5kV | In Service |
| W1-029 | Winfall 230kV | In Service |
| Y1-086 | Morgans Corner | In Service |
| Z1-036 | WinFall-Chowan 230kV | In Service |
| Z1-068 | Birdneck 34.5kV | In Service |
| Z2-027 | Pasquotank 34.5kV | In Service |
| Z2-044 | Whitakers 34.5kV | In Service |
| Z2-088 | Tarboro-Everetts 230kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.
If your project required an Affected System Study, the results are shown below from the Affected System Operator.
For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.
| Impacted Facility | Transmission Owner | Reinforcement | Cost | Cost Allocated to AF2-080 | Scenarios |
|---|---|---|---|---|---|
| CPLE | Reconductor 4.73 miles with bundled 795 ACSS and replace substation components to get 3000A (City of Rocky Mount – Nash 230 kV) Reconductor 4.73 miles with bundled 795 ACSS and replace substation components to get 3000A (City of Rocky Mount – Nash 230 kV) | $14,033,000 | $3,559,000 | |
| CPLE | Replace transformer protection panel, uprate CT ratios, and revise relay settings Replace transformer protection panel, uprate CT ratios, and revise relay settings | $619,000 | $167,000 | |
| CPLE | Reconductor one side of Everetts to Greenville 230 kV Line. Upgrade the terminal equipment. Reconductor one side of Everetts to Greenville 230 kV Line. Upgrade the terminal equipment. | $150,000 | $0 |
|
| CPLE | Rebuild aging double circuit 230kV towers of Everetts to Greenville Line Rebuild aging double circuit 230kV towers of Everetts to Greenville Line | $19,000,000 | $0 |
|
System Reinforcements
Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n9252.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9252.0 / TC1-PH2-DOM-047
- Title
- Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor.
- Description
- Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro, specifically, between structures 2021/31 and 2021/62, with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor at 250 degrees C.
- Total Cost ($USD)
- $12,801,638
- Discounted Total Cost ($USD)
- $12,801,638
- Allocated Cost ($USD)
- $12,801,638
- Time Estimate
- 15 to 16 Months
Contributor
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF2-080 | 9.5 MW | 100.0% | $12,801,638 |
System Reinforcement: n6872
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n6872 / dom-047
- Title
- Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C.
- Description
- Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C
- Total Cost ($USD)
- $59,572,939
- Discounted Total Cost ($USD)
- $59,572,939
- Allocated Cost ($USD)
- $12,754,165
- Time Estimate
- Dec 31 2029
Contributor
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF2-042 | 24.3 MW | 40.2% | $23,940,647 |
| AF2-080 | 13.0 MW | 21.4% | $12,754,165 |
| AF2-222 | 7.6 MW | 12.5% | $7,438,616 |
| AG1-106 | 8.7 MW | 14.3% | $8,545,448 |
| AG1-285 | 7.0 MW | 11.6% | $6,894,063 |
System Reinforcement: n9200.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9200.0 / TC1-PH2-DOM-005
- Title
- Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductors.
- Description
- Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" @ 250C
- Total Cost ($USD)
- $38,691,326
- Discounted Total Cost ($USD)
- $38,691,326
- Allocated Cost ($USD)
- $8,110,757
- Time Estimate
- 45 to 46 Months
Contributor
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CARSON-6SAPONY 230.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF2-042 | 24.3 MW | 39.3% | $15,216,675 |
| AF2-080 | 12.9 MW | 21.0% | $8,110,757 |
| AF2-222 | 8.6 MW | 14.0% | $5,405,710 |
| AG1-106 | 8.7 MW | 14.0% | $5,435,780 |
| AG1-285 | 7.2 MW | 11.7% | $4,522,403 |
System Reinforcement: n9204.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9204.0 / TC1-PH2-DOM-014
- Title
- Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
- Description
- Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C
- Total Cost ($USD)
- $6,764,273
- Discounted Total Cost ($USD)
- $6,764,273
- Allocated Cost ($USD)
- $1,417,583
- Time Estimate
- 42 to 43 Months
Contributor
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6SAPONY-AE2-033 TP 230.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF2-042 | 24.3 MW | 39.3% | $2,660,923 |
| AF2-080 | 13.0 MW | 21.0% | $1,417,583 |
| AF2-222 | 8.6 MW | 14.0% | $945,201 |
| AG1-106 | 8.7 MW | 14.0% | $949,798 |
| AG1-285 | 7.2 MW | 11.7% | $790,769 |
System Reinforcement: n9201.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9201.0 / TC1-PH2-DOM-006
- Title
- Replace wave trap at Carson 230 kV (Carson - Sapony).
- Description
- Replace wave trap at Carson 230 kV (Carson - Sapony).
- Total Cost ($USD)
- $521,941
- Discounted Total Cost ($USD)
- $521,941
- Allocated Cost ($USD)
- $64,253
- Time Estimate
- 14 to 15 Months
Contributor
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CARSON-6SAPONY 230.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF2-042 | 24.3 MW | 43.6% | $227,742 |
| AF2-080 | 6.9 MW | 12.3% | $64,253 |
| AF2-222 | 8.6 MW | 15.5% | $80,905 |
| AG1-106 | 8.7 MW | 15.6% | $81,355 |
| AG1-285 | 7.2 MW | 13.0% | $67,685 |
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending)
- Title
- Dominion facility ratings: 379/390/449 MVA Winter | 372/384/441 MVA LL | 342/352/405 MVA Summer.
- Description
- Dominion facility ratings: 379/390/449 MVA Winter | 372/384/441 MVA LL | 342/352/405 MVA Summer.
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- TBD
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 3ROCKYMT115T-3BTLEBRO 115.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9112.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9112.0 / TC1-PH2-DOM-063
- Title
- Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield.
- Description
- Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield.
- Total Cost ($USD)
- $87,030,447
- Discounted Total Cost ($USD)
- $87,030,447
- Allocated Cost ($USD)
- $0
- Time Estimate
- 46 to 47 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BASIN-6CHESTF B 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9265.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9265.0 / TC1-PH2-DOM-064
- Title
- Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B).
- Description
- Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B).
- Total Cost ($USD)
- $396,021
- Discounted Total Cost ($USD)
- $396,021
- Allocated Cost ($USD)
- $0
- Time Estimate
- 14 to 15 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BASIN-6CHESTF B 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9681.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9681.0
- Title
- Upgrade 1.04 Miles of 230kV transmission line 249 from 249/86 to 249/93
- Description
- Reconductor 1.04 miles of 2*636 ACSR 24/7 MOT 150 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" MOT 250 on 230 kV line 249 between Carson and Chaparral
- Total Cost ($USD)
- $3,042,004
- Discounted Total Cost ($USD)
- $3,042,004
- Allocated Cost ($USD)
- $0
- Time Estimate
- 20 to 21 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3694.8
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3694.8
- Title
- Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1047 MVA.
- Description
- Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1047 MVA. Upgrade terminal equipment at Carson and Locks to not limit the new conductor rating.
- Cost Information
- Time Estimate
- May 03 2025
Not Contingent Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it is already in-service.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | (Any) |
| |||||||||||||
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: s3222.1
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- s3222.1
- Title
- Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA.
- Description
- Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA.
- Cost Information
- Time Estimate
- Dec 31 2028
Contingent Note: Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 may need this upgrade in-service to be deliverable to the PJM system. If AF2-080 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line | (Any) |
| |||||||||||||
| 6SUFFOLK-6NUCO TP 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9379.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9379.0 / TC1-PH3-DOM-011
- Title
- Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase transformers.
- Description
- Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase 500/230 kV transformers.
- Total Cost ($USD)
- $37,836,293
- Discounted Total Cost ($USD)
- $37,836,293
- Allocated Cost ($USD)
- $0
- Time Estimate
- Dec 31 2029
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | (Any) |
|
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
- Cost Information
- Time Estimate
- Jun 01 2029
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.346
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.346
- Title
- Cut-in 500kV line from Kraken substation into Yeat substation
- Description
- Cut-in 500kV line from Kraken substation into Yeat substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.326
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.326
- Title
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Description
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Cost Information
- Time Estimate
- Feb 24 2029
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.326
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.326
- Title
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Description
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Cost Information
- Time Estimate
- Feb 24 2029
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.327
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.327
- Title
- Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
- Description
- Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
- Cost Information
- Time Estimate
- Feb 24 2029
Not ContingentTopology Changing Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8SEPTA-8SURRY 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.327
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.327
- Title
- Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
- Description
- Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
- Cost Information
- Time Estimate
- Feb 24 2029
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.315
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.315
- Title
- Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.
- Description
- Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.
- Cost Information
- Time Estimate
- Apr 22 2030
Not Contingent Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6TYLER1-6POE 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9139.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9139.0 / TC1-PH1-DOM-073
- Title
- Wreck and rebuild 37.41 miles of 500kV line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" and associated substation work.
- Description
- Wreck and rebuild 37.41 miles of 500kV transmission line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA. Remove wave traps.
- Total Cost ($USD)
- $245,455,768
- Discounted Total Cost ($USD)
- $245,455,768
- Allocated Cost ($USD)
- $0
- Time Estimate
- 69 to 70 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line | (Any) |
| |||||||||||||
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: n9264.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9264.0 / TC1-PH1-DOM-080
- Title
- Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1.
- Description
- Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1.
- Total Cost ($USD)
- $582,006
- Discounted Total Cost ($USD)
- $582,006
- Allocated Cost ($USD)
- $0
- Time Estimate
- 12 to 13 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 8CHCKAHM-8SURRY 500.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9191.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9191.0 / TC1-PH1-DOM-090
- Title
- Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor and associated substation work.
- Description
- Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA.
- Total Cost ($USD)
- $256,706,175
- Discounted Total Cost ($USD)
- $256,706,175
- Allocated Cost ($USD)
- $0
- Time Estimate
- 74 to 75 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: WT576_SRT-S | No new ratings for this Flowgate. | |||||||||||||
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-S | No new ratings for this Flowgate. | |||||||||||||
| 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: 57602_SRT-S | No new ratings for this Flowgate. | |||||||||||||
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) |
|
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending) / TC1-PH2-DOM-040
- Title
- ELIM TC1: Wreck and rebuild 18.75 miles of Line 594 btwn Morrisville and Spotsylvania with (3) 1351.5 ACSR (45/7) Dipper at 110 degrees C and assoc substation work (new rating: 4356/4356/5009 MVA)
- Description
- Wreck and rebuild 18.75 miles of Line 594 between Morrisville and Spotsylvania with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA.
- Total Cost ($USD)
- $128,018,212
- Discounted Total Cost ($USD)
- $128,018,212
- Allocated Cost ($USD)
- $0
- Time Estimate
- 60 to 61 Months
Potential Aggregate ContributorEliminated Note 1: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9247.0
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- n9247.0 / TC1-PH2-DOM-041
- Title
- ELIM TC1: Wreck and rebuild 14.02 miles of Line 573 btwn Spotsylvania and North Anna with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and assoc substation work (new rating: 4356/4356/5009 MVA)
- Description
- Wreck and rebuild 14.02 miles of Line 573 between Spotsylvania and North Anna with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA
- Total Cost ($USD)
- $99,636,684
- Discounted Total Cost ($USD)
- $99,636,684
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 Months
Potential Aggregate ContributorEliminated Note 1: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor. Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n8492.2
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n8492.2
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n8492.2
- Title
- Expand Yadkin Substation to accommodate the new 500 kV line.
- Description
- Expansion of yadkins 500 kV switchyard to accommodate the new 500 kV line which includes addition of 5000 amp GIS breakers and relocation of the existing suffolk -yadkin 500 kV line#565
- Total Cost ($USD)
- $16,207,123
- Allocated Cost ($USD)
- $0
- Time Estimate
- 15 to 16 Months
- Cost Alloc Type
- Non-Contingent
System Reinforcement: n9259.0
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n9259.0
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n9259.0
- Title
- Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.
- Description
- Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.
- Total Cost ($USD)
- $25,304,902
- Allocated Cost ($USD)
- $0
- Time Estimate
- 38 to 39 Months
- Cost Alloc Type
- Non-Contingent
System Reinforcement: n9267.0
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n9267.0
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n9267.0 / TC1-PH2-DOM-067
- Title
- Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
- Description
- Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner substations with single (1) 768.2 ACSS/TW “Maumee” at 250 degrees C. This new line will be on separate transmission towers from the existing Northern Neck and Moon Corner line 1059. Station expansion is required at Northern Neck and Moon Corner to accommodate the new line.
- Total Cost ($USD)
- $45,730,074
- Allocated Cost ($USD)
- $0
- Time Estimate
- 45 to 46 Months
- Cost Alloc Type
- Non-Contingent
System Reinforcement: n9630.0
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n9630.0
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n9630.0 / TC1-PH3-DOM-013
- Title
- Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
- Description
- n9630.0 addresses both stability and load flow violations. Construct a new 230 kV Line from the AG1-285 substation to the 230 kV Finneywood substation following the Line 1012 ROW for approximately 1.0 miles, then following the Line 556 ROW for approximately 3.5 miles to terminate at Finneywood. Expand the AG1-285 115 kV substation to accommodate two (2) new 115/230 kV transformers. Build a 230 kV substation at AG1-285 to connect the 115/230 kV transformers and the new 230 kV line to Finneywood. Expand the Finneywood 230 kV substation to accommodate the new line. The existing 1.0 miles of 115 kV from AG1-285 to Chase City does not need to be rebuilt to accommodate a new structure in the same right of way and therefore will be unchanged. The existing 3.5 miles of 500 kV towers from Structure 556/46 to Finneywood substation will need to be rebuilt as a double circuit tower to accommodate the new 230 kV line.
- Total Cost ($USD)
- $71,697,833
- Allocated Cost ($USD)
- $0
- Time Estimate
- Dec 31 2029
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b4000.325
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b4000.325
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.325
- Title
- Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
- Description
- Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: s3047.2
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: s3047.2
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- s3047.2
- Title
- Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
- Description
- Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV line #535 Loudoun – Meadowbrook and #569 Loudoun - Morrisville as the 500 kV sources into the proposed 500 kV ring bus Vint Hill Substation will be expanded to the north of the existing site to accommodate the 500 kV ring required for the addition of the new transformers Existing terminations for 230 kV line #2174 Wheeler – Vint Hill, line #2101 Bristers – Vint Hill, and line #2163 Liberty – Vint Hill will be rearranged to terminate into the expanded Vint Hill Substation 230 kV line #2114 Remington CT – Rollins Ford will also be cut and looped into the expanded Vint Hill Substation due to spatial constraints along the existing right-of-way.
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b3800.312
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.312
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.312
- Title
- Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
- Description
- Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b3800.313
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.313
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.313
- Title
- Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
- Description
- Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b3800.356
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.356
- Title
- Build a new 500 kV line from Vint Hill to Wishing Star.
- Description
- Build a new 500kV line from Vint Hill to Wishing Star. The line will be supported on single circuit monopoles. New conductor to have a summer rating of 4357 MVA. Line length is approximately 16.59 miles
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b3800.357
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.357
- Title
- Build a new 500 kV line from Morrisville to Vint Hill.
- Description
- Build a new 500kV line from Morrisville to Vint Hill. New conductor to have a summer rating of 4357 MVA. Line length is approximately 19.71 miles.
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: b3800.354
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: b3800.354
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b3800.354
- Title
- Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
- Description
- Install terminal equipment at Wishing Star substation to support a 5000A line to Vint Hill. Update relay settings for 500kV Lines #546 and #590.
- Cost Information
- Cost Alloc Type
- Non-Contingent
System Reinforcement: n8492
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n8492
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n8492
- Title
- Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
- Description
- Wreck and rebuild one (1) overhead 500kV transmission line that will start at the existing Fentress 500 kV Substation and terminate at the existing Yadkin 500 kV Substation, located approximately 13.5 miles away.
- Total Cost ($USD)
- $80,172,278
- Allocated Cost ($USD)
- $0
- Time Estimate
- 26 to 27 Months
- Cost Alloc Type
- Non-Contingent
System Reinforcement: n8492.1
AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.
System Reinforcement: n8492.1
- Type
- Stability
- TO
- Dominion
- RTEP ID / TO ID
- n8492.1
- Title
- Two Breaker Additions at Fentress Substation.
- Description
- Install Two 5000 amp GIS Breakers at Fentress Substation to connect the new 500 kV line 5005.
- Total Cost ($USD)
- $19,945,879
- Allocated Cost ($USD)
- $0
- Time Estimate
- 30 to 36 Months
- Cost Alloc Type
- Non-Contingent