AG1-354 Phase II Study Report

v1.00 released 2024-12-18 14:07

Summershade-Green County 161 kV

90.0 MW Capacity / 150.0 MW Energy

Introduction

This Phase II System Impact Study Report (PH2) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle #1. The Project Developer/Eligible Customer (developer) is Exie Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is East Kentucky Power Cooperative, Inc..

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
  1. PJM will retool load flow results from Phase I System Impact Study (summer peak, winter peak[1] and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $49,255,695 $31,739,601 = 1.55 AND ( $49,255,695 - $31,739,601 ) 150.0 = $116,774 per MW

General

The Project Developer has proposed a Solar generating facility located in the East Kentucky Power Cooperative, Inc. zone — Green County, Kentucky. The installed facilities will have a total capability of 150.0 MW with 90.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number AG1-354
Project Name Summershade-Green County 161 kV
Project Developer Name Exie Solar, LLC
State Kentucky
County Green
Transmission Owner East Kentucky Power Cooperative, Inc.
MFO 150.0 MW
MWE 150.0 MW
MWC 90.0 MW
Fuel Type Solar
Basecase Study Year 2027

Physical Interconnection Facility Study

Received

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-354 will interconnect on the EKPC transmission system tapping the Summer Shade to Greene County 161 kV line.

 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AG1-354 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
Description Cost Allocated to AG1-354 Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF) $904,000 $0
Other Scope $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $11,233,000 $11,233,000
Network Upgrades $6,127,000 $6,127,000
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $31,895,695 $31,895,695
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements $0 $0
Total $50,159,695 $49,255,695

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase 2 SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AG1-354

Readiness Deposit #3 has been calculated for the AG1-354 project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID 20% of cost allocation for Phase II Network Upgrades Sum of Readiness Deposit #1 & Readiness Deposit #2 Received (RD1+RD2) Readiness Deposit #3 (RD3) for AG1-354 Project due at DP2
A B A - B
AG1-354 $9,851,139 $3,173,960 $6,677,179

Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

EKPC will construct a 161 kV switching station and a new 161 kV loop-in tap from the EKPC Summer Shade-Green County 161 kV line to accommodate the direct connection of the PD’s substation facilities to the EKPC transmission system.  EKPC will also construct a 161 kV disconnect switch structure which will be the POI interface. EKPC will also complete the required network upgrades at existing EKPC substations, which are system protection changes necessary at the Green County and Summer Shade substations to accommodate the addition of this new facility, and installation of OPGW on the existing 161 kV line section from the new Liletown Road switching station to the Green County and Summer Shade substations in order to provide necessary communications infrastructure for EKPC.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Remote Relay Settings at Greene County Sub

$130,000 $4,000 $11,000 $1,000 $146,000 $146,000
(Pending)

Remote Relay Settings at Summer Shade Sub

$130,000 $4,000 $11,000 $1,000 $146,000 $146,000
(Pending)

Interconnection Substation Tie-In

$620,000 $333,000 $79,000 $9,000 $1,041,000 $1,041,000
(Pending)

Fiber Installation in Existing ROW

$3,372,000 $1,015,000 $366,000 $41,000 $4,794,000 $4,794,000
Stand-Alone Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Liletown Road Substation

$5,202,000 $5,079,000 $857,000 $95,000 $11,233,000 $11,233,000
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Transmission Owner Interconnection Facilities

$477,000 $350,000 $69,000 $8,000 $904,000 $904,000
Developer Build Option

Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.

If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Remote Relay Settings at Greene County Sub

$130,000 $4,000 $11,000 $1,000 $146,000 $146,000
(Pending)

Remote Relay Settings at Summer Shade Sub

$130,000 $4,000 $11,000 $1,000 $146,000 $146,000
(Pending)

Fiber Installation in Existing ROW

$3,372,000 $1,015,000 $366,000 $41,000 $4,794,000 $4,794,000
(Pending)

Interconnection Substation Tie-In

$620,000 $333,000 $79,000 $9,000 $1,041,000 $1,041,000
Other
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Transmission Owner Interconnection Facilities (Oversight)

$66,000 $15,000 $9,000 $9,000 $99,000 $99,000
(Pending)

New Interconnection Substation (Oversight)

$806,000 $212,000 $110,000 $110,000 $1,238,000 $1,238,000
Build Option Price Comparison
Build Option Total Cost Allocated Cost
Transmission Owner Build Option $18,264,000 $18,264,000
Developer Build Option $7,464,000 $7,464,000

Based on the scope of work for the Interconnection Facilities, it is expected to take 51 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

EKPC anticipates that it will take 51 months after the signing of the Generator Interconnection Agreement and the project kickoff call is subsequently held to complete the physical interconnection projects. This assumes no delays due to permitting or environmental issues, and that all necessary outages can be taken as needed to maintain this schedule.

Transmission Owner Analysis

No violations.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. EKPC interconnection requirements can be found here. Refer to AG1-354 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 150.0 MW (90.0 MW Capacity) injection in the EKPC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Summer Peak Analysis
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_MAR W38-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_MAR W38-1014_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342770 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
END
Breaker AC 145.19 39.0 B 56.62 9.2
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 133.61 277.0 B 370.11 17.8
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_SSHAD S11-1014_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1014_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Breaker AC 125.97 39.0 B 49.13 20.28
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
END
Breaker AC 125.16 39.0 B 48.81 20.23
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1537_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1537_MELDAHL345_SRT-A'
 OPEN BUS 249581   /*08MELDAL     345.0
END
Breaker AC 119.57 1532.0 B 1831.83 14.37
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1535_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1535_MELDAHL345_SRT-A'
 OPEN BRANCH FROM BUS 249581 TO BUS 342838 CKT 1   /*08MELDAL     345.0 - 7SPURLOCK    345.0
 OPEN BUS 250145                                   /*08MELDAL     138.0
END
Breaker AC 119.57 1532.0 B 1831.8 14.37
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1539_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1539_MELDAHL345_SRT-A'
 OPEN BRANCH FROM BUS 249581 TO BUS 249577 CKT 1   /*08MELDAL     345.0 - 08ZIMER      345.0
 OPEN BUS 250145                                   /*08MELDAL     138.0
END
Breaker AC 119.55 1532.0 B 1831.43 14.37
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-3_LIB J S4-1024_SRT-A
CONTINGENCY 'EKPC_P2-3_LIB J S4-1024_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BUS 342760                                   /*5LIBERTY J   161.0
END
Breaker AC 111.61 220.0 B 245.55 22.31
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-3_CASEY S89-1008_SRT-A
CONTINGENCY 'EKPC_P2-3_CASEY S89-1008_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 111.52 220.0 B 245.35 22.32
EKPC AG1-354 TP-5SUMM SHADE 161.0 kV Ckt 1 line
964900 to 342814 ckt 1
EKPC_P2-3_MAR W38-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_MAR W38-1014_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342770 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
END
Breaker AC 111.09 298.0 B 331.06 126.86
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-3_LIB J S4-1024_SRT-A
CONTINGENCY 'EKPC_P2-3_LIB J S4-1024_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BUS 342760                                   /*5LIBERTY J   161.0
END
Breaker AC 105.24 234.0 B 246.26 22.31
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-3_CASEY S89-1008_SRT-A
CONTINGENCY 'EKPC_P2-3_CASEY S89-1008_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 105.15 234.0 B 246.05 22.32
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-2_CASEY CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_CASEY CO 161_SRT-A'
 OPEN BUS 342703   /*5CASEY CO    161.0
END
Bus AC 111.52 220.0 B 245.35 22.32
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-2_CASEY CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_CASEY CO 161_SRT-A'
 OPEN BUS 342703   /*5CASEY CO    161.0
END
Bus AC 105.15 234.0 B 246.05 22.32
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P1-2_LAUR-L DAM161_SRT-A
CONTINGENCY 'EKPC_P1-2_LAUR-L DAM161_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
END
Single AC 111.55 277.0 B 309.01 10.71
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
Base Case Single AC 100.84 1240.0 A 1250.44 7.5
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A
CONTINGENCY 'DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A'
 OPEN BRANCH FROM BUS 249577 TO BUS 249581 CKT 1   /*08ZIMER      345.0 - 08MELDAL     345.0
END
Single AC 100.2 1532.0 B 1535.08 8.59
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 155.93 105.0 B 163.73 12.11
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 133.61 277.0 B 370.11 17.8
EKPC/TVA 5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line
342814 to 360334 ckt 1
EKPC_P7-1_BULL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_BULL 161 DBL_SRT-A'
 OPEN BUS 326975   /*5CEDAR GRV   161.0
 OPEN BUS 361788   /*5SUM SHAD TP 161.0
END
Tower AC 123.14 289.0 B 355.89 99.43
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 111.75 220.0 B 245.86 19.17
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 105.36 234.0 B 246.54 19.17

Details for 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line l/o EKPC_P2-3_MAR W38-1014_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_MAR W38-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_MAR W38-1014_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342770 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
END
Breaker AC 145.19 39.0 B 56.62 9.2
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_MAR W38-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_MAR W38-1014_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342770 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
END
Breaker AC 145.84 39.0 B 56.88 9.2
Topology Case Flowgate Details for 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line l/o EKPC_P2-3_MAR W38-1014_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 6.87 MW 6.87 MW
964892 AG1-353 E 50/50 4.58 MW 4.58 MW
964901 AG1-354 C Adder 5.52 MW 4.69 MW
964902 AG1-354 E Adder 3.68 MW 3.13 MW
943821 AF1-050 C Adder 3.44 MW 2.93 MW
943822 AF1-050 E Adder 2.3 MW 1.95 MW
944511 AF1-116 C 50/50 8.42 MW 8.42 MW
944512 AF1-116 E 50/50 5.61 MW 5.61 MW
939132 AE1-143 E 50/50 3.72 MW 3.72 MW
339206 AE1-143 C 50/50 7.5 MW 7.5 MW
944151 AF1-083 C 50/50 3.86 MW 3.86 MW
944152 AF1-083 E 50/50 2.57 MW 2.57 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.75 MW 0.75 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.6 MW 1.6 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.1 MW 0.1 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.11 MW 0.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.48 MW 0.48 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.14 MW 0.14 MW
MEC LTFEXP_MEC->PJM CLTF 0.07 MW 0.07 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.5 MW 0.5 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.44 MW 0.44 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1024_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 133.61 277.0 B 370.11 17.8
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 133.53 277.0 B 369.87 17.8
Topology Case Flowgate Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1024_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 7.75 MW 7.75 MW
964892 AG1-353 E 50/50 5.16 MW 5.16 MW
964901 AG1-354 C 50/50 10.68 MW 10.68 MW
964902 AG1-354 E 50/50 7.12 MW 7.12 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.62 MW 6.62 MW
943702 AF1-038 E 50/50 4.42 MW 4.42 MW
943821 AF1-050 C 50/50 4.45 MW 4.45 MW
943822 AF1-050 E 50/50 2.96 MW 2.96 MW
944511 AF1-116 C 50/50 11.03 MW 11.03 MW
944512 AF1-116 E 50/50 7.35 MW 7.35 MW
945381 AF1-203 C 50/50 0.21 MW 0.21 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 9.77 MW 9.77 MW
342903 1COOPER2 G 50/50 19.02 MW 19.02 MW
342945 1LAUREL 1G 50/50 5.91 MW 5.91 MW
939132 AE1-143 E 50/50 4.87 MW 4.87 MW
940831 AE2-071 C 50/50 0.38 MW 0.38 MW
940832 AE2-071 E 50/50 1.68 MW 1.68 MW
339206 AE1-143 C 50/50 9.83 MW 9.83 MW
962241 AG1-070 C 50/50 3.34 MW 3.34 MW
962242 AG1-070 E 50/50 1.26 MW 1.26 MW
962251 AG1-071 C 50/50 3.83 MW 3.83 MW
962252 AG1-071 E 50/50 1.79 MW 1.79 MW
944151 AF1-083 C 50/50 4.46 MW 4.46 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.56 MW 2.17 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
966951 AE2-000D C 50/50 6.32 MW 6.32 MW
966952 AE2-000D E 50/50 3.07 MW 3.07 MW
962221 AG1-067 C 50/50 2.78 MW 2.78 MW
962222 AG1-067 E 50/50 1.48 MW 1.48 MW
964781 AG1-341 C 50/50 7.33 MW 7.33 MW
964782 AG1-341 E 50/50 4.88 MW 4.88 MW
965411 AG1-406 C 50/50 2.57 MW 2.57 MW
966021 AG1-471 C 50/50 7.28 MW 7.28 MW
966022 AG1-471 E 50/50 4.85 MW 4.85 MW
950000 AG9-001 External Queue 7.4 MW 7.4 MW
950011 AG9-010 External Queue 13.44 MW 13.44 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.48 MW 3.48 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.06 MW 5.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.41 MW 2.41 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.1 MW 0.1 MW
TVA LTFEXP_TVA->PJM CLTF 1.91 MW 1.91 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.77 MW 1.77 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line l/o EKPC_P2-3_SSHAD S11-1014_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_SSHAD S11-1014_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1014_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Breaker AC 125.97 39.0 B 49.13 20.28
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_SSHAD S11-1014_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1014_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Breaker AC 126.49 39.0 B 49.33 20.27
Topology Case Flowgate Details for 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line l/o EKPC_P2-3_SSHAD S11-1014_SRT-A-1
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 6.99 MW 6.99 MW
964892 AG1-353 E 50/50 4.66 MW 4.66 MW
964901 AG1-354 C 50/50 12.17 MW 12.17 MW
964902 AG1-354 E 50/50 8.11 MW 8.11 MW
943821 AF1-050 C 50/50 4.87 MW 4.87 MW
943822 AF1-050 E 50/50 3.24 MW 3.24 MW
944511 AF1-116 C Adder 4.57 MW 3.88 MW
944512 AF1-116 E Adder 3.04 MW 2.59 MW
939132 AE1-143 E Adder 2.02 MW 1.72 MW
339206 AE1-143 C Adder 4.07 MW 3.46 MW
944151 AF1-083 C 50/50 3.57 MW 3.57 MW
944152 AF1-083 E 50/50 2.38 MW 2.38 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.06 MW 0.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.91 MW 0.91 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.03 MW 0.03 MW
VTF LTFEXP_VFT->PJM CMTX 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.07 MW 0.07 MW
TVA LTFEXP_TVA->PJM CLTF 0.21 MW 0.21 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.07 MW 0.07 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.14 MW 0.14 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.17 MW 0.17 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.03 MW 0.03 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.05 MW 0.05 MW

Details for 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line l/o EKPC_P2-3_SSHAD S11-1004_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
END
Breaker AC 125.16 39.0 B 48.81 20.23
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line
341563 to 342325 ckt 1
EKPC_P2-3_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
END
Breaker AC 125.63 39.0 B 49.0 20.22
Topology Case Flowgate Details for 2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line l/o EKPC_P2-3_SSHAD S11-1004_SRT-A-1
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 6.97 MW 6.97 MW
964892 AG1-353 E 50/50 4.65 MW 4.65 MW
964901 AG1-354 C 50/50 12.14 MW 12.14 MW
964902 AG1-354 E 50/50 8.09 MW 8.09 MW
943821 AF1-050 C 50/50 4.85 MW 4.85 MW
943822 AF1-050 E 50/50 3.24 MW 3.24 MW
944511 AF1-116 C Adder 4.55 MW 3.87 MW
944512 AF1-116 E Adder 3.03 MW 2.58 MW
939132 AE1-143 E Adder 2.01 MW 1.71 MW
339206 AE1-143 C Adder 4.05 MW 3.45 MW
944151 AF1-083 C 50/50 3.56 MW 3.56 MW
944152 AF1-083 E 50/50 2.37 MW 2.37 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.8 MW 0.8 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.03 MW 0.03 MW
VTF LTFEXP_VFT->PJM CMTX 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.06 MW 0.06 MW
TVA LTFEXP_TVA->PJM CLTF 0.17 MW 0.17 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.08 MW 0.08 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.46 MW 0.46 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.14 MW 0.14 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.03 MW 0.03 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.05 MW 0.05 MW

Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P2-3_1537_MELDAHL345_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1537_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1537_MELDAHL345_SRT-A'
 OPEN BUS 249581   /*08MELDAL     345.0
END
Breaker AC 119.57 1532.0 B 1831.83 14.37
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1537_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1537_MELDAHL345_SRT-A'
 OPEN BUS 249581   /*08MELDAL     345.0
END
Breaker AC 120.03 1532.0 B 1838.93 14.48
Topology Case Flowgate Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P2-3_1537_MELDAHL345_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 6.96 MW 5.92 MW
964892 AG1-353 E Adder 4.64 MW 3.94 MW
964901 AG1-354 C Adder 8.62 MW 7.33 MW
964902 AG1-354 E Adder 5.75 MW 4.88 MW
965401 AG1-405 C Adder 6.03 MW 5.12 MW
965402 AG1-405 E Adder 4.02 MW 3.42 MW
966571 AG1-526 C Adder 29.12 MW 24.75 MW
966572 AG1-526 E Adder 19.41 MW 16.5 MW
925985 AC1-074 E 50/50 8.05 MW 8.05 MW
926105 AC1-089 E Adder 9.86 MW 8.38 MW
936381 AD2-048 C 50/50 15.16 MW 15.16 MW
936382 AD2-048 E 50/50 7.56 MW 7.56 MW
936576 AD2-072_E Adder 5.7 MW 4.85 MW
942091 AE2-221 C Adder -22.75 MW -19.34 MW
943111 AE2-339 C 50/50 8.96 MW 8.96 MW
943112 AE2-339 E 50/50 4.42 MW 4.42 MW
943701 AF1-038 C Adder 4.39 MW 3.73 MW
943702 AF1-038 E Adder 2.93 MW 2.49 MW
943821 AF1-050 C Adder 3.83 MW 3.25 MW
943822 AF1-050 E Adder 2.55 MW 2.17 MW
944511 AF1-116 C Adder 9.72 MW 8.27 MW
944512 AF1-116 E Adder 6.48 MW 5.51 MW
945681 AF1-233 C 50/50 57.91 MW 57.91 MW
945682 AF1-233 E 50/50 38.61 MW 38.61 MW
959691 AF2-260 C Adder 5.19 MW 4.41 MW
959692 AF2-260 E Adder 3.13 MW 2.66 MW
960161 AF2-307 C 50/50 13.03 MW 13.03 MW
960162 AF2-307 E 50/50 8.69 MW 8.69 MW
960181 AF2-309 C Adder 4.11 MW 3.49 MW
960182 AF2-309 E Adder 2.74 MW 2.33 MW
960571 AF2-348 C 50/50 83.82 MW 83.82 MW
960572 AF2-348 E 50/50 55.88 MW 55.88 MW
342918 1JKCT 1G 50/50 5.24 MW 5.24 MW
342924 1JKCT 3G 50/50 5.15 MW 5.15 MW
342939 1JKCT 9G 50/50 3.85 MW 3.85 MW
342942 1JKCT 10G 50/50 3.85 MW 3.85 MW
342957 1SPURLK1G 50/50 26.98 MW 26.98 MW
342960 1SPURLK2G 50/50 51.44 MW 51.44 MW
342963 1SPURLK3G 50/50 27.02 MW 27.02 MW
342966 1SPURLK4G 50/50 27.02 MW 27.02 MW
939132 AE1-143 E Adder 4.3 MW 3.65 MW
941411 AE2-138 C 50/50 8.33 MW 8.33 MW
941412 AE2-138 E 50/50 95.78 MW 95.78 MW
957961 AF2-090 C Adder 7.01 MW 5.96 MW
957962 AF2-090 E Adder 3.47 MW 2.95 MW
942415 AE2-254 E Adder 3.95 MW 3.36 MW
339200 AD2-072_C Adder 11.63 MW 9.89 MW
339206 AE1-143 C Adder 8.66 MW 7.37 MW
339216 AC1-074 C 50/50 3.04 MW 3.04 MW
962211 AG1-066 C Adder 5.14 MW 4.37 MW
962212 AG1-066 E Adder 3.43 MW 2.92 MW
932554 AC2-075 E 50/50 2.25 MW 2.25 MW
339218 AC2-075 C 50/50 0.68 MW 0.68 MW
942591 AE2-275 C Adder 2.1 MW 1.78 MW
942592 AE2-275 E Adder 24.14 MW 20.52 MW
942891 AE2-308 C Adder 17.42 MW 14.81 MW
942892 AE2-308 E Adder 11.61 MW 9.87 MW
944151 AF1-083 C Adder 4.03 MW 3.42 MW
944152 AF1-083 E Adder 2.69 MW 2.28 MW
960151 AF2-306 C 50/50 8.56 MW 8.56 MW
960171 AF2-308 C Adder 2.74 MW 2.33 MW
960641 AF2-355 C Adder 39.21 MW 33.33 MW
960642 AF2-355 E Adder 26.14 MW 22.22 MW
960741 AF2-365 C Adder 2.81 MW 2.39 MW
960742 AF2-365 E Adder 1.88 MW 1.59 MW
961001 AF2-391 C Adder 7.01 MW 5.96 MW
961002 AF2-391 E Adder 4.67 MW 3.97 MW
964571 AG1-320 C Adder 5.58 MW 4.74 MW
964572 AG1-320 E Adder 2.77 MW 2.35 MW
941981 AE2-210 C 50/50 2.88 MW 2.88 MW
941982 AE2-210 E 50/50 33.15 MW 33.15 MW
958171 AF2-111 C 50/50 89.19 MW 89.19 MW
958172 AF2-111 E 50/50 59.46 MW 59.46 MW
965411 AG1-406 C Adder 3.88 MW 3.3 MW
966021 AG1-471 C Adder 3.71 MW 3.15 MW
966022 AG1-471 E Adder 2.47 MW 2.1 MW
950041 AG9-017 External Queue 26.7 MW 26.7 MW
950051 AG9-018 External Queue 26.64 MW 26.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.44 MW 11.44 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 20.38 MW 20.38 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 18.78 MW 18.78 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.94 MW 0.94 MW
NY PJM->LTFIMP_NY CLTF 0.54 MW 0.54 MW
LGEE LTFEXP_LGEE->PJM CLTF 4.96 MW 4.96 MW
WEC LTFEXP_WEC->PJM CLTF 0.32 MW 0.32 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.13 MW 1.13 MW
TVA LTFEXP_TVA->PJM CLTF 5.89 MW 5.89 MW
MEC LTFEXP_MEC->PJM CLTF 2.82 MW 2.82 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.07 MW 6.07 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.49 MW 0.49 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 6.03 MW 6.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.54 MW 0.54 MW

Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P2-3_1535_MELDAHL345_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1535_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1535_MELDAHL345_SRT-A'
 OPEN BRANCH FROM BUS 249581 TO BUS 342838 CKT 1   /*08MELDAL     345.0 - 7SPURLOCK    345.0
 OPEN BUS 250145                                   /*08MELDAL     138.0
END
Breaker AC 119.57 1532.0 B 1831.8 14.37
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1535_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1535_MELDAHL345_SRT-A'
 OPEN BRANCH FROM BUS 249581 TO BUS 342838 CKT 1   /*08MELDAL     345.0 - 7SPURLOCK    345.0
 OPEN BUS 250145                                   /*08MELDAL     138.0
END
Breaker AC 120.03 1532.0 B 1838.91 14.48
Topology Case Flowgate Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P2-3_1535_MELDAHL345_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 6.96 MW 5.92 MW
964892 AG1-353 E Adder 4.64 MW 3.94 MW
964901 AG1-354 C Adder 8.62 MW 7.33 MW
964902 AG1-354 E Adder 5.75 MW 4.88 MW
965401 AG1-405 C Adder 6.03 MW 5.12 MW
965402 AG1-405 E Adder 4.02 MW 3.42 MW
966571 AG1-526 C Adder 29.12 MW 24.75 MW
966572 AG1-526 E Adder 19.41 MW 16.5 MW
925985 AC1-074 E 50/50 8.05 MW 8.05 MW
926105 AC1-089 E Adder 9.86 MW 8.38 MW
936381 AD2-048 C 50/50 15.16 MW 15.16 MW
936382 AD2-048 E 50/50 7.56 MW 7.56 MW
936576 AD2-072_E Adder 5.7 MW 4.85 MW
942091 AE2-221 C Adder -22.75 MW -19.34 MW
943111 AE2-339 C 50/50 8.96 MW 8.96 MW
943112 AE2-339 E 50/50 4.42 MW 4.42 MW
943701 AF1-038 C Adder 4.39 MW 3.73 MW
943702 AF1-038 E Adder 2.93 MW 2.49 MW
943821 AF1-050 C Adder 3.83 MW 3.25 MW
943822 AF1-050 E Adder 2.55 MW 2.17 MW
944511 AF1-116 C Adder 9.72 MW 8.27 MW
944512 AF1-116 E Adder 6.48 MW 5.51 MW
945681 AF1-233 C 50/50 57.91 MW 57.91 MW
945682 AF1-233 E 50/50 38.61 MW 38.61 MW
959691 AF2-260 C Adder 5.19 MW 4.41 MW
959692 AF2-260 E Adder 3.13 MW 2.66 MW
960161 AF2-307 C 50/50 13.03 MW 13.03 MW
960162 AF2-307 E 50/50 8.69 MW 8.69 MW
960181 AF2-309 C Adder 4.11 MW 3.49 MW
960182 AF2-309 E Adder 2.74 MW 2.33 MW
960571 AF2-348 C 50/50 83.82 MW 83.82 MW
960572 AF2-348 E 50/50 55.88 MW 55.88 MW
342918 1JKCT 1G 50/50 5.24 MW 5.24 MW
342924 1JKCT 3G 50/50 5.15 MW 5.15 MW
342939 1JKCT 9G 50/50 3.85 MW 3.85 MW
342942 1JKCT 10G 50/50 3.85 MW 3.85 MW
342957 1SPURLK1G 50/50 26.98 MW 26.98 MW
342960 1SPURLK2G 50/50 51.44 MW 51.44 MW
342963 1SPURLK3G 50/50 27.02 MW 27.02 MW
342966 1SPURLK4G 50/50 27.02 MW 27.02 MW
939132 AE1-143 E Adder 4.3 MW 3.65 MW
941411 AE2-138 C 50/50 8.33 MW 8.33 MW
941412 AE2-138 E 50/50 95.78 MW 95.78 MW
957961 AF2-090 C Adder 7.01 MW 5.96 MW
957962 AF2-090 E Adder 3.47 MW 2.95 MW
942415 AE2-254 E Adder 3.95 MW 3.36 MW
339200 AD2-072_C Adder 11.63 MW 9.89 MW
339206 AE1-143 C Adder 8.66 MW 7.37 MW
339216 AC1-074 C 50/50 3.04 MW 3.04 MW
962211 AG1-066 C Adder 5.14 MW 4.37 MW
962212 AG1-066 E Adder 3.43 MW 2.92 MW
932554 AC2-075 E 50/50 2.25 MW 2.25 MW
339218 AC2-075 C 50/50 0.68 MW 0.68 MW
942591 AE2-275 C Adder 2.1 MW 1.78 MW
942592 AE2-275 E Adder 24.14 MW 20.52 MW
942891 AE2-308 C Adder 17.42 MW 14.81 MW
942892 AE2-308 E Adder 11.61 MW 9.87 MW
944151 AF1-083 C Adder 4.03 MW 3.42 MW
944152 AF1-083 E Adder 2.69 MW 2.28 MW
960151 AF2-306 C 50/50 8.56 MW 8.56 MW
960171 AF2-308 C Adder 2.74 MW 2.33 MW
960641 AF2-355 C Adder 39.21 MW 33.33 MW
960642 AF2-355 E Adder 26.14 MW 22.22 MW
960741 AF2-365 C Adder 2.81 MW 2.39 MW
960742 AF2-365 E Adder 1.88 MW 1.59 MW
961001 AF2-391 C Adder 7.01 MW 5.96 MW
961002 AF2-391 E Adder 4.67 MW 3.97 MW
964571 AG1-320 C Adder 5.58 MW 4.74 MW
964572 AG1-320 E Adder 2.77 MW 2.35 MW
941981 AE2-210 C 50/50 2.88 MW 2.88 MW
941982 AE2-210 E 50/50 33.15 MW 33.15 MW
958171 AF2-111 C 50/50 89.19 MW 89.19 MW
958172 AF2-111 E 50/50 59.46 MW 59.46 MW
965411 AG1-406 C Adder 3.88 MW 3.3 MW
966021 AG1-471 C Adder 3.71 MW 3.15 MW
966022 AG1-471 E Adder 2.47 MW 2.1 MW
950041 AG9-017 External Queue 26.7 MW 26.7 MW
950051 AG9-018 External Queue 26.64 MW 26.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.44 MW 11.44 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 20.38 MW 20.38 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 18.78 MW 18.78 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.94 MW 0.94 MW
NY PJM->LTFIMP_NY CLTF 0.54 MW 0.54 MW
LGEE LTFEXP_LGEE->PJM CLTF 4.96 MW 4.96 MW
WEC LTFEXP_WEC->PJM CLTF 0.32 MW 0.32 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.13 MW 1.13 MW
TVA LTFEXP_TVA->PJM CLTF 5.89 MW 5.89 MW
MEC LTFEXP_MEC->PJM CLTF 2.82 MW 2.82 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.07 MW 6.07 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.49 MW 0.49 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 6.03 MW 6.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.54 MW 0.54 MW

Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P2-3_1539_MELDAHL345_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1539_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1539_MELDAHL345_SRT-A'
 OPEN BRANCH FROM BUS 249581 TO BUS 249577 CKT 1   /*08MELDAL     345.0 - 08ZIMER      345.0
 OPEN BUS 250145                                   /*08MELDAL     138.0
END
Breaker AC 119.55 1532.0 B 1831.43 14.37
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P2-3_1539_MELDAHL345_SRT-A
CONTINGENCY 'DEOK_P2-3_1539_MELDAHL345_SRT-A'
 OPEN BRANCH FROM BUS 249581 TO BUS 249577 CKT 1   /*08MELDAL     345.0 - 08ZIMER      345.0
 OPEN BUS 250145                                   /*08MELDAL     138.0
END
Breaker AC 120.01 1532.0 B 1838.54 14.48
Topology Case Flowgate Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P2-3_1539_MELDAHL345_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 6.96 MW 5.92 MW
964892 AG1-353 E Adder 4.64 MW 3.94 MW
964901 AG1-354 C Adder 8.62 MW 7.33 MW
964902 AG1-354 E Adder 5.75 MW 4.88 MW
965401 AG1-405 C Adder 6.03 MW 5.12 MW
965402 AG1-405 E Adder 4.02 MW 3.42 MW
966571 AG1-526 C Adder 29.12 MW 24.75 MW
966572 AG1-526 E Adder 19.41 MW 16.5 MW
925985 AC1-074 E 50/50 8.05 MW 8.05 MW
926105 AC1-089 E Adder 9.86 MW 8.38 MW
936381 AD2-048 C 50/50 15.16 MW 15.16 MW
936382 AD2-048 E 50/50 7.56 MW 7.56 MW
936576 AD2-072_E Adder 5.7 MW 4.85 MW
942091 AE2-221 C Adder -22.75 MW -19.34 MW
943111 AE2-339 C 50/50 8.96 MW 8.96 MW
943112 AE2-339 E 50/50 4.42 MW 4.42 MW
943701 AF1-038 C Adder 4.39 MW 3.73 MW
943702 AF1-038 E Adder 2.93 MW 2.49 MW
943821 AF1-050 C Adder 3.83 MW 3.25 MW
943822 AF1-050 E Adder 2.55 MW 2.17 MW
944511 AF1-116 C Adder 9.72 MW 8.27 MW
944512 AF1-116 E Adder 6.48 MW 5.51 MW
945681 AF1-233 C 50/50 57.91 MW 57.91 MW
945682 AF1-233 E 50/50 38.61 MW 38.61 MW
959691 AF2-260 C Adder 5.19 MW 4.41 MW
959692 AF2-260 E Adder 3.13 MW 2.66 MW
960161 AF2-307 C 50/50 13.03 MW 13.03 MW
960162 AF2-307 E 50/50 8.69 MW 8.69 MW
960181 AF2-309 C Adder 4.11 MW 3.49 MW
960182 AF2-309 E Adder 2.74 MW 2.33 MW
960571 AF2-348 C 50/50 83.82 MW 83.82 MW
960572 AF2-348 E 50/50 55.88 MW 55.88 MW
342918 1JKCT 1G 50/50 5.24 MW 5.24 MW
342924 1JKCT 3G 50/50 5.15 MW 5.15 MW
342939 1JKCT 9G 50/50 3.85 MW 3.85 MW
342942 1JKCT 10G 50/50 3.85 MW 3.85 MW
342957 1SPURLK1G 50/50 26.98 MW 26.98 MW
342960 1SPURLK2G 50/50 51.44 MW 51.44 MW
342963 1SPURLK3G 50/50 27.02 MW 27.02 MW
342966 1SPURLK4G 50/50 27.02 MW 27.02 MW
939132 AE1-143 E Adder 4.3 MW 3.65 MW
941411 AE2-138 C 50/50 8.33 MW 8.33 MW
941412 AE2-138 E 50/50 95.78 MW 95.78 MW
957961 AF2-090 C Adder 7.01 MW 5.96 MW
957962 AF2-090 E Adder 3.47 MW 2.95 MW
942415 AE2-254 E Adder 3.95 MW 3.36 MW
339200 AD2-072_C Adder 11.63 MW 9.89 MW
339206 AE1-143 C Adder 8.66 MW 7.37 MW
339216 AC1-074 C 50/50 3.04 MW 3.04 MW
962211 AG1-066 C Adder 5.14 MW 4.37 MW
962212 AG1-066 E Adder 3.43 MW 2.92 MW
932554 AC2-075 E 50/50 2.25 MW 2.25 MW
339218 AC2-075 C 50/50 0.68 MW 0.68 MW
942591 AE2-275 C Adder 2.1 MW 1.78 MW
942592 AE2-275 E Adder 24.14 MW 20.52 MW
942891 AE2-308 C Adder 17.42 MW 14.81 MW
942892 AE2-308 E Adder 11.61 MW 9.87 MW
944151 AF1-083 C Adder 4.03 MW 3.42 MW
944152 AF1-083 E Adder 2.69 MW 2.28 MW
960151 AF2-306 C 50/50 8.56 MW 8.56 MW
960171 AF2-308 C Adder 2.74 MW 2.33 MW
960641 AF2-355 C Adder 39.21 MW 33.33 MW
960642 AF2-355 E Adder 26.14 MW 22.22 MW
960741 AF2-365 C Adder 2.81 MW 2.39 MW
960742 AF2-365 E Adder 1.88 MW 1.59 MW
961001 AF2-391 C Adder 7.01 MW 5.96 MW
961002 AF2-391 E Adder 4.67 MW 3.97 MW
964571 AG1-320 C Adder 5.58 MW 4.74 MW
964572 AG1-320 E Adder 2.77 MW 2.35 MW
941981 AE2-210 C 50/50 2.88 MW 2.88 MW
941982 AE2-210 E 50/50 33.15 MW 33.15 MW
958171 AF2-111 C 50/50 89.19 MW 89.19 MW
958172 AF2-111 E 50/50 59.46 MW 59.46 MW
965411 AG1-406 C Adder 3.88 MW 3.3 MW
966021 AG1-471 C Adder 3.71 MW 3.15 MW
966022 AG1-471 E Adder 2.47 MW 2.1 MW
950041 AG9-017 External Queue 26.7 MW 26.7 MW
950051 AG9-018 External Queue 26.64 MW 26.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.44 MW 11.44 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 20.38 MW 20.38 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 18.78 MW 18.78 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.94 MW 0.94 MW
NY PJM->LTFIMP_NY CLTF 0.54 MW 0.54 MW
LGEE LTFEXP_LGEE->PJM CLTF 4.96 MW 4.96 MW
WEC LTFEXP_WEC->PJM CLTF 0.32 MW 0.32 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.13 MW 1.13 MW
TVA LTFEXP_TVA->PJM CLTF 5.89 MW 5.89 MW
MEC LTFEXP_MEC->PJM CLTF 2.82 MW 2.82 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.07 MW 6.07 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.49 MW 0.49 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 6.03 MW 6.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.54 MW 0.54 MW

Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P2-3_LIB J S4-1024_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-3_LIB J S4-1024_SRT-A
CONTINGENCY 'EKPC_P2-3_LIB J S4-1024_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BUS 342760                                   /*5LIBERTY J   161.0
END
Breaker AC 111.61 220.0 B 245.55 22.31
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-3_LIB J S4-1024_SRT-A
CONTINGENCY 'EKPC_P2-3_LIB J S4-1024_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BUS 342760                                   /*5LIBERTY J   161.0
END
Breaker AC 111.78 220.0 B 245.93 22.31
Topology Case Flowgate Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P2-3_LIB J S4-1024_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 21.16 MW 21.16 MW
964892 AG1-353 E 50/50 14.1 MW 14.1 MW
964901 AG1-354 C 50/50 13.39 MW 13.39 MW
964902 AG1-354 E 50/50 8.93 MW 8.93 MW
943821 AF1-050 C 50/50 8.64 MW 8.64 MW
943822 AF1-050 E 50/50 5.76 MW 5.76 MW
944511 AF1-116 C 50/50 44.7 MW 44.7 MW
944512 AF1-116 E 50/50 29.8 MW 29.8 MW
945382 AF1-203 E Adder 0.66 MW 0.56 MW
939132 AE1-143 E 50/50 19.75 MW 19.75 MW
940832 AE2-071 E Adder 1.15 MW 0.98 MW
339206 AE1-143 C 50/50 39.84 MW 39.84 MW
962241 AG1-070 C Adder 1.94 MW 1.65 MW
962242 AG1-070 E Adder 0.73 MW 0.62 MW
962251 AG1-071 C Adder 2.22 MW 1.89 MW
962252 AG1-071 E Adder 1.04 MW 0.88 MW
944151 AF1-083 C 50/50 13.29 MW 13.29 MW
944152 AF1-083 E 50/50 8.86 MW 8.86 MW
966951 AE2-000D C Adder 4.14 MW 3.52 MW
966952 AE2-000D E Adder 2.01 MW 1.71 MW
962221 AG1-067 C Adder 1.84 MW 1.56 MW
962222 AG1-067 E Adder 0.98 MW 0.83 MW
964781 AG1-341 C Adder 5.24 MW 4.45 MW
964782 AG1-341 E Adder 3.49 MW 2.97 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.14 MW 1.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.48 MW 2.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.28 MW 3.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.23 MW 0.23 MW
TVA LTFEXP_TVA->PJM CLTF 1.12 MW 1.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.32 MW 0.32 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.3 MW 0.3 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.11 MW 0.11 MW

Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P2-3_CASEY S89-1008_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-3_CASEY S89-1008_SRT-A
CONTINGENCY 'EKPC_P2-3_CASEY S89-1008_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 111.52 220.0 B 245.35 22.32
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-3_CASEY S89-1008_SRT-A
CONTINGENCY 'EKPC_P2-3_CASEY S89-1008_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 111.69 220.0 B 245.72 22.31
Topology Case Flowgate Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P2-3_CASEY S89-1008_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 21.16 MW 21.16 MW
964892 AG1-353 E 50/50 14.11 MW 14.11 MW
964901 AG1-354 C 50/50 13.39 MW 13.39 MW
964902 AG1-354 E 50/50 8.93 MW 8.93 MW
943821 AF1-050 C 50/50 8.65 MW 8.65 MW
943822 AF1-050 E 50/50 5.76 MW 5.76 MW
944511 AF1-116 C 50/50 44.71 MW 44.71 MW
944512 AF1-116 E 50/50 29.8 MW 29.8 MW
945382 AF1-203 E Adder 0.66 MW 0.56 MW
939132 AE1-143 E 50/50 19.75 MW 19.75 MW
940832 AE2-071 E Adder 1.15 MW 0.98 MW
339206 AE1-143 C 50/50 39.84 MW 39.84 MW
962241 AG1-070 C Adder 1.94 MW 1.65 MW
962242 AG1-070 E Adder 0.73 MW 0.62 MW
962251 AG1-071 C Adder 2.22 MW 1.89 MW
962252 AG1-071 E Adder 1.04 MW 0.88 MW
944151 AF1-083 C 50/50 13.29 MW 13.29 MW
944152 AF1-083 E 50/50 8.86 MW 8.86 MW
966951 AE2-000D C Adder 4.14 MW 3.52 MW
966952 AE2-000D E Adder 2.01 MW 1.71 MW
962221 AG1-067 C Adder 1.84 MW 1.56 MW
962222 AG1-067 E Adder 0.98 MW 0.83 MW
964781 AG1-341 C Adder 5.24 MW 4.45 MW
964782 AG1-341 E Adder 3.49 MW 2.97 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.14 MW 1.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.48 MW 2.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.28 MW 3.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.23 MW 0.23 MW
TVA LTFEXP_TVA->PJM CLTF 1.12 MW 1.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.32 MW 0.32 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.3 MW 0.3 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.11 MW 0.11 MW

Details for AG1-354 TP-5SUMM SHADE 161.0 kV Ckt 1 line l/o EKPC_P2-3_MAR W38-1014_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC AG1-354 TP-5SUMM SHADE 161.0 kV Ckt 1 line
964900 to 342814 ckt 1
EKPC_P2-3_MAR W38-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_MAR W38-1014_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342770 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
END
Breaker AC 111.09 298.0 B 331.06 126.86
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC AG1-354 TP-5SUMM SHADE 161.0 kV Ckt 1 line
964900 to 342814 ckt 1
EKPC_P2-3_MAR W38-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_MAR W38-1014_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BRANCH FROM BUS 342770 TO BUS 342769 CKT 1   /*4MARION CO   138.0 - 5MARION CO   161.0
END
Breaker AC 111.01 298.0 B 330.81 126.86
Topology Case Flowgate Details for AG1-354 TP-5SUMM SHADE 161.0 kV Ckt 1 line l/o EKPC_P2-3_MAR W38-1014_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 37.33 MW 37.33 MW
964892 AG1-353 E 50/50 24.89 MW 24.89 MW
964901 AG1-354 C 50/50 76.12 MW 76.12 MW
964902 AG1-354 E 50/50 50.74 MW 50.74 MW
943821 AF1-050 C 50/50 26.26 MW 26.26 MW
943822 AF1-050 E 50/50 17.5 MW 17.5 MW
944511 AF1-116 C 50/50 44.65 MW 44.65 MW
944512 AF1-116 E 50/50 29.77 MW 29.77 MW
939132 AE1-143 E 50/50 19.72 MW 19.72 MW
339206 AE1-143 C 50/50 39.79 MW 39.79 MW
944151 AF1-083 C 50/50 20.46 MW 20.46 MW
944152 AF1-083 E 50/50 13.64 MW 13.64 MW
950011 AG9-010 External Queue 10.04 MW 10.04 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.98 MW 0.98 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.13 MW 0.13 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.09 MW 0.09 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.48 MW 0.48 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.02 MW 0.02 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.14 MW 0.14 MW
MDU PJM->LTFIMP_MDU CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.09 MW 0.09 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.15 MW 0.15 MW

Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P2-3_LIB J S4-1024_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-3_LIB J S4-1024_SRT-A
CONTINGENCY 'EKPC_P2-3_LIB J S4-1024_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BUS 342760                                   /*5LIBERTY J   161.0
END
Breaker AC 105.24 234.0 B 246.26 22.31
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-3_LIB J S4-1024_SRT-A
CONTINGENCY 'EKPC_P2-3_LIB J S4-1024_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
 OPEN BUS 342760                                   /*5LIBERTY J   161.0
END
Breaker AC 105.4 234.0 B 246.65 22.31
Topology Case Flowgate Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P2-3_LIB J S4-1024_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 21.16 MW 21.16 MW
964892 AG1-353 E 50/50 14.1 MW 14.1 MW
964901 AG1-354 C 50/50 13.39 MW 13.39 MW
964902 AG1-354 E 50/50 8.93 MW 8.93 MW
943821 AF1-050 C 50/50 8.64 MW 8.64 MW
943822 AF1-050 E 50/50 5.76 MW 5.76 MW
944511 AF1-116 C 50/50 44.7 MW 44.7 MW
944512 AF1-116 E 50/50 29.8 MW 29.8 MW
945382 AF1-203 E Adder 0.66 MW 0.56 MW
939132 AE1-143 E 50/50 19.75 MW 19.75 MW
940832 AE2-071 E Adder 1.15 MW 0.98 MW
339206 AE1-143 C 50/50 39.84 MW 39.84 MW
962241 AG1-070 C Adder 1.94 MW 1.65 MW
962242 AG1-070 E Adder 0.73 MW 0.62 MW
962251 AG1-071 C Adder 2.22 MW 1.89 MW
962252 AG1-071 E Adder 1.04 MW 0.88 MW
944151 AF1-083 C 50/50 13.29 MW 13.29 MW
944152 AF1-083 E 50/50 8.86 MW 8.86 MW
966951 AE2-000D C Adder 4.14 MW 3.52 MW
966952 AE2-000D E Adder 2.01 MW 1.71 MW
962221 AG1-067 C Adder 1.84 MW 1.56 MW
962222 AG1-067 E Adder 0.98 MW 0.83 MW
964781 AG1-341 C Adder 5.24 MW 4.45 MW
964782 AG1-341 E Adder 3.49 MW 2.97 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.14 MW 1.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.48 MW 2.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.28 MW 3.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.23 MW 0.23 MW
TVA LTFEXP_TVA->PJM CLTF 1.12 MW 1.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.32 MW 0.32 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.3 MW 0.3 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.11 MW 0.11 MW

Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P2-3_CASEY S89-1008_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-3_CASEY S89-1008_SRT-A
CONTINGENCY 'EKPC_P2-3_CASEY S89-1008_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 105.15 234.0 B 246.05 22.32
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-3_CASEY S89-1008_SRT-A
CONTINGENCY 'EKPC_P2-3_CASEY S89-1008_SRT-A'
 OPEN BRANCH FROM BUS 341269 TO BUS 342703 CKT 1   /*2CASEY CO     69.0 - 5CASEY CO    161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342760 CKT 1   /*5CASEY CO    161.0 - 5LIBERTY J   161.0
 OPEN BRANCH FROM BUS 342703 TO BUS 342769 CKT 1   /*5CASEY CO    161.0 - 5MARION CO   161.0
END
Breaker AC 105.31 234.0 B 246.42 22.31
Topology Case Flowgate Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P2-3_CASEY S89-1008_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 21.16 MW 21.16 MW
964892 AG1-353 E 50/50 14.11 MW 14.11 MW
964901 AG1-354 C 50/50 13.39 MW 13.39 MW
964902 AG1-354 E 50/50 8.93 MW 8.93 MW
943821 AF1-050 C 50/50 8.65 MW 8.65 MW
943822 AF1-050 E 50/50 5.76 MW 5.76 MW
944511 AF1-116 C 50/50 44.71 MW 44.71 MW
944512 AF1-116 E 50/50 29.8 MW 29.8 MW
945382 AF1-203 E Adder 0.66 MW 0.56 MW
939132 AE1-143 E 50/50 19.75 MW 19.75 MW
940832 AE2-071 E Adder 1.15 MW 0.98 MW
339206 AE1-143 C 50/50 39.84 MW 39.84 MW
962241 AG1-070 C Adder 1.94 MW 1.65 MW
962242 AG1-070 E Adder 0.73 MW 0.62 MW
962251 AG1-071 C Adder 2.22 MW 1.89 MW
962252 AG1-071 E Adder 1.04 MW 0.88 MW
944151 AF1-083 C 50/50 13.29 MW 13.29 MW
944152 AF1-083 E 50/50 8.86 MW 8.86 MW
966951 AE2-000D C Adder 4.14 MW 3.52 MW
966952 AE2-000D E Adder 2.01 MW 1.71 MW
962221 AG1-067 C Adder 1.84 MW 1.56 MW
962222 AG1-067 E Adder 0.98 MW 0.83 MW
964781 AG1-341 C Adder 5.24 MW 4.45 MW
964782 AG1-341 E Adder 3.49 MW 2.97 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.14 MW 1.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.48 MW 2.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.28 MW 3.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.23 MW 0.23 MW
TVA LTFEXP_TVA->PJM CLTF 1.12 MW 1.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.32 MW 0.32 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.3 MW 0.3 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.11 MW 0.11 MW

Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P2-2_CASEY CO 161_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-2_CASEY CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_CASEY CO 161_SRT-A'
 OPEN BUS 342703   /*5CASEY CO    161.0
END
Bus AC 111.52 220.0 B 245.35 22.32
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P2-2_CASEY CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_CASEY CO 161_SRT-A'
 OPEN BUS 342703   /*5CASEY CO    161.0
END
Bus AC 111.7 220.0 B 245.73 22.31
Topology Case Flowgate Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P2-2_CASEY CO 161_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 21.16 MW 21.16 MW
964892 AG1-353 E 50/50 14.11 MW 14.11 MW
964901 AG1-354 C 50/50 13.39 MW 13.39 MW
964902 AG1-354 E 50/50 8.93 MW 8.93 MW
943821 AF1-050 C 50/50 8.65 MW 8.65 MW
943822 AF1-050 E 50/50 5.76 MW 5.76 MW
944511 AF1-116 C 50/50 44.71 MW 44.71 MW
944512 AF1-116 E 50/50 29.8 MW 29.8 MW
945382 AF1-203 E Adder 0.66 MW 0.56 MW
939132 AE1-143 E 50/50 19.75 MW 19.75 MW
940832 AE2-071 E Adder 1.15 MW 0.98 MW
339206 AE1-143 C 50/50 39.84 MW 39.84 MW
962241 AG1-070 C Adder 1.94 MW 1.65 MW
962242 AG1-070 E Adder 0.73 MW 0.62 MW
962251 AG1-071 C Adder 2.22 MW 1.89 MW
962252 AG1-071 E Adder 1.04 MW 0.88 MW
944151 AF1-083 C 50/50 13.29 MW 13.29 MW
944152 AF1-083 E 50/50 8.86 MW 8.86 MW
966951 AE2-000D C Adder 4.14 MW 3.52 MW
966952 AE2-000D E Adder 2.01 MW 1.71 MW
962221 AG1-067 C Adder 1.84 MW 1.56 MW
962222 AG1-067 E Adder 0.98 MW 0.83 MW
964781 AG1-341 C Adder 5.24 MW 4.45 MW
964782 AG1-341 E Adder 3.49 MW 2.97 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.14 MW 1.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.48 MW 2.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.28 MW 3.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.23 MW 0.23 MW
TVA LTFEXP_TVA->PJM CLTF 1.12 MW 1.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.32 MW 0.32 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.3 MW 0.3 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.11 MW 0.11 MW

Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P2-2_CASEY CO 161_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-2_CASEY CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_CASEY CO 161_SRT-A'
 OPEN BUS 342703   /*5CASEY CO    161.0
END
Bus AC 105.15 234.0 B 246.05 22.32
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P2-2_CASEY CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_CASEY CO 161_SRT-A'
 OPEN BUS 342703   /*5CASEY CO    161.0
END
Bus AC 105.31 234.0 B 246.43 22.31
Topology Case Flowgate Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P2-2_CASEY CO 161_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 21.16 MW 21.16 MW
964892 AG1-353 E 50/50 14.11 MW 14.11 MW
964901 AG1-354 C 50/50 13.39 MW 13.39 MW
964902 AG1-354 E 50/50 8.93 MW 8.93 MW
943821 AF1-050 C 50/50 8.65 MW 8.65 MW
943822 AF1-050 E 50/50 5.76 MW 5.76 MW
944511 AF1-116 C 50/50 44.71 MW 44.71 MW
944512 AF1-116 E 50/50 29.8 MW 29.8 MW
945382 AF1-203 E Adder 0.66 MW 0.56 MW
939132 AE1-143 E 50/50 19.75 MW 19.75 MW
940832 AE2-071 E Adder 1.15 MW 0.98 MW
339206 AE1-143 C 50/50 39.84 MW 39.84 MW
962241 AG1-070 C Adder 1.94 MW 1.65 MW
962242 AG1-070 E Adder 0.73 MW 0.62 MW
962251 AG1-071 C Adder 2.22 MW 1.89 MW
962252 AG1-071 E Adder 1.04 MW 0.88 MW
944151 AF1-083 C 50/50 13.29 MW 13.29 MW
944152 AF1-083 E 50/50 8.86 MW 8.86 MW
966951 AE2-000D C Adder 4.14 MW 3.52 MW
966952 AE2-000D E Adder 2.01 MW 1.71 MW
962221 AG1-067 C Adder 1.84 MW 1.56 MW
962222 AG1-067 E Adder 0.98 MW 0.83 MW
964781 AG1-341 C Adder 5.24 MW 4.45 MW
964782 AG1-341 E Adder 3.49 MW 2.97 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.14 MW 1.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.48 MW 2.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.28 MW 3.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.23 MW 0.23 MW
TVA LTFEXP_TVA->PJM CLTF 1.12 MW 1.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.32 MW 0.32 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.3 MW 0.3 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.11 MW 0.11 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P1-2_LAUR-L DAM161_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P1-2_LAUR-L DAM161_SRT-A
CONTINGENCY 'EKPC_P1-2_LAUR-L DAM161_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
END
Single AC 111.55 277.0 B 309.01 10.71
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P1-2_LAUR-L DAM161_SRT-A
CONTINGENCY 'EKPC_P1-2_LAUR-L DAM161_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
END
Single AC 111.48 277.0 B 308.8 10.71
Topology Case Flowgate Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P1-2_LAUR-L DAM161_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 80/20 7.76 MW 7.76 MW
964901 AG1-354 C 80/20 10.71 MW 10.71 MW
965401 AG1-405 C 80/20 4.0 MW 4.0 MW
943701 AF1-038 C 80/20 6.65 MW 6.65 MW
943821 AF1-050 C 80/20 4.46 MW 4.46 MW
944511 AF1-116 C 80/20 11.06 MW 11.06 MW
945381 AF1-203 C 80/20 0.21 MW 0.21 MW
342442 2W GLASGOW 80/20 0.02 MW 0.02 MW
342900 1COOPER1 G 80/20 9.79 MW 9.79 MW
342903 1COOPER2 G 80/20 19.05 MW 19.05 MW
342945 1LAUREL 1G 80/20 5.92 MW 5.92 MW
940831 AE2-071 C 80/20 0.38 MW 0.38 MW
339206 AE1-143 C 80/20 9.85 MW 9.85 MW
962241 AG1-070 C 80/20 3.35 MW 3.35 MW
962251 AG1-071 C 80/20 3.84 MW 3.84 MW
944151 AF1-083 C 80/20 4.48 MW 4.48 MW
960741 AF2-365 C 80/20 2.57 MW 2.57 MW
966951 AE2-000D C 80/20 6.34 MW 6.34 MW
962221 AG1-067 C 80/20 2.79 MW 2.79 MW
964781 AG1-341 C 80/20 7.35 MW 7.35 MW
965411 AG1-406 C 80/20 2.58 MW 2.58 MW
966021 AG1-471 C 80/20 7.3 MW 7.3 MW
950000 AG9-001 External Queue 7.42 MW 7.42 MW
950011 AG9-010 External Queue 13.47 MW 13.47 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.5 MW 3.5 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.12 MW 5.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.5 MW 2.5 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.11 MW 0.11 MW
TVA LTFEXP_TVA->PJM CLTF 1.93 MW 1.93 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.79 MW 1.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
Base Case Single AC 100.84 1240.0 A 1250.44 7.5
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
Base Case Single AC 101.2 1240.0 A 1254.87 7.6
Topology Case Flowgate Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 5.93 MW 5.04 MW
964901 AG1-354 C Adder 7.5 MW 6.37 MW
965401 AG1-405 C 80/20 4.88 MW 4.88 MW
966571 AG1-526 C 80/20 23.52 MW 23.52 MW
936381 AD2-048 C 80/20 12.05 MW 12.05 MW
942091 AE2-221 C Adder -28.84 MW -24.51 MW
943111 AE2-339 C 80/20 7.06 MW 7.06 MW
943701 AF1-038 C Adder 3.68 MW 3.13 MW
943821 AF1-050 C Adder 3.29 MW 2.8 MW
944511 AF1-116 C Adder 8.18 MW 6.96 MW
945681 AF1-233 C 80/20 44.44 MW 44.44 MW
959691 AF2-260 C Adder 4.67 MW 3.97 MW
960161 AF2-307 C 80/20 10.13 MW 10.13 MW
960181 AF2-309 C Adder 3.7 MW 3.15 MW
960571 AF2-348 C 80/20 64.19 MW 64.19 MW
251970 08MELDL1 80/20 1.52 MW 1.52 MW
251971 08MELDL2 80/20 1.52 MW 1.52 MW
251972 08MELDL3 80/20 1.52 MW 1.52 MW
341584 2GRIFFIN 80/20 0.1 MW 0.1 MW
342070 2PINE GROVE 80/20 0.07 MW 0.07 MW
342550 4BAVARIAN LF 80/20 0.12 MW 0.12 MW
342903 1COOPER2 G 80/20 4.04 MW 4.04 MW
342918 1JKCT 1G 80/20 4.12 MW 4.12 MW
342921 1JKCT 2G 80/20 3.99 MW 3.99 MW
342924 1JKCT 3G 80/20 4.05 MW 4.05 MW
342927 1JKCT 4G 80/20 2.71 MW 2.71 MW
342930 1JKCT 5G 80/20 2.64 MW 2.64 MW
342933 1JKCT 6G 80/20 2.64 MW 2.64 MW
342936 1JKCT 7G 80/20 2.64 MW 2.64 MW
342939 1JKCT 9G 80/20 3.02 MW 3.02 MW
342942 1JKCT 10G 80/20 3.02 MW 3.02 MW
342945 1LAUREL 1G 80/20 1.38 MW 1.38 MW
342957 1SPURLK1G 80/20 20.64 MW 20.64 MW
342960 1SPURLK2G 80/20 39.16 MW 39.16 MW
342963 1SPURLK3G 80/20 20.57 MW 20.57 MW
342966 1SPURLK4G 80/20 20.57 MW 20.57 MW
941411 AE2-138 C 80/20 6.47 MW 6.47 MW
957961 AF2-090 C Adder 6.39 MW 5.43 MW
339200 AD2-072_C 80/20 9.65 MW 9.65 MW
339206 AE1-143 C Adder 7.29 MW 6.2 MW
339216 AC1-074 C 80/20 2.42 MW 2.42 MW
962211 AG1-066 C Adder 4.01 MW 3.41 MW
251298 08CRITDN 80/20 0.05 MW 0.05 MW
339218 AC2-075 C 80/20 0.54 MW 0.54 MW
339211 AE2-254 GEN 80/20 0.73 MW 0.73 MW
942591 AE2-275 C 80/20 1.66 MW 1.66 MW
942891 AE2-308 C 80/20 13.77 MW 13.77 MW
944151 AF1-083 C Adder 3.42 MW 2.91 MW
960151 AF2-306 C 80/20 6.65 MW 6.65 MW
960171 AF2-308 C Adder 2.47 MW 2.1 MW
960641 AF2-355 C 80/20 31.0 MW 31.0 MW
960741 AF2-365 C Adder 2.48 MW 2.1 MW
961001 AF2-391 C Adder 6.35 MW 5.4 MW
251968 08ZIMRHP 80/20 152.26 MW 152.26 MW
964571 AG1-320 C Adder 4.98 MW 4.23 MW
941981 AE2-210 C 80/20 2.24 MW 2.24 MW
958171 AF2-111 C 80/20 68.15 MW 68.15 MW
965411 AG1-406 C 80/20 3.14 MW 3.14 MW
966021 AG1-471 C Adder 3.13 MW 2.66 MW
950041 AG9-017 External Queue 19.18 MW 19.18 MW
950051 AG9-018 External Queue 18.98 MW 18.98 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 22.23 MW 22.23 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 21.87 MW 21.87 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 14.4 MW 14.4 MW
NY PJM->LTFIMP_NY CLTF 0.63 MW 0.63 MW
LGEE LTFEXP_LGEE->PJM CLTF 4.83 MW 4.83 MW
WEC LTFEXP_WEC->PJM CLTF 0.55 MW 0.55 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.77 MW 0.77 MW
TVA LTFEXP_TVA->PJM CLTF 5.38 MW 5.38 MW
MEC LTFEXP_MEC->PJM CLTF 3.67 MW 3.67 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.8 MW 5.8 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.53 MW 0.53 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.37 MW 0.37 MW

Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A
CONTINGENCY 'DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A'
 OPEN BRANCH FROM BUS 249577 TO BUS 249581 CKT 1   /*08ZIMER      345.0 - 08MELDAL     345.0
END
Single AC 100.2 1532.0 B 1535.08 8.59
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A
CONTINGENCY 'DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A'
 OPEN BRANCH FROM BUS 249577 TO BUS 249581 CKT 1   /*08ZIMER      345.0 - 08MELDAL     345.0
END
Single AC 100.5 1532.0 B 1539.68 8.65
Topology Case Flowgate Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o DEOK_P1_ZIMMER-MELDAHL 34576_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 80/20 6.94 MW 6.94 MW
964901 AG1-354 C 80/20 8.59 MW 8.59 MW
965401 AG1-405 C 80/20 6.01 MW 6.01 MW
966571 AG1-526 C 80/20 29.07 MW 29.07 MW
936381 AD2-048 C 80/20 15.14 MW 15.14 MW
942091 AE2-221 C Adder -22.82 MW -19.4 MW
943111 AE2-339 C 80/20 8.95 MW 8.95 MW
943701 AF1-038 C 80/20 4.38 MW 4.38 MW
943821 AF1-050 C 80/20 3.81 MW 3.81 MW
944511 AF1-116 C 80/20 9.7 MW 9.7 MW
945381 AF1-203 C 80/20 0.16 MW 0.16 MW
945681 AF1-233 C 80/20 57.87 MW 57.87 MW
959691 AF2-260 C 80/20 5.17 MW 5.17 MW
960161 AF2-307 C 80/20 13.02 MW 13.02 MW
960181 AF2-309 C 80/20 4.09 MW 4.09 MW
960571 AF2-348 C 80/20 83.77 MW 83.77 MW
251970 08MELDL1 80/20 3.56 MW 3.56 MW
251971 08MELDL2 80/20 3.56 MW 3.56 MW
251972 08MELDL3 80/20 3.56 MW 3.56 MW
341200 2BROMLEYEK 80/20 0.04 MW 0.04 MW
341329 2COLESBURG 80/20 0.04 MW 0.04 MW
341584 2GRIFFIN 80/20 0.12 MW 0.12 MW
342070 2PINE GROVE 80/20 0.08 MW 0.08 MW
342442 2W GLASGOW 80/20 0.01 MW 0.01 MW
342550 4BAVARIAN LF 80/20 0.12 MW 0.12 MW
342900 1COOPER1 G 80/20 2.52 MW 2.52 MW
342903 1COOPER2 G 80/20 4.9 MW 4.9 MW
342918 1JKCT 1G 80/20 5.23 MW 5.23 MW
342921 1JKCT 2G 80/20 5.08 MW 5.08 MW
342924 1JKCT 3G 80/20 5.14 MW 5.14 MW
342927 1JKCT 4G 80/20 3.44 MW 3.44 MW
342930 1JKCT 5G 80/20 3.36 MW 3.36 MW
342933 1JKCT 6G 80/20 3.36 MW 3.36 MW
342936 1JKCT 7G 80/20 3.36 MW 3.36 MW
342939 1JKCT 9G 80/20 3.85 MW 3.85 MW
342942 1JKCT 10G 80/20 3.85 MW 3.85 MW
342945 1LAUREL 1G 80/20 1.69 MW 1.69 MW
342957 1SPURLK1G 80/20 26.96 MW 26.96 MW
342960 1SPURLK2G 80/20 51.41 MW 51.41 MW
342963 1SPURLK3G 80/20 27.01 MW 27.01 MW
342966 1SPURLK4G 80/20 27.01 MW 27.01 MW
940831 AE2-071 C 80/20 0.29 MW 0.29 MW
941411 AE2-138 C 80/20 8.32 MW 8.32 MW
957961 AF2-090 C 80/20 6.98 MW 6.98 MW
342031 2PACTOLUS 80/20 0.04 MW 0.04 MW
339200 AD2-072_C 80/20 11.61 MW 11.61 MW
339206 AE1-143 C 80/20 8.64 MW 8.64 MW
339216 AC1-074 C 80/20 3.04 MW 3.04 MW
962211 AG1-066 C 80/20 5.13 MW 5.13 MW
962241 AG1-070 C 80/20 2.85 MW 2.85 MW
962251 AG1-071 C 80/20 3.27 MW 3.27 MW
251298 08CRITDN 80/20 0.06 MW 0.06 MW
251542 08VERONA 80/20 0.04 MW 0.04 MW
270186 AC1-089 C 80/20 0.91 MW 0.91 MW
339218 AC2-075 C 80/20 0.68 MW 0.68 MW
339211 AE2-254 GEN 80/20 0.9 MW 0.9 MW
942591 AE2-275 C 80/20 2.1 MW 2.1 MW
942891 AE2-308 C 80/20 17.4 MW 17.4 MW
944151 AF1-083 C 80/20 4.02 MW 4.02 MW
960151 AF2-306 C 80/20 8.55 MW 8.55 MW
960171 AF2-308 C 80/20 2.73 MW 2.73 MW
960641 AF2-355 C 80/20 39.16 MW 39.16 MW
960741 AF2-365 C 80/20 2.8 MW 2.8 MW
961001 AF2-391 C 80/20 6.98 MW 6.98 MW
966951 AE2-000D C 80/20 5.04 MW 5.04 MW
962221 AG1-067 C 80/20 2.21 MW 2.21 MW
964571 AG1-320 C 80/20 5.56 MW 5.56 MW
941981 AE2-210 C 80/20 2.88 MW 2.88 MW
958171 AF2-111 C 80/20 89.14 MW 89.14 MW
964781 AG1-341 C 80/20 5.58 MW 5.58 MW
965411 AG1-406 C 80/20 3.87 MW 3.87 MW
966021 AG1-471 C 80/20 3.7 MW 3.7 MW
950041 AG9-017 External Queue 26.7 MW 26.7 MW
950051 AG9-018 External Queue 26.64 MW 26.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.81 MW 10.81 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 20.13 MW 20.13 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 18.4 MW 18.4 MW
NY PJM->LTFIMP_NY CLTF 0.56 MW 0.56 MW
LGEE LTFEXP_LGEE->PJM CLTF 4.94 MW 4.94 MW
WEC LTFEXP_WEC->PJM CLTF 0.3 MW 0.3 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.09 MW 1.09 MW
TVA LTFEXP_TVA->PJM CLTF 5.84 MW 5.84 MW
MEC LTFEXP_MEC->PJM CLTF 2.77 MW 2.77 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.0 MW 6.0 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.48 MW 0.48 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.52 MW 0.52 MW

Details for 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 155.93 105.0 B 163.73 12.11
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 155.73 105.0 B 163.52 12.11
Topology Case Flowgate Details for 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 5.1 MW 4.33 MW
964892 AG1-353 E Adder 3.4 MW 2.89 MW
964901 AG1-354 C Adder 7.26 MW 6.17 MW
964902 AG1-354 E Adder 4.84 MW 4.12 MW
965401 AG1-405 C 50/50 10.9 MW 10.9 MW
965402 AG1-405 E 50/50 7.27 MW 7.27 MW
943701 AF1-038 C 50/50 8.41 MW 8.41 MW
943702 AF1-038 E 50/50 5.6 MW 5.6 MW
943821 AF1-050 C Adder 2.98 MW 2.53 MW
943822 AF1-050 E Adder 1.99 MW 1.69 MW
944511 AF1-116 C Adder 7.07 MW 6.01 MW
944512 AF1-116 E Adder 4.72 MW 4.01 MW
945382 AF1-203 E Adder 0.72 MW 0.61 MW
342900 1COOPER1 G 50/50 4.75 MW 4.75 MW
342903 1COOPER2 G 50/50 9.21 MW 9.21 MW
939132 AE1-143 E Adder 3.12 MW 2.66 MW
940832 AE2-071 E Adder 1.26 MW 1.07 MW
339206 AE1-143 C Adder 6.3 MW 5.36 MW
962241 AG1-070 C Adder 2.36 MW 2.0 MW
962242 AG1-070 E Adder 0.89 MW 0.75 MW
962251 AG1-071 C Adder 2.7 MW 2.3 MW
962252 AG1-071 E Adder 1.26 MW 1.07 MW
944151 AF1-083 C Adder 2.92 MW 2.48 MW
944152 AF1-083 E Adder 1.95 MW 1.66 MW
960741 AF2-365 C Adder 1.77 MW 1.5 MW
960742 AF2-365 E Adder 1.18 MW 1.0 MW
966951 AE2-000D C Adder 4.36 MW 3.71 MW
966952 AE2-000D E Adder 2.12 MW 1.8 MW
962221 AG1-067 C Adder 2.03 MW 1.73 MW
962222 AG1-067 E Adder 1.08 MW 0.92 MW
964781 AG1-341 C Adder 5.04 MW 4.28 MW
964782 AG1-341 E Adder 3.36 MW 2.85 MW
965411 AG1-406 C 50/50 7.01 MW 7.01 MW
966021 AG1-471 C 50/50 5.15 MW 5.15 MW
966022 AG1-471 E 50/50 3.44 MW 3.44 MW
950011 AG9-010 External Queue 8.6 MW 8.6 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.02 MW 3.02 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.55 MW 3.55 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.6 MW 1.6 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.08 MW 0.08 MW
NY PJM->LTFIMP_NY CLTF 0.04 MW 0.04 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.07 MW 0.07 MW
TVA LTFEXP_TVA->PJM CLTF 1.27 MW 1.27 MW
MEC LTFEXP_MEC->PJM CLTF 0.55 MW 0.55 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.2 MW 1.2 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.53 MW 0.53 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.04 MW 0.04 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P7-1_LAURL 161 DBL_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 133.61 277.0 B 370.11 17.8
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 133.57 277.0 B 370.0 17.8
Topology Case Flowgate Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P7-1_LAURL 161 DBL_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 7.75 MW 7.75 MW
964892 AG1-353 E 50/50 5.16 MW 5.16 MW
964901 AG1-354 C 50/50 10.68 MW 10.68 MW
964902 AG1-354 E 50/50 7.12 MW 7.12 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.62 MW 6.62 MW
943702 AF1-038 E 50/50 4.42 MW 4.42 MW
943821 AF1-050 C 50/50 4.45 MW 4.45 MW
943822 AF1-050 E 50/50 2.96 MW 2.96 MW
944511 AF1-116 C 50/50 11.03 MW 11.03 MW
944512 AF1-116 E 50/50 7.35 MW 7.35 MW
945381 AF1-203 C 50/50 0.21 MW 0.21 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 9.77 MW 9.77 MW
342903 1COOPER2 G 50/50 19.02 MW 19.02 MW
342945 1LAUREL 1G 50/50 5.91 MW 5.91 MW
939132 AE1-143 E 50/50 4.87 MW 4.87 MW
940831 AE2-071 C 50/50 0.38 MW 0.38 MW
940832 AE2-071 E 50/50 1.68 MW 1.68 MW
339206 AE1-143 C 50/50 9.83 MW 9.83 MW
962241 AG1-070 C 50/50 3.34 MW 3.34 MW
962242 AG1-070 E 50/50 1.26 MW 1.26 MW
962251 AG1-071 C 50/50 3.83 MW 3.83 MW
962252 AG1-071 E 50/50 1.79 MW 1.79 MW
944151 AF1-083 C 50/50 4.46 MW 4.46 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.56 MW 2.17 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
966951 AE2-000D C 50/50 6.32 MW 6.32 MW
966952 AE2-000D E 50/50 3.07 MW 3.07 MW
962221 AG1-067 C 50/50 2.78 MW 2.78 MW
962222 AG1-067 E 50/50 1.48 MW 1.48 MW
964781 AG1-341 C 50/50 7.33 MW 7.33 MW
964782 AG1-341 E 50/50 4.88 MW 4.88 MW
965411 AG1-406 C 50/50 2.57 MW 2.57 MW
966021 AG1-471 C 50/50 7.28 MW 7.28 MW
966022 AG1-471 E 50/50 4.85 MW 4.85 MW
950000 AG9-001 External Queue 7.4 MW 7.4 MW
950011 AG9-010 External Queue 13.44 MW 13.44 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.48 MW 3.48 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.06 MW 5.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.41 MW 2.41 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.1 MW 0.1 MW
TVA LTFEXP_TVA->PJM CLTF 1.91 MW 1.91 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.77 MW 1.77 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.06 MW 1.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for 5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line l/o EKPC_P7-1_BULL 161 DBL_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/TVA 5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line
342814 to 360334 ckt 1
EKPC_P7-1_BULL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_BULL 161 DBL_SRT-A'
 OPEN BUS 326975   /*5CEDAR GRV   161.0
 OPEN BUS 361788   /*5SUM SHAD TP 161.0
END
Tower AC 123.14 289.0 B 355.89 99.43
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/TVA 5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line
342814 to 360334 ckt 1
EKPC_P7-1_BULL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_BULL 161 DBL_SRT-A'
 OPEN BUS 326975   /*5CEDAR GRV   161.0
 OPEN BUS 361788   /*5SUM SHAD TP 161.0
END
Tower AC 122.97 289.0 B 355.39 99.43
Topology Case Flowgate Details for 5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line l/o EKPC_P7-1_BULL 161 DBL_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 22.52 MW 22.52 MW
964892 AG1-353 E 50/50 15.02 MW 15.02 MW
964901 AG1-354 C 50/50 59.66 MW 59.66 MW
964902 AG1-354 E 50/50 39.77 MW 39.77 MW
943701 AF1-038 C Adder 2.79 MW 2.38 MW
943702 AF1-038 E Adder 1.86 MW 1.58 MW
943821 AF1-050 C 50/50 18.92 MW 18.92 MW
943822 AF1-050 E 50/50 12.61 MW 12.61 MW
944511 AF1-116 C 50/50 15.5 MW 15.5 MW
944512 AF1-116 E 50/50 10.34 MW 10.34 MW
945381 AF1-203 C 50/50 0.77 MW 0.77 MW
945382 AF1-203 E 50/50 3.51 MW 3.51 MW
959691 AF2-260 C Adder 3.48 MW 2.96 MW
959692 AF2-260 E Adder 2.1 MW 1.78 MW
342442 2W GLASGOW 50/50 0.03 MW 0.03 MW
939132 AE1-143 E 50/50 6.85 MW 6.85 MW
940831 AE2-071 C 50/50 1.37 MW 1.37 MW
940832 AE2-071 E 50/50 6.15 MW 6.15 MW
339206 AE1-143 C 50/50 13.81 MW 13.81 MW
962241 AG1-070 C 50/50 7.43 MW 7.43 MW
962242 AG1-070 E 50/50 2.79 MW 2.79 MW
962251 AG1-071 C 50/50 8.52 MW 8.52 MW
962252 AG1-071 E 50/50 3.98 MW 3.98 MW
944151 AF1-083 C 50/50 11.37 MW 11.37 MW
944152 AF1-083 E 50/50 7.58 MW 7.58 MW
960741 AF2-365 C 50/50 7.97 MW 7.97 MW
960742 AF2-365 E 50/50 5.31 MW 5.31 MW
966951 AE2-000D C 50/50 36.16 MW 36.16 MW
966952 AE2-000D E 50/50 17.57 MW 17.57 MW
962221 AG1-067 C 50/50 7.35 MW 7.35 MW
962222 AG1-067 E 50/50 3.91 MW 3.91 MW
964571 AG1-320 C Adder 4.7 MW 3.99 MW
964572 AG1-320 E Adder 2.33 MW 1.98 MW
964781 AG1-341 C 50/50 48.51 MW 48.51 MW
964782 AG1-341 E 50/50 32.34 MW 32.34 MW
950000 AG9-001 External Queue 12.33 MW 12.33 MW
950011 AG9-010 External Queue 19.92 MW 19.92 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.05 MW 0.05 MW
NY PJM->LTFIMP_NY CLTF 0.02 MW 0.02 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.51 MW 0.51 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 2.53 MW 2.53 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.31 MW 0.31 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.21 MW 0.21 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 1.44 MW 1.44 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.34 MW 0.34 MW
MDU PJM->LTFIMP_MDU CLTF 0.04 MW 0.04 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.32 MW 0.32 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.35 MW 0.35 MW

Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 111.75 220.0 B 245.86 19.17
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 112.1 220.0 B 246.62 19.17
Topology Case Flowgate Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 16.08 MW 16.08 MW
964892 AG1-353 E 50/50 10.72 MW 10.72 MW
964901 AG1-354 C 50/50 11.5 MW 11.5 MW
964902 AG1-354 E 50/50 7.67 MW 7.67 MW
965401 AG1-405 C Adder 2.61 MW 2.22 MW
965402 AG1-405 E Adder 1.74 MW 1.48 MW
943701 AF1-038 C 50/50 4.19 MW 4.19 MW
943702 AF1-038 E 50/50 2.79 MW 2.79 MW
943821 AF1-050 C 50/50 6.82 MW 6.82 MW
943822 AF1-050 E 50/50 4.55 MW 4.55 MW
944511 AF1-116 C 50/50 34.26 MW 34.26 MW
944512 AF1-116 E 50/50 22.84 MW 22.84 MW
945382 AF1-203 E Adder 0.68 MW 0.58 MW
342900 1COOPER1 G 50/50 2.6 MW 2.6 MW
342903 1COOPER2 G 50/50 5.05 MW 5.05 MW
939132 AE1-143 E 50/50 15.13 MW 15.13 MW
940832 AE2-071 E Adder 1.19 MW 1.01 MW
339206 AE1-143 C 50/50 30.53 MW 30.53 MW
962241 AG1-070 C Adder 1.83 MW 1.56 MW
962242 AG1-070 E Adder 0.69 MW 0.59 MW
962251 AG1-071 C Adder 2.1 MW 1.79 MW
962252 AG1-071 E Adder 0.98 MW 0.83 MW
944151 AF1-083 C 50/50 10.05 MW 10.05 MW
944152 AF1-083 E 50/50 6.7 MW 6.7 MW
966951 AE2-000D C Adder 4.05 MW 3.44 MW
966952 AE2-000D E Adder 1.97 MW 1.67 MW
962221 AG1-067 C Adder 1.86 MW 1.58 MW
962222 AG1-067 E Adder 0.99 MW 0.84 MW
964781 AG1-341 C Adder 5.28 MW 4.48 MW
964782 AG1-341 E Adder 3.52 MW 2.99 MW
965411 AG1-406 C Adder 1.68 MW 1.43 MW
966021 AG1-471 C Adder 3.1 MW 2.64 MW
966022 AG1-471 E Adder 2.07 MW 1.76 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.41 MW 2.41 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 4.48 MW 4.48 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.11 MW 0.11 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.31 MW 0.31 MW
TVA LTFEXP_TVA->PJM CLTF 1.36 MW 1.36 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.26 MW 0.26 MW
MEC LTFEXP_MEC->PJM CLTF 0.23 MW 0.23 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.79 MW 0.79 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.23 MW 1.23 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.15 MW 0.15 MW

Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 105.36 234.0 B 246.54 19.17
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 105.69 234.0 B 247.31 19.17
Topology Case Flowgate Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 16.08 MW 16.08 MW
964892 AG1-353 E 50/50 10.72 MW 10.72 MW
964901 AG1-354 C 50/50 11.5 MW 11.5 MW
964902 AG1-354 E 50/50 7.67 MW 7.67 MW
965401 AG1-405 C Adder 2.61 MW 2.22 MW
965402 AG1-405 E Adder 1.74 MW 1.48 MW
943701 AF1-038 C 50/50 4.19 MW 4.19 MW
943702 AF1-038 E 50/50 2.79 MW 2.79 MW
943821 AF1-050 C 50/50 6.82 MW 6.82 MW
943822 AF1-050 E 50/50 4.55 MW 4.55 MW
944511 AF1-116 C 50/50 34.26 MW 34.26 MW
944512 AF1-116 E 50/50 22.84 MW 22.84 MW
945382 AF1-203 E Adder 0.68 MW 0.58 MW
342900 1COOPER1 G 50/50 2.6 MW 2.6 MW
342903 1COOPER2 G 50/50 5.05 MW 5.05 MW
939132 AE1-143 E 50/50 15.13 MW 15.13 MW
940832 AE2-071 E Adder 1.19 MW 1.01 MW
339206 AE1-143 C 50/50 30.53 MW 30.53 MW
962241 AG1-070 C Adder 1.83 MW 1.56 MW
962242 AG1-070 E Adder 0.69 MW 0.59 MW
962251 AG1-071 C Adder 2.1 MW 1.79 MW
962252 AG1-071 E Adder 0.98 MW 0.83 MW
944151 AF1-083 C 50/50 10.05 MW 10.05 MW
944152 AF1-083 E 50/50 6.7 MW 6.7 MW
966951 AE2-000D C Adder 4.05 MW 3.44 MW
966952 AE2-000D E Adder 1.97 MW 1.67 MW
962221 AG1-067 C Adder 1.86 MW 1.58 MW
962222 AG1-067 E Adder 0.99 MW 0.84 MW
964781 AG1-341 C Adder 5.28 MW 4.48 MW
964782 AG1-341 E Adder 3.52 MW 2.99 MW
965411 AG1-406 C Adder 1.68 MW 1.43 MW
966021 AG1-471 C Adder 3.1 MW 2.64 MW
966022 AG1-471 E Adder 2.07 MW 1.76 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.41 MW 2.41 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 4.48 MW 4.48 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.11 MW 0.11 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.31 MW 0.31 MW
TVA LTFEXP_TVA->PJM CLTF 1.36 MW 1.36 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.26 MW 0.26 MW
MEC LTFEXP_MEC->PJM CLTF 0.23 MW 0.23 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.79 MW 0.79 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.23 MW 1.23 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.15 MW 0.15 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Summer Potential Congestion due to Local Energy Deliverability
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
Base Case OP AC 123.4 1240.0 A 1530.17 12.49
EKPC 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer
342733 to 341563 ckt 1
EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C
CONTINGENCY 'EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C'
 OPEN BRANCH FROM BUS 944150 TO BUS 342817 CKT 1   /*AF1-083 TP   161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 964890 TO BUS 342817 CKT 1   /*AG1-353 TP   161.0 - 5TAYLOR CO J 161.0
END
OP AC 122.0 109.0 B 132.98 19.27
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Base Case OP AC 116.63 219.0 A 255.41 15.2
EKPC 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line
342757 to 342754 ckt 1
P2-3-228_SRT-S
CONTINGENCY 'P2-3-228_SRT-S'
 OPEN BRANCH FROM BUS 324100 TO BUS 324102 CKT 1   /*7ALCALDE     345.0 - 7BROWN NORTH 345.0
 OPEN BRANCH FROM BUS 324100 TO BUS 324112 CKT 1   /*7ALCALDE     345.0 - 7PINEVILLE   345.0
 OPEN BRANCH FROM BUS 324100 TO BUS 324130 CKT 1   /*7ALCALDE     345.0 - 5ALCALDE     161.0
 OPEN BRANCH FROM BUS 324130 TO BUS 324141 CKT 1   /*5ALCALDE     161.0 - 5ELIHU       161.0
 OPEN BRANCH FROM BUS 324130 TO BUS 324143 CKT 1   /*5ALCALDE     161.0 - 5FARLEY      161.0
END
OP AC 106.37 211.0 B 224.45 9.11
EKPC 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line
342769 to 342703 ckt 1
P2-3-102_SRT-S
CONTINGENCY 'P2-3-102_SRT-S'
 OPEN BRANCH FROM BUS 324217 TO BUS 324219 CKT 1   /*4BROWN PLANT 138.0 - 4BROWN T1    138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324220 CKT 1   /*4BROWN PLANT 138.0 - 4BROWN T2    138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324239 CKT 1   /*4BROWN PLANT 138.0 - 4DANVILE N T 138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324248 CKT 1   /*4BROWN PLANT 138.0 - 4FAWKES KU   138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324318 CKT 1   /*4BROWN PLANT 138.0 - 4WEST CLIFF  138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324318 CKT 2   /*4BROWN PLANT 138.0 - 4WEST CLIFF  138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 325012 CKT 1   /*4BROWN PLANT 138.0 - 1BROWN SOLAR  13.2
 OPEN BRANCH FROM BUS 324238 TO BUS 324239 CKT 1   /*4DANVILLE N  138.0 - 4DANVILE N T 138.0
 OPEN BRANCH FROM BUS 324239 TO BUS 950000 CKT 1   /*4DANVILE N T 138.0 - AG9-001      138.0
END
OP AC 109.23 182.0 B 198.81 13.13
LGEE/OVEC 7TRIMBL REAC-06CLIFTY 345.0 kV Ckt 1 line
324010 to 248000 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 110.53 1451.0 B 1603.74 22.82
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
Base Case OP AC 104.47 187.0 A 195.36 16.73
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
Base Case OP AC 102.02 192.0 A 195.88 16.73

Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
Base Case OP AC 123.4 1240.0 A 1530.17 12.49
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
DAY/EKPC 7SPURLOCK-09STUART 345.0 kV Ckt 1 line
342838 to 253077 ckt 1
Base Case OP AC 123.89 1240.0 A 1536.19 12.66
Topology Case Flowgate Details for 7SPURLOCK-09STUART 345.0 kV Ckt 1 line l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 5.93 MW 5.04 MW
964892 AG1-353 E Adder 3.95 MW 3.36 MW
964901 AG1-354 C Adder 7.5 MW 6.37 MW
964902 AG1-354 E Adder 5.0 MW 4.25 MW
965401 AG1-405 C Adder 4.88 MW 4.15 MW
965402 AG1-405 E Adder 3.26 MW 2.77 MW
966571 AG1-526 C Adder 23.52 MW 19.99 MW
966572 AG1-526 E Adder 15.68 MW 13.33 MW
925985 AC1-074 E 50/50 6.42 MW 6.42 MW
926105 AC1-089 E Adder 7.68 MW 6.53 MW
936381 AD2-048 C Adder 12.05 MW 10.24 MW
936382 AD2-048 E Adder 6.01 MW 5.11 MW
936576 AD2-072_E Adder 4.73 MW 4.02 MW
942091 AE2-221 C Adder -28.84 MW -24.51 MW
943111 AE2-339 C 50/50 7.06 MW 7.06 MW
943112 AE2-339 E 50/50 3.48 MW 3.48 MW
943701 AF1-038 C Adder 3.68 MW 3.13 MW
943702 AF1-038 E Adder 2.45 MW 2.08 MW
943821 AF1-050 C Adder 3.29 MW 2.8 MW
943822 AF1-050 E Adder 2.2 MW 1.87 MW
944511 AF1-116 C Adder 8.18 MW 6.96 MW
944512 AF1-116 E Adder 5.46 MW 4.64 MW
945382 AF1-203 E Adder 0.64 MW 0.55 MW
945681 AF1-233 C 50/50 44.44 MW 44.44 MW
945682 AF1-233 E 50/50 29.63 MW 29.63 MW
959691 AF2-260 C Adder 4.67 MW 3.97 MW
959692 AF2-260 E Adder 2.82 MW 2.4 MW
960161 AF2-307 C Adder 10.13 MW 8.61 MW
960162 AF2-307 E Adder 6.75 MW 5.74 MW
960181 AF2-309 C Adder 3.7 MW 3.15 MW
960182 AF2-309 E Adder 2.47 MW 2.1 MW
960571 AF2-348 C 50/50 64.19 MW 64.19 MW
960572 AF2-348 E 50/50 42.79 MW 42.79 MW
251970 08MELDL1 50/50 1.52 MW 1.52 MW
251971 08MELDL2 50/50 1.52 MW 1.52 MW
251972 08MELDL3 50/50 1.52 MW 1.52 MW
342939 1JKCT 9G 50/50 3.02 MW 3.02 MW
342957 1SPURLK1G 50/50 20.65 MW 20.65 MW
342960 1SPURLK2G 50/50 39.16 MW 39.16 MW
342963 1SPURLK3G 50/50 20.58 MW 20.58 MW
342966 1SPURLK4G 50/50 20.58 MW 20.58 MW
939132 AE1-143 E Adder 3.61 MW 3.07 MW
940832 AE2-071 E Adder 1.12 MW 0.96 MW
941411 AE2-138 C 50/50 6.47 MW 6.47 MW
941412 AE2-138 E 50/50 74.43 MW 74.43 MW
957961 AF2-090 C Adder 6.39 MW 5.43 MW
957962 AF2-090 E Adder 3.16 MW 2.69 MW
942415 AE2-254 E Adder 3.22 MW 2.73 MW
339200 AD2-072_C Adder 9.65 MW 8.21 MW
339206 AE1-143 C Adder 7.29 MW 6.2 MW
339216 AC1-074 C 50/50 2.42 MW 2.42 MW
962211 AG1-066 C Adder 4.01 MW 3.41 MW
962212 AG1-066 E Adder 2.68 MW 2.27 MW
932554 AC2-075 E 50/50 1.79 MW 1.79 MW
339218 AC2-075 C 50/50 0.54 MW 0.54 MW
942591 AE2-275 C Adder 1.66 MW 1.41 MW
942592 AE2-275 E Adder 19.06 MW 16.2 MW
942891 AE2-308 C Adder 13.77 MW 11.7 MW
942892 AE2-308 E Adder 9.18 MW 7.8 MW
944151 AF1-083 C Adder 3.42 MW 2.91 MW
944152 AF1-083 E Adder 2.28 MW 1.94 MW
960151 AF2-306 C Adder 6.65 MW 5.65 MW
960171 AF2-308 C Adder 2.47 MW 2.1 MW
960641 AF2-355 C Adder 31.0 MW 26.35 MW
960642 AF2-355 E Adder 20.67 MW 17.57 MW
960741 AF2-365 C Adder 2.48 MW 2.1 MW
960742 AF2-365 E Adder 1.65 MW 1.4 MW
961001 AF2-391 C Adder 6.35 MW 5.4 MW
961002 AF2-391 E Adder 4.23 MW 3.6 MW
251968 08ZIMRHP Adder 152.26 MW 129.42 MW
964571 AG1-320 C Adder 4.98 MW 4.23 MW
964572 AG1-320 E Adder 2.47 MW 2.1 MW
941981 AE2-210 C 50/50 2.24 MW 2.24 MW
941982 AE2-210 E 50/50 25.77 MW 25.77 MW
958171 AF2-111 C 50/50 68.15 MW 68.15 MW
958172 AF2-111 E 50/50 45.43 MW 45.43 MW
965411 AG1-406 C Adder 3.14 MW 2.67 MW
966021 AG1-471 C Adder 3.13 MW 2.66 MW
966022 AG1-471 E Adder 2.09 MW 1.78 MW
950041 AG9-017 External Queue 19.18 MW 19.18 MW
950051 AG9-018 External Queue 18.98 MW 18.98 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 22.23 MW 22.23 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 21.87 MW 21.87 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 14.4 MW 14.4 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.13 MW 1.13 MW
NY PJM->LTFIMP_NY CLTF 0.63 MW 0.63 MW
LGEE LTFEXP_LGEE->PJM CLTF 4.83 MW 4.83 MW
WEC LTFEXP_WEC->PJM CLTF 0.55 MW 0.55 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.77 MW 0.77 MW
TVA LTFEXP_TVA->PJM CLTF 5.38 MW 5.38 MW
MEC LTFEXP_MEC->PJM CLTF 3.67 MW 3.67 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.8 MW 5.8 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.53 MW 0.53 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 7.29 MW 7.29 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.37 MW 0.37 MW

Details for 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer l/o EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer
342733 to 341563 ckt 1
EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C
CONTINGENCY 'EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C'
 OPEN BRANCH FROM BUS 944150 TO BUS 342817 CKT 1   /*AF1-083 TP   161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 964890 TO BUS 342817 CKT 1   /*AG1-353 TP   161.0 - 5TAYLOR CO J 161.0
END
OP AC 122.0 109.0 B 132.98 19.27
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer
342733 to 341563 ckt 1
EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C
CONTINGENCY 'EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C'
 OPEN BRANCH FROM BUS 944150 TO BUS 342817 CKT 1   /*AF1-083 TP   161.0 - 5TAYLOR CO J 161.0
 OPEN BRANCH FROM BUS 964890 TO BUS 342817 CKT 1   /*AG1-353 TP   161.0 - 5TAYLOR CO J 161.0
END
OP AC 122.2 109.0 B 133.2 19.27
Topology Case Flowgate Details for 5GREEN CO-2GREEN CO 161.0/69.0 kV Ckt 1 transformer l/o EKPC_P1-2_GRE-TAY-MAR161_SRT-A-C
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 17.01 MW 17.01 MW
964892 AG1-353 E 50/50 11.34 MW 11.34 MW
964901 AG1-354 C 50/50 11.56 MW 11.56 MW
964902 AG1-354 E 50/50 7.71 MW 7.71 MW
943821 AF1-050 C 50/50 8.22 MW 8.22 MW
943822 AF1-050 E 50/50 5.48 MW 5.48 MW
964781 AG1-341 C Adder 3.56 MW 3.02 MW
964782 AG1-341 E Adder 2.37 MW 2.02 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.01 MW 0.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.49 MW 0.49 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.39 MW 1.39 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.03 MW 2.03 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.1 MW 0.1 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.14 MW 0.14 MW
TVA LTFEXP_TVA->PJM CLTF 0.69 MW 0.69 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.17 MW 0.17 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.38 MW 0.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.65 MW 0.65 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.07 MW 0.07 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Base Case OP AC 116.63 219.0 A 255.41 15.2
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Base Case OP AC 116.54 219.0 A 255.23 15.2
Topology Case Flowgate Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 6.64 MW 6.64 MW
964892 AG1-353 E 50/50 4.43 MW 4.43 MW
964901 AG1-354 C 50/50 9.12 MW 9.12 MW
964902 AG1-354 E 50/50 6.08 MW 6.08 MW
965401 AG1-405 C Adder 3.06 MW 2.6 MW
965402 AG1-405 E Adder 2.04 MW 1.73 MW
943701 AF1-038 C 50/50 5.37 MW 5.37 MW
943702 AF1-038 E 50/50 3.58 MW 3.58 MW
943821 AF1-050 C 50/50 3.8 MW 3.8 MW
943822 AF1-050 E 50/50 2.53 MW 2.53 MW
944511 AF1-116 C 50/50 9.49 MW 9.49 MW
944512 AF1-116 E 50/50 6.33 MW 6.33 MW
945381 AF1-203 C 50/50 0.18 MW 0.18 MW
945382 AF1-203 E 50/50 0.82 MW 0.82 MW
342070 2PINE GROVE 50/50 0.05 MW 0.05 MW
342900 1COOPER1 G 50/50 8.51 MW 8.51 MW
342903 1COOPER2 G 50/50 16.57 MW 16.57 MW
342945 1LAUREL 1G 50/50 3.26 MW 3.26 MW
939132 AE1-143 E 50/50 4.19 MW 4.19 MW
940831 AE2-071 C 50/50 0.32 MW 0.32 MW
940832 AE2-071 E 50/50 1.43 MW 1.43 MW
339206 AE1-143 C 50/50 8.46 MW 8.46 MW
962241 AG1-070 C Adder 2.84 MW 2.41 MW
962242 AG1-070 E Adder 1.07 MW 0.91 MW
962251 AG1-071 C Adder 3.25 MW 2.77 MW
962252 AG1-071 E Adder 1.52 MW 1.29 MW
944151 AF1-083 C 50/50 3.83 MW 3.83 MW
944152 AF1-083 E 50/50 2.55 MW 2.55 MW
960741 AF2-365 C Adder 2.17 MW 1.84 MW
960742 AF2-365 E Adder 1.45 MW 1.23 MW
966951 AE2-000D C Adder 5.38 MW 4.58 MW
966952 AE2-000D E Adder 2.62 MW 2.22 MW
962221 AG1-067 C Adder 2.36 MW 2.0 MW
962222 AG1-067 E Adder 1.26 MW 1.07 MW
964781 AG1-341 C Adder 6.25 MW 5.31 MW
964782 AG1-341 E Adder 4.16 MW 3.54 MW
965411 AG1-406 C Adder 1.97 MW 1.67 MW
966021 AG1-471 C 50/50 6.23 MW 6.23 MW
966022 AG1-471 E 50/50 4.15 MW 4.15 MW
950000 AG9-001 External Queue 6.48 MW 6.48 MW
950011 AG9-010 External Queue 11.69 MW 11.69 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.54 MW 2.54 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.98 MW 3.98 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.81 MW 1.81 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.14 MW 0.14 MW
NY PJM->LTFIMP_NY CLTF 0.07 MW 0.07 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.07 MW 0.07 MW
TVA LTFEXP_TVA->PJM CLTF 1.55 MW 1.55 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.03 MW 0.03 MW
MEC LTFEXP_MEC->PJM CLTF 0.57 MW 0.57 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.42 MW 1.42 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.87 MW 0.87 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.04 MW 0.04 MW

Details for 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line l/o P2-3-228_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line
342757 to 342754 ckt 1
P2-3-228_SRT-S
CONTINGENCY 'P2-3-228_SRT-S'
 OPEN BRANCH FROM BUS 324100 TO BUS 324102 CKT 1   /*7ALCALDE     345.0 - 7BROWN NORTH 345.0
 OPEN BRANCH FROM BUS 324100 TO BUS 324112 CKT 1   /*7ALCALDE     345.0 - 7PINEVILLE   345.0
 OPEN BRANCH FROM BUS 324100 TO BUS 324130 CKT 1   /*7ALCALDE     345.0 - 5ALCALDE     161.0
 OPEN BRANCH FROM BUS 324130 TO BUS 324141 CKT 1   /*5ALCALDE     161.0 - 5ELIHU       161.0
 OPEN BRANCH FROM BUS 324130 TO BUS 324143 CKT 1   /*5ALCALDE     161.0 - 5FARLEY      161.0
END
OP AC 106.37 211.0 B 224.45 9.11
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line
342757 to 342754 ckt 1
P2-3-228_SRT-S
CONTINGENCY 'P2-3-228_SRT-S'
 OPEN BRANCH FROM BUS 324100 TO BUS 324102 CKT 1   /*7ALCALDE     345.0 - 7BROWN NORTH 345.0
 OPEN BRANCH FROM BUS 324100 TO BUS 324112 CKT 1   /*7ALCALDE     345.0 - 7PINEVILLE   345.0
 OPEN BRANCH FROM BUS 324100 TO BUS 324130 CKT 1   /*7ALCALDE     345.0 - 5ALCALDE     161.0
 OPEN BRANCH FROM BUS 324130 TO BUS 324141 CKT 1   /*5ALCALDE     161.0 - 5ELIHU       161.0
 OPEN BRANCH FROM BUS 324130 TO BUS 324143 CKT 1   /*5ALCALDE     161.0 - 5FARLEY      161.0
END
OP AC 106.27 211.0 B 224.23 9.11
Topology Case Flowgate Details for 5LAUREL DAM-5LAUREL CO 161.0 kV Ckt 1 line l/o P2-3-228_SRT-S
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C Adder 3.89 MW 3.3 MW
964892 AG1-353 E Adder 2.59 MW 2.2 MW
964901 AG1-354 C Adder 5.46 MW 4.64 MW
964902 AG1-354 E Adder 3.64 MW 3.1 MW
965401 AG1-405 C 50/50 4.42 MW 4.42 MW
965402 AG1-405 E 50/50 2.95 MW 2.95 MW
943701 AF1-038 C 50/50 4.68 MW 4.68 MW
943702 AF1-038 E 50/50 3.12 MW 3.12 MW
943821 AF1-050 C Adder 2.26 MW 1.92 MW
943822 AF1-050 E Adder 1.5 MW 1.28 MW
944511 AF1-116 C Adder 5.44 MW 4.62 MW
944512 AF1-116 E Adder 3.62 MW 3.08 MW
945382 AF1-203 E Adder 0.52 MW 0.44 MW
342900 1COOPER1 G 50/50 4.25 MW 4.25 MW
342903 1COOPER2 G 50/50 8.27 MW 8.27 MW
342945 1LAUREL 1G 50/50 5.23 MW 5.23 MW
939132 AE1-143 E Adder 2.4 MW 2.04 MW
940832 AE2-071 E Adder 0.9 MW 0.77 MW
339206 AE1-143 C Adder 4.84 MW 4.12 MW
962241 AG1-070 C Adder 1.75 MW 1.49 MW
962242 AG1-070 E Adder 0.66 MW 0.56 MW
962251 AG1-071 C Adder 2.0 MW 1.7 MW
962252 AG1-071 E Adder 0.94 MW 0.8 MW
944151 AF1-083 C Adder 2.23 MW 1.9 MW
944152 AF1-083 E Adder 1.49 MW 1.26 MW
966951 AE2-000D C Adder 3.27 MW 2.78 MW
966952 AE2-000D E Adder 1.59 MW 1.35 MW
962221 AG1-067 C Adder 1.47 MW 1.25 MW
962222 AG1-067 E Adder 0.78 MW 0.67 MW
964781 AG1-341 C Adder 3.77 MW 3.21 MW
964782 AG1-341 E Adder 2.52 MW 2.14 MW
965411 AG1-406 C 50/50 2.84 MW 2.84 MW
966021 AG1-471 C 50/50 3.77 MW 3.77 MW
966022 AG1-471 E 50/50 2.51 MW 2.51 MW
950011 AG9-010 External Queue 6.38 MW 6.38 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.75 MW 2.75 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.13 MW 3.13 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.32 MW 1.32 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.09 MW 0.09 MW
NY PJM->LTFIMP_NY CLTF 0.05 MW 0.05 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.06 MW 0.06 MW
TVA LTFEXP_TVA->PJM CLTF 1.06 MW 1.06 MW
MEC LTFEXP_MEC->PJM CLTF 0.49 MW 0.49 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.01 MW 1.01 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.59 MW 0.59 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.03 MW 0.03 MW

Details for 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line l/o P2-3-102_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line
342769 to 342703 ckt 1
P2-3-102_SRT-S
CONTINGENCY 'P2-3-102_SRT-S'
 OPEN BRANCH FROM BUS 324217 TO BUS 324219 CKT 1   /*4BROWN PLANT 138.0 - 4BROWN T1    138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324220 CKT 1   /*4BROWN PLANT 138.0 - 4BROWN T2    138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324239 CKT 1   /*4BROWN PLANT 138.0 - 4DANVILE N T 138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324248 CKT 1   /*4BROWN PLANT 138.0 - 4FAWKES KU   138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324318 CKT 1   /*4BROWN PLANT 138.0 - 4WEST CLIFF  138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324318 CKT 2   /*4BROWN PLANT 138.0 - 4WEST CLIFF  138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 325012 CKT 1   /*4BROWN PLANT 138.0 - 1BROWN SOLAR  13.2
 OPEN BRANCH FROM BUS 324238 TO BUS 324239 CKT 1   /*4DANVILLE N  138.0 - 4DANVILE N T 138.0
 OPEN BRANCH FROM BUS 324239 TO BUS 950000 CKT 1   /*4DANVILE N T 138.0 - AG9-001      138.0
END
OP AC 109.23 182.0 B 198.81 13.13
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line
342769 to 342703 ckt 1
P2-3-102_SRT-S
CONTINGENCY 'P2-3-102_SRT-S'
 OPEN BRANCH FROM BUS 324217 TO BUS 324219 CKT 1   /*4BROWN PLANT 138.0 - 4BROWN T1    138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324220 CKT 1   /*4BROWN PLANT 138.0 - 4BROWN T2    138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324239 CKT 1   /*4BROWN PLANT 138.0 - 4DANVILE N T 138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324248 CKT 1   /*4BROWN PLANT 138.0 - 4FAWKES KU   138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324318 CKT 1   /*4BROWN PLANT 138.0 - 4WEST CLIFF  138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 324318 CKT 2   /*4BROWN PLANT 138.0 - 4WEST CLIFF  138.0
 OPEN BRANCH FROM BUS 324217 TO BUS 325012 CKT 1   /*4BROWN PLANT 138.0 - 1BROWN SOLAR  13.2
 OPEN BRANCH FROM BUS 324238 TO BUS 324239 CKT 1   /*4DANVILLE N  138.0 - 4DANVILE N T 138.0
 OPEN BRANCH FROM BUS 324239 TO BUS 950000 CKT 1   /*4DANVILE N T 138.0 - AG9-001      138.0
END
OP AC 108.92 182.0 B 198.23 13.13
Topology Case Flowgate Details for 5MARION CO-5CASEY CO 161.0 kV Ckt 1 line l/o P2-3-102_SRT-S
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 13.2 MW 13.2 MW
964892 AG1-353 E 50/50 8.8 MW 8.8 MW
964901 AG1-354 C Adder 7.88 MW 6.69 MW
964902 AG1-354 E Adder 5.25 MW 4.46 MW
943701 AF1-038 C Adder -2.66 MW -2.26 MW
943821 AF1-050 C 50/50 5.38 MW 5.38 MW
943822 AF1-050 E 50/50 3.58 MW 3.58 MW
944511 AF1-116 C 50/50 24.98 MW 24.98 MW
944512 AF1-116 E 50/50 16.65 MW 16.65 MW
939132 AE1-143 E 50/50 11.03 MW 11.03 MW
339206 AE1-143 C 50/50 22.26 MW 22.26 MW
944151 AF1-083 C 50/50 8.23 MW 8.23 MW
944152 AF1-083 E 50/50 5.49 MW 5.49 MW
960741 AF2-365 C Adder 2.2 MW 1.87 MW
960742 AF2-365 E Adder 1.47 MW 1.25 MW
964571 AG1-320 C Adder 3.1 MW 2.63 MW
964572 AG1-320 E Adder 1.54 MW 1.31 MW
950000 AG9-001 External Queue 31.95 MW 31.95 MW
950011 AG9-010 External Queue 34.85 MW 34.85 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.83 MW 3.83 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.54 MW 2.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.18 MW 0.18 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
TVA LTFEXP_TVA->PJM CLTF 0.47 MW 0.47 MW
MEC LTFEXP_MEC->PJM CLTF 0.5 MW 0.5 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.56 MW 0.56 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.08 MW 0.08 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.15 MW 0.15 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.02 MW 0.02 MW

Details for 7TRIMBL REAC-06CLIFTY 345.0 kV Ckt 1 line l/o AEP_P1-2_#10136_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
LGEE/OVEC 7TRIMBL REAC-06CLIFTY 345.0 kV Ckt 1 line
324010 to 248000 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 110.53 1451.0 B 1603.74 22.82
Increase
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
LGEE/OVEC 7TRIMBL REAC-06CLIFTY 345.0 kV Ckt 1 line
324010 to 248000 ckt 1
AEP_P1-2_#10136_SRT-A
CONTINGENCY 'AEP_P1-2_#10136_SRT-A'
 OPEN BRANCH FROM BUS 243208 TO BUS 243209 CKT 1   /*05JEFRSO     765.0 - 05ROCKPT     765.0
 OPEN BRANCH FROM BUS 243209 TO BUS 243443 CKT 2   /*05ROCKPT     765.0 - 05RKG2        26.0
 REMOVE UNIT 2H FROM BUS 243443                    /*05RKG2        26.0
 REMOVE UNIT 2L FROM BUS 243443                    /*05RKG2        26.0
END
OP AC 106.67 1451.0 B 1547.77 22.15
Topology Case Flowgate Details for 7TRIMBL REAC-06CLIFTY 345.0 kV Ckt 1 line l/o AEP_P1-2_#10136_SRT-A
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 9.09 MW 9.09 MW
964892 AG1-353 E 50/50 6.06 MW 6.06 MW
964901 AG1-354 C 50/50 13.69 MW 13.69 MW
964902 AG1-354 E 50/50 9.13 MW 9.13 MW
965401 AG1-405 C 50/50 4.07 MW 4.07 MW
965402 AG1-405 E 50/50 2.71 MW 2.71 MW
966531 AG1-522 C Adder 11.08 MW 9.41 MW
966532 AG1-522 E Adder 7.38 MW 6.28 MW
966541 AG1-523 C Adder 11.08 MW 9.41 MW
966542 AG1-523 E Adder 7.38 MW 6.28 MW
966551 AG1-524 C Adder 11.08 MW 9.41 MW
966552 AG1-524 E Adder 7.38 MW 6.28 MW
966561 AG1-525 C Adder 11.08 MW 9.41 MW
966562 AG1-525 E Adder 7.38 MW 6.28 MW
966571 AG1-526 C 50/50 18.1 MW 18.1 MW
966572 AG1-526 E 50/50 12.07 MW 12.07 MW
925985 AC1-074 E Adder 1.83 MW 1.56 MW
936381 AD2-048 C Adder 3.62 MW 3.08 MW
936382 AD2-048 E Adder 1.8 MW 1.53 MW
936576 AD2-072_E 50/50 5.05 MW 5.05 MW
943111 AE2-339 C Adder 2.64 MW 2.25 MW
943112 AE2-339 E Adder 1.3 MW 1.11 MW
943701 AF1-038 C 50/50 4.74 MW 4.74 MW
943702 AF1-038 E 50/50 3.16 MW 3.16 MW
943821 AF1-050 C 50/50 5.54 MW 5.54 MW
943822 AF1-050 E 50/50 3.69 MW 3.69 MW
944511 AF1-116 C 50/50 10.96 MW 10.96 MW
944512 AF1-116 E 50/50 7.3 MW 7.3 MW
945381 AF1-203 C 50/50 0.26 MW 0.26 MW
945382 AF1-203 E 50/50 1.18 MW 1.18 MW
959691 AF2-260 C 50/50 11.09 MW 11.09 MW
959692 AF2-260 E 50/50 6.7 MW 6.7 MW
960161 AF2-307 C Adder 2.68 MW 2.28 MW
960162 AF2-307 E Adder 1.79 MW 1.52 MW
960181 AF2-309 C 50/50 8.88 MW 8.88 MW
960182 AF2-309 E 50/50 5.92 MW 5.92 MW
341200 2BROMLEYEK 50/50 0.05 MW 0.05 MW
341329 2COLESBURG 50/50 0.08 MW 0.08 MW
342070 2PINE GROVE 50/50 0.05 MW 0.05 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 2.16 MW 2.16 MW
342903 1COOPER2 G 50/50 4.19 MW 4.19 MW
342918 1JKCT 1G 50/50 1.7 MW 1.7 MW
342921 1JKCT 2G 50/50 1.65 MW 1.65 MW
342924 1JKCT 3G 50/50 1.67 MW 1.67 MW
342927 1JKCT 4G 50/50 1.12 MW 1.12 MW
342936 1JKCT 7G 50/50 1.09 MW 1.09 MW
342945 1LAUREL 1G 50/50 1.22 MW 1.22 MW
939132 AE1-143 E 50/50 4.84 MW 4.84 MW
940831 AE2-071 C 50/50 0.46 MW 0.46 MW
940832 AE2-071 E 50/50 2.06 MW 2.06 MW
941411 AE2-138 C Adder 1.74 MW 1.48 MW
941412 AE2-138 E Adder 19.97 MW 16.98 MW
957961 AF2-090 C 50/50 16.84 MW 16.84 MW
957962 AF2-090 E 50/50 8.33 MW 8.33 MW
933441 AC2-157 C Adder 4.68 MW 3.98 MW
933442 AC2-157 E Adder 7.63 MW 6.49 MW
942415 AE2-254 E 50/50 2.73 MW 2.73 MW
339200 AD2-072_C 50/50 10.31 MW 10.31 MW
339206 AE1-143 C 50/50 9.76 MW 9.76 MW
962241 AG1-070 C 50/50 4.88 MW 4.88 MW
962242 AG1-070 E 50/50 1.84 MW 1.84 MW
962251 AG1-071 C 50/50 5.6 MW 5.6 MW
962252 AG1-071 E 50/50 2.61 MW 2.61 MW
932554 AC2-075 E Adder 0.51 MW 0.43 MW
339211 AE2-254 GEN 50/50 0.62 MW 0.62 MW
942591 AE2-275 C 50/50 0.77 MW 0.77 MW
942592 AE2-275 E 50/50 8.82 MW 8.82 MW
942601 AE2-276 C Adder 3.08 MW 2.62 MW
942891 AE2-308 C 50/50 6.42 MW 6.42 MW
942892 AE2-308 E 50/50 4.28 MW 4.28 MW
944151 AF1-083 C 50/50 5.09 MW 5.09 MW
944152 AF1-083 E 50/50 3.39 MW 3.39 MW
960151 AF2-306 C Adder 1.76 MW 1.5 MW
960171 AF2-308 C 50/50 5.92 MW 5.92 MW
960641 AF2-355 C 50/50 15.37 MW 15.37 MW
960642 AF2-355 E 50/50 10.25 MW 10.25 MW
960741 AF2-365 C 50/50 4.84 MW 4.84 MW
960742 AF2-365 E 50/50 3.22 MW 3.22 MW
961001 AF2-391 C 50/50 15.99 MW 15.99 MW
961002 AF2-391 E 50/50 10.66 MW 10.66 MW
966951 AE2-000D C 50/50 8.67 MW 8.67 MW
966952 AE2-000D E 50/50 4.21 MW 4.21 MW
930461 AB1-087 C Adder 33.86 MW 28.78 MW
930462 AB1-087 E Adder 1.54 MW 1.31 MW
930471 AB1-088 C Adder 33.86 MW 28.78 MW
930472 AB1-088 E Adder 1.54 MW 1.31 MW
962221 AG1-067 C 50/50 3.65 MW 3.65 MW
962222 AG1-067 E 50/50 1.94 MW 1.94 MW
964571 AG1-320 C 50/50 11.19 MW 11.19 MW
964572 AG1-320 E 50/50 5.55 MW 5.55 MW
941981 AE2-210 C Adder 0.6 MW 0.51 MW
941982 AE2-210 E Adder 6.91 MW 5.88 MW
964781 AG1-341 C 50/50 9.6 MW 9.6 MW
964782 AG1-341 E 50/50 6.4 MW 6.4 MW
965411 AG1-406 C 50/50 2.62 MW 2.62 MW
966021 AG1-471 C 50/50 4.46 MW 4.46 MW
966022 AG1-471 E 50/50 2.97 MW 2.97 MW
957142 AF2-008 NFTI Adder 36.21 MW 30.78 MW
957141 AF2-008 FTIR Adder 36.21 MW 30.78 MW
944201 AF1-088 FTIR Adder 72.42 MW 61.56 MW
950021 AG9-008 External Queue 69.33 MW 69.33 MW
990427 J1308 G External Queue 25.35 MW 25.35 MW
991207 J1637 External Queue 9.54 MW 9.54 MW
991502 J2063 External Queue 6.36 MW 6.36 MW
991532 J2123 External Queue 6.55 MW 6.55 MW
991547 J2164 External Queue 14.18 MW 14.18 MW
991632 J2236 External Queue -5.4 MW -5.4 MW
991652 J2254 External Queue 5.68 MW 5.68 MW
991657 J2263 External Queue 5.89 MW 5.89 MW
991677 J2280 External Queue -10.69 MW -10.69 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 28.61 MW 28.61 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 45.52 MW 45.52 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 26.47 MW 26.47 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.31 MW 0.31 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 19.35 MW 19.35 MW
WEC LTFEXP_WEC->PJM CLTF 0.69 MW 0.69 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.7 MW 1.7 MW
TVA LTFEXP_TVA->PJM CLTF 9.81 MW 9.81 MW
MEC LTFEXP_MEC->PJM CLTF 6.22 MW 6.22 MW
LAGN LTFEXP_LAGN->PJM CLTF 10.76 MW 10.76 MW
SIGE LTFEXP_SIGE->PJM CLTF 1.62 MW 1.62 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.99 MW 1.99 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.76 MW 0.76 MW

Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
Base Case OP AC 104.47 187.0 A 195.36 16.73
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC/LGEE 4MARION CO-4LEBANON 138.0 kV Ckt 1 line
342770 to 324271 ckt 1
Base Case OP AC 104.88 187.0 A 196.12 16.73
Topology Case Flowgate Details for 4MARION CO-4LEBANON 138.0 kV Ckt 1 line l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 15.02 MW 15.02 MW
964892 AG1-353 E 50/50 10.01 MW 10.01 MW
964901 AG1-354 C 50/50 10.04 MW 10.04 MW
964902 AG1-354 E 50/50 6.69 MW 6.69 MW
965401 AG1-405 C Adder 2.02 MW 1.72 MW
965402 AG1-405 E Adder 1.35 MW 1.14 MW
943701 AF1-038 C Adder 3.25 MW 2.76 MW
943702 AF1-038 E Adder 2.17 MW 1.84 MW
943821 AF1-050 C 50/50 6.22 MW 6.22 MW
943822 AF1-050 E 50/50 4.14 MW 4.14 MW
944511 AF1-116 C 50/50 32.76 MW 32.76 MW
944512 AF1-116 E 50/50 21.84 MW 21.84 MW
945382 AF1-203 E Adder 0.55 MW 0.47 MW
939132 AE1-143 E 50/50 14.47 MW 14.47 MW
940832 AE2-071 E Adder 0.96 MW 0.82 MW
339206 AE1-143 C 50/50 29.2 MW 29.2 MW
944151 AF1-083 C 50/50 9.45 MW 9.45 MW
944152 AF1-083 E 50/50 6.3 MW 6.3 MW
966951 AE2-000D C Adder 3.18 MW 2.71 MW
966952 AE2-000D E Adder 1.55 MW 1.31 MW
962221 AG1-067 C Adder 1.48 MW 1.26 MW
962222 AG1-067 E Adder 0.79 MW 0.67 MW
964781 AG1-341 C Adder 4.27 MW 3.63 MW
964782 AG1-341 E Adder 2.85 MW 2.42 MW
965411 AG1-406 C Adder 1.3 MW 1.1 MW
966021 AG1-471 C Adder 2.11 MW 1.79 MW
966022 AG1-471 E Adder 1.41 MW 1.2 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.03 MW 0.03 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.64 MW 1.64 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 4.05 MW 4.05 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.08 MW 0.08 MW
VTF LTFEXP_VFT->PJM CMTX 0.21 MW 0.21 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.29 MW 0.29 MW
TVA LTFEXP_TVA->PJM CLTF 1.08 MW 1.08 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.28 MW 0.28 MW
MEC LTFEXP_MEC->PJM CLTF 0.12 MW 0.12 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.86 MW 0.86 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.96 MW 0.96 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.14 MW 0.14 MW

Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Impact of Topology Modeling
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
Base Case OP AC 102.02 192.0 A 195.88 16.73
Decrease
Base Run Case Flowgate
Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution
EKPC 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer
342769 to 342770 ckt 1
Base Case OP AC 102.42 192.0 A 196.64 16.73
Topology Case Flowgate Details for 5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer l/o Base Case
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964891 AG1-353 C 50/50 15.02 MW 15.02 MW
964892 AG1-353 E 50/50 10.01 MW 10.01 MW
964901 AG1-354 C 50/50 10.04 MW 10.04 MW
964902 AG1-354 E 50/50 6.69 MW 6.69 MW
965401 AG1-405 C Adder 2.02 MW 1.72 MW
965402 AG1-405 E Adder 1.35 MW 1.14 MW
943701 AF1-038 C Adder 3.25 MW 2.76 MW
943702 AF1-038 E Adder 2.17 MW 1.84 MW
943821 AF1-050 C 50/50 6.22 MW 6.22 MW
943822 AF1-050 E 50/50 4.14 MW 4.14 MW
944511 AF1-116 C 50/50 32.76 MW 32.76 MW
944512 AF1-116 E 50/50 21.84 MW 21.84 MW
945382 AF1-203 E Adder 0.55 MW 0.47 MW
939132 AE1-143 E 50/50 14.47 MW 14.47 MW
940832 AE2-071 E Adder 0.96 MW 0.82 MW
339206 AE1-143 C 50/50 29.2 MW 29.2 MW
944151 AF1-083 C 50/50 9.45 MW 9.45 MW
944152 AF1-083 E 50/50 6.3 MW 6.3 MW
966951 AE2-000D C Adder 3.18 MW 2.71 MW
966952 AE2-000D E Adder 1.55 MW 1.31 MW
962221 AG1-067 C Adder 1.48 MW 1.26 MW
962222 AG1-067 E Adder 0.79 MW 0.67 MW
964781 AG1-341 C Adder 4.27 MW 3.63 MW
964782 AG1-341 E Adder 2.85 MW 2.42 MW
965411 AG1-406 C Adder 1.3 MW 1.1 MW
966021 AG1-471 C Adder 2.11 MW 1.79 MW
966022 AG1-471 E Adder 1.41 MW 1.2 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.03 MW 0.03 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.64 MW 1.64 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 4.05 MW 4.05 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.08 MW 0.08 MW
VTF LTFEXP_VFT->PJM CMTX 0.21 MW 0.21 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.29 MW 0.29 MW
TVA LTFEXP_TVA->PJM CLTF 1.08 MW 1.08 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.28 MW 0.28 MW
MEC LTFEXP_MEC->PJM CLTF 0.12 MW 0.12 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.86 MW 0.86 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.96 MW 0.96 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.14 MW 0.14 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle #2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle #2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 25 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 25 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 25 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 25 projects have been dispatched online at maximum power output, and voltage schedules set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 25 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 142 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 25 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a) Cluster 25 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with Cluster 25 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG-353, AG1-354 and AG1-471 meet the 0.95 leading and lagging PF requirement.

 

Fictitious voltage response at AF1-083 generator terminal bus at fault clearance caused the generator terminal voltage to exceed 1.2 pu for longer than 0.019 seconds resulting in the unit being tripped by voltage relay instance 94415404. The relay pickup time was extended to 0.05 seconds to resolve tripping of the unit.

 

Fictitious voltage response at AF1-050 generator terminal bus at fault clearance caused the generator terminal voltage to exceed 1.2 pu for longer than 0.0292 seconds resulting in the unit being tripped by voltage relay instance 94382404. The relay pickup time  was extended to 0.05 seconds to resolve tripping of the unit.

 

AG1-471 generator unit remained in High Voltage Ride Through mode for several  contingencies. As a result, the AG1-471 generator terminal voltage remained at approximately 1.12 pu after fault recovery causing the voltage relay stage set to 1.1 pu for 10 seconds to pick up and trip AG1-471 generating unit. Modifying CON(J+1): Vup to 1.16 pu of the REECA1 model resolved the issue of AG1-471 getting stuck in HVRT mode and resolved the tripping of the unit.

 

The stability study results in this report are considered preliminary, as PJM is actively performing simulations to assess the impacts of potential dynamic model parameter changes required to address identified stability issues. Additionally, feedback from the Transmission Owner is being incorporated into the stability study. The study will be finalized at the conclusion of Phase III of Transition Cycle 1.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 25 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

25

AG1-353

Solar

EKPC

98

98

58.8

Greene County - Marion County 161 kV

AG1-354

Solar

EKPC

150.0

150.0

90.0

Summershade - Green County 161 kV

AG1-471

Solar

EKPC

60.0

60.0

36.0

Up Church-Wayne County 69 kV

 

Reactive Power Analysis

The reactive power capability of AG1-354 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AC1-074 Jacksonville-Renaker 138kV I Under Construction
AC1-089 Hillsboro-Wildcat 138kV In Service
AC2-075 Jacksonville-Renaker 138 kV Under Construction
AD2-048 Cynthia-Headquarters 69 kV Under Construction
AD2-072 Van Arsdell-Mercer Industrial 69kV Withdrawn
AE1-143 Marion County 161 kV Engineering & Procurement
AE2-071 Patton Rd-Summer Shade 69 kV In Service
AE2-138 Avon-North Clark 345 kV Active
AE2-210 Avon-North Clark 345 kV Active
AE2-221 Clinton-Stuart 345 kV Engineering & Procurement
AE2-254 Garrard County-Tommy-Gooch 69 kV In Service
AE2-275 J.K. Smith-Fawkes 138 kV Active
AE2-308 Three Forks-Dale 138 kV Active
AE2-339 Avon 138 kV Engineering & Procurement
AF1-038 Sewellton Jct-Webbs Crossroads 69 kV Engineering & Procurement
AF1-050 Summer Shade - Green County 161 kV Engineering & Procurement
AF1-083 Green County-Saloma 161 kV Engineering & Procurement
AF1-116 Marion County 161 kV Active
AF1-203 Patton Rd-Summer Shade 69 kV In Service
AF1-233 Flemingsburg – Spurlock 138kV Active
AF2-090 Central Hardin 138 kV Withdrawn
AF2-111 North Clark-Spurlock 345 kV Active
AF2-260 Stephensburg-Central Hardin 69 kV Active
AF2-306 Hope-Blevins Valley Tap 69 kV Engineering & Procurement
AF2-307 Hope-Belvins Valley Tap 69 kV Active
AF2-308 Central Hardin-Stephensburg 69 kV Withdrawn
AF2-309 Central Hardin-Stephensburg 69 kV Withdrawn
AF2-348 North Clark-Spurlock 345 kV Active
AF2-355 West Gerrard-J.K. Smith 345 kV Active
AF2-365 Munfordville KU Tap-Horse Cave Jct. 69 kV Active
AF2-391 Central Hardin 69 kV Active
AG1-066 Bonnyman 69 kV Active
AG1-067 Temple Hill 69 kV Active
AG1-070 Bon Ayr 69 kV Active
AG1-071 Bon Ayr 69 kV Active
AG1-320 Glendale-Stephensburg 69 kV Active
AG1-341 Summer Shade 161 kV Active
AG1-353 Green County-Marion County 161 kV Active
AG1-405 Walnut Grove-Asahi 69 kV Active
AG1-406 Walnut Grove-Asahi 69 kV Active
AG1-471 Up Church-Wayne County 69 kV Active
AG1-526 West Garrard 345 kV Active

Affected Systems

In Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator (MISO) Study Pending
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Study Pending
Louisville Gas & Electric (LG&E) Study Pending
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase II analysis results, this project has potential cost responsibility for the following System Reinforcements:

AG1-354 System Reinforcements Cost Breakdown:
Type TO RTEP ID / TO ID Title MW Impact Percent Allocation Allocated Cost ($USD)
Load Flow EKPC n9175 / EKPC-tc1-r0022a Rebuild the AG1-354 TP-Summer Shade 161 kV line section (19.5 miles) using 556 MCM ACSS conductor. 126.9 MW 67.1% $22,160,563
Load Flow EKPC n8369 / EKPC-tc1-r0015a Replace the existing Marion County 161/138 kV, 200 MVA transformer with a 300 MVA transformer. 19.2 MW 41.7% $3,680,715
Load Flow EKPC n8368.2 / EKPC-tc1-r0012b Rebuild the Cooper-Elihu 161 kV line section using 795 MCM ACSS conductor (4.2 miles) 17.8 MW 41.6% $3,405,719
Load Flow EKPC n6834.1 / EKPC-tc1-r0001a Rebuild the 4/0 ACSR Green County-Summersville 69 kV line section (4.2 miles) using 556 MCM ACSR. 9.2 MW 44.6% $2,370,458
Load Flow EKPC n9174 / EKPC-tc1-r0019a Rebuild the Summer Shade EKPC-Summer Shade TVA 161 kV line (0.13 mile) using bundled 556 MCM ACSR conductor. 99.4 MW 72.6% $203,262
Load Flow EKPC n8364.1 / EKPC-tc1-r0009b Replace the 636 MCM ACSR conductor in the Marion County-KU Lebanon 138 kV line with 954 MCM ACSS conductor. 19.2 MW 37.5% $74,978
Load Flow LGEE (Pending) / LGEE_TC1_15527 Load shedding of 10% PC load is allowed for P2 contingency 19.2 MW 37.5% $0
Load Flow LGEE (Pending) / LGEE_TC1_15521 Load shedding of 10% PC load is allowed for P7 contingency 19.2 MW 14.0% $0
Grand Total: $31,895,695
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n9175 / EKPC-tc1-r0022a Rebuild the AG1-354 TP-Summer Shade 161 kV line section (19.5 miles) using 556 MCM ACSS conductor. $33,030,000 $22,160,563 30 to 36 Months

Contributor

Description: Rebuild the AG1-354 TP-Summer Shade 161 kV line section (19.5 miles) using 556 MCM ACSS conductor.

Flowgates Addressed by this Reinforcement
Facility Contingency
5SUMM SHADE-AG1-354 TP 161.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
5SUMM SHADE-AG1-354 TP 161.0 kV Ckt 1 line SUM A 325.0 MVA
5SUMM SHADE-AG1-354 TP 161.0 kV Ckt 1 line SUM B 360.0 MVA
5SUMM SHADE-AG1-354 TP 161.0 kV Ckt 1 line SUM C 369.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-353 62.2 MW 32.9% $10,869,437
AG1-354 126.9 MW 67.1% $22,160,563
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n8369 / EKPC-tc1-r0015a Replace the existing Marion County 161/138 kV, 200 MVA transformer with a 300 MVA transformer. $8,825,000 $3,680,715 Dec 31 2024

Contributor

Description: Replace the existing Marion County 161/69 kV, 200 MVA transformer with a 300 MVA transformer.

Flowgates Addressed by this Reinforcement
Facility Contingency
5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer SUM A 239.0 MVA
5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer SUM B 280.0 MVA
5MARION CO-4MARION CO 161.0/138.0 kV Ckt 1 transformer SUM C 295.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-353 26.8 MW 58.3% $5,144,285
AG1-354 19.2 MW 41.7% $3,680,715
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n8368.2 / EKPC-tc1-r0012b Rebuild the Cooper-Elihu 161 kV line section using 795 MCM ACSS conductor (4.2 miles) $8,195,000 $3,405,719 30 to 36 Months

Contributor

Description: Rebuild the Cooper-Elihu 161 kV line section using 795 MCM ACSS conductor (4.2 miles)

Flowgates Addressed by this Reinforcement
Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (All) A 308.0 MVA
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (All) B 373.0 MVA
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (All) C 373.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-353 12.9 MW 30.1% $2,469,443
AG1-354 17.8 MW 41.6% $3,405,719
AG1-471 12.1 MW 28.3% $2,319,838
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n6834.1 / EKPC-tc1-r0001a Rebuild the 4/0 ACSR Green County-Summersville 69 kV line section (4.2 miles) using 556 MCM ACSR. $5,320,000 $2,370,458 18 to 24 Months

Contributor

Description: Rebuild the 4/0 ACSR Green County-Summersville 69 kV line section (4.2 miles) using 556 MCM ACSR.

Flowgates Addressed by this Reinforcement
Facility Contingency
2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line SUM A 57.0 MVA
2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line SUM B 63.0 MVA
2GREEN CO-2SUMMERSVIL 69.0 kV Ckt 1 line SUM C 63.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-353 11.4 MW 55.4% $2,949,542
AG1-354 9.2 MW 44.6% $2,370,458
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n9174 / EKPC-tc1-r0019a Rebuild the Summer Shade EKPC-Summer Shade TVA 161 kV line (0.13 mile) using bundled 556 MCM ACSR conductor. $280,000 $203,262 24 to 30 Months

Contributor

Description: Rebuild the Summer Shade EKPC-Summer Shade TVA 161 kV line (0.13 mile) using bundled 556 MCM ACSR conductor.

Flowgates Addressed by this Reinforcement
Facility Contingency
5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line SUM A 244.0 MVA
5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line SUM B 298.0 MVA
5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line SUM C 312.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-353 37.5 MW 27.4% $76,738
AG1-354 99.4 MW 72.6% $203,262
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n8364.1 / EKPC-tc1-r0009b Replace the 636 MCM ACSR conductor in the Marion County-KU Lebanon 138 kV line with 954 MCM ACSS conductor. $200,000 $74,978 Dec 31 2024

Contributor

Description: Replace the 636 MCM ACSR conductor in the Marion County-KU Lebanon 138 kV line with 954 MCM ACSS conductor.

Flowgates Addressed by this Reinforcement
Facility Contingency
4LEBANON-4MARION CO 138.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
4LEBANON-4MARION CO 138.0 kV Ckt 1 line SUM A 202.0 MVA
4LEBANON-4MARION CO 138.0 kV Ckt 1 line SUM B 248.0 MVA
4LEBANON-4MARION CO 138.0 kV Ckt 1 line SUM C 248.0 MVA
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-353 26.8 MW 52.4% $104,791
AG1-354 19.2 MW 37.5% $74,978
AG1-471 5.2 MW 10.1% $20,232
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n5780.3 / EKPC-tc1-r0020b Replace the 1500A interconnection metering CTs at Spurlock Station with 2000A equipment. $1,235,000 $0 18 to 21 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AG1-354 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-354 could receive cost allocation. Although AG1-354 may not presently have cost responsibility for this upgrade, AG1-354 is a potential Aggregate Pool Contributor.

Description: Replace the 1500A interconnection metering CTs at Spurlock Station with 2000A equipment.

Flowgates Addressed by this Reinforcement
Facility Contingency
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
09STUART-7SPURLOCK 345.0 kV Ckt 1 line SUM A 1777.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line SUM B 1867.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line SUM C 1910.0 MVA
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow Dayton n5780.1 / DAYr190040 Replace Stuart substation riser conductor with 2500AAC (parallel) $300,000 $0 12 to 18 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AG1-354 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-354 could receive cost allocation. Although AG1-354 may not presently have cost responsibility for this upgrade, AG1-354 is a potential Aggregate Pool Contributor.

Description: Replace Stuart substation riser conductor with 2500AAC (parallel)

Flowgates Addressed by this Reinforcement
Facility Contingency
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) A 1561.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) B 1800.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) C 1800.0 MVA
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow Dayton n5780 / DAYr190039 Reconductor Stuart-Spurlock line with twin bundle 1033 Curlew ACCR conductor. $47,681,589 $0 36 to 48 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AG1-354 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-354 could receive cost allocation. Although AG1-354 may not presently have cost responsibility for this upgrade, AG1-354 is a potential Aggregate Pool Contributor.

Description: Reconductor Stuart-Spurlock line with twin bundle 1033 Curlew ACCR conductor.

Flowgates Addressed by this Reinforcement
Facility Contingency
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) A 1339.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) B 1556.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) C 1556.0 MVA
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow Dayton n5780.2 / DAYr190041 Reconductor Stuart substation conductor with twin bundle 1033 Curlew ACCR conductor Reconductor Stuart Substation conductor with a bundled 795 hi-temperature conductor. $650,000 $0 18 to 24 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AG1-354 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-354 could receive cost allocation. Although AG1-354 may not presently have cost responsibility for this upgrade, AG1-354 is a potential Aggregate Pool Contributor.

Description: Reconductor Stuart substation conductor with twin bundle 1033 Curlew ACCR conductor Reconductor Stuart Substation conductor with a bundled 795 hi-temperature conductor.

Flowgates Addressed by this Reinforcement
Facility Contingency
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) A 1882.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) B 2062.0 MVA
09STUART-7SPURLOCK 345.0 kV Ckt 1 line (All) C 1958.0 MVA
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow EKPC n7773.1 / EKPC-tc1-r0004b Change the 69 kV current transformer settings associated with circuit breaker S7-654 from 600A to at least 800A. $345,000 $0 9 to 12 Months

Contingent

Note: Based on PJM cost allocation criteria, AG1-354 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-354 could receive cost allocation. Although AG1-354 may not presently have cost responsibility for this upgrade, AG1-354 may need this upgrade in-service to be deliverable to the PJM system. If AG1-354 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: Change the 69 kV current transformer settings associated with circuit breaker S7-654 from 600A to at least 800A.

Flowgates Addressed by this Reinforcement
Facility Contingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (All) A 154.0 MVA
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (All) B 180.0 MVA
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (All) C 185.0 MVA
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow LGEE (Pending) / LGEE_TC1_15519 Invalid - P7 contingency 69kV not monitored by LGEE $0 $0 TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Description: Invalid - P7 contingency 69kV not monitored by LGEE

Flowgates Addressed by this Reinforcement
Facility Contingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (Any)
2SOMERSET-2SOMERSET KU 69.0 kV Ckt 1 line (Any)
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow LGEE (Pending) / LGEE_TC1_15527 Load shedding of 10% PC load is allowed for P2 contingency $0 $0 TBD

Contributor

Description: Load shedding of 10% PC load is allowed for P2 contingency

Flowgates Addressed by this Reinforcement
Facility Contingency
4LEBANON-4MARION CO 138.0 kV Ckt 1 line (Any)
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow LGEE (Pending) / LGEE_TC1_15521 Load shedding of 10% PC load is allowed for P7 contingency $0 $0 TBD

Contributor

Description: Load shedding of 10% PC load is allowed for P7 contingency

Flowgates Addressed by this Reinforcement
Facility Contingency
4LEBANON-4MARION CO 138.0 kV Ckt 1 line (Any)
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow LGEE (Pending) / LGEE_TC1_15510 Upgrade terminal equipment at Elihu 161kV associated with the Elihu-Cooper (EKPC) 161kV line to a minimum SE rating of 1200 amps. $300,000 $0 TBD

Contingent

Note: Based on PJM cost allocation criteria, AG1-354 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-354 could receive cost allocation. Although AG1-354 may not presently have cost responsibility for this upgrade, AG1-354 may need this upgrade in-service to be deliverable to the PJM system. If AG1-354 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Description: Upgrade terminal equipment at Elihu 161kV associated with the Elihu-Cooper (EKPC) 161kV line to a minimum SE rating of 1200 amps.

Flowgates Addressed by this Reinforcement
Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
5ELIHU-5COOPER2 161.0 kV Ckt 1 line SUM A 267.0 MVA
5ELIHU-5COOPER2 161.0 kV Ckt 1 line SUM B 335.0 MVA
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow LGEE (Pending) / LGEE_TC1_15524 Load shedding of 10% PC load is allowed for P7 contingency $0 $0 TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Description: Load shedding of 10% PC load is allowed for P7 contingency

Flowgates Addressed by this Reinforcement
Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow LGEE (Pending) / LGEE_TC1_15525 Load shedding of 10% PC load is allowed for P4 contingency $0 $0 TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Description: Load shedding of 10% PC load is allowed for P4 contingency

Flowgates Addressed by this Reinforcement
Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)
System Reinforcement
Type TO RTEP ID / TO ID Title Total Cost ($USD) Allocated Cost ($USD) Time Estimate
Load Flow TVA (Pending) / TVA_TC1_15534 Replace breaker 924 and 944, switches 929, 943, 945, 947, 949 , 923 and 925, and line CT to a minimum of 2,000 amps. $8,200,000 $0 TBD

Info

Note: AG1-354 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.

Description: Replace breaker 924 and 944, switches 929, 943, 945, 947, 949 , 923 and 925, and line CT to a minimum of 2,000 amps. Replace pulloff, stinger, breaker leads, and jumper to the metering CT to a minimum of 2,000 amps.

Flowgates Addressed by this Reinforcement
Facility Contingency
5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line EKPC_P7-1_BULL 161 DBL_SRT-A
New Ratings
Facility Rating Set Rating Type Rating Value
5SUMM SHADE-5SUMMER SHAD 161.0 kV Ckt 1 line (All) B 557.7 MVA

Attachments


[1]Winter load flow analysis will be performed starting in Transition Cycle #2.