AF1-176 Phase III Study Report

v1.00 released 2025-09-18 16:26

Corey 138 kV

155.682 MW Capacity / 300.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Three Lakes Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $53,450,259 $11,225,348 = 4.76 AND ( $53,450,259 - $11,225,348 ) 300.0 = $140,750 per MW

General

The Project Developer has proposed a Solar/Storage generating facility located in the American Electric Power zone — St. Joseph County, Michigan. The installed facilities will have a total capability of 300.0 MW with 155.682 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF1-176
Project Name:
Corey 138 kV
Project Developer Name:
Three Lakes Solar LLC
State:
Michigan
County:
St. Joseph
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
300.0
MWE:
300.0
MWC:
155.682
Battery Storage Specification:
486.32 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Solar/Storage
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF1-176 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system at the Corey 138 kV substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF1-176 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF1-176 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $1,095,657 $1,095,657
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $1,996,401 $1,996,401
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $23,682,596 $23,682,596
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $26,274,960 $0
AFS - Non-PJM Violations $1,496,302 $0
Total $54,545,916 $26,774,654

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF1-176

Security has been calculated for the AF1-176 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF1-176
Project(s): AF1-176
Final Agreement Security (A): $26,774,654
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $26,774,654
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

AF1-176 will interconnect with the AEP transmission system via a direct connection to the Corey 138 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9614.0

Corey 138 kV Station: Re-terminate Kenzie Creek - Corey 138 kV line. • Remove one (1) steel dead-end structure and associated conductor and shield wire along the Kenzie Creek – Corey 138 kV Circuit. • Install one (1) new 100’ steel, single-circuit, single-pole dead-end structure on a concrete foundation with an anchor bolt cage and two spans of aluminum conductor steel-reinforced 1033.5 (Curlew) transmission line conductor with 7#8 Alumoweld shield wire.

$372,152 $129,068 $66,941 $23,216 $591,377 $591,377
n9613.0

Corey 138 kV Station: • Installation of one (1) new 3000A 40 kA 138 kV circuit breaker with associated control relaying. • Installation of one (1) three-phase 3000A circuit breaker disconnect switch. • Installation of one (1) three-phase coupling capacitor voltage transformer and associated structures for the line exit to the Hydramatic 138 kV Station. • Installation of one (1) H-frame dead-end structure for the line exit to the Hydramatic 138 kV Station. • Installation of associated and additional buswork, bus supports, jumpers, insulators, grounding, and foundations.

$471,817 $278,029 $34,084 $20,085 $804,015 $804,015
n9612.0

Corey 1385 kV Station: Re-terminate the Hydramatic - Corey 138 kV circuit. • Remove two (2) steel tangent structures, one (1) steel dead-end structure, and associated conductor and shield wire along the existing Corey – Hydramatic 138 kV circuit. • Install one (1) new 90’ steel, single-circuit, single-pole, running corner direct embedded structure. • Install one (1) new 90’ steel, single-circuit, single-pole dead-end structure on a concrete foundation with an anchor bolt cage. • Install two (2) spans of alumunim conductor steel-reinforced 1033.5 (Curlew) transmission line conductor with 7#8 Alumoweld shield wire.

$312,808 $149,666 $93,702 $44,833 $601,009 $601,009
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

• Installation of a dual, direct fiber-based current differential relaying protection scheme for the generation lead circuit. • Extension of two (2) underground 48 count all dielectric loose tube (ADLT) fiber optic cables from the Corey 138 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the Corey 138 kV and Project Developer's collector stations. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station. • Installation of a standard revenue metering package, including three (3) single-phase current transformers (CT), three (3) single-phase voltage transformers (VT), associated structures and foundations, one (1) ethernet switch, and one (1) drop-in control module (DICM)-installed metering panel, for the generation lead circuit at the Corey 138 kV station. • Review and revision of the protective relay settings for the remainder of the Corey 138 kV Station.

$632,240 $310,507 $103,733 $49,177 $1,095,657 $1,095,657

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 25 to 26 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

Transmission Owner Identified Network Impacts

There were no network impacts to Distribution facilities identified by the Transmission Owner.

The Transmission Owner identified network impacts to Sub-Regional facilities as follows:

Transmission Owner Identified System Reinforcements on Sub-Regional Facilities
Overloaded Element Contingency Rating [MVA] Final Cycle Loading % Contribution [MW]
246464 05LAKE ST 69.0 - 246477 05NILES 69.0 CKT 1 AEP_P4_#9221_05KENZIE 138_J_SRT-A
CONTINGENCY 'AEP_P4_#9221_05KENZIE 138_J_SRT-A'
 OPEN BRANCH FROM BUS 243028 TO BUS 243631 CKT 1   /*05LAKEHEAD   138.0 - 05SURGES RD  138.0
 OPEN BRANCH FROM BUS 243322 TO BUS 243360 CKT 1   /*05KENZIE     138.0 - 05POKAGO     138.0
 OPEN BRANCH FROM BUS 243322 TO BUS 247539 CKT 1   /*05KENZIE     138.0 - 05KENZIE      69.0
 OPEN BRANCH FROM BUS 243360 TO BUS 243631 CKT 1   /*05POKAGO     138.0 - 05SURGES RD  138.0
END
73.0 116.1 % 20.17
Transmission Owner Identified System Reinforcements
AF1-176 Transmission Owner Identified System Reinforcements Cost Breakdown:
TO RTEP ID / TO ID Category Title MW Impact Percent Allocation Allocated Cost ($USD) Facilities Study
Grand Total: $0

System Reinforcement: s2167.8
TO
AEP
RTEP ID / TO ID
s2167.8 / AEP_TC1_88
Category
SubRegional
Title
Line being rebuilt under TP2019142, s2167
Description
Line being rebuilt under TP2019142, s2167 Projected ISD 11-3-2025 246464 05LAKE ST 69.0 - 246477 05NILES 69.0 CKT 1
Total Cost
$22,800,000
Contingent

Note: Although Queue Project AF1-176 may not have cost responsibility for this upgrade, Queue Project AF1-176 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AF1-176 comes into service prior to completion of the upgrade, Queue Project AF1-176 will need an interim study.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AF1-176 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 300.0 MW (155.68 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
ATSI/ITCT 19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
ATSI_P7-1_TE-345-025T_SRT-A-2
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-2'
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
 DISCONNECT BRANCH FROM BUS 264599 TO BUS 955780 CKT 1   /*19MAJTC      345.0 - J1062 POI    345.0
END
Tower AC 101.76 % 1660.0 B 1689.24 29.27
ATSI/METC 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
256583 to 238530 ckt 1
ATSI_P7-1_TE-345-022T_SRT-A-1_SENS
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-1_SENS'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 264594 CKT 1   /*02LEMOYN     345.0 - 19LULU       345.0
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
END
Tower AC 111.86 % 1793.0 B 2005.59 34.27
ATSI/ITCT 19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
ATSI_P7-1_TE-345-025T_SRT-A-1_SENS
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-1_SENS'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 264594 CKT 1   /*02LEMOYN     345.0 - 19LULU       345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
END
Tower AC 104.14 % 1660.0 B 1728.76 29.27

Details for 19MON12-02LALLENDORF 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-025T_SRT-A-2


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: ATSI/ITCT
Facility Description:
19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-025T_SRT-A-2
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-2'
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
 DISCONNECT BRANCH FROM BUS 264599 TO BUS 955780 CKT 1   /*19MAJTC      345.0 - J1062 POI    345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 101.76 %
Rating: 1660.0 MVA
Rating Type: B
MVA to Mitigate: 1689.24 MVA
MW Contribution: 29.27 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: ATSI/ITCT
Facility Description:
19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-025T_SRT-A-2
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-2'
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
 DISCONNECT BRANCH FROM BUS 264599 TO BUS 955780 CKT 1   /*19MAJTC      345.0 - J1062 POI    345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 112.55 %
Rating: 1660.0 MVA
Rating Type: B
MVA to Mitigate: 1868.38 MVA
MW Contribution: 29.61 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965681 AG1-436 C Adder 5.61 MW 4.77 MW
965682 AG1-436 E Adder 3.74 MW 3.18 MW
966431 AG1-512 C Adder 1.14 MW 0.96 MW
966432 AG1-512 E Adder 1.7 MW 1.45 MW
247528 05COVRT1 50/50 4.64 MW 4.64 MW
247529 05COVRT2 50/50 4.64 MW 4.64 MW
247530 05COVRT3 50/50 4.64 MW 4.64 MW
247531 05COVRT4 50/50 2.79 MW 2.79 MW
247532 05COVRT5 50/50 2.77 MW 2.77 MW
247533 05COVRT6 50/50 2.27 MW 2.27 MW
247966 05WTRV SLR E 50/50 0.25 MW 0.25 MW
247967 05OLIV SLR E Adder 0.21 MW 0.18 MW
247969 Z2-116 E Adder 0.12 MW 0.1 MW
910542 X3-005 E Adder 0.4 MW 0.34 MW
943001 AE2-323 C Adder 5.11 MW 4.34 MW
943002 AE2-323 E Adder 2.51 MW 2.13 MW
943021 AE2-325 C 50/50 3.15 MW 3.15 MW
943022 AE2-325 E 50/50 2.1 MW 2.1 MW
944161 AF1-084 C 50/50 5.55 MW 5.55 MW
944162 AF1-084 E 50/50 3.17 MW 3.17 MW
944961 AF1-161 C 50/50 2.51 MW 2.51 MW
945641 AF1-229 C Adder -7.25 MW -6.16 MW
960681 AF2-359 C Adder 5.61 MW 4.77 MW
960682 AF2-359 E Adder 3.74 MW 3.18 MW
960841 AF2-375 C Adder -7.25 MW -6.16 MW
960981 AF2-389 C Adder 2.89 MW 2.46 MW
960982 AF2-389 E Adder 1.93 MW 1.64 MW
243071 05BERRINSP G 50/50 0.05 MW 0.05 MW
244412 05WTRV SLR C 50/50 0.04 MW 0.04 MW
274675 JOLIET 29;7U Adder 37.59 MW 31.95 MW
274676 JOLIET 29;8U Adder 37.59 MW 31.95 MW
274687 WILL CNTY;4U Adder 34.99 MW 29.74 MW
274788 SE CHICAG;5U Adder 2.64 MW 2.25 MW
274789 SE CHICAG;6U Adder 2.64 MW 2.25 MW
274790 SE CHICAG;7U Adder 2.64 MW 2.25 MW
274791 SE CHICAG;8U Adder 2.64 MW 2.25 MW
274792 SE CHICAG;9U Adder 2.65 MW 2.25 MW
274793 SE CHICAG;0U Adder 2.65 MW 2.25 MW
274794 SE CHICAG;1U Adder 2.65 MW 2.25 MW
274795 SE CHICAG;2U Adder 2.65 MW 2.25 MW
933411 AC2-154 C Adder 1.31 MW 1.11 MW
933412 AC2-154 E Adder 2.14 MW 1.82 MW
941781 AE2-181 C Adder -2.72 MW -2.31 MW
247604 X1-042 50/50 0.07 MW 0.07 MW
275149 KELLYCK ;1E Adder 9.67 MW 8.22 MW
293519 PILOT HIL;1E Adder 9.67 MW 8.22 MW
936632 AD2-079 E O1 Adder 0.72 MW 0.62 MW
936141 AD2-020 C 50/50 6.22 MW 6.22 MW
936371 AD2-047 C Adder 2.35 MW 2.0 MW
936372 AD2-047 E Adder 11.47 MW 9.75 MW
936461 AD2-060 C Adder 1.38 MW 1.17 MW
944932 AF1-158 E Adder 5.19 MW 4.41 MW
945111 AF1-176 C Adder 15.19 MW 12.91 MW
945112 AF1-176 E Adder 14.08 MW 11.97 MW
945421 AF1-207 C Adder 2.36 MW 2.01 MW
945422 AF1-207 E Adder 10.16 MW 8.63 MW
945502 AF1-215 E Adder 9.05 MW 7.69 MW
959141 AF2-205 C Adder 8.69 MW 7.38 MW
959142 AF2-205 E Adder 5.79 MW 4.92 MW
960591 AF2-350 C Adder 4.14 MW 3.52 MW
960592 AF2-350 E Adder 2.76 MW 2.35 MW
961051 AF2-396 C Adder 19.89 MW 16.91 MW
961501 AF2-441 C Adder 5.67 MW 4.82 MW
961502 AF2-441 E Adder 8.5 MW 7.22 MW
939391 AE1-170 C Adder 6.1 MW 5.19 MW
939392 AE1-170 E Adder 8.43 MW 7.17 MW
940581 AE2-045 C Adder 6.04 MW 5.13 MW
940582 AE2-045 E Adder 8.29 MW 7.05 MW
962601 AG1-109 C 50/50 2.51 MW 2.51 MW
964401 AG1-302 C Adder 13.3 MW 11.3 MW
964402 AG1-302 E Adder 8.87 MW 7.54 MW
936142 AD2-020 E 50/50 3.83 MW 3.83 MW
957371 AF2-031 C Adder 0.57 MW 0.49 MW
957372 AF2-031 E Adder 0.86 MW 0.73 MW
957841 AF2-078 C Adder 8.35 MW 7.09 MW
957842 AF2-078 E Adder 5.56 MW 4.73 MW
957891 AF2-083 C Adder 9.63 MW 8.19 MW
957892 AF2-083 E Adder 4.82 MW 4.09 MW
958011 AF2-095 C Adder 5.97 MW 5.07 MW
958012 AF2-095 E Adder 3.98 MW 3.38 MW
958381 AF2-132 C Adder 13.3 MW 11.3 MW
958382 AF2-132 E Adder 8.87 MW 7.54 MW
958391 AF2-133 C Adder 13.12 MW 11.16 MW
958392 AF2-133 E Adder 8.75 MW 7.44 MW
958402 AF2-134 E Adder 3.02 MW 2.56 MW
964861 AG1-349 C Adder 11.48 MW 9.76 MW
964862 AG1-349 E Adder 7.65 MW 6.5 MW
965791 AG1-447 C Adder 4.12 MW 3.5 MW
939161 AE1-146 C Adder -6.96 MW -5.92 MW
943961 AF1-064 C Adder -3.65 MW -3.1 MW
990142 J1224 G External Queue 34.11 MW 34.11 MW
990527 J1329 G External Queue 4.03 MW 4.03 MW
991182 J1586 G External Queue 48.2 MW 48.2 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 217.98 MW 217.98 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 24.24 MW 24.24 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 8.23 MW 8.23 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.0 MW 2.0 MW
NY PJM->LTFIMP_NY CLTF 1.23 MW 1.23 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.74 MW 1.74 MW
WEC LTFEXP_WEC->PJM CLTF 2.13 MW 2.13 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.39 MW 0.39 MW
TVA LTFEXP_TVA->PJM CLTF 3.62 MW 3.62 MW
MEC LTFEXP_MEC->PJM CLTF 8.66 MW 8.66 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.24 MW 5.24 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.39 MW 0.39 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 12.9 MW 12.9 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.19 MW 0.19 MW

Details for 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-022T_SRT-A-1_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: ATSI/METC
Facility Description:
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
256583 to 238530 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-022T_SRT-A-1_SENS
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-1_SENS'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 264594 CKT 1   /*02LEMOYN     345.0 - 19LULU       345.0
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 111.86 %
Rating: 1793.0 MVA
Rating Type: B
MVA to Mitigate: 2005.59 MVA
MW Contribution: 34.27 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243353 05OLIVE 50/50 0.08 MW 0.08 MW
965681 AG1-436 C Adder 6.55 MW 5.56 MW
965682 AG1-436 E Adder 4.36 MW 3.71 MW
246397 05ELKHART HY 50/50 0.03 MW 0.03 MW
246422 05MAYFLWER 50/50 0.1 MW 0.1 MW
246431 05BUCHANAN 50/50 0.04 MW 0.04 MW
247528 05COVRT1 50/50 5.45 MW 5.45 MW
247529 05COVRT2 50/50 5.45 MW 5.45 MW
247530 05COVRT3 50/50 5.45 MW 5.45 MW
247531 05COVRT4 50/50 3.28 MW 3.28 MW
247532 05COVRT5 50/50 3.25 MW 3.25 MW
247533 05COVRT6 50/50 2.67 MW 2.67 MW
247620 Y3-023 50/50 0.08 MW 0.08 MW
247643 Z2-116 C 50/50 0.02 MW 0.02 MW
247966 05WTRV SLR E 50/50 0.29 MW 0.29 MW
247967 05OLIV SLR E 50/50 0.25 MW 0.25 MW
247969 Z2-116 E 50/50 0.14 MW 0.14 MW
943001 AE2-323 C Adder 5.81 MW 4.94 MW
943002 AE2-323 E Adder 2.85 MW 2.42 MW
943021 AE2-325 C 50/50 3.69 MW 3.69 MW
943022 AE2-325 E 50/50 2.46 MW 2.46 MW
944161 AF1-084 C 50/50 6.5 MW 6.5 MW
944162 AF1-084 E 50/50 3.71 MW 3.71 MW
944961 AF1-161 C 50/50 2.94 MW 2.94 MW
945641 AF1-229 C Adder -8.62 MW -7.32 MW
960681 AF2-359 C Adder 6.55 MW 5.56 MW
960682 AF2-359 E Adder 4.36 MW 3.71 MW
960841 AF2-375 C Adder -9.3 MW -7.9 MW
960981 AF2-389 C 50/50 3.38 MW 3.38 MW
960982 AF2-389 E 50/50 2.26 MW 2.26 MW
243071 05BERRINSP G 50/50 0.06 MW 0.06 MW
243440 05CKG1 50/50 18.64 MW 18.64 MW
244412 05WTRV SLR C 50/50 0.05 MW 0.05 MW
244415 05OLIV SLR C 50/50 0.04 MW 0.04 MW
270142 AA2-116_CT1 50/50 6.83 MW 6.83 MW
270143 AA2-116_CT2 50/50 6.83 MW 6.83 MW
270144 AA2-116_ST 50/50 6.04 MW 6.04 MW
274788 SE CHICAG;5U Adder 3.08 MW 2.62 MW
274789 SE CHICAG;6U Adder 3.08 MW 2.62 MW
274790 SE CHICAG;7U Adder 3.08 MW 2.62 MW
274791 SE CHICAG;8U Adder 3.08 MW 2.62 MW
274792 SE CHICAG;9U Adder 3.09 MW 2.62 MW
274793 SE CHICAG;0U Adder 3.09 MW 2.62 MW
274794 SE CHICAG;1U Adder 3.09 MW 2.62 MW
274795 SE CHICAG;2U Adder 3.09 MW 2.62 MW
941781 AE2-181 C Adder -7.38 MW -6.27 MW
243352 05NTRDAM 50/50 0.97 MW 0.97 MW
246416 05TWIN BRNCH 50/50 0.03 MW 0.03 MW
246476 05NILES 50/50 0.02 MW 0.02 MW
246477 05NILES 50/50 0.02 MW 0.02 MW
246536 05MOTTVILLE 50/50 0.01 MW 0.01 MW
247604 X1-042 50/50 0.08 MW 0.08 MW
270216 AD2-079_C O1 50/50 0.21 MW 0.21 MW
936632 AD2-079 E O1 50/50 0.85 MW 0.85 MW
936141 AD2-020 C 50/50 7.29 MW 7.29 MW
944931 AF1-158 C 50/50 1.45 MW 1.45 MW
944932 AF1-158 E 50/50 6.06 MW 6.06 MW
945111 AF1-176 C 50/50 17.78 MW 17.78 MW
945112 AF1-176 E 50/50 16.48 MW 16.48 MW
945502 AF1-215 E Adder 10.56 MW 8.97 MW
959141 AF2-205 C Adder 10.13 MW 8.61 MW
959142 AF2-205 E Adder 6.75 MW 5.74 MW
961051 AF2-396 C 50/50 23.29 MW 23.29 MW
939391 AE1-170 C 50/50 7.15 MW 7.15 MW
939392 AE1-170 E 50/50 9.87 MW 9.87 MW
940581 AE2-045 C Adder 7.04 MW 5.99 MW
940582 AE2-045 E Adder 9.67 MW 8.22 MW
962601 AG1-109 C 50/50 2.94 MW 2.94 MW
964401 AG1-302 C Adder 15.51 MW 13.18 MW
964402 AG1-302 E Adder 10.34 MW 8.79 MW
936142 AD2-020 E 50/50 4.49 MW 4.49 MW
957371 AF2-031 C Adder 0.67 MW 0.57 MW
957372 AF2-031 E Adder 1.0 MW 0.85 MW
957891 AF2-083 C 50/50 11.27 MW 11.27 MW
957892 AF2-083 E 50/50 5.64 MW 5.64 MW
958381 AF2-132 C Adder 15.51 MW 13.18 MW
958382 AF2-132 E Adder 10.34 MW 8.79 MW
958391 AF2-133 C Adder 15.3 MW 13.01 MW
958392 AF2-133 E Adder 10.2 MW 8.67 MW
958402 AF2-134 E Adder 3.52 MW 2.99 MW
964861 AG1-349 C Adder 13.39 MW 11.38 MW
964862 AG1-349 E Adder 8.92 MW 7.58 MW
965791 AG1-447 C Adder 4.8 MW 4.08 MW
939161 AE1-146 C Adder -9.08 MW -7.71 MW
943961 AF1-064 C Adder -7.63 MW -6.49 MW
955182 J996 G External Queue 27.58 MW 27.58 MW
990142 J1224 G External Queue 46.72 MW 46.72 MW
990152 J1226 External Queue 85.53 MW 85.53 MW
990527 J1329 G External Queue 5.52 MW 5.52 MW
991177 J1571 G External Queue 66.23 MW 66.23 MW
991182 J1586 G External Queue 63.3 MW 63.3 MW
991227 J1663 G External Queue 17.12 MW 17.12 MW
955782 J1062 G External Queue 59.26 MW 59.26 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 232.96 MW 232.96 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.98 MW 27.98 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 9.28 MW 9.28 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.29 MW 2.29 MW
NY PJM->LTFIMP_NY CLTF 1.41 MW 1.41 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.98 MW 1.98 MW
WEC LTFEXP_WEC->PJM CLTF 2.48 MW 2.48 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.43 MW 0.43 MW
TVA LTFEXP_TVA->PJM CLTF 4.16 MW 4.16 MW
MEC LTFEXP_MEC->PJM CLTF 10.05 MW 10.05 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.04 MW 6.04 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.45 MW 0.45 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 14.77 MW 14.77 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.21 MW 0.21 MW

Details for 19MON12-02LALLENDORF 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-025T_SRT-A-1_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: ATSI/ITCT
Facility Description:
19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-025T_SRT-A-1_SENS
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-1_SENS'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 264594 CKT 1   /*02LEMOYN     345.0 - 19LULU       345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 104.14 %
Rating: 1660.0 MVA
Rating Type: B
MVA to Mitigate: 1728.76 MVA
MW Contribution: 29.27 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965681 AG1-436 C Adder 5.61 MW 4.77 MW
965682 AG1-436 E Adder 3.74 MW 3.18 MW
966431 AG1-512 C Adder 1.14 MW 0.96 MW
966432 AG1-512 E Adder 1.7 MW 1.45 MW
247528 05COVRT1 50/50 4.64 MW 4.64 MW
247529 05COVRT2 50/50 4.64 MW 4.64 MW
247530 05COVRT3 50/50 4.64 MW 4.64 MW
247531 05COVRT4 50/50 2.79 MW 2.79 MW
247532 05COVRT5 50/50 2.77 MW 2.77 MW
247533 05COVRT6 50/50 2.27 MW 2.27 MW
247966 05WTRV SLR E 50/50 0.25 MW 0.25 MW
247967 05OLIV SLR E Adder 0.21 MW 0.18 MW
247969 Z2-116 E Adder 0.12 MW 0.1 MW
910542 X3-005 E Adder 0.4 MW 0.34 MW
943001 AE2-323 C Adder 5.11 MW 4.34 MW
943002 AE2-323 E Adder 2.51 MW 2.13 MW
943021 AE2-325 C 50/50 3.15 MW 3.15 MW
943022 AE2-325 E 50/50 2.1 MW 2.1 MW
944161 AF1-084 C 50/50 5.55 MW 5.55 MW
944162 AF1-084 E 50/50 3.17 MW 3.17 MW
944961 AF1-161 C 50/50 2.51 MW 2.51 MW
945641 AF1-229 C Adder -7.25 MW -6.16 MW
960681 AF2-359 C Adder 5.61 MW 4.77 MW
960682 AF2-359 E Adder 3.74 MW 3.18 MW
960841 AF2-375 C Adder -7.25 MW -6.16 MW
960981 AF2-389 C Adder 2.89 MW 2.46 MW
960982 AF2-389 E Adder 1.93 MW 1.64 MW
243071 05BERRINSP G 50/50 0.05 MW 0.05 MW
244412 05WTRV SLR C 50/50 0.04 MW 0.04 MW
274675 JOLIET 29;7U Adder 37.59 MW 31.95 MW
274676 JOLIET 29;8U Adder 37.59 MW 31.95 MW
274687 WILL CNTY;4U Adder 34.99 MW 29.74 MW
274788 SE CHICAG;5U Adder 2.64 MW 2.25 MW
274789 SE CHICAG;6U Adder 2.64 MW 2.25 MW
274790 SE CHICAG;7U Adder 2.64 MW 2.25 MW
274791 SE CHICAG;8U Adder 2.64 MW 2.25 MW
274792 SE CHICAG;9U Adder 2.65 MW 2.25 MW
274793 SE CHICAG;0U Adder 2.65 MW 2.25 MW
274794 SE CHICAG;1U Adder 2.65 MW 2.25 MW
274795 SE CHICAG;2U Adder 2.65 MW 2.25 MW
933411 AC2-154 C Adder 1.31 MW 1.11 MW
933412 AC2-154 E Adder 2.14 MW 1.82 MW
941781 AE2-181 C Adder -2.72 MW -2.31 MW
247604 X1-042 50/50 0.07 MW 0.07 MW
275149 KELLYCK ;1E Adder 9.67 MW 8.22 MW
293519 PILOT HIL;1E Adder 9.67 MW 8.22 MW
936632 AD2-079 E O1 Adder 0.72 MW 0.62 MW
936141 AD2-020 C 50/50 6.22 MW 6.22 MW
936371 AD2-047 C Adder 2.35 MW 2.0 MW
936372 AD2-047 E Adder 11.47 MW 9.75 MW
936461 AD2-060 C Adder 1.38 MW 1.17 MW
944932 AF1-158 E Adder 5.19 MW 4.41 MW
945111 AF1-176 C Adder 15.19 MW 12.91 MW
945112 AF1-176 E Adder 14.08 MW 11.97 MW
945421 AF1-207 C Adder 2.36 MW 2.01 MW
945422 AF1-207 E Adder 10.16 MW 8.63 MW
945502 AF1-215 E Adder 9.05 MW 7.69 MW
959141 AF2-205 C Adder 8.69 MW 7.38 MW
959142 AF2-205 E Adder 5.79 MW 4.92 MW
960591 AF2-350 C Adder 4.14 MW 3.52 MW
960592 AF2-350 E Adder 2.76 MW 2.35 MW
961051 AF2-396 C Adder 19.89 MW 16.91 MW
961501 AF2-441 C Adder 5.67 MW 4.82 MW
961502 AF2-441 E Adder 8.5 MW 7.22 MW
939391 AE1-170 C Adder 6.1 MW 5.19 MW
939392 AE1-170 E Adder 8.43 MW 7.17 MW
940581 AE2-045 C Adder 6.04 MW 5.13 MW
940582 AE2-045 E Adder 8.29 MW 7.05 MW
962601 AG1-109 C 50/50 2.51 MW 2.51 MW
964401 AG1-302 C Adder 13.3 MW 11.3 MW
964402 AG1-302 E Adder 8.87 MW 7.54 MW
936142 AD2-020 E 50/50 3.83 MW 3.83 MW
957371 AF2-031 C Adder 0.57 MW 0.49 MW
957372 AF2-031 E Adder 0.86 MW 0.73 MW
957841 AF2-078 C Adder 8.35 MW 7.09 MW
957842 AF2-078 E Adder 5.56 MW 4.73 MW
957891 AF2-083 C Adder 9.63 MW 8.19 MW
957892 AF2-083 E Adder 4.82 MW 4.09 MW
958011 AF2-095 C Adder 5.97 MW 5.07 MW
958012 AF2-095 E Adder 3.98 MW 3.38 MW
958381 AF2-132 C Adder 13.3 MW 11.3 MW
958382 AF2-132 E Adder 8.87 MW 7.54 MW
958391 AF2-133 C Adder 13.12 MW 11.16 MW
958392 AF2-133 E Adder 8.75 MW 7.44 MW
958402 AF2-134 E Adder 3.02 MW 2.56 MW
964861 AG1-349 C Adder 11.48 MW 9.76 MW
964862 AG1-349 E Adder 7.65 MW 6.5 MW
965791 AG1-447 C Adder 4.12 MW 3.5 MW
939161 AE1-146 C Adder -6.96 MW -5.92 MW
943961 AF1-064 C Adder -3.65 MW -3.1 MW
990142 J1224 G External Queue 34.11 MW 34.11 MW
990527 J1329 G External Queue 4.03 MW 4.03 MW
991182 J1586 G External Queue 48.2 MW 48.2 MW
955782 J1062 G External Queue 39.23 MW 39.23 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 217.98 MW 217.98 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 24.24 MW 24.24 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 8.23 MW 8.23 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.0 MW 2.0 MW
NY PJM->LTFIMP_NY CLTF 1.23 MW 1.23 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.74 MW 1.74 MW
WEC LTFEXP_WEC->PJM CLTF 2.13 MW 2.13 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.39 MW 0.39 MW
TVA LTFEXP_TVA->PJM CLTF 3.62 MW 3.62 MW
MEC LTFEXP_MEC->PJM CLTF 8.66 MW 8.66 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.24 MW 5.24 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.39 MW 0.39 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 12.9 MW 12.9 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.19 MW 0.19 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05SORENS-05MARYSV 765.0 kV Ckt 1 line
246999 to 242928 ckt 1
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
CONTINGENCY 'AEP_P4_#7334_05JEFRSO 765_A2_SRT-A'
 OPEN BRANCH FROM BUS 242865 TO BUS 243208 CKT 2    /*05JEFRSO     345.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 242865 TO BUS 248000 CKT Z1   /*05JEFRSO     345.0 - 06CLIFTY     345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1    /*05HANG R     765.0 - 05JEFRSO     765.0
END
Breaker AC 103.54 % 4142.0 B 4288.52 76.31
ATSI/ITCT 19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
ATSI_P7-1_TE-345-025T_SRT-A-1
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-1'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 955780 CKT 1   /*02LEMOYN     345.0 - J1062 POI    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
END
Tower AC 114.87 % 1660.0 B 1906.81 29.61
ATSI/METC 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
256583 to 238530 ckt 1
ATSI_P7-1_TE-345-022T_SRT-A-1
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-1'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 955780 CKT 1   /*02LEMOYN     345.0 - J1062 POI    345.0
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
END
Tower AC 112.32 % 1793.0 B 2013.98 33.36
ATSI/METC 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
256583 to 238530 ckt 1
ATSI_P7-1_TE-345-022T_SRT-A-2
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-2'
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
 DISCONNECT BRANCH FROM BUS 264599 TO BUS 955780 CKT 1   /*19MAJTC      345.0 - J1062 POI    345.0
END
Tower AC 109.89 % 1793.0 B 1970.28 33.36
ATSI/ITCT J1062 POI-02LEMOYN 345.0 kV Ckt 1 line
955780 to 238889 ckt 1
ATSI_P7-1_TE-345-032T_SRT-A-1
CONTINGENCY 'ATSI_P7-1_TE-345-032T_SRT-A-1'
 OPEN BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
 OPEN BRANCH FROM BUS 256583 TO BUS 264594 CKT 1   /*18MOROCCO    345.0 - 19LULU       345.0
 OPEN BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 OPEN BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
END
Tower AC 104.1 % 852.0 B 886.89 19.66

Details for 05SORENS-05MARYSV 765.0 kV Ckt 1 line l/o AEP_P4_#7334_05JEFRSO 765_A2_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP
Facility Description:
05SORENS-05MARYSV 765.0 kV Ckt 1 line
246999 to 242928 ckt 1
Contingency Name:
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
CONTINGENCY 'AEP_P4_#7334_05JEFRSO 765_A2_SRT-A'
 OPEN BRANCH FROM BUS 242865 TO BUS 243208 CKT 2    /*05JEFRSO     345.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 242865 TO BUS 248000 CKT Z1   /*05JEFRSO     345.0 - 06CLIFTY     345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 243208 CKT 1    /*05HANG R     765.0 - 05JEFRSO     765.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 103.54 %
Rating: 4142.0 MVA
Rating Type: B
MVA to Mitigate: 4288.52 MVA
MW Contribution: 76.31 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243353 05OLIVE 50/50 0.21 MW 0.21 MW
965681 AG1-436 C 50/50 19.62 MW 19.62 MW
965682 AG1-436 E 50/50 13.08 MW 13.08 MW
966091 AG1-478 C Adder 3.89 MW 3.31 MW
966092 AG1-478 E Adder 0.98 MW 0.83 MW
966431 AG1-512 C Adder 3.99 MW 3.39 MW
966432 AG1-512 E Adder 5.98 MW 5.09 MW
966441 AG1-513 C Adder 0.97 MW 0.83 MW
966442 AG1-513 E Adder 1.46 MW 1.24 MW
246422 05MAYFLWER 50/50 0.24 MW 0.24 MW
246431 05BUCHANAN 50/50 0.08 MW 0.08 MW
247643 Z2-116 C 50/50 0.06 MW 0.06 MW
247966 05WTRV SLR E Adder 0.58 MW 0.49 MW
247967 05OLIV SLR E 50/50 0.65 MW 0.65 MW
247969 Z2-116 E 50/50 0.34 MW 0.34 MW
910542 X3-005 E Adder 1.4 MW 1.19 MW
918052 AA1-018 E OP Adder 31.26 MW 26.57 MW
934722 AD1-100 E Adder 172.7 MW 146.79 MW
943001 AE2-323 C Adder 16.55 MW 14.07 MW
943002 AE2-323 E Adder 8.12 MW 6.9 MW
943021 AE2-325 C 50/50 7.96 MW 7.96 MW
943022 AE2-325 E 50/50 5.31 MW 5.31 MW
944161 AF1-084 C Adder 13.7 MW 11.65 MW
944162 AF1-084 E Adder 7.83 MW 6.65 MW
944961 AF1-161 C 50/50 6.36 MW 6.36 MW
958481 AF2-142 C Adder 21.56 MW 18.32 MW
958482 AF2-142 E Adder 14.37 MW 12.22 MW
959351 AF2-226 C Adder 4.8 MW 4.08 MW
959352 AF2-226 E Adder 7.2 MW 6.12 MW
960281 AF2-319 C Adder 4.8 MW 4.08 MW
960282 AF2-319 E Adder 7.2 MW 6.12 MW
960681 AF2-359 C 50/50 19.62 MW 19.62 MW
960682 AF2-359 E 50/50 13.08 MW 13.08 MW
960981 AF2-389 C 50/50 7.68 MW 7.68 MW
960982 AF2-389 E 50/50 5.12 MW 5.12 MW
243071 05BERRINSP G 50/50 0.14 MW 0.14 MW
243440 05CKG1 50/50 43.35 MW 43.35 MW
243441 05CKG2 50/50 55.77 MW 55.77 MW
244415 05OLIV SLR C 50/50 0.1 MW 0.1 MW
270142 AA2-116_CT1 50/50 15.9 MW 15.9 MW
270143 AA2-116_CT2 50/50 15.9 MW 15.9 MW
270144 AA2-116_ST 50/50 14.09 MW 14.09 MW
274675 JOLIET 29;7U Adder 134.93 MW 114.69 MW
274676 JOLIET 29;8U Adder 134.93 MW 114.69 MW
274682 WAUKEGAN ;7U Adder 78.66 MW 66.86 MW
274683 WAUKEGAN ;8U Adder 79.26 MW 67.37 MW
274687 WILL CNTY;4U Adder 125.3 MW 106.51 MW
274771 LINCOLN ;2U 50/50 3.19 MW 3.19 MW
274772 LINCOLN ;3U 50/50 3.19 MW 3.19 MW
274773 LINCOLN ;4U 50/50 3.19 MW 3.19 MW
274775 LINCOLN ;6U 50/50 3.19 MW 3.19 MW
274777 LINCOLN ;8U 50/50 3.19 MW 3.19 MW
274788 SE CHICAG;5U Adder 9.28 MW 7.89 MW
274789 SE CHICAG;6U Adder 9.28 MW 7.89 MW
274790 SE CHICAG;7U Adder 9.28 MW 7.89 MW
274791 SE CHICAG;8U Adder 9.28 MW 7.89 MW
274792 SE CHICAG;9U Adder 9.28 MW 7.89 MW
274793 SE CHICAG;0U Adder 9.28 MW 7.89 MW
274794 SE CHICAG;1U Adder 9.28 MW 7.89 MW
274795 SE CHICAG;2U Adder 9.28 MW 7.89 MW
276591 L-013 2 Adder 7.01 MW 5.96 MW
293061 N-015 E Adder 29.32 MW 24.93 MW
293644 O22 E1 Adder 27.56 MW 23.43 MW
293645 O22 E2 Adder 31.56 MW 26.83 MW
294392 P-010 E Adder 37.24 MW 31.66 MW
933411 AC2-154 C Adder 4.7 MW 4.0 MW
933412 AC2-154 E Adder 7.67 MW 6.52 MW
274674 JOLIET 9 ;6U Adder 68.86 MW 58.53 MW
934101 AD2-000 1 Adder 11.24 MW 9.56 MW
934111 AD2-000 2 Adder 11.3 MW 9.61 MW
243352 05NTRDAM 50/50 2.43 MW 2.43 MW
246416 05TWIN BRNCH 50/50 0.07 MW 0.07 MW
246476 05NILES 50/50 0.06 MW 0.06 MW
246477 05NILES 50/50 0.06 MW 0.06 MW
270100 AB1-080 CT1 50/50 9.96 MW 9.96 MW
270101 AB1-080 CT2 50/50 9.96 MW 9.96 MW
270102 AB1-080 ST 50/50 10.77 MW 10.77 MW
270216 AD2-079_C O1 50/50 0.5 MW 0.5 MW
275149 KELLYCK ;1E Adder 34.63 MW 29.44 MW
293519 PILOT HIL;1E Adder 34.63 MW 29.44 MW
936632 AD2-079 E O1 50/50 2.05 MW 2.05 MW
936141 AD2-020 C 50/50 15.74 MW 15.74 MW
936371 AD2-047 C Adder 8.41 MW 7.15 MW
936372 AD2-047 E Adder 41.06 MW 34.91 MW
936461 AD2-060 C Adder 4.95 MW 4.21 MW
942241 AE2-236 C Adder 9.78 MW 8.31 MW
942242 AE2-236 E Adder 4.19 MW 3.56 MW
943121 AE2-341 C Adder 24.45 MW 20.79 MW
943122 AE2-341 E Adder 12.01 MW 10.21 MW
943591 AF1-030 C Adder 16.26 MW 13.82 MW
943592 AF1-030 E Adder 8.05 MW 6.84 MW
944241 AF1-092 C Adder 29.05 MW 24.69 MW
944242 AF1-092 E Adder 8.84 MW 7.52 MW
944931 AF1-158 C 50/50 3.71 MW 3.71 MW
944932 AF1-158 E 50/50 15.58 MW 15.58 MW
945111 AF1-176 C 50/50 39.6 MW 39.6 MW
945112 AF1-176 E 50/50 36.71 MW 36.71 MW
945421 AF1-207 C Adder 8.2 MW 6.97 MW
945422 AF1-207 E Adder 35.22 MW 29.94 MW
945502 AF1-215 E Adder 30.2 MW 25.67 MW
959141 AF2-205 C Adder 29.56 MW 25.12 MW
959142 AF2-205 E Adder 19.7 MW 16.75 MW
960591 AF2-350 C Adder 14.84 MW 12.62 MW
960592 AF2-350 E Adder 9.9 MW 8.41 MW
961051 AF2-396 C 50/50 50.86 MW 50.86 MW
961501 AF2-441 C Adder 20.01 MW 17.0 MW
961502 AF2-441 E Adder 30.01 MW 25.51 MW
939351 AE1-166 C Adder 19.24 MW 16.36 MW
939352 AE1-166 E Adder 17.76 MW 15.1 MW
939391 AE1-170 C 50/50 16.18 MW 16.18 MW
939392 AE1-170 E 50/50 22.34 MW 22.34 MW
940581 AE2-045 C Adder 20.65 MW 17.55 MW
940582 AE2-045 E Adder 28.35 MW 24.1 MW
962601 AG1-109 C 50/50 6.36 MW 6.36 MW
964401 AG1-302 C Adder 44.81 MW 38.09 MW
964402 AG1-302 E Adder 29.87 MW 25.39 MW
936142 AD2-020 E 50/50 9.69 MW 9.69 MW
941551 AE2-152 C Adder 22.2 MW 18.87 MW
941552 AE2-152 E Adder 14.8 MW 12.58 MW
957371 AF2-031 C Adder 2.01 MW 1.71 MW
957372 AF2-031 E Adder 3.01 MW 2.56 MW
957841 AF2-078 C Adder 28.95 MW 24.61 MW
957842 AF2-078 E Adder 19.3 MW 16.41 MW
957891 AF2-083 C 50/50 25.62 MW 25.62 MW
957892 AF2-083 E 50/50 12.81 MW 12.81 MW
958011 AF2-095 C Adder 21.37 MW 18.17 MW
958012 AF2-095 E Adder 14.25 MW 12.11 MW
958381 AF2-132 C Adder 44.81 MW 38.09 MW
958382 AF2-132 E Adder 29.87 MW 25.39 MW
958391 AF2-133 C Adder 44.5 MW 37.82 MW
958392 AF2-133 E Adder 29.67 MW 25.22 MW
958402 AF2-134 E Adder 10.07 MW 8.56 MW
964861 AG1-349 C Adder 38.75 MW 32.94 MW
964862 AG1-349 E Adder 25.83 MW 21.96 MW
965791 AG1-447 C 50/50 14.39 MW 14.39 MW
276675 AE2-062 E Adder 0.29 MW 0.24 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 321.03 MW 321.03 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 75.8 MW 75.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 7.05 MW 7.05 MW
NY PJM->LTFIMP_NY CLTF 3.66 MW 3.66 MW
LGEE LTFEXP_LGEE->PJM CLTF 3.88 MW 3.88 MW
WEC LTFEXP_WEC->PJM CLTF 7.63 MW 7.63 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 1.49 MW 1.49 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.7 MW 0.7 MW
TVA LTFEXP_TVA->PJM CLTF 8.29 MW 8.29 MW
MEC LTFEXP_MEC->PJM CLTF 30.19 MW 30.19 MW
LAGN LTFEXP_LAGN->PJM CLTF 13.89 MW 13.89 MW
SIGE LTFEXP_SIGE->PJM CLTF 1.24 MW 1.24 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 45.17 MW 45.17 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 2.34 MW 2.34 MW

Details for 19MON12-02LALLENDORF 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-025T_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: ATSI/ITCT
Facility Description:
19MON12-02LALLENDORF 345.0 kV Ckt 1 line
264612 to 241901 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-025T_SRT-A-1
CONTINGENCY 'ATSI_P7-1_TE-345-025T_SRT-A-1'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 955780 CKT 1   /*02LEMOYN     345.0 - J1062 POI    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 256583 CKT 1   /*19LULU       345.0 - 18MOROCCO    345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 DISCONNECT BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 114.87 %
Rating: 1660.0 MVA
Rating Type: B
MVA to Mitigate: 1906.81 MVA
MW Contribution: 29.61 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965681 AG1-436 C Adder 6.13 MW 5.21 MW
965682 AG1-436 E Adder 4.09 MW 3.48 MW
966091 AG1-478 C Adder 1.1 MW 0.94 MW
966092 AG1-478 E Adder 0.28 MW 0.24 MW
966431 AG1-512 C Adder 1.15 MW 0.98 MW
966432 AG1-512 E Adder 1.73 MW 1.47 MW
247528 05COVRT1 50/50 4.67 MW 4.67 MW
247529 05COVRT2 50/50 4.67 MW 4.67 MW
247530 05COVRT3 50/50 4.67 MW 4.67 MW
247531 05COVRT4 50/50 2.81 MW 2.81 MW
247532 05COVRT5 50/50 2.79 MW 2.79 MW
247533 05COVRT6 50/50 2.28 MW 2.28 MW
247906 05MDL-1G E Adder 12.22 MW 10.38 MW
247907 05MDL-2G E Adder 5.88 MW 5.0 MW
247912 05MDL-3G E Adder 5.88 MW 4.99 MW
247913 05MDL-4G E Adder 6.12 MW 5.2 MW
247966 05WTRV SLR E 50/50 0.25 MW 0.25 MW
247967 05OLIV SLR E Adder 0.22 MW 0.18 MW
247969 Z2-116 E Adder 0.12 MW 0.1 MW
910542 X3-005 E Adder 0.4 MW 0.34 MW
934722 AD1-100 E Adder 48.52 MW 41.24 MW
943001 AE2-323 C Adder 5.18 MW 4.41 MW
943002 AE2-323 E Adder 2.54 MW 2.16 MW
943021 AE2-325 C 50/50 3.19 MW 3.19 MW
943022 AE2-325 E 50/50 2.12 MW 2.12 MW
944161 AF1-084 C 50/50 5.61 MW 5.61 MW
944162 AF1-084 E 50/50 3.21 MW 3.21 MW
944961 AF1-161 C 50/50 2.54 MW 2.54 MW
945641 AF1-229 C Adder -7.21 MW -6.13 MW
960681 AF2-359 C Adder 6.13 MW 5.21 MW
960682 AF2-359 E Adder 4.09 MW 3.48 MW
960841 AF2-375 C Adder -7.2 MW -6.12 MW
960981 AF2-389 C Adder 2.93 MW 2.49 MW
960982 AF2-389 E Adder 1.95 MW 1.66 MW
243071 05BERRINSP G 50/50 0.05 MW 0.05 MW
244412 05WTRV SLR C 50/50 0.04 MW 0.04 MW
274675 JOLIET 29;7U Adder 38.19 MW 32.46 MW
274676 JOLIET 29;8U Adder 38.19 MW 32.46 MW
274687 WILL CNTY;4U Adder 35.55 MW 30.22 MW
274788 SE CHICAG;5U Adder 2.69 MW 2.29 MW
274789 SE CHICAG;6U Adder 2.69 MW 2.29 MW
274790 SE CHICAG;7U Adder 2.69 MW 2.29 MW
274791 SE CHICAG;8U Adder 2.69 MW 2.29 MW
274792 SE CHICAG;9U Adder 2.7 MW 2.29 MW
274793 SE CHICAG;0U Adder 2.7 MW 2.29 MW
274794 SE CHICAG;1U Adder 2.7 MW 2.29 MW
274795 SE CHICAG;2U Adder 2.7 MW 2.29 MW
933411 AC2-154 C Adder 1.33 MW 1.13 MW
933412 AC2-154 E Adder 2.18 MW 1.85 MW
941781 AE2-181 C Adder -2.69 MW -2.29 MW
946581 AF1-322 C Adder 5.83 MW 4.95 MW
946582 AF1-322 E Adder 8.05 MW 6.84 MW
274674 JOLIET 9 ;6U Adder 19.47 MW 16.55 MW
247604 X1-042 50/50 0.07 MW 0.07 MW
275149 KELLYCK ;1E Adder 9.82 MW 8.35 MW
293519 PILOT HIL;1E Adder 9.82 MW 8.35 MW
936632 AD2-079 E O1 Adder 0.73 MW 0.62 MW
247943 T-127 E Adder 5.54 MW 4.71 MW
930041 AB1-006 E1 Adder 10.56 MW 8.98 MW
930042 AB1-006 E2 Adder 1.51 MW 1.28 MW
936141 AD2-020 C 50/50 6.29 MW 6.29 MW
936371 AD2-047 C Adder 2.39 MW 2.03 MW
936372 AD2-047 E Adder 11.65 MW 9.9 MW
936461 AD2-060 C Adder 1.4 MW 1.19 MW
944932 AF1-158 E Adder 5.26 MW 4.47 MW
945111 AF1-176 C Adder 15.37 MW 13.06 MW
945112 AF1-176 E Adder 14.25 MW 12.11 MW
945421 AF1-207 C Adder 2.41 MW 2.05 MW
945422 AF1-207 E Adder 10.34 MW 8.79 MW
945502 AF1-215 E Adder 9.19 MW 7.82 MW
959141 AF2-205 C Adder 8.84 MW 7.51 MW
959142 AF2-205 E Adder 5.89 MW 5.01 MW
960591 AF2-350 C Adder 4.21 MW 3.58 MW
960592 AF2-350 E Adder 2.81 MW 2.39 MW
961051 AF2-396 C 50/50 20.12 MW 20.12 MW
961501 AF2-441 C Adder 5.76 MW 4.9 MW
961502 AF2-441 E Adder 8.64 MW 7.35 MW
939351 AE1-166 C Adder 5.41 MW 4.6 MW
939352 AE1-166 E Adder 4.99 MW 4.24 MW
939391 AE1-170 C Adder 6.18 MW 5.25 MW
939392 AE1-170 E Adder 8.53 MW 7.25 MW
940581 AE2-045 C Adder 6.15 MW 5.22 MW
940582 AE2-045 E Adder 8.44 MW 7.17 MW
962601 AG1-109 C 50/50 2.54 MW 2.54 MW
964401 AG1-302 C Adder 13.52 MW 11.49 MW
964402 AG1-302 E Adder 9.01 MW 7.66 MW
936142 AD2-020 E 50/50 3.88 MW 3.88 MW
941551 AE2-152 C Adder 6.24 MW 5.3 MW
941552 AE2-152 E Adder 4.16 MW 3.54 MW
957371 AF2-031 C Adder 0.58 MW 0.49 MW
957372 AF2-031 E Adder 0.87 MW 0.74 MW
957841 AF2-078 C Adder 8.5 MW 7.23 MW
957842 AF2-078 E Adder 5.67 MW 4.82 MW
957891 AF2-083 C Adder 9.75 MW 8.28 MW
957892 AF2-083 E Adder 4.87 MW 4.14 MW
958011 AF2-095 C Adder 6.06 MW 5.15 MW
958012 AF2-095 E Adder 4.04 MW 3.44 MW
958381 AF2-132 C Adder 13.52 MW 11.49 MW
958382 AF2-132 E Adder 9.01 MW 7.66 MW
958391 AF2-133 C Adder 13.35 MW 11.34 MW
958392 AF2-133 E Adder 8.9 MW 7.56 MW
958402 AF2-134 E Adder 3.06 MW 2.6 MW
964861 AG1-349 C Adder 11.67 MW 9.92 MW
964862 AG1-349 E Adder 7.78 MW 6.61 MW
965791 AG1-447 C Adder 4.5 MW 3.82 MW
939161 AE1-146 C Adder -6.91 MW -5.88 MW
943961 AF1-064 C Adder -3.62 MW -3.08 MW
276675 AE2-062 E Adder 0.08 MW 0.07 MW
990142 J1224 G External Queue 34.18 MW 34.18 MW
990527 J1329 G External Queue 4.04 MW 4.04 MW
991182 J1586 G External Queue 48.19 MW 48.19 MW
955782 J1062 G External Queue 38.12 MW 38.12 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 219.9 MW 219.9 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 24.94 MW 24.94 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 9.34 MW 9.34 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.09 MW 2.09 MW
NY PJM->LTFIMP_NY CLTF 1.27 MW 1.27 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.75 MW 1.75 MW
WEC LTFEXP_WEC->PJM CLTF 2.16 MW 2.16 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.47 MW 0.47 MW
TVA LTFEXP_TVA->PJM CLTF 3.77 MW 3.77 MW
MEC LTFEXP_MEC->PJM CLTF 8.83 MW 8.83 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.43 MW 5.43 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.4 MW 0.4 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 13.5 MW 13.5 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.23 MW 0.23 MW

Details for 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-022T_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: ATSI/METC
Facility Description:
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
256583 to 238530 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-022T_SRT-A-1
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-1'
 DISCONNECT BRANCH FROM BUS 238889 TO BUS 955780 CKT 1   /*02LEMOYN     345.0 - J1062 POI    345.0
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 112.32 %
Rating: 1793.0 MVA
Rating Type: B
MVA to Mitigate: 2013.98 MVA
MW Contribution: 33.36 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965681 AG1-436 C Adder 6.89 MW 5.86 MW
965682 AG1-436 E Adder 4.59 MW 3.9 MW
246397 05ELKHART HY 50/50 0.03 MW 0.03 MW
246422 05MAYFLWER 50/50 0.1 MW 0.1 MW
246431 05BUCHANAN 50/50 0.03 MW 0.03 MW
247528 05COVRT1 50/50 5.28 MW 5.28 MW
247529 05COVRT2 50/50 5.28 MW 5.28 MW
247530 05COVRT3 50/50 5.28 MW 5.28 MW
247531 05COVRT4 50/50 3.17 MW 3.17 MW
247532 05COVRT5 50/50 3.15 MW 3.15 MW
247533 05COVRT6 50/50 2.58 MW 2.58 MW
247620 Y3-023 50/50 0.07 MW 0.07 MW
247643 Z2-116 C 50/50 0.02 MW 0.02 MW
247966 05WTRV SLR E 50/50 0.28 MW 0.28 MW
247967 05OLIV SLR E Adder 0.24 MW 0.21 MW
247969 Z2-116 E 50/50 0.13 MW 0.13 MW
943001 AE2-323 C Adder 5.67 MW 4.82 MW
943002 AE2-323 E Adder 2.78 MW 2.36 MW
943021 AE2-325 C 50/50 3.59 MW 3.59 MW
943022 AE2-325 E 50/50 2.39 MW 2.39 MW
944161 AF1-084 C 50/50 6.33 MW 6.33 MW
944162 AF1-084 E 50/50 3.62 MW 3.62 MW
944961 AF1-161 C 50/50 2.87 MW 2.87 MW
945641 AF1-229 C Adder -8.25 MW -7.01 MW
960681 AF2-359 C Adder 6.89 MW 5.86 MW
960682 AF2-359 E Adder 4.59 MW 3.9 MW
960841 AF2-375 C Adder -8.9 MW -7.57 MW
960981 AF2-389 C 50/50 3.3 MW 3.3 MW
960982 AF2-389 E 50/50 2.2 MW 2.2 MW
243071 05BERRINSP G 50/50 0.06 MW 0.06 MW
243440 05CKG1 50/50 18.09 MW 18.09 MW
244412 05WTRV SLR C 50/50 0.05 MW 0.05 MW
270142 AA2-116_CT1 50/50 6.62 MW 6.62 MW
270143 AA2-116_CT2 50/50 6.62 MW 6.62 MW
270144 AA2-116_ST 50/50 5.87 MW 5.87 MW
274788 SE CHICAG;5U Adder 3.02 MW 2.56 MW
274789 SE CHICAG;6U Adder 3.02 MW 2.56 MW
274790 SE CHICAG;7U Adder 3.02 MW 2.56 MW
274791 SE CHICAG;8U Adder 3.02 MW 2.56 MW
274792 SE CHICAG;9U Adder 3.02 MW 2.57 MW
274793 SE CHICAG;0U Adder 3.02 MW 2.57 MW
274794 SE CHICAG;1U Adder 3.02 MW 2.57 MW
274795 SE CHICAG;2U Adder 3.02 MW 2.57 MW
941781 AE2-181 C Adder -7.07 MW -6.01 MW
243352 05NTRDAM 50/50 0.94 MW 0.94 MW
246416 05TWIN BRNCH 50/50 0.03 MW 0.03 MW
246476 05NILES 50/50 0.02 MW 0.02 MW
246477 05NILES 50/50 0.02 MW 0.02 MW
246536 05MOTTVILLE 50/50 0.01 MW 0.01 MW
247604 X1-042 50/50 0.08 MW 0.08 MW
270216 AD2-079_C O1 50/50 0.2 MW 0.2 MW
936632 AD2-079 E O1 50/50 0.82 MW 0.82 MW
936141 AD2-020 C 50/50 7.1 MW 7.1 MW
944932 AF1-158 E Adder 5.91 MW 5.02 MW
945111 AF1-176 C 50/50 17.31 MW 17.31 MW
945112 AF1-176 E 50/50 16.05 MW 16.05 MW
945502 AF1-215 E Adder 10.32 MW 8.77 MW
959141 AF2-205 C Adder 9.91 MW 8.43 MW
959142 AF2-205 E Adder 6.61 MW 5.62 MW
961051 AF2-396 C 50/50 22.68 MW 22.68 MW
961501 AF2-441 C Adder 6.46 MW 5.49 MW
961502 AF2-441 E Adder 9.69 MW 8.24 MW
939391 AE1-170 C 50/50 6.96 MW 6.96 MW
939392 AE1-170 E 50/50 9.61 MW 9.61 MW
940581 AE2-045 C Adder 6.89 MW 5.86 MW
940582 AE2-045 E Adder 9.46 MW 8.04 MW
962601 AG1-109 C 50/50 2.87 MW 2.87 MW
964401 AG1-302 C Adder 15.17 MW 12.89 MW
964402 AG1-302 E Adder 10.11 MW 8.59 MW
936142 AD2-020 E 50/50 4.37 MW 4.37 MW
957371 AF2-031 C Adder 0.65 MW 0.55 MW
957372 AF2-031 E Adder 0.98 MW 0.83 MW
957891 AF2-083 C 50/50 10.98 MW 10.98 MW
957892 AF2-083 E 50/50 5.49 MW 5.49 MW
958381 AF2-132 C Adder 15.17 MW 12.89 MW
958382 AF2-132 E Adder 10.11 MW 8.59 MW
958391 AF2-133 C Adder 14.97 MW 12.73 MW
958392 AF2-133 E Adder 9.98 MW 8.48 MW
958402 AF2-134 E Adder 3.44 MW 2.92 MW
964861 AG1-349 C Adder 13.09 MW 11.13 MW
964862 AG1-349 E Adder 8.73 MW 7.42 MW
965791 AG1-447 C Adder 5.05 MW 4.29 MW
939161 AE1-146 C Adder -8.68 MW -7.38 MW
943961 AF1-064 C Adder -7.32 MW -6.22 MW
955182 J996 G External Queue 28.62 MW 28.62 MW
990142 J1224 G External Queue 46.49 MW 46.49 MW
990152 J1226 External Queue 89.71 MW 89.71 MW
990527 J1329 G External Queue 5.5 MW 5.5 MW
991177 J1571 G External Queue 68.56 MW 68.56 MW
991182 J1586 G External Queue 60.05 MW 60.05 MW
991227 J1663 G External Queue 16.32 MW 16.32 MW
955782 J1062 G External Queue 43.45 MW 43.45 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 229.18 MW 229.18 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.68 MW 27.68 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.13 MW 10.13 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.31 MW 2.31 MW
NY PJM->LTFIMP_NY CLTF 1.4 MW 1.4 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.92 MW 1.92 MW
WEC LTFEXP_WEC->PJM CLTF 2.42 MW 2.42 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.5 MW 0.5 MW
TVA LTFEXP_TVA->PJM CLTF 4.17 MW 4.17 MW
MEC LTFEXP_MEC->PJM CLTF 9.87 MW 9.87 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.02 MW 6.02 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.44 MW 0.44 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 14.87 MW 14.87 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.25 MW 0.25 MW

Details for 18MOROCCO-02ALLEN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-022T_SRT-A-2


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: ATSI/METC
Facility Description:
18MOROCCO-02ALLEN 345.0 kV Ckt 1 line
256583 to 238530 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-022T_SRT-A-2
CONTINGENCY 'ATSI_P7-1_TE-345-022T_SRT-A-2'
 DISCONNECT BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
 DISCONNECT BRANCH FROM BUS 264599 TO BUS 955780 CKT 1   /*19MAJTC      345.0 - J1062 POI    345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 109.89 %
Rating: 1793.0 MVA
Rating Type: B
MVA to Mitigate: 1970.28 MVA
MW Contribution: 33.36 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965681 AG1-436 C Adder 6.89 MW 5.86 MW
965682 AG1-436 E Adder 4.59 MW 3.9 MW
246397 05ELKHART HY 50/50 0.03 MW 0.03 MW
246422 05MAYFLWER 50/50 0.1 MW 0.1 MW
246431 05BUCHANAN 50/50 0.03 MW 0.03 MW
247528 05COVRT1 50/50 5.28 MW 5.28 MW
247529 05COVRT2 50/50 5.28 MW 5.28 MW
247530 05COVRT3 50/50 5.28 MW 5.28 MW
247531 05COVRT4 50/50 3.17 MW 3.17 MW
247532 05COVRT5 50/50 3.15 MW 3.15 MW
247533 05COVRT6 50/50 2.58 MW 2.58 MW
247620 Y3-023 50/50 0.07 MW 0.07 MW
247643 Z2-116 C 50/50 0.02 MW 0.02 MW
247966 05WTRV SLR E 50/50 0.28 MW 0.28 MW
247967 05OLIV SLR E Adder 0.24 MW 0.21 MW
247969 Z2-116 E 50/50 0.13 MW 0.13 MW
943001 AE2-323 C Adder 5.67 MW 4.82 MW
943002 AE2-323 E Adder 2.78 MW 2.36 MW
943021 AE2-325 C 50/50 3.59 MW 3.59 MW
943022 AE2-325 E 50/50 2.39 MW 2.39 MW
944161 AF1-084 C 50/50 6.33 MW 6.33 MW
944162 AF1-084 E 50/50 3.62 MW 3.62 MW
944961 AF1-161 C 50/50 2.87 MW 2.87 MW
945641 AF1-229 C Adder -8.25 MW -7.01 MW
960681 AF2-359 C Adder 6.89 MW 5.86 MW
960682 AF2-359 E Adder 4.59 MW 3.9 MW
960841 AF2-375 C Adder -8.9 MW -7.57 MW
960981 AF2-389 C 50/50 3.3 MW 3.3 MW
960982 AF2-389 E 50/50 2.2 MW 2.2 MW
243071 05BERRINSP G 50/50 0.06 MW 0.06 MW
243440 05CKG1 50/50 18.09 MW 18.09 MW
244412 05WTRV SLR C 50/50 0.05 MW 0.05 MW
270142 AA2-116_CT1 50/50 6.62 MW 6.62 MW
270143 AA2-116_CT2 50/50 6.62 MW 6.62 MW
270144 AA2-116_ST 50/50 5.87 MW 5.87 MW
274788 SE CHICAG;5U Adder 3.02 MW 2.56 MW
274789 SE CHICAG;6U Adder 3.02 MW 2.56 MW
274790 SE CHICAG;7U Adder 3.02 MW 2.56 MW
274791 SE CHICAG;8U Adder 3.02 MW 2.56 MW
274792 SE CHICAG;9U Adder 3.02 MW 2.57 MW
274793 SE CHICAG;0U Adder 3.02 MW 2.57 MW
274794 SE CHICAG;1U Adder 3.02 MW 2.57 MW
274795 SE CHICAG;2U Adder 3.02 MW 2.57 MW
941781 AE2-181 C Adder -7.07 MW -6.01 MW
243352 05NTRDAM 50/50 0.94 MW 0.94 MW
246416 05TWIN BRNCH 50/50 0.03 MW 0.03 MW
246476 05NILES 50/50 0.02 MW 0.02 MW
246477 05NILES 50/50 0.02 MW 0.02 MW
246536 05MOTTVILLE 50/50 0.01 MW 0.01 MW
247604 X1-042 50/50 0.08 MW 0.08 MW
270216 AD2-079_C O1 50/50 0.2 MW 0.2 MW
936632 AD2-079 E O1 50/50 0.82 MW 0.82 MW
936141 AD2-020 C 50/50 7.1 MW 7.1 MW
944932 AF1-158 E Adder 5.91 MW 5.02 MW
945111 AF1-176 C 50/50 17.31 MW 17.31 MW
945112 AF1-176 E 50/50 16.05 MW 16.05 MW
945502 AF1-215 E Adder 10.32 MW 8.77 MW
959141 AF2-205 C Adder 9.91 MW 8.43 MW
959142 AF2-205 E Adder 6.61 MW 5.62 MW
961051 AF2-396 C 50/50 22.68 MW 22.68 MW
961501 AF2-441 C Adder 6.46 MW 5.49 MW
961502 AF2-441 E Adder 9.69 MW 8.24 MW
939391 AE1-170 C 50/50 6.96 MW 6.96 MW
939392 AE1-170 E 50/50 9.61 MW 9.61 MW
940581 AE2-045 C Adder 6.89 MW 5.86 MW
940582 AE2-045 E Adder 9.46 MW 8.04 MW
962601 AG1-109 C 50/50 2.87 MW 2.87 MW
964401 AG1-302 C Adder 15.17 MW 12.89 MW
964402 AG1-302 E Adder 10.11 MW 8.59 MW
936142 AD2-020 E 50/50 4.37 MW 4.37 MW
957371 AF2-031 C Adder 0.65 MW 0.55 MW
957372 AF2-031 E Adder 0.98 MW 0.83 MW
957891 AF2-083 C 50/50 10.98 MW 10.98 MW
957892 AF2-083 E 50/50 5.49 MW 5.49 MW
958381 AF2-132 C Adder 15.17 MW 12.89 MW
958382 AF2-132 E Adder 10.11 MW 8.59 MW
958391 AF2-133 C Adder 14.97 MW 12.73 MW
958392 AF2-133 E Adder 9.98 MW 8.48 MW
958402 AF2-134 E Adder 3.44 MW 2.92 MW
964861 AG1-349 C Adder 13.09 MW 11.13 MW
964862 AG1-349 E Adder 8.73 MW 7.42 MW
965791 AG1-447 C Adder 5.05 MW 4.29 MW
939161 AE1-146 C Adder -8.68 MW -7.38 MW
943961 AF1-064 C Adder -7.32 MW -6.22 MW
955182 J996 G External Queue 28.62 MW 28.62 MW
990142 J1224 G External Queue 46.49 MW 46.49 MW
990152 J1226 External Queue 89.71 MW 89.71 MW
990527 J1329 G External Queue 5.5 MW 5.5 MW
991177 J1571 G External Queue 68.56 MW 68.56 MW
991182 J1586 G External Queue 60.05 MW 60.05 MW
991227 J1663 G External Queue 16.32 MW 16.32 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 229.18 MW 229.18 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.68 MW 27.68 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.13 MW 10.13 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.31 MW 2.31 MW
NY PJM->LTFIMP_NY CLTF 1.4 MW 1.4 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.92 MW 1.92 MW
WEC LTFEXP_WEC->PJM CLTF 2.42 MW 2.42 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.5 MW 0.5 MW
TVA LTFEXP_TVA->PJM CLTF 4.17 MW 4.17 MW
MEC LTFEXP_MEC->PJM CLTF 9.87 MW 9.87 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.02 MW 6.02 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.44 MW 0.44 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 14.87 MW 14.87 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.25 MW 0.25 MW

Details for J1062 POI-02LEMOYN 345.0 kV Ckt 1 line l/o ATSI_P7-1_TE-345-032T_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: ATSI/ITCT
Facility Description:
J1062 POI-02LEMOYN 345.0 kV Ckt 1 line
955780 to 238889 ckt 1
Contingency Name:
ATSI_P7-1_TE-345-032T_SRT-A-1
CONTINGENCY 'ATSI_P7-1_TE-345-032T_SRT-A-1'
 OPEN BRANCH FROM BUS 241901 TO BUS 264612 CKT 1   /*02LALLENDORF 345.0 - 19MON12      345.0
 OPEN BRANCH FROM BUS 256583 TO BUS 264594 CKT 1   /*18MOROCCO    345.0 - 19LULU       345.0
 OPEN BRANCH FROM BUS 264594 TO BUS 264613 CKT 1   /*19LULU       345.0 - 19MON34      345.0
 OPEN BRANCH FROM BUS 264594 TO BUS 264839 CKT 1   /*19LULU       345.0 - 19MILAN      345.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 104.1 %
Rating: 852.0 MVA
Rating Type: B
MVA to Mitigate: 886.89 MVA
MW Contribution: 19.66 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965681 AG1-436 C Adder 4.06 MW 3.45 MW
965682 AG1-436 E Adder 2.71 MW 2.3 MW
247966 05WTRV SLR E Adder 0.17 MW 0.14 MW
247967 05OLIV SLR E Adder 0.14 MW 0.12 MW
247969 Z2-116 E Adder 0.08 MW 0.07 MW
943001 AE2-323 C Adder 3.4 MW 2.89 MW
943002 AE2-323 E Adder 1.67 MW 1.42 MW
943021 AE2-325 C Adder 2.11 MW 1.8 MW
943022 AE2-325 E Adder 1.41 MW 1.2 MW
944161 AF1-084 C Adder 3.72 MW 3.16 MW
944162 AF1-084 E Adder 2.12 MW 1.81 MW
944961 AF1-161 C Adder 1.69 MW 1.43 MW
945641 AF1-229 C Adder -5.08 MW -4.31 MW
960681 AF2-359 C Adder 4.06 MW 3.45 MW
960682 AF2-359 E Adder 2.71 MW 2.3 MW
960841 AF2-375 C Adder -5.21 MW -4.42 MW
960981 AF2-389 C Adder 1.94 MW 1.65 MW
960982 AF2-389 E Adder 1.29 MW 1.1 MW
941781 AE2-181 C Adder -2.5 MW -2.12 MW
936632 AD2-079 E O1 Adder 0.49 MW 0.41 MW
936141 AD2-020 C Adder 4.18 MW 3.55 MW
944932 AF1-158 E Adder 3.48 MW 2.96 MW
945111 AF1-176 C Adder 10.2 MW 8.67 MW
945112 AF1-176 E Adder 9.46 MW 8.04 MW
945502 AF1-215 E Adder 6.09 MW 5.18 MW
961051 AF2-396 C Adder 13.35 MW 11.35 MW
939391 AE1-170 C Adder 4.1 MW 3.48 MW
939392 AE1-170 E Adder 5.66 MW 4.81 MW
962601 AG1-109 C Adder 1.69 MW 1.43 MW
936142 AD2-020 E Adder 2.57 MW 2.18 MW
957891 AF2-083 C Adder 6.47 MW 5.5 MW
957892 AF2-083 E Adder 3.23 MW 2.75 MW
958402 AF2-134 E Adder 2.03 MW 1.73 MW
965791 AG1-447 C Adder 2.98 MW 2.53 MW
939161 AE1-146 C Adder -5.03 MW -4.28 MW
943961 AF1-064 C Adder -3.2 MW -2.72 MW
990142 J1224 G External Queue 26.81 MW 26.81 MW
990527 J1329 G External Queue 3.17 MW 3.17 MW
991182 J1586 G External Queue 38.05 MW 38.05 MW
955782 J1062 G External Queue 96.06 MW 96.06 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 127.81 MW 127.81 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 16.34 MW 16.34 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 5.9 MW 5.9 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.38 MW 1.38 MW
NY PJM->LTFIMP_NY CLTF 0.84 MW 0.84 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.14 MW 1.14 MW
WEC LTFEXP_WEC->PJM CLTF 1.43 MW 1.43 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.28 MW 0.28 MW
TVA LTFEXP_TVA->PJM CLTF 2.46 MW 2.46 MW
MEC LTFEXP_MEC->PJM CLTF 5.82 MW 5.82 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.55 MW 3.55 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.26 MW 0.26 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 8.88 MW 8.88 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.14 MW 0.14 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line
939390 to 243322 ckt 1
Base Case OP AC 100.58 % 296.0 A 297.71 36.17

Details for AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line
939390 to 243322 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.58 %
Rating: 296.0 MVA
Rating Type: A
MVA to Mitigate: 297.71 MVA
MW Contribution: 36.17 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
AE1-170 TP-05KENZIE 138.0 kV Ckt 1 line
939390 to 243322 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.41 %
Rating: 296.0 MVA
Rating Type: A
MVA to Mitigate: 297.22 MVA
MW Contribution: 36.16 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247966 05WTRV SLR E 50/50 0.44 MW 0.44 MW
943021 AE2-325 C 50/50 14.49 MW 14.49 MW
943022 AE2-325 E 50/50 9.66 MW 9.66 MW
944161 AF1-084 C 50/50 18.45 MW 18.45 MW
944162 AF1-084 E 50/50 10.54 MW 10.54 MW
944961 AF1-161 C 50/50 11.56 MW 11.56 MW
244412 05WTRV SLR C 50/50 0.07 MW 0.07 MW
936141 AD2-020 C 50/50 28.63 MW 28.63 MW
945111 AF1-176 C 50/50 18.77 MW 18.77 MW
945112 AF1-176 E 50/50 17.4 MW 17.4 MW
961051 AF2-396 C 50/50 66.67 MW 66.67 MW
939391 AE1-170 C 50/50 59.29 MW 59.29 MW
939392 AE1-170 E 50/50 81.88 MW 81.88 MW
962601 AG1-109 C 50/50 11.56 MW 11.56 MW
936142 AD2-020 E 50/50 17.62 MW 17.62 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.02 MW 0.02 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.87 MW 0.87 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.02 MW 0.02 MW
VTF LTFEXP_VFT->PJM CMTX 0.07 MW 0.07 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.0 MW 0.0 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.07 MW 0.07 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.03 MW 0.03 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.03 MW 0.03 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.0 MW 0.0 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request was evaluated as a 121.5 MW injection and 121.58 MW withdrawal in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Light Load Potential Congestion due to Local Energy Deliverability

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 55 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 55 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 55 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 55 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.

 

Cluster 55 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)       Steady-state operation (Category P0);

b)       Three-phase faults with normal clearing time (Category P1);

c)       Single-phase faults with stuck breaker (Category P4);

d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e)       Three-phase faults with normal clearing for common structure (Category P7).

 

Multiple-circuit tower line faults were identified for this study.

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 55 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 55 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 55 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-325, AF1-161, AF1-176, AF2-396 and AG1-109 meet the 0.95 leading and lagging PF requirement.

 

Please note that AE2-325 meets its own requested MFO of the uprate portion. However, AE2-325 combined with AD2-020 does not meet the total requested MFO of 152.2 MW. There are about 1.5 MW deficiencies due to the prior queue project AD2-020.

 

AE1-170, AE2-325 and AF2-396 were tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

 

No other mitigations were found to be required for TC1 Cluster 55.

 

Table 1: TC1 Cluster 55 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

55

AE2-325

Storage

American Electric Power (AEP)

52.2 MW

52.2

MW

31.32

MW

Valley 138 kV substation

AF1-161

Storage

American Electric Power (AEP)

50

MW

50 MW

25 MW

Valley 138 kV

substation

AF1-176

Solar + Storage

American Electric Power (AEP)

300

MW

300 MW

155.684

MW

Corey 138 kV

substation

AF2-396

Solar + Storage

American Electric Power (AEP)

200

MW

200 MW

200 MW

Stinger 138 kV

substation

 

 

Reactive Power Analysis

The reactive power capability of AF1-176 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis complete, no voltage issues found.

 

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA2-116 Cook-East Elkhart 345kV In Service
AC2-154 Davis Creek 138kV Engineering & Procurement
AD2-020 Valley 138 kV Engineering & Procurement
AD2-047 Davis Creek 138 kV Suspended
AD2-060 Davis Creek 138kV Engineering & Procurement
AD2-079 Capitol Ave 34.5kV In Service
AE1-146 Ebersole #2-Fostoria Central 138 kV Under Construction
AE1-170 Kenzie Creek-Colby 138 kV Suspended
AE2-045 Olive-Reynolds 345 kV Engineering & Procurement
AE2-181 Snyder 69kV Under Construction
AE2-323 Twin Branch-Guardian 138 kV Under Construction
AE2-325 Valley 138 kV Active
AF1-064 Weston 69 kV Under Construction
AF1-084 Hartford-Almena 69 kV Engineering & Procurement
AF1-158 Edison-Gravel Pit 138 kV In Service
AF1-161 Valley 138 kV Active
AF1-207 Reynolds-Olive #1 345 kV Engineering & Procurement
AF1-215 Olive-Reynolds 345 kV In Service
AF1-229 Galion-South Berwick 345 kV Engineering & Procurement
AF2-031 Calumet Engineering & Procurement
AF2-078 Reynolds-Olive #1 345 kV Engineering & Procurement
AF2-083 Kenzie Creek-Stone Lake 69 kV Under Construction
AF2-095 Davis Creek 138 kV Active
AF2-132 Reynolds-Olive #1 345 kV Under Construction
AF2-133 Reynolds-Olive #2 345 kV Under Construction
AF2-134 Olive-Reynolds #2 345 kV In Service
AF2-205 Olive-Reynolds #2 345 kV Engineering & Procurement
AF2-350 Kensington 138 kV Active
AF2-359 Olive-University Park 345 kV Engineering & Procurement
AF2-375 Ebersole-Fostoria 138 kV Engineering & Procurement
AF2-389 Kenzie Creek-Stone Lake 69 kV Withdrawn
AF2-396 Stinger 138 kV Active
AF2-441 Burnham 138kV Active
AG1-109 Valley 138 kV Active
AG1-302 Olive-Reynolds #1 345 kV Under Construction
AG1-349 Olive-Reynolds #2 345 kV Engineering & Procurement
AG1-436 Olive-University Park 345 kV Active
AG1-447 Olive-University Park 345 kV Active
AG1-512 University Park North 345 kV Withdrawn
X1-042 Watervliet In Service
X3-005 Wildwood 12kV In Service
Y3-023 Country Side 12kV In Service
Z2-116 Twin Branch 12.47kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
AF1-176 System Reinforcements:
TO Trans Owner ID Title Category Allocated Cost ($USD)
ITCT ITCT_TC1_15164 Reconductor ITCT section of Lallendorf-Monroe line. Post upgrade ratings will be 1677/2124. Cost Allocated $25,902,853
METC METC_TC1_16078 Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1861/2124 MVA. Cost Allocated $372,107
ITCT ITCT_TC1_13866 MTEP24#25223 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027) Contingent $0
Grand Total: $26,274,960

System Reinforcement
Type
Load Flow
TO
ITCT
RTEP ID / TO ID
(Pending) / ITCT_TC1_15164
Title
Reconductor ITCT section of Lallendorf-Monroe line. Post upgrade ratings will be 1677/2124.
Description
Reconductor ITCT section of Lallendorf-Monroe line. Post upgrade ratings will be 1677/2124.
Total Cost ($USD)
$43,500,000
Allocated Cost ($USD)
$25,902,853
Time Estimate
36 Months

Contributor

Facility Contingency
02LALLENDORF-19MON12 345.0 kV Ckt 1 line (Any)
02LALLENDORF-J2486 POI 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-176 29.6 MW 59.5% $25,902,853
AF2-396 20.1 MW 40.5% $17,597,147

System Reinforcement
Type
Load Flow
TO
METC
RTEP ID / TO ID
(Pending) / METC_TC1_16078
Title
Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1861/2124 MVA.
Description
Perform sag mitigation on Allen Junction - Morocco 345kV line. New ratings will be 1861/2124 MVA.
Total Cost ($USD)
$625,000
Allocated Cost ($USD)
$372,107
Time Estimate
18 Months

Contributor

Facility Contingency
02ALLEN-18MOROCCO 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-176 33.4 MW 59.5% $372,107
AF2-396 22.7 MW 40.5% $252,893

System Reinforcement
Type
Load Flow
TO
ITCT
RTEP ID / TO ID
(Pending) / ITCT_TC1_13866
Title
MTEP24#25223 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027)
Description
Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station. This project is a DPP 2020 Network Upgrade associated with the J1516, J1525, J1526, J1527, J1550, J1553, J1557, J1571, J1586, J1587, J1603, J1614, J1635, J1658, J1659, J1663, and J1664 projects. Projected In-Service 6/1/2027
Total Cost ($USD)
$29,916,928
Allocated Cost ($USD)
$0
Time Estimate
TBD

Contingent

Note: Based on PJM cost allocation criteria, AF1-176 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF1-176 could receive cost allocation. Although AF1-176 may not presently have cost responsibility for this upgrade, AF1-176 may need this upgrade in-service to be deliverable to the PJM system. If AF1-176 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
02ALLEN-18MOROCCO 345.0 kV Ckt 1 line (Any)
02LEMOYN-J1062 TAP 345.0 kV Ckt 1 line (Any)
02LALLENDORF-19MON12 345.0 kV Ckt 1 line (Any)
02LEMOYN-J1062 POI 345.0 kV Ckt 1 line (Any)

New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted Facility Transmission Owner Reinforcement Cost Cost Allocated to AF1-176 Scenarios
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
DEI DEI: Rebuild 1 mile of Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$1,500,000 $115,254
  • NIPSCO LPC
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS NIPSCO: Rebuild line (.3miles)Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$0 $0
  • NIPSCO LPC
  • Argos 69.0 - Plymouth 69.0 CKT 1
NIPS Rebuild Argos - Plymouth 69 kV line
Rebuild line, approx 10 miles
$12,654,948 $947,149
  • NIPSCO LPC
  • Argos 69.0 - Rochester TP 69.0 CKT 1
NIPS Rebuild Argos - Rochester TP 69 kV
Rebuild line, approx 3.2 miles
$4,049,583 $311,154
  • NIPSCO LPC
  • CAP BANK 230.0 - Gallagher 230.0 CKT 0
DEI Install 144 MVAR cap bank at Gallagher sub.
Install 144 MVAR cap bank at Gallagher sub.
$3,000,000 $50,139
  • MISO Voltage
  • CAP BANK 138.0 - Shoals 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Shoals sub
Install 28.8 MVAR cap bank at Shoals sub
$3,000,000 $44,304
  • MISO Voltage
  • CAP BANK 138.0 - Avon East 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Avon East sub
Install 28.8 MVAR cap bank at Avon East sub
$3,000,000 $28,302
  • MISO Voltage
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF1-176 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
ATSI n9228.0 Rebuild 6.6 miles of the Lallendorf-Monroe 345 kV line and install OPGW. Replace line drops and wave traps at Lallendorf. Cost Allocated $22,843,720
ATSI n9322.0 Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction. Cost Allocated $838,876
AEP n3985 Upgrade three Marysville Wavetraps ( 3000A) Contingent $0 N/A
Grand Total: $23,682,596

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9228.0
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
n9228.0 / TC1-ATSI-002.b
Title
Rebuild 6.6 miles of the Lallendorf-Monroe 345 kV line and install OPGW. Replace line drops and wave traps at Lallendorf.
Description
Rebuild approximately 6.6 miles of the Lallendorf-Monroe 345 kV line from Lallendorf to the state line. Transfer and reuse approximately 0.9 miles of existing conductor on the Fostoria Central – Lallendorf 345 kV line to maintain double circuit with Lallendorf – Monroe line. Transfer and reuse approximately 5.7 miles of existing conductor on the Lemoyne – Majestic 345 kV line to maintain double circuit with Lallendorf – Monroe line. At Lallendorf substation, Replace line drops and (2) wave traps on the Monroe terminal.
Total Cost ($USD)
$38,362,639
Discounted Total Cost ($USD)
$38,362,639
Allocated Cost ($USD)
$22,843,720
Time Estimate
29 Months

Contributor

Facility Contingency
02LALLENDORF-19MON12 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-176 29.6 MW 59.5% $22,843,720
AF2-396 20.1 MW 40.5% $15,518,919

System Reinforcement: n9322.0
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
n9322.0 / TE-AG1-S-0012a
Title
Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction.
Description
Replace (4) disconnect switches at Allen Junction Replace (4) breaker leads at Allen Junction Reconductor (2) TL Drops at Allen Junction Replace (1) meter at Allen Junction New FE Ratings 1868 / 2249 / 2586 MVA SN/SE/SLD
Total Cost ($USD)
$1,408,997
Discounted Total Cost ($USD)
$1,408,997
Allocated Cost ($USD)
$838,876
Time Estimate
38 Months

Contributor

Facility Contingency
02ALLEN-18MOROCCO 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-176 33.4 MW 59.5% $838,876
AF2-396 22.7 MW 40.5% $570,121

System Reinforcement: n3985
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n3985 / AEPO0036a
Title
Upgrade three Marysville Wavetraps ( 3000A)
Description
Replace 3 Marysville 765 kV wave traps. Costs updated to $705,368 from Facility Study
Total Cost ($USD)
$705,368
Discounted Total Cost ($USD)
$705,368
Allocated Cost ($USD)
$0
Time Estimate
18 to 24 Months

Contingent

Note: Based on PJM cost allocation criteria, AF1-176 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AF1-176 may not have cost responsibility for this upgrade, AF1-176 may need this upgrade in-service to be deliverable to the PJM system. If AF1-176 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05MARYSV-AF2-137 TAP 765.0 kV Ckt 1 line (Any)
05MARYSV-05SORENS 765.0 kV Ckt 1 line (Any)
05MARYSV-AF2-137 TP 765.0 kV Ckt 1 line (Any)

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF1-176


AF1-176 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF1-176 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AF1-176 One Line Diagram

AF1-176 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.