AF2-177 Final System Impact Study (Retool 2) Report
v2.00 released 2026-05-14 11:51
Sorenson-DeSoto #2 345 kV
26.0 MW Capacity / 200.0 MW Energy
Introduction
This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..
Preface
The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:
- Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
- Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
- Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:
In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:
- PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
- The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
The AF2-177 Final System Impact Study (Retool 1) Report is available for download here.
Retool 2 (if needed):
If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:
- PJM will perform Retool 2 (if necessary) considering only the removal of projects from the model which chose not to execute their agreements after Retool 1.
- The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.
General
The Project Developer has proposed a Wind generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Blackford County, Indiana. The installed facilities will have a total capability of 200.0 MW with 26.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AF2-177 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system tapping the Sorenson to Desoto 345 kV line, ckt. 2 (specifically the AF1-148 Tap – Desoto line section).
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).
Based on the Final SIS results, the AF2-177 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AF2-177 | Cost Subject to Security* | |
| Transmission Owner Interconnection Facilities (TOIF) | $2,399,061 | $2,399,061 | |
| Other Scope | $0 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $17,298,380 | $17,298,380 | |
| Network Upgrades | $3,496,108 | $3,496,108 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $9,774,277 | $9,774,277 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | |
| AFS - Non-PJM Violations | $0 ** | $0 ** | |
| Total | $32,967,826 | $32,967,826 | |
* Contributes to calculation for Security. See Security Requirement Section of this report for additional detail.
** This value reflects the results at the time of the report posting and it is subject to change. AFS – Non-PJM Violations are not subject to Security. For latest AFS – Non-PJM Violations, please refer to the latest Affected System Study Report for your project.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Security Requirement
Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).
Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.
Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Security Due for AF2-177
Security has been calculated for the AF2-177 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.
Security Due for AF2-177
In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.
Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.
If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.
Transmission Owner Scope of Work
AF2-177 will interconnect with the AEP transmission system via a new station cut into the Sorenson - Desoto 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Scope
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9502.0 | Proposed AF2-177 345 kV, 3M 345 kV, and Jay 345 kV Stations: Final tie in for fiber installation in new right of way. | $257,425 | $67,268 | $42,716 | $11,162 | $378,571 | $378,571 |
| n9501.0 | 3M 345 kV Station: • Reconfigure the existing ethernet switch, installing one (1) new SFP transceiver. | $28,589 | $11,817 | $21,283 | $8,424 | $70,113 | $70,113 |
| n9500.0 | Jay 345 kV Station: • Reconfigure the existing ethernet switch, installing one (1) new Small Form-Factor Pluggable (SFP) transceiver. | $28,589 | $11,817 | $21,283 | $8,424 | $70,113 | $70,113 |
| n9499.0 | Desoto 345 kV Station: • Review and revise the protective relay settings. | $36,901 | $7,080 | $14,081 | $2,702 | $60,764 | $60,764 |
| n9498.0 | Proposed AF1-148 345 kV Station: • Review and revise the protective relay settings. | $36,901 | $7,080 | $14,081 | $2,702 | $60,764 | $60,764 |
| n9497.0 | Sorenson - Desoto #2 345 kV Circuit: Proposed AF2-177 345 kV Station tie-in. • Remove two (2) tower structures (#419 and #421) along with approximately 0.4 miles of existing wire. • Install two (2) new 150’ custom steel, single circuit, single pole dead end structures on concrete piers with anchor bolt cages along the existing Sorenson - Desoto #2 345 kV Circuit. • Install two (2) new 130’ custom steel, single circuit, single pole, running angle structures on concrete piers with anchor bolt cages along the perimeter of the Proposed AF2-177 345 kV Station. • Install four (4) spans of double bundle ACSR 2156 (Bluebird) transmission line conductor with 12/7 Guinea shield wire. | $1,239,091 | $1,185,343 | $220,456 | $210,893 | $2,855,783 | $2,855,783 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9496.0 | Sorenson - Desoto #2 345 kV Circuit: Construct a new 345 kV breaker and a half station, initially populated with three (3) circuit breakers, expandable to six (6) circuit breakers. • Three (3) 5000A 63 kA circuit breakers with associated control relaying. • Nine (9) 3000A circuit breaker disconnect switches. • Two (2) single phase station service voltage transformers (SSVT). • One (1) 16' x 48' DICM. • Four (4) single phase wave traps, two (2) each on the line exits to the Desoto and Proposed AF1-148 345 kV Stations. • A directional comparison blocking (DCB) protective relaying scheme for the line to the Proposed AF1-148 345 kV Station. • A DCB protective relaying scheme for the line to the Desoto 345 kV Station. • Two (2) 3-phase CCVT, one each for the line exits to the Proposed AF1-148 and Desoto 345 kV Stations. • Two (2) A-Frame line exit structures, one each for the line exits to the Proposed AF1-148 and Desoto 345 kV Stations. • Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures. • The civil work required to develop a site that accommodates the installation of the above station includes grading of a 244' x 556' pad. | $8,041,121 | $6,002,956 | $501,890 | $374,677 | $14,920,644 | $14,920,644 |
| n9495.0 | Proposed AF2-177 345 kV, 3M 345 kV, and Jay 345 kV Stations: Install two (2) ADLT station exit transitions and two (2) new fiber optic cable paths consisting of a total 6.9 miles of 144 count ADLT cable installed underground in new right of way. | $1,555,334 | $463,998 | $276,051 | $82,353 | $2,377,736 | $2,377,736 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | • Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage and one span of double bundle aluminum conductor steel-reinforced (ACSR) 954 (Cardinal) transmission line conductor with 12/7 Guinea shield wire for the generation lead circuit extending from the Proposed AF2-177 345 kV Station to the PCO. • Extension of two (2) underground all dielectric loose tube ("ADLT") fiber optic cables from the Proposed AF2-177 345 kV Station control house to fiber demarcation splice boxes to support direct fiber relaying between the Proposed AF2-177 345 kV and Project Developer's collector stations. • Dual direct fiber current differential relays for the generation lead to the Proposed AF2-177 collector station. • Installation of a standard revenue metering package, including three (3) single phase current transformers ("CT"), three (3) single phase coupling capacitor voltage transformers, associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module ("DICM")-installed metering panel, for the generation lead circuit at the Proposed AF2-177 345 kV Station. | $1,271,405 | $811,707 | $190,689 | $125,260 | $2,399,061 | $2,399,061 |
Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 24 to 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The wind generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Wind speed (meters/second) - (Required)
- Wind direction (decimal degrees from true north) - (Required)
- Ambient air temperature (Fahrenheit) - (Required)
- Air Pressure (Hectopascals) - (Required)
- Humidity (Percent) - (Accepted, not required)
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AF2-177 was evaluated as a 200.0 MW (26.0 MW Capacity) injection in the AEP area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | OVEC | 06DEARB1-06PIERCE 345.0 kV Ckt 1 line | DEOK_P2-3_1403_MIAMI FORT_SRT-A | Breaker | AC | 100.86 % | 971.0 | B | 979.38 | 14.98 | |
| GD1 | OVEC | 06DEARB1-06PIERCE 345.0 kV Ckt 1 line | DEOK_P2-3_1401_MIAMI FORT_SRT-A | Breaker | AC | 100.35 % | 971.0 | B | 974.43 | 14.98 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | AEP | AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line | AEP_P1-2_#8702_2543_SRT-A-C | OP | AC | 111.57 % | 897.0 | B | 1000.79 | 49.02 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Light Load Analysis
The New Service Request AF2-177 was evaluated as a 200.0 MW injection in the AEP area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests (projects) in PJM Transition Cycle 1, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.
This analysis is effectively a screening study to determine whether the addition of the cluster 62 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.
Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 199 contingencies were studied, each with a 20 second simulation time period. Studied faults included:
a) Steady-state operation (20 second run),
a) Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),
b) Single-phase bus faults with normal clearing time,
c) Single-phase faults with stuck breaker,
d) Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).
There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2027 peak load case:
a) Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AF2-173, AF2-177, AF2-407, AG1-367 and AG1-375 meet the 0.95 leading and lagging PF requirement.
AF2-173 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-173, setting Ki to 0.15 from its original value of 0.5.
AF2-177 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-177, setting Ki to 0.15 from its original value of 0.5.
AG1-367 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-367, setting Kc to 0.1 from its original value of 0.
AG1-375 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-375, setting Kc to 0.1 from its original value of 0.
AF2-407 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc, Ki and Kp parameters in the plant controller (REPCA1) for AF2-407, setting Kc to 0.15 from its original value of 0.04, setting Ki to 2 from its original value of 0.5, and setting Kp to 0.5 from its original value of 0.
Fictitious frequency response at AF2-407 generator bus tripped the queue project due to the action of instantaneous under-frequency and over-frequency relays when faults were applied at Fall Creek 345 kV (AF2-407 POI). Therefore, the relay pickup times for frequency relay instances 96116513 and 96116516 were set to 20 seconds to avoid fictitious frequency tripping of the unit.
A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.
No mitigations were found to be required.
Table 1: TC1 Cluster 62 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
62 | AF2-173 | Solar | AEP | 140 | 140 | 84 | Desoto 345 kV Substation |
AF2-177 | Wind | AEP | 200 | 200 | 26 | Sorenson – Desoto #2 345 kV Line | |
AF2-407 | Battery Storage | AEP | 300 | 300 | 300 | Fall Creek 345 kV Substation | |
AG1-367 | Solar | AEP | 100 | 100 | 60 | DeSoto 345 kV Substation | |
AG1-375 | Solar | AEP | 100 | 100 | 100 | Sorenson – Desoto #2 345 kV Line |
Reactive Power Analysis
The reactive power capability of AF2-177 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AC1-174 | Losantville 345kV | In Service |
| AC1-175 | Losantville 345kV | In Service |
| AC2-090 | Losantville 345kV | In Service |
| AC2-111 | College Corner 138kV | Engineering & Procurement |
| AC2-176 | Jay 138 kV | In Service |
| AD1-128 | Modoc-Delaware 138 kV | In Service |
| AD2-071 | Strawton-Deer Creek 138 kV | Suspended |
| AE1-207 | Mississinewa-Gaston 138 kV | Suspended |
| AE1-208 | Delaware-Van Buren 138 kV | Suspended |
| AE1-209 | Desoto 345 kV | Suspended |
| AE1-210 | Desoto 345 kV | Suspended |
| AE2-089 | Pennville-Adams 138 kV | Suspended |
| AE2-169 | Delaware-Van Buren 138 kV | Suspended |
| AE2-172 | Mississinewa-Gaston 138 kV | Suspended |
| AE2-219 | Bluff Point-Randolph 138 kV | Suspended |
| AE2-220 | Losantville 345 kV | Engineering & Procurement |
| AE2-234 | Liberty Center-Buckeye Tap 69 kV | Engineering & Procurement |
| AE2-297 | Madison-Tanners Creek 138 kV | In Service |
| AF1-071 | College Corner 138 kV | Engineering & Procurement |
| AF1-118 | Sorenson-Desoto 345 kV | Withdrawn |
| AF1-119 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF1-202 | Keystone-Desoto 345 kV | Under Construction |
| AF1-223 | Keystone-Desoto 345 kV | Under Construction |
| AF1-268 | Desoto-Jay 138 kV | Engineering & Procurement |
| AF2-068 | Jay 138 kV | Engineering & Procurement |
| AF2-162 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-388 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-408 | Fall Creek 138 kV | Engineering & Procurement |
| AG1-017 | Jay 138 kV | In Service |
| AG1-047 | Jay 138 kV | Engineering & Procurement |
| AG1-324 | Jay-Desoto 138 kV | Engineering & Procurement |
| AG1-414 | Mississinewa 138 kV | Engineering & Procurement |
| AG1-433 | Keystone-DeSoto 345 kV | Engineering & Procurement |
| V3-007 | Desoto-Tanners Creek #1 345kV | In Service |
| Z2-115 | Deer Creek 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In coordination with other Affected System Operators, PJM has determined that the Affected System Operator for this project that requires an Affected System Study. For the latest Affected System Study results pertaining this project, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM lists any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.
System Reinforcements
Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n9680.0
- Type
- Load Flow
- TO
- OVEC
- RTEP ID / TO ID
- n9680.0 / OVEC0001a
- Title
- Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F
- Description
- •Remove and replace sixteen (16) existing double circuit towers with taller double circuit custom steel poles. (Towers 11, 14, 45, 47, 52, 57, 59, 61, 63, 66, 67, 71, 77, 84, 91, and 96) •Remove and replace two (2) existing river crossing lattice towers with taller lattice structures. (Towers 2 and 140)
- Total Cost ($USD)
- $24,006,000
- Discounted Total Cost ($USD)
- $24,006,000
- Allocated Cost ($USD)
- $9,774,277
- Time Estimate
- 38 Months
Contributor
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 06DEARB1-06PIERCE 345.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AF2-177 | 15.0 MW | 40.7% | $9,774,277 |
| AF2-388 ⧉ Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF2-388, AG1-433 | 14.5 MW | 39.5% | $9,487,815 |
| AG1-433 ⧉ Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AF2-388, AG1-433 | 7.3 MW | 19.8% | $4,743,908 |