AF1-128 Phase III Study Report

v1.00 released 2025-09-18 16:23

Chesterfield 230 kV

569.0 MW Capacity / 569.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Virginia Electric and Power Company, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (Dominion Virginia Power).

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $2,182,499 $2,182,499 = 1.00 AND ( $2,182,499 - $2,182,499 ) 569.0 = $0 per MW

General

The Project Developer has proposed a Natural Gas generating facility located in the Virginia Electric and Power Company (Dominion Virginia Power) zone — Chesterfield County, Virginia. The installed facilities will have a total capability of 569.0 MW with 569.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF1-128
Project Name:
Chesterfield 230 kV
Project Developer Name:
Virginia Electric and Power Company
State:
Virginia
County:
Chesterfield
Transmission Owner:
Virginia Electric and Power Company (Dominion Virginia Power)
MFO:
569.0
MWE:
569.0
MWC:
569.0
Fuel Type:
Natural Gas
Basecase Study Year:
2027

Capacity Interconnection Rights (CIR) Transfer Details

This project intends to claim and transfer CIRs from the following Deactivation capacity generation resources. PJM performed a reliability analysis of the impacts to the system capability for the proposed transfer of CIRs from the Deactivation generation resources.

Unit Name Status CIR Claimed POI Transfer
Chesterfield 3 Deactivated Generator 100.0 Yes
Chesterfield 4 Deactivated Generator 119.0 Yes
Chesterfield 5 Deactivated Generator 350.0 No

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF1-128 will interconnect on the Dominion transmission system via a direct connection at the existing 230 kV Chesterfield Power Station.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF1-128 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF1-128 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $799,374 $799,374
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $2,182,499 $2,182,499
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $0 $0
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $2,981,873 $2,981,873

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF1-128

Security has been calculated for the AF1-128 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF1-128
Project(s): AF1-128
Final Agreement Security (A): $2,981,873
Portion of Costs Already Paid (B): $2,310,097
Net Security Due at DP3: A B = $671,776
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The New Service Request Project will interconnect with the Dominion transmission system via a direct connect to the Chesterfield 230 kV Sub. The required work for the interconnection of the New Service Request Project to the Dominion Transmission System is detailed in the following tables.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n8282

Expansion of Existing Chesterfield Substation

$1,436,190 $583,876 $117,227 $45,206 $2,182,499 $2,182,499
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Transmission Owner Interconnection Facilities, including one (1) 230 kV backbone structure and foundation outside the fence of the interconnection substation will be constructed to terminate the Project Developer’s generator lead line. There will also be a line conductor constructed from the backbone structure to the bus position in the switchyard of the interconnection substation.

$524,457 $216,681 $45,422 $12,814 $799,374 $799,374

Based on the scope of work for the Interconnection Facilities, it is expected to take 21 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

It is estimated to take 21 months to complete this work upon execution of the Generator Interconnection Agreement (GIA).This estimated time to complete is dependent on major equipment lead times. These preliminary cost estimates are based on typical engineering costs. A more detailed engineering cost estimates are normally done when the Project Developer provides an exact site plan location for the generation substation during a future study phase.
 
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
 
Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Transmission Owner Analysis

PJM performed a power flow analysis of the transmission system using a 2027 load flow model and the results were verified by Dominion.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here. Refer to AF1-128 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 219.0 MW (569.0 MW Capacity) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 6CHCKAHM-8CHCKAHM 230.0/500.0 kV Ckt 1 transformer
314214 to 314903 ckt 1
DVP_P1-2: LN 567_SRT-A
CONTINGENCY 'DVP_P1-2: LN 567_SRT-A'
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1   /*8CHCKAHM     500.0 - 8SURRY       500.0
END
OP AC 123.73 % 934.92 B 1156.78 38.55
DVP 6CHESTF A-6IRON208 230.0 kV Ckt 1 line
314286 to 314309 ckt 1
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
OP AC 122.25 % 663.64 B 811.33 49.88
DVP 6IRON208-6SOUWEST 230.0 kV Ckt 1 line
314309 to 314338 ckt 1
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
OP AC 113.21 % 663.64 B 751.33 49.87
DVP 6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
OP AC 101.57 % 984.18 B 999.65 12.13
DVP 6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
OP AC 101.52 % 984.18 B 999.16 12.13

Details for 6CHCKAHM-8CHCKAHM 230.0/500.0 kV Ckt 1 transformer l/o DVP_P1-2: LN 567_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHCKAHM-8CHCKAHM 230.0/500.0 kV Ckt 1 transformer
314214 to 314903 ckt 1
Contingency Name:
DVP_P1-2: LN 567_SRT-A
CONTINGENCY 'DVP_P1-2: LN 567_SRT-A'
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1   /*8CHCKAHM     500.0 - 8SURRY       500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 123.73 %
Rating: 934.92 MVA
Rating Type: B
MVA to Mitigate: 1156.78 MVA
MW Contribution: 38.55 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CHCKAHM-8CHCKAHM 230.0/500.0 kV Ckt 1 transformer
314214 to 314903 ckt 1
Contingency Name:
DVP_P1-2: LN 567_SRT-A
CONTINGENCY 'DVP_P1-2: LN 567_SRT-A'
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1   /*8CHCKAHM     500.0 - 8SURRY       500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 128.41 %
Rating: 934.92 MVA
Rating Type: B
MVA to Mitigate: 1200.49 MVA
MW Contribution: 39.14 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961941 AG1-037 C Adder 0.26 MW 0.22 MW
961942 AG1-037 E Adder 0.17 MW 0.14 MW
962331 AG1-082 C Adder 1.02 MW 0.87 MW
962332 AG1-082 E Adder 0.68 MW 0.58 MW
965291 AG1-394 C Adder 0.44 MW 0.37 MW
965292 AG1-394 E Adder 0.81 MW 0.69 MW
314541 3WATKINS Adder 0.38 MW 0.32 MW
918492 AA1-063AE OP Adder 1.96 MW 1.67 MW
919692 AA2-053 E OP Adder 1.97 MW 1.67 MW
920042 AA2-088 E OP Adder 5.49 MW 4.67 MW
927146 AC1-208 E Adder 1.95 MW 1.66 MW
934521 AD1-076 C Adder 6.46 MW 5.49 MW
934522 AD1-076 E Adder 3.29 MW 2.8 MW
943172 AE2-346 E Adder 0.31 MW 0.26 MW
316141 AB2-099 E Adder 0.13 MW 0.11 MW
900672 V4-068 E Adder 0.18 MW 0.15 MW
917342 Z2-044 E Adder 0.3 MW 0.26 MW
940492 AE2-034 E Adder 1.68 MW 1.42 MW
957521 AF2-046 C Adder 7.23 MW 6.14 MW
957522 AF2-046 E Adder 3.65 MW 3.1 MW
314539 3UNCAMP Adder 3.37 MW 2.86 MW
916042 Z1-036 E Adder 16.11 MW 13.69 MW
938771 AE1-103 C Adder 1.64 MW 1.4 MW
938772 AE1-103 E Adder 2.27 MW 1.93 MW
314184 3SHACKLE 50/50 0.6 MW 0.6 MW
314331 6POE Adder 0.72 MW 0.61 MW
314507 3THOMPSN Adder 1.23 MW 1.04 MW
314525 6KINGFORK Adder 0.65 MW 0.55 MW
314550 6HICKORY Adder 1.3 MW 1.1 MW
315060 1CHESTF5 Adder 61.61 MW 52.37 MW
315065 1CHESTF6 Adder 11.1 MW 9.43 MW
315073 1STONECA Adder 5.14 MW 4.37 MW
315083 1SPRUNCA Adder 4.63 MW 3.94 MW
315084 1SPRUNCB Adder 4.63 MW 3.94 MW
315092 1YORKTN3 Adder 112.31 MW 95.46 MW
925865 AC1-065 E 50/50 18.88 MW 18.88 MW
926412 AC1-112 E Adder 0.95 MW 0.81 MW
926472 AC1-118 E Adder 1.07 MW 0.91 MW
926662 AC1-147 E Adder 0.81 MW 0.69 MW
926755 AC1-161 E Adder 7.68 MW 6.53 MW
927226 AC1-216 E Adder 5.58 MW 4.74 MW
934392 AD1-063 E 50/50 1.28 MW 1.28 MW
935112 AD1-144 E Adder 0.6 MW 0.51 MW
936582 AD2-073 E Adder 1.15 MW 0.97 MW
936591 AD2-074 C 50/50 6.21 MW 6.21 MW
936592 AD2-074 E 50/50 10.14 MW 10.14 MW
942341 AE2-247 C Adder 0.89 MW 0.75 MW
942342 AE2-247 E Adder 1.22 MW 1.04 MW
943461 AF1-017 C Adder 0.8 MW 0.68 MW
943462 AF1-017 E Adder 1.31 MW 1.11 MW
943612 AF1-032 E Adder 0.56 MW 0.47 MW
943741 AF1-042 C 50/50 3.25 MW 3.25 MW
943742 AF1-042 E 50/50 5.3 MW 5.3 MW
944491 AF1-114 C Adder 5.07 MW 4.31 MW
944492 AF1-114 E Adder 7.0 MW 5.95 MW
961951 AG1-038 C 50/50 3.59 MW 3.59 MW
961952 AG1-038 E 50/50 4.96 MW 4.96 MW
966661 AG1-536 C 50/50 6.01 MW 6.01 MW
966662 AG1-536 E 50/50 8.07 MW 8.07 MW
315260 1GOSPORTA Adder 1.3 MW 1.1 MW
315261 1GOSPORTB Adder 1.66 MW 1.41 MW
315262 1GOSPORTC Adder 1.41 MW 1.2 MW
316075 AC2-137 C 50/50 0.45 MW 0.45 MW
316076 AC2-137 E 50/50 1.58 MW 1.58 MW
316078 AC2-138 E Adder 1.04 MW 0.89 MW
316156 AD2-030 C 50/50 0.42 MW 0.42 MW
316157 AD2-030 E 50/50 1.33 MW 1.33 MW
913392 Y1-086 E Adder 1.29 MW 1.1 MW
916192 Z1-068 E Adder 1.13 MW 0.96 MW
923832 AB2-022 E Adder 0.73 MW 0.62 MW
923842 AB2-024 E 50/50 2.23 MW 2.23 MW
923852 AB2-025 E Adder 0.54 MW 0.46 MW
930122 AB1-027 E Adder 1.17 MW 0.99 MW
939312 AE1-162 E Adder 0.96 MW 0.81 MW
946262 AF1-291 E Adder 0.81 MW 0.69 MW
957492 AF2-043 E Adder 0.86 MW 0.73 MW
957601 AF2-054 C 50/50 2.37 MW 2.37 MW
957602 AF2-054 E 50/50 1.58 MW 1.58 MW
962861 AG1-135 C 50/50 6.78 MW 6.78 MW
962862 AG1-135 E 50/50 4.52 MW 4.52 MW
962962 AG1-145 E 50/50 1.53 MW 1.53 MW
962971 AG1-146 C 50/50 3.45 MW 3.45 MW
962972 AG1-146 E 50/50 2.3 MW 2.3 MW
962981 AG1-147 C 50/50 8.05 MW 8.05 MW
962982 AG1-147 E 50/50 5.36 MW 5.36 MW
963611 AG1-210 C Adder 0.74 MW 0.63 MW
963612 AG1-210 E Adder 1.12 MW 0.95 MW
964211 AG1-282 C 50/50 2.32 MW 2.32 MW
964212 AG1-282 E 50/50 1.55 MW 1.55 MW
901082 W1-029 E Adder 18.56 MW 15.78 MW
917122 Z2-027 E Adder 0.78 MW 0.67 MW
925332 AB2-190 E Adder 5.9 MW 5.02 MW
925522 AC1-027 E Adder 0.74 MW 0.62 MW
942001 AE2-212 C Adder 1.19 MW 1.01 MW
942002 AE2-212 E Adder 0.79 MW 0.67 MW
957832 AF2-077 E Adder 1.39 MW 1.18 MW
957871 AF2-081 C Adder 5.93 MW 5.04 MW
957872 AF2-081 E Adder 2.54 MW 2.16 MW
957971 AF2-091 C Adder 1.72 MW 1.46 MW
957972 AF2-091 E Adder 2.38 MW 2.02 MW
958161 AF2-110 C Adder 0.81 MW 0.69 MW
958162 AF2-110 E Adder 1.29 MW 1.1 MW
313811 6ELKO L286 50/50 1.65 MW 1.65 MW
314181 3NORNECK Adder 0.99 MW 0.84 MW
933291 AC2-141 C Adder 18.0 MW 15.3 MW
933292 AC2-141 E Adder 7.68 MW 6.53 MW
939411 AE1-173 C Adder 42.86 MW 36.43 MW
939412 AE1-173 E Adder 28.57 MW 24.29 MW
934012 AD1-025 E Adder 7.22 MW 6.14 MW
933981 AD1-022 C Adder 4.58 MW 3.89 MW
933982 AD1-022 E Adder 2.49 MW 2.12 MW
961681 AG1-008 C Adder 7.23 MW 6.14 MW
961682 AG1-008 E Adder 3.65 MW 3.1 MW
313053 6PAPERMILL 50/50 8.16 MW 8.16 MW
314594 6PLYMOUTH TP Adder 0.17 MW 0.15 MW
314632 6AYDLETT TAP Adder 0.8 MW 0.68 MW
316059 AD1-063 C 50/50 0.31 MW 0.31 MW
316159 AE1-175 C 50/50 0.42 MW 0.42 MW
316160 AE1-175 E 50/50 1.27 MW 1.27 MW
316169 AC1-164 GEN 50/50 59.58 MW 59.58 MW
316240 AF1-291 C Adder 1.21 MW 1.03 MW
316274 AC1-208 C Adder 4.4 MW 3.74 MW
316314 AB2-024 C 50/50 0.36 MW 0.36 MW
316382 AG1-145 C 50/50 0.38 MW 0.38 MW
917332 KELFORD E Adder 0.82 MW 0.7 MW
924516 AB2-100 E1 Adder 1.32 MW 1.12 MW
924517 AB2-100 E2 Adder 1.32 MW 1.12 MW
926206 AC1-098 E Adder 1.8 MW 1.53 MW
926214 AC1-099 E Adder 0.6 MW 0.51 MW
926785 AC1-164_E 50/50 26.77 MW 26.77 MW
934065 AD1-033 E Adder 3.0 MW 2.55 MW
937226 AE2-253 E Adder 3.47 MW 2.95 MW
939611 AE1-191 C 50/50 1.54 MW 1.54 MW
939612 AE1-191 E 50/50 6.42 MW 6.42 MW
316201 AC1-065 C 50/50 1.85 MW 1.85 MW
316404 AE1-155 C 50/50 2.37 MW 2.37 MW
939246 AE1-155 E 50/50 9.72 MW 9.72 MW
918512 AA1-065 E OP Adder 2.8 MW 2.38 MW
919153 AA1-139 E2 Adder 2.42 MW 2.06 MW
919152 AA1-139 E1 Adder 2.42 MW 2.06 MW
919710 AA2-057 E Adder 1.98 MW 1.69 MW
920692 AA2-178 E Adder 2.23 MW 1.9 MW
924814 AB2-134 E Adder 9.14 MW 7.77 MW
316084 AB2-161 E Adder 3.28 MW 2.79 MW
925122 AB2-169 E Adder 2.83 MW 2.4 MW
932046 AC2-012 E Adder 7.98 MW 6.79 MW
316311 AC2-079 C Adder 3.41 MW 2.9 MW
932596 AC2-079 E Adder 5.56 MW 4.73 MW
316280 AD1-041 C 50/50 0.98 MW 0.98 MW
934146 AD1-041 E 50/50 4.01 MW 4.01 MW
934576 AD1-082 E Adder 2.62 MW 2.22 MW
316349 AD2-085 C Adder 2.05 MW 1.74 MW
936666 AD2-085 E Adder 3.34 MW 2.84 MW
961611 AG1-000B C Adder 11.28 MW 9.59 MW
941591 AE2-156 C Adder 10.9 MW 9.27 MW
944581 AF1-123 C Adder 27.1 MW 23.03 MW
944582 AF1-123 E Adder 62.05 MW 52.74 MW
944591 AF1-124 C Adder 27.19 MW 23.11 MW
944592 AF1-124 E Adder 62.27 MW 52.93 MW
944601 AF1-125 C Adder 26.68 MW 22.68 MW
944602 AF1-125 E Adder 61.08 MW 51.91 MW
944631 AF1-128 C Adder 38.55 MW 32.77 MW
958261 AF2-120 C 50/50 6.98 MW 6.98 MW
958262 AF2-120 E 50/50 4.66 MW 4.66 MW
965281 AG1-393 C Adder 1.32 MW 1.12 MW
965282 AG1-393 E Adder 0.88 MW 0.75 MW
932632 AC2-084 E Adder 1.59 MW 1.35 MW
934501 AD1-074 C Adder 17.79 MW 15.12 MW
934502 AD1-074 E Adder 9.06 MW 7.7 MW
934511 AD1-075 C Adder 4.45 MW 3.78 MW
934512 AD1-075 E Adder 2.26 MW 1.93 MW
935161 AD1-151 C Adder 11.73 MW 9.97 MW
935162 AD1-151 E Adder 7.82 MW 6.65 MW
938531 AE1-072 C Adder 10.4 MW 8.84 MW
938532 AE1-072 E Adder 5.42 MW 4.61 MW
939191 AE1-149 C Adder 6.37 MW 5.41 MW
939192 AE1-149 E Adder 4.24 MW 3.61 MW
939601 AE1-190 C 50/50 0.38 MW 0.38 MW
939602 AE1-190 E 50/50 1.6 MW 1.6 MW
940431 AE2-027 C Adder 8.04 MW 6.83 MW
940432 AE2-027 E Adder 5.36 MW 4.56 MW
940481 AE2-033 C Adder 7.46 MW 6.34 MW
940482 AE2-033 E Adder 5.03 MW 4.28 MW
940541 AE2-040 C Adder 1.33 MW 1.13 MW
940551 AE2-041 C 50/50 8.53 MW 8.53 MW
940641 AE2-051 C Adder 7.5 MW 6.38 MW
940642 AE2-051 E Adder 5.0 MW 4.25 MW
941101 AE2-104 C Adder 1.99 MW 1.69 MW
941102 AE2-104 E Adder 3.17 MW 2.69 MW
943471 AF1-018 C 50/50 8.53 MW 8.53 MW
944641 AF1-129 C Adder 57.89 MW 49.2 MW
957191 AF2-013 C Adder 8.09 MW 6.87 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 1.13 MW 1.13 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.92 MW 3.92 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 29.25 MW 29.25 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.13 MW 1.13 MW
NY PJM->LTFIMP_NY CLTF 0.56 MW 0.56 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.07 MW 0.07 MW
WEC LTFEXP_WEC->PJM CLTF 0.03 MW 0.03 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.85 MW 3.85 MW
TVA LTFEXP_TVA->PJM CLTF 1.27 MW 1.27 MW
MEC LTFEXP_MEC->PJM CLTF 0.43 MW 0.43 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.66 MW 1.66 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.02 MW 0.02 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 7.22 MW 7.22 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.83 MW 1.83 MW

Details for 6CHESTF A-6IRON208 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 557_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHESTF A-6IRON208 230.0 kV Ckt 1 line
314286 to 314309 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 122.25 %
Rating: 663.64 MVA
Rating Type: B
MVA to Mitigate: 811.33 MVA
MW Contribution: 49.88 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6CHESTF A-6IRON208 230.0 kV Ckt 1 line
314286 to 314309 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 120.34 %
Rating: 663.64 MVA
Rating Type: B
MVA to Mitigate: 798.65 MVA
MW Contribution: 49.4 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
314539 3UNCAMP Adder 1.77 MW 1.51 MW
916042 Z1-036 E Adder 8.51 MW 7.23 MW
938771 AE1-103 C Adder 0.87 MW 0.74 MW
938772 AE1-103 E Adder 1.2 MW 1.02 MW
314507 3THOMPSN Adder 0.68 MW 0.58 MW
314525 6KINGFORK Adder 0.36 MW 0.3 MW
314550 6HICKORY Adder 0.7 MW 0.59 MW
315060 1CHESTF5 50/50 79.72 MW 79.72 MW
315061 1CHESTG7 50/50 4.86 MW 4.86 MW
315062 1CHESTS7 50/50 2.23 MW 2.23 MW
315063 1CHESTG8 50/50 4.79 MW 4.79 MW
315064 1CHESTS8 50/50 2.46 MW 2.46 MW
315073 1STONECA 50/50 4.67 MW 4.67 MW
315076 1HOPPOLC 50/50 1.04 MW 1.04 MW
315077 1HOPHCF1 50/50 1.65 MW 1.65 MW
315078 1HOPHCF2 50/50 1.65 MW 1.65 MW
315079 1HOPHCF3 50/50 1.65 MW 1.65 MW
315080 1HOPHCF4 50/50 2.5 MW 2.5 MW
315092 1YORKTN3 Adder 54.33 MW 46.18 MW
925865 AC1-065 E Adder 7.58 MW 6.44 MW
926472 AC1-118 E Adder 0.4 MW 0.34 MW
926662 AC1-147 E Adder 0.45 MW 0.38 MW
926755 AC1-161 E Adder 3.95 MW 3.36 MW
927226 AC1-216 E 50/50 4.35 MW 4.35 MW
934392 AD1-063 E Adder 0.51 MW 0.43 MW
935112 AD1-144 E Adder 0.33 MW 0.28 MW
936582 AD2-073 E Adder 0.44 MW 0.37 MW
936591 AD2-074 C Adder 2.44 MW 2.08 MW
936592 AD2-074 E Adder 3.99 MW 3.39 MW
942341 AE2-247 C Adder 0.5 MW 0.42 MW
942342 AE2-247 E Adder 0.68 MW 0.58 MW
943461 AF1-017 C Adder 0.45 MW 0.38 MW
943462 AF1-017 E Adder 0.73 MW 0.62 MW
943612 AF1-032 E Adder 0.3 MW 0.25 MW
943741 AF1-042 C Adder 1.28 MW 1.09 MW
943742 AF1-042 E Adder 2.09 MW 1.77 MW
961951 AG1-038 C Adder 1.41 MW 1.2 MW
961952 AG1-038 E Adder 1.95 MW 1.66 MW
966661 AG1-536 C Adder 2.34 MW 1.99 MW
966662 AG1-536 E Adder 3.14 MW 2.67 MW
315260 1GOSPORTA Adder 0.72 MW 0.61 MW
315261 1GOSPORTB Adder 0.92 MW 0.78 MW
315262 1GOSPORTC Adder 0.78 MW 0.66 MW
316076 AC2-137 E Adder 0.53 MW 0.45 MW
316078 AC2-138 E Adder 0.4 MW 0.34 MW
316132 AB2-190 C 50/50 2.52 MW 2.52 MW
316157 AD2-030 E Adder 0.54 MW 0.46 MW
913392 Y1-086 E Adder 0.69 MW 0.59 MW
916192 Z1-068 E Adder 0.62 MW 0.53 MW
923832 AB2-022 E Adder 0.39 MW 0.33 MW
923842 AB2-024 E Adder 0.87 MW 0.74 MW
939312 AE1-162 E Adder 0.6 MW 0.51 MW
957492 AF2-043 E Adder 0.46 MW 0.39 MW
957601 AF2-054 C Adder 0.96 MW 0.81 MW
957602 AF2-054 E Adder 0.64 MW 0.54 MW
962861 AG1-135 C Adder 2.65 MW 2.25 MW
962862 AG1-135 E Adder 1.76 MW 1.5 MW
962962 AG1-145 E Adder 0.66 MW 0.56 MW
962971 AG1-146 C Adder 1.36 MW 1.16 MW
962972 AG1-146 E Adder 0.91 MW 0.77 MW
962981 AG1-147 C Adder 3.18 MW 2.71 MW
962982 AG1-147 E Adder 2.12 MW 1.8 MW
963611 AG1-210 C Adder 0.29 MW 0.24 MW
963612 AG1-210 E Adder 0.43 MW 0.37 MW
964211 AG1-282 C Adder 0.89 MW 0.76 MW
964212 AG1-282 E Adder 0.6 MW 0.51 MW
901082 W1-029 E Adder 9.91 MW 8.42 MW
917122 Z2-027 E Adder 0.42 MW 0.36 MW
925332 AB2-190 E 50/50 4.91 MW 4.91 MW
925522 AC1-027 E Adder 0.4 MW 0.34 MW
957832 AF2-077 E Adder 0.61 MW 0.52 MW
957871 AF2-081 C Adder 3.18 MW 2.71 MW
957872 AF2-081 E Adder 1.36 MW 1.16 MW
958161 AF2-110 C Adder 0.44 MW 0.38 MW
958162 AF2-110 E Adder 0.7 MW 0.6 MW
313811 6ELKO L286 Adder 0.55 MW 0.47 MW
314181 3NORNECK Adder 0.38 MW 0.33 MW
933291 AC2-141 C Adder 9.25 MW 7.86 MW
933292 AC2-141 E Adder 3.95 MW 3.36 MW
934011 AD1-025 C 50/50 1.46 MW 1.46 MW
934012 AD1-025 E 50/50 5.63 MW 5.63 MW
313053 6PAPERMILL Adder 3.2 MW 2.72 MW
314632 6AYDLETT TAP Adder 0.43 MW 0.37 MW
316160 AE1-175 E Adder 0.54 MW 0.46 MW
316169 AC1-164 GEN 50/50 22.39 MW 22.39 MW
316369 AC1-216 C 50/50 0.9 MW 0.9 MW
926785 AC1-164_E 50/50 10.06 MW 10.06 MW
934065 AD1-033 E Adder 1.62 MW 1.38 MW
937226 AE2-253 E Adder 1.87 MW 1.59 MW
939612 AE1-191 E Adder 2.59 MW 2.2 MW
939246 AE1-155 E Adder 3.79 MW 3.22 MW
919153 AA1-139 E2 Adder 1.3 MW 1.11 MW
919152 AA1-139 E1 Adder 1.3 MW 1.11 MW
316033 AB2-134 GEN 50/50 1.18 MW 1.18 MW
924814 AB2-134 E 50/50 7.12 MW 7.12 MW
316084 AB2-161 E Adder 1.92 MW 1.63 MW
932046 AC2-012 E Adder 4.42 MW 3.75 MW
316311 AC2-079 C Adder 1.9 MW 1.61 MW
932596 AC2-079 E Adder 3.1 MW 2.63 MW
934146 AD1-041 E Adder 1.62 MW 1.37 MW
934576 AD1-082 E Adder 1.53 MW 1.3 MW
316349 AD2-085 C Adder 1.14 MW 0.97 MW
936666 AD2-085 E Adder 1.87 MW 1.59 MW
961611 AG1-000B C Adder 7.87 MW 6.69 MW
941591 AE2-156 C Adder 6.02 MW 5.12 MW
944581 AF1-123 C Adder 14.58 MW 12.39 MW
944582 AF1-123 E Adder 33.39 MW 28.38 MW
944591 AF1-124 C Adder 14.63 MW 12.44 MW
944592 AF1-124 E Adder 33.51 MW 28.48 MW
944601 AF1-125 C Adder 14.36 MW 12.2 MW
944602 AF1-125 E Adder 32.86 MW 27.93 MW
944631 AF1-128 C 50/50 49.88 MW 49.88 MW
958261 AF2-120 C Adder 2.72 MW 2.31 MW
958262 AF2-120 E Adder 1.81 MW 1.54 MW
965281 AG1-393 C Adder 0.66 MW 0.56 MW
965282 AG1-393 E Adder 0.44 MW 0.38 MW
935161 AD1-151 C 50/50 9.47 MW 9.47 MW
935162 AD1-151 E 50/50 6.31 MW 6.31 MW
938531 AE1-072 C Adder 5.58 MW 4.75 MW
938532 AE1-072 E Adder 2.91 MW 2.47 MW
939191 AE1-149 C Adder 3.84 MW 3.26 MW
939192 AE1-149 E Adder 2.56 MW 2.17 MW
939602 AE1-190 E Adder 0.65 MW 0.55 MW
940431 AE2-027 C Adder 3.98 MW 3.38 MW
940432 AE2-027 E Adder 2.65 MW 2.25 MW
940551 AE2-041 C Adder 3.38 MW 2.88 MW
941101 AE2-104 C Adder 1.08 MW 0.92 MW
941102 AE2-104 E Adder 1.72 MW 1.46 MW
943471 AF1-018 C Adder 3.38 MW 2.88 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.5 MW 0.5 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.74 MW 1.74 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 12.92 MW 12.92 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.57 MW 0.57 MW
NY PJM->LTFIMP_NY CLTF 0.28 MW 0.28 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.03 MW 0.03 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.71 MW 1.71 MW
TVA LTFEXP_TVA->PJM CLTF 0.56 MW 0.56 MW
MEC LTFEXP_MEC->PJM CLTF 0.19 MW 0.19 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.73 MW 0.73 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.65 MW 3.65 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.81 MW 0.81 MW

Details for 6IRON208-6SOUWEST 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 557_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6IRON208-6SOUWEST 230.0 kV Ckt 1 line
314309 to 314338 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.21 %
Rating: 663.64 MVA
Rating Type: B
MVA to Mitigate: 751.33 MVA
MW Contribution: 49.87 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6IRON208-6SOUWEST 230.0 kV Ckt 1 line
314309 to 314338 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 112.58 %
Rating: 663.64 MVA
Rating Type: B
MVA to Mitigate: 747.13 MVA
MW Contribution: 49.39 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
314539 3UNCAMP Adder 1.77 MW 1.5 MW
916042 Z1-036 E Adder 8.5 MW 7.22 MW
938771 AE1-103 C Adder 0.87 MW 0.74 MW
938772 AE1-103 E Adder 1.2 MW 1.02 MW
314309 6IRON208 50/50 1.15 MW 1.15 MW
314507 3THOMPSN Adder 0.68 MW 0.58 MW
314525 6KINGFORK Adder 0.36 MW 0.3 MW
314550 6HICKORY Adder 0.7 MW 0.59 MW
315060 1CHESTF5 50/50 79.69 MW 79.69 MW
315061 1CHESTG7 50/50 4.86 MW 4.86 MW
315062 1CHESTS7 50/50 2.23 MW 2.23 MW
315063 1CHESTG8 50/50 4.79 MW 4.79 MW
315064 1CHESTS8 50/50 2.46 MW 2.46 MW
315073 1STONECA Adder 4.67 MW 3.97 MW
315077 1HOPHCF1 50/50 1.65 MW 1.65 MW
315078 1HOPHCF2 50/50 1.65 MW 1.65 MW
315079 1HOPHCF3 50/50 1.65 MW 1.65 MW
315080 1HOPHCF4 50/50 2.5 MW 2.5 MW
315092 1YORKTN3 Adder 54.27 MW 46.13 MW
925865 AC1-065 E Adder 7.57 MW 6.43 MW
926472 AC1-118 E Adder 0.4 MW 0.34 MW
926662 AC1-147 E Adder 0.45 MW 0.38 MW
926755 AC1-161 E Adder 3.94 MW 3.35 MW
927226 AC1-216 E Adder 4.34 MW 3.69 MW
934392 AD1-063 E Adder 0.51 MW 0.43 MW
935112 AD1-144 E Adder 0.33 MW 0.28 MW
936582 AD2-073 E Adder 0.44 MW 0.37 MW
936591 AD2-074 C Adder 2.44 MW 2.08 MW
936592 AD2-074 E Adder 3.98 MW 3.39 MW
942341 AE2-247 C Adder 0.5 MW 0.42 MW
942342 AE2-247 E Adder 0.68 MW 0.58 MW
943461 AF1-017 C Adder 0.45 MW 0.38 MW
943462 AF1-017 E Adder 0.73 MW 0.62 MW
943612 AF1-032 E Adder 0.3 MW 0.25 MW
943741 AF1-042 C Adder 1.28 MW 1.09 MW
943742 AF1-042 E Adder 2.08 MW 1.77 MW
961951 AG1-038 C Adder 1.41 MW 1.2 MW
961952 AG1-038 E Adder 1.95 MW 1.66 MW
966661 AG1-536 C Adder 2.34 MW 1.99 MW
966662 AG1-536 E Adder 3.14 MW 2.67 MW
315260 1GOSPORTA Adder 0.72 MW 0.61 MW
315261 1GOSPORTB Adder 0.92 MW 0.78 MW
315262 1GOSPORTC Adder 0.78 MW 0.66 MW
316076 AC2-137 E Adder 0.53 MW 0.45 MW
316078 AC2-138 E Adder 0.4 MW 0.34 MW
316157 AD2-030 E Adder 0.54 MW 0.46 MW
913392 Y1-086 E Adder 0.69 MW 0.59 MW
916192 Z1-068 E Adder 0.62 MW 0.53 MW
923832 AB2-022 E Adder 0.39 MW 0.33 MW
923842 AB2-024 E Adder 0.87 MW 0.74 MW
939312 AE1-162 E Adder 0.6 MW 0.51 MW
957492 AF2-043 E Adder 0.46 MW 0.39 MW
957601 AF2-054 C Adder 0.96 MW 0.81 MW
957602 AF2-054 E Adder 0.64 MW 0.54 MW
962861 AG1-135 C Adder 2.64 MW 2.25 MW
962862 AG1-135 E Adder 1.76 MW 1.5 MW
962962 AG1-145 E Adder 0.66 MW 0.56 MW
962971 AG1-146 C Adder 1.36 MW 1.16 MW
962972 AG1-146 E Adder 0.91 MW 0.77 MW
962981 AG1-147 C Adder 3.18 MW 2.7 MW
962982 AG1-147 E Adder 2.12 MW 1.8 MW
963611 AG1-210 C Adder 0.29 MW 0.24 MW
963612 AG1-210 E Adder 0.43 MW 0.37 MW
964211 AG1-282 C Adder 0.89 MW 0.76 MW
964212 AG1-282 E Adder 0.6 MW 0.51 MW
901082 W1-029 E Adder 9.9 MW 8.41 MW
917122 Z2-027 E Adder 0.42 MW 0.36 MW
925332 AB2-190 E Adder 4.9 MW 4.17 MW
925522 AC1-027 E Adder 0.4 MW 0.34 MW
957832 AF2-077 E Adder 0.61 MW 0.52 MW
957871 AF2-081 C Adder 3.18 MW 2.7 MW
957872 AF2-081 E Adder 1.36 MW 1.16 MW
958161 AF2-110 C Adder 0.44 MW 0.38 MW
958162 AF2-110 E Adder 0.7 MW 0.6 MW
313811 6ELKO L286 Adder 0.55 MW 0.47 MW
314181 3NORNECK Adder 0.38 MW 0.33 MW
933291 AC2-141 C Adder 9.24 MW 7.85 MW
933292 AC2-141 E Adder 3.94 MW 3.35 MW
934012 AD1-025 E Adder 5.62 MW 4.78 MW
313053 6PAPERMILL Adder 3.2 MW 2.72 MW
314632 6AYDLETT TAP Adder 0.43 MW 0.36 MW
316160 AE1-175 E Adder 0.54 MW 0.46 MW
316169 AC1-164 GEN Adder 22.37 MW 19.02 MW
926785 AC1-164_E Adder 10.05 MW 8.54 MW
934065 AD1-033 E Adder 1.62 MW 1.37 MW
937226 AE2-253 E Adder 1.86 MW 1.58 MW
939612 AE1-191 E Adder 2.58 MW 2.2 MW
939246 AE1-155 E Adder 3.78 MW 3.22 MW
919153 AA1-139 E2 Adder 1.3 MW 1.1 MW
919152 AA1-139 E1 Adder 1.3 MW 1.1 MW
924814 AB2-134 E Adder 7.12 MW 6.05 MW
316084 AB2-161 E Adder 1.92 MW 1.63 MW
932046 AC2-012 E Adder 4.41 MW 3.75 MW
316311 AC2-079 C Adder 1.9 MW 1.61 MW
932596 AC2-079 E Adder 3.09 MW 2.63 MW
934146 AD1-041 E Adder 1.61 MW 1.37 MW
934576 AD1-082 E Adder 1.53 MW 1.3 MW
316349 AD2-085 C Adder 1.14 MW 0.97 MW
936666 AD2-085 E Adder 1.86 MW 1.58 MW
961611 AG1-000B C Adder 7.86 MW 6.68 MW
941591 AE2-156 C Adder 6.02 MW 5.11 MW
944581 AF1-123 C Adder 14.56 MW 12.38 MW
944582 AF1-123 E Adder 33.34 MW 28.34 MW
944591 AF1-124 C Adder 14.61 MW 12.42 MW
944592 AF1-124 E Adder 33.46 MW 28.44 MW
944601 AF1-125 C Adder 14.34 MW 12.19 MW
944602 AF1-125 E Adder 32.82 MW 27.9 MW
944631 AF1-128 C 50/50 49.87 MW 49.87 MW
958261 AF2-120 C Adder 2.72 MW 2.31 MW
958262 AF2-120 E Adder 1.81 MW 1.54 MW
965281 AG1-393 C Adder 0.66 MW 0.56 MW
965282 AG1-393 E Adder 0.44 MW 0.38 MW
935161 AD1-151 C Adder 9.46 MW 8.04 MW
935162 AD1-151 E Adder 6.31 MW 5.36 MW
938531 AE1-072 C Adder 5.57 MW 4.74 MW
938532 AE1-072 E Adder 2.91 MW 2.47 MW
939191 AE1-149 C Adder 3.83 MW 3.26 MW
939192 AE1-149 E Adder 2.55 MW 2.17 MW
939602 AE1-190 E Adder 0.65 MW 0.55 MW
940431 AE2-027 C Adder 3.97 MW 3.38 MW
940432 AE2-027 E Adder 2.65 MW 2.25 MW
940551 AE2-041 C Adder 3.38 MW 2.87 MW
941101 AE2-104 C Adder 1.08 MW 0.92 MW
941102 AE2-104 E Adder 1.72 MW 1.46 MW
943471 AF1-018 C Adder 3.38 MW 2.87 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.37 MW 0.37 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.69 MW 1.69 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 12.84 MW 12.84 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.58 MW 0.58 MW
NY PJM->LTFIMP_NY CLTF 0.29 MW 0.29 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.03 MW 0.03 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 1.7 MW 1.7 MW
TVA LTFEXP_TVA->PJM CLTF 0.55 MW 0.55 MW
MEC LTFEXP_MEC->PJM CLTF 0.18 MW 0.18 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.72 MW 0.72 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.7 MW 3.7 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.81 MW 0.81 MW

Details for 6CHESTF B-6VARINA 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 557_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 101.57 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 999.65 MVA
MW Contribution: 12.13 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.2 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 986.11 MVA
MW Contribution: 11.04 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.31 MW 0.27 MW
961672 AG1-007 E Adder 0.18 MW 0.15 MW
961941 AG1-037 C Adder 0.19 MW 0.16 MW
961942 AG1-037 E Adder 0.13 MW 0.11 MW
962331 AG1-082 C Adder 0.76 MW 0.64 MW
962332 AG1-082 E Adder 0.5 MW 0.43 MW
963041 AG1-153 C Adder 1.68 MW 1.42 MW
963042 AG1-153 E Adder 2.51 MW 2.14 MW
966801 AG1-551 C Adder 0.72 MW 0.62 MW
966802 AG1-551 E Adder 0.38 MW 0.32 MW
966811 AG1-552 C Adder 0.79 MW 0.67 MW
966812 AG1-552 E Adder 0.38 MW 0.32 MW
965291 AG1-394 C Adder 0.33 MW 0.28 MW
965292 AG1-394 E Adder 0.61 MW 0.52 MW
966621 AG1-532 C Adder 0.58 MW 0.5 MW
966622 AG1-532 E Adder 0.39 MW 0.33 MW
314541 3WATKINS Adder 0.27 MW 0.23 MW
314572 3EMPORIA Adder 0.18 MW 0.15 MW
315131 1EDGECMA Adder 5.12 MW 4.35 MW
918492 AA1-063AE OP Adder 1.57 MW 1.33 MW
918532 AA1-067 E Adder 0.24 MW 0.21 MW
919692 AA2-053 E OP Adder 1.61 MW 1.37 MW
920042 AA2-088 E OP Adder 4.1 MW 3.48 MW
925785 AC1-054 E Adder 1.14 MW 0.97 MW
927146 AC1-208 E Adder 1.58 MW 1.34 MW
934521 AD1-076 C Adder 4.42 MW 3.76 MW
934522 AD1-076 E Adder 2.26 MW 1.92 MW
943172 AE2-346 E Adder 0.23 MW 0.19 MW
944011 AF1-069 C Adder 3.91 MW 3.33 MW
944012 AF1-069 E Adder 1.52 MW 1.29 MW
960081 AF2-299 C Adder 0.78 MW 0.66 MW
960082 AF2-299 E Adder 0.52 MW 0.44 MW
316141 AB2-099 E Adder 0.09 MW 0.08 MW
900672 V4-068 E Adder 0.14 MW 0.12 MW
917342 Z2-044 E Adder 0.24 MW 0.21 MW
922923 AB1-081 E OP Adder 1.24 MW 1.06 MW
923263 AB1-132 E OP Adder 2.48 MW 2.11 MW
923573 AB1-173 E OP Adder 1.32 MW 1.12 MW
940492 AE2-034 E Adder 1.11 MW 0.95 MW
941031 AE2-094 C Adder 11.98 MW 10.18 MW
941032 AE2-094 E Adder 5.37 MW 4.56 MW
946281 AF1-292 C Adder 0.65 MW 0.55 MW
946282 AF1-292 E Adder 0.43 MW 0.37 MW
957521 AF2-046 C Adder 5.39 MW 4.58 MW
957522 AF2-046 E Adder 2.72 MW 2.32 MW
957861 AF2-080 C Adder 2.57 MW 2.19 MW
957862 AF2-080 E Adder 1.14 MW 0.97 MW
314539 3UNCAMP Adder 2.37 MW 2.02 MW
916042 Z1-036 E Adder 10.3 MW 8.75 MW
938771 AE1-103 C Adder 1.14 MW 0.97 MW
938772 AE1-103 E Adder 1.58 MW 1.34 MW
314331 6POE 50/50 1.07 MW 1.07 MW
314507 3THOMPSN Adder 0.73 MW 0.62 MW
314525 6KINGFORK Adder 0.38 MW 0.32 MW
314550 6HICKORY Adder 0.77 MW 0.65 MW
315060 1CHESTF5 Adder 19.38 MW 16.47 MW
315065 1CHESTF6 50/50 23.34 MW 23.34 MW
315073 1STONECA 50/50 4.73 MW 4.73 MW
315076 1HOPPOLC 50/50 1.05 MW 1.05 MW
315077 1HOPHCF1 50/50 1.67 MW 1.67 MW
315078 1HOPHCF2 50/50 1.67 MW 1.67 MW
315079 1HOPHCF3 50/50 1.67 MW 1.67 MW
315080 1HOPHCF4 50/50 2.54 MW 2.54 MW
315083 1SPRUNCA Adder 3.09 MW 2.63 MW
315084 1SPRUNCB Adder 3.09 MW 2.63 MW
315092 1YORKTN3 Adder 40.74 MW 34.62 MW
926662 AC1-147 E Adder 0.48 MW 0.41 MW
926755 AC1-161 E Adder 4.16 MW 3.54 MW
927226 AC1-216 E 50/50 4.37 MW 4.37 MW
935112 AD1-144 E Adder 0.35 MW 0.3 MW
942341 AE2-247 C Adder 0.7 MW 0.6 MW
942342 AE2-247 E Adder 0.97 MW 0.83 MW
943461 AF1-017 C Adder 0.64 MW 0.54 MW
943462 AF1-017 E Adder 1.04 MW 0.88 MW
943612 AF1-032 E Adder 0.34 MW 0.29 MW
315260 1GOSPORTA Adder 0.78 MW 0.66 MW
315261 1GOSPORTB Adder 0.99 MW 0.84 MW
315262 1GOSPORTC Adder 0.84 MW 0.71 MW
316132 AB2-190 C 50/50 2.54 MW 2.54 MW
913392 Y1-086 E Adder 0.78 MW 0.67 MW
916192 Z1-068 E Adder 0.67 MW 0.57 MW
923832 AB2-022 E Adder 0.44 MW 0.38 MW
923852 AB2-025 E Adder 0.6 MW 0.51 MW
939312 AE1-162 E Adder 0.61 MW 0.52 MW
946262 AF1-291 E 50/50 1.65 MW 1.65 MW
957492 AF2-043 E Adder 0.52 MW 0.44 MW
901082 W1-029 E Adder 11.48 MW 9.76 MW
917122 Z2-027 E Adder 0.48 MW 0.41 MW
925332 AB2-190 E 50/50 4.94 MW 4.94 MW
925522 AC1-027 E Adder 0.44 MW 0.37 MW
942001 AE2-212 C 50/50 2.12 MW 2.12 MW
942002 AE2-212 E 50/50 1.41 MW 1.41 MW
957871 AF2-081 C Adder 3.54 MW 3.0 MW
957872 AF2-081 E Adder 1.52 MW 1.29 MW
958161 AF2-110 C Adder 0.54 MW 0.46 MW
958162 AF2-110 E Adder 0.86 MW 0.73 MW
917512 Z2-088 E OP1 Adder 1.64 MW 1.39 MW
926071 AC1-086 C Adder 8.52 MW 7.24 MW
926072 AC1-086 E Adder 3.88 MW 3.29 MW
927021 AC1-189 C Adder 2.83 MW 2.41 MW
927022 AC1-189 E Adder 1.41 MW 1.2 MW
933291 AC2-141 C Adder 9.75 MW 8.29 MW
933292 AC2-141 E Adder 4.16 MW 3.54 MW
939411 AE1-173 C Adder 28.95 MW 24.61 MW
939412 AE1-173 E Adder 19.3 MW 16.4 MW
934011 AD1-025 C 50/50 1.47 MW 1.47 MW
934012 AD1-025 E 50/50 5.65 MW 5.65 MW
933981 AD1-022 C Adder 3.18 MW 2.71 MW
933982 AD1-022 E Adder 1.73 MW 1.47 MW
962572 AG1-106 E Adder 0.48 MW 0.41 MW
961681 AG1-008 C Adder 5.39 MW 4.58 MW
961682 AG1-008 E Adder 2.72 MW 2.32 MW
962571 AG1-106 C Adder 1.1 MW 0.94 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
314632 6AYDLETT TAP Adder 0.48 MW 0.41 MW
316240 AF1-291 C 50/50 2.47 MW 2.47 MW
316263 AC1-034 C Adder 2.21 MW 1.88 MW
316274 AC1-208 C Adder 3.55 MW 3.02 MW
316369 AC1-216 C 50/50 0.91 MW 0.91 MW
917332 KELFORD E Adder 0.62 MW 0.53 MW
924516 AB2-100 E1 Adder 1.31 MW 1.11 MW
924517 AB2-100 E2 Adder 1.31 MW 1.11 MW
925595 AC1-034 E Adder 1.67 MW 1.42 MW
926206 AC1-098 E Adder 1.43 MW 1.21 MW
926214 AC1-099 E Adder 0.47 MW 0.4 MW
934065 AD1-033 E Adder 1.77 MW 1.5 MW
937226 AE2-253 E Adder 2.06 MW 1.75 MW
918512 AA1-065 E OP Adder 2.04 MW 1.73 MW
919153 AA1-139 E2 Adder 1.45 MW 1.23 MW
919152 AA1-139 E1 Adder 1.45 MW 1.23 MW
919710 AA2-057 E Adder 1.59 MW 1.35 MW
920692 AA2-178 E Adder 1.48 MW 1.26 MW
923994 AB2-040_E Adder 2.47 MW 2.1 MW
924152 AB2-059 E OP Adder 1.75 MW 1.49 MW
316033 AB2-134 GEN 50/50 1.19 MW 1.19 MW
924814 AB2-134 E 50/50 7.15 MW 7.15 MW
316083 AB2-161 C 50/50 0.33 MW 0.33 MW
316084 AB2-161 E 50/50 3.25 MW 3.25 MW
925122 AB2-169 E Adder 2.02 MW 1.72 MW
316088 AB2-174 E Adder 2.65 MW 2.25 MW
932046 AC2-012 E Adder 4.77 MW 4.05 MW
316311 AC2-079 C Adder 2.65 MW 2.25 MW
932596 AC2-079 E Adder 4.32 MW 3.67 MW
316381 AD1-082 C 50/50 0.74 MW 0.74 MW
934576 AD1-082 E 50/50 2.59 MW 2.59 MW
316349 AD2-085 C Adder 1.62 MW 1.38 MW
936666 AD2-085 E Adder 2.65 MW 2.25 MW
961611 AG1-000B C Adder 7.84 MW 6.67 MW
941591 AE2-156 C Adder 6.51 MW 5.53 MW
944581 AF1-123 C Adder 15.97 MW 13.57 MW
944582 AF1-123 E Adder 36.57 MW 31.09 MW
944591 AF1-124 C Adder 16.03 MW 13.62 MW
944592 AF1-124 E Adder 36.7 MW 31.2 MW
944601 AF1-125 C Adder 15.72 MW 13.37 MW
944602 AF1-125 E Adder 36.0 MW 30.6 MW
944631 AF1-128 C Adder 12.13 MW 10.31 MW
965281 AG1-393 C 50/50 1.29 MW 1.29 MW
965282 AG1-393 E 50/50 0.86 MW 0.86 MW
313764 3SOCKMAN Adder 0.28 MW 0.24 MW
932632 AC2-084 E Adder 1.26 MW 1.07 MW
934321 AD1-056 C Adder 2.26 MW 1.92 MW
934322 AD1-056 E Adder 1.23 MW 1.04 MW
934331 AD1-057 C Adder 1.26 MW 1.07 MW
934332 AD1-057 E Adder 0.66 MW 0.56 MW
934501 AD1-074 C Adder 12.18 MW 10.35 MW
934502 AD1-074 E Adder 6.2 MW 5.27 MW
934511 AD1-075 C Adder 3.05 MW 2.59 MW
934512 AD1-075 E Adder 1.55 MW 1.32 MW
935161 AD1-151 C 50/50 9.53 MW 9.53 MW
935162 AD1-151 E 50/50 6.35 MW 6.35 MW
938531 AE1-072 C Adder 6.22 MW 5.29 MW
938532 AE1-072 E Adder 3.24 MW 2.76 MW
939191 AE1-149 C 50/50 7.19 MW 7.19 MW
939192 AE1-149 E 50/50 4.79 MW 4.79 MW
940431 AE2-027 C 50/50 7.22 MW 7.22 MW
940432 AE2-027 E 50/50 4.81 MW 4.81 MW
940481 AE2-033 C Adder 8.23 MW 6.99 MW
940482 AE2-033 E Adder 5.55 MW 4.71 MW
940541 AE2-040 C Adder 1.48 MW 1.26 MW
940641 AE2-051 C Adder 5.34 MW 4.54 MW
940642 AE2-051 E Adder 3.56 MW 3.02 MW
941101 AE2-104 C Adder 1.32 MW 1.12 MW
941102 AE2-104 E Adder 2.1 MW 1.79 MW
944641 AF1-129 C 50/50 121.71 MW 121.71 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.89 MW 4.89 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.57 MW 4.57 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 24.51 MW 24.51 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.83 MW 0.83 MW
NY PJM->LTFIMP_NY CLTF 0.4 MW 0.4 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.2 MW 0.2 MW
WEC LTFEXP_WEC->PJM CLTF 0.1 MW 0.1 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.11 MW 3.11 MW
TVA LTFEXP_TVA->PJM CLTF 1.3 MW 1.3 MW
MEC LTFEXP_MEC->PJM CLTF 0.71 MW 0.71 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.68 MW 1.68 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.27 MW 5.27 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.48 MW 1.48 MW

Details for 6VARINA-6CHARCTY 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 557_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 101.52 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 999.16 MVA
MW Contribution: 12.13 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
Contingency Name:
DVP_P1-2: LN 557_SRT-S
CONTINGENCY 'DVP_P1-2: LN 557_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.15 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 985.65 MVA
MW Contribution: 11.04 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.31 MW 0.27 MW
961672 AG1-007 E Adder 0.18 MW 0.15 MW
961941 AG1-037 C Adder 0.19 MW 0.16 MW
961942 AG1-037 E Adder 0.13 MW 0.11 MW
962331 AG1-082 C Adder 0.76 MW 0.64 MW
962332 AG1-082 E Adder 0.5 MW 0.43 MW
963041 AG1-153 C Adder 1.68 MW 1.42 MW
963042 AG1-153 E Adder 2.51 MW 2.14 MW
966801 AG1-551 C Adder 0.72 MW 0.62 MW
966802 AG1-551 E Adder 0.38 MW 0.32 MW
966811 AG1-552 C Adder 0.79 MW 0.67 MW
966812 AG1-552 E Adder 0.38 MW 0.32 MW
965291 AG1-394 C Adder 0.33 MW 0.28 MW
965292 AG1-394 E Adder 0.61 MW 0.52 MW
966621 AG1-532 C Adder 0.58 MW 0.5 MW
966622 AG1-532 E Adder 0.39 MW 0.33 MW
314541 3WATKINS Adder 0.27 MW 0.23 MW
314572 3EMPORIA Adder 0.18 MW 0.15 MW
315131 1EDGECMA Adder 5.12 MW 4.35 MW
918492 AA1-063AE OP Adder 1.57 MW 1.33 MW
918532 AA1-067 E Adder 0.24 MW 0.21 MW
919692 AA2-053 E OP Adder 1.61 MW 1.37 MW
920042 AA2-088 E OP Adder 4.1 MW 3.48 MW
925785 AC1-054 E Adder 1.14 MW 0.97 MW
927146 AC1-208 E Adder 1.58 MW 1.34 MW
934521 AD1-076 C Adder 4.42 MW 3.76 MW
934522 AD1-076 E Adder 2.26 MW 1.92 MW
943172 AE2-346 E Adder 0.23 MW 0.19 MW
944011 AF1-069 C Adder 3.91 MW 3.33 MW
944012 AF1-069 E Adder 1.52 MW 1.29 MW
960081 AF2-299 C Adder 0.78 MW 0.66 MW
960082 AF2-299 E Adder 0.52 MW 0.44 MW
316141 AB2-099 E Adder 0.09 MW 0.08 MW
900672 V4-068 E Adder 0.14 MW 0.12 MW
917342 Z2-044 E Adder 0.24 MW 0.21 MW
922923 AB1-081 E OP Adder 1.24 MW 1.06 MW
923263 AB1-132 E OP Adder 2.48 MW 2.11 MW
923573 AB1-173 E OP Adder 1.32 MW 1.12 MW
940492 AE2-034 E Adder 1.11 MW 0.95 MW
941031 AE2-094 C Adder 11.98 MW 10.18 MW
941032 AE2-094 E Adder 5.37 MW 4.56 MW
946281 AF1-292 C Adder 0.65 MW 0.55 MW
946282 AF1-292 E Adder 0.43 MW 0.37 MW
957521 AF2-046 C Adder 5.39 MW 4.58 MW
957522 AF2-046 E Adder 2.72 MW 2.32 MW
957861 AF2-080 C Adder 2.57 MW 2.19 MW
957862 AF2-080 E Adder 1.14 MW 0.97 MW
314539 3UNCAMP Adder 2.37 MW 2.02 MW
916042 Z1-036 E Adder 10.3 MW 8.75 MW
938771 AE1-103 C Adder 1.14 MW 0.97 MW
938772 AE1-103 E Adder 1.58 MW 1.34 MW
314331 6POE 50/50 1.07 MW 1.07 MW
314507 3THOMPSN Adder 0.73 MW 0.62 MW
314525 6KINGFORK Adder 0.38 MW 0.32 MW
314550 6HICKORY Adder 0.77 MW 0.65 MW
315060 1CHESTF5 Adder 19.38 MW 16.47 MW
315065 1CHESTF6 50/50 23.34 MW 23.34 MW
315073 1STONECA 50/50 4.73 MW 4.73 MW
315076 1HOPPOLC 50/50 1.05 MW 1.05 MW
315077 1HOPHCF1 50/50 1.67 MW 1.67 MW
315078 1HOPHCF2 50/50 1.67 MW 1.67 MW
315079 1HOPHCF3 50/50 1.67 MW 1.67 MW
315080 1HOPHCF4 50/50 2.54 MW 2.54 MW
315083 1SPRUNCA Adder 3.09 MW 2.63 MW
315084 1SPRUNCB Adder 3.09 MW 2.63 MW
315092 1YORKTN3 Adder 40.74 MW 34.62 MW
926662 AC1-147 E Adder 0.48 MW 0.41 MW
926755 AC1-161 E Adder 4.16 MW 3.54 MW
927226 AC1-216 E 50/50 4.37 MW 4.37 MW
935112 AD1-144 E Adder 0.35 MW 0.3 MW
942341 AE2-247 C Adder 0.7 MW 0.6 MW
942342 AE2-247 E Adder 0.97 MW 0.83 MW
943461 AF1-017 C Adder 0.64 MW 0.54 MW
943462 AF1-017 E Adder 1.04 MW 0.88 MW
943612 AF1-032 E Adder 0.34 MW 0.29 MW
315260 1GOSPORTA Adder 0.78 MW 0.66 MW
315261 1GOSPORTB Adder 0.99 MW 0.84 MW
315262 1GOSPORTC Adder 0.84 MW 0.71 MW
316132 AB2-190 C 50/50 2.54 MW 2.54 MW
913392 Y1-086 E Adder 0.78 MW 0.67 MW
916192 Z1-068 E Adder 0.67 MW 0.57 MW
923832 AB2-022 E Adder 0.44 MW 0.38 MW
923852 AB2-025 E Adder 0.6 MW 0.51 MW
939312 AE1-162 E Adder 0.61 MW 0.52 MW
946262 AF1-291 E 50/50 1.65 MW 1.65 MW
957492 AF2-043 E Adder 0.52 MW 0.44 MW
901082 W1-029 E Adder 11.48 MW 9.76 MW
917122 Z2-027 E Adder 0.48 MW 0.41 MW
925332 AB2-190 E 50/50 4.94 MW 4.94 MW
925522 AC1-027 E Adder 0.44 MW 0.37 MW
942001 AE2-212 C 50/50 2.12 MW 2.12 MW
942002 AE2-212 E 50/50 1.41 MW 1.41 MW
957871 AF2-081 C Adder 3.54 MW 3.0 MW
957872 AF2-081 E Adder 1.52 MW 1.29 MW
958161 AF2-110 C Adder 0.54 MW 0.46 MW
958162 AF2-110 E Adder 0.86 MW 0.73 MW
917512 Z2-088 E OP1 Adder 1.64 MW 1.39 MW
926071 AC1-086 C Adder 8.52 MW 7.24 MW
926072 AC1-086 E Adder 3.88 MW 3.29 MW
927021 AC1-189 C Adder 2.83 MW 2.41 MW
927022 AC1-189 E Adder 1.41 MW 1.2 MW
933291 AC2-141 C Adder 9.75 MW 8.29 MW
933292 AC2-141 E Adder 4.16 MW 3.54 MW
939411 AE1-173 C Adder 28.95 MW 24.61 MW
939412 AE1-173 E Adder 19.3 MW 16.4 MW
934011 AD1-025 C 50/50 1.47 MW 1.47 MW
934012 AD1-025 E 50/50 5.65 MW 5.65 MW
933981 AD1-022 C Adder 3.18 MW 2.71 MW
933982 AD1-022 E Adder 1.73 MW 1.47 MW
962572 AG1-106 E Adder 0.48 MW 0.41 MW
961681 AG1-008 C Adder 5.39 MW 4.58 MW
961682 AG1-008 E Adder 2.72 MW 2.32 MW
962571 AG1-106 C Adder 1.1 MW 0.94 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
314632 6AYDLETT TAP Adder 0.48 MW 0.41 MW
316240 AF1-291 C 50/50 2.47 MW 2.47 MW
316263 AC1-034 C Adder 2.21 MW 1.88 MW
316274 AC1-208 C Adder 3.55 MW 3.02 MW
316369 AC1-216 C 50/50 0.91 MW 0.91 MW
917332 KELFORD E Adder 0.62 MW 0.53 MW
924516 AB2-100 E1 Adder 1.31 MW 1.11 MW
924517 AB2-100 E2 Adder 1.31 MW 1.11 MW
925595 AC1-034 E Adder 1.67 MW 1.42 MW
926206 AC1-098 E Adder 1.43 MW 1.21 MW
926214 AC1-099 E Adder 0.47 MW 0.4 MW
934065 AD1-033 E Adder 1.77 MW 1.5 MW
937226 AE2-253 E Adder 2.06 MW 1.75 MW
918512 AA1-065 E OP Adder 2.04 MW 1.73 MW
919153 AA1-139 E2 Adder 1.45 MW 1.23 MW
919152 AA1-139 E1 Adder 1.45 MW 1.23 MW
919710 AA2-057 E Adder 1.59 MW 1.35 MW
920692 AA2-178 E Adder 1.48 MW 1.26 MW
923994 AB2-040_E Adder 2.47 MW 2.1 MW
924152 AB2-059 E OP Adder 1.75 MW 1.49 MW
316033 AB2-134 GEN 50/50 1.19 MW 1.19 MW
924814 AB2-134 E 50/50 7.15 MW 7.15 MW
316083 AB2-161 C 50/50 0.33 MW 0.33 MW
316084 AB2-161 E 50/50 3.25 MW 3.25 MW
925122 AB2-169 E Adder 2.02 MW 1.72 MW
316088 AB2-174 E Adder 2.65 MW 2.25 MW
932046 AC2-012 E Adder 4.77 MW 4.05 MW
316311 AC2-079 C Adder 2.65 MW 2.25 MW
932596 AC2-079 E Adder 4.32 MW 3.67 MW
316381 AD1-082 C 50/50 0.74 MW 0.74 MW
934576 AD1-082 E 50/50 2.59 MW 2.59 MW
316349 AD2-085 C Adder 1.62 MW 1.38 MW
936666 AD2-085 E Adder 2.65 MW 2.25 MW
961611 AG1-000B C Adder 7.84 MW 6.67 MW
941591 AE2-156 C Adder 6.51 MW 5.53 MW
944581 AF1-123 C Adder 15.97 MW 13.57 MW
944582 AF1-123 E Adder 36.57 MW 31.09 MW
944591 AF1-124 C Adder 16.03 MW 13.62 MW
944592 AF1-124 E Adder 36.7 MW 31.2 MW
944601 AF1-125 C Adder 15.72 MW 13.37 MW
944602 AF1-125 E Adder 36.0 MW 30.6 MW
944631 AF1-128 C Adder 12.13 MW 10.31 MW
965281 AG1-393 C 50/50 1.29 MW 1.29 MW
965282 AG1-393 E 50/50 0.86 MW 0.86 MW
313764 3SOCKMAN Adder 0.28 MW 0.24 MW
932632 AC2-084 E Adder 1.26 MW 1.07 MW
934321 AD1-056 C Adder 2.26 MW 1.92 MW
934322 AD1-056 E Adder 1.23 MW 1.04 MW
934331 AD1-057 C Adder 1.26 MW 1.07 MW
934332 AD1-057 E Adder 0.66 MW 0.56 MW
934501 AD1-074 C Adder 12.18 MW 10.35 MW
934502 AD1-074 E Adder 6.2 MW 5.27 MW
934511 AD1-075 C Adder 3.05 MW 2.59 MW
934512 AD1-075 E Adder 1.55 MW 1.32 MW
935161 AD1-151 C 50/50 9.53 MW 9.53 MW
935162 AD1-151 E 50/50 6.35 MW 6.35 MW
938531 AE1-072 C Adder 6.22 MW 5.29 MW
938532 AE1-072 E Adder 3.24 MW 2.76 MW
939191 AE1-149 C 50/50 7.19 MW 7.19 MW
939192 AE1-149 E 50/50 4.79 MW 4.79 MW
940431 AE2-027 C 50/50 7.22 MW 7.22 MW
940432 AE2-027 E 50/50 4.81 MW 4.81 MW
940481 AE2-033 C Adder 8.23 MW 6.99 MW
940482 AE2-033 E Adder 5.55 MW 4.71 MW
940541 AE2-040 C Adder 1.48 MW 1.26 MW
940641 AE2-051 C Adder 5.34 MW 4.54 MW
940642 AE2-051 E Adder 3.56 MW 3.02 MW
941101 AE2-104 C Adder 1.32 MW 1.12 MW
941102 AE2-104 E Adder 2.1 MW 1.79 MW
944641 AF1-129 C 50/50 121.71 MW 121.71 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 4.89 MW 4.89 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.57 MW 4.57 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 24.51 MW 24.51 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.83 MW 0.83 MW
NY PJM->LTFIMP_NY CLTF 0.4 MW 0.4 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.2 MW 0.2 MW
WEC LTFEXP_WEC->PJM CLTF 0.1 MW 0.1 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.11 MW 3.11 MW
TVA LTFEXP_TVA->PJM CLTF 1.3 MW 1.3 MW
MEC LTFEXP_MEC->PJM CLTF 0.71 MW 0.71 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.68 MW 1.68 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.27 MW 5.27 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.48 MW 1.48 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request was evaluated as a 411.5 MW injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Light Load Potential Congestion due to Local Energy Deliverability

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 48 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 48 project.

 

Table 1: Transition Cycle 1 Cluster 48 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

48

AF1-128

Natural Gas

Dominion

569

569

569

Chesterfield 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 48 project will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2027 light load case, modified to include applicable projects. Projects in vicinity of Cluster 48 have been dispatched online at maximum power output with electrically close generators dispatched near 50% of the respective units minimum reactive power output.

 

Cluster 48 were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 126 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 light load case:

 

  • Cluster 48 was able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 48 included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes in Dominion area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus)
  • For Dominion area, the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The transmission system being studied met the evaluation criteria. Below are some notable results.

 

AD2-074 was observed to trip on overvoltage (1.11 p.u. for 1 second and 1.2 p.u. for 0.001 second) for a number of P1 contingencies. Terminal voltage plots showed that the controller for this unit was freezing and not absorbing reactive power within the studied 20 second simulation. After reviewing the dynamic model, it was found that the REGCA model for this unit had reactive power ramp rate parameters Iqrmax and Iqrmin set to 0.02 and -0.02 p.u. respectively. These values are typically set much higher to allow the unit to respond to voltage variations quicker. Therefore, these values were increased to 100 and -100 p.u.. AD2-074 was then able to reduce the voltage post fault which prevented the unit from tripping on the 1.1 p.u. setpoint. The unit was still tripping for the 1.2 p.u. setpoint because of the low time delay (0.001 second). This time delay was increased slightly to 0.0167s. These changes enabled the unit to ride through all faults.

 

Surry units reactive response took over 20 seconds to settle for some contingencies. A longer 40 second test simulation was conducted which demonstrated that the unit settled shortly after 20 seconds shown in Figure 1 below. Slow settling is not a criteria violation and will not affect the results of the study.

 

AD1-151 reactive power was found to have some oscillations post fault that are positively damped with adequate damping ratio. This is not a criteria violation.

 

AB2-134 unit reactive power was found to not settle during the 20 second simulation. The following adjustments were made:

 

  • REPCA CON (J+1) Kp was adjusted to 1
  • REPCA CON (J+2) Ki was adjusted to 5

 

After these adjustments, the reactive power settlement improved but it did not settle within 20 seconds for some contingencies. This is not criteria violation. The developer should be requested to tune the dynamic model.

AB2-190 units reactive power was found to not settle during the 20 second simulation. The following adjustments were made:

  • PLNTBU1 CON (J+1) Kp was adjusted to 1
  • PLNTBU1 CON (J+2) Ki was adjusted to 5
  • PLNTBU1 CON (J+8) Kc was adjusted to 0.04

 

After these adjustments, the reactive power settlement improved but it did not settle within 20 seconds for some contingencies. This is not criteria violation. The developer should be requested to tune the dynamic model.

 

AG1-154 reactive power was observed to not settle during the 20 second simulation. The following adjustments were made:

 

  • REPCA CON (J+8) Kc was adjusted to 0.04

 

This adjustment improved the reactive power settlement for all contingencies.

 

No mitigation was required.

Reactive Power Analysis

The AF1-128 facility met the 0.95 leading and 0.9 lagging power factor requirements at the generators terminals.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA1-063A Carolina–Seaboard 115kV In Service
AA1-065 Earleys 230kV In Service
AA1-139 Hickory-Shawboro 230kV In Service
AA1-145 Four Rivers 230kV In Service
AA2-088 Boykins-Handsome 115kV In Service
AA2-178 Mackeys 230kV In Service
AB1-027 Old Church 34.5 KV In Service
AB2-022 Elizabeth City 34.5kV In Service
AB2-024 Correctional 34.5kV In Service
AB2-025 Sapony 34.5kV In Service
AB2-026 Powhatan 34.5kV In Service
AB2-099 Ahoskie 34.5kV In Service
AB2-100 Clubhouse-Lakeview 230kV In Service
AB2-134 Hopewell-Surry 230kV In Service
AB2-161 Waverly #2 DP 115kV In Service
AB2-174 Emporia-Trego 115kV In Service
AB2-190 Hopewell-Surry 230kV In Service
AC1-027 Pendleton 34.5kV In Service
AC1-034 Heartsease DP - Mayo Dunbar 115kV Suspended
AC1-065 Harmony Village-Shackleford 115kV Under Construction
AC1-086 Thelma 230kV Suspended
AC1-098 Dawson-South Justice 115kV Under Construction
AC1-112 Old Church 34.5kV In Service
AC1-118 Westmoreland 34.5kV In Service
AC1-147 Grassfield 34.5kV In Service
AC1-161 Septa 500kV In Service
AC1-164 Chickahominy 230kV Partially in Service - Under Construction
AC1-189 Chinquapin-Everetts 230kV Engineering & Procurement
AC1-191 Elmont 115kV Engineering & Procurement
AC1-208 Cox-Whitakers 115kV Under Construction
AC1-216 Hopewell-Surry 230kV In Service
AC2-012 Grassfield-Great Bridge 115kV In Service
AC2-079 Ivor-Oak Ridge 115kV Suspended
AC2-137 Elko 34.5kV In Service
AC2-138 Northern Neck 34.5kV In Service
AC2-141 Septa 500kV Engineering & Procurement
AC2-165 Bremo-Powhatan 230kV Suspended
AD1-022 Cashie-Trowbridge 230 kV Engineering & Procurement
AD1-025 Hopewell-Surry 230 kV Under Construction
AD1-033 Fentress-Landstown 230 kV In Service
AD1-041 Harmony Village-Shackleford 115 kV In Service
AD1-056 Hornertown-Hathaway 230 kV Suspended
AD1-057 Hornertown-Hathaway 230 kV Suspended
AD1-063 Harmony Village 34.5 kV In Service
AD1-074 Trowbridge 230 kV Engineering & Procurement
AD1-075 Trowbridge 230 kV Engineering & Procurement
AD1-076 Trowbridge 230 kV Engineering & Procurement
AD1-082 Bakers Pond-Ivor 115kV In Service
AD1-087 Clover-Sedge Hill 230 kV In Service
AD1-088 Briery-Clover 230 kV Suspended
AD1-105 Kings Dominion DP 115 kV Under Construction
AD1-144 Kings Fork 34.5 kV In Service
AD1-151 Hopewell-Surry 230 kV Suspended
AD2-030 Wan 34.5 kV In Service
AD2-033 Chase City-Lunenburg 115 kV Engineering & Procurement
AD2-073 Sanders DP 230 kV In Service
AD2-074 Garner DP-Lancaster 115 kV Engineering & Procurement
AD2-085 Myrtle-Windsor DP 115kV Engineering & Procurement
AD2-202 Clover-Sedge Hill 230kV In Service
AE1-056 Red House-South Creek 115 kV Suspended
AE1-072 Shawboro-Sligo 230 kV Engineering & Procurement
AE1-074 Winterpock 34.5 kV Under Construction
AE1-075 Powhatan 34.5 kV In Service
AE1-103 Holland-Union Camp 115 kV Under Construction
AE1-148 Kerr Dam-Ridge Rd 115 kV Active
AE1-149 Disputanta-Poe 115 kV Suspended
AE1-155 Garner-Northern Neck 115 kV In Service
AE1-157 Ladysmith CT-St. Johns 230 kV Suspended
AE1-162 Smithfield 34.5 kV In Service
AE1-173 Carson-Suffolk 500 kV Under Construction
AE1-175 Light Foot 34.5 kV In Service
AE1-190 Harmony Village-Shackleford 115 kV Partially in Service - Under Construction
AE1-191 Harmony Village-Shackleford 115 kV Partially in Service - Under Construction
AE2-027 Harrowgate-Locks 115kV Suspended
AE2-033 Clubhouse-Sapony 230 kV Suspended
AE2-034 Mackeys 230 kV Partially in Service - Under Construction
AE2-040 Sapony 34.5 kV Under Construction
AE2-041 Harmony Village 230 kV Engineering & Procurement
AE2-051 Carson-Septa 500 kV Engineering & Procurement
AE2-094 Carson-Rogers Road 500 kV Engineering & Procurement
AE2-104 Suffolk 115 kV Suspended
AE2-156 Yadkin 115 kV Active
AE2-212 Harrowgate 34 kV Engineering & Procurement
AE2-247 Myrtle-Windsor 115 kV Engineering & Procurement
AE2-253 Hickory-Moyock 230 kV In Service
AE2-259 Curdsville-Willis Mtn 115 kV Engineering & Procurement
AE2-346 Ahoskie 34.5 kV In Service
AF1-017 Myrtle-Windsor 115 kV Engineering & Procurement
AF1-018 Harmony Village 230 kV Engineering & Procurement
AF1-028 Endless Caverns 115 kV Under Construction
AF1-032 Suffolk 34.5 kV In Service
AF1-042 Garner DP-Lancaster 115 kV Engineering & Procurement
AF1-069 Carson-Rogers Rd 500 kV Engineering & Procurement
AF1-114 Oak Grove-Dahlgren 230 kV Engineering & Procurement
AF1-123 Oceana 230 kV Active
AF1-124 Oceana 230 kV Active
AF1-125 Oceana 230 kV Active
AF1-129 Chesterfield 230 kV Engineering & Procurement
AF1-291 Tyler 34.5 kV Engineering & Procurement
AF1-292 Fields 34.5kV Engineering & Procurement
AF1-294 Jetersville-Ponton 115 kV Active
AF2-013 Arnold's Corner-Dahlgren 230 kV Engineering & Procurement
AF2-035 St. Johns 115 kV Active
AF2-042 Clover-Rawlings 500 kV Active
AF2-043 Suffolk 34.5 kV In Service
AF2-046 Tunis-Mapleton 115 kV Active
AF2-054 Wan 34.5 kV In Service
AF2-077 White Marsh 34.5 kV In Service
AF2-080 Chinquapin-Everetts 230 kV Active
AF2-081 Moyock 230 kV Active
AF2-085 Midlothian 34.5 kV In Service
AF2-091 Oak Grove-Dahlgren 230 kV Engineering & Procurement
AF2-110 Suffolk 115 kV Suspended
AF2-115 Jetersville-Ponton 115 kV Active
AF2-120 Garner-Northern Neck 115 kV Active
AF2-144 Powhatan 34.5 kV In Service
AF2-222 Madisonville DP-Twitty's Creek 115 kV Active
AF2-297 Sedge Hill 115 kV Active
AF2-299 Fields 34.5 kV Active
AG1-007 Tar River 12.5 kV Engineering & Procurement
AG1-008 Tunis-Mapleton 115 kV Active
AG1-021 Jetersville-Ponton 115 kV Active
AG1-037 Ahoskie 34.5 kV Engineering & Procurement
AG1-038 Garner DP-Lancaster 115 kV Engineering & Procurement
AG1-082 Ahoskie 34.5 kV Active
AG1-098 Briery-Clover 230 kV Active
AG1-105 Mount Laurel-Barnes Junction 115 kV Active
AG1-106 Thelma 230 kV Active
AG1-135 Garner-Lancaster 115 kV Active
AG1-145 Lightfoot 34.5 kV In Service
AG1-146 Garner DP-Lancaster 115 kV Active
AG1-147 Garner DP-Lancaster 115 kV Active
AG1-153 Heritage 500 kV Active
AG1-154 Ladysmith CT 230 kV Active
AG1-166 Lone Pine 115 kV Active
AG1-167 Lone Pine 115 kV Active
AG1-168 Lone Pine 115 kV Active
AG1-210 Northern Neck 34.5 kV Engineering & Procurement
AG1-282 Dunnsville 34.5 kV Engineering & Procurement
AG1-285 Chase City-Central 115 kV Active
AG1-342 Dryburg 115 kV Active
AG1-393 Fort Pickett DP 34.5 kV Active
AG1-394 Boykins 34.5 kV Active
AG1-532 Fields 34.5 kV Engineering & Procurement
AG1-536 Garner-Northern Neck 115 kV Active
AG1-551 Parmele 34.5 kV Active
AG1-552 Carolina 34.5 kV Active
AG1-558 Buckner 34.5 kV Engineering & Procurement
AG1-559 Caroline Pines 22 kV Engineering & Procurement
V4-068 Murphy's 34.5kV In Service
W1-029 Winfall 230kV In Service
Y1-086 Morgans Corner In Service
Z1-036 WinFall-Chowan 230kV In Service
Z1-068 Birdneck 34.5kV In Service
Z2-027 Pasquotank 34.5kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase III System Impact Study load flow analysis.

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF1-128


AF1-128 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF1-128 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AF1-128 One Line Diagram

AF1-128 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.