AG1-411 Final System Impact Study (Retool 2) Report

v2.00 released 2026-05-14 11:56

Maddox Creek-RP Mone 345 kV

100.0 MW Capacity / 100.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Butterfly Meadows Solar Project, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Ohio Power Company.

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.

The AG1-411 Final System Impact Study (Retool 1) Report is available for download here.

Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Ohio Power Company zone — Van Wert County, Ohio. This project is an increase to the developer’s AG1-410 project(s), which will share the same Point of Interconnection. The AG1-411 project is a 100.0 MW uprate (100.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 400.0 MW with 280.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-411
Project Name:
Maddox Creek-RP Mone 345 kV
Project Developer Name:
Butterfly Meadows Solar Project, LLC
State:
Ohio
County:
Van Wert
Transmission Owner:
Ohio Power Company
MFO:
400.0
MWE:
100.0
MWC:
100.0
Battery Storage Specification:
400.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-411 will interconnect on the AEP Ohio Power Company transmission system at RP Mone to Maddox Creek 345kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AG1-411 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AG1-411Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$1,279,780$1,279,780
Other Scope$193,802$193,802
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$8,545,201$8,545,201
Network Upgrades$1,962,166$1,962,166
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0
AFS - Non-PJM Violations$36,109 **$0 **
Total$12,017,058$11,980,949

* Contributes to calculation for Security. See Security Requirement Section of this report for additional detail.

** This value reflects the results at the time of the report posting and it is subject to change. AFS – Non-PJM Violations are not subject to Security. For latest AFS – Non-PJM Violations, please refer to the latest Affected System Study Report for your project.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AG1-410/AG1-411

Security has been calculated for the AG1-410/AG1-411 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AG1-410/AG1-411
Project(s): AG1-410/AG1-411
Final Agreement Security (A): $23,707,332
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $23,707,332
Security on Hand with PJM (D): $23,707,332
Additional Security Due at Agreement Execution (E): C D = $0
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

AG1-411 will interconnect with the AEP transmission system via a new station cut into the RP Mone - Maddox Creek 345 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

AG1-411 shares physical interconnection scope with AG1-410, which is also in Transition Cycle 1.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9590.0

RP Mone 345 kV: Review and revise relay Settings.

$36,901$7,080$14,081$2,702$60,764$30,382 (See Note 1)
n9589.0

Maddox Creek - RP Mone 345 kV: Work required for the new station tie-in. Install two (2) steel, 150’ single circuit, single pole dead end structures on concrete piers with anchor bolt cages in the existing Maddox Creek - RP Mone 345 kV Circuit right of way, two (2) additional steel, single circuit, single pole, dead end structures on concrete piers with anchor bolt cages along the perimeter of the AG1-410 Proposed 345 kV Station, and four (4) spans of double bundle ACSR 954 (Cardinal) transmission line conductor with 96 fiber optical ground wire shield wire, cutting in the AG1-410 Proposed 345 kV Station in an in-and-out arrangement.

$742,359$791,482$226,608$241,603$2,002,052$1,001,026 (See Note 1)
n9588.0

Maddox Creek 345 kV: • Remove two (2) single phase line traps on the line exit to the AG1-410 Proposed 345 kV Station. • Replace the protective relaying scheme at the Maddox Creek 345 kV Station with a dual, fiber-based integrated communications optical network multiplexor current differential scheme. • Reconfigure the existing integrated communications optical network at the Maddox Creek 345 kV Station, installing a new SFP transceiver.

$239,674$78,891$66,974$22,045$407,584$203,792 (See Note 1)
n9587.0

Van Wert 345 kV: Reconfigure the existing integrated communications optical network at the Van Wert Station, installing a new small form-factor pluggable ("SFP") transceiver.

$10,352$2,474$8,526$2,038$23,390$11,695 (See Note 1)
n9586.0

Maddox Creek - RP Mone 345 kV: Install two (2) station exit transitions and 3.05 miles of OPGW fiber cable along the existing Maddox Creek – RP Mone 345 kV circuit, terminating at the Maddox Creek 345 kV Station.

$689,528$154,666$115,241$25,829$985,264$492,632 (See Note 1)
n9585.0

AG1-410 Proposed 345 kV Station: Install one (1) station exit transition from the AG1-410 Proposed 345 kV Station, 0.7 miles of 96 ct ADLT fiber cable in new underground right of way, and 0.6 miles of 96 ct all dielectric self supporting fiber optic cable along existing distribution structures to a splice an existing AEP fiber cable.

$210,171$57,509$43,860$12,210$323,750$161,875 (See Note 1)
n9394.0

Proposed AG1-410 345 kV Station: Review and revise the protective relay settings at the AG1-410 Proposed 345 kV Station to account for the additional generation

$36,901$7,080$14,081$2,702$60,764$60,764
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• OHPCo will procure one (1) metering panel with two (2) primary meters and one (1) ethernet switch for installation by the Project Developer in the AG1-411 Project Developer's collector station. • OHPCo will procure one (1) connected grid router for installation by the Project Developer in the Project Developer's originating project collector station.

$106,608$51,442$23,199$12,553$193,802$193,802
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9591.0

Maddox Creek - RP Mone 345 kV: Construct a new 345 kV ring bus station, initially populated with three (3) circuit breakers, expandable to four (4) circuit breakers, including • Three (3) 63 kA circuit breakers with associated control relaying. • One (1) 16' x 48' DICM. • Six (6) motorized breaker disconnect switches. • Two (2) 3-phase CCVT, one (1) each on the line exits to the Maddox Creek and RP Mone 345 kV Stations. • Two (2) single phase station service voltage transformers. • Two (2) A-Frame line exit structures, one (1) each for the line exits to the Maddox Creek and RP Mone 345 kV Stations. • Two (2) single phase line traps for the line exit to the RP Mone 345 kV Station. • Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures. • A fiber-based integrated communications optical network multiplexor dual current differential line protective relay scheme for the line to the Maddox Creek 345 kV Station. • A directional comparison blocking protective relay scheme for the line exit to the RP Mone 345 kV Station. • The civil work required to develop a site that accommodates the installation of the above station includes grading of a 460' x 350' pad.

$9,308,597$5,447,252$1,472,732$861,821$17,090,402$8,545,201 (See Note 1)
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• Installation of one (1) new steel, 150', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage and one span of aluminum conductor steel-reinforced ("ACSR") 336.4 (Oriole) transmission line conductor with 7#8 Alumoweld shield wire for the generation lead circuit extending from the AG1-410 Proposed 345 kV Station to the PCO. • Extension of two (2) underground all dielectric loose tube ("ADLT") fiber optic cables from the AG1-410 proposed 345 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the AG1-410 proposed 345 kV and Project Developer's collector station. • Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase coupling capacitor voltage transformers ("CCVT"), associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module ("DICM")-installed metering panel, for the generation lead circuit at the AG1-410 Proposed 345 kV Station. • Installation of one (1) A-Frame line exit structure for the line exits to the AG1-410 Proposed 345 kV Station. • A dual, direct-fiber current differential relay protection scheme for the generation lead to the proposed AG1-410 collector station.

$1,444,159$728,268$261,391$125,742$2,559,560$1,279,780 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 25 to 31 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement assuming commercial operation of the preceding project has been achieved. The minimum schedule assumes that the Transmission Owners only scope of work is review and revision of relay settings at the interconnection station. The maximum schedule assumes the need for additional work being required at the interconnection station.  Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG1-411 was evaluated as a 100.0 MW (100.0 MW Capacity) injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
05RPMONE-05ALLEN 345.0 kV Ckt 1 line
AEP_P1-2_#6463_16757_SRT-A
OPAC118.17 %1154.0B1363.7299.74
GD1AEP
AF1-227 POI-05MARYSV 345.0 kV Ckt 1 line
Base Case
OPAC102.72 %897.0A921.4213.05

Details for 05RPMONE-05ALLEN 345.0 kV Ckt 1 line l/o AEP_P1-2_#6463_16757_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05RPMONE-05ALLEN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#6463_16757_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:118.17 %
Rating:1154.0 MVA
Rating Type:B
MVA to Mitigate:1363.72
MW Contribution:99.74
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP
Facility Description:
05RPMONE-05ALLEN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#6463_16757_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:118.18 %
Rating:1154.0 MVA
Rating Type:B
MVA to Mitigate:1363.84
MW Contribution:99.74
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24693605BLCK-1 C
50/50
2.6732.673
24693705BLCK-2 C
50/50
2.6732.673
24693805BLCK-3 C
50/50
2.6892.689
24727005RPMNG1
50/50
24.41424.414
24727105RPMNG2
50/50
24.39824.398
24727205RPMNG3
50/50
24.28424.284
24790805BLCK-1 E
50/50
99.64199.641
24790905BLCK-2 E
50/50
99.64199.641
24791005BLCK-3 E
50/50
100.638100.638
932301AC2-044 C
50/50
7.587.58
932302AC2-044 E
50/50
12.36812.368
938761AE1-102 C
50/50
15.55915.559
938762AE1-102 E
50/50
10.37310.373
957201AF2-014 C
50/50
89.76689.766
957202AF2-014 E
50/50
59.84459.844
965421AG1-410 C
50/50
179.532179.532
965422AG1-410 E
50/50
119.688119.688
965431AG1-411 C
50/50
99.7499.74
G-007PJM->LTFIMP_G-007
CMTX_NF
0.2730.273
NYPJM->LTFIMP_NY
CLTF
0.1440.144
COTTONWOODPJM->LTFIMP_COTTONWOOD
CLTF
0.5450.545
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.150.15
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.0910.091
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
0.6710.671
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.1450.145
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.450.45
O66PJM->LTFIMP_O-066
CMTX_NF
1.7481.748
MDUPJM->LTFIMP_MDU
CLTF
0.0260.026
LTFEXP_AC1-056LTFEXP_AC1-056->LTFIMP_AC1-056
CLTF
0.260.26
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.1950.195

Details for AF1-227 POI-05MARYSV 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF1-227 POI-05MARYSV 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:102.72 %
Rating:897.0 MVA
Rating Type:A
MVA to Mitigate:921.42
MW Contribution:13.05
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AF1-227 POI-05MARYSV 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:102.33 %
Rating:897.0 MVA
Rating Type:A
MVA to Mitigate:917.87
MW Contribution:13.04
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
24693605BLCK-1 C
50/50
0.3750.375
24693705BLCK-2 C
50/50
0.3750.375
24693805BLCK-3 C
50/50
0.3780.378
24727005RPMNG1
50/50
2.7092.709
24727105RPMNG2
50/50
2.7072.707
24727205RPMNG3
50/50
2.6942.694
247522U1-059 C
50/50
0.1660.166
247549V3-028 C
50/50
4.2524.252
24790805BLCK-1 E
50/50
13.99413.994
24790905BLCK-2 E
50/50
13.99413.994
24791005BLCK-3 E
50/50
14.13414.134
247948V3-028 E
50/50
5.665.66
936671AD2-086 C
50/50
10.19410.194
936672AD2-086 E
50/50
41.99741.997
960841AF2-375 C
Adder
7.646.494
960842AF2-375 E
Adder
5.0929411764705884.329
24435705GRANGER EL
50/50
0.3580.358
270165U1-059 E
50/50
4.1054.105
925135AB2-170 E
50/50
36.79336.793
932301AC2-044 C
50/50
1.0651.065
932302AC2-044 E
50/50
1.7371.737
938681AE1-090 C
50/50
0.5510.551
938682AE1-090 E
50/50
3.6523.652
938691AE1-091 C
50/50
6.2366.236
938692AE1-091 E
50/50
8.388.38
938761AE1-102 C
50/50
2.1852.185
938762AE1-102 E
50/50
1.4571.457
940031AE1-245 C
Adder
1.7682352941176471.503
940032AE1-245 E
Adder
11.83176470588235310.057
957201AF2-014 C
50/50
12.60712.607
957202AF2-014 E
50/50
8.4058.405
958092AF2-103 E
Adder
0.165882352941176450.141
247540U2-072 C
50/50
3.3623.362
247932U2-072 E
50/50
137.669137.669
934981AD1-130 C
50/50
7.4477.447
934982AD1-130 E
50/50
22.15422.154
247555W1-056 C
50/50
0.0420.042
247942W1-056 E
50/50
1.6971.697
936721AD2-091 C
50/50
22.82522.825
270297AD1-101 C
50/50
0.3120.312
966831AG1-554 C
50/50
3.5743.574
247959V1-011 E
Adder
7.8835294117647056.701
934742AD1-101 E
50/50
3.1113.111
946201AF1-285 C
50/50
29.53829.538
966832AG1-554 E
50/50
1.891.89
945617AF1-227 E1
50/50
56.12656.126
945618AF1-227 E2
50/50
40.5440.54
945619AF1-227 E3
50/50
0.840.84
946202AF1-285 E
50/50
23.20923.209
270284AF1-227 C1
50/50
13.75813.758
270286AF1-227 C2
50/50
9.9369.936
270287AF1-227 C3
50/50
0.2060.206
965421AG1-410 C
50/50
23.48523.485
965422AG1-410 E
50/50
15.65715.657
965431AG1-411 C
50/50
13.04713.047
934461AD1-070 C
Adder
3.34941176470588252.847
934462AD1-070 E
Adder
11.4435294117647069.727
939161AE1-146 C
50/50
8.6228.622
939162AE1-146 E
50/50
4.0264.026
940841AE2-072 C
50/50
1.451.45
940842AE2-072 E
50/50
6.3456.345
942041AE2-216 C
50/50
25.10725.107
942871AE2-306 C
50/50
9.4949.494
942872AE2-306 E
50/50
6.336.33
962281AG1-076 C
Adder
4.283.638
CBM West 1LTFEXP_CBM-W1->PJM
CBM
39.21639.216
CBM West 2LTFEXP_CBM-W2->PJM
CBM
4.0514.051
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.8250.825
NYPJM->LTFIMP_NY
CLTF
0.3730.373
LGEELTFEXP_LGEE->PJM
CLTF
0.30.3
WECLTFEXP_WEC->PJM
CLTF
0.4990.499
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.4070.407
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.2310.231
TVALTFEXP_TVA->PJM
CLTF
0.1480.148
MECLTFEXP_MEC->PJM
CLTF
1.8781.878
LAGNLTFEXP_LAGN->PJM
CLTF
0.4640.464
SIGELTFEXP_SIGE->PJM
CLTF
0.0840.084
O66PJM->LTFIMP_O-066
CMTX_NF
5.2675.267
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.5630.563
CONTINGENCY 'AEP_P1-2_#6463_16757_SRT-A'
 OPEN BRANCH FROM BUS 242935 TO BUS 246929 CKT 1   /*05E LIMA     345.0 - 05MADDOX     345.0
END
242933 to 243211 ckt 1
270279 to 242939 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AG1-411 was evaluated as a 100.0 MW injection and 100.0 MW withdrawal in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 56 are listed in Table 1 below . This report will cover the dynamic analysis of Cluster 56 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 56 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 56 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 56 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 34 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

       

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 56 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 56 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-410 and AG1-411 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA model of AG1-410 GEN, and AG1-411 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The AG1-411 generator terminal voltage settles beyond the acceptable voltage limits after fault clearance during 17 contingencies (P1.02, P1.03, P1.04, P1.08, P1.10, P4.07, P4.08, P4.09, P4.12, P4.13, P4.14, P4.15, P4.16, P4.17, P4.18, P4.19, and P4.20). This violation has been mitigated by adjusting the following parameters in the plant controller (REPCA1) for both AG1-410 and AG1-411: Kc (the reactive current compensation gain) to 0.1 (originally set to 0.0) and VC Flag (droop flag) to 0 (originally set to 1). These changes have been confirmed by the developer and updated in the latest data package received.

 

Fictitious frequency response at AG1-410 generator bus tripped the queue project due to the action of instantaneous over-frequency relay for several contingencies. Therefore, the relay pickup time for frequency relay instance 96542509 was set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

Voltage tripping was observed at the terminals of the AG1-410 generating unit after fault clearing during contingency P1.03. This issue was mitigated by adjusting Ki (Reactive power PI control integral gain) to 1.0 (originally set to 3.0) for AG1-410 in the plant controller REPCA1. The change was confirmed through correspondence with the developer.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 56 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

56

AG1-410

Solar

AEP

300

300

180

Maddox Creek-RP Mone 345 kV

AG1-411

Storage

AEP

100

100

100

Maddox Creek-RP Mone 345 kV

 

 

Reactive Power Analysis

The reactive power capability of AG1-411 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AB2-170East Lima-Marysville 345kVIn Service
AC2-044Maddox Creek 345kVSuspended
AD1-130Hardin Switch 345 kVIn Service
AD2-086Hardin Switch 345 kVIn Service
AD2-091Hardin Tap 345kVSuspended
AE1-090Hardin Switch 345 kVIn Service
AE1-102Maddox Creek 345 kVSuspended
AE1-146Ebersole #2-Fostoria Central 138 kVUnder Construction
AE1-245Haviland 138 kVPartially in Service - Under Construction
AE2-216Hardin Switch 345 kVSuspended
AE2-298Cavett Switch - West Van Wert 69 kVWithdrawn
AE2-306Gunn Road 345 kVUnder Construction
AF1-285Gunn Road 345 kVUnder Construction
AF2-014Maddox Creek 345 kVUnder Construction
AF2-375Ebersole-Fostoria 138 kVEngineering & Procurement
AG1-410Maddox Creek-RP Mone 345 kVEngineering & Procurement
U2-072East Lima-Marysville 345kVIn Service
V3-028East Lima-Marysville 345kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In coordination with other Affected System Operators, PJM has determined that the Affected System Operator for this project that requires an Affected System Study. For the latest Affected System Study results pertaining this project, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM lists any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Final System Impact Study load flow analysis.

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-411


AG1-411 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AG1-411 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AG1-411 One Line Diagram

AG1-411 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.