AF2-177 Final System Impact Study (Retool 1) Report

v1.00 released 2025-12-08 18:18

Sorenson-DeSoto #2 345 kV

26.0 MW Capacity / 200.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed a Wind generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Blackford County, Indiana. The installed facilities will have a total capability of 200.0 MW with 26.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-177
Project Name:
Sorenson-DeSoto #2 345 kV
Project Developer Name:
Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
State:
Indiana
County:
Blackford
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
200.0
MWE:
200.0
MWC:
26.0
Fuel Type:
Wind
Basecase Study Year:
2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF2-177 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system tapping the Sorenson to Desoto 345 kV line, ckt. 2 (specifically the AF1-148 Tap – Desoto line section).

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AF2-177 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AF2-177Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$2,399,061$2,399,061
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$17,298,380$17,298,380
Network Upgrades$3,496,108$3,496,108
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$5,909,187$5,909,187
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$29,102,736$29,102,736

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF2-177

Security has been calculated for the AF2-177 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF2-177
Project(s): AF2-177
Final Agreement Security (A): $29,102,736
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $29,102,736
Security on Hand with PJM (D): $14,450,534
Additional Security Due at Agreement Execution (E): C D = $14,652,202
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

AF2-177 will interconnect with the AEP transmission system via a new station cut into the Sorenson - Desoto 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9502.0

Proposed AF2-177 345 kV, 3M 345 kV, and Jay 345 kV Stations: Final tie in for fiber installation in new right of way.

$257,425$67,268$42,716$11,162$378,571$378,571
n9501.0

3M 345 kV Station: • Reconfigure the existing ethernet switch, installing one (1) new SFP transceiver.

$28,589$11,817$21,283$8,424$70,113$70,113
n9500.0

Jay 345 kV Station: • Reconfigure the existing ethernet switch, installing one (1) new Small Form-Factor Pluggable (SFP) transceiver.

$28,589$11,817$21,283$8,424$70,113$70,113
n9499.0

Desoto 345 kV Station: • Review and revise the protective relay settings.

$36,901$7,080$14,081$2,702$60,764$60,764
n9498.0

Proposed AF1-148 345 kV Station: • Review and revise the protective relay settings.

$36,901$7,080$14,081$2,702$60,764$60,764
n9497.0

Sorenson - Desoto #2 345 kV Circuit: Proposed AF2-177 345 kV Station tie-in. • Remove two (2) tower structures (#419 and #421) along with approximately 0.4 miles of existing wire. • Install two (2) new 150’ custom steel, single circuit, single pole dead end structures on concrete piers with anchor bolt cages along the existing Sorenson - Desoto #2 345 kV Circuit. • Install two (2) new 130’ custom steel, single circuit, single pole, running angle structures on concrete piers with anchor bolt cages along the perimeter of the Proposed AF2-177 345 kV Station. • Install four (4) spans of double bundle ACSR 2156 (Bluebird) transmission line conductor with 12/7 Guinea shield wire.

$1,239,091$1,185,343$220,456$210,893$2,855,783$2,855,783
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9496.0

Sorenson - Desoto #2 345 kV Circuit: Construct a new 345 kV breaker and a half station, initially populated with three (3) circuit breakers, expandable to six (6) circuit breakers. • Three (3) 5000A 63 kA circuit breakers with associated control relaying. • Nine (9) 3000A circuit breaker disconnect switches. • Two (2) single phase station service voltage transformers (SSVT). • One (1) 16' x 48' DICM. • Four (4) single phase wave traps, two (2) each on the line exits to the Desoto and Proposed AF1-148 345 kV Stations. • A directional comparison blocking (DCB) protective relaying scheme for the line to the Proposed AF1-148 345 kV Station. • A DCB protective relaying scheme for the line to the Desoto 345 kV Station. • Two (2) 3-phase CCVT, one each for the line exits to the Proposed AF1-148 and Desoto 345 kV Stations. • Two (2) A-Frame line exit structures, one each for the line exits to the Proposed AF1-148 and Desoto 345 kV Stations. • Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures. • The civil work required to develop a site that accommodates the installation of the above station includes grading of a 244' x 556' pad.

$8,041,121$6,002,956$501,890$374,677$14,920,644$14,920,644
n9495.0

Proposed AF2-177 345 kV, 3M 345 kV, and Jay 345 kV Stations: Install two (2) ADLT station exit transitions and two (2) new fiber optic cable paths consisting of a total 6.9 miles of 144 count ADLT cable installed underground in new right of way.

$1,555,334$463,998$276,051$82,353$2,377,736$2,377,736
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage and one span of double bundle aluminum conductor steel-reinforced (ACSR) 954 (Cardinal) transmission line conductor with 12/7 Guinea shield wire for the generation lead circuit extending from the Proposed AF2-177 345 kV Station to the PCO. • Extension of two (2) underground all dielectric loose tube ("ADLT") fiber optic cables from the Proposed AF2-177 345 kV Station control house to fiber demarcation splice boxes to support direct fiber relaying between the Proposed AF2-177 345 kV and Project Developer's collector stations. • Dual direct fiber current differential relays for the generation lead to the Proposed AF2-177 collector station. • Installation of a standard revenue metering package, including three (3) single phase current transformers ("CT"), three (3) single phase coupling capacitor voltage transformers, associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module ("DICM")-installed metering panel, for the generation lead circuit at the Proposed AF2-177 345 kV Station.

$1,271,405$811,707$190,689$125,260$2,399,061$2,399,061

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 24 to 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to c, including remote end work, considering the Project Developer selection of the Option To Build, allocating the long lead material ordering as part of the Project Developer scope. The maximum schedule is based off of AEP assumed long lead material ordering not considering allocation of existing material production slots, advanced progress enabled by Engineering and Procurement Agreements, or other schedule expediting methods. AEP may be able to allocate material production slots for long lead time materials to expedite this schedule. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to these agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The wind generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Wind speed (meters/second) - (Required)
  • Wind direction (decimal degrees from true north) - (Required)
  • Ambient air temperature (Fahrenheit) - (Required)
  • Air Pressure (Hectopascals) - (Required)
  • Humidity (Percent) - (Accepted, not required)
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AF2-177 was evaluated as a 200.0 MW (26.0 MW Capacity) injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1OVEC
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
DEOK_P2-3_1403_MIAMI FORT_SRT-A
BreakerAC103.03 %971.0B1000.414.98
GD1OVEC
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
DEOK_P2-3_1401_MIAMI FORT_SRT-A
BreakerAC102.52 %971.0B995.4514.98

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1403_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:103.03 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:1000.4
MW Contribution:14.98
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.75 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:997.74
MW Contribution:14.96
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.13882352941176470.118
961762AG1-017 E
Adder
0.63647058823529420.541
962031AG1-047 C
Adder
3.67647058823529443.125
962032AG1-047 E
Adder
2.45058823529411772.083
965651AG1-433 C
Adder
1.281.088
965652AG1-433 E
Adder
5.9905882352941175.092
24726405LAWG1A
50/50
6.86.8
24726505LAWG1B
50/50
6.86.8
24726605LAWG1S
50/50
10.86110.861
24726705LAWG2A
50/50
6.86.8
24726805LAWG2B
50/50
6.3116.311
24726905LAWG2S
50/50
10.86110.861
247543V3-007 C
50/50
0.4930.493
247929S-071 E
Adder
5.8552941176470594.977
247935V3-007 E
50/50
20.20920.209
24795805WLD G2 E
Adder
12.55764705882352810.674
24796305HDWTR1G E
50/50
20.20920.209
934962AD1-128 E
Adder
7.3717647058823536.266
936561AD2-071 C
Adder
4.7094117647058834.003
936562AD2-071 E
Adder
2.321.972
942081AE2-220 C
50/50
6.0976.097
942082AE2-220 E
50/50
8.428.42
944031AF1-071 C
Adder
0.47411764705882360.403
944032AF1-071 E
Adder
0.77411764705882360.658
958711AF2-162 C
Adder
2.18117647058823531.854
958712AF2-162 E
Adder
1.09058823529411760.927
960971AF2-388 C
Adder
2.55882352941176452.175
960972AF2-388 E
Adder
11.98117647058823510.184
24379505HDWTR1G C
50/50
0.4930.493
25194708EBND2
50/50
16.23816.238
932681AC2-090 C
50/50
0.720.72
932682AC2-090 E
50/50
7.2017.201
939761AE1-207 C
Adder
4.4658823529411763.796
939762AE1-207 E
Adder
6.1682352941176485.243
939771AE1-208 C
Adder
3.9588235294117653.365
939772AE1-208 E
Adder
5.3988235294117654.589
942071AE2-219 C
Adder
2.56941176470588272.184
942072AE2-219 E
Adder
3.5482352941176473.016
247968Z2-115 E
Adder
0.070588235294117650.06
926874AC1-174 E
50/50
7.2017.201
926881AC1-175 E
50/50
7.2017.201
270209AC1-174 C
50/50
0.7210.721
270210AC1-175 C
50/50
0.7210.721
270222AC2-111 C
Adder
2.1082352941176471.792
932844AC2-111 E
Adder
3.40588235294117642.895
933596AC2-176 E
Adder
6.9294117647058825.89
942221AE2-234 C
Adder
1.2988235294117651.104
942222AE2-234 E
Adder
0.58705882352941170.499
942791AE2-297 C O1
50/50
1.5831.583
942792AE2-297 E O1
50/50
6.6276.627
944531AF1-118 C
Adder
16.3613.906
944532AF1-118 E
Adder
4.9341176470588244.194
944541AF1-119 C
Adder
10.1788235294117648.652
944542AF1-119 E
Adder
4.36235294117647053.708
945371AF1-202 C
Adder
2.61411764705882372.222
945372AF1-202 E
Adder
12.76352941176470610.849
945581AF1-223 C
Adder
6.925.882
945582AF1-223 E
Adder
4.61294117647058853.921
946032AF1-268 E
Adder
2.04470588235294141.738
958861AF2-177 C
Adder
1.9470588235294121.655
958862AF2-177 E
Adder
13.03176470588235211.077
961161AF2-407 C
Adder
24.0623529411764720.453
961171AF2-408 C
Adder
6.4976470588235295.523
939781AE1-209 C
Adder
1.21.02
939782AE1-209 E
Adder
8.0282352941176466.824
939791AE1-210 C
Adder
1.21.02
939792AE1-210 E
Adder
8.0282352941176466.824
946031AF1-268 C
Adder
4.5082352941176473.832
964611AG1-324 C
Adder
1.8117647058823531.54
964612AG1-324 E
Adder
0.72117647058823530.613
940981AE2-089 C
Adder
4.99529411764705964.246
940982AE2-089 E
Adder
3.33058823529411762.831
941691AE2-169 C
Adder
2.3752941176470592.019
941721AE2-172 C
Adder
2.65882352941176462.26
957741AF2-068 C
Adder
5.5141176470588244.687
957742AF2-068 E
Adder
3.67647058823529443.125
965461AG1-414 C
Adder
2.7552941176470592.342
965462AG1-414 E
Adder
1.8364705882352941.561
CBM West 1LTFEXP_CBM-W1->PJM
CBM
36.45236.452
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.19914.199
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.9220.922
NYPJM->LTFIMP_NY
CLTF
0.4740.474
LGEELTFEXP_LGEE->PJM
CLTF
0.6180.618
WECLTFEXP_WEC->PJM
CLTF
0.8430.843
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.2640.264
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1350.135
TVALTFEXP_TVA->PJM
CLTF
1.3261.326
MECLTFEXP_MEC->PJM
CLTF
3.7733.773
LAGNLTFEXP_LAGN->PJM
CLTF
2.092.09
SIGELTFEXP_SIGE->PJM
CLTF
0.320.32
O66PJM->LTFIMP_O-066
CMTX_NF
5.9075.907
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.3980.398

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1401_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.52 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:995.45
MW Contribution:14.98
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.24 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:992.73
MW Contribution:14.96
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.13882352941176470.118
961762AG1-017 E
Adder
0.63647058823529420.541
962031AG1-047 C
Adder
3.67764705882352953.126
962032AG1-047 E
Adder
2.45176470588235332.084
965651AG1-433 C
Adder
1.281.088
965652AG1-433 E
Adder
5.9929411764705885.094
24726405LAWG1A
50/50
6.8016.801
24726505LAWG1B
50/50
6.8016.801
24726605LAWG1S
50/50
10.86210.862
24726705LAWG2A
50/50
6.8016.801
24726805LAWG2B
50/50
6.3126.312
24726905LAWG2S
50/50
10.86210.862
247543V3-007 C
50/50
0.4940.494
247929S-071 E
Adder
5.8588235294117654.98
247935V3-007 E
50/50
20.21420.214
24795805WLD G2 E
Adder
12.56117647058823510.677
24796305HDWTR1G E
50/50
20.21420.214
934962AD1-128 E
Adder
7.37529411764705946.269
936561AD2-071 C
Adder
4.7105882352941174.004
936562AD2-071 E
Adder
2.321.972
942081AE2-220 C
50/50
6.0996.099
942082AE2-220 E
50/50
8.4228.422
944031AF1-071 C
Adder
0.475294117647058870.404
944032AF1-071 E
Adder
0.77411764705882360.658
958711AF2-162 C
Adder
2.1823529411764711.855
958712AF2-162 E
Adder
1.09058823529411760.927
960971AF2-388 C
Adder
2.562.176
960972AF2-388 E
Adder
11.98588235294117710.188
24379505HDWTR1G C
50/50
0.4940.494
25194708EBND2
50/50
16.24416.244
932681AC2-090 C
50/50
0.720.72
932682AC2-090 E
50/50
7.2037.203
939761AE1-207 C
Adder
4.46823529411764753.798
939762AE1-207 E
Adder
6.1694117647058825.244
939771AE1-208 C
Adder
3.96117647058823553.367
939772AE1-208 E
Adder
5.40117647058823554.591
942071AE2-219 C
Adder
2.5705882352941182.185
942072AE2-219 E
Adder
3.55058823529411743.018
247968Z2-115 E
Adder
0.070588235294117650.06
926874AC1-174 E
50/50
7.2037.203
926881AC1-175 E
50/50
7.2037.203
270209AC1-174 C
50/50
0.7210.721
270210AC1-175 C
50/50
0.7210.721
270222AC2-111 C
Adder
2.1105882352941181.794
932844AC2-111 E
Adder
3.4082352941176472.897
933596AC2-176 E
Adder
6.9329411764705885.893
942221AE2-234 C
Adder
1.31.105
942222AE2-234 E
Adder
0.58823529411764710.5
942791AE2-297 C O1
50/50
1.5831.583
942792AE2-297 E O1
50/50
6.6286.628
944531AF1-118 C
Adder
16.36705882352941213.912
944532AF1-118 E
Adder
4.9364705882352944.196
944541AF1-119 C
Adder
10.182352941176478.655
944542AF1-119 E
Adder
4.3635294117647063.709
945371AF1-202 C
Adder
2.61529411764705882.223
945372AF1-202 E
Adder
12.76823529411764610.853
945581AF1-223 C
Adder
6.9223529411764715.884
945582AF1-223 E
Adder
4.6152941176470593.923
946032AF1-268 E
Adder
2.04588235294117651.739
958861AF2-177 C
Adder
1.9482352941176471.656
958862AF2-177 E
Adder
13.03647058823529511.081
961161AF2-407 C
Adder
24.06705882352941520.457
961171AF2-408 C
Adder
6.4976470588235295.523
939781AE1-209 C
Adder
1.21.02
939782AE1-209 E
Adder
8.0305882352941186.826
939791AE1-210 C
Adder
1.21.02
939792AE1-210 E
Adder
8.0305882352941186.826
946031AF1-268 C
Adder
4.5105882352941183.834
964611AG1-324 C
Adder
1.8117647058823531.54
964612AG1-324 E
Adder
0.72117647058823530.613
940981AE2-089 C
Adder
4.9988235294117644.249
940982AE2-089 E
Adder
3.33294117647058872.833
941691AE2-169 C
Adder
2.3764705882352942.02
941721AE2-172 C
Adder
2.662.261
957741AF2-068 C
Adder
5.517647058823534.69
957742AF2-068 E
Adder
3.67764705882352953.126
965461AG1-414 C
Adder
2.7552941176470592.342
965462AG1-414 E
Adder
1.83764705882352961.562
CBM West 1LTFEXP_CBM-W1->PJM
CBM
36.49436.494
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.20814.208
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.9180.918
NYPJM->LTFIMP_NY
CLTF
0.4720.472
LGEELTFEXP_LGEE->PJM
CLTF
0.6160.616
WECLTFEXP_WEC->PJM
CLTF
0.8440.844
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.2620.262
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1340.134
TVALTFEXP_TVA->PJM
CLTF
1.3281.328
MECLTFEXP_MEC->PJM
CLTF
3.7763.776
LAGNLTFEXP_LAGN->PJM
CLTF
2.0932.093
SIGELTFEXP_SIGE->PJM
CLTF
0.320.32
O66PJM->LTFIMP_O-066
CMTX_NF
5.8835.883
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.3960.396
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7   /*08M.FORT     345.0 - 08M.FRT7      22.0
END
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9   /*08M.FORT     345.0 - 08M.FORT     138.0
END
248001 to 248013 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
AEP_P1-2_#8702_2543_SRT-A-C
OPAC116.58 %897.0B1045.7249.02

Details for AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line l/o AEP_P1-2_#8702_2543_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:116.58 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1045.72
MW Contribution:49.02
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:117.94 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1057.88
MW Contribution:49.08
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
50/50
0.2450.245
961762AG1-017 E
50/50
1.1251.125
962031AG1-047 C
50/50
6.5036.503
962032AG1-047 E
50/50
4.3364.336
965651AG1-433 C
50/50
8.2918.291
965652AG1-433 E
50/50
38.81938.819
24699105WLD G1 C
50/50
0.2420.242
24725505WLD G2 C
50/50
0.2350.235
24728505AND G1
50/50
0.5880.588
24728605AND G2
50/50
0.5880.588
24728705AND G3
50/50
1.231.23
24728805RICHG1
50/50
0.6040.604
24728905RICHG2
50/50
0.6040.604
24753605BLUFF P WF
50/50
0.4130.413
247543V3-007 C
50/50
0.9250.925
247929S-071 E
50/50
10.110.1
247935V3-007 E
50/50
37.89937.899
24795805WLD G2 E
50/50
19.56819.568
24796305HDWTR1G E
50/50
37.89937.899
934961AD1-128 C
50/50
1.4761.476
934962AD1-128 E
50/50
15.74415.744
936561AD2-071 C
50/50
7.2167.216
936562AD2-071 E
50/50
3.5543.554
942081AE2-220 C
50/50
11.43511.435
942082AE2-220 E
50/50
15.79115.791
944031AF1-071 C
Adder
0.64588235294117660.549
944032AF1-071 E
Adder
1.05411764705882360.896
958711AF2-162 C
50/50
14.13314.133
958712AF2-162 E
50/50
7.0677.067
960971AF2-388 C
50/50
16.58316.583
960972AF2-388 E
50/50
77.63877.638
24341505WWVSTA
50/50
1.6751.675
24379505HDWTR1G C
50/50
0.9250.925
932681AC2-090 C
50/50
1.3511.351
932682AC2-090 E
50/50
13.50413.504
939761AE1-207 C
50/50
7.9447.944
939762AE1-207 E
50/50
10.9710.97
939771AE1-208 C
50/50
6.3866.386
939772AE1-208 E
50/50
8.7088.708
942071AE2-219 C
50/50
4.4324.432
942072AE2-219 E
50/50
6.1216.121
926874AC1-174 E
50/50
13.50413.504
926881AC1-175 E
50/50
13.50413.504
270201AC2-176 GEN
50/50
0.2990.299
270209AC1-174 C
50/50
1.3531.353
270210AC1-175 C
50/50
1.3531.353
270222AC2-111 C
Adder
2.86941176470588262.439
932844AC2-111 E
Adder
4.6352941176470593.94
933596AC2-176 E
50/50
12.25912.259
942791AE2-297 C O1
50/50
1.8541.854
942792AE2-297 E O1
50/50
7.767.76
944531AF1-118 C
50/50
65.88465.884
944532AF1-118 E
50/50
19.87119.871
944541AF1-119 C
50/50
65.95565.955
944542AF1-119 E
50/50
28.26628.266
945371AF1-202 C
50/50
14.37414.374
945372AF1-202 E
50/50
70.17970.179
945581AF1-223 C
50/50
38.04938.049
945582AF1-223 E
50/50
25.36625.366
946032AF1-268 E
50/50
4.5994.599
958861AF2-177 C
50/50
6.3726.372
958862AF2-177 E
50/50
42.64542.645
961161AF2-407 C
50/50
45.44345.443
961171AF2-408 C
50/50
11.20711.207
24336205RANDOLPH1
50/50
0.0690.069
939781AE1-209 C
50/50
3.1873.187
939782AE1-209 E
50/50
21.3321.33
939791AE1-210 C
50/50
3.1873.187
939792AE1-210 E
50/50
21.3321.33
946031AF1-268 C
50/50
10.13810.138
964611AG1-324 C
50/50
3.4223.422
964612AG1-324 E
50/50
1.3621.362
941691AE2-169 C
50/50
3.8323.832
941721AE2-172 C
50/50
4.7294.729
957741AF2-068 C
50/50
9.7559.755
957742AF2-068 E
50/50
6.5036.503
965461AG1-414 C
Adder
4.2541176470588233.616
965462AG1-414 E
Adder
2.8364705882352942.411
955152J993 G
External Queue
18.25959205627441418.259592056274414
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.73313.733
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
10.80710.807
G-007ALTFEXP_G-007A->PJM
CMTX
0.1370.137
VTFLTFEXP_VFT->PJM
CMTX
0.3560.356
NYPJM->LTFIMP_NY
CLTF
0.0070.007
LGEELTFEXP_LGEE->PJM
CLTF
2.4272.427
CPLELTFEXP_CPLE->PJM
CLTF
0.8360.836
TVALTFEXP_TVA->PJM
CLTF
2.5252.525
LAGNLTFEXP_LAGN->PJM
CLTF
2.5582.558
SIGELTFEXP_SIGE->PJM
CLTF
0.4430.443
MDUPJM->LTFIMP_MDU
CLTF
0.0440.044
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.4110.411
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
944540 to 243225 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
Base Case
OPAC100.8 %897.0A904.219.24

Details for 05KEYSTN-05SORENS 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP
Facility Description:
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:100.8 %
Rating:897.0 MVA
Rating Type:A
MVA to Mitigate:904.2
MW Contribution:19.24
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.17764705882352940.151
961762AG1-017 E
Adder
0.81529411764705880.693
962031AG1-047 C
Adder
4.7129411764705884.006
962032AG1-047 E
Adder
3.14235294117647032.671
965651AG1-433 C
50/50
7.727.72
965652AG1-433 E
50/50
36.14336.143
24729205KEY G1
50/50
5.1485.148
24729305KEY G2
50/50
5.1765.176
24729405KEY G3
50/50
5.2645.264
24729505KEY G4
50/50
5.3365.336
247543V3-007 C
50/50
0.6720.672
247929S-071 E
Adder
7.3176470588235296.22
247935V3-007 E
50/50
27.61527.615
24795805WLD G2 E
Adder
14.18823529411764812.06
24796305HDWTR1G E
50/50
27.61527.615
934961AD1-128 C
50/50
1.071.07
934962AD1-128 E
50/50
11.45511.455
936561AD2-071 C
Adder
5.23058823529411754.446
936562AD2-071 E
Adder
2.57647058823529432.19
942081AE2-220 C
50/50
8.3328.332
942082AE2-220 E
50/50
11.50611.506
958711AF2-162 C
50/50
13.15913.159
958712AF2-162 E
50/50
6.5796.579
960971AF2-388 C
50/50
15.4415.44
960972AF2-388 E
50/50
72.28772.287
24379505HDWTR1G C
50/50
0.6720.672
932681AC2-090 C
50/50
0.9810.981
932682AC2-090 E
50/50
9.849.84
939761AE1-207 C
Adder
5.762352941176474.898
939762AE1-207 E
Adder
7.957647058823536.764
939771AE1-208 C
Adder
4.6317647058823533.937
939772AE1-208 E
Adder
6.3164705882352945.369
942071AE2-219 C
Adder
3.2117647058823532.73
942072AE2-219 E
Adder
4.4352941176470593.77
926874AC1-174 E
50/50
9.849.84
926881AC1-175 E
50/50
9.849.84
270209AC1-174 C
50/50
0.9820.982
270210AC1-175 C
50/50
0.9820.982
933596AC2-176 E
Adder
8.8847058823529417.552
942792AE2-297 E O1
Adder
5.6341176470588234.789
944541AF1-119 C
50/50
61.40961.409
944542AF1-119 E
50/50
26.31826.318
945371AF1-202 C
50/50
13.02313.023
945372AF1-202 E
50/50
63.58263.582
945581AF1-223 C
50/50
34.47234.472
945582AF1-223 E
50/50
22.98122.981
946032AF1-268 E
50/50
3.3473.347
958861AF2-177 C
Adder
2.5011764705882352.126
958862AF2-177 E
Adder
16.73882352941176414.228
961161AF2-407 C
50/50
33.03933.039
961171AF2-408 C
50/50
8.1438.143
939781AE1-209 C
50/50
2.3242.324
939782AE1-209 E
50/50
15.55115.551
939791AE1-210 C
50/50
2.3242.324
939792AE1-210 E
50/50
15.55115.551
946031AF1-268 C
50/50
7.3787.378
964611AG1-324 C
Adder
2.4835294117647062.111
964612AG1-324 E
Adder
0.98823529411764710.84
941691AE2-169 C
Adder
2.77882352941176472.362
941721AE2-172 C
Adder
3.43058823529411772.916
957741AF2-068 C
Adder
7.0705882352941176.01
957742AF2-068 E
Adder
4.7129411764705884.006
CBM West 2LTFEXP_CBM-W2->PJM
CBM
9.5549.554
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
7.1357.135
G-007PJM->LTFIMP_G-007
CMTX_NF
0.0930.093
NYPJM->LTFIMP_NY
CLTF
0.0750.075
LGEELTFEXP_LGEE->PJM
CLTF
1.7311.731
CPLELTFEXP_CPLE->PJM
CLTF
0.5340.534
TVALTFEXP_TVA->PJM
CLTF
1.7451.745
LAGNLTFEXP_LAGN->PJM
CLTF
1.7421.742
SIGELTFEXP_SIGE->PJM
CLTF
0.3160.316
O66PJM->LTFIMP_O-066
CMTX_NF
0.6070.607
MDUPJM->LTFIMP_MDU
CLTF
0.040.04
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.2640.264
243225 to 243232 ckt 1

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AF2-177 was evaluated as a 200.0 MW injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP/OVEC
06KYGER-05SPORN 345.0 kV Ckt 1 line
AEP_P1-2_#7441_100545_SRT-A
SingleDC101.06 %1204.0B1216.7210.89

Details for 06KYGER-05SPORN 345.0 kV Ckt 1 line l/o AEP_P1-2_#7441_100545_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
Contingency Type:Single
DC|AC:DC
Final Cycle Loading:101.06 %
Rating:1204.0 MVA
Rating Type:B
MVA to Mitigate:1216.72
MW Contribution:10.89
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24725505WLD G2 C
80/20
0.2270.227
24385905FR-11G C
80/20
0.3740.374
24386205FR-12G C
80/20
0.1820.182
24386405FR-21G C
80/20
0.1890.189
24386605FR-22G C
80/20
0.1890.189
24387005FR-3G C
80/20
0.1820.182
24387305FR-4G C
80/20
0.4240.424
24790105FR-12G E
80/20
1.2271.227
24790205FR-21G E
80/20
1.3041.304
24790405FR-3G E
80/20
2.432.43
24790505FR-4G E
80/20
1.9261.926
24790605MDL-1G E
80/20
2.5232.523
24790705MDL-2G E
80/20
1.2151.215
24791205MDL-3G E
80/20
1.2141.214
24791305MDL-4G E
80/20
1.2641.264
24795805WLD G2 E
80/20
3.0893.089
274847GR RIDGE ;BU
80/20
0.3660.366
274848CAMPGROVE;RU
80/20
0.1730.173
274849CRESCENT ;1U
80/20
0.1290.129
274851PROVIDENC;RU
80/20
0.1370.137
274853TWINGROVE;U1
80/20
0.4790.479
274854TWINGROVE;U2
80/20
0.4920.492
274861TOP CROP ;1U
80/20
0.2450.245
274862TOP CROP ;2U
80/20
0.4680.468
274863CAYUGA RI;1U
80/20
0.3050.305
274864CAYUGA RI;2U
80/20
0.3050.305
274871GR RIDGE ;2U
80/20
0.1360.136
274877BISHOP HL;1U
80/20
0.2660.266
274878BISHOP HL;2U
80/20
0.2660.266
274879MINONK ;1U
80/20
0.5330.533
274880RADFORD R;1U
80/20
0.6340.634
274887PILOT HIL;1U
80/20
0.4670.467
274888KELLY CRK;1U
80/20
0.4670.467
276615W2-048 GEN
80/20
0.9020.902
276621X2-022 GEN
80/20
2.5692.569
290021O50 E
80/20
2.1322.132
290261S-027 E
80/20
2.2452.245
290265S-028 E
80/20
2.2322.232
293061N-015 E
80/20
1.6031.603
293644O22 E1
80/20
1.5311.531
293645O22 E2
80/20
1.7541.754
293771O-035 E
80/20
0.8490.849
294392P-010 E
80/20
2.0362.036
294401BSHIL;1U E
80/20
1.0641.064
294410BSHIL;2U E
80/20
1.0641.064
917502Z2-087 E
80/20
2.3892.389
918052AA1-018 E OP
80/20
1.7391.739
925581AC1-033 C
80/20
0.2790.279
925582AC1-033 E
80/20
1.8681.868
934721AD1-100 C
80/20
1.9291.929
934722AD1-100 E
80/20
30.0130.01
942111AE2-223 C
80/20
0.8570.857
942112AE2-223 E
80/20
5.7335.733
959351AF2-226 C
80/20
1.0661.066
959352AF2-226 E
80/20
1.5991.599
959611AF2-252 C
80/20
1.1011.101
959612AF2-252 E
80/20
1.6511.651
960281AF2-319 C
80/20
1.0661.066
960282AF2-319 E
80/20
1.5991.599
960611AF2-352 C
80/20
1.1011.101
960612AF2-352 E
80/20
1.6511.651
960971AF2-388 C
80/20
1.8951.895
960972AF2-388 E
80/20
8.8738.873
965651AG1-433 C
80/20
0.9480.948
965652AG1-433 E
80/20
4.4364.436
966091AG1-478 C
80/20
0.2130.213
966092AG1-478 E
80/20
0.320.32
966842AG1-555 E
80/20
5.1515.151
24344305RKG2
80/20
49.81949.819
24379505HDWTR1G C
80/20
0.5180.518
24699105WLD G1 C
80/20
0.2340.234
24753605BLUFF P WF
80/20
0.4330.433
247543V3-007 C
80/20
0.5180.518
247929S-071 E
80/20
1.7341.734
247935V3-007 E
80/20
3.4643.464
24796305HDWTR1G E
80/20
3.4643.464
274674JOLIET 9 ;6U
80/20
6.7426.742
274675JOLIET 29;7U
80/20
17.57617.576
274676JOLIET 29;8U
80/20
17.57617.576
274687WILL CNTY;4U
80/20
16.29816.298
943771AF1-045 C
80/20
3.7493.749
943772AF1-045 E
80/20
2.5032.503
945382AF1-203 E
80/20
1.0781.078
961761AG1-017 C
80/20
0.1560.156
961762AG1-017 E
80/20
0.7170.717
24690905MDL-1G C
80/20
0.3710.371
24691005MDL-2G C
80/20
0.2180.218
24697605MDL-3G C
80/20
0.2190.219
24697905MDL-4G C
80/20
0.1690.169
274890CAYUG;1U E
80/20
1.6261.626
274891CAYUG;2U E
80/20
1.6261.626
925771AC1-053 C
80/20
0.5780.578
925772AC1-053 E
80/20
3.8683.868
938851AE1-113 C
80/20
2.8142.814
938852AE1-113 E
80/20
9.9789.978
24790005FR-11G E
80/20
1.2461.246
24790305FR-22G E
80/20
1.2531.253
939401AE1-172 C
80/20
1.941.94
939402AE1-172 E
80/20
9.0819.081
942651AE2-281 C
80/20
0.2980.298
942652AE2-281 E
80/20
1.8341.834
939781AE1-209 C
80/20
0.7710.771
939782AE1-209 E
80/20
5.1615.161
957382AF2-032 E
80/20
0.1110.111
964782AG1-341 E
80/20
5.6895.689
24755605MDL-5G
80/20
0.2890.289
247943T-127 E
80/20
1.1431.143
251828CLNTESP1
80/20
1.0531.053
25196808ZIMRHP
80/20
48.79548.795
270180AB1-006 W1
80/20
0.3260.326
270181AB1-006 W2
80/20
0.0470.047
270681BRIGHTSTK; R
80/20
0.3570.357
270839OTTER CRK; R
80/20
0.260.26
275149KELLYCK ;1E
80/20
1.8691.869
276174W4-005 E
80/20
3.6233.623
276645AC1-214 C1
80/20
0.1130.113
276646AC1-214 C2
80/20
0.1130.113
276655AB2-047 C1
80/20
0.2230.223
276656AB2-047 C2
80/20
0.2230.223
276668AB2-070 C
80/20
0.3610.361
276675AE2-062 E
80/20
0.0530.053
293519PILOT HIL;1E
80/20
1.8691.869
916212CRESCENT ;1U
80/20
0.5970.597
924048AB2-047 E1
80/20
1.4811.481
924049AB2-047 E2
80/20
1.5041.504
924266AB2-070 E
80/20
2.1882.188
926821AC1-168 C
80/20
0.4360.436
926822AC1-168 E
80/20
2.9272.927
927208AC1-214 E1
80/20
0.4030.403
927209AC1-214 E2
80/20
0.4030.403
930041AB1-006 E1
80/20
2.1822.182
930042AB1-006 E2
80/20
0.3120.312
935141AD1-148 C
80/20
0.8070.807
936371AD2-047 C
80/20
1.4531.453
936372AD2-047 E
80/20
7.0937.093
939321AE1-163 C
80/20
2.092.09
939322AE1-163 E
80/20
12.83712.837
939791AE1-210 C
80/20
0.7710.771
939792AE1-210 E
80/20
5.1615.161
941721AE2-172 C
80/20
2.7562.756
942421AE2-255 C
80/20
1.0661.066
942422AE2-255 E
80/20
3.1983.198
942601AE2-276 C
80/20
3.1363.136
944221AF1-090 C
80/20
1.5711.571
944222AF1-090 E
80/20
7.3577.357
944242AF1-092 E
80/20
6.476.47
944532AF1-118 E
80/20
22.09922.099
944542AF1-119 E
80/20
13.12313.123
945371AF1-202 C
80/20
1.871.87
945372AF1-202 E
80/20
9.1319.131
945391AF1-204 C
80/20
3.1723.172
945392AF1-204 E
80/20
9.5179.517
957372AF2-031 E
80/20
0.6380.638
957842AF2-078 E
80/20
1.1371.137
958861AF2-177 C
80/20
1.4161.416
958862AF2-177 E
80/20
9.4749.474
960261AF2-317 C
80/20
0.3490.349
961161AF2-407 C
80/20
22.20322.203
961171AF2-408 C
80/20
5.9915.991
961501AF2-441 C
80/20
4.2584.258
961502AF2-441 E
80/20
6.3886.388
963581AG1-207 C
80/20
6.7246.724
963841AG1-237 C
80/20
1.2281.228
963842AG1-237 E
80/20
8.2188.218
964611AG1-324 C
80/20
0.3140.314
964612AG1-324 E
80/20
0.4710.471
965331AG1-398 C
80/20
0.1630.163
965462AG1-414 E
80/20
1.6981.698
990901L-005 E
80/20
1.5991.599
270201AC2-176 GEN
80/20
0.2920.292
933596AC2-176 E
80/20
1.9521.952
25016408BKJDB1
80/20
0.2670.267
251827WILLYESP
80/20
0.6880.688
965913AG1-460 BT
80/20
0.0060.006
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
248005 to 242528 ckt 1

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 62 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 199 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-173, AF2-177, AF2-407, AG1-367 and AG1-375 meet the 0.95 leading and lagging PF requirement.

 

AF2-173 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-173, setting Ki to 0.15 from its original value of 0.5.

 

AF2-177 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-177, setting Ki to 0.15 from its original value of 0.5.

 

AG1-367 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-367, setting Kc to 0.1 from its original value of 0.

 

AG1-375 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-375, setting Kc to 0.1 from its original value of 0.

 

AF2-407 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc, Ki and Kp parameters in the plant controller (REPCA1) for AF2-407, setting Kc to 0.15 from its original value of 0.04, setting Ki to 2 from its original value of 0.5, and setting Kp to 0.5 from its original value of 0.

 

Fictitious frequency response at AF2-407 generator bus tripped the queue project due to the action of instantaneous under-frequency and over-frequency relays when faults were applied at Fall Creek 345 kV (AF2-407 POI). Therefore, the relay pickup times for frequency relay instances 96116513 and 96116516 were set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 62 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

62

AF2-173

Solar

AEP

140

140

84

Desoto 345 kV Substation

AF2-177

Wind

AEP

200

200

26

Sorenson – Desoto #2 345 kV Line

AF2-407

Battery Storage

AEP

300

300

300

Fall Creek 345 kV Substation

AG1-367

Solar

AEP

100

100

60

DeSoto 345 kV Substation

AG1-375

Solar

AEP

100

100

100

Sorenson – Desoto #2 345 kV Line

 

Reactive Power Analysis

The reactive power capability of AF2-177 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AC1-174Losantville 345kVIn Service
AC1-175Losantville 345kVIn Service
AC2-090Losantville 345kVIn Service
AC2-111College Corner 138kVEngineering & Procurement
AC2-176Jay 138 kVIn Service
AD1-128Modoc-Delaware 138 kVPartially in Service - Under Construction
AD2-071Strawton-Deer Creek 138 kVSuspended
AE1-207Mississinewa-Gaston 138 kVSuspended
AE1-208Delaware-Van Buren 138 kVSuspended
AE1-209Desoto 345 kVSuspended
AE1-210Desoto 345 kVSuspended
AE2-089Pennville-Adams 138 kVEngineering & Procurement
AE2-169Delaware-Van Buren 138 kVSuspended
AE2-172Mississinewa-Gaston 138 kVSuspended
AE2-219Bluff Point-Randolph 138 kVSuspended
AE2-220Losantville 345 kVEngineering & Procurement
AE2-234Liberty Center-Buckeye Tap 69 kVEngineering & Procurement
AE2-297Madison-Tanners Creek 138 kVIn Service
AF1-071College Corner 138 kVEngineering & Procurement
AF1-118Sorenson-Desoto 345 kVEngineering & Procurement
AF1-119Keystone-Desoto 345 kVEngineering & Procurement
AF1-202Keystone-Desoto 345 kVUnder Construction
AF1-223Keystone-Desoto 345 kVUnder Construction
AF1-268Desoto-Jay 138 kVEngineering & Procurement
AF2-068Jay 138 kVActive
AF2-162Keystone-Desoto 345 kVEngineering & Procurement
AF2-388Keystone-Desoto 345 kVActive
AF2-407Fall Creek 345 kVActive
AF2-408Fall Creek 138 kVEngineering & Procurement
AG1-017Jay 138 kVPartially in Service - Under Construction
AG1-047Jay 138 kVEngineering & Procurement
AG1-324Jay-Desoto 138 kVEngineering & Procurement
AG1-414Mississinewa 138 kVEngineering & Procurement
AG1-433Keystone-DeSoto 345 kVActive
V3-007Desoto-Tanners Creek #1 345kVIn Service
Z2-115Deer Creek 12.47kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
Note: Please communicate with the Affected System Operator regarding the status of the Affected System Study for your project.
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF2-177 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
OVECn9680.0Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° FCost Allocated$5,909,187
Grand Total:$5,909,187

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9680.0
Type
Load Flow
TO
OVEC
RTEP ID / TO ID
n9680.0 / OVEC0001a
Title
Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F
Description
•Remove and replace sixteen (16) existing double circuit towers with taller double circuit custom steel poles. (Towers 11, 14, 45, 47, 52, 57, 59, 61, 63, 66, 67, 71, 77, 84, 91, and 96) •Remove and replace two (2) existing river crossing lattice towers with taller lattice structures. (Towers 2 and 140)
Total Cost ($USD)
$24,006,000
Discounted Total Cost ($USD)
$24,006,000
Allocated Cost ($USD)
$5,909,187
Time Estimate
38 Months

Contributor

FacilityContingency
06DEARB1-06PIERCE 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)B1165.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AF2-17715.0 MW24.6%$5,909,187
AF2-388 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
14.5 MW23.9%$5,736,003
AF2-40724.1 MW39.5%$9,492,808
AG1-433 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
7.3 MW11.9%$2,868,001

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-177


AF2-177 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AF2-177 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AF2-177 One Line Diagram

AF2-177 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.