AF2-010 Phase III Study Report

v1.00 released 2025-09-18 16:28

Union City-Titusville 115 kV

46.0 MW Capacity / 77.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is RWE Solar Development, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Mid-Atlantic Interstate Transmission, LLC.

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $12,226,120 $18,097,381 = 0.68 AND ( $12,226,120 - $18,097,381 ) 77.0 = $-76,250 per MW

General

The Project Developer has proposed a Solar generating facility located in the Mid-Atlantic Interstate Transmission, LLC zone — Erie County, Pennsylvania. The installed facilities will have a total capability of 77.0 MW with 46.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-010
Project Name:
Union City-Titusville 115 kV
Project Developer Name:
RWE Solar Development, LLC
State:
Pennsylvania
County:
Erie
Transmission Owner:
Mid-Atlantic Interstate Transmission, LLC
MFO:
77.0
MWE:
77.0
MWC:
46.0
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF2-010 will interconnect with the Mid-Atlantic Interstate Transmission, LLC transmission system by constructing a new 115 kV three (3) breaker ring bus substation and looping the Titusville – Union City 115 kV Line into the new station. The new substation will be located approximately 1.27 miles from Union City Substation. The developer will be responsible for acquiring all easements, properties, and permits that may be required to construct both the new interconnection switching station and the associated interconnection facilities. The developer will also be responsible for the rough grade of the property and an access road to the proposed three-breaker ring bus site. The project will also require remote end upgrades at Union City Substation and Titusville Substation.

Attachment 1 shows a one-line diagram of the proposed interconnection facilities for the AF2-010 generation project to connect to the Mid-Atlantic Interstate Transmission, LLC Transmission System.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF2-010 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF2-010 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $52,291 $52,291
Other Scope $4,973 $4,973
Option to Build Oversight $957,485 $957,485
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $2,008,005 $2,008,005
Network Upgrades $2,930,505 $2,930,505
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $7,287,610 $7,287,610
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $13,240,869 $13,240,869

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF2-010

Security has been calculated for the AF2-010 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF2-010
Project(s): AF2-010
Final Agreement Security (A): $13,240,869
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $13,240,869
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The interconnection of the project at the Primary POI will be accomplished by constructing a new 115 kV three (3) breaker ring bus substation and looping the Titusville – Union City 115 kV line into the new station. The new substation will be located approximately 1.27 miles from Union City Substation. The developer will be responsible for acquiring all easements, properties, and permits that may be required to construct both the new interconnection switching station and the associated facilities. The developer will also be responsible for the rough grade of the property and an access road to the proposed three-breaker ring bus site.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Project Developer has elected the option Option to Build where they will assume responsibility for the design, procurement and construction of the Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades identified in this Phase III SIS report.

The Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9524.0

Install equipment for anti-islanding scheme at Grandview Substation.

$267,578 $27,328 $4,843 $191 $299,940 $149,970 (See Note 1)
n9523.0

Install equipment for anti-islanding scheme at Erie South Substation.

$267,578 $27,328 $4,843 $191 $299,940 $149,970 (See Note 1)
n9522.0

Install equipment for anti-islanding scheme at Titusville Substation.

$291,403 $53,276 $5,274 $373 $350,326 $175,163 (See Note 1)
n9521.0

Install equipment for anti-islanding scheme at Union City Substation.

$412,550 $53,312 $7,467 $373 $473,702 $236,851 (See Note 1)
n9520.0

Replace line relaying at Union City Substation.

$490,507 $46,346 $8,878 $324 $546,055 $546,055
n9519.0

Replace line relaying at Titusville Substation.

$308,185 $38,593 $5,578 $270 $352,626 $352,626
n9518.0

The Titusville – Union City 115 kV, PNT-115-DU line will be cut and looped into the new interconnection substation at a point approximately 1.27 miles from Union City substation, between structures 208 and 209.

$999,141 $295,538 $18,084 $7,107 $1,319,870 $1,319,870
Option to Build Oversight
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

FirstEnergy oversight of developer design and construction of new interconnection substation

$940,463 $0 $17,022 $0 $957,485 $957,485
Other
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Support for Project Developer owned revenue metering.

$3,730 $0 $1,243 $0 $4,973 $4,973
Stand-Alone Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9517.0

Design, Installation, and testing/commissioning for MPLS equipment SCADA transport, Crossbow engineering and materials at AF2-010 Substation.

$203,737 $88,286 $3,688 $618 $296,329 $296,329
n9516.0

New ADSS Fiber installation between Titusville Substation and Union City Substation.

$446,321 $40,444 $8,078 $283 $495,126 $495,126
n9515.0

Install FE network and security equipment at interconnection substation.

$946,575 $251,084 $17,133 $1,758 $1,216,550 $1,216,550
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Energize and integrate generator interconnection facilities to the transmission system.

$51,273 $0 $1,018 $0 $52,291 $52,291

Based on the scope of work for the Interconnection Facilities, it is expected to take 57 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

 

Transmission Owner Analysis

TO performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AF2-010 did not contribute to any overloads on the TO transmission <100 kV system.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. PENELEC interconnection requirements can be found here. Refer to AF2-010 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 77.0 MW (46.0 MW Capacity) injection in the PENELEC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
PN_P2-3_PN-230-0347-2_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-2_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200741 CKT 9   /*26SEWARD 2   230.0 - 26SEWARD     115.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Breaker AC 113.85 % 980.0 B 1115.71 10.71
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
PN_P2-3_PN-230-0347-A_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-A_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200767 CKT 1   /*26SEWARD 2   230.0 - 26HOMER CT   230.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Breaker AC 110.83 % 980.0 B 1086.11 10.8
PENELEC 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line
999310 to 200767 ckt S
PN_P2-3_PN-230-0183-210_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0183-210_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Breaker AC 106.62 % 827.0 B 881.73 12.33
PENELEC 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer
200769 to 999310 ckt S
PN_P2-3_PN-230-0183-210_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0183-210_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Breaker AC 106.56 % 827.0 B 881.23 12.33
PENELEC 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line
200795 to 200810 ckt 1
PN_P2-3_PN-230-0347-2_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-2_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200741 CKT 9   /*26SEWARD 2   230.0 - 26SEWARD     115.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Breaker AC 103.7 % 980.0 B 1016.27 11.82
PENELEC 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line
999310 to 200767 ckt S
PN_P2-2_PN-230-001T_SRT-A
CONTINGENCY 'PN_P2-2_PN-230-001T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Bus AC 106.62 % 827.0 B 881.73 12.33
PENELEC 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer
200769 to 999310 ckt S
PN_P2-2_PN-230-001T_SRT-A
CONTINGENCY 'PN_P2-2_PN-230-001T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Bus AC 106.56 % 827.0 B 881.23 12.33

Details for 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line l/o PN_P2-3_PN-230-0347-2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Contingency Name:
PN_P2-3_PN-230-0347-2_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-2_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200741 CKT 9   /*26SEWARD 2   230.0 - 26SEWARD     115.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 113.85 %
Rating: 980.0 MVA
Rating Type: B
MVA to Mitigate: 1115.71 MVA
MW Contribution: 10.71 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Contingency Name:
PN_P2-3_PN-230-0347-2_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-2_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200741 CKT 9   /*26SEWARD 2   230.0 - 26SEWARD     115.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 114.1 %
Rating: 980.0 MVA
Rating Type: B
MVA to Mitigate: 1118.22 MVA
MW Contribution: 10.71 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 1.7 MW 1.45 MW
961972 AG1-040 E Adder 1.14 MW 0.96 MW
961981 AG1-041 C 50/50 2.13 MW 2.13 MW
961982 AG1-041 E 50/50 1.42 MW 1.42 MW
962511 AG1-100 C Adder 1.63 MW 1.39 MW
962512 AG1-100 E Adder 1.09 MW 0.92 MW
962912 AG1-140 E Adder 0.12 MW 0.1 MW
963441 AG1-193 C Adder 0.94 MW 0.8 MW
963442 AG1-193 E Adder 0.63 MW 0.53 MW
963481 AG1-197 C Adder 1.29 MW 1.1 MW
963482 AG1-197 E Adder 0.86 MW 0.73 MW
963491 AG1-198 C Adder 1.0 MW 0.85 MW
963492 AG1-198 E Adder 0.67 MW 0.57 MW
963992 AG1-253 E Adder 0.18 MW 0.16 MW
964201 AG1-281 C 50/50 3.26 MW 3.26 MW
964202 AG1-281 E 50/50 2.17 MW 2.17 MW
964391 AG1-301 C Adder 2.25 MW 1.91 MW
964392 AG1-301 E Adder 1.5 MW 1.27 MW
290086 Q-036 E 50/50 23.83 MW 23.83 MW
296332 R-032 E 50/50 19.4 MW 19.4 MW
942351 AE2-248 C Adder 1.26 MW 1.07 MW
942352 AE2-248 E Adder 0.84 MW 0.72 MW
942491 AE2-262 C Adder 7.18 MW 6.1 MW
942492 AE2-262 E Adder 4.82 MW 4.1 MW
942501 AE2-263 C Adder 6.75 MW 5.73 MW
942502 AE2-263 E Adder 4.5 MW 3.83 MW
942811 AE2-299 C Adder 4.51 MW 3.83 MW
942812 AE2-299 E Adder 18.05 MW 15.34 MW
942961 AE2-316 C Adder 6.76 MW 5.75 MW
942962 AE2-316 E Adder 8.01 MW 6.8 MW
943151 AE2-344 C Adder 9.49 MW 8.07 MW
943152 AE2-344 E Adder 6.33 MW 5.38 MW
943352 AF1-006 E Adder 0.93 MW 0.79 MW
943712 AF1-039 E O1 Adder 1.08 MW 0.92 MW
944261 AF1-094 C Adder 1.66 MW 1.42 MW
944262 AF1-094 E Adder 1.11 MW 0.94 MW
944691 AF1-134 C Adder 1.91 MW 1.62 MW
944692 AF1-134 E Adder 1.27 MW 1.08 MW
944752 AF1-140 E 50/50 1.91 MW 1.91 MW
944781 AF1-143 C 50/50 14.2 MW 14.2 MW
944782 AF1-143 E 50/50 7.57 MW 7.57 MW
944902 AF1-155 E Adder 1.28 MW 1.09 MW
945021 AF1-167 C Adder 1.14 MW 0.97 MW
945022 AF1-167 E Adder 0.76 MW 0.65 MW
958742 AF2-165 E Adder 1.14 MW 0.97 MW
958751 AF2-166 C Adder 1.78 MW 1.51 MW
958752 AF2-166 E Adder 1.19 MW 1.01 MW
959441 AF2-235 C Adder 0.88 MW 0.74 MW
959442 AF2-235 E Adder 0.58 MW 0.5 MW
959471 AF2-238 C Adder 2.16 MW 1.83 MW
959472 AF2-238 E Adder 1.44 MW 1.22 MW
960031 AF2-294 C Adder 1.7 MW 1.44 MW
960032 AF2-294 E Adder 1.13 MW 0.96 MW
960051 AF2-296 C Adder 1.91 MW 1.62 MW
960052 AF2-296 E Adder 1.27 MW 1.08 MW
200503 26C.SLOPE 50/50 2.46 MW 2.46 MW
200794 26CONEMAGH 50/50 0.5 MW 0.5 MW
200809 26SITHE 50/50 2.71 MW 2.71 MW
200834 26SW_E13_K22 50/50 0.02 MW 0.02 MW
200835 26ARN_Z1-066 50/50 1.89 MW 1.89 MW
200837 26HOMER C1 50/50 285.88 MW 285.88 MW
200838 26HOMER C2 50/50 237.2 MW 237.2 MW
200839 26HOMER C3 50/50 251.1 MW 251.1 MW
200846 26FORWARD 50/50 0.17 MW 0.17 MW
200852 26WARR RDG Adder 0.47 MW 0.4 MW
200864 K-013 E 50/50 8.32 MW 8.32 MW
200883 Q-053 E 50/50 8.55 MW 8.55 MW
200888 26HIGHLAND 50/50 0.41 MW 0.41 MW
200889 26STNY CRK 50/50 0.4 MW 0.4 MW
200890 26BF_G21_K23 50/50 0.18 MW 0.18 MW
200891 26CSLMN_L13 50/50 0.23 MW 0.23 MW
200892 26LOOKOUT 50/50 0.24 MW 0.24 MW
200894 26K02 Adder 7.82 MW 6.64 MW
200925 26R32 50/50 0.65 MW 0.65 MW
200945 26CT_V3-030 50/50 0.18 MW 0.18 MW
202225 26SCI_S29B 50/50 0.08 MW 0.08 MW
203349 26Z1-069 C 50/50 0.63 MW 0.63 MW
203999 P-047 E Adder 16.46 MW 13.99 MW
236828 01GRAYMONT Adder 0.53 MW 0.45 MW
292350 K-023 50/50 6.07 MW 6.07 MW
292542 L-013 1 50/50 7.57 MW 7.57 MW
293301 N-039 E 50/50 16.37 MW 16.37 MW
293393 V3-030E 50/50 5.39 MW 5.39 MW
293603 O-018 E 50/50 16.94 MW 16.94 MW
293902 O-048 E 50/50 6.81 MW 6.81 MW
294515 O38_P22 50/50 15.58 MW 15.58 MW
294903 P-060 E 50/50 12.75 MW 12.75 MW
916202 Z1-069 E 50/50 16.5 MW 16.5 MW
940201 AE2-001 C Adder 1.6 MW 1.36 MW
940202 AE2-001 E Adder 1.07 MW 0.91 MW
940861 AE2-074 C 50/50 3.52 MW 3.52 MW
940862 AE2-074 E 50/50 4.63 MW 4.63 MW
941232 AE2-117 E Adder 1.52 MW 1.29 MW
941241 AE2-118 C 50/50 2.45 MW 2.45 MW
941242 AE2-118 E 50/50 1.63 MW 1.63 MW
941322 AE2-126 E Adder 1.37 MW 1.17 MW
941332 AE2-129 E Adder 1.52 MW 1.3 MW
941352 AE2-131 E Adder 1.52 MW 1.3 MW
941421 AE2-139 C Adder 8.05 MW 6.84 MW
941422 AE2-139 E Adder 5.37 MW 4.56 MW
946222 AF1-287 E Adder 1.09 MW 0.93 MW
946381 AF1-302 C Adder 2.95 MW 2.51 MW
946382 AF1-302 E Adder 3.94 MW 3.35 MW
946772 AF1-217 E Adder 1.09 MW 0.93 MW
957161 AF2-010 C Adder 6.4 MW 5.44 MW
957162 AF2-010 E Adder 4.31 MW 3.66 MW
957451 AF2-039 C Adder 1.32 MW 1.12 MW
957452 AF2-039 E Adder 0.88 MW 0.75 MW
957941 AF2-088 C Adder 0.64 MW 0.54 MW
957942 AF2-088 E Adder 0.42 MW 0.36 MW
957981 AF2-092 C 50/50 2.14 MW 2.14 MW
957982 AF2-092 E 50/50 1.43 MW 1.43 MW
958362 AF2-130 E Adder 1.19 MW 1.01 MW
200833 26SEWRDB34 50/50 34.27 MW 34.27 MW
200886 26ARWF_N39 50/50 0.46 MW 0.46 MW
200915 26CHSTN_FL 50/50 0.28 MW 0.28 MW
203034 26NA_O38_P22 50/50 0.38 MW 0.38 MW
959301 AF2-221 C 50/50 2.02 MW 2.02 MW
959302 AF2-221 E 50/50 2.79 MW 2.79 MW
913142 Y1-033 E OP1 Adder 5.99 MW 5.09 MW
957012 AF2-002 E 50/50 1.27 MW 1.27 MW
203940 AF1-140 C 50/50 2.86 MW 2.86 MW
203946 AE2-131 C Adder 2.29 MW 1.94 MW
203948 AG1-140 C Adder 0.25 MW 0.22 MW
203950 AF1-217 C Adder 1.64 MW 1.39 MW
203955 AF1-039 C O1 Adder 1.62 MW 1.38 MW
203962 AF1-287 C Adder 1.64 MW 1.39 MW
203963 AG1-253 C Adder 0.38 MW 0.32 MW
237050 AF1-155 C Adder 1.92 MW 1.63 MW
293432 R-040 E 50/50 0.43 MW 0.43 MW
294573 P-028 E Adder 13.36 MW 11.35 MW
916004 26SW_E13_K22 50/50 2.29 MW 2.29 MW
957001 AF2-001 C 50/50 3.82 MW 3.82 MW
957002 AF2-001 E 50/50 2.55 MW 2.55 MW
957011 AF2-002 C 50/50 1.91 MW 1.91 MW
957561 AF2-050 C 50/50 8.81 MW 8.81 MW
957562 AF2-050 E 50/50 5.88 MW 5.88 MW
203961 AE2-224 C 50/50 2.88 MW 2.88 MW
942126 AE2-224 E 50/50 11.75 MW 11.75 MW
200905 26Q36 50/50 0.79 MW 0.79 MW
941191 AE2-113 C 50/50 13.12 MW 13.12 MW
941192 AE2-113 E 50/50 12.32 MW 12.32 MW
944182 AF1-086 E Adder 13.95 MW 11.86 MW
944301 AF1-098 C Adder 6.85 MW 5.82 MW
944302 AF1-098 E Adder 4.56 MW 3.88 MW
944411 AF1-106 C Adder 3.66 MW 3.11 MW
944881 AF1-153 C Adder 1.92 MW 1.63 MW
944882 AF1-153 E Adder 1.28 MW 1.09 MW
945751 AF1-240 C Adder 1.61 MW 1.37 MW
945752 AF1-240 E Adder 0.7 MW 0.59 MW
946571 AF1-321 C 50/50 3.82 MW 3.82 MW
946572 AF1-321 E 50/50 2.55 MW 2.55 MW
962411 AG1-090 C Adder 5.72 MW 4.86 MW
962412 AG1-090 E Adder 12.39 MW 10.53 MW
965121 AG1-377 C Adder 1.14 MW 0.97 MW
965122 AG1-377 E Adder 2.67 MW 2.27 MW
965131 AG1-378 C Adder 1.14 MW 0.97 MW
965132 AG1-378 E Adder 2.67 MW 2.27 MW
966771 AG1-548 C Adder 6.22 MW 5.29 MW
966772 AG1-548 E Adder 14.51 MW 12.33 MW
203915 26BF_Z2-108 50/50 4.26 MW 4.26 MW
235003 AC1-025 E Adder 0.23 MW 0.2 MW
961581 Q1080_CY23 External Queue 40.35 MW 40.35 MW
CBM North LTFEXP_CBM-N->PJM CBM 9.16 MW 9.16 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.15 MW 0.15 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.51 MW 0.51 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.26 MW 0.26 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.14 MW 0.14 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.41 MW 0.41 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.09 MW 0.09 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.28 MW 0.28 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.28 MW 0.28 MW
MDU PJM->LTFIMP_MDU CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.14 MW 0.14 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.35 MW 0.35 MW

Details for 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line l/o PN_P2-3_PN-230-0347-A_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Contingency Name:
PN_P2-3_PN-230-0347-A_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-A_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200767 CKT 1   /*26SEWARD 2   230.0 - 26HOMER CT   230.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.83 %
Rating: 980.0 MVA
Rating Type: B
MVA to Mitigate: 1086.11 MVA
MW Contribution: 10.8 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Contingency Name:
PN_P2-3_PN-230-0347-A_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-A_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200767 CKT 1   /*26SEWARD 2   230.0 - 26HOMER CT   230.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 111.06 %
Rating: 980.0 MVA
Rating Type: B
MVA to Mitigate: 1088.38 MVA
MW Contribution: 10.8 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 1.72 MW 1.47 MW
961972 AG1-040 E Adder 1.15 MW 0.98 MW
961981 AG1-041 C 50/50 2.0 MW 2.0 MW
961982 AG1-041 E 50/50 1.33 MW 1.33 MW
962511 AG1-100 C Adder 1.65 MW 1.4 MW
962512 AG1-100 E Adder 1.1 MW 0.94 MW
962912 AG1-140 E Adder 0.12 MW 0.1 MW
963441 AG1-193 C Adder 0.95 MW 0.81 MW
963442 AG1-193 E Adder 0.63 MW 0.54 MW
963481 AG1-197 C Adder 1.31 MW 1.11 MW
963482 AG1-197 E Adder 0.87 MW 0.74 MW
963491 AG1-198 C Adder 1.01 MW 0.86 MW
963492 AG1-198 E Adder 0.67 MW 0.57 MW
963992 AG1-253 E Adder 0.19 MW 0.16 MW
964201 AG1-281 C 50/50 3.0 MW 3.0 MW
964202 AG1-281 E 50/50 2.0 MW 2.0 MW
964391 AG1-301 C Adder 2.04 MW 1.74 MW
964392 AG1-301 E Adder 1.36 MW 1.16 MW
290086 Q-036 E Adder 22.29 MW 18.94 MW
296332 R-032 E 50/50 17.93 MW 17.93 MW
942351 AE2-248 C Adder 1.21 MW 1.03 MW
942352 AE2-248 E Adder 0.81 MW 0.69 MW
942491 AE2-262 C Adder 6.96 MW 5.91 MW
942492 AE2-262 E Adder 4.68 MW 3.98 MW
942501 AE2-263 C Adder 6.54 MW 5.56 MW
942502 AE2-263 E Adder 4.37 MW 3.71 MW
942811 AE2-299 C Adder 4.57 MW 3.88 MW
942812 AE2-299 E Adder 18.26 MW 15.52 MW
942961 AE2-316 C Adder 6.74 MW 5.73 MW
942962 AE2-316 E Adder 7.98 MW 6.79 MW
943151 AE2-344 C Adder 9.61 MW 8.17 MW
943152 AE2-344 E Adder 6.4 MW 5.44 MW
943352 AF1-006 E Adder 0.94 MW 0.8 MW
943712 AF1-039 E O1 Adder 1.03 MW 0.88 MW
944261 AF1-094 C Adder 1.68 MW 1.43 MW
944262 AF1-094 E Adder 1.12 MW 0.95 MW
944691 AF1-134 C Adder 1.82 MW 1.55 MW
944692 AF1-134 E Adder 1.22 MW 1.03 MW
944752 AF1-140 E 50/50 1.77 MW 1.77 MW
944781 AF1-143 C 50/50 13.57 MW 13.57 MW
944782 AF1-143 E 50/50 7.24 MW 7.24 MW
944902 AF1-155 E Adder 1.26 MW 1.07 MW
945021 AF1-167 C Adder 1.15 MW 0.97 MW
945022 AF1-167 E Adder 0.76 MW 0.65 MW
958742 AF2-165 E Adder 1.14 MW 0.97 MW
958751 AF2-166 C Adder 1.78 MW 1.51 MW
958752 AF2-166 E Adder 1.19 MW 1.01 MW
959441 AF2-235 C Adder 0.88 MW 0.75 MW
959442 AF2-235 E Adder 0.59 MW 0.5 MW
959471 AF2-238 C Adder 2.18 MW 1.85 MW
959472 AF2-238 E Adder 1.45 MW 1.24 MW
960031 AF2-294 C Adder 1.72 MW 1.46 MW
960032 AF2-294 E Adder 1.14 MW 0.97 MW
960051 AF2-296 C Adder 1.82 MW 1.55 MW
960052 AF2-296 E Adder 1.22 MW 1.03 MW
200503 26C.SLOPE 50/50 2.24 MW 2.24 MW
200794 26CONEMAGH 50/50 0.47 MW 0.47 MW
200809 26SITHE 50/50 2.77 MW 2.77 MW
200834 26SW_E13_K22 50/50 0.02 MW 0.02 MW
200835 26ARN_Z1-066 50/50 1.81 MW 1.81 MW
200837 26HOMER C1 50/50 291.81 MW 291.81 MW
200838 26HOMER C2 50/50 241.85 MW 241.85 MW
200839 26HOMER C3 50/50 256.03 MW 256.03 MW
200846 26FORWARD 50/50 0.16 MW 0.16 MW
200852 26WARR RDG Adder 0.43 MW 0.36 MW
200864 K-013 E 50/50 7.97 MW 7.97 MW
200883 Q-053 E 50/50 7.87 MW 7.87 MW
200888 26HIGHLAND 50/50 0.38 MW 0.38 MW
200889 26STNY CRK 50/50 0.38 MW 0.38 MW
200890 26BF_G21_K23 50/50 0.18 MW 0.18 MW
200891 26CSLMN_L13 50/50 0.22 MW 0.22 MW
200892 26LOOKOUT 50/50 0.23 MW 0.23 MW
200894 26K02 Adder 7.77 MW 6.61 MW
200925 26R32 50/50 0.6 MW 0.6 MW
202225 26SCI_S29B 50/50 0.08 MW 0.08 MW
203349 26Z1-069 C 50/50 0.64 MW 0.64 MW
203999 P-047 E Adder 16.65 MW 14.16 MW
236828 01GRAYMONT Adder 0.51 MW 0.43 MW
292350 K-023 50/50 5.8 MW 5.8 MW
292542 L-013 1 50/50 7.24 MW 7.24 MW
293301 N-039 E 50/50 14.5 MW 14.5 MW
293393 V3-030E Adder 5.0 MW 4.25 MW
293603 O-018 E 50/50 15.65 MW 15.65 MW
293902 O-048 E 50/50 6.51 MW 6.51 MW
294515 O38_P22 50/50 13.79 MW 13.79 MW
294903 P-060 E 50/50 12.1 MW 12.1 MW
916202 Z1-069 E 50/50 16.69 MW 16.69 MW
940201 AE2-001 C Adder 1.54 MW 1.31 MW
940202 AE2-001 E Adder 1.03 MW 0.87 MW
940861 AE2-074 C 50/50 3.56 MW 3.56 MW
940862 AE2-074 E 50/50 4.69 MW 4.69 MW
941232 AE2-117 E Adder 1.39 MW 1.18 MW
941241 AE2-118 C Adder 2.22 MW 1.89 MW
941242 AE2-118 E Adder 1.48 MW 1.26 MW
941322 AE2-126 E Adder 1.34 MW 1.14 MW
941332 AE2-129 E Adder 1.44 MW 1.23 MW
941352 AE2-131 E Adder 1.44 MW 1.23 MW
941421 AE2-139 C Adder 8.07 MW 6.86 MW
941422 AE2-139 E Adder 5.38 MW 4.57 MW
946222 AF1-287 E Adder 1.1 MW 0.94 MW
946381 AF1-302 C Adder 2.94 MW 2.5 MW
946382 AF1-302 E Adder 3.93 MW 3.34 MW
946772 AF1-217 E Adder 1.1 MW 0.94 MW
957161 AF2-010 C Adder 6.45 MW 5.49 MW
957162 AF2-010 E Adder 4.35 MW 3.7 MW
957451 AF2-039 C Adder 1.28 MW 1.09 MW
957452 AF2-039 E Adder 0.85 MW 0.72 MW
957941 AF2-088 C Adder 0.62 MW 0.52 MW
957942 AF2-088 E Adder 0.41 MW 0.35 MW
957981 AF2-092 C 50/50 2.01 MW 2.01 MW
957982 AF2-092 E 50/50 1.34 MW 1.34 MW
958362 AF2-130 E Adder 1.19 MW 1.01 MW
200833 26SEWRDB34 50/50 27.1 MW 27.1 MW
200886 26ARWF_N39 50/50 0.41 MW 0.41 MW
200915 26CHSTN_FL 50/50 0.26 MW 0.26 MW
203034 26NA_O38_P22 50/50 0.34 MW 0.34 MW
959301 AF2-221 C 50/50 1.89 MW 1.89 MW
959302 AF2-221 E 50/50 2.62 MW 2.62 MW
913142 Y1-033 E OP1 Adder 5.73 MW 4.87 MW
957012 AF2-002 E 50/50 1.22 MW 1.22 MW
203940 AF1-140 C 50/50 2.65 MW 2.65 MW
203946 AE2-131 C Adder 2.17 MW 1.84 MW
203948 AG1-140 C Adder 0.26 MW 0.22 MW
203950 AF1-217 C Adder 1.66 MW 1.41 MW
203955 AF1-039 C O1 Adder 1.55 MW 1.32 MW
203962 AF1-287 C Adder 1.66 MW 1.41 MW
203963 AG1-253 C Adder 0.38 MW 0.33 MW
237050 AF1-155 C Adder 1.9 MW 1.61 MW
293432 R-040 E 50/50 0.41 MW 0.41 MW
294573 P-028 E Adder 13.45 MW 11.43 MW
916004 26SW_E13_K22 50/50 2.18 MW 2.18 MW
957001 AF2-001 C 50/50 3.67 MW 3.67 MW
957002 AF2-001 E 50/50 2.44 MW 2.44 MW
957011 AF2-002 C 50/50 1.83 MW 1.83 MW
957561 AF2-050 C 50/50 7.75 MW 7.75 MW
957562 AF2-050 E 50/50 5.17 MW 5.17 MW
203961 AE2-224 C 50/50 2.53 MW 2.53 MW
942126 AE2-224 E 50/50 10.33 MW 10.33 MW
941191 AE2-113 C 50/50 13.16 MW 13.16 MW
941192 AE2-113 E 50/50 12.36 MW 12.36 MW
944182 AF1-086 E Adder 13.21 MW 11.22 MW
944301 AF1-098 C Adder 6.92 MW 5.88 MW
944302 AF1-098 E Adder 4.61 MW 3.92 MW
944411 AF1-106 C Adder 3.7 MW 3.14 MW
944881 AF1-153 C Adder 1.9 MW 1.61 MW
944882 AF1-153 E Adder 1.26 MW 1.07 MW
945751 AF1-240 C Adder 1.57 MW 1.33 MW
945752 AF1-240 E Adder 0.68 MW 0.58 MW
946571 AF1-321 C 50/50 3.67 MW 3.67 MW
946572 AF1-321 E 50/50 2.44 MW 2.44 MW
962411 AG1-090 C Adder 5.42 MW 4.6 MW
962412 AG1-090 E Adder 11.73 MW 9.97 MW
965121 AG1-377 C Adder 1.08 MW 0.92 MW
965122 AG1-377 E Adder 2.53 MW 2.15 MW
965131 AG1-378 C Adder 1.08 MW 0.92 MW
965132 AG1-378 E Adder 2.53 MW 2.15 MW
966771 AG1-548 C Adder 6.28 MW 5.34 MW
966772 AG1-548 E Adder 14.65 MW 12.45 MW
203915 26BF_Z2-108 50/50 4.07 MW 4.07 MW
235003 AC1-025 E Adder 0.22 MW 0.19 MW
961581 Q1080_CY23 External Queue 41.47 MW 41.47 MW
CBM North LTFEXP_CBM-N->PJM CBM 9.27 MW 9.27 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.87 MW 0.87 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.18 MW 0.18 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.41 MW 0.41 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.24 MW 0.24 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.13 MW 0.13 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.29 MW 0.29 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.06 MW 0.06 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.2 MW 0.2 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.44 MW 0.44 MW
MDU PJM->LTFIMP_MDU CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.09 MW 0.09 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.33 MW 0.33 MW

Details for 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line l/o PN_P2-3_PN-230-0183-210_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT _-26HOMER CT 230.0 kV Ckt S line
999310 to 200767 ckt S
Contingency Name:
PN_P2-3_PN-230-0183-210_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0183-210_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 106.62 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 881.73 MVA
MW Contribution: 12.33 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT _-26HOMER CT 230.0 kV Ckt S line
999310 to 200767 ckt S
Contingency Name:
PN_P2-3_PN-230-0183-210_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0183-210_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 108.08 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 893.85 MVA
MW Contribution: 12.33 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 2.08 MW 1.77 MW
961972 AG1-040 E Adder 1.39 MW 1.18 MW
962511 AG1-100 C Adder 1.99 MW 1.7 MW
962512 AG1-100 E Adder 1.33 MW 1.13 MW
962912 AG1-140 E Adder 0.14 MW 0.12 MW
963441 AG1-193 C Adder 1.08 MW 0.92 MW
963442 AG1-193 E Adder 0.72 MW 0.61 MW
963481 AG1-197 C Adder 1.57 MW 1.34 MW
963482 AG1-197 E Adder 1.05 MW 0.89 MW
963491 AG1-198 C Adder 1.15 MW 0.98 MW
963492 AG1-198 E Adder 0.77 MW 0.65 MW
963992 AG1-253 E Adder 0.22 MW 0.19 MW
942491 AE2-262 C Adder 4.14 MW 3.52 MW
942492 AE2-262 E Adder 2.78 MW 2.37 MW
942501 AE2-263 C Adder 3.89 MW 3.31 MW
942502 AE2-263 E Adder 2.6 MW 2.21 MW
942811 AE2-299 C Adder 5.51 MW 4.68 MW
942812 AE2-299 E Adder 22.03 MW 18.73 MW
942961 AE2-316 C Adder 6.66 MW 5.66 MW
942962 AE2-316 E Adder 7.88 MW 6.7 MW
943151 AE2-344 C Adder 11.58 MW 9.85 MW
943152 AE2-344 E Adder 7.72 MW 6.56 MW
943352 AF1-006 E Adder 1.14 MW 0.97 MW
944261 AF1-094 C Adder 1.92 MW 1.64 MW
944262 AF1-094 E Adder 1.28 MW 1.09 MW
944902 AF1-155 E Adder 1.06 MW 0.91 MW
945021 AF1-167 C Adder 1.21 MW 1.02 MW
945022 AF1-167 E Adder 0.8 MW 0.68 MW
958742 AF2-165 E Adder 1.19 MW 1.01 MW
958751 AF2-166 C Adder 1.7 MW 1.45 MW
958752 AF2-166 E Adder 1.14 MW 0.96 MW
959441 AF2-235 C Adder 0.94 MW 0.8 MW
959442 AF2-235 E Adder 0.63 MW 0.53 MW
959471 AF2-238 C 50/50 2.6 MW 2.6 MW
959472 AF2-238 E 50/50 1.73 MW 1.73 MW
960031 AF2-294 C Adder 2.09 MW 1.77 MW
960032 AF2-294 E Adder 1.39 MW 1.18 MW
200642 26SENECA#1 50/50 7.93 MW 7.93 MW
200643 26SENECA#2 50/50 7.42 MW 7.42 MW
200828 26HNSMLK 1 50/50 2.22 MW 2.22 MW
200829 26HNSMLK 2 50/50 2.22 MW 2.22 MW
200830 26HNSMLK 3 50/50 2.22 MW 2.22 MW
200831 26HNSMLK 4 50/50 2.22 MW 2.22 MW
200832 26HNSMLK 5 50/50 2.22 MW 2.22 MW
200838 26HOMER C2 50/50 323.63 MW 323.63 MW
200839 26HOMER C3 50/50 342.61 MW 342.61 MW
200887 26ARMNA MT 50/50 0.59 MW 0.59 MW
200894 26K02 Adder 7.45 MW 6.34 MW
203261 26BLOSSBCT 50/50 0.81 MW 0.81 MW
203349 26Z1-069 C 50/50 0.78 MW 0.78 MW
203350 26MILZ1-092 50/50 0.77 MW 0.77 MW
203999 P-047 E 50/50 20.3 MW 20.3 MW
916202 Z1-069 E 50/50 20.35 MW 20.35 MW
940861 AE2-074 C 50/50 4.3 MW 4.3 MW
940862 AE2-074 E 50/50 5.67 MW 5.67 MW
941322 AE2-126 E Adder 0.94 MW 0.8 MW
941421 AE2-139 C Adder 8.78 MW 7.46 MW
941422 AE2-139 E Adder 5.85 MW 4.97 MW
946222 AF1-287 E Adder 1.33 MW 1.13 MW
946381 AF1-302 C Adder 2.91 MW 2.47 MW
946382 AF1-302 E Adder 3.88 MW 3.3 MW
946772 AF1-217 E Adder 1.33 MW 1.13 MW
957161 AF2-010 C Adder 7.37 MW 6.26 MW
957162 AF2-010 E Adder 4.97 MW 4.22 MW
958362 AF2-130 E Adder 1.14 MW 0.96 MW
959301 AF2-221 C Adder -0.98 MW -0.83 MW
203940 AF1-140 C Adder -1.26 MW -1.07 MW
203948 AG1-140 C Adder 0.31 MW 0.26 MW
203950 AF1-217 C Adder 2.0 MW 1.7 MW
203955 AF1-039 C O1 Adder -0.84 MW -0.72 MW
203962 AF1-287 C Adder 2.0 MW 1.7 MW
203963 AG1-253 C Adder 0.46 MW 0.4 MW
237050 AF1-155 C Adder 1.6 MW 1.36 MW
294573 P-028 E Adder 15.4 MW 13.09 MW
941191 AE2-113 C 50/50 14.27 MW 14.27 MW
941192 AE2-113 E 50/50 13.4 MW 13.4 MW
944301 AF1-098 C Adder 8.16 MW 6.93 MW
944302 AF1-098 E Adder 5.44 MW 4.62 MW
944411 AF1-106 C 50/50 4.49 MW 4.49 MW
944881 AF1-153 C Adder 1.59 MW 1.35 MW
944882 AF1-153 E Adder 1.06 MW 0.9 MW
946071 AF1-272 C Adder -5.75 MW -4.89 MW
966771 AG1-548 C Adder 7.23 MW 6.14 MW
966772 AG1-548 E Adder 16.87 MW 14.34 MW
961581 Q1080_CY23 External Queue 60.49 MW 60.49 MW
CBM North LTFEXP_CBM-N->PJM CBM 11.13 MW 11.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.99 MW 10.99 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.26 MW 2.26 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.66 MW 0.66 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.25 MW 0.25 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.33 MW 0.33 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.45 MW 0.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.45 MW 3.45 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.14 MW 0.14 MW

Details for 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer l/o PN_P2-3_PN-230-0183-210_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer
200769 to 999310 ckt S
Contingency Name:
PN_P2-3_PN-230-0183-210_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0183-210_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 106.56 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 881.23 MVA
MW Contribution: 12.33 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer
200769 to 999310 ckt S
Contingency Name:
PN_P2-3_PN-230-0183-210_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0183-210_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200769 TO BUS 202640 CKT N /*26HOMER CT   230.0 - 26HOMER CY   345.0 - 26HOMERCITYN  23.0
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200807 TO BUS 200808 CKT 1          /*26PIERC230   230.0 - 26PIERC138   138.0
 DISCONNECT BRANCH FROM BUS 200808 TO BUS 200809 CKT 1          /*26PIERC138   138.0 - 26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 108.01 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 893.28 MVA
MW Contribution: 12.33 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 2.08 MW 1.77 MW
961972 AG1-040 E Adder 1.39 MW 1.18 MW
962511 AG1-100 C Adder 1.99 MW 1.7 MW
962512 AG1-100 E Adder 1.33 MW 1.13 MW
962912 AG1-140 E Adder 0.14 MW 0.12 MW
963441 AG1-193 C Adder 1.08 MW 0.92 MW
963442 AG1-193 E Adder 0.72 MW 0.61 MW
963481 AG1-197 C Adder 1.57 MW 1.34 MW
963482 AG1-197 E Adder 1.05 MW 0.89 MW
963491 AG1-198 C Adder 1.15 MW 0.98 MW
963492 AG1-198 E Adder 0.77 MW 0.65 MW
963992 AG1-253 E Adder 0.22 MW 0.19 MW
942491 AE2-262 C Adder 4.14 MW 3.52 MW
942492 AE2-262 E Adder 2.78 MW 2.37 MW
942501 AE2-263 C Adder 3.89 MW 3.31 MW
942502 AE2-263 E Adder 2.6 MW 2.21 MW
942811 AE2-299 C Adder 5.51 MW 4.68 MW
942812 AE2-299 E Adder 22.03 MW 18.73 MW
942961 AE2-316 C Adder 6.66 MW 5.66 MW
942962 AE2-316 E Adder 7.88 MW 6.7 MW
943151 AE2-344 C Adder 11.58 MW 9.85 MW
943152 AE2-344 E Adder 7.72 MW 6.56 MW
943352 AF1-006 E Adder 1.14 MW 0.97 MW
944261 AF1-094 C Adder 1.92 MW 1.64 MW
944262 AF1-094 E Adder 1.28 MW 1.09 MW
944902 AF1-155 E Adder 1.06 MW 0.91 MW
945021 AF1-167 C Adder 1.21 MW 1.02 MW
945022 AF1-167 E Adder 0.8 MW 0.68 MW
958742 AF2-165 E Adder 1.19 MW 1.01 MW
958751 AF2-166 C Adder 1.7 MW 1.45 MW
958752 AF2-166 E Adder 1.14 MW 0.96 MW
959441 AF2-235 C Adder 0.94 MW 0.8 MW
959442 AF2-235 E Adder 0.63 MW 0.53 MW
959471 AF2-238 C 50/50 2.6 MW 2.6 MW
959472 AF2-238 E 50/50 1.73 MW 1.73 MW
960031 AF2-294 C Adder 2.09 MW 1.77 MW
960032 AF2-294 E Adder 1.39 MW 1.18 MW
200642 26SENECA#1 50/50 7.93 MW 7.93 MW
200643 26SENECA#2 50/50 7.42 MW 7.42 MW
200828 26HNSMLK 1 50/50 2.22 MW 2.22 MW
200829 26HNSMLK 2 50/50 2.22 MW 2.22 MW
200830 26HNSMLK 3 50/50 2.22 MW 2.22 MW
200831 26HNSMLK 4 50/50 2.22 MW 2.22 MW
200832 26HNSMLK 5 50/50 2.22 MW 2.22 MW
200838 26HOMER C2 50/50 323.63 MW 323.63 MW
200839 26HOMER C3 50/50 342.61 MW 342.61 MW
200887 26ARMNA MT 50/50 0.59 MW 0.59 MW
200894 26K02 Adder 7.45 MW 6.34 MW
203261 26BLOSSBCT 50/50 0.81 MW 0.81 MW
203349 26Z1-069 C 50/50 0.78 MW 0.78 MW
203350 26MILZ1-092 50/50 0.77 MW 0.77 MW
203999 P-047 E 50/50 20.3 MW 20.3 MW
916202 Z1-069 E 50/50 20.35 MW 20.35 MW
940861 AE2-074 C 50/50 4.3 MW 4.3 MW
940862 AE2-074 E 50/50 5.67 MW 5.67 MW
941322 AE2-126 E Adder 0.94 MW 0.8 MW
941421 AE2-139 C Adder 8.78 MW 7.46 MW
941422 AE2-139 E Adder 5.85 MW 4.97 MW
946222 AF1-287 E Adder 1.33 MW 1.13 MW
946381 AF1-302 C Adder 2.91 MW 2.47 MW
946382 AF1-302 E Adder 3.88 MW 3.3 MW
946772 AF1-217 E Adder 1.33 MW 1.13 MW
957161 AF2-010 C Adder 7.37 MW 6.26 MW
957162 AF2-010 E Adder 4.97 MW 4.22 MW
958362 AF2-130 E Adder 1.14 MW 0.96 MW
959301 AF2-221 C Adder -0.98 MW -0.83 MW
203940 AF1-140 C Adder -1.26 MW -1.07 MW
203948 AG1-140 C Adder 0.31 MW 0.26 MW
203950 AF1-217 C Adder 2.0 MW 1.7 MW
203955 AF1-039 C O1 Adder -0.84 MW -0.72 MW
203962 AF1-287 C Adder 2.0 MW 1.7 MW
203963 AG1-253 C Adder 0.46 MW 0.4 MW
237050 AF1-155 C Adder 1.6 MW 1.36 MW
294573 P-028 E Adder 15.4 MW 13.09 MW
941191 AE2-113 C 50/50 14.27 MW 14.27 MW
941192 AE2-113 E 50/50 13.4 MW 13.4 MW
944301 AF1-098 C Adder 8.16 MW 6.93 MW
944302 AF1-098 E Adder 5.44 MW 4.62 MW
944411 AF1-106 C 50/50 4.49 MW 4.49 MW
944881 AF1-153 C Adder 1.59 MW 1.35 MW
944882 AF1-153 E Adder 1.06 MW 0.9 MW
946071 AF1-272 C Adder -5.75 MW -4.89 MW
966771 AG1-548 C Adder 7.23 MW 6.14 MW
966772 AG1-548 E Adder 16.87 MW 14.34 MW
961581 Q1080_CY23 External Queue 60.49 MW 60.49 MW
CBM North LTFEXP_CBM-N->PJM CBM 11.13 MW 11.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.99 MW 10.99 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.26 MW 2.26 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.66 MW 0.66 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.25 MW 0.25 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.33 MW 0.33 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.45 MW 0.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.45 MW 3.45 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.14 MW 0.14 MW

Details for 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line l/o PN_P2-3_PN-230-0347-2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line
200795 to 200810 ckt 1
Contingency Name:
PN_P2-3_PN-230-0347-2_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-2_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200741 CKT 9   /*26SEWARD 2   230.0 - 26SEWARD     115.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 103.7 %
Rating: 980.0 MVA
Rating Type: B
MVA to Mitigate: 1016.27 MVA
MW Contribution: 11.82 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line
200795 to 200810 ckt 1
Contingency Name:
PN_P2-3_PN-230-0347-2_SRT-A
CONTINGENCY 'PN_P2-3_PN-230-0347-2_SRT-A'
 OPEN BRANCH FROM BUS 200793 TO BUS 200741 CKT 9   /*26SEWARD 2   230.0 - 26SEWARD     115.0
 OPEN BRANCH FROM BUS 200793 TO BUS 200912 CKT 1   /*26SEWARD 2   230.0 - 26CONEMAGH   230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 104.28 %
Rating: 980.0 MVA
Rating Type: B
MVA to Mitigate: 1021.91 MVA
MW Contribution: 11.82 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 1.81 MW 1.54 MW
961972 AG1-040 E Adder 1.21 MW 1.03 MW
961981 AG1-041 C 50/50 2.37 MW 2.37 MW
961982 AG1-041 E 50/50 1.58 MW 1.58 MW
962511 AG1-100 C Adder 1.73 MW 1.47 MW
962512 AG1-100 E Adder 1.15 MW 0.98 MW
962912 AG1-140 E Adder 0.12 MW 0.1 MW
963441 AG1-193 C Adder 1.05 MW 0.9 MW
963442 AG1-193 E Adder 0.7 MW 0.6 MW
963481 AG1-197 C Adder 1.37 MW 1.17 MW
963482 AG1-197 E Adder 0.92 MW 0.78 MW
963491 AG1-198 C Adder 1.1 MW 0.93 MW
963492 AG1-198 E Adder 0.73 MW 0.62 MW
963992 AG1-253 E Adder 0.19 MW 0.16 MW
964201 AG1-281 C Adder 3.62 MW 3.08 MW
964202 AG1-281 E Adder 2.41 MW 2.05 MW
964391 AG1-301 C Adder 2.44 MW 2.07 MW
964392 AG1-301 E Adder 1.63 MW 1.38 MW
290086 Q-036 E Adder 27.34 MW 23.24 MW
296332 R-032 E 50/50 21.51 MW 21.51 MW
942351 AE2-248 C Adder 1.41 MW 1.2 MW
942352 AE2-248 E Adder 0.94 MW 0.8 MW
942491 AE2-262 C Adder 8.02 MW 6.81 MW
942492 AE2-262 E Adder 5.39 MW 4.58 MW
942501 AE2-263 C Adder 7.54 MW 6.41 MW
942502 AE2-263 E Adder 5.03 MW 4.28 MW
942811 AE2-299 C Adder 4.71 MW 4.01 MW
942812 AE2-299 E Adder 18.85 MW 16.02 MW
942961 AE2-316 C Adder 7.43 MW 6.32 MW
942962 AE2-316 E Adder 8.8 MW 7.48 MW
943151 AE2-344 C Adder 10.07 MW 8.56 MW
943152 AE2-344 E Adder 6.71 MW 5.71 MW
943352 AF1-006 E Adder 0.98 MW 0.83 MW
943712 AF1-039 E O1 Adder 1.2 MW 1.02 MW
944261 AF1-094 C Adder 1.83 MW 1.56 MW
944262 AF1-094 E Adder 1.22 MW 1.04 MW
944691 AF1-134 C Adder 2.93 MW 2.49 MW
944692 AF1-134 E Adder 1.96 MW 1.66 MW
944752 AF1-140 E 50/50 2.13 MW 2.13 MW
944781 AF1-143 C Adder 15.7 MW 13.35 MW
944782 AF1-143 E Adder 8.37 MW 7.12 MW
944902 AF1-155 E Adder 1.43 MW 1.22 MW
945021 AF1-167 C Adder 1.35 MW 1.15 MW
945022 AF1-167 E Adder 0.9 MW 0.77 MW
958742 AF2-165 E Adder 1.36 MW 1.16 MW
958751 AF2-166 C Adder 2.24 MW 1.9 MW
958752 AF2-166 E Adder 1.49 MW 1.27 MW
959441 AF2-235 C Adder 1.02 MW 0.87 MW
959442 AF2-235 E Adder 0.68 MW 0.58 MW
959471 AF2-238 C Adder 2.16 MW 1.83 MW
959472 AF2-238 E Adder 1.44 MW 1.22 MW
960031 AF2-294 C Adder 1.68 MW 1.43 MW
960032 AF2-294 E Adder 1.12 MW 0.95 MW
960051 AF2-296 C Adder 2.93 MW 2.49 MW
960052 AF2-296 E Adder 1.96 MW 1.66 MW
200503 26C.SLOPE 50/50 2.79 MW 2.79 MW
200636 26IUP CO-G 50/50 0.79 MW 0.79 MW
200794 26CONEMAGH 50/50 0.63 MW 0.63 MW
200809 26SITHE 50/50 2.6 MW 2.6 MW
200835 26ARN_Z1-066 Adder 2.09 MW 1.78 MW
200837 26HOMER C1 50/50 273.81 MW 273.81 MW
200838 26HOMER C2 50/50 229.66 MW 229.66 MW
200839 26HOMER C3 50/50 243.13 MW 243.13 MW
200846 26FORWARD 50/50 0.18 MW 0.18 MW
200852 26WARR RDG Adder 0.51 MW 0.43 MW
200864 K-013 E 50/50 9.12 MW 9.12 MW
200883 Q-053 E Adder 9.65 MW 8.2 MW
200888 26HIGHLAND 50/50 0.46 MW 0.46 MW
200889 26STNY CRK 50/50 0.45 MW 0.45 MW
200894 26K02 Adder 8.2 MW 6.97 MW
200925 26R32 50/50 0.72 MW 0.72 MW
202158 26CON.GEN1 50/50 0.13 MW 0.13 MW
203999 P-047 E Adder 16.35 MW 13.9 MW
236828 01GRAYMONT Adder 0.59 MW 0.5 MW
292350 K-023 Adder 6.71 MW 5.7 MW
292542 L-013 1 Adder 8.37 MW 7.12 MW
293301 N-039 E Adder 17.02 MW 14.46 MW
293393 V3-030E Adder 7.84 MW 6.67 MW
293603 O-018 E 50/50 18.78 MW 18.78 MW
293902 O-048 E Adder 7.54 MW 6.41 MW
294515 O38_P22 Adder 16.19 MW 13.76 MW
294903 P-060 E 50/50 14.1 MW 14.1 MW
916202 Z1-069 E Adder 16.5 MW 14.02 MW
940201 AE2-001 C Adder 1.78 MW 1.51 MW
940202 AE2-001 E Adder 1.19 MW 1.01 MW
940861 AE2-074 C Adder 3.54 MW 3.01 MW
940862 AE2-074 E Adder 4.66 MW 3.96 MW
941232 AE2-117 E Adder 1.66 MW 1.41 MW
941241 AE2-118 C Adder 2.66 MW 2.26 MW
941242 AE2-118 E Adder 1.77 MW 1.51 MW
941322 AE2-126 E Adder 1.56 MW 1.33 MW
941332 AE2-129 E Adder 1.78 MW 1.51 MW
941352 AE2-131 E Adder 1.78 MW 1.51 MW
941421 AE2-139 C Adder 8.17 MW 6.95 MW
941422 AE2-139 E Adder 5.45 MW 4.63 MW
946222 AF1-287 E Adder 1.16 MW 0.98 MW
946381 AF1-302 C Adder 3.25 MW 2.76 MW
946382 AF1-302 E Adder 4.33 MW 3.68 MW
946772 AF1-217 E Adder 1.16 MW 0.98 MW
957161 AF2-010 C Adder 7.06 MW 6.0 MW
957162 AF2-010 E Adder 4.76 MW 4.04 MW
957451 AF2-039 C Adder 1.58 MW 1.34 MW
957452 AF2-039 E Adder 1.06 MW 0.9 MW
957941 AF2-088 C Adder 0.76 MW 0.65 MW
957942 AF2-088 E Adder 0.51 MW 0.43 MW
957981 AF2-092 C 50/50 2.38 MW 2.38 MW
957982 AF2-092 E 50/50 1.58 MW 1.58 MW
958362 AF2-130 E Adder 1.49 MW 1.27 MW
200833 26SEWRDB34 50/50 34.62 MW 34.62 MW
959301 AF2-221 C 50/50 2.22 MW 2.22 MW
959302 AF2-221 E 50/50 3.07 MW 3.07 MW
913142 Y1-033 E OP1 Adder 6.66 MW 5.66 MW
957012 AF2-002 E 50/50 1.4 MW 1.4 MW
203940 AF1-140 C 50/50 3.2 MW 3.2 MW
203946 AE2-131 C Adder 2.67 MW 2.27 MW
203948 AG1-140 C Adder 0.26 MW 0.23 MW
203950 AF1-217 C Adder 1.74 MW 1.48 MW
203955 AF1-039 C O1 Adder 1.8 MW 1.53 MW
203962 AF1-287 C Adder 1.74 MW 1.48 MW
203963 AG1-253 C Adder 0.4 MW 0.34 MW
237050 AF1-155 C Adder 2.14 MW 1.82 MW
293432 R-040 E Adder 0.47 MW 0.4 MW
916004 26SW_E13_K22 Adder 2.52 MW 2.14 MW
957001 AF2-001 C 50/50 4.2 MW 4.2 MW
957002 AF2-001 E 50/50 2.8 MW 2.8 MW
957011 AF2-002 C 50/50 2.1 MW 2.1 MW
957561 AF2-050 C Adder 9.07 MW 7.71 MW
957562 AF2-050 E Adder 6.04 MW 5.14 MW
942126 AE2-224 E Adder 12.09 MW 10.28 MW
941191 AE2-113 C Adder 13.65 MW 11.6 MW
941192 AE2-113 E Adder 12.81 MW 10.89 MW
944182 AF1-086 E Adder 25.15 MW 21.38 MW
944301 AF1-098 C Adder 7.21 MW 6.13 MW
944302 AF1-098 E Adder 4.8 MW 4.08 MW
944411 AF1-106 C Adder 3.63 MW 3.09 MW
944881 AF1-153 C Adder 2.14 MW 1.82 MW
944882 AF1-153 E Adder 1.43 MW 1.22 MW
945751 AF1-240 C Adder 2.7 MW 2.3 MW
945752 AF1-240 E Adder 1.17 MW 0.99 MW
946071 AF1-272 C 50/50 25.8 MW 25.8 MW
946072 AF1-272 E 50/50 17.2 MW 17.2 MW
946571 AF1-321 C 50/50 4.2 MW 4.2 MW
946572 AF1-321 E 50/50 2.8 MW 2.8 MW
962411 AG1-090 C Adder 6.67 MW 5.67 MW
962412 AG1-090 E Adder 14.44 MW 12.28 MW
965121 AG1-377 C Adder 1.33 MW 1.13 MW
965122 AG1-377 E Adder 3.11 MW 2.64 MW
965131 AG1-378 C Adder 1.33 MW 1.13 MW
965132 AG1-378 E Adder 3.11 MW 2.64 MW
966771 AG1-548 C Adder 6.81 MW 5.79 MW
966772 AG1-548 E Adder 15.89 MW 13.51 MW
203915 26BF_Z2-108 Adder 5.54 MW 4.71 MW
235003 AC1-025 E Adder 0.26 MW 0.22 MW
CBM North LTFEXP_CBM-N->PJM CBM 8.78 MW 8.78 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.75 MW 2.75 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.52 MW 0.52 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.23 MW 0.23 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.21 MW 0.21 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.11 MW 0.11 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.04 MW 0.04 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.04 MW 0.04 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.02 MW 0.02 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.63 MW 2.63 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.3 MW 0.3 MW

Details for 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line l/o PN_P2-2_PN-230-001T_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT _-26HOMER CT 230.0 kV Ckt S line
999310 to 200767 ckt S
Contingency Name:
PN_P2-2_PN-230-001T_SRT-A
CONTINGENCY 'PN_P2-2_PN-230-001T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 106.62 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 881.73 MVA
MW Contribution: 12.33 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT _-26HOMER CT 230.0 kV Ckt S line
999310 to 200767 ckt S
Contingency Name:
PN_P2-2_PN-230-001T_SRT-A
CONTINGENCY 'PN_P2-2_PN-230-001T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 108.08 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 893.84 MVA
MW Contribution: 12.33 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 2.08 MW 1.77 MW
961972 AG1-040 E Adder 1.39 MW 1.18 MW
962511 AG1-100 C Adder 1.99 MW 1.7 MW
962512 AG1-100 E Adder 1.33 MW 1.13 MW
962912 AG1-140 E Adder 0.14 MW 0.12 MW
963441 AG1-193 C Adder 1.08 MW 0.92 MW
963442 AG1-193 E Adder 0.72 MW 0.61 MW
963481 AG1-197 C Adder 1.57 MW 1.34 MW
963482 AG1-197 E Adder 1.05 MW 0.89 MW
963491 AG1-198 C Adder 1.15 MW 0.98 MW
963492 AG1-198 E Adder 0.77 MW 0.65 MW
963992 AG1-253 E Adder 0.22 MW 0.19 MW
942491 AE2-262 C Adder 4.14 MW 3.52 MW
942492 AE2-262 E Adder 2.78 MW 2.37 MW
942501 AE2-263 C Adder 3.89 MW 3.31 MW
942502 AE2-263 E Adder 2.6 MW 2.21 MW
942811 AE2-299 C Adder 5.51 MW 4.68 MW
942812 AE2-299 E Adder 22.03 MW 18.73 MW
942961 AE2-316 C Adder 6.66 MW 5.66 MW
942962 AE2-316 E Adder 7.88 MW 6.7 MW
943151 AE2-344 C Adder 11.58 MW 9.85 MW
943152 AE2-344 E Adder 7.72 MW 6.56 MW
943352 AF1-006 E Adder 1.14 MW 0.97 MW
944261 AF1-094 C Adder 1.92 MW 1.64 MW
944262 AF1-094 E Adder 1.28 MW 1.09 MW
944902 AF1-155 E Adder 1.06 MW 0.91 MW
945021 AF1-167 C Adder 1.21 MW 1.02 MW
945022 AF1-167 E Adder 0.8 MW 0.68 MW
958742 AF2-165 E Adder 1.19 MW 1.01 MW
958751 AF2-166 C Adder 1.7 MW 1.45 MW
958752 AF2-166 E Adder 1.14 MW 0.96 MW
959441 AF2-235 C Adder 0.94 MW 0.8 MW
959442 AF2-235 E Adder 0.63 MW 0.53 MW
959471 AF2-238 C 50/50 2.6 MW 2.6 MW
959472 AF2-238 E 50/50 1.73 MW 1.73 MW
960031 AF2-294 C Adder 2.09 MW 1.77 MW
960032 AF2-294 E Adder 1.39 MW 1.18 MW
200642 26SENECA#1 50/50 7.93 MW 7.93 MW
200643 26SENECA#2 50/50 7.42 MW 7.42 MW
200828 26HNSMLK 1 50/50 2.22 MW 2.22 MW
200829 26HNSMLK 2 50/50 2.22 MW 2.22 MW
200830 26HNSMLK 3 50/50 2.22 MW 2.22 MW
200831 26HNSMLK 4 50/50 2.22 MW 2.22 MW
200832 26HNSMLK 5 50/50 2.22 MW 2.22 MW
200838 26HOMER C2 50/50 323.63 MW 323.63 MW
200839 26HOMER C3 50/50 342.61 MW 342.61 MW
200887 26ARMNA MT 50/50 0.59 MW 0.59 MW
200894 26K02 Adder 7.45 MW 6.34 MW
203261 26BLOSSBCT 50/50 0.81 MW 0.81 MW
203349 26Z1-069 C 50/50 0.78 MW 0.78 MW
203350 26MILZ1-092 50/50 0.77 MW 0.77 MW
203999 P-047 E 50/50 20.3 MW 20.3 MW
916202 Z1-069 E 50/50 20.35 MW 20.35 MW
940861 AE2-074 C 50/50 4.3 MW 4.3 MW
940862 AE2-074 E 50/50 5.67 MW 5.67 MW
941322 AE2-126 E Adder 0.94 MW 0.8 MW
941421 AE2-139 C Adder 8.78 MW 7.46 MW
941422 AE2-139 E Adder 5.85 MW 4.97 MW
946222 AF1-287 E Adder 1.33 MW 1.13 MW
946381 AF1-302 C Adder 2.91 MW 2.47 MW
946382 AF1-302 E Adder 3.88 MW 3.3 MW
946772 AF1-217 E Adder 1.33 MW 1.13 MW
957161 AF2-010 C Adder 7.37 MW 6.26 MW
957162 AF2-010 E Adder 4.97 MW 4.22 MW
958362 AF2-130 E Adder 1.14 MW 0.96 MW
959301 AF2-221 C Adder -0.98 MW -0.83 MW
203940 AF1-140 C Adder -1.26 MW -1.07 MW
203948 AG1-140 C Adder 0.31 MW 0.26 MW
203950 AF1-217 C Adder 2.0 MW 1.7 MW
203955 AF1-039 C O1 Adder -0.84 MW -0.72 MW
203962 AF1-287 C Adder 2.0 MW 1.7 MW
203963 AG1-253 C Adder 0.46 MW 0.4 MW
237050 AF1-155 C Adder 1.6 MW 1.36 MW
294573 P-028 E Adder 15.4 MW 13.09 MW
941191 AE2-113 C 50/50 14.27 MW 14.27 MW
941192 AE2-113 E 50/50 13.4 MW 13.4 MW
944301 AF1-098 C Adder 8.16 MW 6.93 MW
944302 AF1-098 E Adder 5.44 MW 4.62 MW
944411 AF1-106 C 50/50 4.49 MW 4.49 MW
944881 AF1-153 C Adder 1.59 MW 1.35 MW
944882 AF1-153 E Adder 1.06 MW 0.9 MW
946071 AF1-272 C Adder -5.75 MW -4.89 MW
966771 AG1-548 C Adder 7.23 MW 6.14 MW
966772 AG1-548 E Adder 16.87 MW 14.34 MW
961581 Q1080_CY23 External Queue 60.49 MW 60.49 MW
CBM North LTFEXP_CBM-N->PJM CBM 11.13 MW 11.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.99 MW 10.99 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.26 MW 2.26 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.66 MW 0.66 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.25 MW 0.25 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.33 MW 0.33 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.45 MW 0.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.45 MW 3.45 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.14 MW 0.14 MW

Details for 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer l/o PN_P2-2_PN-230-001T_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer
200769 to 999310 ckt S
Contingency Name:
PN_P2-2_PN-230-001T_SRT-A
CONTINGENCY 'PN_P2-2_PN-230-001T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 106.56 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 881.23 MVA
MW Contribution: 12.33 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer
200769 to 999310 ckt S
Contingency Name:
PN_P2-2_PN-230-001T_SRT-A
CONTINGENCY 'PN_P2-2_PN-230-001T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200767 TO BUS 200807 CKT 1          /*26HOMER CT   230.0 - 26PIERC230   230.0
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202640 CKT N /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYN  23.0
 DISCONNECT BUS 200807                                          /*26PIERC230   230.0
 DISCONNECT BUS 200808                                          /*26PIERC138   138.0
 DISCONNECT BUS 200809                                          /*26SITHE      138.0
 REMOVE MACHINE 1 FROM BUS 200809                               /*26SITHE      138.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 108.01 %
Rating: 827.0 MVA
Rating Type: B
MVA to Mitigate: 893.27 MVA
MW Contribution: 12.33 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 2.08 MW 1.77 MW
961972 AG1-040 E Adder 1.39 MW 1.18 MW
962511 AG1-100 C Adder 1.99 MW 1.7 MW
962512 AG1-100 E Adder 1.33 MW 1.13 MW
962912 AG1-140 E Adder 0.14 MW 0.12 MW
963441 AG1-193 C Adder 1.08 MW 0.92 MW
963442 AG1-193 E Adder 0.72 MW 0.61 MW
963481 AG1-197 C Adder 1.57 MW 1.34 MW
963482 AG1-197 E Adder 1.05 MW 0.89 MW
963491 AG1-198 C Adder 1.15 MW 0.98 MW
963492 AG1-198 E Adder 0.77 MW 0.65 MW
963992 AG1-253 E Adder 0.22 MW 0.19 MW
942491 AE2-262 C Adder 4.14 MW 3.52 MW
942492 AE2-262 E Adder 2.78 MW 2.37 MW
942501 AE2-263 C Adder 3.89 MW 3.31 MW
942502 AE2-263 E Adder 2.6 MW 2.21 MW
942811 AE2-299 C Adder 5.51 MW 4.68 MW
942812 AE2-299 E Adder 22.03 MW 18.73 MW
942961 AE2-316 C Adder 6.66 MW 5.66 MW
942962 AE2-316 E Adder 7.88 MW 6.7 MW
943151 AE2-344 C Adder 11.58 MW 9.85 MW
943152 AE2-344 E Adder 7.72 MW 6.56 MW
943352 AF1-006 E Adder 1.14 MW 0.97 MW
944261 AF1-094 C Adder 1.92 MW 1.64 MW
944262 AF1-094 E Adder 1.28 MW 1.09 MW
944902 AF1-155 E Adder 1.06 MW 0.91 MW
945021 AF1-167 C Adder 1.21 MW 1.02 MW
945022 AF1-167 E Adder 0.8 MW 0.68 MW
958742 AF2-165 E Adder 1.19 MW 1.01 MW
958751 AF2-166 C Adder 1.7 MW 1.45 MW
958752 AF2-166 E Adder 1.14 MW 0.96 MW
959441 AF2-235 C Adder 0.94 MW 0.8 MW
959442 AF2-235 E Adder 0.63 MW 0.53 MW
959471 AF2-238 C 50/50 2.6 MW 2.6 MW
959472 AF2-238 E 50/50 1.73 MW 1.73 MW
960031 AF2-294 C Adder 2.09 MW 1.77 MW
960032 AF2-294 E Adder 1.39 MW 1.18 MW
200642 26SENECA#1 50/50 7.93 MW 7.93 MW
200643 26SENECA#2 50/50 7.42 MW 7.42 MW
200828 26HNSMLK 1 50/50 2.22 MW 2.22 MW
200829 26HNSMLK 2 50/50 2.22 MW 2.22 MW
200830 26HNSMLK 3 50/50 2.22 MW 2.22 MW
200831 26HNSMLK 4 50/50 2.22 MW 2.22 MW
200832 26HNSMLK 5 50/50 2.22 MW 2.22 MW
200838 26HOMER C2 50/50 323.63 MW 323.63 MW
200839 26HOMER C3 50/50 342.61 MW 342.61 MW
200887 26ARMNA MT 50/50 0.59 MW 0.59 MW
200894 26K02 Adder 7.45 MW 6.34 MW
203261 26BLOSSBCT 50/50 0.81 MW 0.81 MW
203349 26Z1-069 C 50/50 0.78 MW 0.78 MW
203350 26MILZ1-092 50/50 0.77 MW 0.77 MW
203999 P-047 E 50/50 20.3 MW 20.3 MW
916202 Z1-069 E 50/50 20.35 MW 20.35 MW
940861 AE2-074 C 50/50 4.3 MW 4.3 MW
940862 AE2-074 E 50/50 5.67 MW 5.67 MW
941322 AE2-126 E Adder 0.94 MW 0.8 MW
941421 AE2-139 C Adder 8.78 MW 7.46 MW
941422 AE2-139 E Adder 5.85 MW 4.97 MW
946222 AF1-287 E Adder 1.33 MW 1.13 MW
946381 AF1-302 C Adder 2.91 MW 2.47 MW
946382 AF1-302 E Adder 3.88 MW 3.3 MW
946772 AF1-217 E Adder 1.33 MW 1.13 MW
957161 AF2-010 C Adder 7.37 MW 6.26 MW
957162 AF2-010 E Adder 4.97 MW 4.22 MW
958362 AF2-130 E Adder 1.14 MW 0.96 MW
959301 AF2-221 C Adder -0.98 MW -0.83 MW
203940 AF1-140 C Adder -1.26 MW -1.07 MW
203948 AG1-140 C Adder 0.31 MW 0.26 MW
203950 AF1-217 C Adder 2.0 MW 1.7 MW
203955 AF1-039 C O1 Adder -0.84 MW -0.72 MW
203962 AF1-287 C Adder 2.0 MW 1.7 MW
203963 AG1-253 C Adder 0.46 MW 0.4 MW
237050 AF1-155 C Adder 1.6 MW 1.36 MW
294573 P-028 E Adder 15.4 MW 13.09 MW
941191 AE2-113 C 50/50 14.27 MW 14.27 MW
941192 AE2-113 E 50/50 13.4 MW 13.4 MW
944301 AF1-098 C Adder 8.16 MW 6.93 MW
944302 AF1-098 E Adder 5.44 MW 4.62 MW
944411 AF1-106 C 50/50 4.49 MW 4.49 MW
944881 AF1-153 C Adder 1.59 MW 1.35 MW
944882 AF1-153 E Adder 1.06 MW 0.9 MW
946071 AF1-272 C Adder -5.75 MW -4.89 MW
966771 AG1-548 C Adder 7.23 MW 6.14 MW
966772 AG1-548 E Adder 16.87 MW 14.34 MW
961581 Q1080_CY23 External Queue 60.49 MW 60.49 MW
CBM North LTFEXP_CBM-N->PJM CBM 11.13 MW 11.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.99 MW 10.99 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.26 MW 2.26 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.66 MW 0.66 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.25 MW 0.25 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.33 MW 0.33 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.45 MW 0.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.45 MW 3.45 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.14 MW 0.14 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AP 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line
235282 to 235240 ckt 1
PN_P1-2_PN-345-107T_SRT-A
CONTINGENCY 'PN_P1-2_PN-345-107T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200599 TO BUS 239082 CKT 1   /*26ERIE W     345.0 - 02S8-ATT     345.0
END
OP AC 104.84 % 151.0 B 158.31 6.51
AP 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line
235240 to 235202 ckt 1
PN_P1-2_PN-345-107T_SRT-A
CONTINGENCY 'PN_P1-2_PN-345-107T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200599 TO BUS 239082 CKT 1   /*26ERIE W     345.0 - 02S8-ATT     345.0
END
OP AC 102.68 % 151.0 B 155.04 6.51
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Base Case OP AC 107.08 % 809.0 A 866.28 8.13
PENELEC 26HOMER CT _-26HOMER CT 230.0 kV Ckt N line
999311 to 200767 ckt N
PN_P1-3_DRT-230-004-DRT_SRT-SL
CONTINGENCY 'PN_P1-3_DRT-230-004-DRT_SRT-SL'
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202641 CKT S /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYS  23.0
 SET POSTCONTRATING 1434 BRANCH FROM BUS 200769 TO BUS 961580 CKT 1 /*26HOMER CY   345.0 - Q1080 TAP    345.0
END
OP AC 102.05 % 854.0 B 871.54 12.27
PENELEC 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt N transformer
200769 to 999311 ckt N
PN_P1-3_DRT-230-004-DRT_SRT-SL
CONTINGENCY 'PN_P1-3_DRT-230-004-DRT_SRT-SL'
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202641 CKT S /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYS  23.0
 SET POSTCONTRATING 1434 BRANCH FROM BUS 200769 TO BUS 961580 CKT 1 /*26HOMER CY   345.0 - Q1080 TAP    345.0
END
OP AC 101.36 % 854.0 B 865.64 12.27

Details for 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line l/o PN_P1-2_PN-345-107T_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AP
Facility Description:
01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line
235282 to 235240 ckt 1
Contingency Name:
PN_P1-2_PN-345-107T_SRT-A
CONTINGENCY 'PN_P1-2_PN-345-107T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200599 TO BUS 239082 CKT 1   /*26ERIE W     345.0 - 02S8-ATT     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.84 %
Rating: 151.0 MVA
Rating Type: B
MVA to Mitigate: 158.31 MVA
MW Contribution: 6.51 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AP
Facility Description:
01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line
235282 to 235240 ckt 1
Contingency Name:
PN_P1-2_PN-345-107T_SRT-A
CONTINGENCY 'PN_P1-2_PN-345-107T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200599 TO BUS 239082 CKT 1   /*26ERIE W     345.0 - 02S8-ATT     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.24 %
Rating: 151.0 MVA
Rating Type: B
MVA to Mitigate: 154.38 MVA
MW Contribution: 6.52 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 1.02 MW 0.87 MW
961972 AG1-040 E Adder 0.68 MW 0.58 MW
962511 AG1-100 C Adder 1.0 MW 0.85 MW
962512 AG1-100 E Adder 0.67 MW 0.57 MW
962912 AG1-140 E Adder 0.06 MW 0.05 MW
963441 AG1-193 C Adder 0.56 MW 0.47 MW
963442 AG1-193 E Adder 0.37 MW 0.32 MW
963481 AG1-197 C Adder 0.77 MW 0.66 MW
963482 AG1-197 E Adder 0.51 MW 0.44 MW
963491 AG1-198 C Adder 0.61 MW 0.52 MW
963492 AG1-198 E Adder 0.4 MW 0.34 MW
963992 AG1-253 E Adder 0.1 MW 0.09 MW
942811 AE2-299 C Adder 2.47 MW 2.1 MW
942812 AE2-299 E Adder 9.86 MW 8.38 MW
942961 AE2-316 C 50/50 4.35 MW 4.35 MW
942962 AE2-316 E 50/50 5.15 MW 5.15 MW
943151 AE2-344 C Adder 5.79 MW 4.92 MW
943152 AE2-344 E Adder 3.86 MW 3.28 MW
943352 AF1-006 E Adder 0.58 MW 0.49 MW
944261 AF1-094 C Adder 1.01 MW 0.86 MW
944262 AF1-094 E Adder 0.67 MW 0.57 MW
944902 AF1-155 E Adder 0.58 MW 0.49 MW
945021 AF1-167 C 50/50 1.01 MW 1.01 MW
945022 AF1-167 E 50/50 0.68 MW 0.68 MW
958742 AF2-165 E Adder 0.72 MW 0.61 MW
958751 AF2-166 C Adder 1.18 MW 1.0 MW
958752 AF2-166 E Adder 0.79 MW 0.67 MW
959441 AF2-235 C Adder 0.55 MW 0.47 MW
959442 AF2-235 E Adder 0.37 MW 0.31 MW
200608 26PINEY #1 50/50 0.5 MW 0.5 MW
200838 26HOMER C2 Adder 32.75 MW 27.84 MW
200839 26HOMER C3 Adder 34.67 MW 29.47 MW
235030 01MHNG-T155 50/50 0.19 MW 0.19 MW
235134 01AL&D6 50/50 0.2 MW 0.2 MW
916202 Z1-069 E Adder 3.72 MW 3.16 MW
940861 AE2-074 C Adder 0.82 MW 0.7 MW
940862 AE2-074 E Adder 1.09 MW 0.92 MW
941322 AE2-126 E Adder 0.45 MW 0.38 MW
946222 AF1-287 E Adder 0.66 MW 0.56 MW
946381 AF1-302 C 50/50 1.9 MW 1.9 MW
946382 AF1-302 E 50/50 2.53 MW 2.53 MW
946772 AF1-217 E Adder 0.66 MW 0.56 MW
957161 AF2-010 C Adder 3.89 MW 3.31 MW
957162 AF2-010 E Adder 2.62 MW 2.23 MW
957451 AF2-039 C Adder 0.41 MW 0.35 MW
957452 AF2-039 E Adder 0.27 MW 0.23 MW
957941 AF2-088 C Adder 0.2 MW 0.17 MW
957942 AF2-088 E Adder 0.13 MW 0.11 MW
958362 AF2-130 E Adder 0.79 MW 0.67 MW
203932 AE1-123 50/50 0.3 MW 0.3 MW
203948 AG1-140 C Adder 0.14 MW 0.12 MW
203950 AF1-217 C Adder 0.99 MW 0.84 MW
203962 AF1-287 C Adder 0.99 MW 0.84 MW
203963 AG1-253 C Adder 0.21 MW 0.18 MW
237050 AF1-155 C Adder 0.87 MW 0.74 MW
941191 AE2-113 C Adder 3.68 MW 3.13 MW
941192 AE2-113 E Adder 3.46 MW 2.94 MW
944301 AF1-098 C Adder 3.72 MW 3.16 MW
944302 AF1-098 E Adder 2.48 MW 2.1 MW
944881 AF1-153 C Adder 0.86 MW 0.73 MW
944882 AF1-153 E Adder 0.57 MW 0.49 MW
945751 AF1-240 C Adder 0.83 MW 0.7 MW
945752 AF1-240 E Adder 0.36 MW 0.3 MW
966771 AG1-548 C Adder 3.77 MW 3.2 MW
966772 AG1-548 E Adder 8.79 MW 7.47 MW
CBM North LTFEXP_CBM-N->PJM CBM 2.76 MW 2.76 MW
G-007A LTFEXP_G-007A->PJM CMTX 1.86 MW 1.86 MW
VTF LTFEXP_VFT->PJM CMTX 5.12 MW 5.12 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.95 MW 0.95 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.2 MW 0.2 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.13 MW 0.13 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 1.26 MW 1.26 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.28 MW 0.28 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.87 MW 0.87 MW
MDU PJM->LTFIMP_MDU CLTF 0.05 MW 0.05 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.5 MW 0.5 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.24 MW 0.24 MW

Details for 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line l/o PN_P1-2_PN-345-107T_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AP
Facility Description:
01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line
235240 to 235202 ckt 1
Contingency Name:
PN_P1-2_PN-345-107T_SRT-A
CONTINGENCY 'PN_P1-2_PN-345-107T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200599 TO BUS 239082 CKT 1   /*26ERIE W     345.0 - 02S8-ATT     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.68 %
Rating: 151.0 MVA
Rating Type: B
MVA to Mitigate: 155.04 MVA
MW Contribution: 6.51 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AP
Facility Description:
01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line
235240 to 235202 ckt 1
Contingency Name:
PN_P1-2_PN-345-107T_SRT-A
CONTINGENCY 'PN_P1-2_PN-345-107T_SRT-A'
 DISCONNECT BRANCH FROM BUS 200599 TO BUS 239082 CKT 1   /*26ERIE W     345.0 - 02S8-ATT     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.22 %
Rating: 151.0 MVA
Rating Type: B
MVA to Mitigate: 151.34 MVA
MW Contribution: 6.52 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 1.02 MW 0.87 MW
961972 AG1-040 E Adder 0.68 MW 0.58 MW
962511 AG1-100 C Adder 1.0 MW 0.85 MW
962512 AG1-100 E Adder 0.67 MW 0.57 MW
962912 AG1-140 E Adder 0.06 MW 0.05 MW
963441 AG1-193 C Adder 0.56 MW 0.47 MW
963442 AG1-193 E Adder 0.37 MW 0.32 MW
963481 AG1-197 C Adder 0.77 MW 0.66 MW
963482 AG1-197 E Adder 0.51 MW 0.44 MW
963491 AG1-198 C Adder 0.61 MW 0.52 MW
963492 AG1-198 E Adder 0.4 MW 0.34 MW
963992 AG1-253 E Adder 0.1 MW 0.09 MW
942811 AE2-299 C Adder 2.47 MW 2.1 MW
942812 AE2-299 E Adder 9.86 MW 8.38 MW
942961 AE2-316 C 50/50 4.35 MW 4.35 MW
942962 AE2-316 E 50/50 5.15 MW 5.15 MW
943151 AE2-344 C Adder 5.79 MW 4.92 MW
943152 AE2-344 E Adder 3.86 MW 3.28 MW
943352 AF1-006 E Adder 0.58 MW 0.49 MW
944261 AF1-094 C Adder 1.01 MW 0.86 MW
944262 AF1-094 E Adder 0.67 MW 0.57 MW
944902 AF1-155 E Adder 0.58 MW 0.49 MW
945021 AF1-167 C 50/50 1.01 MW 1.01 MW
945022 AF1-167 E 50/50 0.68 MW 0.68 MW
958742 AF2-165 E Adder 0.72 MW 0.61 MW
958751 AF2-166 C Adder 1.18 MW 1.0 MW
958752 AF2-166 E Adder 0.79 MW 0.67 MW
959441 AF2-235 C Adder 0.55 MW 0.47 MW
959442 AF2-235 E Adder 0.37 MW 0.31 MW
200608 26PINEY #1 50/50 0.5 MW 0.5 MW
200838 26HOMER C2 Adder 32.75 MW 27.84 MW
200839 26HOMER C3 Adder 34.67 MW 29.47 MW
235030 01MHNG-T155 50/50 0.19 MW 0.19 MW
235134 01AL&D6 50/50 0.2 MW 0.2 MW
916202 Z1-069 E Adder 3.72 MW 3.16 MW
940861 AE2-074 C Adder 0.82 MW 0.7 MW
940862 AE2-074 E Adder 1.09 MW 0.92 MW
941322 AE2-126 E Adder 0.45 MW 0.38 MW
946222 AF1-287 E Adder 0.66 MW 0.56 MW
946381 AF1-302 C 50/50 1.9 MW 1.9 MW
946382 AF1-302 E 50/50 2.53 MW 2.53 MW
946772 AF1-217 E Adder 0.66 MW 0.56 MW
957161 AF2-010 C Adder 3.89 MW 3.31 MW
957162 AF2-010 E Adder 2.62 MW 2.23 MW
957451 AF2-039 C Adder 0.41 MW 0.35 MW
957452 AF2-039 E Adder 0.27 MW 0.23 MW
957941 AF2-088 C Adder 0.2 MW 0.17 MW
957942 AF2-088 E Adder 0.13 MW 0.11 MW
958362 AF2-130 E Adder 0.79 MW 0.67 MW
203932 AE1-123 50/50 0.3 MW 0.3 MW
203948 AG1-140 C Adder 0.14 MW 0.12 MW
203950 AF1-217 C Adder 0.99 MW 0.84 MW
203962 AF1-287 C Adder 0.99 MW 0.84 MW
203963 AG1-253 C Adder 0.21 MW 0.18 MW
237050 AF1-155 C Adder 0.87 MW 0.74 MW
941191 AE2-113 C Adder 3.68 MW 3.13 MW
941192 AE2-113 E Adder 3.46 MW 2.94 MW
944301 AF1-098 C Adder 3.72 MW 3.16 MW
944302 AF1-098 E Adder 2.48 MW 2.1 MW
944881 AF1-153 C Adder 0.86 MW 0.73 MW
944882 AF1-153 E Adder 0.57 MW 0.49 MW
945751 AF1-240 C Adder 0.83 MW 0.7 MW
945752 AF1-240 E Adder 0.36 MW 0.3 MW
966771 AG1-548 C Adder 3.77 MW 3.2 MW
966772 AG1-548 E Adder 8.79 MW 7.47 MW
CBM North LTFEXP_CBM-N->PJM CBM 2.76 MW 2.76 MW
G-007A LTFEXP_G-007A->PJM CMTX 1.86 MW 1.86 MW
VTF LTFEXP_VFT->PJM CMTX 5.12 MW 5.12 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.95 MW 0.95 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.2 MW 0.2 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.13 MW 0.13 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 1.26 MW 1.26 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.28 MW 0.28 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.87 MW 0.87 MW
MDU PJM->LTFIMP_MDU CLTF 0.05 MW 0.05 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.5 MW 0.5 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.24 MW 0.24 MW

Details for 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 107.08 %
Rating: 809.0 MVA
Rating Type: A
MVA to Mitigate: 866.28 MVA
MW Contribution: 8.13 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 106.72 %
Rating: 809.0 MVA
Rating Type: A
MVA to Mitigate: 863.33 MVA
MW Contribution: 8.13 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 1.31 MW 1.11 MW
961972 AG1-040 E Adder 0.87 MW 0.74 MW
961981 AG1-041 C 50/50 1.54 MW 1.54 MW
961982 AG1-041 E 50/50 1.02 MW 1.02 MW
962511 AG1-100 C Adder 1.25 MW 1.06 MW
962512 AG1-100 E Adder 0.83 MW 0.71 MW
962912 AG1-140 E Adder 0.09 MW 0.08 MW
963441 AG1-193 C Adder 0.71 MW 0.61 MW
963442 AG1-193 E Adder 0.48 MW 0.4 MW
963481 AG1-197 C Adder 0.99 MW 0.84 MW
963482 AG1-197 E Adder 0.66 MW 0.56 MW
963491 AG1-198 C Adder 0.76 MW 0.65 MW
963492 AG1-198 E Adder 0.51 MW 0.43 MW
963992 AG1-253 E Adder 0.14 MW 0.12 MW
964201 AG1-281 C 50/50 2.31 MW 2.31 MW
964202 AG1-281 E 50/50 1.54 MW 1.54 MW
964391 AG1-301 C Adder 1.6 MW 1.36 MW
964392 AG1-301 E Adder 1.06 MW 0.91 MW
290086 Q-036 E Adder 17.07 MW 14.51 MW
296332 R-032 E 50/50 13.78 MW 13.78 MW
942351 AE2-248 C Adder 0.95 MW 0.81 MW
942352 AE2-248 E Adder 0.63 MW 0.54 MW
942491 AE2-262 C Adder 5.39 MW 4.58 MW
942492 AE2-262 E Adder 3.62 MW 3.08 MW
942501 AE2-263 C Adder 5.07 MW 4.31 MW
942502 AE2-263 E Adder 3.39 MW 2.88 MW
942811 AE2-299 C Adder 3.48 MW 2.96 MW
942812 AE2-299 E Adder 13.91 MW 11.82 MW
942961 AE2-316 C Adder 5.14 MW 4.37 MW
942962 AE2-316 E Adder 6.09 MW 5.18 MW
943151 AE2-344 C Adder 7.27 MW 6.18 MW
943152 AE2-344 E Adder 4.85 MW 4.12 MW
943352 AF1-006 E Adder 0.71 MW 0.61 MW
943712 AF1-039 E O1 Adder 0.79 MW 0.67 MW
944261 AF1-094 C Adder 1.26 MW 1.07 MW
944262 AF1-094 E Adder 0.84 MW 0.72 MW
944691 AF1-134 C Adder 1.29 MW 1.1 MW
944692 AF1-134 E Adder 0.86 MW 0.73 MW
944752 AF1-140 E 50/50 1.36 MW 1.36 MW
944781 AF1-143 C 50/50 10.4 MW 10.4 MW
944782 AF1-143 E 50/50 5.54 MW 5.54 MW
944902 AF1-155 E Adder 0.97 MW 0.82 MW
945021 AF1-167 C Adder 0.85 MW 0.72 MW
945022 AF1-167 E Adder 0.56 MW 0.48 MW
958742 AF2-165 E Adder 0.85 MW 0.72 MW
958751 AF2-166 C Adder 1.31 MW 1.11 MW
958752 AF2-166 E Adder 0.87 MW 0.74 MW
959441 AF2-235 C Adder 0.66 MW 0.56 MW
959442 AF2-235 E Adder 0.44 MW 0.37 MW
959471 AF2-238 C Adder 1.72 MW 1.47 MW
959472 AF2-238 E Adder 1.15 MW 0.98 MW
960031 AF2-294 C Adder 1.36 MW 1.16 MW
960032 AF2-294 E Adder 0.91 MW 0.77 MW
960051 AF2-296 C Adder 1.29 MW 1.1 MW
960052 AF2-296 E Adder 0.86 MW 0.73 MW
200503 26C.SLOPE 50/50 1.72 MW 1.72 MW
200794 26CONEMAGH 50/50 0.35 MW 0.35 MW
200809 26SITHE 50/50 2.18 MW 2.18 MW
200834 26SW_E13_K22 50/50 0.02 MW 0.02 MW
200835 26ARN_Z1-066 50/50 1.39 MW 1.39 MW
200837 26HOMER C1 50/50 229.56 MW 229.56 MW
200838 26HOMER C2 50/50 189.74 MW 189.74 MW
200839 26HOMER C3 50/50 200.86 MW 200.86 MW
200846 26FORWARD 50/50 0.12 MW 0.12 MW
200852 26WARR RDG Adder 0.33 MW 0.28 MW
200864 K-013 E 50/50 6.14 MW 6.14 MW
200883 Q-053 E 50/50 6.04 MW 6.04 MW
200887 26ARMNA MT 50/50 0.38 MW 0.38 MW
200888 26HIGHLAND 50/50 0.29 MW 0.29 MW
200889 26STNY CRK 50/50 0.29 MW 0.29 MW
200890 26BF_G21_K23 50/50 0.14 MW 0.14 MW
200891 26CSLMN_L13 50/50 0.17 MW 0.17 MW
200892 26LOOKOUT 50/50 0.18 MW 0.18 MW
200894 26K02 Adder 6.14 MW 5.22 MW
200925 26R32 50/50 0.46 MW 0.46 MW
202225 26SCI_S29B 50/50 0.06 MW 0.06 MW
203349 26Z1-069 C 50/50 0.5 MW 0.5 MW
203999 P-047 E 50/50 13.16 MW 13.16 MW
236828 01GRAYMONT Adder 0.4 MW 0.34 MW
292350 K-023 50/50 4.44 MW 4.44 MW
292542 L-013 1 50/50 5.54 MW 5.54 MW
293301 N-039 E 50/50 11.33 MW 11.33 MW
293393 V3-030E Adder 3.6 MW 3.06 MW
293603 O-018 E 50/50 12.03 MW 12.03 MW
293902 O-048 E 50/50 4.99 MW 4.99 MW
294515 O38_P22 50/50 10.79 MW 10.79 MW
294903 P-060 E 50/50 9.3 MW 9.3 MW
916202 Z1-069 E 50/50 13.09 MW 13.09 MW
940201 AE2-001 C Adder 1.2 MW 1.02 MW
940202 AE2-001 E Adder 0.8 MW 0.68 MW
940861 AE2-074 C 50/50 2.78 MW 2.78 MW
940862 AE2-074 E 50/50 3.66 MW 3.66 MW
941232 AE2-117 E Adder 1.08 MW 0.92 MW
941241 AE2-118 C Adder 1.73 MW 1.47 MW
941242 AE2-118 E Adder 1.15 MW 0.98 MW
941322 AE2-126 E Adder 1.03 MW 0.88 MW
941332 AE2-129 E Adder 1.1 MW 0.94 MW
941352 AE2-131 E Adder 1.1 MW 0.94 MW
941421 AE2-139 C Adder 6.44 MW 5.48 MW
941422 AE2-139 E Adder 4.29 MW 3.65 MW
946222 AF1-287 E Adder 0.84 MW 0.71 MW
946381 AF1-302 C Adder 2.25 MW 1.91 MW
946382 AF1-302 E Adder 2.99 MW 2.54 MW
946772 AF1-217 E Adder 0.84 MW 0.71 MW
957161 AF2-010 C Adder 4.86 MW 4.13 MW
957162 AF2-010 E Adder 3.27 MW 2.78 MW
957451 AF2-039 C Adder 0.97 MW 0.82 MW
957452 AF2-039 E Adder 0.65 MW 0.55 MW
957941 AF2-088 C Adder 0.47 MW 0.4 MW
957942 AF2-088 E Adder 0.31 MW 0.27 MW
957981 AF2-092 C 50/50 1.54 MW 1.54 MW
957982 AF2-092 E 50/50 1.03 MW 1.03 MW
958362 AF2-130 E Adder 0.87 MW 0.74 MW
200833 26SEWRDB34 50/50 21.1 MW 21.1 MW
200886 26ARWF_N39 50/50 0.32 MW 0.32 MW
200915 26CHSTN_FL 50/50 0.2 MW 0.2 MW
203034 26NA_O38_P22 50/50 0.26 MW 0.26 MW
959301 AF2-221 C 50/50 1.46 MW 1.46 MW
959302 AF2-221 E 50/50 2.01 MW 2.01 MW
913142 Y1-033 E OP1 Adder 4.36 MW 3.71 MW
957012 AF2-002 E 50/50 0.94 MW 0.94 MW
203940 AF1-140 C 50/50 2.04 MW 2.04 MW
203946 AE2-131 C Adder 1.65 MW 1.41 MW
203948 AG1-140 C Adder 0.2 MW 0.17 MW
203950 AF1-217 C Adder 1.25 MW 1.07 MW
203955 AF1-039 C O1 Adder 1.18 MW 1.0 MW
203962 AF1-287 C Adder 1.25 MW 1.07 MW
203963 AG1-253 C Adder 0.29 MW 0.25 MW
237050 AF1-155 C Adder 1.45 MW 1.24 MW
293432 R-040 E 50/50 0.31 MW 0.31 MW
294573 P-028 E Adder 10.95 MW 9.3 MW
916004 26SW_E13_K22 50/50 1.68 MW 1.68 MW
957001 AF2-001 C 50/50 2.82 MW 2.82 MW
957002 AF2-001 E 50/50 1.88 MW 1.88 MW
957011 AF2-002 C 50/50 1.41 MW 1.41 MW
957561 AF2-050 C 50/50 6.05 MW 6.05 MW
957562 AF2-050 E 50/50 4.04 MW 4.04 MW
203961 AE2-224 C 50/50 1.98 MW 1.98 MW
942126 AE2-224 E 50/50 8.07 MW 8.07 MW
941191 AE2-113 C 50/50 10.22 MW 10.22 MW
941192 AE2-113 E 50/50 9.59 MW 9.59 MW
944182 AF1-086 E Adder 8.83 MW 7.51 MW
944301 AF1-098 C Adder 5.27 MW 4.48 MW
944302 AF1-098 E Adder 3.51 MW 2.98 MW
944411 AF1-106 C Adder 2.93 MW 2.49 MW
944881 AF1-153 C Adder 1.45 MW 1.24 MW
944882 AF1-153 E Adder 0.97 MW 0.82 MW
945751 AF1-240 C Adder 1.07 MW 0.91 MW
945752 AF1-240 E Adder 0.46 MW 0.39 MW
946571 AF1-321 C 50/50 2.82 MW 2.82 MW
946572 AF1-321 E 50/50 1.88 MW 1.88 MW
962411 AG1-090 C Adder 4.14 MW 3.52 MW
962412 AG1-090 E Adder 8.96 MW 7.62 MW
965121 AG1-377 C Adder 0.83 MW 0.7 MW
965122 AG1-377 E Adder 1.93 MW 1.64 MW
965131 AG1-378 C Adder 0.83 MW 0.7 MW
965132 AG1-378 E Adder 1.93 MW 1.64 MW
966771 AG1-548 C Adder 4.73 MW 4.02 MW
966772 AG1-548 E Adder 11.04 MW 9.38 MW
235003 AC1-025 E Adder 0.17 MW 0.15 MW
203915 26BF_Z2-108 50/50 3.12 MW 3.12 MW
961581 Q1080_CY23 External Queue 32.49 MW 32.49 MW
CBM North LTFEXP_CBM-N->PJM CBM 7.82 MW 7.82 MW
G-007A LTFEXP_G-007A->PJM CMTX 1.14 MW 1.14 MW
VTF LTFEXP_VFT->PJM CMTX 3.39 MW 3.39 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.93 MW 0.93 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.3 MW 0.3 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.18 MW 0.18 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 1.04 MW 1.04 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.23 MW 0.23 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.72 MW 0.72 MW
MDU PJM->LTFIMP_MDU CLTF 0.04 MW 0.04 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.39 MW 0.39 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.4 MW 0.4 MW

Details for 26HOMER CT _-26HOMER CT 230.0 kV Ckt N line l/o PN_P1-3_DRT-230-004-DRT_SRT-SL


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT _-26HOMER CT 230.0 kV Ckt N line
999311 to 200767 ckt N
Contingency Name:
PN_P1-3_DRT-230-004-DRT_SRT-SL
CONTINGENCY 'PN_P1-3_DRT-230-004-DRT_SRT-SL'
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202641 CKT S /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYS  23.0
 SET POSTCONTRATING 1434 BRANCH FROM BUS 200769 TO BUS 961580 CKT 1 /*26HOMER CY   345.0 - Q1080 TAP    345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.05 %
Rating: 854.0 MVA
Rating Type: B
MVA to Mitigate: 871.54 MVA
MW Contribution: 12.27 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CT _-26HOMER CT 230.0 kV Ckt N line
999311 to 200767 ckt N
Contingency Name:
PN_P1-3_DRT-230-004-DRT_SRT-SL
CONTINGENCY 'PN_P1-3_DRT-230-004-DRT_SRT-SL'
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202641 CKT S /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYS  23.0
 SET POSTCONTRATING 1434 BRANCH FROM BUS 200769 TO BUS 961580 CKT 1 /*26HOMER CY   345.0 - Q1080 TAP    345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.42 %
Rating: 854.0 MVA
Rating Type: B
MVA to Mitigate: 883.21 MVA
MW Contribution: 12.27 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 2.07 MW 1.76 MW
961972 AG1-040 E Adder 1.38 MW 1.17 MW
962511 AG1-100 C Adder 1.98 MW 1.69 MW
962512 AG1-100 E Adder 1.32 MW 1.12 MW
962912 AG1-140 E Adder 0.14 MW 0.12 MW
963441 AG1-193 C Adder 1.08 MW 0.92 MW
963442 AG1-193 E Adder 0.72 MW 0.61 MW
963481 AG1-197 C Adder 1.57 MW 1.33 MW
963482 AG1-197 E Adder 1.04 MW 0.89 MW
963491 AG1-198 C Adder 1.15 MW 0.98 MW
963492 AG1-198 E Adder 0.77 MW 0.65 MW
963992 AG1-253 E Adder 0.22 MW 0.19 MW
942491 AE2-262 C Adder 4.12 MW 3.5 MW
942492 AE2-262 E Adder 2.77 MW 2.35 MW
942501 AE2-263 C Adder 3.87 MW 3.29 MW
942502 AE2-263 E Adder 2.59 MW 2.2 MW
942811 AE2-299 C Adder 5.48 MW 4.66 MW
942812 AE2-299 E Adder 21.92 MW 18.63 MW
942961 AE2-316 C Adder 6.62 MW 5.63 MW
942962 AE2-316 E Adder 7.84 MW 6.67 MW
943151 AE2-344 C Adder 11.52 MW 9.79 MW
943152 AE2-344 E Adder 7.68 MW 6.53 MW
943352 AF1-006 E Adder 1.13 MW 0.96 MW
944261 AF1-094 C Adder 1.91 MW 1.63 MW
944262 AF1-094 E Adder 1.28 MW 1.08 MW
944902 AF1-155 E Adder 1.06 MW 0.9 MW
945021 AF1-167 C Adder 1.2 MW 1.02 MW
945022 AF1-167 E Adder 0.8 MW 0.68 MW
958742 AF2-165 E Adder 1.18 MW 1.0 MW
958751 AF2-166 C Adder 1.7 MW 1.44 MW
958752 AF2-166 E Adder 1.13 MW 0.96 MW
959441 AF2-235 C Adder 0.93 MW 0.79 MW
959442 AF2-235 E Adder 0.62 MW 0.53 MW
959471 AF2-238 C 50/50 2.58 MW 2.58 MW
959472 AF2-238 E 50/50 1.72 MW 1.72 MW
960031 AF2-294 C Adder 2.08 MW 1.77 MW
960032 AF2-294 E Adder 1.38 MW 1.18 MW
200642 26SENECA#1 50/50 7.89 MW 7.89 MW
200643 26SENECA#2 50/50 7.38 MW 7.38 MW
200828 26HNSMLK 1 50/50 2.21 MW 2.21 MW
200829 26HNSMLK 2 50/50 2.21 MW 2.21 MW
200830 26HNSMLK 3 50/50 2.21 MW 2.21 MW
200831 26HNSMLK 4 50/50 2.21 MW 2.21 MW
200832 26HNSMLK 5 50/50 2.21 MW 2.21 MW
200838 26HOMER C2 50/50 321.9 MW 321.9 MW
200839 26HOMER C3 50/50 340.77 MW 340.77 MW
200887 26ARMNA MT 50/50 0.59 MW 0.59 MW
200894 26K02 Adder 7.42 MW 6.3 MW
203261 26BLOSSBCT 50/50 0.8 MW 0.8 MW
203349 26Z1-069 C 50/50 0.78 MW 0.78 MW
203350 26MILZ1-092 50/50 0.77 MW 0.77 MW
203999 P-047 E 50/50 20.19 MW 20.19 MW
916202 Z1-069 E 50/50 20.24 MW 20.24 MW
940861 AE2-074 C 50/50 4.28 MW 4.28 MW
940862 AE2-074 E 50/50 5.63 MW 5.63 MW
941322 AE2-126 E Adder 0.94 MW 0.8 MW
941421 AE2-139 C Adder 8.73 MW 7.42 MW
941422 AE2-139 E Adder 5.82 MW 4.95 MW
946222 AF1-287 E Adder 1.32 MW 1.12 MW
946381 AF1-302 C Adder 2.89 MW 2.46 MW
946382 AF1-302 E Adder 3.86 MW 3.28 MW
946772 AF1-217 E Adder 1.32 MW 1.12 MW
957161 AF2-010 C Adder 7.33 MW 6.23 MW
957162 AF2-010 E Adder 4.94 MW 4.2 MW
958362 AF2-130 E Adder 1.13 MW 0.96 MW
959301 AF2-221 C Adder -0.98 MW -0.83 MW
203940 AF1-140 C Adder -1.25 MW -1.06 MW
203948 AG1-140 C Adder 0.31 MW 0.26 MW
203950 AF1-217 C Adder 1.98 MW 1.69 MW
203955 AF1-039 C O1 Adder -0.84 MW -0.71 MW
203962 AF1-287 C Adder 1.98 MW 1.69 MW
203963 AG1-253 C Adder 0.46 MW 0.39 MW
237050 AF1-155 C Adder 1.59 MW 1.35 MW
294573 P-028 E Adder 15.33 MW 13.03 MW
941191 AE2-113 C 50/50 14.2 MW 14.2 MW
941192 AE2-113 E 50/50 13.33 MW 13.33 MW
944301 AF1-098 C Adder 8.12 MW 6.9 MW
944302 AF1-098 E Adder 5.41 MW 4.6 MW
944411 AF1-106 C 50/50 4.46 MW 4.46 MW
944881 AF1-153 C Adder 1.58 MW 1.35 MW
944882 AF1-153 E Adder 1.06 MW 0.9 MW
946071 AF1-272 C Adder -5.72 MW -4.86 MW
966771 AG1-548 C Adder 7.19 MW 6.11 MW
966772 AG1-548 E Adder 16.78 MW 14.26 MW
961581 Q1080_CY23 External Queue 60.16 MW 60.16 MW
CBM North LTFEXP_CBM-N->PJM CBM 11.08 MW 11.08 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.02 MW 11.02 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.29 MW 2.29 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.65 MW 0.65 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.25 MW 0.25 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.33 MW 0.33 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.45 MW 0.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.4 MW 3.4 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.14 MW 0.14 MW

Details for 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt N transformer l/o PN_P1-3_DRT-230-004-DRT_SRT-SL


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt N transformer
200769 to 999311 ckt N
Contingency Name:
PN_P1-3_DRT-230-004-DRT_SRT-SL
CONTINGENCY 'PN_P1-3_DRT-230-004-DRT_SRT-SL'
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202641 CKT S /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYS  23.0
 SET POSTCONTRATING 1434 BRANCH FROM BUS 200769 TO BUS 961580 CKT 1 /*26HOMER CY   345.0 - Q1080 TAP    345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 101.36 %
Rating: 854.0 MVA
Rating Type: B
MVA to Mitigate: 865.64 MVA
MW Contribution: 12.27 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: PENELEC
Facility Description:
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt N transformer
200769 to 999311 ckt N
Contingency Name:
PN_P1-3_DRT-230-004-DRT_SRT-SL
CONTINGENCY 'PN_P1-3_DRT-230-004-DRT_SRT-SL'
 DISCONNECT BRANCH FROM BUS 200769 TO BUS 200767 TO BUS 202641 CKT S /*26HOMER CY   345.0 - 26HOMER CT   230.0 - 26HOMERCITYS  23.0
 SET POSTCONTRATING 1434 BRANCH FROM BUS 200769 TO BUS 961580 CKT 1 /*26HOMER CY   345.0 - Q1080 TAP    345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.73 %
Rating: 854.0 MVA
Rating Type: B
MVA to Mitigate: 877.29 MVA
MW Contribution: 12.27 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961971 AG1-040 C Adder 2.07 MW 1.76 MW
961972 AG1-040 E Adder 1.38 MW 1.17 MW
962511 AG1-100 C Adder 1.98 MW 1.69 MW
962512 AG1-100 E Adder 1.32 MW 1.12 MW
962912 AG1-140 E Adder 0.14 MW 0.12 MW
963441 AG1-193 C Adder 1.08 MW 0.92 MW
963442 AG1-193 E Adder 0.72 MW 0.61 MW
963481 AG1-197 C Adder 1.57 MW 1.33 MW
963482 AG1-197 E Adder 1.04 MW 0.89 MW
963491 AG1-198 C Adder 1.15 MW 0.98 MW
963492 AG1-198 E Adder 0.77 MW 0.65 MW
963992 AG1-253 E Adder 0.22 MW 0.19 MW
942491 AE2-262 C Adder 4.12 MW 3.5 MW
942492 AE2-262 E Adder 2.77 MW 2.35 MW
942501 AE2-263 C Adder 3.87 MW 3.29 MW
942502 AE2-263 E Adder 2.59 MW 2.2 MW
942811 AE2-299 C Adder 5.48 MW 4.66 MW
942812 AE2-299 E Adder 21.92 MW 18.63 MW
942961 AE2-316 C Adder 6.62 MW 5.63 MW
942962 AE2-316 E Adder 7.84 MW 6.67 MW
943151 AE2-344 C Adder 11.52 MW 9.79 MW
943152 AE2-344 E Adder 7.68 MW 6.53 MW
943352 AF1-006 E Adder 1.13 MW 0.96 MW
944261 AF1-094 C Adder 1.91 MW 1.63 MW
944262 AF1-094 E Adder 1.28 MW 1.08 MW
944902 AF1-155 E Adder 1.06 MW 0.9 MW
945021 AF1-167 C Adder 1.2 MW 1.02 MW
945022 AF1-167 E Adder 0.8 MW 0.68 MW
958742 AF2-165 E Adder 1.18 MW 1.0 MW
958751 AF2-166 C Adder 1.7 MW 1.44 MW
958752 AF2-166 E Adder 1.13 MW 0.96 MW
959441 AF2-235 C Adder 0.93 MW 0.79 MW
959442 AF2-235 E Adder 0.62 MW 0.53 MW
959471 AF2-238 C 50/50 2.58 MW 2.58 MW
959472 AF2-238 E 50/50 1.72 MW 1.72 MW
960031 AF2-294 C Adder 2.08 MW 1.77 MW
960032 AF2-294 E Adder 1.38 MW 1.18 MW
200642 26SENECA#1 50/50 7.89 MW 7.89 MW
200643 26SENECA#2 50/50 7.38 MW 7.38 MW
200828 26HNSMLK 1 50/50 2.21 MW 2.21 MW
200829 26HNSMLK 2 50/50 2.21 MW 2.21 MW
200830 26HNSMLK 3 50/50 2.21 MW 2.21 MW
200831 26HNSMLK 4 50/50 2.21 MW 2.21 MW
200832 26HNSMLK 5 50/50 2.21 MW 2.21 MW
200838 26HOMER C2 50/50 321.9 MW 321.9 MW
200839 26HOMER C3 50/50 340.77 MW 340.77 MW
200887 26ARMNA MT 50/50 0.59 MW 0.59 MW
200894 26K02 Adder 7.42 MW 6.3 MW
203261 26BLOSSBCT 50/50 0.8 MW 0.8 MW
203349 26Z1-069 C 50/50 0.78 MW 0.78 MW
203350 26MILZ1-092 50/50 0.77 MW 0.77 MW
203999 P-047 E 50/50 20.19 MW 20.19 MW
916202 Z1-069 E 50/50 20.24 MW 20.24 MW
940861 AE2-074 C 50/50 4.28 MW 4.28 MW
940862 AE2-074 E 50/50 5.63 MW 5.63 MW
941322 AE2-126 E Adder 0.94 MW 0.8 MW
941421 AE2-139 C Adder 8.73 MW 7.42 MW
941422 AE2-139 E Adder 5.82 MW 4.95 MW
946222 AF1-287 E Adder 1.32 MW 1.12 MW
946381 AF1-302 C Adder 2.89 MW 2.46 MW
946382 AF1-302 E Adder 3.86 MW 3.28 MW
946772 AF1-217 E Adder 1.32 MW 1.12 MW
957161 AF2-010 C Adder 7.33 MW 6.23 MW
957162 AF2-010 E Adder 4.94 MW 4.2 MW
958362 AF2-130 E Adder 1.13 MW 0.96 MW
959301 AF2-221 C Adder -0.98 MW -0.83 MW
203940 AF1-140 C Adder -1.25 MW -1.06 MW
203948 AG1-140 C Adder 0.31 MW 0.26 MW
203950 AF1-217 C Adder 1.98 MW 1.69 MW
203955 AF1-039 C O1 Adder -0.84 MW -0.71 MW
203962 AF1-287 C Adder 1.98 MW 1.69 MW
203963 AG1-253 C Adder 0.46 MW 0.39 MW
237050 AF1-155 C Adder 1.59 MW 1.35 MW
294573 P-028 E Adder 15.33 MW 13.03 MW
941191 AE2-113 C 50/50 14.2 MW 14.2 MW
941192 AE2-113 E 50/50 13.33 MW 13.33 MW
944301 AF1-098 C Adder 8.12 MW 6.9 MW
944302 AF1-098 E Adder 5.41 MW 4.6 MW
944411 AF1-106 C 50/50 4.46 MW 4.46 MW
944881 AF1-153 C Adder 1.58 MW 1.35 MW
944882 AF1-153 E Adder 1.06 MW 0.9 MW
946071 AF1-272 C Adder -5.72 MW -4.86 MW
966771 AG1-548 C Adder 7.19 MW 6.11 MW
966772 AG1-548 E Adder 16.78 MW 14.26 MW
961581 Q1080_CY23 External Queue 60.16 MW 60.16 MW
CBM North LTFEXP_CBM-N->PJM CBM 11.08 MW 11.08 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.02 MW 11.02 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 2.29 MW 2.29 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.65 MW 0.65 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.25 MW 0.25 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.08 MW 0.08 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.33 MW 0.33 MW
MEC LTFEXP_MEC->PJM CLTF 0.74 MW 0.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.45 MW 0.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.4 MW 3.4 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.14 MW 0.14 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

PSSE Dynamic Study Analysis

 

Executive Summary

 

New Service Request projects in PJM Transition Cycle 1, Cluster 69 are listed in Table 1 below. The report covers the dynamic analysis of Cluster 69 projects.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 69 projects will meet the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 69 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.01 pu voltage at the AF2-010 POI bus, and 1.01 pu voltage at the AG1-548 POI bus.

 

Cluster 69 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 81 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)  Steady-state operation (Category P0);

b)  Three-phase faults with normal clearing time (Category P1);

c)  Single-phase faults with stuck breaker (Category P4);

d)  Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 69 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For 75 out of 81 fault contingencies tested on the 2027 peak load case:

a)  Cluster 69 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)  The system with Cluster 69 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter-area modes and 4% for local modes.

c)  Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)  No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-010 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AF2-010 was observed.

 

For P1.27, P4.12, P4.13, P4.14, P4.15, and P5.13, after losing 115 kV circuit from Erie South to AG1-548 POI, the results show undamped oscillations indicating system instability. The CSCR assessment shows under these fault contingencies, the CSCR values would be below 1.5 which could be considered very weak grid conditions. The PSSE dynamic analysis shows that system reinforcement is needed to resolve the undamped oscillations. Since the PSSE generic model might be not accurate at very low SC levels, an electromagnetic transient analysis with a more detailed model is required. An electromagnetic transient study was performed in TC1 Phase III.

 

PSCAD Electromagnetic Study Analysis

 

Executive Summary

 

Electromagnetic transient model quality tests were performed for the 150 MW French Creek Solar and Storage project and the Union Solar project. PSCAD models were used to perform testing and analysis to ensure compliance with PJM requirements.

 

The French Creek Solar and Storage project located in Erie County, Pennsylvania was modeled with forty-two (42) Sungrow SG4400UD-US inverters and forty-two (42) step-up transformers for the photovoltaic generation portion; eight (8) Sungrow SC4400UD-US inverters and eight (8) step-up transformers for the battery energy storage system (BESS) portion; two (2) collection systems; one (1) main power transformer; and a 1-mile (5280 ft) transmission line connected to a 115 kV tap on the Erie South to Union City transmission line.

 

The Union Solar project located in Erie County, Pennsylvania was modeled with nineteen (19) SMA SC 4600-UP inverters and nineteen (19) step-up transformers, one (1) collection system, one (1) main power transformer, and a 0.02-mile transmission line connected to the 115 kV tap on Union City to Titusville transmission line.

 

Model quality tests for the French Creek Solar and Storage project, and the Union Solar project were performed for the following scenarios:

 

•  Flat Start Test Voltage Step-Down

•  Voltage Step-Up

•  Frequency Step-Down, No Headroom

•  Frequency Step-Up/Down, Headroom (@ 80% Pmax)

•  HVRT Leading (Legacy Curve)

•  HVRT Lagging (Legacy Curve)

•  LVRT Leading (Legacy Curve)

•  LVRT Lagging (Legacy Curve)

•  Voltage Ride Through (VRT)

•  Phase Angle Step-Down

•  Phase Angle Step-Up

•  System Strength Test

 

The French Creek Solar and Storage project PSCAD model, and the Union Solar project PSCAD model, with fine tuning, both passed all the model quality tests. The undamped oscillations identified in the PSSE dynamic study are not observed in the PSCAD study with a more detailed model. It is therefore concluded that undamped oscillations under P1.27, P4.12, P4.13, P4.14, P4.15, and P5.13 can be resolved with fine tuning of the plant.

 

Table 1: TC1 Cluster 69 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

69

AF2-010

Solar

FirstEnergy (Mid-Atlantic Interstate Transmission, LLC - Penelec Zone)

77 MW

77 MW

46 MW

Union City –Titusville 115 kV

69

AG1-548

Solar + Storage

FirstEnergy (Mid-Atlantic Interstate Transmission, LLC - Penelec Zone)

150 MW

150 MW

45 MW

Erie South -Union City 115 kV

 

Reactive Power Analysis

PJM Queue projects AF2-010 and AG1-548 meet the PJM reactive power requirement, maintaining a 0.95 leading and lagging power factor at the high side of the Main Power Transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AC1-025 Dale Summit In Service
AE2-001 Nittany-Zion 46 kV Suspended
AE2-074 Potter 46 kV Engineering & Procurement
AE2-113 Farmers Valley-Ridgeway 115 kV Under Construction
AE2-117 ABW Tap-Alexandria 46 kV Suspended
AE2-118 ABW Tap-Williamsburg 46 kV Suspended
AE2-126 Dubois-Curwensville 34.5 kV In Service
AE2-129 Philipsburg-Clarence 34.5 kV In Service
AE2-131 Philipsburg-Karthaus 34.5 Under Construction
AE2-139 East Towanda-Grover 230 kV Engineering & Procurement
AE2-224 Bear Rock-Johnstown 230 kV In Service
AE2-248 Fillmore-Thompson Farm 46 kV Suspended
AE2-262 Moshannon-Milesburg 230 kV Engineering & Procurement
AE2-263 Moshannon-Milesburg 230 kV II Engineering & Procurement
AE2-299 Erie East 230 kV Suspended
AE2-316 Brookville-Squab Hollow 138 kV Under Construction
AE2-344 Edinboro South-Venango Junction 115 kV Suspended
AF1-006 Fairview East 34.5 kV In Service
AF1-039 Listonburg-Highpoint 24.9 kV In Service
AF1-086 Madera-Westover South 115 kV Under Construction
AF1-094 Union City-Cambridge Springs 34.5 kV Engineering & Procurement
AF1-098 Four Mile Jct-Corry East 115 kV Engineering & Procurement
AF1-106 East Sayre 34.5 kV Engineering & Procurement
AF1-134 Philipsburg-Madera 34.5 kV Engineering & Procurement
AF1-140 Claysburg 23 kV Engineering & Procurement
AF1-143 Lick Run 115 kV Engineering & Procurement
AF1-153 Motion-Ridgeway 46 kV Engineering & Procurement
AF1-155 Paper City-Wilcox 46 kV Withdrawn
AF1-167 West Freedom-C&K Coal 25 kV Suspended
AF1-217 Edinboro -Cambridge Springs 34.5 kV Withdrawn
AF1-240 Timblin 34.5 kV Active
AF1-272 Lucerne 115 kV Engineering & Procurement
AF1-287 Edinboro South 34.5 kV II Suspended
AF1-302 Brookville-Squab Hollow 138 kV Engineering & Procurement
AF1-321 Hooversville 115 kV I Suspended
AF2-001 Hooversville 115 kV II Suspended
AF2-002 Hooversville 115 kV III Suspended
AF2-039 Shawville-Clearfield 34.5 kV Engineering & Procurement
AF2-050 Bear Rock-Johnstown 230 kV Active
AF2-088 Shawville-Clearfield 34.5 kV II Engineering & Procurement
AF2-092 Snake Spring-Bedford Area 23 kV Suspended
AF2-130 Cobalt Corners 34.5 kV In Service
AF2-165 Clark Summit-Emlenton 34.5 kV In Service
AF2-166 Emlenton 34.5 kV Suspended
AF2-221 Scalp Level 22.9 kV Suspended
AF2-235 Titusville-Oil Creek 34.5 kV Withdrawn
AF2-238 Mansfield-South Troy 34.5 kV Engineering & Procurement
AF2-294 Thompson 34.5 kV Suspended
AF2-296 Madera 34.5 kV Active
AG1-040 Morgan Street-Mount Hope 34.5 kV Engineering & Procurement
AG1-041 Osterburg-Bedford North 23 kV Withdrawn
AG1-090 Philipsburg 115 kV Active
AG1-100 Venango-Saegertown 34.5 kV Engineering & Procurement
AG1-140 Union City 34.5 kV Suspended
AG1-193 Utica Junction 34.5 kV Suspended
AG1-197 Morgan Street-Cochranton 34.5 kV Suspended
AG1-198 Union City 34.5 kV Under Construction
AG1-253 Erie East-Union City 34.5 kV Suspended
AG1-281 Claysburg-HCR Tap 46 kV Engineering & Procurement
AG1-301 Miller REC-Warrior Ridge 46 kV Engineering & Procurement
AG1-377 Philipsburg 115 kV Active
AG1-378 Philipsburg 115 kV Active
AG1-548 Erie South-Union City 115 kV Active
V3-030 St. Benedict-Patton 46kV In Service
Y1-033 Penn Mar-Rock Wood 115kV In Service
Z1-069 Gold-Sabinsville 115kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF2-010 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
PENELEC n9116.0 Rebuild approximately 11 miles of the Homer City-Shelocta 230 kV line with double bundled 795 kcmil 26/7 ACSS conductor Cost Allocated $5,856,899
PENELEC n9119.0 Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor Cost Allocated $1,414,685
PENELEC n9225.0 Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal Cost Allocated $16,026
PENELEC s3335.1 Replace Homer City South 345/230-23kV Transformer (Projected ISD 6/1/2027) Contingent $0 N/A
Grand Total: $7,287,610

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9116.0
Type
Load Flow
TO
PENELEC
RTEP ID / TO ID
n9116.0 / TC1-PN-001.d
Title
Rebuild approximately 11 miles of the Homer City-Shelocta 230 kV line with double bundled 795 kcmil 26/7 ACSS conductor
Description
Rebuild the Homer City – Shelocta 230 kV Line, approximately 11 miles, with double bunded 795 kcmil 26/7 ACSS conductor. Terminate new conductor at Homer City substation. Terminate new conductor at Shelocta substation.
Total Cost ($USD)
$39,312,233
Discounted Total Cost ($USD)
$39,312,233
Allocated Cost ($USD)
$5,856,899
Time Estimate
31 Months

Contributor

Facility Contingency
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-010 10.7 MW 14.9% $5,856,899
AF2-050 14.7 MW 20.4% $8,035,867
AG1-090 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
18.1 MW 25.2% $9,907,383
AG1-377 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
3.8 MW 5.3% $2,085,966
AG1-378 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
3.8 MW 5.3% $2,085,966
AG1-548 20.7 MW 28.8% $11,340,151

System Reinforcement: n9119.0
Type
Load Flow
TO
PENELEC
RTEP ID / TO ID
n9119.0 / TC1-PN-003.b
Title
Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor
Description
Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor. Terminate new conductor at Keystone substation. Terminate new conductor at Shelocta substation.
Total Cost ($USD)
$9,533,592
Discounted Total Cost ($USD)
$9,533,592
Allocated Cost ($USD)
$1,414,685
Time Estimate
23 Months

Contributor

Facility Contingency
26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-010 11.8 MW 14.8% $1,414,685
AF2-050 15.1 MW 19.0% $1,809,150
AG1-090 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
21.1 MW 26.5% $2,527,327
AG1-377 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
4.4 MW 5.6% $532,018
AG1-378 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
4.4 MW 5.6% $532,018
AG1-548 22.7 MW 28.5% $2,718,394

System Reinforcement: n9225.0
Type
Load Flow
TO
PENELEC
RTEP ID / TO ID
n9225.0 / TC1-PN-001.e
Title
Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal
Description
Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal
Total Cost ($USD)
$107,569
Discounted Total Cost ($USD)
$107,569
Allocated Cost ($USD)
$16,026
Time Estimate
13 Months

Contributor

Facility Contingency
26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-010 10.7 MW 14.9% $16,026
AF2-050 14.7 MW 20.4% $21,988
AG1-090 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
18.1 MW 25.2% $27,109
AG1-377 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
3.8 MW 5.3% $5,708
AG1-378 Philipsburg 115kV yard - Penelec: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG1-090, AG1-377, AG1-378
3.8 MW 5.3% $5,708
AG1-548 20.7 MW 28.8% $31,030

System Reinforcement: s3335.1
Type
Load Flow
TO
PENELEC
RTEP ID / TO ID
s3335.1 / PN-2024-007
Title
Replace Homer City South 345/230-23kV Transformer (Projected ISD 6/1/2027)
Description
Replace the South 345/230-23kV Transformer and associated equipment with: - One(1) 345/230kV Transformer with three single-phase units - Replace 345 kV circuit switcher, disconnects, circuit breaker, and substation conductor Transformer Ratings: - Before Proposed Solution: 649/836/793/984 MVA (SN/SLTE/WN/WLTE) - After Proposed Solution: 913/1147/1201/1376 MVA (SN/SLTE/WN/WLTE)
Cost Information
Time Estimate
Jun 01 2027

Contingent

Note: Although AF2-010 may not presently have cost responsibility for this upgrade, AF2-010 may need this upgrade in-service to be deliverable to the PJM system. If AF2-010 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
26HOMER CT-26HOMER CT _ 230.0 kV Ckt S line (Any)
26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer (Any)

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-010


AF2-010 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF2-010 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AF2-010 One Line Diagram

AF2-010 One Line Diagram.pdf

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.