Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
AE2-283 System Reinforcements:
TO
RTEP ID
Title
Category
Allocated Cost ($USD)
Facilities Study
Dominion
n9143.0
Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor.
Cost Allocated
$1,768,447
Dominion
n9138.0
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Cost Allocated
$33,945
Dominion
n9250.0
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Cost Allocated
$33,212
Dominion
n9630.0
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
Cost Allocated
$27,329
Dominion
n8492
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
Cost Allocated
$24,489
Dominion
n9267.0
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
Cost Allocated
$13,968
Dominion
n9259.0
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Cost Allocated
$7,730
Dominion
n7541
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Cost Allocated
$6,958
Dominion
n8492.1
Two Breaker Additions at Fentress Substation.
Cost Allocated
$6,093
Dominion
n8492.2
Expand Yadkin Substation to accommodate the new 500 kV line.
Cost Allocated
$4,951
Dominion
n6588
Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Cost Allocated
$526
ComEd
b3811.1
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Contingent
$0
N/A
ComEd
s3011
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.
Contingent
$0
N/A
ComEd
b3775.1
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line
Contingent
$0
N/A
AEP
n9243.0
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Contingent
$0
N/A
ComEd
n9195.0
Install a new 345 kV circuit breaker at Station 12 Dresden.
Contingent
$0
N/A
Dominion
b4000.357
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Contingent
$0
N/A
Dominion
b4000.356
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Contingent
$0
N/A
Dominion
b4000.355
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Contingent
$0
N/A
Dominion
b4000.352
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Contingent
$0
N/A
Dominion
b4000.351
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Contingent
$0
N/A
Dominion
b4000.350
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Contingent
$0
N/A
Dominion
b4000.349
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Contingent
$0
N/A
Dominion
b4000.348
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Contingent
$0
N/A
Dominion
b4000.346
Cut-in 500kV line from Kraken substation into Yeat substation
Contingent
$0
N/A
Dominion
b4000.345
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Contingent
$0
N/A
Dominion
b4000.344
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Contingent
$0
N/A
Dominion
b4000.342
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Contingent
$0
N/A
Dominion
b4000.341
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Contingent
$0
N/A
Dominion
b4000.325
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Contingent
$0
N/A
Dominion
b3689.2
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA
Contingent
$0
N/A
Dominion
b4000.103
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Contingent
$0
N/A
Dominion
b3800.405
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Contingent
$0
N/A
Dominion
b3854.1
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Contingent
$0
N/A
Dominion
b4000.108
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Contingent
$0
N/A
Dominion
b4000.326
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Contingent
$0
N/A
Dominion
b4000.327
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Contingent
$0
N/A
Dominion
b3800.406
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Contingent
$0
N/A
Dominion
b4000.115
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Contingent
$0
N/A
Dominion
b4000.354
Ladysmith substation breakers replacement: 574T575 and 568T581
Contingent
$0
N/A
Dominion
b3853.1
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Contingent
$0
N/A
Dominion
b4000.114
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Contingent
$0
N/A
Dominion
b3800.235
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers
Contingent
$0
N/A
Dominion
b3800.334
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.
Contingent
$0
N/A
Dominion
b3800.407
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.
Contingent
$0
N/A
Dominion
b4000.119
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.
Contingent
$0
N/A
Dominion
b4000.128
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.
Contingent
$0
N/A
Dominion
b3800.408
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.
Contingent
$0
N/A
Dominion
s2609.6
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Contingent
$0
N/A
Dominion
s2609.9
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.
Contingent
$0
N/A
Dominion
b4000.134
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.
Contingent
$0
N/A
Dominion
b1696
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Contingent
$0
N/A
Dominion
b3800.236
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.
Contingent
$0
N/A
Dominion
s3047.2
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
Contingent
$0
N/A
Dominion
b3800.312
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
Contingent
$0
N/A
Dominion
b3800.313
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Contingent
$0
N/A
Dominion
b3800.356
Build a new 500 kV line from Vint Hill to Wishing Star.
Contingent
$0
N/A
Dominion
b3800.357
Build a new 500 kV line from Morrisville to Vint Hill.
Contingent
$0
N/A
Dominion
b3800.354
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
Contingent
$0
N/A
Dominion
b3800.335
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker
Contingent
$0
N/A
AEP
b4000.211
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line
Contingent
$0
N/A
AEP
b4000.210
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
Contingent
$0
N/A
AEP
n5613
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
Contingent
$0
N/A
Grand Total:
$1,927,648
PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests.
PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements.
PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to
apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the
topology changing reinforcements. For additional details, please click the icon below
Regional Topology Upgrade Conversion
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate
contributor reinforcements for this project. Please refer to the System Reinforcement table above and the
information below for more detail.
System Reinforcement: n6588
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
n6588 / TC1-PH2-DOM-034
Title
Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Description
Replace 230kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Total Cost ($USD)
$1,725,040
Discounted Total Cost ($USD)
$1,725,040
Allocated Cost ($USD)
$526
Time Estimate
Dec 01 2028
Contributor
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.57%
$9,757
AE2-185
0.03%
$597
AE2-187
0.03%
$518
AE2-283
0.03%
$526
AE2-291
0.54%
$9,277
AF1-123
10.21%
$176,104
AF1-124
10.25%
$176,739
AF1-125
10.05%
$173,379
AF1-294
0.41%
$7,047
AF2-035
0.26%
$4,527
AF2-042
28.18%
$486,093
AF2-046
2.88%
$49,766
AF2-115
0.25%
$4,292
AF2-120
4.50%
$77,663
AF2-222
3.88%
$66,923
AF2-297
0.72%
$12,360
AG1-008
2.88%
$49,766
AG1-021
0.20%
$3,433
AG1-082
0.19%
$3,231
AG1-098
1.60%
$27,651
AG1-105
0.68%
$11,763
AG1-124
1.06%
$18,318
AG1-135
4.42%
$76,186
AG1-146
2.12%
$36,633
AG1-147
4.96%
$85,476
AG1-154
0.14%
$2,384
AG1-166
0.13%
$2,249
AG1-167
0.10%
$1,687
AG1-168
0.10%
$1,687
AG1-285
2.80%
$48,263
AG1-342
0.06%
$1,087
AG1-494
0.82%
$14,097
AG1-536
4.96%
$85,562
System Reinforcement: n9143.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9143.0 / TC1-PH1-DOM-001
Title
Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor.
Description
Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C.
Total Cost ($USD)
$6,315,811
Discounted Total Cost ($USD)
$6,315,811
Allocated Cost ($USD)
$1,768,447
Time Estimate
20 to 21 Months
Contributor
Facility
Contingency
2ALTVSTA-2GLADYS TAP 69.0 kV Ckt 1 line
(Any)
Cost Allocation
Project
MW Impact
Percent Allocation
Allocated Cost ($USD)
AE2-185
⧉
AE2-185 69 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-185, AF2-404
36.0 MW
36.0%
$2,273,682
AE2-187
36.0 MW
36.0%
$2,273,682
AE2-283
28.0 MW
28.0%
$1,768,447
System Reinforcement: n7687
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7687 / dom-046
Title
Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV).
Description
Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV).
Total Cost ($USD)
$10,595,849
Discounted Total Cost ($USD)
$4,330,015
Allocated Cost ($USD)
$158,674
Time Estimate
Jun 01 2029
Contributor Eliminated Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.
Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.
Facility
Contingency
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 1 transformer
(Any)
3SEDGE HILL-6SEDGE HILL 115.0/230.0 kV Ckt 2 transformer
(Any)
Cost Allocation
Project
MW Impact
Percent Allocation
Allocated Cost ($USD)
AE1-148
14.3 MW
3.9%
$170,620
AE2-185
⧉
AE2-185 69 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-185, AF2-404
15.1 MW
4.1%
$179,625
AE2-187
13.1 MW
3.6%
$155,672
AE2-283
13.3 MW
3.7%
$158,674
AE2-291
61.5 MW
16.9%
$732,935
AF1-294
⧉
AF1-294 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-294, AF2-115, AG1-021, AH1-280
6.0 MW
1.7%
$71,940
AF2-115
⧉
AF1-294 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-294, AF2-115, AG1-021, AH1-280
3.7 MW
1.0%
$43,867
AF2-222
33.6 MW
9.2%
$400,282
AF2-297
82.8 MW
22.8%
$986,024
AG1-021
⧉
AF1-294 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-294, AF2-115, AG1-021, AH1-280
2.9 MW
0.8%
$35,089
AG1-105
58.9 MW
16.2%
$700,955
AG1-285
32.3 MW
8.9%
$384,167
AG1-342
26.0 MW
7.2%
$310,166
System Reinforcement: b4000.211
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.211
Title
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line
Description
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line
Projected In Service Date: 06/01/2029
Cost Information
Time Estimate
Jun 01 2029
Contingent Note: Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
Facility
Contingency
05JOHNMT-05NEWLDN 138.0 kV Ckt 1 line
(Any)
System Reinforcement: b4000.210
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.210
Title
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
Description
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.
Cost Information
Time Estimate
Jun 01 2029
Contingent Note: Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
Facility
Contingency
05JOHNMT-05OTTER 138.0 kV Ckt 1 line
(Any)
System Reinforcement
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
(Pending)
Title
Most limiting rating on the Dominion side is the Wave Trap and Lead at Altavista: 363 / 382 /420 MVA.
Description
Most limiting rating on the Dominion side is the Wave Trap and Lead at Altavista: 363 / 382 /420 MVA.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
99 Months
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
Facility
Contingency
05OTTER-4ALTVSTA 138.0 kV Ckt 1 line
(Any)
System Reinforcement: n5613
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n5613 / AEPA0014a
Title
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
Description
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.
Total Cost ($USD)
$2,740,849
Discounted Total Cost ($USD)
$2,740,849
Allocated Cost ($USD)
$0
Time Estimate
Nov 21 2027
Contingent Note: Based on PJM cost allocation criteria, AE2-283 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AE2-283 may not have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
Facility
Contingency
05OTTER-4ALTVSTA 138.0 kV Ckt 1 line
(Any)
System Reinforcement: n7812
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7812 / dom-397
Title
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C.
Total Cost ($USD)
$23,887,052
Discounted Total Cost ($USD)
$23,887,052
Allocated Cost ($USD)
$0
Time Estimate
43 to 44 Months
Contingent Eliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
Facility
Contingency
4BREMO-AE1-108 TAP 138.0 kV Ckt 1 line
(Any)
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line
(Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line
(Any)
System Reinforcement: n9179.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9179.0 / AEPAPRJV008
Title
Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.
Description
"•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design.
•Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line by installing one floating deadend and replacing one structure"
Total Cost ($USD)
$1,245,000
Discounted Total Cost ($USD)
$1,245,000
Allocated Cost ($USD)
$0
Time Estimate
15 Months
Contingent Eliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
Facility
Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line
(Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line
(Any)
System Reinforcement
Type
Load Flow
TO
AEP
RTEP ID / TO ID
(Pending) / NONAEPRJV01
Title
Reinforcement for AE1-108 TP 138 KV to 4BREMO 138 KV ckt 1: Non-AEP Limiting Element.
Description
Non-AEP Limiting Element
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
0 to 1 Months
Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.
Facility
Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line
(Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line
(Any)
System Reinforcement: n9178.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9178.0 / AEPAPRJV007
Title
Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.
Description
•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design.
•Replace 3 structures and 1 floating dead ends along the Reusens – Scottsville – Bremo Bluff line determined in preliminary engineering study.
Total Cost ($USD)
$4,759,000
Discounted Total Cost ($USD)
$4,759,000
Allocated Cost ($USD)
$0
Time Estimate
29 Months
Contingent Eliminated Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 may need this upgrade in-service to be deliverable to the PJM system. If AE2-283 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.
Facility
Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line
(Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line
(Any)
System Reinforcement: n9220.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9220.0 / TC1-PH2-DOM-033
Title
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Total Cost ($USD)
$44,465,922
Discounted Total Cost ($USD)
$44,465,922
Allocated Cost ($USD)
$0
Time Estimate
42 to 48 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.
Facility
Contingency
6BUCKING-6BREMO 230.0 kV Ckt 1 line
(Any)
System Reinforcement: n9217.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9217.0 / TC1-PH2-DOM-028
Title
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
Total Cost ($USD)
$40,414,822
Discounted Total Cost ($USD)
$40,414,822
Allocated Cost ($USD)
$0
Time Estimate
45 to 46 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.
Facility
Contingency
6BUCKING-6FARMVIL 230.0 kV Ckt 1 line
(Any)
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9138.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9138.0 / TC1-PH1-DOM-070
Title
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Description
Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
Total Cost ($USD)
$111,130,292
Discounted Total Cost ($USD)
$111,130,292
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months
Potential Aggregate Contributor Topology Changing Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.
Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
Facility
Contingency
8CARSON-8RAWLINGS 500.0 kV Ckt 1 line
(Any)
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-C
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-A
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P4-2: 51192_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P4-2: 51172_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P4-2: 511T544_SRT-S
8CARSON-AE2-313 TP 500.0 kV Ckt 1 line
(Any)
8RAWLINGS-AE2-313 TP 500.0 kV Ckt 1 line
(Any)
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-C
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-A
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S
System Reinforcement: n9138.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9138.0 / TC1-PH1-DOM-070
Title
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Description
Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
Total Cost ($USD)
$111,130,292
Allocated Cost ($USD)
$33,945
Time Estimate
60 to 61 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$628,539
AE2-185
0.0346 %
$38,427
AE2-187
0.0300 %
$33,303
AE2-283
0.0305 %
$33,945
AE2-291
0.5378 %
$597,692
AF1-123
10.2087 %
$11,345,010
AF1-124
10.2455 %
$11,385,904
AF1-125
10.0507 %
$11,169,384
AF1-294
0.4085 %
$453,960
AF2-035
0.2624 %
$291,649
AF2-042
28.1786 %
$31,314,939
AF2-046
2.8849 %
$3,206,002
AF2-115
0.2488 %
$276,491
AF2-120
4.5021 %
$5,003,236
AF2-222
3.8795 %
$4,311,266
AF2-297
0.7165 %
$796,270
AG1-008
2.8849 %
$3,206,002
AG1-021
0.1990 %
$221,202
AG1-082
0.1873 %
$208,113
AG1-098
1.6029 %
$1,781,295
AG1-105
0.6819 %
$757,790
AG1-124
1.0619 %
$1,180,088
AG1-135
4.4165 %
$4,908,028
AG1-146
2.1236 %
$2,359,969
AG1-147
4.9550 %
$5,506,458
AG1-154
0.1382 %
$153,603
AG1-166
0.1304 %
$144,897
AG1-167
0.0978 %
$108,677
AG1-168
0.0978 %
$108,677
AG1-285
2.7978 %
$3,109,245
AG1-342
0.0630 %
$70,013
AG1-494
0.8172 %
$908,203
AG1-536
4.9600 %
$5,512,015
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9250.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9250.0 / TC1-PH2-DOM-044
Title
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Description
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Total Cost ($USD)
$108,728,086
Discounted Total Cost ($USD)
$108,728,086
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months
Potential Aggregate Contributor Topology Changing Note 1: Based on PJM cost allocation criteria, AE2-283 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AE2-283 could receive cost allocation. Although AE2-283 may not presently have cost responsibility for this upgrade, AE2-283 is a potential Aggregate Pool Contributor.
Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
Facility
Contingency
8CARSON-8RAWLINGS 500.0 kV Ckt 1 line
(Any)
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-C
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-A
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P4-2: 51192_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P4-2: 51172_SRT-S
8CARSON-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P4-2: 511T544_SRT-S
8CARSON-AE2-313 TP 500.0 kV Ckt 1 line
(Any)
8RAWLINGS-AE2-313 TP 500.0 kV Ckt 1 line
(Any)
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-C
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S-A
8ROGERS RD-AE2-094 TP 500.0 kV Ckt 1 line
DVP_P1-2: LN 511_SRT-S
System Reinforcement: n9250.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9250.0 / TC1-PH2-DOM-044
Title
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Description
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Total Cost ($USD)
$108,728,086
Allocated Cost ($USD)
$33,212
Time Estimate
60 to 61 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$614,953
AE2-185
0.0346 %
$37,597
AE2-187
0.0300 %
$32,583
AE2-283
0.0305 %
$33,212
AE2-291
0.5378 %
$584,772
AF1-123
10.2087 %
$11,099,775
AF1-124
10.2455 %
$11,139,785
AF1-125
10.0507 %
$10,927,946
AF1-294
0.4085 %
$444,147
AF2-035
0.2624 %
$285,345
AF2-042
28.1786 %
$30,638,032
AF2-046
2.8849 %
$3,136,700
AF2-115
0.2488 %
$270,514
AF2-120
4.5021 %
$4,895,086
AF2-222
3.8795 %
$4,218,073
AF2-297
0.7165 %
$779,058
AG1-008
2.8849 %
$3,136,700
AG1-021
0.1990 %
$216,420
AG1-082
0.1873 %
$203,614
AG1-098
1.6029 %
$1,742,790
AG1-105
0.6819 %
$741,409
AG1-124
1.0619 %
$1,154,579
AG1-135
4.4165 %
$4,801,936
AG1-146
2.1236 %
$2,308,955
AG1-147
4.9550 %
$5,387,430
AG1-154
0.1382 %
$150,283
AG1-166
0.1304 %
$141,765
AG1-167
0.0978 %
$106,328
AG1-168
0.0978 %
$106,328
AG1-285
2.7978 %
$3,042,035
AG1-342
0.0630 %
$68,500
AG1-494
0.8172 %
$888,571
AG1-536
4.9600 %
$5,392,867
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9630.0
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n9630.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9630.0 / TC1-PH3-DOM-013
Title
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
Description
n9630.0 addresses both stability and load flow violations.
Construct a new 230 kV Line from the AG1-285 substation to the 230 kV Finneywood substation following the Line 1012 ROW for approximately 1.0 miles, then following the Line 556 ROW for approximately 3.5 miles to terminate at Finneywood. Expand the AG1-285 115 kV substation to accommodate two (2) new 115/230 kV transformers. Build a 230 kV substation at AG1-285 to connect the 115/230 kV transformers and the new 230 kV line to Finneywood. Expand the Finneywood 230 kV substation to accommodate the new line. The existing 1.0 miles of 115 kV from AG1-285 to Chase City does not need to be rebuilt to accommodate a new structure in the same right of way and therefore will be unchanged. The existing 3.5 miles of 500 kV towers from Structure 556/46 to Finneywood substation will need to be rebuilt as a double circuit tower to accommodate the new 230 kV line.
Total Cost ($USD)
$89,468,616
Allocated Cost ($USD)
$27,329
Time Estimate
Dec 31 2029
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$506,034
AE2-185
0.0346 %
$30,956
AE2-187
0.0300 %
$26,841
AE2-283
0.0305 %
$27,288
AE2-291
0.5378 %
$481,162
AF1-123
10.2087 %
$9,133,583
AF1-124
10.2455 %
$9,166,507
AF1-125
10.0507 %
$8,992,222
AF1-294
0.4085 %
$365,479
AF2-035
0.2624 %
$234,766
AF2-042
28.1786 %
$25,211,003
AF2-046
2.8849 %
$2,581,080
AF2-115
0.2488 %
$222,598
AF2-120
4.5021 %
$4,027,967
AF2-222
3.8795 %
$3,470,935
AF2-297
0.7165 %
$641,043
AG1-008
2.8849 %
$2,581,080
AG1-021
0.1990 %
$178,043
AG1-082
0.1873 %
$167,575
AG1-098
1.6029 %
$1,434,092
AG1-105
0.6819 %
$610,086
AG1-124
1.0619 %
$950,067
AG1-135
4.4165 %
$3,951,381
AG1-146
2.1236 %
$1,899,956
AG1-147
4.9550 %
$4,433,170
AG1-154
0.1382 %
$123,646
AG1-166
0.1304 %
$116,667
AG1-167
0.0978 %
$87,500
AG1-168
0.0978 %
$87,500
AG1-285
2.7978 %
$2,503,153
AG1-342
0.0630 %
$56,365
AG1-494
0.8172 %
$731,138
AG1-536
4.9600 %
$4,437,643
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n8492
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n8492
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492
Title
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
Description
Wreck and rebuild one (1) overhead 500kV transmission line that will start at the existing Fentress 500 kV Substation and terminate at the existing Yadkin 500 kV Substation, located approximately 13.5 miles away.
Total Cost ($USD)
$80,172,278
Allocated Cost ($USD)
$24,489
Time Estimate
26 to 27 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$453,454
AE2-185
0.0346 %
$27,740
AE2-187
0.0300 %
$24,052
AE2-283
0.0305 %
$24,453
AE2-291
0.5378 %
$431,167
AF1-123
10.2087 %
$8,184,547
AF1-124
10.2455 %
$8,214,051
AF1-125
10.0507 %
$8,057,875
AF1-294
0.4085 %
$327,504
AF2-035
0.2624 %
$210,372
AF2-042
28.1786 %
$22,591,426
AF2-046
2.8849 %
$2,312,890
AF2-115
0.2488 %
$199,469
AF2-120
4.5021 %
$3,609,436
AF2-222
3.8795 %
$3,110,284
AF2-297
0.7165 %
$574,434
AG1-008
2.8849 %
$2,312,890
AG1-021
0.1990 %
$159,543
AG1-082
0.1873 %
$150,163
AG1-098
1.6029 %
$1,285,081
AG1-105
0.6819 %
$546,695
AG1-124
1.0619 %
$851,349
AG1-135
4.4165 %
$3,540,809
AG1-146
2.1236 %
$1,702,538
AG1-147
4.9550 %
$3,972,536
AG1-154
0.1382 %
$110,798
AG1-166
0.1304 %
$104,545
AG1-167
0.0978 %
$78,408
AG1-168
0.0978 %
$78,408
AG1-285
2.7978 %
$2,243,060
AG1-342
0.0630 %
$50,509
AG1-494
0.8172 %
$655,168
AG1-536
4.9600 %
$3,976,545
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9267.0
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n9267.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9267.0 / TC1-PH2-DOM-067
Title
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
Description
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner substations with single (1) 768.2 ACSS/TW “Maumee” at 250 degrees C. This new line will be on separate transmission towers from the existing Northern Neck and Moon Corner line 1059. Station expansion is required at Northern Neck and Moon Corner to accommodate the new line.
Total Cost ($USD)
$45,730,074
Allocated Cost ($USD)
$13,968
Time Estimate
45 to 46 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$258,649
AE2-185
0.0346 %
$15,823
AE2-187
0.0300 %
$13,719
AE2-283
0.0305 %
$13,948
AE2-291
0.5378 %
$245,936
AF1-123
10.2087 %
$4,668,446
AF1-124
10.2455 %
$4,685,275
AF1-125
10.0507 %
$4,596,193
AF1-294
0.4085 %
$186,807
AF2-035
0.2624 %
$119,996
AF2-042
28.1786 %
$12,886,095
AF2-046
2.8849 %
$1,319,267
AF2-115
0.2488 %
$113,776
AF2-120
4.5021 %
$2,058,814
AF2-222
3.8795 %
$1,774,098
AF2-297
0.7165 %
$327,656
AG1-008
2.8849 %
$1,319,267
AG1-021
0.1990 %
$91,003
AG1-082
0.1873 %
$85,652
AG1-098
1.6029 %
$733,007
AG1-105
0.6819 %
$311,833
AG1-124
1.0619 %
$485,608
AG1-135
4.4165 %
$2,019,669
AG1-146
2.1236 %
$971,124
AG1-147
4.9550 %
$2,265,925
AG1-154
0.1382 %
$63,199
AG1-166
0.1304 %
$59,632
AG1-167
0.0978 %
$44,724
AG1-168
0.0978 %
$44,724
AG1-285
2.7978 %
$1,279,436
AG1-342
0.0630 %
$28,810
AG1-494
0.8172 %
$373,706
AG1-536
4.9600 %
$2,268,212
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9259.0
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n9259.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9259.0
Title
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Description
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Total Cost ($USD)
$25,304,902
Allocated Cost ($USD)
$7,730
Time Estimate
38 to 39 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$143,125
AE2-185
0.0346 %
$8,755
AE2-187
0.0300 %
$7,591
AE2-283
0.0305 %
$7,718
AE2-291
0.5378 %
$136,090
AF1-123
10.2087 %
$2,583,302
AF1-124
10.2455 %
$2,592,614
AF1-125
10.0507 %
$2,543,320
AF1-294
0.4085 %
$103,371
AF2-035
0.2624 %
$66,400
AF2-042
28.1786 %
$7,130,567
AF2-046
2.8849 %
$730,021
AF2-115
0.2488 %
$62,959
AF2-120
4.5021 %
$1,139,252
AF2-222
3.8795 %
$981,704
AF2-297
0.7165 %
$181,310
AG1-008
2.8849 %
$730,021
AG1-021
0.1990 %
$50,357
AG1-082
0.1873 %
$47,396
AG1-098
1.6029 %
$405,612
AG1-105
0.6819 %
$172,554
AG1-124
1.0619 %
$268,713
AG1-135
4.4165 %
$1,117,591
AG1-146
2.1236 %
$537,375
AG1-147
4.9550 %
$1,253,858
AG1-154
0.1382 %
$34,971
AG1-166
0.1304 %
$32,998
AG1-167
0.0978 %
$24,748
AG1-168
0.0978 %
$24,748
AG1-285
2.7978 %
$707,981
AG1-342
0.0630 %
$15,942
AG1-494
0.8172 %
$206,792
AG1-536
4.9600 %
$1,255,123
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n7541
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n7541
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7541 / dom-016
Title
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Description
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Total Cost ($USD)
$22,779,395
Allocated Cost ($USD)
$6,958
Time Estimate
Dec 31 2029
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$128,840
AE2-185
0.0346 %
$7,882
AE2-187
0.0300 %
$6,834
AE2-283
0.0305 %
$6,948
AE2-291
0.5378 %
$122,508
AF1-123
10.2087 %
$2,325,480
AF1-124
10.2455 %
$2,333,863
AF1-125
10.0507 %
$2,289,489
AF1-294
0.4085 %
$93,054
AF2-035
0.2624 %
$59,773
AF2-042
28.1786 %
$6,418,915
AF2-046
2.8849 %
$657,163
AF2-115
0.2488 %
$56,675
AF2-120
4.5021 %
$1,025,551
AF2-222
3.8795 %
$883,727
AF2-297
0.7165 %
$163,214
AG1-008
2.8849 %
$657,163
AG1-021
0.1990 %
$45,331
AG1-082
0.1873 %
$42,666
AG1-098
1.6029 %
$365,131
AG1-105
0.6819 %
$155,333
AG1-124
1.0619 %
$241,894
AG1-135
4.4165 %
$1,006,052
AG1-146
2.1236 %
$483,743
AG1-147
4.9550 %
$1,128,719
AG1-154
0.1382 %
$31,481
AG1-166
0.1304 %
$29,704
AG1-167
0.0978 %
$22,278
AG1-168
0.0978 %
$22,278
AG1-285
2.7978 %
$637,322
AG1-342
0.0630 %
$14,351
AG1-494
0.8172 %
$186,153
AG1-536
4.9600 %
$1,129,858
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n8492.1
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n8492.1
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.1
Title
Two Breaker Additions at Fentress Substation.
Description
Install Two 5000 amp GIS Breakers at Fentress Substation to connect the new 500 kV line 5005.
Total Cost ($USD)
$19,945,879
Allocated Cost ($USD)
$6,093
Time Estimate
30 to 36 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$112,814
AE2-185
0.0346 %
$6,901
AE2-187
0.0300 %
$5,984
AE2-283
0.0305 %
$6,083
AE2-291
0.5378 %
$107,269
AF1-123
10.2087 %
$2,036,215
AF1-124
10.2455 %
$2,043,555
AF1-125
10.0507 %
$2,004,700
AF1-294
0.4085 %
$81,479
AF2-035
0.2624 %
$52,338
AF2-042
28.1786 %
$5,620,469
AF2-046
2.8849 %
$575,419
AF2-115
0.2488 %
$49,625
AF2-120
4.5021 %
$897,983
AF2-222
3.8795 %
$773,800
AF2-297
0.7165 %
$142,912
AG1-008
2.8849 %
$575,419
AG1-021
0.1990 %
$39,692
AG1-082
0.1873 %
$37,359
AG1-098
1.6029 %
$319,712
AG1-105
0.6819 %
$136,011
AG1-124
1.0619 %
$211,805
AG1-135
4.4165 %
$880,910
AG1-146
2.1236 %
$423,571
AG1-147
4.9550 %
$988,318
AG1-154
0.1382 %
$27,565
AG1-166
0.1304 %
$26,009
AG1-167
0.0978 %
$19,507
AG1-168
0.0978 %
$19,507
AG1-285
2.7978 %
$558,046
AG1-342
0.0630 %
$12,566
AG1-494
0.8172 %
$162,998
AG1-536
4.9600 %
$989,316
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n8492.2
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n8492.2
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.2
Title
Expand Yadkin Substation to accommodate the new 500 kV line.
Description
Expansion of yadkins 500 kV switchyard to accommodate the new 500 kV line which includes addition of 5000 amp GIS breakers and relocation of the existing suffolk -yadkin 500 kV line#565
Total Cost ($USD)
$16,207,123
Allocated Cost ($USD)
$4,951
Time Estimate
15 to 16 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project
Percent Allocation
Allocated Cost ($USD)
AE1-148
0.5656 %
$91,667
AE2-185
0.0346 %
$5,608
AE2-187
0.0300 %
$4,862
AE2-283
0.0305 %
$4,943
AE2-291
0.5378 %
$87,162
AF1-123
10.2087 %
$1,654,537
AF1-124
10.2455 %
$1,660,501
AF1-125
10.0507 %
$1,628,929
AF1-294
0.4085 %
$66,206
AF2-035
0.2624 %
$42,527
AF2-042
28.1786 %
$4,566,940
AF2-046
2.8849 %
$467,559
AF2-115
0.2488 %
$40,323
AF2-120
4.5021 %
$729,661
AF2-222
3.8795 %
$628,755
AF2-297
0.7165 %
$116,124
AG1-008
2.8849 %
$467,559
AG1-021
0.1990 %
$32,252
AG1-082
0.1873 %
$30,356
AG1-098
1.6029 %
$259,784
AG1-105
0.6819 %
$110,516
AG1-124
1.0619 %
$172,103
AG1-135
4.4165 %
$715,788
AG1-146
2.1236 %
$344,174
AG1-147
4.9550 %
$803,063
AG1-154
0.1382 %
$22,398
AG1-166
0.1304 %
$21,134
AG1-167
0.0978 %
$15,851
AG1-168
0.0978 %
$15,851
AG1-285
2.7978 %
$453,443
AG1-342
0.0630 %
$10,210
AG1-494
0.8172 %
$132,445
AG1-536
4.9600 %
$803,873
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3811.1
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3811.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3811.1 / CE_PJM B3811_L11323
Title
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Description
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: s3011
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: s3011
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
s3011 / CE_S3011
Title
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.
Description
Replace 345 kV open air straight bus with GIS in a breaker and
half configuration (34 Circuit Breakers) at Goodings Grove with
80kA capability.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3775.1
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3775.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3775.1
Title
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line
Description
Outside of the Green Acres substation, swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line to the University Park N-Olive 345 kV line to create a University Park N-Green Acres-Olive and St. John-Olive 345 kV lines.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9243.0
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n9243.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9243.0 / AEPSERG13
Title
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Description
At the Jefferson Station:
• Expand the northeast corner of the station
• Remove Circuit breaker C1
• Install one (1) new 765/345 kV transformer and associated equipment
• Install one (1) new 765 kV circuit breaker with associated control relaying and breaker disconnect switches
• Install one (1) new 345 kV circuit breaker with associated control relaying and breaker disconnect switches
• Install a new station service center
At the Clifty Creek Station:
• Extend 345 kV bus 1 and 2 to make room for a new breaker string
• Move a section of the 138 kV bus underground to make room for the new breaker string
• Relocate circuit breaker S to the new string
• Install two (2) new 345 kV circuit breakers on the new string
•Remove the existing Jefferson – Clifty Creek 345 kV line
•Construct a new Jefferson – Clifty Creek 345 kV double circuit line
•Evaluate line settings for all appropriate lines
•Install direct fiber relaying between the Jefferson and Clifty Creek station
•Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures
Total Cost ($USD)
$200,238,000
Allocated Cost ($USD)
$0
Time Estimate
55 Months
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: n9195.0
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: n9195.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9195.0 / CE_NUN_STA12_345 NEW CB
Title
Install a new 345 kV circuit breaker at Station 12 Dresden.
Description
• Upgrade the existing substation STA 12 Dresden by adding 345kV BT 14-15 circuit breaker and associated disconnect switches.
• Upgrade relay & protection at 345kV substation STA 12 Dresden to support installation of 345kV BT 14-15
Total Cost ($USD)
$3,357,627
Allocated Cost ($USD)
$0
Time Estimate
45 Months
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.357
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.357
Title
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Description
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.356
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.356
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.355
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.355
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.355
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.352
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.352
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.352
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.351
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.351
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.351
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.350
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.350
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.350
Title
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Description
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.349
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.349
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.349
Title
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Description
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.348
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.348
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.348
Title
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Description
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.346
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.346
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.346
Title
Cut-in 500kV line from Kraken substation into Yeat substation
Description
Cut-in 500kV line from Kraken substation into Yeat substation
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.345
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.345
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.345
Title
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.344
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.344
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.344
Title
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.342
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.342
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.342
Title
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Description
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.341
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.341
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.341
Title
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Description
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.325
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.325
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.325
Title
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Description
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3689.2
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3689.2
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3689.2
Title
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA
Description
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 4000A 80 kA breakers and associated equipment including breaker leads as necessary to address breaker duty issues identified in short circuit analysis.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.103
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.103
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.103
Title
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Description
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.405
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.405
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.405
Title
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Description
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3854.1
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3854.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3854.1
Title
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Description
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.108
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.108
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.108
Title
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Description
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.326
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.326
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.326
Title
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Description
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.327
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.327
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.327
Title
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Description
Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.406
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.406
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.406
Title
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Description
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.115
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.115
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.115
Title
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Description
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.354
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.354
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.354
Title
Ladysmith substation breakers replacement: 574T575 and 568T581
Description
Expand Ladysmith substation to a add redundant circuit breakers to the middle breakers on both 500kV strings (574T575 and 568T581). The equipment including switches 57518, 57515, H115 will be replaced with 5000A equipment.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3853.1
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3853.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3853.1 / (Pending)
Title
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Description
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.114
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.114
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.114
Title
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Description
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.235
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.235
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.235
Title
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers
Description
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers: 212352, 2123T2173, 2030T2117, 211752, and 2008T2045
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.334
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.334
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.334
Title
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.
Description
Replace 4 overdutied 230kV breakers at Loudoun Substation with 80kA breakers: 2094T2140, 214052, 200852 and 203052.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.407
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.407
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.407
Title
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.
Description
Replace Loudoun 230 kV breakers 204552, 217352 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.119
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.119
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.119
Title
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.
Description
Loudoun Cap Sub 230kV - replace 50kA breaker SC352 with 63kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.128
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.128
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.128
Title
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.
Description
North Anna Sub 500kV - replace 40kA breakers 57502, G102-1, G102-2, G202, G2T575, XT573 with 63kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.408
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.408
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.408
Title
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.
Description
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, H342 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: s2609.6
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: s2609.6
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.6
Title
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Description
Upgrade (2) 230 kV breakers 201342 & L142 from 50kA to 63kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: s2609.9
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: s2609.9
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.9
Title
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.
Description
Upgrade 230kV Pleasant View breakers L3T203 and L3T2180 from 50kA to 80kA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b4000.134
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b4000.134
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.134
Title
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.
Description
Remington Sub 230kV - replace 40kA and 50kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, H9T299 with 63kA
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b1696
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b1696
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b1696
Title
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Description
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.236
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.236
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.236
Title
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.
Description
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers: H1T539 and H2T539
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: s3047.2
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: s3047.2
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
s3047.2
Title
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
Description
Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV line #535 Loudoun – Meadowbrook and #569 Loudoun - Morrisville as the 500 kV sources into the proposed 500 kV ring bus Vint Hill Substation will be expanded to the north of the existing site to accommodate the 500 kV ring required for the addition of the new transformers Existing terminations for 230 kV line #2174 Wheeler – Vint Hill, line #2101 Bristers – Vint Hill, and line #2163 Liberty – Vint Hill will be rearranged to terminate into the expanded Vint Hill Substation 230 kV line #2114 Remington CT – Rollins Ford will also be cut and looped into the expanded Vint Hill Substation due to spatial constraints along the existing right-of-way.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.312
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.312
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.312
Title
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
Description
Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.313
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.313
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.313
Title
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Description
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.356
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.356
Title
Build a new 500 kV line from Vint Hill to Wishing Star.
Description
Build a new 500kV line from Vint Hill to Wishing Star. The line will be supported on single circuit monopoles. New conductor to have a summer rating of 4357 MVA. Line length is approximately 16.59 miles
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.357
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.357
Title
Build a new 500 kV line from Morrisville to Vint Hill.
Description
Build a new 500kV line from Morrisville to Vint Hill. New conductor to have a summer rating of 4357 MVA. Line length is approximately 19.71 miles.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.354
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.354
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.354
Title
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
Description
Install terminal equipment at Wishing Star substation to support a 5000A line to Vint Hill. Update relay settings for 500kV Lines #546 and #590.
Cost Information
Cost Alloc Type
Contingent
Unconverted Regional Topology Upgrade
Converted Regional Topology Upgrade
System Reinforcement: b3800.335
AE2-283 did not load into this reinforcement
directly however this project contributed to an topology or eliminated upgrade and therefore this
project is responsible for relevant regional upgrades.
System Reinforcement: b3800.335
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.335
Title
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker
Description
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker: 56142
Cost Information
Cost Alloc Type
Contingent
×
Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AE2-283
AE2-283 Contributions into Topology or Eliminated Reinforcements:
Type
TO
RTEP ID / TO ID
Title
Topo or Elim
MW Impact
Percent Allocation
Category
Allocated Cost ($USD)
Load Flow
Dominion
n7687 / dom-046
Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV).
Eliminated
13.3 MW
3.7%
Cost Allocated
$158,674
Load Flow
Dominion
n7812 / dom-397
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Eliminated
-
0.0%
Contingent
$0
Load Flow
AEP
n9179.0 / AEPAPRJV008
Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.
Eliminated
-
0.0%
Contingent
$0
Load Flow
AEP
n9178.0 / AEPAPRJV007
Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.
Eliminated
-
0.0%
Contingent
$0
Contributions into Topology or Eliminated Reinforcement Total:
$158,674
AE2-283 Contingent Region Topology Upgrades:
TO
RTEP ID
Title
Category
Allocated Cost ($USD)
Dominion
n9138.0
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Cost Allocated
$33,945
Dominion
n9250.0
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Cost Allocated
$33,212
Dominion
n9630.0
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
Cost Allocated
$27,329
Dominion
n8492
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
Cost Allocated
$24,489
Dominion
n9267.0
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
Cost Allocated
$13,968
Dominion
n9259.0
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Cost Allocated
$7,730
Dominion
n7541
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Cost Allocated
$6,958
Dominion
n8492.1
Two Breaker Additions at Fentress Substation.
Cost Allocated
$6,093
Dominion
n8492.2
Expand Yadkin Substation to accommodate the new 500 kV line.
Cost Allocated
$4,951
ComEd
b3811.1
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Contingent
$0
ComEd
s3011
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.
Contingent
$0
ComEd
b3775.1
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line
Contingent
$0
AEP
n9243.0
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Contingent
$0
ComEd
n9195.0
Install a new 345 kV circuit breaker at Station 12 Dresden.
Contingent
$0
Dominion
b4000.357
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Contingent
$0
Dominion
b4000.356
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Contingent
$0
Dominion
b4000.355
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Contingent
$0
Dominion
b4000.352
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Contingent
$0
Dominion
b4000.351
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Contingent
$0
Dominion
b4000.350
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Contingent
$0
Dominion
b4000.349
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Contingent
$0
Dominion
b4000.348
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Contingent
$0
Dominion
b4000.346
Cut-in 500kV line from Kraken substation into Yeat substation
Contingent
$0
Dominion
b4000.345
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Contingent
$0
Dominion
b4000.344
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Contingent
$0
Dominion
b4000.342
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Contingent
$0
Dominion
b4000.341
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Contingent
$0
Dominion
b4000.325
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Contingent
$0
Dominion
b3689.2
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA
Contingent
$0
Dominion
b4000.103
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Contingent
$0
Dominion
b3800.405
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Contingent
$0
Dominion
b3854.1
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Contingent
$0
Dominion
b4000.108
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Contingent
$0
Dominion
b4000.326
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Contingent
$0
Dominion
b4000.327
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Contingent
$0
Dominion
b3800.406
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Contingent
$0
Dominion
b4000.115
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Contingent
$0
Dominion
b4000.354
Ladysmith substation breakers replacement: 574T575 and 568T581
Contingent
$0
Dominion
b3853.1
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Contingent
$0
Dominion
b4000.114
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Contingent
$0
Dominion
b3800.235
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers
Contingent
$0
Dominion
b3800.334
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.
Contingent
$0
Dominion
b3800.407
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.
Contingent
$0
Dominion
b4000.119
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.
Contingent
$0
Dominion
b4000.128
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.
Contingent
$0
Dominion
b3800.408
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.
Contingent
$0
Dominion
s2609.6
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Contingent
$0
Dominion
s2609.9
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.
Contingent
$0
Dominion
b4000.134
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.
Contingent
$0
Dominion
b1696
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Contingent
$0
Dominion
b3800.236
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.
Contingent
$0
Dominion
s3047.2
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
Contingent
$0
Dominion
b3800.312
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
Contingent
$0
Dominion
b3800.313
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Contingent
$0
Dominion
b3800.356
Build a new 500 kV line from Vint Hill to Wishing Star.
Contingent
$0
Dominion
b3800.357
Build a new 500 kV line from Morrisville to Vint Hill.
Contingent
$0
Dominion
b3800.354
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
Contingent
$0
Dominion
b3800.335
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker
Contingent
$0
Region Topology Upgrade Total:
$158,675