AG1-433 Final System Impact Study (Retool 2) Report

v2.00 released 2026-05-14 11:57

Keystone-DeSoto 345 kV

17.6 MW Capacity / 100.0 MW Energy

Introduction

This Final System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 314 for New Service Requests (projects) in Transition Cycle 1 (TC1). The Project Developer/Eligible Customer (developer) is Prairie Creek Wind Farm II, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

The Final System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Final System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 5, Final Agreement Negotiation Phase, the purpose of the Final Agreement Negotiation Phase is to:

  1. Negotiate, execute and enter into the applicable final interconnection related service agreement found in Tariff, Part IX;
  2. Conduct any remaining analyses or updated analyses based on New Service Requests withdrawn during Decision Point III (DP3); and
  3. Adjust the security obligation based on New Service Requests withdrawn during Decision Point III and/or during the Final Agreement Negotiation Phase.
Retool 1:

In accordance with PJM Tariff Part VII.D 314 B(1)(a), Final Agreement Negotiation Phase:

  • PJM will perform a retool (Retool 1) after the conclusion of DP3 considering only the projects moving on in the Final Agreement Negotiation Phase (Removes DP3 withdrawals).
  • The Final System Impact Study reflecting results from the retooled analysis (Retool 1) will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • PJM will provide updated final electronic agreements to Project Developers and Eligible Customers in the Cycle reflecting updates from the Final System Impact Study after Retool 1 including the adjusted Security requirements.

The AG1-433 Final System Impact Study (Retool 1) Report is available for download here.

Retool 2 (if needed):

If particular New Service Requests do not sign their final agreements after receiving the updated information after Retool 1, there may be the need to run a second retool (Retool 2) to identify if any network upgrades are no longer necessary:

  • PJM will perform Retool 2 (if necessary) considering only the removal of projects from the model which chose not to execute their agreements after Retool 1.
  • The updated Final System Impact Study reflecting results from Retool 2 will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  • If there are any adjustments to the agreements required after Retool 2, the necessary network upgrade or Security changes will be handled via the scope change process post-GIA.

General

The Project Developer has proposed a Wind generating facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Blackford County, Indiana. The installed facilities will have a total capability of 100.0 MW with 17.6 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-433
Project Name:
Keystone-DeSoto 345 kV
Project Developer Name:
Prairie Creek Wind Farm II, LLC
State:
Indiana
County:
Blackford
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
100.0
MWE:
100.0
MWC:
17.6
Fuel Type:
Wind
Basecase Study Year:
2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-433 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system tapping the Keystone to DeSoto 345 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II. Facilities Studies are available for download on PJM.com (see General Section for document links). The Interconnected Transmission Owner has performed a Facilities Study for the required System Reliability Network Upgrades in Phase III (see System Reinforcement Section for document links).

Based on the Final SIS results, the AG1-433 project has the following allocation of costs for interconnection. The Security amount required after the Final SIS and revised agreements is also shown below.

Cost Summary
DescriptionCost Allocated to AG1-433Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$982,483$982,483
Other Scope$193,802$193,802
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$752,226$752,226
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$4,743,908$4,743,908
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0
AFS - Non-PJM Violations$0 **$0 **
Total$6,672,419$6,672,419

* Contributes to calculation for Security. See Security Requirement Section of this report for additional detail.

** This value reflects the results at the time of the report posting and it is subject to change. AFS – Non-PJM Violations are not subject to Security. For latest AFS – Non-PJM Violations, please refer to the latest Affected System Study Report for your project.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 314 (Final Agreement Negotiation Phase) A.1 and PJM Manual 14H, Section 5, if a Transition Cycle 1 New Service Request is withdrawn during Decision Point III and/or the Final Agreement Negotiation Phase, PJM shall remove the New Service Request from the Cycle and adjust the Security obligations of other New Service Requests based on the withdrawal. The Final System Impact Study results will reflect the updated Security amount for this project. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Final System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AG1-433

Security has been calculated for the AG1-433 project(s) based on the Final System Impact Study results and is shown in the table below. This Security must be provided at Final SIS through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AG1-433
Project(s): AG1-433
Final Agreement Security (A): $6,672,419
Portion of Costs Already Paid (B): $0
Revised Net Security (C): A B = $6,672,419
Security on Hand with PJM (D): $4,796,513
Additional Security Due at Agreement Execution (E): C D = $1,875,906
Note:

In accordance with Tariff, Part VII, Subpart D, section 314(B)(4)(a) (Final Agreement Negotiation Phase) failure to provide any required adjustments to Security within the 15 Business Day period will result in the New Service Request project being terminated and withdrawn.

Please see the cover letter for more details on Letter of Credit/Wire details to satisfy the additional Security requirement.

If no additional Security is required, please coordinate with your assigned Project Manager to initiate any refunds of Security reductions.

Transmission Owner Scope of Work

AG1-433 will interconnect with the AEP transmission system as an uprate to a previous interconnection at the Keystone - Desoto 345 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

AG1-433 shares physical interconnection scope with AF2-388, which is also in Transition Cycle 1.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Scope
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
n9370.0

Proposed AF1-119 345 kV station Expansion: • Installation of one (1) new 5000A 63 kA 345 kV circuit breaker and associated control relaying. • Installation of two (2) new 3000 A breaker disconnect switches. • Installation of three (3) single-phase surge arresters on the generation lead to the Proposed AF2-388 collector station. • Associated buswork, bus supports, jumpers, insulators, grounding, Supervisory Control and Data Acquisition connectivity, structures, and foundations.

$563,111$670,350$68,235$81,229$1,382,925$691,462 (See Note 1)
n9348.0

Proposed AF1-119 345 kV Station: Review and revise the protective relay settings to account for the additional generation of AG1-433.

$36,901$7,080$14,081$2,702$60,764$60,764
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Submetering Scope for AG1-433: • Procure one (1) metering panel with two (2) primary meters and one (1) ethernet switch to be installed by the Project Developer in the AG1-433 Project Developer's collector station. • Procure one (1) connected grid router to be installed by the Project Developer in the Project Developer's originating project collector station (AF2-388).

$106,608$51,442$23,199$12,553$193,802$193,802
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

• Installation of one (1) new A-Frame take off structure for the generation lead. • Extension of two (2) underground all dielectric loose tube fiber optic cables from the Proposed AF1-119 345 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the Proposed AF1-119 345 kV and Project Developer's collector stations. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station. • Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase coupling capacitor voltage transformers, associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module-installed metering panel, for the generation lead circuit at the Proposed AF1-119 345 kV station. • Installation of one (1) new 150 ft. custom steel pole, single circuit dead end structure on a concrete foundation with anchor bolt cages. • Installation of one (1) new span of aluminum conductor steel reinforced (ACSR) 2-bundled 954 54/7 (Cardinal) transmission line conductor with Guinea 159 ACSR 12-7 shield wire for the generation lead circuit exiting the Proposed AF1-119 345 kV station. • Dual, direct fiber-based current differential relays for the generation lead circuit. • Review and revision of the protective relay settings for the remainder of the Proposed AF1-119 345 kV Station.

$1,041,611$667,322$154,649$101,384$1,964,966$982,483 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take 31 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement assuming commercial operation of the preceding project has been achieved. The minimum schedule assumes that the Transmission Owners only scope of work is review and revision of relay settings at the interconnection station. The maximum schedule assumes the need for additional work being required at the interconnection station.  Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The wind generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Wind speed (meters/second) - (Required)
  • Wind direction (decimal degrees from true north) - (Required)
  • Ambient air temperature (Fahrenheit) - (Required)
  • Air Pressure (Hectopascals) - (Required)
  • Humidity (Percent) - (Accepted, not required)
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG1-433 was evaluated as a 100.0 MW (17.6 MW Capacity) injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1OVEC
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
DEOK_P2-3_1403_MIAMI FORT_SRT-A
BreakerAC100.86 %971.0B979.387.27
GD1OVEC
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
DEOK_P2-3_1401_MIAMI FORT_SRT-A
BreakerAC100.35 %971.0B974.437.27

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1403_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.86 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:979.38
MW Contribution:7.27
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.59 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:976.75
MW Contribution:7.26
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.13882352941176470.118
961762AG1-017 E
Adder
0.63647058823529420.541
962031AG1-047 C
Adder
3.67647058823529443.125
962032AG1-047 E
Adder
2.45058823529411772.083
965651AG1-433 C
Adder
1.281.088
965652AG1-433 E
Adder
5.9905882352941175.092
24726405LAWG1A
50/50
6.86.8
24726505LAWG1B
50/50
6.86.8
24726605LAWG1S
50/50
10.86110.861
24726705LAWG2A
50/50
6.86.8
24726805LAWG2B
50/50
6.3116.311
24726905LAWG2S
50/50
10.86110.861
247543V3-007 C
50/50
0.4930.493
247929S-071 E
Adder
5.8552941176470594.977
247935V3-007 E
50/50
20.20920.209
24795805WLD G2 E
Adder
12.55764705882352810.674
24796305HDWTR1G E
50/50
20.20920.209
934962AD1-128 E
Adder
7.3717647058823536.266
936561AD2-071 C
Adder
4.7094117647058834.003
936562AD2-071 E
Adder
2.321.972
942081AE2-220 C
50/50
6.0976.097
942082AE2-220 E
50/50
8.428.42
944031AF1-071 C
Adder
0.47411764705882360.403
944032AF1-071 E
Adder
0.77411764705882360.658
958711AF2-162 C
Adder
2.18117647058823531.854
958712AF2-162 E
Adder
1.09058823529411760.927
960971AF2-388 C
Adder
2.55882352941176452.175
960972AF2-388 E
Adder
11.98117647058823510.184
24379505HDWTR1G C
50/50
0.4930.493
25194708EBND2
50/50
16.23816.238
932681AC2-090 C
50/50
0.720.72
932682AC2-090 E
50/50
7.2017.201
939761AE1-207 C
Adder
4.4658823529411763.796
939762AE1-207 E
Adder
6.1682352941176485.243
939771AE1-208 C
Adder
3.9588235294117653.365
939772AE1-208 E
Adder
5.3988235294117654.589
942071AE2-219 C
Adder
2.56941176470588272.184
942072AE2-219 E
Adder
3.5482352941176473.016
247968Z2-115 E
Adder
0.070588235294117650.06
926874AC1-174 E
50/50
7.2017.201
926881AC1-175 E
50/50
7.2017.201
270209AC1-174 C
50/50
0.7210.721
270210AC1-175 C
50/50
0.7210.721
270222AC2-111 C
Adder
2.1082352941176471.792
932844AC2-111 E
Adder
3.40588235294117642.895
933596AC2-176 E
Adder
6.9294117647058825.89
942221AE2-234 C
Adder
1.2988235294117651.104
942222AE2-234 E
Adder
0.58705882352941170.499
942791AE2-297 C O1
50/50
1.5831.583
942792AE2-297 E O1
50/50
6.6276.627
944531AF1-118 C
Adder
16.3613.906
944532AF1-118 E
Adder
4.9341176470588244.194
944541AF1-119 C
Adder
10.1788235294117648.652
944542AF1-119 E
Adder
4.36235294117647053.708
945371AF1-202 C
Adder
2.61411764705882372.222
945372AF1-202 E
Adder
12.76352941176470610.849
945581AF1-223 C
Adder
6.925.882
945582AF1-223 E
Adder
4.61294117647058853.921
946032AF1-268 E
Adder
2.04470588235294141.738
958861AF2-177 C
Adder
1.9470588235294121.655
958862AF2-177 E
Adder
13.03176470588235211.077
961171AF2-408 C
Adder
6.4976470588235295.523
939781AE1-209 C
Adder
1.21.02
939782AE1-209 E
Adder
8.0282352941176466.824
939791AE1-210 C
Adder
1.21.02
939792AE1-210 E
Adder
8.0282352941176466.824
946031AF1-268 C
Adder
4.5082352941176473.832
964611AG1-324 C
Adder
1.8117647058823531.54
964612AG1-324 E
Adder
0.72117647058823530.613
940981AE2-089 C
Adder
4.99529411764705964.246
940982AE2-089 E
Adder
3.33058823529411762.831
941691AE2-169 C
Adder
2.3752941176470592.019
941721AE2-172 C
Adder
2.65882352941176462.26
957741AF2-068 C
Adder
5.5141176470588244.687
957742AF2-068 E
Adder
3.67647058823529443.125
965461AG1-414 C
Adder
2.7552941176470592.342
965462AG1-414 E
Adder
1.8364705882352941.561
CBM West 1LTFEXP_CBM-W1->PJM
CBM
36.45236.452
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.19914.199
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.9220.922
NYPJM->LTFIMP_NY
CLTF
0.4740.474
LGEELTFEXP_LGEE->PJM
CLTF
0.6180.618
WECLTFEXP_WEC->PJM
CLTF
0.8430.843
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.2640.264
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1350.135
TVALTFEXP_TVA->PJM
CLTF
1.3261.326
MECLTFEXP_MEC->PJM
CLTF
3.7733.773
LAGNLTFEXP_LAGN->PJM
CLTF
2.092.09
SIGELTFEXP_SIGE->PJM
CLTF
0.320.32
O66PJM->LTFIMP_O-066
CMTX_NF
5.9075.907
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.3980.398

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1401_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.35 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:974.43
MW Contribution:7.27
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.08 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:971.74
MW Contribution:7.26
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
Adder
0.13882352941176470.118
961762AG1-017 E
Adder
0.63647058823529420.541
962031AG1-047 C
Adder
3.67764705882352953.126
962032AG1-047 E
Adder
2.45176470588235332.084
965651AG1-433 C
Adder
1.281.088
965652AG1-433 E
Adder
5.9929411764705885.094
24726405LAWG1A
50/50
6.8016.801
24726505LAWG1B
50/50
6.8016.801
24726605LAWG1S
50/50
10.86210.862
24726705LAWG2A
50/50
6.8016.801
24726805LAWG2B
50/50
6.3126.312
24726905LAWG2S
50/50
10.86210.862
247543V3-007 C
50/50
0.4940.494
247929S-071 E
Adder
5.8588235294117654.98
247935V3-007 E
50/50
20.21420.214
24795805WLD G2 E
Adder
12.56117647058823510.677
24796305HDWTR1G E
50/50
20.21420.214
934962AD1-128 E
Adder
7.37529411764705946.269
936561AD2-071 C
Adder
4.7105882352941174.004
936562AD2-071 E
Adder
2.321.972
942081AE2-220 C
50/50
6.0996.099
942082AE2-220 E
50/50
8.4228.422
944031AF1-071 C
Adder
0.475294117647058870.404
944032AF1-071 E
Adder
0.77411764705882360.658
958711AF2-162 C
Adder
2.1823529411764711.855
958712AF2-162 E
Adder
1.09058823529411760.927
960971AF2-388 C
Adder
2.562.176
960972AF2-388 E
Adder
11.98588235294117710.188
24379505HDWTR1G C
50/50
0.4940.494
25194708EBND2
50/50
16.24416.244
932681AC2-090 C
50/50
0.720.72
932682AC2-090 E
50/50
7.2037.203
939761AE1-207 C
Adder
4.46823529411764753.798
939762AE1-207 E
Adder
6.1694117647058825.244
939771AE1-208 C
Adder
3.96117647058823553.367
939772AE1-208 E
Adder
5.40117647058823554.591
942071AE2-219 C
Adder
2.5705882352941182.185
942072AE2-219 E
Adder
3.55058823529411743.018
247968Z2-115 E
Adder
0.070588235294117650.06
926874AC1-174 E
50/50
7.2037.203
926881AC1-175 E
50/50
7.2037.203
270209AC1-174 C
50/50
0.7210.721
270210AC1-175 C
50/50
0.7210.721
270222AC2-111 C
Adder
2.1105882352941181.794
932844AC2-111 E
Adder
3.4082352941176472.897
933596AC2-176 E
Adder
6.9329411764705885.893
942221AE2-234 C
Adder
1.31.105
942222AE2-234 E
Adder
0.58823529411764710.5
942791AE2-297 C O1
50/50
1.5831.583
942792AE2-297 E O1
50/50
6.6286.628
944531AF1-118 C
Adder
16.36705882352941213.912
944532AF1-118 E
Adder
4.9364705882352944.196
944541AF1-119 C
Adder
10.182352941176478.655
944542AF1-119 E
Adder
4.3635294117647063.709
945371AF1-202 C
Adder
2.61529411764705882.223
945372AF1-202 E
Adder
12.76823529411764610.853
945581AF1-223 C
Adder
6.9223529411764715.884
945582AF1-223 E
Adder
4.6152941176470593.923
946032AF1-268 E
Adder
2.04588235294117651.739
958861AF2-177 C
Adder
1.9482352941176471.656
958862AF2-177 E
Adder
13.03647058823529511.081
961171AF2-408 C
Adder
6.4976470588235295.523
939781AE1-209 C
Adder
1.21.02
939782AE1-209 E
Adder
8.0305882352941186.826
939791AE1-210 C
Adder
1.21.02
939792AE1-210 E
Adder
8.0305882352941186.826
946031AF1-268 C
Adder
4.5105882352941183.834
964611AG1-324 C
Adder
1.8117647058823531.54
964612AG1-324 E
Adder
0.72117647058823530.613
940981AE2-089 C
Adder
4.9988235294117644.249
940982AE2-089 E
Adder
3.33294117647058872.833
941691AE2-169 C
Adder
2.3764705882352942.02
941721AE2-172 C
Adder
2.662.261
957741AF2-068 C
Adder
5.517647058823534.69
957742AF2-068 E
Adder
3.67764705882352953.126
965461AG1-414 C
Adder
2.7552941176470592.342
965462AG1-414 E
Adder
1.83764705882352961.562
CBM West 1LTFEXP_CBM-W1->PJM
CBM
36.49436.494
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.20814.208
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
G-007PJM->LTFIMP_G-007
CMTX_NF
0.9180.918
NYPJM->LTFIMP_NY
CLTF
0.4720.472
LGEELTFEXP_LGEE->PJM
CLTF
0.6160.616
WECLTFEXP_WEC->PJM
CLTF
0.8440.844
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.2620.262
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.1340.134
TVALTFEXP_TVA->PJM
CLTF
1.3281.328
MECLTFEXP_MEC->PJM
CLTF
3.7763.776
LAGNLTFEXP_LAGN->PJM
CLTF
2.0932.093
SIGELTFEXP_SIGE->PJM
CLTF
0.320.32
O66PJM->LTFIMP_O-066
CMTX_NF
5.8835.883
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.3960.396
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7   /*08M.FORT     345.0 - 08M.FRT7      22.0
END
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9   /*08M.FORT     345.0 - 08M.FORT     138.0
END
248001 to 248013 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD1AEP
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
AEP_P1-2_#8702_2543_SRT-A-C
OPAC111.57 %897.0B1000.7947.11
GD1AEP
AF1-202 TP-05DESOTO 345.0 kV Ckt 1 line
AEP_P1-2_#4817_6341_SRT-A
OPAC125.81 %897.0B1128.5499.88

Details for AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line l/o AEP_P1-2_#8702_2543_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:111.57 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1000.79
MW Contribution:47.11
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:112.91 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1012.81
MW Contribution:47.14
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
961761AG1-017 C
50/50
0.2450.245
961762AG1-017 E
50/50
1.1251.125
962031AG1-047 C
50/50
6.5036.503
962032AG1-047 E
50/50
4.3364.336
965651AG1-433 C
50/50
8.2918.291
965652AG1-433 E
50/50
38.81938.819
24699105WLD G1 C
50/50
0.2420.242
24725505WLD G2 C
50/50
0.2350.235
24728505AND G1
50/50
0.5880.588
24728605AND G2
50/50
0.5880.588
24728705AND G3
50/50
1.231.23
24728805RICHG1
50/50
0.6040.604
24728905RICHG2
50/50
0.6040.604
24753605BLUFF P WF
50/50
0.4130.413
247543V3-007 C
50/50
0.9250.925
247929S-071 E
50/50
10.110.1
247935V3-007 E
50/50
37.89937.899
24795805WLD G2 E
50/50
19.56819.568
24796305HDWTR1G E
50/50
37.89937.899
934961AD1-128 C
50/50
1.4761.476
934962AD1-128 E
50/50
15.74415.744
936561AD2-071 C
50/50
7.2167.216
936562AD2-071 E
50/50
3.5543.554
942081AE2-220 C
50/50
11.43511.435
942082AE2-220 E
50/50
15.79115.791
944031AF1-071 C
Adder
0.64588235294117660.549
944032AF1-071 E
Adder
1.05411764705882360.896
958711AF2-162 C
50/50
14.13314.133
958712AF2-162 E
50/50
7.0677.067
960971AF2-388 C
50/50
16.58316.583
960972AF2-388 E
50/50
77.63877.638
24341505WWVSTA
50/50
1.6751.675
24379505HDWTR1G C
50/50
0.9250.925
932681AC2-090 C
50/50
1.3511.351
932682AC2-090 E
50/50
13.50413.504
939761AE1-207 C
50/50
7.9447.944
939762AE1-207 E
50/50
10.9710.97
939771AE1-208 C
50/50
6.3866.386
939772AE1-208 E
50/50
8.7088.708
942071AE2-219 C
50/50
4.4324.432
942072AE2-219 E
50/50
6.1216.121
926874AC1-174 E
50/50
13.50413.504
926881AC1-175 E
50/50
13.50413.504
270201AC2-176 GEN
50/50
0.2990.299
270209AC1-174 C
50/50
1.3531.353
270210AC1-175 C
50/50
1.3531.353
270222AC2-111 C
Adder
2.86941176470588262.439
932844AC2-111 E
Adder
4.6352941176470593.94
933596AC2-176 E
50/50
12.25912.259
942791AE2-297 C O1
50/50
1.8541.854
942792AE2-297 E O1
50/50
7.767.76
944531AF1-118 C
50/50
65.88465.884
944532AF1-118 E
50/50
19.87119.871
944541AF1-119 C
50/50
65.95565.955
944542AF1-119 E
50/50
28.26628.266
945371AF1-202 C
50/50
14.37414.374
945372AF1-202 E
50/50
70.17970.179
945581AF1-223 C
50/50
38.04938.049
945582AF1-223 E
50/50
25.36625.366
946032AF1-268 E
50/50
4.5994.599
958861AF2-177 C
50/50
6.3726.372
958862AF2-177 E
50/50
42.64542.645
961171AF2-408 C
50/50
11.20711.207
24336205RANDOLPH1
50/50
0.0690.069
939781AE1-209 C
50/50
3.1873.187
939782AE1-209 E
50/50
21.3321.33
939791AE1-210 C
50/50
3.1873.187
939792AE1-210 E
50/50
21.3321.33
946031AF1-268 C
50/50
10.13810.138
964611AG1-324 C
50/50
3.4223.422
964612AG1-324 E
50/50
1.3621.362
941691AE2-169 C
50/50
3.8323.832
941721AE2-172 C
50/50
4.7294.729
957741AF2-068 C
50/50
9.7559.755
957742AF2-068 E
50/50
6.5036.503
965461AG1-414 C
Adder
4.2541176470588233.616
965462AG1-414 E
Adder
2.8364705882352942.411
955152J993 G
External Queue
18.25959396362304718.259593963623047
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.73313.733
CBM South 1LTFEXP_CBM-S1->PJM
CBM
00
CBM South 2LTFEXP_CBM-S2->PJM
CBM
10.80710.807
G-007ALTFEXP_G-007A->PJM
CMTX
0.1370.137
VTFLTFEXP_VFT->PJM
CMTX
0.3560.356
NYPJM->LTFIMP_NY
CLTF
0.0070.007
LGEELTFEXP_LGEE->PJM
CLTF
2.4272.427
CPLELTFEXP_CPLE->PJM
CLTF
0.8360.836
TVALTFEXP_TVA->PJM
CLTF
2.5252.525
LAGNLTFEXP_LAGN->PJM
CLTF
2.5582.558
SIGELTFEXP_SIGE->PJM
CLTF
0.4430.443
MDUPJM->LTFIMP_MDU
CLTF
0.0440.044
LTFEXP_AA2-074LTFEXP_AA2-074->LTFIMP_AA2-074
CLTF
0.4110.411

Details for AF1-202 TP-05DESOTO 345.0 kV Ckt 1 line l/o AEP_P1-2_#4817_6341_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF1-202 TP-05DESOTO 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#4817_6341_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:125.81 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1128.54
MW Contribution:99.88
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AF1-202 TP-05DESOTO 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#4817_6341_SRT-A
Contingency Type:OP
DC|AC:AC
Final Cycle Loading:125.8 %
Rating:897.0 MVA
Rating Type:B
MVA to Mitigate:1128.42
MW Contribution:99.88
Bus #Bus NameTypeFull MW ContributionGenDeliv MW Contribution
965651AG1-433 C
50/50
17.57817.578
965652AG1-433 E
50/50
82.29982.299
24729205KEY G1
50/50
9.4329.432
24729305KEY G2
50/50
9.4829.482
24729405KEY G3
50/50
9.6459.645
24729505KEY G4
50/50
9.7769.776
958711AF2-162 C
50/50
29.96329.963
958712AF2-162 E
50/50
14.98214.982
960971AF2-388 C
50/50
35.15735.157
960972AF2-388 E
50/50
164.598164.598
944541AF1-119 C
50/50
139.828139.828
944542AF1-119 E
50/50
59.92659.926
945371AF1-202 C
50/50
33.95833.958
945372AF1-202 E
50/50
165.797165.797
945581AF1-223 C
50/50
89.8989.89
945582AF1-223 E
50/50
59.92659.926
G-007PJM->LTFIMP_G-007
CMTX_NF
0.1290.129
NYPJM->LTFIMP_NY
CLTF
0.0680.068
COTTONWOODPJM->LTFIMP_COTTONWOOD
CLTF
0.2570.257
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.0710.071
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.0430.043
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
0.3170.317
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.0680.068
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.2120.212
O66PJM->LTFIMP_O-066
CMTX_NF
0.8250.825
MDUPJM->LTFIMP_MDU
CLTF
0.0120.012
LTFEXP_AC1-056LTFEXP_AC1-056->LTFIMP_AC1-056
CLTF
0.1230.123
LTFEXP_AC1-131LTFEXP_AC1-131->LTFIMP_AC1-131
CLTF
0.0920.092
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A'
 OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1   /*05KEYSTN     345.0 - 05SORENS     345.0
END
944540 to 243225 ckt 1
945370 to 243218 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request AG1-433 was evaluated as a 100.0 MW injection in the AEP area.

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Based on PJM’s Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 63 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 63 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 63 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 63 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 63 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 102 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

a)       Steady-state operation (20 second run),

b)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

c)       Single-phase bus faults with normal clearing time,

d)       Single-phase faults with stuck breakers,

e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 63 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 63 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-433 and AF2-388 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCAU model of AG1-433 GEN, and AF2-388 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

It was observed that the terminal voltage of the AF1-119 and AF2-162 generating units after fault clearing for several contingency goes beyond the limits. This can be eliminated by adjusting the following for both AF1-119 and AF2-162 in the REPCA1 model: Kc to 0.1 (originally set to 0), Ki to 8 (originally set to 50), and Kp to 2 (originally set to 1).

 

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from Cluster 63. The CSCR results are summarized in Table 4 through Table 8 and revealed a minimum and maximum CSCR values of 3.17 for P7.13, and 4.99 for P1.09, respectively.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 63 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

63

AF2-388

Wind

AEP

200 MW

200

35.2

Keystone-Desoto 345 kV

AG1-433

Wind

AEP

100 MW

100

17.6

Keystone-Desoto 345 kV

 

 

Reactive Power Analysis

The reactive power capability of AG1-433 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AC1-174Losantville 345kVIn Service
AC1-175Losantville 345kVIn Service
AC2-090Losantville 345kVIn Service
AC2-111College Corner 138kVEngineering & Procurement
AC2-176Jay 138 kVIn Service
AD1-128Modoc-Delaware 138 kVIn Service
AD2-071Strawton-Deer Creek 138 kVSuspended
AE1-207Mississinewa-Gaston 138 kVSuspended
AE1-208Delaware-Van Buren 138 kVSuspended
AE1-209Desoto 345 kVSuspended
AE1-210Desoto 345 kVSuspended
AE2-089Pennville-Adams 138 kVSuspended
AE2-169Delaware-Van Buren 138 kVSuspended
AE2-172Mississinewa-Gaston 138 kVSuspended
AE2-219Bluff Point-Randolph 138 kVSuspended
AE2-220Losantville 345 kVEngineering & Procurement
AE2-234Liberty Center-Buckeye Tap 69 kVEngineering & Procurement
AE2-297Madison-Tanners Creek 138 kVIn Service
AF1-071College Corner 138 kVEngineering & Procurement
AF1-118Sorenson-Desoto 345 kVWithdrawn
AF1-119Keystone-Desoto 345 kVEngineering & Procurement
AF1-202Keystone-Desoto 345 kVUnder Construction
AF1-223Keystone-Desoto 345 kVUnder Construction
AF1-268Desoto-Jay 138 kVEngineering & Procurement
AF2-068Jay 138 kVEngineering & Procurement
AF2-162Keystone-Desoto 345 kVEngineering & Procurement
AF2-177Sorenson-DeSoto #2 345 kVEngineering & Procurement
AF2-388Keystone-Desoto 345 kVEngineering & Procurement
AF2-408Fall Creek 138 kVEngineering & Procurement
AG1-017Jay 138 kVIn Service
AG1-047Jay 138 kVEngineering & Procurement
AG1-324Jay-Desoto 138 kVEngineering & Procurement
AG1-414Mississinewa 138 kVEngineering & Procurement
V3-007Desoto-Tanners Creek #1 345kVIn Service
Z2-115Deer Creek 12.47kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In coordination with other Affected System Operators, PJM has determined that the Affected System Operator for this project that requires an Affected System Study. For the latest Affected System Study results pertaining this project, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM lists any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Final System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AG1-433 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
OVECn9680.0Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° FCost Allocated$4,743,908
Grand Total:$4,743,908

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9680.0
Type
Load Flow
TO
OVEC
RTEP ID / TO ID
n9680.0 / OVEC0001a
Title
Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F
Description
•Remove and replace sixteen (16) existing double circuit towers with taller double circuit custom steel poles. (Towers 11, 14, 45, 47, 52, 57, 59, 61, 63, 66, 67, 71, 77, 84, 91, and 96) •Remove and replace two (2) existing river crossing lattice towers with taller lattice structures. (Towers 2 and 140)
Total Cost ($USD)
$24,006,000
Discounted Total Cost ($USD)
$24,006,000
Allocated Cost ($USD)
$4,743,908
Time Estimate
38 Months

Contributor

FacilityContingency
06DEARB1-06PIERCE 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)B1165.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AF2-17715.0 MW40.7%$9,774,277
AF2-388 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
14.5 MW39.5%$9,487,815
AG1-433 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
7.3 MW19.8%$4,743,908

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-433


AG1-433 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AG1-433 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AG1-433 One Line Diagram

AG1-433 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.