AE2-283 Phase III Study Report

v1.00 released 2025-09-18 16:23

Gladys-Stone Mill 69 kV

28.0 MW Capacity / 53.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Gladys Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (Dominion Virginia Power).

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $5,545,402 $20,494,619 = 0.27 AND ( $5,545,402 - $20,494,619 ) 53.0 = $-282,061 per MW

General

The Project Developer has proposed a Solar generating facility located in the Virginia Electric and Power Company (Dominion Virginia Power) zone — Campbell County, Virginia. The installed facilities will have a total capability of 53.0 MW with 28.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AE2-283
Project Name:
Gladys-Stone Mill 69 kV
Project Developer Name:
Gladys Solar, LLC
State:
Virginia
County:
Campbell
Transmission Owner:
Virginia Electric and Power Company (Dominion Virginia Power)
MFO:
53.0
MWE:
53.0
MWC:
28.0
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AE2-283 “Gladys-Stone Mill 69 kV” will interconnect with the Dominion’s transmission system through a new single breaker 69 kV switching station tapped off the Gladys to Stone Mill 69 kV line. 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AE2-283 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AE2-283 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $8,300,735 $8,300,735
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $3,617,755 $3,617,755
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $1,927,121 $1,927,121
Transient Stability $0 $0
Short Circuit $526 $526
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $13,846,137 $13,846,137

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AE2-283

Security has been calculated for the AE2-283 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AE2-283
Project(s): AE2-283
Final Agreement Security (A): $13,846,137
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $13,846,137
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The New Service Request Project will interconnect with the Dominion transmission system by tapping the Gladys-Stone Mill 69 kV Line 35. The required work for the interconnection of the New Service Request Project to the Dominion Transmission System is detailed in the following tables.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9429.0

Re-arrange line #35 to loop into and out of the new AE2-283 single breaker 69 kV tap

$2,095,134 $1,088,327 $201,664 $136,420 $3,521,545 $3,521,545
n9323.0

Remote Relay at Stone Mill Substation.

$144,634 $99,161 $27,348 $17,487 $288,630 $96,210 (See Note 1)
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Build a new 69 kV single breaker tap located along VEPCO’s existing 69 kV #35 line from Gladys DP to Stone Mill Substation and terminate generator lead line.

$4,163,093 $2,829,319 $1,037,413 $270,910 $8,300,735 $8,300,735

Based on the scope of work for the Interconnection Facilities, it is expected to take 39 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

 

Transmission Owner Analysis

PJM performed a power flow analysis of the transmission system using a 2027 load flow model and the results were verified by Dominion.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here. Refer to AE2-283 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request was evaluated as a 53.0 MW (28.0 MW Capacity) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Base Case Single AC 134.44 % 167.0 A 224.51 9.71
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Base Case Single AC 133.11 % 167.0 A 222.29 9.71
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Base Case Single AC 130.98 % 167.0 A 218.73 9.71
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Single AC 133.79 % 245.0 B 327.79 9.52
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Single AC 132.82 % 245.0 B 325.42 9.52
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Single AC 131.31 % 245.0 B 321.72 9.52
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
AEP_P1-2_#311_5_SRT-A
CONTINGENCY 'AEP_P1-2_#311_5_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242514 CKT 1   /*05CLOVRD     765.0 - 05J.FERR     765.0
END
Single AC 114.52 % 245.0 B 280.57 9.59
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
AEP_P1-2_#311_5_SRT-A
CONTINGENCY 'AEP_P1-2_#311_5_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242514 CKT 1   /*05CLOVRD     765.0 - 05J.FERR     765.0
END
Single AC 113.58 % 245.0 B 278.27 9.59
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
AEP_P1-2_#311_5_SRT-A
CONTINGENCY 'AEP_P1-2_#311_5_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242514 CKT 1   /*05CLOVRD     765.0 - 05J.FERR     765.0
END
Single AC 112.09 % 245.0 B 274.63 9.59
DVP 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 126.69 % 559.3 B 708.6 1.52
DVP 6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 125.44 % 571.52 B 716.93 1.52
DVP 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Single AC 101.96 % 101.52 B 103.51 28.0

Details for 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 134.44 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 224.51 MVA
MW Contribution: 9.71 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 103.76 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 173.28 MVA
MW Contribution: 9.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.76 MW 1.76 MW
315156 1HALLBR1 80/20 2.68 MW 2.68 MW
942671 AE2-283 C 80/20 9.71 MW 9.71 MW
942751 AE2-291 C 80/20 12.86 MW 12.86 MW
960061 AF2-297 C 80/20 3.03 MW 3.03 MW
315266 1PLYWOOD A 80/20 0.42 MW 0.42 MW
316118 AC1-105 C 80/20 0.31 MW 0.31 MW
940081 AE1-250 C 80/20 5.18 MW 5.18 MW
941801 AE2-185 C 80/20 12.48 MW 12.48 MW
941821 AE2-187 C 80/20 12.48 MW 12.48 MW
246843 05SMG1 80/20 1.06 MW 1.06 MW
246844 05SMG2 80/20 2.92 MW 2.92 MW
246845 05SMG3 80/20 1.79 MW 1.79 MW
246846 05SMG4 80/20 2.92 MW 2.92 MW
246847 05SMG5 80/20 1.11 MW 1.11 MW
316003 AC1-222 C 80/20 0.56 MW 0.56 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.08 MW 1.08 MW
270197 AC1-083 C 80/20 0.56 MW 0.56 MW
316197 AC1-042 C 80/20 0.9 MW 0.9 MW
316123 AC1-075 C 80/20 1.13 MW 1.13 MW
316205 AC1-080 C 80/20 0.38 MW 0.38 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.54 MW 0.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.98 MW 7.98 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.11 MW 1.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.22 MW 0.22 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.11 MW 0.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.31 MW 0.31 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.53 MW 0.53 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW

Details for 05OTTER-05JOHNMT 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 133.11 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 222.29 MVA
MW Contribution: 9.71 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 102.51 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 171.18 MVA
MW Contribution: 9.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.76 MW 1.76 MW
315156 1HALLBR1 80/20 2.68 MW 2.68 MW
942671 AE2-283 C 80/20 9.71 MW 9.71 MW
942751 AE2-291 C 80/20 12.86 MW 12.86 MW
960061 AF2-297 C 80/20 3.03 MW 3.03 MW
315266 1PLYWOOD A 80/20 0.42 MW 0.42 MW
316118 AC1-105 C 80/20 0.31 MW 0.31 MW
940081 AE1-250 C 80/20 5.18 MW 5.18 MW
941801 AE2-185 C 80/20 12.48 MW 12.48 MW
941821 AE2-187 C 80/20 12.48 MW 12.48 MW
246843 05SMG1 80/20 1.06 MW 1.06 MW
246844 05SMG2 80/20 2.92 MW 2.92 MW
246845 05SMG3 80/20 1.79 MW 1.79 MW
246846 05SMG4 80/20 2.92 MW 2.92 MW
246847 05SMG5 80/20 1.11 MW 1.11 MW
316003 AC1-222 C 80/20 0.56 MW 0.56 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.08 MW 1.08 MW
270197 AC1-083 C 80/20 0.56 MW 0.56 MW
316197 AC1-042 C 80/20 0.9 MW 0.9 MW
316123 AC1-075 C 80/20 1.13 MW 1.13 MW
316205 AC1-080 C 80/20 0.38 MW 0.38 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.54 MW 0.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.98 MW 7.98 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.11 MW 1.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.22 MW 0.22 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.11 MW 0.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.31 MW 0.31 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.53 MW 0.53 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW

Details for 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 130.98 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 218.73 MVA
MW Contribution: 9.71 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 100.46 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 167.76 MVA
MW Contribution: 9.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.76 MW 1.76 MW
315156 1HALLBR1 80/20 2.68 MW 2.68 MW
942671 AE2-283 C 80/20 9.71 MW 9.71 MW
942751 AE2-291 C 80/20 12.86 MW 12.86 MW
960061 AF2-297 C 80/20 3.03 MW 3.03 MW
315266 1PLYWOOD A 80/20 0.42 MW 0.42 MW
316118 AC1-105 C 80/20 0.31 MW 0.31 MW
940081 AE1-250 C 80/20 5.18 MW 5.18 MW
941801 AE2-185 C 80/20 12.48 MW 12.48 MW
941821 AE2-187 C 80/20 12.48 MW 12.48 MW
246843 05SMG1 80/20 1.06 MW 1.06 MW
246844 05SMG2 80/20 2.92 MW 2.92 MW
246845 05SMG3 80/20 1.79 MW 1.79 MW
246846 05SMG4 80/20 2.92 MW 2.92 MW
246847 05SMG5 80/20 1.11 MW 1.11 MW
316003 AC1-222 C 80/20 0.56 MW 0.56 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.08 MW 1.08 MW
270197 AC1-083 C 80/20 0.56 MW 0.56 MW
316197 AC1-042 C 80/20 0.9 MW 0.9 MW
316123 AC1-075 C 80/20 1.13 MW 1.13 MW
316205 AC1-080 C 80/20 0.38 MW 0.38 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.54 MW 0.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.98 MW 7.98 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.11 MW 1.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.22 MW 0.22 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.11 MW 0.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.31 MW 0.31 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.53 MW 0.53 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW

Details for 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 133.79 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 327.79 MVA
MW Contribution: 9.52 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.73 MW 1.73 MW
315156 1HALLBR1 80/20 2.62 MW 2.62 MW
942671 AE2-283 C 80/20 9.52 MW 9.52 MW
942751 AE2-291 C 80/20 12.56 MW 12.56 MW
960061 AF2-297 C 80/20 2.93 MW 2.93 MW
315266 1PLYWOOD A 80/20 0.4 MW 0.4 MW
316118 AC1-105 C 80/20 0.3 MW 0.3 MW
940081 AE1-250 C 80/20 5.19 MW 5.19 MW
941801 AE2-185 C 80/20 12.24 MW 12.24 MW
941821 AE2-187 C 80/20 12.24 MW 12.24 MW
246843 05SMG1 80/20 1.04 MW 1.04 MW
246844 05SMG2 80/20 2.86 MW 2.86 MW
246845 05SMG3 80/20 1.76 MW 1.76 MW
246846 05SMG4 80/20 2.86 MW 2.86 MW
246847 05SMG5 80/20 1.09 MW 1.09 MW
316003 AC1-222 C 80/20 0.55 MW 0.55 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.06 MW 1.06 MW
270197 AC1-083 C 80/20 0.56 MW 0.56 MW
316197 AC1-042 C 80/20 0.89 MW 0.89 MW
316123 AC1-075 C 80/20 1.1 MW 1.1 MW
316205 AC1-080 C 80/20 0.37 MW 0.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.34 MW 4.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.79 MW 2.79 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.59 MW 10.59 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.17 MW 0.17 MW
WEC LTFEXP_WEC->PJM CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 05OTTER-05JOHNMT 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 132.82 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 325.42 MVA
MW Contribution: 9.52 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.73 MW 1.73 MW
315156 1HALLBR1 80/20 2.62 MW 2.62 MW
942671 AE2-283 C 80/20 9.52 MW 9.52 MW
942751 AE2-291 C 80/20 12.56 MW 12.56 MW
960061 AF2-297 C 80/20 2.93 MW 2.93 MW
315266 1PLYWOOD A 80/20 0.4 MW 0.4 MW
316118 AC1-105 C 80/20 0.3 MW 0.3 MW
940081 AE1-250 C 80/20 5.19 MW 5.19 MW
941801 AE2-185 C 80/20 12.24 MW 12.24 MW
941821 AE2-187 C 80/20 12.24 MW 12.24 MW
246843 05SMG1 80/20 1.04 MW 1.04 MW
246844 05SMG2 80/20 2.86 MW 2.86 MW
246845 05SMG3 80/20 1.76 MW 1.76 MW
246846 05SMG4 80/20 2.86 MW 2.86 MW
246847 05SMG5 80/20 1.09 MW 1.09 MW
316003 AC1-222 C 80/20 0.55 MW 0.55 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.06 MW 1.06 MW
270197 AC1-083 C 80/20 0.56 MW 0.56 MW
316197 AC1-042 C 80/20 0.89 MW 0.89 MW
316123 AC1-075 C 80/20 1.1 MW 1.1 MW
316205 AC1-080 C 80/20 0.37 MW 0.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.34 MW 4.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.79 MW 2.79 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.59 MW 10.59 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.17 MW 0.17 MW
WEC LTFEXP_WEC->PJM CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 131.31 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 321.72 MVA
MW Contribution: 9.52 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.73 MW 1.73 MW
315156 1HALLBR1 80/20 2.62 MW 2.62 MW
942671 AE2-283 C 80/20 9.52 MW 9.52 MW
942751 AE2-291 C 80/20 12.56 MW 12.56 MW
960061 AF2-297 C 80/20 2.93 MW 2.93 MW
315266 1PLYWOOD A 80/20 0.4 MW 0.4 MW
316118 AC1-105 C 80/20 0.3 MW 0.3 MW
940081 AE1-250 C 80/20 5.19 MW 5.19 MW
941801 AE2-185 C 80/20 12.24 MW 12.24 MW
941821 AE2-187 C 80/20 12.24 MW 12.24 MW
246843 05SMG1 80/20 1.04 MW 1.04 MW
246844 05SMG2 80/20 2.86 MW 2.86 MW
246845 05SMG3 80/20 1.76 MW 1.76 MW
246846 05SMG4 80/20 2.86 MW 2.86 MW
246847 05SMG5 80/20 1.09 MW 1.09 MW
316003 AC1-222 C 80/20 0.55 MW 0.55 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.06 MW 1.06 MW
270197 AC1-083 C 80/20 0.56 MW 0.56 MW
316197 AC1-042 C 80/20 0.89 MW 0.89 MW
316123 AC1-075 C 80/20 1.1 MW 1.1 MW
316205 AC1-080 C 80/20 0.37 MW 0.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.34 MW 4.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.79 MW 2.79 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.59 MW 10.59 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.17 MW 0.17 MW
WEC LTFEXP_WEC->PJM CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line l/o AEP_P1-2_#311_5_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
AEP_P1-2_#311_5_SRT-A
CONTINGENCY 'AEP_P1-2_#311_5_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242514 CKT 1   /*05CLOVRD     765.0 - 05J.FERR     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 114.52 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 280.57 MVA
MW Contribution: 9.59 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.73 MW 1.73 MW
315156 1HALLBR1 80/20 2.64 MW 2.64 MW
942671 AE2-283 C 80/20 9.59 MW 9.59 MW
942751 AE2-291 C 80/20 12.66 MW 12.66 MW
960061 AF2-297 C 80/20 2.96 MW 2.96 MW
315266 1PLYWOOD A 80/20 0.41 MW 0.41 MW
316118 AC1-105 C 80/20 0.3 MW 0.3 MW
940081 AE1-250 C 80/20 5.06 MW 5.06 MW
941801 AE2-185 C 80/20 12.33 MW 12.33 MW
941821 AE2-187 C 80/20 12.33 MW 12.33 MW
246843 05SMG1 80/20 1.02 MW 1.02 MW
246844 05SMG2 80/20 2.8 MW 2.8 MW
246845 05SMG3 80/20 1.72 MW 1.72 MW
246846 05SMG4 80/20 2.8 MW 2.8 MW
246847 05SMG5 80/20 1.06 MW 1.06 MW
316003 AC1-222 C 80/20 0.55 MW 0.55 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.06 MW 1.06 MW
270197 AC1-083 C 80/20 0.55 MW 0.55 MW
316197 AC1-042 C 80/20 0.89 MW 0.89 MW
316123 AC1-075 C 80/20 1.11 MW 1.11 MW
316205 AC1-080 C 80/20 0.37 MW 0.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.92 MW 2.92 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.25 MW 2.25 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.13 MW 10.13 MW
NY PJM->LTFIMP_NY CLTF 0.15 MW 0.15 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.2 MW 1.2 MW
TVA LTFEXP_TVA->PJM CLTF 0.63 MW 0.63 MW
MEC LTFEXP_MEC->PJM CLTF 0.38 MW 0.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.79 MW 0.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.02 MW 0.02 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.57 MW 0.57 MW

Details for 05OTTER-05JOHNMT 138.0 kV Ckt 1 line l/o AEP_P1-2_#311_5_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
AEP_P1-2_#311_5_SRT-A
CONTINGENCY 'AEP_P1-2_#311_5_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242514 CKT 1   /*05CLOVRD     765.0 - 05J.FERR     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 113.58 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 278.27 MVA
MW Contribution: 9.59 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.73 MW 1.73 MW
315156 1HALLBR1 80/20 2.64 MW 2.64 MW
942671 AE2-283 C 80/20 9.59 MW 9.59 MW
942751 AE2-291 C 80/20 12.66 MW 12.66 MW
960061 AF2-297 C 80/20 2.96 MW 2.96 MW
315266 1PLYWOOD A 80/20 0.41 MW 0.41 MW
316118 AC1-105 C 80/20 0.3 MW 0.3 MW
940081 AE1-250 C 80/20 5.06 MW 5.06 MW
941801 AE2-185 C 80/20 12.33 MW 12.33 MW
941821 AE2-187 C 80/20 12.33 MW 12.33 MW
246843 05SMG1 80/20 1.02 MW 1.02 MW
246844 05SMG2 80/20 2.8 MW 2.8 MW
246845 05SMG3 80/20 1.72 MW 1.72 MW
246846 05SMG4 80/20 2.8 MW 2.8 MW
246847 05SMG5 80/20 1.06 MW 1.06 MW
316003 AC1-222 C 80/20 0.55 MW 0.55 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.06 MW 1.06 MW
270197 AC1-083 C 80/20 0.55 MW 0.55 MW
316197 AC1-042 C 80/20 0.89 MW 0.89 MW
316123 AC1-075 C 80/20 1.11 MW 1.11 MW
316205 AC1-080 C 80/20 0.37 MW 0.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.92 MW 2.92 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.25 MW 2.25 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.13 MW 10.13 MW
NY PJM->LTFIMP_NY CLTF 0.15 MW 0.15 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.2 MW 1.2 MW
TVA LTFEXP_TVA->PJM CLTF 0.63 MW 0.63 MW
MEC LTFEXP_MEC->PJM CLTF 0.38 MW 0.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.79 MW 0.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.02 MW 0.02 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.57 MW 0.57 MW

Details for 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line l/o AEP_P1-2_#311_5_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
AEP_P1-2_#311_5_SRT-A
CONTINGENCY 'AEP_P1-2_#311_5_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242514 CKT 1   /*05CLOVRD     765.0 - 05J.FERR     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 112.09 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 274.63 MVA
MW Contribution: 9.59 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 80/20 1.73 MW 1.73 MW
315156 1HALLBR1 80/20 2.64 MW 2.64 MW
942671 AE2-283 C 80/20 9.59 MW 9.59 MW
942751 AE2-291 C 80/20 12.66 MW 12.66 MW
960061 AF2-297 C 80/20 2.96 MW 2.96 MW
315266 1PLYWOOD A 80/20 0.41 MW 0.41 MW
316118 AC1-105 C 80/20 0.3 MW 0.3 MW
940081 AE1-250 C 80/20 5.06 MW 5.06 MW
941801 AE2-185 C 80/20 12.33 MW 12.33 MW
941821 AE2-187 C 80/20 12.33 MW 12.33 MW
246843 05SMG1 80/20 1.02 MW 1.02 MW
246844 05SMG2 80/20 2.8 MW 2.8 MW
246845 05SMG3 80/20 1.72 MW 1.72 MW
246846 05SMG4 80/20 2.8 MW 2.8 MW
246847 05SMG5 80/20 1.06 MW 1.06 MW
316003 AC1-222 C 80/20 0.55 MW 0.55 MW
316248 AF1-058 C 80/20 0.12 MW 0.12 MW
316217 AC1-145 C 80/20 1.06 MW 1.06 MW
270197 AC1-083 C 80/20 0.55 MW 0.55 MW
316197 AC1-042 C 80/20 0.89 MW 0.89 MW
316123 AC1-075 C 80/20 1.11 MW 1.11 MW
316205 AC1-080 C 80/20 0.37 MW 0.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.92 MW 2.92 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.25 MW 2.25 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.13 MW 10.13 MW
NY PJM->LTFIMP_NY CLTF 0.15 MW 0.15 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.12 MW 0.12 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.2 MW 1.2 MW
TVA LTFEXP_TVA->PJM CLTF 0.63 MW 0.63 MW
MEC LTFEXP_MEC->PJM CLTF 0.38 MW 0.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.79 MW 0.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.02 MW 0.02 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.57 MW 0.57 MW

Details for 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 556_SRT-S-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 126.69 %
Rating: 559.3 MVA
Rating Type: B
MVA to Mitigate: 708.6 MVA
MW Contribution: 1.52 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 133.47 %
Rating: 559.3 MVA
Rating Type: B
MVA to Mitigate: 746.52 MVA
MW Contribution: 1.63 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 4.68 MW 4.68 MW
963171 AG1-166 C 80/20 2.6 MW 2.6 MW
963181 AG1-167 C 80/20 1.95 MW 1.95 MW
963191 AG1-168 C 80/20 1.95 MW 1.95 MW
964791 AG1-342 C 80/20 5.54 MW 5.54 MW
966811 AG1-552 C 80/20 1.03 MW 1.03 MW
965291 AG1-394 C 80/20 0.26 MW 0.26 MW
966621 AG1-532 C 80/20 0.71 MW 0.71 MW
313506 AB1-173 C OP 80/20 0.57 MW 0.57 MW
313853 3PONTONDP 80/20 1.73 MW 1.73 MW
314429 3JTRSVLE 80/20 1.08 MW 1.08 MW
314704 3LAWRENC 80/20 0.27 MW 0.27 MW
315126 1ROARAP2 80/20 0.69 MW 0.69 MW
315128 1ROARAP4 80/20 0.66 MW 0.66 MW
315136 1ROSEMG1 80/20 0.62 MW 0.62 MW
315137 1ROSEMS1 80/20 0.39 MW 0.39 MW
315138 1ROSEMG2 80/20 0.29 MW 0.29 MW
315139 1GASTONA 80/20 0.93 MW 0.93 MW
315153 1CLOVER1 80/20 22.48 MW 22.48 MW
315154 1CLOVER2 80/20 22.27 MW 22.27 MW
315156 1HALLBR1 80/20 0.56 MW 0.56 MW
315158 1KERR 1 80/20 0.56 MW 0.56 MW
315159 1KERR 2 80/20 1.56 MW 1.56 MW
315160 1KERR 3 80/20 1.56 MW 1.56 MW
315161 1KERR 4 80/20 1.56 MW 1.56 MW
315162 1KERR 5 80/20 1.56 MW 1.56 MW
942671 AE2-283 C 80/20 1.52 MW 1.52 MW
942751 AE2-291 C 80/20 8.13 MW 8.13 MW
959311 AF2-222 C 80/20 38.9 MW 38.9 MW
960061 AF2-297 C 80/20 11.02 MW 11.02 MW
960081 AF2-299 C 80/20 0.95 MW 0.95 MW
315163 1KERR 6 80/20 1.56 MW 1.56 MW
315164 1KERR 7 80/20 1.56 MW 1.56 MW
315266 1PLYWOOD A 80/20 1.75 MW 1.75 MW
315606 3AA2-053SOLA 80/20 0.69 MW 0.69 MW
316118 AC1-105 C 80/20 1.37 MW 1.37 MW
316129 AC1-054 C 80/20 1.19 MW 1.19 MW
316131 AB2-060 C 80/20 2.66 MW 2.66 MW
938371 AE1-056 C 80/20 17.9 MW 17.9 MW
939181 AE1-148 C 80/20 12.97 MW 12.97 MW
941011 AE2-092 C Adder -9.7 MW -8.25 MW
941801 AE2-185 C 80/20 1.96 MW 1.96 MW
941821 AE2-187 C 80/20 1.96 MW 1.96 MW
946281 AF1-292 C 80/20 0.78 MW 0.78 MW
946301 AF1-294 C 80/20 9.61 MW 9.61 MW
957481 AF2-042 C 80/20 98.02 MW 98.02 MW
958211 AF2-115 C 80/20 5.85 MW 5.85 MW
315141 1GASTONB 80/20 0.93 MW 0.93 MW
315607 3AA1-063SOLA 80/20 0.59 MW 0.59 MW
926071 AC1-086 C 80/20 6.39 MW 6.39 MW
936261 AD2-033 C 80/20 27.66 MW 27.66 MW
934621 AD1-088 C 80/20 24.98 MW 24.98 MW
962571 AG1-106 C 80/20 0.83 MW 0.83 MW
316003 AC1-222 C 80/20 1.35 MW 1.35 MW
316011 AB1-132 C OP 80/20 0.71 MW 0.71 MW
316034 AC1-036 C 80/20 0.54 MW 0.54 MW
316210 AC1-098 C 80/20 0.38 MW 0.38 MW
316212 AC1-099 C 80/20 0.13 MW 0.13 MW
316222 AC1-221 C 80/20 1.58 MW 1.58 MW
316237 AB2-079 C O1 80/20 0.57 MW 0.57 MW
316238 AB2-078 C O1 80/20 0.57 MW 0.57 MW
316239 AB2-077 C O1 80/20 0.57 MW 0.57 MW
316248 AF1-058 C 80/20 0.45 MW 0.45 MW
316274 AC1-208 C 80/20 3.98 MW 3.98 MW
316283 AC2-100 C 80/20 1.23 MW 1.23 MW
316317 KELFORD C 80/20 0.11 MW 0.11 MW
316319 Z2-044 C 80/20 0.09 MW 0.09 MW
316336 AC2-165 C Adder -5.87 MW -4.99 MW
316217 AC1-145 C 80/20 0.17 MW 0.17 MW
316327 AA2-057 C 80/20 0.57 MW 0.57 MW
316181 AB2-040 GEN 80/20 0.64 MW 0.64 MW
313527 AB2-043 C 80/20 0.91 MW 0.91 MW
316087 AB2-174 C 80/20 0.59 MW 0.59 MW
316197 AC1-042 C 80/20 0.14 MW 0.14 MW
316123 AC1-075 C 80/20 0.95 MW 0.95 MW
316205 AC1-080 C 80/20 0.32 MW 0.32 MW
962491 AG1-098 C 80/20 22.91 MW 22.91 MW
962561 AG1-105 C 80/20 14.17 MW 14.17 MW
964241 AG1-285 C 80/20 25.14 MW 25.14 MW
313764 3SOCKMAN 80/20 0.36 MW 0.36 MW
932631 AC2-084 C 80/20 0.4 MW 0.4 MW
934321 AD1-056 C 80/20 1.95 MW 1.95 MW
934331 AD1-057 C 80/20 1.09 MW 1.09 MW
934611 AD1-087 C 80/20 2.21 MW 2.21 MW
935171 AD1-152 C 80/20 2.15 MW 2.15 MW
936161 AD2-022 C 80/20 3.6 MW 3.6 MW
936171 AD2-023 C 80/20 2.1 MW 2.1 MW
937481 AD2-202 C 80/20 0.64 MW 0.64 MW
938821 AE1-108 C Adder -10.59 MW -9.0 MW
942461 AE2-259 C 80/20 31.14 MW 31.14 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 9.0 MW 9.0 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.03 MW 7.03 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 34.86 MW 34.86 MW
NY PJM->LTFIMP_NY CLTF 0.37 MW 0.37 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.35 MW 0.35 MW
WEC LTFEXP_WEC->PJM CLTF 0.19 MW 0.19 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.4 MW 4.4 MW
TVA LTFEXP_TVA->PJM CLTF 1.94 MW 1.94 MW
MEC LTFEXP_MEC->PJM CLTF 1.18 MW 1.18 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.49 MW 2.49 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.1 MW 2.1 MW

Details for 6BUCKING-6BREMO 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 556_SRT-S-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 125.44 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 716.93 MVA
MW Contribution: 1.52 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 130.87 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 747.95 MVA
MW Contribution: 1.63 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 4.68 MW 4.68 MW
963171 AG1-166 C 80/20 2.6 MW 2.6 MW
963181 AG1-167 C 80/20 1.95 MW 1.95 MW
963191 AG1-168 C 80/20 1.95 MW 1.95 MW
964791 AG1-342 C 80/20 5.54 MW 5.54 MW
966811 AG1-552 C 80/20 1.03 MW 1.03 MW
965291 AG1-394 C 80/20 0.26 MW 0.26 MW
966621 AG1-532 C 80/20 0.71 MW 0.71 MW
313506 AB1-173 C OP 80/20 0.57 MW 0.57 MW
313853 3PONTONDP 80/20 1.73 MW 1.73 MW
314429 3JTRSVLE 80/20 1.08 MW 1.08 MW
314704 3LAWRENC 80/20 0.27 MW 0.27 MW
315126 1ROARAP2 80/20 0.69 MW 0.69 MW
315128 1ROARAP4 80/20 0.66 MW 0.66 MW
315136 1ROSEMG1 80/20 0.62 MW 0.62 MW
315137 1ROSEMS1 80/20 0.39 MW 0.39 MW
315138 1ROSEMG2 80/20 0.29 MW 0.29 MW
315139 1GASTONA 80/20 0.93 MW 0.93 MW
315153 1CLOVER1 80/20 22.47 MW 22.47 MW
315154 1CLOVER2 80/20 22.26 MW 22.26 MW
315156 1HALLBR1 80/20 0.56 MW 0.56 MW
315158 1KERR 1 80/20 0.56 MW 0.56 MW
315159 1KERR 2 80/20 1.56 MW 1.56 MW
315160 1KERR 3 80/20 1.56 MW 1.56 MW
315161 1KERR 4 80/20 1.56 MW 1.56 MW
315162 1KERR 5 80/20 1.56 MW 1.56 MW
942671 AE2-283 C 80/20 1.52 MW 1.52 MW
942751 AE2-291 C 80/20 8.12 MW 8.12 MW
959311 AF2-222 C 80/20 38.89 MW 38.89 MW
960061 AF2-297 C 80/20 11.01 MW 11.01 MW
960081 AF2-299 C 80/20 0.95 MW 0.95 MW
315163 1KERR 6 80/20 1.56 MW 1.56 MW
315164 1KERR 7 80/20 1.56 MW 1.56 MW
315266 1PLYWOOD A 80/20 1.75 MW 1.75 MW
315606 3AA2-053SOLA 80/20 0.69 MW 0.69 MW
316118 AC1-105 C 80/20 1.37 MW 1.37 MW
316129 AC1-054 C 80/20 1.19 MW 1.19 MW
316131 AB2-060 C 80/20 2.66 MW 2.66 MW
938371 AE1-056 C 80/20 17.9 MW 17.9 MW
939181 AE1-148 C 80/20 12.96 MW 12.96 MW
941011 AE2-092 C Adder -9.71 MW -8.25 MW
941801 AE2-185 C 80/20 1.95 MW 1.95 MW
941821 AE2-187 C 80/20 1.95 MW 1.95 MW
946281 AF1-292 C 80/20 0.78 MW 0.78 MW
946301 AF1-294 C 80/20 9.61 MW 9.61 MW
957481 AF2-042 C 80/20 98.0 MW 98.0 MW
958211 AF2-115 C 80/20 5.84 MW 5.84 MW
315141 1GASTONB 80/20 0.93 MW 0.93 MW
315607 3AA1-063SOLA 80/20 0.59 MW 0.59 MW
926071 AC1-086 C 80/20 6.39 MW 6.39 MW
936261 AD2-033 C 80/20 27.66 MW 27.66 MW
934621 AD1-088 C 80/20 24.98 MW 24.98 MW
962571 AG1-106 C 80/20 0.83 MW 0.83 MW
316003 AC1-222 C 80/20 1.35 MW 1.35 MW
316011 AB1-132 C OP 80/20 0.71 MW 0.71 MW
316034 AC1-036 C 80/20 0.53 MW 0.53 MW
316210 AC1-098 C 80/20 0.38 MW 0.38 MW
316212 AC1-099 C 80/20 0.13 MW 0.13 MW
316222 AC1-221 C 80/20 1.58 MW 1.58 MW
316237 AB2-079 C O1 80/20 0.57 MW 0.57 MW
316238 AB2-078 C O1 80/20 0.57 MW 0.57 MW
316239 AB2-077 C O1 80/20 0.57 MW 0.57 MW
316248 AF1-058 C 80/20 0.45 MW 0.45 MW
316274 AC1-208 C 80/20 3.98 MW 3.98 MW
316283 AC2-100 C 80/20 1.23 MW 1.23 MW
316317 KELFORD C 80/20 0.11 MW 0.11 MW
316319 Z2-044 C 80/20 0.09 MW 0.09 MW
316322 AB2-045 C 80/20 1.29 MW 1.29 MW
316336 AC2-165 C Adder -5.88 MW -5.0 MW
316217 AC1-145 C 80/20 0.17 MW 0.17 MW
316327 AA2-057 C 80/20 0.57 MW 0.57 MW
316181 AB2-040 GEN 80/20 0.64 MW 0.64 MW
313527 AB2-043 C 80/20 0.91 MW 0.91 MW
316087 AB2-174 C 80/20 0.59 MW 0.59 MW
316197 AC1-042 C 80/20 0.14 MW 0.14 MW
316123 AC1-075 C 80/20 0.95 MW 0.95 MW
316205 AC1-080 C 80/20 0.32 MW 0.32 MW
962491 AG1-098 C 80/20 22.9 MW 22.9 MW
962561 AG1-105 C 80/20 14.16 MW 14.16 MW
964241 AG1-285 C 80/20 25.14 MW 25.14 MW
313764 3SOCKMAN 80/20 0.36 MW 0.36 MW
932631 AC2-084 C 80/20 0.4 MW 0.4 MW
934321 AD1-056 C 80/20 1.95 MW 1.95 MW
934331 AD1-057 C 80/20 1.09 MW 1.09 MW
934611 AD1-087 C 80/20 2.21 MW 2.21 MW
935171 AD1-152 C 80/20 2.15 MW 2.15 MW
936161 AD2-022 C 80/20 3.6 MW 3.6 MW
936171 AD2-023 C 80/20 2.1 MW 2.1 MW
937481 AD2-202 C 80/20 0.64 MW 0.64 MW
938821 AE1-108 C Adder -10.59 MW -9.0 MW
942461 AE2-259 C 80/20 31.14 MW 31.14 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.9 MW 8.9 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.99 MW 6.99 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 34.8 MW 34.8 MW
NY PJM->LTFIMP_NY CLTF 0.37 MW 0.37 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.35 MW 0.35 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.39 MW 4.39 MW
TVA LTFEXP_TVA->PJM CLTF 1.94 MW 1.94 MW
MEC LTFEXP_MEC->PJM CLTF 1.17 MW 1.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.48 MW 2.48 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.09 MW 2.09 MW

Details for 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line l/o DVP_P1-2: LN 173_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Contingency Name:
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 101.96 %
Rating: 101.52 MVA
Rating Type: B
MVA to Mitigate: 103.51 MVA
MW Contribution: 28.0 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Contingency Name:
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 101.4 %
Rating: 101.52 MVA
Rating Type: B
MVA to Mitigate: 102.94 MVA
MW Contribution: 28.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
942671 AE2-283 C 80/20 28.0 MW 28.0 MW
941801 AE2-185 C 80/20 35.99 MW 35.99 MW
941821 AE2-187 C 80/20 35.99 MW 35.99 MW
316217 AC1-145 C 80/20 3.1 MW 3.1 MW
316197 AC1-042 C 80/20 2.61 MW 2.61 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.05 MW 0.05 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.03 MW 0.03 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.02 MW 0.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Single AC 119.75 % 167.0 B 199.99 1.41
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
DVP_P4-2: 547T566_SRT-A
CONTINGENCY 'DVP_P4-2: 547T566_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314901 TO BUS 314987 CKT 1   /*8BATH CO     500.0 - 8LEXINGTN SC 500.0
 OPEN BRANCH FROM BUS 314912 TO BUS 314987 CKT 1   /*8LEXNGTN     500.0 - 8LEXINGTN SC 500.0
 OPEN BUS 314987                                   /*8LEXINGTN SC 500.0
END
Breaker AC 153.22 % 167.0 B 255.88 2.67
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
DVP_P4-2: 56602_SRT-A
CONTINGENCY 'DVP_P4-2: 56602_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314856 TO BUS 314912 CKT 1   /*6LEXNGT2     230.0 - 8LEXNGTN     500.0
END
Breaker AC 151.88 % 167.0 B 253.63 2.67
DVP 8RAWLINGS-8CARSON 500.0 kV Ckt 1 line
314936 to 314902 ckt 1
DVP_P1-2: LN 585_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 585_SRT-A-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 941030 CKT 1   /*8CARSON      500.0 - AE2-094 TP   500.0
END
Single AC 109.08 % 4070.2 B 4439.64 3.73
DVP AE2-094 TP-8CARSON 500.0 kV Ckt 1 line
941030 to 314902 ckt 1
DVP_P1-2: LN 511_SRT-S
CONTINGENCY 'DVP_P1-2: LN 511_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314936 CKT 1                /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 106.03 % 4070.2 B 4315.65 3.39
DVP 8RAWLINGS-8CARSON 500.0 kV Ckt 1 line
314936 to 314902 ckt 1
DVP_P1-2: LN 585_SRT-A-2
CONTINGENCY 'DVP_P1-2: LN 585_SRT-A-2'
 OPEN BRANCH FROM BUS 314940 TO BUS 941030 CKT 1   /*8ROGERS RD   500.0 - AE2-094 TP   500.0
END
Single AC 104.91 % 4070.2 B 4270.21 3.73
DVP 8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
314940 to 941030 ckt 1
DVP_P1-2: LN 511_SRT-S
CONTINGENCY 'DVP_P1-2: LN 511_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314936 CKT 1                /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 101.17 % 4070.2 B 4117.87 3.39
DVP 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 1 transformer
314696 to 314697 ckt 1
DVP_P4-2: H2T296_SRT-A
CONTINGENCY 'DVP_P4-2: H2T296_SRT-A'
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 2   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314697 TO BUS 316218 CKT 1   /*6SEDGE HILL  230.0 - AC1-221 TAP  230.0
END
Breaker AC 108.73 % 264.5 C 287.59 6.5
DVP 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
314696 to 314697 ckt 2
DVP_P4-2: 3202_SRT-A
CONTINGENCY 'DVP_P4-2: 3202_SRT-A'
 OPEN BRANCH FROM BUS 313852 TO BUS 314716 CKT 1   /*3WELCOTAP    115.0 - 3REEDY C     115.0
 OPEN BRANCH FROM BUS 313852 TO BUS 314718 CKT 1   /*3WELCOTAP    115.0 - 3S BOSTN     115.0
 OPEN BRANCH FROM BUS 313852 TO BUS 314724 CKT 1   /*3WELCOTAP    115.0 - 3WELCO       115.0
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 1   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314696 TO BUS 314717 CKT 1   /*3SEDGE HILL  115.0 - 3SINAI       115.0
 OPEN BRANCH FROM BUS 314717 TO BUS 314718 CKT 1   /*3SINAI       115.0 - 3S BOSTN     115.0
 OPEN BUS 313852                                   /*3WELCOTAP    115.0
 OPEN BUS 314717                                   /*3SINAI       115.0
 OPEN BUS 314718                                   /*3S BOSTN     115.0
 OPEN BUS 314724                                   /*3WELCO       115.0
 OPEN BUS 316248                                   /*AF1-058 C    115.0
 OPEN BUS 943902                                   /*AF1-058 E    115.0
END
Breaker AC 102.93 % 279.1 C 287.26 6.82
DVP 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
314696 to 314697 ckt 2
DVP_P4-2: H1T296_SRT-A
CONTINGENCY 'DVP_P4-2: H1T296_SRT-A'
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 1   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314697 TO BUS 316218 CKT 1   /*6SEDGE HILL  230.0 - AC1-221 TAP  230.0
END
Breaker AC 102.75 % 279.1 C 286.78 6.48

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 119.75 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 199.99 MVA
MW Contribution: 1.41 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 80/20 3.41 MW 3.41 MW
942671 AE2-283 C 80/20 1.41 MW 1.41 MW
242889 05REUSENS 80/20 0.05 MW 0.05 MW
941011 AE2-092 C Adder -6.94 MW -5.9 MW
941801 AE2-185 C 80/20 1.81 MW 1.81 MW
941821 AE2-187 C 80/20 1.81 MW 1.81 MW
958131 AF2-107 C 80/20 9.27 MW 9.27 MW
962751 AG1-124 C 80/20 6.52 MW 6.52 MW
316217 AC1-145 C 80/20 0.16 MW 0.16 MW
270173 AC1-122 C 80/20 0.46 MW 0.46 MW
316197 AC1-042 C 80/20 0.13 MW 0.13 MW
938821 AE1-108 C 80/20 62.13 MW 62.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.24 MW 15.24 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.56 MW 6.56 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.75 MW 7.75 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.61 MW 0.61 MW
WEC LTFEXP_WEC->PJM CLTF 0.31 MW 0.31 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.36 MW 0.36 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.53 MW 1.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.18 MW 0.18 MW

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o DVP_P4-2: 547T566_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
DVP_P4-2: 547T566_SRT-A
CONTINGENCY 'DVP_P4-2: 547T566_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314901 TO BUS 314987 CKT 1   /*8BATH CO     500.0 - 8LEXINGTN SC 500.0
 OPEN BRANCH FROM BUS 314912 TO BUS 314987 CKT 1   /*8LEXNGTN     500.0 - 8LEXINGTN SC 500.0
 OPEN BUS 314987                                   /*8LEXINGTN SC 500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 153.22 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 255.88 MVA
MW Contribution: 2.67 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.41 MW 3.41 MW
966252 AG1-494 E 50/50 5.11 MW 5.11 MW
926646 AC1-145 E Adder 0.86 MW 0.73 MW
942671 AE2-283 C Adder 1.41 MW 1.2 MW
942672 AE2-283 E Adder 1.26 MW 1.07 MW
941011 AE2-092 C Adder -6.96 MW -5.91 MW
941801 AE2-185 C Adder 1.81 MW 1.54 MW
941802 AE2-185 E Adder 1.21 MW 1.03 MW
941821 AE2-187 C Adder 1.81 MW 1.54 MW
941822 AE2-187 E Adder 0.8 MW 0.68 MW
958131 AF2-107 C 50/50 9.27 MW 9.27 MW
958132 AF2-107 E 50/50 5.08 MW 5.08 MW
962751 AG1-124 C 50/50 6.52 MW 6.52 MW
962752 AG1-124 E 50/50 4.55 MW 4.55 MW
926516 AC1-122_E Adder 1.33 MW 1.13 MW
925665 AC1-042 E Adder 1.31 MW 1.11 MW
938821 AE1-108 C 50/50 62.12 MW 62.12 MW
938822 AE1-108 E 50/50 29.64 MW 29.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.22 MW 15.22 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.55 MW 6.55 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.71 MW 7.71 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.57 MW 0.57 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.61 MW 0.61 MW
WEC LTFEXP_WEC->PJM CLTF 0.31 MW 0.31 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.36 MW 0.36 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.53 MW 1.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.64 MW 3.64 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.17 MW 0.17 MW

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o DVP_P4-2: 56602_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
DVP_P4-2: 56602_SRT-A
CONTINGENCY 'DVP_P4-2: 56602_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314856 TO BUS 314912 CKT 1   /*6LEXNGT2     230.0 - 8LEXNGTN     500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 151.88 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 253.63 MVA
MW Contribution: 2.67 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.41 MW 3.41 MW
966252 AG1-494 E 50/50 5.11 MW 5.11 MW
926646 AC1-145 E Adder 0.86 MW 0.73 MW
942671 AE2-283 C Adder 1.41 MW 1.2 MW
942672 AE2-283 E Adder 1.26 MW 1.07 MW
941011 AE2-092 C Adder -6.95 MW -5.91 MW
941801 AE2-185 C Adder 1.81 MW 1.54 MW
941802 AE2-185 E Adder 1.21 MW 1.03 MW
941821 AE2-187 C Adder 1.81 MW 1.54 MW
941822 AE2-187 E Adder 0.81 MW 0.69 MW
958131 AF2-107 C 50/50 9.27 MW 9.27 MW
958132 AF2-107 E 50/50 5.08 MW 5.08 MW
962751 AG1-124 C 50/50 6.52 MW 6.52 MW
962752 AG1-124 E 50/50 4.55 MW 4.55 MW
926516 AC1-122_E Adder 1.33 MW 1.13 MW
925665 AC1-042 E Adder 1.31 MW 1.11 MW
938821 AE1-108 C 50/50 62.13 MW 62.13 MW
938822 AE1-108 E 50/50 29.64 MW 29.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.24 MW 15.24 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.56 MW 6.56 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.74 MW 7.74 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.57 MW 0.57 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.61 MW 0.61 MW
WEC LTFEXP_WEC->PJM CLTF 0.31 MW 0.31 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.36 MW 0.36 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.53 MW 1.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.63 MW 3.63 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.18 MW 0.18 MW

Details for 8RAWLINGS-8CARSON 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 585_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8RAWLINGS-8CARSON 500.0 kV Ckt 1 line
314936 to 314902 ckt 1
Contingency Name:
DVP_P1-2: LN 585_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 585_SRT-A-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 941030 CKT 1   /*8CARSON      500.0 - AE2-094 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 109.08 %
Rating: 4070.2 MVA
Rating Type: B
MVA to Mitigate: 4439.64 MVA
MW Contribution: 3.73 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 2.64 MW 2.64 MW
963041 AG1-153 C 80/20 17.25 MW 17.25 MW
963171 AG1-166 C 80/20 1.47 MW 1.47 MW
963181 AG1-167 C 80/20 1.1 MW 1.1 MW
963191 AG1-168 C 80/20 1.1 MW 1.1 MW
964791 AG1-342 C 80/20 6.5 MW 6.5 MW
247284 05LEESVG 80/20 0.97 MW 0.97 MW
313853 3PONTONDP 80/20 0.98 MW 0.98 MW
314429 3JTRSVLE 80/20 0.6 MW 0.6 MW
315131 1EDGECMA 80/20 10.36 MW 10.36 MW
315153 1CLOVER1 80/20 32.85 MW 32.85 MW
315154 1CLOVER2 80/20 32.54 MW 32.54 MW
315156 1HALLBR1 80/20 1.24 MW 1.24 MW
315158 1KERR 1 80/20 0.65 MW 0.65 MW
315159 1KERR 2 80/20 1.82 MW 1.82 MW
315160 1KERR 3 80/20 1.82 MW 1.82 MW
315161 1KERR 4 80/20 1.82 MW 1.82 MW
315162 1KERR 5 80/20 1.82 MW 1.82 MW
942671 AE2-283 C 80/20 3.73 MW 3.73 MW
942751 AE2-291 C 80/20 13.51 MW 13.51 MW
943811 AF1-049 C 80/20 9.43 MW 9.43 MW
944011 AF1-069 C 80/20 38.91 MW 38.91 MW
959311 AF2-222 C 80/20 25.14 MW 25.14 MW
960061 AF2-297 C 80/20 15.78 MW 15.78 MW
315163 1KERR 6 80/20 1.82 MW 1.82 MW
315164 1KERR 7 80/20 1.82 MW 1.82 MW
315266 1PLYWOOD A 80/20 2.35 MW 2.35 MW
316118 AC1-105 C 80/20 1.77 MW 1.77 MW
316129 AC1-054 C 80/20 1.19 MW 1.19 MW
316131 AB2-060 C 80/20 2.31 MW 2.31 MW
938371 AE1-056 C 80/20 9.38 MW 9.38 MW
939181 AE1-148 C 80/20 14.33 MW 14.33 MW
940081 AE1-250 C 80/20 13.65 MW 13.65 MW
941031 AE2-094 C 80/20 119.1 MW 119.1 MW
941801 AE2-185 C 80/20 4.79 MW 4.79 MW
941821 AE2-187 C 80/20 4.79 MW 4.79 MW
946301 AF1-294 C 80/20 5.43 MW 5.43 MW
957481 AF2-042 C 80/20 148.19 MW 148.19 MW
958211 AF2-115 C 80/20 3.3 MW 3.3 MW
314507 3THOMPSN Adder -2.08 MW -1.77 MW
315102 1BRUNSWICKG1 80/20 25.37 MW 25.37 MW
315103 1BRUNSWICKG2 80/20 25.37 MW 25.37 MW
315104 1BRUNSWICKG3 80/20 25.37 MW 25.37 MW
315105 1BRUNSWICKS1 80/20 52.71 MW 52.71 MW
315241 1Z1-086 GT1 80/20 32.09 MW 32.09 MW
315242 1Z1-086 GT2 80/20 32.08 MW 32.08 MW
315243 1Z1-086 GT3 80/20 32.08 MW 32.08 MW
315244 1Z1-086 ST 80/20 55.86 MW 55.86 MW
957601 AF2-054 C Adder -1.89 MW -1.61 MW
942001 AE2-212 C Adder -2.12 MW -1.8 MW
936261 AD2-033 C 80/20 19.84 MW 19.84 MW
941671 AE2-166 C 80/20 5.71 MW 5.71 MW
933291 AC2-141 C Adder -33.98 MW -28.89 MW
934621 AD1-088 C 80/20 32.25 MW 32.25 MW
246843 05SMG1 80/20 1.17 MW 1.17 MW
246844 05SMG2 80/20 3.23 MW 3.23 MW
246845 05SMG3 80/20 1.99 MW 1.99 MW
246846 05SMG4 80/20 3.23 MW 3.23 MW
246847 05SMG5 80/20 1.23 MW 1.23 MW
316003 AC1-222 C 80/20 1.96 MW 1.96 MW
316034 AC1-036 C 80/20 0.35 MW 0.35 MW
316049 AB1-081 C OP 80/20 0.96 MW 0.96 MW
316222 AC1-221 C 80/20 2.9 MW 2.9 MW
316237 AB2-079 C O1 80/20 0.52 MW 0.52 MW
316238 AB2-078 C O1 80/20 0.52 MW 0.52 MW
316239 AB2-077 C O1 80/20 0.52 MW 0.52 MW
316240 AF1-291 C Adder -2.03 MW -1.73 MW
316248 AF1-058 C 80/20 0.64 MW 0.64 MW
316263 AC1-034 C 80/20 4.52 MW 4.52 MW
316283 AC2-100 C 80/20 2.33 MW 2.33 MW
316322 AB2-045 C 80/20 0.27 MW 0.27 MW
316217 AC1-145 C 80/20 0.41 MW 0.41 MW
270197 AC1-083 C 80/20 1.0 MW 1.0 MW
313527 AB2-043 C 80/20 0.81 MW 0.81 MW
316359 AB2-059 C OP 80/20 1.14 MW 1.14 MW
316197 AC1-042 C 80/20 0.35 MW 0.35 MW
316123 AC1-075 C 80/20 1.51 MW 1.51 MW
316205 AC1-080 C 80/20 0.51 MW 0.51 MW
962491 AG1-098 C 80/20 28.57 MW 28.57 MW
962561 AG1-105 C 80/20 15.92 MW 15.92 MW
964241 AG1-285 C 80/20 19.4 MW 19.4 MW
934611 AD1-087 C 80/20 3.23 MW 3.23 MW
935171 AD1-152 C 80/20 3.23 MW 3.23 MW
936161 AD2-022 C 80/20 12.8 MW 12.8 MW
936171 AD2-023 C 80/20 7.47 MW 7.47 MW
937481 AD2-202 C 80/20 0.94 MW 0.94 MW
938531 AE1-072 C Adder -16.89 MW -14.36 MW
940641 AE2-051 C Adder -22.24 MW -18.9 MW
941431 AE2-140 C 80/20 14.14 MW 14.14 MW
942461 AE2-259 C 80/20 14.03 MW 14.03 MW
944641 AF1-129 C Adder -95.17 MW -80.9 MW
938741 AE1-100 C 80/20 0.73 MW 0.73 MW
940601 AE2-047 C 80/20 4.25 MW 4.25 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 74.76 MW 74.76 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 46.8 MW 46.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 177.28 MW 177.28 MW
NY PJM->LTFIMP_NY CLTF 2.19 MW 2.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.88 MW 2.88 MW
WEC LTFEXP_WEC->PJM CLTF 1.52 MW 1.52 MW
CPLE LTFEXP_CPLE->PJM CLTF 20.16 MW 20.16 MW
TVA LTFEXP_TVA->PJM CLTF 12.22 MW 12.22 MW
MEC LTFEXP_MEC->PJM CLTF 8.76 MW 8.76 MW
LAGN LTFEXP_LAGN->PJM CLTF 15.49 MW 15.49 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.55 MW 0.55 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 9.62 MW 9.62 MW

Details for AE2-094 TP-8CARSON 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 511_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
AE2-094 TP-8CARSON 500.0 kV Ckt 1 line
941030 to 314902 ckt 1
Contingency Name:
DVP_P1-2: LN 511_SRT-S
CONTINGENCY 'DVP_P1-2: LN 511_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314936 CKT 1                /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 106.03 %
Rating: 4070.2 MVA
Rating Type: B
MVA to Mitigate: 4315.65 MVA
MW Contribution: 3.39 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 2.31 MW 2.31 MW
963041 AG1-153 C 80/20 17.1 MW 17.1 MW
963171 AG1-166 C 80/20 1.28 MW 1.28 MW
963181 AG1-167 C 80/20 0.96 MW 0.96 MW
963191 AG1-168 C 80/20 0.96 MW 0.96 MW
964791 AG1-342 C 80/20 5.77 MW 5.77 MW
247284 05LEESVG 80/20 0.89 MW 0.89 MW
313853 3PONTONDP 80/20 0.86 MW 0.86 MW
314429 3JTRSVLE 80/20 0.53 MW 0.53 MW
315153 1CLOVER1 80/20 28.87 MW 28.87 MW
315154 1CLOVER2 80/20 28.6 MW 28.6 MW
315156 1HALLBR1 80/20 1.12 MW 1.12 MW
315158 1KERR 1 80/20 0.58 MW 0.58 MW
315159 1KERR 2 80/20 1.62 MW 1.62 MW
315160 1KERR 3 80/20 1.62 MW 1.62 MW
315161 1KERR 4 80/20 1.62 MW 1.62 MW
315162 1KERR 5 80/20 1.62 MW 1.62 MW
942671 AE2-283 C 80/20 3.39 MW 3.39 MW
942751 AE2-291 C 80/20 12.11 MW 12.11 MW
943811 AF1-049 C 80/20 8.93 MW 8.93 MW
944011 AF1-069 C 80/20 45.16 MW 45.16 MW
959311 AF2-222 C 80/20 22.06 MW 22.06 MW
960061 AF2-297 C 80/20 14.04 MW 14.04 MW
315163 1KERR 6 80/20 1.62 MW 1.62 MW
315164 1KERR 7 80/20 1.62 MW 1.62 MW
315266 1PLYWOOD A 80/20 2.09 MW 2.09 MW
316118 AC1-105 C 80/20 1.57 MW 1.57 MW
316129 AC1-054 C 80/20 1.05 MW 1.05 MW
316131 AB2-060 C 80/20 2.04 MW 2.04 MW
938371 AE1-056 C 80/20 8.19 MW 8.19 MW
939181 AE1-148 C 80/20 12.7 MW 12.7 MW
940081 AE1-250 C 80/20 12.86 MW 12.86 MW
941031 AE2-094 C 80/20 138.22 MW 138.22 MW
941801 AE2-185 C 80/20 4.36 MW 4.36 MW
941821 AE2-187 C 80/20 4.36 MW 4.36 MW
946301 AF1-294 C 80/20 4.75 MW 4.75 MW
957481 AF2-042 C 80/20 129.9 MW 129.9 MW
958211 AF2-115 C 80/20 2.89 MW 2.89 MW
314507 3THOMPSN Adder -1.98 MW -1.68 MW
315102 1BRUNSWICKG1 80/20 25.16 MW 25.16 MW
315103 1BRUNSWICKG2 80/20 25.16 MW 25.16 MW
315104 1BRUNSWICKG3 80/20 25.16 MW 25.16 MW
315105 1BRUNSWICKS1 80/20 52.27 MW 52.27 MW
315241 1Z1-086 GT1 80/20 33.48 MW 33.48 MW
315242 1Z1-086 GT2 80/20 33.47 MW 33.47 MW
315243 1Z1-086 GT3 80/20 33.47 MW 33.47 MW
315244 1Z1-086 ST 80/20 58.27 MW 58.27 MW
957601 AF2-054 C Adder -1.8 MW -1.53 MW
942001 AE2-212 C Adder -2.01 MW -1.71 MW
936261 AD2-033 C 80/20 17.44 MW 17.44 MW
933291 AC2-141 C Adder -32.2 MW -27.37 MW
934621 AD1-088 C 80/20 28.26 MW 28.26 MW
246843 05SMG1 80/20 1.09 MW 1.09 MW
246844 05SMG2 80/20 3.0 MW 3.0 MW
246845 05SMG3 80/20 1.84 MW 1.84 MW
246846 05SMG4 80/20 3.0 MW 3.0 MW
246847 05SMG5 80/20 1.14 MW 1.14 MW
316003 AC1-222 C 80/20 1.74 MW 1.74 MW
316034 AC1-036 C 80/20 0.31 MW 0.31 MW
316049 AB1-081 C OP 80/20 0.92 MW 0.92 MW
316222 AC1-221 C 80/20 2.64 MW 2.64 MW
316237 AB2-079 C O1 80/20 0.46 MW 0.46 MW
316238 AB2-078 C O1 80/20 0.46 MW 0.46 MW
316239 AB2-077 C O1 80/20 0.46 MW 0.46 MW
316240 AF1-291 C Adder -1.93 MW -1.64 MW
316248 AF1-058 C 80/20 0.57 MW 0.57 MW
316263 AC1-034 C 80/20 4.33 MW 4.33 MW
316283 AC2-100 C 80/20 2.12 MW 2.12 MW
316322 AB2-045 C 80/20 0.23 MW 0.23 MW
316217 AC1-145 C 80/20 0.38 MW 0.38 MW
270197 AC1-083 C 80/20 0.93 MW 0.93 MW
313527 AB2-043 C 80/20 0.71 MW 0.71 MW
316359 AB2-059 C OP 80/20 1.09 MW 1.09 MW
316197 AC1-042 C 80/20 0.32 MW 0.32 MW
316123 AC1-075 C 80/20 1.35 MW 1.35 MW
316205 AC1-080 C 80/20 0.45 MW 0.45 MW
962491 AG1-098 C 80/20 25.03 MW 25.03 MW
962561 AG1-105 C 80/20 14.11 MW 14.11 MW
964241 AG1-285 C 80/20 17.08 MW 17.08 MW
934611 AD1-087 C 80/20 2.84 MW 2.84 MW
935171 AD1-152 C 80/20 2.85 MW 2.85 MW
936161 AD2-022 C 80/20 12.16 MW 12.16 MW
936171 AD2-023 C 80/20 7.09 MW 7.09 MW
937481 AD2-202 C 80/20 0.82 MW 0.82 MW
938531 AE1-072 C Adder -16.01 MW -13.61 MW
940641 AE2-051 C Adder -21.04 MW -17.88 MW
941431 AE2-140 C 80/20 13.39 MW 13.39 MW
942461 AE2-259 C 80/20 12.21 MW 12.21 MW
944641 AF1-129 C Adder -90.48 MW -76.91 MW
938741 AE1-100 C 80/20 0.69 MW 0.69 MW
940601 AE2-047 C 80/20 4.03 MW 4.03 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 71.05 MW 71.05 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 44.76 MW 44.76 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 170.64 MW 170.64 MW
NY PJM->LTFIMP_NY CLTF 2.11 MW 2.11 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.74 MW 2.74 MW
WEC LTFEXP_WEC->PJM CLTF 1.45 MW 1.45 MW
CPLE LTFEXP_CPLE->PJM CLTF 19.42 MW 19.42 MW
TVA LTFEXP_TVA->PJM CLTF 11.71 MW 11.71 MW
MEC LTFEXP_MEC->PJM CLTF 8.35 MW 8.35 MW
LAGN LTFEXP_LAGN->PJM CLTF 14.85 MW 14.85 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.52 MW 0.52 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 9.26 MW 9.26 MW

Details for 8RAWLINGS-8CARSON 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 585_SRT-A-2


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8RAWLINGS-8CARSON 500.0 kV Ckt 1 line
314936 to 314902 ckt 1
Contingency Name:
DVP_P1-2: LN 585_SRT-A-2
CONTINGENCY 'DVP_P1-2: LN 585_SRT-A-2'
 OPEN BRANCH FROM BUS 314940 TO BUS 941030 CKT 1   /*8ROGERS RD   500.0 - AE2-094 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 104.91 %
Rating: 4070.2 MVA
Rating Type: B
MVA to Mitigate: 4270.21 MVA
MW Contribution: 3.73 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 2.64 MW 2.64 MW
963041 AG1-153 C 80/20 17.25 MW 17.25 MW
963171 AG1-166 C 80/20 1.47 MW 1.47 MW
963181 AG1-167 C 80/20 1.1 MW 1.1 MW
963191 AG1-168 C 80/20 1.1 MW 1.1 MW
964791 AG1-342 C 80/20 6.5 MW 6.5 MW
247284 05LEESVG 80/20 0.97 MW 0.97 MW
313853 3PONTONDP 80/20 0.98 MW 0.98 MW
314429 3JTRSVLE 80/20 0.6 MW 0.6 MW
315131 1EDGECMA 80/20 10.36 MW 10.36 MW
315153 1CLOVER1 80/20 32.85 MW 32.85 MW
315154 1CLOVER2 80/20 32.54 MW 32.54 MW
315156 1HALLBR1 80/20 1.24 MW 1.24 MW
315158 1KERR 1 80/20 0.65 MW 0.65 MW
315159 1KERR 2 80/20 1.82 MW 1.82 MW
315160 1KERR 3 80/20 1.82 MW 1.82 MW
315161 1KERR 4 80/20 1.82 MW 1.82 MW
315162 1KERR 5 80/20 1.82 MW 1.82 MW
942671 AE2-283 C 80/20 3.73 MW 3.73 MW
942751 AE2-291 C 80/20 13.51 MW 13.51 MW
943811 AF1-049 C 80/20 9.43 MW 9.43 MW
959311 AF2-222 C 80/20 25.14 MW 25.14 MW
960061 AF2-297 C 80/20 15.78 MW 15.78 MW
315163 1KERR 6 80/20 1.82 MW 1.82 MW
315164 1KERR 7 80/20 1.82 MW 1.82 MW
315266 1PLYWOOD A 80/20 2.35 MW 2.35 MW
316118 AC1-105 C 80/20 1.77 MW 1.77 MW
316129 AC1-054 C 80/20 1.19 MW 1.19 MW
316131 AB2-060 C 80/20 2.31 MW 2.31 MW
938371 AE1-056 C 80/20 9.38 MW 9.38 MW
939181 AE1-148 C 80/20 14.33 MW 14.33 MW
940081 AE1-250 C 80/20 13.65 MW 13.65 MW
941801 AE2-185 C 80/20 4.79 MW 4.79 MW
941821 AE2-187 C 80/20 4.79 MW 4.79 MW
946301 AF1-294 C 80/20 5.43 MW 5.43 MW
957481 AF2-042 C 80/20 148.19 MW 148.19 MW
958211 AF2-115 C 80/20 3.3 MW 3.3 MW
314507 3THOMPSN Adder -2.08 MW -1.77 MW
315102 1BRUNSWICKG1 80/20 25.37 MW 25.37 MW
315103 1BRUNSWICKG2 80/20 25.37 MW 25.37 MW
315104 1BRUNSWICKG3 80/20 25.37 MW 25.37 MW
315105 1BRUNSWICKS1 80/20 52.71 MW 52.71 MW
315241 1Z1-086 GT1 80/20 32.09 MW 32.09 MW
315242 1Z1-086 GT2 80/20 32.08 MW 32.08 MW
315243 1Z1-086 GT3 80/20 32.08 MW 32.08 MW
315244 1Z1-086 ST 80/20 55.86 MW 55.86 MW
957601 AF2-054 C Adder -1.89 MW -1.61 MW
964211 AG1-282 C Adder -1.79 MW -1.52 MW
942001 AE2-212 C Adder -2.12 MW -1.8 MW
936261 AD2-033 C 80/20 19.84 MW 19.84 MW
941671 AE2-166 C 80/20 5.71 MW 5.71 MW
933291 AC2-141 C Adder -33.98 MW -28.89 MW
934621 AD1-088 C 80/20 32.25 MW 32.25 MW
246843 05SMG1 80/20 1.17 MW 1.17 MW
246844 05SMG2 80/20 3.23 MW 3.23 MW
246845 05SMG3 80/20 1.99 MW 1.99 MW
246846 05SMG4 80/20 3.23 MW 3.23 MW
246847 05SMG5 80/20 1.23 MW 1.23 MW
316003 AC1-222 C 80/20 1.96 MW 1.96 MW
316034 AC1-036 C 80/20 0.35 MW 0.35 MW
316049 AB1-081 C OP 80/20 0.96 MW 0.96 MW
316222 AC1-221 C 80/20 2.9 MW 2.9 MW
316237 AB2-079 C O1 80/20 0.52 MW 0.52 MW
316238 AB2-078 C O1 80/20 0.52 MW 0.52 MW
316239 AB2-077 C O1 80/20 0.52 MW 0.52 MW
316240 AF1-291 C Adder -2.03 MW -1.73 MW
316248 AF1-058 C 80/20 0.64 MW 0.64 MW
316263 AC1-034 C 80/20 4.52 MW 4.52 MW
316283 AC2-100 C 80/20 2.33 MW 2.33 MW
316322 AB2-045 C 80/20 0.27 MW 0.27 MW
316217 AC1-145 C 80/20 0.41 MW 0.41 MW
270197 AC1-083 C 80/20 1.0 MW 1.0 MW
313527 AB2-043 C 80/20 0.81 MW 0.81 MW
316359 AB2-059 C OP 80/20 1.14 MW 1.14 MW
316197 AC1-042 C 80/20 0.35 MW 0.35 MW
316123 AC1-075 C 80/20 1.51 MW 1.51 MW
316205 AC1-080 C 80/20 0.51 MW 0.51 MW
962491 AG1-098 C 80/20 28.57 MW 28.57 MW
962561 AG1-105 C 80/20 15.92 MW 15.92 MW
964241 AG1-285 C 80/20 19.4 MW 19.4 MW
934611 AD1-087 C 80/20 3.23 MW 3.23 MW
935171 AD1-152 C 80/20 3.23 MW 3.23 MW
936161 AD2-022 C 80/20 12.8 MW 12.8 MW
936171 AD2-023 C 80/20 7.47 MW 7.47 MW
937481 AD2-202 C 80/20 0.94 MW 0.94 MW
938531 AE1-072 C Adder -16.89 MW -14.36 MW
940641 AE2-051 C Adder -22.24 MW -18.9 MW
941431 AE2-140 C 80/20 14.14 MW 14.14 MW
942461 AE2-259 C 80/20 14.03 MW 14.03 MW
944641 AF1-129 C Adder -95.17 MW -80.9 MW
938741 AE1-100 C 80/20 0.73 MW 0.73 MW
940601 AE2-047 C 80/20 4.25 MW 4.25 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 74.76 MW 74.76 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 46.8 MW 46.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 177.28 MW 177.28 MW
NY PJM->LTFIMP_NY CLTF 2.19 MW 2.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.88 MW 2.88 MW
WEC LTFEXP_WEC->PJM CLTF 1.52 MW 1.52 MW
CPLE LTFEXP_CPLE->PJM CLTF 20.16 MW 20.16 MW
TVA LTFEXP_TVA->PJM CLTF 12.22 MW 12.22 MW
MEC LTFEXP_MEC->PJM CLTF 8.76 MW 8.76 MW
LAGN LTFEXP_LAGN->PJM CLTF 15.49 MW 15.49 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.55 MW 0.55 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 9.62 MW 9.62 MW

Details for 8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 511_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
314940 to 941030 ckt 1
Contingency Name:
DVP_P1-2: LN 511_SRT-S
CONTINGENCY 'DVP_P1-2: LN 511_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314936 CKT 1                /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 101.17 %
Rating: 4070.2 MVA
Rating Type: B
MVA to Mitigate: 4117.87 MVA
MW Contribution: 3.39 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 2.31 MW 2.31 MW
963041 AG1-153 C 80/20 17.1 MW 17.1 MW
963171 AG1-166 C 80/20 1.28 MW 1.28 MW
963181 AG1-167 C 80/20 0.96 MW 0.96 MW
963191 AG1-168 C 80/20 0.96 MW 0.96 MW
964791 AG1-342 C 80/20 5.77 MW 5.77 MW
247284 05LEESVG 80/20 0.89 MW 0.89 MW
313853 3PONTONDP 80/20 0.86 MW 0.86 MW
314429 3JTRSVLE 80/20 0.53 MW 0.53 MW
315153 1CLOVER1 80/20 28.87 MW 28.87 MW
315154 1CLOVER2 80/20 28.6 MW 28.6 MW
315156 1HALLBR1 80/20 1.12 MW 1.12 MW
315158 1KERR 1 80/20 0.58 MW 0.58 MW
315159 1KERR 2 80/20 1.62 MW 1.62 MW
315160 1KERR 3 80/20 1.62 MW 1.62 MW
315161 1KERR 4 80/20 1.62 MW 1.62 MW
315162 1KERR 5 80/20 1.62 MW 1.62 MW
942671 AE2-283 C 80/20 3.39 MW 3.39 MW
942751 AE2-291 C 80/20 12.11 MW 12.11 MW
943811 AF1-049 C 80/20 8.93 MW 8.93 MW
959311 AF2-222 C 80/20 22.06 MW 22.06 MW
960061 AF2-297 C 80/20 14.04 MW 14.04 MW
315163 1KERR 6 80/20 1.62 MW 1.62 MW
315164 1KERR 7 80/20 1.62 MW 1.62 MW
315266 1PLYWOOD A 80/20 2.09 MW 2.09 MW
316118 AC1-105 C 80/20 1.57 MW 1.57 MW
316129 AC1-054 C 80/20 1.05 MW 1.05 MW
316131 AB2-060 C 80/20 2.04 MW 2.04 MW
938371 AE1-056 C 80/20 8.19 MW 8.19 MW
939181 AE1-148 C 80/20 12.7 MW 12.7 MW
940081 AE1-250 C 80/20 12.86 MW 12.86 MW
941801 AE2-185 C 80/20 4.36 MW 4.36 MW
941821 AE2-187 C 80/20 4.36 MW 4.36 MW
946301 AF1-294 C 80/20 4.75 MW 4.75 MW
957481 AF2-042 C 80/20 129.9 MW 129.9 MW
958211 AF2-115 C 80/20 2.89 MW 2.89 MW
314507 3THOMPSN Adder -1.98 MW -1.68 MW
315102 1BRUNSWICKG1 80/20 25.16 MW 25.16 MW
315103 1BRUNSWICKG2 80/20 25.16 MW 25.16 MW
315104 1BRUNSWICKG3 80/20 25.16 MW 25.16 MW
315105 1BRUNSWICKS1 80/20 52.27 MW 52.27 MW
315241 1Z1-086 GT1 80/20 33.48 MW 33.48 MW
315242 1Z1-086 GT2 80/20 33.47 MW 33.47 MW
315243 1Z1-086 GT3 80/20 33.47 MW 33.47 MW
315244 1Z1-086 ST 80/20 58.27 MW 58.27 MW
957601 AF2-054 C Adder -1.8 MW -1.53 MW
964211 AG1-282 C Adder -1.7 MW -1.45 MW
942001 AE2-212 C Adder -2.01 MW -1.71 MW
936261 AD2-033 C 80/20 17.44 MW 17.44 MW
933291 AC2-141 C Adder -32.2 MW -27.37 MW
934621 AD1-088 C 80/20 28.26 MW 28.26 MW
246843 05SMG1 80/20 1.09 MW 1.09 MW
246844 05SMG2 80/20 3.0 MW 3.0 MW
246845 05SMG3 80/20 1.84 MW 1.84 MW
246846 05SMG4 80/20 3.0 MW 3.0 MW
246847 05SMG5 80/20 1.14 MW 1.14 MW
316003 AC1-222 C 80/20 1.74 MW 1.74 MW
316034 AC1-036 C 80/20 0.31 MW 0.31 MW
316049 AB1-081 C OP 80/20 0.92 MW 0.92 MW
316222 AC1-221 C 80/20 2.64 MW 2.64 MW
316237 AB2-079 C O1 80/20 0.46 MW 0.46 MW
316238 AB2-078 C O1 80/20 0.46 MW 0.46 MW
316239 AB2-077 C O1 80/20 0.46 MW 0.46 MW
316240 AF1-291 C Adder -1.93 MW -1.64 MW
316248 AF1-058 C 80/20 0.57 MW 0.57 MW
316263 AC1-034 C 80/20 4.33 MW 4.33 MW
316283 AC2-100 C 80/20 2.12 MW 2.12 MW
316322 AB2-045 C 80/20 0.23 MW 0.23 MW
316217 AC1-145 C 80/20 0.38 MW 0.38 MW
270197 AC1-083 C 80/20 0.93 MW 0.93 MW
313527 AB2-043 C 80/20 0.71 MW 0.71 MW
316359 AB2-059 C OP 80/20 1.09 MW 1.09 MW
316197 AC1-042 C 80/20 0.32 MW 0.32 MW
316123 AC1-075 C 80/20 1.35 MW 1.35 MW
316205 AC1-080 C 80/20 0.45 MW 0.45 MW
962491 AG1-098 C 80/20 25.03 MW 25.03 MW
962561 AG1-105 C 80/20 14.11 MW 14.11 MW
964241 AG1-285 C 80/20 17.08 MW 17.08 MW
934611 AD1-087 C 80/20 2.84 MW 2.84 MW
935171 AD1-152 C 80/20 2.85 MW 2.85 MW
936161 AD2-022 C 80/20 12.16 MW 12.16 MW
936171 AD2-023 C 80/20 7.09 MW 7.09 MW
937481 AD2-202 C 80/20 0.82 MW 0.82 MW
938531 AE1-072 C Adder -16.01 MW -13.61 MW
940641 AE2-051 C Adder -21.04 MW -17.88 MW
941431 AE2-140 C 80/20 13.39 MW 13.39 MW
942461 AE2-259 C 80/20 12.21 MW 12.21 MW
944641 AF1-129 C Adder -90.48 MW -76.91 MW
938741 AE1-100 C 80/20 0.69 MW 0.69 MW
940601 AE2-047 C 80/20 4.03 MW 4.03 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 71.05 MW 71.05 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 44.76 MW 44.76 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 170.64 MW 170.64 MW
NY PJM->LTFIMP_NY CLTF 2.11 MW 2.11 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.74 MW 2.74 MW
WEC LTFEXP_WEC->PJM CLTF 1.45 MW 1.45 MW
CPLE LTFEXP_CPLE->PJM CLTF 19.42 MW 19.42 MW
TVA LTFEXP_TVA->PJM CLTF 11.71 MW 11.71 MW
MEC LTFEXP_MEC->PJM CLTF 8.35 MW 8.35 MW
LAGN LTFEXP_LAGN->PJM CLTF 14.85 MW 14.85 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.52 MW 0.52 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 9.26 MW 9.26 MW

Details for 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 1 transformer l/o DVP_P4-2: H2T296_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 1 transformer
314696 to 314697 ckt 1
Contingency Name:
DVP_P4-2: H2T296_SRT-A
CONTINGENCY 'DVP_P4-2: H2T296_SRT-A'
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 2   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314697 TO BUS 316218 CKT 1   /*6SEDGE HILL  230.0 - AC1-221 TAP  230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 108.73 %
Rating: 264.5 MVA
Rating Type: C
MVA to Mitigate: 287.59 MVA
MW Contribution: 6.5 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C Adder 0.69 MW 0.59 MW
961792 AG1-021 E Adder 0.59 MW 0.5 MW
963171 AG1-166 C Adder 0.38 MW 0.33 MW
963172 AG1-166 E Adder 0.9 MW 0.76 MW
963181 AG1-167 C Adder 0.29 MW 0.24 MW
963182 AG1-167 E Adder 0.67 MW 0.57 MW
963191 AG1-168 C Adder 0.29 MW 0.24 MW
963192 AG1-168 E Adder 0.67 MW 0.57 MW
964791 AG1-342 C 50/50 7.44 MW 7.44 MW
964792 AG1-342 E 50/50 4.96 MW 4.96 MW
313853 3PONTONDP Adder 0.26 MW 0.22 MW
315156 1HALLBR1 50/50 1.25 MW 1.25 MW
926274 AC1-105 E 50/50 6.94 MW 6.94 MW
926646 AC1-145 E 50/50 2.09 MW 2.09 MW
942671 AE2-283 C 50/50 3.44 MW 3.44 MW
942672 AE2-283 E 50/50 3.07 MW 3.07 MW
942751 AE2-291 C 50/50 17.76 MW 17.76 MW
942752 AE2-291 E 50/50 11.84 MW 11.84 MW
943902 AF1-058 E 50/50 3.97 MW 3.97 MW
959311 AF2-222 C Adder 9.04 MW 7.68 MW
959312 AF2-222 E Adder 6.05 MW 5.15 MW
960061 AF2-297 C 50/50 23.8 MW 23.8 MW
960062 AF2-297 E 50/50 15.86 MW 15.86 MW
315266 1PLYWOOD A 50/50 3.14 MW 3.14 MW
316118 AC1-105 C 50/50 2.36 MW 2.36 MW
316131 AB2-060 C 50/50 1.14 MW 1.14 MW
924162 AB2-060 E OP 50/50 3.29 MW 3.29 MW
924302 AB2-077 E O1 50/50 1.1 MW 1.1 MW
924312 AB2-078 E O1 50/50 1.1 MW 1.1 MW
924322 AB2-079 E O1 50/50 1.1 MW 1.1 MW
925612 AC1-036 E Adder 0.49 MW 0.41 MW
939181 AE1-148 C Adder 3.85 MW 3.27 MW
939182 AE1-148 E Adder 2.56 MW 2.18 MW
941801 AE2-185 C 50/50 4.42 MW 4.42 MW
941802 AE2-185 E 50/50 2.94 MW 2.94 MW
941821 AE2-187 C 50/50 4.42 MW 4.42 MW
941822 AE2-187 E 50/50 1.96 MW 1.96 MW
946301 AF1-294 C Adder 1.42 MW 1.21 MW
946302 AF1-294 E Adder 1.2 MW 1.02 MW
958211 AF2-115 C Adder 0.86 MW 0.73 MW
958212 AF2-115 E Adder 0.74 MW 0.62 MW
314722 3TWITTYS Adder 0.54 MW 0.46 MW
936261 AD2-033 C 50/50 7.94 MW 7.94 MW
936262 AD2-033 E 50/50 5.29 MW 5.29 MW
316003 AC1-222 C 50/50 2.91 MW 2.91 MW
316237 AB2-079 C O1 50/50 0.27 MW 0.27 MW
316238 AB2-078 C O1 50/50 0.27 MW 0.27 MW
316239 AB2-077 C O1 50/50 0.27 MW 0.27 MW
316248 AF1-058 C 50/50 0.97 MW 0.97 MW
927264 AC1-222 E 50/50 11.91 MW 11.91 MW
316217 AC1-145 C 50/50 0.38 MW 0.38 MW
313527 AB2-043 C 50/50 0.4 MW 0.4 MW
924022 AB2-043 E O1 50/50 4.06 MW 4.06 MW
316197 AC1-042 C 50/50 0.32 MW 0.32 MW
925665 AC1-042 E 50/50 3.19 MW 3.19 MW
316123 AC1-075 C 50/50 2.07 MW 2.07 MW
925997 AC1-075 E 50/50 7.2 MW 7.2 MW
316205 AC1-080 C 50/50 0.69 MW 0.69 MW
926024 AC1-080 E 50/50 2.39 MW 2.39 MW
962561 AG1-105 C 50/50 16.77 MW 16.77 MW
962562 AG1-105 E 50/50 11.18 MW 11.18 MW
964241 AG1-285 C 50/50 8.86 MW 8.86 MW
964242 AG1-285 E 50/50 5.91 MW 5.91 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.8 MW 6.8 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.77 MW 2.77 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.6 MW 2.6 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.28 MW 0.28 MW
NY PJM->LTFIMP_NY CLTF 0.11 MW 0.11 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.27 MW 0.27 MW
WEC LTFEXP_WEC->PJM CLTF 0.14 MW 0.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.09 MW 0.09 MW
TVA LTFEXP_TVA->PJM CLTF 0.61 MW 0.61 MW
MEC LTFEXP_MEC->PJM CLTF 0.67 MW 0.67 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.72 MW 0.72 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.75 MW 1.75 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer l/o DVP_P4-2: 3202_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
314696 to 314697 ckt 2
Contingency Name:
DVP_P4-2: 3202_SRT-A
CONTINGENCY 'DVP_P4-2: 3202_SRT-A'
 OPEN BRANCH FROM BUS 313852 TO BUS 314716 CKT 1   /*3WELCOTAP    115.0 - 3REEDY C     115.0
 OPEN BRANCH FROM BUS 313852 TO BUS 314718 CKT 1   /*3WELCOTAP    115.0 - 3S BOSTN     115.0
 OPEN BRANCH FROM BUS 313852 TO BUS 314724 CKT 1   /*3WELCOTAP    115.0 - 3WELCO       115.0
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 1   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314696 TO BUS 314717 CKT 1   /*3SEDGE HILL  115.0 - 3SINAI       115.0
 OPEN BRANCH FROM BUS 314717 TO BUS 314718 CKT 1   /*3SINAI       115.0 - 3S BOSTN     115.0
 OPEN BUS 313852                                   /*3WELCOTAP    115.0
 OPEN BUS 314717                                   /*3SINAI       115.0
 OPEN BUS 314718                                   /*3S BOSTN     115.0
 OPEN BUS 314724                                   /*3WELCO       115.0
 OPEN BUS 316248                                   /*AF1-058 C    115.0
 OPEN BUS 943902                                   /*AF1-058 E    115.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.93 %
Rating: 279.1 MVA
Rating Type: C
MVA to Mitigate: 287.26 MVA
MW Contribution: 6.82 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C Adder 0.9 MW 0.77 MW
961792 AG1-021 E Adder 0.77 MW 0.65 MW
963171 AG1-166 C Adder 0.5 MW 0.42 MW
963172 AG1-166 E Adder 1.17 MW 0.99 MW
963181 AG1-167 C Adder 0.38 MW 0.32 MW
963182 AG1-167 E Adder 0.88 MW 0.74 MW
963191 AG1-168 C Adder 0.38 MW 0.32 MW
963192 AG1-168 E Adder 0.88 MW 0.74 MW
964791 AG1-342 C 50/50 8.19 MW 8.19 MW
964792 AG1-342 E 50/50 5.46 MW 5.46 MW
313853 3PONTONDP Adder 0.33 MW 0.28 MW
314713 3PAMPLIN Adder 0.43 MW 0.36 MW
315156 1HALLBR1 50/50 1.32 MW 1.32 MW
926274 AC1-105 E 50/50 7.58 MW 7.58 MW
926646 AC1-145 E 50/50 2.19 MW 2.19 MW
942671 AE2-283 C 50/50 3.6 MW 3.6 MW
942672 AE2-283 E 50/50 3.22 MW 3.22 MW
942751 AE2-291 C 50/50 19.16 MW 19.16 MW
942752 AE2-291 E 50/50 12.77 MW 12.77 MW
959311 AF2-222 C 50/50 11.09 MW 11.09 MW
959312 AF2-222 E 50/50 7.43 MW 7.43 MW
960061 AF2-297 C 50/50 25.88 MW 25.88 MW
960062 AF2-297 E 50/50 17.25 MW 17.25 MW
315266 1PLYWOOD A 50/50 3.42 MW 3.42 MW
316118 AC1-105 C 50/50 2.58 MW 2.58 MW
316131 AB2-060 C 50/50 1.33 MW 1.33 MW
924162 AB2-060 E OP 50/50 3.86 MW 3.86 MW
924302 AB2-077 E O1 50/50 1.28 MW 1.28 MW
924312 AB2-078 E O1 50/50 1.28 MW 1.28 MW
924322 AB2-079 E O1 50/50 1.28 MW 1.28 MW
925612 AC1-036 E 50/50 0.59 MW 0.59 MW
938371 AE1-056 C Adder 2.79 MW 2.37 MW
938372 AE1-056 E Adder 1.52 MW 1.29 MW
939181 AE1-148 C Adder 4.75 MW 4.04 MW
939182 AE1-148 E Adder 3.17 MW 2.69 MW
941801 AE2-185 C 50/50 4.63 MW 4.63 MW
941802 AE2-185 E 50/50 3.09 MW 3.09 MW
941821 AE2-187 C 50/50 4.63 MW 4.63 MW
941822 AE2-187 E 50/50 2.06 MW 2.06 MW
946301 AF1-294 C Adder 1.85 MW 1.57 MW
946302 AF1-294 E Adder 1.57 MW 1.33 MW
958211 AF2-115 C Adder 1.12 MW 0.96 MW
958212 AF2-115 E Adder 0.96 MW 0.81 MW
314722 3TWITTYS 50/50 0.66 MW 0.66 MW
936261 AD2-033 C 50/50 9.58 MW 9.58 MW
936262 AD2-033 E 50/50 6.39 MW 6.39 MW
316003 AC1-222 C 50/50 3.16 MW 3.16 MW
316034 AC1-036 C 50/50 0.16 MW 0.16 MW
316237 AB2-079 C O1 50/50 0.31 MW 0.31 MW
316238 AB2-078 C O1 50/50 0.31 MW 0.31 MW
316239 AB2-077 C O1 50/50 0.31 MW 0.31 MW
927264 AC1-222 E 50/50 12.94 MW 12.94 MW
316217 AC1-145 C 50/50 0.4 MW 0.4 MW
313527 AB2-043 C 50/50 0.47 MW 0.47 MW
924022 AB2-043 E O1 50/50 4.75 MW 4.75 MW
316197 AC1-042 C 50/50 0.33 MW 0.33 MW
925665 AC1-042 E 50/50 3.35 MW 3.35 MW
316123 AC1-075 C 50/50 2.24 MW 2.24 MW
925997 AC1-075 E 50/50 7.78 MW 7.78 MW
316205 AC1-080 C 50/50 0.75 MW 0.75 MW
926024 AC1-080 E 50/50 2.58 MW 2.58 MW
962561 AG1-105 C 50/50 18.54 MW 18.54 MW
962562 AG1-105 E 50/50 12.36 MW 12.36 MW
964241 AG1-285 C 50/50 10.49 MW 10.49 MW
964242 AG1-285 E 50/50 6.99 MW 6.99 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.44 MW 1.44 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.14 MW 0.14 MW
NY PJM->LTFIMP_NY CLTF 0.06 MW 0.06 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.07 MW 0.07 MW
WEC LTFEXP_WEC->PJM CLTF 0.03 MW 0.03 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.28 MW 0.28 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.59 MW 0.59 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.25 MW 0.25 MW
MEC LTFEXP_MEC->PJM CLTF 0.07 MW 0.07 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.91 MW 0.91 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.96 MW 0.96 MW

Details for 3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer l/o DVP_P4-2: H1T296_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
314696 to 314697 ckt 2
Contingency Name:
DVP_P4-2: H1T296_SRT-A
CONTINGENCY 'DVP_P4-2: H1T296_SRT-A'
 OPEN BRANCH FROM BUS 314696 TO BUS 314697 CKT 1   /*3SEDGE HILL  115.0 - 6SEDGE HILL  230.0
 OPEN BRANCH FROM BUS 314697 TO BUS 316218 CKT 1   /*6SEDGE HILL  230.0 - AC1-221 TAP  230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.75 %
Rating: 279.1 MVA
Rating Type: C
MVA to Mitigate: 286.78 MVA
MW Contribution: 6.48 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C Adder 0.69 MW 0.59 MW
961792 AG1-021 E Adder 0.59 MW 0.5 MW
963171 AG1-166 C Adder 0.38 MW 0.33 MW
963172 AG1-166 E Adder 0.89 MW 0.76 MW
963181 AG1-167 C Adder 0.29 MW 0.24 MW
963182 AG1-167 E Adder 0.67 MW 0.57 MW
963191 AG1-168 C Adder 0.29 MW 0.24 MW
963192 AG1-168 E Adder 0.67 MW 0.57 MW
964791 AG1-342 C 50/50 7.42 MW 7.42 MW
964792 AG1-342 E 50/50 4.95 MW 4.95 MW
313853 3PONTONDP Adder 0.26 MW 0.22 MW
315156 1HALLBR1 50/50 1.25 MW 1.25 MW
926274 AC1-105 E 50/50 6.92 MW 6.92 MW
926646 AC1-145 E 50/50 2.09 MW 2.09 MW
942671 AE2-283 C 50/50 3.42 MW 3.42 MW
942672 AE2-283 E 50/50 3.06 MW 3.06 MW
942751 AE2-291 C 50/50 17.71 MW 17.71 MW
942752 AE2-291 E 50/50 11.81 MW 11.81 MW
943902 AF1-058 E 50/50 3.95 MW 3.95 MW
959311 AF2-222 C Adder 9.01 MW 7.66 MW
959312 AF2-222 E Adder 6.04 MW 5.13 MW
960061 AF2-297 C 50/50 23.73 MW 23.73 MW
960062 AF2-297 E 50/50 15.82 MW 15.82 MW
315266 1PLYWOOD A 50/50 3.13 MW 3.13 MW
316118 AC1-105 C 50/50 2.35 MW 2.35 MW
316131 AB2-060 C 50/50 1.14 MW 1.14 MW
924162 AB2-060 E OP 50/50 3.28 MW 3.28 MW
924302 AB2-077 E O1 50/50 1.09 MW 1.09 MW
924312 AB2-078 E O1 50/50 1.09 MW 1.09 MW
924322 AB2-079 E O1 50/50 1.09 MW 1.09 MW
925612 AC1-036 E Adder 0.49 MW 0.41 MW
939181 AE1-148 C Adder 3.83 MW 3.26 MW
939182 AE1-148 E Adder 2.56 MW 2.17 MW
941801 AE2-185 C 50/50 4.4 MW 4.4 MW
941802 AE2-185 E 50/50 2.94 MW 2.94 MW
941821 AE2-187 C 50/50 4.4 MW 4.4 MW
941822 AE2-187 E 50/50 1.96 MW 1.96 MW
946301 AF1-294 C Adder 1.42 MW 1.2 MW
946302 AF1-294 E Adder 1.2 MW 1.02 MW
958211 AF2-115 C Adder 0.86 MW 0.73 MW
958212 AF2-115 E Adder 0.73 MW 0.62 MW
314722 3TWITTYS Adder 0.54 MW 0.46 MW
936261 AD2-033 C 50/50 7.92 MW 7.92 MW
936262 AD2-033 E 50/50 5.28 MW 5.28 MW
316003 AC1-222 C 50/50 2.9 MW 2.9 MW
316237 AB2-079 C O1 50/50 0.27 MW 0.27 MW
316238 AB2-078 C O1 50/50 0.27 MW 0.27 MW
316239 AB2-077 C O1 50/50 0.27 MW 0.27 MW
316248 AF1-058 C 50/50 0.97 MW 0.97 MW
927264 AC1-222 E 50/50 11.88 MW 11.88 MW
316217 AC1-145 C 50/50 0.38 MW 0.38 MW
313527 AB2-043 C 50/50 0.4 MW 0.4 MW
924022 AB2-043 E O1 50/50 4.04 MW 4.04 MW
316197 AC1-042 C 50/50 0.32 MW 0.32 MW
925665 AC1-042 E 50/50 3.19 MW 3.19 MW
316123 AC1-075 C 50/50 2.06 MW 2.06 MW
925997 AC1-075 E 50/50 7.18 MW 7.18 MW
316205 AC1-080 C 50/50 0.69 MW 0.69 MW
926024 AC1-080 E 50/50 2.38 MW 2.38 MW
962561 AG1-105 C 50/50 16.73 MW 16.73 MW
962562 AG1-105 E 50/50 11.15 MW 11.15 MW
964241 AG1-285 C 50/50 8.84 MW 8.84 MW
964242 AG1-285 E 50/50 5.89 MW 5.89 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.78 MW 6.78 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.76 MW 2.76 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.59 MW 2.59 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.28 MW 0.28 MW
NY PJM->LTFIMP_NY CLTF 0.11 MW 0.11 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.27 MW 0.27 MW
WEC LTFEXP_WEC->PJM CLTF 0.14 MW 0.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.09 MW 0.09 MW
TVA LTFEXP_TVA->PJM CLTF 0.61 MW 0.61 MW
MEC LTFEXP_MEC->PJM CLTF 0.67 MW 0.67 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.72 MW 0.72 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.75 MW 1.75 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Base Case OP AC 164.69 % 167.0 A 275.04 18.38
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Base Case OP AC 163.36 % 167.0 A 272.82 18.38
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Base Case OP AC 161.25 % 167.0 A 269.28 18.38
AEP/DVP 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
OP AC 155.05 % 245.0 B 379.88 18.02
AEP 05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
OP AC 154.09 % 245.0 B 377.51 18.02
AEP 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
OP AC 152.59 % 245.0 B 373.85 18.02
AEP 05REDEYE-05CANDLER MT 138.0 kV Ckt 1 line
243814 to 242575 ckt 1
AEP_P1-2_#375_5201_SRT-A
CONTINGENCY 'AEP_P1-2_#375_5201_SRT-A'
 OPEN BRANCH FROM BUS 242687 TO BUS 242734 CKT 1   /*05JOHNMT     138.0 - 05NEWLDN     138.0
 OPEN BRANCH FROM BUS 242687 TO BUS 242741 CKT 1   /*05JOHNMT     138.0 - 05OTTER      138.0
 OPEN BRANCH FROM BUS 242741 TO BUS 314667 CKT 1   /*05OTTER      138.0 - 4ALTVSTA     138.0
END
OP AC 101.19 % 284.0 B 287.37 5.68
AEP 05JOSHUA-05JOSHUA_XFL 138.0 kV Ckt 1 line
242688 to 247670 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
OP AC 100.49 % 747.0 B 750.68 15.33
DVP 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
OP AC 206.24 % 101.52 B 209.37 52.99
DVP 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Base Case OP AC 199.41 % 101.52 A 202.44 52.99
DVP AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line
942670 to 314730 ckt 1
DVP_P1-2: LN 35_SRT-A-3
CONTINGENCY 'DVP_P1-2: LN 35_SRT-A-3'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TP    69.0
END
OP AC 172.99 % 66.74 B 115.45 53.0
DVP 3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line
314730 to 314709 ckt 1
DVP_P1-2: LN 35_SRT-A-3
CONTINGENCY 'DVP_P1-2: LN 35_SRT-A-3'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TP    69.0
END
OP AC 172.9 % 66.74 B 115.39 53.0
DVP 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
Base Case OP AC 171.63 % 128.78 A 221.03 52.99
DVP 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
OP AC 170.4 % 134.04 B 228.41 52.99
DVP AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line
942670 to 314730 ckt 1
Base Case OP AC 166.59 % 66.74 A 111.18 53.0
DVP 3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line
314730 to 314709 ckt 1
Base Case OP AC 166.5 % 66.74 A 111.12 53.0

Details for 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 164.69 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 275.04 MVA
MW Contribution: 18.38 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 133.12 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 222.3 MVA
MW Contribution: 18.11 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.76 MW 1.76 MW
315156 1HALLBR1 50/50 2.68 MW 2.68 MW
926274 AC1-105 E Adder 0.91 MW 0.78 MW
926646 AC1-145 E 50/50 5.91 MW 5.91 MW
942671 AE2-283 C 50/50 9.71 MW 9.71 MW
942672 AE2-283 E 50/50 8.67 MW 8.67 MW
942751 AE2-291 C 50/50 12.86 MW 12.86 MW
942752 AE2-291 E 50/50 8.57 MW 8.57 MW
943902 AF1-058 E Adder 0.5 MW 0.43 MW
960061 AF2-297 C Adder 3.03 MW 2.58 MW
960062 AF2-297 E Adder 2.02 MW 1.72 MW
940081 AE1-250 C Adder 5.18 MW 4.41 MW
940082 AE1-250 E Adder 3.46 MW 2.94 MW
941801 AE2-185 C 50/50 12.48 MW 12.48 MW
941802 AE2-185 E 50/50 8.32 MW 8.32 MW
941821 AE2-187 C 50/50 12.48 MW 12.48 MW
941822 AE2-187 E 50/50 5.55 MW 5.55 MW
926055 AC1-083 E Adder 5.63 MW 4.78 MW
927264 AC1-222 E Adder 2.3 MW 1.95 MW
316217 AC1-145 C 50/50 1.08 MW 1.08 MW
316197 AC1-042 C 50/50 0.9 MW 0.9 MW
925665 AC1-042 E 50/50 9.03 MW 9.03 MW
316123 AC1-075 C 50/50 1.13 MW 1.13 MW
925997 AC1-075 E 50/50 3.92 MW 3.92 MW
316205 AC1-080 C 50/50 0.38 MW 0.38 MW
926024 AC1-080 E 50/50 1.3 MW 1.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.54 MW 0.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.98 MW 7.98 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.11 MW 1.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.22 MW 0.22 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.11 MW 0.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.31 MW 0.31 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.09 MW 1.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.53 MW 0.53 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW

Details for 05OTTER-05JOHNMT 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 163.36 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 272.82 MVA
MW Contribution: 18.38 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 131.85 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 220.19 MVA
MW Contribution: 18.11 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.76 MW 1.76 MW
315156 1HALLBR1 50/50 2.68 MW 2.68 MW
926274 AC1-105 E Adder 0.91 MW 0.78 MW
926646 AC1-145 E 50/50 5.91 MW 5.91 MW
942671 AE2-283 C 50/50 9.71 MW 9.71 MW
942672 AE2-283 E 50/50 8.67 MW 8.67 MW
942751 AE2-291 C 50/50 12.86 MW 12.86 MW
942752 AE2-291 E 50/50 8.57 MW 8.57 MW
943902 AF1-058 E Adder 0.5 MW 0.43 MW
960061 AF2-297 C Adder 3.03 MW 2.58 MW
960062 AF2-297 E Adder 2.02 MW 1.72 MW
940081 AE1-250 C Adder 5.18 MW 4.41 MW
940082 AE1-250 E Adder 3.46 MW 2.94 MW
941801 AE2-185 C 50/50 12.48 MW 12.48 MW
941802 AE2-185 E 50/50 8.32 MW 8.32 MW
941821 AE2-187 C 50/50 12.48 MW 12.48 MW
941822 AE2-187 E 50/50 5.55 MW 5.55 MW
926055 AC1-083 E Adder 5.63 MW 4.78 MW
927264 AC1-222 E Adder 2.3 MW 1.95 MW
316217 AC1-145 C 50/50 1.08 MW 1.08 MW
316197 AC1-042 C 50/50 0.9 MW 0.9 MW
925665 AC1-042 E 50/50 9.03 MW 9.03 MW
316123 AC1-075 C 50/50 1.13 MW 1.13 MW
925997 AC1-075 E 50/50 3.92 MW 3.92 MW
316205 AC1-080 C 50/50 0.38 MW 0.38 MW
926024 AC1-080 E 50/50 1.3 MW 1.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.54 MW 0.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.98 MW 7.98 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.11 MW 1.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.22 MW 0.22 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.11 MW 0.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.31 MW 0.31 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.09 MW 1.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.53 MW 0.53 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW

Details for 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 161.25 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 269.28 MVA
MW Contribution: 18.38 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 129.81 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 216.78 MVA
MW Contribution: 18.11 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.76 MW 1.76 MW
315156 1HALLBR1 50/50 2.68 MW 2.68 MW
926274 AC1-105 E Adder 0.91 MW 0.78 MW
926646 AC1-145 E 50/50 5.91 MW 5.91 MW
942671 AE2-283 C 50/50 9.71 MW 9.71 MW
942672 AE2-283 E 50/50 8.67 MW 8.67 MW
942751 AE2-291 C 50/50 12.86 MW 12.86 MW
942752 AE2-291 E 50/50 8.57 MW 8.57 MW
943902 AF1-058 E Adder 0.5 MW 0.43 MW
960061 AF2-297 C Adder 3.03 MW 2.58 MW
960062 AF2-297 E Adder 2.02 MW 1.72 MW
940081 AE1-250 C Adder 5.18 MW 4.41 MW
940082 AE1-250 E Adder 3.46 MW 2.94 MW
941801 AE2-185 C 50/50 12.48 MW 12.48 MW
941802 AE2-185 E 50/50 8.32 MW 8.32 MW
941821 AE2-187 C 50/50 12.48 MW 12.48 MW
941822 AE2-187 E 50/50 5.55 MW 5.55 MW
926055 AC1-083 E Adder 5.63 MW 4.78 MW
927264 AC1-222 E Adder 2.3 MW 1.95 MW
316217 AC1-145 C 50/50 1.08 MW 1.08 MW
316197 AC1-042 C 50/50 0.9 MW 0.9 MW
925665 AC1-042 E 50/50 9.03 MW 9.03 MW
316123 AC1-075 C 50/50 1.13 MW 1.13 MW
925997 AC1-075 E 50/50 3.92 MW 3.92 MW
316205 AC1-080 C 50/50 0.38 MW 0.38 MW
926024 AC1-080 E 50/50 1.3 MW 1.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.54 MW 0.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.98 MW 7.98 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.11 MW 1.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.22 MW 0.22 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.11 MW 0.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.31 MW 0.31 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.09 MW 1.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.53 MW 0.53 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW

Details for 4ALTVSTA-05OTTER 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DVP
Facility Description:
4ALTVSTA-05OTTER 138.0 kV Ckt 1 line
314667 to 242741 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 155.05 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 379.88 MVA
MW Contribution: 18.02 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.73 MW 1.73 MW
315156 1HALLBR1 50/50 2.62 MW 2.62 MW
926274 AC1-105 E Adder 0.88 MW 0.75 MW
926646 AC1-145 E 50/50 5.8 MW 5.8 MW
942671 AE2-283 C 50/50 9.52 MW 9.52 MW
942672 AE2-283 E 50/50 8.5 MW 8.5 MW
942751 AE2-291 C 50/50 12.56 MW 12.56 MW
942752 AE2-291 E 50/50 8.38 MW 8.38 MW
943902 AF1-058 E Adder 0.49 MW 0.41 MW
960061 AF2-297 C Adder 2.93 MW 2.49 MW
960062 AF2-297 E Adder 1.95 MW 1.66 MW
940081 AE1-250 C Adder 5.19 MW 4.41 MW
940082 AE1-250 E Adder 3.46 MW 2.94 MW
941801 AE2-185 C 50/50 12.24 MW 12.24 MW
941802 AE2-185 E 50/50 8.16 MW 8.16 MW
941821 AE2-187 C 50/50 12.24 MW 12.24 MW
941822 AE2-187 E 50/50 5.44 MW 5.44 MW
926055 AC1-083 E Adder 5.57 MW 4.74 MW
927264 AC1-222 E Adder 2.23 MW 1.9 MW
316217 AC1-145 C 50/50 1.06 MW 1.06 MW
316197 AC1-042 C 50/50 0.89 MW 0.89 MW
925665 AC1-042 E 50/50 8.86 MW 8.86 MW
316123 AC1-075 C 50/50 1.1 MW 1.1 MW
925997 AC1-075 E 50/50 3.82 MW 3.82 MW
316205 AC1-080 C 50/50 0.37 MW 0.37 MW
926024 AC1-080 E 50/50 1.27 MW 1.27 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.34 MW 4.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.79 MW 2.79 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.59 MW 10.59 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.43 MW 0.43 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.17 MW 0.17 MW
WEC LTFEXP_WEC->PJM CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.73 MW 2.73 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 05OTTER-05JOHNMT 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05OTTER-05JOHNMT 138.0 kV Ckt 1 line
242741 to 242687 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 154.09 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 377.51 MVA
MW Contribution: 18.02 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.73 MW 1.73 MW
315156 1HALLBR1 50/50 2.62 MW 2.62 MW
926274 AC1-105 E Adder 0.88 MW 0.75 MW
926646 AC1-145 E 50/50 5.8 MW 5.8 MW
942671 AE2-283 C 50/50 9.52 MW 9.52 MW
942672 AE2-283 E 50/50 8.5 MW 8.5 MW
942751 AE2-291 C 50/50 12.56 MW 12.56 MW
942752 AE2-291 E 50/50 8.38 MW 8.38 MW
943902 AF1-058 E Adder 0.49 MW 0.41 MW
960061 AF2-297 C Adder 2.93 MW 2.49 MW
960062 AF2-297 E Adder 1.95 MW 1.66 MW
940081 AE1-250 C Adder 5.19 MW 4.41 MW
940082 AE1-250 E Adder 3.46 MW 2.94 MW
941801 AE2-185 C 50/50 12.24 MW 12.24 MW
941802 AE2-185 E 50/50 8.16 MW 8.16 MW
941821 AE2-187 C 50/50 12.24 MW 12.24 MW
941822 AE2-187 E 50/50 5.44 MW 5.44 MW
926055 AC1-083 E Adder 5.57 MW 4.74 MW
927264 AC1-222 E Adder 2.23 MW 1.9 MW
316217 AC1-145 C 50/50 1.06 MW 1.06 MW
316197 AC1-042 C 50/50 0.89 MW 0.89 MW
925665 AC1-042 E 50/50 8.86 MW 8.86 MW
316123 AC1-075 C 50/50 1.1 MW 1.1 MW
925997 AC1-075 E 50/50 3.82 MW 3.82 MW
316205 AC1-080 C 50/50 0.37 MW 0.37 MW
926024 AC1-080 E 50/50 1.27 MW 1.27 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.34 MW 4.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.79 MW 2.79 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.59 MW 10.59 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.43 MW 0.43 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.17 MW 0.17 MW
WEC LTFEXP_WEC->PJM CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.73 MW 2.73 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
242687 to 242734 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 152.59 %
Rating: 245.0 MVA
Rating Type: B
MVA to Mitigate: 373.85 MVA
MW Contribution: 18.02 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.73 MW 1.73 MW
315156 1HALLBR1 50/50 2.62 MW 2.62 MW
926274 AC1-105 E Adder 0.88 MW 0.75 MW
926646 AC1-145 E 50/50 5.8 MW 5.8 MW
942671 AE2-283 C 50/50 9.52 MW 9.52 MW
942672 AE2-283 E 50/50 8.5 MW 8.5 MW
942751 AE2-291 C 50/50 12.56 MW 12.56 MW
942752 AE2-291 E 50/50 8.38 MW 8.38 MW
943902 AF1-058 E Adder 0.49 MW 0.41 MW
960061 AF2-297 C Adder 2.93 MW 2.49 MW
960062 AF2-297 E Adder 1.95 MW 1.66 MW
940081 AE1-250 C Adder 5.19 MW 4.41 MW
940082 AE1-250 E Adder 3.46 MW 2.94 MW
941801 AE2-185 C 50/50 12.24 MW 12.24 MW
941802 AE2-185 E 50/50 8.16 MW 8.16 MW
941821 AE2-187 C 50/50 12.24 MW 12.24 MW
941822 AE2-187 E 50/50 5.44 MW 5.44 MW
926055 AC1-083 E Adder 5.57 MW 4.74 MW
927264 AC1-222 E Adder 2.23 MW 1.9 MW
316217 AC1-145 C 50/50 1.06 MW 1.06 MW
316197 AC1-042 C 50/50 0.89 MW 0.89 MW
925665 AC1-042 E 50/50 8.86 MW 8.86 MW
316123 AC1-075 C 50/50 1.1 MW 1.1 MW
925997 AC1-075 E 50/50 3.82 MW 3.82 MW
316205 AC1-080 C 50/50 0.37 MW 0.37 MW
926024 AC1-080 E 50/50 1.27 MW 1.27 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.34 MW 4.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.79 MW 2.79 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.59 MW 10.59 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.43 MW 0.43 MW
NY PJM->LTFIMP_NY CLTF 0.2 MW 0.2 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.17 MW 0.17 MW
WEC LTFEXP_WEC->PJM CLTF 0.09 MW 0.09 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 0.52 MW 0.52 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.73 MW 2.73 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 05REDEYE-05CANDLER MT 138.0 kV Ckt 1 line l/o AEP_P1-2_#375_5201_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05REDEYE-05CANDLER MT 138.0 kV Ckt 1 line
243814 to 242575 ckt 1
Contingency Name:
AEP_P1-2_#375_5201_SRT-A
CONTINGENCY 'AEP_P1-2_#375_5201_SRT-A'
 OPEN BRANCH FROM BUS 242687 TO BUS 242734 CKT 1   /*05JOHNMT     138.0 - 05NEWLDN     138.0
 OPEN BRANCH FROM BUS 242687 TO BUS 242741 CKT 1   /*05JOHNMT     138.0 - 05OTTER      138.0
 OPEN BRANCH FROM BUS 242741 TO BUS 314667 CKT 1   /*05OTTER      138.0 - 4ALTVSTA     138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 101.19 %
Rating: 284.0 MVA
Rating Type: B
MVA to Mitigate: 287.37 MVA
MW Contribution: 5.68 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.15 MW 1.15 MW
926646 AC1-145 E 50/50 1.83 MW 1.83 MW
942671 AE2-283 C 50/50 3.0 MW 3.0 MW
942672 AE2-283 E 50/50 2.68 MW 2.68 MW
942751 AE2-291 C Adder 3.99 MW 3.39 MW
942752 AE2-291 E Adder 2.66 MW 2.26 MW
940081 AE1-250 C Adder 8.82 MW 7.49 MW
940082 AE1-250 E Adder 5.88 MW 5.0 MW
941801 AE2-185 C 50/50 3.86 MW 3.86 MW
941802 AE2-185 E 50/50 2.57 MW 2.57 MW
941821 AE2-187 C 50/50 3.86 MW 3.86 MW
941822 AE2-187 E 50/50 1.72 MW 1.72 MW
246843 05SMG1 50/50 1.88 MW 1.88 MW
246844 05SMG2 50/50 5.18 MW 5.18 MW
246845 05SMG3 50/50 3.18 MW 3.18 MW
246846 05SMG4 50/50 5.18 MW 5.18 MW
246847 05SMG5 50/50 1.97 MW 1.97 MW
926055 AC1-083 E 50/50 9.81 MW 9.81 MW
316217 AC1-145 C 50/50 0.33 MW 0.33 MW
270197 AC1-083 C 50/50 0.98 MW 0.98 MW
270173 AC1-122 C 50/50 3.75 MW 3.75 MW
926516 AC1-122_E 50/50 10.8 MW 10.8 MW
316197 AC1-042 C 50/50 0.28 MW 0.28 MW
925665 AC1-042 E 50/50 2.79 MW 2.79 MW
925997 AC1-075 E Adder 1.23 MW 1.04 MW
926024 AC1-080 E Adder 0.41 MW 0.35 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.04 MW 1.04 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.26 MW 1.26 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 8.13 MW 8.13 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.24 MW 0.24 MW
NY PJM->LTFIMP_NY CLTF 0.12 MW 0.12 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.04 MW 0.04 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.04 MW 1.04 MW
TVA LTFEXP_TVA->PJM CLTF 0.37 MW 0.37 MW
MEC LTFEXP_MEC->PJM CLTF 0.18 MW 0.18 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.49 MW 0.49 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.56 MW 1.56 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.49 MW 0.49 MW

Details for 05JOSHUA-05JOSHUA_XFL 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOSHUA-05JOSHUA_XFL 138.0 kV Ckt 1 line
242688 to 247670 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.49 %
Rating: 747.0 MVA
Rating Type: B
MVA to Mitigate: 750.68 MVA
MW Contribution: 15.33 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 8.97 MW 8.97 MW
966252 AG1-494 E 50/50 13.45 MW 13.45 MW
247284 05LEESVG 50/50 1.98 MW 1.98 MW
315156 1HALLBR1 50/50 2.39 MW 2.39 MW
926646 AC1-145 E 50/50 4.93 MW 4.93 MW
942671 AE2-283 C 50/50 8.1 MW 8.1 MW
942672 AE2-283 E 50/50 7.23 MW 7.23 MW
942751 AE2-291 C 50/50 11.6 MW 11.6 MW
942752 AE2-291 E 50/50 7.73 MW 7.73 MW
242889 05REUSENS 50/50 0.3 MW 0.3 MW
940081 AE1-250 C 50/50 11.28 MW 11.28 MW
940082 AE1-250 E 50/50 7.52 MW 7.52 MW
941801 AE2-185 C 50/50 10.41 MW 10.41 MW
941802 AE2-185 E 50/50 6.94 MW 6.94 MW
941821 AE2-187 C 50/50 10.41 MW 10.41 MW
941822 AE2-187 E 50/50 4.63 MW 4.63 MW
958131 AF2-107 C 50/50 12.29 MW 12.29 MW
958132 AF2-107 E 50/50 6.74 MW 6.74 MW
246843 05SMG1 50/50 2.19 MW 2.19 MW
246844 05SMG2 50/50 6.03 MW 6.03 MW
246845 05SMG3 50/50 3.7 MW 3.7 MW
246846 05SMG4 50/50 6.03 MW 6.03 MW
246847 05SMG5 50/50 2.29 MW 2.29 MW
926055 AC1-083 E 50/50 11.9 MW 11.9 MW
927264 AC1-222 E Adder 2.17 MW 1.84 MW
962751 AG1-124 C 50/50 26.42 MW 26.42 MW
962752 AG1-124 E 50/50 18.44 MW 18.44 MW
316217 AC1-145 C 50/50 0.9 MW 0.9 MW
270197 AC1-083 C 50/50 1.19 MW 1.19 MW
270173 AC1-122 C 50/50 2.77 MW 2.77 MW
926516 AC1-122_E 50/50 7.96 MW 7.96 MW
316197 AC1-042 C 50/50 0.75 MW 0.75 MW
925665 AC1-042 E 50/50 7.53 MW 7.53 MW
316123 AC1-075 C 50/50 1.02 MW 1.02 MW
925997 AC1-075 E 50/50 3.55 MW 3.55 MW
316205 AC1-080 C 50/50 0.34 MW 0.34 MW
926024 AC1-080 E 50/50 1.18 MW 1.18 MW
938821 AE1-108 C 50/50 13.78 MW 13.78 MW
938822 AE1-108 E 50/50 6.58 MW 6.58 MW
940601 AE2-047 C Adder 2.13 MW 1.81 MW
940602 AE2-047 E Adder 1.16 MW 0.98 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 30.12 MW 30.12 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 14.44 MW 14.44 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 29.54 MW 29.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.95 MW 1.95 MW
NY PJM->LTFIMP_NY CLTF 0.85 MW 0.85 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.2 MW 1.2 MW
WEC LTFEXP_WEC->PJM CLTF 0.61 MW 0.61 MW
CPLE LTFEXP_CPLE->PJM CLTF 2.67 MW 2.67 MW
TVA LTFEXP_TVA->PJM CLTF 3.45 MW 3.45 MW
MEC LTFEXP_MEC->PJM CLTF 3.15 MW 3.15 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.19 MW 4.19 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.21 MW 0.21 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 12.4 MW 12.4 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.28 MW 1.28 MW

Details for 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line l/o DVP_P1-2: LN 173_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Contingency Name:
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 206.24 %
Rating: 101.52 MVA
Rating Type: B
MVA to Mitigate: 209.37 MVA
MW Contribution: 52.99 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Contingency Name:
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 206.28 %
Rating: 101.52 MVA
Rating Type: B
MVA to Mitigate: 209.41 MVA
MW Contribution: 52.99 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
926646 AC1-145 E 50/50 17.05 MW 17.05 MW
942671 AE2-283 C 50/50 28.0 MW 28.0 MW
942672 AE2-283 E 50/50 25.0 MW 25.0 MW
941801 AE2-185 C 50/50 35.99 MW 35.99 MW
941802 AE2-185 E 50/50 24.0 MW 24.0 MW
941821 AE2-187 C 50/50 35.99 MW 35.99 MW
941822 AE2-187 E 50/50 16.0 MW 16.0 MW
316217 AC1-145 C 50/50 3.1 MW 3.1 MW
316197 AC1-042 C 50/50 2.61 MW 2.61 MW
925665 AC1-042 E 50/50 26.04 MW 26.04 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.05 MW 0.05 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.12 MW 0.12 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.02 MW 0.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for 2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 199.41 %
Rating: 101.52 MVA
Rating Type: A
MVA to Mitigate: 202.44 MVA
MW Contribution: 52.99 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
2GLADYS TAP-2ALTVSTA 69.0 kV Ckt 1 line
314709 to 314670 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 199.45 %
Rating: 101.52 MVA
Rating Type: A
MVA to Mitigate: 202.48 MVA
MW Contribution: 52.99 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
926646 AC1-145 E 50/50 17.05 MW 17.05 MW
942671 AE2-283 C 50/50 28.0 MW 28.0 MW
942672 AE2-283 E 50/50 25.0 MW 25.0 MW
941801 AE2-185 C 50/50 35.99 MW 35.99 MW
941802 AE2-185 E 50/50 24.0 MW 24.0 MW
941821 AE2-187 C 50/50 35.99 MW 35.99 MW
941822 AE2-187 E 50/50 16.0 MW 16.0 MW
316217 AC1-145 C 50/50 3.1 MW 3.1 MW
316197 AC1-042 C 50/50 2.61 MW 2.61 MW
925665 AC1-042 E 50/50 26.04 MW 26.04 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.05 MW 0.05 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.12 MW 0.12 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.02 MW 0.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line l/o DVP_P1-2: LN 35_SRT-A-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line
942670 to 314730 ckt 1
Contingency Name:
DVP_P1-2: LN 35_SRT-A-3
CONTINGENCY 'DVP_P1-2: LN 35_SRT-A-3'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TP    69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 172.99 %
Rating: 66.74 MVA
Rating Type: B
MVA to Mitigate: 115.45 MVA
MW Contribution: 53.0 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line
942670 to 314730 ckt 1
Contingency Name:
DVP_P1-2: LN 35_SRT-A-3
CONTINGENCY 'DVP_P1-2: LN 35_SRT-A-3'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TP    69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 173.01 %
Rating: 66.74 MVA
Rating Type: B
MVA to Mitigate: 115.47 MVA
MW Contribution: 53.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
942671 AE2-283 C 50/50 28 MW 28 MW
942672 AE2-283 E 50/50 25 MW 25 MW
941801 AE2-185 C 50/50 36 MW 36 MW
941802 AE2-185 E 50/50 24 MW 24 MW

Details for 3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line l/o DVP_P1-2: LN 35_SRT-A-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line
314730 to 314709 ckt 1
Contingency Name:
DVP_P1-2: LN 35_SRT-A-3
CONTINGENCY 'DVP_P1-2: LN 35_SRT-A-3'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TP    69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 172.9 %
Rating: 66.74 MVA
Rating Type: B
MVA to Mitigate: 115.39 MVA
MW Contribution: 53.0 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line
314730 to 314709 ckt 1
Contingency Name:
DVP_P1-2: LN 35_SRT-A-3
CONTINGENCY 'DVP_P1-2: LN 35_SRT-A-3'
 OPEN BRANCH FROM BUS 314729 TO BUS 941800 CKT 1   /*2GLADYS       69.0 - AE2-185 TP    69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 172.91 %
Rating: 66.74 MVA
Rating Type: B
MVA to Mitigate: 115.4 MVA
MW Contribution: 53.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
942671 AE2-283 C 50/50 28 MW 28 MW
942672 AE2-283 E 50/50 25 MW 25 MW
941801 AE2-185 C 50/50 36 MW 36 MW
941802 AE2-185 E 50/50 24 MW 24 MW

Details for 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 171.63 %
Rating: 128.78 MVA
Rating Type: A
MVA to Mitigate: 221.03 MVA
MW Contribution: 52.99 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 171.78 %
Rating: 128.78 MVA
Rating Type: A
MVA to Mitigate: 221.22 MVA
MW Contribution: 52.99 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
926646 AC1-145 E 50/50 17.05 MW 17.05 MW
942671 AE2-283 C 50/50 28.0 MW 28.0 MW
942672 AE2-283 E 50/50 25.0 MW 25.0 MW
941801 AE2-185 C 50/50 35.99 MW 35.99 MW
941802 AE2-185 E 50/50 24.0 MW 24.0 MW
941821 AE2-187 C 50/50 35.99 MW 35.99 MW
941822 AE2-187 E 50/50 16.0 MW 16.0 MW
316217 AC1-145 C 50/50 3.1 MW 3.1 MW
316197 AC1-042 C 50/50 2.61 MW 2.61 MW
925665 AC1-042 E 50/50 26.04 MW 26.04 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.05 MW 0.05 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.12 MW 0.12 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.02 MW 0.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for 2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer l/o DVP_P1-2: LN 173_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
Contingency Name:
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 170.4 %
Rating: 134.04 MVA
Rating Type: B
MVA to Mitigate: 228.41 MVA
MW Contribution: 52.99 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
2ALTVSTA-4ALTVSTA 69.0/138.0 kV Ckt 1 transformer
314670 to 314667 ckt 1
Contingency Name:
DVP_P1-2: LN 173_SRT-A-1
CONTINGENCY 'DVP_P1-2: LN 173_SRT-A-1'
 OPEN BRANCH FROM BUS 314680 TO BUS 941820 CKT 1   /*2CHATHAM      69.0 - AE2-187 TP    69.0
 OPEN BUS 314680                                   /*2CHATHAM      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 170.55 %
Rating: 134.04 MVA
Rating Type: B
MVA to Mitigate: 228.6 MVA
MW Contribution: 52.99 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
926646 AC1-145 E 50/50 17.05 MW 17.05 MW
942671 AE2-283 C 50/50 28.0 MW 28.0 MW
942672 AE2-283 E 50/50 25.0 MW 25.0 MW
941801 AE2-185 C 50/50 35.99 MW 35.99 MW
941802 AE2-185 E 50/50 24.0 MW 24.0 MW
941821 AE2-187 C 50/50 35.99 MW 35.99 MW
941822 AE2-187 E 50/50 16.0 MW 16.0 MW
316217 AC1-145 C 50/50 3.1 MW 3.1 MW
316197 AC1-042 C 50/50 2.61 MW 2.61 MW
925665 AC1-042 E 50/50 26.04 MW 26.04 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.05 MW 0.05 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.03 MW 0.03 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.12 MW 0.12 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.02 MW 0.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line
942670 to 314730 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 166.59 %
Rating: 66.74 MVA
Rating Type: A
MVA to Mitigate: 111.18 MVA
MW Contribution: 53.0 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
AE2-283 TP-3STONE MILL 69.0 kV Ckt 1 line
942670 to 314730 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 166.6 %
Rating: 66.74 MVA
Rating Type: A
MVA to Mitigate: 111.19 MVA
MW Contribution: 53.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
942671 AE2-283 C 50/50 28 MW 28 MW
942672 AE2-283 E 50/50 25 MW 25 MW
941801 AE2-185 C 50/50 36 MW 36 MW
941802 AE2-185 E 50/50 24 MW 24 MW

Details for 3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line
314730 to 314709 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 166.5 %
Rating: 66.74 MVA
Rating Type: A
MVA to Mitigate: 111.12 MVA
MW Contribution: 53.0 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
3STONE MILL-2GLADYS TAP 69.0 kV Ckt 1 line
314730 to 314709 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 166.51 %
Rating: 66.74 MVA
Rating Type: A
MVA to Mitigate: 111.13 MVA
MW Contribution: 53.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
942671 AE2-283 C 50/50 28 MW 28 MW
942672 AE2-283 E 50/50 25 MW 25 MW
941801 AE2-185 C 50/50 36 MW 36 MW
941802 AE2-185 E 50/50 24 MW 24 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 4ALTVSTA-3ALTVSTA 138.0/115.0 kV Ckt 2 transformer
314667 to 314666 ckt 2
DVP_P1-3: 4ALTVSTA-TX#3_SRT-A
CONTINGENCY 'DVP_P1-3: 4ALTVSTA-TX#3_SRT-A'
 OPEN BRANCH FROM BUS 314666 TO BUS 314667 CKT 1   /*3ALTVSTA     115.0 - 4ALTVSTA     138.0
END
OP AC 110.42 % 130.47 B 144.06 14.34
DVP 4ALTVSTA-3ALTVSTA 138.0/115.0 kV Ckt 1 transformer
314667 to 314666 ckt 1
DVP_P1-3: 4ALTVSTA-TX#4_SRT-A
CONTINGENCY 'DVP_P1-3: 4ALTVSTA-TX#4_SRT-A'
 OPEN BRANCH FROM BUS 314666 TO BUS 314667 CKT 2   /*3ALTVSTA     115.0 - 4ALTVSTA     138.0
END
OP AC 106.61 % 126.52 B 134.88 13.5
DVP AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line
316000 to 313168 ckt 1
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
OP AC 105.86 % 285.76 B 302.51 11.81
DVP 3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line
313168 to 314696 ckt 1
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
OP AC 105.68 % 285.76 B 302.0 11.81
DVP 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line
314901 to 314991 ckt 1
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
OP AC 104.77 % 3220.44 B 3374.15 7.45
DVP 8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line
314991 to 314926 ckt 1
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
OP AC 104.55 % 3220.44 B 3366.96 7.45

Details for 4ALTVSTA-3ALTVSTA 138.0/115.0 kV Ckt 2 transformer l/o DVP_P1-3: 4ALTVSTA-TX#3_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
4ALTVSTA-3ALTVSTA 138.0/115.0 kV Ckt 2 transformer
314667 to 314666 ckt 2
Contingency Name:
DVP_P1-3: 4ALTVSTA-TX#3_SRT-A
CONTINGENCY 'DVP_P1-3: 4ALTVSTA-TX#3_SRT-A'
 OPEN BRANCH FROM BUS 314666 TO BUS 314667 CKT 1   /*3ALTVSTA     115.0 - 4ALTVSTA     138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 110.42 %
Rating: 130.47 MVA
Rating Type: B
MVA to Mitigate: 144.06 MVA
MW Contribution: 14.34 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.46 MW 1.46 MW
926646 AC1-145 E 50/50 4.61 MW 4.61 MW
942671 AE2-283 C 50/50 7.58 MW 7.58 MW
942672 AE2-283 E 50/50 6.76 MW 6.76 MW
941801 AE2-185 C 50/50 9.74 MW 9.74 MW
941802 AE2-185 E 50/50 6.49 MW 6.49 MW
941821 AE2-187 C 50/50 9.74 MW 9.74 MW
941822 AE2-187 E 50/50 4.33 MW 4.33 MW
926055 AC1-083 E Adder 5.24 MW 4.46 MW
316217 AC1-145 C 50/50 0.84 MW 0.84 MW
926516 AC1-122_E Adder 2.03 MW 1.72 MW
316197 AC1-042 C 50/50 0.7 MW 0.7 MW
925665 AC1-042 E 50/50 7.05 MW 7.05 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.4 MW 6.4 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.97 MW 1.97 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.16 MW 0.16 MW
NY PJM->LTFIMP_NY CLTF 0.05 MW 0.05 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 0.13 MW 0.13 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.34 MW 0.34 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.08 MW 0.08 MW
TVA LTFEXP_TVA->PJM CLTF 0.36 MW 0.36 MW
MEC LTFEXP_MEC->PJM CLTF 0.57 MW 0.57 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.39 MW 0.39 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.99 MW 0.99 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.64 MW 0.64 MW

Details for 4ALTVSTA-3ALTVSTA 138.0/115.0 kV Ckt 1 transformer l/o DVP_P1-3: 4ALTVSTA-TX#4_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
4ALTVSTA-3ALTVSTA 138.0/115.0 kV Ckt 1 transformer
314667 to 314666 ckt 1
Contingency Name:
DVP_P1-3: 4ALTVSTA-TX#4_SRT-A
CONTINGENCY 'DVP_P1-3: 4ALTVSTA-TX#4_SRT-A'
 OPEN BRANCH FROM BUS 314666 TO BUS 314667 CKT 2   /*3ALTVSTA     115.0 - 4ALTVSTA     138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 106.61 %
Rating: 126.52 MVA
Rating Type: B
MVA to Mitigate: 134.88 MVA
MW Contribution: 13.5 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247284 05LEESVG 50/50 1.37 MW 1.37 MW
926646 AC1-145 E 50/50 4.34 MW 4.34 MW
942671 AE2-283 C 50/50 7.13 MW 7.13 MW
942672 AE2-283 E 50/50 6.37 MW 6.37 MW
941801 AE2-185 C 50/50 9.17 MW 9.17 MW
941802 AE2-185 E 50/50 6.11 MW 6.11 MW
941821 AE2-187 C 50/50 9.17 MW 9.17 MW
941822 AE2-187 E 50/50 4.08 MW 4.08 MW
926055 AC1-083 E Adder 4.94 MW 4.2 MW
316217 AC1-145 C 50/50 0.79 MW 0.79 MW
926516 AC1-122_E Adder 1.91 MW 1.62 MW
316197 AC1-042 C 50/50 0.66 MW 0.66 MW
925665 AC1-042 E 50/50 6.63 MW 6.63 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.02 MW 6.02 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.85 MW 1.85 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.15 MW 0.15 MW
NY PJM->LTFIMP_NY CLTF 0.05 MW 0.05 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.24 MW 0.24 MW
WEC LTFEXP_WEC->PJM CLTF 0.12 MW 0.12 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.32 MW 0.32 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.08 MW 0.08 MW
TVA LTFEXP_TVA->PJM CLTF 0.34 MW 0.34 MW
MEC LTFEXP_MEC->PJM CLTF 0.54 MW 0.54 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.37 MW 0.37 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.93 MW 0.93 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.6 MW 0.6 MW

Details for AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line l/o AEP_P1-2_#5366_42_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line
316000 to 313168 ckt 1
Contingency Name:
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.86 %
Rating: 285.76 MVA
Rating Type: B
MVA to Mitigate: 302.51 MVA
MW Contribution: 11.81 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 1.3 MW 1.11 MW
966252 AG1-494 E Adder 1.96 MW 1.66 MW
247284 05LEESVG 50/50 1.33 MW 1.33 MW
315156 1HALLBR1 50/50 2.24 MW 2.24 MW
926646 AC1-145 E 50/50 3.8 MW 3.8 MW
942671 AE2-283 C 50/50 6.24 MW 6.24 MW
942672 AE2-283 E 50/50 5.57 MW 5.57 MW
942751 AE2-291 C 50/50 30.94 MW 30.94 MW
942752 AE2-291 E 50/50 20.63 MW 20.63 MW
940081 AE1-250 C 50/50 10.19 MW 10.19 MW
940082 AE1-250 E 50/50 6.79 MW 6.79 MW
941801 AE2-185 C 50/50 8.02 MW 8.02 MW
941802 AE2-185 E 50/50 5.35 MW 5.35 MW
941821 AE2-187 C 50/50 8.02 MW 8.02 MW
941822 AE2-187 E 50/50 3.56 MW 3.56 MW
246843 05SMG1 50/50 1.2 MW 1.2 MW
246844 05SMG2 50/50 3.3 MW 3.3 MW
246845 05SMG3 50/50 2.03 MW 2.03 MW
246846 05SMG4 50/50 3.3 MW 3.3 MW
246847 05SMG5 50/50 1.25 MW 1.25 MW
316003 AC1-222 C 50/50 5.01 MW 5.01 MW
926055 AC1-083 E 50/50 8.42 MW 8.42 MW
927264 AC1-222 E 50/50 20.52 MW 20.52 MW
962751 AG1-124 C Adder 3.5 MW 2.98 MW
962752 AG1-124 E Adder 2.44 MW 2.08 MW
316217 AC1-145 C 50/50 0.69 MW 0.69 MW
270197 AC1-083 C 50/50 0.84 MW 0.84 MW
270173 AC1-122 C 50/50 0.89 MW 0.89 MW
926516 AC1-122_E 50/50 2.58 MW 2.58 MW
316197 AC1-042 C 50/50 0.58 MW 0.58 MW
925665 AC1-042 E 50/50 5.8 MW 5.8 MW
316123 AC1-075 C 50/50 3.59 MW 3.59 MW
925997 AC1-075 E 50/50 12.49 MW 12.49 MW
316205 AC1-080 C 50/50 1.2 MW 1.2 MW
926024 AC1-080 E 50/50 4.14 MW 4.14 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.37 MW 6.37 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.46 MW 1.46 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.26 MW 0.26 MW
NY PJM->LTFIMP_NY CLTF 0.1 MW 0.1 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 0.13 MW 0.13 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.72 MW 0.72 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.25 MW 0.25 MW
TVA LTFEXP_TVA->PJM CLTF 0.19 MW 0.19 MW
MEC LTFEXP_MEC->PJM CLTF 0.53 MW 0.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.15 MW 0.15 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.61 MW 1.61 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.26 MW 1.26 MW

Details for 3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line l/o AEP_P1-2_#5366_42_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line
313168 to 314696 ckt 1
Contingency Name:
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.68 %
Rating: 285.76 MVA
Rating Type: B
MVA to Mitigate: 302.0 MVA
MW Contribution: 11.81 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 1.3 MW 1.11 MW
966252 AG1-494 E Adder 1.96 MW 1.66 MW
247284 05LEESVG 50/50 1.33 MW 1.33 MW
315156 1HALLBR1 50/50 2.24 MW 2.24 MW
926646 AC1-145 E 50/50 3.8 MW 3.8 MW
942671 AE2-283 C 50/50 6.24 MW 6.24 MW
942672 AE2-283 E 50/50 5.57 MW 5.57 MW
942751 AE2-291 C 50/50 30.94 MW 30.94 MW
942752 AE2-291 E 50/50 20.63 MW 20.63 MW
940081 AE1-250 C 50/50 10.19 MW 10.19 MW
940082 AE1-250 E 50/50 6.79 MW 6.79 MW
941801 AE2-185 C 50/50 8.02 MW 8.02 MW
941802 AE2-185 E 50/50 5.35 MW 5.35 MW
941821 AE2-187 C 50/50 8.02 MW 8.02 MW
941822 AE2-187 E 50/50 3.56 MW 3.56 MW
246843 05SMG1 50/50 1.2 MW 1.2 MW
246844 05SMG2 50/50 3.3 MW 3.3 MW
246845 05SMG3 50/50 2.03 MW 2.03 MW
246846 05SMG4 50/50 3.3 MW 3.3 MW
246847 05SMG5 50/50 1.25 MW 1.25 MW
316003 AC1-222 C 50/50 5.01 MW 5.01 MW
926055 AC1-083 E 50/50 8.42 MW 8.42 MW
927264 AC1-222 E 50/50 20.52 MW 20.52 MW
962751 AG1-124 C Adder 3.5 MW 2.98 MW
962752 AG1-124 E Adder 2.44 MW 2.08 MW
316217 AC1-145 C 50/50 0.69 MW 0.69 MW
270197 AC1-083 C 50/50 0.84 MW 0.84 MW
270173 AC1-122 C 50/50 0.89 MW 0.89 MW
926516 AC1-122_E 50/50 2.58 MW 2.58 MW
316197 AC1-042 C 50/50 0.58 MW 0.58 MW
925665 AC1-042 E 50/50 5.8 MW 5.8 MW
316123 AC1-075 C 50/50 3.59 MW 3.59 MW
925997 AC1-075 E 50/50 12.49 MW 12.49 MW
316205 AC1-080 C 50/50 1.2 MW 1.2 MW
926024 AC1-080 E 50/50 4.14 MW 4.14 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.37 MW 6.37 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.46 MW 1.46 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.26 MW 0.26 MW
NY PJM->LTFIMP_NY CLTF 0.1 MW 0.1 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 0.13 MW 0.13 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.72 MW 0.72 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.25 MW 0.25 MW
TVA LTFEXP_TVA->PJM CLTF 0.19 MW 0.19 MW
MEC LTFEXP_MEC->PJM CLTF 0.53 MW 0.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.15 MW 0.15 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.61 MW 1.61 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.26 MW 1.26 MW

Details for 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 555_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line
314901 to 314991 ckt 1
Contingency Name:
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.77 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3374.15 MVA
MW Contribution: 7.45 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 3.06 MW 2.6 MW
966252 AG1-494 E Adder 4.6 MW 3.91 MW
926646 AC1-145 E Adder 2.4 MW 2.04 MW
942671 AE2-283 C Adder 3.93 MW 3.34 MW
942672 AE2-283 E Adder 3.51 MW 2.99 MW
943031 AE2-326 C Adder 4.43 MW 3.77 MW
943032 AE2-326 E Adder 2.95 MW 2.51 MW
242889 05REUSENS 50/50 0.12 MW 0.12 MW
244165 05FRIES Adder 0.72 MW 0.61 MW
941801 AE2-185 C Adder 5.06 MW 4.3 MW
941802 AE2-185 E Adder 3.37 MW 2.87 MW
941821 AE2-187 C Adder 5.06 MW 4.3 MW
941822 AE2-187 E Adder 2.25 MW 1.91 MW
958121 AF2-106 C Adder 14.69 MW 12.48 MW
958122 AF2-106 E Adder 9.79 MW 8.32 MW
958131 AF2-107 C Adder 3.77 MW 3.21 MW
958132 AF2-107 E Adder 2.07 MW 1.76 MW
940451 AE2-029 C Adder -4.93 MW -4.19 MW
313738 3CUSHAW 50/50 0.28 MW 0.28 MW
314860 4E MILL 50/50 15.81 MW 15.81 MW
315186 1LOWMORA 50/50 1.29 MW 1.29 MW
315188 1LOWMORC 50/50 1.3 MW 1.3 MW
315201 1BATH 1A 50/50 47.86 MW 47.86 MW
315202 1BATH 2B 50/50 47.86 MW 47.86 MW
315203 1BATH 3C 50/50 47.89 MW 47.89 MW
315204 1BATH 4D 50/50 47.88 MW 47.88 MW
315205 1BATH 5E 50/50 47.94 MW 47.94 MW
315206 1BATH 6F 50/50 48.03 MW 48.03 MW
941671 AE2-166 C Adder 7.02 MW 5.96 MW
941672 AE2-166 E Adder 4.68 MW 3.98 MW
316370 X2-060 E 50/50 9.49 MW 9.49 MW
918234 AA1-038_E 50/50 21.54 MW 21.54 MW
926055 AC1-083 E Adder 9.77 MW 8.3 MW
932996 AC2-123 E Adder 4.3 MW 3.66 MW
962751 AG1-124 C 50/50 8.97 MW 8.97 MW
962752 AG1-124 E 50/50 6.26 MW 6.26 MW
270205 AE1-176 50/50 0.08 MW 0.08 MW
926516 AC1-122_E Adder 4.22 MW 3.59 MW
925665 AC1-042 E Adder 3.66 MW 3.11 MW
937351 AD2-179 C Adder 9.78 MW 8.32 MW
937352 AD2-179 E Adder 6.52 MW 5.54 MW
938742 AE1-100 E Adder 3.01 MW 2.56 MW
941431 AE2-140 C Adder 14.41 MW 12.25 MW
941432 AE2-140 E Adder 9.61 MW 8.16 MW
966391 AG1-508 C Adder 1.29 MW 1.1 MW
966392 AG1-508 E Adder 7.5 MW 6.37 MW
940601 AE2-047 C Adder 3.82 MW 3.24 MW
940602 AE2-047 E Adder 2.07 MW 1.76 MW
315616 AA1-038_C 50/50 3.19 MW 3.19 MW
270167 AD2-205 E Adder 0.65 MW 0.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 88.3 MW 88.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 41.42 MW 41.42 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 58.94 MW 58.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 5.88 MW 5.88 MW
NY PJM->LTFIMP_NY CLTF 2.7 MW 2.7 MW
LGEE LTFEXP_LGEE->PJM CLTF 3.69 MW 3.69 MW
WEC LTFEXP_WEC->PJM CLTF 1.81 MW 1.81 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.38 MW 3.38 MW
TVA LTFEXP_TVA->PJM CLTF 9.84 MW 9.84 MW
MEC LTFEXP_MEC->PJM CLTF 9.24 MW 9.24 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.64 MW 11.64 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.64 MW 0.64 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 37.45 MW 37.45 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.64 MW 1.64 MW

Details for 8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 555_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line
314991 to 314926 ckt 1
Contingency Name:
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.55 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3366.96 MVA
MW Contribution: 7.45 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 3.06 MW 2.6 MW
966252 AG1-494 E Adder 4.6 MW 3.91 MW
926646 AC1-145 E Adder 2.4 MW 2.04 MW
942671 AE2-283 C Adder 3.93 MW 3.34 MW
942672 AE2-283 E Adder 3.51 MW 2.99 MW
943031 AE2-326 C Adder 4.43 MW 3.77 MW
943032 AE2-326 E Adder 2.95 MW 2.51 MW
242889 05REUSENS 50/50 0.12 MW 0.12 MW
244165 05FRIES Adder 0.72 MW 0.61 MW
941801 AE2-185 C Adder 5.06 MW 4.3 MW
941802 AE2-185 E Adder 3.37 MW 2.87 MW
941821 AE2-187 C Adder 5.06 MW 4.3 MW
941822 AE2-187 E Adder 2.25 MW 1.91 MW
958121 AF2-106 C Adder 14.69 MW 12.48 MW
958122 AF2-106 E Adder 9.79 MW 8.32 MW
958131 AF2-107 C Adder 3.77 MW 3.21 MW
958132 AF2-107 E Adder 2.07 MW 1.76 MW
940451 AE2-029 C Adder -4.93 MW -4.19 MW
313738 3CUSHAW 50/50 0.28 MW 0.28 MW
314860 4E MILL 50/50 15.81 MW 15.81 MW
315186 1LOWMORA 50/50 1.29 MW 1.29 MW
315188 1LOWMORC 50/50 1.3 MW 1.3 MW
315201 1BATH 1A 50/50 47.86 MW 47.86 MW
315202 1BATH 2B 50/50 47.86 MW 47.86 MW
315203 1BATH 3C 50/50 47.89 MW 47.89 MW
315204 1BATH 4D 50/50 47.88 MW 47.88 MW
315205 1BATH 5E 50/50 47.94 MW 47.94 MW
315206 1BATH 6F 50/50 48.03 MW 48.03 MW
941671 AE2-166 C Adder 7.02 MW 5.96 MW
941672 AE2-166 E Adder 4.68 MW 3.98 MW
316370 X2-060 E 50/50 9.49 MW 9.49 MW
918234 AA1-038_E 50/50 21.54 MW 21.54 MW
926055 AC1-083 E Adder 9.77 MW 8.3 MW
932996 AC2-123 E Adder 4.3 MW 3.66 MW
962751 AG1-124 C 50/50 8.97 MW 8.97 MW
962752 AG1-124 E 50/50 6.26 MW 6.26 MW
270205 AE1-176 50/50 0.08 MW 0.08 MW
926516 AC1-122_E Adder 4.22 MW 3.59 MW
925665 AC1-042 E Adder 3.66 MW 3.11 MW
937351 AD2-179 C Adder 9.78 MW 8.32 MW
937352 AD2-179 E Adder 6.52 MW 5.54 MW
938742 AE1-100 E Adder 3.01 MW 2.56 MW
941431 AE2-140 C Adder 14.41 MW 12.25 MW
941432 AE2-140 E Adder 9.61 MW 8.16 MW
966391 AG1-508 C Adder 1.29 MW 1.1 MW
966392 AG1-508 E Adder 7.5 MW 6.37 MW
940601 AE2-047 C Adder 3.82 MW 3.24 MW
940602 AE2-047 E Adder 2.07 MW 1.76 MW
315616 AA1-038_C 50/50 3.19 MW 3.19 MW
270167 AD2-205 E Adder 0.65 MW 0.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 88.3 MW 88.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 41.42 MW 41.42 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 58.94 MW 58.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 5.88 MW 5.88 MW
NY PJM->LTFIMP_NY CLTF 2.7 MW 2.7 MW
LGEE LTFEXP_LGEE->PJM CLTF 3.69 MW 3.69 MW
WEC LTFEXP_WEC->PJM CLTF 1.81 MW 1.81 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.38 MW 3.38 MW
TVA LTFEXP_TVA->PJM CLTF 9.84 MW 9.84 MW
MEC LTFEXP_MEC->PJM CLTF 9.24 MW 9.24 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.64 MW 11.64 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.64 MW 0.64 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 37.45 MW 37.45 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.64 MW 1.64 MW

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios:

 

  • Scenario 1 - TC1 Project Impacts;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

 

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1. The result is detailed in the following table:

 

 Short Circuit Analysis

 

 

 

 

 

 

 

Bus Name

Breaker

Interrupting Capability (Amps)

Duty Percent TC1 Phase 3 - Scenario 2 Topology Upgrades (%)

Duty Percent TC1 Phase 3 - Scenario 2 No Topology Upgrades (%)

Duty Percent Difference (%)

Reinforcement

Projected In Service Date (ISD)

BRAMBLETON 230.kV

20102

63000

103.66%

95.89%

7.76%

b3800.405

1/8/2031

BRAMBLETON 230.kV

20602

63000

105.40%

97.28%

8.12%

b3800.405

1/8/2031

BRAMBLETON 230.kV

204502

63000

105.03%

97.32%

7.72%

b3800.405

1/8/2031

BRAMBLETON 230.kV

209402

63000

105.07%

97.35%

7.72%

b3800.405

1/8/2031

BRAMBLETON 230.kV

217202

63000

103.17%

95.89%

7.28%

b4000.103

1/8/2031

BRAMBLETON 230.kV

218302

63000

109.45%

101.02%

8.43%

b3689.2

3/31/2027

BRAMBLETON 230.kV

201T2045

63000

105.03%

97.32%

7.72%

b3800.405

1/8/2031

BRAMBLETON 230.kV

206T2094

63000

105.40%

97.35%

8.05%

b3800.405

1/8/2031

BRAMBLETON 230.kV

2172T2183

63000

107.20%

99.03%

8.17%

b4000.103

1/8/2031

BRAMBLETON 230.kV

H302

63000

109.45%

101.02%

8.43%

b3689.2

3/31/2027

BRAMBLETON 230.kV

H402

63000

109.45%

101.02%

8.43%

b3689.2

3/31/2027

BRAMBLETON 230.kV

L102

63000

103.17%

95.89%

7.28%

b4000.103

6/1/2028

BRAMBLETON 230.kV

SC102

63000

109.45%

101.02%

8.43%

b3689.2

3/31/2027

CARSON 230.kV

23872

40000

100.25%

98.16%

2.09%

b4000.108

6/12/2029

CARSON 230.kV

200272

40000

100.40%

98.51%

1.88%

b3854.1

6/1/2025

GAINESVILLE 230.kV

216192

40000

126.89%

104.16%

22.73%

b3800.406

3/15/2030

IDYLWOOD 230.kV

20212

40000

103.71%

100.35%

3.35%

b1696

12/30/2026

IDYLWOOD 230.kV

20712

40000

101.95%

98.56%

3.39%

b1696

12/30/2026

LADYSMITH 500.kV

568T575

40000

103.90%

88.38%

15.52%

b4000.354

11/14/2029

LADYSMITH 500.kV

574T581

40000

112.03%

87.44%

24.59%

b4000.115

11/27/2031

LADYSMITH S1 230.kV

GT172

40000

101.24%

94.15%

7.09%

b4000.114

7/18/2030

LADYSMITH S1 230.kV

GT272

40000

101.24%

94.15%

7.09%

b4000.114

7/18/2030

LADYSMITH S1 230.kV

GT372

40000

101.04%

93.94%

7.10%

b4000.114

7/18/2030

LADYSMITH S1 230.kV

GT472

40000

101.04%

93.94%

7.10%

b4000.114

7/18/2030

LADYSMITH S1 230.kV

GT572

40000

101.03%

93.93%

7.10%

b4000.114

7/18/2030

LADYSMITH S1 230.kV

SX1272

40000

105.46%

98.43%

7.04%

b3853.1

6/1/2025

LADYSMITH S1 230.kV

SX3472

40000

105.46%

98.43%

7.04%

b3853.1

6/1/2025

LOUDOUN 230.kV

200852

63000

103.92%

95.27%

8.65%

b3800.334

10/5/2031

LOUDOUN 230.kV

203052

63000

102.57%

95.02%

7.56%

b3800.334

10/5/2031

LOUDOUN 230.kV

204552

63000

101.56%

93.15%

8.41%

b3800.407

10/5/2031

LOUDOUN 230.kV

211752

63000

107.05%

98.13%

8.92%

b3800.235

10/5/2031

LOUDOUN 230.kV

212352

63000

107.59%

98.67%

8.92%

b3800.235

10/5/2031

LOUDOUN 230.kV

214052

63000

104.61%

96.50%

8.11%

b3800.334

10/5/2031

LOUDOUN 230.kV

217352

63000

101.82%

93.34%

8.47%

b3800.407

10/5/2031

LOUDOUN 230.kV

2008T2045

63000

103.92%

95.27%

8.65%

b3800.235

10/5/2031

LOUDOUN 230.kV

2030T2117

63000

107.05%

98.13%

8.92%

b3800.235

10/5/2031

LOUDOUN 230.kV

2094T2140

63000

104.61%

96.50%

8.11%

b3800.334

10/5/2031

LOUDOUN 230.kV

2123T2173

63000

107.59%

98.67%

8.92%

b3800.235

10/5/2031

LOUDOUN CAP 230.kV

SC352

50000

100.12%

93.62%

6.50%

b4000.119

10/31/2030

NORTH ANNA 500.kV

57502

40000

113.86%

95.53%

18.33%

b4000.128

10/13/2032

NORTH ANNA 500.kV

G102-1

40000

113.86%

95.53%

18.33%

b4000.128

10/13/2032

NORTH ANNA 500.kV

G102-2

40000

113.48%

95.12%

18.36%

b4000.128

10/13/2032

NORTH ANNA 500.kV

G202

40000

113.86%

95.53%

18.33%

b4000.128

10/13/2032

NORTH ANNA 500.kV

G2T575

40000

106.24%

87.81%

18.44%

b4000.128

10/13/2032

NORTH ANNA 500.kV

XT573

40000

113.86%

95.53%

18.33%

b4000.128

10/13/2032

OX 230.kV

22042

63000

100.37%

96.12%

4.24%

b3800.408

4/21/1931

OX 230.kV

220T2063

63000

100.37%

96.12%

4.24%

b3800.408

4/21/1931

OX 500.kV

56142

40000

105.23%

98.27%

6.96%

b3800.335

12/15/1931

OX 500.kV

H1T539

40000

104.44%

97.54%

6.90%

b3800.236

1/5/2029

OX 500.kV

H2T539

40000

104.44%

97.54%

6.90%

b3800.236

1/5/2029

OX L142 230.kV

L142

50000

108.05%

103.82%

4.22%

s2609.6

12/15/2030

PLEASANTVIEW 230.kV

L3T203

50000

108.44%

103.89%

4.56%

s2609.9

12/15/2030

PLEASANTVIEW 230.kV

L3T2180

50000

108.44%

103.89%

4.56%

s2609.9

12/15/2030

REMINGTON CT 230.kV

211462

40000

102.56%

95.98%

6.58%

b4000.134

1/9/2031

REMINGTON S1 230.kV

GT162

40000

101.45%

95.39%

6.06%

b4000.134

1/9/2031

REMINGTON S1 230.kV

GT262

40000

101.45%

95.39%

6.06%

b4000.134

1/9/2031

REMINGTON S2 230.kV

GT362

40000

101.45%

95.39%

6.06%

b4000.134

1/9/2031

REMINGTON S2 230.kV

GT462

40000

101.45%

95.39%

6.06%

b4000.134

1/9/2031

YADKIN 2&4 230.kV

210512

40000

101.22%

99.46%

1.76%

n6588

12/1/2028

 

 

Stability Analysis

Analysis Complete - No Issues

Executive Summary for Dynamic Stability Analysis Using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 35 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 35 projects.

 

Table 1: Transition Cycle 1 Cluster 35 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

35

AE2-185

Solar

Dominion

60

60

36

Gladys DP – Stonemill 69 kV

AF2-404

Battery

Dominion

0

0

AE2-283

Solar

Dominion

53

53

28

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 35 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 35 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 35 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 35 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

For Cluster 35 the dispatch of the study units was based on two scenarios.

  • Scenario 1: MFO met with solar generation and energy storage offline (solar output = 61.9 MW and storage is offline)
  • Scenario 3: MFO met with the solar generation and energy storage dispatched proportionally to their power capability (solar output = 47.44 MW and storage output = 14.56 MW)

 

Cluster 35 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 75 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 35 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 35 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy and AEP’s transmission planning criteria.
    • Dominion Energy:
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
    • AEP:
      • 0.92 p.u. to 1.05 p.u. for all voltage levels for each NERC Category Contingency
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The results of the analysis indicated all evaluation criteria were met. The following observations were made.

 

The initial results showed that Cluster 35 generators units exhibited slow reactive power recovery for several contingencies, Power Plant Controller (PPC) freezing, divergence and low frequency controller oscillations. These issues did not cause instability, and the generating units were tuned to achieve a faster recovery with better response.

The following adjustments were required for the respective queue projects based on the analysis results:

 

  • For AE2-187 the following adjustments were made:
    • The REECA1 Vup (p.u.) (CON J+1) parameter was set to 1.15 p.u to mitigate PPC freezing
    • Generator tripped for overvoltage protection model for voltage above 1.21 p.u and the time delay setting was updated from 0.16 to 0.3 seconds to allow generator to ride through the fault

 

  • For AE2-283 the following adjustments were made:
    • The REGCA1 Accel (CON J+13) parameter was set to 0.5 to improve PSS/E network solution calculations

 

  • For AC1-122 the following adjustments were made:
    • The REPCA Ki (CON J+2) parameter was changed from 0 to 10 to improve reactive power recovery

 

During phase 3 analysis all generations near Cluster 35 (AC1-042, AC1-145, AE2-185, AE2-187, and AF2-404) have their REGCA1 Accel set to 0.7. This was implemented as part of a phase 2 observation.  It should be noted that this parameter does not affect the performance or recovery of the renewable model, but is used to smooth the voltage and angle calculations within PSS/E.

 

Voltages above 1.05 p.u. were observed at Altavista 69 kV. This is due to Altavista 138-69 kV load tap changer operating at 1.10 p.u. to maintain the Altavista 69 kV scheduled voltage. A significant voltage drop was observed between Altavista, Gladys Tap, Altavista DP, and Mt Airy Tap due to the amount of generation served within the Altavista 69 kV system. To ensure that the post contingency voltage is below 1.05 p.u., the Altavista 138/69 kV load tap changing transformer would need to operate at 1.0375 p.u. tap and under System Normal (P0) conditions, would produce a 0.968 p.u. voltage on the Altavista 69 kV bus, which is within Dominion Energy’s P0 voltage levels. A voltage coordination study is recommended in the future to determine an acceptable voltage schedule for the Altavista 138/69 kV load tap changing transformer to coordinate with the generations served in the Altavista 69 kV system.

 

AE2-185, AF2-404, AE2-283, AC1-042 and AE2-187 were observed to have controller oscillations for a few faults such as P415. This is not a concern, and IC can tune their model to eliminate this behavior.

 

AD1-131, and AF2-107’s reactive power was observed to not settle within the 30 second simulation window for various faults. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement.

 

Low-frequency oscillations were observed for AE1-250 that were positively damped and settled in less than 15 seconds.  This issue did not cause instability in the system.

 

The AE2-185 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

The AE2-185 and AF2-404 BESS queue projects combined met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

The AE2-283 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

A voltage coordination study and Electromagnetic Transients (EMT) study around Altavista is recommended due to the findings of this analysis.  Additionally, any future projects connecting near Altavista should provide EMT models for their facility.

 

No mitigations were found to be required

 

Executive Summary for Dynamic Stability Analysis Using  PSCAD/EMT

 

Model Quality Testing Report

 

PSCAD model for Queue project AE2-185/AF2-404 and AE2-283 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each project

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

Weak Grid Assessment

 

This Weak Grid Assessment evaluates three projects from PJM Transition Cycle 1 (TC1) Cluster 35 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The three projects, AE2-185, AF2-404, and AE2-283, were identified in the Cluster Study as having potential risk of weak grid instability during contingency conditions after dynamic simulation analysis in PSS/E. System reinforcement was found to not be required, although evaluation using detailed models in an EMT simulation was recommended.

 

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability due to low short circuit ratio as identified in the Cluster Study, using detailed models in an EMT simulation.  A summary description of each project can be found below:

Table 3. Summary Description of TC1 Cluster 35 Projects

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AE2-185 / AF2-404 Pigeon Run Solar and BESS

PV + BESS

60

Gladys DP – Stonemill 69 kV

941800

AE2-283 Gladys Solar

PV

53

Gladys DP – Stonemill 69 kV

942670

 

Individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test process,  model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

Two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. For Cluster 35, the following contingency cases were chosen (all projects operating at rated power pre-fault).

 

  • Fault ID: P1.01: Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35
  • Fault ID: P1.18: Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

 

Simulation results in PSCAD are summarized below.  It can be observed that in case P1.01 the islanded condition results in the projects tripping, similar to the Cluster Study.  Overall system recovery as observed from the remaining 138kV network is stable.  In P1.18, stable recovery is observed in PSCAD and is consistent with the results of the Cluster Study. 

 

Table 4. Summary of cases tested in PSCAD system study

Fault ID

Fault Description

Cluster Study Result

PSCAD Study Result

P1.01

Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35. Islanded condition in the 69 kV subnetwork. Cluster projects expected to trip.

System Stable,
Projects on 69kV trip

System Stable,
Projects on 69kV trip

P1.18

Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

Stable

Stable

 

The results of this weak grid assessment using PSCAD show overall stable system recovery in the two worst-case contingencies and supports the conclusion from the Cluster Study that mitigation's are not required.

Reactive Power Analysis

The reactive power capability of AE2-283 met the 0.95 leading and lagging power factor requirements at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA2-057 Hornertown-Whitakers 115kV In Service
AB1-132 Thelma 230kV In Service
AB1-173 Brink-Trego 115kV In Service
AB2-040 Brink 115kV In Service
AB2-043 Chase City 115kV In Service
AB2-045 Buckingham 34.5kV In Service
AB2-060 Chase City-Lunenburg 115kV In Service
AB2-077 Buggs Island-Chase City 115kV In Service
AB2-078 Buggs Island-Chase City 115kV In Service
AB2-079 Buggs Island-Chase City 115kV In Service
AB2-174 Emporia-Trego 115kV In Service
AC1-036 Twittys Creek 34.5kV In Service
AC1-042 Altavista-Mt. Airy 69kV In Service
AC1-054 Kerr Dam–Eatons Ferry 115 kV In Service
AC1-075 Perth-Hickory Grove 115kV In Service
AC1-080 Perth-Hickory Grove 115kV In Service
AC1-083 Smith Mountain-Bearskin 138kV In Service
AC1-086 Thelma 230kV Suspended
AC1-098 Dawson-South Justice 115kV Under Construction
AC1-099 Dawson-South Justice 115kV Under Construction
AC1-105 Halifax-Mt. Laurel 115kV In Service
AC1-145 Gretna DP 69 kV In Service
AC1-208 Cox-Whitakers 115kV Under Construction
AC1-221 Halifax-Person 230kV In Service
AC1-222 Crystal Hill-Halifax 115kV In Service
AC2-084 Dawson-South Justice 115kV Under Construction
AC2-100 Halifax-Person 230kV In Service
AC2-165 Bremo-Powhatan 230kV Suspended
AD1-056 Hornertown-Hathaway 230 kV Suspended
AD1-057 Hornertown-Hathaway 230 kV Suspended
AD1-087 Clover-Sedge Hill 230 kV In Service
AD1-088 Briery-Clover 230 kV Suspended
AD1-152 Clover-Sedge Hill 230 kV In Service
AD2-022 East Danville - Roxborough 230 kV Engineering & Procurement
AD2-023 East Danville - Roxborough 230 kV Engineering & Procurement
AD2-033 Chase City-Lunenburg 115 kV Engineering & Procurement
AD2-202 Clover-Sedge Hill 230kV In Service
AE1-056 Red House-South Creek 115 kV Suspended
AE1-108 Bremo-Scottsville 138 kV Engineering & Procurement
AE1-148 Kerr Dam-Ridge Rd 115 kV Active
AE1-250 Smith Mountain-E. Danville 138 kV Engineering & Procurement
AE2-092 Kidds Store-Sherwood 115 kV Engineering & Procurement
AE2-185 Gladys DP-Stonemill Switching Station 69 kV Active
AE2-187 Shockoe DP-Chatham 69 kV Active
AE2-259 Curdsville-Willis Mtn 115 kV Engineering & Procurement
AE2-291 Grit DP-Perth 115 kV Active
AF1-058 Welco 34.5 kV In Service
AF1-292 Fields 34.5kV Engineering & Procurement
AF1-294 Jetersville-Ponton 115 kV Active
AF2-042 Clover-Rawlings 500 kV Active
AF2-115 Jetersville-Ponton 115 kV Active
AF2-222 Madisonville DP-Twitty's Creek 115 kV Active
AF2-297 Sedge Hill 115 kV Active
AF2-299 Fields 34.5 kV Active
AG1-021 Jetersville-Ponton 115 kV Active
AG1-098 Briery-Clover 230 kV Active
AG1-105 Mount Laurel-Barnes Junction 115 kV Active
AG1-106 Thelma 230 kV Active
AG1-166 Lone Pine 115 kV Active
AG1-167 Lone Pine 115 kV Active
AG1-168 Lone Pine 115 kV Active
AG1-285 Chase City-Central 115 kV Active
AG1-342 Dryburg 115 kV Active
AG1-394 Boykins 34.5 kV Active
AG1-532 Fields 34.5 kV Engineering & Procurement
AG1-552 Carolina 34.5 kV Active
Z2-044 Whitakers 34.5kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AE2-283 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
Dominion n9143.0 Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor. Cost Allocated $1,768,447
Dominion n9138.0 Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. Cost Allocated $33,945
Dominion n9250.0 Construct a new 22.59 mile line between Carson and Rawlings Substations. Cost Allocated $33,212
Dominion n9630.0 Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. Cost Allocated $27,329
Dominion n8492 Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. Cost Allocated $24,489
Dominion n9267.0 Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. Cost Allocated $13,968
Dominion n9259.0 Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. Cost Allocated $7,730
Dominion n7541 Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. Cost Allocated $6,958
Dominion n8492.1 Two Breaker Additions at Fentress Substation. Cost Allocated $6,093
Dominion n8492.2 Expand Yadkin Substation to accommodate the new 500 kV line. Cost Allocated $4,951
Dominion n6588 Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker. Cost Allocated $526
ComEd b3811.1 Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. Contingent $0 N/A
ComEd s3011 Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. Contingent $0 N/A
ComEd b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line Contingent $0 N/A
AEP n9243.0 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Contingent $0 N/A
ComEd n9195.0 Install a new 345 kV circuit breaker at Station 12 Dresden. Contingent $0 N/A
Dominion b4000.357 Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. Contingent $0 N/A
Dominion b4000.356 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). Contingent $0 N/A
Dominion b4000.355 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). Contingent $0 N/A
Dominion b4000.352 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. Contingent $0 N/A
Dominion b4000.351 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. Contingent $0 N/A
Dominion b4000.350 Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. Contingent $0 N/A
Dominion b4000.349 Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. Contingent $0 N/A
Dominion b4000.348 Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. Contingent $0 N/A
Dominion b4000.346 Cut-in 500kV line from Kraken substation into Yeat substation Contingent $0 N/A
Dominion b4000.345 Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0 N/A
Dominion b4000.344 Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0 N/A
Dominion b4000.342 Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. Contingent $0 N/A
Dominion b4000.341 Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. Contingent $0 N/A
Dominion b4000.325 Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. Contingent $0 N/A
Dominion b3689.2 Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA Contingent $0 N/A
Dominion b4000.103 Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA Contingent $0 N/A
Dominion b3800.405 Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. Contingent $0 N/A
Dominion b3854.1 Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA Contingent $0 N/A
Dominion b4000.108 Carson Sub 230kV - replace 40kA breaker 23872 with 63kA Contingent $0 N/A
Dominion b4000.326 At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. Contingent $0 N/A
Dominion b4000.327 Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. Contingent $0 N/A
Dominion b3800.406 Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. Contingent $0 N/A
Dominion b4000.115 Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA Contingent $0 N/A
Dominion b4000.354 Ladysmith substation breakers replacement: 574T575 and 568T581 Contingent $0 N/A
Dominion b3853.1 Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA Contingent $0 N/A
Dominion b4000.114 Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA Contingent $0 N/A
Dominion b3800.235 Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers Contingent $0 N/A
Dominion b3800.334 Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. Contingent $0 N/A
Dominion b3800.407 Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. Contingent $0 N/A
Dominion b4000.119 Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. Contingent $0 N/A
Dominion b4000.128 North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. Contingent $0 N/A
Dominion b3800.408 Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. Contingent $0 N/A
Dominion s2609.6 Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. Contingent $0 N/A
Dominion s2609.9 Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. Contingent $0 N/A
Dominion b4000.134 Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. Contingent $0 N/A
Dominion b1696 Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 Contingent $0 N/A
Dominion b3800.236 Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. Contingent $0 N/A
Dominion s3047.2 Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. Contingent $0 N/A
Dominion b3800.312 Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. Contingent $0 N/A
Dominion b3800.313 Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. Contingent $0 N/A
Dominion b3800.356 Build a new 500 kV line from Vint Hill to Wishing Star. Contingent $0 N/A
Dominion b3800.357 Build a new 500 kV line from Morrisville to Vint Hill. Contingent $0 N/A
Dominion b3800.354 Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. Contingent $0 N/A
Dominion b3800.335 Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker Contingent $0 N/A
AEP b4000.211 Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line Contingent $0 N/A
AEP b4000.210 Rebuild 7 miles of Otter - Johnson Mountain 138 kV line. Contingent $0 N/A
AEP n5613 Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line. Contingent $0 N/A
Grand Total: $1,927,648

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n6588
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
n6588 / TC1-PH2-DOM-034
Title
Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Description
Replace 230kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Total Cost ($USD)
$1,725,040
Discounted Total Cost ($USD)
$1,725,040
Allocated Cost ($USD)
$526
Time Estimate
Dec 01 2028

Contributor

Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $9,757
AE2-185 0.03% $597
AE2-187 0.03% $518
AE2-283 0.03% $526
AE2-291 0.54% $9,277
AF1-123 10.21% $176,104
AF1-124 10.25% $176,739
AF1-125 10.05% $173,379
AF1-294 0.41% $7,047
AF2-035 0.26% $4,527
AF2-042 28.18% $486,093
AF2-046 2.88% $49,766
AF2-115 0.25% $4,292
AF2-120 4.50% $77,663
AF2-222 3.88% $66,923
AF2-297 0.72% $12,360
AG1-008 2.88% $49,766
AG1-021 0.20% $3,433
AG1-082 0.19% $3,231
AG1-098 1.60% $27,651
AG1-105 0.68% $11,763
AG1-124 1.06% $18,318
AG1-135 4.42% $76,186
AG1-146 2.12% $36,633
AG1-147 4.96% $85,476
AG1-154 0.14% $2,384
AG1-166 0.13% $2,249
AG1-167 0.10% $1,687
AG1-168 0.10% $1,687
AG1-285 2.80% $48,263
AG1-342 0.06% $1,087
AG1-494 0.82% $14,097
AG1-536 4.96% $85,562

System Reinforcement: n9143.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9143.0 / TC1-PH1-DOM-001
Title
Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor.
Description
Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C.
Total Cost ($USD)
$6,315,811
Discounted Total Cost ($USD)
$6,315,811
Allocated Cost ($USD)
$1,768,447
Time Estimate
20 to 21 Months

Contributor

Facility Contingency
2ALTVSTA-2GLADYS TAP 69.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-185 AE2-185 69 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-185, AF2-404
36.0 MW 36.0% $2,273,682
AE2-187 36.0 MW 36.0% $2,273,682
AE2-283 28.0 MW 28.0% $1,768,447

System Reinforcement: n7687
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7687 / dom-046
Title
Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV).
Description
Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV).
Total Cost ($USD)
$10,595,849
Discounted Total Cost ($USD)
$4,330,015
Allocated Cost ($USD)
$158,674
Time Estimate
Jun 01 2029

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Facility Contingency
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 1 transformer (Any)
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE1-148 14.3 MW 3.9% $170,620
AE2-185 AE2-185 69 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-185, AF2-404
15.1 MW 4.1% $179,625
AE2-187 13.1 MW 3.6% $155,672
AE2-283 13.3 MW 3.7% $158,674
AE2-291 61.5 MW 16.9% $732,935
AF1-294 AF1-294 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-294, AF2-115, AG1-021, AH1-280
6.0 MW 1.7% $71,940
AF2-115 AF1-294 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-294, AF2-115, AG1-021, AH1-280
3.7 MW 1.0% $43,867
AF2-222 33.6 MW 9.2% $400,282
AF2-297 82.8 MW 22.8% $986,024
AG1-021 AF1-294 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-294, AF2-115, AG1-021, AH1-280
2.9 MW 0.8% $35,089
AG1-105 58.9 MW 16.2% $700,955
AG1-285 32.3 MW 8.9% $384,167
AG1-342 26.0 MW 7.2% $310,166

System Reinforcement: b4000.211
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.211
Title
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line
Description
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line Projected In Service Date: 06/01/2029
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.210
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.210
Title
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
Description
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05JOHNMT-05OTTER 138.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
(Pending)
Title
Most limiting rating on the Dominion side is the Wave Trap and Lead at Altavista: 363 / 382 /420 MVA.
Description
Most limiting rating on the Dominion side is the Wave Trap and Lead at Altavista: 363 / 382 /420 MVA.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
99 Months

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
05OTTER-4ALTVSTA 138.0 kV Ckt 1 line (Any)

System Reinforcement: n5613
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n5613 / AEPA0014a
Title
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
Description
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
Total Cost ($USD)
$2,740,849
Discounted Total Cost ($USD)
$2,740,849
Allocated Cost ($USD)
$0
Time Estimate
Nov 21 2027

Contingent

Note: Based on PJM cost allocation criteria, AE2-283 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AE2-283 may not have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05OTTER-4ALTVSTA 138.0 kV Ckt 1 line (Any)

System Reinforcement: n7812
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7812 / dom-397
Title
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C.
Total Cost ($USD)
$23,887,052
Discounted Total Cost ($USD)
$23,887,052
Allocated Cost ($USD)
$0
Time Estimate
43 to 44 Months

ContingentEliminated

Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
4BREMO-AE1-108 TAP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)

System Reinforcement: n9179.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9179.0 / AEPAPRJV008
Title
Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.
Description
"•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design. •Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line by installing one floating deadend and replacing one structure"
Total Cost ($USD)
$1,245,000
Discounted Total Cost ($USD)
$1,245,000
Allocated Cost ($USD)
$0
Time Estimate
15 Months

ContingentEliminated

Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
AEP
RTEP ID / TO ID
(Pending) / NONAEPRJV01
Title
Reinforcement for AE1-108 TP 138 KV to 4BREMO 138 KV ckt 1: Non-AEP Limiting Element.
Description
Non-AEP Limiting Element
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
0 to 1 Months

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)

System Reinforcement: n9178.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9178.0 / AEPAPRJV007
Title
Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.
Description
•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design. •Replace 3 structures and 1 floating dead ends along the Reusens – Scottsville – Bremo Bluff line determined in preliminary engineering study.
Total Cost ($USD)
$4,759,000
Discounted Total Cost ($USD)
$4,759,000
Allocated Cost ($USD)
$0
Time Estimate
29 Months

ContingentEliminated

Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)

System Reinforcement: n9220.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9220.0 / TC1-PH2-DOM-033
Title
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Total Cost ($USD)
$44,465,922
Discounted Total Cost ($USD)
$44,465,922
Allocated Cost ($USD)
$0
Time Estimate
42 to 48 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.

Facility Contingency
6BUCKING-6BREMO 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9217.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9217.0 / TC1-PH2-DOM-028
Title
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
Total Cost ($USD)
$40,414,822
Discounted Total Cost ($USD)
$40,414,822
Allocated Cost ($USD)
$0
Time Estimate
45 to 46 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.

Facility Contingency
6BUCKING-6FARMVIL 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9138.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9138.0 / TC1-PH1-DOM-070
Title
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Description
Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
Total Cost ($USD)
$111,130,292
Discounted Total Cost ($USD)
$111,130,292
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months

Potential Aggregate ContributorTopology Changing

Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8CARSON-8RAWLINGS 500.0 kV Ckt 1 line (Any)
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-C
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-A
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P4-2: 51192_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P4-2: 51172_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P4-2: 511T544_SRT-S
8CARSON-AE2-313 TP 500.0 kV Ckt 1 line (Any)
8RAWLINGS-AE2-313 TP 500.0 kV Ckt 1 line (Any)
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-C
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-A
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S
System Reinforcement: n9138.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9138.0 / TC1-PH1-DOM-070
Title
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Description
Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
Total Cost ($USD)
$111,130,292
Allocated Cost ($USD)
$33,945
Time Estimate
60 to 61 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $628,539
AE2-185 0.0346 % $38,427
AE2-187 0.0300 % $33,303
AE2-283 0.0305 % $33,945
AE2-291 0.5378 % $597,692
AF1-123 10.2087 % $11,345,010
AF1-124 10.2455 % $11,385,904
AF1-125 10.0507 % $11,169,384
AF1-294 0.4085 % $453,960
AF2-035 0.2624 % $291,649
AF2-042 28.1786 % $31,314,939
AF2-046 2.8849 % $3,206,002
AF2-115 0.2488 % $276,491
AF2-120 4.5021 % $5,003,236
AF2-222 3.8795 % $4,311,266
AF2-297 0.7165 % $796,270
AG1-008 2.8849 % $3,206,002
AG1-021 0.1990 % $221,202
AG1-082 0.1873 % $208,113
AG1-098 1.6029 % $1,781,295
AG1-105 0.6819 % $757,790
AG1-124 1.0619 % $1,180,088
AG1-135 4.4165 % $4,908,028
AG1-146 2.1236 % $2,359,969
AG1-147 4.9550 % $5,506,458
AG1-154 0.1382 % $153,603
AG1-166 0.1304 % $144,897
AG1-167 0.0978 % $108,677
AG1-168 0.0978 % $108,677
AG1-285 2.7978 % $3,109,245
AG1-342 0.0630 % $70,013
AG1-494 0.8172 % $908,203
AG1-536 4.9600 % $5,512,015

System Reinforcement: n9250.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9250.0 / TC1-PH2-DOM-044
Title
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Description
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Total Cost ($USD)
$108,728,086
Discounted Total Cost ($USD)
$108,728,086
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months

Potential Aggregate ContributorTopology Changing

Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8CARSON-8RAWLINGS 500.0 kV Ckt 1 line (Any)
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-C
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-A
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P4-2: 51192_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P4-2: 51172_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line DVP_P4-2: 511T544_SRT-S
8CARSON-AE2-313 TP 500.0 kV Ckt 1 line (Any)
8RAWLINGS-AE2-313 TP 500.0 kV Ckt 1 line (Any)
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-C
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S-A
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line DVP_P1-2: LN 511_SRT-S
System Reinforcement: n9250.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9250.0 / TC1-PH2-DOM-044
Title
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Description
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Total Cost ($USD)
$108,728,086
Allocated Cost ($USD)
$33,212
Time Estimate
60 to 61 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $614,953
AE2-185 0.0346 % $37,597
AE2-187 0.0300 % $32,583
AE2-283 0.0305 % $33,212
AE2-291 0.5378 % $584,772
AF1-123 10.2087 % $11,099,775
AF1-124 10.2455 % $11,139,785
AF1-125 10.0507 % $10,927,946
AF1-294 0.4085 % $444,147
AF2-035 0.2624 % $285,345
AF2-042 28.1786 % $30,638,032
AF2-046 2.8849 % $3,136,700
AF2-115 0.2488 % $270,514
AF2-120 4.5021 % $4,895,086
AF2-222 3.8795 % $4,218,073
AF2-297 0.7165 % $779,058
AG1-008 2.8849 % $3,136,700
AG1-021 0.1990 % $216,420
AG1-082 0.1873 % $203,614
AG1-098 1.6029 % $1,742,790
AG1-105 0.6819 % $741,409
AG1-124 1.0619 % $1,154,579
AG1-135 4.4165 % $4,801,936
AG1-146 2.1236 % $2,308,955
AG1-147 4.9550 % $5,387,430
AG1-154 0.1382 % $150,283
AG1-166 0.1304 % $141,765
AG1-167 0.0978 % $106,328
AG1-168 0.0978 % $106,328
AG1-285 2.7978 % $3,042,035
AG1-342 0.0630 % $68,500
AG1-494 0.8172 % $888,571
AG1-536 4.9600 % $5,392,867

System Reinforcement: n9630.0

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9630.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9630.0 / TC1-PH3-DOM-013
Title
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
Description
n9630.0 addresses both stability and load flow violations. Construct a new 230 kV Line from the AG1-285 substation to the 230 kV Finneywood substation following the Line 1012 ROW for approximately 1.0 miles, then following the Line 556 ROW for approximately 3.5 miles to terminate at Finneywood. Expand the AG1-285 115 kV substation to accommodate two (2) new 115/230 kV transformers. Build a 230 kV substation at AG1-285 to connect the 115/230 kV transformers and the new 230 kV line to Finneywood. Expand the Finneywood 230 kV substation to accommodate the new line. The existing 1.0 miles of 115 kV from AG1-285 to Chase City does not need to be rebuilt to accommodate a new structure in the same right of way and therefore will be unchanged. The existing 3.5 miles of 500 kV towers from Structure 556/46 to Finneywood substation will need to be rebuilt as a double circuit tower to accommodate the new 230 kV line.
Total Cost ($USD)
$89,468,616
Allocated Cost ($USD)
$27,329
Time Estimate
Dec 31 2029
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $506,034
AE2-185 0.0346 % $30,956
AE2-187 0.0300 % $26,841
AE2-283 0.0305 % $27,288
AE2-291 0.5378 % $481,162
AF1-123 10.2087 % $9,133,583
AF1-124 10.2455 % $9,166,507
AF1-125 10.0507 % $8,992,222
AF1-294 0.4085 % $365,479
AF2-035 0.2624 % $234,766
AF2-042 28.1786 % $25,211,003
AF2-046 2.8849 % $2,581,080
AF2-115 0.2488 % $222,598
AF2-120 4.5021 % $4,027,967
AF2-222 3.8795 % $3,470,935
AF2-297 0.7165 % $641,043
AG1-008 2.8849 % $2,581,080
AG1-021 0.1990 % $178,043
AG1-082 0.1873 % $167,575
AG1-098 1.6029 % $1,434,092
AG1-105 0.6819 % $610,086
AG1-124 1.0619 % $950,067
AG1-135 4.4165 % $3,951,381
AG1-146 2.1236 % $1,899,956
AG1-147 4.9550 % $4,433,170
AG1-154 0.1382 % $123,646
AG1-166 0.1304 % $116,667
AG1-167 0.0978 % $87,500
AG1-168 0.0978 % $87,500
AG1-285 2.7978 % $2,503,153
AG1-342 0.0630 % $56,365
AG1-494 0.8172 % $731,138
AG1-536 4.9600 % $4,437,643

System Reinforcement: n8492

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492
Title
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
Description
Wreck and rebuild one (1) overhead 500kV transmission line that will start at the existing Fentress 500 kV Substation and terminate at the existing Yadkin 500 kV Substation, located approximately 13.5 miles away.
Total Cost ($USD)
$80,172,278
Allocated Cost ($USD)
$24,489
Time Estimate
26 to 27 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $453,454
AE2-185 0.0346 % $27,740
AE2-187 0.0300 % $24,052
AE2-283 0.0305 % $24,453
AE2-291 0.5378 % $431,167
AF1-123 10.2087 % $8,184,547
AF1-124 10.2455 % $8,214,051
AF1-125 10.0507 % $8,057,875
AF1-294 0.4085 % $327,504
AF2-035 0.2624 % $210,372
AF2-042 28.1786 % $22,591,426
AF2-046 2.8849 % $2,312,890
AF2-115 0.2488 % $199,469
AF2-120 4.5021 % $3,609,436
AF2-222 3.8795 % $3,110,284
AF2-297 0.7165 % $574,434
AG1-008 2.8849 % $2,312,890
AG1-021 0.1990 % $159,543
AG1-082 0.1873 % $150,163
AG1-098 1.6029 % $1,285,081
AG1-105 0.6819 % $546,695
AG1-124 1.0619 % $851,349
AG1-135 4.4165 % $3,540,809
AG1-146 2.1236 % $1,702,538
AG1-147 4.9550 % $3,972,536
AG1-154 0.1382 % $110,798
AG1-166 0.1304 % $104,545
AG1-167 0.0978 % $78,408
AG1-168 0.0978 % $78,408
AG1-285 2.7978 % $2,243,060
AG1-342 0.0630 % $50,509
AG1-494 0.8172 % $655,168
AG1-536 4.9600 % $3,976,545

System Reinforcement: n9267.0

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9267.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9267.0 / TC1-PH2-DOM-067
Title
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
Description
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner substations with single (1) 768.2 ACSS/TW “Maumee” at 250 degrees C. This new line will be on separate transmission towers from the existing Northern Neck and Moon Corner line 1059. Station expansion is required at Northern Neck and Moon Corner to accommodate the new line.
Total Cost ($USD)
$45,730,074
Allocated Cost ($USD)
$13,968
Time Estimate
45 to 46 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $258,649
AE2-185 0.0346 % $15,823
AE2-187 0.0300 % $13,719
AE2-283 0.0305 % $13,948
AE2-291 0.5378 % $245,936
AF1-123 10.2087 % $4,668,446
AF1-124 10.2455 % $4,685,275
AF1-125 10.0507 % $4,596,193
AF1-294 0.4085 % $186,807
AF2-035 0.2624 % $119,996
AF2-042 28.1786 % $12,886,095
AF2-046 2.8849 % $1,319,267
AF2-115 0.2488 % $113,776
AF2-120 4.5021 % $2,058,814
AF2-222 3.8795 % $1,774,098
AF2-297 0.7165 % $327,656
AG1-008 2.8849 % $1,319,267
AG1-021 0.1990 % $91,003
AG1-082 0.1873 % $85,652
AG1-098 1.6029 % $733,007
AG1-105 0.6819 % $311,833
AG1-124 1.0619 % $485,608
AG1-135 4.4165 % $2,019,669
AG1-146 2.1236 % $971,124
AG1-147 4.9550 % $2,265,925
AG1-154 0.1382 % $63,199
AG1-166 0.1304 % $59,632
AG1-167 0.0978 % $44,724
AG1-168 0.0978 % $44,724
AG1-285 2.7978 % $1,279,436
AG1-342 0.0630 % $28,810
AG1-494 0.8172 % $373,706
AG1-536 4.9600 % $2,268,212

System Reinforcement: n9259.0

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9259.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9259.0
Title
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Description
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Total Cost ($USD)
$25,304,902
Allocated Cost ($USD)
$7,730
Time Estimate
38 to 39 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $143,125
AE2-185 0.0346 % $8,755
AE2-187 0.0300 % $7,591
AE2-283 0.0305 % $7,718
AE2-291 0.5378 % $136,090
AF1-123 10.2087 % $2,583,302
AF1-124 10.2455 % $2,592,614
AF1-125 10.0507 % $2,543,320
AF1-294 0.4085 % $103,371
AF2-035 0.2624 % $66,400
AF2-042 28.1786 % $7,130,567
AF2-046 2.8849 % $730,021
AF2-115 0.2488 % $62,959
AF2-120 4.5021 % $1,139,252
AF2-222 3.8795 % $981,704
AF2-297 0.7165 % $181,310
AG1-008 2.8849 % $730,021
AG1-021 0.1990 % $50,357
AG1-082 0.1873 % $47,396
AG1-098 1.6029 % $405,612
AG1-105 0.6819 % $172,554
AG1-124 1.0619 % $268,713
AG1-135 4.4165 % $1,117,591
AG1-146 2.1236 % $537,375
AG1-147 4.9550 % $1,253,858
AG1-154 0.1382 % $34,971
AG1-166 0.1304 % $32,998
AG1-167 0.0978 % $24,748
AG1-168 0.0978 % $24,748
AG1-285 2.7978 % $707,981
AG1-342 0.0630 % $15,942
AG1-494 0.8172 % $206,792
AG1-536 4.9600 % $1,255,123

System Reinforcement: n7541

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n7541
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7541 / dom-016
Title
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Description
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Total Cost ($USD)
$22,779,395
Allocated Cost ($USD)
$6,958
Time Estimate
Dec 31 2029
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $128,840
AE2-185 0.0346 % $7,882
AE2-187 0.0300 % $6,834
AE2-283 0.0305 % $6,948
AE2-291 0.5378 % $122,508
AF1-123 10.2087 % $2,325,480
AF1-124 10.2455 % $2,333,863
AF1-125 10.0507 % $2,289,489
AF1-294 0.4085 % $93,054
AF2-035 0.2624 % $59,773
AF2-042 28.1786 % $6,418,915
AF2-046 2.8849 % $657,163
AF2-115 0.2488 % $56,675
AF2-120 4.5021 % $1,025,551
AF2-222 3.8795 % $883,727
AF2-297 0.7165 % $163,214
AG1-008 2.8849 % $657,163
AG1-021 0.1990 % $45,331
AG1-082 0.1873 % $42,666
AG1-098 1.6029 % $365,131
AG1-105 0.6819 % $155,333
AG1-124 1.0619 % $241,894
AG1-135 4.4165 % $1,006,052
AG1-146 2.1236 % $483,743
AG1-147 4.9550 % $1,128,719
AG1-154 0.1382 % $31,481
AG1-166 0.1304 % $29,704
AG1-167 0.0978 % $22,278
AG1-168 0.0978 % $22,278
AG1-285 2.7978 % $637,322
AG1-342 0.0630 % $14,351
AG1-494 0.8172 % $186,153
AG1-536 4.9600 % $1,129,858

System Reinforcement: n8492.1

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492.1
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.1
Title
Two Breaker Additions at Fentress Substation.
Description
Install Two 5000 amp GIS Breakers at Fentress Substation to connect the new 500 kV line 5005.
Total Cost ($USD)
$19,945,879
Allocated Cost ($USD)
$6,093
Time Estimate
30 to 36 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $112,814
AE2-185 0.0346 % $6,901
AE2-187 0.0300 % $5,984
AE2-283 0.0305 % $6,083
AE2-291 0.5378 % $107,269
AF1-123 10.2087 % $2,036,215
AF1-124 10.2455 % $2,043,555
AF1-125 10.0507 % $2,004,700
AF1-294 0.4085 % $81,479
AF2-035 0.2624 % $52,338
AF2-042 28.1786 % $5,620,469
AF2-046 2.8849 % $575,419
AF2-115 0.2488 % $49,625
AF2-120 4.5021 % $897,983
AF2-222 3.8795 % $773,800
AF2-297 0.7165 % $142,912
AG1-008 2.8849 % $575,419
AG1-021 0.1990 % $39,692
AG1-082 0.1873 % $37,359
AG1-098 1.6029 % $319,712
AG1-105 0.6819 % $136,011
AG1-124 1.0619 % $211,805
AG1-135 4.4165 % $880,910
AG1-146 2.1236 % $423,571
AG1-147 4.9550 % $988,318
AG1-154 0.1382 % $27,565
AG1-166 0.1304 % $26,009
AG1-167 0.0978 % $19,507
AG1-168 0.0978 % $19,507
AG1-285 2.7978 % $558,046
AG1-342 0.0630 % $12,566
AG1-494 0.8172 % $162,998
AG1-536 4.9600 % $989,316

System Reinforcement: n8492.2

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492.2
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.2
Title
Expand Yadkin Substation to accommodate the new 500 kV line.
Description
Expansion of yadkins 500 kV switchyard to accommodate the new 500 kV line which includes addition of 5000 amp GIS breakers and relocation of the existing suffolk -yadkin 500 kV line#565
Total Cost ($USD)
$16,207,123
Allocated Cost ($USD)
$4,951
Time Estimate
15 to 16 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $91,667
AE2-185 0.0346 % $5,608
AE2-187 0.0300 % $4,862
AE2-283 0.0305 % $4,943
AE2-291 0.5378 % $87,162
AF1-123 10.2087 % $1,654,537
AF1-124 10.2455 % $1,660,501
AF1-125 10.0507 % $1,628,929
AF1-294 0.4085 % $66,206
AF2-035 0.2624 % $42,527
AF2-042 28.1786 % $4,566,940
AF2-046 2.8849 % $467,559
AF2-115 0.2488 % $40,323
AF2-120 4.5021 % $729,661
AF2-222 3.8795 % $628,755
AF2-297 0.7165 % $116,124
AG1-008 2.8849 % $467,559
AG1-021 0.1990 % $32,252
AG1-082 0.1873 % $30,356
AG1-098 1.6029 % $259,784
AG1-105 0.6819 % $110,516
AG1-124 1.0619 % $172,103
AG1-135 4.4165 % $715,788
AG1-146 2.1236 % $344,174
AG1-147 4.9550 % $803,063
AG1-154 0.1382 % $22,398
AG1-166 0.1304 % $21,134
AG1-167 0.0978 % $15,851
AG1-168 0.0978 % $15,851
AG1-285 2.7978 % $453,443
AG1-342 0.0630 % $10,210
AG1-494 0.8172 % $132,445
AG1-536 4.9600 % $803,873

System Reinforcement: b3811.1

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3811.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3811.1 / CE_PJM B3811_L11323
Title
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Description
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s3011

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s3011
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
s3011 / CE_S3011
Title
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.
Description
Replace 345 kV open air straight bus with GIS in a breaker and half configuration (34 Circuit Breakers) at Goodings Grove with 80kA capability.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3775.1

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3775.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3775.1
Title
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line
Description
Outside of the Green Acres substation, swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line to the University Park N-Olive 345 kV line to create a University Park N-Green Acres-Olive and St. John-Olive 345 kV lines.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: n9243.0

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9243.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9243.0 / AEPSERG13
Title
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Description
At the Jefferson Station: • Expand the northeast corner of the station • Remove Circuit breaker C1 • Install one (1) new 765/345 kV transformer and associated equipment • Install one (1) new 765 kV circuit breaker with associated control relaying and breaker disconnect switches • Install one (1) new 345 kV circuit breaker with associated control relaying and breaker disconnect switches • Install a new station service center At the Clifty Creek Station: • Extend 345 kV bus 1 and 2 to make room for a new breaker string • Move a section of the 138 kV bus underground to make room for the new breaker string • Relocate circuit breaker S to the new string • Install two (2) new 345 kV circuit breakers on the new string •Remove the existing Jefferson – Clifty Creek 345 kV line •Construct a new Jefferson – Clifty Creek 345 kV double circuit line •Evaluate line settings for all appropriate lines •Install direct fiber relaying between the Jefferson and Clifty Creek station •Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures
Total Cost ($USD)
$200,238,000
Allocated Cost ($USD)
$0
Time Estimate
55 Months
Cost Alloc Type
Contingent

System Reinforcement: n9195.0

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9195.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9195.0 / CE_NUN_STA12_345 NEW CB
Title
Install a new 345 kV circuit breaker at Station 12 Dresden.
Description
• Upgrade the existing substation STA 12 Dresden by adding 345kV BT 14-15 circuit breaker and associated disconnect switches. • Upgrade relay & protection at 345kV substation STA 12 Dresden to support installation of 345kV BT 14-15
Total Cost ($USD)
$3,357,627
Allocated Cost ($USD)
$0
Time Estimate
45 Months
Cost Alloc Type
Contingent

System Reinforcement: b4000.357

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.357
Title
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Description
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.356

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.356
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.355

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.355
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.355
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.352

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.352
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.352
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.351

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.351
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.351
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.350

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.350
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.350
Title
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Description
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.349

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.349
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.349
Title
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Description
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.348

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.348
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.348
Title
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Description
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.346

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.346
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.346
Title
Cut-in 500kV line from Kraken substation into Yeat substation
Description
Cut-in 500kV line from Kraken substation into Yeat substation
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.345

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.345
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.345
Title
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.344

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.344
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.344
Title
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.342

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.342
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.342
Title
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Description
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.341

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.341
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.341
Title
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Description
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.325

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.325
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.325
Title
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Description
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3689.2

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3689.2
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3689.2
Title
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA
Description
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 4000A 80 kA breakers and associated equipment including breaker leads as necessary to address breaker duty issues identified in short circuit analysis.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.103

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.103
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.103
Title
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Description
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.405

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.405
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.405
Title
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Description
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3854.1

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3854.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3854.1
Title
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Description
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.108

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.108
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.108
Title
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Description
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.326

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.326
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.326
Title
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Description
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.327

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.327
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.327
Title
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Description
Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.406

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.406
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.406
Title
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Description
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.115

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.115
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.115
Title
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Description
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.354

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.354
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.354
Title
Ladysmith substation breakers replacement: 574T575 and 568T581
Description
Expand Ladysmith substation to a add redundant circuit breakers to the middle breakers on both 500kV strings (574T575 and 568T581). The equipment including switches 57518, 57515, H115 will be replaced with 5000A equipment.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3853.1

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3853.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3853.1 / (Pending)
Title
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Description
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.114

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.114
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.114
Title
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Description
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.235

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.235
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.235
Title
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers
Description
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers: 212352, 2123T2173, 2030T2117, 211752, and 2008T2045
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.334

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.334
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.334
Title
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.
Description
Replace 4 overdutied 230kV breakers at Loudoun Substation with 80kA breakers: 2094T2140, 214052, 200852 and 203052.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.407

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.407
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.407
Title
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.
Description
Replace Loudoun 230 kV breakers 204552, 217352 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.119

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.119
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.119
Title
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.
Description
Loudoun Cap Sub 230kV - replace 50kA breaker SC352 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.128

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.128
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.128
Title
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.
Description
North Anna Sub 500kV - replace 40kA breakers 57502, G102-1, G102-2, G202, G2T575, XT573 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.408

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.408
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.408
Title
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.
Description
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, H342 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s2609.6

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s2609.6
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.6
Title
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Description
Upgrade (2) 230 kV breakers 201342 & L142 from 50kA to 63kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s2609.9

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s2609.9
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.9
Title
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.
Description
Upgrade 230kV Pleasant View breakers L3T203 and L3T2180 from 50kA to 80kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.134

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.134
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.134
Title
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.
Description
Remington Sub 230kV - replace 40kA and 50kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, H9T299 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b1696

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b1696
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b1696
Title
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Description
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.236

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.236
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.236
Title
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.
Description
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers: H1T539 and H2T539
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s3047.2

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s3047.2
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
s3047.2
Title
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
Description
Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV line #535 Loudoun – Meadowbrook and #569 Loudoun - Morrisville as the 500 kV sources into the proposed 500 kV ring bus Vint Hill Substation will be expanded to the north of the existing site to accommodate the 500 kV ring required for the addition of the new transformers Existing terminations for 230 kV line #2174 Wheeler – Vint Hill, line #2101 Bristers – Vint Hill, and line #2163 Liberty – Vint Hill will be rearranged to terminate into the expanded Vint Hill Substation 230 kV line #2114 Remington CT – Rollins Ford will also be cut and looped into the expanded Vint Hill Substation due to spatial constraints along the existing right-of-way.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.312

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.312
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.312
Title
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
Description
Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.313

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.313
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.313
Title
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Description
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.356

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.356
Title
Build a new 500 kV line from Vint Hill to Wishing Star.
Description
Build a new 500kV line from Vint Hill to Wishing Star. The line will be supported on single circuit monopoles. New conductor to have a summer rating of 4357 MVA. Line length is approximately 16.59 miles
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.357

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.357
Title
Build a new 500 kV line from Morrisville to Vint Hill.
Description
Build a new 500kV line from Morrisville to Vint Hill. New conductor to have a summer rating of 4357 MVA. Line length is approximately 19.71 miles.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.354

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.354
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.354
Title
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
Description
Install terminal equipment at Wishing Star substation to support a 5000A line to Vint Hill. Update relay settings for 500kV Lines #546 and #590.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.335

AE2-283 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.335
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.335
Title
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker
Description
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker: 56142
Cost Information
Cost Alloc Type
Contingent

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AE2-283


AE2-283 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Load Flow Dominion n7687 / dom-046 Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV). Eliminated 13.3 MW 3.7% Cost Allocated $158,674
Load Flow Dominion n7812 / dom-397 Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor. Eliminated - 0.0% Contingent $0
Load Flow AEP n9179.0 / AEPAPRJV008 Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line. Eliminated - 0.0% Contingent $0
Load Flow AEP n9178.0 / AEPAPRJV007 Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station. Eliminated - 0.0% Contingent $0
Contributions into Topology or Eliminated Reinforcement Total: $158,674
AE2-283 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Dominion n9138.0 Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. Cost Allocated $33,945
Dominion n9250.0 Construct a new 22.59 mile line between Carson and Rawlings Substations. Cost Allocated $33,212
Dominion n9630.0 Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. Cost Allocated $27,329
Dominion n8492 Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. Cost Allocated $24,489
Dominion n9267.0 Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. Cost Allocated $13,968
Dominion n9259.0 Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. Cost Allocated $7,730
Dominion n7541 Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. Cost Allocated $6,958
Dominion n8492.1 Two Breaker Additions at Fentress Substation. Cost Allocated $6,093
Dominion n8492.2 Expand Yadkin Substation to accommodate the new 500 kV line. Cost Allocated $4,951
ComEd b3811.1 Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. Contingent $0
ComEd s3011 Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. Contingent $0
ComEd b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line Contingent $0
AEP n9243.0 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Contingent $0
ComEd n9195.0 Install a new 345 kV circuit breaker at Station 12 Dresden. Contingent $0
Dominion b4000.357 Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. Contingent $0
Dominion b4000.356 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). Contingent $0
Dominion b4000.355 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). Contingent $0
Dominion b4000.352 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. Contingent $0
Dominion b4000.351 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. Contingent $0
Dominion b4000.350 Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. Contingent $0
Dominion b4000.349 Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. Contingent $0
Dominion b4000.348 Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. Contingent $0
Dominion b4000.346 Cut-in 500kV line from Kraken substation into Yeat substation Contingent $0
Dominion b4000.345 Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0
Dominion b4000.344 Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0
Dominion b4000.342 Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. Contingent $0
Dominion b4000.341 Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. Contingent $0
Dominion b4000.325 Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. Contingent $0
Dominion b3689.2 Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA Contingent $0
Dominion b4000.103 Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA Contingent $0
Dominion b3800.405 Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. Contingent $0
Dominion b3854.1 Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA Contingent $0
Dominion b4000.108 Carson Sub 230kV - replace 40kA breaker 23872 with 63kA Contingent $0
Dominion b4000.326 At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. Contingent $0
Dominion b4000.327 Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. Contingent $0
Dominion b3800.406 Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. Contingent $0
Dominion b4000.115 Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA Contingent $0
Dominion b4000.354 Ladysmith substation breakers replacement: 574T575 and 568T581 Contingent $0
Dominion b3853.1 Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA Contingent $0
Dominion b4000.114 Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA Contingent $0
Dominion b3800.235 Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers Contingent $0
Dominion b3800.334 Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. Contingent $0
Dominion b3800.407 Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. Contingent $0
Dominion b4000.119 Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. Contingent $0
Dominion b4000.128 North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. Contingent $0
Dominion b3800.408 Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. Contingent $0
Dominion s2609.6 Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. Contingent $0
Dominion s2609.9 Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. Contingent $0
Dominion b4000.134 Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. Contingent $0
Dominion b1696 Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 Contingent $0
Dominion b3800.236 Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. Contingent $0
Dominion s3047.2 Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. Contingent $0
Dominion b3800.312 Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. Contingent $0
Dominion b3800.313 Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. Contingent $0
Dominion b3800.356 Build a new 500 kV line from Vint Hill to Wishing Star. Contingent $0
Dominion b3800.357 Build a new 500 kV line from Morrisville to Vint Hill. Contingent $0
Dominion b3800.354 Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. Contingent $0
Dominion b3800.335 Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker Contingent $0
Region Topology Upgrade Total: $158,675

Attachments

AE2-283 One Line Diagram

AE2-283 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.