AF1-088 Phase III Study Report

v1.00 released 2025-09-18 16:22

Sullivan 345 kV

1000.0 MW Capacity / 1000.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Grain Belt Express LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $92,566,895 $32,761,288 = 2.83 AND ( $92,566,895 - $32,761,288 ) 1000.0 = $59,806 per MW

General

The Project Developer has proposed an uprate to a planned/existing Merchant Transmission facility located in the American Electric Power zone — Sullivan County, Indiana. The installed facilities will have a total of 1000.0 MW (1000.0 MW Capacity) of Transmission Injection Rights and 1000.0 MW (0.0 MW Firm) of Transmission Withdrawal Rights.

Project Information
New Service Request Number:
AF1-088
Project Name:
Sullivan 345 kV
Project Developer Name:
Grain Belt Express LLC
State:
Indiana
County:
Sullivan
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
FTIR:
1000.0 MW
NFTIR:
1000.0 MW
FTWR:
0.0 MW
NFTWR:
1000.0 MW
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF1-088 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system as a 525kV HVDC tie at the Sullivan 345kV substation.

 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF1-088 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF1-088 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $3,945,524 $3,945,524
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $1,454,913 $1,454,913
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $86,109,849 $86,109,849
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $1,925,781 $0
AFS - Non-PJM Violations $3,076,351 $0
Total $96,512,419 $91,510,286

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF1-088/AF2-008

Security has been calculated for the AF1-088/AF2-008 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF1-088/AF2-008
Project(s): AF1-088/AF2-008
Final Agreement Security (A): $184,452,241
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $184,452,241
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

AF1-088 will interconnect with the AEP transmission system via a direct connection to the Sullivan 345 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9533.0

Sullivan 345 kV Station: Expansion. • Installation of one (1) new 5000A 345 kV circuit breaker (“E2”), associated control relaying, and disconnect switches. • Associated conductors (buswork, jumpers, etc.), insulators, arresters, foundations, and structures. • Review and revision of the protective relay settings for the remainder of the Sullivan 345 kV Station.

$602,406 $690,035 $91,937 $70,535 $1,454,913 $1,454,913
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

AF1-088: • Extension of rigid bus from the “E” - “E2” breaker position at Sullivan 345 kV Station for the Merchant Transmission lead circuit line exit. • Installation of one (1) new A-Frame take off structure at the end of the new rigid bus extension. • Installation of one (1) new steel, single pole, single circuit, tangent structure on a concrete pier foundation with an anchor bolt cage. • Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage. • Installation of two (2) spans of double bundle aluminum conductor steel reinforced (ACSR) 1272 (Pheasant) transmission line conductor with 7#8 Alumoweld shield wire for the Merchant Transmission lead circuit extending from the Sullivan 345 kV station. • Extension of two (2) underground 48 count all dielectric loose tube (ADLT) fiber optic cables from the Sullivan 345 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the Sullivan 345 kV and Project Developer's converter station. The Project Developer will be responsible for the fiber extension from the splice boxes to the converter station. • Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase coupling capacitor voltage transformers (CCVT), associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module (DICM)-installed metering panel for the Merchant Transmission lead circuit at the Sullivan 345 kV station.

$2,202,063 $1,220,511 $345,211 $177,739 $3,945,524 $3,945,524

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 30 to 60 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AF1-088 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 1000.0 MW (1000.0 MW Capacity) injection and 1000.0 MW (0.0 MW Firm) withdrawal in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Merchant Transmission Requests are evaluated for single or N-1 contingencies. The full energy output of Merchant Transmission Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/AMIL J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
AEP_P4_#3128_05EUGENE 345_A2_SRT-A
CONTINGENCY 'AEP_P4_#3128_05EUGENE 345_A2_SRT-A'
 OPEN BRANCH FROM BUS 243221 TO BUS 249504 CKT 1   /*05EUGENE     345.0 - 08CAYSUB     345.0
 OPEN BRANCH FROM BUS 243221 TO BUS 348885 CKT 1   /*05EUGENE     345.0 - 7BUNSONVILLE 345.0
END
Breaker AC 108.18 % 1635.0 B 1768.74 272.55
AEP/AMIL J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
COMED_P4_080-45-BT4-5___SRT-A
CONTINGENCY 'COMED_P4_080-45-BT4-5___SRT-A'
 TRIP BRANCH FROM BUS 270852 TO BUS 270668 CKT 1   /*PONTIAC  ; B 345.0 - BLUEMOUND; B 345.0
 TRIP BRANCH FROM BUS 270852 TO BUS 270704 CKT 1   /*PONTIAC  ; B 345.0 - LORETTO  ; B 345.0
END
Breaker AC 104.63 % 1635.0 B 1710.77 247.36
AEP/AMIL J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
COMED_P4_080-45-BT7-8___SRT-A
CONTINGENCY 'COMED_P4_080-45-BT7-8___SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270819 CKT 1   /*PONTIAC  ; R 345.0 - MCLEAN ; R   345.0
END
Breaker AC 104.17 % 1635.0 B 1703.12 247.34
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Breaker AC 111.81 % 1374.0 B 1536.32 108.73
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Tower AC 122.0 % 1374.0 B 1676.24 125.18
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-2
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-2'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TP   345.0 - AG1-226 TP   345.0
END
Tower AC 115.45 % 1374.0 B 1586.22 125.18
AEP 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Tower AC 105.61 % 4571.0 B 4827.21 334.5

Details for J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line l/o AEP_P4_#3128_05EUGENE 345_A2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
AEP_P4_#3128_05EUGENE 345_A2_SRT-A
CONTINGENCY 'AEP_P4_#3128_05EUGENE 345_A2_SRT-A'
 OPEN BRANCH FROM BUS 243221 TO BUS 249504 CKT 1   /*05EUGENE     345.0 - 08CAYSUB     345.0
 OPEN BRANCH FROM BUS 243221 TO BUS 348885 CKT 1   /*05EUGENE     345.0 - 7BUNSONVILLE 345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 108.18 %
Rating: 1635.0 MVA
Rating Type: B
MVA to Mitigate: 1768.74 MVA
MW Contribution: 272.55 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
AEP_P4_#3128_05EUGENE 345_A2_SRT-A
CONTINGENCY 'AEP_P4_#3128_05EUGENE 345_A2_SRT-A'
 OPEN BRANCH FROM BUS 243221 TO BUS 249504 CKT 1   /*05EUGENE     345.0 - 08CAYSUB     345.0
 OPEN BRANCH FROM BUS 243221 TO BUS 348885 CKT 1   /*05EUGENE     345.0 - 7BUNSONVILLE 345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 108.04 %
Rating: 1635.0 MVA
Rating Type: B
MVA to Mitigate: 1766.38 MVA
MW Contribution: 274.02 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
272363 ESS H440 ; R Adder 1.42 MW 1.2 MW
962012 AG1-044 E Adder 0.04 MW 0.04 MW
962781 AG1-127 C Adder 3.51 MW 2.98 MW
962782 AG1-127 E Adder 2.33 MW 1.98 MW
965091 AG1-374 C 50/50 21.92 MW 21.92 MW
965092 AG1-374 E 50/50 14.61 MW 14.61 MW
965911 AG1-460 C 50/50 2.06 MW 2.06 MW
965912 AG1-460 E 50/50 3.08 MW 3.08 MW
290021 O50 E Adder 11.02 MW 9.37 MW
290051 GSG-6; E Adder 5.65 MW 4.8 MW
290261 S-027 E 50/50 19.87 MW 19.87 MW
290265 S-028 E 50/50 19.75 MW 19.75 MW
295109 WESTBROOK E Adder 3.03 MW 2.57 MW
295111 SUBLETTE E Adder 1.47 MW 1.25 MW
918052 AA1-018 E OP Adder 8.15 MW 6.93 MW
933911 AD1-013 C Adder 0.99 MW 0.84 MW
933912 AD1-013 E Adder 1.58 MW 1.34 MW
936771 AD2-100 C 50/50 22.16 MW 22.16 MW
936772 AD2-100 E 50/50 14.77 MW 14.77 MW
936971 AD2-131 C 50/50 1.46 MW 1.46 MW
936972 AD2-131 E 50/50 7.33 MW 7.33 MW
937002 AD2-134 E Adder 5.47 MW 4.65 MW
937312 AD2-172 E Adder 1.96 MW 1.67 MW
942111 AE2-223 C 50/50 2.2 MW 2.2 MW
942112 AE2-223 E 50/50 14.73 MW 14.73 MW
942481 AE2-261 C 50/50 30.71 MW 30.71 MW
942482 AE2-261 E 50/50 20.48 MW 20.48 MW
942991 AE2-321 C Adder 4.17 MW 3.54 MW
942992 AE2-321 E Adder 2.05 MW 1.75 MW
958481 AF2-142 C Adder 5.62 MW 4.78 MW
958482 AF2-142 E Adder 3.75 MW 3.19 MW
958491 AF2-143 C Adder 6.05 MW 5.14 MW
958492 AF2-143 E Adder 4.03 MW 3.43 MW
958912 AF2-182 E Adder 21.33 MW 18.13 MW
959081 AF2-199 C Adder 3.94 MW 3.35 MW
959082 AF2-199 E Adder 1.97 MW 1.68 MW
959341 AF2-225 C 50/50 7.11 MW 7.11 MW
959342 AF2-225 E 50/50 9.82 MW 9.82 MW
959351 AF2-226 C Adder 1.23 MW 1.05 MW
959352 AF2-226 E Adder 1.85 MW 1.57 MW
959611 AF2-252 C 50/50 2.44 MW 2.44 MW
959612 AF2-252 E 50/50 3.65 MW 3.65 MW
960281 AF2-319 C Adder 1.23 MW 1.05 MW
960282 AF2-319 E Adder 1.85 MW 1.57 MW
960582 AF2-349 E Adder 18.99 MW 16.14 MW
960611 AF2-352 C 50/50 2.44 MW 2.44 MW
960612 AF2-352 E 50/50 3.65 MW 3.65 MW
960751 AF2-366 C Adder 3.5 MW 2.97 MW
960752 AF2-366 E Adder 2.33 MW 1.98 MW
274650 KINCAID ;1U 50/50 15.4 MW 15.4 MW
274651 KINCAID ;2U 50/50 15.39 MW 15.39 MW
274853 TWINGROVE;U1 50/50 0.69 MW 0.69 MW
274854 TWINGROVE;U2 50/50 0.71 MW 0.71 MW
274859 EASYR;U1 E Adder 7.36 MW 6.26 MW
274860 EASYR;U2 E Adder 7.36 MW 6.26 MW
274880 RADFORD R;1U 50/50 1.12 MW 1.12 MW
276615 W2-048 GEN 50/50 8.47 MW 8.47 MW
276621 X2-022 GEN 50/50 29.0 MW 29.0 MW
293644 O22 E1 Adder 7.09 MW 6.03 MW
293645 O22 E2 Adder 8.12 MW 6.9 MW
293715 O-029 E Adder 6.72 MW 5.71 MW
293716 O-029 E Adder 3.69 MW 3.13 MW
293717 O-029 E Adder 3.39 MW 2.88 MW
293771 O-035 E Adder 5.49 MW 4.66 MW
294401 BSHIL;1U E Adder 6.9 MW 5.87 MW
294410 BSHIL;2U E Adder 6.9 MW 5.87 MW
294763 P-046 E Adder 5.45 MW 4.63 MW
917502 Z2-087 E 50/50 19.64 MW 19.64 MW
925582 AC1-033 E Adder 7.56 MW 6.43 MW
939061 AE1-134 2 Adder 0.89 MW 0.76 MW
940502 AE2-035 E Adder 1.96 MW 1.67 MW
957381 AF2-032 C 50/50 2.31 MW 2.31 MW
957382 AF2-032 E 50/50 1.08 MW 1.08 MW
957471 AF2-041 C Adder 11.83 MW 10.06 MW
957472 AF2-041 E Adder 5.92 MW 5.03 MW
274890 CAYUG;1U E Adder 10.09 MW 8.57 MW
274891 CAYUG;2U E Adder 10.09 MW 8.57 MW
925771 AC1-053 C 50/50 0.64 MW 0.64 MW
925772 AC1-053 E 50/50 26.51 MW 26.51 MW
933441 AC2-157 C Adder -20.71 MW -17.61 MW
938851 AE1-113 C Adder 4.55 MW 3.87 MW
938852 AE1-113 E Adder 16.12 MW 13.7 MW
934101 AD2-000 1 Adder 2.96 MW 2.51 MW
270681 BRIGHTSTK; R 50/50 0.48 MW 0.48 MW
276174 W4-005 E 50/50 39.32 MW 39.32 MW
276655 AB2-047 C1 50/50 0.3 MW 0.3 MW
276656 AB2-047 C2 50/50 0.3 MW 0.3 MW
293516 O-009 E Adder 13.0 MW 11.05 MW
916212 CRESCENT ;1U Adder 3.85 MW 3.28 MW
924048 AB2-047 E1 50/50 12.18 MW 12.18 MW
924049 AB2-047 E2 50/50 12.37 MW 12.37 MW
927208 AC1-214 E1 Adder 2.6 MW 2.21 MW
927209 AC1-214 E2 Adder 2.6 MW 2.21 MW
957751 AF2-069 C Adder 0.17 MW 0.15 MW
957752 AF2-069 E Adder 0.55 MW 0.47 MW
990901 L-005 E Adder 10.69 MW 9.08 MW
290108 LEEDK;1U E Adder 12.25 MW 10.42 MW
916221 Z1-073 E Adder 3.98 MW 3.39 MW
276668 AB2-070 C 50/50 0.64 MW 0.64 MW
924266 AB2-070 E 50/50 23.67 MW 23.67 MW
926821 AC1-168 C Adder 0.83 MW 0.71 MW
926822 AC1-168 E Adder 5.6 MW 4.76 MW
934051 AD1-031 C Adder 2.3 MW 1.95 MW
934052 AD1-031 E Adder 3.75 MW 3.19 MW
935141 AD1-148 C 50/50 0.92 MW 0.92 MW
936292 AD2-038 E Adder 8.31 MW 7.06 MW
936511 AD2-066 C Adder 4.82 MW 4.1 MW
936512 AD2-066 E Adder 3.21 MW 2.73 MW
942421 AE2-255 C Adder 1.72 MW 1.46 MW
942422 AE2-255 E Adder 5.17 MW 4.39 MW
942651 AE2-281 C Adder 0.47 MW 0.4 MW
942652 AE2-281 E Adder 2.89 MW 2.46 MW
959091 AF2-200 C Adder 7.89 MW 6.71 MW
959092 AF2-200 E Adder 5.26 MW 4.47 MW
960141 AF2-305_AG1- 50/50 1.38 MW 1.38 MW
960261 AF2-317 C 50/50 0.39 MW 0.39 MW
961011 AF2-392 C Adder 2.56 MW 2.18 MW
961012 AF2-392 E Adder 11.92 MW 10.13 MW
966822 AG1-553 E Adder 20.92 MW 17.78 MW
930462 AB1-087 E Adder -6.81 MW -5.79 MW
930472 AB1-088 E Adder -6.81 MW -5.79 MW
930481 AB1-089 C Adder 35.71 MW 30.35 MW
930482 AB1-089 E Adder 1.62 MW 1.38 MW
938861 AE1-114 C Adder 2.36 MW 2.0 MW
938862 AE1-114 E Adder 8.04 MW 6.83 MW
939321 AE1-163 C Adder 3.29 MW 2.8 MW
939322 AE1-163 E Adder 20.23 MW 17.19 MW
939401 AE1-172 C Adder 3.39 MW 2.88 MW
939402 AE1-172 E Adder 15.88 MW 13.5 MW
939741 AE1-205 C 50/50 9.48 MW 9.48 MW
939742 AE1-205 E 50/50 13.09 MW 13.09 MW
946152 AF1-280 E Adder 14.22 MW 12.09 MW
946321 AF1-296 C Adder 2.66 MW 2.26 MW
946322 AF1-296 E Adder 12.47 MW 10.6 MW
946671 AF1-331 C Adder 1.29 MW 1.09 MW
962691 AG1-118 C Adder 10.95 MW 9.31 MW
962692 AG1-118 E Adder 7.3 MW 6.21 MW
963831 AG1-236 C 50/50 3.57 MW 3.57 MW
963832 AG1-236 E 50/50 23.86 MW 23.86 MW
941731 AE2-173 C 50/50 5.64 MW 5.64 MW
944221 AF1-090 C 50/50 6.67 MW 6.67 MW
944222 AF1-090 E 50/50 31.22 MW 31.22 MW
965331 AG1-398 C 50/50 0.17 MW 0.17 MW
965931 AG1-462 C Adder 12.31 MW 10.46 MW
965932 AG1-462 E Adder 8.21 MW 6.97 MW
944202 AF1-088 NFTW 50/50 272.55 MW 272.55 MW
920272 AA2-123 E Adder 1.46 MW 1.24 MW
276626 AG1-044 E Adder 0.05 MW 0.04 MW
991082 J1475 G External Queue 3.86 MW 3.86 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 82.78 MW 82.78 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 52.73 MW 52.73 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 14.74 MW 14.74 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.61 MW 0.61 MW
NY PJM->LTFIMP_NY CLTF 0.34 MW 0.34 MW
WEC LTFEXP_WEC->PJM CLTF 2.11 MW 2.11 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.85 MW 0.85 MW
TVA LTFEXP_TVA->PJM CLTF 7.29 MW 7.29 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.86 MW 0.86 MW
MEC LTFEXP_MEC->PJM CLTF 14.61 MW 14.61 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.17 MW 2.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.43 MW 11.43 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.18 MW 0.18 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.94 MW 3.94 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.39 MW 0.39 MW

Details for J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line l/o COMED_P4_080-45-BT4-5___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
COMED_P4_080-45-BT4-5___SRT-A
CONTINGENCY 'COMED_P4_080-45-BT4-5___SRT-A'
 TRIP BRANCH FROM BUS 270852 TO BUS 270668 CKT 1   /*PONTIAC  ; B 345.0 - BLUEMOUND; B 345.0
 TRIP BRANCH FROM BUS 270852 TO BUS 270704 CKT 1   /*PONTIAC  ; B 345.0 - LORETTO  ; B 345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 104.63 %
Rating: 1635.0 MVA
Rating Type: B
MVA to Mitigate: 1710.77 MVA
MW Contribution: 247.36 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
COMED_P4_080-45-BT4-5___SRT-A
CONTINGENCY 'COMED_P4_080-45-BT4-5___SRT-A'
 TRIP BRANCH FROM BUS 270852 TO BUS 270668 CKT 1   /*PONTIAC  ; B 345.0 - BLUEMOUND; B 345.0
 TRIP BRANCH FROM BUS 270852 TO BUS 270704 CKT 1   /*PONTIAC  ; B 345.0 - LORETTO  ; B 345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 104.25 %
Rating: 1635.0 MVA
Rating Type: B
MVA to Mitigate: 1704.44 MVA
MW Contribution: 248.49 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
272363 ESS H440 ; R Adder 1.12 MW 0.96 MW
962012 AG1-044 E Adder 0.03 MW 0.03 MW
965091 AG1-374 C 50/50 24.92 MW 24.92 MW
965092 AG1-374 E 50/50 16.61 MW 16.61 MW
965911 AG1-460 C 50/50 1.8 MW 1.8 MW
965912 AG1-460 E 50/50 2.71 MW 2.71 MW
290021 O50 E Adder 8.83 MW 7.5 MW
290051 GSG-6; E Adder 4.49 MW 3.82 MW
290261 S-027 E 50/50 22.59 MW 22.59 MW
290265 S-028 E 50/50 22.45 MW 22.45 MW
295109 WESTBROOK E Adder 2.4 MW 2.04 MW
295111 SUBLETTE E Adder 1.17 MW 0.99 MW
933911 AD1-013 C Adder 0.79 MW 0.67 MW
933912 AD1-013 E Adder 1.26 MW 1.07 MW
936771 AD2-100 C 50/50 19.52 MW 19.52 MW
936772 AD2-100 E 50/50 13.01 MW 13.01 MW
936971 AD2-131 C 50/50 1.28 MW 1.28 MW
936972 AD2-131 E 50/50 6.46 MW 6.46 MW
937002 AD2-134 E Adder 4.34 MW 3.69 MW
937312 AD2-172 E Adder 1.58 MW 1.34 MW
942111 AE2-223 C Adder 1.87 MW 1.59 MW
942112 AE2-223 E Adder 12.52 MW 10.64 MW
942481 AE2-261 C 50/50 26.99 MW 26.99 MW
942482 AE2-261 E 50/50 17.99 MW 17.99 MW
958491 AF2-143 C Adder 4.83 MW 4.1 MW
958492 AF2-143 E Adder 3.22 MW 2.73 MW
958912 AF2-182 E Adder 17.31 MW 14.71 MW
959081 AF2-199 C Adder 3.15 MW 2.68 MW
959082 AF2-199 E Adder 1.58 MW 1.34 MW
959341 AF2-225 C Adder 6.04 MW 5.14 MW
959342 AF2-225 E Adder 8.35 MW 7.09 MW
959611 AF2-252 C 50/50 2.77 MW 2.77 MW
959612 AF2-252 E 50/50 4.15 MW 4.15 MW
960611 AF2-352 C 50/50 2.77 MW 2.77 MW
960612 AF2-352 E 50/50 4.15 MW 4.15 MW
274650 KINCAID ;1U 50/50 13.52 MW 13.52 MW
274651 KINCAID ;2U 50/50 13.52 MW 13.52 MW
274853 TWINGROVE;U1 50/50 0.79 MW 0.79 MW
274854 TWINGROVE;U2 50/50 0.81 MW 0.81 MW
274859 EASYR;U1 E Adder 5.97 MW 5.07 MW
274860 EASYR;U2 E Adder 5.97 MW 5.07 MW
274880 RADFORD R;1U 50/50 1.03 MW 1.03 MW
276615 W2-048 GEN 50/50 7.23 MW 7.23 MW
276621 X2-022 GEN 50/50 24.75 MW 24.75 MW
293715 O-029 E Adder 5.48 MW 4.66 MW
293716 O-029 E Adder 3.0 MW 2.55 MW
293717 O-029 E Adder 2.76 MW 2.35 MW
293771 O-035 E Adder 4.45 MW 3.78 MW
294401 BSHIL;1U E Adder 5.64 MW 4.79 MW
294410 BSHIL;2U E Adder 5.64 MW 4.79 MW
294763 P-046 E Adder 4.38 MW 3.72 MW
917502 Z2-087 E Adder 16.69 MW 14.19 MW
925582 AC1-033 E Adder 6.18 MW 5.25 MW
939061 AE1-134 2 Adder 0.72 MW 0.62 MW
940502 AE2-035 E Adder 1.58 MW 1.34 MW
957381 AF2-032 C 50/50 2.02 MW 2.02 MW
957382 AF2-032 E 50/50 0.95 MW 0.95 MW
957471 AF2-041 C Adder 9.45 MW 8.04 MW
957472 AF2-041 E Adder 4.73 MW 4.02 MW
925771 AC1-053 C 50/50 0.54 MW 0.54 MW
925772 AC1-053 E 50/50 22.34 MW 22.34 MW
933441 AC2-157 C Adder -18.8 MW -15.98 MW
938851 AE1-113 C Adder 3.64 MW 3.1 MW
938852 AE1-113 E Adder 12.91 MW 10.97 MW
934101 AD2-000 1 Adder 2.37 MW 2.02 MW
276174 W4-005 E 50/50 36.05 MW 36.05 MW
293516 O-009 E Adder 10.59 MW 9.01 MW
916212 CRESCENT ;1U Adder 3.13 MW 2.66 MW
924048 AB2-047 E1 Adder 10.35 MW 8.8 MW
924049 AB2-047 E2 Adder 10.52 MW 8.94 MW
927208 AC1-214 E1 Adder 2.11 MW 1.79 MW
927209 AC1-214 E2 Adder 2.11 MW 1.79 MW
957751 AF2-069 C Adder 0.14 MW 0.12 MW
957752 AF2-069 E Adder 0.44 MW 0.38 MW
990901 L-005 E Adder 8.75 MW 7.44 MW
916221 Z1-073 E Adder 3.17 MW 2.69 MW
276668 AB2-070 C 50/50 0.54 MW 0.54 MW
924266 AB2-070 E 50/50 19.82 MW 19.82 MW
926821 AC1-168 C Adder 0.67 MW 0.57 MW
926822 AC1-168 E Adder 4.46 MW 3.79 MW
934051 AD1-031 C Adder 1.88 MW 1.59 MW
934052 AD1-031 E Adder 3.06 MW 2.6 MW
935141 AD1-148 C 50/50 0.79 MW 0.79 MW
936292 AD2-038 E Adder 6.63 MW 5.63 MW
936511 AD2-066 C Adder 3.77 MW 3.2 MW
936512 AD2-066 E Adder 2.51 MW 2.14 MW
942421 AE2-255 C Adder 1.38 MW 1.17 MW
942422 AE2-255 E Adder 4.14 MW 3.52 MW
942651 AE2-281 C Adder 0.38 MW 0.32 MW
942652 AE2-281 E Adder 2.31 MW 1.96 MW
959091 AF2-200 C Adder 6.3 MW 5.36 MW
959092 AF2-200 E Adder 4.2 MW 3.57 MW
960141 AF2-305_AG1- 50/50 1.16 MW 1.16 MW
960261 AF2-317 C 50/50 0.33 MW 0.33 MW
961011 AF2-392 C Adder 2.08 MW 1.77 MW
961012 AF2-392 E Adder 9.7 MW 8.24 MW
966822 AG1-553 E Adder 17.36 MW 14.76 MW
930462 AB1-087 E Adder -6.18 MW -5.26 MW
930472 AB1-088 E Adder -6.18 MW -5.26 MW
930481 AB1-089 C Adder 28.51 MW 24.23 MW
930482 AB1-089 E Adder 1.3 MW 1.1 MW
938861 AE1-114 C Adder 1.9 MW 1.62 MW
938862 AE1-114 E Adder 6.49 MW 5.52 MW
939321 AE1-163 C Adder 2.63 MW 2.23 MW
939322 AE1-163 E Adder 16.14 MW 13.72 MW
939741 AE1-205 C Adder 8.06 MW 6.85 MW
939742 AE1-205 E Adder 11.13 MW 9.46 MW
946152 AF1-280 E Adder 11.54 MW 9.81 MW
946321 AF1-296 C Adder 2.2 MW 1.87 MW
946322 AF1-296 E Adder 10.32 MW 8.77 MW
946671 AF1-331 C Adder 1.02 MW 0.87 MW
963831 AG1-236 C 50/50 3.0 MW 3.0 MW
963832 AG1-236 E 50/50 20.1 MW 20.1 MW
941731 AE2-173 C Adder 4.8 MW 4.08 MW
944221 AF1-090 C 50/50 5.91 MW 5.91 MW
944222 AF1-090 E 50/50 27.66 MW 27.66 MW
965331 AG1-398 C 50/50 0.14 MW 0.14 MW
965931 AG1-462 C Adder 10.22 MW 8.69 MW
965932 AG1-462 E Adder 6.81 MW 5.79 MW
944202 AF1-088 NFTW 50/50 247.36 MW 247.36 MW
276626 AG1-044 E Adder 0.04 MW 0.03 MW
954822 J955 External Queue 96.61 MW 96.61 MW
990057 J1201 External Queue 6.13 MW 6.13 MW
990272 J1263 G External Queue 104.23 MW 104.23 MW
990857 J1408 External Queue 8.69 MW 8.69 MW
991037 J1464 G External Queue 11.55 MW 11.55 MW
991082 J1475 G External Queue 38.48 MW 38.48 MW
991197 J1626 External Queue 25.45 MW 25.45 MW
991267 J1714 External Queue 16.96 MW 16.96 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 71.28 MW 71.28 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 46.07 MW 46.07 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 14.05 MW 14.05 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.42 MW 0.42 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
WEC LTFEXP_WEC->PJM CLTF 1.69 MW 1.69 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.84 MW 0.84 MW
TVA LTFEXP_TVA->PJM CLTF 6.61 MW 6.61 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.82 MW 0.82 MW
MEC LTFEXP_MEC->PJM CLTF 12.57 MW 12.57 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.12 MW 2.12 MW
LAGN LTFEXP_LAGN->PJM CLTF 10.31 MW 10.31 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.12 MW 0.12 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.71 MW 2.71 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.39 MW 0.39 MW

Details for J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line l/o COMED_P4_080-45-BT7-8___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
COMED_P4_080-45-BT7-8___SRT-A
CONTINGENCY 'COMED_P4_080-45-BT7-8___SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270819 CKT 1   /*PONTIAC  ; R 345.0 - MCLEAN ; R   345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 104.17 %
Rating: 1635.0 MVA
Rating Type: B
MVA to Mitigate: 1703.12 MVA
MW Contribution: 247.34 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
COMED_P4_080-45-BT7-8___SRT-A
CONTINGENCY 'COMED_P4_080-45-BT7-8___SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
 TRIP BRANCH FROM BUS 270853 TO BUS 270819 CKT 1   /*PONTIAC  ; R 345.0 - MCLEAN ; R   345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 103.76 %
Rating: 1635.0 MVA
Rating Type: B
MVA to Mitigate: 1696.48 MVA
MW Contribution: 248.47 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
962012 AG1-044 E Adder 0.03 MW 0.03 MW
965091 AG1-374 C Adder 16.54 MW 14.06 MW
965092 AG1-374 E Adder 11.03 MW 9.38 MW
965911 AG1-460 C 50/50 1.77 MW 1.77 MW
965912 AG1-460 E 50/50 2.65 MW 2.65 MW
290021 O50 E Adder 8.5 MW 7.23 MW
290261 S-027 E Adder 15.0 MW 12.75 MW
290265 S-028 E Adder 14.91 MW 12.67 MW
936771 AD2-100 C 50/50 19.16 MW 19.16 MW
936772 AD2-100 E 50/50 12.77 MW 12.77 MW
936971 AD2-131 C 50/50 1.26 MW 1.26 MW
936972 AD2-131 E 50/50 6.34 MW 6.34 MW
937312 AD2-172 E Adder 1.53 MW 1.3 MW
942111 AE2-223 C 50/50 2.5 MW 2.5 MW
942112 AE2-223 E 50/50 16.74 MW 16.74 MW
942481 AE2-261 C 50/50 26.46 MW 26.46 MW
942482 AE2-261 E 50/50 17.64 MW 17.64 MW
958491 AF2-143 C Adder 4.71 MW 4.0 MW
958492 AF2-143 E Adder 3.14 MW 2.67 MW
958912 AF2-182 E Adder 16.87 MW 14.34 MW
959081 AF2-199 C Adder 3.07 MW 2.61 MW
959082 AF2-199 E Adder 1.53 MW 1.3 MW
959341 AF2-225 C 50/50 8.08 MW 8.08 MW
959342 AF2-225 E 50/50 11.16 MW 11.16 MW
959611 AF2-252 C Adder 1.84 MW 1.56 MW
959612 AF2-252 E Adder 2.76 MW 2.34 MW
960611 AF2-352 C Adder 1.84 MW 1.56 MW
960612 AF2-352 E Adder 2.76 MW 2.34 MW
274650 KINCAID ;1U 50/50 13.25 MW 13.25 MW
274651 KINCAID ;2U 50/50 13.24 MW 13.24 MW
274859 EASYR;U1 E Adder 5.81 MW 4.94 MW
274860 EASYR;U2 E Adder 5.81 MW 4.94 MW
274880 RADFORD R;1U 50/50 0.91 MW 0.91 MW
276615 W2-048 GEN 50/50 7.42 MW 7.42 MW
276621 X2-022 GEN 50/50 25.39 MW 25.39 MW
293715 O-029 E Adder 5.38 MW 4.57 MW
293716 O-029 E Adder 2.95 MW 2.51 MW
293717 O-029 E Adder 2.71 MW 2.3 MW
293771 O-035 E Adder 4.45 MW 3.78 MW
294401 BSHIL;1U E Adder 5.6 MW 4.76 MW
294410 BSHIL;2U E Adder 5.6 MW 4.76 MW
294763 P-046 E Adder 4.26 MW 3.62 MW
917502 Z2-087 E 50/50 22.32 MW 22.32 MW
925582 AC1-033 E Adder 6.13 MW 5.21 MW
939061 AE1-134 2 Adder 0.71 MW 0.6 MW
940502 AE2-035 E Adder 1.53 MW 1.3 MW
957381 AF2-032 C 50/50 1.98 MW 1.98 MW
957382 AF2-032 E 50/50 0.93 MW 0.93 MW
957471 AF2-041 C Adder 9.2 MW 7.82 MW
957472 AF2-041 E Adder 4.6 MW 3.91 MW
274890 CAYUG;1U E Adder 7.11 MW 6.04 MW
274891 CAYUG;2U E Adder 7.11 MW 6.04 MW
925771 AC1-053 C 50/50 0.56 MW 0.56 MW
925772 AC1-053 E 50/50 23.45 MW 23.45 MW
933441 AC2-157 C Adder -18.8 MW -15.98 MW
938851 AE1-113 C Adder 3.51 MW 2.98 MW
938852 AE1-113 E Adder 12.44 MW 10.57 MW
270681 BRIGHTSTK; R 50/50 0.55 MW 0.55 MW
276174 W4-005 E 50/50 31.62 MW 31.62 MW
276655 AB2-047 C1 50/50 0.34 MW 0.34 MW
276656 AB2-047 C2 50/50 0.34 MW 0.34 MW
293516 O-009 E Adder 10.4 MW 8.84 MW
916212 CRESCENT ;1U Adder 3.12 MW 2.66 MW
924048 AB2-047 E1 50/50 13.84 MW 13.84 MW
924049 AB2-047 E2 50/50 14.06 MW 14.06 MW
927208 AC1-214 E1 Adder 2.11 MW 1.79 MW
927209 AC1-214 E2 Adder 2.11 MW 1.79 MW
957751 AF2-069 C Adder 0.14 MW 0.12 MW
957752 AF2-069 E Adder 0.44 MW 0.38 MW
990901 L-005 E Adder 8.69 MW 7.39 MW
276668 AB2-070 C 50/50 0.57 MW 0.57 MW
924266 AB2-070 E 50/50 21.04 MW 21.04 MW
926821 AC1-168 C Adder 0.67 MW 0.57 MW
926822 AC1-168 E Adder 4.5 MW 3.82 MW
934051 AD1-031 C Adder 1.86 MW 1.58 MW
934052 AD1-031 E Adder 3.04 MW 2.58 MW
935141 AD1-148 C 50/50 0.81 MW 0.81 MW
936292 AD2-038 E Adder 6.46 MW 5.49 MW
936511 AD2-066 C Adder 3.73 MW 3.17 MW
936512 AD2-066 E Adder 2.49 MW 2.12 MW
942421 AE2-255 C Adder 1.33 MW 1.13 MW
942422 AE2-255 E Adder 3.99 MW 3.39 MW
942651 AE2-281 C Adder 0.37 MW 0.31 MW
942652 AE2-281 E Adder 2.25 MW 1.91 MW
959091 AF2-200 C Adder 6.13 MW 5.21 MW
959092 AF2-200 E Adder 4.09 MW 3.48 MW
960141 AF2-305_AG1- 50/50 1.23 MW 1.23 MW
960261 AF2-317 C 50/50 0.34 MW 0.34 MW
961011 AF2-392 C Adder 2.04 MW 1.73 MW
961012 AF2-392 E Adder 9.47 MW 8.05 MW
966822 AG1-553 E Adder 16.99 MW 14.44 MW
930462 AB1-087 E Adder -6.18 MW -5.26 MW
930472 AB1-088 E Adder -6.18 MW -5.26 MW
938861 AE1-114 C Adder 1.85 MW 1.57 MW
938862 AE1-114 E Adder 6.32 MW 5.37 MW
939321 AE1-163 C Adder 2.56 MW 2.18 MW
939322 AE1-163 E Adder 15.74 MW 13.38 MW
939401 AE1-172 C Adder 2.41 MW 2.05 MW
939402 AE1-172 E Adder 11.29 MW 9.6 MW
939741 AE1-205 C 50/50 10.78 MW 10.78 MW
939742 AE1-205 E 50/50 14.88 MW 14.88 MW
946152 AF1-280 E Adder 11.25 MW 9.56 MW
946321 AF1-296 C Adder 2.16 MW 1.83 MW
946322 AF1-296 E Adder 10.1 MW 8.58 MW
963831 AG1-236 C 50/50 3.15 MW 3.15 MW
963832 AG1-236 E 50/50 21.1 MW 21.1 MW
941731 AE2-173 C 50/50 6.41 MW 6.41 MW
944221 AF1-090 C 50/50 5.83 MW 5.83 MW
944222 AF1-090 E 50/50 27.27 MW 27.27 MW
965331 AG1-398 C 50/50 0.15 MW 0.15 MW
965931 AG1-462 C Adder 10.0 MW 8.5 MW
965932 AG1-462 E Adder 6.66 MW 5.66 MW
944202 AF1-088 NFTW 50/50 247.34 MW 247.34 MW
276626 AG1-044 E Adder 0.04 MW 0.03 MW
954822 J955 External Queue 94.27 MW 94.27 MW
990057 J1201 External Queue 6.09 MW 6.09 MW
990272 J1263 G External Queue 104.38 MW 104.38 MW
990857 J1408 External Queue 8.5 MW 8.5 MW
991037 J1464 G External Queue 43.53 MW 43.53 MW
991082 J1475 G External Queue 38.52 MW 38.52 MW
991197 J1626 External Queue 25.35 MW 25.35 MW
991267 J1714 External Queue 16.9 MW 16.9 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 70.07 MW 70.07 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 45.8 MW 45.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 14.02 MW 14.02 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.41 MW 0.41 MW
NY PJM->LTFIMP_NY CLTF 0.23 MW 0.23 MW
WEC LTFEXP_WEC->PJM CLTF 1.64 MW 1.64 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.85 MW 0.85 MW
TVA LTFEXP_TVA->PJM CLTF 6.57 MW 6.57 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.81 MW 0.81 MW
MEC LTFEXP_MEC->PJM CLTF 12.37 MW 12.37 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.11 MW 2.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 10.22 MW 10.22 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.12 MW 0.12 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.61 MW 2.61 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.39 MW 0.39 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P4_#4697_05DEQUIN 345_B_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 111.81 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1536.32 MVA
MW Contribution: 108.73 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P4_#4697_05DEQUIN 345_B_SRT-A
CONTINGENCY 'AEP_P4_#4697_05DEQUIN 345_B_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 113.11 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1554.07 MVA
MW Contribution: 109.52 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 13.83 MW 11.76 MW
965092 AG1-374 E Adder 9.22 MW 7.84 MW
965911 AG1-460 C Adder 1.02 MW 0.86 MW
965912 AG1-460 E Adder 1.52 MW 1.29 MW
290261 S-027 E Adder 12.54 MW 10.66 MW
290265 S-028 E Adder 12.46 MW 10.59 MW
936771 AD2-100 C Adder 10.57 MW 8.99 MW
936772 AD2-100 E Adder 7.05 MW 5.99 MW
936971 AD2-131 C Adder 0.7 MW 0.59 MW
936972 AD2-131 E Adder 3.5 MW 2.98 MW
942111 AE2-223 C Adder 1.46 MW 1.24 MW
942112 AE2-223 E Adder 9.76 MW 8.29 MW
942481 AE2-261 C Adder 15.19 MW 12.91 MW
942482 AE2-261 E Adder 10.12 MW 8.61 MW
959341 AF2-225 C Adder 4.71 MW 4.0 MW
959342 AF2-225 E Adder 6.51 MW 5.53 MW
959611 AF2-252 C Adder 1.54 MW 1.31 MW
959612 AF2-252 E Adder 2.3 MW 1.96 MW
960611 AF2-352 C Adder 1.54 MW 1.31 MW
960612 AF2-352 E Adder 2.3 MW 1.96 MW
276615 W2-048 GEN Adder 4.86 MW 4.13 MW
276621 X2-022 GEN Adder 16.62 MW 14.13 MW
917502 Z2-087 E Adder 13.01 MW 11.06 MW
957381 AF2-032 C Adder 1.16 MW 0.98 MW
957382 AF2-032 E Adder 0.54 MW 0.46 MW
274890 CAYUG;1U E Adder 6.35 MW 5.39 MW
274891 CAYUG;2U E Adder 6.35 MW 5.39 MW
925772 AC1-053 E Adder 16.01 MW 13.61 MW
933441 AC2-157 C 50/50 8.26 MW 8.26 MW
933442 AC2-157 E 50/50 13.48 MW 13.48 MW
276174 W4-005 E Adder 24.47 MW 20.8 MW
924048 AB2-047 E1 Adder 8.07 MW 6.86 MW
924049 AB2-047 E2 Adder 8.2 MW 6.97 MW
924266 AB2-070 E Adder 14.64 MW 12.45 MW
942601 AE2-276 C 50/50 5.44 MW 5.44 MW
945391 AF1-204 C 50/50 33.47 MW 33.47 MW
945392 AF1-204 E 50/50 100.41 MW 100.41 MW
960141 AF2-305_AG1- Adder 0.86 MW 0.73 MW
930461 AB1-087 C 50/50 9.5 MW 9.5 MW
930462 AB1-087 E 50/50 2.72 MW 2.72 MW
930471 AB1-088 C 50/50 9.36 MW 9.36 MW
930472 AB1-088 E 50/50 2.72 MW 2.72 MW
939741 AE1-205 C Adder 6.28 MW 5.34 MW
939742 AE1-205 E Adder 8.67 MW 7.37 MW
963741 AG1-226 C 50/50 74.54 MW 74.54 MW
963742 AG1-226 E 50/50 161.69 MW 161.69 MW
963831 AG1-236 C Adder 2.15 MW 1.83 MW
963832 AG1-236 E Adder 14.4 MW 12.24 MW
963841 AG1-237 C 50/50 13.65 MW 13.65 MW
963842 AG1-237 E 50/50 91.34 MW 91.34 MW
941731 AE2-173 C Adder 3.74 MW 3.18 MW
944221 AF1-090 C Adder 2.88 MW 2.45 MW
944222 AF1-090 E Adder 13.48 MW 11.46 MW
944201 AF1-088 FTIR 50/50 108.73 MW 108.73 MW
957141 AF2-008 FTIR 50/50 54.36 MW 54.36 MW
957142 AF2-008 NFTI 50/50 54.36 MW 54.36 MW
954822 J955 External Queue 75.8 MW 75.8 MW
956282 J1115 C External Queue 3.09 MW 3.09 MW
956283 J1115 E External Queue 16.7 MW 16.7 MW
956452 J1139 External Queue 34.17 MW 34.17 MW
990272 J1263 G External Queue 31.21 MW 31.21 MW
990672 J1360 External Queue 48.18 MW 48.18 MW
990857 J1408 External Queue 6.87 MW 6.87 MW
991037 J1464 G External Queue 39.09 MW 39.09 MW
991082 J1475 G External Queue 6.57 MW 6.57 MW
991192 J1610 G External Queue 6.93 MW 6.93 MW
991197 J1626 External Queue 4.71 MW 4.71 MW
992572 J1022 External Queue 22.82 MW 22.82 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 30.94 MW 30.94 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.08 MW 2.08 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.7 MW 0.7 MW
NY PJM->LTFIMP_NY CLTF 0.38 MW 0.38 MW
WEC LTFEXP_WEC->PJM CLTF 1.05 MW 1.05 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.14 MW 0.14 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.07 MW 0.07 MW
TVA LTFEXP_TVA->PJM CLTF 0.83 MW 0.83 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.87 MW 0.87 MW
MEC LTFEXP_MEC->PJM CLTF 5.72 MW 5.72 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.9 MW 2.9 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.25 MW 2.25 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.5 MW 4.5 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.22 MW 0.22 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 122.0 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1676.24 MVA
MW Contribution: 125.18 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 123.47 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1696.42 MVA
MW Contribution: 126.04 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 14.0 MW 11.9 MW
965092 AG1-374 E Adder 9.34 MW 7.93 MW
965911 AG1-460 C Adder 1.05 MW 0.9 MW
965912 AG1-460 E Adder 1.58 MW 1.34 MW
290261 S-027 E Adder 12.7 MW 10.79 MW
290265 S-028 E Adder 12.62 MW 10.72 MW
936771 AD2-100 C Adder 10.99 MW 9.34 MW
936772 AD2-100 E Adder 7.32 MW 6.23 MW
936971 AD2-131 C Adder 0.72 MW 0.61 MW
936972 AD2-131 E Adder 3.64 MW 3.09 MW
942111 AE2-223 C Adder 1.47 MW 1.25 MW
942112 AE2-223 E Adder 9.83 MW 8.36 MW
942481 AE2-261 C Adder 15.74 MW 13.38 MW
942482 AE2-261 E Adder 10.49 MW 8.92 MW
959341 AF2-225 C Adder 4.75 MW 4.04 MW
959342 AF2-225 E Adder 6.56 MW 5.57 MW
959611 AF2-252 C Adder 1.56 MW 1.32 MW
959612 AF2-252 E Adder 2.33 MW 1.98 MW
960611 AF2-352 C Adder 1.56 MW 1.32 MW
960612 AF2-352 E Adder 2.33 MW 1.98 MW
276615 W2-048 GEN Adder 4.99 MW 4.24 MW
276621 X2-022 GEN Adder 17.08 MW 14.52 MW
917502 Z2-087 E Adder 13.11 MW 11.14 MW
957381 AF2-032 C Adder 1.2 MW 1.02 MW
957382 AF2-032 E Adder 0.56 MW 0.48 MW
274890 CAYUG;1U E Adder 6.27 MW 5.33 MW
274891 CAYUG;2U E Adder 6.27 MW 5.33 MW
925772 AC1-053 E Adder 16.4 MW 13.94 MW
933441 AC2-157 C 50/50 9.51 MW 9.51 MW
933442 AC2-157 E 50/50 15.52 MW 15.52 MW
276174 W4-005 E Adder 25.05 MW 21.29 MW
924048 AB2-047 E1 Adder 8.13 MW 6.91 MW
924049 AB2-047 E2 Adder 8.26 MW 7.02 MW
924266 AB2-070 E Adder 14.99 MW 12.74 MW
942601 AE2-276 C 50/50 6.26 MW 6.26 MW
945391 AF1-204 C 50/50 33.85 MW 33.85 MW
945392 AF1-204 E 50/50 101.56 MW 101.56 MW
960141 AF2-305_AG1- Adder 0.88 MW 0.74 MW
930461 AB1-087 C 50/50 10.94 MW 10.94 MW
930462 AB1-087 E 50/50 3.13 MW 3.13 MW
930471 AB1-088 C 50/50 10.77 MW 10.77 MW
930472 AB1-088 E 50/50 3.13 MW 3.13 MW
939741 AE1-205 C Adder 6.33 MW 5.38 MW
939742 AE1-205 E Adder 8.74 MW 7.43 MW
963741 AG1-226 C 50/50 75.4 MW 75.4 MW
963742 AG1-226 E 50/50 163.54 MW 163.54 MW
963831 AG1-236 C Adder 2.21 MW 1.88 MW
963832 AG1-236 E Adder 14.76 MW 12.55 MW
963841 AG1-237 C 50/50 13.8 MW 13.8 MW
963842 AG1-237 E 50/50 92.39 MW 92.39 MW
941731 AE2-173 C Adder 3.77 MW 3.2 MW
944221 AF1-090 C Adder 3.01 MW 2.56 MW
944222 AF1-090 E Adder 14.11 MW 11.99 MW
944201 AF1-088 FTIR 50/50 125.18 MW 125.18 MW
957141 AF2-008 FTIR 50/50 62.59 MW 62.59 MW
957142 AF2-008 NFTI 50/50 62.59 MW 62.59 MW
954822 J955 External Queue 78.34 MW 78.34 MW
956282 J1115 C External Queue 3.15 MW 3.15 MW
956283 J1115 E External Queue 17.03 MW 17.03 MW
956452 J1139 External Queue 34.85 MW 34.85 MW
990272 J1263 G External Queue 34.36 MW 34.36 MW
990672 J1360 External Queue 49.1 MW 49.1 MW
990857 J1408 External Queue 7.09 MW 7.09 MW
991037 J1464 G External Queue 40.3 MW 40.3 MW
991082 J1475 G External Queue 7.5 MW 7.5 MW
991192 J1610 G External Queue 7.12 MW 7.12 MW
991197 J1626 External Queue 5.1 MW 5.1 MW
992572 J1022 External Queue 23.21 MW 23.21 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 29.07 MW 29.07 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.16 MW 4.16 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.69 MW 0.69 MW
NY PJM->LTFIMP_NY CLTF 0.38 MW 0.38 MW
WEC LTFEXP_WEC->PJM CLTF 1.01 MW 1.01 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.03 MW 0.03 MW
TVA LTFEXP_TVA->PJM CLTF 1.16 MW 1.16 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 5.85 MW 5.85 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.46 MW 2.46 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.65 MW 2.65 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.46 MW 4.46 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.15 MW 0.15 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-2


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11014___SRT-A-2
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-2'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TP   345.0 - AG1-226 TP   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 115.45 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1586.22 MVA
MW Contribution: 125.18 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11014___SRT-A-2
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-2'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 963840 TO BUS 963740 CKT 1   /*AG1-237 TP   345.0 - AG1-226 TP   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 116.96 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1606.98 MVA
MW Contribution: 126.04 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 14.0 MW 11.9 MW
965092 AG1-374 E Adder 9.34 MW 7.93 MW
965911 AG1-460 C Adder 1.05 MW 0.9 MW
965912 AG1-460 E Adder 1.58 MW 1.34 MW
290261 S-027 E Adder 12.7 MW 10.79 MW
290265 S-028 E Adder 12.62 MW 10.72 MW
936771 AD2-100 C Adder 10.99 MW 9.34 MW
936772 AD2-100 E Adder 7.32 MW 6.23 MW
936971 AD2-131 C Adder 0.72 MW 0.61 MW
936972 AD2-131 E Adder 3.64 MW 3.09 MW
942111 AE2-223 C Adder 1.47 MW 1.25 MW
942112 AE2-223 E Adder 9.83 MW 8.36 MW
942481 AE2-261 C Adder 15.74 MW 13.38 MW
942482 AE2-261 E Adder 10.49 MW 8.92 MW
959341 AF2-225 C Adder 4.75 MW 4.04 MW
959342 AF2-225 E Adder 6.56 MW 5.57 MW
959611 AF2-252 C Adder 1.56 MW 1.32 MW
959612 AF2-252 E Adder 2.33 MW 1.98 MW
960611 AF2-352 C Adder 1.56 MW 1.32 MW
960612 AF2-352 E Adder 2.33 MW 1.98 MW
276615 W2-048 GEN Adder 4.99 MW 4.24 MW
276621 X2-022 GEN Adder 17.08 MW 14.52 MW
917502 Z2-087 E Adder 13.11 MW 11.14 MW
957381 AF2-032 C Adder 1.2 MW 1.02 MW
957382 AF2-032 E Adder 0.56 MW 0.48 MW
274890 CAYUG;1U E Adder 6.27 MW 5.33 MW
274891 CAYUG;2U E Adder 6.27 MW 5.33 MW
925772 AC1-053 E Adder 16.4 MW 13.94 MW
933441 AC2-157 C 50/50 9.51 MW 9.51 MW
933442 AC2-157 E 50/50 15.52 MW 15.52 MW
276174 W4-005 E Adder 25.05 MW 21.29 MW
924048 AB2-047 E1 Adder 8.13 MW 6.91 MW
924049 AB2-047 E2 Adder 8.26 MW 7.02 MW
924266 AB2-070 E Adder 14.99 MW 12.74 MW
942601 AE2-276 C 50/50 6.26 MW 6.26 MW
945391 AF1-204 C 50/50 33.85 MW 33.85 MW
945392 AF1-204 E 50/50 101.56 MW 101.56 MW
960141 AF2-305_AG1- Adder 0.88 MW 0.74 MW
930461 AB1-087 C 50/50 10.94 MW 10.94 MW
930462 AB1-087 E 50/50 3.13 MW 3.13 MW
930471 AB1-088 C 50/50 10.77 MW 10.77 MW
930472 AB1-088 E 50/50 3.13 MW 3.13 MW
939741 AE1-205 C Adder 6.33 MW 5.38 MW
939742 AE1-205 E Adder 8.74 MW 7.43 MW
963741 AG1-226 C 50/50 75.4 MW 75.4 MW
963742 AG1-226 E 50/50 163.54 MW 163.54 MW
963831 AG1-236 C Adder 2.21 MW 1.88 MW
963832 AG1-236 E Adder 14.76 MW 12.55 MW
941731 AE2-173 C Adder 3.77 MW 3.2 MW
944221 AF1-090 C Adder 3.01 MW 2.56 MW
944222 AF1-090 E Adder 14.11 MW 11.99 MW
944201 AF1-088 FTIR 50/50 125.18 MW 125.18 MW
957141 AF2-008 FTIR 50/50 62.59 MW 62.59 MW
957142 AF2-008 NFTI 50/50 62.59 MW 62.59 MW
954822 J955 External Queue 78.34 MW 78.34 MW
956282 J1115 C External Queue 3.15 MW 3.15 MW
956283 J1115 E External Queue 17.03 MW 17.03 MW
956452 J1139 External Queue 34.85 MW 34.85 MW
990057 J1201 External Queue 1.74 MW 1.74 MW
990272 J1263 G External Queue 34.36 MW 34.36 MW
990672 J1360 External Queue 49.1 MW 49.1 MW
990857 J1408 External Queue 7.09 MW 7.09 MW
991037 J1464 G External Queue 40.3 MW 40.3 MW
991082 J1475 G External Queue 7.5 MW 7.5 MW
991192 J1610 G External Queue 7.12 MW 7.12 MW
991197 J1626 External Queue 9.95 MW 9.95 MW
991267 J1714 External Queue 6.63 MW 6.63 MW
992572 J1022 External Queue 23.21 MW 23.21 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 29.07 MW 29.07 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.16 MW 4.16 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.69 MW 0.69 MW
NY PJM->LTFIMP_NY CLTF 0.38 MW 0.38 MW
WEC LTFEXP_WEC->PJM CLTF 1.01 MW 1.01 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.03 MW 0.03 MW
TVA LTFEXP_TVA->PJM CLTF 1.16 MW 1.16 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.73 MW 0.73 MW
MEC LTFEXP_MEC->PJM CLTF 5.85 MW 5.85 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.46 MW 2.46 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.65 MW 2.65 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.46 MW 4.46 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.15 MW 0.15 MW

Details for 05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line l/o AEP_P7-1_#11042___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
Contingency Name:
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 105.61 %
Rating: 4571.0 MVA
Rating Type: B
MVA to Mitigate: 4827.21 MVA
MW Contribution: 334.5 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05ROCKPT-05JEFRSO 765.0 kV Ckt 1 line
243209 to 243208 ckt 1
Contingency Name:
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 104.08 %
Rating: 4571.0 MVA
Rating Type: B
MVA to Mitigate: 4757.51 MVA
MW Contribution: 331.22 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 16.1 MW 16.1 MW
966842 AG1-555 E 50/50 5.76 MW 5.76 MW
965911 AG1-460 C 50/50 1.3 MW 1.3 MW
965912 AG1-460 E 50/50 1.96 MW 1.96 MW
247900 05FR-11G E 50/50 15.57 MW 15.57 MW
247901 05FR-12G E 50/50 15.34 MW 15.34 MW
247902 05FR-21G E 50/50 16.3 MW 16.3 MW
247903 05FR-22G E 50/50 15.67 MW 15.67 MW
247904 05FR-3G E 50/50 30.38 MW 30.38 MW
247905 05FR-4G E 50/50 24.08 MW 24.08 MW
247906 05MDL-1G E 50/50 32.08 MW 32.08 MW
247907 05MDL-2G E 50/50 15.45 MW 15.45 MW
247912 05MDL-3G E 50/50 15.43 MW 15.43 MW
247913 05MDL-4G E 50/50 16.07 MW 16.07 MW
936771 AD2-100 C 50/50 14.01 MW 14.01 MW
936772 AD2-100 E 50/50 9.34 MW 9.34 MW
936971 AD2-131 C 50/50 0.92 MW 0.92 MW
936972 AD2-131 E 50/50 4.63 MW 4.63 MW
942481 AE2-261 C 50/50 19.49 MW 19.49 MW
942482 AE2-261 E 50/50 12.99 MW 12.99 MW
243442 05RKG1 50/50 137.41 MW 137.41 MW
243443 05RKG2 50/50 135.58 MW 135.58 MW
243859 05FR-11G C 50/50 0.77 MW 0.77 MW
243862 05FR-12G C 50/50 0.37 MW 0.37 MW
243864 05FR-21G C 50/50 0.39 MW 0.39 MW
243866 05FR-22G C 50/50 0.39 MW 0.39 MW
243870 05FR-3G C 50/50 0.37 MW 0.37 MW
243873 05FR-4G C 50/50 0.87 MW 0.87 MW
274650 KINCAID ;1U 50/50 9.79 MW 9.79 MW
274651 KINCAID ;2U 50/50 9.78 MW 9.78 MW
276615 W2-048 GEN 50/50 5.46 MW 5.46 MW
276621 X2-022 GEN 50/50 18.68 MW 18.68 MW
946581 AF1-322 C 50/50 15.3 MW 15.3 MW
946582 AF1-322 E 50/50 21.13 MW 21.13 MW
957381 AF2-032 C 50/50 1.47 MW 1.47 MW
957382 AF2-032 E 50/50 0.69 MW 0.69 MW
246909 05MDL-1G C 50/50 0.77 MW 0.77 MW
246910 05MDL-2G C 50/50 0.45 MW 0.45 MW
246976 05MDL-3G C 50/50 0.46 MW 0.46 MW
246979 05MDL-4G C 50/50 0.35 MW 0.35 MW
933441 AC2-157 C 50/50 25.42 MW 25.42 MW
933442 AC2-157 E 50/50 41.48 MW 41.48 MW
247556 05MDL-5G 50/50 0.6 MW 0.6 MW
247943 T-127 E 50/50 14.54 MW 14.54 MW
930041 AB1-006 E1 50/50 27.73 MW 27.73 MW
930042 AB1-006 E2 50/50 3.96 MW 3.96 MW
270180 AB1-006 W1 50/50 0.68 MW 0.68 MW
270181 AB1-006 W2 50/50 0.1 MW 0.1 MW
935141 AD1-148 C 50/50 0.59 MW 0.59 MW
942601 AE2-276 C 50/50 16.73 MW 16.73 MW
945391 AF1-204 C 50/50 10.6 MW 10.6 MW
945392 AF1-204 E 50/50 31.79 MW 31.79 MW
960261 AF2-317 C 50/50 0.25 MW 0.25 MW
930461 AB1-087 C 50/50 29.24 MW 29.24 MW
930462 AB1-087 E 50/50 8.36 MW 8.36 MW
930471 AB1-088 C 50/50 28.79 MW 28.79 MW
930472 AB1-088 E 50/50 8.36 MW 8.36 MW
963741 AG1-226 C 50/50 25.02 MW 25.02 MW
963742 AG1-226 E 50/50 54.26 MW 54.26 MW
963841 AG1-237 C 50/50 4.65 MW 4.65 MW
963842 AG1-237 E 50/50 31.15 MW 31.15 MW
944221 AF1-090 C 50/50 4.17 MW 4.17 MW
944222 AF1-090 E 50/50 19.53 MW 19.53 MW
944201 AF1-088 FTIR 50/50 334.5 MW 334.5 MW
957141 AF2-008 FTIR 50/50 167.25 MW 167.25 MW
957142 AF2-008 NFTI 50/50 167.25 MW 167.25 MW
990272 J1263 G External Queue 55.53 MW 55.53 MW
991082 J1475 G External Queue 16.21 MW 16.21 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 55.63 MW 55.63 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 47.2 MW 47.2 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.19 MW 2.19 MW
NY PJM->LTFIMP_NY CLTF 1.15 MW 1.15 MW
WEC LTFEXP_WEC->PJM CLTF 1.45 MW 1.45 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.33 MW 0.33 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 5.09 MW 5.09 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 1.16 MW 1.16 MW
MEC LTFEXP_MEC->PJM CLTF 9.9 MW 9.9 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.39 MW 2.39 MW
LAGN LTFEXP_LAGN->PJM CLTF 7.72 MW 7.72 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.83 MW 0.83 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 14.02 MW 14.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.6 MW 0.6 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P1-2_#709_546_SRT-A
CONTINGENCY 'AEP_P1-2_#709_546_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Single AC 116.44 % 2255.0 B 2625.64 168.72
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 144.19 % 2255.0 B 3251.55 232.9
AEP/OVEC 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2 FROM BUS 247249                     /*05HRKG2B      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Breaker AC 128.54 % 2255.0 B 2898.49 168.41
AEP 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Breaker AC 107.32 % 3039.0 B 3261.43 232.9

Details for 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P1-2_#709_546_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/OVEC
Facility Description:
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
Contingency Name:
AEP_P1-2_#709_546_SRT-A
CONTINGENCY 'AEP_P1-2_#709_546_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 116.44 %
Rating: 2255.0 MVA
Rating Type: B
MVA to Mitigate: 2625.64 MVA
MW Contribution: 168.72 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243353 05OLIVE 80/20 0.08 MW 0.08 MW
962781 AG1-127 C Adder 5.41 MW 4.59 MW
966841 AG1-555 C 80/20 11.45 MW 11.45 MW
965091 AG1-374 C Adder 17.23 MW 14.65 MW
965681 AG1-436 C 80/20 7.82 MW 7.82 MW
966091 AG1-478 C Adder 1.56 MW 1.33 MW
966431 AG1-512 C Adder 1.6 MW 1.36 MW
966441 AG1-513 C Adder 0.39 MW 0.33 MW
942111 AE2-223 C Adder 1.88 MW 1.6 MW
958481 AF2-142 C Adder 8.68 MW 7.38 MW
958491 AF2-143 C Adder 8.6 MW 7.31 MW
959341 AF2-225 C Adder 6.08 MW 5.16 MW
959351 AF2-226 C Adder 1.93 MW 1.64 MW
959611 AF2-252 C Adder 1.91 MW 1.63 MW
960281 AF2-319 C Adder 1.93 MW 1.64 MW
960611 AF2-352 C Adder 1.91 MW 1.63 MW
960681 AF2-359 C 80/20 7.82 MW 7.82 MW
960751 AF2-366 C Adder 5.39 MW 4.58 MW
243441 05CKG2 80/20 20.68 MW 20.68 MW
243442 05RKG1 80/20 67.03 MW 67.03 MW
243443 05RKG2 80/20 66.14 MW 66.14 MW
243859 05FR-11G C 80/20 0.54 MW 0.54 MW
243862 05FR-12G C 80/20 0.26 MW 0.26 MW
243864 05FR-21G C 80/20 0.27 MW 0.27 MW
243866 05FR-22G C 80/20 0.27 MW 0.27 MW
243870 05FR-3G C 80/20 0.26 MW 0.26 MW
243873 05FR-4G C 80/20 0.61 MW 0.61 MW
244415 05OLIV SLR C 80/20 0.04 MW 0.04 MW
274675 JOLIET 29;7U Adder 53.94 MW 45.85 MW
274676 JOLIET 29;8U Adder 53.94 MW 45.85 MW
274682 WAUKEGAN ;7U Adder 31.34 MW 26.64 MW
274683 WAUKEGAN ;8U Adder 33.81 MW 28.74 MW
274687 WILL CNTY;4U Adder 50.12 MW 42.6 MW
274752 CRETE EC ;2U 80/20 1.24 MW 1.24 MW
274753 CRETE EC ;3U 80/20 1.24 MW 1.24 MW
274754 CRETE EC ;4U 80/20 1.24 MW 1.24 MW
274771 LINCOLN ;2U 80/20 1.26 MW 1.26 MW
274772 LINCOLN ;3U 80/20 1.26 MW 1.26 MW
274773 LINCOLN ;4U 80/20 1.26 MW 1.26 MW
274774 LINCOLN ;5U 80/20 1.26 MW 1.26 MW
274775 LINCOLN ;6U 80/20 1.26 MW 1.26 MW
274776 LINCOLN ;7U 80/20 1.26 MW 1.26 MW
274777 LINCOLN ;8U 80/20 1.26 MW 1.26 MW
274788 SE CHICAG;5U Adder 3.71 MW 3.15 MW
274789 SE CHICAG;6U Adder 3.71 MW 3.15 MW
274790 SE CHICAG;7U Adder 3.71 MW 3.15 MW
274791 SE CHICAG;8U Adder 3.71 MW 3.15 MW
274792 SE CHICAG;9U 80/20 3.71 MW 3.71 MW
274793 SE CHICAG;0U 80/20 3.71 MW 3.71 MW
274794 SE CHICAG;1U 80/20 3.71 MW 3.71 MW
274795 SE CHICAG;2U 80/20 3.71 MW 3.71 MW
933411 AC2-154 C Adder 1.89 MW 1.6 MW
946581 AF1-322 C 80/20 11.11 MW 11.11 MW
957331 AF2-027 C Adder 1.9 MW 1.61 MW
274674 JOLIET 9 ;6U Adder 27.57 MW 23.44 MW
246909 05MDL-1G C 80/20 0.56 MW 0.56 MW
246910 05MDL-2G C 80/20 0.33 MW 0.33 MW
246976 05MDL-3G C 80/20 0.33 MW 0.33 MW
246979 05MDL-4G C 80/20 0.25 MW 0.25 MW
933441 AC2-157 C 80/20 12.82 MW 12.82 MW
938851 AE1-113 C Adder 6.29 MW 5.34 MW
934101 AD2-000 1 Adder 4.53 MW 3.85 MW
934111 AD2-000 2 Adder 4.53 MW 3.85 MW
270100 AB1-080 CT1 80/20 3.96 MW 3.96 MW
270101 AB1-080 CT2 80/20 3.96 MW 3.96 MW
270102 AB1-080 ST 80/20 4.28 MW 4.28 MW
247556 05MDL-5G 80/20 0.43 MW 0.43 MW
270180 AB1-006 W1 80/20 0.49 MW 0.49 MW
270181 AB1-006 W2 80/20 0.07 MW 0.07 MW
936371 AD2-047 C Adder 3.37 MW 2.87 MW
936461 AD2-060 C Adder 1.98 MW 1.69 MW
936511 AD2-066 C Adder 6.68 MW 5.68 MW
942421 AE2-255 C Adder 2.38 MW 2.02 MW
942521 AE2-267 C Adder -3.0 MW -2.55 MW
942601 AE2-276 C 80/20 8.44 MW 8.44 MW
942651 AE2-281 C Adder 0.67 MW 0.57 MW
943121 AE2-341 C Adder 9.74 MW 8.28 MW
943591 AF1-030 C Adder 6.48 MW 5.5 MW
945391 AF1-204 C 80/20 6.56 MW 6.56 MW
945421 AF1-207 C 80/20 4.53 MW 4.53 MW
945501 AF1-215 C 80/20 3.31 MW 3.31 MW
959141 AF2-205 C 80/20 15.2 MW 15.2 MW
960591 AF2-350 C Adder 5.95 MW 5.06 MW
961501 AF2-441 C Adder 8.0 MW 6.8 MW
930461 AB1-087 C 80/20 14.7 MW 14.7 MW
930471 AB1-088 C 80/20 14.47 MW 14.47 MW
939321 AE1-163 C Adder 4.68 MW 3.98 MW
939351 AE1-166 C Adder 7.74 MW 6.58 MW
939391 AE1-170 C Adder 5.94 MW 5.05 MW
939401 AE1-172 C Adder 4.41 MW 3.75 MW
939741 AE1-205 C Adder 8.1 MW 6.89 MW
940581 AE2-045 C 80/20 10.82 MW 10.82 MW
962691 AG1-118 C Adder 17.08 MW 14.52 MW
963741 AG1-226 C 80/20 16.97 MW 16.97 MW
963841 AG1-237 C 80/20 3.23 MW 3.23 MW
964401 AG1-302 C 80/20 22.18 MW 22.18 MW
941551 AE2-152 C Adder 8.94 MW 7.59 MW
941731 AE2-173 C Adder 4.82 MW 4.1 MW
957371 AF2-031 C Adder 0.8 MW 0.68 MW
957841 AF2-078 C 80/20 16.0 MW 16.0 MW
958011 AF2-095 C Adder 8.57 MW 7.29 MW
958381 AF2-132 C 80/20 22.18 MW 22.18 MW
958391 AF2-133 C 80/20 22.59 MW 22.59 MW
958401 AF2-134 C 80/20 1.1 MW 1.1 MW
964861 AG1-349 C 80/20 19.34 MW 19.34 MW
965791 AG1-447 C 80/20 5.73 MW 5.73 MW
274751 CRETE EC ;1U 80/20 1.24 MW 1.24 MW
274770 LINCOLN ;1U 80/20 1.26 MW 1.26 MW
957141 AF2-008 FTIR 80/20 84.36 MW 84.36 MW
944201 AF1-088 FTIR 80/20 168.72 MW 168.72 MW
990742 J1381 External Queue 20.02 MW 20.02 MW
991112 J1481 External Queue 20.02 MW 20.02 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 114.41 MW 114.41 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 18.27 MW 18.27 MW
NY PJM->LTFIMP_NY CLTF 1.03 MW 1.03 MW
WEC LTFEXP_WEC->PJM CLTF 3.02 MW 3.02 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 1.29 MW 1.29 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.79 MW 0.79 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 10.29 MW 10.29 MW
MEC LTFEXP_MEC->PJM CLTF 11.45 MW 11.45 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 29.46 MW 29.46 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.75 MW 1.75 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.71 MW 1.71 MW

Details for 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/OVEC
Facility Description:
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
Contingency Name:
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 144.19 %
Rating: 2255.0 MVA
Rating Type: B
MVA to Mitigate: 3251.55 MVA
MW Contribution: 232.9 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C Adder 6.62 MW 5.63 MW
966842 AG1-555 E Adder 2.37 MW 2.01 MW
965091 AG1-374 C Adder 12.12 MW 10.31 MW
965092 AG1-374 E Adder 8.08 MW 6.87 MW
965911 AG1-460 C Adder 0.96 MW 0.81 MW
965912 AG1-460 E Adder 1.44 MW 1.22 MW
247900 05FR-11G E Adder 6.41 MW 5.45 MW
247901 05FR-12G E Adder 6.31 MW 5.36 MW
247902 05FR-21G E Adder 6.71 MW 5.7 MW
247903 05FR-22G E Adder 6.45 MW 5.48 MW
247904 05FR-3G E Adder 12.5 MW 10.63 MW
247905 05FR-4G E Adder 9.91 MW 8.42 MW
247906 05MDL-1G E Adder 11.13 MW 9.46 MW
247907 05MDL-2G E Adder 5.36 MW 4.55 MW
247912 05MDL-3G E Adder 5.35 MW 4.55 MW
247913 05MDL-4G E Adder 5.57 MW 4.74 MW
290261 S-027 E Adder 10.99 MW 9.34 MW
290265 S-028 E Adder 10.93 MW 9.29 MW
936771 AD2-100 C Adder 10.23 MW 8.69 MW
936772 AD2-100 E Adder 6.82 MW 5.79 MW
936971 AD2-131 C Adder 0.67 MW 0.57 MW
936972 AD2-131 E Adder 3.38 MW 2.88 MW
942111 AE2-223 C Adder 1.27 MW 1.08 MW
942112 AE2-223 E Adder 8.49 MW 7.22 MW
942481 AE2-261 C Adder 14.34 MW 12.19 MW
942482 AE2-261 E Adder 9.56 MW 8.13 MW
959341 AF2-225 C Adder 4.1 MW 3.48 MW
959342 AF2-225 E Adder 5.66 MW 4.81 MW
959611 AF2-252 C Adder 1.35 MW 1.15 MW
959612 AF2-252 E Adder 2.02 MW 1.72 MW
960611 AF2-352 C Adder 1.35 MW 1.15 MW
960612 AF2-352 E Adder 2.02 MW 1.72 MW
243442 05RKG1 50/50 101.86 MW 101.86 MW
243443 05RKG2 50/50 100.5 MW 100.5 MW
276615 W2-048 GEN Adder 4.14 MW 3.52 MW
276621 X2-022 GEN Adder 14.15 MW 12.03 MW
917502 Z2-087 E Adder 11.32 MW 9.62 MW
946581 AF1-322 C Adder 5.31 MW 4.51 MW
946582 AF1-322 E Adder 7.33 MW 6.23 MW
957381 AF2-032 C Adder 1.08 MW 0.92 MW
957382 AF2-032 E Adder 0.51 MW 0.43 MW
925772 AC1-053 E Adder 13.14 MW 11.17 MW
933441 AC2-157 C 50/50 17.7 MW 17.7 MW
933442 AC2-157 E 50/50 28.88 MW 28.88 MW
276174 W4-005 E Adder 19.61 MW 16.66 MW
924048 AB2-047 E1 Adder 7.02 MW 5.97 MW
924049 AB2-047 E2 Adder 7.13 MW 6.06 MW
247943 T-127 E Adder 5.04 MW 4.29 MW
930041 AB1-006 E1 Adder 9.62 MW 8.18 MW
930042 AB1-006 E2 Adder 1.37 MW 1.17 MW
252511 Y1-054 E Adder -1.33 MW -1.13 MW
924266 AB2-070 E Adder 11.82 MW 10.04 MW
942521 AE2-267 C Adder -1.71 MW -1.46 MW
942601 AE2-276 C 50/50 11.64 MW 11.64 MW
945391 AF1-204 C Adder 6.32 MW 5.37 MW
945392 AF1-204 E Adder 18.96 MW 16.11 MW
960141 AF2-305_AG1- Adder 0.69 MW 0.59 MW
930461 AB1-087 C 50/50 20.29 MW 20.29 MW
930462 AB1-087 E 50/50 5.82 MW 5.82 MW
930471 AB1-088 C 50/50 19.97 MW 19.97 MW
930472 AB1-088 E 50/50 5.82 MW 5.82 MW
939741 AE1-205 C Adder 5.47 MW 4.65 MW
939742 AE1-205 E Adder 7.55 MW 6.42 MW
963741 AG1-226 C Adder 11.93 MW 10.14 MW
963742 AG1-226 E Adder 25.88 MW 22.0 MW
963831 AG1-236 C Adder 1.77 MW 1.5 MW
963832 AG1-236 E Adder 11.83 MW 10.05 MW
963841 AG1-237 C Adder 2.07 MW 1.76 MW
963842 AG1-237 E Adder 13.87 MW 11.79 MW
941731 AE2-173 C Adder 3.25 MW 2.77 MW
944221 AF1-090 C Adder 2.98 MW 2.54 MW
944222 AF1-090 E Adder 13.97 MW 11.87 MW
957141 AF2-008 FTIR 50/50 116.45 MW 116.45 MW
944201 AF1-088 FTIR 50/50 232.9 MW 232.9 MW
957142 AF2-008 NFTI 50/50 116.45 MW 116.45 MW
990272 J1263 G External Queue 34.01 MW 34.01 MW
991082 J1475 G External Queue 10.67 MW 10.67 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 60.39 MW 60.39 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 26.14 MW 26.14 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.69 MW 1.69 MW
NY PJM->LTFIMP_NY CLTF 0.88 MW 0.88 MW
WEC LTFEXP_WEC->PJM CLTF 1.63 MW 1.63 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.59 MW 0.59 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.33 MW 0.33 MW
TVA LTFEXP_TVA->PJM CLTF 1.7 MW 1.7 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 5.34 MW 5.34 MW
MEC LTFEXP_MEC->PJM CLTF 8.18 MW 8.18 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 14.93 MW 14.93 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.8 MW 3.8 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.25 MW 0.25 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 10.86 MW 10.86 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.84 MW 0.84 MW

Details for 05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line l/o AEP_P4_#6189_05HANG R 765_D1_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/OVEC
Facility Description:
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line
242865 to 248000 ckt Z1
Contingency Name:
AEP_P4_#6189_05HANG R 765_D1_SRT-A
CONTINGENCY 'AEP_P4_#6189_05HANG R 765_D1_SRT-A'
 OPEN BRANCH FROM BUS 242921 TO BUS 242924 CKT 1   /*05CORNU      765.0 - 05HANG R     765.0
 OPEN BRANCH FROM BUS 242921 TO BUS 242934 CKT 1   /*05CORNU      765.0 - 05CORNU      345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 REMOVE UNIT 1A FROM BUS 247245                    /*05HRKG1A      18.0
 REMOVE UNIT 1B FROM BUS 247246                    /*05HRKG1B      18.0
 REMOVE UNIT 1S FROM BUS 247247                    /*05HRKG1S      18.0
 REMOVE UNIT 2 FROM BUS 247249                     /*05HRKG2B      18.0
 REMOVE UNIT 2A FROM BUS 247248                    /*05HRKG2A      18.0
 REMOVE UNIT 2S FROM BUS 247250                    /*05HRKG2S      18.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 128.54 %
Rating: 2255.0 MVA
Rating Type: B
MVA to Mitigate: 2898.49 MVA
MW Contribution: 168.41 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 11.42 MW 11.42 MW
966842 AG1-555 E 50/50 4.08 MW 4.08 MW
965681 AG1-436 C 50/50 7.8 MW 7.8 MW
965682 AG1-436 E 50/50 5.2 MW 5.2 MW
966431 AG1-512 C Adder 1.59 MW 1.35 MW
966432 AG1-512 E Adder 2.39 MW 2.03 MW
247900 05FR-11G E 50/50 11.04 MW 11.04 MW
247901 05FR-12G E 50/50 10.88 MW 10.88 MW
247902 05FR-21G E 50/50 11.56 MW 11.56 MW
247903 05FR-22G E 50/50 11.11 MW 11.11 MW
247904 05FR-3G E 50/50 21.54 MW 21.54 MW
247905 05FR-4G E 50/50 17.07 MW 17.07 MW
247906 05MDL-1G E 50/50 23.24 MW 23.24 MW
247907 05MDL-2G E 50/50 11.19 MW 11.19 MW
247912 05MDL-3G E 50/50 11.18 MW 11.18 MW
247913 05MDL-4G E 50/50 11.64 MW 11.64 MW
247967 05OLIV SLR E Adder 0.25 MW 0.21 MW
910542 X3-005 E Adder 0.56 MW 0.47 MW
934722 AD1-100 E Adder 64.94 MW 55.2 MW
960681 AF2-359 C 50/50 7.8 MW 7.8 MW
960682 AF2-359 E 50/50 5.2 MW 5.2 MW
243441 05CKG2 50/50 20.62 MW 20.62 MW
243442 05RKG1 50/50 66.97 MW 66.97 MW
243443 05RKG2 50/50 66.07 MW 66.07 MW
243859 05FR-11G C 50/50 0.54 MW 0.54 MW
243862 05FR-12G C 50/50 0.26 MW 0.26 MW
243864 05FR-21G C 50/50 0.27 MW 0.27 MW
243866 05FR-22G C 50/50 0.27 MW 0.27 MW
243870 05FR-3G C 50/50 0.26 MW 0.26 MW
243873 05FR-4G C 50/50 0.61 MW 0.61 MW
274753 CRETE EC ;3U 50/50 1.23 MW 1.23 MW
274754 CRETE EC ;4U 50/50 1.23 MW 1.23 MW
274788 SE CHICAG;5U Adder 3.7 MW 3.14 MW
274789 SE CHICAG;6U Adder 3.7 MW 3.14 MW
274790 SE CHICAG;7U Adder 3.7 MW 3.14 MW
274791 SE CHICAG;8U Adder 3.7 MW 3.14 MW
274792 SE CHICAG;9U Adder 3.7 MW 3.15 MW
274793 SE CHICAG;0U Adder 3.7 MW 3.15 MW
274794 SE CHICAG;1U Adder 3.7 MW 3.15 MW
274795 SE CHICAG;2U Adder 3.7 MW 3.15 MW
946581 AF1-322 C 50/50 11.09 MW 11.09 MW
946582 AF1-322 E 50/50 15.31 MW 15.31 MW
246909 05MDL-1G C 50/50 0.56 MW 0.56 MW
246910 05MDL-2G C 50/50 0.33 MW 0.33 MW
246976 05MDL-3G C 50/50 0.33 MW 0.33 MW
246979 05MDL-4G C 50/50 0.25 MW 0.25 MW
933441 AC2-157 C 50/50 12.8 MW 12.8 MW
933442 AC2-157 E 50/50 20.88 MW 20.88 MW
270100 AB1-080 CT1 50/50 3.94 MW 3.94 MW
270101 AB1-080 CT2 50/50 3.94 MW 3.94 MW
270102 AB1-080 ST 50/50 4.27 MW 4.27 MW
247556 05MDL-5G 50/50 0.43 MW 0.43 MW
247943 T-127 E 50/50 10.53 MW 10.53 MW
930041 AB1-006 E1 50/50 20.09 MW 20.09 MW
930042 AB1-006 E2 50/50 2.87 MW 2.87 MW
252511 Y1-054 E Adder -2.36 MW -2.0 MW
270180 AB1-006 W1 50/50 0.49 MW 0.49 MW
270181 AB1-006 W2 50/50 0.07 MW 0.07 MW
942521 AE2-267 C Adder -3.01 MW -2.56 MW
942601 AE2-276 C 50/50 8.42 MW 8.42 MW
944932 AF1-158 E Adder 5.95 MW 5.06 MW
945391 AF1-204 C 50/50 6.54 MW 6.54 MW
945392 AF1-204 E 50/50 19.62 MW 19.62 MW
945421 AF1-207 C 50/50 4.52 MW 4.52 MW
945422 AF1-207 E 50/50 19.42 MW 19.42 MW
945501 AF1-215 C 50/50 3.31 MW 3.31 MW
945502 AF1-215 E 50/50 14.32 MW 14.32 MW
959141 AF2-205 C 50/50 15.17 MW 15.17 MW
959142 AF2-205 E 50/50 10.11 MW 10.11 MW
961501 AF2-441 C Adder 7.97 MW 6.78 MW
961502 AF2-441 E Adder 11.96 MW 10.16 MW
930461 AB1-087 C 50/50 14.67 MW 14.67 MW
930462 AB1-087 E 50/50 4.21 MW 4.21 MW
930471 AB1-088 C 50/50 14.44 MW 14.44 MW
930472 AB1-088 E 50/50 4.21 MW 4.21 MW
940581 AE2-045 C 50/50 10.79 MW 10.79 MW
940582 AE2-045 E 50/50 14.82 MW 14.82 MW
963741 AG1-226 C 50/50 16.93 MW 16.93 MW
963742 AG1-226 E 50/50 36.71 MW 36.71 MW
963841 AG1-237 C 50/50 3.22 MW 3.22 MW
963842 AG1-237 E 50/50 21.56 MW 21.56 MW
964401 AG1-302 C 50/50 22.13 MW 22.13 MW
964402 AG1-302 E 50/50 14.75 MW 14.75 MW
957371 AF2-031 C Adder 0.8 MW 0.68 MW
957372 AF2-031 E Adder 1.2 MW 1.02 MW
957841 AF2-078 C 50/50 15.96 MW 15.96 MW
957842 AF2-078 E 50/50 10.64 MW 10.64 MW
958381 AF2-132 C 50/50 22.13 MW 22.13 MW
958382 AF2-132 E 50/50 14.75 MW 14.75 MW
958391 AF2-133 C 50/50 22.54 MW 22.54 MW
958392 AF2-133 E 50/50 15.02 MW 15.02 MW
958401 AF2-134 C 50/50 1.1 MW 1.1 MW
958402 AF2-134 E 50/50 4.77 MW 4.77 MW
964861 AG1-349 C 50/50 19.29 MW 19.29 MW
964862 AG1-349 E 50/50 12.86 MW 12.86 MW
965791 AG1-447 C 50/50 5.72 MW 5.72 MW
274751 CRETE EC ;1U 50/50 1.23 MW 1.23 MW
957141 AF2-008 FTIR 50/50 84.21 MW 84.21 MW
944201 AF1-088 FTIR 50/50 168.41 MW 168.41 MW
957142 AF2-008 NFTI 50/50 84.21 MW 84.21 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 113.88 MW 113.88 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 18.07 MW 18.07 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.08 MW 2.08 MW
NY PJM->LTFIMP_NY CLTF 1.05 MW 1.05 MW
WEC LTFEXP_WEC->PJM CLTF 3.01 MW 3.01 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 1.31 MW 1.31 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.8 MW 0.8 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 10.3 MW 10.3 MW
MEC LTFEXP_MEC->PJM CLTF 11.4 MW 11.4 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 29.51 MW 29.51 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.69 MW 1.69 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 13.3 MW 13.3 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.73 MW 1.73 MW

Details for 05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP
Facility Description:
05JEFRSO-05JEFRSO 765.0/345.0 kV Ckt 2 transformer
243208 to 242865 ckt 2
Contingency Name:
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1   /*05HANG R     765.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 243208 CKT 1   /*05GRNTWN     765.0 - 05JEFRSO     765.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 107.32 %
Rating: 3039.0 MVA
Rating Type: B
MVA to Mitigate: 3261.43 MVA
MW Contribution: 232.9 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C Adder 6.62 MW 5.63 MW
966842 AG1-555 E Adder 2.37 MW 2.01 MW
965091 AG1-374 C Adder 12.12 MW 10.31 MW
965092 AG1-374 E Adder 8.08 MW 6.87 MW
965911 AG1-460 C Adder 0.96 MW 0.81 MW
965912 AG1-460 E Adder 1.44 MW 1.22 MW
247900 05FR-11G E Adder 6.41 MW 5.45 MW
247901 05FR-12G E Adder 6.31 MW 5.36 MW
247902 05FR-21G E Adder 6.71 MW 5.7 MW
247903 05FR-22G E Adder 6.45 MW 5.48 MW
247904 05FR-3G E Adder 12.5 MW 10.63 MW
247905 05FR-4G E Adder 9.91 MW 8.42 MW
247906 05MDL-1G E Adder 11.13 MW 9.46 MW
247907 05MDL-2G E Adder 5.36 MW 4.55 MW
247912 05MDL-3G E Adder 5.35 MW 4.55 MW
247913 05MDL-4G E Adder 5.57 MW 4.74 MW
290261 S-027 E Adder 10.99 MW 9.34 MW
290265 S-028 E Adder 10.93 MW 9.29 MW
936771 AD2-100 C Adder 10.23 MW 8.69 MW
936772 AD2-100 E Adder 6.82 MW 5.79 MW
936971 AD2-131 C Adder 0.67 MW 0.57 MW
936972 AD2-131 E Adder 3.38 MW 2.88 MW
942111 AE2-223 C Adder 1.27 MW 1.08 MW
942112 AE2-223 E Adder 8.49 MW 7.22 MW
942481 AE2-261 C Adder 14.34 MW 12.19 MW
942482 AE2-261 E Adder 9.56 MW 8.13 MW
959341 AF2-225 C Adder 4.1 MW 3.48 MW
959342 AF2-225 E Adder 5.66 MW 4.81 MW
959611 AF2-252 C Adder 1.35 MW 1.15 MW
959612 AF2-252 E Adder 2.02 MW 1.72 MW
960611 AF2-352 C Adder 1.35 MW 1.15 MW
960612 AF2-352 E Adder 2.02 MW 1.72 MW
243442 05RKG1 50/50 101.86 MW 101.86 MW
243443 05RKG2 50/50 100.5 MW 100.5 MW
276615 W2-048 GEN Adder 4.14 MW 3.52 MW
276621 X2-022 GEN Adder 14.15 MW 12.03 MW
917502 Z2-087 E Adder 11.32 MW 9.62 MW
946581 AF1-322 C Adder 5.31 MW 4.51 MW
946582 AF1-322 E Adder 7.33 MW 6.23 MW
957381 AF2-032 C Adder 1.08 MW 0.92 MW
957382 AF2-032 E Adder 0.51 MW 0.43 MW
925772 AC1-053 E Adder 13.14 MW 11.17 MW
933441 AC2-157 C 50/50 17.7 MW 17.7 MW
933442 AC2-157 E 50/50 28.88 MW 28.88 MW
276174 W4-005 E Adder 19.61 MW 16.66 MW
924048 AB2-047 E1 Adder 7.02 MW 5.97 MW
924049 AB2-047 E2 Adder 7.13 MW 6.06 MW
247943 T-127 E Adder 5.04 MW 4.29 MW
930041 AB1-006 E1 Adder 9.62 MW 8.18 MW
930042 AB1-006 E2 Adder 1.37 MW 1.17 MW
252511 Y1-054 E Adder -1.33 MW -1.13 MW
924266 AB2-070 E Adder 11.82 MW 10.04 MW
942521 AE2-267 C Adder -1.71 MW -1.46 MW
942601 AE2-276 C 50/50 11.64 MW 11.64 MW
945391 AF1-204 C Adder 6.32 MW 5.37 MW
945392 AF1-204 E Adder 18.96 MW 16.11 MW
960141 AF2-305_AG1- Adder 0.69 MW 0.59 MW
930461 AB1-087 C 50/50 20.29 MW 20.29 MW
930462 AB1-087 E 50/50 5.82 MW 5.82 MW
930471 AB1-088 C 50/50 19.97 MW 19.97 MW
930472 AB1-088 E 50/50 5.82 MW 5.82 MW
939741 AE1-205 C Adder 5.47 MW 4.65 MW
939742 AE1-205 E Adder 7.55 MW 6.42 MW
963741 AG1-226 C Adder 11.93 MW 10.14 MW
963742 AG1-226 E Adder 25.88 MW 22.0 MW
963831 AG1-236 C Adder 1.77 MW 1.5 MW
963832 AG1-236 E Adder 11.83 MW 10.05 MW
963841 AG1-237 C Adder 2.07 MW 1.76 MW
963842 AG1-237 E Adder 13.87 MW 11.79 MW
941731 AE2-173 C Adder 3.25 MW 2.77 MW
944221 AF1-090 C Adder 2.98 MW 2.54 MW
944222 AF1-090 E Adder 13.97 MW 11.87 MW
957141 AF2-008 FTIR 50/50 116.45 MW 116.45 MW
944201 AF1-088 FTIR 50/50 232.9 MW 232.9 MW
957142 AF2-008 NFTI 50/50 116.45 MW 116.45 MW
990272 J1263 G External Queue 34.01 MW 34.01 MW
991082 J1475 G External Queue 10.67 MW 10.67 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 60.39 MW 60.39 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 26.14 MW 26.14 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.69 MW 1.69 MW
NY PJM->LTFIMP_NY CLTF 0.88 MW 0.88 MW
WEC LTFEXP_WEC->PJM CLTF 1.63 MW 1.63 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.59 MW 0.59 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.33 MW 0.33 MW
TVA LTFEXP_TVA->PJM CLTF 1.7 MW 1.7 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 5.34 MW 5.34 MW
MEC LTFEXP_MEC->PJM CLTF 8.18 MW 8.18 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 14.93 MW 14.93 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.8 MW 3.8 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.25 MW 0.25 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 10.86 MW 10.86 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.84 MW 0.84 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 146.83 % 1868.0 B 2742.77 144.26
AEP/NIPS 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
OP AC 146.83 % 1868.0 B 2742.77 144.26
AEP/AMIL J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Base Case OP AC 110.12 % 1334.0 A 1468.99 250.78
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Base Case OP AC 103.54 % 1409.0 A 1458.95 57.12
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 102.25 % 1958.0 B 2002.1 137.22
AEP 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
OP AC 101.41 % 1958.0 B 1985.55 136.07
AEP AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345/69XFR_SRT-S
CONTINGENCY 'EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345
 CLOSE BRANCH FROM BUS 250595 TO BUS 250896 CKT 1   /*08INLNDC      69.0 - 08WROWJ       69.0
 OPEN BRANCH FROM BUS 249504 TO BUS 249505 CKT 1    /*08CAYSUB     345.0 - 08CAYUGA     345.0
 OPEN BRANCH FROM BUS 249504 TO BUS 250340 CKT 1    /*08CAYSUB     345.0 - 08CAYSUB      69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250341 CKT 1    /*08CAYSUB      69.0 - 08CAY69       69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250595 CKT 1    /*08CAYSUB      69.0 - 08INLNDC      69.0
END
OP AC 100.2 % 1868.0 B 1871.77 84.43

Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line l/o AEP_P1-2_#8695_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
Contingency Name:
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 146.83 %
Rating: 1868.0 MVA
Rating Type: B
MVA to Mitigate: 2742.77 MVA
MW Contribution: 144.26 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 2 line
243878 to 255205 ckt 2
Contingency Name:
AEP_P1-2_#8695_SRT-A
CONTINGENCY 'AEP_P1-2_#8695_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 147.54 %
Rating: 1868.0 MVA
Rating Type: B
MVA to Mitigate: 2756.13 MVA
MW Contribution: 144.19 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 51.19 MW 51.19 MW
966842 AG1-555 E 50/50 18.3 MW 18.3 MW
247900 05FR-11G E 50/50 49.51 MW 49.51 MW
247901 05FR-12G E 50/50 48.76 MW 48.76 MW
247902 05FR-21G E 50/50 51.83 MW 51.83 MW
247903 05FR-22G E 50/50 49.8 MW 49.8 MW
247904 05FR-3G E 50/50 96.59 MW 96.59 MW
247905 05FR-4G E 50/50 76.56 MW 76.56 MW
247906 05MDL-1G E 50/50 120.84 MW 120.84 MW
247907 05MDL-2G E 50/50 58.19 MW 58.19 MW
247912 05MDL-3G E 50/50 58.12 MW 58.12 MW
247913 05MDL-4G E 50/50 60.52 MW 60.52 MW
243859 05FR-11G C 50/50 2.43 MW 2.43 MW
243862 05FR-12G C 50/50 1.18 MW 1.18 MW
243864 05FR-21G C 50/50 1.23 MW 1.23 MW
243866 05FR-22G C 50/50 1.23 MW 1.23 MW
243870 05FR-3G C 50/50 1.18 MW 1.18 MW
243873 05FR-4G C 50/50 2.75 MW 2.75 MW
946581 AF1-322 C 50/50 57.64 MW 57.64 MW
946582 AF1-322 E 50/50 79.6 MW 79.6 MW
246909 05MDL-1G C 50/50 2.9 MW 2.9 MW
246910 05MDL-2G C 50/50 1.71 MW 1.71 MW
246976 05MDL-3G C 50/50 1.72 MW 1.72 MW
246979 05MDL-4G C 50/50 1.32 MW 1.32 MW
933441 AC2-157 C 50/50 10.96 MW 10.96 MW
933442 AC2-157 E 50/50 17.89 MW 17.89 MW
247556 05MDL-5G 50/50 2.27 MW 2.27 MW
247943 T-127 E 50/50 54.76 MW 54.76 MW
930041 AB1-006 E1 50/50 104.48 MW 104.48 MW
930042 AB1-006 E2 50/50 14.93 MW 14.93 MW
270180 AB1-006 W1 50/50 2.55 MW 2.55 MW
270181 AB1-006 W2 50/50 0.36 MW 0.36 MW
942601 AE2-276 C 50/50 7.21 MW 7.21 MW
945391 AF1-204 C 50/50 13.99 MW 13.99 MW
945392 AF1-204 E 50/50 41.98 MW 41.98 MW
930461 AB1-087 C 50/50 12.61 MW 12.61 MW
930462 AB1-087 E 50/50 3.61 MW 3.61 MW
930471 AB1-088 C 50/50 12.42 MW 12.42 MW
930472 AB1-088 E 50/50 3.61 MW 3.61 MW
963741 AG1-226 C 50/50 63.07 MW 63.07 MW
963742 AG1-226 E 50/50 136.8 MW 136.8 MW
963841 AG1-237 C 50/50 13.21 MW 13.21 MW
963842 AG1-237 E 50/50 88.41 MW 88.41 MW
958391 AF2-133 C Adder -32.33 MW -27.48 MW
944201 AF1-088 FTIR 50/50 144.26 MW 144.26 MW
957142 AF2-008 NFTI 50/50 72.13 MW 72.13 MW
957141 AF2-008 FTIR 50/50 72.13 MW 72.13 MW
956452 J1139 External Queue 17.74 MW 17.74 MW
991082 J1475 G External Queue 8.58 MW 8.58 MW
991162 J1518 External Queue 26.3 MW 26.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 36.31 MW 36.31 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 16.8 MW 16.8 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.01 MW 0.01 MW
VTF LTFEXP_VFT->PJM CMTX 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.04 MW 0.04 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.2 MW 2.2 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 5.12 MW 5.12 MW
MEC LTFEXP_MEC->PJM CLTF 2.86 MW 2.86 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.26 MW 6.26 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.76 MW 0.76 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for 05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line l/o AEP_P1-2_#8807_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
Contingency Name:
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 146.83 %
Rating: 1868.0 MVA
Rating Type: B
MVA to Mitigate: 2742.77 MVA
MW Contribution: 144.26 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/NIPS
Facility Description:
05MEADOW-17REYNOLDS 345.0 kV Ckt 1 line
243878 to 255205 ckt 1
Contingency Name:
AEP_P1-2_#8807_SRT-A
CONTINGENCY 'AEP_P1-2_#8807_SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 147.54 %
Rating: 1868.0 MVA
Rating Type: B
MVA to Mitigate: 2756.13 MVA
MW Contribution: 144.19 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 51.19 MW 51.19 MW
966842 AG1-555 E 50/50 18.3 MW 18.3 MW
247900 05FR-11G E 50/50 49.51 MW 49.51 MW
247901 05FR-12G E 50/50 48.76 MW 48.76 MW
247902 05FR-21G E 50/50 51.83 MW 51.83 MW
247903 05FR-22G E 50/50 49.8 MW 49.8 MW
247904 05FR-3G E 50/50 96.59 MW 96.59 MW
247905 05FR-4G E 50/50 76.56 MW 76.56 MW
247906 05MDL-1G E 50/50 120.84 MW 120.84 MW
247907 05MDL-2G E 50/50 58.19 MW 58.19 MW
247912 05MDL-3G E 50/50 58.12 MW 58.12 MW
247913 05MDL-4G E 50/50 60.52 MW 60.52 MW
243859 05FR-11G C 50/50 2.43 MW 2.43 MW
243862 05FR-12G C 50/50 1.18 MW 1.18 MW
243864 05FR-21G C 50/50 1.23 MW 1.23 MW
243866 05FR-22G C 50/50 1.23 MW 1.23 MW
243870 05FR-3G C 50/50 1.18 MW 1.18 MW
243873 05FR-4G C 50/50 2.75 MW 2.75 MW
946581 AF1-322 C 50/50 57.64 MW 57.64 MW
946582 AF1-322 E 50/50 79.6 MW 79.6 MW
246909 05MDL-1G C 50/50 2.9 MW 2.9 MW
246910 05MDL-2G C 50/50 1.71 MW 1.71 MW
246976 05MDL-3G C 50/50 1.72 MW 1.72 MW
246979 05MDL-4G C 50/50 1.32 MW 1.32 MW
933441 AC2-157 C 50/50 10.96 MW 10.96 MW
933442 AC2-157 E 50/50 17.89 MW 17.89 MW
247556 05MDL-5G 50/50 2.27 MW 2.27 MW
247943 T-127 E 50/50 54.76 MW 54.76 MW
930041 AB1-006 E1 50/50 104.48 MW 104.48 MW
930042 AB1-006 E2 50/50 14.93 MW 14.93 MW
270180 AB1-006 W1 50/50 2.55 MW 2.55 MW
270181 AB1-006 W2 50/50 0.36 MW 0.36 MW
942601 AE2-276 C 50/50 7.21 MW 7.21 MW
945391 AF1-204 C 50/50 13.99 MW 13.99 MW
945392 AF1-204 E 50/50 41.98 MW 41.98 MW
930461 AB1-087 C 50/50 12.61 MW 12.61 MW
930462 AB1-087 E 50/50 3.61 MW 3.61 MW
930471 AB1-088 C 50/50 12.42 MW 12.42 MW
930472 AB1-088 E 50/50 3.61 MW 3.61 MW
963741 AG1-226 C 50/50 63.07 MW 63.07 MW
963742 AG1-226 E 50/50 136.8 MW 136.8 MW
963841 AG1-237 C 50/50 13.21 MW 13.21 MW
963842 AG1-237 E 50/50 88.41 MW 88.41 MW
958391 AF2-133 C Adder -32.33 MW -27.48 MW
944201 AF1-088 FTIR 50/50 144.26 MW 144.26 MW
957142 AF2-008 NFTI 50/50 72.13 MW 72.13 MW
957141 AF2-008 FTIR 50/50 72.13 MW 72.13 MW
956452 J1139 External Queue 17.74 MW 17.74 MW
991082 J1475 G External Queue 8.58 MW 8.58 MW
991162 J1518 External Queue 26.3 MW 26.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 36.31 MW 36.31 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 16.8 MW 16.8 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.01 MW 0.01 MW
VTF LTFEXP_VFT->PJM CMTX 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.04 MW 0.04 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.2 MW 2.2 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.23 MW 1.23 MW
TVA LTFEXP_TVA->PJM CLTF 5.12 MW 5.12 MW
MEC LTFEXP_MEC->PJM CLTF 2.86 MW 2.86 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.26 MW 6.26 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.76 MW 0.76 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.59 MW 0.59 MW

Details for J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 110.12 %
Rating: 1334.0 MVA
Rating Type: A
MVA to Mitigate: 1468.99 MVA
MW Contribution: 250.78 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP/AMIL
Facility Description:
J1180 POI-05SULLIVAN 345.0 kV Ckt 1 line
956820 to 247712 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 109.59 %
Rating: 1334.0 MVA
Rating Type: A
MVA to Mitigate: 1461.96 MVA
MW Contribution: 251.91 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
272363 ESS H440 ; R Adder 1.18 MW 1.0 MW
962012 AG1-044 E Adder 0.03 MW 0.03 MW
962781 AG1-127 C Adder 2.93 MW 2.49 MW
962782 AG1-127 E Adder 1.95 MW 1.66 MW
965091 AG1-374 C Adder 16.49 MW 14.02 MW
965092 AG1-374 E Adder 10.99 MW 9.34 MW
965911 AG1-460 C 50/50 1.64 MW 1.64 MW
965912 AG1-460 E 50/50 2.46 MW 2.46 MW
290021 O50 E Adder 9.07 MW 7.71 MW
290051 GSG-6; E Adder 4.71 MW 4.01 MW
290261 S-027 E Adder 14.95 MW 12.71 MW
290265 S-028 E Adder 14.86 MW 12.63 MW
295109 WESTBROOK E Adder 2.52 MW 2.15 MW
295111 SUBLETTE E Adder 1.23 MW 1.04 MW
918052 AA1-018 E OP Adder 6.77 MW 5.75 MW
933911 AD1-013 C Adder 0.83 MW 0.7 MW
933912 AD1-013 E Adder 1.32 MW 1.12 MW
936771 AD2-100 C 50/50 17.85 MW 17.85 MW
936772 AD2-100 E 50/50 11.9 MW 11.9 MW
936971 AD2-131 C 50/50 1.18 MW 1.18 MW
936972 AD2-131 E 50/50 5.91 MW 5.91 MW
937002 AD2-134 E Adder 4.56 MW 3.88 MW
937312 AD2-172 E Adder 1.64 MW 1.39 MW
942111 AE2-223 C Adder 1.63 MW 1.39 MW
942112 AE2-223 E Adder 10.94 MW 9.3 MW
942481 AE2-261 C 50/50 24.54 MW 24.54 MW
942482 AE2-261 E 50/50 16.36 MW 16.36 MW
942991 AE2-321 C Adder 3.49 MW 2.96 MW
942992 AE2-321 E Adder 1.72 MW 1.46 MW
958481 AF2-142 C Adder 4.67 MW 3.97 MW
958482 AF2-142 E Adder 3.11 MW 2.64 MW
958491 AF2-143 C Adder 4.99 MW 4.24 MW
958492 AF2-143 E Adder 3.33 MW 2.83 MW
958912 AF2-182 E Adder 17.77 MW 15.11 MW
959081 AF2-199 C Adder 3.29 MW 2.8 MW
959082 AF2-199 E Adder 1.65 MW 1.4 MW
959341 AF2-225 C Adder 5.28 MW 4.49 MW
959342 AF2-225 E Adder 7.29 MW 6.2 MW
959351 AF2-226 C Adder 1.03 MW 0.87 MW
959352 AF2-226 E Adder 1.54 MW 1.31 MW
959611 AF2-252 C Adder 1.83 MW 1.56 MW
959612 AF2-252 E Adder 2.75 MW 2.34 MW
960281 AF2-319 C Adder 1.03 MW 0.87 MW
960282 AF2-319 E Adder 1.54 MW 1.31 MW
960582 AF2-349 E Adder 15.88 MW 13.5 MW
960611 AF2-352 C Adder 1.83 MW 1.56 MW
960612 AF2-352 E Adder 2.75 MW 2.34 MW
960751 AF2-366 C Adder 2.92 MW 2.48 MW
960752 AF2-366 E Adder 1.95 MW 1.66 MW
274650 KINCAID ;1U 50/50 12.27 MW 12.27 MW
274651 KINCAID ;2U 50/50 12.26 MW 12.26 MW
274859 EASYR;U1 E Adder 6.14 MW 5.22 MW
274860 EASYR;U2 E Adder 6.14 MW 5.22 MW
274880 RADFORD R;1U 50/50 0.84 MW 0.84 MW
276615 W2-048 GEN 50/50 6.51 MW 6.51 MW
276621 X2-022 GEN 50/50 22.27 MW 22.27 MW
293644 O22 E1 Adder 5.89 MW 5.01 MW
293645 O22 E2 Adder 6.75 MW 5.74 MW
293715 O-029 E Adder 5.53 MW 4.7 MW
293716 O-029 E Adder 3.03 MW 2.58 MW
293717 O-029 E Adder 2.79 MW 2.37 MW
293771 O-035 E Adder 4.39 MW 3.73 MW
294401 BSHIL;1U E Adder 5.56 MW 4.72 MW
294410 BSHIL;2U E Adder 5.56 MW 4.72 MW
294763 P-046 E Adder 4.54 MW 3.86 MW
917502 Z2-087 E Adder 14.58 MW 12.39 MW
925582 AC1-033 E Adder 6.09 MW 5.18 MW
939061 AE1-134 2 Adder 0.74 MW 0.63 MW
940502 AE2-035 E Adder 1.64 MW 1.39 MW
957381 AF2-032 C 50/50 1.84 MW 1.84 MW
957382 AF2-032 E 50/50 0.86 MW 0.86 MW
957471 AF2-041 C Adder 9.88 MW 8.39 MW
957472 AF2-041 E Adder 4.94 MW 4.2 MW
274890 CAYUG;1U E Adder 7.79 MW 6.62 MW
274891 CAYUG;2U E Adder 7.79 MW 6.62 MW
925771 AC1-053 C 50/50 0.48 MW 0.48 MW
925772 AC1-053 E 50/50 20.04 MW 20.04 MW
933441 AC2-157 C Adder -19.06 MW -16.2 MW
938851 AE1-113 C Adder 3.74 MW 3.18 MW
938852 AE1-113 E Adder 13.26 MW 11.27 MW
934101 AD2-000 1 Adder 2.41 MW 2.05 MW
276174 W4-005 E 50/50 29.4 MW 29.4 MW
293516 O-009 E Adder 10.7 MW 9.1 MW
916212 CRESCENT ;1U Adder 3.08 MW 2.62 MW
924048 AB2-047 E1 Adder 9.04 MW 7.69 MW
924049 AB2-047 E2 Adder 9.18 MW 7.81 MW
927208 AC1-214 E1 Adder 2.08 MW 1.77 MW
927209 AC1-214 E2 Adder 2.08 MW 1.77 MW
957751 AF2-069 C Adder 0.14 MW 0.12 MW
957752 AF2-069 E Adder 0.44 MW 0.37 MW
990901 L-005 E Adder 8.57 MW 7.28 MW
290108 LEEDK;1U E Adder 10.24 MW 8.7 MW
916221 Z1-073 E Adder 3.32 MW 2.82 MW
276668 AB2-070 C 50/50 0.48 MW 0.48 MW
924266 AB2-070 E 50/50 17.75 MW 17.75 MW
926821 AC1-168 C Adder 0.67 MW 0.57 MW
926822 AC1-168 E Adder 4.48 MW 3.8 MW
934051 AD1-031 C Adder 1.85 MW 1.57 MW
934052 AD1-031 E Adder 3.02 MW 2.56 MW
935141 AD1-148 C 50/50 0.71 MW 0.71 MW
936292 AD2-038 E Adder 6.86 MW 5.83 MW
936511 AD2-066 C Adder 3.9 MW 3.32 MW
936512 AD2-066 E Adder 2.6 MW 2.21 MW
942421 AE2-255 C Adder 1.42 MW 1.2 MW
942422 AE2-255 E Adder 4.25 MW 3.61 MW
942651 AE2-281 C Adder 0.39 MW 0.33 MW
942652 AE2-281 E Adder 2.38 MW 2.03 MW
959091 AF2-200 C Adder 6.58 MW 5.6 MW
959092 AF2-200 E Adder 4.39 MW 3.73 MW
960141 AF2-305_AG1- 50/50 1.04 MW 1.04 MW
960261 AF2-317 C 50/50 0.3 MW 0.3 MW
961011 AF2-392 C Adder 2.13 MW 1.81 MW
961012 AF2-392 E Adder 9.9 MW 8.42 MW
966822 AG1-553 E Adder 17.41 MW 14.8 MW
930462 AB1-087 E Adder -6.27 MW -5.33 MW
930472 AB1-088 E Adder -6.27 MW -5.33 MW
930481 AB1-089 C Adder 29.83 MW 25.36 MW
930482 AB1-089 E Adder 1.36 MW 1.15 MW
938861 AE1-114 C Adder 1.96 MW 1.67 MW
938862 AE1-114 E Adder 6.7 MW 5.69 MW
939321 AE1-163 C Adder 2.72 MW 2.31 MW
939322 AE1-163 E Adder 16.69 MW 14.19 MW
939401 AE1-172 C Adder 2.66 MW 2.26 MW
939402 AE1-172 E Adder 12.44 MW 10.58 MW
939741 AE1-205 C Adder 7.04 MW 5.98 MW
939742 AE1-205 E Adder 9.72 MW 8.26 MW
946152 AF1-280 E Adder 11.85 MW 10.07 MW
946321 AF1-296 C Adder 2.22 MW 1.88 MW
946322 AF1-296 E Adder 10.37 MW 8.82 MW
946671 AF1-331 C Adder 1.07 MW 0.91 MW
962691 AG1-118 C Adder 9.15 MW 7.78 MW
962692 AG1-118 E Adder 6.1 MW 5.19 MW
963831 AG1-236 C 50/50 2.69 MW 2.69 MW
963832 AG1-236 E 50/50 18.04 MW 18.04 MW
941731 AE2-173 C Adder 4.19 MW 3.56 MW
944221 AF1-090 C 50/50 5.49 MW 5.49 MW
944222 AF1-090 E 50/50 25.72 MW 25.72 MW
965331 AG1-398 C 50/50 0.13 MW 0.13 MW
965931 AG1-462 C Adder 10.25 MW 8.71 MW
965932 AG1-462 E Adder 6.83 MW 5.81 MW
276626 AG1-044 E Adder 0.04 MW 0.04 MW
944202 AF1-088 NFTW 50/50 250.78 MW 250.78 MW
920272 AA2-123 E Adder 1.22 MW 1.04 MW
990272 J1263 G External Queue 52.7 MW 52.7 MW
991082 J1475 G External Queue 38.23 MW 38.23 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 72.06 MW 72.06 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 43.82 MW 43.82 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 12.77 MW 12.77 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.47 MW 0.47 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 1.77 MW 1.77 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.74 MW 0.74 MW
TVA LTFEXP_TVA->PJM CLTF 6.28 MW 6.28 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.9 MW 0.9 MW
MEC LTFEXP_MEC->PJM CLTF 12.35 MW 12.35 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.39 MW 2.39 MW
LAGN LTFEXP_LAGN->PJM CLTF 9.87 MW 9.87 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.02 MW 3.02 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.34 MW 0.34 MW

Details for AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.54 %
Rating: 1409.0 MVA
Rating Type: A
MVA to Mitigate: 1458.95 MVA
MW Contribution: 57.12 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.1 %
Rating: 1409.0 MVA
Rating Type: A
MVA to Mitigate: 1480.91 MVA
MW Contribution: 56.86 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965911 AG1-460 C Adder 0.62 MW 0.53 MW
965912 AG1-460 E Adder 0.94 MW 0.8 MW
936771 AD2-100 C Adder 6.7 MW 5.7 MW
936772 AD2-100 E Adder 4.47 MW 3.8 MW
936971 AD2-131 C Adder 0.44 MW 0.38 MW
936972 AD2-131 E Adder 2.22 MW 1.89 MW
942481 AE2-261 C Adder 9.35 MW 7.95 MW
942482 AE2-261 E Adder 6.23 MW 5.3 MW
957381 AF2-032 C Adder 0.7 MW 0.6 MW
957382 AF2-032 E Adder 0.33 MW 0.28 MW
933441 AC2-157 C Adder 4.34 MW 3.69 MW
933442 AC2-157 E Adder 7.08 MW 6.02 MW
942601 AE2-276 C Adder 2.86 MW 2.43 MW
945391 AF1-204 C 50/50 14.7 MW 14.7 MW
945392 AF1-204 E 50/50 44.1 MW 44.1 MW
930462 AB1-087 E Adder 1.43 MW 1.21 MW
930472 AB1-088 E Adder 1.43 MW 1.21 MW
963741 AG1-226 C 50/50 82.02 MW 82.02 MW
963742 AG1-226 E 50/50 177.89 MW 177.89 MW
963841 AG1-237 C 50/50 17.59 MW 17.59 MW
963842 AG1-237 E 50/50 117.69 MW 117.69 MW
944221 AF1-090 C Adder 1.98 MW 1.69 MW
944222 AF1-090 E Adder 9.29 MW 7.89 MW
958391 AF2-133 C Adder -19.34 MW -16.44 MW
944201 AF1-088 FTIR Adder 67.2 MW 57.12 MW
957142 AF2-008 NFTI Adder 33.6 MW 28.56 MW
957141 AF2-008 FTIR Adder 33.6 MW 28.56 MW
955152 J993 G External Queue 10.66 MW 10.66 MW
956452 J1139 External Queue 16.46 MW 16.46 MW
990272 J1263 G External Queue 28.22 MW 28.22 MW
990577 J1339 External Queue -10.83 MW -10.83 MW
990582 J1340 External Queue -10.83 MW -10.83 MW
990647 J1355 External Queue -8.06 MW -8.06 MW
990672 J1360 External Queue 21.55 MW 21.55 MW
991162 J1518 External Queue 20.05 MW 20.05 MW
991252 J1691 External Queue 15.46 MW 15.46 MW
992572 J1022 External Queue 9.7 MW 9.7 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.33 MW 27.33 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 11.65 MW 11.65 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.04 MW 0.04 MW
VTF LTFEXP_VFT->PJM CMTX 0.09 MW 0.09 MW
NY PJM->LTFIMP_NY CLTF 0.02 MW 0.02 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.44 MW 1.44 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.85 MW 0.85 MW
TVA LTFEXP_TVA->PJM CLTF 3.64 MW 3.64 MW
MEC LTFEXP_MEC->PJM CLTF 2.87 MW 2.87 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.58 MW 4.58 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.53 MW 0.53 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.41 MW 0.41 MW

Details for 05DEQUIN-05MEADOW 345.0 kV Ckt 1 line l/o AEP_P1-2_#6490_16000_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
Contingency Name:
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.25 %
Rating: 1958.0 MVA
Rating Type: B
MVA to Mitigate: 2002.1 MVA
MW Contribution: 137.22 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
05DEQUIN-05MEADOW 345.0 kV Ckt 1 line
243217 to 243878 ckt 1
Contingency Name:
AEP_P1-2_#6490_16000_SRT-A
CONTINGENCY 'AEP_P1-2_#6490_16000_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 2   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.89 %
Rating: 1958.0 MVA
Rating Type: B
MVA to Mitigate: 2014.59 MVA
MW Contribution: 137.16 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 48.55 MW 48.55 MW
966842 AG1-555 E 50/50 17.36 MW 17.36 MW
247900 05FR-11G E 50/50 46.96 MW 46.96 MW
247901 05FR-12G E 50/50 46.24 MW 46.24 MW
247902 05FR-21G E 50/50 49.15 MW 49.15 MW
247903 05FR-22G E 50/50 47.23 MW 47.23 MW
247904 05FR-3G E 50/50 91.61 MW 91.61 MW
247905 05FR-4G E 50/50 72.61 MW 72.61 MW
243859 05FR-11G C 50/50 2.31 MW 2.31 MW
243862 05FR-12G C 50/50 1.12 MW 1.12 MW
243864 05FR-21G C 50/50 1.17 MW 1.17 MW
243866 05FR-22G C 50/50 1.17 MW 1.17 MW
243870 05FR-3G C 50/50 1.12 MW 1.12 MW
243873 05FR-4G C 50/50 2.61 MW 2.61 MW
933441 AC2-157 C 50/50 10.43 MW 10.43 MW
933442 AC2-157 E 50/50 17.02 MW 17.02 MW
942601 AE2-276 C 50/50 6.86 MW 6.86 MW
945391 AF1-204 C 50/50 13.29 MW 13.29 MW
945392 AF1-204 E 50/50 39.87 MW 39.87 MW
930461 AB1-087 C 50/50 11.99 MW 11.99 MW
930462 AB1-087 E 50/50 3.43 MW 3.43 MW
930471 AB1-088 C 50/50 11.81 MW 11.81 MW
930472 AB1-088 E 50/50 3.43 MW 3.43 MW
963741 AG1-226 C 50/50 59.83 MW 59.83 MW
963742 AG1-226 E 50/50 129.77 MW 129.77 MW
963841 AG1-237 C 50/50 12.53 MW 12.53 MW
963842 AG1-237 E 50/50 83.86 MW 83.86 MW
958391 AF2-133 C Adder -30.54 MW -25.96 MW
944201 AF1-088 FTIR 50/50 137.22 MW 137.22 MW
957142 AF2-008 NFTI 50/50 68.61 MW 68.61 MW
957141 AF2-008 FTIR 50/50 68.61 MW 68.61 MW
956452 J1139 External Queue 16.81 MW 16.81 MW
990272 J1263 G External Queue 40.74 MW 40.74 MW
991082 J1475 G External Queue 8.13 MW 8.13 MW
991162 J1518 External Queue 24.92 MW 24.92 MW
991252 J1691 External Queue 19.08 MW 19.08 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 34.76 MW 34.76 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 16.46 MW 16.46 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.14 MW 0.14 MW
VTF LTFEXP_VFT->PJM CMTX 0.36 MW 0.36 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.11 MW 2.11 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.21 MW 1.21 MW
TVA LTFEXP_TVA->PJM CLTF 4.93 MW 4.93 MW
MEC LTFEXP_MEC->PJM CLTF 2.8 MW 2.8 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.02 MW 6.02 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.72 MW 0.72 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.58 MW 0.58 MW

Details for 05DEQUIN-05MEADOW 345.0 kV Ckt 2 line l/o AEP_P1-2_#6472_15258_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
Contingency Name:
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 101.41 %
Rating: 1958.0 MVA
Rating Type: B
MVA to Mitigate: 1985.55 MVA
MW Contribution: 136.07 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
05DEQUIN-05MEADOW 345.0 kV Ckt 2 line
243217 to 243878 ckt 2
Contingency Name:
AEP_P1-2_#6472_15258_SRT-A
CONTINGENCY 'AEP_P1-2_#6472_15258_SRT-A'
 OPEN BRANCH FROM BUS 243217 TO BUS 243878 CKT 1   /*05DEQUIN     345.0 - 05MEADOW     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.04 %
Rating: 1958.0 MVA
Rating Type: B
MVA to Mitigate: 1997.96 MVA
MW Contribution: 136.01 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966841 AG1-555 C 50/50 48.14 MW 48.14 MW
966842 AG1-555 E 50/50 17.21 MW 17.21 MW
247900 05FR-11G E 50/50 46.56 MW 46.56 MW
247901 05FR-12G E 50/50 45.86 MW 45.86 MW
247902 05FR-21G E 50/50 48.74 MW 48.74 MW
247903 05FR-22G E 50/50 46.84 MW 46.84 MW
247904 05FR-3G E 50/50 90.84 MW 90.84 MW
247905 05FR-4G E 50/50 72.0 MW 72.0 MW
243859 05FR-11G C 50/50 2.29 MW 2.29 MW
243862 05FR-12G C 50/50 1.11 MW 1.11 MW
243864 05FR-21G C 50/50 1.16 MW 1.16 MW
243866 05FR-22G C 50/50 1.16 MW 1.16 MW
243870 05FR-3G C 50/50 1.11 MW 1.11 MW
243873 05FR-4G C 50/50 2.59 MW 2.59 MW
933441 AC2-157 C 50/50 10.34 MW 10.34 MW
933442 AC2-157 E 50/50 16.87 MW 16.87 MW
942601 AE2-276 C 50/50 6.8 MW 6.8 MW
945391 AF1-204 C 50/50 13.18 MW 13.18 MW
945392 AF1-204 E 50/50 39.54 MW 39.54 MW
930461 AB1-087 C 50/50 11.89 MW 11.89 MW
930462 AB1-087 E 50/50 3.4 MW 3.4 MW
930471 AB1-088 C 50/50 11.71 MW 11.71 MW
930472 AB1-088 E 50/50 3.4 MW 3.4 MW
963741 AG1-226 C 50/50 59.33 MW 59.33 MW
963742 AG1-226 E 50/50 128.69 MW 128.69 MW
963841 AG1-237 C 50/50 12.43 MW 12.43 MW
963842 AG1-237 E 50/50 83.16 MW 83.16 MW
958391 AF2-133 C Adder -30.28 MW -25.74 MW
944201 AF1-088 FTIR 50/50 136.07 MW 136.07 MW
957142 AF2-008 NFTI 50/50 68.04 MW 68.04 MW
957141 AF2-008 FTIR 50/50 68.04 MW 68.04 MW
956452 J1139 External Queue 16.67 MW 16.67 MW
990272 J1263 G External Queue 40.4 MW 40.4 MW
991082 J1475 G External Queue 8.06 MW 8.06 MW
991162 J1518 External Queue 24.71 MW 24.71 MW
991252 J1691 External Queue 18.92 MW 18.92 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 34.47 MW 34.47 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 16.33 MW 16.33 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.14 MW 0.14 MW
VTF LTFEXP_VFT->PJM CMTX 0.36 MW 0.36 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.1 MW 2.1 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.2 MW 1.2 MW
TVA LTFEXP_TVA->PJM CLTF 4.89 MW 4.89 MW
MEC LTFEXP_MEC->PJM CLTF 2.77 MW 2.77 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.97 MW 5.97 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.72 MW 0.72 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.58 MW 0.58 MW

Details for AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line l/o EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345/69XFR_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Contingency Name:
EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345/69XFR_SRT-S
CONTINGENCY 'EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345
 CLOSE BRANCH FROM BUS 250595 TO BUS 250896 CKT 1   /*08INLNDC      69.0 - 08WROWJ       69.0
 OPEN BRANCH FROM BUS 249504 TO BUS 249505 CKT 1    /*08CAYSUB     345.0 - 08CAYUGA     345.0
 OPEN BRANCH FROM BUS 249504 TO BUS 250340 CKT 1    /*08CAYSUB     345.0 - 08CAYSUB      69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250341 CKT 1    /*08CAYSUB      69.0 - 08CAY69       69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250595 CKT 1    /*08CAYSUB      69.0 - 08INLNDC      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.2 %
Rating: 1868.0 MVA
Rating Type: B
MVA to Mitigate: 1871.77 MVA
MW Contribution: 84.43 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
AG1-237 TP-05DEQUIN 345.0 kV Ckt 1 line
963840 to 243217 ckt 1
Contingency Name:
EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345/69XFR_SRT-S
CONTINGENCY 'EXT_P1:345:DEI:CAYUGA GEN-CAYUGA 34535+CAYU 345
 CLOSE BRANCH FROM BUS 250595 TO BUS 250896 CKT 1   /*08INLNDC      69.0 - 08WROWJ       69.0
 OPEN BRANCH FROM BUS 249504 TO BUS 249505 CKT 1    /*08CAYSUB     345.0 - 08CAYUGA     345.0
 OPEN BRANCH FROM BUS 249504 TO BUS 250340 CKT 1    /*08CAYSUB     345.0 - 08CAYSUB      69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250341 CKT 1    /*08CAYSUB      69.0 - 08CAY69       69.0
 OPEN BRANCH FROM BUS 250340 TO BUS 250595 CKT 1    /*08CAYSUB      69.0 - 08INLNDC      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.79 %
Rating: 1868.0 MVA
Rating Type: B
MVA to Mitigate: 1882.7 MVA
MW Contribution: 84.49 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965091 AG1-374 C Adder 9.61 MW 8.17 MW
965092 AG1-374 E Adder 6.41 MW 5.45 MW
965911 AG1-460 C Adder 0.86 MW 0.73 MW
965912 AG1-460 E Adder 1.3 MW 1.1 MW
290261 S-027 E Adder 8.72 MW 7.41 MW
290265 S-028 E Adder 8.66 MW 7.36 MW
936771 AD2-100 C Adder 9.15 MW 7.78 MW
936772 AD2-100 E Adder 6.1 MW 5.18 MW
936971 AD2-131 C Adder 0.6 MW 0.51 MW
936972 AD2-131 E Adder 3.03 MW 2.57 MW
942481 AE2-261 C Adder 12.91 MW 10.97 MW
942482 AE2-261 E Adder 8.61 MW 7.32 MW
959611 AF2-252 C Adder 1.07 MW 0.91 MW
959612 AF2-252 E Adder 1.6 MW 1.36 MW
960611 AF2-352 C Adder 1.07 MW 0.91 MW
960612 AF2-352 E Adder 1.6 MW 1.36 MW
276615 W2-048 GEN Adder 3.87 MW 3.29 MW
276621 X2-022 GEN Adder 13.24 MW 11.25 MW
957381 AF2-032 C Adder 0.98 MW 0.83 MW
957382 AF2-032 E Adder 0.46 MW 0.39 MW
925772 AC1-053 E Adder 12.48 MW 10.61 MW
933441 AC2-157 C Adder 6.42 MW 5.45 MW
933442 AC2-157 E Adder 10.47 MW 8.9 MW
276174 W4-005 E Adder 18.94 MW 16.1 MW
924266 AB2-070 E Adder 11.31 MW 9.62 MW
942601 AE2-276 C Adder 4.22 MW 3.59 MW
945391 AF1-204 C 50/50 23.64 MW 23.64 MW
945392 AF1-204 E 50/50 70.92 MW 70.92 MW
960141 AF2-305_AG1- Adder 0.66 MW 0.56 MW
930462 AB1-087 E Adder 2.11 MW 1.79 MW
930472 AB1-088 E Adder 2.11 MW 1.79 MW
963741 AG1-226 C 50/50 92.85 MW 92.85 MW
963742 AG1-226 E 50/50 201.38 MW 201.38 MW
963831 AG1-236 C Adder 1.68 MW 1.43 MW
963832 AG1-236 E Adder 11.24 MW 9.55 MW
963841 AG1-237 C 50/50 19.09 MW 19.09 MW
963842 AG1-237 E 50/50 127.79 MW 127.79 MW
944221 AF1-090 C Adder 2.62 MW 2.23 MW
944222 AF1-090 E Adder 12.27 MW 10.43 MW
958391 AF2-133 C Adder -16.0 MW -13.6 MW
944201 AF1-088 FTIR Adder 99.33 MW 84.43 MW
957142 AF2-008 NFTI Adder 49.66 MW 42.21 MW
957141 AF2-008 FTIR Adder 49.66 MW 42.21 MW
956282 J1115 C External Queue 2.03 MW 2.03 MW
956283 J1115 E External Queue 10.97 MW 10.97 MW
956452 J1139 External Queue 25.02 MW 25.02 MW
990272 J1263 G External Queue 33.08 MW 33.08 MW
990647 J1355 External Queue -7.29 MW -7.29 MW
990672 J1360 External Queue 33.75 MW 33.75 MW
991082 J1475 G External Queue 5.09 MW 5.09 MW
991197 J1626 External Queue 8.17 MW 8.17 MW
991267 J1714 External Queue 5.45 MW 5.45 MW
992572 J1022 External Queue 15.56 MW 15.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.83 MW 6.83 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 24.78 MW 24.78 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 8.88 MW 8.88 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.23 MW 0.23 MW
NY PJM->LTFIMP_NY CLTF 0.15 MW 0.15 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.81 MW 0.81 MW
WEC LTFEXP_WEC->PJM CLTF 0.34 MW 0.34 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.59 MW 0.59 MW
TVA LTFEXP_TVA->PJM CLTF 3.26 MW 3.26 MW
MEC LTFEXP_MEC->PJM CLTF 4.33 MW 4.33 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.53 MW 4.53 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.33 MW 0.33 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.5 MW 1.5 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.28 MW 0.28 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request was evaluated as a 1000.0 MW injection and 0.0 MW withdrawal in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Single AC 135.55 % 1180.0 B 1599.51 98.43
AEP/OVEC 06KYGER-05SPORN 345.0 kV Ckt 1 line
248005 to 242528 ckt 1
AEP_P1-2_#7441_100545_SRT-A
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
Single DC 105.64 % 1204.0 B 1271.86 63.79
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L
CONTINGENCY 'EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L'
 OPEN BRANCH FROM BUS 249521 TO BUS 347340 CKT 1   /*08SUGCRK     345.0 - 7KANSAS      345.0
END
Single AC 103.06 % 1374.0 B 1416.03 92.72
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Tower AC 110.56 % 1374.0 B 1519.03 115.78
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Tower AC 102.18 % 1374.0 B 1403.98 122.92

Details for 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 135.55 %
Rating: 1180.0 MVA
Rating Type: B
MVA to Mitigate: 1599.51 MVA
MW Contribution: 98.43 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943031 AE2-326 C 80/20 6.34 MW 6.34 MW
943032 AE2-326 E 80/20 4.23 MW 4.23 MW
242892 05AMG2 80/20 56.42 MW 56.42 MW
242893 05AMG3 80/20 92.58 MW 92.58 MW
243443 05RKG2 80/20 78.36 MW 78.36 MW
274675 JOLIET 29;7U Adder 30.54 MW 25.96 MW
274676 JOLIET 29;8U Adder 30.54 MW 25.96 MW
944971 AF1-162 C 80/20 7.93 MW 7.93 MW
944972 AF1-162 E 80/20 5.29 MW 5.29 MW
945382 AF1-203 E 80/20 2.17 MW 2.17 MW
964782 AG1-341 E 80/20 11.47 MW 11.47 MW
223403 AG1-063 C Adder -0.07 MW -0.06 MW
940351 AE2-019 C Adder -15.78 MW -13.41 MW
965411 AG1-406 C 80/20 2.46 MW 2.46 MW
966391 AG1-508 C 80/20 1.47 MW 1.47 MW
966392 AG1-508 E 80/20 8.51 MW 8.51 MW
242899 05CRG1H 80/20 8.49 MW 8.49 MW
242900 05CRG1L 80/20 7.11 MW 7.11 MW
242901 05CRG2H 80/20 8.55 MW 8.55 MW
242902 05CRG2L 80/20 7.17 MW 7.17 MW
243758 05MIDDLECR 80/20 0.26 MW 0.26 MW
270167 AD2-205 E 80/20 0.79 MW 0.79 MW
940353 AE2-019 BT 80/20 15.78 MW 15.78 MW
944201 AF1-088 FTIR Adder 115.8 MW 98.43 MW
957193 AF2-013 BT 80/20 11.36 MW 11.36 MW
962183 AG1-063 BAT 80/20 0.26 MW 0.26 MW
962553 AG1-104 BT 80/20 30.68 MW 30.68 MW
963033 AG1-152 BT 80/20 13.61 MW 13.61 MW
963053 AG1-154 BT 80/20 5.97 MW 5.97 MW
963693 AG1-221 BT 80/20 6.49 MW 6.49 MW
966143 AG1-483 BAT 80/20 55.8 MW 55.8 MW
966253 AG1-494 BT 80/20 12.02 MW 12.02 MW

Details for 06KYGER-05SPORN 345.0 kV Ckt 1 line l/o AEP_P1-2_#7441_100545_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
248005 to 242528 ckt 1
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
Contingency Type: Single
DC|AC: DC
Final Cycle Loading: 105.64 %
Rating: 1204.0 MVA
Rating Type: B
MVA to Mitigate: 1271.86 MVA
MW Contribution: 63.79 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
248005 to 242528 ckt 1
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
Contingency Type: Single
DC|AC: DC
Final Cycle Loading: 107.98 %
Rating: 1204.0 MVA
Rating Type: B
MVA to Mitigate: 1300.13 MVA
MW Contribution: 62.72 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247255 05WLD G2 C 80/20 0.23 MW 0.23 MW
243859 05FR-11G C 80/20 0.38 MW 0.38 MW
243862 05FR-12G C 80/20 0.18 MW 0.18 MW
243864 05FR-21G C 80/20 0.19 MW 0.19 MW
243866 05FR-22G C 80/20 0.19 MW 0.19 MW
243870 05FR-3G C 80/20 0.18 MW 0.18 MW
243873 05FR-4G C 80/20 0.43 MW 0.43 MW
247901 05FR-12G E 80/20 1.24 MW 1.24 MW
247902 05FR-21G E 80/20 1.32 MW 1.32 MW
247904 05FR-3G E 80/20 2.46 MW 2.46 MW
247905 05FR-4G E 80/20 1.95 MW 1.95 MW
247906 05MDL-1G E 80/20 2.56 MW 2.56 MW
247907 05MDL-2G E 80/20 1.23 MW 1.23 MW
247912 05MDL-3G E 80/20 1.23 MW 1.23 MW
247913 05MDL-4G E 80/20 1.28 MW 1.28 MW
247958 05WLD G2 E 80/20 3.06 MW 3.06 MW
274847 GR RIDGE ;BU 80/20 0.37 MW 0.37 MW
274853 TWINGROVE;U1 80/20 0.48 MW 0.48 MW
274854 TWINGROVE;U2 80/20 0.49 MW 0.49 MW
274861 TOP CROP ;1U 80/20 0.25 MW 0.25 MW
274862 TOP CROP ;2U 80/20 0.47 MW 0.47 MW
274863 CAYUGA RI;1U 80/20 0.31 MW 0.31 MW
274864 CAYUGA RI;2U 80/20 0.31 MW 0.31 MW
274871 GR RIDGE ;2U 80/20 0.14 MW 0.14 MW
274880 RADFORD R;1U 80/20 0.64 MW 0.64 MW
274887 PILOT HIL;1U 80/20 0.47 MW 0.47 MW
274888 KELLY CRK;1U 80/20 0.47 MW 0.47 MW
276615 W2-048 GEN 80/20 0.91 MW 0.91 MW
276621 X2-022 GEN 80/20 2.58 MW 2.58 MW
290261 S-027 E 80/20 2.26 MW 2.26 MW
290265 S-028 E 80/20 2.25 MW 2.25 MW
293061 N-015 E 80/20 1.62 MW 1.62 MW
293644 O22 E1 80/20 1.54 MW 1.54 MW
293645 O22 E2 80/20 1.77 MW 1.77 MW
294392 P-010 E 80/20 2.05 MW 2.05 MW
917502 Z2-087 E 80/20 2.4 MW 2.4 MW
918052 AA1-018 E OP 80/20 1.75 MW 1.75 MW
934721 AD1-100 C 80/20 1.95 MW 1.95 MW
934722 AD1-100 E 80/20 30.27 MW 30.27 MW
942111 AE2-223 C 80/20 0.86 MW 0.86 MW
942112 AE2-223 E 80/20 5.77 MW 5.77 MW
959351 AF2-226 C 80/20 1.07 MW 1.07 MW
959352 AF2-226 E 80/20 1.61 MW 1.61 MW
959611 AF2-252 C 80/20 1.11 MW 1.11 MW
959612 AF2-252 E 80/20 1.66 MW 1.66 MW
960281 AF2-319 C 80/20 1.07 MW 1.07 MW
960282 AF2-319 E 80/20 1.61 MW 1.61 MW
960611 AF2-352 C 80/20 1.11 MW 1.11 MW
960612 AF2-352 E 80/20 1.66 MW 1.66 MW
960971 AF2-388 C 80/20 1.88 MW 1.88 MW
960972 AF2-388 E 80/20 8.78 MW 8.78 MW
965651 AG1-433 C 80/20 0.94 MW 0.94 MW
965652 AG1-433 E 80/20 4.39 MW 4.39 MW
966091 AG1-478 C 80/20 0.21 MW 0.21 MW
966092 AG1-478 E 80/20 0.32 MW 0.32 MW
966431 AG1-512 C 80/20 0.86 MW 0.86 MW
966432 AG1-512 E 80/20 1.29 MW 1.29 MW
966842 AG1-555 E 80/20 5.22 MW 5.22 MW
243443 05RKG2 80/20 52.1 MW 52.1 MW
243795 05HDWTR1G C 80/20 0.51 MW 0.51 MW
246991 05WLD G1 C 80/20 0.23 MW 0.23 MW
247536 05BLUFF P WF 80/20 0.43 MW 0.43 MW
247543 V3-007 C 80/20 0.51 MW 0.51 MW
247929 S-071 E 80/20 1.71 MW 1.71 MW
247935 V3-007 E 80/20 3.4 MW 3.4 MW
247963 05HDWTR1G E 80/20 3.4 MW 3.4 MW
274674 JOLIET 9 ;6U 80/20 6.8 MW 6.8 MW
274676 JOLIET 29;8U 80/20 17.72 MW 17.72 MW
943771 AF1-045 C 80/20 3.67 MW 3.67 MW
943772 AF1-045 E 80/20 2.45 MW 2.45 MW
961761 AG1-017 C 80/20 0.15 MW 0.15 MW
961762 AG1-017 E 80/20 0.71 MW 0.71 MW
246909 05MDL-1G C 80/20 0.38 MW 0.38 MW
246910 05MDL-2G C 80/20 0.22 MW 0.22 MW
246976 05MDL-3G C 80/20 0.22 MW 0.22 MW
246979 05MDL-4G C 80/20 0.17 MW 0.17 MW
274890 CAYUG;1U E 80/20 1.64 MW 1.64 MW
274891 CAYUG;2U E 80/20 1.64 MW 1.64 MW
925771 AC1-053 C 80/20 0.58 MW 0.58 MW
925772 AC1-053 E 80/20 3.89 MW 3.89 MW
247900 05FR-11G E 80/20 1.26 MW 1.26 MW
247903 05FR-22G E 80/20 1.27 MW 1.27 MW
939401 AE1-172 C 80/20 1.96 MW 1.96 MW
939402 AE1-172 E 80/20 9.15 MW 9.15 MW
939781 AE1-209 C 80/20 0.76 MW 0.76 MW
939782 AE1-209 E 80/20 5.09 MW 5.09 MW
957382 AF2-032 E 80/20 0.11 MW 0.11 MW
247556 05MDL-5G 80/20 0.29 MW 0.29 MW
247943 T-127 E 80/20 1.16 MW 1.16 MW
251828 CLNTESP1 80/20 1.03 MW 1.03 MW
251968 08ZIMRHP 80/20 47.67 MW 47.67 MW
270180 AB1-006 W1 80/20 0.33 MW 0.33 MW
270181 AB1-006 W2 80/20 0.05 MW 0.05 MW
270681 BRIGHTSTK; R 80/20 0.36 MW 0.36 MW
270839 OTTER CRK; R 80/20 0.26 MW 0.26 MW
275149 KELLYCK ;1E 80/20 1.89 MW 1.89 MW
276174 W4-005 E 80/20 3.64 MW 3.64 MW
276655 AB2-047 C1 80/20 0.23 MW 0.23 MW
276656 AB2-047 C2 80/20 0.23 MW 0.23 MW
276668 AB2-070 C 80/20 0.36 MW 0.36 MW
293519 PILOT HIL;1E 80/20 1.89 MW 1.89 MW
924048 AB2-047 E1 80/20 1.49 MW 1.49 MW
924049 AB2-047 E2 80/20 1.51 MW 1.51 MW
924266 AB2-070 E 80/20 2.2 MW 2.2 MW
926821 AC1-168 C 80/20 0.44 MW 0.44 MW
926822 AC1-168 E 80/20 2.95 MW 2.95 MW
930041 AB1-006 E1 80/20 2.21 MW 2.21 MW
930042 AB1-006 E2 80/20 0.32 MW 0.32 MW
935141 AD1-148 C 80/20 0.81 MW 0.81 MW
936371 AD2-047 C 80/20 1.47 MW 1.47 MW
936372 AD2-047 E 80/20 7.16 MW 7.16 MW
939791 AE1-210 C 80/20 0.76 MW 0.76 MW
939792 AE1-210 E 80/20 5.09 MW 5.09 MW
941721 AE2-172 C 80/20 2.74 MW 2.74 MW
941731 AE2-173 C 80/20 2.76 MW 2.76 MW
942601 AE2-276 C 80/20 3.19 MW 3.19 MW
944221 AF1-090 C 80/20 1.58 MW 1.58 MW
944222 AF1-090 E 80/20 7.38 MW 7.38 MW
944242 AF1-092 E 80/20 6.5 MW 6.5 MW
944532 AF1-118 E 80/20 21.95 MW 21.95 MW
944542 AF1-119 E 80/20 12.99 MW 12.99 MW
945371 AF1-202 C 80/20 1.85 MW 1.85 MW
945372 AF1-202 E 80/20 9.03 MW 9.03 MW
945391 AF1-204 C 80/20 3.19 MW 3.19 MW
945392 AF1-204 E 80/20 9.56 MW 9.56 MW
957842 AF2-078 E 80/20 1.16 MW 1.16 MW
958861 AF2-177 C 80/20 1.4 MW 1.4 MW
958862 AF2-177 E 80/20 9.38 MW 9.38 MW
960261 AF2-317 C 80/20 0.35 MW 0.35 MW
960791 AF2-370 C 80/20 1.43 MW 1.43 MW
961161 AF2-407 C 80/20 21.89 MW 21.89 MW
961171 AF2-408 C 80/20 5.91 MW 5.91 MW
961501 AF2-441 C 80/20 4.3 MW 4.3 MW
961502 AF2-441 E 80/20 6.45 MW 6.45 MW
963581 AG1-207 C 80/20 6.56 MW 6.56 MW
963831 AG1-236 C 80/20 1.04 MW 1.04 MW
963832 AG1-236 E 80/20 6.99 MW 6.99 MW
963841 AG1-237 C 80/20 1.24 MW 1.24 MW
963842 AG1-237 E 80/20 8.31 MW 8.31 MW
964351 AG1-297 C 80/20 6.24 MW 6.24 MW
964352 AG1-297 E 80/20 18.7 MW 18.7 MW
964611 AG1-324 C 80/20 0.31 MW 0.31 MW
964612 AG1-324 E 80/20 0.47 MW 0.47 MW
965331 AG1-398 C 80/20 0.16 MW 0.16 MW
965411 AG1-406 C 80/20 1.3 MW 1.3 MW
965462 AG1-414 E 80/20 1.69 MW 1.69 MW
270201 AC2-176 GEN 80/20 0.29 MW 0.29 MW
933596 AC2-176 E 80/20 1.93 MW 1.93 MW
250164 08BKJDB1 80/20 0.26 MW 0.26 MW
251827 WILLYESP 80/20 0.67 MW 0.67 MW
944201 AF1-088 FTIR 80/20 63.79 MW 63.79 MW
957141 AF2-008 FTIR 80/20 31.89 MW 31.89 MW
965913 AG1-460 BT 80/20 0.01 MW 0.01 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L
CONTINGENCY 'EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L'
 OPEN BRANCH FROM BUS 249521 TO BUS 347340 CKT 1   /*08SUGCRK     345.0 - 7KANSAS      345.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 103.06 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1416.03 MVA
MW Contribution: 92.72 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L
CONTINGENCY 'EXT_249521 08SUGCRK 345 347340 7KANSAS 345 1 _SRT-L'
 OPEN BRANCH FROM BUS 249521 TO BUS 347340 CKT 1   /*08SUGCRK     345.0 - 7KANSAS      345.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 104.08 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1430.04 MVA
MW Contribution: 93.89 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243859 05FR-11G C 80/20 0.66 MW 0.66 MW
243862 05FR-12G C 80/20 0.32 MW 0.32 MW
243864 05FR-21G C 80/20 0.34 MW 0.34 MW
243866 05FR-22G C 80/20 0.34 MW 0.34 MW
243870 05FR-3G C 80/20 0.32 MW 0.32 MW
243873 05FR-4G C 80/20 0.75 MW 0.75 MW
247901 05FR-12G E 80/20 2.17 MW 2.17 MW
247902 05FR-21G E 80/20 2.31 MW 2.31 MW
247904 05FR-3G E 80/20 4.3 MW 4.3 MW
247905 05FR-4G E 80/20 3.4 MW 3.4 MW
247906 05MDL-1G E 80/20 3.26 MW 3.26 MW
247907 05MDL-2G E 80/20 1.57 MW 1.57 MW
247912 05MDL-3G E 80/20 1.57 MW 1.57 MW
247913 05MDL-4G E 80/20 1.63 MW 1.63 MW
274848 CAMPGROVE;RU 80/20 0.18 MW 0.18 MW
274849 CRESCENT ;1U 80/20 0.13 MW 0.13 MW
274851 PROVIDENC;RU 80/20 0.14 MW 0.14 MW
274853 TWINGROVE;U1 80/20 0.71 MW 0.71 MW
274854 TWINGROVE;U2 80/20 0.73 MW 0.73 MW
274863 CAYUGA RI;1U 80/20 0.34 MW 0.34 MW
274864 CAYUGA RI;2U 80/20 0.34 MW 0.34 MW
274877 BISHOP HL;1U 80/20 0.27 MW 0.27 MW
274878 BISHOP HL;2U 80/20 0.27 MW 0.27 MW
274880 RADFORD R;1U 80/20 1.1 MW 1.1 MW
276615 W2-048 GEN 80/20 1.52 MW 1.52 MW
276621 X2-022 GEN 80/20 4.34 MW 4.34 MW
290261 S-027 E 80/20 3.32 MW 3.32 MW
290265 S-028 E 80/20 3.3 MW 3.3 MW
293771 O-035 E 80/20 0.86 MW 0.86 MW
294401 BSHIL;1U E 80/20 1.06 MW 1.06 MW
294410 BSHIL;2U E 80/20 1.06 MW 1.06 MW
917502 Z2-087 E 80/20 3.44 MW 3.44 MW
925581 AC1-033 C 80/20 0.28 MW 0.28 MW
925582 AC1-033 E 80/20 1.86 MW 1.86 MW
942111 AE2-223 C 80/20 1.23 MW 1.23 MW
942112 AE2-223 E 80/20 8.26 MW 8.26 MW
959611 AF2-252 C 80/20 1.63 MW 1.63 MW
959612 AF2-252 E 80/20 2.44 MW 2.44 MW
960611 AF2-352 C 80/20 1.63 MW 1.63 MW
960612 AF2-352 E 80/20 2.44 MW 2.44 MW
966842 AG1-555 E 80/20 9.11 MW 9.11 MW
246909 05MDL-1G C 80/20 0.48 MW 0.48 MW
246910 05MDL-2G C 80/20 0.28 MW 0.28 MW
246976 05MDL-3G C 80/20 0.28 MW 0.28 MW
246979 05MDL-4G C 80/20 0.22 MW 0.22 MW
274890 CAYUG;1U E 80/20 1.81 MW 1.81 MW
274891 CAYUG;2U E 80/20 1.81 MW 1.81 MW
925771 AC1-053 C 80/20 0.99 MW 0.99 MW
925772 AC1-053 E 80/20 6.62 MW 6.62 MW
247900 05FR-11G E 80/20 2.2 MW 2.2 MW
247903 05FR-22G E 80/20 2.21 MW 2.21 MW
939401 AE1-172 C 80/20 1.99 MW 1.99 MW
939402 AE1-172 E 80/20 9.31 MW 9.31 MW
939781 AE1-209 C Adder -0.63 MW -0.53 MW
957382 AF2-032 E 80/20 0.18 MW 0.18 MW
247556 05MDL-5G 80/20 0.37 MW 0.37 MW
247943 T-127 E 80/20 1.48 MW 1.48 MW
270180 AB1-006 W1 80/20 0.42 MW 0.42 MW
270181 AB1-006 W2 80/20 0.06 MW 0.06 MW
270681 BRIGHTSTK; R 80/20 0.51 MW 0.51 MW
276174 W4-005 E 80/20 6.3 MW 6.3 MW
276645 AC1-214 C1 80/20 0.12 MW 0.12 MW
276646 AC1-214 C2 80/20 0.12 MW 0.12 MW
276655 AB2-047 C1 80/20 0.32 MW 0.32 MW
276656 AB2-047 C2 80/20 0.32 MW 0.32 MW
276668 AB2-070 C 80/20 0.62 MW 0.62 MW
916212 CRESCENT ;1U 80/20 0.61 MW 0.61 MW
924048 AB2-047 E1 80/20 2.13 MW 2.13 MW
924049 AB2-047 E2 80/20 2.17 MW 2.17 MW
924266 AB2-070 E 80/20 3.77 MW 3.77 MW
926821 AC1-168 C 80/20 0.43 MW 0.43 MW
926822 AC1-168 E 80/20 2.92 MW 2.92 MW
927208 AC1-214 E1 80/20 0.41 MW 0.41 MW
927209 AC1-214 E2 80/20 0.41 MW 0.41 MW
930041 AB1-006 E1 80/20 2.82 MW 2.82 MW
930042 AB1-006 E2 80/20 0.4 MW 0.4 MW
935141 AD1-148 C 80/20 1.36 MW 1.36 MW
939791 AE1-210 C Adder -0.63 MW -0.53 MW
941721 AE2-172 C Adder -2.08 MW -1.76 MW
941731 AE2-173 C 80/20 3.96 MW 3.96 MW
942601 AE2-276 C 80/20 4.64 MW 4.64 MW
944221 AF1-090 C 80/20 2.56 MW 2.56 MW
944222 AF1-090 E 80/20 11.97 MW 11.97 MW
945391 AF1-204 C 80/20 19.51 MW 19.51 MW
945392 AF1-204 E 80/20 58.54 MW 58.54 MW
957751 AF2-069 C 80/20 0.09 MW 0.09 MW
957752 AF2-069 E 80/20 0.28 MW 0.28 MW
957842 AF2-078 E 80/20 1.22 MW 1.22 MW
960261 AF2-317 C 80/20 0.59 MW 0.59 MW
963831 AG1-236 C 80/20 1.78 MW 1.78 MW
963832 AG1-236 E 80/20 11.91 MW 11.91 MW
963841 AG1-237 C 80/20 3.29 MW 3.29 MW
963842 AG1-237 E 80/20 22.02 MW 22.02 MW
965331 AG1-398 C 80/20 0.28 MW 0.28 MW
990901 L-005 E 80/20 1.64 MW 1.64 MW
941723 AE2-172 BT 80/20 2.08 MW 2.08 MW
944201 AF1-088 FTIR 80/20 92.72 MW 92.72 MW
957141 AF2-008 FTIR 80/20 46.36 MW 46.36 MW
961163 AF2-407 BT 80/20 32.43 MW 32.43 MW
961173 AF2-408 BT 80/20 7.62 MW 7.62 MW
964353 AG1-297 BT 80/20 31.12 MW 31.12 MW
965913 AG1-460 BT 80/20 0.01 MW 0.01 MW
954942 J968 External Queue 10.55 MW 10.55 MW
955842 J1069 External Queue 10.55 MW 10.55 MW
956282 J1115 G External Queue 20.0 MW 20.0 MW
990057 J1201 External Queue 0.77 MW 0.77 MW
990272 J1263 G External Queue 15.33 MW 15.33 MW
990352 J1289 External Queue 13.21 MW 13.21 MW
990857 J1408 External Queue 7.61 MW 7.61 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11042___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 110.56 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1519.03 MVA
MW Contribution: 115.78 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11042___SRT-A
CONTINGENCY 'AEP_P7-1_#11042___SRT-A'
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 1   /*05MEADOW     345.0 - 17REYNOLDS   345.0
 OPEN BRANCH FROM BUS 243878 TO BUS 255205 CKT 2   /*05MEADOW     345.0 - 17REYNOLDS   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 111.46 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1531.51 MVA
MW Contribution: 116.66 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243859 05FR-11G C 50/50 1.75 MW 1.75 MW
243862 05FR-12G C 50/50 0.85 MW 0.85 MW
243864 05FR-21G C 50/50 0.89 MW 0.89 MW
243866 05FR-22G C 50/50 0.89 MW 0.89 MW
243870 05FR-3G C 50/50 0.85 MW 0.85 MW
243873 05FR-4G C 50/50 1.98 MW 1.98 MW
247901 05FR-12G E 50/50 5.73 MW 5.73 MW
247902 05FR-21G E 50/50 6.09 MW 6.09 MW
247904 05FR-3G E 50/50 11.35 MW 11.35 MW
247905 05FR-4G E 50/50 8.99 MW 8.99 MW
247906 05MDL-1G E 50/50 11.98 MW 11.98 MW
247907 05MDL-2G E 50/50 5.77 MW 5.77 MW
247912 05MDL-3G E 50/50 5.76 MW 5.76 MW
247913 05MDL-4G E 50/50 6.0 MW 6.0 MW
942111 AE2-223 C Adder 0.97 MW 0.82 MW
942112 AE2-223 E Adder 6.5 MW 5.52 MW
959611 AF2-252 C Adder 1.28 MW 1.09 MW
959612 AF2-252 E Adder 1.92 MW 1.63 MW
960611 AF2-352 C Adder 1.28 MW 1.09 MW
960612 AF2-352 E Adder 1.92 MW 1.63 MW
966842 AG1-555 E 50/50 24.06 MW 24.06 MW
243443 05RKG2 Adder 41.19 MW 35.01 MW
246909 05MDL-1G C 50/50 1.76 MW 1.76 MW
246910 05MDL-2G C 50/50 1.03 MW 1.03 MW
246976 05MDL-3G C 50/50 1.04 MW 1.04 MW
246979 05MDL-4G C 50/50 0.8 MW 0.8 MW
247900 05FR-11G E 50/50 5.82 MW 5.82 MW
247903 05FR-22G E 50/50 5.85 MW 5.85 MW
957382 AF2-032 E Adder 0.14 MW 0.12 MW
247556 05MDL-5G 50/50 1.37 MW 1.37 MW
247943 T-127 E 50/50 5.43 MW 5.43 MW
270180 AB1-006 W1 50/50 1.55 MW 1.55 MW
270181 AB1-006 W2 50/50 0.22 MW 0.22 MW
930041 AB1-006 E1 50/50 10.36 MW 10.36 MW
930042 AB1-006 E2 50/50 1.48 MW 1.48 MW
941731 AE2-173 C Adder 3.11 MW 2.65 MW
942601 AE2-276 C 50/50 5.79 MW 5.79 MW
944221 AF1-090 C Adder 1.9 MW 1.62 MW
944222 AF1-090 E Adder 8.92 MW 7.58 MW
945391 AF1-204 C 50/50 23.56 MW 23.56 MW
945392 AF1-204 E 50/50 70.69 MW 70.69 MW
963831 AG1-236 C Adder 1.44 MW 1.23 MW
963832 AG1-236 E Adder 9.66 MW 8.21 MW
963841 AG1-237 C 50/50 6.44 MW 6.44 MW
963842 AG1-237 E 50/50 43.1 MW 43.1 MW
944201 AF1-088 FTIR 50/50 115.78 MW 115.78 MW
957141 AF2-008 FTIR 50/50 57.89 MW 57.89 MW
965913 AG1-460 BT Adder 0.01 MW 0.01 MW
956282 J1115 G External Queue 16.94 MW 16.94 MW
990057 J1201 External Queue 0.57 MW 0.57 MW
990272 J1263 G External Queue 8.69 MW 8.69 MW
990672 J1360 External Queue 41.71 MW 41.71 MW
990857 J1408 External Queue 5.8 MW 5.8 MW
992572 J1022 External Queue 19.79 MW 19.79 MW

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P7-1_#11014___SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 102.18 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1403.98 MVA
MW Contribution: 122.92 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P7-1_#11014___SRT-A-1
CONTINGENCY 'AEP_P7-1_#11014___SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 247712 CKT 1   /*05DEQUIN     345.0 - 05SULLIVAN   345.0
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 103.23 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1418.36 MVA
MW Contribution: 123.77 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
942111 AE2-223 C Adder 1.14 MW 0.97 MW
942112 AE2-223 E Adder 7.64 MW 6.49 MW
959611 AF2-252 C Adder 1.51 MW 1.28 MW
959612 AF2-252 E Adder 2.27 MW 1.93 MW
960611 AF2-352 C Adder 1.51 MW 1.28 MW
960612 AF2-352 E Adder 2.27 MW 1.93 MW
243443 05RKG2 Adder 44.43 MW 37.76 MW
957382 AF2-032 E Adder 0.17 MW 0.15 MW
941731 AE2-173 C Adder 3.66 MW 3.11 MW
942601 AE2-276 C 50/50 6.15 MW 6.15 MW
944221 AF1-090 C Adder 2.35 MW 2.0 MW
944222 AF1-090 E Adder 11.02 MW 9.37 MW
945391 AF1-204 C 50/50 26.96 MW 26.96 MW
945392 AF1-204 E 50/50 80.89 MW 80.89 MW
963831 AG1-236 C Adder 1.73 MW 1.47 MW
963832 AG1-236 E Adder 11.55 MW 9.81 MW
963841 AG1-237 C 50/50 11.0 MW 11.0 MW
963842 AG1-237 E 50/50 73.59 MW 73.59 MW
944201 AF1-088 FTIR 50/50 122.92 MW 122.92 MW
957141 AF2-008 FTIR 50/50 61.46 MW 61.46 MW
965913 AG1-460 BT Adder 0.01 MW 0.01 MW
956282 J1115 G External Queue 18.98 MW 18.98 MW
990057 J1201 External Queue 0.66 MW 0.66 MW
990272 J1263 G External Queue 10.54 MW 10.54 MW
990352 J1289 External Queue 11.05 MW 11.05 MW
990672 J1360 External Queue 47.28 MW 47.28 MW
990857 J1408 External Queue 6.52 MW 6.52 MW
992572 J1022 External Queue 22.29 MW 22.29 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DEI 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
AEP_P1-2_#672_1713_SRT-A-1
CONTINGENCY 'AEP_P1-2_#672_1713_SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Single AC 101.15 % 1374.0 B 1389.74 107.05

Details for 05EUGENE-08CAYSUB 345.0 kV Ckt 1 line l/o AEP_P1-2_#672_1713_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DEI
Facility Description:
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line
243221 to 249504 ckt 1
Contingency Name:
AEP_P1-2_#672_1713_SRT-A-1
CONTINGENCY 'AEP_P1-2_#672_1713_SRT-A-1'
 OPEN BRANCH FROM BUS 243217 TO BUS 963840 CKT 1   /*05DEQUIN     345.0 - AG1-237 TP   345.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 101.15 %
Rating: 1374.0 MVA
Rating Type: B
MVA to Mitigate: 1389.74 MVA
MW Contribution: 107.05 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
274853 TWINGROVE;U1 80/20 0.65 MW 0.65 MW
274854 TWINGROVE;U2 80/20 0.67 MW 0.67 MW
274863 CAYUGA RI;1U 80/20 0.29 MW 0.29 MW
274864 CAYUGA RI;2U 80/20 0.29 MW 0.29 MW
274880 RADFORD R;1U 80/20 1.05 MW 1.05 MW
276615 W2-048 GEN 80/20 1.43 MW 1.43 MW
276621 X2-022 GEN 80/20 4.07 MW 4.07 MW
290261 S-027 E 80/20 3.06 MW 3.06 MW
290265 S-028 E 80/20 3.04 MW 3.04 MW
917502 Z2-087 E 80/20 3.17 MW 3.17 MW
942111 AE2-223 C 80/20 1.14 MW 1.14 MW
942112 AE2-223 E 80/20 7.61 MW 7.61 MW
959611 AF2-252 C 80/20 1.5 MW 1.5 MW
959612 AF2-252 E 80/20 2.25 MW 2.25 MW
960611 AF2-352 C 80/20 1.5 MW 1.5 MW
960612 AF2-352 E 80/20 2.25 MW 2.25 MW
243443 05RKG2 80/20 39.19 MW 39.19 MW
274890 CAYUG;1U E 80/20 1.53 MW 1.53 MW
274891 CAYUG;2U E 80/20 1.53 MW 1.53 MW
925771 AC1-053 C 80/20 0.94 MW 0.94 MW
925772 AC1-053 E 80/20 6.27 MW 6.27 MW
957382 AF2-032 E 80/20 0.17 MW 0.17 MW
270681 BRIGHTSTK; R 80/20 0.47 MW 0.47 MW
276174 W4-005 E 80/20 6.0 MW 6.0 MW
276655 AB2-047 C1 80/20 0.3 MW 0.3 MW
276656 AB2-047 C2 80/20 0.3 MW 0.3 MW
276668 AB2-070 C 80/20 0.59 MW 0.59 MW
924048 AB2-047 E1 80/20 1.97 MW 1.97 MW
924049 AB2-047 E2 80/20 2.0 MW 2.0 MW
924266 AB2-070 E 80/20 3.59 MW 3.59 MW
935141 AD1-148 C 80/20 1.28 MW 1.28 MW
941731 AE2-173 C 80/20 3.64 MW 3.64 MW
942601 AE2-276 C 80/20 5.35 MW 5.35 MW
944221 AF1-090 C 80/20 2.25 MW 2.25 MW
944222 AF1-090 E 80/20 10.54 MW 10.54 MW
945391 AF1-204 C 80/20 26.66 MW 26.66 MW
945392 AF1-204 E 80/20 79.99 MW 79.99 MW
960261 AF2-317 C 80/20 0.55 MW 0.55 MW
963831 AG1-236 C 80/20 1.69 MW 1.69 MW
963832 AG1-236 E 80/20 11.29 MW 11.29 MW
963841 AG1-237 C 80/20 10.87 MW 10.87 MW
963842 AG1-237 E 80/20 72.77 MW 72.77 MW
965331 AG1-398 C 80/20 0.27 MW 0.27 MW
944201 AF1-088 FTIR 80/20 107.05 MW 107.05 MW
957141 AF2-008 FTIR 80/20 53.52 MW 53.52 MW
961163 AF2-407 BT 80/20 22.03 MW 22.03 MW
961173 AF2-408 BT 80/20 5.2 MW 5.2 MW
964353 AG1-297 BT 80/20 19.6 MW 19.6 MW
965913 AG1-460 BT 80/20 0.01 MW 0.01 MW
956282 J1115 G External Queue 18.62 MW 18.62 MW
990057 J1201 External Queue 0.61 MW 0.61 MW
990272 J1263 G External Queue 9.52 MW 9.52 MW
990352 J1289 External Queue 10.74 MW 10.74 MW
990857 J1408 External Queue 6.31 MW 6.31 MW

Light Load Potential Congestion due to Local Energy Deliverability

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
OP AC 134.08 % 1180.0 B 1582.1 98.43
CE AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line
939400 to 934720 ckt 1
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
OP AC 127.51 % 1528.0 B 1948.4 53.43
CE LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line
270704 to 939400 ckt 1
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
OP AC 118.04 % 1528.0 B 1803.7 53.43
CE PONTIAC ; B-LORETTO ; B 345.0 kV Ckt 1 line
270852 to 270704 ckt 1
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
OP AC 105.2 % 1528.0 B 1607.53 55.19

Details for 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 134.08 %
Rating: 1180.0 MVA
Rating Type: B
MVA to Mitigate: 1582.1 MVA
MW Contribution: 98.43 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943031 AE2-326 C 50/50 6.34 MW 6.34 MW
943032 AE2-326 E 50/50 4.23 MW 4.23 MW
242892 05AMG2 50/50 56.42 MW 56.42 MW
242893 05AMG3 50/50 92.58 MW 92.58 MW
243443 05RKG2 Adder 78.36 MW 66.61 MW
274675 JOLIET 29;7U Adder 30.54 MW 25.96 MW
274676 JOLIET 29;8U Adder 30.54 MW 25.96 MW
944971 AF1-162 C 50/50 7.93 MW 7.93 MW
944972 AF1-162 E 50/50 5.29 MW 5.29 MW
945382 AF1-203 E 50/50 2.17 MW 2.17 MW
964782 AG1-341 E 50/50 11.47 MW 11.47 MW
223403 AG1-063 C Adder -0.07 MW -0.06 MW
940351 AE2-019 C Adder -15.78 MW -13.41 MW
965411 AG1-406 C 50/50 2.46 MW 2.46 MW
966391 AG1-508 C 50/50 1.47 MW 1.47 MW
966392 AG1-508 E 50/50 8.51 MW 8.51 MW
242899 05CRG1H 50/50 8.49 MW 8.49 MW
242900 05CRG1L 50/50 7.11 MW 7.11 MW
242901 05CRG2H 50/50 8.55 MW 8.55 MW
242902 05CRG2L 50/50 7.17 MW 7.17 MW
243758 05MIDDLECR 50/50 0.26 MW 0.26 MW
270167 AD2-205 E 50/50 0.79 MW 0.79 MW
940353 AE2-019 BT 50/50 15.78 MW 15.78 MW
944201 AF1-088 FTIR Adder 115.8 MW 98.43 MW
957193 AF2-013 BT 50/50 11.36 MW 11.36 MW
962183 AG1-063 BAT 50/50 0.26 MW 0.26 MW
962553 AG1-104 BT 50/50 30.68 MW 30.68 MW
963033 AG1-152 BT 50/50 13.61 MW 13.61 MW
963053 AG1-154 BT 50/50 5.97 MW 5.97 MW
963693 AG1-221 BT 50/50 6.49 MW 6.49 MW
966143 AG1-483 BAT 50/50 55.8 MW 55.8 MW
966253 AG1-494 BT 50/50 12.02 MW 12.02 MW

Details for AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L8014__R-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CE
Facility Description:
AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line
939400 to 934720 ckt 1
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 127.51 %
Rating: 1528.0 MVA
Rating Type: B
MVA to Mitigate: 1948.4 MVA
MW Contribution: 53.43 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: CE
Facility Description:
AE1-172 TP-AD1-100 TAP 345.0 kV Ckt 1 line
939400 to 934720 ckt 1
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 127.33 %
Rating: 1528.0 MVA
Rating Type: B
MVA to Mitigate: 1945.55 MVA
MW Contribution: 53.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
274853 TWINGROVE;U1 50/50 3.58 MW 3.58 MW
274854 TWINGROVE;U2 50/50 3.68 MW 3.68 MW
274863 CAYUGA RI;1U 50/50 3.48 MW 3.48 MW
274864 CAYUGA RI;2U 50/50 3.48 MW 3.48 MW
274880 RADFORD R;1U 50/50 3.28 MW 3.28 MW
276615 W2-048 GEN 50/50 3.98 MW 3.98 MW
276621 X2-022 GEN 50/50 11.31 MW 11.31 MW
290261 S-027 E 50/50 16.77 MW 16.77 MW
290265 S-028 E 50/50 16.67 MW 16.67 MW
917502 Z2-087 E 50/50 19.25 MW 19.25 MW
942111 AE2-223 C 50/50 6.9 MW 6.9 MW
942112 AE2-223 E 50/50 46.2 MW 46.2 MW
959611 AF2-252 C 50/50 8.22 MW 8.22 MW
959612 AF2-252 E 50/50 12.34 MW 12.34 MW
960611 AF2-352 C 50/50 8.22 MW 8.22 MW
960612 AF2-352 E 50/50 12.34 MW 12.34 MW
966091 AG1-478 C Adder -0.37 MW -0.32 MW
966431 AG1-512 C Adder -1.42 MW -1.21 MW
274674 JOLIET 9 ;6U Adder -10.92 MW -9.28 MW
274675 JOLIET 29;7U Adder -26.59 MW -22.61 MW
274890 CAYUG;1U E 50/50 18.55 MW 18.55 MW
274891 CAYUG;2U E 50/50 18.55 MW 18.55 MW
925771 AC1-053 C 50/50 2.74 MW 2.74 MW
925772 AC1-053 E 50/50 18.35 MW 18.35 MW
939401 AE1-172 C 50/50 24.45 MW 24.45 MW
939402 AE1-172 E 50/50 114.49 MW 114.49 MW
957382 AF2-032 E 50/50 0.41 MW 0.41 MW
270681 BRIGHTSTK; R 50/50 2.88 MW 2.88 MW
276174 W4-005 E 50/50 18.71 MW 18.71 MW
276655 AB2-047 C1 50/50 1.8 MW 1.8 MW
276656 AB2-047 C2 50/50 1.8 MW 1.8 MW
276668 AB2-070 C 50/50 1.77 MW 1.77 MW
924048 AB2-047 E1 50/50 11.94 MW 11.94 MW
924049 AB2-047 E2 50/50 12.13 MW 12.13 MW
924266 AB2-070 E 50/50 10.73 MW 10.73 MW
935141 AD1-148 C 50/50 3.56 MW 3.56 MW
941731 AE2-173 C 50/50 22.13 MW 22.13 MW
942601 AE2-276 C Adder 2.67 MW 2.27 MW
944221 AF1-090 C 50/50 4.92 MW 4.92 MW
944222 AF1-090 E 50/50 23.06 MW 23.06 MW
945391 AF1-204 C Adder 3.28 MW 2.79 MW
945392 AF1-204 E Adder 9.83 MW 8.36 MW
960141 AF2-305_AG1- 50/50 1.0 MW 1.0 MW
960261 AF2-317 C 50/50 1.54 MW 1.54 MW
963831 AG1-236 C 50/50 4.93 MW 4.93 MW
963832 AG1-236 E 50/50 33.02 MW 33.02 MW
965331 AG1-398 C 50/50 0.8 MW 0.8 MW
944201 AF1-088 FTIR Adder 62.86 MW 53.43 MW
957141 AF2-008 FTIR Adder 31.43 MW 26.71 MW
965913 AG1-460 BT 50/50 0.02 MW 0.02 MW
956282 J1115 G External Queue 47.52 MW 47.52 MW
990057 J1201 External Queue 1.21 MW 1.21 MW
990272 J1263 G External Queue 10.01 MW 10.01 MW
990352 J1289 External Queue 23.14 MW 23.14 MW
990672 J1360 External Queue 55.96 MW 55.96 MW
990857 J1408 External Queue 15.21 MW 15.21 MW
992572 J1022 External Queue 29.76 MW 29.76 MW

Details for LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L8014__R-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CE
Facility Description:
LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line
270704 to 939400 ckt 1
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 118.04 %
Rating: 1528.0 MVA
Rating Type: B
MVA to Mitigate: 1803.7 MVA
MW Contribution: 53.43 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: CE
Facility Description:
LORETTO ; B-AE1-172 TP 345.0 kV Ckt 1 line
270704 to 939400 ckt 1
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 117.83 %
Rating: 1528.0 MVA
Rating Type: B
MVA to Mitigate: 1800.51 MVA
MW Contribution: 53.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
274853 TWINGROVE;U1 50/50 3.58 MW 3.58 MW
274854 TWINGROVE;U2 50/50 3.68 MW 3.68 MW
274863 CAYUGA RI;1U 50/50 3.48 MW 3.48 MW
274864 CAYUGA RI;2U 50/50 3.48 MW 3.48 MW
274880 RADFORD R;1U 50/50 3.28 MW 3.28 MW
276615 W2-048 GEN 50/50 3.98 MW 3.98 MW
276621 X2-022 GEN 50/50 11.31 MW 11.31 MW
290261 S-027 E 50/50 16.77 MW 16.77 MW
290265 S-028 E 50/50 16.67 MW 16.67 MW
917502 Z2-087 E 50/50 19.25 MW 19.25 MW
942111 AE2-223 C 50/50 6.9 MW 6.9 MW
942112 AE2-223 E 50/50 46.2 MW 46.2 MW
959611 AF2-252 C 50/50 8.22 MW 8.22 MW
959612 AF2-252 E 50/50 12.34 MW 12.34 MW
960611 AF2-352 C 50/50 8.22 MW 8.22 MW
960612 AF2-352 E 50/50 12.34 MW 12.34 MW
966091 AG1-478 C Adder -0.37 MW -0.32 MW
966431 AG1-512 C Adder -1.42 MW -1.21 MW
274674 JOLIET 9 ;6U Adder -10.92 MW -9.28 MW
274675 JOLIET 29;7U Adder -26.59 MW -22.61 MW
274890 CAYUG;1U E 50/50 18.55 MW 18.55 MW
274891 CAYUG;2U E 50/50 18.55 MW 18.55 MW
925771 AC1-053 C 50/50 2.74 MW 2.74 MW
925772 AC1-053 E 50/50 18.35 MW 18.35 MW
957382 AF2-032 E 50/50 0.41 MW 0.41 MW
270681 BRIGHTSTK; R 50/50 2.88 MW 2.88 MW
276174 W4-005 E 50/50 18.71 MW 18.71 MW
276655 AB2-047 C1 50/50 1.8 MW 1.8 MW
276656 AB2-047 C2 50/50 1.8 MW 1.8 MW
276668 AB2-070 C 50/50 1.77 MW 1.77 MW
924048 AB2-047 E1 50/50 11.94 MW 11.94 MW
924049 AB2-047 E2 50/50 12.13 MW 12.13 MW
924266 AB2-070 E 50/50 10.73 MW 10.73 MW
935141 AD1-148 C 50/50 3.56 MW 3.56 MW
941731 AE2-173 C 50/50 22.13 MW 22.13 MW
942601 AE2-276 C Adder 2.67 MW 2.27 MW
944221 AF1-090 C 50/50 4.92 MW 4.92 MW
944222 AF1-090 E 50/50 23.06 MW 23.06 MW
945391 AF1-204 C Adder 3.28 MW 2.79 MW
945392 AF1-204 E Adder 9.83 MW 8.36 MW
960141 AF2-305_AG1- 50/50 1.0 MW 1.0 MW
960261 AF2-317 C 50/50 1.54 MW 1.54 MW
963831 AG1-236 C 50/50 4.93 MW 4.93 MW
963832 AG1-236 E 50/50 33.02 MW 33.02 MW
965331 AG1-398 C 50/50 0.8 MW 0.8 MW
944201 AF1-088 FTIR Adder 62.86 MW 53.43 MW
957141 AF2-008 FTIR Adder 31.43 MW 26.71 MW
965913 AG1-460 BT 50/50 0.02 MW 0.02 MW
956282 J1115 G External Queue 47.52 MW 47.52 MW
990057 J1201 External Queue 1.21 MW 1.21 MW
990272 J1263 G External Queue 10.01 MW 10.01 MW
990352 J1289 External Queue 23.14 MW 23.14 MW
990672 J1360 External Queue 55.96 MW 55.96 MW
990857 J1408 External Queue 15.21 MW 15.21 MW
992572 J1022 External Queue 29.76 MW 29.76 MW

Details for PONTIAC ; B-LORETTO ; B 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L8014__R-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CE
Facility Description:
PONTIAC ; B-LORETTO ; B 345.0 kV Ckt 1 line
270852 to 270704 ckt 1
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.2 %
Rating: 1528.0 MVA
Rating Type: B
MVA to Mitigate: 1607.53 MVA
MW Contribution: 55.19 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: CE
Facility Description:
PONTIAC ; B-LORETTO ; B 345.0 kV Ckt 1 line
270852 to 270704 ckt 1
Contingency Name:
COMED_P1-2_345-L8014__R-S_SRT-A
CONTINGENCY 'COMED_P1-2_345-L8014__R-S_SRT-A'
 TRIP BRANCH FROM BUS 270853 TO BUS 270717 CKT 1   /*PONTIAC  ; R 345.0 - DRESDEN  ; R 345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.06 %
Rating: 1528.0 MVA
Rating Type: B
MVA to Mitigate: 1605.28 MVA
MW Contribution: 55.33 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
274853 TWINGROVE;U1 50/50 3.59 MW 3.59 MW
274854 TWINGROVE;U2 50/50 3.7 MW 3.7 MW
274880 RADFORD R;1U 50/50 3.3 MW 3.3 MW
276615 W2-048 GEN 50/50 4.0 MW 4.0 MW
276621 X2-022 GEN 50/50 11.4 MW 11.4 MW
290261 S-027 E 50/50 16.85 MW 16.85 MW
290265 S-028 E 50/50 16.74 MW 16.74 MW
917502 Z2-087 E 50/50 19.33 MW 19.33 MW
942111 AE2-223 C 50/50 6.93 MW 6.93 MW
942112 AE2-223 E 50/50 46.39 MW 46.39 MW
959611 AF2-252 C 50/50 8.26 MW 8.26 MW
959612 AF2-252 E 50/50 12.39 MW 12.39 MW
960611 AF2-352 C 50/50 8.26 MW 8.26 MW
960612 AF2-352 E 50/50 12.39 MW 12.39 MW
966091 AG1-478 C Adder -0.37 MW -0.31 MW
966431 AG1-512 C Adder -1.4 MW -1.19 MW
274674 JOLIET 9 ;6U Adder -10.7 MW -9.09 MW
274675 JOLIET 29;7U Adder -26.01 MW -22.11 MW
925771 AC1-053 C 50/50 2.76 MW 2.76 MW
925772 AC1-053 E 50/50 18.47 MW 18.47 MW
957382 AF2-032 E 50/50 0.41 MW 0.41 MW
270681 BRIGHTSTK; R 50/50 2.89 MW 2.89 MW
276174 W4-005 E 50/50 18.83 MW 18.83 MW
276655 AB2-047 C1 50/50 1.8 MW 1.8 MW
276656 AB2-047 C2 50/50 1.8 MW 1.8 MW
276668 AB2-070 C 50/50 1.78 MW 1.78 MW
924048 AB2-047 E1 50/50 11.99 MW 11.99 MW
924049 AB2-047 E2 50/50 12.17 MW 12.17 MW
924266 AB2-070 E 50/50 10.8 MW 10.8 MW
935141 AD1-148 C 50/50 3.58 MW 3.58 MW
941731 AE2-173 C 50/50 22.22 MW 22.22 MW
942601 AE2-276 C Adder 2.76 MW 2.35 MW
944221 AF1-090 C 50/50 4.97 MW 4.97 MW
944222 AF1-090 E 50/50 23.29 MW 23.29 MW
945391 AF1-204 C Adder 3.37 MW 2.86 MW
945392 AF1-204 E Adder 10.1 MW 8.59 MW
960141 AF2-305_AG1- 50/50 1.01 MW 1.01 MW
960261 AF2-317 C 50/50 1.55 MW 1.55 MW
963831 AG1-236 C 50/50 4.97 MW 4.97 MW
963832 AG1-236 E 50/50 33.25 MW 33.25 MW
965331 AG1-398 C 50/50 0.81 MW 0.81 MW
944201 AF1-088 FTIR Adder 64.93 MW 55.19 MW
957141 AF2-008 FTIR Adder 32.46 MW 27.59 MW
965913 AG1-460 BT 50/50 0.02 MW 0.02 MW
956282 J1115 G External Queue 47.52 MW 47.52 MW
990057 J1201 External Queue 1.21 MW 1.21 MW
990272 J1263 G External Queue 10.01 MW 10.01 MW
990352 J1289 External Queue 23.14 MW 23.14 MW
990672 J1360 External Queue 55.96 MW 55.96 MW
990857 J1408 External Queue 15.21 MW 15.21 MW
992572 J1022 External Queue 29.76 MW 29.76 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios:

 

  • Scenario 1 - TC1 Project Impacts;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

 

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1. The result is detailed in the following table:

Short Circuit Analysis

 

 

 

 

 

 

 

Bus Name

Breaker

Interrupting Capability (Amps)

Duty Percent TC1 Phase 3 - Scenario 2 Topology Upgrades (%)

Duty Percent TC1 Phase 3 - Scenario 2 No Topology Upgrades (%)

Duty Percent Difference (%)

Reinforcement

Projected In Service Date (ISD)

GOODING 345 kV

270769

57267

100.77%

98.71%

2.06%

s3011

12/31/2028

 

 

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests AF1-088 and AF2-008 in PJM Transition Cycle 1, Cluster 52 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 52 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 52 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 52 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 52 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 769 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing);

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Three-phase faults with loss of multiple-circuit tower line,

       f)       Three-phase Faults with Normal Clearing Time, Prior Outage of Rockport – Jefferson 765 kV Line,

       g)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Rockport 765kV,

       h)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan T-1 765-345 kV Transformer,

       i)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan T-2 765-345 kV Transformer,

       j)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Snyder 345 kV Line,

       k)       Three-phase Faults with Normal Clearing Time, Prior Outage of Snyder – Casey 345 kV Line,

       l)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Petersburg 345 kV Line,

       m)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Eugene 345 kV Line,

       n)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Dequine 345 kV Line,

       o)       Three-phase Faults with Normal Clearing Time, Prior Outage of Eugene – Cayuga 345 kV Line,

       p)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Dequine/Eugene Double-Circuit 345 kV Line.

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

The outages of the circuits (P6 contingencies) were provided to PJM by the Transmission Owner (AEP) as potential generation curtailment scenarios.  PJM has performed analysis of these contingencies in the study. These scenarios may result in operational restrictions to the project under study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

One of the Rockport Unit has been taken out when fault has been applied to Rockport to Jefferson 765 kV circuit .

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 52 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 52 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

       e)       Since no tripping instances (protection schemes) were implemented, compliance with PRC-024 could not be tested. This does not cause instability in the system.

       f)       After the fault clears, the system shows an inverted power transient of up to 1600 MW per pole. This does not cause instability in the system.

       g)       For the scenario A: Prior Outage of Rockport – Jefferson 765 kV Line, one of the units at Rockport unit has been switched off in the basecase. For several contingencies, post fault bus voltage dropped below 0.95 per unit for Petersburg and Dequine substation.

       h)       For the scenario F: Prior Outage of Snyder – Casey 345 kV Line, P6F.55 contingency, leading to the tripping of Petersburg G2 unit.

       i)       For the scenario E, F, G, H, I, J, K: Post fault bus voltage for Rockport bus went above 1.05 for Contingencies P6.12 and P6.50.

 

A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 52 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

52

AF1-088

Original HVDC facility

AEP

1000

1000

1000

Sullivan 345 kV

AF2-008

Additional HVDC unit

AEP

2000

1000

500

Sullivan 345 kV

 

 

Reactive Power Analysis

The reactive power capability of AF1-088 meets the 0.95 leading and lagging PF requirement

Steady-State Voltage Analysis

Steady State Voltage Analysis complete, no voltage issues found.  N-1-1 Thermal and Voltage Analysis Complete, no issues found.

AF1-088

  • 1000 MW Firm Injection
  • 1000 MW NonFirm Withdrawal

 

AF2-008 Uprate

  • 500 MW Firm Injection (total between both projects of Firm Injection: 1500 MW)
  • 500 MW NonFirm Injection (total between both project of Firm+NonFirm Injection 2000 MW)

 

The following tests were performed:

  • Voltage Summer Peak (N-1)
    • Injection
      • 2,000 MW (AF1-088+AF2-008) Injection for Common Mode Only (Non Firm)
      • 1,500 MW (AF1-088+AF2-008) Injection at SP - Single & Common Mode (Firm)
    • Withdrawal
      • 1,000 MW (AF1-088+AF2-008) Common Mode Withdrawal only (Non Firm)
  • Voltage Light Load (N-1)
    • Injection
      • 2,000 MW (AF1-088+AF2-008) Injection for Single Mode Only (Non Firm)
    • Withdrawal
      • 1,000 MW (AF1-088+AF2-008) Common Mode Withdrawal only (Non Firm)
  • Thermal and Voltage Summer Peak (N-1-1)
    • Injection
      • 1,500 MW (AF1-088+AF2-008) Injection Singles (Firm)

 

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA1-018 Powerton-Goodings Grove In Service
AA2-123 Marengo 34kV In Service
AB1-006 Meadow Lake 345kV In Service
AB1-087 Sullivan 345kV #1 Under Construction
AB1-088 Sullivan 345kV #2 Engineering & Procurement
AB1-089 Byron-Wayne 345kV #1 Withdrawn
AB2-047 Brokaw-Pontiac Midpoint In Service
AB2-070 Mt. Pulaski-Brokaw In Service
AC1-033 Kewanee 138 kV In Service
AC1-053 Lanesville-Brokaw Under Construction
AC1-168 Kewanee-Streator Suspended
AC1-214 Crescent Ridge In Service
AC2-157 Sullivan 345 kV Under Construction
AC2-176 Jay 138 kV In Service
AD1-013 Twombly Road 138kV Engineering & Procurement
AD1-031 Kewanee - E.D. Edwards 138 kV Withdrawn
AD1-100 Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV Under Construction
AD1-148 Brokaw-Lanesville In Service
AD2-038 Powerton-Nevada 345 kV Under Construction
AD2-047 Davis Creek 138 kV Suspended
AD2-066 Mazon-Crescent Ridge 138 kV Engineering & Procurement
AD2-100 Kincaid-Pana 345 kV Suspended
AD2-131 Kincaid-Pana 345kV Suspended
AD2-134 Shady Oaks Partially in Service - Under Construction
AD2-172 Lena 138kV In Service
AD2-205 Byllesby 69 kV In Service
AE1-113 Mole Creek 345 kV Engineering & Procurement
AE1-114 Maryland-Lancaster 138 kV Active
AE1-134 Nelson 345 kV In Service
AE1-163 Powerton-Nevada 345 kV Engineering & Procurement
AE1-172 Loretto-Wilton Center Active
AE1-205 McLean 345 kV Engineering & Procurement
AE1-209 Desoto 345 kV Suspended
AE1-210 Desoto 345 kV Suspended
AE2-019 New Road 230 kV Engineering & Procurement
AE2-035 Lena 138 kV In Service
AE2-172 Mississinewa-Gaston 138 kV Suspended
AE2-173 McLean 345 kV Active
AE2-223 McLean 345 kV Active
AE2-255 Molecreek 345 kV Engineering & Procurement
AE2-261 Kincaid-Pana 345 kV Active
AE2-276 Sullivan 345kV Engineering & Procurement
AE2-281 Powerton-Nevada 345 kV Engineering & Procurement
AE2-321 Belvidere-Marengo 138 kV Active
AE2-326 Jacksons Ferry 138 kV Engineering & Procurement
AF1-045 Cedarville-Ford 138 kV Suspended
AF1-090 Kincaid-Pana Engineering & Procurement
AF1-092 Huntington Jct. 138 kV Suspended
AF1-118 Sorenson-Desoto 345 kV Engineering & Procurement
AF1-119 Keystone-Desoto 345 kV Engineering & Procurement
AF1-162 Inez 138 kV Engineering & Procurement
AF1-202 Keystone-Desoto 345 kV Under Construction
AF1-203 Patton Rd-Summer Shade 69 kV In Service
AF1-204 Eugene 345 kV Active
AF1-280 Nelson-Lee County Active
AF1-296 Garden Plain 138 kV Active
AF1-322 Meadow Lake 345 kV Engineering & Procurement
AF1-331 Twombley Road Engineering & Procurement
AF2-008 Sullivan 345 kV Active
AF2-013 Arnold's Corner-Dahlgren 230 kV Engineering & Procurement
AF2-032 Kincaid 345 kV Engineering & Procurement
AF2-041 Nelson-Electric Junction 345 kV Active
AF2-069 Crescent Ridge 138 kV Active
AF2-078 Reynolds-Olive #1 345 kV Engineering & Procurement
AF2-142 Nevada 345 kV Active
AF2-143 Powerton-Nevada 345 kV Active
AF2-177 Sorenson-DeSoto #2 345 kV Active
AF2-182 Nelson-Lee County 345 kV II Active
AF2-199 Nelson-Electric Junction 345 kV Active
AF2-200 Nelson-Electric Junction 345 kV Active
AF2-225 McLean 345 kV Active
AF2-226 Katydid Road 345 kV Active
AF2-252 Blue Mound 345 kV Engineering & Procurement
AF2-305 Brokaw-Lanesville 345 kV In Service
AF2-317 Hill Topper 345 kV In Service
AF2-319 Katydid Road 345 kV Active
AF2-349 SILVER LAKE- CHERRY VALLEY 345 KV Active
AF2-352 Blue Mound 345 kV Engineering & Procurement
AF2-366 Crego Rd 138 kV Engineering & Procurement
AF2-370 Delaware-Royerton 138 kV Active
AF2-388 Keystone-Desoto 345 kV Active
AF2-392 Nelson-Dixon 138 kV Active
AF2-407 Fall Creek 345 kV Active
AF2-408 Fall Creek 138 kV Engineering & Procurement
AF2-441 Burnham 138kV Active
AG1-017 Jay 138 kV Under Construction
AG1-044 Whiteside County In Service
AG1-063 Fairhaven 13,8 kV In Service
AG1-104 Waugh Chapel 230 kV Engineering & Procurement
AG1-118 Sugar Grove-Waterman 138kV Active
AG1-127 Crego Rd 138 kV Active
AG1-152 Remington CT 230 kV Engineering & Procurement
AG1-154 Ladysmith CT 230 kV Active
AG1-207 Vandalia 69 kV Engineering & Procurement
AG1-221 Poland Rd-Runway DP 230 kV Under Construction
AG1-226 Dequine-Eugene 345 kV Active
AG1-236 Lanesville-Brokaw 345 kV Active
AG1-237 Dequine-Eugene 345 kV Engineering & Procurement
AG1-297 Hanna-Tanners Creek 345 kV Active
AG1-324 Jay-Desoto 138 kV Engineering & Procurement
AG1-341 Summer Shade 161 kV Active
AG1-374 Blue Mound 345 kV Active
AG1-398 Brokaw-Lanesville 345 kV In Service
AG1-406 Walnut Grove-Asahi 69 kV Active
AG1-414 Mississinewa 138 kV Engineering & Procurement
AG1-433 Keystone-DeSoto 345 kV Active
AG1-460 Kincaid-Pana 345 kV Active
AG1-462 Cordova 345 kV Active
AG1-478 Wilmington 34.5 kV Engineering & Procurement
AG1-483 Dickerson 230 kV Engineering & Procurement
AG1-494 Boxwood-Riverville 138 kV Active
AG1-508 Point Lookout 69 kV Engineering & Procurement
AG1-512 University Park North 345 kV Withdrawn
AG1-553 Cordova 345 kV Active
AG1-555 Dequine 345 kV Engineering & Procurement
V3-007 Desoto-Tanners Creek #1 345kV In Service
W2-048 Brokaw-Lanesville In Service
W4-005 Blue Mound-Latham In Service
X2-022 Brokaw-Lanesville In Service
Z1-073 Mendota Hills In Service
Z2-087 Pontiac MidPoint-Brokaw 345kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
AF1-088 System Reinforcements:
TO Trans Owner ID Title Category Allocated Cost ($USD)
DEI DEI_TC1_16079 Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. New rating 2430 MVA. Cost Allocated $1,925,781
Grand Total: $1,925,781

System Reinforcement
Type
Load Flow
TO
DEI
RTEP ID / TO ID
(Pending) / DEI_TC1_16079
Title
Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. New rating 2430 MVA.
Description
Reconductor Eugene to Cayuga 345kV #1 line with 4000A conductor. New rating 2430 MVA.
Total Cost ($USD)
$12,000,000
Allocated Cost ($USD)
$1,925,781
Time Estimate
8 Months

Contributor

Facility Contingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-223 McLean 345kV (ComEd): This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.3 MW 1.4% $173,898
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
26.2 MW 3.4% $403,577
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
125.2 MW 16.0% $1,925,781
AF1-204 135.4 MW 17.4% $2,083,172
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
125.2 MW 16.0% $1,925,781
AF2-225 McLean 345kV (ComEd): This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-223, AF2-225
11.3 MW 1.4% $173,898
AF2-407 32.4 MW 4.2% $498,894
AG1-226 238.9 MW 30.6% $3,675,742
AG1-236 17.0 MW 2.2% $261,016
AG1-297 31.1 MW 4.0% $478,742
AG1-374 23.3 MW 3.0% $359,010
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.6 MW 0.3% $40,490

New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.

 

Impacted Facility Transmission Owner Reinforcement Cost Cost Allocated to AF1-088 Scenarios
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
DEI DEI: Rebuild 1 mile of Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$1,500,000 $94,633
  • NIPSCO LPC
  • Cayuga 345.0 - Nucor 345.0 CKT 1
DEI MTEP Proj ID 50718: Cayuga Gen Yard to Nucor
MTEP Proj ID 50718: Rebuild with 954 ZTACSR @ 200C
from
Cayuga Gen Yard to Nucor. Upgrade terminal
equipment
accordingly.
$0 $0
  • Contingent
  • Argos 69.0 - Plymouth 69.0 CKT 1
NIPS Rebuild Argos - Plymouth 69 kV line
Rebuild line, approx 10 miles
$12,654,948 $780,553
  • NIPSCO LPC
  • Argos 69.0 - Rochester TP 69.0 CKT 1
NIPS Rebuild Argos - Rochester TP 69 kV
Rebuild line, approx 3.2 miles
$4,049,583 $255,481
  • NIPSCO LPC
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS NIPSCO: Rebuild line (.3miles)Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$0 $0
  • NIPSCO LPC
  • CAP BANK 230.0 - Gallagher 230.0 CKT 0
DEI Install 144 MVAR cap bank at Gallagher sub.
Install 144 MVAR cap bank at Gallagher sub.
$3,000,000 $614,206
  • MISO Voltage
  • CAP BANK 138.0 - Shoals 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Shoals sub
Install 28.8 MVAR cap bank at Shoals sub
$3,000,000 $655,063
  • MISO Voltage
  • CAP BANK 138.0 - Avon East 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Avon East sub
Install 28.8 MVAR cap bank at Avon East sub
$3,000,000 $676,415
  • MISO Voltage
  • Morrison Ditch 345.0 - Reynolds 345.0 CKT 1
NIPS LRTP-16: Morrison Ditch – Reynolds – Burr Oak
Install single circuit 345kV transmission line
from the existing Morrison Ditch
Substation, to the existing Reynolds Substation,
to the existing Burr Oak
Substation, to the existing Leesburg Substation,
to the existing Hiple Substation.
$0 $0
  • Contingent
  • Greentown 765.0 - Sorenson 765.0 CKT 1
ITCT LRTP-33: Greentown - Sorenson - Lulu
Install single circuit 765kV transmission line
from the existing Greentown
Substation to the existing Sorenson Substation, to
the existing Lulu Substation.
$0 $0
  • Contingent
  • Petersburg 345.0 - Pike County 345.0 CKT 1
DEI LRTP-35: Southwest Indiana-Kentucky
Install double circuit 345kV transmission line
from the existing Petersburg
Substation to the new Pike County Substation.
Install single circuit 345kV
transmission line from the new Pike County
Substation to the existing Duff
Substation, to the existing Culley Substation, to
the existing Reid EHV Substation.
$0 $0
  • Contingent
  • Reynolds 765.0 - Reynolds 345.0 CKT 3
NIPS Reynold 765/345 kV xfmr MISO MTEP LRTP-40 Project
2nd 765/345kV Transformer. MISO MTEP LRTP-40
Project.
$0 $0
  • Contingent
  • Madison County 345.0 - Greensboro 345.0 CKT 1
DEI LRTP-36: Southeast Indiana
Install single circuit 345kV transmission line
from the new Madison County
Substation to the existing Greensboro Substation.
Install single circuit 138kV
transmission line from the existing Decatur County
Substation to the existing
Greensburg Substation. Install double circuit
138kV transmission line from the existing
Batesville Substation to the existing Hubbell
Substation, to the existing Greendale Substation,
to the existing Miami Fort Substation.
$0 $0
  • Contingent
  • Maywood 345.0 - Belleau 345.0 CKT 1
AMIL LRTP-37: Maywood - Belleau - MRPD - Sioux - Bugle
Install single circuit 345kV transmission line
from the existing Maywood Substation to the
existing Belleau Substation, to the new MRPD
Substation, to the existing Sioux Substation, from
the new MRPD Substation to the existing Bugle
Substation.
$0 $0
  • Contingent
  • Burr Oak 345.0 - Schahfer 345.0 CKT 1
NIPS LRTP-42: Burr Oak - Schahfer
Install single circuit 345kV transmission line
from the existing Burr Oak Substation to the
existing Schahfer Substation.
$0 $0
  • Contingent
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF1-088 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
AEP n9243.0 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Cost Allocated $84,156,895
ComEd n9195.0 Install a new 345 kV circuit breaker at Station 12 Dresden. Cost Allocated $1,411,158
AEP n6497.4 Replace line traps on the Jefferson - Rockport 765 kV line Cost Allocated $541,797
ComEd b3811.1 Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. Contingent $0 N/A
ComEd s3011 Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. Contingent $0 N/A
ComEd b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line Contingent $0 N/A
AEP b4000.251 Replace the wave trap and upgrade the relay at Cloverdale 765kV substation Contingent $0 N/A
AEP b4000.252 Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation Contingent $0 N/A
AEP b3788.1 Replace limiting station elements at Kyger Creek Contingent $0 N/A
OVEC b3788.2 Replace limiting station elements at Kyger Creek Contingent $0 N/A
AEP n7925.1 Reconductor ~0.41 miles of the Sullivan – West Casey (Ameren) line Contingent $0 N/A
AEP n5808 CON Upgrade_AEP: eliminate the Eugene stuck breaker contingency. (AMIL upgrade will not be required) Contingent $0 N/A
Grand Total: $86,109,850

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9243.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9243.0 / AEPSERG13
Title
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Description
At the Jefferson Station: • Expand the northeast corner of the station • Remove Circuit breaker C1 • Install one (1) new 765/345 kV transformer and associated equipment • Install one (1) new 765 kV circuit breaker with associated control relaying and breaker disconnect switches • Install one (1) new 345 kV circuit breaker with associated control relaying and breaker disconnect switches • Install a new station service center At the Clifty Creek Station: • Extend 345 kV bus 1 and 2 to make room for a new breaker string • Move a section of the 138 kV bus underground to make room for the new breaker string • Relocate circuit breaker S to the new string • Install two (2) new 345 kV circuit breakers on the new string •Remove the existing Jefferson – Clifty Creek 345 kV line •Construct a new Jefferson – Clifty Creek 345 kV double circuit line •Evaluate line settings for all appropriate lines •Install direct fiber relaying between the Jefferson and Clifty Creek station •Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures
Total Cost ($USD)
$200,238,000
Discounted Total Cost ($USD)
$194,389,945
Allocated Cost ($USD)
$85,518,776
Time Estimate
55 Months

ContributorTopology Changing

Note: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement. Hence, this project is receiving a cost allocation based on its MW contribution to the need for this topology changing reinforcement but at a reduced amount considering the other reinforcements that were able to be eliminated. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
05JEFRSO-05JEFRSO 345.0/765.0 kV Ckt 2 transformer (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
23.9 MW 2.3% $4,388,040
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
465.8 MW 44.0% $85,518,776
AF1-204 25.3 MW 2.4% $4,640,847
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
465.8 MW 44.0% $85,518,776
AG1-226 75.6 MW 7.1% $13,883,252
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.2% $440,254
System Reinforcement: n9243.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9243.0 / AEPSERG13
Title
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Description
At the Jefferson Station: • Expand the northeast corner of the station • Remove Circuit breaker C1 • Install one (1) new 765/345 kV transformer and associated equipment • Install one (1) new 765 kV circuit breaker with associated control relaying and breaker disconnect switches • Install one (1) new 345 kV circuit breaker with associated control relaying and breaker disconnect switches • Install a new station service center At the Clifty Creek Station: • Extend 345 kV bus 1 and 2 to make room for a new breaker string • Move a section of the 138 kV bus underground to make room for the new breaker string • Relocate circuit breaker S to the new string • Install two (2) new 345 kV circuit breakers on the new string •Remove the existing Jefferson – Clifty Creek 345 kV line •Construct a new Jefferson – Clifty Creek 345 kV double circuit line •Evaluate line settings for all appropriate lines •Install direct fiber relaying between the Jefferson and Clifty Creek station •Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures
Total Cost ($USD)
$200,238,000
Allocated Cost ($USD)
$84,156,895
Time Estimate
55 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 0.2057 % $411,965
AE2-173 0.0788 % $157,736
AE2-223 0.2363 % $473,207
AE2-261 2.3717 % $4,749,102
AF1-088 42.0284 % $84,156,895
AF1-204 2.2821 % $4,569,572
AF2-008 42.0284 % $84,156,895
AF2-225 0.2363 % $473,207
AG1-124 1.6178 % $3,239,436
AG1-226 6.8230 % $13,662,162
AG1-236 0.1693 % $338,968
AG1-374 0.4391 % $879,283
AG1-460 0.2380 % $476,484
AG1-494 1.2451 % $2,493,090

System Reinforcement: n6497.4
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n6497.4 / AEPI0002e/f
Title
Replace line traps on the Jefferson - Rockport 765 kV line
Description
Remove three (3) existing 765 kV 3000A single phase line traps on the Jefferson 765 kV line at the Rockport 765 kV Station and replace with three (3) 765 kV 4000A single phase line traps. Remove three (3) existing 765 kV 3000A single phase line traps on the Rockport 765 kV line at the Jefferson 765 kV Station and replace with three (3) 765 kV 4000A single phase line traps.
Total Cost ($USD)
$1,212,000
Discounted Total Cost ($USD)
$1,212,000
Allocated Cost ($USD)
$541,797
Time Estimate
35 Months

Contributor

Facility Contingency
05JEFRSO-05ROCKPT 765.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
334.5 MW 44.7% $541,797
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
334.5 MW 44.7% $541,797
AG1-226 79.3 MW 10.6% $128,407

System Reinforcement: n4106.5
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n4106.5 / AEPI0045c
Title
Upgrade the 345 kV bus 2 towards Jefferson in the Clifty Creek Station
Description
Remove and replace ~ 100 ft of Clifty Creek 345kV Bus 2 towards Jefferson from 5" IPS SCH 40 to 5" IPS SCH 80
Total Cost ($USD)
$121,000
Discounted Total Cost ($USD)
$117,466
Allocated Cost ($USD)
$49,277
Time Estimate
17 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Facility Contingency
05JEFRSO-06CLIFTY 345.0 kV Ckt Z1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AE2-261 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
23.9 MW 4.3% $5,057
AF1-088 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
232.9 MW 41.9% $49,277
AF1-204 25.3 MW 4.6% $5,348
AF2-008 Sullivan 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-088, AF2-008, AH1-084
232.9 MW 41.9% $49,277
AG1-226 37.8 MW 6.8% $8,000
AG1-460 Kincaid Pana Tap - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE2-261, AG1-460
2.4 MW 0.4% $507

System Reinforcement: b4000.251
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.251
Title
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Description
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AF1-088 may not presently have cost responsibility for this upgrade, AF1-088 may need this upgrade in-service to be deliverable to the PJM system. If AF1-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.252
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.252
Title
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Description
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AF1-088 may not presently have cost responsibility for this upgrade, AF1-088 may need this upgrade in-service to be deliverable to the PJM system. If AF1-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
AEP
RTEP ID / TO ID
(Pending) / AEP_TC1_13727
Title
AEP SE rating is 1868 MVA
Description
AEP SE rating is 1868 MVA
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
0 to 1 Months

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
05EUGENE-08CAYSUB 345.0 kV Ckt 1 line (Any)

System Reinforcement: b3788.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b3788.1 / B3788.1
Title
Replace limiting station elements at Kyger Creek
Description
Upgrade existing 345 kV terminal equipment at Kyger Creek on the Kyger Creek-Sporn 345 kV line. Projected in-service date 6/1/2028 Replace AEP-owned station takeoff riser and breaker BB risers at OVEC-owned Kyger Creek station.
Cost Information
Time Estimate
Nov 18 2027

Contingent

Note: Although AF1-088 may not presently have cost responsibility for this upgrade, AF1-088 may need this upgrade in-service to be deliverable to the PJM system. If AF1-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05SPORN-06KYGER 345.0 kV Ckt 1 line (Any)

System Reinforcement: b3788.2
Type
Load Flow
TO
OVEC
RTEP ID / TO ID
b3788.2 / B3788.2
Title
Replace limiting station elements at Kyger Creek
Description
Upgrade existing 345 kV terminal equipment at Kyger Creek on the Kyger Creek-Sporn 345 kV line. Projected in-service date 6/1/2028 Replace OVEC-owned breaker AA risers, bus work, and breaker AA disconnect switches at OVEC-owned Kyger Creek station.
Cost Information
Time Estimate
Jun 01 2028

Contingent

Note: Although AF1-088 may not presently have cost responsibility for this upgrade, AF1-088 may need this upgrade in-service to be deliverable to the PJM system. If AF1-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05SPORN-06KYGER 345.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
AEP
RTEP ID / TO ID
(Pending)
Title
*Ameren Limit* AEP Ratings: 1443/1635 MVA SN/SE. (AMEREN: 1681/1793 MVA SN/SE)
Description
AEP Ratings: 1443/1635 MVA SN/SE. (AMEREN: 1681/1793 MVA SN/SE)
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
0 to 1 Months

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
05SULLIVAN-J1180 TAP 345.0 kV Ckt 1 line (Any)
05SULLIVAN-J1180 TAP 345.0 kV Ckt 1 line (Any)
05SULLIVAN-J2170 POI 345.0 kV Ckt 1 line (Any)
05SULLIVAN-J1180 POI 345.0 kV Ckt 1 line (Any)

System Reinforcement: n7925.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n7925.1 / AEPI0010a
Title
Reconductor ~0.41 miles of the Sullivan – West Casey (Ameren) line
Description
•Remove ~0.41 miles of 1024.5 ACAR 30/7 conductor on the Sullivan – West Casey (Ameren) 345 kV line. •Rebuild line with ACSS Cardinal 974 KCM (54/7) •Evaluate line settings
Total Cost ($USD)
$1,216,000
Discounted Total Cost ($USD)
$1,216,000
Allocated Cost ($USD)
$0
Time Estimate
11 Months

Contingent

Note: Based on PJM cost allocation criteria, AF1-088 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF1-088 could receive cost allocation. Although AF1-088 may not presently have cost responsibility for this upgrade, AF1-088 may need this upgrade in-service to be deliverable to the PJM system. If AF1-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05SULLIVAN-J1180 TAP 345.0 kV Ckt 1 line (Any)
05SULLIVAN-J1180 TAP 345.0 kV Ckt 1 line (Any)
05SULLIVAN-J2170 POI 345.0 kV Ckt 1 line (Any)
05SULLIVAN-J1180 POI 345.0 kV Ckt 1 line (Any)

System Reinforcement: n5808
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n5808 / N5808
Title
CON Upgrade_AEP: eliminate the Eugene stuck breaker contingency. (AMIL upgrade will not be required)
Description
• AEP will install two (2) new 345 kV circuit breakers into the "A1" and "B1" breaker positions at the Eugene 345 kV Station. • AEP will relocate the Bunsonville 345 kV line connection from bus #2 to bus #1. The metering associated with this line connection will also be replaced and relocated accordingly.
Total Cost ($USD)
$3,424,014
Discounted Total Cost ($USD)
$3,424,014
Allocated Cost ($USD)
$0
Time Estimate
May 15 2026

Contingent

Note: Based on PJM cost allocation criteria, AF1-088 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AF1-088 may not have cost responsibility for this upgrade, AF1-088 may need this upgrade in-service to be deliverable to the PJM system. If AF1-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
(Any) AEP_P4_#3128_05EUGENE 345_A2
(Any) AEP_P4_#3128_05EUGENE 345_A2_SRT-A

System Reinforcement: n9195.0

AF1-088 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9195.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9195.0 / CE_NUN_STA12_345 NEW CB
Title
Install a new 345 kV circuit breaker at Station 12 Dresden.
Description
• Upgrade the existing substation STA 12 Dresden by adding 345kV BT 14-15 circuit breaker and associated disconnect switches. • Upgrade relay & protection at 345kV substation STA 12 Dresden to support installation of 345kV BT 14-15
Total Cost ($USD)
$3,357,627
Allocated Cost ($USD)
$1,411,158
Time Estimate
45 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 0.2057 % $6,907
AE2-173 0.0788 % $2,646
AE2-223 0.2363 % $7,934
AE2-261 2.3717 % $79,633
AF1-088 42.0284 % $1,411,157
AF1-204 2.2821 % $76,624
AF2-008 42.0284 % $1,411,157
AF2-225 0.2363 % $7,934
AG1-124 1.6178 % $54,320
AG1-226 6.8230 % $229,091
AG1-236 0.1693 % $5,684
AG1-374 0.4391 % $14,743
AG1-460 0.2380 % $7,991
AG1-494 1.2451 % $41,806

System Reinforcement: b3811.1

AF1-088 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3811.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3811.1 / CE_PJM B3811_L11323
Title
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Description
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s3011

AF1-088 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s3011
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
s3011 / CE_S3011
Title
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.
Description
Replace 345 kV open air straight bus with GIS in a breaker and half configuration (34 Circuit Breakers) at Goodings Grove with 80kA capability.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3775.1

AF1-088 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3775.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3775.1
Title
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line
Description
Outside of the Green Acres substation, swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line to the University Park N-Olive 345 kV line to create a University Park N-Green Acres-Olive and St. John-Olive 345 kV lines.
Cost Information
Cost Alloc Type
Contingent

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF1-088


AF1-088 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Load Flow AEP n9243.0 / AEPSERG13 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Topology 465.8 MW 44.0% Cost Allocated $85,518,776
Load Flow AEP n4106.5 / AEPI0045c Upgrade the 345 kV bus 2 towards Jefferson in the Clifty Creek Station Eliminated 232.9 MW 41.9% Cost Allocated $49,277
Contributions into Topology or Eliminated Reinforcement Total: $85,568,053
AF1-088 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
AEP n9243.0 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Cost Allocated $84,156,895
ComEd n9195.0 Install a new 345 kV circuit breaker at Station 12 Dresden. Cost Allocated $1,411,158
ComEd b3811.1 Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. Contingent $0
ComEd s3011 Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. Contingent $0
ComEd b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line Contingent $0
Region Topology Upgrade Total: $85,568,053

Attachments

AF1-088 One Line Diagram

AF1-088 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.