AG1-226 Final System Impact Study (Retool 2) Report
v2.00 released 2026-05-14 11:54
Dequine-Eugene 345 kV
142.0 MW Capacity / 450.0 MW Energy
Introduction
This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Dolphin Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..
Preface
The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:
- Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
- Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
- Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:
In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:
- PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
- The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
The AG1-226 Final System Impact Study (Retool 1) Report is available for download here.
Retool 2 (if needed):
If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:
- PJM will perform Retool 2 (if necessary) considering only the removal of projects from the model which chose not to execute their agreements after Retool 1.
- The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.
General
The Project Developer has proposed a Solar generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Fountain County, Indiana. The installed facilities will have a total capability of 450.0 MW with 142.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AG1-226 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system tapping the Eugene to Dequine 345 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).
Based on the Final SIS results, the AG1-226 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG1-226 | Cost Subject to Security* | |
| Transmission Owner Interconnection Facilities (TOIF) | $2,930,035 | $2,930,035 | |
| Other Scope | $0 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $25,004,681 | $25,004,681 | |
| Network Upgrades | $8,068,798 | $8,068,798 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $0 | $0 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $12,341,670 | $0 | |
| AFS - Non-PJM Violations | $517,059 ** | $0 ** | |
| Total | $48,862,243 | $36,003,514 | |
* Contributes to calculation for Security. See Security Requirement Section of this report for additional detail.
** This value reflects the results at the time of the report posting and it is subject to change. AFS – Non-PJM Violations are not subject to Security. For latest AFS – Non-PJM Violations, please refer to the latest Affected System Study Report for your project.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Security Requirement
Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).
Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.
Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Security Due for AG1-226
Security has been calculated for the AG1-226 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.
Security Due for AG1-226
In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.
Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.
If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.
Transmission Owner Scope of Work
AG1-226 will interconnect with the AEP transmission system via a new station cut into the Eugene - Dequine 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Scope
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9597.0 | Eugene - Dequine 345 kV Circuit: Proposed AG1-226 345 kV Station tie-in. • Remove two (2) steel lattice structures, #354 and #355, with associated conductor and shield wire along the existing Eugene – Dequine 345 kV Circuit. • Install two (2) single pole, double circuit, steel dead end structures along the existing Eugene – Dequine 345 kV Circuit. • Install two (2) three pole, single circuit, horizontally configured steel dead end structures for the Dequine – Sullivan 345 kV Circuit. • Install two (2) new steel, 120' single circuit, single pole dead-end structures and two (2) spans of double bundle aluminum conductor steel-reinforced ("ACSR") 1272 (Pheasant) transmission line conductor ACSR 159 (Guinea) shield wire routing the Eugene – Proposed AG1-237 Circuit above the Dequine – Sullivan 345 kV Circuit, cutting in the Proposed AG1-226 345 kV Station in an in-and-out arrangement. | $3,463,702 | $2,538,944 | $577,854 | $422,162 | $7,002,662 | $7,002,662 |
| n9596.0 | Eugene 345 kV Station: Review and revise the protective relay settings. Reconfigure the ICON MUX and install SFP transceivers. | $146,060 | $31,397 | $82,884 | $18,728 | $279,069 | $279,069 |
| n9595.0 | Proposed AG1-237 345 kV Station: • Review and revise the protective relay settings. • Reconfigure the ICON MUX, and install SFP transceivers. | $134,232 | $28,384 | $72,890 | $16,183 | $251,689 | $251,689 |
| n9594.0 | Dequine 345 kV Station: Review and revise the protective relay settings. Reconfigure the integrated communications optical network multiplexors (“ICON MUX”) and install Small Form-factor Pluggable (“SFP”) transceivers. | $23,657 | $6,026 | $19,989 | $5,092 | $54,764 | $54,764 |
| n9592.0 | Proposed AG1-226, Proposed AG1-237, Eugene, and Dequine 345 kV Stations: Final Tie in for Fiber installation in new right of way. | $331,151 | $81,362 | $54,669 | $13,432 | $480,614 | $480,614 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9598.0 | Eugene - Deguine 345 kV Circuit: Construct a new 345 kV breaker and a half station, to be operated as a three (3) circuit breaker ring bus, initially expandable to six (6) circuit breakers. • Three (3) 63 kA circuit breakers with associated control relaying. • One (1) 16' x 48' DICM. • Nine (9) motorized breaker disconnect switches. • Six (6) single phase CCVTs, three (3) each on the line exits to the Eugene and Proposed AG1-237 345 kV Stations. • Two (2) single phase station service voltage transformers (SSVT). • Two (2) A-Frame line exit structures, one (1) each for the line exits to Eugene and the Proposed AG1-237 345 kV Stations. • Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures. • A dual, fiber-based ICON MUX current differential line protection relay scheme for the line to the Eugene 345 kV Station. • A dual, fiber-based, ICON MUX current differential line protection relay scheme for the line to the Proposed AG1-237 345 kV Station. • The civil work required to develop a site that accommodates the installation of the above station includes grading of a 350' x 300' pad with an assumed fall across the pad of 5' and a minimum of 2000' x 20' of access road. | $7,094,103 | $7,608,514 | $648,995 | $700,373 | $16,051,985 | $16,051,985 |
| n9593.0 | Proposed AG1-226, Proposed AG1-237, Eugene, and Dequine 345 kV Stations: • Install exit transitions at the Proposed AG1-226, Proposed AG1-237, and Eugene 345 kV Stations. • Install a new fiber optic cable path consisting of 25.1 miles of ADLT cable in new underground right-of-way. | $6,008,977 | $1,487,051 | $1,177,654 | $279,014 | $8,952,696 | $8,952,696 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | • Installation of one (1) A-frame dead-end take off structure for the generation lead circuit line exit. • Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage and one span of double bundle aluminum conductor steel-reinforced ("ACSR") 954 (Cardinal) transmission line conductor with 7#8 Alumoweld shield wire for the generation lead circuit extending from the Proposed AG1-226 345 kV Station. • Extension of two (2) underground all dielectric loose tube ("ADLT") fiber optic cables from the Proposed AG1-226 345 kV Station control house to fiber demarcation splice boxes to support direct fiber relaying between the Proposed AG1-226 345 kV and Project Developer's collector stations. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station. • Installation of a standard revenue metering package, including three (3) single phase current transformers ("CT"), three (3) single phase coupling capacitor voltage transformers ("CCVT"), associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module ("DICM")-installed metering panel, for the generation lead circuit at the Proposed AG1-226 345 kV Station. • Installation of a dual, direct-fiber, current differential protection scheme for the generation lead circuit. | $1,602,066 | $869,267 | $304,726 | $153,976 | $2,930,035 | $2,930,035 |
Based on the scope of work for the Interconnection Facilities, it is expected to take 31 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. The maximum schedule is based off of AEP assumed long lead material ordering not considering allocation of existing material production slots, advanced progress enabled by Engineering and Procurement Agreements, or other schedule expediting methods. AEP may be able to allocate material production slots for long lead time materials to expedite this schedule. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to these agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AG1-226 was evaluated as a 450.0 MW (142.0 MW Capacity) injection in the AEP area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P7-1_#11014___SRT-A-1 | Tower | AC | 106.03 % | 1374.0 | B | 1456.89 | 239.04 | |
| GD1 | AEP/DEI | 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | AEP_P7-1_#11042___SRT-A | Tower | AC | 104.37 % | 1374.0 | B | 1434.0 | 156.72 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD1 | AEP/NIPS | 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line | AEP_P1-2_#8807_SRT-A | OP | AC | 130.68 % | 1868.0 | B | 2441.14 | 199.76 | |
| GD1 | AEP/NIPS | 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line | AEP_P1-2_#8695_SRT-A | OP | AC | 130.68 % | 1868.0 | B | 2441.14 | 199.76 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Light Load Analysis
The New Service Request AG1-226 was evaluated as a 450.0 MW injection in the AEP area.
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests AF1-204 and AG1-226 in PJM Transition Cycle 1, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.
Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 131 contingencies were studied, each with a 20 second simulation time period. Studied faults included:
a) Steady-state operation (20 second run),
a) Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),
b) Single-phase bus faults with normal clearing time,
c) Single-phase faults with stuck breakers,
d) Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).
There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2027 peak load case:
a) Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AF1-204 and AG1-226 meet the 0.95 leading and lagging PF requirement.
AG1-237 exhibited slow reactive power recovery for P7.04 contingency. This issue did not cause instability in the system and the models can be tuned if required to achieve a faster reactive power output settlement.
No mitigations were found to be required.
Table 1: TC1 Cluster 64 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
64 | AF1-204 | Wind | AEP | 255 | 255 | 63.75 | Eugene 345 kV |
AG1-226 | Solar | AEP | 450 | 450 | 142 | Eugene-Dequine 345 kV |
Reactive Power Analysis
The reactive power capability of AG1-226 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AB1-006 | Meadow Lake 345kV | In Service |
| AB1-080 | Dumont-Olive 345kV | In Service |
| AB1-087 | Sullivan 345kV #1 | Under Construction |
| AB1-088 | Sullivan 345kV #2 | Engineering & Procurement |
| AB2-047 | Brokaw-Pontiac Midpoint | In Service |
| AB2-070 | Mt. Pulaski-Brokaw | In Service |
| AC1-053 | Lanesville-Brokaw | In Service |
| AC1-168 | Kewanee-Streator | Suspended |
| AC2-154 | Davis Creek 138kV | Engineering & Procurement |
| AC2-157 | Sullivan 345 kV | Partially in Service - Under Construction |
| AD1-013 | Twombly Road 138kV | Engineering & Procurement |
| AD1-100 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Under Construction |
| AD2-047 | Davis Creek 138 kV | Suspended |
| AD2-060 | Davis Creek 138kV | Engineering & Procurement |
| AD2-066 | Mazon-Crescent Ridge 138 kV | Under Construction |
| AD2-100 | Kincaid-Pana 345 kV | Suspended |
| AD2-131 | Kincaid-Pana 345kV | Suspended |
| AE1-113 | Mole Creek 345 kV | Under Construction |
| AE1-163 | Powerton-Nevada 345 kV | Under Construction |
| AE1-166 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE1-170 | Kenzie Creek-Colby 138 kV | Suspended |
| AE1-205 | McLean 345 kV | Engineering & Procurement |
| AE2-045 | Olive-Reynolds 345 kV | Engineering & Procurement |
| AE2-152 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE2-223 | McLean 345 kV | Engineering & Procurement |
| AE2-255 | Molecreek 345 kV | Under Construction |
| AE2-261 | Kincaid-Pana 345 kV | Engineering & Procurement |
| AE2-267 | Woodsdale 345 kV | Engineering & Procurement |
| AE2-276 | Sullivan 345kV | Engineering & Procurement |
| AE2-281 | Powerton-Nevada 345 kV | Under Construction |
| AE2-341 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-030 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-090 | Kincaid-Pana | Engineering & Procurement |
| AF1-158 | Edison-Gravel Pit 138 kV | In Service |
| AF1-204 | Eugene 345 kV | Engineering & Procurement |
| AF1-207 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF1-215 | Olive-Reynolds 345 kV | In Service |
| AF1-322 | Meadow Lake 345 kV | Engineering & Procurement |
| AF1-331 | Twombley Road | Engineering & Procurement |
| AF2-027 | Zion Energy Center 345 kV | Engineering & Procurement |
| AF2-031 | Calumet | Engineering & Procurement |
| AF2-032 | Kincaid 345 kV | Withdrawn |
| AF2-078 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF2-083 | Kenzie Creek-Stone Lake 69 kV | Under Construction |
| AF2-095 | Davis Creek 138 kV | Engineering & Procurement |
| AF2-132 | Reynolds-Olive #1 345 kV | Under Construction |
| AF2-133 | Reynolds-Olive #2 345 kV | Under Construction |
| AF2-134 | Olive-Reynolds #2 345 kV | In Service |
| AF2-142 | Nevada 345 kV | Engineering & Procurement |
| AF2-143 | Powerton-Nevada 345 kV | Engineering & Procurement |
| AF2-205 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AF2-225 | McLean 345 kV | Engineering & Procurement |
| AF2-226 | Katydid Road 345 kV | Engineering & Procurement |
| AF2-252 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-305 | Brokaw-Lanesville 345 kV | In Service |
| AF2-319 | Katydid Road 345 kV | Engineering & Procurement |
| AF2-350 | Kensington 138 kV | Engineering & Procurement |
| AF2-352 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-359 | Olive-University Park 345 kV | Engineering & Procurement |
| AF2-366 | Crego Rd 138 kV | Engineering & Procurement |
| AF2-441 | Burnham 138kV | Engineering & Procurement |
| AG1-118 | Sugar Grove-Waterman 138kV | Engineering & Procurement |
| AG1-127 | Crego Rd 138 kV | Engineering & Procurement |
| AG1-237 | Dequine-Eugene 345 kV | Engineering & Procurement |
| AG1-302 | Olive-Reynolds #1 345 kV | Under Construction |
| AG1-349 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AG1-374 | Blue Mound 345 kV | Engineering & Procurement |
| AG1-436 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-447 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-460 | Kincaid-Pana 345 kV | Engineering & Procurement |
| AG1-478 | Wilmington 34.5 kV | Engineering & Procurement |
| AG1-513 | Aurora 138 kV | Suspended |
| AG1-555 | Dequine 345 kV | Engineering & Procurement |
| W2-048 | Brokaw-Lanesville | In Service |
| W4-005 | Blue Mound-Latham | In Service |
| X2-022 | Brokaw-Lanesville | In Service |
| X3-005 | Wildwood 12kV | In Service |
| Y1-054 | Rochelle 138kV | In Service |
| Z2-087 | Pontiac MidPoint-Brokaw 345kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
| AG1-226 System Reinforcements: | TO | Trans Owner ID | Title | Category | Allocated Cost ($USD) | |||||
|---|---|---|---|---|---|---|---|---|---|---|
| DEI | DEI_TC1_16079 | Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. | Cost Allocated | $12,341,670 | ||||||
| Grand Total: | $12,341,670 | |||||||||
System Reinforcement
- Type
- Load Flow
- TO
- DEI
- RTEP ID / TO ID
- (Pending) / DEI_TC1_16079
- Title
- Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor.
- Description
- Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. Projected in-service date is 6/1/2030.
- Total Cost ($USD)
- $23,213,515
- Allocated Cost ($USD)
- $12,341,670
- Time Estimate
- 48 Months
Contributor
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (Any) |
|
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AE2-223 ⧉ McLean 345kV (ComEd): This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-223, AF2-225 | 11.4 MW | 2.5% | $586,216 |
| AE2-261 ⧉ Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 | 26.3 MW | 5.9% | $1,358,664 |
| AF1-204 | 135.5 MW | 30.1% | $6,994,424 |
| AF2-225 ⧉ McLean 345kV (ComEd): This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-223, AF2-225 | 11.4 MW | 2.5% | $586,216 |
| AG1-226 | 239.0 MW | 53.2% | $12,341,670 |
| AG1-374 | 23.4 MW | 5.2% | $1,210,019 |
| AG1-460 ⧉ Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI: AE2-261, AG1-460 | 2.6 MW | 0.6% | $136,305 |
Affected System - Non-PJM Identified Violations
In coordination with other Affected System Operators, PJM has determined that the Affected System Operator for this project that requires an Affected System Study. For the latest Affected System Study results pertaining this project, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM lists any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.
System Reinforcements
Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| Grand Total: | $0 | ||||
PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP_TC1_13727
- Title
- AEP SE rating is 1868 MVA
- Description
- AEP SE rating is 1868 MVA
- Total Cost ($USD)
- $0
- Discounted Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- 0 to 1 Months
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
| Facility | Contingency | ||||||||
|---|---|---|---|---|---|---|---|---|---|
| 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line | (Any) |
|