AG1-341 Final System Impact Study (Retool 1) Report

v1.00 released 2025-12-08 18:22

Summer Shade 161 kV

63.6 MW Capacity / 106.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Summer Shade Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is East Kentucky Power Cooperative, Inc..

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the TC1 projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.
Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of TC1 projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed a Solar/Storage generating facility located in the East Kentucky Power Cooperative, Inc. zone — Metcalfe County, Kentucky. The installed facilities will have a total capability of 106.0 MW with 63.6 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-341
Project Name:
Summer Shade 161 kV
Project Developer Name:
Summer Shade Solar, LLC
State:
Kentucky
County:
Metcalfe
Transmission Owner:
East Kentucky Power Cooperative, Inc.
MFO:
106.0
MWE:
106.0
MWC:
63.6
Battery Storage Specification:
424.0 MWh, 4.0-hr class
Grid Charging:
No
Fuel Type:
Solar/Storage
Basecase Study Year:
2027

Physical Interconnection Facility Study

Reviewed

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-341 will interconnect on the East Kentucky Power Cooperative, Inc. transmission system at the Summer Shade 161kV substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AG1-341 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AG1-341Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$1,683,000$1,683,000
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$6,002,000$6,002,000
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$7,562,355$0
Total$15,247,355$7,685,000

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AG1-341

Security has been calculated for the AG1-341 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AG1-341
Project(s): AG1-341
Final Agreement Security (A): $7,685,000
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $7,685,000
Security on Hand with PJM (D): $7,685,000
Additional Security Due at Agreement Execution (E): C D = $0
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

EKPC will connect the Generating Facility to the EKPC transmission system via a direct connection into Summer Shade 161 kV substation. EKPC will expand the existing Summer Shade 161 substation. EKPC will construct a 161 kV monopole dead-end structure and foundation outside of the fence with a 3-pole disconnect switch mounted to the monopole structure. There are not additional network upgrades identified at adjacent EKPC substations.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9635.0

Expansion of existing 161 kV Summer Shade substation to include one (1) 161 kV A-Frame substation structure, one (1) 161 kV 2000 amp Circuit Breaker, four (4) 2000 amp switches (includes PCO switch), three (3) 161 kV metering CTs, and three (3) 108 kV station class surge arrestors.

$2,400,000$2,782,000$738,000$82,000$6,002,000$6,002,000
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install one (1) 161 kV dead-end structure and foundation, 161 kV 3-pole disconnect switch attached to the new dead-end structure, line conductor from the dead-end structure to switching station bus position, installation of two (2) 48-strand fiber optic cables, interconnection metering and telecommunications facilities, a 161 kV circuit breaker and associated 161 disconnect switches, and a relay panel for the line.

$708,000$745,000$207,000$23,000$1,683,000$1,683,000

Based on the scope of work for the Interconnection Facilities, it is expected to take 28 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

EKPC anticipates that it will take 28 months after the signing of the Generator Interconnection Agreement and the project kickoff call is subsequently held to complete the physical interconnection projects. This assumes no delays due to permitting or environmental issues, and that all necessary outages can be taken as needed to maintain this schedule.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. EKPC interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG1-341 was evaluated as a 106.0 MW (63.6 MW Capacity) injection in the EKPC area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1EKPC/LGEE
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
EKPC_P7-1_COOP 161 DBL 2_SRT-A
TowerAC100.5 %105.0B105.528.4
GD1EKPC/LGEE
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
EKPC_P7-1_LAURL 161 DBL_SRT-A
TowerAC106.47 %277.0B294.9312.22
GD1EKPC/LGEE
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
EKPC_P4-5_LAURL S50-1024_SRT-A
BreakerAC106.47 %277.0B294.9312.22
GD1EKPC/LGEE
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
EKPC_P4-5_LAURL S50-1014_SRT-A
BreakerAC106.14 %277.0B294.0212.24
GD1EKPC/LGEE
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
EKPC_P2-2_LAUREL CO 161_SRT-A
BusAC106.14 %277.0B294.0212.24

Details for 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:EKPC/LGEE
Facility Description:
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
Contingency Name:
EKPC_P7-1_COOP 161 DBL 2_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:100.5 %
Rating:105.0 MVA
Rating Type:B
MVA to Mitigate:105.52
MW Contribution:8.4
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:EKPC/LGEE
Facility Description:
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
Contingency Name:
EKPC_P7-1_COOP 161 DBL 2_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:99.43 %
Rating:105.0 MVA
Rating Type:B
MVA to Mitigate:104.4
MW Contribution:8.4
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
964901AG1-354 C
Adder
7.2682352941176476.178
964902AG1-354 E
Adder
4.8458823529411764.119
943701AF1-038 C
50/50
8.4088.408
943702AF1-038 E
50/50
5.6055.605
943821AF1-050 C
Adder
2.9811764705882352.534
943822AF1-050 E
Adder
1.9870588235294121.689
945382AF1-203 E
Adder
0.72235294117647060.614
3429001COOPER1 G
50/50
5.115.11
3429031COOPER2 G
50/50
9.9119.911
939132AE1-143 E
Adder
3.12588235294117662.657
940832AE2-071 E
Adder
1.26470588235294111.075
339206AE1-143 C
Adder
6.3070588235294115.361
944151AF1-083 C
Adder
2.92470588235294172.486
944152AF1-083 E
Adder
1.94941176470588241.657
964781AG1-341 C
Adder
5.0411764705882364.285
964782AG1-341 E
Adder
3.36117647058823542.857
966021AG1-471 C
50/50
4.6414.641
966022AG1-471 E
50/50
2.8362.836
950011AG9-010
External Queue
8.6052598953247078.605259895324707
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.1073.107
CBM West 2LTFEXP_CBM-W2->PJM
CBM
3.5913.591
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
1.6741.674
G-007PJM->LTFIMP_G-007
CMTX_NF
0.0890.089
NYPJM->LTFIMP_NY
CLTF
0.0470.047
WECLTFEXP_WEC->PJM
CLTF
0.0660.066
CPLELTFEXP_CPLE->PJM
CLTF
0.0810.081
TVALTFEXP_TVA->PJM
CLTF
1.2851.285
MECLTFEXP_MEC->PJM
CLTF
0.5590.559
LAGNLTFEXP_LAGN->PJM
CLTF
1.211.21
SIGELTFEXP_SIGE->PJM
CLTF
0.0430.043
O66PJM->LTFIMP_O-066
CMTX_NF
0.5690.569
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.0380.038

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P7-1_LAURL 161 DBL_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P7-1_LAURL 161 DBL_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:106.47 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:294.93
MW Contribution:12.22
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P7-1_LAURL 161 DBL_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:105.98 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:293.57
MW Contribution:12.21
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
964901AG1-354 C
50/50
10.68810.688
964902AG1-354 E
50/50
7.1257.125
943701AF1-038 C
50/50
6.6266.626
943702AF1-038 E
50/50
4.4184.418
943821AF1-050 C
50/50
4.4474.447
943822AF1-050 E
50/50
2.9652.965
945381AF1-203 C
50/50
0.2290.229
945382AF1-203 E
50/50
0.9620.962
3424422W GLASGOW
50/50
0.0170.017
3429001COOPER1 G
50/50
10.51510.515
3429031COOPER2 G
50/50
20.45820.458
3429451LAUREL 1G
50/50
6.3646.364
939132AE1-143 E
50/50
4.8744.874
940831AE2-071 C
50/50
0.4040.404
940832AE2-071 E
50/50
1.6841.684
339206AE1-143 C
50/50
9.8339.833
944151AF1-083 C
50/50
4.4674.467
944152AF1-083 E
50/50
2.9782.978
964781AG1-341 C
50/50
7.3317.331
964782AG1-341 E
50/50
4.8884.888
966021AG1-471 C
50/50
6.5516.551
966022AG1-471 E
50/50
4.0034.003
950011AG9-010
External Queue
13.441103935241713.4411039352417
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.6133.613
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.1215.121
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
2.5362.536
G-007PJM->LTFIMP_G-007
CMTX_NF
0.1730.173
NYPJM->LTFIMP_NY
CLTF
0.0920.092
WECLTFEXP_WEC->PJM
CLTF
0.0780.078
CPLELTFEXP_CPLE->PJM
CLTF
0.1160.116
TVALTFEXP_TVA->PJM
CLTF
1.921.92
MECLTFEXP_MEC->PJM
CLTF
0.750.75
LAGNLTFEXP_LAGN->PJM
CLTF
1.7841.784
SIGELTFEXP_SIGE->PJM
CLTF
0.0560.056
O66PJM->LTFIMP_O-066
CMTX_NF
1.1091.109
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.0540.054

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1024_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P4-5_LAURL S50-1024_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:106.47 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:294.93
MW Contribution:12.22
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P4-5_LAURL S50-1024_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:105.97 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:293.54
MW Contribution:12.21
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
964901AG1-354 C
50/50
10.68810.688
964902AG1-354 E
50/50
7.1257.125
943701AF1-038 C
50/50
6.6266.626
943702AF1-038 E
50/50
4.4184.418
943821AF1-050 C
50/50
4.4474.447
943822AF1-050 E
50/50
2.9652.965
945381AF1-203 C
50/50
0.2290.229
945382AF1-203 E
50/50
0.9620.962
3424422W GLASGOW
50/50
0.0170.017
3429001COOPER1 G
50/50
10.51510.515
3429031COOPER2 G
50/50
20.45820.458
3429451LAUREL 1G
50/50
6.3646.364
939132AE1-143 E
50/50
4.8744.874
940831AE2-071 C
50/50
0.4040.404
940832AE2-071 E
50/50
1.6841.684
339206AE1-143 C
50/50
9.8339.833
944151AF1-083 C
50/50
4.4674.467
944152AF1-083 E
50/50
2.9782.978
964781AG1-341 C
50/50
7.3317.331
964782AG1-341 E
50/50
4.8884.888
966021AG1-471 C
50/50
6.5516.551
966022AG1-471 E
50/50
4.0034.003
950011AG9-010
External Queue
13.44110488891601613.441104888916016
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.6133.613
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.1215.121
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
2.5362.536
G-007PJM->LTFIMP_G-007
CMTX_NF
0.1730.173
NYPJM->LTFIMP_NY
CLTF
0.0920.092
WECLTFEXP_WEC->PJM
CLTF
0.0780.078
CPLELTFEXP_CPLE->PJM
CLTF
0.1160.116
TVALTFEXP_TVA->PJM
CLTF
1.921.92
MECLTFEXP_MEC->PJM
CLTF
0.750.75
LAGNLTFEXP_LAGN->PJM
CLTF
1.7841.784
SIGELTFEXP_SIGE->PJM
CLTF
0.0560.056
O66PJM->LTFIMP_O-066
CMTX_NF
1.1091.109
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.0540.054

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1014_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P4-5_LAURL S50-1014_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:106.14 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:294.02
MW Contribution:12.24
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P4-5_LAURL S50-1014_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:105.65 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:292.65
MW Contribution:12.23
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
964901AG1-354 C
50/50
10.70410.704
964902AG1-354 E
50/50
7.1367.136
943701AF1-038 C
50/50
6.6396.639
943702AF1-038 E
50/50
4.4264.426
943821AF1-050 C
50/50
4.4544.454
943822AF1-050 E
50/50
2.9692.969
945381AF1-203 C
50/50
0.2290.229
945382AF1-203 E
50/50
0.9640.964
3424422W GLASGOW
50/50
0.0170.017
3429001COOPER1 G
50/50
10.52410.524
3429031COOPER2 G
50/50
20.47520.475
3429451LAUREL 1G
50/50
6.3696.369
939132AE1-143 E
50/50
4.884.88
940831AE2-071 C
50/50
0.4050.405
940832AE2-071 E
50/50
1.6871.687
339206AE1-143 C
50/50
9.8469.846
944151AF1-083 C
50/50
4.4734.473
944152AF1-083 E
50/50
2.9822.982
964781AG1-341 C
50/50
7.3437.343
964782AG1-341 E
50/50
4.8954.895
966021AG1-471 C
50/50
6.5616.561
966022AG1-471 E
50/50
4.014.01
950011AG9-010
External Queue
13.46012592315673813.460125923156738
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.6283.628
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.1495.149
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
2.5792.579
G-007PJM->LTFIMP_G-007
CMTX_NF
0.1730.173
NYPJM->LTFIMP_NY
CLTF
0.0920.092
WECLTFEXP_WEC->PJM
CLTF
0.0790.079
CPLELTFEXP_CPLE->PJM
CLTF
0.1190.119
TVALTFEXP_TVA->PJM
CLTF
1.931.93
MECLTFEXP_MEC->PJM
CLTF
0.7540.754
LAGNLTFEXP_LAGN->PJM
CLTF
1.7951.795
SIGELTFEXP_SIGE->PJM
CLTF
0.0560.056
O66PJM->LTFIMP_O-066
CMTX_NF
1.1081.108
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.0560.056

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P2-2_LAUREL CO 161_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P2-2_LAUREL CO 161_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:106.14 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:294.02
MW Contribution:12.24
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
Contingency Name:
EKPC_P2-2_LAUREL CO 161_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:105.66 %
Rating:277.0 MVA
Rating Type:B
MVA to Mitigate:292.69
MW Contribution:12.23
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
964901AG1-354 C
50/50
10.70410.704
964902AG1-354 E
50/50
7.1367.136
943701AF1-038 C
50/50
6.6396.639
943702AF1-038 E
50/50
4.4264.426
943821AF1-050 C
50/50
4.4544.454
943822AF1-050 E
50/50
2.9692.969
945381AF1-203 C
50/50
0.2290.229
945382AF1-203 E
50/50
0.9640.964
3424422W GLASGOW
50/50
0.0170.017
3429001COOPER1 G
50/50
10.52410.524
3429031COOPER2 G
50/50
20.47520.475
3429451LAUREL 1G
50/50
6.3696.369
939132AE1-143 E
50/50
4.884.88
940831AE2-071 C
50/50
0.4050.405
940832AE2-071 E
50/50
1.6871.687
339206AE1-143 C
50/50
9.8469.846
944151AF1-083 C
50/50
4.4734.473
944152AF1-083 E
50/50
2.9822.982
964781AG1-341 C
50/50
7.3437.343
964782AG1-341 E
50/50
4.8954.895
966021AG1-471 C
50/50
6.5616.561
966022AG1-471 E
50/50
4.014.01
950011AG9-010
External Queue
13.46012592315673813.460125923156738
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.6283.628
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.1495.149
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
2.5792.579
G-007PJM->LTFIMP_G-007
CMTX_NF
0.1730.173
NYPJM->LTFIMP_NY
CLTF
0.0920.092
WECLTFEXP_WEC->PJM
CLTF
0.0790.079
CPLELTFEXP_CPLE->PJM
CLTF
0.1190.119
TVALTFEXP_TVA->PJM
CLTF
1.931.93
MECLTFEXP_MEC->PJM
CLTF
0.7540.754
LAGNLTFEXP_LAGN->PJM
CLTF
1.7951.795
SIGELTFEXP_SIGE->PJM
CLTF
0.0560.056
O66PJM->LTFIMP_O-066
CMTX_NF
1.1081.108
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.0560.056
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
CONTINGENCY 'EKPC_P4-5_LAURL S50-1014_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
CONTINGENCY 'EKPC_P2-2_LAUREL CO 161_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
342287 to 324531 ckt 1
342718 to 324141 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AG1-341 was evaluated as a 106.0 MW injection in the EKPC area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
AEP_P1-2_#7422_16_SRT-A
SingleAC126.36 %1180.0B1491.0911.47

Details for 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:126.36 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1491.09
MW Contribution:11.47
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
943031AE2-326 C
80/20
6.3456.345
943032AE2-326 E
80/20
4.234.23
24289205AMG2
80/20
56.44356.443
24289305AMG3
80/20
92.61692.616
24344305RKG2
80/20
78.52378.523
274675JOLIET 29;7U
Adder
30.56470588235294325.98
274676JOLIET 29;8U
Adder
30.56470588235294325.98
944971AF1-162 C
80/20
7.9367.936
944972AF1-162 E
80/20
5.2915.291
945382AF1-203 E
80/20
2.1692.169
964782AG1-341 E
80/20
11.47211.472
223403AG1-063 C
Adder
-0.07176470588235294-0.061
940351AE2-019 C
Adder
-15.808235294117647-13.437
966391AG1-508 C
80/20
1.4661.466
966392AG1-508 E
80/20
8.5158.515
24289905CRG1H
80/20
8.58.5
24290005CRG1L
80/20
7.1147.114
24290105CRG2H
80/20
8.5548.554
24290205CRG2L
80/20
7.1757.175
24375805MIDDLECR
80/20
0.2630.263
270167AD2-205 E
80/20
0.7890.789
940353AE2-019 BT
80/20
15.80815.808
957193AF2-013 BT
80/20
11.39811.398
962183AG1-063 BAT
80/20
0.2560.256
962553AG1-104 BT
80/20
30.74130.741
963033AG1-152 BT
80/20
13.62813.628
963693AG1-221 BT
80/20
6.5036.503
964443AG1-307 BT
80/20
2.0032.003
966143AG1-483 BAT
80/20
55.90555.905
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
242512 to 242515 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP/OVEC
06KYGER-05SPORN 345.0 kV Ckt 1 line
AEP_P1-2_#7441_100545_SRT-A
SingleDC101.06 %1204.0B1216.725.69

Details for 06KYGER-05SPORN 345.0 kV Ckt 1 line l/o AEP_P1-2_#7441_100545_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
Contingency Type:Single
DC|AC:DC
Final Cycle Loading:101.06 %
Rating:1204.0 MVA
Rating Type:B
MVA to Mitigate:1216.72
MW Contribution:5.69
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24725505WLD G2 C
80/20
0.2270.227
24385905FR-11G C
80/20
0.3740.374
24386205FR-12G C
80/20
0.1820.182
24386405FR-21G C
80/20
0.1890.189
24386605FR-22G C
80/20
0.1890.189
24387005FR-3G C
80/20
0.1820.182
24387305FR-4G C
80/20
0.4240.424
24790105FR-12G E
80/20
1.2271.227
24790205FR-21G E
80/20
1.3041.304
24790405FR-3G E
80/20
2.432.43
24790505FR-4G E
80/20
1.9261.926
24790605MDL-1G E
80/20
2.5232.523
24790705MDL-2G E
80/20
1.2151.215
24791205MDL-3G E
80/20
1.2141.214
24791305MDL-4G E
80/20
1.2641.264
24795805WLD G2 E
80/20
3.0893.089
274847GR RIDGE ;BU
80/20
0.3660.366
274848CAMPGROVE;RU
80/20
0.1730.173
274849CRESCENT ;1U
80/20
0.1290.129
274851PROVIDENC;RU
80/20
0.1370.137
274853TWINGROVE;U1
80/20
0.4790.479
274854TWINGROVE;U2
80/20
0.4920.492
274861TOP CROP ;1U
80/20
0.2450.245
274862TOP CROP ;2U
80/20
0.4680.468
274863CAYUGA RI;1U
80/20
0.3050.305
274864CAYUGA RI;2U
80/20
0.3050.305
274871GR RIDGE ;2U
80/20
0.1360.136
274877BISHOP HL;1U
80/20
0.2660.266
274878BISHOP HL;2U
80/20
0.2660.266
274879MINONK ;1U
80/20
0.5330.533
274880RADFORD R;1U
80/20
0.6340.634
274887PILOT HIL;1U
80/20
0.4670.467
274888KELLY CRK;1U
80/20
0.4670.467
276615W2-048 GEN
80/20
0.9020.902
276621X2-022 GEN
80/20
2.5692.569
290021O50 E
80/20
2.1322.132
290261S-027 E
80/20
2.2452.245
290265S-028 E
80/20
2.2322.232
293061N-015 E
80/20
1.6031.603
293644O22 E1
80/20
1.5311.531
293645O22 E2
80/20
1.7541.754
293771O-035 E
80/20
0.8490.849
294392P-010 E
80/20
2.0362.036
294401BSHIL;1U E
80/20
1.0641.064
294410BSHIL;2U E
80/20
1.0641.064
917502Z2-087 E
80/20
2.3892.389
918052AA1-018 E OP
80/20
1.7391.739
925581AC1-033 C
80/20
0.2790.279
925582AC1-033 E
80/20
1.8681.868
934721AD1-100 C
80/20
1.9291.929
934722AD1-100 E
80/20
30.0130.01
942111AE2-223 C
80/20
0.8570.857
942112AE2-223 E
80/20
5.7335.733
959351AF2-226 C
80/20
1.0661.066
959352AF2-226 E
80/20
1.5991.599
959611AF2-252 C
80/20
1.1011.101
959612AF2-252 E
80/20
1.6511.651
960281AF2-319 C
80/20
1.0661.066
960282AF2-319 E
80/20
1.5991.599
960611AF2-352 C
80/20
1.1011.101
960612AF2-352 E
80/20
1.6511.651
960971AF2-388 C
80/20
1.8951.895
960972AF2-388 E
80/20
8.8738.873
965651AG1-433 C
80/20
0.9480.948
965652AG1-433 E
80/20
4.4364.436
966091AG1-478 C
80/20
0.2130.213
966092AG1-478 E
80/20
0.320.32
966842AG1-555 E
80/20
5.1515.151
24344305RKG2
80/20
49.81949.819
24379505HDWTR1G C
80/20
0.5180.518
24699105WLD G1 C
80/20
0.2340.234
24753605BLUFF P WF
80/20
0.4330.433
247543V3-007 C
80/20
0.5180.518
247929S-071 E
80/20
1.7341.734
247935V3-007 E
80/20
3.4643.464
24796305HDWTR1G E
80/20
3.4643.464
274674JOLIET 9 ;6U
80/20
6.7426.742
274675JOLIET 29;7U
80/20
17.57617.576
274676JOLIET 29;8U
80/20
17.57617.576
274687WILL CNTY;4U
80/20
16.29816.298
943771AF1-045 C
80/20
3.7493.749
943772AF1-045 E
80/20
2.5032.503
945382AF1-203 E
80/20
1.0781.078
961761AG1-017 C
80/20
0.1560.156
961762AG1-017 E
80/20
0.7170.717
24690905MDL-1G C
80/20
0.3710.371
24691005MDL-2G C
80/20
0.2180.218
24697605MDL-3G C
80/20
0.2190.219
24697905MDL-4G C
80/20
0.1690.169
274890CAYUG;1U E
80/20
1.6261.626
274891CAYUG;2U E
80/20
1.6261.626
925771AC1-053 C
80/20
0.5780.578
925772AC1-053 E
80/20
3.8683.868
938851AE1-113 C
80/20
2.8142.814
938852AE1-113 E
80/20
9.9789.978
24790005FR-11G E
80/20
1.2461.246
24790305FR-22G E
80/20
1.2531.253
939401AE1-172 C
80/20
1.941.94
939402AE1-172 E
80/20
9.0819.081
942651AE2-281 C
80/20
0.2980.298
942652AE2-281 E
80/20
1.8341.834
939781AE1-209 C
80/20
0.7710.771
939782AE1-209 E
80/20
5.1615.161
957382AF2-032 E
80/20
0.1110.111
964782AG1-341 E
80/20
5.6895.689
24755605MDL-5G
80/20
0.2890.289
247943T-127 E
80/20
1.1431.143
251828CLNTESP1
80/20
1.0531.053
25196808ZIMRHP
80/20
48.79548.795
270180AB1-006 W1
80/20
0.3260.326
270181AB1-006 W2
80/20
0.0470.047
270681BRIGHTSTK; R
80/20
0.3570.357
270839OTTER CRK; R
80/20
0.260.26
275149KELLYCK ;1E
80/20
1.8691.869
276174W4-005 E
80/20
3.6233.623
276645AC1-214 C1
80/20
0.1130.113
276646AC1-214 C2
80/20
0.1130.113
276655AB2-047 C1
80/20
0.2230.223
276656AB2-047 C2
80/20
0.2230.223
276668AB2-070 C
80/20
0.3610.361
276675AE2-062 E
80/20
0.0530.053
293519PILOT HIL;1E
80/20
1.8691.869
916212CRESCENT ;1U
80/20
0.5970.597
924048AB2-047 E1
80/20
1.4811.481
924049AB2-047 E2
80/20
1.5041.504
924266AB2-070 E
80/20
2.1882.188
926821AC1-168 C
80/20
0.4360.436
926822AC1-168 E
80/20
2.9272.927
927208AC1-214 E1
80/20
0.4030.403
927209AC1-214 E2
80/20
0.4030.403
930041AB1-006 E1
80/20
2.1822.182
930042AB1-006 E2
80/20
0.3120.312
935141AD1-148 C
80/20
0.8070.807
936371AD2-047 C
80/20
1.4531.453
936372AD2-047 E
80/20
7.0937.093
939321AE1-163 C
80/20
2.092.09
939322AE1-163 E
80/20
12.83712.837
939791AE1-210 C
80/20
0.7710.771
939792AE1-210 E
80/20
5.1615.161
941721AE2-172 C
80/20
2.7562.756
942421AE2-255 C
80/20
1.0661.066
942422AE2-255 E
80/20
3.1983.198
942601AE2-276 C
80/20
3.1363.136
944221AF1-090 C
80/20
1.5711.571
944222AF1-090 E
80/20
7.3577.357
944242AF1-092 E
80/20
6.476.47
944532AF1-118 E
80/20
22.09922.099
944542AF1-119 E
80/20
13.12313.123
945371AF1-202 C
80/20
1.871.87
945372AF1-202 E
80/20
9.1319.131
945391AF1-204 C
80/20
3.1723.172
945392AF1-204 E
80/20
9.5179.517
957372AF2-031 E
80/20
0.6380.638
957842AF2-078 E
80/20
1.1371.137
958861AF2-177 C
80/20
1.4161.416
958862AF2-177 E
80/20
9.4749.474
960261AF2-317 C
80/20
0.3490.349
961161AF2-407 C
80/20
22.20322.203
961171AF2-408 C
80/20
5.9915.991
961501AF2-441 C
80/20
4.2584.258
961502AF2-441 E
80/20
6.3886.388
963581AG1-207 C
80/20
6.7246.724
963841AG1-237 C
80/20
1.2281.228
963842AG1-237 E
80/20
8.2188.218
964611AG1-324 C
80/20
0.3140.314
964612AG1-324 E
80/20
0.4710.471
965331AG1-398 C
80/20
0.1630.163
965462AG1-414 E
80/20
1.6981.698
990901L-005 E
80/20
1.5991.599
270201AC2-176 GEN
80/20
0.2920.292
933596AC2-176 E
80/20
1.9521.952
25016408BKJDB1
80/20
0.2670.267
251827WILLYESP
80/20
0.6880.688
965913AG1-460 BT
80/20
0.0060.006
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
248005 to 242528 ckt 1

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
AEP_P1-2_#7422_16_SRT-A
OPAC126.36 %1180.0B1491.0911.47

Details for 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:126.36 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1491.09
MW Contribution:11.47
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
943031AE2-326 C
50/50
6.3456.345
943032AE2-326 E
50/50
4.234.23
24289205AMG2
50/50
56.44356.443
24289305AMG3
50/50
92.61692.616
24344305RKG2
50/50
78.52378.523
274675JOLIET 29;7U
Adder
30.56470588235294325.98
274676JOLIET 29;8U
Adder
30.56470588235294325.98
944971AF1-162 C
50/50
7.9367.936
944972AF1-162 E
50/50
5.2915.291
945382AF1-203 E
50/50
2.1692.169
964782AG1-341 E
50/50
11.47211.472
223403AG1-063 C
Adder
-0.07176470588235294-0.061
940351AE2-019 C
Adder
-15.808235294117647-13.437
966391AG1-508 C
50/50
1.4661.466
966392AG1-508 E
50/50
8.5158.515
24289905CRG1H
50/50
8.58.5
24290005CRG1L
50/50
7.1147.114
24290105CRG2H
50/50
8.5548.554
24290205CRG2L
50/50
7.1757.175
24375805MIDDLECR
50/50
0.2630.263
270167AD2-205 E
50/50
0.7890.789
940353AE2-019 BT
50/50
15.80815.808
957193AF2-013 BT
50/50
11.39811.398
962183AG1-063 BAT
50/50
0.2560.256
962553AG1-104 BT
50/50
30.74130.741
963033AG1-152 BT
50/50
13.62813.628
963693AG1-221 BT
50/50
6.5036.503
964443AG1-307 BT
50/50
2.0032.003
966143AG1-483 BAT
50/50
55.90555.905
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
242512 to 242515 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Request (project) AG1-341 in PJM Transition Cycle 1 is listed in Table 1 below. This report will cover the dynamic analysis of AG1-341.

 

This analysis is effectively a screening study to determine whether the addition of the AG1-341 will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-341 have been dispatched online at maximum output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

AG1-341 was tested for compliance with NERC, EKPC, PJM, and other applicable criteria. Steady-state condition and 233 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Three-phase bus faults with normal clearing time;

       d)       Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker;

       e)       Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Three-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the AG1-341 project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       AG1-341 project was able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with AG1-341 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-341 meets the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-341 GEN, AF1-050 GEN and AE2-071 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system these plots are ignored.

 

AG1-341, AF1-050 and AE2-071 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 AG1-341 Project

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-341

Solar/Storage

EKPC

106

106

63.6

Summer Shade 161 kV

 

Reactive Power Analysis

The reactive power capability of AG1-341 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AD2-205Byllesby 69 kVIn Service
AE1-143Marion County 161 kVEngineering & Procurement
AE2-019New Road 230 kVUnder Construction
AE2-071Patton Rd-Summer Shade 69 kVIn Service
AE2-326Jacksons Ferry 138 kVEngineering & Procurement
AF1-038Sewellton Jct-Webbs Crossroads 69 kVEngineering & Procurement
AF1-050Summer Shade - Green County 161 kVEngineering & Procurement
AF1-083Green County-Saloma 161 kVEngineering & Procurement
AF1-162Inez 138 kVEngineering & Procurement
AF1-203Patton Rd-Summer Shade 69 kVIn Service
AF2-013Arnold's Corner-Dahlgren 230 kVEngineering & Procurement
AG1-063Fairhaven 13,8 kVIn Service
AG1-104Waugh Chapel 230 kVWithdrawn
AG1-152Remington CT 230 kVEngineering & Procurement
AG1-221Poland Rd-Runway DP 230 kVUnder Construction
AG1-307Old Chapel-Millville 138 kVEngineering & Procurement
AG1-354Summershade-Green County 161 kVActive
AG1-471Up Church-Wayne County 69 kVActive
AG1-483Dickerson 230 kVEngineering & Procurement
AG1-508Point Lookout 69 kVEngineering & Procurement

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)Identified Impacts
AG1-341 System Reinforcements:
TOTrans Owner IDTitleCategoryAllocated Cost ($USD)
LGEELGEE_TC1_15519Invalid - P7 contingency 69kV not monitored by LGEEInformational$0
LGEELGEE_TC1_15524Load shedding of 10% PC load is allowed for P7 contingencyInformational$0
LGEENoneLoad shedding of 10% PC load is allowed for P2 contingencyInformational$0
LGEELGEE_TC1_15523Load shedding of 10% PC load is allowed for P4 contingencyInformational$0
Grand Total:$0

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_15519
Title
Invalid - P7 contingency 69kV not monitored by LGEE
Description
Invalid - P7 contingency 69kV not monitored by LGEE EKPC emergency rating is 143 MVA on the Somerset KU - Ferguston 69kV line.
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_15524
Title
Load shedding of 10% PC load is allowed for P7 contingency
Description
Load shedding of 10% PC load is allowed for P7 contingency
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending)
Title
Load shedding of 10% PC load is allowed for P2 contingency
Description
Load shedding of 10% PC load is allowed for P2 contingency
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_15523
Title
Load shedding of 10% PC load is allowed for P4 contingency
Description
Load shedding of 10% PC load is allowed for P4 contingency
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: Please communicate with the Affected System Operator regarding the status of the Affected System Study for your project.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AG1-341Scenarios
  • CAP BANK 138.0 - Avon East 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Avon East sub
Install 28.8 MVAR cap bank at Avon East sub
$3,000,000$16,981
  • MISO Voltage
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E) Identified Impacts
Note: Please communicate with the Affected System Operator regarding the status of the Affected System Study for your project.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AG1-341Scenarios
  • 2CAMPBELVL 69.0 - 2TAYLOR CO 69.0 CKT 1
LGEE Campbellsville 2 Tap - Taylor County 69 kV Line Reconductor
Replace 0.38 miles of 266.8 MCM 26X7 ACSR
conductor in the Campbellsville 2 Tap to Taylor
County section of the Lebanon to Taylor County 69
kV line, using 556 MCM 26X7 ACSR or better
conductor.
$950,000$144,293
  • 2LEBANON 69.0 - 2SPRINGFL KU 69.0 CKT 1
LGEE Lebanon - Springfield 69 kV Line Reconductor
Reconductor the 6.58 miles of 266.8 26x7 ACSR and
replace 266.8 26x7 ACSR line riser in the Lebanon
to Springfield 69 kV line with 397.5 MCM ACSR
$16,527,000$1,676,535
  • 2MOREHEAD W 69.0 - 2MOREHEAD 69.0 CKT 1
LGEE Morehead W - Morehead 69 kV Line Reconductor
Reconductor the 0.19 miles of 2/0 7x CU in the
Morehead W to Morehead 69kV, to 266.8 MCM 26x7
ACSR.
$475,000$26,243
  • 2SHELBY CO T 69.0 - 2SHELBYVIL S 69.0 CKT 1
LGEE Shelbyville South - Shelby Co Tap 69 kV Line MOT
Increase the maximum operating temperature of 1.96
miles of 397.5 ACSR in the Shelbyville South to
Shelby Co tap section of the Shelbyville to
Finchville 69 kV line from 150°F to a minimum of
170°F.
$682,500$147,058
  • 2SPRINGFL KU 69.0 - 2N SPRINGFLD 69.0 CKT 1
LGEE Springfield - North Springfield 69 kV Line MOT
Increase the MOT of 3.24 miles of 266.8 26x7 ACSR
to 176/212F in the Springfield-North Springfield
69 kV line.
$1,134,000$114,574
  • 4TYRONE 138.0 - 4BROWN N 1 138.0 CKT 1
LGEE Brown North - Tyrone 138 kV Line Reconductor
Reconductor the 556.5 MCM 26X7 ACSR 20.12 mi with
795 MCM 45X7 ACSR or better in the Brown North to
Tyrone 138 kV line.
$60,360,000$5,436,671
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Final System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b4000.251
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.251
Title
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Description
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG1-341 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG1-341 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A5523.0 MVA
(All)B5523.0 MVA

System Reinforcement: b4000.252
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.252
Title
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Description
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG1-341 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG1-341 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A5523.0 MVA
(All)B5523.0 MVA

System Reinforcement
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
(Pending) / EKPC-tc1-r0004a
Title
EKPC emergency rating is 143 MVA.
Description
EKPC emergency rating is 143 MVA. LG&E: SE rating is 105 MVA.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A143.0 MVA
(All)B143.0 MVA
(All)C143.0 MVA

System Reinforcement
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
(Pending) / EKPC-tc1-r0012a
Title
LGE/KU is limiting this facility. EKPC emergency rating is 298 MVA.
Description
LGE/KU is limiting this facility (LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B). EKPC emergency rating is 298 MVA. LGEE AFS for TC1 has determined they will not require an reinforcement and thus EKPC existing 298 MVA Rate B is adequate as LGEE is the limiting element of the line.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
SUMA267.0 MVA
SUMB298.0 MVA
SUMC298.0 MVA


Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-341


AG1-341 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AG1-341 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AG1-341 One Line Diagram

AG1-341 One Line Diagram.png
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.