AF2-080 Phase III Study Report

v1.00 released 2025-09-18 16:44

Chinquapin-Everetts 230 kV

48.5 MW Capacity / 70.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Pitt Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (Dominion Virginia Power).

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $24,649,633 $20,549,683 = 1.20 AND ( $24,649,633 - $20,549,683 ) 70.0 = $58,571 per MW

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Virginia Electric and Power Company (Dominion Virginia Power) zone — Pitt County, North Carolina. This project is an increase to the developer’s AC1-189 project(s), which will share the same Point of Interconnection. The AF2-080 project is a 70.0 MW uprate (48.5 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 150.0 MW with 101.9 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-080
Project Name:
Chinquapin-Everetts 230 kV
Project Developer Name:
Pitt Solar, LLC
State:
North Carolina
County:
Pitt
Transmission Owner:
Virginia Electric and Power Company (Dominion Virginia Power)
MFO:
150.0
MWE:
70.0
MWC:
48.5
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Not Required

A Physical Interconnection Facilities Study is not required for this project.

Point of Interconnection

AF2-080 will interconnect with the Dominion on transmission system as an uprate to AC1-189 which is tapping the Chinquapin to Everetts 230 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF2-080 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF2-080 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $0 $0
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $0 $0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $20,923,633 $20,923,633
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $3,726,000 $0
Total $24,649,633 $20,923,633

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AC1-189/AF2-080

Security has been calculated for the AC1-189/AF2-080 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AC1-189/AF2-080
Project(s): AC1-189/AF2-080
Final Agreement Security (A): $26,431,603
Portion of Costs Already Paid (B): $5,331,157
Net Security Due at DP3: A B = $21,100,445
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The New Service Request Project will interconnect with the Dominion transmission system at the existing AC1-189 switching station on the Chinquapin-Everetts 230 kV Line.

No TO Interconnection Facilities or Physical Network Upgrades are required for this project.

AF2-080 is sharing the POI and Transmission Owner Interconnection Facilities with AC1-189, there are no associated interconnection costs for this project. Should AC1-189 withdraw  the Interconnection Request, AF2-080 will assume the Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and applicable Network Upgrade costs identified in the AC1-189 study report for connection to the Dominion system.
 

Transmission Owner Analysis

PJM performed a power flow analysis of the transmission system using a 2027 load flow model and the results were verified by Dominion.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request was evaluated as a 70.0 MW (48.5 MW Capacity) injection in the Dominion area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 6CHESTF B-6BASIN 230.0 kV Ckt 1 line
314287 to 314276 ckt 1
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Breaker AC 147.68 % 812.0 C 1199.17 4.19
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
DVP_P4-2: 246T2034_SRT-A-1
CONTINGENCY 'DVP_P4-2: 246T2034_SRT-A-1'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314620 CKT 1   /*6EARLEYS     230.0 - 6CASHIE      230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BRANCH FROM BUS 314620 TO BUS 933980 CKT 1   /*6CASHIE      230.0 - AD1-022 TP   230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 129.41 % 830.0 C 1074.11 13.46
DVP 6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line
314638 to 314647 ckt 1
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 126.31 % 699.0 C 882.94 9.22
DVP 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 121.24 % 830.0 C 1006.27 12.81
DVP 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
DVP_P4-2: 24662_SRT-A
CONTINGENCY 'DVP_P4-2: 24662_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314568 TO BUS 314569 CKT 1   /*3EARLEYS     115.0 - 6EARLEYS     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 116.16 % 830.0 C 964.12 12.36
DVP 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Breaker AC 115.93 % 1204.0 C 1395.79 6.01
DVP 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Breaker AC 114.15 % 1204.0 C 1374.4 6.01
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-2: 557T574_SRT-S
CONTINGENCY 'DVP_P4-2: 557T574_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Breaker AC 107.33 % 3940.0 C 4228.89 10.89
DVP 6POE-6TYLER1 230.0 kV Ckt 1 line
314331 to 314263 ckt 1
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Breaker AC 112.93 % 541.0 C 610.96 3.54
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P4-2: 563T576_SRT-S
CONTINGENCY 'DVP_P4-2: 563T576_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Breaker AC 102.26 % 3144.0 C 3215.2 13.04
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P4-2: 56372_SRT-S
CONTINGENCY 'DVP_P4-2: 56372_SRT-S'
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1                /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Breaker AC 101.94 % 3144.0 C 3205.05 12.7
DVP 6PEMBROKE-6WALBMRL 230.0 kV Ckt 1 line
313714 to 313885 ckt 1
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 102.99 % 897.0 C 923.8 10.73
DVP 6WALBMRL-6S HERTFORD 230.0 kV Ckt 1 line
313885 to 314662 ckt 1
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 101.9 % 897.0 C 914.05 10.73
DVP 6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line
314662 to 314651 ckt 1
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 101.55 % 897.0 C 910.93 10.73
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 131.93 % 830.0 C 1095.02 12.8
DVP AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Breaker AC 131.54 % 830.0 C 1091.79 12.81
CPLE/DVP 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
DVP_P4-2: 2058T2167_SRT-A
CONTINGENCY 'DVP_P4-2: 2058T2167_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314564 CKT 1   /*6HATHAWAY    230.0 - 6EDGECOM     230.0
END
Breaker AC 119.3 % 478.0 B 570.27 29.25
DVP 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Breaker AC 116.2 % 830.0 C 964.47 12.4
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-2: H1T567_SRT-A
CONTINGENCY 'DVP_P4-2: H1T567_SRT-A'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1   /*8CHCKAHM     500.0 - 8SURRY       500.0
END
Breaker AC 105.01 % 3940.0 C 4137.47 15.66
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P4-2: H6T576_SRT-A
CONTINGENCY 'DVP_P4-2: H6T576_SRT-A'
 OPEN BRANCH FROM BUS 314322 TO BUS 314914 CKT 1   /*6MDLTHAN     230.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Breaker AC 102.27 % 3144.0 C 3215.35 13.04
DVP 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
DVP_P4-2: H6T563_SRT-S
CONTINGENCY 'DVP_P4-2: H6T563_SRT-S'
 OPEN BRANCH FROM BUS 314322 TO BUS 314914 CKT 1                /*6MDLTHAN     230.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Breaker AC 102.27 % 3144.0 C 3215.35 13.04
DVP 6CHESTF B-6BASIN 230.0 kV Ckt 1 line
314287 to 314276 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Single AC 138.18 % 663.64 B 917.03 2.79
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Single AC 128.4 % 571.52 B 733.82 10.17
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
DVP_P1-2: LN 2131_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2131_SRT-A'
 OPEN BRANCH FROM BUS 313015 TO BUS 313714 CKT 1   /*6CHOWAN      230.0 - 6PEMBROKE    230.0
 OPEN BRANCH FROM BUS 313015 TO BUS 314637 CKT 1   /*6CHOWAN      230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313015                                   /*6CHOWAN      230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Single AC 127.21 % 571.52 B 727.02 10.17
DVP 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Single AC 123.46 % 571.52 B 705.6 10.17
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Single AC 117.31 % 678.68 B 796.16 8.56
DVP 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
DVP_P1-2: LN 2131_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2131_SRT-A'
 OPEN BRANCH FROM BUS 313015 TO BUS 313714 CKT 1   /*6CHOWAN      230.0 - 6PEMBROKE    230.0
 OPEN BRANCH FROM BUS 313015 TO BUS 314637 CKT 1   /*6CHOWAN      230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313015                                   /*6CHOWAN      230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Single AC 122.28 % 571.52 B 698.84 10.17
DVP AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Single AC 114.48 % 678.68 B 776.96 8.57
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 118.96 % 678.68 B 807.34 6.8
DVP AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 116.16 % 678.68 B 788.36 6.81
DVP 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Single AC 105.2 % 678.68 B 713.99 8.57
DVP 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Single AC 107.24 % 678.68 B 727.84 6.81
DVP 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Single AC 105.13 % 1058.16 B 1112.41 3.33
DVP 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
DVP_P1-2: LN 574_SRT-S_SENS
CONTINGENCY 'DVP_P1-2: LN 574_SRT-S_SENS'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2598 BRANCH FROM BUS 314908 TO BUS 314903 CKT 1 /*8ELMONT      500.0 - 8CHCKAHM     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314918 TO BUS 314911 CKT 1 /*8NO ANNA     500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2598 BRANCH FROM BUS 314908 TO BUS 314903 CKT 1 /*8ELMONT      500.0 - 8CHCKAHM     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314918 TO BUS 314911 CKT 1 /*8NO ANNA     500.0 - 8LADYSMITH   500.0
END
Single AC 104.61 % 3220.44 B 3368.83 10.33
CPLE/DVP 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
DVP_P7-1: LN 2058-2181_SRT-A
CONTINGENCY 'DVP_P7-1: LN 2058-2181_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Tower AC 119.28 % 478.0 B 570.16 19.85
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P7-1: ELMONT-LADYSMITH_500_230_SRT-A
CONTINGENCY 'DVP_P7-1: ELMONT-LADYSMITH_500_230_SRT-A'
 OPEN BRANCH FROM BUS 314218 TO BUS 314196 CKT 1   /*6ELMONT      230.0 - 6LADYSMITH   230.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1   /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Tower AC 105.56 % 3940.0 C 4158.88 14.86

Details for 6CHESTF B-6BASIN 230.0 kV Ckt 1 line l/o DVP_P4-2: 562T563_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6BASIN 230.0 kV Ckt 1 line
314287 to 314276 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 147.68 %
Rating: 812.0 MVA
Rating Type: C
MVA to Mitigate: 1199.17 MVA
MW Contribution: 4.19 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.36 MW 0.31 MW
961672 AG1-007 E Adder 0.2 MW 0.17 MW
961941 AG1-037 C Adder 0.2 MW 0.17 MW
961942 AG1-037 E Adder 0.13 MW 0.11 MW
962331 AG1-082 C Adder 0.8 MW 0.68 MW
962332 AG1-082 E Adder 0.53 MW 0.45 MW
963041 AG1-153 C Adder 2.36 MW 2.0 MW
963042 AG1-153 E Adder 3.54 MW 3.01 MW
964791 AG1-342 C Adder 1.17 MW 0.99 MW
964792 AG1-342 E Adder 0.78 MW 0.66 MW
966801 AG1-551 C Adder 0.79 MW 0.67 MW
966802 AG1-551 E Adder 0.41 MW 0.35 MW
966811 AG1-552 C Adder 0.89 MW 0.76 MW
966812 AG1-552 E Adder 0.42 MW 0.36 MW
965291 AG1-394 C Adder 0.35 MW 0.29 MW
965292 AG1-394 E Adder 0.64 MW 0.54 MW
966621 AG1-532 C Adder 0.68 MW 0.58 MW
966622 AG1-532 E Adder 0.45 MW 0.39 MW
314541 3WATKINS Adder 0.27 MW 0.23 MW
314572 3EMPORIA Adder 0.21 MW 0.18 MW
315131 1EDGECMA Adder 6.01 MW 5.11 MW
918492 AA1-063AE OP Adder 1.72 MW 1.47 MW
918532 AA1-067 E Adder 0.27 MW 0.23 MW
919692 AA2-053 E OP Adder 1.8 MW 1.53 MW
920042 AA2-088 E OP Adder 4.28 MW 3.63 MW
925785 AC1-054 E Adder 1.34 MW 1.14 MW
926274 AC1-105 E Adder 0.88 MW 0.74 MW
927146 AC1-208 E Adder 1.75 MW 1.48 MW
934521 AD1-076 C Adder 4.44 MW 3.77 MW
934522 AD1-076 E Adder 2.26 MW 1.92 MW
943172 AE2-346 E Adder 0.24 MW 0.2 MW
944011 AF1-069 C Adder 5.55 MW 4.72 MW
944012 AF1-069 E Adder 2.16 MW 1.83 MW
960081 AF2-299 C Adder 0.91 MW 0.77 MW
960082 AF2-299 E Adder 0.61 MW 0.52 MW
316141 AB2-099 E Adder 0.1 MW 0.09 MW
900672 V4-068 E Adder 0.14 MW 0.12 MW
917342 Z2-044 E Adder 0.27 MW 0.23 MW
922923 AB1-081 E OP Adder 1.44 MW 1.23 MW
923263 AB1-132 E OP Adder 2.84 MW 2.41 MW
923573 AB1-173 E OP Adder 1.52 MW 1.29 MW
924162 AB2-060 E OP Adder 1.45 MW 1.23 MW
924302 AB2-077 E O1 Adder 0.46 MW 0.39 MW
924312 AB2-078 E O1 Adder 0.46 MW 0.39 MW
924322 AB2-079 E O1 Adder 0.46 MW 0.39 MW
939181 AE1-148 C Adder 3.19 MW 2.71 MW
939182 AE1-148 E Adder 2.13 MW 1.81 MW
940492 AE2-034 E Adder 1.09 MW 0.92 MW
941031 AE2-094 C Adder 16.98 MW 14.43 MW
941032 AE2-094 E Adder 7.6 MW 6.46 MW
946281 AF1-292 C Adder 0.75 MW 0.64 MW
946282 AF1-292 E Adder 0.5 MW 0.43 MW
957481 AF2-042 C Adder 19.92 MW 16.93 MW
957482 AF2-042 E Adder 13.28 MW 11.29 MW
957521 AF2-046 C Adder 5.67 MW 4.82 MW
957522 AF2-046 E Adder 2.87 MW 2.44 MW
957861 AF2-080 C Adder 2.9 MW 2.47 MW
957862 AF2-080 E Adder 1.29 MW 1.09 MW
314539 3UNCAMP Adder 2.36 MW 2.01 MW
916042 Z1-036 E Adder 9.71 MW 8.26 MW
938771 AE1-103 C Adder 1.13 MW 0.96 MW
938772 AE1-103 E Adder 1.56 MW 1.32 MW
314331 6POE 50/50 1.23 MW 1.23 MW
314507 3THOMPSN Adder 0.64 MW 0.54 MW
314525 6KINGFORK Adder 0.34 MW 0.29 MW
314550 6HICKORY Adder 0.66 MW 0.56 MW
315065 1CHESTF6 50/50 26.43 MW 26.43 MW
315073 1STONECA 50/50 4.75 MW 4.75 MW
315076 1HOPPOLC 50/50 1.05 MW 1.05 MW
315077 1HOPHCF1 50/50 1.68 MW 1.68 MW
315078 1HOPHCF2 50/50 1.68 MW 1.68 MW
315079 1HOPHCF3 50/50 1.68 MW 1.68 MW
315080 1HOPHCF4 50/50 2.54 MW 2.54 MW
926662 AC1-147 E Adder 0.42 MW 0.35 MW
927226 AC1-216 E Adder 4.19 MW 3.56 MW
935112 AD1-144 E Adder 0.31 MW 0.27 MW
942341 AE2-247 C Adder 0.7 MW 0.59 MW
942342 AE2-247 E Adder 0.96 MW 0.82 MW
943461 AF1-017 C Adder 0.63 MW 0.54 MW
943462 AF1-017 E Adder 1.03 MW 0.87 MW
943612 AF1-032 E Adder 0.3 MW 0.26 MW
315260 1GOSPORTA Adder 0.67 MW 0.57 MW
315261 1GOSPORTB Adder 0.86 MW 0.73 MW
315262 1GOSPORTC Adder 0.73 MW 0.62 MW
316132 AB2-190 C 50/50 2.49 MW 2.49 MW
913392 Y1-086 E Adder 0.7 MW 0.59 MW
916192 Z1-068 E Adder 0.58 MW 0.49 MW
923832 AB2-022 E Adder 0.4 MW 0.34 MW
923852 AB2-025 E 50/50 0.71 MW 0.71 MW
939312 AE1-162 E Adder 0.55 MW 0.46 MW
946262 AF1-291 E 50/50 1.87 MW 1.87 MW
957492 AF2-043 E Adder 0.47 MW 0.4 MW
901082 W1-029 E Adder 10.5 MW 8.92 MW
917122 Z2-027 E Adder 0.43 MW 0.37 MW
925332 AB2-190 E 50/50 4.84 MW 4.84 MW
925522 AC1-027 E Adder 0.38 MW 0.32 MW
942001 AE2-212 C 50/50 2.38 MW 2.38 MW
942002 AE2-212 E 50/50 1.59 MW 1.59 MW
957871 AF2-081 C Adder 3.08 MW 2.62 MW
957872 AF2-081 E Adder 1.32 MW 1.12 MW
958161 AF2-110 C Adder 0.51 MW 0.43 MW
958162 AF2-110 E Adder 0.81 MW 0.69 MW
917512 Z2-088 E OP1 Adder 1.87 MW 1.59 MW
926071 AC1-086 C Adder 9.75 MW 8.29 MW
926072 AC1-086 E Adder 4.44 MW 3.77 MW
927021 AC1-189 C Adder 3.2 MW 2.72 MW
927022 AC1-189 E Adder 1.59 MW 1.35 MW
934621 AD1-088 C Adder 4.3 MW 3.66 MW
934622 AD1-088 E Adder 2.02 MW 1.72 MW
939411 AE1-173 C Adder 34.69 MW 29.49 MW
939412 AE1-173 E Adder 23.13 MW 19.66 MW
934012 AD1-025 E Adder 5.43 MW 4.61 MW
933981 AD1-022 C Adder 3.23 MW 2.74 MW
933982 AD1-022 E Adder 1.76 MW 1.49 MW
962572 AG1-106 E Adder 0.55 MW 0.47 MW
961681 AG1-008 C Adder 5.67 MW 4.82 MW
961682 AG1-008 E Adder 2.87 MW 2.44 MW
962571 AG1-106 C Adder 1.26 MW 1.07 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
314632 6AYDLETT TAP Adder 0.42 MW 0.36 MW
316240 AF1-291 C 50/50 2.8 MW 2.8 MW
316263 AC1-034 C Adder 2.57 MW 2.18 MW
316274 AC1-208 C Adder 3.93 MW 3.34 MW
316315 AB2-025 C 50/50 0.25 MW 0.25 MW
917332 KELFORD E Adder 0.67 MW 0.57 MW
924516 AB2-100 E1 Adder 1.53 MW 1.3 MW
924517 AB2-100 E2 Adder 1.53 MW 1.3 MW
925595 AC1-034 E Adder 1.94 MW 1.65 MW
926206 AC1-098 E Adder 1.57 MW 1.33 MW
926214 AC1-099 E Adder 0.52 MW 0.44 MW
934065 AD1-033 E Adder 1.52 MW 1.29 MW
937226 AE2-253 E Adder 1.79 MW 1.52 MW
918512 AA1-065 E OP Adder 2.13 MW 1.81 MW
919153 AA1-139 E2 Adder 1.26 MW 1.07 MW
919152 AA1-139 E1 Adder 1.26 MW 1.07 MW
919710 AA2-057 E Adder 1.76 MW 1.5 MW
920692 AA2-178 E Adder 1.45 MW 1.23 MW
923994 AB2-040_E Adder 2.84 MW 2.42 MW
924022 AB2-043 E O1 Adder 1.77 MW 1.5 MW
924152 AB2-059 E OP Adder 2.04 MW 1.74 MW
924814 AB2-134 E Adder 6.87 MW 5.84 MW
316083 AB2-161 C 50/50 0.34 MW 0.34 MW
316084 AB2-161 E 50/50 3.38 MW 3.38 MW
925122 AB2-169 E Adder 2.12 MW 1.8 MW
316088 AB2-174 E Adder 3.06 MW 2.6 MW
932046 AC2-012 E Adder 4.12 MW 3.5 MW
316311 AC2-079 C Adder 2.6 MW 2.21 MW
932596 AC2-079 E Adder 4.25 MW 3.61 MW
316381 AD1-082 C 50/50 0.77 MW 0.77 MW
934576 AD1-082 E 50/50 2.7 MW 2.7 MW
316349 AD2-085 C Adder 1.6 MW 1.36 MW
936666 AD2-085 E Adder 2.62 MW 2.22 MW
961611 AG1-000B C Adder 7.24 MW 6.16 MW
941591 AE2-156 C Adder 5.62 MW 4.78 MW
944581 AF1-123 C Adder 13.72 MW 11.66 MW
944582 AF1-123 E Adder 31.41 MW 26.7 MW
944591 AF1-124 C Adder 13.77 MW 11.7 MW
944592 AF1-124 E Adder 31.52 MW 26.8 MW
944601 AF1-125 C Adder 13.51 MW 11.48 MW
944602 AF1-125 E Adder 30.92 MW 26.28 MW
962491 AG1-098 C Adder 3.8 MW 3.23 MW
962492 AG1-098 E Adder 2.53 MW 2.15 MW
962561 AG1-105 C Adder 2.95 MW 2.51 MW
962562 AG1-105 E Adder 1.97 MW 1.67 MW
964241 AG1-285 C Adder 4.28 MW 3.64 MW
964242 AG1-285 E Adder 2.86 MW 2.43 MW
965281 AG1-393 C Adder 1.08 MW 0.92 MW
965282 AG1-393 E Adder 0.72 MW 0.61 MW
313764 3SOCKMAN Adder 0.32 MW 0.27 MW
932632 AC2-084 E Adder 1.38 MW 1.18 MW
934321 AD1-056 C Adder 2.63 MW 2.23 MW
934322 AD1-056 E Adder 1.43 MW 1.21 MW
934331 AD1-057 C Adder 1.47 MW 1.25 MW
934332 AD1-057 E Adder 0.76 MW 0.65 MW
934501 AD1-074 C Adder 12.21 MW 10.38 MW
934502 AD1-074 E Adder 6.22 MW 5.29 MW
934511 AD1-075 C Adder 3.05 MW 2.6 MW
934512 AD1-075 E Adder 1.55 MW 1.32 MW
934612 AD1-087 E Adder 1.29 MW 1.1 MW
935161 AD1-151 C 50/50 9.25 MW 9.25 MW
935162 AD1-151 E 50/50 6.17 MW 6.17 MW
935172 AD1-152 E Adder 1.9 MW 1.62 MW
937482 AD2-202 E Adder 0.38 MW 0.32 MW
938531 AE1-072 C Adder 5.45 MW 4.63 MW
938532 AE1-072 E Adder 2.84 MW 2.42 MW
939191 AE1-149 C 50/50 7.65 MW 7.65 MW
939192 AE1-149 E 50/50 5.1 MW 5.1 MW
940431 AE2-027 C Adder 5.5 MW 4.67 MW
940432 AE2-027 E Adder 3.66 MW 3.11 MW
940481 AE2-033 C 50/50 9.77 MW 9.77 MW
940482 AE2-033 E 50/50 6.59 MW 6.59 MW
940541 AE2-040 C 50/50 1.77 MW 1.77 MW
941101 AE2-104 C Adder 1.24 MW 1.06 MW
941102 AE2-104 E Adder 1.97 MW 1.68 MW
944641 AF1-129 C 50/50 137.81 MW 137.81 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.15 MW 8.15 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.56 MW 6.56 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 32.14 MW 32.14 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.99 MW 0.99 MW
NY PJM->LTFIMP_NY CLTF 0.47 MW 0.47 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.32 MW 0.32 MW
WEC LTFEXP_WEC->PJM CLTF 0.17 MW 0.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.01 MW 4.01 MW
TVA LTFEXP_TVA->PJM CLTF 1.82 MW 1.82 MW
MEC LTFEXP_MEC->PJM CLTF 1.09 MW 1.09 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.34 MW 2.34 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 6.32 MW 6.32 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.91 MW 1.91 MW

Details for 6SAPONY-6CARSON 230.0 kV Ckt 1 line l/o DVP_P4-2: 246T2034_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
DVP_P4-2: 246T2034_SRT-A-1
CONTINGENCY 'DVP_P4-2: 246T2034_SRT-A-1'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314620 CKT 1   /*6EARLEYS     230.0 - 6CASHIE      230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BRANCH FROM BUS 314620 TO BUS 933980 CKT 1   /*6CASHIE      230.0 - AD1-022 TP   230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 129.41 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1074.11 MVA
MW Contribution: 13.46 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
DVP_P4-2: 246T2034_SRT-A-1
CONTINGENCY 'DVP_P4-2: 246T2034_SRT-A-1'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314620 CKT 1   /*6EARLEYS     230.0 - 6CASHIE      230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BRANCH FROM BUS 314620 TO BUS 933980 CKT 1   /*6CASHIE      230.0 - AD1-022 TP   230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 135.12 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1121.51 MVA
MW Contribution: 13.69 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.18 MW 1.18 MW
961672 AG1-007 E 50/50 0.67 MW 0.67 MW
961941 AG1-037 C 50/50 0.79 MW 0.79 MW
961942 AG1-037 E 50/50 0.52 MW 0.52 MW
962331 AG1-082 C 50/50 3.14 MW 3.14 MW
962332 AG1-082 E 50/50 2.1 MW 2.1 MW
966801 AG1-551 C 50/50 2.17 MW 2.17 MW
966802 AG1-551 E 50/50 1.14 MW 1.14 MW
966811 AG1-552 C 50/50 3.75 MW 3.75 MW
966812 AG1-552 E 50/50 1.78 MW 1.78 MW
965291 AG1-394 C 50/50 1.0 MW 1.0 MW
965292 AG1-394 E 50/50 1.85 MW 1.85 MW
966621 AG1-532 C 50/50 3.53 MW 3.53 MW
966622 AG1-532 E 50/50 2.35 MW 2.35 MW
313506 AB1-173 C OP 50/50 2.48 MW 2.48 MW
314541 3WATKINS 50/50 0.53 MW 0.53 MW
314572 3EMPORIA 50/50 1.05 MW 1.05 MW
314704 3LAWRENC 50/50 0.59 MW 0.59 MW
315126 1ROARAP2 50/50 2.53 MW 2.53 MW
315128 1ROARAP4 50/50 2.39 MW 2.39 MW
315131 1EDGECMA 50/50 19.79 MW 19.79 MW
315136 1ROSEMG1 50/50 4.56 MW 4.56 MW
315137 1ROSEMS1 50/50 2.83 MW 2.83 MW
315138 1ROSEMG2 50/50 2.14 MW 2.14 MW
315139 1GASTONA 50/50 7.14 MW 7.14 MW
918492 AA1-063AE OP 50/50 6.4 MW 6.4 MW
918532 AA1-067 E 50/50 0.85 MW 0.85 MW
919692 AA2-053 E OP 50/50 7.57 MW 7.57 MW
920042 AA2-088 E OP 50/50 11.88 MW 11.88 MW
925785 AC1-054 E 50/50 3.96 MW 3.96 MW
927146 AC1-208 E 50/50 7.31 MW 7.31 MW
943171 AE2-346 C 50/50 0.35 MW 0.35 MW
943172 AE2-346 E 50/50 0.94 MW 0.94 MW
960081 AF2-299 C 50/50 4.71 MW 4.71 MW
960082 AF2-299 E 50/50 3.14 MW 3.14 MW
315601 1CONETOE2SOL 50/50 1.55 MW 1.55 MW
315606 3AA2-053SOLA 50/50 2.7 MW 2.7 MW
316129 AC1-054 C 50/50 1.41 MW 1.41 MW
316140 AB2-099 C 50/50 0.15 MW 0.15 MW
316141 AB2-099 E 50/50 0.39 MW 0.39 MW
900672 V4-068 E 50/50 0.47 MW 0.47 MW
917342 Z2-044 E 50/50 1.12 MW 1.12 MW
922923 AB1-081 E OP 50/50 4.71 MW 4.71 MW
923263 AB1-132 E OP 50/50 14.3 MW 14.3 MW
923573 AB1-173 E OP 50/50 7.22 MW 7.22 MW
946281 AF1-292 C 50/50 3.9 MW 3.9 MW
946282 AF1-292 E 50/50 2.6 MW 2.6 MW
957521 AF2-046 C 50/50 19.39 MW 19.39 MW
957522 AF2-046 E 50/50 9.8 MW 9.8 MW
957861 AF2-080 C 50/50 9.33 MW 9.33 MW
957862 AF2-080 E 50/50 4.13 MW 4.13 MW
315115 1S HAMPT1 50/50 1.18 MW 1.18 MW
315141 1GASTONB 50/50 7.14 MW 7.14 MW
315607 3AA1-063SOLA 50/50 2.2 MW 2.2 MW
315608 3AA2-088SOLA 50/50 1.19 MW 1.19 MW
923852 AB2-025 E 50/50 4.86 MW 4.86 MW
917512 Z2-088 E OP1 50/50 6.05 MW 6.05 MW
926071 AC1-086 C 50/50 49.15 MW 49.15 MW
926072 AC1-086 E 50/50 22.37 MW 22.37 MW
927021 AC1-189 C 50/50 10.27 MW 10.27 MW
927022 AC1-189 E 50/50 5.12 MW 5.12 MW
962572 AG1-106 E 50/50 2.78 MW 2.78 MW
961681 AG1-008 C 50/50 19.39 MW 19.39 MW
961682 AG1-008 E 50/50 9.8 MW 9.8 MW
962571 AG1-106 C 50/50 6.36 MW 6.36 MW
316005 AA1-067 C 50/50 0.33 MW 0.33 MW
316011 AB1-132 C OP 50/50 5.45 MW 5.45 MW
316023 AB2-100 C2 50/50 2.98 MW 2.98 MW
316049 AB1-081 C OP 50/50 1.79 MW 1.79 MW
316210 AC1-098 C 50/50 1.69 MW 1.69 MW
316212 AC1-099 C 50/50 0.57 MW 0.57 MW
316263 AC1-034 C 50/50 8.4 MW 8.4 MW
316274 AC1-208 C 50/50 16.47 MW 16.47 MW
316315 AB2-025 C 50/50 1.71 MW 1.71 MW
316317 KELFORD C 50/50 0.6 MW 0.6 MW
316318 V4-068 C 50/50 0.11 MW 0.11 MW
316319 Z2-044 C 50/50 0.4 MW 0.4 MW
316365 AB2-100 C1 50/50 2.98 MW 2.98 MW
917332 KELFORD E 50/50 2.78 MW 2.78 MW
924516 AB2-100 E1 50/50 8.98 MW 8.98 MW
924517 AB2-100 E2 50/50 8.98 MW 8.98 MW
925595 AC1-034 E 50/50 6.34 MW 6.34 MW
926206 AC1-098 E 50/50 6.55 MW 6.55 MW
926214 AC1-099 E 50/50 2.16 MW 2.16 MW
315602 1HOLLOMANSOL 50/50 3.01 MW 3.01 MW
918512 AA1-065 E OP 50/50 9.05 MW 9.05 MW
316327 AA2-057 C 50/50 2.42 MW 2.42 MW
919710 AA2-057 E 50/50 7.37 MW 7.37 MW
316181 AB2-040 GEN 50/50 2.8 MW 2.8 MW
923994 AB2-040_E 50/50 13.54 MW 13.54 MW
316359 AB2-059 C OP 50/50 2.12 MW 2.12 MW
924152 AB2-059 E OP 50/50 6.69 MW 6.69 MW
316174 AB2-169_C 50/50 0.77 MW 0.77 MW
925122 AB2-169 E 50/50 4.2 MW 4.2 MW
316087 AB2-174 C 50/50 2.71 MW 2.71 MW
316088 AB2-174 E 50/50 14.99 MW 14.99 MW
313764 3SOCKMAN 50/50 1.42 MW 1.42 MW
932631 AC2-084 C 50/50 1.8 MW 1.8 MW
932632 AC2-084 E 50/50 5.79 MW 5.79 MW
934321 AD1-056 C 50/50 10.78 MW 10.78 MW
934322 AD1-056 E 50/50 5.85 MW 5.85 MW
934331 AD1-057 C 50/50 6.01 MW 6.01 MW
934332 AD1-057 E 50/50 3.13 MW 3.13 MW
940481 AE2-033 C 50/50 65.43 MW 65.43 MW
940482 AE2-033 E 50/50 44.11 MW 44.11 MW
940541 AE2-040 C 50/50 12.01 MW 12.01 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.31 MW 12.31 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.49 MW 8.49 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 39.38 MW 39.38 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.83 MW 0.83 MW
NY PJM->LTFIMP_NY CLTF 0.38 MW 0.38 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.47 MW 0.47 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.37 MW 5.37 MW
TVA LTFEXP_TVA->PJM CLTF 2.27 MW 2.27 MW
MEC LTFEXP_MEC->PJM CLTF 1.51 MW 1.51 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.92 MW 2.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.26 MW 5.26 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.56 MW 2.56 MW

Details for 6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line l/o DVP_P4-2: 246T247_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line
314638 to 314647 ckt 1
Contingency Name:
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 126.31 %
Rating: 699.0 MVA
Rating Type: C
MVA to Mitigate: 882.94 MVA
MW Contribution: 9.22 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line
314638 to 314647 ckt 1
Contingency Name:
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 128.6 %
Rating: 699.0 MVA
Rating Type: C
MVA to Mitigate: 898.9 MVA
MW Contribution: 9.33 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.62 MW 0.62 MW
961672 AG1-007 E 50/50 0.35 MW 0.35 MW
961941 AG1-037 C 50/50 0.49 MW 0.49 MW
961942 AG1-037 E 50/50 0.33 MW 0.33 MW
962331 AG1-082 C 50/50 1.95 MW 1.95 MW
962332 AG1-082 E 50/50 1.3 MW 1.3 MW
966801 AG1-551 C 50/50 2.56 MW 2.56 MW
966802 AG1-551 E 50/50 1.35 MW 1.35 MW
918532 AA1-067 E 50/50 0.71 MW 0.71 MW
919692 AA2-053 E OP 50/50 2.59 MW 2.59 MW
927146 AC1-208 E 50/50 2.81 MW 2.81 MW
934521 AD1-076 C 50/50 27.18 MW 27.18 MW
934522 AD1-076 E 50/50 13.85 MW 13.85 MW
943171 AE2-346 C 50/50 0.22 MW 0.22 MW
943172 AE2-346 E 50/50 0.58 MW 0.58 MW
315601 1CONETOE2SOL 50/50 0.95 MW 0.95 MW
315606 3AA2-053SOLA 50/50 0.92 MW 0.92 MW
316140 AB2-099 C 50/50 0.09 MW 0.09 MW
316141 AB2-099 E 50/50 0.24 MW 0.24 MW
900672 V4-068 E 50/50 0.22 MW 0.22 MW
917342 Z2-044 E 50/50 0.45 MW 0.45 MW
922923 AB1-081 E OP 50/50 2.41 MW 2.41 MW
923263 AB1-132 E OP Adder 3.33 MW 2.83 MW
940491 AE2-034 C 50/50 3.13 MW 3.13 MW
940492 AE2-034 E 50/50 8.36 MW 8.36 MW
957521 AF2-046 C 50/50 9.84 MW 9.84 MW
957522 AF2-046 E 50/50 4.97 MW 4.97 MW
957861 AF2-080 C 50/50 6.38 MW 6.38 MW
957862 AF2-080 E 50/50 2.83 MW 2.83 MW
916042 Z1-036 E 50/50 95.99 MW 95.99 MW
313526 AB2-022 C 50/50 1.67 MW 1.67 MW
315292 1DOMTR78 50/50 2.67 MW 2.67 MW
315605 6W1-029WIND 50/50 3.02 MW 3.02 MW
315611 6Z1-036WIND 50/50 2.21 MW 2.21 MW
913392 Y1-086 E 50/50 9.74 MW 9.74 MW
923832 AB2-022 E 50/50 5.5 MW 5.5 MW
901082 W1-029 E 50/50 123.7 MW 123.7 MW
917122 Z2-027 E 50/50 5.7 MW 5.7 MW
917512 Z2-088 E OP1 50/50 3.73 MW 3.73 MW
926071 AC1-086 C Adder 11.43 MW 9.72 MW
926072 AC1-086 E Adder 5.2 MW 4.42 MW
927021 AC1-189 C 50/50 7.03 MW 7.03 MW
927022 AC1-189 E 50/50 3.5 MW 3.5 MW
933981 AD1-022 C 50/50 17.11 MW 17.11 MW
933982 AD1-022 E 50/50 9.31 MW 9.31 MW
962572 AG1-106 E Adder 0.65 MW 0.55 MW
961681 AG1-008 C 50/50 9.84 MW 9.84 MW
961682 AG1-008 E 50/50 4.97 MW 4.97 MW
962571 AG1-106 C Adder 1.48 MW 1.26 MW
314594 6PLYMOUTH TP 50/50 0.74 MW 0.74 MW
316005 AA1-067 C 50/50 0.27 MW 0.27 MW
316049 AB1-081 C OP 50/50 0.92 MW 0.92 MW
316210 AC1-098 C 50/50 0.74 MW 0.74 MW
316212 AC1-099 C 50/50 0.25 MW 0.25 MW
316263 AC1-034 C Adder 4.17 MW 3.55 MW
316274 AC1-208 C 50/50 6.34 MW 6.34 MW
316317 KELFORD C 50/50 0.35 MW 0.35 MW
316318 V4-068 C 50/50 0.05 MW 0.05 MW
316319 Z2-044 C 50/50 0.16 MW 0.16 MW
316320 Y1-086 C 50/50 0.97 MW 0.97 MW
316321 Z2-027 C 50/50 1.54 MW 1.54 MW
917332 KELFORD E 50/50 1.6 MW 1.6 MW
925595 AC1-034 E Adder 3.15 MW 2.68 MW
926206 AC1-098 E 50/50 2.87 MW 2.87 MW
926214 AC1-099 E 50/50 0.95 MW 0.95 MW
315602 1HOLLOMANSOL 50/50 2.19 MW 2.19 MW
918512 AA1-065 E OP 50/50 6.58 MW 6.58 MW
316327 AA2-057 C 50/50 0.96 MW 0.96 MW
919710 AA2-057 E 50/50 2.94 MW 2.94 MW
315614 AA2-178 C 50/50 4.25 MW 4.25 MW
920692 AA2-178 E 50/50 11.15 MW 11.15 MW
924152 AB2-059 E OP Adder 3.23 MW 2.75 MW
316174 AB2-169_C 50/50 1.71 MW 1.71 MW
925122 AB2-169 E 50/50 9.41 MW 9.41 MW
932631 AC2-084 C 50/50 0.79 MW 0.79 MW
932632 AC2-084 E 50/50 2.54 MW 2.54 MW
934321 AD1-056 C Adder 3.43 MW 2.92 MW
934322 AD1-056 E Adder 1.86 MW 1.58 MW
934331 AD1-057 C Adder 1.91 MW 1.63 MW
934332 AD1-057 E Adder 1.0 MW 0.85 MW
934501 AD1-074 C 50/50 74.83 MW 74.83 MW
934502 AD1-074 E 50/50 38.09 MW 38.09 MW
934511 AD1-075 C 50/50 18.71 MW 18.71 MW
934512 AD1-075 E 50/50 9.52 MW 9.52 MW
938531 AE1-072 C Adder -13.61 MW -11.57 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.91 MW 6.91 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 4.69 MW 4.69 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 21.64 MW 21.64 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.4 MW 0.4 MW
NY PJM->LTFIMP_NY CLTF 0.18 MW 0.18 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 0.14 MW 0.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.0 MW 3.0 MW
TVA LTFEXP_TVA->PJM CLTF 1.25 MW 1.25 MW
MEC LTFEXP_MEC->PJM CLTF 0.84 MW 0.84 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.6 MW 1.6 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.52 MW 2.52 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.43 MW 1.43 MW

Details for 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line l/o DVP_P4-2: 246T247_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 121.24 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1006.27 MVA
MW Contribution: 12.81 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 126.89 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1053.22 MVA
MW Contribution: 13.04 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.12 MW 1.12 MW
961672 AG1-007 E 50/50 0.63 MW 0.63 MW
961941 AG1-037 C 50/50 0.68 MW 0.68 MW
961942 AG1-037 E 50/50 0.45 MW 0.45 MW
962331 AG1-082 C 50/50 2.71 MW 2.71 MW
962332 AG1-082 E 50/50 1.8 MW 1.8 MW
966801 AG1-551 C 50/50 2.31 MW 2.31 MW
966802 AG1-551 E 50/50 1.22 MW 1.22 MW
966811 AG1-552 C 50/50 3.53 MW 3.53 MW
966812 AG1-552 E 50/50 1.68 MW 1.68 MW
965291 AG1-394 C 50/50 0.92 MW 0.92 MW
965292 AG1-394 E 50/50 1.69 MW 1.69 MW
966621 AG1-532 C 50/50 3.43 MW 3.43 MW
966622 AG1-532 E 50/50 2.29 MW 2.29 MW
313506 AB1-173 C OP 50/50 2.38 MW 2.38 MW
314541 3WATKINS Adder 0.48 MW 0.41 MW
314572 3EMPORIA 50/50 1.02 MW 1.02 MW
314704 3LAWRENC 50/50 0.58 MW 0.58 MW
315126 1ROARAP2 50/50 2.38 MW 2.38 MW
315128 1ROARAP4 50/50 2.25 MW 2.25 MW
315131 1EDGECMA 50/50 18.85 MW 18.85 MW
315136 1ROSEMG1 50/50 4.35 MW 4.35 MW
315137 1ROSEMS1 50/50 2.69 MW 2.69 MW
315138 1ROSEMG2 50/50 2.04 MW 2.04 MW
315139 1GASTONA 50/50 6.82 MW 6.82 MW
918492 AA1-063AE OP 50/50 5.96 MW 5.96 MW
918532 AA1-067 E 50/50 0.81 MW 0.81 MW
919692 AA2-053 E OP 50/50 7.01 MW 7.01 MW
920042 AA2-088 E OP 50/50 10.85 MW 10.85 MW
925785 AC1-054 E 50/50 3.73 MW 3.73 MW
927146 AC1-208 E 50/50 6.7 MW 6.7 MW
934521 AD1-076 C 50/50 11.67 MW 11.67 MW
934522 AD1-076 E 50/50 5.95 MW 5.95 MW
943171 AE2-346 C 50/50 0.3 MW 0.3 MW
943172 AE2-346 E 50/50 0.81 MW 0.81 MW
960081 AF2-299 C 50/50 4.58 MW 4.58 MW
960082 AF2-299 E 50/50 3.05 MW 3.05 MW
315601 1CONETOE2SOL 50/50 1.47 MW 1.47 MW
315606 3AA2-053SOLA 50/50 2.5 MW 2.5 MW
316129 AC1-054 C 50/50 1.32 MW 1.32 MW
316140 AB2-099 C 50/50 0.13 MW 0.13 MW
316141 AB2-099 E 50/50 0.34 MW 0.34 MW
900672 V4-068 E 50/50 0.42 MW 0.42 MW
917342 Z2-044 E 50/50 1.03 MW 1.03 MW
922923 AB1-081 E OP 50/50 4.48 MW 4.48 MW
923263 AB1-132 E OP 50/50 13.65 MW 13.65 MW
923573 AB1-173 E OP 50/50 6.93 MW 6.93 MW
940491 AE2-034 C 50/50 0.91 MW 0.91 MW
940492 AE2-034 E 50/50 2.42 MW 2.42 MW
946281 AF1-292 C 50/50 3.79 MW 3.79 MW
946282 AF1-292 E 50/50 2.53 MW 2.53 MW
957521 AF2-046 C 50/50 17.14 MW 17.14 MW
957522 AF2-046 E 50/50 8.66 MW 8.66 MW
957861 AF2-080 C 50/50 8.87 MW 8.87 MW
957862 AF2-080 E 50/50 3.93 MW 3.93 MW
916042 Z1-036 E Adder 16.14 MW 13.72 MW
315141 1GASTONB 50/50 6.82 MW 6.82 MW
315292 1DOMTR78 50/50 1.35 MW 1.35 MW
315607 3AA1-063SOLA 50/50 2.06 MW 2.06 MW
315608 3AA2-088SOLA 50/50 1.09 MW 1.09 MW
917512 Z2-088 E OP1 50/50 5.75 MW 5.75 MW
926071 AC1-086 C 50/50 46.9 MW 46.9 MW
926072 AC1-086 E 50/50 21.35 MW 21.35 MW
927021 AC1-189 C 50/50 9.77 MW 9.77 MW
927022 AC1-189 E 50/50 4.87 MW 4.87 MW
933981 AD1-022 C 50/50 9.31 MW 9.31 MW
933982 AD1-022 E 50/50 5.07 MW 5.07 MW
962572 AG1-106 E 50/50 2.65 MW 2.65 MW
961681 AG1-008 C 50/50 17.14 MW 17.14 MW
961682 AG1-008 E 50/50 8.66 MW 8.66 MW
962571 AG1-106 C 50/50 6.07 MW 6.07 MW
314594 6PLYMOUTH TP 50/50 0.3 MW 0.3 MW
316005 AA1-067 C 50/50 0.31 MW 0.31 MW
316011 AB1-132 C OP 50/50 5.21 MW 5.21 MW
316023 AB2-100 C2 50/50 2.91 MW 2.91 MW
316049 AB1-081 C OP 50/50 1.71 MW 1.71 MW
316210 AC1-098 C 50/50 1.53 MW 1.53 MW
316212 AC1-099 C 50/50 0.51 MW 0.51 MW
316263 AC1-034 C 50/50 8.0 MW 8.0 MW
316274 AC1-208 C 50/50 15.1 MW 15.1 MW
316317 KELFORD C 50/50 0.53 MW 0.53 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.36 MW 0.36 MW
316365 AB2-100 C1 50/50 2.91 MW 2.91 MW
917332 KELFORD E 50/50 2.42 MW 2.42 MW
924516 AB2-100 E1 50/50 8.77 MW 8.77 MW
924517 AB2-100 E2 50/50 8.77 MW 8.77 MW
925595 AC1-034 E 50/50 6.04 MW 6.04 MW
926206 AC1-098 E 50/50 5.92 MW 5.92 MW
926214 AC1-099 E 50/50 1.96 MW 1.96 MW
315602 1HOLLOMANSOL 50/50 2.52 MW 2.52 MW
918512 AA1-065 E OP 50/50 7.58 MW 7.58 MW
316327 AA2-057 C 50/50 2.21 MW 2.21 MW
919710 AA2-057 E 50/50 6.73 MW 6.73 MW
315614 AA2-178 C 50/50 1.23 MW 1.23 MW
920692 AA2-178 E 50/50 3.23 MW 3.23 MW
316181 AB2-040 GEN 50/50 2.68 MW 2.68 MW
923994 AB2-040_E 50/50 12.99 MW 12.99 MW
316359 AB2-059 C OP 50/50 2.02 MW 2.02 MW
924152 AB2-059 E OP 50/50 6.37 MW 6.37 MW
316174 AB2-169_C 50/50 1.09 MW 1.09 MW
925122 AB2-169 E 50/50 5.97 MW 5.97 MW
316087 AB2-174 C 50/50 2.61 MW 2.61 MW
316088 AB2-174 E 50/50 14.45 MW 14.45 MW
313764 3SOCKMAN 50/50 1.35 MW 1.35 MW
932631 AC2-084 C 50/50 1.63 MW 1.63 MW
932632 AC2-084 E 50/50 5.23 MW 5.23 MW
934321 AD1-056 C 50/50 10.28 MW 10.28 MW
934322 AD1-056 E 50/50 5.58 MW 5.58 MW
934331 AD1-057 C 50/50 5.73 MW 5.73 MW
934332 AD1-057 E 50/50 2.99 MW 2.99 MW
934501 AD1-074 C 50/50 32.14 MW 32.14 MW
934502 AD1-074 E 50/50 16.36 MW 16.36 MW
934511 AD1-075 C 50/50 8.04 MW 8.04 MW
934512 AD1-075 E 50/50 4.09 MW 4.09 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.57 MW 11.57 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.02 MW 8.02 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 37.33 MW 37.33 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.79 MW 0.79 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.44 MW 0.44 MW
WEC LTFEXP_WEC->PJM CLTF 0.24 MW 0.24 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.1 MW 5.1 MW
TVA LTFEXP_TVA->PJM CLTF 2.15 MW 2.15 MW
MEC LTFEXP_MEC->PJM CLTF 1.42 MW 1.42 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.76 MW 2.76 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.05 MW 5.05 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.43 MW 2.43 MW

Details for 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line l/o DVP_P4-2: 24662_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P4-2: 24662_SRT-A
CONTINGENCY 'DVP_P4-2: 24662_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314568 TO BUS 314569 CKT 1   /*3EARLEYS     115.0 - 6EARLEYS     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 116.16 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 964.12 MVA
MW Contribution: 12.36 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P4-2: 24662_SRT-A
CONTINGENCY 'DVP_P4-2: 24662_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314568 TO BUS 314569 CKT 1   /*3EARLEYS     115.0 - 6EARLEYS     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 123.11 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1021.8 MVA
MW Contribution: 12.55 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.09 MW 1.09 MW
961672 AG1-007 E 50/50 0.62 MW 0.62 MW
961941 AG1-037 C 50/50 0.66 MW 0.66 MW
961942 AG1-037 E 50/50 0.44 MW 0.44 MW
962331 AG1-082 C 50/50 2.63 MW 2.63 MW
962332 AG1-082 E 50/50 1.75 MW 1.75 MW
966801 AG1-551 C 50/50 2.19 MW 2.19 MW
966802 AG1-551 E 50/50 1.15 MW 1.15 MW
966811 AG1-552 C 50/50 3.48 MW 3.48 MW
966812 AG1-552 E 50/50 1.66 MW 1.66 MW
965291 AG1-394 C 50/50 0.91 MW 0.91 MW
965292 AG1-394 E 50/50 1.68 MW 1.68 MW
966621 AG1-532 C 50/50 3.41 MW 3.41 MW
966622 AG1-532 E 50/50 2.28 MW 2.28 MW
313506 AB1-173 C OP 50/50 2.36 MW 2.36 MW
314541 3WATKINS Adder 0.48 MW 0.41 MW
314572 3EMPORIA 50/50 1.01 MW 1.01 MW
314704 3LAWRENC 50/50 0.57 MW 0.57 MW
315126 1ROARAP2 50/50 2.35 MW 2.35 MW
315128 1ROARAP4 50/50 2.22 MW 2.22 MW
315131 1EDGECMA 50/50 18.43 MW 18.43 MW
315136 1ROSEMG1 50/50 4.3 MW 4.3 MW
315137 1ROSEMS1 50/50 2.66 MW 2.66 MW
315138 1ROSEMG2 50/50 2.01 MW 2.01 MW
315139 1GASTONA 50/50 6.74 MW 6.74 MW
918492 AA1-063AE OP 50/50 5.9 MW 5.9 MW
918532 AA1-067 E 50/50 0.78 MW 0.78 MW
919692 AA2-053 E OP 50/50 6.9 MW 6.9 MW
920042 AA2-088 E OP 50/50 10.78 MW 10.78 MW
925785 AC1-054 E 50/50 3.69 MW 3.69 MW
927146 AC1-208 E 50/50 6.59 MW 6.59 MW
934521 AD1-076 C 50/50 10.32 MW 10.32 MW
934522 AD1-076 E 50/50 5.26 MW 5.26 MW
943171 AE2-346 C 50/50 0.29 MW 0.29 MW
943172 AE2-346 E 50/50 0.79 MW 0.79 MW
960081 AF2-299 C 50/50 4.55 MW 4.55 MW
960082 AF2-299 E 50/50 3.03 MW 3.03 MW
315601 1CONETOE2SOL 50/50 1.42 MW 1.42 MW
315606 3AA2-053SOLA 50/50 2.46 MW 2.46 MW
316129 AC1-054 C 50/50 1.31 MW 1.31 MW
316140 AB2-099 C 50/50 0.13 MW 0.13 MW
316141 AB2-099 E 50/50 0.33 MW 0.33 MW
900672 V4-068 E 50/50 0.41 MW 0.41 MW
917342 Z2-044 E 50/50 1.01 MW 1.01 MW
922923 AB1-081 E OP 50/50 4.37 MW 4.37 MW
923263 AB1-132 E OP 50/50 13.49 MW 13.49 MW
923573 AB1-173 E OP 50/50 6.87 MW 6.87 MW
940492 AE2-034 E Adder 2.01 MW 1.71 MW
946281 AF1-292 C 50/50 3.77 MW 3.77 MW
946282 AF1-292 E 50/50 2.51 MW 2.51 MW
957521 AF2-046 C 50/50 16.81 MW 16.81 MW
957522 AF2-046 E 50/50 8.5 MW 8.5 MW
957861 AF2-080 C 50/50 8.56 MW 8.56 MW
957862 AF2-080 E 50/50 3.79 MW 3.79 MW
314539 3UNCAMP Adder 3.38 MW 2.87 MW
315141 1GASTONB 50/50 6.74 MW 6.74 MW
315292 1DOMTR78 50/50 1.22 MW 1.22 MW
315607 3AA1-063SOLA 50/50 2.03 MW 2.03 MW
315608 3AA2-088SOLA 50/50 1.08 MW 1.08 MW
917512 Z2-088 E OP1 50/50 5.57 MW 5.57 MW
926071 AC1-086 C 50/50 46.37 MW 46.37 MW
926072 AC1-086 E 50/50 21.1 MW 21.1 MW
927021 AC1-189 C 50/50 9.43 MW 9.43 MW
927022 AC1-189 E 50/50 4.7 MW 4.7 MW
933981 AD1-022 C 50/50 8.46 MW 8.46 MW
933982 AD1-022 E 50/50 4.61 MW 4.61 MW
962572 AG1-106 E 50/50 2.62 MW 2.62 MW
961681 AG1-008 C 50/50 16.81 MW 16.81 MW
961682 AG1-008 E 50/50 8.5 MW 8.5 MW
962571 AG1-106 C 50/50 6.0 MW 6.0 MW
314594 6PLYMOUTH TP 50/50 0.26 MW 0.26 MW
316005 AA1-067 C 50/50 0.29 MW 0.29 MW
316011 AB1-132 C OP 50/50 5.14 MW 5.14 MW
316023 AB2-100 C2 50/50 2.9 MW 2.9 MW
316049 AB1-081 C OP 50/50 1.66 MW 1.66 MW
316210 AC1-098 C 50/50 1.5 MW 1.5 MW
316212 AC1-099 C 50/50 0.5 MW 0.5 MW
316263 AC1-034 C 50/50 7.8 MW 7.8 MW
316274 AC1-208 C 50/50 14.84 MW 14.84 MW
316317 KELFORD C 50/50 0.51 MW 0.51 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.36 MW 0.36 MW
316365 AB2-100 C1 50/50 2.9 MW 2.9 MW
917332 KELFORD E 50/50 2.36 MW 2.36 MW
924516 AB2-100 E1 50/50 8.73 MW 8.73 MW
924517 AB2-100 E2 50/50 8.73 MW 8.73 MW
925595 AC1-034 E 50/50 5.88 MW 5.88 MW
926206 AC1-098 E 50/50 5.8 MW 5.8 MW
926214 AC1-099 E 50/50 1.92 MW 1.92 MW
315602 1HOLLOMANSOL 50/50 2.42 MW 2.42 MW
918512 AA1-065 E OP 50/50 7.26 MW 7.26 MW
316327 AA2-057 C 50/50 2.17 MW 2.17 MW
919710 AA2-057 E 50/50 6.62 MW 6.62 MW
920692 AA2-178 E Adder 2.68 MW 2.28 MW
316181 AB2-040 GEN 50/50 2.66 MW 2.66 MW
923994 AB2-040_E 50/50 12.89 MW 12.89 MW
316359 AB2-059 C OP 50/50 1.97 MW 1.97 MW
924152 AB2-059 E OP 50/50 6.22 MW 6.22 MW
316174 AB2-169_C 50/50 1.0 MW 1.0 MW
925122 AB2-169 E 50/50 5.5 MW 5.5 MW
316087 AB2-174 C 50/50 2.59 MW 2.59 MW
316088 AB2-174 E 50/50 14.34 MW 14.34 MW
313764 3SOCKMAN 50/50 1.34 MW 1.34 MW
932631 AC2-084 C 50/50 1.6 MW 1.6 MW
932632 AC2-084 E 50/50 5.13 MW 5.13 MW
934321 AD1-056 C 50/50 10.12 MW 10.12 MW
934322 AD1-056 E 50/50 5.49 MW 5.49 MW
934331 AD1-057 C 50/50 5.64 MW 5.64 MW
934332 AD1-057 E 50/50 2.94 MW 2.94 MW
934501 AD1-074 C 50/50 28.43 MW 28.43 MW
934502 AD1-074 E 50/50 14.47 MW 14.47 MW
934511 AD1-075 C 50/50 7.11 MW 7.11 MW
934512 AD1-075 E 50/50 3.62 MW 3.62 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.24 MW 11.24 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.8 MW 7.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 36.27 MW 36.27 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.77 MW 0.77 MW
NY PJM->LTFIMP_NY CLTF 0.35 MW 0.35 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.43 MW 0.43 MW
WEC LTFEXP_WEC->PJM CLTF 0.23 MW 0.23 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.95 MW 4.95 MW
TVA LTFEXP_TVA->PJM CLTF 2.09 MW 2.09 MW
MEC LTFEXP_MEC->PJM CLTF 1.38 MW 1.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.68 MW 2.68 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.08 MW 0.08 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.92 MW 4.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.36 MW 2.36 MW

Details for 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line l/o DVP_P4-2: 562T563_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 115.93 %
Rating: 1204.0 MVA
Rating Type: C
MVA to Mitigate: 1395.79 MVA
MW Contribution: 6.01 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 120.42 %
Rating: 1204.0 MVA
Rating Type: C
MVA to Mitigate: 1449.91 MVA
MW Contribution: 5.9 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.54 MW 0.46 MW
961672 AG1-007 E Adder 0.31 MW 0.26 MW
961791 AG1-021 C Adder 0.85 MW 0.73 MW
961792 AG1-021 E Adder 0.73 MW 0.62 MW
961941 AG1-037 C Adder 0.25 MW 0.21 MW
961942 AG1-037 E Adder 0.17 MW 0.14 MW
962331 AG1-082 C Adder 0.99 MW 0.84 MW
962332 AG1-082 E Adder 0.66 MW 0.56 MW
963041 AG1-153 C 50/50 4.03 MW 4.03 MW
963042 AG1-153 E 50/50 6.04 MW 6.04 MW
963171 AG1-166 C Adder 0.47 MW 0.4 MW
963172 AG1-166 E Adder 1.11 MW 0.94 MW
963181 AG1-167 C Adder 0.36 MW 0.3 MW
963182 AG1-167 E Adder 0.83 MW 0.71 MW
963191 AG1-168 C Adder 0.36 MW 0.3 MW
963192 AG1-168 E Adder 0.83 MW 0.71 MW
964791 AG1-342 C Adder 2.05 MW 1.74 MW
964792 AG1-342 E Adder 1.37 MW 1.16 MW
966801 AG1-551 C Adder 1.03 MW 0.88 MW
966802 AG1-551 E Adder 0.54 MW 0.46 MW
966811 AG1-552 C 50/50 1.37 MW 1.37 MW
966812 AG1-552 E 50/50 0.65 MW 0.65 MW
965291 AG1-394 C Adder 0.41 MW 0.35 MW
965292 AG1-394 E Adder 0.75 MW 0.64 MW
966621 AG1-532 C 50/50 1.17 MW 1.17 MW
966622 AG1-532 E 50/50 0.78 MW 0.78 MW
313506 AB1-173 C OP 50/50 0.85 MW 0.85 MW
313853 3PONTONDP Adder 0.32 MW 0.27 MW
314541 3WATKINS Adder 0.26 MW 0.23 MW
314572 3EMPORIA 50/50 0.35 MW 0.35 MW
314704 3LAWRENC 50/50 0.24 MW 0.24 MW
314713 3PAMPLIN Adder 0.46 MW 0.39 MW
315126 1ROARAP2 50/50 0.92 MW 0.92 MW
315128 1ROARAP4 50/50 0.87 MW 0.87 MW
315131 1EDGECMA Adder 9.36 MW 7.96 MW
315136 1ROSEMG1 50/50 1.5 MW 1.5 MW
315137 1ROSEMS1 50/50 0.93 MW 0.93 MW
315138 1ROSEMG2 50/50 0.7 MW 0.7 MW
315139 1GASTONA 50/50 2.29 MW 2.29 MW
918492 AA1-063AE OP Adder 2.41 MW 2.05 MW
918532 AA1-067 E Adder 0.37 MW 0.31 MW
919692 AA2-053 E OP Adder 2.69 MW 2.28 MW
920042 AA2-088 E OP Adder 4.92 MW 4.18 MW
925785 AC1-054 E Adder 2.17 MW 1.85 MW
926274 AC1-105 E Adder 1.53 MW 1.3 MW
927146 AC1-208 E Adder 2.55 MW 2.16 MW
934521 AD1-076 C Adder 4.78 MW 4.06 MW
934522 AD1-076 E Adder 2.43 MW 2.07 MW
943172 AE2-346 E Adder 0.3 MW 0.25 MW
943902 AF1-058 E Adder 0.73 MW 0.62 MW
944011 AF1-069 C 50/50 9.47 MW 9.47 MW
944012 AF1-069 E 50/50 3.68 MW 3.68 MW
959311 AF2-222 C Adder 9.15 MW 7.78 MW
959312 AF2-222 E Adder 6.13 MW 5.21 MW
960061 AF2-297 C Adder 4.36 MW 3.71 MW
960062 AF2-297 E Adder 2.91 MW 2.47 MW
960081 AF2-299 C 50/50 1.56 MW 1.56 MW
960082 AF2-299 E 50/50 1.04 MW 1.04 MW
316141 AB2-099 E Adder 0.12 MW 0.11 MW
900672 V4-068 E Adder 0.17 MW 0.15 MW
917342 Z2-044 E Adder 0.39 MW 0.33 MW
922923 AB1-081 E OP Adder 2.19 MW 1.86 MW
923263 AB1-132 E OP 50/50 4.59 MW 4.59 MW
923573 AB1-173 E OP 50/50 2.48 MW 2.48 MW
924162 AB2-060 E OP Adder 2.56 MW 2.18 MW
924302 AB2-077 E O1 Adder 0.8 MW 0.68 MW
924312 AB2-078 E O1 Adder 0.8 MW 0.68 MW
924322 AB2-079 E O1 Adder 0.8 MW 0.68 MW
925612 AC1-036 E Adder 0.48 MW 0.41 MW
938371 AE1-056 C Adder 3.01 MW 2.56 MW
938372 AE1-056 E Adder 1.64 MW 1.4 MW
939181 AE1-148 C Adder 5.45 MW 4.63 MW
939182 AE1-148 E Adder 3.63 MW 3.09 MW
941031 AE2-094 C 50/50 28.98 MW 28.98 MW
941032 AE2-094 E 50/50 12.98 MW 12.98 MW
946281 AF1-292 C 50/50 1.29 MW 1.29 MW
946282 AF1-292 E 50/50 0.86 MW 0.86 MW
946301 AF1-294 C Adder 1.76 MW 1.49 MW
946302 AF1-294 E Adder 1.49 MW 1.26 MW
957481 AF2-042 C 50/50 34.73 MW 34.73 MW
957482 AF2-042 E 50/50 23.15 MW 23.15 MW
957521 AF2-046 C Adder 6.88 MW 5.84 MW
957522 AF2-046 E Adder 3.48 MW 2.95 MW
957861 AF2-080 C Adder 4.17 MW 3.54 MW
957862 AF2-080 E Adder 1.85 MW 1.57 MW
958211 AF2-115 C Adder 1.07 MW 0.91 MW
958212 AF2-115 E Adder 0.91 MW 0.77 MW
314331 6POE Adder 0.5 MW 0.43 MW
315102 1BRUNSWICKG1 50/50 5.94 MW 5.94 MW
315103 1BRUNSWICKG2 50/50 5.94 MW 5.94 MW
315104 1BRUNSWICKG3 50/50 5.94 MW 5.94 MW
315105 1BRUNSWICKS1 50/50 12.35 MW 12.35 MW
315141 1GASTONB 50/50 2.29 MW 2.29 MW
315241 1Z1-086 GT1 50/50 7.62 MW 7.62 MW
315242 1Z1-086 GT2 50/50 7.61 MW 7.61 MW
315243 1Z1-086 GT3 50/50 7.61 MW 7.61 MW
315244 1Z1-086 ST 50/50 13.26 MW 13.26 MW
923852 AB2-025 E 50/50 1.34 MW 1.34 MW
942001 AE2-212 C Adder -3.8 MW -3.23 MW
314722 3TWITTYS Adder 0.53 MW 0.45 MW
917512 Z2-088 E OP1 Adder 2.74 MW 2.33 MW
926071 AC1-086 C 50/50 15.79 MW 15.79 MW
926072 AC1-086 E 50/50 7.19 MW 7.19 MW
927021 AC1-189 C Adder 4.59 MW 3.9 MW
927022 AC1-189 E Adder 2.28 MW 1.94 MW
936261 AD2-033 C Adder 7.13 MW 6.06 MW
936262 AD2-033 E Adder 4.75 MW 4.04 MW
934621 AD1-088 C Adder 7.64 MW 6.49 MW
934622 AD1-088 E Adder 3.6 MW 3.06 MW
939411 AE1-173 C Adder 49.14 MW 41.77 MW
939412 AE1-173 E Adder 32.76 MW 27.85 MW
933981 AD1-022 C Adder 3.61 MW 3.07 MW
933982 AD1-022 E Adder 1.96 MW 1.67 MW
962572 AG1-106 E 50/50 0.89 MW 0.89 MW
961681 AG1-008 C Adder 6.88 MW 5.84 MW
961682 AG1-008 E Adder 3.48 MW 2.95 MW
962571 AG1-106 C 50/50 2.04 MW 2.04 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
316011 AB1-132 C OP 50/50 1.75 MW 1.75 MW
316023 AB2-100 C2 50/50 0.89 MW 0.89 MW
316240 AF1-291 C Adder -1.57 MW -1.33 MW
316263 AC1-034 C Adder 3.92 MW 3.33 MW
316274 AC1-208 C Adder 5.73 MW 4.87 MW
316315 AB2-025 C 50/50 0.47 MW 0.47 MW
316365 AB2-100 C1 50/50 0.89 MW 0.89 MW
917332 KELFORD E Adder 0.88 MW 0.75 MW
924516 AB2-100 E1 50/50 2.67 MW 2.67 MW
924517 AB2-100 E2 50/50 2.67 MW 2.67 MW
925595 AC1-034 E Adder 2.96 MW 2.51 MW
926206 AC1-098 E Adder 2.22 MW 1.89 MW
926214 AC1-099 E Adder 0.73 MW 0.62 MW
927255 AC1-221 E Adder 2.08 MW 1.77 MW
927264 AC1-222 E Adder 2.2 MW 1.87 MW
932763 AC2-100 E Adder 1.41 MW 1.2 MW
918512 AA1-065 E OP Adder 2.62 MW 2.22 MW
919710 AA2-057 E Adder 2.55 MW 2.17 MW
316181 AB2-040 GEN 50/50 0.96 MW 0.96 MW
923994 AB2-040_E 50/50 4.66 MW 4.66 MW
924022 AB2-043 E O1 Adder 3.13 MW 2.66 MW
924152 AB2-059 E OP Adder 3.13 MW 2.66 MW
925122 AB2-169 E Adder 2.58 MW 2.19 MW
316087 AB2-174 C 50/50 0.92 MW 0.92 MW
316088 AB2-174 E 50/50 5.09 MW 5.09 MW
925997 AC1-075 E Adder 1.39 MW 1.18 MW
926024 AC1-080 E Adder 0.46 MW 0.39 MW
962491 AG1-098 C Adder 6.77 MW 5.75 MW
962492 AG1-098 E Adder 4.51 MW 3.84 MW
962561 AG1-105 C Adder 5.18 MW 4.4 MW
962562 AG1-105 E Adder 3.45 MW 2.94 MW
964241 AG1-285 C Adder 7.64 MW 6.5 MW
964242 AG1-285 E Adder 5.09 MW 4.33 MW
313764 3SOCKMAN 50/50 0.5 MW 0.5 MW
932632 AC2-084 E Adder 1.96 MW 1.67 MW
934321 AD1-056 C Adder 4.17 MW 3.54 MW
934322 AD1-056 E Adder 2.26 MW 1.92 MW
934331 AD1-057 C Adder 2.33 MW 1.98 MW
934332 AD1-057 E Adder 1.21 MW 1.03 MW
934501 AD1-074 C Adder 13.15 MW 11.18 MW
934502 AD1-074 E Adder 6.69 MW 5.69 MW
934511 AD1-075 C Adder 3.29 MW 2.79 MW
934512 AD1-075 E Adder 1.67 MW 1.42 MW
934612 AD1-087 E Adder 2.25 MW 1.92 MW
935172 AD1-152 E Adder 3.31 MW 2.82 MW
936161 AD2-022 C Adder 3.86 MW 3.28 MW
936162 AD2-022 E Adder 2.31 MW 1.97 MW
936171 AD2-023 C Adder 2.25 MW 1.91 MW
936172 AD2-023 E Adder 1.22 MW 1.04 MW
937482 AD2-202 E Adder 0.66 MW 0.56 MW
940481 AE2-033 C 50/50 18.17 MW 18.17 MW
940482 AE2-033 E 50/50 12.25 MW 12.25 MW
940541 AE2-040 C 50/50 3.31 MW 3.31 MW
942461 AE2-259 C Adder 3.98 MW 3.38 MW
942462 AE2-259 E Adder 2.65 MW 2.25 MW
944641 AF1-129 C Adder -88.26 MW -75.02 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 17.6 MW 17.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 12.28 MW 12.28 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 54.08 MW 54.08 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.33 MW 1.33 MW
NY PJM->LTFIMP_NY CLTF 0.61 MW 0.61 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.68 MW 0.68 MW
WEC LTFEXP_WEC->PJM CLTF 0.36 MW 0.36 MW
CPLE LTFEXP_CPLE->PJM CLTF 6.61 MW 6.61 MW
TVA LTFEXP_TVA->PJM CLTF 3.3 MW 3.3 MW
MEC LTFEXP_MEC->PJM CLTF 2.17 MW 2.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.22 MW 4.22 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.13 MW 0.13 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 8.48 MW 8.48 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 3.15 MW 3.15 MW

Details for 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line l/o DVP_P4-2: 562T563_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 114.15 %
Rating: 1204.0 MVA
Rating Type: C
MVA to Mitigate: 1374.4 MVA
MW Contribution: 6.01 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 118.63 %
Rating: 1204.0 MVA
Rating Type: C
MVA to Mitigate: 1428.25 MVA
MW Contribution: 5.9 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.54 MW 0.46 MW
961672 AG1-007 E Adder 0.31 MW 0.26 MW
961791 AG1-021 C Adder 0.85 MW 0.73 MW
961792 AG1-021 E Adder 0.73 MW 0.62 MW
961941 AG1-037 C Adder 0.25 MW 0.21 MW
961942 AG1-037 E Adder 0.17 MW 0.14 MW
962331 AG1-082 C Adder 0.99 MW 0.84 MW
962332 AG1-082 E Adder 0.66 MW 0.56 MW
963041 AG1-153 C 50/50 4.03 MW 4.03 MW
963042 AG1-153 E 50/50 6.04 MW 6.04 MW
963171 AG1-166 C Adder 0.47 MW 0.4 MW
963172 AG1-166 E Adder 1.11 MW 0.94 MW
963181 AG1-167 C Adder 0.36 MW 0.3 MW
963182 AG1-167 E Adder 0.83 MW 0.71 MW
963191 AG1-168 C Adder 0.36 MW 0.3 MW
963192 AG1-168 E Adder 0.83 MW 0.71 MW
964791 AG1-342 C Adder 2.05 MW 1.74 MW
964792 AG1-342 E Adder 1.37 MW 1.16 MW
966801 AG1-551 C Adder 1.03 MW 0.88 MW
966802 AG1-551 E Adder 0.54 MW 0.46 MW
966811 AG1-552 C 50/50 1.37 MW 1.37 MW
966812 AG1-552 E 50/50 0.65 MW 0.65 MW
965291 AG1-394 C Adder 0.41 MW 0.35 MW
965292 AG1-394 E Adder 0.75 MW 0.64 MW
966621 AG1-532 C 50/50 1.17 MW 1.17 MW
966622 AG1-532 E 50/50 0.78 MW 0.78 MW
313506 AB1-173 C OP 50/50 0.85 MW 0.85 MW
313853 3PONTONDP Adder 0.32 MW 0.27 MW
314541 3WATKINS Adder 0.26 MW 0.23 MW
314572 3EMPORIA 50/50 0.35 MW 0.35 MW
314704 3LAWRENC 50/50 0.24 MW 0.24 MW
314713 3PAMPLIN Adder 0.46 MW 0.39 MW
315126 1ROARAP2 50/50 0.92 MW 0.92 MW
315128 1ROARAP4 50/50 0.87 MW 0.87 MW
315131 1EDGECMA Adder 9.36 MW 7.96 MW
315136 1ROSEMG1 50/50 1.5 MW 1.5 MW
315137 1ROSEMS1 50/50 0.93 MW 0.93 MW
315138 1ROSEMG2 50/50 0.7 MW 0.7 MW
315139 1GASTONA 50/50 2.29 MW 2.29 MW
918492 AA1-063AE OP Adder 2.41 MW 2.05 MW
918532 AA1-067 E Adder 0.37 MW 0.31 MW
919692 AA2-053 E OP Adder 2.69 MW 2.28 MW
920042 AA2-088 E OP Adder 4.92 MW 4.18 MW
925785 AC1-054 E Adder 2.17 MW 1.85 MW
926274 AC1-105 E Adder 1.53 MW 1.3 MW
927146 AC1-208 E Adder 2.55 MW 2.16 MW
934521 AD1-076 C Adder 4.78 MW 4.06 MW
934522 AD1-076 E Adder 2.43 MW 2.07 MW
943172 AE2-346 E Adder 0.3 MW 0.25 MW
943902 AF1-058 E Adder 0.73 MW 0.62 MW
944011 AF1-069 C 50/50 9.47 MW 9.47 MW
944012 AF1-069 E 50/50 3.68 MW 3.68 MW
959311 AF2-222 C Adder 9.15 MW 7.78 MW
959312 AF2-222 E Adder 6.13 MW 5.21 MW
960061 AF2-297 C Adder 4.36 MW 3.71 MW
960062 AF2-297 E Adder 2.91 MW 2.47 MW
960081 AF2-299 C 50/50 1.56 MW 1.56 MW
960082 AF2-299 E 50/50 1.04 MW 1.04 MW
316141 AB2-099 E Adder 0.12 MW 0.11 MW
900672 V4-068 E Adder 0.17 MW 0.15 MW
917342 Z2-044 E Adder 0.39 MW 0.33 MW
922923 AB1-081 E OP Adder 2.19 MW 1.86 MW
923263 AB1-132 E OP 50/50 4.59 MW 4.59 MW
923573 AB1-173 E OP 50/50 2.48 MW 2.48 MW
924162 AB2-060 E OP Adder 2.56 MW 2.18 MW
924302 AB2-077 E O1 Adder 0.8 MW 0.68 MW
924312 AB2-078 E O1 Adder 0.8 MW 0.68 MW
924322 AB2-079 E O1 Adder 0.8 MW 0.68 MW
925612 AC1-036 E Adder 0.48 MW 0.41 MW
938371 AE1-056 C Adder 3.01 MW 2.56 MW
938372 AE1-056 E Adder 1.64 MW 1.4 MW
939181 AE1-148 C Adder 5.45 MW 4.63 MW
939182 AE1-148 E Adder 3.63 MW 3.09 MW
941031 AE2-094 C 50/50 28.98 MW 28.98 MW
941032 AE2-094 E 50/50 12.98 MW 12.98 MW
946281 AF1-292 C 50/50 1.29 MW 1.29 MW
946282 AF1-292 E 50/50 0.86 MW 0.86 MW
946301 AF1-294 C Adder 1.76 MW 1.49 MW
946302 AF1-294 E Adder 1.49 MW 1.26 MW
957481 AF2-042 C 50/50 34.73 MW 34.73 MW
957482 AF2-042 E 50/50 23.15 MW 23.15 MW
957521 AF2-046 C Adder 6.88 MW 5.84 MW
957522 AF2-046 E Adder 3.48 MW 2.95 MW
957861 AF2-080 C Adder 4.17 MW 3.54 MW
957862 AF2-080 E Adder 1.85 MW 1.57 MW
958211 AF2-115 C Adder 1.07 MW 0.91 MW
958212 AF2-115 E Adder 0.91 MW 0.77 MW
314331 6POE Adder 0.5 MW 0.43 MW
315102 1BRUNSWICKG1 50/50 5.94 MW 5.94 MW
315103 1BRUNSWICKG2 50/50 5.94 MW 5.94 MW
315104 1BRUNSWICKG3 50/50 5.94 MW 5.94 MW
315105 1BRUNSWICKS1 50/50 12.35 MW 12.35 MW
315141 1GASTONB 50/50 2.29 MW 2.29 MW
315241 1Z1-086 GT1 50/50 7.62 MW 7.62 MW
315242 1Z1-086 GT2 50/50 7.61 MW 7.61 MW
315243 1Z1-086 GT3 50/50 7.61 MW 7.61 MW
315244 1Z1-086 ST 50/50 13.26 MW 13.26 MW
923852 AB2-025 E 50/50 1.34 MW 1.34 MW
942001 AE2-212 C Adder -3.8 MW -3.23 MW
314722 3TWITTYS Adder 0.53 MW 0.45 MW
917512 Z2-088 E OP1 Adder 2.74 MW 2.33 MW
926071 AC1-086 C 50/50 15.79 MW 15.79 MW
926072 AC1-086 E 50/50 7.19 MW 7.19 MW
927021 AC1-189 C Adder 4.59 MW 3.9 MW
927022 AC1-189 E Adder 2.28 MW 1.94 MW
936261 AD2-033 C Adder 7.13 MW 6.06 MW
936262 AD2-033 E Adder 4.75 MW 4.04 MW
934621 AD1-088 C Adder 7.64 MW 6.49 MW
934622 AD1-088 E Adder 3.6 MW 3.06 MW
939411 AE1-173 C Adder 49.14 MW 41.77 MW
939412 AE1-173 E Adder 32.76 MW 27.85 MW
933981 AD1-022 C Adder 3.61 MW 3.07 MW
933982 AD1-022 E Adder 1.96 MW 1.67 MW
962572 AG1-106 E 50/50 0.89 MW 0.89 MW
961681 AG1-008 C Adder 6.88 MW 5.84 MW
961682 AG1-008 E Adder 3.48 MW 2.95 MW
962571 AG1-106 C 50/50 2.04 MW 2.04 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
316011 AB1-132 C OP 50/50 1.75 MW 1.75 MW
316023 AB2-100 C2 50/50 0.89 MW 0.89 MW
316240 AF1-291 C Adder -1.57 MW -1.33 MW
316263 AC1-034 C Adder 3.92 MW 3.33 MW
316274 AC1-208 C Adder 5.73 MW 4.87 MW
316315 AB2-025 C 50/50 0.47 MW 0.47 MW
316365 AB2-100 C1 50/50 0.89 MW 0.89 MW
917332 KELFORD E Adder 0.88 MW 0.75 MW
924516 AB2-100 E1 50/50 2.67 MW 2.67 MW
924517 AB2-100 E2 50/50 2.67 MW 2.67 MW
925595 AC1-034 E Adder 2.96 MW 2.51 MW
926206 AC1-098 E Adder 2.22 MW 1.89 MW
926214 AC1-099 E Adder 0.73 MW 0.62 MW
927255 AC1-221 E Adder 2.08 MW 1.77 MW
927264 AC1-222 E Adder 2.2 MW 1.87 MW
932763 AC2-100 E Adder 1.41 MW 1.2 MW
918512 AA1-065 E OP Adder 2.62 MW 2.22 MW
919710 AA2-057 E Adder 2.55 MW 2.17 MW
316181 AB2-040 GEN 50/50 0.96 MW 0.96 MW
923994 AB2-040_E 50/50 4.66 MW 4.66 MW
924022 AB2-043 E O1 Adder 3.13 MW 2.66 MW
924152 AB2-059 E OP Adder 3.13 MW 2.66 MW
925122 AB2-169 E Adder 2.58 MW 2.19 MW
316087 AB2-174 C 50/50 0.92 MW 0.92 MW
316088 AB2-174 E 50/50 5.09 MW 5.09 MW
925997 AC1-075 E Adder 1.39 MW 1.18 MW
926024 AC1-080 E Adder 0.46 MW 0.39 MW
962491 AG1-098 C Adder 6.77 MW 5.75 MW
962492 AG1-098 E Adder 4.51 MW 3.84 MW
962561 AG1-105 C Adder 5.18 MW 4.4 MW
962562 AG1-105 E Adder 3.45 MW 2.94 MW
964241 AG1-285 C Adder 7.64 MW 6.5 MW
964242 AG1-285 E Adder 5.09 MW 4.33 MW
313764 3SOCKMAN 50/50 0.5 MW 0.5 MW
932632 AC2-084 E Adder 1.96 MW 1.67 MW
934321 AD1-056 C Adder 4.17 MW 3.54 MW
934322 AD1-056 E Adder 2.26 MW 1.92 MW
934331 AD1-057 C Adder 2.33 MW 1.98 MW
934332 AD1-057 E Adder 1.21 MW 1.03 MW
934501 AD1-074 C Adder 13.15 MW 11.18 MW
934502 AD1-074 E Adder 6.69 MW 5.69 MW
934511 AD1-075 C Adder 3.29 MW 2.79 MW
934512 AD1-075 E Adder 1.67 MW 1.42 MW
934612 AD1-087 E Adder 2.25 MW 1.92 MW
935172 AD1-152 E Adder 3.31 MW 2.82 MW
936161 AD2-022 C Adder 3.86 MW 3.28 MW
936162 AD2-022 E Adder 2.31 MW 1.97 MW
936171 AD2-023 C Adder 2.25 MW 1.91 MW
936172 AD2-023 E Adder 1.22 MW 1.04 MW
937482 AD2-202 E Adder 0.66 MW 0.56 MW
940481 AE2-033 C 50/50 18.17 MW 18.17 MW
940482 AE2-033 E 50/50 12.25 MW 12.25 MW
940541 AE2-040 C 50/50 3.31 MW 3.31 MW
942461 AE2-259 C Adder 3.98 MW 3.38 MW
942462 AE2-259 E Adder 2.65 MW 2.25 MW
944641 AF1-129 C Adder -88.26 MW -75.02 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 17.6 MW 17.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 12.28 MW 12.28 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 54.08 MW 54.08 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.33 MW 1.33 MW
NY PJM->LTFIMP_NY CLTF 0.61 MW 0.61 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.68 MW 0.68 MW
WEC LTFEXP_WEC->PJM CLTF 0.36 MW 0.36 MW
CPLE LTFEXP_CPLE->PJM CLTF 6.61 MW 6.61 MW
TVA LTFEXP_TVA->PJM CLTF 3.3 MW 3.3 MW
MEC LTFEXP_MEC->PJM CLTF 2.17 MW 2.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.22 MW 4.22 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.13 MW 0.13 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 8.48 MW 8.48 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 3.15 MW 3.15 MW

Details for 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line l/o DVP_P4-2: 557T574_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
DVP_P4-2: 557T574_SRT-S
CONTINGENCY 'DVP_P4-2: 557T574_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 107.33 %
Rating: 3940.0 MVA
Rating Type: C
MVA to Mitigate: 4228.89 MVA
MW Contribution: 10.89 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
DVP_P4-2: 557T574_SRT-S
CONTINGENCY 'DVP_P4-2: 557T574_SRT-S'
 OPEN BRANCH FROM BUS 314903 TO BUS 314908 CKT 1                /*8CHCKAHM     500.0 - 8ELMONT      500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 118.29 %
Rating: 3940.0 MVA
Rating Type: C
MVA to Mitigate: 4660.82 MVA
MW Contribution: 16.07 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961941 AG1-037 C Adder 0.75 MW 0.63 MW
961942 AG1-037 E Adder 0.5 MW 0.42 MW
962331 AG1-082 C Adder 2.98 MW 2.54 MW
962332 AG1-082 E Adder 1.99 MW 1.69 MW
963041 AG1-153 C 50/50 9.95 MW 9.95 MW
963042 AG1-153 E 50/50 14.93 MW 14.93 MW
964791 AG1-342 C Adder 4.89 MW 4.16 MW
964792 AG1-342 E Adder 3.26 MW 2.77 MW
966801 AG1-551 C Adder 3.05 MW 2.59 MW
966802 AG1-551 E Adder 1.6 MW 1.36 MW
966811 AG1-552 C Adder 3.01 MW 2.56 MW
966812 AG1-552 E Adder 1.43 MW 1.22 MW
965291 AG1-394 C Adder 1.26 MW 1.07 MW
965292 AG1-394 E Adder 2.32 MW 1.97 MW
966621 AG1-532 C Adder 2.04 MW 1.74 MW
966622 AG1-532 E Adder 1.36 MW 1.16 MW
314541 3WATKINS Adder 1.02 MW 0.87 MW
314572 3EMPORIA Adder 0.63 MW 0.54 MW
918492 AA1-063AE OP Adder 6.0 MW 5.1 MW
918532 AA1-067 E Adder 1.03 MW 0.87 MW
919692 AA2-053 E OP Adder 6.21 MW 5.28 MW
920042 AA2-088 E OP Adder 15.68 MW 13.33 MW
925785 AC1-054 E Adder 4.96 MW 4.21 MW
927146 AC1-208 E Adder 6.09 MW 5.17 MW
934521 AD1-076 C Adder 18.21 MW 15.48 MW
934522 AD1-076 E Adder 9.28 MW 7.89 MW
943172 AE2-346 E Adder 0.9 MW 0.76 MW
944011 AF1-069 C 50/50 23.43 MW 23.43 MW
944012 AF1-069 E 50/50 9.1 MW 9.1 MW
960081 AF2-299 C Adder 2.72 MW 2.31 MW
960082 AF2-299 E Adder 1.82 MW 1.54 MW
316141 AB2-099 E Adder 0.37 MW 0.32 MW
900672 V4-068 E Adder 0.53 MW 0.45 MW
917342 Z2-044 E Adder 0.94 MW 0.8 MW
923263 AB1-132 E OP Adder 8.87 MW 7.54 MW
923573 AB1-173 E OP Adder 4.8 MW 4.08 MW
924162 AB2-060 E OP Adder 6.0 MW 5.1 MW
924302 AB2-077 E O1 Adder 1.89 MW 1.6 MW
924312 AB2-078 E O1 Adder 1.89 MW 1.6 MW
924322 AB2-079 E O1 Adder 1.89 MW 1.6 MW
925612 AC1-036 E Adder 1.16 MW 0.99 MW
939181 AE1-148 C Adder 12.81 MW 10.89 MW
939182 AE1-148 E Adder 8.54 MW 7.26 MW
940492 AE2-034 E Adder 4.62 MW 3.92 MW
941031 AE2-094 C 50/50 71.7 MW 71.7 MW
941032 AE2-094 E 50/50 32.11 MW 32.11 MW
946281 AF1-292 C Adder 2.25 MW 1.92 MW
946282 AF1-292 E Adder 1.5 MW 1.28 MW
957481 AF2-042 C 50/50 85.34 MW 85.34 MW
957482 AF2-042 E 50/50 56.89 MW 56.89 MW
957521 AF2-046 C Adder 20.97 MW 17.83 MW
957522 AF2-046 E Adder 10.6 MW 9.01 MW
957861 AF2-080 C Adder 10.9 MW 9.26 MW
314539 3UNCAMP Adder 9.01 MW 7.66 MW
916042 Z1-036 E Adder 43.12 MW 36.66 MW
938771 AE1-103 C Adder 4.34 MW 3.69 MW
938772 AE1-103 E Adder 6.0 MW 5.1 MW
314331 6POE Adder 1.7 MW 1.45 MW
314507 3THOMPSN Adder 3.07 MW 2.61 MW
314525 6KINGFORK Adder 1.48 MW 1.26 MW
314550 6HICKORY 50/50 3.36 MW 3.36 MW
315092 1YORKTN3 Adder 167.73 MW 142.57 MW
926662 AC1-147 E Adder 2.01 MW 1.71 MW
926755 AC1-161 E 50/50 20.6 MW 20.6 MW
935112 AD1-144 E Adder 1.37 MW 1.17 MW
942341 AE2-247 C Adder 2.1 MW 1.79 MW
942342 AE2-247 E Adder 2.91 MW 2.47 MW
943461 AF1-017 C Adder 1.9 MW 1.62 MW
943462 AF1-017 E Adder 3.11 MW 2.64 MW
943612 AF1-032 E Adder 1.4 MW 1.19 MW
315102 1BRUNSWICKG1 50/50 14.69 MW 14.69 MW
315103 1BRUNSWICKG2 50/50 14.69 MW 14.69 MW
315104 1BRUNSWICKG3 50/50 14.69 MW 14.69 MW
315105 1BRUNSWICKS1 50/50 30.52 MW 30.52 MW
315108 1ELIZAR1 50/50 4.88 MW 4.88 MW
315109 1ELIZAR2 50/50 4.79 MW 4.79 MW
315110 1ELIZAR3 50/50 4.94 MW 4.94 MW
315241 1Z1-086 GT1 50/50 18.83 MW 18.83 MW
315242 1Z1-086 GT2 50/50 18.82 MW 18.82 MW
315243 1Z1-086 GT3 50/50 18.82 MW 18.82 MW
315244 1Z1-086 ST 50/50 32.77 MW 32.77 MW
315260 1GOSPORTA 50/50 3.23 MW 3.23 MW
315261 1GOSPORTB 50/50 4.13 MW 4.13 MW
315262 1GOSPORTC 50/50 3.51 MW 3.51 MW
913392 Y1-086 E Adder 3.36 MW 2.85 MW
916192 Z1-068 E 50/50 2.88 MW 2.88 MW
923832 AB2-022 E Adder 1.9 MW 1.61 MW
923852 AB2-025 E Adder 1.71 MW 1.46 MW
939312 AE1-162 E Adder 1.94 MW 1.65 MW
957492 AF2-043 E Adder 2.15 MW 1.83 MW
901082 W1-029 E Adder 48.36 MW 41.1 MW
917122 Z2-027 E Adder 2.05 MW 1.74 MW
925522 AC1-027 E 50/50 1.86 MW 1.86 MW
957871 AF2-081 C 50/50 15.37 MW 15.37 MW
957872 AF2-081 E 50/50 6.59 MW 6.59 MW
958161 AF2-110 C Adder 2.03 MW 1.73 MW
958162 AF2-110 E Adder 3.23 MW 2.75 MW
314722 3TWITTYS Adder 1.29 MW 1.09 MW
926071 AC1-086 C Adder 30.49 MW 25.91 MW
926072 AC1-086 E Adder 13.88 MW 11.79 MW
927021 AC1-189 C Adder 12.0 MW 10.2 MW
927022 AC1-189 E Adder 3.71 MW 3.15 MW
933291 AC2-141 C 50/50 48.25 MW 48.25 MW
933292 AC2-141 E 50/50 20.6 MW 20.6 MW
934621 AD1-088 C Adder 18.74 MW 15.93 MW
934622 AD1-088 E Adder 8.82 MW 7.5 MW
939411 AE1-173 C 50/50 157.55 MW 157.55 MW
939412 AE1-173 E 50/50 105.03 MW 105.03 MW
916191 Z1-068 C 50/50 0.07 MW 0.07 MW
933981 AD1-022 C Adder 13.01 MW 11.06 MW
933982 AD1-022 E Adder 7.08 MW 6.02 MW
962572 AG1-106 E Adder 1.72 MW 1.47 MW
961681 AG1-008 C Adder 20.97 MW 17.83 MW
961682 AG1-008 E Adder 10.6 MW 9.01 MW
962571 AG1-106 C Adder 3.94 MW 3.35 MW
314594 6PLYMOUTH TP Adder 0.48 MW 0.41 MW
314632 6AYDLETT TAP 50/50 2.08 MW 2.08 MW
316185 AD1-033 C 50/50 1.9 MW 1.9 MW
316274 AC1-208 C Adder 13.7 MW 11.65 MW
316294 AC1-161 C 50/50 7.88 MW 7.88 MW
316316 AC1-027 C 50/50 0.48 MW 0.48 MW
917332 KELFORD E Adder 2.45 MW 2.09 MW
924516 AB2-100 E1 Adder 4.23 MW 3.6 MW
924517 AB2-100 E2 Adder 4.23 MW 3.6 MW
926206 AC1-098 E Adder 5.54 MW 4.71 MW
926214 AC1-099 E Adder 1.83 MW 1.56 MW
934065 AD1-033 E 50/50 7.74 MW 7.74 MW
937226 AE2-253 E 50/50 9.0 MW 9.0 MW
918512 AA1-065 E OP Adder 8.15 MW 6.93 MW
316017 AA1-139 ULT1 50/50 1.66 MW 1.66 MW
316018 AA1-139 ULT2 50/50 1.66 MW 1.66 MW
919153 AA1-139 E2 50/50 6.29 MW 6.29 MW
919152 AA1-139 E1 50/50 6.29 MW 6.29 MW
919710 AA2-057 E Adder 6.16 MW 5.24 MW
920692 AA2-178 E Adder 6.16 MW 5.23 MW
923994 AB2-040_E Adder 8.99 MW 7.64 MW
924022 AB2-043 E O1 Adder 7.32 MW 6.22 MW
316084 AB2-161 E Adder 7.16 MW 6.09 MW
925122 AB2-169 E Adder 8.42 MW 7.16 MW
316088 AB2-174 E Adder 9.52 MW 8.09 MW
932046 AC2-012 E Adder 19.89 MW 16.91 MW
316311 AC2-079 C Adder 8.14 MW 6.92 MW
932596 AC2-079 E Adder 13.28 MW 11.29 MW
934576 AD1-082 E Adder 5.71 MW 4.85 MW
316349 AD2-085 C Adder 4.85 MW 4.13 MW
936666 AD2-085 E Adder 7.92 MW 6.73 MW
316388 AE2-253 GEN 50/50 3.03 MW 3.03 MW
941591 AE2-156 C 50/50 27.2 MW 27.2 MW
944581 AF1-123 C 50/50 70.09 MW 70.09 MW
944582 AF1-123 E 50/50 160.5 MW 160.5 MW
944591 AF1-124 C 50/50 70.34 MW 70.34 MW
944592 AF1-124 E 50/50 161.08 MW 161.08 MW
944601 AF1-125 C 50/50 69.01 MW 69.01 MW
944602 AF1-125 E 50/50 157.98 MW 157.98 MW
962491 AG1-098 C Adder 16.62 MW 14.13 MW
962492 AG1-098 E Adder 11.08 MW 9.42 MW
962561 AG1-105 C Adder 12.3 MW 10.46 MW
962562 AG1-105 E Adder 8.2 MW 6.97 MW
964241 AG1-285 C Adder 18.38 MW 15.63 MW
964242 AG1-285 E Adder 12.26 MW 10.42 MW
313764 3SOCKMAN Adder 1.04 MW 0.89 MW
932632 AC2-084 E Adder 4.9 MW 4.17 MW
934321 AD1-056 C Adder 8.91 MW 7.57 MW
934322 AD1-056 E Adder 4.83 MW 4.11 MW
934331 AD1-057 C Adder 4.97 MW 4.22 MW
934332 AD1-057 E Adder 2.59 MW 2.2 MW
934501 AD1-074 C Adder 50.15 MW 42.63 MW
934502 AD1-074 E Adder 25.53 MW 21.7 MW
934511 AD1-075 C Adder 12.54 MW 10.66 MW
934512 AD1-075 E Adder 6.38 MW 5.42 MW
934612 AD1-087 E Adder 5.52 MW 4.69 MW
935172 AD1-152 E Adder 8.1 MW 6.88 MW
937482 AD2-202 E Adder 1.62 MW 1.37 MW
938531 AE1-072 C 50/50 27.0 MW 27.0 MW
938532 AE1-072 E 50/50 14.07 MW 14.07 MW
940481 AE2-033 C Adder 23.87 MW 20.29 MW
940482 AE2-033 E Adder 16.09 MW 13.68 MW
940541 AE2-040 C Adder 4.24 MW 3.6 MW
940641 AE2-051 C 50/50 31.13 MW 31.13 MW
940642 AE2-051 E 50/50 20.75 MW 20.75 MW
941101 AE2-104 C Adder 4.98 MW 4.23 MW
941102 AE2-104 E Adder 7.91 MW 6.73 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 35.4 MW 35.4 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.72 MW 27.72 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 131.32 MW 131.32 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 4.67 MW 4.67 MW
NY PJM->LTFIMP_NY CLTF 2.19 MW 2.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.4 MW 1.4 MW
WEC LTFEXP_WEC->PJM CLTF 0.74 MW 0.74 MW
CPLE LTFEXP_CPLE->PJM CLTF 16.18 MW 16.18 MW
TVA LTFEXP_TVA->PJM CLTF 7.65 MW 7.65 MW
MEC LTFEXP_MEC->PJM CLTF 4.67 MW 4.67 MW
LAGN LTFEXP_LAGN->PJM CLTF 9.79 MW 9.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.28 MW 0.28 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 29.78 MW 29.78 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.71 MW 7.71 MW

Details for 6POE-6TYLER1 230.0 kV Ckt 1 line l/o DVP_P4-2: 562T563_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6POE-6TYLER1 230.0 kV Ckt 1 line
314331 to 314263 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 112.93 %
Rating: 541.0 MVA
Rating Type: C
MVA to Mitigate: 610.96 MVA
MW Contribution: 3.54 MW
Impact of Topology Modeling:
Decrease
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.32 MW 0.27 MW
961672 AG1-007 E Adder 0.18 MW 0.15 MW
961941 AG1-037 C Adder 0.16 MW 0.13 MW
961942 AG1-037 E Adder 0.11 MW 0.09 MW
962331 AG1-082 C Adder 0.63 MW 0.54 MW
962332 AG1-082 E Adder 0.42 MW 0.36 MW
963041 AG1-153 C Adder 2.22 MW 1.89 MW
963042 AG1-153 E Adder 3.33 MW 2.83 MW
964791 AG1-342 C Adder 1.14 MW 0.97 MW
964792 AG1-342 E Adder 0.76 MW 0.65 MW
966811 AG1-552 C Adder 0.8 MW 0.68 MW
966812 AG1-552 E Adder 0.38 MW 0.32 MW
965291 AG1-394 C Adder 0.28 MW 0.24 MW
965292 AG1-394 E Adder 0.52 MW 0.44 MW
966621 AG1-532 C Adder 0.65 MW 0.55 MW
966622 AG1-532 E Adder 0.43 MW 0.37 MW
314541 3WATKINS Adder 0.22 MW 0.18 MW
314572 3EMPORIA Adder 0.2 MW 0.17 MW
315131 1EDGECMA Adder 5.37 MW 4.56 MW
918492 AA1-063AE OP Adder 1.5 MW 1.27 MW
919692 AA2-053 E OP Adder 1.59 MW 1.35 MW
920042 AA2-088 E OP Adder 3.5 MW 2.97 MW
925785 AC1-054 E Adder 1.24 MW 1.06 MW
926274 AC1-105 E Adder 0.85 MW 0.72 MW
927146 AC1-208 E Adder 1.51 MW 1.29 MW
943172 AE2-346 E Adder 0.19 MW 0.16 MW
943902 AF1-058 E Adder 0.4 MW 0.34 MW
944011 AF1-069 C Adder 5.21 MW 4.43 MW
944012 AF1-069 E Adder 2.02 MW 1.72 MW
959311 AF2-222 C Adder 5.05 MW 4.29 MW
959312 AF2-222 E Adder 3.38 MW 2.88 MW
960061 AF2-297 C Adder 2.42 MW 2.05 MW
960062 AF2-297 E Adder 1.61 MW 1.37 MW
960081 AF2-299 C Adder 0.87 MW 0.74 MW
960082 AF2-299 E Adder 0.58 MW 0.49 MW
316141 AB2-099 E Adder 0.08 MW 0.07 MW
900672 V4-068 E Adder 0.12 MW 0.1 MW
917342 Z2-044 E Adder 0.23 MW 0.2 MW
922923 AB1-081 E OP Adder 1.26 MW 1.07 MW
923263 AB1-132 E OP Adder 2.61 MW 2.21 MW
923573 AB1-173 E OP Adder 1.41 MW 1.2 MW
924162 AB2-060 E OP Adder 1.42 MW 1.21 MW
924302 AB2-077 E O1 Adder 0.45 MW 0.38 MW
924312 AB2-078 E O1 Adder 0.45 MW 0.38 MW
924322 AB2-079 E O1 Adder 0.45 MW 0.38 MW
925612 AC1-036 E Adder 0.26 MW 0.23 MW
939181 AE1-148 C Adder 3.05 MW 2.6 MW
939182 AE1-148 E Adder 2.04 MW 1.73 MW
941031 AE2-094 C Adder 15.95 MW 13.55 MW
941032 AE2-094 E Adder 7.14 MW 6.07 MW
946281 AF1-292 C Adder 0.72 MW 0.61 MW
946282 AF1-292 E Adder 0.48 MW 0.41 MW
957481 AF2-042 C Adder 19.15 MW 16.27 MW
957482 AF2-042 E Adder 12.76 MW 10.85 MW
957521 AF2-046 C Adder 4.58 MW 3.9 MW
957522 AF2-046 E Adder 2.32 MW 1.97 MW
957861 AF2-080 C Adder 2.46 MW 2.09 MW
957862 AF2-080 E Adder 1.09 MW 0.93 MW
314539 3UNCAMP Adder 1.84 MW 1.56 MW
938771 AE1-103 C Adder 0.87 MW 0.74 MW
938772 AE1-103 E Adder 1.2 MW 1.02 MW
314331 6POE 50/50 2.8 MW 2.8 MW
942341 AE2-247 C Adder 0.73 MW 0.62 MW
942342 AE2-247 E Adder 1.01 MW 0.86 MW
943461 AF1-017 C Adder 0.66 MW 0.56 MW
943462 AF1-017 E Adder 1.08 MW 0.92 MW
923852 AB2-025 E 50/50 0.72 MW 0.72 MW
314722 3TWITTYS Adder 0.29 MW 0.25 MW
917512 Z2-088 E OP1 Adder 1.6 MW 1.36 MW
926071 AC1-086 C Adder 8.95 MW 7.61 MW
926072 AC1-086 E Adder 4.07 MW 3.46 MW
927021 AC1-189 C Adder 2.7 MW 2.3 MW
927022 AC1-189 E Adder 1.35 MW 1.14 MW
936261 AD2-033 C Adder 3.94 MW 3.35 MW
936262 AD2-033 E Adder 2.63 MW 2.23 MW
934621 AD1-088 C Adder 4.21 MW 3.58 MW
934622 AD1-088 E Adder 1.98 MW 1.69 MW
939411 AE1-173 C Adder 28.33 MW 24.08 MW
939412 AE1-173 E Adder 18.89 MW 16.05 MW
962572 AG1-106 E Adder 0.51 MW 0.43 MW
961681 AG1-008 C Adder 4.58 MW 3.9 MW
961682 AG1-008 E Adder 2.32 MW 1.97 MW
962571 AG1-106 C Adder 1.16 MW 0.98 MW
316240 AF1-291 C Adder -2.15 MW -1.83 MW
316263 AC1-034 C Adder 2.26 MW 1.92 MW
316274 AC1-208 C Adder 3.41 MW 2.9 MW
316315 AB2-025 C 50/50 0.25 MW 0.25 MW
917332 KELFORD E Adder 0.54 MW 0.46 MW
924516 AB2-100 E1 Adder 1.47 MW 1.25 MW
924517 AB2-100 E2 Adder 1.47 MW 1.25 MW
925595 AC1-034 E Adder 1.71 MW 1.45 MW
926206 AC1-098 E Adder 1.33 MW 1.13 MW
926214 AC1-099 E Adder 0.44 MW 0.37 MW
919710 AA2-057 E Adder 1.52 MW 1.29 MW
923994 AB2-040_E Adder 2.65 MW 2.25 MW
924022 AB2-043 E O1 Adder 1.74 MW 1.48 MW
924152 AB2-059 E OP Adder 1.8 MW 1.53 MW
316083 AB2-161 C 50/50 0.46 MW 0.46 MW
316084 AB2-161 E 50/50 4.6 MW 4.6 MW
316088 AB2-174 E Adder 2.88 MW 2.44 MW
316311 AC2-079 C Adder 2.66 MW 2.26 MW
932596 AC2-079 E Adder 4.34 MW 3.69 MW
316381 AD1-082 C 50/50 1.05 MW 1.05 MW
934576 AD1-082 E 50/50 3.67 MW 3.67 MW
316349 AD2-085 C Adder 1.69 MW 1.44 MW
936666 AD2-085 E Adder 2.76 MW 2.35 MW
962491 AG1-098 C Adder 3.73 MW 3.17 MW
962492 AG1-098 E Adder 2.49 MW 2.12 MW
962561 AG1-105 C Adder 2.87 MW 2.44 MW
962562 AG1-105 E Adder 1.92 MW 1.63 MW
964241 AG1-285 C Adder 4.22 MW 3.59 MW
964242 AG1-285 E Adder 2.82 MW 2.39 MW
313764 3SOCKMAN Adder 0.29 MW 0.25 MW
932632 AC2-084 E Adder 1.18 MW 1.0 MW
934321 AD1-056 C Adder 2.38 MW 2.02 MW
934322 AD1-056 E Adder 1.29 MW 1.1 MW
934331 AD1-057 C Adder 1.33 MW 1.13 MW
934332 AD1-057 E Adder 0.69 MW 0.59 MW
934612 AD1-087 E Adder 1.24 MW 1.06 MW
935172 AD1-152 E Adder 1.83 MW 1.56 MW
937482 AD2-202 E Adder 0.36 MW 0.31 MW
939191 AE1-149 C 50/50 11.46 MW 11.46 MW
939192 AE1-149 E 50/50 7.64 MW 7.64 MW
940481 AE2-033 C 50/50 9.81 MW 9.81 MW
940482 AE2-033 E 50/50 6.61 MW 6.61 MW
940541 AE2-040 C 50/50 1.78 MW 1.78 MW
944641 AF1-129 C Adder -70.51 MW -59.94 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 9.57 MW 9.57 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.78 MW 6.78 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 30.25 MW 30.25 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.77 MW 0.77 MW
NY PJM->LTFIMP_NY CLTF 0.35 MW 0.35 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.37 MW 0.37 MW
WEC LTFEXP_WEC->PJM CLTF 0.2 MW 0.2 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.71 MW 3.71 MW
TVA LTFEXP_TVA->PJM CLTF 1.83 MW 1.83 MW
MEC LTFEXP_MEC->PJM CLTF 1.19 MW 1.19 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.34 MW 2.34 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.89 MW 4.89 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.77 MW 1.77 MW

Details for 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line l/o DVP_P4-2: 563T576_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
Contingency Name:
DVP_P4-2: 563T576_SRT-S
CONTINGENCY 'DVP_P4-2: 563T576_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.26 %
Rating: 3144.0 MVA
Rating Type: C
MVA to Mitigate: 3215.2 MVA
MW Contribution: 13.04 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
Contingency Name:
DVP_P4-2: 563T576_SRT-S
CONTINGENCY 'DVP_P4-2: 563T576_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 107.02 %
Rating: 3144.0 MVA
Rating Type: C
MVA to Mitigate: 3364.71 MVA
MW Contribution: 13.22 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.06 MW 0.9 MW
961672 AG1-007 E Adder 0.6 MW 0.51 MW
961941 AG1-037 C Adder 0.67 MW 0.57 MW
961942 AG1-037 E Adder 0.45 MW 0.38 MW
962331 AG1-082 C Adder 2.67 MW 2.27 MW
962332 AG1-082 E Adder 1.78 MW 1.51 MW
963041 AG1-153 C Adder 6.86 MW 5.83 MW
963042 AG1-153 E Adder 10.28 MW 8.74 MW
964791 AG1-342 C Adder 3.49 MW 2.96 MW
964792 AG1-342 E Adder 2.33 MW 1.98 MW
966801 AG1-551 C Adder 2.65 MW 2.25 MW
966802 AG1-551 E Adder 1.4 MW 1.19 MW
966811 AG1-552 C Adder 2.45 MW 2.08 MW
966812 AG1-552 E Adder 1.16 MW 0.99 MW
965291 AG1-394 C Adder 1.13 MW 0.96 MW
965292 AG1-394 E Adder 2.08 MW 1.77 MW
966621 AG1-532 C Adder 1.56 MW 1.32 MW
966622 AG1-532 E Adder 1.04 MW 0.88 MW
314541 3WATKINS Adder 0.96 MW 0.81 MW
314572 3EMPORIA Adder 0.48 MW 0.41 MW
315131 1EDGECMA Adder 17.13 MW 14.56 MW
918492 AA1-063AE OP Adder 5.08 MW 4.32 MW
918532 AA1-067 E Adder 0.88 MW 0.74 MW
919692 AA2-053 E OP Adder 5.13 MW 4.36 MW
920042 AA2-088 E OP Adder 14.14 MW 12.02 MW
925785 AC1-054 E Adder 3.81 MW 3.24 MW
926274 AC1-105 E Adder 0.55 MW 0.47 MW
927146 AC1-208 E Adder 5.09 MW 4.33 MW
934521 AD1-076 C Adder 17.3 MW 14.7 MW
934522 AD1-076 E Adder 8.82 MW 7.5 MW
943172 AE2-346 E Adder 0.8 MW 0.68 MW
944011 AF1-069 C Adder 16.1 MW 13.68 MW
944012 AF1-069 E Adder 6.25 MW 5.32 MW
959311 AF2-222 C Adder 16.0 MW 13.6 MW
959312 AF2-222 E Adder 10.72 MW 9.11 MW
960081 AF2-299 C Adder 2.08 MW 1.76 MW
960082 AF2-299 E Adder 1.38 MW 1.18 MW
316141 AB2-099 E Adder 0.33 MW 0.28 MW
900672 V4-068 E Adder 0.47 MW 0.4 MW
917342 Z2-044 E Adder 0.79 MW 0.67 MW
922923 AB1-081 E OP Adder 4.22 MW 3.59 MW
923263 AB1-132 E OP Adder 7.05 MW 6.0 MW
923573 AB1-173 E OP Adder 3.76 MW 3.2 MW
924162 AB2-060 E OP Adder 4.33 MW 3.68 MW
924302 AB2-077 E O1 Adder 1.36 MW 1.16 MW
924312 AB2-078 E O1 Adder 1.36 MW 1.16 MW
924322 AB2-079 E O1 Adder 1.36 MW 1.16 MW
925612 AC1-036 E Adder 0.84 MW 0.71 MW
939181 AE1-148 C Adder 9.38 MW 7.97 MW
939182 AE1-148 E Adder 6.25 MW 5.31 MW
940492 AE2-034 E Adder 4.5 MW 3.83 MW
941031 AE2-094 C Adder 49.26 MW 41.87 MW
941032 AE2-094 E Adder 22.06 MW 18.75 MW
946281 AF1-292 C Adder 1.72 MW 1.46 MW
946282 AF1-292 E Adder 1.14 MW 0.97 MW
957481 AF2-042 C Adder 59.6 MW 50.66 MW
957482 AF2-042 E Adder 39.74 MW 33.77 MW
957521 AF2-046 C Adder 18.79 MW 15.97 MW
957522 AF2-046 E Adder 9.5 MW 8.07 MW
957861 AF2-080 C Adder 9.04 MW 7.68 MW
957862 AF2-080 E Adder 4.0 MW 3.4 MW
314539 3UNCAMP Adder 8.59 MW 7.3 MW
916042 Z1-036 E Adder 43.42 MW 36.91 MW
938771 AE1-103 C Adder 4.18 MW 3.55 MW
938772 AE1-103 E Adder 5.77 MW 4.91 MW
314507 3THOMPSN Adder 3.3 MW 2.8 MW
314525 6KINGFORK Adder 1.53 MW 1.3 MW
314550 6HICKORY 50/50 3.64 MW 3.64 MW
315092 1YORKTN3 Adder 182.37 MW 155.02 MW
926662 AC1-147 E 50/50 2.16 MW 2.16 MW
926755 AC1-161 E 50/50 24.41 MW 24.41 MW
927226 AC1-216 E Adder 7.2 MW 6.12 MW
935112 AD1-144 E Adder 1.42 MW 1.21 MW
942341 AE2-247 C Adder 2.0 MW 1.7 MW
942342 AE2-247 E Adder 2.76 MW 2.34 MW
943461 AF1-017 C Adder 1.81 MW 1.53 MW
943462 AF1-017 E Adder 2.95 MW 2.5 MW
943612 AF1-032 E Adder 1.46 MW 1.24 MW
315098 1CHESPKA 50/50 0.71 MW 0.71 MW
315099 1CHESPKB 50/50 1.18 MW 1.18 MW
315108 1ELIZAR1 50/50 5.25 MW 5.25 MW
315109 1ELIZAR2 50/50 5.16 MW 5.16 MW
315110 1ELIZAR3 50/50 5.32 MW 5.32 MW
315233 1SURRY 2 50/50 52.27 MW 52.27 MW
315260 1GOSPORTA Adder 3.48 MW 2.96 MW
315261 1GOSPORTB 50/50 4.44 MW 4.44 MW
315262 1GOSPORTC 50/50 3.77 MW 3.77 MW
913392 Y1-086 E Adder 3.54 MW 3.01 MW
916192 Z1-068 E 50/50 3.11 MW 3.11 MW
923832 AB2-022 E Adder 2.0 MW 1.7 MW
923852 AB2-025 E Adder 1.22 MW 1.03 MW
939312 AE1-162 E Adder 1.97 MW 1.67 MW
957492 AF2-043 E Adder 2.25 MW 1.91 MW
962962 AG1-145 E Adder 1.4 MW 1.19 MW
901082 W1-029 E Adder 50.02 MW 42.52 MW
917122 Z2-027 E Adder 2.14 MW 1.82 MW
925522 AC1-027 E 50/50 2.01 MW 2.01 MW
957832 AF2-077 E Adder 1.41 MW 1.2 MW
957871 AF2-081 C 50/50 16.49 MW 16.49 MW
957872 AF2-081 E 50/50 7.07 MW 7.07 MW
958161 AF2-110 C Adder 2.05 MW 1.75 MW
958162 AF2-110 E Adder 3.27 MW 2.78 MW
314722 3TWITTYS Adder 0.93 MW 0.79 MW
917512 Z2-088 E OP1 Adder 5.69 MW 4.83 MW
926071 AC1-086 C Adder 24.24 MW 20.6 MW
926072 AC1-086 E Adder 11.03 MW 9.38 MW
927021 AC1-189 C Adder 9.95 MW 8.46 MW
927022 AC1-189 E Adder 4.96 MW 4.21 MW
933291 AC2-141 C 50/50 57.19 MW 57.19 MW
933292 AC2-141 E 50/50 24.41 MW 24.41 MW
934621 AD1-088 C Adder 13.21 MW 11.23 MW
934622 AD1-088 E Adder 6.22 MW 5.28 MW
939411 AE1-173 C Adder 130.54 MW 110.96 MW
939412 AE1-173 E Adder 87.03 MW 73.97 MW
934012 AD1-025 E Adder 9.32 MW 7.92 MW
916191 Z1-068 C 50/50 0.07 MW 0.07 MW
933981 AD1-022 C Adder 12.21 MW 10.38 MW
933982 AD1-022 E Adder 6.65 MW 5.65 MW
962572 AG1-106 E Adder 1.37 MW 1.17 MW
961681 AG1-008 C Adder 18.79 MW 15.97 MW
961682 AG1-008 E Adder 9.5 MW 8.07 MW
962571 AG1-106 C Adder 3.14 MW 2.67 MW
314594 6PLYMOUTH TP Adder 0.46 MW 0.39 MW
314632 6AYDLETT TAP Adder 2.22 MW 1.89 MW
316036 AC1-147 C 50/50 0.6 MW 0.6 MW
316160 AE1-175 E Adder 1.15 MW 0.98 MW
316185 AD1-033 C 50/50 2.06 MW 2.06 MW
316263 AC1-034 C Adder 7.48 MW 6.36 MW
316274 AC1-208 C Adder 11.47 MW 9.75 MW
316294 AC1-161 C 50/50 9.35 MW 9.35 MW
316316 AC1-027 C 50/50 0.52 MW 0.52 MW
917332 KELFORD E Adder 2.16 MW 1.83 MW
924516 AB2-100 E1 Adder 3.2 MW 2.72 MW
924517 AB2-100 E2 Adder 3.2 MW 2.72 MW
925595 AC1-034 E Adder 5.65 MW 4.8 MW
926206 AC1-098 E Adder 4.71 MW 4.0 MW
926214 AC1-099 E Adder 1.56 MW 1.32 MW
934065 AD1-033 E 50/50 8.39 MW 8.39 MW
937226 AE2-253 E 50/50 9.68 MW 9.68 MW
918512 AA1-065 E OP Adder 7.39 MW 6.28 MW
316017 AA1-139 ULT1 50/50 1.78 MW 1.78 MW
316018 AA1-139 ULT2 50/50 1.78 MW 1.78 MW
919153 AA1-139 E2 50/50 6.74 MW 6.74 MW
919152 AA1-139 E1 50/50 6.74 MW 6.74 MW
919710 AA2-057 E Adder 5.17 MW 4.4 MW
920692 AA2-178 E Adder 6.0 MW 5.1 MW
923994 AB2-040_E Adder 7.06 MW 6.0 MW
924022 AB2-043 E O1 Adder 5.28 MW 4.49 MW
924152 AB2-059 E OP Adder 5.92 MW 5.03 MW
924814 AB2-134 E Adder 11.79 MW 10.02 MW
316084 AB2-161 E Adder 6.01 MW 5.11 MW
925122 AB2-169 E Adder 7.62 MW 6.47 MW
316088 AB2-174 E Adder 7.4 MW 6.29 MW
316375 AC2-012 C 50/50 2.21 MW 2.21 MW
932046 AC2-012 E 50/50 21.39 MW 21.39 MW
316311 AC2-079 C Adder 7.79 MW 6.62 MW
932596 AC2-079 E Adder 12.72 MW 10.81 MW
934576 AD1-082 E Adder 4.79 MW 4.07 MW
316349 AD2-085 C Adder 4.61 MW 3.92 MW
936666 AD2-085 E Adder 7.52 MW 6.39 MW
316388 AE2-253 GEN 50/50 3.26 MW 3.26 MW
961611 AG1-000B C Adder 18.13 MW 15.41 MW
941591 AE2-156 C 50/50 29.28 MW 29.28 MW
944581 AF1-123 C 50/50 76.02 MW 76.02 MW
944582 AF1-123 E 50/50 174.06 MW 174.06 MW
944591 AF1-124 C 50/50 76.28 MW 76.28 MW
944592 AF1-124 E 50/50 174.7 MW 174.7 MW
944601 AF1-125 C 50/50 74.84 MW 74.84 MW
944602 AF1-125 E 50/50 171.33 MW 171.33 MW
962491 AG1-098 C Adder 11.73 MW 9.97 MW
962492 AG1-098 E Adder 7.82 MW 6.65 MW
962561 AG1-105 C Adder 8.8 MW 7.48 MW
962562 AG1-105 E Adder 5.86 MW 4.98 MW
964241 AG1-285 C Adder 13.12 MW 11.15 MW
964242 AG1-285 E Adder 8.75 MW 7.43 MW
313764 3SOCKMAN Adder 0.83 MW 0.71 MW
932632 AC2-084 E Adder 4.16 MW 3.54 MW
934321 AD1-056 C Adder 7.04 MW 5.98 MW
934322 AD1-056 E Adder 3.82 MW 3.25 MW
934331 AD1-057 C Adder 3.93 MW 3.34 MW
934332 AD1-057 E Adder 2.04 MW 1.74 MW
934501 AD1-074 C Adder 47.63 MW 40.49 MW
934502 AD1-074 E Adder 24.25 MW 20.61 MW
934511 AD1-075 C Adder 11.91 MW 10.12 MW
934512 AD1-075 E Adder 6.06 MW 5.15 MW
934612 AD1-087 E Adder 3.87 MW 3.29 MW
935172 AD1-152 E Adder 5.69 MW 4.84 MW
937482 AD2-202 E Adder 1.13 MW 0.96 MW
938531 AE1-072 C 50/50 28.87 MW 28.87 MW
938532 AE1-072 E 50/50 15.05 MW 15.05 MW
939191 AE1-149 C Adder 9.8 MW 8.33 MW
939192 AE1-149 E Adder 6.53 MW 5.55 MW
940481 AE2-033 C Adder 17.07 MW 14.51 MW
940482 AE2-033 E Adder 11.51 MW 9.78 MW
940541 AE2-040 C Adder 3.01 MW 2.56 MW
940641 AE2-051 C Adder 23.72 MW 20.16 MW
940642 AE2-051 E Adder 15.81 MW 13.44 MW
941101 AE2-104 C Adder 5.03 MW 4.28 MW
941102 AE2-104 E Adder 8.0 MW 6.8 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 19.03 MW 19.03 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 17.52 MW 17.52 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 92.84 MW 92.84 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 3.12 MW 3.12 MW
NY PJM->LTFIMP_NY CLTF 1.49 MW 1.49 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.77 MW 0.77 MW
WEC LTFEXP_WEC->PJM CLTF 0.41 MW 0.41 MW
CPLE LTFEXP_CPLE->PJM CLTF 11.71 MW 11.71 MW
TVA LTFEXP_TVA->PJM CLTF 4.99 MW 4.99 MW
MEC LTFEXP_MEC->PJM CLTF 2.75 MW 2.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.43 MW 6.43 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.16 MW 0.16 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 19.92 MW 19.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 5.58 MW 5.58 MW

Details for 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line l/o DVP_P4-2: 56372_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
Contingency Name:
DVP_P4-2: 56372_SRT-S
CONTINGENCY 'DVP_P4-2: 56372_SRT-S'
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1                /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 101.94 %
Rating: 3144.0 MVA
Rating Type: C
MVA to Mitigate: 3205.05 MVA
MW Contribution: 12.7 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
Contingency Name:
DVP_P4-2: 56372_SRT-S
CONTINGENCY 'DVP_P4-2: 56372_SRT-S'
 OPEN BRANCH FROM BUS 314282 TO BUS 314902 CKT 1                /*6CARSON      230.0 - 8CARSON      500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 106.06 %
Rating: 3144.0 MVA
Rating Type: C
MVA to Mitigate: 3334.59 MVA
MW Contribution: 12.8 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.03 MW 0.88 MW
961672 AG1-007 E Adder 0.58 MW 0.5 MW
961941 AG1-037 C Adder 0.65 MW 0.55 MW
961942 AG1-037 E Adder 0.43 MW 0.37 MW
962331 AG1-082 C Adder 2.6 MW 2.21 MW
962332 AG1-082 E Adder 1.73 MW 1.47 MW
963041 AG1-153 C Adder 6.95 MW 5.91 MW
963042 AG1-153 E Adder 10.42 MW 8.86 MW
964791 AG1-342 C Adder 3.46 MW 2.94 MW
964792 AG1-342 E Adder 2.31 MW 1.96 MW
966801 AG1-551 C Adder 2.59 MW 2.2 MW
966802 AG1-551 E Adder 1.36 MW 1.16 MW
966811 AG1-552 C Adder 2.34 MW 1.99 MW
966812 AG1-552 E Adder 1.11 MW 0.94 MW
965291 AG1-394 C Adder 1.1 MW 0.93 MW
965292 AG1-394 E Adder 2.02 MW 1.72 MW
966621 AG1-532 C Adder 1.45 MW 1.23 MW
966622 AG1-532 E Adder 0.97 MW 0.82 MW
314541 3WATKINS Adder 0.93 MW 0.79 MW
314572 3EMPORIA Adder 0.45 MW 0.38 MW
315131 1EDGECMA Adder 16.62 MW 14.13 MW
918492 AA1-063AE OP Adder 4.88 MW 4.15 MW
918532 AA1-067 E Adder 0.85 MW 0.73 MW
919692 AA2-053 E OP Adder 4.92 MW 4.18 MW
920042 AA2-088 E OP Adder 13.72 MW 11.66 MW
925785 AC1-054 E Adder 3.7 MW 3.15 MW
926274 AC1-105 E Adder 2.6 MW 2.21 MW
927146 AC1-208 E Adder 4.89 MW 4.16 MW
934521 AD1-076 C Adder 16.95 MW 14.41 MW
934522 AD1-076 E Adder 8.64 MW 7.34 MW
943172 AE2-346 E Adder 0.78 MW 0.66 MW
943902 AF1-058 E Adder 0.87 MW 0.74 MW
944011 AF1-069 C Adder 16.33 MW 13.88 MW
944012 AF1-069 E Adder 6.35 MW 5.39 MW
959311 AF2-222 C Adder 15.78 MW 13.42 MW
959312 AF2-222 E Adder 10.58 MW 8.99 MW
960061 AF2-297 C Adder 7.42 MW 6.31 MW
960062 AF2-297 E Adder 4.95 MW 4.21 MW
960081 AF2-299 C Adder 1.93 MW 1.64 MW
960082 AF2-299 E Adder 1.29 MW 1.09 MW
316141 AB2-099 E Adder 0.32 MW 0.28 MW
900672 V4-068 E Adder 0.46 MW 0.39 MW
917342 Z2-044 E Adder 0.76 MW 0.65 MW
922923 AB1-081 E OP Adder 4.1 MW 3.49 MW
923263 AB1-132 E OP Adder 6.64 MW 5.65 MW
923573 AB1-173 E OP Adder 3.55 MW 3.02 MW
924162 AB2-060 E OP Adder 4.27 MW 3.63 MW
924302 AB2-077 E O1 Adder 1.34 MW 1.14 MW
924312 AB2-078 E O1 Adder 1.34 MW 1.14 MW
924322 AB2-079 E O1 Adder 1.34 MW 1.14 MW
925612 AC1-036 E Adder 0.83 MW 0.7 MW
939181 AE1-148 C Adder 9.24 MW 7.85 MW
939182 AE1-148 E Adder 6.16 MW 5.23 MW
940492 AE2-034 E Adder 4.42 MW 3.76 MW
941031 AE2-094 C Adder 49.99 MW 42.49 MW
941032 AE2-094 E Adder 22.39 MW 19.03 MW
946281 AF1-292 C Adder 1.6 MW 1.36 MW
946282 AF1-292 E Adder 1.07 MW 0.91 MW
957481 AF2-042 C Adder 59.92 MW 50.93 MW
957482 AF2-042 E Adder 39.94 MW 33.95 MW
957521 AF2-046 C Adder 18.23 MW 15.5 MW
957522 AF2-046 E Adder 9.21 MW 7.83 MW
957861 AF2-080 C Adder 8.8 MW 7.48 MW
957862 AF2-080 E Adder 3.9 MW 3.32 MW
314539 3UNCAMP Adder 8.38 MW 7.12 MW
916042 Z1-036 E Adder 42.8 MW 36.38 MW
938771 AE1-103 C Adder 4.09 MW 3.47 MW
938772 AE1-103 E Adder 5.64 MW 4.8 MW
314507 3THOMPSN Adder 3.27 MW 2.78 MW
314525 6KINGFORK Adder 1.51 MW 1.28 MW
314550 6HICKORY 50/50 3.61 MW 3.61 MW
315092 1YORKTN3 Adder 179.07 MW 152.21 MW
926662 AC1-147 E 50/50 2.14 MW 2.14 MW
926755 AC1-161 E 50/50 24.36 MW 24.36 MW
927226 AC1-216 E Adder 6.77 MW 5.76 MW
935112 AD1-144 E Adder 1.4 MW 1.19 MW
942341 AE2-247 C Adder 1.93 MW 1.64 MW
942342 AE2-247 E Adder 2.66 MW 2.26 MW
943461 AF1-017 C Adder 1.74 MW 1.48 MW
943462 AF1-017 E Adder 2.85 MW 2.42 MW
943612 AF1-032 E Adder 1.44 MW 1.23 MW
315098 1CHESPKA 50/50 0.71 MW 0.71 MW
315099 1CHESPKB 50/50 1.17 MW 1.17 MW
315108 1ELIZAR1 50/50 5.21 MW 5.21 MW
315109 1ELIZAR2 50/50 5.12 MW 5.12 MW
315110 1ELIZAR3 50/50 5.28 MW 5.28 MW
315233 1SURRY 2 50/50 52.02 MW 52.02 MW
315260 1GOSPORTA Adder 3.45 MW 2.93 MW
315261 1GOSPORTB 50/50 4.4 MW 4.4 MW
315262 1GOSPORTC 50/50 3.74 MW 3.74 MW
913392 Y1-086 E Adder 3.5 MW 2.98 MW
916192 Z1-068 E 50/50 3.08 MW 3.08 MW
923832 AB2-022 E Adder 1.98 MW 1.68 MW
923852 AB2-025 E Adder 1.06 MW 0.91 MW
939312 AE1-162 E Adder 1.93 MW 1.64 MW
957492 AF2-043 E Adder 2.22 MW 1.89 MW
962962 AG1-145 E Adder 1.35 MW 1.15 MW
901082 W1-029 E Adder 49.43 MW 42.02 MW
917122 Z2-027 E Adder 2.12 MW 1.8 MW
925522 AC1-027 E 50/50 1.99 MW 1.99 MW
957832 AF2-077 E Adder 1.37 MW 1.16 MW
957871 AF2-081 C 50/50 16.36 MW 16.36 MW
957872 AF2-081 E 50/50 7.01 MW 7.01 MW
958161 AF2-110 C Adder 2.02 MW 1.72 MW
958162 AF2-110 E Adder 3.21 MW 2.73 MW
314722 3TWITTYS Adder 0.92 MW 0.78 MW
917512 Z2-088 E OP1 Adder 5.53 MW 4.7 MW
926071 AC1-086 C Adder 22.83 MW 19.4 MW
926072 AC1-086 E Adder 10.39 MW 8.83 MW
927021 AC1-189 C Adder 9.69 MW 8.24 MW
927022 AC1-189 E Adder 4.83 MW 4.1 MW
933291 AC2-141 C 50/50 57.06 MW 57.06 MW
933292 AC2-141 E 50/50 24.36 MW 24.36 MW
934621 AD1-088 C Adder 13.21 MW 11.23 MW
934622 AD1-088 E Adder 6.22 MW 5.28 MW
939411 AE1-173 C Adder 131.36 MW 111.66 MW
939412 AE1-173 E Adder 87.57 MW 74.44 MW
934012 AD1-025 E Adder 8.77 MW 7.46 MW
916191 Z1-068 C 50/50 0.07 MW 0.07 MW
933981 AD1-022 C Adder 11.94 MW 10.15 MW
933982 AD1-022 E Adder 6.5 MW 5.53 MW
962572 AG1-106 E Adder 1.29 MW 1.1 MW
961681 AG1-008 C Adder 18.23 MW 15.5 MW
961682 AG1-008 E Adder 9.21 MW 7.83 MW
962571 AG1-106 C Adder 2.95 MW 2.51 MW
314594 6PLYMOUTH TP Adder 0.45 MW 0.38 MW
314632 6AYDLETT TAP 50/50 2.21 MW 2.21 MW
316036 AC1-147 C 50/50 0.6 MW 0.6 MW
316160 AE1-175 E Adder 1.12 MW 0.95 MW
316185 AD1-033 C 50/50 2.04 MW 2.04 MW
316263 AC1-034 C Adder 7.27 MW 6.18 MW
316274 AC1-208 C Adder 11.02 MW 9.36 MW
316294 AC1-161 C 50/50 9.32 MW 9.32 MW
316316 AC1-027 C 50/50 0.52 MW 0.52 MW
917332 KELFORD E Adder 2.09 MW 1.78 MW
924516 AB2-100 E1 Adder 2.92 MW 2.49 MW
924517 AB2-100 E2 Adder 2.92 MW 2.49 MW
925595 AC1-034 E Adder 5.48 MW 4.66 MW
926206 AC1-098 E Adder 4.54 MW 3.85 MW
926214 AC1-099 E Adder 1.5 MW 1.27 MW
934065 AD1-033 E 50/50 8.33 MW 8.33 MW
937226 AE2-253 E 50/50 9.61 MW 9.61 MW
918512 AA1-065 E OP Adder 7.19 MW 6.11 MW
316017 AA1-139 ULT1 50/50 1.77 MW 1.77 MW
316018 AA1-139 ULT2 50/50 1.77 MW 1.77 MW
919153 AA1-139 E2 50/50 6.69 MW 6.69 MW
919152 AA1-139 E1 50/50 6.69 MW 6.69 MW
919710 AA2-057 E Adder 4.97 MW 4.23 MW
920692 AA2-178 E Adder 5.9 MW 5.01 MW
923994 AB2-040_E Adder 6.66 MW 5.66 MW
924022 AB2-043 E O1 Adder 5.21 MW 4.43 MW
924152 AB2-059 E OP Adder 5.75 MW 4.89 MW
924814 AB2-134 E Adder 11.1 MW 9.43 MW
316084 AB2-161 E Adder 5.59 MW 4.75 MW
925122 AB2-169 E Adder 7.45 MW 6.33 MW
316088 AB2-174 E Adder 6.96 MW 5.91 MW
316375 AC2-012 C 50/50 2.19 MW 2.19 MW
932046 AC2-012 E 50/50 21.21 MW 21.21 MW
316311 AC2-079 C Adder 7.55 MW 6.41 MW
932596 AC2-079 E Adder 12.31 MW 10.46 MW
934576 AD1-082 E Adder 4.46 MW 3.79 MW
316349 AD2-085 C Adder 4.45 MW 3.78 MW
936666 AD2-085 E Adder 7.26 MW 6.17 MW
316388 AE2-253 GEN 50/50 3.23 MW 3.23 MW
961611 AG1-000B C Adder 17.46 MW 14.84 MW
941591 AE2-156 C 50/50 29.03 MW 29.03 MW
944581 AF1-123 C 50/50 75.49 MW 75.49 MW
944582 AF1-123 E 50/50 172.86 MW 172.86 MW
944591 AF1-124 C 50/50 75.75 MW 75.75 MW
944592 AF1-124 E 50/50 173.48 MW 173.48 MW
944601 AF1-125 C 50/50 74.32 MW 74.32 MW
944602 AF1-125 E 50/50 170.14 MW 170.14 MW
962491 AG1-098 C Adder 11.72 MW 9.96 MW
962492 AG1-098 E Adder 7.81 MW 6.64 MW
962561 AG1-105 C Adder 8.72 MW 7.41 MW
962562 AG1-105 E Adder 5.81 MW 4.94 MW
964241 AG1-285 C Adder 13.02 MW 11.07 MW
964242 AG1-285 E Adder 8.68 MW 7.38 MW
313764 3SOCKMAN Adder 0.79 MW 0.67 MW
932632 AC2-084 E Adder 4.01 MW 3.41 MW
934321 AD1-056 C Adder 6.74 MW 5.73 MW
934322 AD1-056 E Adder 3.66 MW 3.11 MW
934331 AD1-057 C Adder 3.76 MW 3.2 MW
934332 AD1-057 E Adder 1.96 MW 1.67 MW
934501 AD1-074 C Adder 46.68 MW 39.68 MW
934502 AD1-074 E Adder 23.76 MW 20.2 MW
934511 AD1-075 C Adder 11.67 MW 9.92 MW
934512 AD1-075 E Adder 5.94 MW 5.05 MW
934612 AD1-087 E Adder 3.88 MW 3.3 MW
935172 AD1-152 E Adder 5.7 MW 4.84 MW
937482 AD2-202 E Adder 1.14 MW 0.97 MW
938531 AE1-072 C 50/50 28.63 MW 28.63 MW
938532 AE1-072 E 50/50 14.92 MW 14.92 MW
940481 AE2-033 C Adder 15.03 MW 12.78 MW
940482 AE2-033 E Adder 10.13 MW 8.61 MW
940541 AE2-040 C Adder 2.63 MW 2.24 MW
940641 AE2-051 C Adder 23.99 MW 20.39 MW
940642 AE2-051 E Adder 16.0 MW 13.6 MW
941101 AE2-104 C Adder 4.95 MW 4.2 MW
941102 AE2-104 E Adder 7.86 MW 6.68 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 18.96 MW 18.96 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 17.43 MW 17.43 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 92.34 MW 92.34 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 3.05 MW 3.05 MW
NY PJM->LTFIMP_NY CLTF 1.46 MW 1.46 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.77 MW 0.77 MW
WEC LTFEXP_WEC->PJM CLTF 0.4 MW 0.4 MW
CPLE LTFEXP_CPLE->PJM CLTF 11.63 MW 11.63 MW
TVA LTFEXP_TVA->PJM CLTF 4.97 MW 4.97 MW
MEC LTFEXP_MEC->PJM CLTF 2.74 MW 2.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.39 MW 6.39 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.16 MW 0.16 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 19.46 MW 19.46 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 5.54 MW 5.54 MW

Details for 6PEMBROKE-6WALBMRL 230.0 kV Ckt 1 line l/o DVP_P4-2: 24642_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6PEMBROKE-6WALBMRL 230.0 kV Ckt 1 line
313714 to 313885 ckt 1
Contingency Name:
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.99 %
Rating: 897.0 MVA
Rating Type: C
MVA to Mitigate: 923.8 MVA
MW Contribution: 10.73 MW
Impact of Topology Modeling:
Decrease
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.72 MW 0.72 MW
961672 AG1-007 E 50/50 0.41 MW 0.41 MW
961941 AG1-037 C 50/50 0.56 MW 0.56 MW
961942 AG1-037 E 50/50 0.38 MW 0.38 MW
962331 AG1-082 C 50/50 2.25 MW 2.25 MW
962332 AG1-082 E 50/50 1.5 MW 1.5 MW
966801 AG1-551 C 50/50 2.98 MW 2.98 MW
966802 AG1-551 E 50/50 1.57 MW 1.57 MW
966811 AG1-552 C Adder 1.21 MW 1.03 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C Adder 0.4 MW 0.34 MW
965292 AG1-394 E Adder 0.73 MW 0.62 MW
315131 1EDGECMA 50/50 10.05 MW 10.05 MW
315136 1ROSEMG1 50/50 1.29 MW 1.29 MW
315137 1ROSEMS1 50/50 0.8 MW 0.8 MW
315138 1ROSEMG2 50/50 0.6 MW 0.6 MW
315139 1GASTONA 50/50 1.93 MW 1.93 MW
918492 AA1-063AE OP Adder 2.2 MW 1.87 MW
918532 AA1-067 E 50/50 0.82 MW 0.82 MW
919692 AA2-053 E OP 50/50 2.99 MW 2.99 MW
920042 AA2-088 E OP Adder 4.54 MW 3.86 MW
927146 AC1-208 E 50/50 3.25 MW 3.25 MW
934521 AD1-076 C 50/50 31.66 MW 31.66 MW
934522 AD1-076 E 50/50 16.14 MW 16.14 MW
943171 AE2-346 C 50/50 0.25 MW 0.25 MW
943172 AE2-346 E 50/50 0.68 MW 0.68 MW
315601 1CONETOE2SOL 50/50 1.11 MW 1.11 MW
315606 3AA2-053SOLA 50/50 1.06 MW 1.06 MW
316140 AB2-099 C 50/50 0.11 MW 0.11 MW
316141 AB2-099 E 50/50 0.28 MW 0.28 MW
900672 V4-068 E 50/50 0.25 MW 0.25 MW
917342 Z2-044 E 50/50 0.52 MW 0.52 MW
922923 AB1-081 E OP 50/50 2.81 MW 2.81 MW
923263 AB1-132 E OP 50/50 3.86 MW 3.86 MW
923573 AB1-173 E OP Adder 1.58 MW 1.34 MW
940491 AE2-034 C 50/50 3.65 MW 3.65 MW
940492 AE2-034 E 50/50 9.75 MW 9.75 MW
957521 AF2-046 C 50/50 11.16 MW 11.16 MW
957522 AF2-046 E 50/50 5.64 MW 5.64 MW
957861 AF2-080 C 50/50 7.43 MW 7.43 MW
957862 AF2-080 E 50/50 3.29 MW 3.29 MW
916042 Z1-036 E 50/50 111.91 MW 111.91 MW
315141 1GASTONB 50/50 1.93 MW 1.93 MW
315292 1DOMTR78 50/50 3.11 MW 3.11 MW
315611 6Z1-036WIND 50/50 2.58 MW 2.58 MW
917512 Z2-088 E OP1 50/50 4.34 MW 4.34 MW
926071 AC1-086 C 50/50 13.27 MW 13.27 MW
926072 AC1-086 E 50/50 6.04 MW 6.04 MW
927021 AC1-189 C 50/50 8.18 MW 8.18 MW
927022 AC1-189 E 50/50 4.08 MW 4.08 MW
933981 AD1-022 C 50/50 19.93 MW 19.93 MW
933982 AD1-022 E 50/50 10.85 MW 10.85 MW
962572 AG1-106 E 50/50 0.75 MW 0.75 MW
961681 AG1-008 C 50/50 11.16 MW 11.16 MW
961682 AG1-008 E 50/50 5.64 MW 5.64 MW
962571 AG1-106 C 50/50 1.72 MW 1.72 MW
314594 6PLYMOUTH TP 50/50 0.87 MW 0.87 MW
316005 AA1-067 C 50/50 0.31 MW 0.31 MW
316011 AB1-132 C OP 50/50 1.47 MW 1.47 MW
316049 AB1-081 C OP 50/50 1.07 MW 1.07 MW
316210 AC1-098 C 50/50 0.86 MW 0.86 MW
316212 AC1-099 C 50/50 0.29 MW 0.29 MW
316263 AC1-034 C 50/50 4.86 MW 4.86 MW
316274 AC1-208 C 50/50 7.32 MW 7.32 MW
316317 KELFORD C 50/50 0.4 MW 0.4 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.18 MW 0.18 MW
917332 KELFORD E 50/50 1.85 MW 1.85 MW
925595 AC1-034 E 50/50 3.67 MW 3.67 MW
926206 AC1-098 E 50/50 3.33 MW 3.33 MW
926214 AC1-099 E 50/50 1.1 MW 1.1 MW
315602 1HOLLOMANSOL 50/50 2.55 MW 2.55 MW
918512 AA1-065 E OP 50/50 7.65 MW 7.65 MW
316327 AA2-057 C 50/50 1.11 MW 1.11 MW
919710 AA2-057 E 50/50 3.39 MW 3.39 MW
315614 AA2-178 C 50/50 4.96 MW 4.96 MW
920692 AA2-178 E 50/50 13.0 MW 13.0 MW
923994 AB2-040_E Adder 2.97 MW 2.52 MW
316359 AB2-059 C OP 50/50 1.19 MW 1.19 MW
924152 AB2-059 E OP 50/50 3.76 MW 3.76 MW
316174 AB2-169_C 50/50 2.0 MW 2.0 MW
925122 AB2-169 E 50/50 10.96 MW 10.96 MW
316088 AB2-174 E Adder 2.96 MW 2.52 MW
313764 3SOCKMAN Adder 0.38 MW 0.33 MW
932631 AC2-084 C 50/50 0.92 MW 0.92 MW
932632 AC2-084 E 50/50 2.94 MW 2.94 MW
934321 AD1-056 C 50/50 3.99 MW 3.99 MW
934322 AD1-056 E 50/50 2.16 MW 2.16 MW
934331 AD1-057 C 50/50 2.23 MW 2.23 MW
934332 AD1-057 E 50/50 1.16 MW 1.16 MW
934501 AD1-074 C 50/50 87.18 MW 87.18 MW
934502 AD1-074 E 50/50 44.38 MW 44.38 MW
934511 AD1-075 C 50/50 21.8 MW 21.8 MW
934512 AD1-075 E 50/50 11.1 MW 11.1 MW
938531 AE1-072 C Adder -9.94 MW -8.45 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.58 MW 8.58 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.67 MW 5.67 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 25.54 MW 25.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.43 MW 0.43 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.32 MW 0.32 MW
WEC LTFEXP_WEC->PJM CLTF 0.17 MW 0.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.52 MW 3.52 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.03 MW 1.03 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.93 MW 1.93 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.74 MW 2.74 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.68 MW 1.68 MW

Details for 6WALBMRL-6S HERTFORD 230.0 kV Ckt 1 line l/o DVP_P4-2: 24642_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6WALBMRL-6S HERTFORD 230.0 kV Ckt 1 line
313885 to 314662 ckt 1
Contingency Name:
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 101.9 %
Rating: 897.0 MVA
Rating Type: C
MVA to Mitigate: 914.05 MVA
MW Contribution: 10.73 MW
Impact of Topology Modeling:
Decrease
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.72 MW 0.72 MW
961672 AG1-007 E 50/50 0.41 MW 0.41 MW
961941 AG1-037 C 50/50 0.56 MW 0.56 MW
961942 AG1-037 E 50/50 0.38 MW 0.38 MW
962331 AG1-082 C 50/50 2.25 MW 2.25 MW
962332 AG1-082 E 50/50 1.5 MW 1.5 MW
966801 AG1-551 C 50/50 2.98 MW 2.98 MW
966802 AG1-551 E 50/50 1.57 MW 1.57 MW
966811 AG1-552 C Adder 1.21 MW 1.03 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C Adder 0.4 MW 0.34 MW
965292 AG1-394 E Adder 0.73 MW 0.62 MW
315131 1EDGECMA 50/50 10.05 MW 10.05 MW
315136 1ROSEMG1 50/50 1.29 MW 1.29 MW
315137 1ROSEMS1 50/50 0.8 MW 0.8 MW
315138 1ROSEMG2 50/50 0.6 MW 0.6 MW
315139 1GASTONA 50/50 1.93 MW 1.93 MW
918492 AA1-063AE OP Adder 2.2 MW 1.87 MW
918532 AA1-067 E 50/50 0.82 MW 0.82 MW
919692 AA2-053 E OP 50/50 2.99 MW 2.99 MW
920042 AA2-088 E OP Adder 4.54 MW 3.86 MW
927146 AC1-208 E 50/50 3.25 MW 3.25 MW
934521 AD1-076 C 50/50 31.66 MW 31.66 MW
934522 AD1-076 E 50/50 16.14 MW 16.14 MW
943171 AE2-346 C 50/50 0.25 MW 0.25 MW
943172 AE2-346 E 50/50 0.68 MW 0.68 MW
315601 1CONETOE2SOL 50/50 1.11 MW 1.11 MW
315606 3AA2-053SOLA 50/50 1.06 MW 1.06 MW
316140 AB2-099 C 50/50 0.11 MW 0.11 MW
316141 AB2-099 E 50/50 0.28 MW 0.28 MW
900672 V4-068 E 50/50 0.25 MW 0.25 MW
917342 Z2-044 E 50/50 0.52 MW 0.52 MW
922923 AB1-081 E OP 50/50 2.81 MW 2.81 MW
923263 AB1-132 E OP 50/50 3.86 MW 3.86 MW
923573 AB1-173 E OP Adder 1.58 MW 1.34 MW
940491 AE2-034 C 50/50 3.65 MW 3.65 MW
940492 AE2-034 E 50/50 9.75 MW 9.75 MW
957521 AF2-046 C 50/50 11.16 MW 11.16 MW
957522 AF2-046 E 50/50 5.64 MW 5.64 MW
957861 AF2-080 C 50/50 7.43 MW 7.43 MW
957862 AF2-080 E 50/50 3.29 MW 3.29 MW
916042 Z1-036 E 50/50 111.91 MW 111.91 MW
315141 1GASTONB 50/50 1.93 MW 1.93 MW
315292 1DOMTR78 50/50 3.11 MW 3.11 MW
315611 6Z1-036WIND 50/50 2.58 MW 2.58 MW
917512 Z2-088 E OP1 50/50 4.34 MW 4.34 MW
926071 AC1-086 C 50/50 13.27 MW 13.27 MW
926072 AC1-086 E 50/50 6.04 MW 6.04 MW
927021 AC1-189 C 50/50 8.18 MW 8.18 MW
927022 AC1-189 E 50/50 4.08 MW 4.08 MW
933981 AD1-022 C 50/50 19.93 MW 19.93 MW
933982 AD1-022 E 50/50 10.85 MW 10.85 MW
962572 AG1-106 E 50/50 0.75 MW 0.75 MW
961681 AG1-008 C 50/50 11.16 MW 11.16 MW
961682 AG1-008 E 50/50 5.64 MW 5.64 MW
962571 AG1-106 C 50/50 1.72 MW 1.72 MW
314594 6PLYMOUTH TP 50/50 0.87 MW 0.87 MW
316005 AA1-067 C 50/50 0.31 MW 0.31 MW
316011 AB1-132 C OP 50/50 1.47 MW 1.47 MW
316049 AB1-081 C OP 50/50 1.07 MW 1.07 MW
316210 AC1-098 C 50/50 0.86 MW 0.86 MW
316212 AC1-099 C 50/50 0.29 MW 0.29 MW
316263 AC1-034 C 50/50 4.86 MW 4.86 MW
316274 AC1-208 C 50/50 7.32 MW 7.32 MW
316317 KELFORD C 50/50 0.4 MW 0.4 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.18 MW 0.18 MW
917332 KELFORD E 50/50 1.85 MW 1.85 MW
925595 AC1-034 E 50/50 3.67 MW 3.67 MW
926206 AC1-098 E 50/50 3.33 MW 3.33 MW
926214 AC1-099 E 50/50 1.1 MW 1.1 MW
315602 1HOLLOMANSOL 50/50 2.55 MW 2.55 MW
918512 AA1-065 E OP 50/50 7.65 MW 7.65 MW
316327 AA2-057 C 50/50 1.11 MW 1.11 MW
919710 AA2-057 E 50/50 3.39 MW 3.39 MW
315614 AA2-178 C 50/50 4.96 MW 4.96 MW
920692 AA2-178 E 50/50 13.0 MW 13.0 MW
923994 AB2-040_E Adder 2.97 MW 2.52 MW
316359 AB2-059 C OP 50/50 1.19 MW 1.19 MW
924152 AB2-059 E OP 50/50 3.76 MW 3.76 MW
316174 AB2-169_C 50/50 2.0 MW 2.0 MW
925122 AB2-169 E 50/50 10.96 MW 10.96 MW
316088 AB2-174 E Adder 2.96 MW 2.52 MW
313764 3SOCKMAN Adder 0.38 MW 0.33 MW
932631 AC2-084 C 50/50 0.92 MW 0.92 MW
932632 AC2-084 E 50/50 2.94 MW 2.94 MW
934321 AD1-056 C 50/50 3.99 MW 3.99 MW
934322 AD1-056 E 50/50 2.16 MW 2.16 MW
934331 AD1-057 C 50/50 2.23 MW 2.23 MW
934332 AD1-057 E 50/50 1.16 MW 1.16 MW
934501 AD1-074 C 50/50 87.18 MW 87.18 MW
934502 AD1-074 E 50/50 44.38 MW 44.38 MW
934511 AD1-075 C 50/50 21.8 MW 21.8 MW
934512 AD1-075 E 50/50 11.1 MW 11.1 MW
938531 AE1-072 C Adder -9.94 MW -8.45 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.58 MW 8.58 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.67 MW 5.67 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 25.54 MW 25.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.43 MW 0.43 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.32 MW 0.32 MW
WEC LTFEXP_WEC->PJM CLTF 0.17 MW 0.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.52 MW 3.52 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.03 MW 1.03 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.93 MW 1.93 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.74 MW 2.74 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.68 MW 1.68 MW

Details for 6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line l/o DVP_P4-2: 24642_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6S HERTFORD-6WINFALL 230.0 kV Ckt 1 line
314662 to 314651 ckt 1
Contingency Name:
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 101.55 %
Rating: 897.0 MVA
Rating Type: C
MVA to Mitigate: 910.93 MVA
MW Contribution: 10.73 MW
Impact of Topology Modeling:
Decrease
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.72 MW 0.72 MW
961672 AG1-007 E 50/50 0.41 MW 0.41 MW
961941 AG1-037 C 50/50 0.56 MW 0.56 MW
961942 AG1-037 E 50/50 0.38 MW 0.38 MW
962331 AG1-082 C 50/50 2.25 MW 2.25 MW
962332 AG1-082 E 50/50 1.5 MW 1.5 MW
966801 AG1-551 C 50/50 2.98 MW 2.98 MW
966802 AG1-551 E 50/50 1.57 MW 1.57 MW
966811 AG1-552 C Adder 1.21 MW 1.03 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C Adder 0.4 MW 0.34 MW
965292 AG1-394 E Adder 0.73 MW 0.62 MW
315131 1EDGECMA 50/50 10.05 MW 10.05 MW
315136 1ROSEMG1 50/50 1.29 MW 1.29 MW
315137 1ROSEMS1 50/50 0.8 MW 0.8 MW
315138 1ROSEMG2 50/50 0.6 MW 0.6 MW
315139 1GASTONA 50/50 1.93 MW 1.93 MW
918492 AA1-063AE OP Adder 2.2 MW 1.87 MW
918532 AA1-067 E 50/50 0.82 MW 0.82 MW
919692 AA2-053 E OP 50/50 2.99 MW 2.99 MW
920042 AA2-088 E OP Adder 4.54 MW 3.86 MW
927146 AC1-208 E 50/50 3.25 MW 3.25 MW
934521 AD1-076 C 50/50 31.66 MW 31.66 MW
934522 AD1-076 E 50/50 16.14 MW 16.14 MW
943171 AE2-346 C 50/50 0.25 MW 0.25 MW
943172 AE2-346 E 50/50 0.68 MW 0.68 MW
315601 1CONETOE2SOL 50/50 1.11 MW 1.11 MW
315606 3AA2-053SOLA 50/50 1.06 MW 1.06 MW
316140 AB2-099 C 50/50 0.11 MW 0.11 MW
316141 AB2-099 E 50/50 0.28 MW 0.28 MW
900672 V4-068 E 50/50 0.25 MW 0.25 MW
917342 Z2-044 E 50/50 0.52 MW 0.52 MW
922923 AB1-081 E OP 50/50 2.81 MW 2.81 MW
923263 AB1-132 E OP 50/50 3.86 MW 3.86 MW
923573 AB1-173 E OP Adder 1.58 MW 1.34 MW
940491 AE2-034 C 50/50 3.65 MW 3.65 MW
940492 AE2-034 E 50/50 9.75 MW 9.75 MW
957521 AF2-046 C 50/50 11.16 MW 11.16 MW
957522 AF2-046 E 50/50 5.64 MW 5.64 MW
957861 AF2-080 C 50/50 7.43 MW 7.43 MW
957862 AF2-080 E 50/50 3.29 MW 3.29 MW
916042 Z1-036 E 50/50 111.91 MW 111.91 MW
315141 1GASTONB 50/50 1.93 MW 1.93 MW
315292 1DOMTR78 50/50 3.11 MW 3.11 MW
315611 6Z1-036WIND 50/50 2.58 MW 2.58 MW
917512 Z2-088 E OP1 50/50 4.34 MW 4.34 MW
926071 AC1-086 C 50/50 13.27 MW 13.27 MW
926072 AC1-086 E 50/50 6.04 MW 6.04 MW
927021 AC1-189 C 50/50 8.18 MW 8.18 MW
927022 AC1-189 E 50/50 4.08 MW 4.08 MW
933981 AD1-022 C 50/50 19.93 MW 19.93 MW
933982 AD1-022 E 50/50 10.85 MW 10.85 MW
962572 AG1-106 E 50/50 0.75 MW 0.75 MW
961681 AG1-008 C 50/50 11.16 MW 11.16 MW
961682 AG1-008 E 50/50 5.64 MW 5.64 MW
962571 AG1-106 C 50/50 1.72 MW 1.72 MW
314594 6PLYMOUTH TP 50/50 0.87 MW 0.87 MW
316005 AA1-067 C 50/50 0.31 MW 0.31 MW
316011 AB1-132 C OP 50/50 1.47 MW 1.47 MW
316049 AB1-081 C OP 50/50 1.07 MW 1.07 MW
316210 AC1-098 C 50/50 0.86 MW 0.86 MW
316212 AC1-099 C 50/50 0.29 MW 0.29 MW
316263 AC1-034 C 50/50 4.86 MW 4.86 MW
316274 AC1-208 C 50/50 7.32 MW 7.32 MW
316317 KELFORD C 50/50 0.4 MW 0.4 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.18 MW 0.18 MW
917332 KELFORD E 50/50 1.85 MW 1.85 MW
925595 AC1-034 E 50/50 3.67 MW 3.67 MW
926206 AC1-098 E 50/50 3.33 MW 3.33 MW
926214 AC1-099 E 50/50 1.1 MW 1.1 MW
315602 1HOLLOMANSOL 50/50 2.55 MW 2.55 MW
918512 AA1-065 E OP 50/50 7.65 MW 7.65 MW
316327 AA2-057 C 50/50 1.11 MW 1.11 MW
919710 AA2-057 E 50/50 3.39 MW 3.39 MW
315614 AA2-178 C 50/50 4.96 MW 4.96 MW
920692 AA2-178 E 50/50 13.0 MW 13.0 MW
923994 AB2-040_E Adder 2.97 MW 2.52 MW
316359 AB2-059 C OP 50/50 1.19 MW 1.19 MW
924152 AB2-059 E OP 50/50 3.76 MW 3.76 MW
316174 AB2-169_C 50/50 2.0 MW 2.0 MW
925122 AB2-169 E 50/50 10.96 MW 10.96 MW
316088 AB2-174 E Adder 2.96 MW 2.52 MW
313764 3SOCKMAN Adder 0.38 MW 0.33 MW
932631 AC2-084 C 50/50 0.92 MW 0.92 MW
932632 AC2-084 E 50/50 2.94 MW 2.94 MW
934321 AD1-056 C 50/50 3.99 MW 3.99 MW
934322 AD1-056 E 50/50 2.16 MW 2.16 MW
934331 AD1-057 C 50/50 2.23 MW 2.23 MW
934332 AD1-057 E 50/50 1.16 MW 1.16 MW
934501 AD1-074 C 50/50 87.18 MW 87.18 MW
934502 AD1-074 E 50/50 44.38 MW 44.38 MW
934511 AD1-075 C 50/50 21.8 MW 21.8 MW
934512 AD1-075 E 50/50 11.1 MW 11.1 MW
938531 AE1-072 C Adder -9.94 MW -8.45 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.58 MW 8.58 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.67 MW 5.67 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 25.54 MW 25.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.43 MW 0.43 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.32 MW 0.32 MW
WEC LTFEXP_WEC->PJM CLTF 0.17 MW 0.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.52 MW 3.52 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.03 MW 1.03 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.93 MW 1.93 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.74 MW 2.74 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.68 MW 1.68 MW

Details for 6SAPONY-6CARSON 230.0 kV Ckt 1 line l/o DVP_P4-2: 246T247_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 131.93 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1095.02 MVA
MW Contribution: 12.8 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.12 MW 1.12 MW
961672 AG1-007 E 50/50 0.63 MW 0.63 MW
961941 AG1-037 C 50/50 0.68 MW 0.68 MW
961942 AG1-037 E 50/50 0.45 MW 0.45 MW
962331 AG1-082 C 50/50 2.71 MW 2.71 MW
962332 AG1-082 E 50/50 1.8 MW 1.8 MW
966801 AG1-551 C 50/50 2.31 MW 2.31 MW
966802 AG1-551 E 50/50 1.22 MW 1.22 MW
966811 AG1-552 C 50/50 3.53 MW 3.53 MW
966812 AG1-552 E 50/50 1.68 MW 1.68 MW
965291 AG1-394 C 50/50 0.92 MW 0.92 MW
965292 AG1-394 E 50/50 1.69 MW 1.69 MW
966621 AG1-532 C 50/50 3.43 MW 3.43 MW
966622 AG1-532 E 50/50 2.29 MW 2.29 MW
313506 AB1-173 C OP 50/50 2.38 MW 2.38 MW
314541 3WATKINS Adder 0.48 MW 0.41 MW
314572 3EMPORIA 50/50 1.02 MW 1.02 MW
314704 3LAWRENC 50/50 0.58 MW 0.58 MW
315126 1ROARAP2 50/50 2.38 MW 2.38 MW
315128 1ROARAP4 50/50 2.25 MW 2.25 MW
315131 1EDGECMA 50/50 18.84 MW 18.84 MW
315136 1ROSEMG1 50/50 4.35 MW 4.35 MW
315137 1ROSEMS1 50/50 2.69 MW 2.69 MW
315138 1ROSEMG2 50/50 2.04 MW 2.04 MW
315139 1GASTONA 50/50 6.82 MW 6.82 MW
918492 AA1-063AE OP 50/50 5.96 MW 5.96 MW
918532 AA1-067 E 50/50 0.81 MW 0.81 MW
919692 AA2-053 E OP 50/50 7.01 MW 7.01 MW
920042 AA2-088 E OP 50/50 10.84 MW 10.84 MW
925785 AC1-054 E 50/50 3.73 MW 3.73 MW
927146 AC1-208 E 50/50 6.7 MW 6.7 MW
934521 AD1-076 C Adder 11.67 MW 9.92 MW
934522 AD1-076 E Adder 5.95 MW 5.05 MW
943171 AE2-346 C 50/50 0.3 MW 0.3 MW
943172 AE2-346 E 50/50 0.81 MW 0.81 MW
960081 AF2-299 C 50/50 4.58 MW 4.58 MW
960082 AF2-299 E 50/50 3.05 MW 3.05 MW
315601 1CONETOE2SOL 50/50 1.47 MW 1.47 MW
315606 3AA2-053SOLA 50/50 2.5 MW 2.5 MW
316129 AC1-054 C 50/50 1.32 MW 1.32 MW
316140 AB2-099 C 50/50 0.13 MW 0.13 MW
316141 AB2-099 E 50/50 0.34 MW 0.34 MW
900672 V4-068 E 50/50 0.42 MW 0.42 MW
917342 Z2-044 E 50/50 1.03 MW 1.03 MW
922923 AB1-081 E OP 50/50 4.48 MW 4.48 MW
923263 AB1-132 E OP 50/50 13.65 MW 13.65 MW
923573 AB1-173 E OP 50/50 6.93 MW 6.93 MW
940492 AE2-034 E Adder 2.42 MW 2.06 MW
946281 AF1-292 C 50/50 3.79 MW 3.79 MW
946282 AF1-292 E 50/50 2.53 MW 2.53 MW
957521 AF2-046 C 50/50 17.13 MW 17.13 MW
957522 AF2-046 E 50/50 8.66 MW 8.66 MW
957861 AF2-080 C 50/50 8.87 MW 8.87 MW
957862 AF2-080 E 50/50 3.93 MW 3.93 MW
315141 1GASTONB 50/50 6.82 MW 6.82 MW
315607 3AA1-063SOLA 50/50 2.05 MW 2.05 MW
315608 3AA2-088SOLA 50/50 1.09 MW 1.09 MW
923852 AB2-025 E 50/50 4.83 MW 4.83 MW
917512 Z2-088 E OP1 50/50 5.75 MW 5.75 MW
926071 AC1-086 C 50/50 46.89 MW 46.89 MW
926072 AC1-086 E 50/50 21.34 MW 21.34 MW
927021 AC1-189 C 50/50 9.77 MW 9.77 MW
927022 AC1-189 E 50/50 4.87 MW 4.87 MW
933981 AD1-022 C 50/50 9.3 MW 9.3 MW
933982 AD1-022 E 50/50 5.07 MW 5.07 MW
962572 AG1-106 E 50/50 2.65 MW 2.65 MW
961681 AG1-008 C 50/50 17.13 MW 17.13 MW
961682 AG1-008 E 50/50 8.66 MW 8.66 MW
962571 AG1-106 C 50/50 6.07 MW 6.07 MW
314594 6PLYMOUTH TP Adder 0.3 MW 0.25 MW
316005 AA1-067 C 50/50 0.31 MW 0.31 MW
316011 AB1-132 C OP 50/50 5.2 MW 5.2 MW
316023 AB2-100 C2 50/50 2.91 MW 2.91 MW
316049 AB1-081 C OP 50/50 1.71 MW 1.71 MW
316210 AC1-098 C 50/50 1.53 MW 1.53 MW
316212 AC1-099 C 50/50 0.51 MW 0.51 MW
316263 AC1-034 C 50/50 8.0 MW 8.0 MW
316274 AC1-208 C 50/50 15.09 MW 15.09 MW
316315 AB2-025 C 50/50 1.69 MW 1.69 MW
316317 KELFORD C 50/50 0.53 MW 0.53 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.36 MW 0.36 MW
316365 AB2-100 C1 50/50 2.91 MW 2.91 MW
917332 KELFORD E 50/50 2.42 MW 2.42 MW
924516 AB2-100 E1 50/50 8.77 MW 8.77 MW
924517 AB2-100 E2 50/50 8.77 MW 8.77 MW
925595 AC1-034 E 50/50 6.03 MW 6.03 MW
926206 AC1-098 E 50/50 5.92 MW 5.92 MW
926214 AC1-099 E 50/50 1.96 MW 1.96 MW
315602 1HOLLOMANSOL 50/50 2.52 MW 2.52 MW
918512 AA1-065 E OP 50/50 7.58 MW 7.58 MW
316327 AA2-057 C 50/50 2.21 MW 2.21 MW
919710 AA2-057 E 50/50 6.73 MW 6.73 MW
920692 AA2-178 E Adder 3.23 MW 2.74 MW
316181 AB2-040 GEN 50/50 2.68 MW 2.68 MW
923994 AB2-040_E 50/50 12.99 MW 12.99 MW
316359 AB2-059 C OP 50/50 2.02 MW 2.02 MW
924152 AB2-059 E OP 50/50 6.37 MW 6.37 MW
316174 AB2-169_C 50/50 1.09 MW 1.09 MW
925122 AB2-169 E 50/50 5.97 MW 5.97 MW
316087 AB2-174 C 50/50 2.61 MW 2.61 MW
316088 AB2-174 E 50/50 14.45 MW 14.45 MW
313764 3SOCKMAN 50/50 1.35 MW 1.35 MW
932631 AC2-084 C 50/50 1.63 MW 1.63 MW
932632 AC2-084 E 50/50 5.23 MW 5.23 MW
934321 AD1-056 C 50/50 10.28 MW 10.28 MW
934322 AD1-056 E 50/50 5.57 MW 5.57 MW
934331 AD1-057 C 50/50 5.73 MW 5.73 MW
934332 AD1-057 E 50/50 2.98 MW 2.98 MW
934501 AD1-074 C Adder 32.13 MW 27.31 MW
934502 AD1-074 E Adder 16.35 MW 13.9 MW
934511 AD1-075 C Adder 8.03 MW 6.83 MW
934512 AD1-075 E Adder 4.09 MW 3.48 MW
940481 AE2-033 C 50/50 64.88 MW 64.88 MW
940482 AE2-033 E 50/50 43.74 MW 43.74 MW
940541 AE2-040 C 50/50 11.93 MW 11.93 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.46 MW 11.46 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.98 MW 7.98 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 37.26 MW 37.26 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.8 MW 0.8 MW
NY PJM->LTFIMP_NY CLTF 0.37 MW 0.37 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.44 MW 0.44 MW
WEC LTFEXP_WEC->PJM CLTF 0.23 MW 0.23 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.09 MW 5.09 MW
TVA LTFEXP_TVA->PJM CLTF 2.14 MW 2.14 MW
MEC LTFEXP_MEC->PJM CLTF 1.41 MW 1.41 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.74 MW 2.74 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.1 MW 5.1 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.43 MW 2.43 MW

Details for AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line l/o DVP_P4-2: 246T247_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
DVP_P4-2: 246T247_SRT-A
CONTINGENCY 'DVP_P4-2: 246T247_SRT-A'
 OPEN BRANCH FROM BUS 313713 TO BUS 314648 CKT 1   /*6SWAMP       230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314648 CKT 1   /*6SUFFOLK     230.0 - 6SUNBURY     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
 OPEN BUS 314648                                   /*6SUNBURY     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 131.54 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 1091.79 MVA
MW Contribution: 12.81 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.12 MW 1.12 MW
961672 AG1-007 E 50/50 0.63 MW 0.63 MW
961941 AG1-037 C 50/50 0.68 MW 0.68 MW
961942 AG1-037 E 50/50 0.45 MW 0.45 MW
962331 AG1-082 C 50/50 2.71 MW 2.71 MW
962332 AG1-082 E 50/50 1.8 MW 1.8 MW
966801 AG1-551 C 50/50 2.31 MW 2.31 MW
966802 AG1-551 E 50/50 1.22 MW 1.22 MW
966811 AG1-552 C 50/50 3.53 MW 3.53 MW
966812 AG1-552 E 50/50 1.68 MW 1.68 MW
965291 AG1-394 C 50/50 0.92 MW 0.92 MW
965292 AG1-394 E 50/50 1.69 MW 1.69 MW
966621 AG1-532 C 50/50 3.43 MW 3.43 MW
966622 AG1-532 E 50/50 2.29 MW 2.29 MW
313506 AB1-173 C OP 50/50 2.38 MW 2.38 MW
314541 3WATKINS Adder 0.48 MW 0.41 MW
314572 3EMPORIA 50/50 1.02 MW 1.02 MW
314704 3LAWRENC 50/50 0.58 MW 0.58 MW
315126 1ROARAP2 50/50 2.38 MW 2.38 MW
315128 1ROARAP4 50/50 2.25 MW 2.25 MW
315131 1EDGECMA 50/50 18.85 MW 18.85 MW
315136 1ROSEMG1 50/50 4.35 MW 4.35 MW
315137 1ROSEMS1 50/50 2.69 MW 2.69 MW
315138 1ROSEMG2 50/50 2.04 MW 2.04 MW
315139 1GASTONA 50/50 6.82 MW 6.82 MW
918492 AA1-063AE OP 50/50 5.96 MW 5.96 MW
918532 AA1-067 E 50/50 0.81 MW 0.81 MW
919692 AA2-053 E OP 50/50 7.01 MW 7.01 MW
920042 AA2-088 E OP 50/50 10.85 MW 10.85 MW
925785 AC1-054 E 50/50 3.73 MW 3.73 MW
927146 AC1-208 E 50/50 6.7 MW 6.7 MW
934521 AD1-076 C 50/50 11.67 MW 11.67 MW
934522 AD1-076 E 50/50 5.95 MW 5.95 MW
943171 AE2-346 C 50/50 0.3 MW 0.3 MW
943172 AE2-346 E 50/50 0.81 MW 0.81 MW
960081 AF2-299 C 50/50 4.58 MW 4.58 MW
960082 AF2-299 E 50/50 3.05 MW 3.05 MW
315601 1CONETOE2SOL 50/50 1.47 MW 1.47 MW
315606 3AA2-053SOLA 50/50 2.5 MW 2.5 MW
316129 AC1-054 C 50/50 1.32 MW 1.32 MW
316140 AB2-099 C 50/50 0.13 MW 0.13 MW
316141 AB2-099 E 50/50 0.34 MW 0.34 MW
900672 V4-068 E 50/50 0.42 MW 0.42 MW
917342 Z2-044 E 50/50 1.03 MW 1.03 MW
922923 AB1-081 E OP 50/50 4.48 MW 4.48 MW
923263 AB1-132 E OP 50/50 13.65 MW 13.65 MW
923573 AB1-173 E OP 50/50 6.93 MW 6.93 MW
940491 AE2-034 C 50/50 0.91 MW 0.91 MW
940492 AE2-034 E 50/50 2.42 MW 2.42 MW
946281 AF1-292 C 50/50 3.79 MW 3.79 MW
946282 AF1-292 E 50/50 2.53 MW 2.53 MW
957521 AF2-046 C 50/50 17.14 MW 17.14 MW
957522 AF2-046 E 50/50 8.66 MW 8.66 MW
957861 AF2-080 C 50/50 8.87 MW 8.87 MW
957862 AF2-080 E 50/50 3.93 MW 3.93 MW
315141 1GASTONB 50/50 6.82 MW 6.82 MW
315292 1DOMTR78 50/50 1.35 MW 1.35 MW
315607 3AA1-063SOLA 50/50 2.06 MW 2.06 MW
315608 3AA2-088SOLA 50/50 1.09 MW 1.09 MW
917512 Z2-088 E OP1 50/50 5.75 MW 5.75 MW
926071 AC1-086 C 50/50 46.9 MW 46.9 MW
926072 AC1-086 E 50/50 21.35 MW 21.35 MW
927021 AC1-189 C 50/50 9.77 MW 9.77 MW
927022 AC1-189 E 50/50 4.87 MW 4.87 MW
933981 AD1-022 C 50/50 9.31 MW 9.31 MW
933982 AD1-022 E 50/50 5.07 MW 5.07 MW
962572 AG1-106 E 50/50 2.65 MW 2.65 MW
961681 AG1-008 C 50/50 17.14 MW 17.14 MW
961682 AG1-008 E 50/50 8.66 MW 8.66 MW
962571 AG1-106 C 50/50 6.07 MW 6.07 MW
314594 6PLYMOUTH TP 50/50 0.3 MW 0.3 MW
316005 AA1-067 C 50/50 0.31 MW 0.31 MW
316011 AB1-132 C OP 50/50 5.21 MW 5.21 MW
316023 AB2-100 C2 50/50 2.91 MW 2.91 MW
316049 AB1-081 C OP 50/50 1.71 MW 1.71 MW
316210 AC1-098 C 50/50 1.53 MW 1.53 MW
316212 AC1-099 C 50/50 0.51 MW 0.51 MW
316263 AC1-034 C 50/50 8.0 MW 8.0 MW
316274 AC1-208 C 50/50 15.1 MW 15.1 MW
316317 KELFORD C 50/50 0.53 MW 0.53 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.36 MW 0.36 MW
316365 AB2-100 C1 50/50 2.91 MW 2.91 MW
917332 KELFORD E 50/50 2.42 MW 2.42 MW
924516 AB2-100 E1 50/50 8.77 MW 8.77 MW
924517 AB2-100 E2 50/50 8.77 MW 8.77 MW
925595 AC1-034 E 50/50 6.04 MW 6.04 MW
926206 AC1-098 E 50/50 5.92 MW 5.92 MW
926214 AC1-099 E 50/50 1.96 MW 1.96 MW
315602 1HOLLOMANSOL 50/50 2.52 MW 2.52 MW
918512 AA1-065 E OP 50/50 7.58 MW 7.58 MW
316327 AA2-057 C 50/50 2.21 MW 2.21 MW
919710 AA2-057 E 50/50 6.73 MW 6.73 MW
315614 AA2-178 C 50/50 1.23 MW 1.23 MW
920692 AA2-178 E 50/50 3.23 MW 3.23 MW
316181 AB2-040 GEN 50/50 2.68 MW 2.68 MW
923994 AB2-040_E 50/50 12.99 MW 12.99 MW
316359 AB2-059 C OP 50/50 2.02 MW 2.02 MW
924152 AB2-059 E OP 50/50 6.37 MW 6.37 MW
316174 AB2-169_C 50/50 1.09 MW 1.09 MW
925122 AB2-169 E 50/50 5.97 MW 5.97 MW
316087 AB2-174 C 50/50 2.61 MW 2.61 MW
316088 AB2-174 E 50/50 14.45 MW 14.45 MW
313764 3SOCKMAN 50/50 1.35 MW 1.35 MW
932631 AC2-084 C 50/50 1.63 MW 1.63 MW
932632 AC2-084 E 50/50 5.23 MW 5.23 MW
934321 AD1-056 C 50/50 10.28 MW 10.28 MW
934322 AD1-056 E 50/50 5.58 MW 5.58 MW
934331 AD1-057 C 50/50 5.73 MW 5.73 MW
934332 AD1-057 E 50/50 2.99 MW 2.99 MW
934501 AD1-074 C 50/50 32.14 MW 32.14 MW
934502 AD1-074 E 50/50 16.36 MW 16.36 MW
934511 AD1-075 C 50/50 8.04 MW 8.04 MW
934512 AD1-075 E 50/50 4.09 MW 4.09 MW
940481 AE2-033 C 50/50 64.88 MW 64.88 MW
940482 AE2-033 E 50/50 43.74 MW 43.74 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.57 MW 11.57 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.02 MW 8.02 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 37.33 MW 37.33 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.79 MW 0.79 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.44 MW 0.44 MW
WEC LTFEXP_WEC->PJM CLTF 0.24 MW 0.24 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.1 MW 5.1 MW
TVA LTFEXP_TVA->PJM CLTF 2.15 MW 2.15 MW
MEC LTFEXP_MEC->PJM CLTF 1.42 MW 1.42 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.76 MW 2.76 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.05 MW 5.05 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.43 MW 2.43 MW

Details for 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line l/o DVP_P4-2: 2058T2167_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CPLE/DVP
Facility Description:
6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
Contingency Name:
DVP_P4-2: 2058T2167_SRT-A
CONTINGENCY 'DVP_P4-2: 2058T2167_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314564 CKT 1   /*6HATHAWAY    230.0 - 6EDGECOM     230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 119.3 %
Rating: 478.0 MVA
Rating Type: B
MVA to Mitigate: 570.27 MVA
MW Contribution: 29.25 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 2.51 MW 2.51 MW
961672 AG1-007 E 50/50 1.42 MW 1.42 MW
961941 AG1-037 C 50/50 0.46 MW 0.46 MW
961942 AG1-037 E 50/50 0.31 MW 0.31 MW
962331 AG1-082 C 50/50 1.85 MW 1.85 MW
962332 AG1-082 E 50/50 1.23 MW 1.23 MW
966801 AG1-551 C 50/50 4.93 MW 4.93 MW
966802 AG1-551 E 50/50 2.59 MW 2.59 MW
966811 AG1-552 C Adder 0.84 MW 0.72 MW
966812 AG1-552 E Adder 0.4 MW 0.34 MW
965291 AG1-394 C Adder 0.44 MW 0.37 MW
965292 AG1-394 E Adder 0.81 MW 0.69 MW
314541 3WATKINS Adder 0.31 MW 0.26 MW
315131 1EDGECMA 50/50 41.79 MW 41.79 MW
918492 AA1-063AE OP Adder 1.84 MW 1.56 MW
918532 AA1-067 E 50/50 1.88 MW 1.88 MW
919692 AA2-053 E OP Adder 2.17 MW 1.85 MW
920042 AA2-088 E OP Adder 5.35 MW 4.54 MW
927146 AC1-208 E Adder 2.42 MW 2.06 MW
934521 AD1-076 C 50/50 13.16 MW 13.16 MW
934522 AD1-076 E 50/50 6.71 MW 6.71 MW
943171 AE2-346 C 50/50 0.2 MW 0.2 MW
943172 AE2-346 E 50/50 0.56 MW 0.56 MW
315601 1CONETOE2SOL 50/50 3.33 MW 3.33 MW
316140 AB2-099 C 50/50 0.09 MW 0.09 MW
316141 AB2-099 E 50/50 0.23 MW 0.23 MW
900672 V4-068 E 50/50 0.24 MW 0.24 MW
917342 Z2-044 E 50/50 0.39 MW 0.39 MW
922923 AB1-081 E OP 50/50 10.03 MW 10.03 MW
940491 AE2-034 C 50/50 1.05 MW 1.05 MW
940492 AE2-034 E 50/50 2.8 MW 2.8 MW
957521 AF2-046 C 50/50 10.12 MW 10.12 MW
957522 AF2-046 E 50/50 5.12 MW 5.12 MW
957861 AF2-080 C 50/50 20.27 MW 20.27 MW
957862 AF2-080 E 50/50 8.98 MW 8.98 MW
314539 3UNCAMP Adder 2.56 MW 2.18 MW
916042 Z1-036 E 50/50 19.57 MW 19.57 MW
938771 AE1-103 C Adder 1.18 MW 1.0 MW
938772 AE1-103 E Adder 1.63 MW 1.39 MW
315292 1DOMTR78 50/50 1.92 MW 1.92 MW
315611 6Z1-036WIND 50/50 0.45 MW 0.45 MW
913392 Y1-086 E Adder 0.88 MW 0.75 MW
923832 AB2-022 E Adder 0.5 MW 0.42 MW
901082 W1-029 E Adder 15.31 MW 13.01 MW
917122 Z2-027 E Adder 0.58 MW 0.5 MW
917512 Z2-088 E OP1 50/50 13.04 MW 13.04 MW
927021 AC1-189 C 50/50 22.32 MW 22.32 MW
927022 AC1-189 E 50/50 11.12 MW 11.12 MW
933981 AD1-022 C 50/50 9.49 MW 9.49 MW
933982 AD1-022 E 50/50 5.17 MW 5.17 MW
961681 AG1-008 C 50/50 10.12 MW 10.12 MW
961682 AG1-008 E 50/50 5.12 MW 5.12 MW
314594 6PLYMOUTH TP 50/50 0.34 MW 0.34 MW
316005 AA1-067 C 50/50 0.72 MW 0.72 MW
316049 AB1-081 C OP 50/50 3.82 MW 3.82 MW
316210 AC1-098 C 50/50 0.65 MW 0.65 MW
316212 AC1-099 C 50/50 0.22 MW 0.22 MW
316263 AC1-034 C 50/50 17.86 MW 17.86 MW
316274 AC1-208 C Adder 5.45 MW 4.64 MW
316317 KELFORD C 50/50 0.32 MW 0.32 MW
316318 V4-068 C 50/50 0.05 MW 0.05 MW
316319 Z2-044 C 50/50 0.14 MW 0.14 MW
917332 KELFORD E 50/50 1.46 MW 1.46 MW
925595 AC1-034 E 50/50 13.48 MW 13.48 MW
926206 AC1-098 E 50/50 2.53 MW 2.53 MW
926214 AC1-099 E 50/50 0.84 MW 0.84 MW
315602 1HOLLOMANSOL 50/50 2.03 MW 2.03 MW
918512 AA1-065 E OP 50/50 6.11 MW 6.11 MW
316327 AA2-057 C 50/50 0.83 MW 0.83 MW
919710 AA2-057 E 50/50 2.54 MW 2.54 MW
315614 AA2-178 C 50/50 1.42 MW 1.42 MW
920692 AA2-178 E 50/50 3.73 MW 3.73 MW
316359 AB2-059 C OP 50/50 4.51 MW 4.51 MW
924152 AB2-059 E OP 50/50 14.21 MW 14.21 MW
316174 AB2-169_C 50/50 1.9 MW 1.9 MW
925122 AB2-169 E 50/50 10.42 MW 10.42 MW
932631 AC2-084 C 50/50 0.7 MW 0.7 MW
932632 AC2-084 E 50/50 2.24 MW 2.24 MW
934501 AD1-074 C 50/50 36.24 MW 36.24 MW
934502 AD1-074 E 50/50 18.45 MW 18.45 MW
934511 AD1-075 C 50/50 9.06 MW 9.06 MW
934512 AD1-075 E 50/50 4.61 MW 4.61 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.28 MW 0.28 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.74 MW 0.74 MW
VTF LTFEXP_VFT->PJM CMTX 1.96 MW 1.96 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 4.22 MW 4.22 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 2.78 MW 2.78 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 1.27 MW 1.27 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 3.66 MW 3.66 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.61 MW 0.61 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 1.94 MW 1.94 MW
MDU PJM->LTFIMP_MDU CLTF 0.13 MW 0.13 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 1.28 MW 1.28 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 5.1 MW 5.1 MW

Details for 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line l/o DVP_P4-2: 24642_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P4-2: 24642_SRT-A
CONTINGENCY 'DVP_P4-2: 24642_SRT-A'
 OPEN BRANCH FROM BUS 314536 TO BUS 314537 CKT 3   /*3SUFFOLK     115.0 - 6SUFFOLK     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314537 TO BUS 314928 CKT 2   /*6SUFFOLK     230.0 - 8SUFFOLK     500.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 116.2 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 964.47 MVA
MW Contribution: 12.4 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.09 MW 1.09 MW
961672 AG1-007 E 50/50 0.62 MW 0.62 MW
961941 AG1-037 C 50/50 0.66 MW 0.66 MW
961942 AG1-037 E 50/50 0.44 MW 0.44 MW
962331 AG1-082 C 50/50 2.63 MW 2.63 MW
962332 AG1-082 E 50/50 1.76 MW 1.76 MW
966801 AG1-551 C 50/50 2.2 MW 2.2 MW
966802 AG1-551 E 50/50 1.16 MW 1.16 MW
966811 AG1-552 C 50/50 3.49 MW 3.49 MW
966812 AG1-552 E 50/50 1.66 MW 1.66 MW
965291 AG1-394 C 50/50 0.92 MW 0.92 MW
965292 AG1-394 E 50/50 1.7 MW 1.7 MW
966621 AG1-532 C 50/50 3.42 MW 3.42 MW
966622 AG1-532 E 50/50 2.28 MW 2.28 MW
313506 AB1-173 C OP 50/50 2.37 MW 2.37 MW
314541 3WATKINS Adder 0.5 MW 0.42 MW
314572 3EMPORIA 50/50 1.01 MW 1.01 MW
314704 3LAWRENC 50/50 0.57 MW 0.57 MW
315126 1ROARAP2 50/50 2.35 MW 2.35 MW
315128 1ROARAP4 50/50 2.23 MW 2.23 MW
315131 1EDGECMA 50/50 18.48 MW 18.48 MW
315136 1ROSEMG1 50/50 4.31 MW 4.31 MW
315137 1ROSEMS1 50/50 2.67 MW 2.67 MW
315138 1ROSEMG2 50/50 2.02 MW 2.02 MW
315139 1GASTONA 50/50 6.75 MW 6.75 MW
918492 AA1-063AE OP 50/50 5.93 MW 5.93 MW
918532 AA1-067 E 50/50 0.78 MW 0.78 MW
919692 AA2-053 E OP 50/50 6.91 MW 6.91 MW
920042 AA2-088 E OP 50/50 10.94 MW 10.94 MW
925785 AC1-054 E 50/50 3.69 MW 3.69 MW
927146 AC1-208 E 50/50 6.6 MW 6.6 MW
934521 AD1-076 C 50/50 10.41 MW 10.41 MW
934522 AD1-076 E 50/50 5.31 MW 5.31 MW
943171 AE2-346 C 50/50 0.29 MW 0.29 MW
943172 AE2-346 E 50/50 0.79 MW 0.79 MW
960081 AF2-299 C 50/50 4.56 MW 4.56 MW
960082 AF2-299 E 50/50 3.04 MW 3.04 MW
315601 1CONETOE2SOL 50/50 1.43 MW 1.43 MW
315606 3AA2-053SOLA 50/50 2.47 MW 2.47 MW
316129 AC1-054 C 50/50 1.31 MW 1.31 MW
316140 AB2-099 C 50/50 0.13 MW 0.13 MW
316141 AB2-099 E 50/50 0.33 MW 0.33 MW
900672 V4-068 E 50/50 0.42 MW 0.42 MW
917342 Z2-044 E 50/50 1.01 MW 1.01 MW
922923 AB1-081 E OP 50/50 4.38 MW 4.38 MW
923263 AB1-132 E OP 50/50 13.52 MW 13.52 MW
923573 AB1-173 E OP 50/50 6.88 MW 6.88 MW
940492 AE2-034 E Adder 2.03 MW 1.73 MW
946281 AF1-292 C 50/50 3.77 MW 3.77 MW
946282 AF1-292 E 50/50 2.51 MW 2.51 MW
957521 AF2-046 C 50/50 16.92 MW 16.92 MW
957522 AF2-046 E 50/50 8.55 MW 8.55 MW
957861 AF2-080 C 50/50 8.59 MW 8.59 MW
957862 AF2-080 E 50/50 3.81 MW 3.81 MW
314539 3UNCAMP Adder 3.54 MW 3.01 MW
315141 1GASTONB 50/50 6.75 MW 6.75 MW
315292 1DOMTR78 50/50 1.23 MW 1.23 MW
315607 3AA1-063SOLA 50/50 2.04 MW 2.04 MW
315608 3AA2-088SOLA 50/50 1.1 MW 1.1 MW
917512 Z2-088 E OP1 50/50 5.59 MW 5.59 MW
926071 AC1-086 C 50/50 46.44 MW 46.44 MW
926072 AC1-086 E 50/50 21.14 MW 21.14 MW
927021 AC1-189 C 50/50 9.46 MW 9.46 MW
927022 AC1-189 E 50/50 4.71 MW 4.71 MW
933981 AD1-022 C 50/50 8.52 MW 8.52 MW
933982 AD1-022 E 50/50 4.64 MW 4.64 MW
962572 AG1-106 E 50/50 2.63 MW 2.63 MW
961681 AG1-008 C 50/50 16.92 MW 16.92 MW
961682 AG1-008 E 50/50 8.55 MW 8.55 MW
962571 AG1-106 C 50/50 6.01 MW 6.01 MW
314594 6PLYMOUTH TP 50/50 0.27 MW 0.27 MW
316005 AA1-067 C 50/50 0.3 MW 0.3 MW
316011 AB1-132 C OP 50/50 5.15 MW 5.15 MW
316023 AB2-100 C2 50/50 2.9 MW 2.9 MW
316049 AB1-081 C OP 50/50 1.67 MW 1.67 MW
316210 AC1-098 C 50/50 1.5 MW 1.5 MW
316212 AC1-099 C 50/50 0.5 MW 0.5 MW
316263 AC1-034 C 50/50 7.82 MW 7.82 MW
316274 AC1-208 C 50/50 14.86 MW 14.86 MW
316317 KELFORD C 50/50 0.51 MW 0.51 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.36 MW 0.36 MW
316365 AB2-100 C1 50/50 2.9 MW 2.9 MW
917332 KELFORD E 50/50 2.36 MW 2.36 MW
924516 AB2-100 E1 50/50 8.73 MW 8.73 MW
924517 AB2-100 E2 50/50 8.73 MW 8.73 MW
925595 AC1-034 E 50/50 5.9 MW 5.9 MW
926206 AC1-098 E 50/50 5.81 MW 5.81 MW
926214 AC1-099 E 50/50 1.92 MW 1.92 MW
315602 1HOLLOMANSOL 50/50 2.43 MW 2.43 MW
918512 AA1-065 E OP 50/50 7.3 MW 7.3 MW
316327 AA2-057 C 50/50 2.17 MW 2.17 MW
919710 AA2-057 E 50/50 6.62 MW 6.62 MW
920692 AA2-178 E Adder 2.71 MW 2.3 MW
316181 AB2-040 GEN 50/50 2.67 MW 2.67 MW
923994 AB2-040_E 50/50 12.9 MW 12.9 MW
316359 AB2-059 C OP 50/50 1.98 MW 1.98 MW
924152 AB2-059 E OP 50/50 6.23 MW 6.23 MW
316174 AB2-169_C 50/50 1.01 MW 1.01 MW
925122 AB2-169 E 50/50 5.54 MW 5.54 MW
316087 AB2-174 C 50/50 2.59 MW 2.59 MW
316088 AB2-174 E 50/50 14.36 MW 14.36 MW
313764 3SOCKMAN 50/50 1.34 MW 1.34 MW
932631 AC2-084 C 50/50 1.6 MW 1.6 MW
932632 AC2-084 E 50/50 5.13 MW 5.13 MW
934321 AD1-056 C 50/50 10.13 MW 10.13 MW
934322 AD1-056 E 50/50 5.5 MW 5.5 MW
934331 AD1-057 C 50/50 5.65 MW 5.65 MW
934332 AD1-057 E 50/50 2.94 MW 2.94 MW
934501 AD1-074 C 50/50 28.68 MW 28.68 MW
934502 AD1-074 E 50/50 14.6 MW 14.6 MW
934511 AD1-075 C 50/50 7.17 MW 7.17 MW
934512 AD1-075 E 50/50 3.65 MW 3.65 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.25 MW 11.25 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.81 MW 7.81 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 36.34 MW 36.34 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.78 MW 0.78 MW
NY PJM->LTFIMP_NY CLTF 0.35 MW 0.35 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.43 MW 0.43 MW
WEC LTFEXP_WEC->PJM CLTF 0.23 MW 0.23 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.96 MW 4.96 MW
TVA LTFEXP_TVA->PJM CLTF 2.09 MW 2.09 MW
MEC LTFEXP_MEC->PJM CLTF 1.38 MW 1.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.68 MW 2.68 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.93 MW 4.93 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.37 MW 2.37 MW

Details for 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line l/o DVP_P4-2: H1T567_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
DVP_P4-2: H1T567_SRT-A
CONTINGENCY 'DVP_P4-2: H1T567_SRT-A'
 OPEN BRANCH FROM BUS 314214 TO BUS 314903 CKT 1   /*6CHCKAHM     230.0 - 8CHCKAHM     500.0
 OPEN BRANCH FROM BUS 314903 TO BUS 314924 CKT 1   /*8CHCKAHM     500.0 - 8SURRY       500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 105.01 %
Rating: 3940.0 MVA
Rating Type: C
MVA to Mitigate: 4137.47 MVA
MW Contribution: 15.66 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961941 AG1-037 C Adder 0.74 MW 0.63 MW
961942 AG1-037 E Adder 0.5 MW 0.42 MW
962331 AG1-082 C Adder 2.98 MW 2.53 MW
962332 AG1-082 E Adder 1.99 MW 1.69 MW
963041 AG1-153 C 50/50 9.97 MW 9.97 MW
963042 AG1-153 E 50/50 14.95 MW 14.95 MW
964791 AG1-342 C Adder 4.84 MW 4.12 MW
964792 AG1-342 E Adder 3.23 MW 2.74 MW
966801 AG1-551 C Adder 3.04 MW 2.59 MW
966802 AG1-551 E Adder 1.6 MW 1.36 MW
966811 AG1-552 C Adder 2.99 MW 2.54 MW
966812 AG1-552 E Adder 1.42 MW 1.21 MW
965291 AG1-394 C Adder 1.26 MW 1.07 MW
965292 AG1-394 E Adder 2.32 MW 1.97 MW
966621 AG1-532 C Adder 2.01 MW 1.71 MW
966622 AG1-532 E Adder 1.34 MW 1.14 MW
314541 3WATKINS Adder 1.02 MW 0.87 MW
314572 3EMPORIA Adder 0.62 MW 0.53 MW
918492 AA1-063AE OP Adder 5.97 MW 5.07 MW
918532 AA1-067 E Adder 1.03 MW 0.87 MW
919692 AA2-053 E OP Adder 6.16 MW 5.24 MW
920042 AA2-088 E OP Adder 15.64 MW 13.3 MW
925785 AC1-054 E Adder 4.92 MW 4.18 MW
926274 AC1-105 E Adder 3.64 MW 3.1 MW
927146 AC1-208 E Adder 6.05 MW 5.14 MW
934521 AD1-076 C Adder 18.29 MW 15.54 MW
934522 AD1-076 E Adder 9.32 MW 7.92 MW
943172 AE2-346 E Adder 0.89 MW 0.76 MW
944011 AF1-069 C 50/50 23.47 MW 23.47 MW
944012 AF1-069 E 50/50 9.12 MW 9.12 MW
960081 AF2-299 C Adder 2.69 MW 2.28 MW
960082 AF2-299 E Adder 1.79 MW 1.52 MW
316141 AB2-099 E Adder 0.37 MW 0.32 MW
900672 V4-068 E Adder 0.53 MW 0.45 MW
917342 Z2-044 E Adder 0.94 MW 0.8 MW
923263 AB1-132 E OP Adder 8.78 MW 7.46 MW
923573 AB1-173 E OP Adder 4.74 MW 4.03 MW
924162 AB2-060 E OP Adder 5.93 MW 5.04 MW
924302 AB2-077 E O1 Adder 1.87 MW 1.59 MW
924312 AB2-078 E O1 Adder 1.87 MW 1.59 MW
924322 AB2-079 E O1 Adder 1.87 MW 1.59 MW
925612 AC1-036 E Adder 1.15 MW 0.97 MW
939181 AE1-148 C Adder 12.7 MW 10.79 MW
939182 AE1-148 E Adder 8.47 MW 7.2 MW
940492 AE2-034 E Adder 4.64 MW 3.95 MW
941031 AE2-094 C 50/50 71.84 MW 71.84 MW
941032 AE2-094 E 50/50 32.18 MW 32.18 MW
946281 AF1-292 C Adder 2.22 MW 1.89 MW
946282 AF1-292 E Adder 1.48 MW 1.26 MW
957481 AF2-042 C 50/50 85.03 MW 85.03 MW
957482 AF2-042 E 50/50 56.68 MW 56.68 MW
957521 AF2-046 C Adder 20.93 MW 17.79 MW
957522 AF2-046 E Adder 10.58 MW 8.99 MW
957861 AF2-080 C Adder 10.85 MW 9.22 MW
957862 AF2-080 E Adder 4.81 MW 4.09 MW
314539 3UNCAMP Adder 9.02 MW 7.67 MW
916042 Z1-036 E Adder 43.5 MW 36.98 MW
938771 AE1-103 C Adder 4.35 MW 3.69 MW
938772 AE1-103 E Adder 6.0 MW 5.1 MW
314507 3THOMPSN Adder 3.11 MW 2.64 MW
314525 6KINGFORK Adder 1.48 MW 1.26 MW
314550 6HICKORY 50/50 3.42 MW 3.42 MW
315092 1YORKTN3 Adder 100.08 MW 85.07 MW
926662 AC1-147 E Adder 2.04 MW 1.73 MW
926755 AC1-161 E 50/50 21.29 MW 21.29 MW
935112 AD1-144 E Adder 1.37 MW 1.17 MW
942341 AE2-247 C Adder 2.08 MW 1.77 MW
942342 AE2-247 E Adder 2.87 MW 2.44 MW
943461 AF1-017 C Adder 1.88 MW 1.6 MW
943462 AF1-017 E Adder 3.07 MW 2.61 MW
943612 AF1-032 E Adder 1.41 MW 1.2 MW
315102 1BRUNSWICKG1 50/50 14.71 MW 14.71 MW
315103 1BRUNSWICKG2 50/50 14.71 MW 14.71 MW
315104 1BRUNSWICKG3 50/50 14.71 MW 14.71 MW
315105 1BRUNSWICKS1 50/50 30.56 MW 30.56 MW
315108 1ELIZAR1 50/50 4.94 MW 4.94 MW
315109 1ELIZAR2 50/50 4.86 MW 4.86 MW
315110 1ELIZAR3 50/50 5.01 MW 5.01 MW
315233 1SURRY 2 50/50 38.77 MW 38.77 MW
315241 1Z1-086 GT1 50/50 18.86 MW 18.86 MW
315242 1Z1-086 GT2 50/50 18.85 MW 18.85 MW
315243 1Z1-086 GT3 50/50 18.85 MW 18.85 MW
315244 1Z1-086 ST 50/50 32.82 MW 32.82 MW
315260 1GOSPORTA 50/50 3.28 MW 3.28 MW
315261 1GOSPORTB 50/50 4.18 MW 4.18 MW
315262 1GOSPORTC 50/50 3.55 MW 3.55 MW
913392 Y1-086 E Adder 3.4 MW 2.89 MW
916192 Z1-068 E 50/50 2.92 MW 2.92 MW
923832 AB2-022 E Adder 1.92 MW 1.63 MW
923852 AB2-025 E Adder 1.68 MW 1.42 MW
939312 AE1-162 E Adder 1.91 MW 1.63 MW
957492 AF2-043 E Adder 2.17 MW 1.85 MW
901082 W1-029 E Adder 48.89 MW 41.55 MW
917122 Z2-027 E Adder 2.07 MW 1.76 MW
925522 AC1-027 E 50/50 1.89 MW 1.89 MW
957871 AF2-081 C 50/50 15.62 MW 15.62 MW
957872 AF2-081 E 50/50 6.69 MW 6.69 MW
958161 AF2-110 C Adder 2.04 MW 1.73 MW
958162 AF2-110 E Adder 3.24 MW 2.76 MW
314722 3TWITTYS Adder 1.27 MW 1.08 MW
917512 Z2-088 E OP1 Adder 6.92 MW 5.88 MW
926071 AC1-086 C Adder 30.16 MW 25.64 MW
926072 AC1-086 E Adder 13.73 MW 11.67 MW
927021 AC1-189 C Adder 11.95 MW 10.15 MW
927022 AC1-189 E Adder 5.95 MW 5.06 MW
933291 AC2-141 C 50/50 49.88 MW 49.88 MW
933292 AC2-141 E 50/50 21.29 MW 21.29 MW
934621 AD1-088 C Adder 18.6 MW 15.81 MW
934622 AD1-088 E Adder 8.76 MW 7.44 MW
939411 AE1-173 C 50/50 159.01 MW 159.01 MW
939412 AE1-173 E 50/50 106.0 MW 106.0 MW
916191 Z1-068 C 50/50 0.07 MW 0.07 MW
933981 AD1-022 C Adder 13.05 MW 11.09 MW
933982 AD1-022 E Adder 7.1 MW 6.04 MW
962572 AG1-106 E Adder 1.71 MW 1.45 MW
961681 AG1-008 C Adder 20.93 MW 17.79 MW
961682 AG1-008 E Adder 10.58 MW 8.99 MW
962571 AG1-106 C Adder 3.9 MW 3.32 MW
314594 6PLYMOUTH TP Adder 0.48 MW 0.41 MW
314632 6AYDLETT TAP 50/50 2.11 MW 2.11 MW
316185 AD1-033 C 50/50 1.93 MW 1.93 MW
316274 AC1-208 C Adder 13.62 MW 11.58 MW
316294 AC1-161 C 50/50 8.15 MW 8.15 MW
316316 AC1-027 C 50/50 0.49 MW 0.49 MW
917332 KELFORD E Adder 2.45 MW 2.08 MW
924516 AB2-100 E1 Adder 4.16 MW 3.54 MW
924517 AB2-100 E2 Adder 4.16 MW 3.54 MW
926206 AC1-098 E Adder 5.52 MW 4.69 MW
926214 AC1-099 E Adder 1.82 MW 1.55 MW
934065 AD1-033 E 50/50 7.87 MW 7.87 MW
937226 AE2-253 E 50/50 9.15 MW 9.15 MW
918512 AA1-065 E OP Adder 8.15 MW 6.93 MW
316017 AA1-139 ULT1 50/50 1.69 MW 1.69 MW
316018 AA1-139 ULT2 50/50 1.69 MW 1.69 MW
919153 AA1-139 E2 50/50 6.39 MW 6.39 MW
919152 AA1-139 E1 50/50 6.39 MW 6.39 MW
919710 AA2-057 E Adder 6.12 MW 5.21 MW
920692 AA2-178 E Adder 6.19 MW 5.26 MW
923994 AB2-040_E Adder 8.89 MW 7.56 MW
924022 AB2-043 E O1 Adder 7.24 MW 6.15 MW
316084 AB2-161 E Adder 6.88 MW 5.85 MW
925122 AB2-169 E Adder 8.43 MW 7.17 MW
316088 AB2-174 E Adder 9.4 MW 7.99 MW
932046 AC2-012 E Adder 20.16 MW 17.13 MW
316311 AC2-079 C Adder 8.06 MW 6.85 MW
932596 AC2-079 E Adder 13.16 MW 11.18 MW
934576 AD1-082 E Adder 5.48 MW 4.66 MW
316349 AD2-085 C Adder 4.8 MW 4.08 MW
936666 AD2-085 E Adder 7.83 MW 6.65 MW
316388 AE2-253 GEN 50/50 3.08 MW 3.08 MW
941591 AE2-156 C 50/50 27.57 MW 27.57 MW
944581 AF1-123 C 50/50 71.32 MW 71.32 MW
944582 AF1-123 E 50/50 163.32 MW 163.32 MW
944591 AF1-124 C 50/50 71.58 MW 71.58 MW
944592 AF1-124 E 50/50 163.91 MW 163.91 MW
944601 AF1-125 C 50/50 70.22 MW 70.22 MW
944602 AF1-125 E 50/50 160.75 MW 160.75 MW
962491 AG1-098 C Adder 16.49 MW 14.02 MW
962492 AG1-098 E Adder 10.99 MW 9.34 MW
962561 AG1-105 C Adder 12.18 MW 10.36 MW
962562 AG1-105 E Adder 8.12 MW 6.91 MW
964241 AG1-285 C Adder 18.2 MW 15.47 MW
964242 AG1-285 E Adder 12.14 MW 10.31 MW
313764 3SOCKMAN Adder 1.03 MW 0.88 MW
932632 AC2-084 E Adder 4.88 MW 4.14 MW
934321 AD1-056 C Adder 8.83 MW 7.51 MW
934322 AD1-056 E Adder 4.79 MW 4.07 MW
934331 AD1-057 C Adder 4.93 MW 4.19 MW
934332 AD1-057 E Adder 2.57 MW 2.18 MW
934501 AD1-074 C Adder 50.35 MW 42.8 MW
934502 AD1-074 E Adder 25.63 MW 21.79 MW
934511 AD1-075 C Adder 12.59 MW 10.7 MW
934512 AD1-075 E Adder 6.41 MW 5.45 MW
934612 AD1-087 E Adder 5.5 MW 4.67 MW
935172 AD1-152 E Adder 8.05 MW 6.84 MW
937482 AD2-202 E Adder 1.61 MW 1.37 MW
938531 AE1-072 C 50/50 27.42 MW 27.42 MW
938532 AE1-072 E 50/50 14.29 MW 14.29 MW
940481 AE2-033 C Adder 23.34 MW 19.84 MW
940482 AE2-033 E Adder 15.74 MW 13.38 MW
940541 AE2-040 C Adder 4.14 MW 3.52 MW
940641 AE2-051 C 50/50 31.36 MW 31.36 MW
940642 AE2-051 E 50/50 20.91 MW 20.91 MW
941101 AE2-104 C Adder 5.0 MW 4.25 MW
941102 AE2-104 E Adder 7.94 MW 6.75 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 32.86 MW 32.86 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 26.58 MW 26.58 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 129.49 MW 129.49 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 4.3 MW 4.3 MW
NY PJM->LTFIMP_NY CLTF 2.02 MW 2.02 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.3 MW 1.3 MW
WEC LTFEXP_WEC->PJM CLTF 0.69 MW 0.69 MW
CPLE LTFEXP_CPLE->PJM CLTF 16.03 MW 16.03 MW
TVA LTFEXP_TVA->PJM CLTF 7.39 MW 7.39 MW
MEC LTFEXP_MEC->PJM CLTF 4.41 MW 4.41 MW
LAGN LTFEXP_LAGN->PJM CLTF 9.47 MW 9.47 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.27 MW 0.27 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 27.38 MW 27.38 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.64 MW 7.64 MW

Details for 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line l/o DVP_P4-2: H6T576_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
Contingency Name:
DVP_P4-2: H6T576_SRT-A
CONTINGENCY 'DVP_P4-2: H6T576_SRT-A'
 OPEN BRANCH FROM BUS 314322 TO BUS 314914 CKT 1   /*6MDLTHAN     230.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1   /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.27 %
Rating: 3144.0 MVA
Rating Type: C
MVA to Mitigate: 3215.35 MVA
MW Contribution: 13.04 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.06 MW 0.9 MW
961672 AG1-007 E Adder 0.6 MW 0.51 MW
961941 AG1-037 C Adder 0.67 MW 0.57 MW
961942 AG1-037 E Adder 0.45 MW 0.38 MW
962331 AG1-082 C Adder 2.67 MW 2.27 MW
962332 AG1-082 E Adder 1.78 MW 1.51 MW
963041 AG1-153 C Adder 6.86 MW 5.83 MW
963042 AG1-153 E Adder 10.28 MW 8.74 MW
964791 AG1-342 C Adder 3.49 MW 2.96 MW
964792 AG1-342 E Adder 2.33 MW 1.98 MW
966801 AG1-551 C Adder 2.65 MW 2.25 MW
966802 AG1-551 E Adder 1.4 MW 1.19 MW
966811 AG1-552 C Adder 2.45 MW 2.08 MW
966812 AG1-552 E Adder 1.16 MW 0.99 MW
965291 AG1-394 C Adder 1.13 MW 0.96 MW
965292 AG1-394 E Adder 2.08 MW 1.77 MW
966621 AG1-532 C Adder 1.56 MW 1.32 MW
966622 AG1-532 E Adder 1.04 MW 0.88 MW
314541 3WATKINS Adder 0.96 MW 0.81 MW
314572 3EMPORIA Adder 0.48 MW 0.41 MW
315131 1EDGECMA Adder 17.13 MW 14.56 MW
918492 AA1-063AE OP Adder 5.08 MW 4.32 MW
918532 AA1-067 E Adder 0.88 MW 0.74 MW
919692 AA2-053 E OP Adder 5.13 MW 4.36 MW
920042 AA2-088 E OP Adder 14.14 MW 12.02 MW
925785 AC1-054 E Adder 3.81 MW 3.24 MW
926274 AC1-105 E Adder 0.55 MW 0.47 MW
927146 AC1-208 E Adder 5.09 MW 4.33 MW
934521 AD1-076 C Adder 17.3 MW 14.7 MW
934522 AD1-076 E Adder 8.82 MW 7.5 MW
943172 AE2-346 E Adder 0.8 MW 0.68 MW
944011 AF1-069 C Adder 16.1 MW 13.68 MW
944012 AF1-069 E Adder 6.25 MW 5.32 MW
959311 AF2-222 C Adder 16.0 MW 13.6 MW
959312 AF2-222 E Adder 10.72 MW 9.11 MW
960081 AF2-299 C Adder 2.08 MW 1.76 MW
960082 AF2-299 E Adder 1.38 MW 1.18 MW
316141 AB2-099 E Adder 0.33 MW 0.28 MW
900672 V4-068 E Adder 0.47 MW 0.4 MW
917342 Z2-044 E Adder 0.79 MW 0.67 MW
922923 AB1-081 E OP Adder 4.22 MW 3.59 MW
923263 AB1-132 E OP Adder 7.05 MW 6.0 MW
923573 AB1-173 E OP Adder 3.76 MW 3.2 MW
924162 AB2-060 E OP Adder 4.33 MW 3.68 MW
924302 AB2-077 E O1 Adder 1.36 MW 1.16 MW
924312 AB2-078 E O1 Adder 1.36 MW 1.16 MW
924322 AB2-079 E O1 Adder 1.36 MW 1.16 MW
925612 AC1-036 E Adder 0.84 MW 0.71 MW
939181 AE1-148 C Adder 9.38 MW 7.97 MW
939182 AE1-148 E Adder 6.25 MW 5.31 MW
940492 AE2-034 E Adder 4.5 MW 3.83 MW
941031 AE2-094 C Adder 49.26 MW 41.87 MW
941032 AE2-094 E Adder 22.06 MW 18.75 MW
946281 AF1-292 C Adder 1.72 MW 1.46 MW
946282 AF1-292 E Adder 1.14 MW 0.97 MW
957481 AF2-042 C Adder 59.6 MW 50.66 MW
957482 AF2-042 E Adder 39.74 MW 33.77 MW
957521 AF2-046 C Adder 18.79 MW 15.97 MW
957522 AF2-046 E Adder 9.5 MW 8.07 MW
957861 AF2-080 C Adder 9.04 MW 7.68 MW
957862 AF2-080 E Adder 4.0 MW 3.4 MW
314539 3UNCAMP Adder 8.59 MW 7.3 MW
916042 Z1-036 E Adder 43.42 MW 36.91 MW
938771 AE1-103 C Adder 4.18 MW 3.55 MW
938772 AE1-103 E Adder 5.77 MW 4.91 MW
314507 3THOMPSN Adder 3.3 MW 2.8 MW
314525 6KINGFORK Adder 1.53 MW 1.3 MW
314550 6HICKORY 50/50 3.64 MW 3.64 MW
315092 1YORKTN3 Adder 182.37 MW 155.02 MW
926662 AC1-147 E 50/50 2.16 MW 2.16 MW
926755 AC1-161 E 50/50 24.41 MW 24.41 MW
927226 AC1-216 E Adder 7.2 MW 6.12 MW
935112 AD1-144 E Adder 1.42 MW 1.21 MW
942341 AE2-247 C Adder 2.0 MW 1.7 MW
942342 AE2-247 E Adder 2.76 MW 2.34 MW
943461 AF1-017 C Adder 1.81 MW 1.53 MW
943462 AF1-017 E Adder 2.95 MW 2.5 MW
943612 AF1-032 E Adder 1.46 MW 1.24 MW
315098 1CHESPKA 50/50 0.71 MW 0.71 MW
315099 1CHESPKB 50/50 1.18 MW 1.18 MW
315108 1ELIZAR1 50/50 5.25 MW 5.25 MW
315109 1ELIZAR2 50/50 5.16 MW 5.16 MW
315110 1ELIZAR3 50/50 5.32 MW 5.32 MW
315233 1SURRY 2 50/50 52.27 MW 52.27 MW
315260 1GOSPORTA Adder 3.48 MW 2.96 MW
315261 1GOSPORTB 50/50 4.44 MW 4.44 MW
315262 1GOSPORTC 50/50 3.77 MW 3.77 MW
913392 Y1-086 E Adder 3.54 MW 3.01 MW
916192 Z1-068 E 50/50 3.11 MW 3.11 MW
923832 AB2-022 E Adder 2.0 MW 1.7 MW
923852 AB2-025 E Adder 1.22 MW 1.03 MW
939312 AE1-162 E Adder 1.97 MW 1.67 MW
957492 AF2-043 E Adder 2.25 MW 1.91 MW
962962 AG1-145 E Adder 1.4 MW 1.19 MW
901082 W1-029 E Adder 50.02 MW 42.52 MW
917122 Z2-027 E Adder 2.14 MW 1.82 MW
925522 AC1-027 E 50/50 2.01 MW 2.01 MW
957832 AF2-077 E Adder 1.41 MW 1.2 MW
957871 AF2-081 C 50/50 16.49 MW 16.49 MW
957872 AF2-081 E 50/50 7.07 MW 7.07 MW
958161 AF2-110 C Adder 2.05 MW 1.75 MW
958162 AF2-110 E Adder 3.27 MW 2.78 MW
314722 3TWITTYS Adder 0.93 MW 0.79 MW
917512 Z2-088 E OP1 Adder 5.69 MW 4.83 MW
926071 AC1-086 C Adder 24.24 MW 20.6 MW
926072 AC1-086 E Adder 11.03 MW 9.38 MW
927021 AC1-189 C Adder 9.95 MW 8.46 MW
927022 AC1-189 E Adder 4.96 MW 4.21 MW
933291 AC2-141 C 50/50 57.19 MW 57.19 MW
933292 AC2-141 E 50/50 24.41 MW 24.41 MW
934621 AD1-088 C Adder 13.21 MW 11.23 MW
934622 AD1-088 E Adder 6.22 MW 5.28 MW
939411 AE1-173 C Adder 130.54 MW 110.96 MW
939412 AE1-173 E Adder 87.03 MW 73.97 MW
934012 AD1-025 E Adder 9.32 MW 7.92 MW
916191 Z1-068 C 50/50 0.07 MW 0.07 MW
933981 AD1-022 C Adder 12.21 MW 10.38 MW
933982 AD1-022 E Adder 6.65 MW 5.65 MW
962572 AG1-106 E Adder 1.37 MW 1.17 MW
961681 AG1-008 C Adder 18.79 MW 15.97 MW
961682 AG1-008 E Adder 9.5 MW 8.07 MW
962571 AG1-106 C Adder 3.14 MW 2.67 MW
314594 6PLYMOUTH TP Adder 0.46 MW 0.39 MW
314632 6AYDLETT TAP Adder 2.22 MW 1.89 MW
316036 AC1-147 C 50/50 0.6 MW 0.6 MW
316160 AE1-175 E Adder 1.15 MW 0.98 MW
316185 AD1-033 C 50/50 2.06 MW 2.06 MW
316263 AC1-034 C Adder 7.48 MW 6.36 MW
316274 AC1-208 C Adder 11.47 MW 9.75 MW
316294 AC1-161 C 50/50 9.35 MW 9.35 MW
316316 AC1-027 C 50/50 0.52 MW 0.52 MW
917332 KELFORD E Adder 2.16 MW 1.83 MW
924516 AB2-100 E1 Adder 3.2 MW 2.72 MW
924517 AB2-100 E2 Adder 3.2 MW 2.72 MW
925595 AC1-034 E Adder 5.65 MW 4.8 MW
926206 AC1-098 E Adder 4.71 MW 4.0 MW
926214 AC1-099 E Adder 1.56 MW 1.32 MW
934065 AD1-033 E 50/50 8.39 MW 8.39 MW
937226 AE2-253 E 50/50 9.68 MW 9.68 MW
918512 AA1-065 E OP Adder 7.39 MW 6.28 MW
316017 AA1-139 ULT1 50/50 1.78 MW 1.78 MW
316018 AA1-139 ULT2 50/50 1.78 MW 1.78 MW
919153 AA1-139 E2 50/50 6.74 MW 6.74 MW
919152 AA1-139 E1 50/50 6.74 MW 6.74 MW
919710 AA2-057 E Adder 5.17 MW 4.4 MW
920692 AA2-178 E Adder 6.0 MW 5.1 MW
923994 AB2-040_E Adder 7.06 MW 6.0 MW
924022 AB2-043 E O1 Adder 5.28 MW 4.49 MW
924152 AB2-059 E OP Adder 5.92 MW 5.03 MW
924814 AB2-134 E Adder 11.79 MW 10.02 MW
316084 AB2-161 E Adder 6.01 MW 5.11 MW
925122 AB2-169 E Adder 7.62 MW 6.47 MW
316088 AB2-174 E Adder 7.4 MW 6.29 MW
316375 AC2-012 C 50/50 2.21 MW 2.21 MW
932046 AC2-012 E 50/50 21.39 MW 21.39 MW
316311 AC2-079 C Adder 7.79 MW 6.62 MW
932596 AC2-079 E Adder 12.72 MW 10.81 MW
934576 AD1-082 E Adder 4.79 MW 4.07 MW
316349 AD2-085 C Adder 4.61 MW 3.92 MW
936666 AD2-085 E Adder 7.52 MW 6.39 MW
316388 AE2-253 GEN 50/50 3.26 MW 3.26 MW
961611 AG1-000B C Adder 18.13 MW 15.41 MW
941591 AE2-156 C 50/50 29.28 MW 29.28 MW
944581 AF1-123 C 50/50 76.02 MW 76.02 MW
944582 AF1-123 E 50/50 174.06 MW 174.06 MW
944591 AF1-124 C 50/50 76.28 MW 76.28 MW
944592 AF1-124 E 50/50 174.7 MW 174.7 MW
944601 AF1-125 C 50/50 74.84 MW 74.84 MW
944602 AF1-125 E 50/50 171.33 MW 171.33 MW
962491 AG1-098 C Adder 11.73 MW 9.97 MW
962492 AG1-098 E Adder 7.82 MW 6.65 MW
962561 AG1-105 C Adder 8.8 MW 7.48 MW
962562 AG1-105 E Adder 5.86 MW 4.98 MW
964241 AG1-285 C Adder 13.12 MW 11.15 MW
964242 AG1-285 E Adder 8.75 MW 7.43 MW
313764 3SOCKMAN Adder 0.83 MW 0.71 MW
932632 AC2-084 E Adder 4.16 MW 3.54 MW
934321 AD1-056 C Adder 7.04 MW 5.98 MW
934322 AD1-056 E Adder 3.82 MW 3.25 MW
934331 AD1-057 C Adder 3.93 MW 3.34 MW
934332 AD1-057 E Adder 2.04 MW 1.74 MW
934501 AD1-074 C Adder 47.63 MW 40.49 MW
934502 AD1-074 E Adder 24.25 MW 20.61 MW
934511 AD1-075 C Adder 11.91 MW 10.12 MW
934512 AD1-075 E Adder 6.06 MW 5.15 MW
934612 AD1-087 E Adder 3.87 MW 3.29 MW
935172 AD1-152 E Adder 5.69 MW 4.84 MW
937482 AD2-202 E Adder 1.13 MW 0.96 MW
938531 AE1-072 C 50/50 28.87 MW 28.87 MW
938532 AE1-072 E 50/50 15.05 MW 15.05 MW
939191 AE1-149 C Adder 9.8 MW 8.33 MW
939192 AE1-149 E Adder 6.53 MW 5.55 MW
940481 AE2-033 C Adder 17.07 MW 14.51 MW
940482 AE2-033 E Adder 11.51 MW 9.78 MW
940541 AE2-040 C Adder 3.01 MW 2.56 MW
940641 AE2-051 C Adder 23.72 MW 20.16 MW
940642 AE2-051 E Adder 15.81 MW 13.44 MW
941101 AE2-104 C Adder 5.03 MW 4.28 MW
941102 AE2-104 E Adder 8.0 MW 6.8 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 19.03 MW 19.03 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 17.52 MW 17.52 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 92.84 MW 92.84 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 3.12 MW 3.12 MW
NY PJM->LTFIMP_NY CLTF 1.49 MW 1.49 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.77 MW 0.77 MW
WEC LTFEXP_WEC->PJM CLTF 0.41 MW 0.41 MW
CPLE LTFEXP_CPLE->PJM CLTF 11.71 MW 11.71 MW
TVA LTFEXP_TVA->PJM CLTF 4.99 MW 4.99 MW
MEC LTFEXP_MEC->PJM CLTF 2.75 MW 2.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.43 MW 6.43 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.16 MW 0.16 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 19.92 MW 19.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 5.58 MW 5.58 MW

Details for 8SURRY-8CHCKAHM 500.0 kV Ckt 1 line l/o DVP_P4-2: H6T563_SRT-S


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8SURRY-8CHCKAHM 500.0 kV Ckt 1 line
314924 to 314903 ckt 1
Contingency Name:
DVP_P4-2: H6T563_SRT-S
CONTINGENCY 'DVP_P4-2: H6T563_SRT-S'
 OPEN BRANCH FROM BUS 314322 TO BUS 314914 CKT 1                /*6MDLTHAN     230.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1                /*8MDLTHAN     500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.27 %
Rating: 3144.0 MVA
Rating Type: C
MVA to Mitigate: 3215.35 MVA
MW Contribution: 13.04 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.06 MW 0.9 MW
961672 AG1-007 E Adder 0.6 MW 0.51 MW
961941 AG1-037 C Adder 0.67 MW 0.57 MW
961942 AG1-037 E Adder 0.45 MW 0.38 MW
962331 AG1-082 C Adder 2.67 MW 2.27 MW
962332 AG1-082 E Adder 1.78 MW 1.51 MW
963041 AG1-153 C Adder 6.86 MW 5.83 MW
963042 AG1-153 E Adder 10.28 MW 8.74 MW
964791 AG1-342 C Adder 3.49 MW 2.96 MW
964792 AG1-342 E Adder 2.33 MW 1.98 MW
966801 AG1-551 C Adder 2.65 MW 2.25 MW
966802 AG1-551 E Adder 1.4 MW 1.19 MW
966811 AG1-552 C Adder 2.45 MW 2.08 MW
966812 AG1-552 E Adder 1.16 MW 0.99 MW
965291 AG1-394 C Adder 1.13 MW 0.96 MW
965292 AG1-394 E Adder 2.08 MW 1.77 MW
966621 AG1-532 C Adder 1.56 MW 1.32 MW
966622 AG1-532 E Adder 1.04 MW 0.88 MW
314541 3WATKINS Adder 0.96 MW 0.81 MW
314572 3EMPORIA Adder 0.48 MW 0.41 MW
315131 1EDGECMA Adder 17.13 MW 14.56 MW
918492 AA1-063AE OP Adder 5.08 MW 4.32 MW
918532 AA1-067 E Adder 0.88 MW 0.74 MW
919692 AA2-053 E OP Adder 5.13 MW 4.36 MW
920042 AA2-088 E OP Adder 14.14 MW 12.02 MW
925785 AC1-054 E Adder 3.81 MW 3.24 MW
926274 AC1-105 E Adder 0.55 MW 0.47 MW
927146 AC1-208 E Adder 5.09 MW 4.33 MW
934521 AD1-076 C Adder 17.3 MW 14.7 MW
934522 AD1-076 E Adder 8.82 MW 7.5 MW
943172 AE2-346 E Adder 0.8 MW 0.68 MW
944011 AF1-069 C Adder 16.1 MW 13.68 MW
944012 AF1-069 E Adder 6.25 MW 5.32 MW
959311 AF2-222 C Adder 16.0 MW 13.6 MW
959312 AF2-222 E Adder 10.72 MW 9.11 MW
960081 AF2-299 C Adder 2.08 MW 1.76 MW
960082 AF2-299 E Adder 1.38 MW 1.18 MW
316141 AB2-099 E Adder 0.33 MW 0.28 MW
900672 V4-068 E Adder 0.47 MW 0.4 MW
917342 Z2-044 E Adder 0.79 MW 0.67 MW
922923 AB1-081 E OP Adder 4.22 MW 3.59 MW
923263 AB1-132 E OP Adder 7.05 MW 6.0 MW
923573 AB1-173 E OP Adder 3.76 MW 3.2 MW
924162 AB2-060 E OP Adder 4.33 MW 3.68 MW
924302 AB2-077 E O1 Adder 1.36 MW 1.16 MW
924312 AB2-078 E O1 Adder 1.36 MW 1.16 MW
924322 AB2-079 E O1 Adder 1.36 MW 1.16 MW
925612 AC1-036 E Adder 0.84 MW 0.71 MW
939181 AE1-148 C Adder 9.38 MW 7.97 MW
939182 AE1-148 E Adder 6.25 MW 5.31 MW
940492 AE2-034 E Adder 4.5 MW 3.83 MW
941031 AE2-094 C Adder 49.26 MW 41.87 MW
941032 AE2-094 E Adder 22.06 MW 18.75 MW
946281 AF1-292 C Adder 1.72 MW 1.46 MW
946282 AF1-292 E Adder 1.14 MW 0.97 MW
957481 AF2-042 C Adder 59.6 MW 50.66 MW
957482 AF2-042 E Adder 39.74 MW 33.77 MW
957521 AF2-046 C Adder 18.79 MW 15.97 MW
957522 AF2-046 E Adder 9.5 MW 8.07 MW
957861 AF2-080 C Adder 9.04 MW 7.68 MW
957862 AF2-080 E Adder 4.0 MW 3.4 MW
314539 3UNCAMP Adder 8.59 MW 7.3 MW
916042 Z1-036 E Adder 43.42 MW 36.91 MW
938771 AE1-103 C Adder 4.18 MW 3.55 MW
938772 AE1-103 E Adder 5.77 MW 4.91 MW
314507 3THOMPSN Adder 3.3 MW 2.8 MW
314525 6KINGFORK Adder 1.53 MW 1.3 MW
314550 6HICKORY 50/50 3.64 MW 3.64 MW
315092 1YORKTN3 Adder 182.37 MW 155.02 MW
926662 AC1-147 E 50/50 2.16 MW 2.16 MW
926755 AC1-161 E 50/50 24.41 MW 24.41 MW
927226 AC1-216 E Adder 7.2 MW 6.12 MW
935112 AD1-144 E Adder 1.42 MW 1.21 MW
942341 AE2-247 C Adder 2.0 MW 1.7 MW
942342 AE2-247 E Adder 2.76 MW 2.34 MW
943461 AF1-017 C Adder 1.81 MW 1.53 MW
943462 AF1-017 E Adder 2.95 MW 2.5 MW
943612 AF1-032 E Adder 1.46 MW 1.24 MW
315098 1CHESPKA 50/50 0.71 MW 0.71 MW
315099 1CHESPKB 50/50 1.18 MW 1.18 MW
315108 1ELIZAR1 50/50 5.25 MW 5.25 MW
315109 1ELIZAR2 50/50 5.16 MW 5.16 MW
315110 1ELIZAR3 50/50 5.32 MW 5.32 MW
315233 1SURRY 2 50/50 52.27 MW 52.27 MW
315260 1GOSPORTA Adder 3.48 MW 2.96 MW
315261 1GOSPORTB 50/50 4.44 MW 4.44 MW
315262 1GOSPORTC 50/50 3.77 MW 3.77 MW
913392 Y1-086 E Adder 3.54 MW 3.01 MW
916192 Z1-068 E 50/50 3.11 MW 3.11 MW
923832 AB2-022 E Adder 2.0 MW 1.7 MW
923852 AB2-025 E Adder 1.22 MW 1.03 MW
939312 AE1-162 E Adder 1.97 MW 1.67 MW
957492 AF2-043 E Adder 2.25 MW 1.91 MW
962962 AG1-145 E Adder 1.4 MW 1.19 MW
901082 W1-029 E Adder 50.02 MW 42.52 MW
917122 Z2-027 E Adder 2.14 MW 1.82 MW
925522 AC1-027 E 50/50 2.01 MW 2.01 MW
957832 AF2-077 E Adder 1.41 MW 1.2 MW
957871 AF2-081 C 50/50 16.49 MW 16.49 MW
957872 AF2-081 E 50/50 7.07 MW 7.07 MW
958161 AF2-110 C Adder 2.05 MW 1.75 MW
958162 AF2-110 E Adder 3.27 MW 2.78 MW
314722 3TWITTYS Adder 0.93 MW 0.79 MW
917512 Z2-088 E OP1 Adder 5.69 MW 4.83 MW
926071 AC1-086 C Adder 24.24 MW 20.6 MW
926072 AC1-086 E Adder 11.03 MW 9.38 MW
927021 AC1-189 C Adder 9.95 MW 8.46 MW
927022 AC1-189 E Adder 4.96 MW 4.21 MW
933291 AC2-141 C 50/50 57.19 MW 57.19 MW
933292 AC2-141 E 50/50 24.41 MW 24.41 MW
934621 AD1-088 C Adder 13.21 MW 11.23 MW
934622 AD1-088 E Adder 6.22 MW 5.28 MW
939411 AE1-173 C Adder 130.54 MW 110.96 MW
939412 AE1-173 E Adder 87.03 MW 73.97 MW
934012 AD1-025 E Adder 9.32 MW 7.92 MW
916191 Z1-068 C 50/50 0.07 MW 0.07 MW
933981 AD1-022 C Adder 12.21 MW 10.38 MW
933982 AD1-022 E Adder 6.65 MW 5.65 MW
962572 AG1-106 E Adder 1.37 MW 1.17 MW
961681 AG1-008 C Adder 18.79 MW 15.97 MW
961682 AG1-008 E Adder 9.5 MW 8.07 MW
962571 AG1-106 C Adder 3.14 MW 2.67 MW
314594 6PLYMOUTH TP Adder 0.46 MW 0.39 MW
314632 6AYDLETT TAP Adder 2.22 MW 1.89 MW
316036 AC1-147 C 50/50 0.6 MW 0.6 MW
316160 AE1-175 E Adder 1.15 MW 0.98 MW
316185 AD1-033 C 50/50 2.06 MW 2.06 MW
316263 AC1-034 C Adder 7.48 MW 6.36 MW
316274 AC1-208 C Adder 11.47 MW 9.75 MW
316294 AC1-161 C 50/50 9.35 MW 9.35 MW
316316 AC1-027 C 50/50 0.52 MW 0.52 MW
917332 KELFORD E Adder 2.16 MW 1.83 MW
924516 AB2-100 E1 Adder 3.2 MW 2.72 MW
924517 AB2-100 E2 Adder 3.2 MW 2.72 MW
925595 AC1-034 E Adder 5.65 MW 4.8 MW
926206 AC1-098 E Adder 4.71 MW 4.0 MW
926214 AC1-099 E Adder 1.56 MW 1.32 MW
934065 AD1-033 E 50/50 8.39 MW 8.39 MW
937226 AE2-253 E 50/50 9.68 MW 9.68 MW
918512 AA1-065 E OP Adder 7.39 MW 6.28 MW
316017 AA1-139 ULT1 50/50 1.78 MW 1.78 MW
316018 AA1-139 ULT2 50/50 1.78 MW 1.78 MW
919153 AA1-139 E2 50/50 6.74 MW 6.74 MW
919152 AA1-139 E1 50/50 6.74 MW 6.74 MW
919710 AA2-057 E Adder 5.17 MW 4.4 MW
920692 AA2-178 E Adder 6.0 MW 5.1 MW
923994 AB2-040_E Adder 7.06 MW 6.0 MW
924022 AB2-043 E O1 Adder 5.28 MW 4.49 MW
924152 AB2-059 E OP Adder 5.92 MW 5.03 MW
924814 AB2-134 E Adder 11.79 MW 10.02 MW
316084 AB2-161 E Adder 6.01 MW 5.11 MW
925122 AB2-169 E Adder 7.62 MW 6.47 MW
316088 AB2-174 E Adder 7.4 MW 6.29 MW
316375 AC2-012 C 50/50 2.21 MW 2.21 MW
932046 AC2-012 E 50/50 21.39 MW 21.39 MW
316311 AC2-079 C Adder 7.79 MW 6.62 MW
932596 AC2-079 E Adder 12.72 MW 10.81 MW
934576 AD1-082 E Adder 4.79 MW 4.07 MW
316349 AD2-085 C Adder 4.61 MW 3.92 MW
936666 AD2-085 E Adder 7.52 MW 6.39 MW
316388 AE2-253 GEN 50/50 3.26 MW 3.26 MW
961611 AG1-000B C Adder 18.13 MW 15.41 MW
941591 AE2-156 C 50/50 29.28 MW 29.28 MW
944581 AF1-123 C 50/50 76.02 MW 76.02 MW
944582 AF1-123 E 50/50 174.06 MW 174.06 MW
944591 AF1-124 C 50/50 76.28 MW 76.28 MW
944592 AF1-124 E 50/50 174.7 MW 174.7 MW
944601 AF1-125 C 50/50 74.84 MW 74.84 MW
944602 AF1-125 E 50/50 171.33 MW 171.33 MW
962491 AG1-098 C Adder 11.73 MW 9.97 MW
962492 AG1-098 E Adder 7.82 MW 6.65 MW
962561 AG1-105 C Adder 8.8 MW 7.48 MW
962562 AG1-105 E Adder 5.86 MW 4.98 MW
964241 AG1-285 C Adder 13.12 MW 11.15 MW
964242 AG1-285 E Adder 8.75 MW 7.43 MW
313764 3SOCKMAN Adder 0.83 MW 0.71 MW
932632 AC2-084 E Adder 4.16 MW 3.54 MW
934321 AD1-056 C Adder 7.04 MW 5.98 MW
934322 AD1-056 E Adder 3.82 MW 3.25 MW
934331 AD1-057 C Adder 3.93 MW 3.34 MW
934332 AD1-057 E Adder 2.04 MW 1.74 MW
934501 AD1-074 C Adder 47.63 MW 40.49 MW
934502 AD1-074 E Adder 24.25 MW 20.61 MW
934511 AD1-075 C Adder 11.91 MW 10.12 MW
934512 AD1-075 E Adder 6.06 MW 5.15 MW
934612 AD1-087 E Adder 3.87 MW 3.29 MW
935172 AD1-152 E Adder 5.69 MW 4.84 MW
937482 AD2-202 E Adder 1.13 MW 0.96 MW
938531 AE1-072 C 50/50 28.87 MW 28.87 MW
938532 AE1-072 E 50/50 15.05 MW 15.05 MW
939191 AE1-149 C Adder 9.8 MW 8.33 MW
939192 AE1-149 E Adder 6.53 MW 5.55 MW
940481 AE2-033 C Adder 17.07 MW 14.51 MW
940482 AE2-033 E Adder 11.51 MW 9.78 MW
940541 AE2-040 C Adder 3.01 MW 2.56 MW
940641 AE2-051 C Adder 23.72 MW 20.16 MW
940642 AE2-051 E Adder 15.81 MW 13.44 MW
941101 AE2-104 C Adder 5.03 MW 4.28 MW
941102 AE2-104 E Adder 8.0 MW 6.8 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 19.03 MW 19.03 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 17.52 MW 17.52 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 92.84 MW 92.84 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 3.12 MW 3.12 MW
NY PJM->LTFIMP_NY CLTF 1.49 MW 1.49 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.77 MW 0.77 MW
WEC LTFEXP_WEC->PJM CLTF 0.41 MW 0.41 MW
CPLE LTFEXP_CPLE->PJM CLTF 11.71 MW 11.71 MW
TVA LTFEXP_TVA->PJM CLTF 4.99 MW 4.99 MW
MEC LTFEXP_MEC->PJM CLTF 2.75 MW 2.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.43 MW 6.43 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.16 MW 0.16 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 19.92 MW 19.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 5.58 MW 5.58 MW

Details for 6CHESTF B-6BASIN 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6BASIN 230.0 kV Ckt 1 line
314287 to 314276 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 138.18 %
Rating: 663.64 MVA
Rating Type: B
MVA to Mitigate: 917.03 MVA
MW Contribution: 2.79 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6BASIN 230.0 kV Ckt 1 line
314287 to 314276 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 141.48 %
Rating: 663.64 MVA
Rating Type: B
MVA to Mitigate: 938.91 MVA
MW Contribution: 2.78 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.34 MW 0.29 MW
961941 AG1-037 C Adder 0.2 MW 0.17 MW
962331 AG1-082 C Adder 0.79 MW 0.67 MW
963041 AG1-153 C Adder 2.05 MW 1.74 MW
966801 AG1-551 C Adder 0.77 MW 0.66 MW
966811 AG1-552 C 80/20 0.85 MW 0.85 MW
965291 AG1-394 C 80/20 0.34 MW 0.34 MW
966621 AG1-532 C 80/20 0.65 MW 0.65 MW
313506 AB1-173 C OP 80/20 0.5 MW 0.5 MW
314704 3LAWRENC 80/20 0.13 MW 0.13 MW
315126 1ROARAP2 80/20 0.58 MW 0.58 MW
315128 1ROARAP4 80/20 0.55 MW 0.55 MW
315131 1EDGECMA Adder 5.67 MW 4.82 MW
315136 1ROSEMG1 80/20 0.89 MW 0.89 MW
315137 1ROSEMS1 80/20 0.55 MW 0.55 MW
315138 1ROSEMG2 80/20 0.42 MW 0.42 MW
315139 1GASTONA 80/20 1.36 MW 1.36 MW
934521 AD1-076 C Adder 4.52 MW 3.84 MW
944011 AF1-069 C 80/20 4.81 MW 4.81 MW
960081 AF2-299 C 80/20 0.86 MW 0.86 MW
315606 3AA2-053SOLA 80/20 0.62 MW 0.62 MW
939181 AE1-148 C Adder 2.86 MW 2.44 MW
941031 AE2-094 C 80/20 14.73 MW 14.73 MW
946281 AF1-292 C 80/20 0.71 MW 0.71 MW
957481 AF2-042 C Adder 17.33 MW 14.73 MW
957521 AF2-046 C Adder 5.63 MW 4.79 MW
957861 AF2-080 C Adder 2.79 MW 2.37 MW
938771 AE1-103 C 80/20 1.16 MW 1.16 MW
314507 3THOMPSN Adder 0.7 MW 0.6 MW
315065 1CHESTF6 80/20 26.33 MW 26.33 MW
315073 1STONECA 80/20 4.79 MW 4.79 MW
315076 1HOPPOLC 80/20 1.06 MW 1.06 MW
315077 1HOPHCF1 80/20 1.69 MW 1.69 MW
315078 1HOPHCF2 80/20 1.69 MW 1.69 MW
315079 1HOPHCF3 80/20 1.69 MW 1.69 MW
315080 1HOPHCF4 80/20 2.57 MW 2.57 MW
942341 AE2-247 C 80/20 0.71 MW 0.71 MW
943461 AF1-017 C 80/20 0.65 MW 0.65 MW
315102 1BRUNSWICKG1 80/20 3.02 MW 3.02 MW
315103 1BRUNSWICKG2 80/20 3.02 MW 3.02 MW
315104 1BRUNSWICKG3 80/20 3.02 MW 3.02 MW
315105 1BRUNSWICKS1 80/20 6.28 MW 6.28 MW
315115 1S HAMPT1 80/20 0.6 MW 0.6 MW
315116 1SURRY 1 80/20 11.05 MW 11.05 MW
315117 1GRAVELC 80/20 0.39 MW 0.39 MW
315119 1GRAVEL3 80/20 1.12 MW 1.12 MW
315120 1GRAVEL4 80/20 1.14 MW 1.14 MW
315121 1GRAVEL5 80/20 1.12 MW 1.12 MW
315122 1GRAVEL6 80/20 1.14 MW 1.14 MW
315141 1GASTONB 80/20 1.36 MW 1.36 MW
315241 1Z1-086 GT1 80/20 3.87 MW 3.87 MW
315242 1Z1-086 GT2 80/20 3.87 MW 3.87 MW
315243 1Z1-086 GT3 80/20 3.87 MW 3.87 MW
315244 1Z1-086 ST 80/20 6.74 MW 6.74 MW
315260 1GOSPORTA Adder 0.74 MW 0.63 MW
315261 1GOSPORTB Adder 0.95 MW 0.81 MW
315262 1GOSPORTC Adder 0.81 MW 0.69 MW
315607 3AA1-063SOLA 80/20 0.58 MW 0.58 MW
315608 3AA2-088SOLA 80/20 0.43 MW 0.43 MW
316132 AB2-190 C 80/20 2.54 MW 2.54 MW
942001 AE2-212 C 80/20 2.35 MW 2.35 MW
957871 AF2-081 C Adder 3.41 MW 2.9 MW
958161 AF2-110 C 80/20 0.53 MW 0.53 MW
926071 AC1-086 C 80/20 9.33 MW 9.33 MW
927021 AC1-189 C Adder 3.07 MW 2.61 MW
933291 AC2-141 C Adder 8.97 MW 7.62 MW
934621 AD1-088 C Adder 3.74 MW 3.18 MW
939411 AE1-173 C Adder 32.45 MW 27.59 MW
934011 AD1-025 C 80/20 1.45 MW 1.45 MW
933981 AD1-022 C Adder 3.27 MW 2.78 MW
961681 AG1-008 C Adder 5.63 MW 4.79 MW
962571 AG1-106 C 80/20 1.21 MW 1.21 MW
316011 AB1-132 C OP 80/20 1.04 MW 1.04 MW
316023 AB2-100 C2 80/20 0.48 MW 0.48 MW
316236 AE1-162 C 80/20 0.14 MW 0.14 MW
316240 AF1-291 C 80/20 2.79 MW 2.79 MW
316263 AC1-034 C Adder 2.43 MW 2.07 MW
316274 AC1-208 C 80/20 3.8 MW 3.8 MW
316315 AB2-025 C 80/20 0.24 MW 0.24 MW
316319 Z2-044 C 80/20 0.09 MW 0.09 MW
316365 AB2-100 C1 80/20 0.48 MW 0.48 MW
316369 AC1-216 C 80/20 0.9 MW 0.9 MW
316327 AA2-057 C 80/20 0.56 MW 0.56 MW
316181 AB2-040 GEN 80/20 0.56 MW 0.56 MW
316033 AB2-134 GEN 80/20 1.18 MW 1.18 MW
316083 AB2-161 C 80/20 0.34 MW 0.34 MW
316087 AB2-174 C 80/20 0.53 MW 0.53 MW
316311 AC2-079 C 80/20 2.68 MW 2.68 MW
316381 AD1-082 C 80/20 0.77 MW 0.77 MW
316349 AD2-085 C 80/20 1.65 MW 1.65 MW
961611 AG1-000B C 80/20 7.59 MW 7.59 MW
941591 AE2-156 C Adder 6.23 MW 5.3 MW
944581 AF1-123 C Adder 15.31 MW 13.02 MW
944591 AF1-124 C Adder 15.37 MW 13.06 MW
944601 AF1-125 C Adder 15.08 MW 12.81 MW
965281 AG1-393 C 80/20 1.07 MW 1.07 MW
313764 3SOCKMAN 80/20 0.3 MW 0.3 MW
934321 AD1-056 C Adder 2.5 MW 2.12 MW
934331 AD1-057 C Adder 1.39 MW 1.18 MW
934501 AD1-074 C Adder 12.45 MW 10.58 MW
934511 AD1-075 C Adder 3.11 MW 2.65 MW
935161 AD1-151 C 80/20 9.48 MW 9.48 MW
938531 AE1-072 C Adder 6.01 MW 5.11 MW
939191 AE1-149 C 80/20 7.58 MW 7.58 MW
940431 AE2-027 C 80/20 5.4 MW 5.4 MW
940481 AE2-033 C 80/20 9.25 MW 9.25 MW
940541 AE2-040 C 80/20 1.67 MW 1.67 MW
940641 AE2-051 C 80/20 6.29 MW 6.29 MW
941101 AE2-104 C 80/20 1.31 MW 1.31 MW
944641 AF1-129 C 80/20 137.34 MW 137.34 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.96 MW 6.96 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.77 MW 5.77 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 28.82 MW 28.82 MW
NY PJM->LTFIMP_NY CLTF 0.43 MW 0.43 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.28 MW 0.28 MW
WEC LTFEXP_WEC->PJM CLTF 0.15 MW 0.15 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.61 MW 3.61 MW
TVA LTFEXP_TVA->PJM CLTF 1.61 MW 1.61 MW
MEC LTFEXP_MEC->PJM CLTF 0.95 MW 0.95 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.07 MW 2.07 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.72 MW 1.72 MW

Details for 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2092_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 128.4 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 733.82 MVA
MW Contribution: 10.17 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 133.17 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 761.07 MVA
MW Contribution: 10.43 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.01 MW 1.01 MW
961941 AG1-037 C 80/20 0.91 MW 0.91 MW
962331 AG1-082 C 80/20 3.62 MW 3.62 MW
966801 AG1-551 C 80/20 3.46 MW 3.46 MW
966811 AG1-552 C 80/20 1.92 MW 1.92 MW
965291 AG1-394 C 80/20 0.61 MW 0.61 MW
966621 AG1-532 C 80/20 0.86 MW 0.86 MW
313506 AB1-173 C OP 80/20 0.86 MW 0.86 MW
314704 3LAWRENC 80/20 0.15 MW 0.15 MW
315126 1ROARAP2 80/20 1.29 MW 1.29 MW
315128 1ROARAP4 80/20 1.22 MW 1.22 MW
315131 1EDGECMA 80/20 14.36 MW 14.36 MW
315136 1ROSEMG1 80/20 2.0 MW 2.0 MW
315137 1ROSEMS1 80/20 1.24 MW 1.24 MW
315138 1ROSEMG2 80/20 0.94 MW 0.94 MW
315139 1GASTONA 80/20 3.02 MW 3.02 MW
315158 1KERR 1 80/20 0.12 MW 0.12 MW
315159 1KERR 2 80/20 0.35 MW 0.35 MW
315160 1KERR 3 80/20 0.35 MW 0.35 MW
315161 1KERR 4 80/20 0.35 MW 0.35 MW
315162 1KERR 5 80/20 0.35 MW 0.35 MW
934521 AD1-076 C 80/20 24.97 MW 24.97 MW
943171 AE2-346 C 80/20 0.4 MW 0.4 MW
960081 AF2-299 C 80/20 1.15 MW 1.15 MW
315163 1KERR 6 80/20 0.35 MW 0.35 MW
315164 1KERR 7 80/20 0.35 MW 0.35 MW
315601 1CONETOE2SOL 80/20 1.53 MW 1.53 MW
315606 3AA2-053SOLA 80/20 1.69 MW 1.69 MW
316129 AC1-054 C 80/20 0.71 MW 0.71 MW
316140 AB2-099 C 80/20 0.17 MW 0.17 MW
940491 AE2-034 C 80/20 2.33 MW 2.33 MW
946281 AF1-292 C 80/20 0.95 MW 0.95 MW
957521 AF2-046 C 80/20 17.77 MW 17.77 MW
957861 AF2-080 C 80/20 10.17 MW 10.17 MW
315115 1S HAMPT1 80/20 0.5 MW 0.5 MW
315141 1GASTONB 80/20 3.02 MW 3.02 MW
315292 1DOMTR78 80/20 2.64 MW 2.64 MW
315607 3AA1-063SOLA 80/20 1.19 MW 1.19 MW
315608 3AA2-088SOLA 80/20 0.7 MW 0.7 MW
315611 6Z1-036WIND 80/20 1.31 MW 1.31 MW
926071 AC1-086 C 80/20 20.79 MW 20.79 MW
927021 AC1-189 C 80/20 11.2 MW 11.2 MW
933981 AD1-022 C 80/20 18.32 MW 18.32 MW
961681 AG1-008 C 80/20 17.77 MW 17.77 MW
962571 AG1-106 C 80/20 2.69 MW 2.69 MW
316005 AA1-067 C 80/20 0.42 MW 0.42 MW
316011 AB1-132 C OP 80/20 2.31 MW 2.31 MW
316023 AB2-100 C2 80/20 0.6 MW 0.6 MW
316049 AB1-081 C OP 80/20 1.5 MW 1.5 MW
316210 AC1-098 C 80/20 1.38 MW 1.38 MW
316212 AC1-099 C 80/20 0.46 MW 0.46 MW
316263 AC1-034 C 80/20 6.84 MW 6.84 MW
316274 AC1-208 C 80/20 11.68 MW 11.68 MW
316317 KELFORD C 80/20 0.65 MW 0.65 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.29 MW 0.29 MW
316365 AB2-100 C1 80/20 0.6 MW 0.6 MW
315602 1HOLLOMANSOL 80/20 4.11 MW 4.11 MW
316327 AA2-057 C 80/20 1.78 MW 1.78 MW
315614 AA2-178 C 80/20 3.17 MW 3.17 MW
316181 AB2-040 GEN 80/20 0.97 MW 0.97 MW
316359 AB2-059 C OP 80/20 1.68 MW 1.68 MW
316174 AB2-169_C 80/20 1.89 MW 1.89 MW
316087 AB2-174 C 80/20 0.84 MW 0.84 MW
313764 3SOCKMAN 80/20 0.61 MW 0.61 MW
932631 AC2-084 C 80/20 1.46 MW 1.46 MW
934321 AD1-056 C 80/20 5.93 MW 5.93 MW
934331 AD1-057 C 80/20 3.31 MW 3.31 MW
934501 AD1-074 C 80/20 68.76 MW 68.76 MW
934511 AD1-075 C 80/20 17.19 MW 17.19 MW
940481 AE2-033 C 80/20 4.49 MW 4.49 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.3 MW 12.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.06 MW 8.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 35.94 MW 35.94 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.46 MW 0.46 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.94 MW 4.94 MW
TVA LTFEXP_TVA->PJM CLTF 2.13 MW 2.13 MW
MEC LTFEXP_MEC->PJM CLTF 1.47 MW 1.47 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.73 MW 2.73 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.35 MW 2.35 MW

Details for 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2131_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
DVP_P1-2: LN 2131_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2131_SRT-A'
 OPEN BRANCH FROM BUS 313015 TO BUS 313714 CKT 1   /*6CHOWAN      230.0 - 6PEMBROKE    230.0
 OPEN BRANCH FROM BUS 313015 TO BUS 314637 CKT 1   /*6CHOWAN      230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313015                                   /*6CHOWAN      230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 127.21 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 727.02 MVA
MW Contribution: 10.17 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
DVP_P1-2: LN 2131_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2131_SRT-A'
 OPEN BRANCH FROM BUS 313015 TO BUS 313714 CKT 1   /*6CHOWAN      230.0 - 6PEMBROKE    230.0
 OPEN BRANCH FROM BUS 313015 TO BUS 314637 CKT 1   /*6CHOWAN      230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313015                                   /*6CHOWAN      230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 131.98 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 754.27 MVA
MW Contribution: 10.43 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.01 MW 1.01 MW
961941 AG1-037 C 80/20 0.91 MW 0.91 MW
962331 AG1-082 C 80/20 3.62 MW 3.62 MW
966801 AG1-551 C 80/20 3.46 MW 3.46 MW
966811 AG1-552 C 80/20 1.92 MW 1.92 MW
965291 AG1-394 C 80/20 0.61 MW 0.61 MW
966621 AG1-532 C 80/20 0.86 MW 0.86 MW
313506 AB1-173 C OP 80/20 0.86 MW 0.86 MW
314704 3LAWRENC 80/20 0.15 MW 0.15 MW
315126 1ROARAP2 80/20 1.29 MW 1.29 MW
315128 1ROARAP4 80/20 1.22 MW 1.22 MW
315131 1EDGECMA 80/20 14.36 MW 14.36 MW
315136 1ROSEMG1 80/20 2.0 MW 2.0 MW
315137 1ROSEMS1 80/20 1.24 MW 1.24 MW
315138 1ROSEMG2 80/20 0.94 MW 0.94 MW
315139 1GASTONA 80/20 3.02 MW 3.02 MW
315158 1KERR 1 80/20 0.12 MW 0.12 MW
315159 1KERR 2 80/20 0.35 MW 0.35 MW
315160 1KERR 3 80/20 0.35 MW 0.35 MW
315161 1KERR 4 80/20 0.35 MW 0.35 MW
315162 1KERR 5 80/20 0.35 MW 0.35 MW
934521 AD1-076 C 80/20 24.98 MW 24.98 MW
943171 AE2-346 C 80/20 0.4 MW 0.4 MW
960081 AF2-299 C 80/20 1.15 MW 1.15 MW
315163 1KERR 6 80/20 0.35 MW 0.35 MW
315164 1KERR 7 80/20 0.35 MW 0.35 MW
315601 1CONETOE2SOL 80/20 1.53 MW 1.53 MW
315606 3AA2-053SOLA 80/20 1.7 MW 1.7 MW
316129 AC1-054 C 80/20 0.71 MW 0.71 MW
316140 AB2-099 C 80/20 0.17 MW 0.17 MW
940491 AE2-034 C 80/20 2.33 MW 2.33 MW
946281 AF1-292 C 80/20 0.95 MW 0.95 MW
957521 AF2-046 C 80/20 17.77 MW 17.77 MW
957861 AF2-080 C 80/20 10.17 MW 10.17 MW
315115 1S HAMPT1 80/20 0.5 MW 0.5 MW
315141 1GASTONB 80/20 3.02 MW 3.02 MW
315292 1DOMTR78 80/20 2.64 MW 2.64 MW
315607 3AA1-063SOLA 80/20 1.19 MW 1.19 MW
315608 3AA2-088SOLA 80/20 0.7 MW 0.7 MW
926071 AC1-086 C 80/20 20.8 MW 20.8 MW
927021 AC1-189 C 80/20 11.2 MW 11.2 MW
933981 AD1-022 C 80/20 18.32 MW 18.32 MW
961681 AG1-008 C 80/20 17.77 MW 17.77 MW
962571 AG1-106 C 80/20 2.69 MW 2.69 MW
316005 AA1-067 C 80/20 0.42 MW 0.42 MW
316011 AB1-132 C OP 80/20 2.31 MW 2.31 MW
316023 AB2-100 C2 80/20 0.6 MW 0.6 MW
316049 AB1-081 C OP 80/20 1.5 MW 1.5 MW
316210 AC1-098 C 80/20 1.38 MW 1.38 MW
316212 AC1-099 C 80/20 0.46 MW 0.46 MW
316263 AC1-034 C 80/20 6.84 MW 6.84 MW
316274 AC1-208 C 80/20 11.69 MW 11.69 MW
316317 KELFORD C 80/20 0.65 MW 0.65 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.29 MW 0.29 MW
316365 AB2-100 C1 80/20 0.6 MW 0.6 MW
315602 1HOLLOMANSOL 80/20 4.11 MW 4.11 MW
316327 AA2-057 C 80/20 1.78 MW 1.78 MW
315614 AA2-178 C 80/20 3.17 MW 3.17 MW
316181 AB2-040 GEN 80/20 0.97 MW 0.97 MW
316359 AB2-059 C OP 80/20 1.69 MW 1.69 MW
316174 AB2-169_C 80/20 1.9 MW 1.9 MW
316087 AB2-174 C 80/20 0.84 MW 0.84 MW
313764 3SOCKMAN 80/20 0.61 MW 0.61 MW
932631 AC2-084 C 80/20 1.46 MW 1.46 MW
934321 AD1-056 C 80/20 5.93 MW 5.93 MW
934331 AD1-057 C 80/20 3.31 MW 3.31 MW
934501 AD1-074 C 80/20 68.78 MW 68.78 MW
934511 AD1-075 C 80/20 17.19 MW 17.19 MW
940481 AE2-033 C 80/20 4.49 MW 4.49 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.4 MW 12.4 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.1 MW 8.1 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 35.99 MW 35.99 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.47 MW 0.47 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.95 MW 4.95 MW
TVA LTFEXP_TVA->PJM CLTF 2.13 MW 2.13 MW
MEC LTFEXP_MEC->PJM CLTF 1.48 MW 1.48 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.74 MW 2.74 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.36 MW 2.36 MW

Details for 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2092_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 123.46 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 705.6 MVA
MW Contribution: 10.17 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 128.25 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 732.95 MVA
MW Contribution: 10.43 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.01 MW 1.01 MW
961941 AG1-037 C 80/20 0.91 MW 0.91 MW
962331 AG1-082 C 80/20 3.62 MW 3.62 MW
966801 AG1-551 C 80/20 3.46 MW 3.46 MW
966811 AG1-552 C 80/20 1.92 MW 1.92 MW
965291 AG1-394 C 80/20 0.61 MW 0.61 MW
966621 AG1-532 C 80/20 0.86 MW 0.86 MW
313506 AB1-173 C OP 80/20 0.86 MW 0.86 MW
314704 3LAWRENC 80/20 0.15 MW 0.15 MW
315126 1ROARAP2 80/20 1.29 MW 1.29 MW
315128 1ROARAP4 80/20 1.22 MW 1.22 MW
315131 1EDGECMA 80/20 14.36 MW 14.36 MW
315136 1ROSEMG1 80/20 2.0 MW 2.0 MW
315137 1ROSEMS1 80/20 1.24 MW 1.24 MW
315138 1ROSEMG2 80/20 0.94 MW 0.94 MW
315139 1GASTONA 80/20 3.02 MW 3.02 MW
315158 1KERR 1 80/20 0.12 MW 0.12 MW
315159 1KERR 2 80/20 0.35 MW 0.35 MW
315160 1KERR 3 80/20 0.35 MW 0.35 MW
315161 1KERR 4 80/20 0.35 MW 0.35 MW
315162 1KERR 5 80/20 0.35 MW 0.35 MW
934521 AD1-076 C 80/20 24.97 MW 24.97 MW
943171 AE2-346 C 80/20 0.4 MW 0.4 MW
960081 AF2-299 C 80/20 1.15 MW 1.15 MW
315163 1KERR 6 80/20 0.35 MW 0.35 MW
315164 1KERR 7 80/20 0.35 MW 0.35 MW
315601 1CONETOE2SOL 80/20 1.53 MW 1.53 MW
315606 3AA2-053SOLA 80/20 1.69 MW 1.69 MW
316129 AC1-054 C 80/20 0.71 MW 0.71 MW
316140 AB2-099 C 80/20 0.17 MW 0.17 MW
940491 AE2-034 C 80/20 2.33 MW 2.33 MW
946281 AF1-292 C 80/20 0.95 MW 0.95 MW
957521 AF2-046 C 80/20 17.77 MW 17.77 MW
957861 AF2-080 C 80/20 10.17 MW 10.17 MW
315115 1S HAMPT1 80/20 0.5 MW 0.5 MW
315141 1GASTONB 80/20 3.02 MW 3.02 MW
315292 1DOMTR78 80/20 2.64 MW 2.64 MW
315607 3AA1-063SOLA 80/20 1.19 MW 1.19 MW
315608 3AA2-088SOLA 80/20 0.7 MW 0.7 MW
315611 6Z1-036WIND 80/20 1.31 MW 1.31 MW
926071 AC1-086 C 80/20 20.79 MW 20.79 MW
927021 AC1-189 C 80/20 11.2 MW 11.2 MW
933981 AD1-022 C 80/20 18.32 MW 18.32 MW
961681 AG1-008 C 80/20 17.77 MW 17.77 MW
962571 AG1-106 C 80/20 2.69 MW 2.69 MW
316005 AA1-067 C 80/20 0.42 MW 0.42 MW
316011 AB1-132 C OP 80/20 2.31 MW 2.31 MW
316023 AB2-100 C2 80/20 0.6 MW 0.6 MW
316049 AB1-081 C OP 80/20 1.5 MW 1.5 MW
316210 AC1-098 C 80/20 1.38 MW 1.38 MW
316212 AC1-099 C 80/20 0.46 MW 0.46 MW
316263 AC1-034 C 80/20 6.84 MW 6.84 MW
316274 AC1-208 C 80/20 11.68 MW 11.68 MW
316317 KELFORD C 80/20 0.65 MW 0.65 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.29 MW 0.29 MW
316365 AB2-100 C1 80/20 0.6 MW 0.6 MW
315602 1HOLLOMANSOL 80/20 4.11 MW 4.11 MW
316327 AA2-057 C 80/20 1.78 MW 1.78 MW
315614 AA2-178 C 80/20 3.17 MW 3.17 MW
316181 AB2-040 GEN 80/20 0.97 MW 0.97 MW
316359 AB2-059 C OP 80/20 1.68 MW 1.68 MW
316174 AB2-169_C 80/20 1.89 MW 1.89 MW
316087 AB2-174 C 80/20 0.84 MW 0.84 MW
313764 3SOCKMAN 80/20 0.61 MW 0.61 MW
932631 AC2-084 C 80/20 1.46 MW 1.46 MW
934321 AD1-056 C 80/20 5.93 MW 5.93 MW
934331 AD1-057 C 80/20 3.31 MW 3.31 MW
934501 AD1-074 C 80/20 68.76 MW 68.76 MW
934511 AD1-075 C 80/20 17.19 MW 17.19 MW
940481 AE2-033 C 80/20 4.49 MW 4.49 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.3 MW 12.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.06 MW 8.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 35.94 MW 35.94 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.46 MW 0.46 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.94 MW 4.94 MW
TVA LTFEXP_TVA->PJM CLTF 2.13 MW 2.13 MW
MEC LTFEXP_MEC->PJM CLTF 1.47 MW 1.47 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.73 MW 2.73 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.35 MW 2.35 MW

Details for 6SAPONY-6CARSON 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 246_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 117.31 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 796.16 MVA
MW Contribution: 8.56 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 127.67 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 866.5 MVA
MW Contribution: 8.7 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.09 MW 1.09 MW
961941 AG1-037 C 80/20 0.65 MW 0.65 MW
962331 AG1-082 C 80/20 2.62 MW 2.62 MW
964791 AG1-342 C 80/20 1.1 MW 1.1 MW
966801 AG1-551 C 80/20 2.19 MW 2.19 MW
966811 AG1-552 C 80/20 3.48 MW 3.48 MW
965291 AG1-394 C 80/20 0.91 MW 0.91 MW
966621 AG1-532 C 80/20 3.41 MW 3.41 MW
313506 AB1-173 C OP 80/20 2.36 MW 2.36 MW
314704 3LAWRENC 80/20 0.57 MW 0.57 MW
315126 1ROARAP2 80/20 2.34 MW 2.34 MW
315128 1ROARAP4 80/20 2.22 MW 2.22 MW
315131 1EDGECMA 80/20 18.43 MW 18.43 MW
315136 1ROSEMG1 80/20 4.3 MW 4.3 MW
315137 1ROSEMS1 80/20 2.66 MW 2.66 MW
315138 1ROSEMG2 80/20 2.01 MW 2.01 MW
315139 1GASTONA 80/20 6.74 MW 6.74 MW
315158 1KERR 1 80/20 0.23 MW 0.23 MW
315159 1KERR 2 80/20 0.66 MW 0.66 MW
315160 1KERR 3 80/20 0.66 MW 0.66 MW
315161 1KERR 4 80/20 0.66 MW 0.66 MW
315162 1KERR 5 80/20 0.66 MW 0.66 MW
934521 AD1-076 C 80/20 10.33 MW 10.33 MW
943171 AE2-346 C 80/20 0.29 MW 0.29 MW
960081 AF2-299 C 80/20 4.55 MW 4.55 MW
315163 1KERR 6 80/20 0.66 MW 0.66 MW
315164 1KERR 7 80/20 0.66 MW 0.66 MW
315601 1CONETOE2SOL 80/20 1.42 MW 1.42 MW
315606 3AA2-053SOLA 80/20 2.46 MW 2.46 MW
316129 AC1-054 C 80/20 1.31 MW 1.31 MW
316131 AB2-060 C 80/20 0.65 MW 0.65 MW
316140 AB2-099 C 80/20 0.12 MW 0.12 MW
939181 AE1-148 C 80/20 4.96 MW 4.96 MW
940491 AE2-034 C 80/20 0.75 MW 0.75 MW
946281 AF1-292 C 80/20 3.77 MW 3.77 MW
957521 AF2-046 C 80/20 16.74 MW 16.74 MW
957861 AF2-080 C 80/20 8.56 MW 8.56 MW
938771 AE1-103 C 80/20 1.34 MW 1.34 MW
315115 1S HAMPT1 80/20 1.08 MW 1.08 MW
315141 1GASTONB 80/20 6.74 MW 6.74 MW
315292 1DOMTR78 80/20 1.22 MW 1.22 MW
315607 3AA1-063SOLA 80/20 2.03 MW 2.03 MW
315608 3AA2-088SOLA 80/20 1.08 MW 1.08 MW
315611 6Z1-036WIND 80/20 0.26 MW 0.26 MW
926071 AC1-086 C 80/20 46.36 MW 46.36 MW
927021 AC1-189 C 80/20 9.43 MW 9.43 MW
936261 AD2-033 C 80/20 4.7 MW 4.7 MW
933981 AD1-022 C 80/20 8.47 MW 8.47 MW
961681 AG1-008 C 80/20 16.74 MW 16.74 MW
962571 AG1-106 C 80/20 6.0 MW 6.0 MW
316005 AA1-067 C 80/20 0.29 MW 0.29 MW
316011 AB1-132 C OP 80/20 5.14 MW 5.14 MW
316023 AB2-100 C2 80/20 2.9 MW 2.9 MW
316049 AB1-081 C OP 80/20 1.66 MW 1.66 MW
316210 AC1-098 C 80/20 1.49 MW 1.49 MW
316212 AC1-099 C 80/20 0.5 MW 0.5 MW
316237 AB2-079 C O1 80/20 0.15 MW 0.15 MW
316238 AB2-078 C O1 80/20 0.15 MW 0.15 MW
316239 AB2-077 C O1 80/20 0.15 MW 0.15 MW
316263 AC1-034 C 80/20 7.8 MW 7.8 MW
316274 AC1-208 C 80/20 14.8 MW 14.8 MW
316315 AB2-025 C 80/20 1.69 MW 1.69 MW
316317 KELFORD C 80/20 0.51 MW 0.51 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.35 MW 0.35 MW
316365 AB2-100 C1 80/20 2.9 MW 2.9 MW
315602 1HOLLOMANSOL 80/20 2.42 MW 2.42 MW
316327 AA2-057 C 80/20 2.17 MW 2.17 MW
315614 AA2-178 C 80/20 1.02 MW 1.02 MW
316181 AB2-040 GEN 80/20 2.66 MW 2.66 MW
313527 AB2-043 C 80/20 0.23 MW 0.23 MW
316359 AB2-059 C OP 80/20 1.97 MW 1.97 MW
316174 AB2-169_C 80/20 1.0 MW 1.0 MW
316087 AB2-174 C 80/20 2.59 MW 2.59 MW
962561 AG1-105 C 80/20 2.96 MW 2.96 MW
313764 3SOCKMAN 80/20 1.34 MW 1.34 MW
932631 AC2-084 C 80/20 1.59 MW 1.59 MW
934321 AD1-056 C 80/20 10.11 MW 10.11 MW
934331 AD1-057 C 80/20 5.64 MW 5.64 MW
934501 AD1-074 C 80/20 28.45 MW 28.45 MW
934511 AD1-075 C 80/20 7.11 MW 7.11 MW
940481 AE2-033 C 80/20 64.77 MW 64.77 MW
940541 AE2-040 C 80/20 11.91 MW 11.91 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.13 MW 11.13 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.75 MW 7.75 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 36.21 MW 36.21 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.42 MW 0.42 MW
WEC LTFEXP_WEC->PJM CLTF 0.23 MW 0.23 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.95 MW 4.95 MW
TVA LTFEXP_TVA->PJM CLTF 2.08 MW 2.08 MW
MEC LTFEXP_MEC->PJM CLTF 1.37 MW 1.37 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.67 MW 2.67 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.08 MW 0.08 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.36 MW 2.36 MW

Details for 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2131_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
DVP_P1-2: LN 2131_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2131_SRT-A'
 OPEN BRANCH FROM BUS 313015 TO BUS 313714 CKT 1   /*6CHOWAN      230.0 - 6PEMBROKE    230.0
 OPEN BRANCH FROM BUS 313015 TO BUS 314637 CKT 1   /*6CHOWAN      230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313015                                   /*6CHOWAN      230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 122.28 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 698.84 MVA
MW Contribution: 10.17 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
DVP_P1-2: LN 2131_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2131_SRT-A'
 OPEN BRANCH FROM BUS 313015 TO BUS 313714 CKT 1   /*6CHOWAN      230.0 - 6PEMBROKE    230.0
 OPEN BRANCH FROM BUS 313015 TO BUS 314637 CKT 1   /*6CHOWAN      230.0 - 6EDENTON     230.0
 OPEN BRANCH FROM BUS 314203 TO BUS 314637 CKT 1   /*6MACKEYS     230.0 - 6EDENTON     230.0
 OPEN BUS 313015                                   /*6CHOWAN      230.0
 OPEN BUS 314637                                   /*6EDENTON     230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 127.06 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 726.15 MVA
MW Contribution: 10.43 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.01 MW 1.01 MW
961941 AG1-037 C 80/20 0.91 MW 0.91 MW
962331 AG1-082 C 80/20 3.62 MW 3.62 MW
966801 AG1-551 C 80/20 3.46 MW 3.46 MW
966811 AG1-552 C 80/20 1.92 MW 1.92 MW
965291 AG1-394 C 80/20 0.61 MW 0.61 MW
966621 AG1-532 C 80/20 0.86 MW 0.86 MW
313506 AB1-173 C OP 80/20 0.86 MW 0.86 MW
314704 3LAWRENC 80/20 0.15 MW 0.15 MW
315126 1ROARAP2 80/20 1.29 MW 1.29 MW
315128 1ROARAP4 80/20 1.22 MW 1.22 MW
315131 1EDGECMA 80/20 14.36 MW 14.36 MW
315136 1ROSEMG1 80/20 2.0 MW 2.0 MW
315137 1ROSEMS1 80/20 1.24 MW 1.24 MW
315138 1ROSEMG2 80/20 0.94 MW 0.94 MW
315139 1GASTONA 80/20 3.02 MW 3.02 MW
315158 1KERR 1 80/20 0.12 MW 0.12 MW
315159 1KERR 2 80/20 0.35 MW 0.35 MW
315160 1KERR 3 80/20 0.35 MW 0.35 MW
315161 1KERR 4 80/20 0.35 MW 0.35 MW
315162 1KERR 5 80/20 0.35 MW 0.35 MW
934521 AD1-076 C 80/20 24.98 MW 24.98 MW
943171 AE2-346 C 80/20 0.4 MW 0.4 MW
960081 AF2-299 C 80/20 1.15 MW 1.15 MW
315163 1KERR 6 80/20 0.35 MW 0.35 MW
315164 1KERR 7 80/20 0.35 MW 0.35 MW
315601 1CONETOE2SOL 80/20 1.53 MW 1.53 MW
315606 3AA2-053SOLA 80/20 1.7 MW 1.7 MW
316129 AC1-054 C 80/20 0.71 MW 0.71 MW
316140 AB2-099 C 80/20 0.17 MW 0.17 MW
940491 AE2-034 C 80/20 2.33 MW 2.33 MW
946281 AF1-292 C 80/20 0.95 MW 0.95 MW
957521 AF2-046 C 80/20 17.77 MW 17.77 MW
957861 AF2-080 C 80/20 10.17 MW 10.17 MW
315115 1S HAMPT1 80/20 0.5 MW 0.5 MW
315141 1GASTONB 80/20 3.02 MW 3.02 MW
315292 1DOMTR78 80/20 2.64 MW 2.64 MW
315607 3AA1-063SOLA 80/20 1.19 MW 1.19 MW
315608 3AA2-088SOLA 80/20 0.7 MW 0.7 MW
926071 AC1-086 C 80/20 20.8 MW 20.8 MW
927021 AC1-189 C 80/20 11.2 MW 11.2 MW
933981 AD1-022 C 80/20 18.32 MW 18.32 MW
961681 AG1-008 C 80/20 17.77 MW 17.77 MW
962571 AG1-106 C 80/20 2.69 MW 2.69 MW
316005 AA1-067 C 80/20 0.42 MW 0.42 MW
316011 AB1-132 C OP 80/20 2.31 MW 2.31 MW
316023 AB2-100 C2 80/20 0.6 MW 0.6 MW
316049 AB1-081 C OP 80/20 1.5 MW 1.5 MW
316210 AC1-098 C 80/20 1.38 MW 1.38 MW
316212 AC1-099 C 80/20 0.46 MW 0.46 MW
316263 AC1-034 C 80/20 6.84 MW 6.84 MW
316274 AC1-208 C 80/20 11.69 MW 11.69 MW
316317 KELFORD C 80/20 0.65 MW 0.65 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.29 MW 0.29 MW
316365 AB2-100 C1 80/20 0.6 MW 0.6 MW
315602 1HOLLOMANSOL 80/20 4.11 MW 4.11 MW
316327 AA2-057 C 80/20 1.78 MW 1.78 MW
315614 AA2-178 C 80/20 3.17 MW 3.17 MW
316181 AB2-040 GEN 80/20 0.97 MW 0.97 MW
316359 AB2-059 C OP 80/20 1.69 MW 1.69 MW
316174 AB2-169_C 80/20 1.9 MW 1.9 MW
316087 AB2-174 C 80/20 0.84 MW 0.84 MW
313764 3SOCKMAN 80/20 0.61 MW 0.61 MW
932631 AC2-084 C 80/20 1.46 MW 1.46 MW
934321 AD1-056 C 80/20 5.93 MW 5.93 MW
934331 AD1-057 C 80/20 3.31 MW 3.31 MW
934501 AD1-074 C 80/20 68.78 MW 68.78 MW
934511 AD1-075 C 80/20 17.19 MW 17.19 MW
940481 AE2-033 C 80/20 4.49 MW 4.49 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.4 MW 12.4 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.1 MW 8.1 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 35.99 MW 35.99 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.47 MW 0.47 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.95 MW 4.95 MW
TVA LTFEXP_TVA->PJM CLTF 2.13 MW 2.13 MW
MEC LTFEXP_MEC->PJM CLTF 1.48 MW 1.48 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.74 MW 2.74 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.36 MW 2.36 MW

Details for AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 246_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 114.48 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 776.96 MVA
MW Contribution: 8.57 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 124.97 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 848.14 MVA
MW Contribution: 8.7 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.09 MW 1.09 MW
961941 AG1-037 C 80/20 0.66 MW 0.66 MW
962331 AG1-082 C 80/20 2.62 MW 2.62 MW
964791 AG1-342 C 80/20 1.11 MW 1.11 MW
966801 AG1-551 C 80/20 2.19 MW 2.19 MW
966811 AG1-552 C 80/20 3.48 MW 3.48 MW
965291 AG1-394 C 80/20 0.91 MW 0.91 MW
966621 AG1-532 C 80/20 3.41 MW 3.41 MW
313506 AB1-173 C OP 80/20 2.36 MW 2.36 MW
314704 3LAWRENC 80/20 0.57 MW 0.57 MW
315126 1ROARAP2 80/20 2.35 MW 2.35 MW
315128 1ROARAP4 80/20 2.22 MW 2.22 MW
315131 1EDGECMA 80/20 18.44 MW 18.44 MW
315136 1ROSEMG1 80/20 4.3 MW 4.3 MW
315137 1ROSEMS1 80/20 2.66 MW 2.66 MW
315138 1ROSEMG2 80/20 2.01 MW 2.01 MW
315139 1GASTONA 80/20 6.74 MW 6.74 MW
315158 1KERR 1 80/20 0.23 MW 0.23 MW
315159 1KERR 2 80/20 0.66 MW 0.66 MW
315160 1KERR 3 80/20 0.66 MW 0.66 MW
315161 1KERR 4 80/20 0.66 MW 0.66 MW
315162 1KERR 5 80/20 0.66 MW 0.66 MW
934521 AD1-076 C 80/20 10.34 MW 10.34 MW
943171 AE2-346 C 80/20 0.29 MW 0.29 MW
960081 AF2-299 C 80/20 4.55 MW 4.55 MW
315163 1KERR 6 80/20 0.66 MW 0.66 MW
315164 1KERR 7 80/20 0.66 MW 0.66 MW
315601 1CONETOE2SOL 80/20 1.43 MW 1.43 MW
315606 3AA2-053SOLA 80/20 2.46 MW 2.46 MW
316129 AC1-054 C 80/20 1.31 MW 1.31 MW
316131 AB2-060 C 80/20 0.65 MW 0.65 MW
316140 AB2-099 C 80/20 0.12 MW 0.12 MW
939181 AE1-148 C 80/20 4.96 MW 4.96 MW
940491 AE2-034 C 80/20 0.75 MW 0.75 MW
946281 AF1-292 C 80/20 3.77 MW 3.77 MW
957521 AF2-046 C 80/20 16.75 MW 16.75 MW
957861 AF2-080 C 80/20 8.57 MW 8.57 MW
938771 AE1-103 C 80/20 1.35 MW 1.35 MW
315115 1S HAMPT1 80/20 1.08 MW 1.08 MW
315141 1GASTONB 80/20 6.74 MW 6.74 MW
315292 1DOMTR78 80/20 1.22 MW 1.22 MW
315607 3AA1-063SOLA 80/20 2.03 MW 2.03 MW
315608 3AA2-088SOLA 80/20 1.08 MW 1.08 MW
315611 6Z1-036WIND 80/20 0.26 MW 0.26 MW
926071 AC1-086 C 80/20 46.37 MW 46.37 MW
927021 AC1-189 C 80/20 9.43 MW 9.43 MW
936261 AD2-033 C 80/20 4.71 MW 4.71 MW
933981 AD1-022 C 80/20 8.47 MW 8.47 MW
961681 AG1-008 C 80/20 16.75 MW 16.75 MW
962571 AG1-106 C 80/20 6.0 MW 6.0 MW
316005 AA1-067 C 80/20 0.3 MW 0.3 MW
316011 AB1-132 C OP 80/20 5.14 MW 5.14 MW
316023 AB2-100 C2 80/20 2.9 MW 2.9 MW
316049 AB1-081 C OP 80/20 1.67 MW 1.67 MW
316210 AC1-098 C 80/20 1.5 MW 1.5 MW
316212 AC1-099 C 80/20 0.5 MW 0.5 MW
316237 AB2-079 C O1 80/20 0.15 MW 0.15 MW
316238 AB2-078 C O1 80/20 0.15 MW 0.15 MW
316239 AB2-077 C O1 80/20 0.15 MW 0.15 MW
316263 AC1-034 C 80/20 7.8 MW 7.8 MW
316274 AC1-208 C 80/20 14.81 MW 14.81 MW
316317 KELFORD C 80/20 0.51 MW 0.51 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.35 MW 0.35 MW
316365 AB2-100 C1 80/20 2.9 MW 2.9 MW
315602 1HOLLOMANSOL 80/20 2.42 MW 2.42 MW
316327 AA2-057 C 80/20 2.17 MW 2.17 MW
315614 AA2-178 C 80/20 1.02 MW 1.02 MW
316181 AB2-040 GEN 80/20 2.66 MW 2.66 MW
313527 AB2-043 C 80/20 0.23 MW 0.23 MW
316359 AB2-059 C OP 80/20 1.97 MW 1.97 MW
316174 AB2-169_C 80/20 1.0 MW 1.0 MW
316087 AB2-174 C 80/20 2.59 MW 2.59 MW
962561 AG1-105 C 80/20 2.96 MW 2.96 MW
313764 3SOCKMAN 80/20 1.34 MW 1.34 MW
932631 AC2-084 C 80/20 1.59 MW 1.59 MW
934321 AD1-056 C 80/20 10.12 MW 10.12 MW
934331 AD1-057 C 80/20 5.64 MW 5.64 MW
934501 AD1-074 C 80/20 28.46 MW 28.46 MW
934511 AD1-075 C 80/20 7.12 MW 7.12 MW
940481 AE2-033 C 80/20 64.78 MW 64.78 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.25 MW 11.25 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.8 MW 7.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 36.28 MW 36.28 MW
NY PJM->LTFIMP_NY CLTF 0.35 MW 0.35 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.43 MW 0.43 MW
WEC LTFEXP_WEC->PJM CLTF 0.23 MW 0.23 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.95 MW 4.95 MW
TVA LTFEXP_TVA->PJM CLTF 2.09 MW 2.09 MW
MEC LTFEXP_MEC->PJM CLTF 1.38 MW 1.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.68 MW 2.68 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.36 MW 2.36 MW

Details for 6SAPONY-6CARSON 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 556_SRT-S-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 118.96 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 807.34 MVA
MW Contribution: 6.8 MW
Impact of Topology Modeling:
Decrease
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.92 MW 0.92 MW
961791 AG1-021 C 80/20 0.91 MW 0.91 MW
961941 AG1-037 C 80/20 0.48 MW 0.48 MW
962331 AG1-082 C 80/20 1.93 MW 1.93 MW
963171 AG1-166 C 80/20 0.51 MW 0.51 MW
963181 AG1-167 C 80/20 0.38 MW 0.38 MW
963191 AG1-168 C 80/20 0.38 MW 0.38 MW
964791 AG1-342 C 80/20 2.04 MW 2.04 MW
966801 AG1-551 C 80/20 1.62 MW 1.62 MW
966811 AG1-552 C 80/20 3.22 MW 3.22 MW
965291 AG1-394 C 80/20 0.8 MW 0.8 MW
966621 AG1-532 C 80/20 3.32 MW 3.32 MW
313506 AB1-173 C OP 80/20 2.25 MW 2.25 MW
313853 3PONTONDP 80/20 0.34 MW 0.34 MW
314429 3JTRSVLE 80/20 0.21 MW 0.21 MW
314704 3LAWRENC 80/20 0.58 MW 0.58 MW
315126 1ROARAP2 80/20 2.17 MW 2.17 MW
315128 1ROARAP4 80/20 2.06 MW 2.06 MW
315131 1EDGECMA 80/20 16.07 MW 16.07 MW
315136 1ROSEMG1 80/20 3.94 MW 3.94 MW
315137 1ROSEMS1 80/20 2.44 MW 2.44 MW
315138 1ROSEMG2 80/20 1.85 MW 1.85 MW
315139 1GASTONA 80/20 6.2 MW 6.2 MW
315153 1CLOVER1 80/20 5.83 MW 5.83 MW
315158 1KERR 1 80/20 0.31 MW 0.31 MW
315159 1KERR 2 80/20 0.87 MW 0.87 MW
315160 1KERR 3 80/20 0.87 MW 0.87 MW
315161 1KERR 4 80/20 0.87 MW 0.87 MW
315162 1KERR 5 80/20 0.87 MW 0.87 MW
934521 AD1-076 C 80/20 7.16 MW 7.16 MW
943171 AE2-346 C 80/20 0.21 MW 0.21 MW
959311 AF2-222 C 80/20 8.68 MW 8.68 MW
960081 AF2-299 C 80/20 4.42 MW 4.42 MW
315163 1KERR 6 80/20 0.87 MW 0.87 MW
315164 1KERR 7 80/20 0.87 MW 0.87 MW
315266 1PLYWOOD A 80/20 0.64 MW 0.64 MW
315601 1CONETOE2SOL 80/20 1.16 MW 1.16 MW
315606 3AA2-053SOLA 80/20 2.2 MW 2.2 MW
316118 AC1-105 C 80/20 0.48 MW 0.48 MW
316129 AC1-054 C 80/20 1.36 MW 1.36 MW
316131 AB2-060 C 80/20 1.04 MW 1.04 MW
316140 AB2-099 C 80/20 0.09 MW 0.09 MW
939181 AE1-148 C 80/20 6.76 MW 6.76 MW
946281 AF1-292 C 80/20 3.66 MW 3.66 MW
946301 AF1-294 C 80/20 1.88 MW 1.88 MW
957481 AF2-042 C 80/20 24.39 MW 24.39 MW
957521 AF2-046 C 80/20 13.45 MW 13.45 MW
957861 AF2-080 C 80/20 6.8 MW 6.8 MW
958211 AF2-115 C 80/20 1.14 MW 1.14 MW
315115 1S HAMPT1 80/20 0.98 MW 0.98 MW
315141 1GASTONB 80/20 6.2 MW 6.2 MW
315292 1DOMTR78 80/20 0.86 MW 0.86 MW
315607 3AA1-063SOLA 80/20 1.85 MW 1.85 MW
315608 3AA2-088SOLA 80/20 0.95 MW 0.95 MW
926071 AC1-086 C 80/20 42.64 MW 42.64 MW
927021 AC1-189 C 80/20 7.49 MW 7.49 MW
936261 AD2-033 C 80/20 8.08 MW 8.08 MW
934621 AD1-088 C 80/20 5.85 MW 5.85 MW
933981 AD1-022 C 80/20 5.8 MW 5.8 MW
961681 AG1-008 C 80/20 13.45 MW 13.45 MW
962571 AG1-106 C 80/20 5.52 MW 5.52 MW
316005 AA1-067 C 80/20 0.22 MW 0.22 MW
316011 AB1-132 C OP 80/20 4.73 MW 4.73 MW
316023 AB2-100 C2 80/20 2.78 MW 2.78 MW
316034 AC1-036 C 80/20 0.12 MW 0.12 MW
316049 AB1-081 C OP 80/20 1.41 MW 1.41 MW
316210 AC1-098 C 80/20 1.26 MW 1.26 MW
316212 AC1-099 C 80/20 0.42 MW 0.42 MW
316237 AB2-079 C O1 80/20 0.23 MW 0.23 MW
316238 AB2-078 C O1 80/20 0.23 MW 0.23 MW
316239 AB2-077 C O1 80/20 0.23 MW 0.23 MW
316263 AC1-034 C 80/20 6.65 MW 6.65 MW
316274 AC1-208 C 80/20 12.92 MW 12.92 MW
316315 AB2-025 C 80/20 1.66 MW 1.66 MW
316317 KELFORD C 80/20 0.39 MW 0.39 MW
316318 V4-068 C 80/20 0.08 MW 0.08 MW
316319 Z2-044 C 80/20 0.31 MW 0.31 MW
316365 AB2-100 C1 80/20 2.78 MW 2.78 MW
315602 1HOLLOMANSOL 80/20 1.62 MW 1.62 MW
316327 AA2-057 C 80/20 1.87 MW 1.87 MW
316181 AB2-040 GEN 80/20 2.54 MW 2.54 MW
313527 AB2-043 C 80/20 0.36 MW 0.36 MW
316359 AB2-059 C OP 80/20 1.69 MW 1.69 MW
316174 AB2-169_C 80/20 0.72 MW 0.72 MW
316087 AB2-174 C 80/20 2.49 MW 2.49 MW
962561 AG1-105 C 80/20 5.31 MW 5.31 MW
964241 AG1-285 C 80/20 7.26 MW 7.26 MW
313764 3SOCKMAN 80/20 1.26 MW 1.26 MW
932631 AC2-084 C 80/20 1.34 MW 1.34 MW
934321 AD1-056 C 80/20 9.1 MW 9.1 MW
934331 AD1-057 C 80/20 5.08 MW 5.08 MW
934501 AD1-074 C 80/20 19.73 MW 19.73 MW
934511 AD1-075 C 80/20 4.93 MW 4.93 MW
940481 AE2-033 C 80/20 63.5 MW 63.5 MW
940541 AE2-040 C 80/20 11.7 MW 11.7 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.6 MW 10.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.24 MW 7.24 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 32.94 MW 32.94 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.41 MW 0.41 MW
WEC LTFEXP_WEC->PJM CLTF 0.22 MW 0.22 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.44 MW 4.44 MW
TVA LTFEXP_TVA->PJM CLTF 1.93 MW 1.93 MW
MEC LTFEXP_MEC->PJM CLTF 1.29 MW 1.29 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.47 MW 2.47 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.08 MW 0.08 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.12 MW 2.12 MW

Details for AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 556_SRT-S-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 116.16 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 788.36 MVA
MW Contribution: 6.81 MW
Impact of Topology Modeling:
Decrease
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.92 MW 0.92 MW
961791 AG1-021 C 80/20 0.91 MW 0.91 MW
961941 AG1-037 C 80/20 0.48 MW 0.48 MW
962331 AG1-082 C 80/20 1.93 MW 1.93 MW
963171 AG1-166 C 80/20 0.51 MW 0.51 MW
963181 AG1-167 C 80/20 0.38 MW 0.38 MW
963191 AG1-168 C 80/20 0.38 MW 0.38 MW
964791 AG1-342 C 80/20 2.04 MW 2.04 MW
966801 AG1-551 C 80/20 1.62 MW 1.62 MW
966811 AG1-552 C 80/20 3.22 MW 3.22 MW
965291 AG1-394 C 80/20 0.8 MW 0.8 MW
966621 AG1-532 C 80/20 3.32 MW 3.32 MW
313506 AB1-173 C OP 80/20 2.26 MW 2.26 MW
313853 3PONTONDP 80/20 0.34 MW 0.34 MW
314429 3JTRSVLE 80/20 0.21 MW 0.21 MW
314704 3LAWRENC 80/20 0.58 MW 0.58 MW
315126 1ROARAP2 80/20 2.17 MW 2.17 MW
315128 1ROARAP4 80/20 2.06 MW 2.06 MW
315131 1EDGECMA 80/20 16.08 MW 16.08 MW
315136 1ROSEMG1 80/20 3.94 MW 3.94 MW
315137 1ROSEMS1 80/20 2.44 MW 2.44 MW
315138 1ROSEMG2 80/20 1.85 MW 1.85 MW
315139 1GASTONA 80/20 6.2 MW 6.2 MW
315153 1CLOVER1 80/20 5.84 MW 5.84 MW
315158 1KERR 1 80/20 0.31 MW 0.31 MW
315159 1KERR 2 80/20 0.87 MW 0.87 MW
315160 1KERR 3 80/20 0.87 MW 0.87 MW
315161 1KERR 4 80/20 0.87 MW 0.87 MW
315162 1KERR 5 80/20 0.87 MW 0.87 MW
934521 AD1-076 C 80/20 7.17 MW 7.17 MW
943171 AE2-346 C 80/20 0.21 MW 0.21 MW
959311 AF2-222 C 80/20 8.69 MW 8.69 MW
960081 AF2-299 C 80/20 4.42 MW 4.42 MW
315163 1KERR 6 80/20 0.87 MW 0.87 MW
315164 1KERR 7 80/20 0.87 MW 0.87 MW
315266 1PLYWOOD A 80/20 0.64 MW 0.64 MW
315601 1CONETOE2SOL 80/20 1.16 MW 1.16 MW
315606 3AA2-053SOLA 80/20 2.2 MW 2.2 MW
316118 AC1-105 C 80/20 0.49 MW 0.49 MW
316129 AC1-054 C 80/20 1.36 MW 1.36 MW
316131 AB2-060 C 80/20 1.04 MW 1.04 MW
316140 AB2-099 C 80/20 0.09 MW 0.09 MW
939181 AE1-148 C 80/20 6.76 MW 6.76 MW
946281 AF1-292 C 80/20 3.66 MW 3.66 MW
946301 AF1-294 C 80/20 1.88 MW 1.88 MW
957481 AF2-042 C 80/20 24.41 MW 24.41 MW
957521 AF2-046 C 80/20 13.45 MW 13.45 MW
957861 AF2-080 C 80/20 6.81 MW 6.81 MW
958211 AF2-115 C 80/20 1.14 MW 1.14 MW
315115 1S HAMPT1 80/20 0.98 MW 0.98 MW
315141 1GASTONB 80/20 6.2 MW 6.2 MW
315292 1DOMTR78 80/20 0.87 MW 0.87 MW
315607 3AA1-063SOLA 80/20 1.85 MW 1.85 MW
315608 3AA2-088SOLA 80/20 0.95 MW 0.95 MW
926071 AC1-086 C 80/20 42.65 MW 42.65 MW
927021 AC1-189 C 80/20 7.49 MW 7.49 MW
936261 AD2-033 C 80/20 8.08 MW 8.08 MW
934621 AD1-088 C 80/20 5.85 MW 5.85 MW
933981 AD1-022 C 80/20 5.8 MW 5.8 MW
961681 AG1-008 C 80/20 13.45 MW 13.45 MW
962571 AG1-106 C 80/20 5.52 MW 5.52 MW
316005 AA1-067 C 80/20 0.22 MW 0.22 MW
316011 AB1-132 C OP 80/20 4.73 MW 4.73 MW
316023 AB2-100 C2 80/20 2.78 MW 2.78 MW
316034 AC1-036 C 80/20 0.12 MW 0.12 MW
316049 AB1-081 C OP 80/20 1.41 MW 1.41 MW
316210 AC1-098 C 80/20 1.26 MW 1.26 MW
316212 AC1-099 C 80/20 0.42 MW 0.42 MW
316237 AB2-079 C O1 80/20 0.23 MW 0.23 MW
316238 AB2-078 C O1 80/20 0.23 MW 0.23 MW
316239 AB2-077 C O1 80/20 0.23 MW 0.23 MW
316263 AC1-034 C 80/20 6.66 MW 6.66 MW
316274 AC1-208 C 80/20 12.92 MW 12.92 MW
316317 KELFORD C 80/20 0.39 MW 0.39 MW
316318 V4-068 C 80/20 0.08 MW 0.08 MW
316319 Z2-044 C 80/20 0.31 MW 0.31 MW
316365 AB2-100 C1 80/20 2.78 MW 2.78 MW
315602 1HOLLOMANSOL 80/20 1.62 MW 1.62 MW
316327 AA2-057 C 80/20 1.88 MW 1.88 MW
316181 AB2-040 GEN 80/20 2.54 MW 2.54 MW
313527 AB2-043 C 80/20 0.36 MW 0.36 MW
316359 AB2-059 C OP 80/20 1.69 MW 1.69 MW
316174 AB2-169_C 80/20 0.72 MW 0.72 MW
316087 AB2-174 C 80/20 2.49 MW 2.49 MW
962561 AG1-105 C 80/20 5.31 MW 5.31 MW
964241 AG1-285 C 80/20 7.27 MW 7.27 MW
313764 3SOCKMAN 80/20 1.26 MW 1.26 MW
932631 AC2-084 C 80/20 1.34 MW 1.34 MW
934321 AD1-056 C 80/20 9.11 MW 9.11 MW
934331 AD1-057 C 80/20 5.08 MW 5.08 MW
934501 AD1-074 C 80/20 19.74 MW 19.74 MW
934511 AD1-075 C 80/20 4.93 MW 4.93 MW
940481 AE2-033 C 80/20 63.5 MW 63.5 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.72 MW 10.72 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.28 MW 7.28 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 33.02 MW 33.02 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.41 MW 0.41 MW
WEC LTFEXP_WEC->PJM CLTF 0.22 MW 0.22 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.45 MW 4.45 MW
TVA LTFEXP_TVA->PJM CLTF 1.94 MW 1.94 MW
MEC LTFEXP_MEC->PJM CLTF 1.31 MW 1.31 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.48 MW 2.48 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.08 MW 0.08 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.12 MW 2.12 MW

Details for 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 246_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 105.2 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 713.99 MVA
MW Contribution: 8.57 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 116.12 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 788.11 MVA
MW Contribution: 8.7 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 1.09 MW 1.09 MW
961941 AG1-037 C 80/20 0.66 MW 0.66 MW
962331 AG1-082 C 80/20 2.62 MW 2.62 MW
964791 AG1-342 C 80/20 1.11 MW 1.11 MW
966801 AG1-551 C 80/20 2.19 MW 2.19 MW
966811 AG1-552 C 80/20 3.48 MW 3.48 MW
965291 AG1-394 C 80/20 0.91 MW 0.91 MW
966621 AG1-532 C 80/20 3.41 MW 3.41 MW
313506 AB1-173 C OP 80/20 2.36 MW 2.36 MW
314704 3LAWRENC 80/20 0.57 MW 0.57 MW
315126 1ROARAP2 80/20 2.35 MW 2.35 MW
315128 1ROARAP4 80/20 2.22 MW 2.22 MW
315131 1EDGECMA 80/20 18.44 MW 18.44 MW
315136 1ROSEMG1 80/20 4.3 MW 4.3 MW
315137 1ROSEMS1 80/20 2.66 MW 2.66 MW
315138 1ROSEMG2 80/20 2.01 MW 2.01 MW
315139 1GASTONA 80/20 6.74 MW 6.74 MW
315158 1KERR 1 80/20 0.23 MW 0.23 MW
315159 1KERR 2 80/20 0.66 MW 0.66 MW
315160 1KERR 3 80/20 0.66 MW 0.66 MW
315161 1KERR 4 80/20 0.66 MW 0.66 MW
315162 1KERR 5 80/20 0.66 MW 0.66 MW
934521 AD1-076 C 80/20 10.34 MW 10.34 MW
943171 AE2-346 C 80/20 0.29 MW 0.29 MW
960081 AF2-299 C 80/20 4.55 MW 4.55 MW
315163 1KERR 6 80/20 0.66 MW 0.66 MW
315164 1KERR 7 80/20 0.66 MW 0.66 MW
315601 1CONETOE2SOL 80/20 1.43 MW 1.43 MW
315606 3AA2-053SOLA 80/20 2.46 MW 2.46 MW
316129 AC1-054 C 80/20 1.31 MW 1.31 MW
316131 AB2-060 C 80/20 0.65 MW 0.65 MW
316140 AB2-099 C 80/20 0.12 MW 0.12 MW
939181 AE1-148 C 80/20 4.96 MW 4.96 MW
940491 AE2-034 C 80/20 0.75 MW 0.75 MW
946281 AF1-292 C 80/20 3.77 MW 3.77 MW
957521 AF2-046 C 80/20 16.75 MW 16.75 MW
957861 AF2-080 C 80/20 8.57 MW 8.57 MW
938771 AE1-103 C 80/20 1.35 MW 1.35 MW
315115 1S HAMPT1 80/20 1.08 MW 1.08 MW
315141 1GASTONB 80/20 6.74 MW 6.74 MW
315292 1DOMTR78 80/20 1.22 MW 1.22 MW
315607 3AA1-063SOLA 80/20 2.03 MW 2.03 MW
315608 3AA2-088SOLA 80/20 1.08 MW 1.08 MW
315611 6Z1-036WIND 80/20 0.26 MW 0.26 MW
926071 AC1-086 C 80/20 46.37 MW 46.37 MW
927021 AC1-189 C 80/20 9.43 MW 9.43 MW
936261 AD2-033 C 80/20 4.71 MW 4.71 MW
933981 AD1-022 C 80/20 8.47 MW 8.47 MW
961681 AG1-008 C 80/20 16.75 MW 16.75 MW
962571 AG1-106 C 80/20 6.0 MW 6.0 MW
316005 AA1-067 C 80/20 0.3 MW 0.3 MW
316011 AB1-132 C OP 80/20 5.14 MW 5.14 MW
316023 AB2-100 C2 80/20 2.9 MW 2.9 MW
316049 AB1-081 C OP 80/20 1.67 MW 1.67 MW
316210 AC1-098 C 80/20 1.5 MW 1.5 MW
316212 AC1-099 C 80/20 0.5 MW 0.5 MW
316237 AB2-079 C O1 80/20 0.15 MW 0.15 MW
316238 AB2-078 C O1 80/20 0.15 MW 0.15 MW
316239 AB2-077 C O1 80/20 0.15 MW 0.15 MW
316263 AC1-034 C 80/20 7.8 MW 7.8 MW
316274 AC1-208 C 80/20 14.81 MW 14.81 MW
316317 KELFORD C 80/20 0.51 MW 0.51 MW
316318 V4-068 C 80/20 0.09 MW 0.09 MW
316319 Z2-044 C 80/20 0.35 MW 0.35 MW
316365 AB2-100 C1 80/20 2.9 MW 2.9 MW
315602 1HOLLOMANSOL 80/20 2.42 MW 2.42 MW
316327 AA2-057 C 80/20 2.17 MW 2.17 MW
315614 AA2-178 C 80/20 1.02 MW 1.02 MW
316181 AB2-040 GEN 80/20 2.66 MW 2.66 MW
313527 AB2-043 C 80/20 0.23 MW 0.23 MW
316359 AB2-059 C OP 80/20 1.97 MW 1.97 MW
316174 AB2-169_C 80/20 1.0 MW 1.0 MW
316087 AB2-174 C 80/20 2.59 MW 2.59 MW
962561 AG1-105 C 80/20 2.96 MW 2.96 MW
313764 3SOCKMAN 80/20 1.34 MW 1.34 MW
932631 AC2-084 C 80/20 1.59 MW 1.59 MW
934321 AD1-056 C 80/20 10.12 MW 10.12 MW
934331 AD1-057 C 80/20 5.64 MW 5.64 MW
934501 AD1-074 C 80/20 28.46 MW 28.46 MW
934511 AD1-075 C 80/20 7.12 MW 7.12 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.25 MW 11.25 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.8 MW 7.8 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 36.28 MW 36.28 MW
NY PJM->LTFIMP_NY CLTF 0.35 MW 0.35 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.43 MW 0.43 MW
WEC LTFEXP_WEC->PJM CLTF 0.23 MW 0.23 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.95 MW 4.95 MW
TVA LTFEXP_TVA->PJM CLTF 2.09 MW 2.09 MW
MEC LTFEXP_MEC->PJM CLTF 1.38 MW 1.38 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.68 MW 2.68 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.36 MW 2.36 MW

Details for 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 556_SRT-S-3


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 107.24 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 727.84 MVA
MW Contribution: 6.81 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
DVP_P1-2: LN 556_SRT-S-3
CONTINGENCY 'DVP_P1-2: LN 556_SRT-S-3'
 OPEN BRANCH FROM BUS 313995 TO BUS 314936 CKT 1                /*8FINNEYWOOD  500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET POSTCONTRATING 3811 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314902 TO BUS 314936 CKT 1 /*8CARSON      500.0 - 8RAWLINGS    500.0
 SET PRECONTRATING 3533 BRANCH FROM BUS 314935 TO BUS 314936 CKT 1 /*8HERITAGE    500.0 - 8RAWLINGS    500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 111.07 %
Rating: 678.68 MVA
Rating Type: B
MVA to Mitigate: 753.82 MVA
MW Contribution: 6.85 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.92 MW 0.92 MW
961791 AG1-021 C 80/20 0.91 MW 0.91 MW
961941 AG1-037 C 80/20 0.48 MW 0.48 MW
962331 AG1-082 C 80/20 1.93 MW 1.93 MW
963171 AG1-166 C 80/20 0.51 MW 0.51 MW
963181 AG1-167 C 80/20 0.38 MW 0.38 MW
963191 AG1-168 C 80/20 0.38 MW 0.38 MW
964791 AG1-342 C 80/20 2.04 MW 2.04 MW
966801 AG1-551 C 80/20 1.62 MW 1.62 MW
966811 AG1-552 C 80/20 3.22 MW 3.22 MW
965291 AG1-394 C 80/20 0.8 MW 0.8 MW
966621 AG1-532 C 80/20 3.32 MW 3.32 MW
313506 AB1-173 C OP 80/20 2.26 MW 2.26 MW
313853 3PONTONDP 80/20 0.34 MW 0.34 MW
314429 3JTRSVLE 80/20 0.21 MW 0.21 MW
314704 3LAWRENC 80/20 0.58 MW 0.58 MW
315126 1ROARAP2 80/20 2.17 MW 2.17 MW
315128 1ROARAP4 80/20 2.06 MW 2.06 MW
315131 1EDGECMA 80/20 16.08 MW 16.08 MW
315136 1ROSEMG1 80/20 3.94 MW 3.94 MW
315137 1ROSEMS1 80/20 2.44 MW 2.44 MW
315138 1ROSEMG2 80/20 1.85 MW 1.85 MW
315139 1GASTONA 80/20 6.2 MW 6.2 MW
315153 1CLOVER1 80/20 5.84 MW 5.84 MW
315158 1KERR 1 80/20 0.31 MW 0.31 MW
315159 1KERR 2 80/20 0.87 MW 0.87 MW
315160 1KERR 3 80/20 0.87 MW 0.87 MW
315161 1KERR 4 80/20 0.87 MW 0.87 MW
315162 1KERR 5 80/20 0.87 MW 0.87 MW
934521 AD1-076 C 80/20 7.17 MW 7.17 MW
943171 AE2-346 C 80/20 0.21 MW 0.21 MW
959311 AF2-222 C 80/20 8.69 MW 8.69 MW
960081 AF2-299 C 80/20 4.42 MW 4.42 MW
315163 1KERR 6 80/20 0.87 MW 0.87 MW
315164 1KERR 7 80/20 0.87 MW 0.87 MW
315266 1PLYWOOD A 80/20 0.64 MW 0.64 MW
315601 1CONETOE2SOL 80/20 1.16 MW 1.16 MW
315606 3AA2-053SOLA 80/20 2.2 MW 2.2 MW
316118 AC1-105 C 80/20 0.49 MW 0.49 MW
316129 AC1-054 C 80/20 1.36 MW 1.36 MW
316131 AB2-060 C 80/20 1.04 MW 1.04 MW
316140 AB2-099 C 80/20 0.09 MW 0.09 MW
939181 AE1-148 C 80/20 6.76 MW 6.76 MW
946281 AF1-292 C 80/20 3.66 MW 3.66 MW
946301 AF1-294 C 80/20 1.88 MW 1.88 MW
957481 AF2-042 C 80/20 24.41 MW 24.41 MW
957521 AF2-046 C 80/20 13.45 MW 13.45 MW
957861 AF2-080 C 80/20 6.81 MW 6.81 MW
958211 AF2-115 C 80/20 1.14 MW 1.14 MW
315115 1S HAMPT1 80/20 0.98 MW 0.98 MW
315141 1GASTONB 80/20 6.2 MW 6.2 MW
315292 1DOMTR78 80/20 0.87 MW 0.87 MW
315607 3AA1-063SOLA 80/20 1.85 MW 1.85 MW
315608 3AA2-088SOLA 80/20 0.95 MW 0.95 MW
926071 AC1-086 C 80/20 42.65 MW 42.65 MW
927021 AC1-189 C 80/20 7.49 MW 7.49 MW
936261 AD2-033 C 80/20 8.08 MW 8.08 MW
934621 AD1-088 C 80/20 5.85 MW 5.85 MW
933981 AD1-022 C 80/20 5.8 MW 5.8 MW
961681 AG1-008 C 80/20 13.45 MW 13.45 MW
962571 AG1-106 C 80/20 5.52 MW 5.52 MW
316005 AA1-067 C 80/20 0.22 MW 0.22 MW
316011 AB1-132 C OP 80/20 4.73 MW 4.73 MW
316023 AB2-100 C2 80/20 2.78 MW 2.78 MW
316034 AC1-036 C 80/20 0.12 MW 0.12 MW
316049 AB1-081 C OP 80/20 1.41 MW 1.41 MW
316210 AC1-098 C 80/20 1.26 MW 1.26 MW
316212 AC1-099 C 80/20 0.42 MW 0.42 MW
316237 AB2-079 C O1 80/20 0.23 MW 0.23 MW
316238 AB2-078 C O1 80/20 0.23 MW 0.23 MW
316239 AB2-077 C O1 80/20 0.23 MW 0.23 MW
316263 AC1-034 C 80/20 6.66 MW 6.66 MW
316274 AC1-208 C 80/20 12.92 MW 12.92 MW
316317 KELFORD C 80/20 0.39 MW 0.39 MW
316318 V4-068 C 80/20 0.08 MW 0.08 MW
316319 Z2-044 C 80/20 0.31 MW 0.31 MW
316365 AB2-100 C1 80/20 2.78 MW 2.78 MW
315602 1HOLLOMANSOL 80/20 1.62 MW 1.62 MW
316327 AA2-057 C 80/20 1.88 MW 1.88 MW
316181 AB2-040 GEN 80/20 2.54 MW 2.54 MW
313527 AB2-043 C 80/20 0.36 MW 0.36 MW
316359 AB2-059 C OP 80/20 1.69 MW 1.69 MW
316174 AB2-169_C 80/20 0.72 MW 0.72 MW
316087 AB2-174 C 80/20 2.49 MW 2.49 MW
962561 AG1-105 C 80/20 5.31 MW 5.31 MW
964241 AG1-285 C 80/20 7.27 MW 7.27 MW
313764 3SOCKMAN 80/20 1.26 MW 1.26 MW
932631 AC2-084 C 80/20 1.34 MW 1.34 MW
934321 AD1-056 C 80/20 9.11 MW 9.11 MW
934331 AD1-057 C 80/20 5.08 MW 5.08 MW
934501 AD1-074 C 80/20 19.74 MW 19.74 MW
934511 AD1-075 C 80/20 4.93 MW 4.93 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 10.72 MW 10.72 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.28 MW 7.28 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 33.02 MW 33.02 MW
NY PJM->LTFIMP_NY CLTF 0.36 MW 0.36 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.41 MW 0.41 MW
WEC LTFEXP_WEC->PJM CLTF 0.22 MW 0.22 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.45 MW 4.45 MW
TVA LTFEXP_TVA->PJM CLTF 1.94 MW 1.94 MW
MEC LTFEXP_MEC->PJM CLTF 1.31 MW 1.31 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.48 MW 2.48 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.08 MW 0.08 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.12 MW 2.12 MW

Details for 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer l/o DVP_P1-2: LN 576_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
Contingency Name:
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 105.13 %
Rating: 1058.16 MVA
Rating Type: B
MVA to Mitigate: 1112.41 MVA
MW Contribution: 3.33 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
Contingency Name:
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 104.72 %
Rating: 1058.16 MVA
Rating Type: B
MVA to Mitigate: 1108.12 MVA
MW Contribution: 3.22 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.41 MW 0.35 MW
961941 AG1-037 C 80/20 0.21 MW 0.21 MW
962331 AG1-082 C 80/20 0.85 MW 0.85 MW
963041 AG1-153 C 80/20 3.75 MW 3.75 MW
964791 AG1-342 C 80/20 1.53 MW 1.53 MW
966801 AG1-551 C Adder 0.91 MW 0.77 MW
966811 AG1-552 C 80/20 0.89 MW 0.89 MW
965291 AG1-394 C Adder 0.35 MW 0.3 MW
966621 AG1-532 C 80/20 0.6 MW 0.6 MW
313506 AB1-173 C OP 80/20 0.49 MW 0.49 MW
314704 3LAWRENC 80/20 0.13 MW 0.13 MW
315126 1ROARAP2 80/20 0.6 MW 0.6 MW
315128 1ROARAP4 80/20 0.56 MW 0.56 MW
315131 1EDGECMA Adder 6.83 MW 5.81 MW
315136 1ROSEMG1 80/20 0.88 MW 0.88 MW
315137 1ROSEMS1 80/20 0.54 MW 0.54 MW
315138 1ROSEMG2 80/20 0.41 MW 0.41 MW
315139 1GASTONA 80/20 1.31 MW 1.31 MW
315153 1CLOVER1 80/20 6.55 MW 6.55 MW
315154 1CLOVER2 80/20 6.49 MW 6.49 MW
315158 1KERR 1 80/20 0.18 MW 0.18 MW
315159 1KERR 2 80/20 0.51 MW 0.51 MW
315160 1KERR 3 80/20 0.51 MW 0.51 MW
315161 1KERR 4 80/20 0.51 MW 0.51 MW
315162 1KERR 5 80/20 0.51 MW 0.51 MW
934521 AD1-076 C 80/20 5.13 MW 5.13 MW
943171 AE2-346 C 80/20 0.1 MW 0.1 MW
944011 AF1-069 C 80/20 8.9 MW 8.9 MW
959311 AF2-222 C Adder 5.8 MW 4.93 MW
960061 AF2-297 C 80/20 3.42 MW 3.42 MW
960081 AF2-299 C 80/20 0.8 MW 0.8 MW
315163 1KERR 6 80/20 0.51 MW 0.51 MW
315164 1KERR 7 80/20 0.51 MW 0.51 MW
315266 1PLYWOOD A 80/20 0.53 MW 0.53 MW
315606 3AA2-053SOLA 80/20 0.65 MW 0.65 MW
316118 AC1-105 C 80/20 0.4 MW 0.4 MW
316129 AC1-054 C 80/20 0.53 MW 0.53 MW
316140 AB2-099 C 80/20 0.04 MW 0.04 MW
939181 AE1-148 C 80/20 3.96 MW 3.96 MW
940491 AE2-034 C 80/20 0.48 MW 0.48 MW
941011 AE2-092 C Adder -4.44 MW -3.77 MW
941031 AE2-094 C 80/20 27.23 MW 27.23 MW
946281 AF1-292 C 80/20 0.67 MW 0.67 MW
957481 AF2-042 C 80/20 29.33 MW 29.33 MW
957521 AF2-046 C 80/20 5.93 MW 5.93 MW
957861 AF2-080 C Adder 3.33 MW 2.83 MW
938771 AE1-103 C Adder 1.16 MW 0.99 MW
313526 AB2-022 C 80/20 0.15 MW 0.15 MW
314507 3THOMPSN Adder 0.8 MW 0.68 MW
942341 AE2-247 C Adder 0.49 MW 0.42 MW
943461 AF1-017 C Adder 0.45 MW 0.38 MW
315102 1BRUNSWICKG1 80/20 5.53 MW 5.53 MW
315103 1BRUNSWICKG2 80/20 5.53 MW 5.53 MW
315104 1BRUNSWICKG3 80/20 5.53 MW 5.53 MW
315105 1BRUNSWICKS1 80/20 11.49 MW 11.49 MW
315108 1ELIZAR1 80/20 1.27 MW 1.27 MW
315109 1ELIZAR2 80/20 1.25 MW 1.25 MW
315110 1ELIZAR3 80/20 1.29 MW 1.29 MW
315141 1GASTONB 80/20 1.31 MW 1.31 MW
315241 1Z1-086 GT1 80/20 7.11 MW 7.11 MW
315242 1Z1-086 GT2 80/20 7.1 MW 7.1 MW
315243 1Z1-086 GT3 80/20 7.1 MW 7.1 MW
315244 1Z1-086 ST 80/20 12.37 MW 12.37 MW
315260 1GOSPORTA Adder 0.84 MW 0.71 MW
315261 1GOSPORTB Adder 1.08 MW 0.91 MW
315262 1GOSPORTC Adder 0.91 MW 0.78 MW
315605 6W1-029WIND 80/20 0.32 MW 0.32 MW
315607 3AA1-063SOLA 80/20 0.6 MW 0.6 MW
315611 6Z1-036WIND 80/20 0.27 MW 0.27 MW
957871 AF2-081 C 80/20 4.13 MW 4.13 MW
958161 AF2-110 C Adder 0.52 MW 0.44 MW
926071 AC1-086 C 80/20 9.03 MW 9.03 MW
927021 AC1-189 C Adder 3.67 MW 3.12 MW
936261 AD2-033 C Adder 4.4 MW 3.74 MW
933291 AC2-141 C 80/20 13.23 MW 13.23 MW
934621 AD1-088 C 80/20 5.98 MW 5.98 MW
939411 AE1-173 C 80/20 54.42 MW 54.42 MW
916191 Z1-068 C 80/20 0.02 MW 0.02 MW
933981 AD1-022 C 80/20 3.68 MW 3.68 MW
961681 AG1-008 C 80/20 5.93 MW 5.93 MW
962571 AG1-106 C 80/20 1.17 MW 1.17 MW
316011 AB1-132 C OP 80/20 1.0 MW 1.0 MW
316023 AB2-100 C2 80/20 0.41 MW 0.41 MW
316185 AD1-033 C 80/20 0.51 MW 0.51 MW
316210 AC1-098 C 80/20 0.42 MW 0.42 MW
316212 AC1-099 C 80/20 0.14 MW 0.14 MW
316222 AC1-221 C 80/20 0.65 MW 0.65 MW
316246 AF1-032 C 80/20 0.11 MW 0.11 MW
316248 AF1-058 C 80/20 0.14 MW 0.14 MW
316263 AC1-034 C Adder 2.92 MW 2.48 MW
316274 AC1-208 C 80/20 4.0 MW 4.0 MW
316294 AC1-161 C 80/20 2.16 MW 2.16 MW
316305 AF2-043 C 80/20 0.14 MW 0.14 MW
316315 AB2-025 C 80/20 0.18 MW 0.18 MW
316316 AC1-027 C 80/20 0.13 MW 0.13 MW
316317 KELFORD C 80/20 0.15 MW 0.15 MW
316318 V4-068 C 80/20 0.03 MW 0.03 MW
316319 Z2-044 C 80/20 0.1 MW 0.1 MW
316320 Y1-086 C 80/20 0.09 MW 0.09 MW
316321 Z2-027 C 80/20 0.15 MW 0.15 MW
316336 AC2-165 C Adder -10.77 MW -9.16 MW
316365 AB2-100 C1 80/20 0.41 MW 0.41 MW
315602 1HOLLOMANSOL 80/20 0.78 MW 0.78 MW
316017 AA1-139 ULT1 80/20 0.45 MW 0.45 MW
316018 AA1-139 ULT2 80/20 0.45 MW 0.45 MW
316327 AA2-057 C 80/20 0.59 MW 0.59 MW
315614 AA2-178 C 80/20 0.65 MW 0.65 MW
316181 AB2-040 GEN 80/20 0.55 MW 0.55 MW
316087 AB2-174 C 80/20 0.51 MW 0.51 MW
316311 AC2-079 C Adder 1.94 MW 1.65 MW
316349 AD2-085 C Adder 1.14 MW 0.97 MW
316388 AE2-253 GEN 80/20 0.81 MW 0.81 MW
941591 AE2-156 C 80/20 7.09 MW 7.09 MW
944581 AF1-123 C 80/20 18.83 MW 18.83 MW
944591 AF1-124 C 80/20 18.89 MW 18.89 MW
944601 AF1-125 C 80/20 18.54 MW 18.54 MW
962491 AG1-098 C 80/20 5.22 MW 5.22 MW
962561 AG1-105 C 80/20 3.83 MW 3.83 MW
964241 AG1-285 C 80/20 5.55 MW 5.55 MW
313764 3SOCKMAN 80/20 0.31 MW 0.31 MW
932631 AC2-084 C 80/20 0.44 MW 0.44 MW
934321 AD1-056 C Adder 2.73 MW 2.32 MW
934331 AD1-057 C Adder 1.52 MW 1.29 MW
934501 AD1-074 C 80/20 14.13 MW 14.13 MW
934511 AD1-075 C 80/20 3.53 MW 3.53 MW
934611 AD1-087 C 80/20 0.65 MW 0.65 MW
935171 AD1-152 C 80/20 0.66 MW 0.66 MW
936161 AD2-022 C Adder 3.15 MW 2.67 MW
936171 AD2-023 C Adder 1.84 MW 1.56 MW
937481 AD2-202 C 80/20 0.19 MW 0.19 MW
938531 AE1-072 C 80/20 7.26 MW 7.26 MW
938821 AE1-108 C Adder -4.69 MW -3.99 MW
940481 AE2-033 C 80/20 6.99 MW 6.99 MW
940541 AE2-040 C 80/20 1.24 MW 1.24 MW
940641 AE2-051 C 80/20 11.4 MW 11.4 MW
941101 AE2-104 C Adder 1.28 MW 1.09 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.81 MW 11.81 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 9.22 MW 9.22 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 44.44 MW 44.44 MW
NY PJM->LTFIMP_NY CLTF 0.52 MW 0.52 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.46 MW 0.46 MW
WEC LTFEXP_WEC->PJM CLTF 0.24 MW 0.24 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.48 MW 5.48 MW
TVA LTFEXP_TVA->PJM CLTF 2.54 MW 2.54 MW
MEC LTFEXP_MEC->PJM CLTF 1.55 MW 1.55 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.27 MW 3.27 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.61 MW 2.61 MW

Details for 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 574_SRT-S_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
Contingency Name:
DVP_P1-2: LN 574_SRT-S_SENS
CONTINGENCY 'DVP_P1-2: LN 574_SRT-S_SENS'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2598 BRANCH FROM BUS 314908 TO BUS 314903 CKT 1 /*8ELMONT      500.0 - 8CHCKAHM     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314918 TO BUS 314911 CKT 1 /*8NO ANNA     500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2598 BRANCH FROM BUS 314908 TO BUS 314903 CKT 1 /*8ELMONT      500.0 - 8CHCKAHM     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314918 TO BUS 314911 CKT 1 /*8NO ANNA     500.0 - 8LADYSMITH   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 104.61 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3368.83 MVA
MW Contribution: 10.33 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.25 MW 1.06 MW
961791 AG1-021 C Adder 2.39 MW 2.03 MW
961941 AG1-037 C Adder 0.72 MW 0.61 MW
962331 AG1-082 C Adder 2.86 MW 2.44 MW
963041 AG1-153 C 80/20 8.7 MW 8.7 MW
963171 AG1-166 C Adder 1.33 MW 1.13 MW
963181 AG1-167 C Adder 1.0 MW 0.85 MW
963191 AG1-168 C Adder 1.0 MW 0.85 MW
964791 AG1-342 C Adder 4.75 MW 4.04 MW
966801 AG1-551 C Adder 2.89 MW 2.46 MW
966811 AG1-552 C Adder 2.92 MW 2.48 MW
965291 AG1-394 C Adder 1.22 MW 1.04 MW
966621 AG1-532 C Adder 2.0 MW 1.7 MW
313853 3PONTONDP Adder 0.89 MW 0.75 MW
315131 1EDGECMA Adder 20.63 MW 17.54 MW
315153 1CLOVER1 80/20 18.21 MW 18.21 MW
315154 1CLOVER2 80/20 18.04 MW 18.04 MW
934521 AD1-076 C Adder 17.34 MW 14.74 MW
944011 AF1-069 C 80/20 20.35 MW 20.35 MW
959311 AF2-222 C Adder 23.44 MW 19.92 MW
960061 AF2-297 C Adder 10.08 MW 8.56 MW
960081 AF2-299 C Adder 2.66 MW 2.27 MW
938371 AE1-056 C Adder 8.67 MW 7.37 MW
939181 AE1-148 C Adder 12.46 MW 10.59 MW
941031 AE2-094 C 80/20 62.29 MW 62.29 MW
946281 AF1-292 C Adder 2.21 MW 1.88 MW
946301 AF1-294 C Adder 4.92 MW 4.18 MW
957481 AF2-042 C 80/20 78.99 MW 78.99 MW
957521 AF2-046 C Adder 20.2 MW 17.17 MW
957861 AF2-080 C Adder 10.33 MW 8.78 MW
958211 AF2-115 C Adder 2.99 MW 2.54 MW
938771 AE1-103 C 80/20 4.21 MW 4.21 MW
313526 AB2-022 C 80/20 0.54 MW 0.54 MW
314507 3THOMPSN 80/20 2.92 MW 2.92 MW
315060 1CHESTF5 Adder 76.37 MW 64.91 MW
315065 1CHESTF6 Adder 25.69 MW 21.84 MW
315073 1STONECA Adder 8.91 MW 7.57 MW
315083 1SPRUNCA Adder 12.3 MW 10.46 MW
315084 1SPRUNCB Adder 12.3 MW 10.46 MW
315092 1YORKTN3 Adder 173.21 MW 147.23 MW
942341 AE2-247 C 80/20 2.14 MW 2.14 MW
943461 AF1-017 C 80/20 1.93 MW 1.93 MW
315098 1CHESPKA 80/20 0.63 MW 0.63 MW
315099 1CHESPKB 80/20 1.04 MW 1.04 MW
315102 1BRUNSWICKG1 80/20 12.84 MW 12.84 MW
315103 1BRUNSWICKG2 80/20 12.84 MW 12.84 MW
315104 1BRUNSWICKG3 80/20 12.84 MW 12.84 MW
315105 1BRUNSWICKS1 80/20 26.68 MW 26.68 MW
315108 1ELIZAR1 80/20 4.63 MW 4.63 MW
315109 1ELIZAR2 80/20 4.55 MW 4.55 MW
315110 1ELIZAR3 80/20 4.69 MW 4.69 MW
315233 1SURRY 2 80/20 34.31 MW 34.31 MW
315241 1Z1-086 GT1 80/20 16.43 MW 16.43 MW
315242 1Z1-086 GT2 80/20 16.42 MW 16.42 MW
315243 1Z1-086 GT3 80/20 16.42 MW 16.42 MW
315244 1Z1-086 ST 80/20 28.59 MW 28.59 MW
315260 1GOSPORTA 80/20 3.08 MW 3.08 MW
315261 1GOSPORTB 80/20 3.94 MW 3.94 MW
315262 1GOSPORTC 80/20 3.34 MW 3.34 MW
315605 6W1-029WIND 80/20 1.12 MW 1.12 MW
315611 6Z1-036WIND 80/20 0.94 MW 0.94 MW
957601 AF2-054 C Adder 2.36 MW 2.01 MW
962971 AG1-146 C Adder 3.22 MW 2.73 MW
962981 AG1-147 C Adder 7.5 MW 6.38 MW
942001 AE2-212 C Adder 2.96 MW 2.52 MW
957871 AF2-081 C 80/20 14.49 MW 14.49 MW
958161 AF2-110 C 80/20 1.97 MW 1.97 MW
926071 AC1-086 C Adder 29.52 MW 25.09 MW
927021 AC1-189 C Adder 11.38 MW 9.67 MW
936261 AD2-033 C Adder 17.84 MW 15.16 MW
933291 AC2-141 C 80/20 44.2 MW 44.2 MW
934621 AD1-088 C 80/20 18.07 MW 18.07 MW
939411 AE1-173 C 80/20 139.74 MW 139.74 MW
916191 Z1-068 C 80/20 0.06 MW 0.06 MW
933981 AD1-022 C Adder 12.4 MW 10.54 MW
961681 AG1-008 C Adder 20.2 MW 17.17 MW
962571 AG1-106 C Adder 3.82 MW 3.25 MW
316023 AB2-100 C2 80/20 1.37 MW 1.37 MW
316036 AC1-147 C 80/20 0.53 MW 0.53 MW
316072 AD1-144 C 80/20 0.4 MW 0.4 MW
316169 AC1-164 GEN Adder 44.74 MW 38.03 MW
316185 AD1-033 C 80/20 1.79 MW 1.79 MW
316233 AE1-074 C 80/20 3.77 MW 3.77 MW
316236 AE1-162 C 80/20 0.49 MW 0.49 MW
316240 AF1-291 C Adder 2.86 MW 2.43 MW
316246 AF1-032 C 80/20 0.41 MW 0.41 MW
316258 AE1-075 C 80/20 0.5 MW 0.5 MW
316263 AC1-034 C Adder 8.89 MW 7.56 MW
316274 AC1-208 C Adder 13.23 MW 11.24 MW
316294 AC1-161 C 80/20 7.22 MW 7.22 MW
316305 AF2-043 C 80/20 0.5 MW 0.5 MW
316313 AB2-026 C 80/20 0.55 MW 0.55 MW
316315 AB2-025 C 80/20 0.6 MW 0.6 MW
316316 AC1-027 C 80/20 0.46 MW 0.46 MW
316320 Y1-086 C 80/20 0.32 MW 0.32 MW
316321 Z2-027 C 80/20 0.53 MW 0.53 MW
316336 AC2-165 C Adder 13.69 MW 11.64 MW
316365 AB2-100 C1 80/20 1.37 MW 1.37 MW
316405 AF2-144 C 80/20 0.43 MW 0.43 MW
316017 AA1-139 ULT1 80/20 1.57 MW 1.57 MW
316018 AA1-139 ULT2 80/20 1.57 MW 1.57 MW
316083 AB2-161 C 80/20 0.78 MW 0.78 MW
316375 AC2-012 C 80/20 1.95 MW 1.95 MW
316311 AC2-079 C 80/20 8.22 MW 8.22 MW
316381 AD1-082 C 80/20 1.79 MW 1.79 MW
316349 AD2-085 C 80/20 4.93 MW 4.93 MW
316388 AE2-253 GEN 80/20 2.85 MW 2.85 MW
961611 AG1-000B C Adder 21.63 MW 18.38 MW
941591 AE2-156 C 80/20 25.9 MW 25.9 MW
944581 AF1-123 C 80/20 65.92 MW 65.92 MW
944591 AF1-124 C 80/20 66.16 MW 66.16 MW
944601 AF1-125 C 80/20 64.91 MW 64.91 MW
944631 AF1-128 C Adder 47.78 MW 40.62 MW
962491 AG1-098 C 80/20 16.16 MW 16.16 MW
962561 AG1-105 C Adder 12.0 MW 10.2 MW
964241 AG1-285 C Adder 18.19 MW 15.46 MW
965281 AG1-393 C Adder 2.89 MW 2.46 MW
313764 3SOCKMAN Adder 1.01 MW 0.86 MW
934321 AD1-056 C Adder 8.52 MW 7.24 MW
934331 AD1-057 C Adder 4.75 MW 4.04 MW
934501 AD1-074 C Adder 47.76 MW 40.59 MW
934511 AD1-075 C Adder 11.94 MW 10.15 MW
934611 AD1-087 C 80/20 1.79 MW 1.79 MW
935161 AD1-151 C Adder 21.37 MW 18.16 MW
937481 AD2-202 C 80/20 0.52 MW 0.52 MW
938531 AE1-072 C 80/20 25.46 MW 25.46 MW
939191 AE1-149 C 80/20 15.1 MW 15.1 MW
940431 AE2-027 C Adder 17.19 MW 14.61 MW
940481 AE2-033 C 80/20 23.6 MW 23.6 MW
940541 AE2-040 C 80/20 4.2 MW 4.2 MW
940551 AE2-041 C Adder 7.91 MW 6.73 MW
940641 AE2-051 C 80/20 27.15 MW 27.15 MW
941101 AE2-104 C 80/20 4.83 MW 4.83 MW
942461 AE2-259 C Adder 12.88 MW 10.95 MW
943471 AF1-018 C Adder 7.91 MW 6.73 MW
944641 AF1-129 C Adder 133.99 MW 113.89 MW
316303 AF2-085 80/20 6.37 MW 6.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 37.93 MW 37.93 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 27.88 MW 27.88 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 123.76 MW 123.76 MW
NY PJM->LTFIMP_NY CLTF 2.48 MW 2.48 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.51 MW 1.51 MW
WEC LTFEXP_WEC->PJM CLTF 0.79 MW 0.79 MW
CPLE LTFEXP_CPLE->PJM CLTF 15.06 MW 15.06 MW
TVA LTFEXP_TVA->PJM CLTF 7.58 MW 7.58 MW
MEC LTFEXP_MEC->PJM CLTF 4.84 MW 4.84 MW
LAGN LTFEXP_LAGN->PJM CLTF 9.66 MW 9.66 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.3 MW 0.3 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.18 MW 7.18 MW

Details for 6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line l/o DVP_P7-1: LN 2058-2181_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CPLE/DVP
Facility Description:
6EVERETS-6GREENVILE T 230.0 kV Ckt 1 line
314574 to 304451 ckt 1
Contingency Name:
DVP_P7-1: LN 2058-2181_SRT-A
CONTINGENCY 'DVP_P7-1: LN 2058-2181_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 119.28 %
Rating: 478.0 MVA
Rating Type: B
MVA to Mitigate: 570.16 MVA
MW Contribution: 19.85 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.36 MW 1.36 MW
961672 AG1-007 E 50/50 0.77 MW 0.77 MW
961941 AG1-037 C 50/50 0.46 MW 0.46 MW
961942 AG1-037 E 50/50 0.31 MW 0.31 MW
962331 AG1-082 C 50/50 1.85 MW 1.85 MW
962332 AG1-082 E 50/50 1.23 MW 1.23 MW
966801 AG1-551 C 50/50 4.16 MW 4.16 MW
966802 AG1-551 E 50/50 2.19 MW 2.19 MW
966811 AG1-552 C Adder 1.22 MW 1.03 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C 50/50 0.51 MW 0.51 MW
965292 AG1-394 E 50/50 0.94 MW 0.94 MW
966621 AG1-532 C Adder 0.63 MW 0.54 MW
966622 AG1-532 E Adder 0.42 MW 0.36 MW
314541 3WATKINS Adder 0.35 MW 0.3 MW
314572 3EMPORIA Adder 0.2 MW 0.17 MW
315131 1EDGECMA 50/50 15.48 MW 15.48 MW
315136 1ROSEMG1 50/50 1.44 MW 1.44 MW
315137 1ROSEMS1 50/50 0.89 MW 0.89 MW
315138 1ROSEMG2 50/50 0.68 MW 0.68 MW
315139 1GASTONA 50/50 2.07 MW 2.07 MW
918492 AA1-063AE OP 50/50 2.42 MW 2.42 MW
918532 AA1-067 E 50/50 1.57 MW 1.57 MW
919692 AA2-053 E OP 50/50 2.79 MW 2.79 MW
920042 AA2-088 E OP Adder 6.18 MW 5.25 MW
927146 AC1-208 E 50/50 2.93 MW 2.93 MW
934521 AD1-076 C 50/50 12.07 MW 12.07 MW
934522 AD1-076 E 50/50 6.15 MW 6.15 MW
943171 AE2-346 C 50/50 0.21 MW 0.21 MW
943172 AE2-346 E 50/50 0.56 MW 0.56 MW
960081 AF2-299 C Adder 0.85 MW 0.72 MW
960082 AF2-299 E Adder 0.56 MW 0.48 MW
315601 1CONETOE2SOL 50/50 2.01 MW 2.01 MW
315606 3AA2-053SOLA 50/50 1.0 MW 1.0 MW
316140 AB2-099 C 50/50 0.09 MW 0.09 MW
316141 AB2-099 E 50/50 0.23 MW 0.23 MW
900672 V4-068 E 50/50 0.26 MW 0.26 MW
917342 Z2-044 E 50/50 0.46 MW 0.46 MW
922923 AB1-081 E OP 50/50 5.44 MW 5.44 MW
923263 AB1-132 E OP 50/50 4.15 MW 4.15 MW
923573 AB1-173 E OP Adder 1.7 MW 1.44 MW
940491 AE2-034 C 50/50 0.97 MW 0.97 MW
940492 AE2-034 E 50/50 2.58 MW 2.58 MW
946281 AF1-292 C Adder 0.7 MW 0.59 MW
946282 AF1-292 E Adder 0.47 MW 0.4 MW
957521 AF2-046 C 50/50 10.71 MW 10.71 MW
957522 AF2-046 E 50/50 5.41 MW 5.41 MW
957861 AF2-080 C 50/50 13.75 MW 13.75 MW
957862 AF2-080 E 50/50 6.1 MW 6.1 MW
314539 3UNCAMP Adder 2.85 MW 2.42 MW
916042 Z1-036 E 50/50 18.36 MW 18.36 MW
938771 AE1-103 C Adder 1.3 MW 1.11 MW
938772 AE1-103 E Adder 1.8 MW 1.53 MW
315141 1GASTONB 50/50 2.07 MW 2.07 MW
315292 1DOMTR78 50/50 1.7 MW 1.7 MW
315607 3AA1-063SOLA 50/50 0.83 MW 0.83 MW
315611 6Z1-036WIND 50/50 0.42 MW 0.42 MW
913392 Y1-086 E Adder 0.86 MW 0.73 MW
923832 AB2-022 E Adder 0.48 MW 0.41 MW
901082 W1-029 E Adder 14.74 MW 12.53 MW
917122 Z2-027 E Adder 0.57 MW 0.48 MW
958161 AF2-110 C Adder 0.46 MW 0.39 MW
958162 AF2-110 E Adder 0.73 MW 0.62 MW
917512 Z2-088 E OP1 50/50 7.85 MW 7.85 MW
926071 AC1-086 C 50/50 14.25 MW 14.25 MW
926072 AC1-086 E 50/50 6.49 MW 6.49 MW
927021 AC1-189 C 50/50 15.14 MW 15.14 MW
927022 AC1-189 E 50/50 7.54 MW 7.54 MW
933981 AD1-022 C 50/50 8.8 MW 8.8 MW
933982 AD1-022 E 50/50 4.79 MW 4.79 MW
962572 AG1-106 E 50/50 0.81 MW 0.81 MW
961681 AG1-008 C 50/50 10.71 MW 10.71 MW
961682 AG1-008 E 50/50 5.41 MW 5.41 MW
962571 AG1-106 C 50/50 1.84 MW 1.84 MW
314594 6PLYMOUTH TP 50/50 0.31 MW 0.31 MW
314632 6AYDLETT TAP Adder 0.44 MW 0.38 MW
316005 AA1-067 C 50/50 0.6 MW 0.6 MW
316011 AB1-132 C OP 50/50 1.58 MW 1.58 MW
316049 AB1-081 C OP 50/50 2.07 MW 2.07 MW
316210 AC1-098 C 50/50 0.74 MW 0.74 MW
316212 AC1-099 C 50/50 0.25 MW 0.25 MW
316263 AC1-034 C 50/50 9.69 MW 9.69 MW
316274 AC1-208 C 50/50 6.6 MW 6.6 MW
316317 KELFORD C 50/50 0.33 MW 0.33 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.16 MW 0.16 MW
917332 KELFORD E 50/50 1.5 MW 1.5 MW
924516 AB2-100 E1 Adder 1.42 MW 1.21 MW
924517 AB2-100 E2 Adder 1.42 MW 1.21 MW
925595 AC1-034 E 50/50 7.31 MW 7.31 MW
926206 AC1-098 E 50/50 2.88 MW 2.88 MW
926214 AC1-099 E 50/50 0.95 MW 0.95 MW
315602 1HOLLOMANSOL 50/50 1.94 MW 1.94 MW
918512 AA1-065 E OP 50/50 5.84 MW 5.84 MW
316327 AA2-057 C 50/50 0.99 MW 0.99 MW
919710 AA2-057 E 50/50 3.03 MW 3.03 MW
315614 AA2-178 C 50/50 1.31 MW 1.31 MW
920692 AA2-178 E 50/50 3.44 MW 3.44 MW
923994 AB2-040_E Adder 3.18 MW 2.7 MW
316359 AB2-059 C OP 50/50 2.44 MW 2.44 MW
924152 AB2-059 E OP 50/50 7.71 MW 7.71 MW
316174 AB2-169_C 50/50 1.64 MW 1.64 MW
925122 AB2-169 E 50/50 8.98 MW 8.98 MW
316088 AB2-174 E Adder 3.24 MW 2.75 MW
313764 3SOCKMAN Adder 0.4 MW 0.34 MW
932631 AC2-084 C 50/50 0.79 MW 0.79 MW
932632 AC2-084 E 50/50 2.55 MW 2.55 MW
934321 AD1-056 C 50/50 5.34 MW 5.34 MW
934322 AD1-056 E 50/50 2.9 MW 2.9 MW
934331 AD1-057 C 50/50 2.98 MW 2.98 MW
934332 AD1-057 E 50/50 1.55 MW 1.55 MW
934501 AD1-074 C 50/50 33.25 MW 33.25 MW
934502 AD1-074 E 50/50 16.93 MW 16.93 MW
934511 AD1-075 C 50/50 8.31 MW 8.31 MW
934512 AD1-075 E 50/50 4.23 MW 4.23 MW
941101 AE2-104 C Adder 1.12 MW 0.95 MW
941102 AE2-104 E Adder 1.78 MW 1.52 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.33 MW 0.33 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.86 MW 0.86 MW
VTF LTFEXP_VFT->PJM CMTX 2.29 MW 2.29 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 4.76 MW 4.76 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 3.15 MW 3.15 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 1.43 MW 1.43 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 4.11 MW 4.11 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.69 MW 0.69 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 2.17 MW 2.17 MW
MDU PJM->LTFIMP_MDU CLTF 0.15 MW 0.15 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 1.44 MW 1.44 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 5.75 MW 5.75 MW

Details for 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line l/o DVP_P7-1: ELMONT-LADYSMITH_500_230_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
DVP_P7-1: ELMONT-LADYSMITH_500_230_SRT-A
CONTINGENCY 'DVP_P7-1: ELMONT-LADYSMITH_500_230_SRT-A'
 OPEN BRANCH FROM BUS 314218 TO BUS 314196 CKT 1   /*6ELMONT      230.0 - 6LADYSMITH   230.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1   /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 105.56 %
Rating: 3940.0 MVA
Rating Type: C
MVA to Mitigate: 4158.88 MVA
MW Contribution: 14.86 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961941 AG1-037 C Adder 0.7 MW 0.59 MW
961942 AG1-037 E Adder 0.46 MW 0.4 MW
962331 AG1-082 C Adder 2.79 MW 2.37 MW
962332 AG1-082 E Adder 1.86 MW 1.58 MW
963041 AG1-153 C 50/50 9.53 MW 9.53 MW
963042 AG1-153 E 50/50 14.3 MW 14.3 MW
964791 AG1-342 C Adder 4.71 MW 4.0 MW
964792 AG1-342 E Adder 3.14 MW 2.67 MW
966801 AG1-551 C Adder 2.86 MW 2.43 MW
966802 AG1-551 E Adder 1.51 MW 1.28 MW
966811 AG1-552 C Adder 2.86 MW 2.43 MW
966812 AG1-552 E Adder 1.36 MW 1.15 MW
965291 AG1-394 C Adder 1.18 MW 1.0 MW
965292 AG1-394 E Adder 2.17 MW 1.84 MW
966621 AG1-532 C Adder 1.95 MW 1.66 MW
966622 AG1-532 E Adder 1.3 MW 1.1 MW
314541 3WATKINS Adder 0.95 MW 0.81 MW
314572 3EMPORIA Adder 0.6 MW 0.51 MW
315153 1CLOVER1 50/50 18.69 MW 18.69 MW
315154 1CLOVER2 50/50 18.52 MW 18.52 MW
918492 AA1-063AE OP Adder 5.66 MW 4.81 MW
918532 AA1-067 E Adder 0.97 MW 0.82 MW
919692 AA2-053 E OP Adder 5.87 MW 4.99 MW
920042 AA2-088 E OP Adder 14.65 MW 12.45 MW
925785 AC1-054 E Adder 4.73 MW 4.02 MW
926274 AC1-105 E Adder 3.54 MW 3.01 MW
927146 AC1-208 E Adder 5.74 MW 4.88 MW
934521 AD1-076 C Adder 16.89 MW 14.36 MW
934522 AD1-076 E Adder 8.61 MW 7.32 MW
943172 AE2-346 E Adder 0.84 MW 0.71 MW
943902 AF1-058 E Adder 1.69 MW 1.44 MW
944011 AF1-069 C 50/50 22.43 MW 22.43 MW
944012 AF1-069 E 50/50 8.71 MW 8.71 MW
959311 AF2-222 C Adder 21.48 MW 18.26 MW
959312 AF2-222 E Adder 14.39 MW 12.23 MW
960061 AF2-297 C Adder 10.15 MW 8.63 MW
960062 AF2-297 E Adder 6.77 MW 5.75 MW
960081 AF2-299 C Adder 2.6 MW 2.21 MW
960082 AF2-299 E Adder 1.73 MW 1.47 MW
316141 AB2-099 E Adder 0.35 MW 0.3 MW
900672 V4-068 E Adder 0.49 MW 0.42 MW
917342 Z2-044 E Adder 0.89 MW 0.75 MW
923263 AB1-132 E OP Adder 8.43 MW 7.16 MW
923573 AB1-173 E OP Adder 4.56 MW 3.88 MW
924162 AB2-060 E OP Adder 5.78 MW 4.91 MW
924302 AB2-077 E O1 Adder 1.82 MW 1.54 MW
924312 AB2-078 E O1 Adder 1.82 MW 1.54 MW
924322 AB2-079 E O1 Adder 1.82 MW 1.54 MW
925612 AC1-036 E Adder 1.12 MW 0.95 MW
939181 AE1-148 C Adder 12.3 MW 10.46 MW
939182 AE1-148 E Adder 8.2 MW 6.97 MW
940492 AE2-034 E Adder 4.26 MW 3.62 MW
941031 AE2-094 C 50/50 68.64 MW 68.64 MW
941032 AE2-094 E 50/50 30.74 MW 30.74 MW
946281 AF1-292 C Adder 2.15 MW 1.83 MW
946282 AF1-292 E Adder 1.44 MW 1.22 MW
957481 AF2-042 C 50/50 81.96 MW 81.96 MW
957482 AF2-042 E 50/50 54.64 MW 54.64 MW
957521 AF2-046 C Adder 19.61 MW 16.67 MW
957522 AF2-046 E Adder 9.91 MW 8.42 MW
957861 AF2-080 C Adder 10.3 MW 8.75 MW
957862 AF2-080 E Adder 4.56 MW 3.88 MW
314539 3UNCAMP Adder 8.35 MW 7.1 MW
916042 Z1-036 E Adder 39.63 MW 33.68 MW
938771 AE1-103 C Adder 4.02 MW 3.42 MW
938772 AE1-103 E Adder 5.55 MW 4.72 MW
313526 AB2-022 C 50/50 0.53 MW 0.53 MW
314331 6POE Adder 1.66 MW 1.41 MW
314507 3THOMPSN Adder 2.79 MW 2.37 MW
314525 6KINGFORK Adder 1.35 MW 1.15 MW
314550 6HICKORY 50/50 3.06 MW 3.06 MW
926662 AC1-147 E Adder 1.83 MW 1.55 MW
926755 AC1-161 E 50/50 18.47 MW 18.47 MW
935112 AD1-144 E Adder 1.25 MW 1.06 MW
942341 AE2-247 C Adder 1.95 MW 1.66 MW
942342 AE2-247 E Adder 2.7 MW 2.29 MW
943461 AF1-017 C Adder 1.77 MW 1.5 MW
943462 AF1-017 E Adder 2.88 MW 2.45 MW
943612 AF1-032 E Adder 1.28 MW 1.09 MW
315102 1BRUNSWICKG1 50/50 14.07 MW 14.07 MW
315103 1BRUNSWICKG2 50/50 14.07 MW 14.07 MW
315104 1BRUNSWICKG3 50/50 14.07 MW 14.07 MW
315105 1BRUNSWICKS1 50/50 29.23 MW 29.23 MW
315108 1ELIZAR1 50/50 4.43 MW 4.43 MW
315109 1ELIZAR2 50/50 4.35 MW 4.35 MW
315110 1ELIZAR3 50/50 4.49 MW 4.49 MW
315241 1Z1-086 GT1 50/50 18.03 MW 18.03 MW
315242 1Z1-086 GT2 50/50 18.02 MW 18.02 MW
315243 1Z1-086 GT3 50/50 18.02 MW 18.02 MW
315244 1Z1-086 ST 50/50 31.38 MW 31.38 MW
315260 1GOSPORTA Adder 2.94 MW 2.5 MW
315261 1GOSPORTB Adder 3.76 MW 3.19 MW
315262 1GOSPORTC Adder 3.19 MW 2.71 MW
913392 Y1-086 E 50/50 3.06 MW 3.06 MW
916192 Z1-068 E 50/50 2.62 MW 2.62 MW
923832 AB2-022 E 50/50 1.73 MW 1.73 MW
923852 AB2-025 E 50/50 1.65 MW 1.65 MW
939312 AE1-162 E Adder 1.78 MW 1.51 MW
957492 AF2-043 E Adder 1.96 MW 1.67 MW
901082 W1-029 E Adder 44.24 MW 37.6 MW
917122 Z2-027 E Adder 1.87 MW 1.59 MW
925522 AC1-027 E 50/50 1.69 MW 1.69 MW
957871 AF2-081 C 50/50 13.99 MW 13.99 MW
957872 AF2-081 E 50/50 5.99 MW 5.99 MW
958161 AF2-110 C Adder 1.86 MW 1.58 MW
958162 AF2-110 E Adder 2.97 MW 2.52 MW
314722 3TWITTYS Adder 1.25 MW 1.06 MW
917512 Z2-088 E OP1 Adder 6.58 MW 5.59 MW
926071 AC1-086 C Adder 28.96 MW 24.61 MW
926072 AC1-086 E Adder 13.18 MW 11.2 MW
927021 AC1-189 C Adder 11.34 MW 9.64 MW
927022 AC1-189 E Adder 5.65 MW 4.8 MW
936261 AD2-033 C Adder 16.34 MW 13.89 MW
936262 AD2-033 E Adder 2.66 MW 2.26 MW
933291 AC2-141 C 50/50 43.28 MW 43.28 MW
933292 AC2-141 E 50/50 18.47 MW 18.47 MW
934621 AD1-088 C 50/50 18.04 MW 18.04 MW
934622 AD1-088 E 50/50 8.49 MW 8.49 MW
939411 AE1-173 C 50/50 148.04 MW 148.04 MW
939412 AE1-173 E 50/50 98.69 MW 98.69 MW
916191 Z1-068 C 50/50 0.06 MW 0.06 MW
933981 AD1-022 C Adder 12.08 MW 10.27 MW
933982 AD1-022 E Adder 6.58 MW 5.59 MW
962572 AG1-106 E Adder 1.64 MW 1.39 MW
961681 AG1-008 C Adder 19.61 MW 16.67 MW
961682 AG1-008 E Adder 9.91 MW 8.42 MW
962571 AG1-106 C Adder 3.75 MW 3.18 MW
314594 6PLYMOUTH TP Adder 0.45 MW 0.38 MW
314632 6AYDLETT TAP 50/50 1.9 MW 1.9 MW
316185 AD1-033 C 50/50 1.72 MW 1.72 MW
316274 AC1-208 C Adder 12.93 MW 10.99 MW
316294 AC1-161 C 50/50 7.07 MW 7.07 MW
316315 AB2-025 C 50/50 0.58 MW 0.58 MW
316316 AC1-027 C 50/50 0.44 MW 0.44 MW
316320 Y1-086 C 50/50 0.31 MW 0.31 MW
917332 KELFORD E Adder 2.3 MW 1.96 MW
924516 AB2-100 E1 Adder 4.04 MW 3.44 MW
924517 AB2-100 E2 Adder 4.04 MW 3.44 MW
926206 AC1-098 E Adder 5.22 MW 4.44 MW
926214 AC1-099 E Adder 1.73 MW 1.47 MW
934065 AD1-033 E 50/50 7.03 MW 7.03 MW
937226 AE2-253 E 50/50 8.18 MW 8.18 MW
918512 AA1-065 E OP Adder 7.61 MW 6.47 MW
316017 AA1-139 ULT1 50/50 1.51 MW 1.51 MW
316018 AA1-139 ULT2 50/50 1.51 MW 1.51 MW
919153 AA1-139 E2 50/50 5.72 MW 5.72 MW
919152 AA1-139 E1 50/50 5.72 MW 5.72 MW
919710 AA2-057 E Adder 5.81 MW 4.94 MW
920692 AA2-178 E Adder 5.68 MW 4.83 MW
923994 AB2-040_E Adder 8.56 MW 7.27 MW
924022 AB2-043 E O1 Adder 7.04 MW 5.99 MW
316084 AB2-161 E Adder 6.78 MW 5.76 MW
925122 AB2-169 E Adder 7.87 MW 6.69 MW
316088 AB2-174 E Adder 9.07 MW 7.71 MW
932046 AC2-012 E Adder 18.08 MW 15.37 MW
316311 AC2-079 C Adder 7.55 MW 6.42 MW
932596 AC2-079 E Adder 12.32 MW 10.47 MW
934576 AD1-082 E Adder 5.4 MW 4.59 MW
316349 AD2-085 C Adder 4.51 MW 3.83 MW
936666 AD2-085 E Adder 7.35 MW 6.25 MW
316388 AE2-253 GEN 50/50 2.75 MW 2.75 MW
941591 AE2-156 C 50/50 24.73 MW 24.73 MW
944581 AF1-123 C 50/50 63.67 MW 63.67 MW
944582 AF1-123 E 50/50 145.79 MW 145.79 MW
944591 AF1-124 C 50/50 63.89 MW 63.89 MW
944592 AF1-124 E 50/50 146.32 MW 146.32 MW
944601 AF1-125 C 50/50 62.69 MW 62.69 MW
944602 AF1-125 E 50/50 143.5 MW 143.5 MW
962491 AG1-098 C 50/50 16.0 MW 16.0 MW
962492 AG1-098 E 50/50 10.67 MW 10.67 MW
962561 AG1-105 C Adder 11.85 MW 10.07 MW
962562 AG1-105 E Adder 7.9 MW 6.72 MW
964241 AG1-285 C Adder 17.71 MW 15.05 MW
964242 AG1-285 E Adder 11.81 MW 10.04 MW
313764 3SOCKMAN Adder 0.99 MW 0.84 MW
932632 AC2-084 E Adder 4.62 MW 3.92 MW
934321 AD1-056 C Adder 8.47 MW 7.2 MW
934322 AD1-056 E Adder 4.6 MW 3.91 MW
934331 AD1-057 C Adder 4.73 MW 4.02 MW
934332 AD1-057 E Adder 2.46 MW 2.09 MW
934501 AD1-074 C Adder 46.5 MW 39.53 MW
934502 AD1-074 E Adder 23.67 MW 20.12 MW
934511 AD1-075 C Adder 11.63 MW 9.88 MW
934512 AD1-075 E Adder 5.92 MW 5.03 MW
934611 AD1-087 C 50/50 1.84 MW 1.84 MW
934612 AD1-087 E 50/50 5.31 MW 5.31 MW
935172 AD1-152 E Adder 7.79 MW 6.62 MW
937481 AD2-202 C 50/50 0.53 MW 0.53 MW
937482 AD2-202 E 50/50 1.55 MW 1.55 MW
938531 AE1-072 C 50/50 24.58 MW 24.58 MW
938532 AE1-072 E 50/50 12.81 MW 12.81 MW
940481 AE2-033 C 50/50 22.94 MW 22.94 MW
940482 AE2-033 E 50/50 15.47 MW 15.47 MW
940541 AE2-040 C 50/50 4.08 MW 4.08 MW
940641 AE2-051 C 50/50 29.5 MW 29.5 MW
940642 AE2-051 E 50/50 19.67 MW 19.67 MW
941101 AE2-104 C Adder 4.57 MW 3.88 MW
941102 AE2-104 E Adder 7.27 MW 6.18 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 37.48 MW 37.48 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 28.0 MW 28.0 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 127.4 MW 127.4 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 4.78 MW 4.78 MW
NY PJM->LTFIMP_NY CLTF 2.22 MW 2.22 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.48 MW 1.48 MW
WEC LTFEXP_WEC->PJM CLTF 0.78 MW 0.78 MW
CPLE LTFEXP_CPLE->PJM CLTF 15.57 MW 15.57 MW
TVA LTFEXP_TVA->PJM CLTF 7.65 MW 7.65 MW
MEC LTFEXP_MEC->PJM CLTF 4.82 MW 4.82 MW
LAGN LTFEXP_LAGN->PJM CLTF 9.76 MW 9.76 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.29 MW 0.29 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 30.41 MW 30.41 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.42 MW 7.42 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
DVP_P1-2: LN 575_SRT-S
CONTINGENCY 'DVP_P1-2: LN 575_SRT-S'
 OPEN BRANCH FROM BUS 314911 TO BUS 314918 CKT 1                /*8LADYSMITH   500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
END
Single AC 122.94 % 3220.44 B 3959.17 6.58
DVP 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
DVP_P1-2: LN 552_SRT-S
CONTINGENCY 'DVP_P1-2: LN 552_SRT-S'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 1                /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314900 TO BUS 314905 CKT 1                /*8BRISTER     500.0 - 8CHANCE      500.0
 SET POSTCONTRATING 2831 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2552 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
END
Single AC 122.77 % 3220.44 B 3953.87 7.65
DVP 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
DVP_P1-2: LN 574_SRT-S
CONTINGENCY 'DVP_P1-2: LN 574_SRT-S'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 120.01 % 3220.44 B 3864.83 11.03
DVP 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
DVP_P1-2: LN 575_SRT-S
CONTINGENCY 'DVP_P1-2: LN 575_SRT-S'
 OPEN BRANCH FROM BUS 314911 TO BUS 314918 CKT 1                /*8LADYSMITH   500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
END
Single AC 118.84 % 3220.44 B 3827.26 6.76
DVP 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
DVP_P1-2: LN 581_SRT-S
CONTINGENCY 'DVP_P1-2: LN 581_SRT-S'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 2                /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314905 TO BUS 314911 CKT 1                /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2831 BRANCH FROM BUS 314900 TO BUS 314905 CKT 1 /*8BRISTER     500.0 - 8CHANCE      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2552 BRANCH FROM BUS 314900 TO BUS 314905 CKT 1 /*8BRISTER     500.0 - 8CHANCE      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Single AC 117.57 % 3220.44 B 3786.34 7.82
DVP 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Single AC 113.8 % 4070.2 B 4632.05 11.93
DVP 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line
314918 to 314911 ckt 1
DVP_P1-2: LN 573_SRT-A
CONTINGENCY 'DVP_P1-2: LN 573_SRT-A'
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1   /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Single AC 111.16 % 3220.44 B 3579.93 5.98
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Base Case Single AC 108.58 % 678.68 A 736.88 6.82
DVP 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Single AC 107.79 % 559.3 B 602.85 2.74
DVP 6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Single AC 106.88 % 571.52 B 610.86 2.74
DVP AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Base Case Single AC 105.77 % 678.68 A 717.82 6.82
DVP 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Single AC 104.68 % 984.18 B 1030.28 3.77
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P1-2: LN 574_SRT-S
CONTINGENCY 'DVP_P1-2: LN 574_SRT-S'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Single AC 103.22 % 3220.44 B 3324.19 10.17
DVP 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Single AC 102.52 % 984.18 B 1008.98 3.77
DVP 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Single AC 100.88 % 4070.2 B 4105.97 10.13
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
DVP_P4-2: H2T574_SRT-S
CONTINGENCY 'DVP_P4-2: H2T574_SRT-S'
 OPEN BRANCH FROM BUS 314196 TO BUS 314911 CKT 2                /*6LADYSMITH   230.0 - 8LADYSMITH   500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
END
Breaker AC 115.67 % 3940.0 C 4557.54 14.76
DVP 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line
314918 to 314911 ckt 1
DVP_P4-2: SPOTS H1T594_SRT-S
CONTINGENCY 'DVP_P4-2: SPOTS H1T594_SRT-S'
 OPEN BRANCH FROM BUS 314755 TO BUS 314934 CKT 1                /*3SPOTSYL     115.0 - 8SPOTSYL     500.0
 OPEN BRANCH FROM BUS 314916 TO BUS 314934 CKT 1                /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
END
Breaker AC 112.93 % 3940.0 C 4449.5 8.56
DVP 6CARSON-6POE 230.0 kV Ckt 1 line
314282 to 314331 ckt 1
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Breaker AC 102.1 % 830.0 C 847.45 3.79
CPLE/DVP 3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
314554 to 304223 ckt 1
DVP_P7-1: LN 2058-2181_SRT-A
CONTINGENCY 'DVP_P7-1: LN 2058-2181_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Tower AC 120.73 % 313.0 B 377.88 7.95

Details for 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 575_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
Contingency Name:
DVP_P1-2: LN 575_SRT-S
CONTINGENCY 'DVP_P1-2: LN 575_SRT-S'
 OPEN BRANCH FROM BUS 314911 TO BUS 314918 CKT 1                /*8LADYSMITH   500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 122.94 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3959.17 MVA
MW Contribution: 6.58 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.81 MW 0.69 MW
961791 AG1-021 C Adder 1.58 MW 1.34 MW
961941 AG1-037 C Adder 0.44 MW 0.38 MW
962331 AG1-082 C Adder 1.77 MW 1.5 MW
963041 AG1-153 C 80/20 5.54 MW 5.54 MW
963171 AG1-166 C Adder 0.88 MW 0.75 MW
963181 AG1-167 C Adder 0.66 MW 0.56 MW
963191 AG1-168 C Adder 0.66 MW 0.56 MW
964791 AG1-342 C Adder 3.07 MW 2.61 MW
966801 AG1-551 C Adder 1.82 MW 1.55 MW
966811 AG1-552 C Adder 1.82 MW 1.54 MW
965291 AG1-394 C Adder 0.75 MW 0.64 MW
966621 AG1-532 C Adder 1.26 MW 1.07 MW
313853 3PONTONDP Adder 0.59 MW 0.5 MW
315131 1EDGECMA Adder 13.29 MW 11.3 MW
315153 1CLOVER1 80/20 11.78 MW 11.78 MW
315154 1CLOVER2 80/20 11.67 MW 11.67 MW
934521 AD1-076 C Adder 10.68 MW 9.08 MW
944011 AF1-069 C 80/20 13.04 MW 13.04 MW
959311 AF2-222 C Adder 14.69 MW 12.48 MW
960061 AF2-297 C Adder 6.63 MW 5.63 MW
960081 AF2-299 C Adder 1.67 MW 1.42 MW
938371 AE1-056 C Adder 5.68 MW 4.83 MW
939181 AE1-148 C Adder 7.94 MW 6.75 MW
941031 AE2-094 C 80/20 39.92 MW 39.92 MW
946281 AF1-292 C Adder 1.39 MW 1.18 MW
946301 AF1-294 C Adder 3.25 MW 2.76 MW
957481 AF2-042 C 80/20 51.04 MW 51.04 MW
957521 AF2-046 C Adder 12.46 MW 10.59 MW
957861 AF2-080 C Adder 6.58 MW 5.59 MW
958211 AF2-115 C Adder 1.98 MW 1.68 MW
938771 AE1-103 C Adder 2.57 MW 2.18 MW
314507 3THOMPSN Adder 1.76 MW 1.5 MW
315065 1CHESTF6 Adder 15.65 MW 13.3 MW
315073 1STONECA Adder 5.33 MW 4.53 MW
315083 1SPRUNCA Adder 7.63 MW 6.49 MW
315084 1SPRUNCB Adder 7.63 MW 6.49 MW
315092 1YORKTN3 Adder 100.44 MW 85.37 MW
934861 AD1-115 C Adder 2.85 MW 2.42 MW
942341 AE2-247 C Adder 1.3 MW 1.1 MW
943461 AF1-017 C Adder 1.18 MW 1.0 MW
315098 1CHESPKA 80/20 0.38 MW 0.38 MW
315099 1CHESPKB 80/20 0.63 MW 0.63 MW
315102 1BRUNSWICKG1 80/20 8.15 MW 8.15 MW
315103 1BRUNSWICKG2 80/20 8.15 MW 8.15 MW
315104 1BRUNSWICKG3 80/20 8.15 MW 8.15 MW
315105 1BRUNSWICKS1 80/20 16.93 MW 16.93 MW
315108 1ELIZAR1 80/20 2.78 MW 2.78 MW
315109 1ELIZAR2 80/20 2.73 MW 2.73 MW
315110 1ELIZAR3 80/20 2.82 MW 2.82 MW
315172 1LOISA A 80/20 2.69 MW 2.69 MW
315173 1LOISA B 80/20 2.71 MW 2.71 MW
315174 1LOISA C 80/20 2.71 MW 2.71 MW
315175 1LOISA D 80/20 2.71 MW 2.71 MW
315176 1LOISA E 80/20 5.52 MW 5.52 MW
315177 1S ANNAG1 80/20 2.65 MW 2.65 MW
315178 1S ANNAS1 80/20 1.36 MW 1.36 MW
315179 1S ANNAG2 80/20 2.65 MW 2.65 MW
315180 1S ANNAS2 80/20 1.36 MW 1.36 MW
315225 1N ANNA1 80/20 89.05 MW 89.05 MW
315226 1N ANNA2 80/20 89.08 MW 89.08 MW
315241 1Z1-086 GT1 80/20 10.44 MW 10.44 MW
315242 1Z1-086 GT2 80/20 10.44 MW 10.44 MW
315243 1Z1-086 GT3 80/20 10.44 MW 10.44 MW
315244 1Z1-086 ST 80/20 18.18 MW 18.18 MW
315260 1GOSPORTA Adder 1.86 MW 1.58 MW
315261 1GOSPORTB 80/20 2.37 MW 2.37 MW
315262 1GOSPORTC Adder 2.01 MW 1.71 MW
966001 AG1-469 C 80/20 1.96 MW 1.96 MW
942001 AE2-212 C Adder 1.82 MW 1.55 MW
957871 AF2-081 C Adder 8.73 MW 7.42 MW
958161 AF2-110 C Adder 1.2 MW 1.02 MW
926071 AC1-086 C Adder 18.57 MW 15.79 MW
927021 AC1-189 C Adder 7.24 MW 6.15 MW
936261 AD2-033 C Adder 11.47 MW 9.75 MW
933291 AC2-141 C 80/20 26.48 MW 26.48 MW
934621 AD1-088 C 80/20 11.86 MW 11.86 MW
939411 AE1-173 C 80/20 88.01 MW 88.01 MW
916191 Z1-068 C 80/20 0.04 MW 0.04 MW
933981 AD1-022 C Adder 7.65 MW 6.5 MW
961681 AG1-008 C Adder 12.46 MW 10.59 MW
962571 AG1-106 C Adder 2.4 MW 2.04 MW
208900 BRIS G1 80/20 -2.63 MW -2.63 MW
208901 BRIS G2 80/20 -3.11 MW -3.11 MW
316023 AB2-100 C2 80/20 0.86 MW 0.86 MW
316036 AC1-147 C 80/20 0.32 MW 0.32 MW
316164 AC1-076_C 80/20 1.11 MW 1.11 MW
316170 AC1-121 C 80/20 2.73 MW 2.73 MW
316185 AD1-033 C 80/20 1.07 MW 1.07 MW
316192 AB2-158 C 80/20 3.63 MW 3.63 MW
316233 AE1-074 C 80/20 2.42 MW 2.42 MW
316240 AF1-291 C Adder 1.74 MW 1.48 MW
316254 AC1-120 C 80/20 7.93 MW 7.93 MW
316257 AC1-043 C Adder 5.7 MW 4.84 MW
316258 AE1-075 C 80/20 0.35 MW 0.35 MW
316263 AC1-034 C Adder 5.69 MW 4.83 MW
316274 AC1-208 C Adder 7.86 MW 6.68 MW
316294 AC1-161 C 80/20 4.31 MW 4.31 MW
316313 AB2-026 C 80/20 0.38 MW 0.38 MW
316315 AB2-025 C 80/20 0.38 MW 0.38 MW
316316 AC1-027 C 80/20 0.28 MW 0.28 MW
316336 AC2-165 C 80/20 9.63 MW 9.63 MW
316365 AB2-100 C1 80/20 0.86 MW 0.86 MW
316405 AF2-144 C 80/20 0.29 MW 0.29 MW
316044 AC1-158 C1 80/20 19.42 MW 19.42 MW
316045 AC1-158 C2 80/20 19.42 MW 19.42 MW
316375 AC2-012 C 80/20 1.17 MW 1.17 MW
316311 AC2-079 C Adder 5.0 MW 4.25 MW
316349 AD2-085 C Adder 3.0 MW 2.55 MW
316388 AE2-253 GEN 80/20 1.71 MW 1.71 MW
961611 AG1-000B C Adder 12.92 MW 10.98 MW
941591 AE2-156 C 80/20 15.61 MW 15.61 MW
944581 AF1-123 C 80/20 39.93 MW 39.93 MW
944591 AF1-124 C 80/20 40.07 MW 40.07 MW
944601 AF1-125 C 80/20 39.32 MW 39.32 MW
962491 AG1-098 C 80/20 10.62 MW 10.62 MW
962561 AG1-105 C Adder 7.71 MW 6.55 MW
964241 AG1-285 C Adder 11.04 MW 9.39 MW
965281 AG1-393 C Adder 1.77 MW 1.5 MW
313764 3SOCKMAN Adder 0.63 MW 0.54 MW
934321 AD1-056 C Adder 5.44 MW 4.62 MW
934331 AD1-057 C Adder 3.03 MW 2.58 MW
934501 AD1-074 C Adder 29.42 MW 25.01 MW
934511 AD1-075 C Adder 7.36 MW 6.25 MW
934611 AD1-087 C 80/20 1.16 MW 1.16 MW
935161 AD1-151 C Adder 12.77 MW 10.86 MW
937481 AD2-202 C 80/20 0.34 MW 0.34 MW
938531 AE1-072 C Adder 15.36 MW 13.05 MW
939191 AE1-149 C Adder 9.27 MW 7.88 MW
940431 AE2-027 C Adder 10.48 MW 8.9 MW
940481 AE2-033 C 80/20 14.9 MW 14.9 MW
940541 AE2-040 C 80/20 2.65 MW 2.65 MW
940641 AE2-051 C 80/20 17.3 MW 17.3 MW
941101 AE2-104 C Adder 2.93 MW 2.49 MW
942461 AE2-259 C Adder 8.75 MW 7.44 MW
944641 AF1-129 C Adder 81.61 MW 69.36 MW
316303 AF2-085 80/20 4.19 MW 4.19 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 21.91 MW 21.91 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 18.48 MW 18.48 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 83.41 MW 83.41 MW
NY PJM->LTFIMP_NY CLTF 2.53 MW 2.53 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.97 MW 0.97 MW
WEC LTFEXP_WEC->PJM CLTF 0.47 MW 0.47 MW
CPLE LTFEXP_CPLE->PJM CLTF 9.95 MW 9.95 MW
TVA LTFEXP_TVA->PJM CLTF 5.19 MW 5.19 MW
MEC LTFEXP_MEC->PJM CLTF 3.06 MW 3.06 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.53 MW 6.53 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.19 MW 0.19 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 4.74 MW 4.74 MW

Details for 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 552_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line
314934 to 314916 ckt 1
Contingency Name:
DVP_P1-2: LN 552_SRT-S
CONTINGENCY 'DVP_P1-2: LN 552_SRT-S'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 1                /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314900 TO BUS 314905 CKT 1                /*8BRISTER     500.0 - 8CHANCE      500.0
 SET POSTCONTRATING 2831 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2552 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 122.77 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3953.87 MVA
MW Contribution: 7.65 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.93 MW 0.79 MW
961791 AG1-021 C Adder 1.7 MW 1.45 MW
961941 AG1-037 C Adder 0.53 MW 0.45 MW
962331 AG1-082 C Adder 2.11 MW 1.79 MW
963041 AG1-153 C Adder 5.77 MW 4.9 MW
963171 AG1-166 C Adder 0.95 MW 0.8 MW
963181 AG1-167 C Adder 0.71 MW 0.6 MW
963191 AG1-168 C Adder 0.71 MW 0.6 MW
964791 AG1-342 C Adder 3.32 MW 2.83 MW
966801 AG1-551 C Adder 2.15 MW 1.82 MW
966811 AG1-552 C Adder 2.1 MW 1.78 MW
965291 AG1-394 C Adder 0.9 MW 0.76 MW
966621 AG1-532 C Adder 1.44 MW 1.22 MW
313853 3PONTONDP Adder 0.63 MW 0.54 MW
934521 AD1-076 C Adder 12.97 MW 11.02 MW
944011 AF1-069 C 80/20 13.52 MW 13.52 MW
959311 AF2-222 C Adder 15.87 MW 13.49 MW
960081 AF2-299 C Adder 1.92 MW 1.63 MW
938371 AE1-056 C Adder 6.1 MW 5.18 MW
939181 AE1-148 C Adder 8.68 MW 7.38 MW
941031 AE2-094 C 80/20 41.39 MW 41.39 MW
946281 AF1-292 C Adder 1.58 MW 1.35 MW
946301 AF1-294 C Adder 3.5 MW 2.98 MW
957481 AF2-042 C Adder 53.68 MW 45.62 MW
957521 AF2-046 C Adder 14.87 MW 12.64 MW
957861 AF2-080 C Adder 7.65 MW 6.5 MW
958211 AF2-115 C Adder 2.13 MW 1.81 MW
938771 AE1-103 C Adder 3.16 MW 2.69 MW
314236 6NRTHEST 80/20 0.2 MW 0.2 MW
314309 6IRON208 80/20 0.48 MW 0.48 MW
314507 3THOMPSN Adder 2.23 MW 1.9 MW
315060 1CHESTF5 Adder 69.01 MW 58.66 MW
315065 1CHESTF6 80/20 21.77 MW 21.77 MW
315073 1STONECA 80/20 7.61 MW 7.61 MW
315076 1HOPPOLC 80/20 1.69 MW 1.69 MW
315077 1HOPHCF1 80/20 2.68 MW 2.68 MW
315078 1HOPHCF2 80/20 2.68 MW 2.68 MW
315079 1HOPHCF3 80/20 2.68 MW 2.68 MW
315080 1HOPHCF4 80/20 4.07 MW 4.07 MW
315083 1SPRUNCA 80/20 10.22 MW 10.22 MW
315084 1SPRUNCB 80/20 10.22 MW 10.22 MW
315092 1YORKTN3 Adder 144.43 MW 122.76 MW
936591 AD2-074 C Adder 5.73 MW 4.87 MW
942341 AE2-247 C Adder 1.64 MW 1.4 MW
943461 AF1-017 C Adder 1.49 MW 1.26 MW
943741 AF1-042 C Adder 3.0 MW 2.55 MW
961951 AG1-038 C Adder 3.31 MW 2.82 MW
966661 AG1-536 C Adder 5.51 MW 4.68 MW
966871 AG1-558 C Adder 2.51 MW 2.13 MW
966881 AG1-559 C Adder 2.4 MW 2.04 MW
315099 1CHESPKB 80/20 0.8 MW 0.8 MW
315108 1ELIZAR1 80/20 3.53 MW 3.53 MW
315109 1ELIZAR2 80/20 3.47 MW 3.47 MW
315110 1ELIZAR3 80/20 3.57 MW 3.57 MW
315225 1N ANNA1 80/20 55.33 MW 55.33 MW
315226 1N ANNA2 80/20 55.35 MW 55.35 MW
315233 1SURRY 2 80/20 27.3 MW 27.3 MW
315260 1GOSPORTA Adder 2.36 MW 2.0 MW
315261 1GOSPORTB Adder 3.01 MW 2.56 MW
315262 1GOSPORTC Adder 2.55 MW 2.17 MW
957411 AF2-035 C Adder 8.65 MW 7.35 MW
957601 AF2-054 C Adder 2.21 MW 1.88 MW
962861 AG1-135 C Adder 6.23 MW 5.29 MW
962971 AG1-146 C Adder 3.19 MW 2.71 MW
962981 AG1-147 C Adder 7.44 MW 6.32 MW
963051 AG1-154 C Adder 3.44 MW 2.92 MW
963611 AG1-210 C Adder 0.67 MW 0.57 MW
964211 AG1-282 C Adder 2.03 MW 1.73 MW
942001 AE2-212 C 80/20 2.4 MW 2.4 MW
957871 AF2-081 C Adder 10.98 MW 9.34 MW
958161 AF2-110 C Adder 1.5 MW 1.28 MW
926071 AC1-086 C Adder 21.52 MW 18.29 MW
927021 AC1-189 C Adder 8.42 MW 7.16 MW
936261 AD2-033 C Adder 12.42 MW 10.55 MW
933291 AC2-141 C 80/20 33.68 MW 33.68 MW
934621 AD1-088 C Adder 12.5 MW 10.63 MW
939411 AE1-173 C 80/20 97.69 MW 97.69 MW
927041 AC1-191 C Adder 10.08 MW 8.57 MW
933981 AD1-022 C Adder 9.25 MW 7.87 MW
961681 AG1-008 C Adder 14.87 MW 12.64 MW
962571 AG1-106 C Adder 2.78 MW 2.37 MW
316164 AC1-076_C 80/20 0.99 MW 0.99 MW
316169 AC1-164 GEN Adder 42.79 MW 36.37 MW
316192 AB2-158 C 80/20 2.12 MW 2.12 MW
316233 AE1-074 C 80/20 2.82 MW 2.82 MW
316240 AF1-291 C 80/20 2.4 MW 2.4 MW
316274 AC1-208 C Adder 9.1 MW 7.73 MW
316294 AC1-161 C 80/20 5.48 MW 5.48 MW
316336 AC2-165 C Adder 10.13 MW 8.61 MW
316044 AC1-158 C1 80/20 14.96 MW 14.96 MW
316045 AC1-158 C2 80/20 14.96 MW 14.96 MW
316375 AC2-012 C 80/20 1.49 MW 1.49 MW
316311 AC2-079 C Adder 6.32 MW 5.37 MW
316349 AD2-085 C Adder 3.79 MW 3.22 MW
961611 AG1-000B C Adder 17.56 MW 14.93 MW
941591 AE2-156 C 80/20 19.8 MW 19.8 MW
944581 AF1-123 C 80/20 50.24 MW 50.24 MW
944591 AF1-124 C 80/20 50.42 MW 50.42 MW
944601 AF1-125 C 80/20 49.47 MW 49.47 MW
944631 AF1-128 C Adder 43.18 MW 36.7 MW
958261 AF2-120 C Adder 6.41 MW 5.45 MW
962491 AG1-098 C Adder 11.2 MW 9.52 MW
962561 AG1-105 C Adder 8.36 MW 7.11 MW
964241 AG1-285 C Adder 11.99 MW 10.19 MW
965281 AG1-393 C 80/20 2.39 MW 2.39 MW
313764 3SOCKMAN Adder 0.73 MW 0.62 MW
934321 AD1-056 C Adder 6.26 MW 5.32 MW
934331 AD1-057 C Adder 3.49 MW 2.97 MW
934501 AD1-074 C Adder 35.71 MW 30.35 MW
934511 AD1-075 C Adder 8.93 MW 7.59 MW
935161 AD1-151 C Adder 17.8 MW 15.13 MW
938531 AE1-072 C Adder 19.3 MW 16.41 MW
939191 AE1-149 C 80/20 11.91 MW 11.91 MW
939261 AE1-157 C Adder 13.78 MW 11.71 MW
940431 AE2-027 C 80/20 14.32 MW 14.32 MW
940481 AE2-033 C Adder 17.09 MW 14.53 MW
940541 AE2-040 C Adder 3.04 MW 2.58 MW
940551 AE2-041 C Adder 7.46 MW 6.34 MW
940641 AE2-051 C 80/20 18.5 MW 18.5 MW
941101 AE2-104 C Adder 3.68 MW 3.13 MW
942461 AE2-259 C Adder 9.36 MW 7.96 MW
943471 AF1-018 C Adder 7.46 MW 6.34 MW
944641 AF1-129 C 80/20 113.54 MW 113.54 MW
315085 1SPRUNCC 80/20 0.18 MW 0.18 MW
315086 1SPRUNCD 80/20 0.18 MW 0.18 MW
316303 AF2-085 80/20 4.37 MW 4.37 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 27.62 MW 27.62 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 22.07 MW 22.07 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 94.18 MW 94.18 MW
NY PJM->LTFIMP_NY CLTF 2.81 MW 2.81 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.22 MW 1.22 MW
WEC LTFEXP_WEC->PJM CLTF 0.59 MW 0.59 MW
CPLE LTFEXP_CPLE->PJM CLTF 11.09 MW 11.09 MW
TVA LTFEXP_TVA->PJM CLTF 6.14 MW 6.14 MW
MEC LTFEXP_MEC->PJM CLTF 3.74 MW 3.74 MW
LAGN LTFEXP_LAGN->PJM CLTF 7.67 MW 7.67 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.24 MW 0.24 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 5.29 MW 5.29 MW

Details for 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 574_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line
314914 to 314918 ckt 1
Contingency Name:
DVP_P1-2: LN 574_SRT-S
CONTINGENCY 'DVP_P1-2: LN 574_SRT-S'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 120.01 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3864.83 MVA
MW Contribution: 11.03 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.35 MW 1.15 MW
961791 AG1-021 C Adder 2.41 MW 2.05 MW
961941 AG1-037 C Adder 0.74 MW 0.63 MW
962331 AG1-082 C Adder 2.98 MW 2.53 MW
963041 AG1-153 C 80/20 8.78 MW 8.78 MW
963171 AG1-166 C Adder 1.34 MW 1.14 MW
963181 AG1-167 C Adder 1.0 MW 0.85 MW
963191 AG1-168 C Adder 1.0 MW 0.85 MW
964791 AG1-342 C Adder 4.88 MW 4.15 MW
966801 AG1-551 C Adder 3.07 MW 2.61 MW
966811 AG1-552 C Adder 3.01 MW 2.56 MW
965291 AG1-394 C Adder 1.27 MW 1.08 MW
966621 AG1-532 C Adder 2.06 MW 1.75 MW
313853 3PONTONDP Adder 0.89 MW 0.76 MW
315131 1EDGECMA Adder 22.17 MW 18.85 MW
934521 AD1-076 C Adder 18.18 MW 15.45 MW
944011 AF1-069 C 80/20 20.64 MW 20.64 MW
959311 AF2-222 C Adder 22.69 MW 19.29 MW
960061 AF2-297 C Adder 10.62 MW 9.03 MW
960081 AF2-299 C Adder 2.75 MW 2.34 MW
938371 AE1-056 C Adder 8.59 MW 7.3 MW
939181 AE1-148 C Adder 12.7 MW 10.79 MW
941031 AE2-094 C 80/20 63.18 MW 63.18 MW
946281 AF1-292 C Adder 2.28 MW 1.94 MW
946301 AF1-294 C Adder 4.95 MW 4.21 MW
957481 AF2-042 C 80/20 80.42 MW 80.42 MW
957521 AF2-046 C Adder 20.99 MW 17.84 MW
957861 AF2-080 C Adder 11.03 MW 9.38 MW
958211 AF2-115 C Adder 3.01 MW 2.56 MW
938771 AE1-103 C 80/20 4.38 MW 4.38 MW
313526 AB2-022 C 80/20 0.56 MW 0.56 MW
314507 3THOMPSN 80/20 3.05 MW 3.05 MW
315060 1CHESTF5 Adder 83.1 MW 70.64 MW
315065 1CHESTF6 Adder 27.68 MW 23.53 MW
315073 1STONECA Adder 9.58 MW 8.15 MW
315083 1SPRUNCA 80/20 13.16 MW 13.16 MW
315084 1SPRUNCB 80/20 13.16 MW 13.16 MW
315092 1YORKTN3 Adder 183.57 MW 156.03 MW
942341 AE2-247 C 80/20 2.24 MW 2.24 MW
943461 AF1-017 C 80/20 2.02 MW 2.02 MW
315098 1CHESPKA 80/20 0.66 MW 0.66 MW
315099 1CHESPKB 80/20 1.09 MW 1.09 MW
315102 1BRUNSWICKG1 80/20 12.92 MW 12.92 MW
315103 1BRUNSWICKG2 80/20 12.92 MW 12.92 MW
315104 1BRUNSWICKG3 80/20 12.92 MW 12.92 MW
315105 1BRUNSWICKS1 80/20 26.84 MW 26.84 MW
315108 1ELIZAR1 80/20 4.82 MW 4.82 MW
315109 1ELIZAR2 80/20 4.74 MW 4.74 MW
315110 1ELIZAR3 80/20 4.88 MW 4.88 MW
315233 1SURRY 2 80/20 35.97 MW 35.97 MW
315241 1Z1-086 GT1 80/20 16.55 MW 16.55 MW
315242 1Z1-086 GT2 80/20 16.54 MW 16.54 MW
315243 1Z1-086 GT3 80/20 16.54 MW 16.54 MW
315244 1Z1-086 ST 80/20 28.8 MW 28.8 MW
315260 1GOSPORTA 80/20 3.22 MW 3.22 MW
315261 1GOSPORTB 80/20 4.11 MW 4.11 MW
315262 1GOSPORTC 80/20 3.49 MW 3.49 MW
315605 6W1-029WIND 80/20 1.16 MW 1.16 MW
315611 6Z1-036WIND 80/20 0.98 MW 0.98 MW
957601 AF2-054 C Adder 2.53 MW 2.15 MW
942001 AE2-212 C 80/20 3.15 MW 3.15 MW
957871 AF2-081 C 80/20 15.08 MW 15.08 MW
958161 AF2-110 C 80/20 2.06 MW 2.06 MW
926071 AC1-086 C Adder 30.85 MW 26.22 MW
927021 AC1-189 C Adder 12.14 MW 10.32 MW
936261 AD2-033 C Adder 17.83 MW 15.16 MW
933291 AC2-141 C 80/20 46.1 MW 46.1 MW
934621 AD1-088 C 80/20 18.55 MW 18.55 MW
939411 AE1-173 C 80/20 143.54 MW 143.54 MW
916191 Z1-068 C 80/20 0.07 MW 0.07 MW
933981 AD1-022 C Adder 12.99 MW 11.04 MW
961681 AG1-008 C Adder 20.99 MW 17.84 MW
962571 AG1-106 C Adder 3.99 MW 3.39 MW
316023 AB2-100 C2 80/20 1.42 MW 1.42 MW
316036 AC1-147 C 80/20 0.56 MW 0.56 MW
316072 AD1-144 C 80/20 0.42 MW 0.42 MW
316169 AC1-164 GEN Adder 49.05 MW 41.69 MW
316185 AD1-033 C 80/20 1.85 MW 1.85 MW
316233 AE1-074 C 80/20 3.92 MW 3.92 MW
316236 AE1-162 C 80/20 0.51 MW 0.51 MW
316240 AF1-291 C Adder 3.07 MW 2.61 MW
316246 AF1-032 C 80/20 0.43 MW 0.43 MW
316258 AE1-075 C 80/20 0.51 MW 0.51 MW
316263 AC1-034 C Adder 9.48 MW 8.06 MW
316274 AC1-208 C Adder 13.09 MW 11.13 MW
316294 AC1-161 C 80/20 7.51 MW 7.51 MW
316305 AF2-043 C 80/20 0.52 MW 0.52 MW
316313 AB2-026 C 80/20 0.56 MW 0.56 MW
316315 AB2-025 C 80/20 0.62 MW 0.62 MW
316316 AC1-027 C 80/20 0.48 MW 0.48 MW
316320 Y1-086 C 80/20 0.33 MW 0.33 MW
316321 Z2-027 C 80/20 0.55 MW 0.55 MW
316336 AC2-165 C Adder 14.08 MW 11.97 MW
316365 AB2-100 C1 80/20 1.42 MW 1.42 MW
316405 AF2-144 C 80/20 0.44 MW 0.44 MW
316017 AA1-139 ULT1 80/20 1.63 MW 1.63 MW
316018 AA1-139 ULT2 80/20 1.63 MW 1.63 MW
316083 AB2-161 C 80/20 0.82 MW 0.82 MW
316375 AC2-012 C 80/20 2.03 MW 2.03 MW
316311 AC2-079 C 80/20 8.61 MW 8.61 MW
316381 AD1-082 C 80/20 1.88 MW 1.88 MW
316349 AD2-085 C 80/20 5.17 MW 5.17 MW
316388 AE2-253 GEN 80/20 2.96 MW 2.96 MW
961611 AG1-000B C Adder 22.92 MW 19.48 MW
941591 AE2-156 C 80/20 27.04 MW 27.04 MW
944581 AF1-123 C 80/20 69.0 MW 69.0 MW
944591 AF1-124 C 80/20 69.25 MW 69.25 MW
944601 AF1-125 C 80/20 67.94 MW 67.94 MW
944631 AF1-128 C Adder 52.0 MW 44.2 MW
962491 AG1-098 C Adder 16.59 MW 14.1 MW
962561 AG1-105 C Adder 12.27 MW 10.43 MW
964241 AG1-285 C Adder 17.33 MW 14.73 MW
965281 AG1-393 C Adder 3.09 MW 2.63 MW
313764 3SOCKMAN Adder 1.04 MW 0.89 MW
934321 AD1-056 C Adder 9.05 MW 7.69 MW
934331 AD1-057 C Adder 5.05 MW 4.29 MW
934501 AD1-074 C Adder 50.05 MW 42.54 MW
934511 AD1-075 C Adder 12.51 MW 10.64 MW
935161 AD1-151 C Adder 22.81 MW 19.39 MW
938531 AE1-072 C 80/20 26.51 MW 26.51 MW
939191 AE1-149 C 80/20 15.95 MW 15.95 MW
940431 AE2-027 C Adder 18.41 MW 15.64 MW
940481 AE2-033 C 80/20 24.51 MW 24.51 MW
940541 AE2-040 C 80/20 4.36 MW 4.36 MW
940551 AE2-041 C Adder 8.5 MW 7.22 MW
940641 AE2-051 C 80/20 27.76 MW 27.76 MW
941101 AE2-104 C 80/20 5.05 MW 5.05 MW
942461 AE2-259 C Adder 13.02 MW 11.06 MW
943471 AF1-018 C Adder 8.5 MW 7.22 MW
944641 AF1-129 C Adder 144.36 MW 122.71 MW
315085 1SPRUNCC 80/20 0.24 MW 0.24 MW
315086 1SPRUNCD 80/20 0.24 MW 0.24 MW
316303 AF2-085 80/20 6.48 MW 6.48 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 65.07 MW 65.07 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 40.2 MW 40.2 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 144.5 MW 144.5 MW
NY PJM->LTFIMP_NY CLTF 3.19 MW 3.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.59 MW 2.59 MW
WEC LTFEXP_WEC->PJM CLTF 1.34 MW 1.34 MW
CPLE LTFEXP_CPLE->PJM CLTF 16.72 MW 16.72 MW
TVA LTFEXP_TVA->PJM CLTF 10.46 MW 10.46 MW
MEC LTFEXP_MEC->PJM CLTF 7.62 MW 7.62 MW
LAGN LTFEXP_LAGN->PJM CLTF 13.13 MW 13.13 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.49 MW 0.49 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.98 MW 7.98 MW

Details for 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 575_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
Contingency Name:
DVP_P1-2: LN 575_SRT-S
CONTINGENCY 'DVP_P1-2: LN 575_SRT-S'
 OPEN BRANCH FROM BUS 314911 TO BUS 314918 CKT 1                /*8LADYSMITH   500.0 - 8NO ANNA     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 118.84 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3827.26 MVA
MW Contribution: 6.76 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.83 MW 0.7 MW
961791 AG1-021 C Adder 1.62 MW 1.37 MW
961941 AG1-037 C Adder 0.45 MW 0.39 MW
962331 AG1-082 C Adder 1.82 MW 1.54 MW
963041 AG1-153 C 80/20 5.71 MW 5.71 MW
963171 AG1-166 C Adder 0.9 MW 0.76 MW
963181 AG1-167 C Adder 0.67 MW 0.57 MW
963191 AG1-168 C Adder 0.67 MW 0.57 MW
964791 AG1-342 C Adder 3.15 MW 2.68 MW
966801 AG1-551 C Adder 1.87 MW 1.59 MW
966811 AG1-552 C Adder 1.87 MW 1.59 MW
965291 AG1-394 C Adder 0.77 MW 0.66 MW
966621 AG1-532 C Adder 1.29 MW 1.1 MW
313853 3PONTONDP Adder 0.6 MW 0.51 MW
315131 1EDGECMA Adder 13.68 MW 11.63 MW
315153 1CLOVER1 80/20 12.11 MW 12.11 MW
315154 1CLOVER2 80/20 11.99 MW 11.99 MW
934521 AD1-076 C Adder 10.97 MW 9.32 MW
944011 AF1-069 C 80/20 13.44 MW 13.44 MW
959311 AF2-222 C Adder 15.02 MW 12.77 MW
960061 AF2-297 C Adder 6.81 MW 5.79 MW
960081 AF2-299 C Adder 1.72 MW 1.46 MW
938371 AE1-056 C Adder 5.79 MW 4.92 MW
939181 AE1-148 C Adder 8.16 MW 6.93 MW
941031 AE2-094 C 80/20 41.13 MW 41.13 MW
946281 AF1-292 C Adder 1.42 MW 1.21 MW
946301 AF1-294 C Adder 3.32 MW 2.82 MW
957481 AF2-042 C 80/20 52.49 MW 52.49 MW
957521 AF2-046 C Adder 12.79 MW 10.88 MW
957861 AF2-080 C Adder 6.76 MW 5.75 MW
958211 AF2-115 C Adder 2.02 MW 1.72 MW
938771 AE1-103 C Adder 2.63 MW 2.24 MW
314507 3THOMPSN Adder 1.8 MW 1.53 MW
315060 1CHESTF5 Adder 45.32 MW 38.52 MW
315065 1CHESTF6 Adder 15.98 MW 13.58 MW
315073 1STONECA Adder 5.44 MW 4.62 MW
315083 1SPRUNCA Adder 7.8 MW 6.63 MW
315084 1SPRUNCB Adder 7.8 MW 6.63 MW
315092 1YORKTN3 Adder 102.5 MW 87.13 MW
942341 AE2-247 C Adder 1.33 MW 1.13 MW
943461 AF1-017 C Adder 1.2 MW 1.02 MW
315098 1CHESPKA 80/20 0.39 MW 0.39 MW
315099 1CHESPKB 80/20 0.64 MW 0.64 MW
315102 1BRUNSWICKG1 80/20 8.39 MW 8.39 MW
315103 1BRUNSWICKG2 80/20 8.39 MW 8.39 MW
315104 1BRUNSWICKG3 80/20 8.39 MW 8.39 MW
315105 1BRUNSWICKS1 80/20 17.44 MW 17.44 MW
315108 1ELIZAR1 80/20 2.85 MW 2.85 MW
315109 1ELIZAR2 80/20 2.8 MW 2.8 MW
315110 1ELIZAR3 80/20 2.89 MW 2.89 MW
315172 1LOISA A 80/20 2.38 MW 2.38 MW
315173 1LOISA B 80/20 2.39 MW 2.39 MW
315174 1LOISA C 80/20 2.39 MW 2.39 MW
315175 1LOISA D 80/20 2.39 MW 2.39 MW
315176 1LOISA E 80/20 4.87 MW 4.87 MW
315177 1S ANNAG1 80/20 2.37 MW 2.37 MW
315178 1S ANNAS1 80/20 1.22 MW 1.22 MW
315179 1S ANNAG2 80/20 2.37 MW 2.37 MW
315180 1S ANNAS2 80/20 1.22 MW 1.22 MW
315225 1N ANNA1 80/20 92.73 MW 92.73 MW
315226 1N ANNA2 80/20 92.77 MW 92.77 MW
315241 1Z1-086 GT1 80/20 10.76 MW 10.76 MW
315242 1Z1-086 GT2 80/20 10.76 MW 10.76 MW
315243 1Z1-086 GT3 80/20 10.76 MW 10.76 MW
315244 1Z1-086 ST 80/20 18.73 MW 18.73 MW
315260 1GOSPORTA Adder 1.9 MW 1.62 MW
315261 1GOSPORTB 80/20 2.43 MW 2.43 MW
315262 1GOSPORTC Adder 2.06 MW 1.75 MW
966001 AG1-469 C Adder 1.44 MW 1.22 MW
942001 AE2-212 C Adder 1.86 MW 1.58 MW
957871 AF2-081 C 80/20 8.95 MW 8.95 MW
958161 AF2-110 C Adder 1.23 MW 1.04 MW
926071 AC1-086 C Adder 19.09 MW 16.22 MW
927021 AC1-189 C Adder 7.45 MW 6.33 MW
936261 AD2-033 C Adder 11.74 MW 9.98 MW
933291 AC2-141 C 80/20 27.13 MW 27.13 MW
934621 AD1-088 C 80/20 12.18 MW 12.18 MW
939411 AE1-173 C 80/20 90.52 MW 90.52 MW
916191 Z1-068 C 80/20 0.04 MW 0.04 MW
933981 AD1-022 C Adder 7.85 MW 6.67 MW
961681 AG1-008 C Adder 12.79 MW 10.88 MW
962571 AG1-106 C Adder 2.47 MW 2.1 MW
208900 BRIS G1 80/20 -2.56 MW -2.56 MW
208901 BRIS G2 80/20 -3.03 MW -3.03 MW
316023 AB2-100 C2 80/20 0.89 MW 0.89 MW
316036 AC1-147 C 80/20 0.33 MW 0.33 MW
316185 AD1-033 C 80/20 1.1 MW 1.1 MW
316192 AB2-158 C 80/20 3.56 MW 3.56 MW
316233 AE1-074 C 80/20 2.48 MW 2.48 MW
316240 AF1-291 C Adder 1.78 MW 1.51 MW
316258 AE1-075 C 80/20 0.35 MW 0.35 MW
316263 AC1-034 C Adder 5.85 MW 4.98 MW
316274 AC1-208 C Adder 8.08 MW 6.87 MW
316294 AC1-161 C 80/20 4.42 MW 4.42 MW
316313 AB2-026 C 80/20 0.39 MW 0.39 MW
316315 AB2-025 C 80/20 0.39 MW 0.39 MW
316316 AC1-027 C 80/20 0.28 MW 0.28 MW
316336 AC2-165 C 80/20 9.81 MW 9.81 MW
316365 AB2-100 C1 80/20 0.89 MW 0.89 MW
316405 AF2-144 C 80/20 0.3 MW 0.3 MW
316017 AA1-139 ULT1 80/20 0.97 MW 0.97 MW
316018 AA1-139 ULT2 80/20 0.97 MW 0.97 MW
316375 AC2-012 C 80/20 1.2 MW 1.2 MW
316311 AC2-079 C Adder 5.12 MW 4.35 MW
316349 AD2-085 C Adder 3.07 MW 2.61 MW
316388 AE2-253 GEN 80/20 1.75 MW 1.75 MW
961611 AG1-000B C Adder 13.21 MW 11.23 MW
941591 AE2-156 C 80/20 15.99 MW 15.99 MW
944581 AF1-123 C 80/20 40.92 MW 40.92 MW
944591 AF1-124 C 80/20 41.07 MW 41.07 MW
944601 AF1-125 C 80/20 40.3 MW 40.3 MW
944631 AF1-128 C Adder 28.36 MW 24.11 MW
962491 AG1-098 C 80/20 10.9 MW 10.9 MW
962561 AG1-105 C Adder 7.92 MW 6.73 MW
964241 AG1-285 C Adder 11.32 MW 9.62 MW
965281 AG1-393 C Adder 1.81 MW 1.54 MW
313764 3SOCKMAN Adder 0.65 MW 0.55 MW
934321 AD1-056 C Adder 5.59 MW 4.75 MW
934331 AD1-057 C Adder 3.12 MW 2.65 MW
934501 AD1-074 C Adder 30.2 MW 25.67 MW
934511 AD1-075 C Adder 7.55 MW 6.42 MW
934611 AD1-087 C 80/20 1.19 MW 1.19 MW
935161 AD1-151 C Adder 13.05 MW 11.09 MW
937481 AD2-202 C 80/20 0.35 MW 0.35 MW
938531 AE1-072 C Adder 15.74 MW 13.38 MW
939191 AE1-149 C Adder 9.49 MW 8.07 MW
940431 AE2-027 C Adder 10.7 MW 9.1 MW
940481 AE2-033 C 80/20 15.31 MW 15.31 MW
940541 AE2-040 C 80/20 2.72 MW 2.72 MW
940641 AE2-051 C 80/20 17.81 MW 17.81 MW
941101 AE2-104 C Adder 3.0 MW 2.55 MW
942461 AE2-259 C Adder 8.91 MW 7.58 MW
944641 AF1-129 C Adder 83.34 MW 70.84 MW
316303 AF2-085 80/20 4.31 MW 4.31 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 25.14 MW 25.14 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 19.84 MW 19.84 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 86.43 MW 86.43 MW
NY PJM->LTFIMP_NY CLTF 2.45 MW 2.45 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.08 MW 1.08 MW
WEC LTFEXP_WEC->PJM CLTF 0.54 MW 0.54 MW
CPLE LTFEXP_CPLE->PJM CLTF 10.27 MW 10.27 MW
TVA LTFEXP_TVA->PJM CLTF 5.5 MW 5.5 MW
MEC LTFEXP_MEC->PJM CLTF 3.37 MW 3.37 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.91 MW 6.91 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.21 MW 0.21 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 4.9 MW 4.9 MW

Details for 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 581_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line
314918 to 314934 ckt 1
Contingency Name:
DVP_P1-2: LN 581_SRT-S
CONTINGENCY 'DVP_P1-2: LN 581_SRT-S'
 OPEN BRANCH FROM BUS 314135 TO BUS 314905 CKT 2                /*3CHANCE      115.0 - 8CHANCE      500.0
 OPEN BRANCH FROM BUS 314905 TO BUS 314911 CKT 1                /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2831 BRANCH FROM BUS 314900 TO BUS 314905 CKT 1 /*8BRISTER     500.0 - 8CHANCE      500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2552 BRANCH FROM BUS 314900 TO BUS 314905 CKT 1 /*8BRISTER     500.0 - 8CHANCE      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314908 TO BUS 314911 CKT 1 /*8ELMONT      500.0 - 8LADYSMITH   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 117.57 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3786.34 MVA
MW Contribution: 7.82 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.95 MW 0.81 MW
961791 AG1-021 C Adder 1.72 MW 1.46 MW
961941 AG1-037 C Adder 0.54 MW 0.46 MW
962331 AG1-082 C Adder 2.15 MW 1.83 MW
963041 AG1-153 C Adder 5.89 MW 5.0 MW
963171 AG1-166 C Adder 0.96 MW 0.81 MW
963181 AG1-167 C Adder 0.72 MW 0.61 MW
963191 AG1-168 C Adder 0.72 MW 0.61 MW
964791 AG1-342 C Adder 3.38 MW 2.88 MW
966801 AG1-551 C Adder 2.19 MW 1.86 MW
966811 AG1-552 C Adder 2.14 MW 1.82 MW
965291 AG1-394 C Adder 0.92 MW 0.78 MW
966621 AG1-532 C Adder 1.46 MW 1.25 MW
313853 3PONTONDP Adder 0.64 MW 0.54 MW
315131 1EDGECMA Adder 15.56 MW 13.23 MW
934521 AD1-076 C Adder 13.24 MW 11.26 MW
944011 AF1-069 C 80/20 13.81 MW 13.81 MW
959311 AF2-222 C Adder 16.08 MW 13.66 MW
960081 AF2-299 C Adder 1.95 MW 1.66 MW
938371 AE1-056 C Adder 6.16 MW 5.23 MW
939181 AE1-148 C Adder 8.84 MW 7.51 MW
941031 AE2-094 C 80/20 42.26 MW 42.26 MW
946281 AF1-292 C Adder 1.62 MW 1.38 MW
946301 AF1-294 C Adder 3.54 MW 3.01 MW
957481 AF2-042 C Adder 54.68 MW 46.48 MW
957521 AF2-046 C Adder 15.19 MW 12.91 MW
957861 AF2-080 C Adder 7.82 MW 6.64 MW
958211 AF2-115 C Adder 2.15 MW 1.83 MW
938771 AE1-103 C Adder 3.23 MW 2.74 MW
314236 6NRTHEST 80/20 0.2 MW 0.2 MW
314309 6IRON208 80/20 0.49 MW 0.49 MW
314507 3THOMPSN Adder 2.28 MW 1.94 MW
315060 1CHESTF5 Adder 70.44 MW 59.87 MW
315065 1CHESTF6 80/20 22.22 MW 22.22 MW
315073 1STONECA 80/20 7.77 MW 7.77 MW
315076 1HOPPOLC 80/20 1.72 MW 1.72 MW
315077 1HOPHCF1 80/20 2.73 MW 2.73 MW
315078 1HOPHCF2 80/20 2.73 MW 2.73 MW
315079 1HOPHCF3 80/20 2.73 MW 2.73 MW
315080 1HOPHCF4 80/20 4.15 MW 4.15 MW
315083 1SPRUNCA 80/20 10.43 MW 10.43 MW
315084 1SPRUNCB 80/20 10.43 MW 10.43 MW
315092 1YORKTN3 Adder 147.47 MW 125.35 MW
934861 AD1-115 C Adder -3.06 MW -2.6 MW
936591 AD2-074 C Adder 5.86 MW 4.98 MW
942341 AE2-247 C Adder 1.68 MW 1.43 MW
943461 AF1-017 C Adder 1.52 MW 1.29 MW
943741 AF1-042 C Adder 3.06 MW 2.6 MW
961951 AG1-038 C Adder 3.39 MW 2.88 MW
966661 AG1-536 C Adder 5.64 MW 4.79 MW
966871 AG1-558 C Adder 2.56 MW 2.18 MW
966881 AG1-559 C Adder 2.45 MW 2.08 MW
315099 1CHESPKB 80/20 0.81 MW 0.81 MW
315108 1ELIZAR1 80/20 3.6 MW 3.6 MW
315109 1ELIZAR2 80/20 3.54 MW 3.54 MW
315110 1ELIZAR3 80/20 3.65 MW 3.65 MW
315225 1N ANNA1 80/20 56.71 MW 56.71 MW
315226 1N ANNA2 80/20 56.73 MW 56.73 MW
315233 1SURRY 2 80/20 27.88 MW 27.88 MW
315260 1GOSPORTA Adder 2.4 MW 2.04 MW
315261 1GOSPORTB Adder 3.07 MW 2.61 MW
315262 1GOSPORTC Adder 2.61 MW 2.22 MW
957411 AF2-035 C Adder 8.85 MW 7.52 MW
957601 AF2-054 C Adder 2.26 MW 1.92 MW
962861 AG1-135 C Adder 6.37 MW 5.41 MW
962971 AG1-146 C Adder 3.26 MW 2.77 MW
962981 AG1-147 C Adder 7.6 MW 6.46 MW
963051 AG1-154 C Adder 3.52 MW 2.99 MW
963611 AG1-210 C Adder 0.68 MW 0.58 MW
964211 AG1-282 C Adder 2.08 MW 1.77 MW
942001 AE2-212 C 80/20 2.45 MW 2.45 MW
957871 AF2-081 C Adder 11.22 MW 9.53 MW
958161 AF2-110 C Adder 1.53 MW 1.3 MW
926071 AC1-086 C Adder 21.97 MW 18.68 MW
927021 AC1-189 C Adder 8.6 MW 7.31 MW
936261 AD2-033 C Adder 12.59 MW 10.7 MW
933291 AC2-141 C 80/20 34.38 MW 34.38 MW
934621 AD1-088 C Adder 12.72 MW 10.81 MW
939411 AE1-173 C 80/20 99.75 MW 99.75 MW
927041 AC1-191 C Adder 10.29 MW 8.75 MW
933981 AD1-022 C Adder 9.45 MW 8.03 MW
961681 AG1-008 C Adder 15.19 MW 12.91 MW
962571 AG1-106 C Adder 2.84 MW 2.42 MW
316169 AC1-164 GEN Adder 43.68 MW 37.13 MW
316233 AE1-074 C 80/20 2.88 MW 2.88 MW
316240 AF1-291 C 80/20 2.44 MW 2.44 MW
316254 AC1-120 C Adder -6.38 MW -5.42 MW
316257 AC1-043 C Adder -6.12 MW -5.2 MW
316263 AC1-034 C Adder 6.66 MW 5.66 MW
316274 AC1-208 C Adder 9.29 MW 7.89 MW
316294 AC1-161 C 80/20 5.6 MW 5.6 MW
316336 AC2-165 C Adder 10.2 MW 8.67 MW
316375 AC2-012 C 80/20 1.52 MW 1.52 MW
316311 AC2-079 C Adder 6.45 MW 5.48 MW
316349 AD2-085 C Adder 3.87 MW 3.29 MW
961611 AG1-000B C Adder 17.93 MW 15.24 MW
941591 AE2-156 C 80/20 20.22 MW 20.22 MW
944581 AF1-123 C 80/20 51.3 MW 51.3 MW
944591 AF1-124 C 80/20 51.48 MW 51.48 MW
944601 AF1-125 C 80/20 50.51 MW 50.51 MW
944631 AF1-128 C Adder 44.08 MW 37.46 MW
958261 AF2-120 C Adder 6.55 MW 5.57 MW
962491 AG1-098 C Adder 11.39 MW 9.68 MW
962561 AG1-105 C Adder 8.51 MW 7.23 MW
964241 AG1-285 C Adder 12.17 MW 10.35 MW
965281 AG1-393 C 80/20 2.44 MW 2.44 MW
313764 3SOCKMAN Adder 0.74 MW 0.63 MW
934321 AD1-056 C Adder 6.39 MW 5.43 MW
934331 AD1-057 C Adder 3.56 MW 3.03 MW
934501 AD1-074 C Adder 36.47 MW 31.0 MW
934511 AD1-075 C Adder 9.12 MW 7.75 MW
935161 AD1-151 C Adder 18.17 MW 15.44 MW
938531 AE1-072 C Adder 19.71 MW 16.75 MW
939191 AE1-149 C 80/20 12.16 MW 12.16 MW
939261 AE1-157 C Adder 14.11 MW 11.99 MW
940431 AE2-027 C 80/20 14.62 MW 14.62 MW
940481 AE2-033 C Adder 17.45 MW 14.83 MW
940541 AE2-040 C Adder 3.1 MW 2.64 MW
940551 AE2-041 C Adder 7.62 MW 6.47 MW
940641 AE2-051 C 80/20 18.89 MW 18.89 MW
941101 AE2-104 C Adder 3.76 MW 3.19 MW
942461 AE2-259 C Adder 9.42 MW 8.01 MW
943471 AF1-018 C Adder 7.62 MW 6.47 MW
944641 AF1-129 C 80/20 115.89 MW 115.89 MW
315085 1SPRUNCC 80/20 0.19 MW 0.19 MW
315086 1SPRUNCD 80/20 0.19 MW 0.19 MW
316303 AF2-085 80/20 4.45 MW 4.45 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 30.69 MW 30.69 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 23.32 MW 23.32 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 96.7 MW 96.7 MW
NY PJM->LTFIMP_NY CLTF 2.7 MW 2.7 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.33 MW 1.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.65 MW 0.65 MW
CPLE LTFEXP_CPLE->PJM CLTF 11.35 MW 11.35 MW
TVA LTFEXP_TVA->PJM CLTF 6.41 MW 6.41 MW
MEC LTFEXP_MEC->PJM CLTF 4.04 MW 4.04 MW
LAGN LTFEXP_LAGN->PJM CLTF 8.02 MW 8.02 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.26 MW 0.26 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 5.41 MW 5.41 MW

Details for 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 576_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
Contingency Name:
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 113.8 %
Rating: 4070.2 MVA
Rating Type: B
MVA to Mitigate: 4632.05 MVA
MW Contribution: 11.93 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.45 MW 1.23 MW
961941 AG1-037 C Adder 0.82 MW 0.7 MW
962331 AG1-082 C Adder 3.29 MW 2.79 MW
963041 AG1-153 C Adder 8.3 MW 7.06 MW
966801 AG1-551 C Adder 3.36 MW 2.86 MW
966811 AG1-552 C Adder 3.22 MW 2.73 MW
965291 AG1-394 C Adder 1.4 MW 1.19 MW
966621 AG1-532 C Adder 2.18 MW 1.85 MW
934521 AD1-076 C Adder 20.42 MW 17.36 MW
944011 AF1-069 C Adder 19.36 MW 16.46 MW
960081 AF2-299 C Adder 2.9 MW 2.47 MW
939181 AE1-148 C Adder 12.96 MW 11.02 MW
941031 AE2-094 C Adder 59.26 MW 50.37 MW
946281 AF1-292 C Adder 2.4 MW 2.04 MW
957481 AF2-042 C Adder 77.81 MW 66.14 MW
957521 AF2-046 C Adder 23.18 MW 19.71 MW
957861 AF2-080 C Adder 11.93 MW 10.14 MW
938771 AE1-103 C Adder 4.98 MW 4.23 MW
314229 6MT RD221 80/20 0.22 MW 0.22 MW
314236 6NRTHEST 80/20 0.33 MW 0.33 MW
314309 6IRON208 80/20 0.79 MW 0.79 MW
314421 6WINCHST 80/20 0.24 MW 0.24 MW
314507 3THOMPSN Adder 3.57 MW 3.03 MW
315060 1CHESTF5 80/20 114.01 MW 114.01 MW
315061 1CHESTG7 80/20 6.93 MW 6.93 MW
315062 1CHESTS7 80/20 3.18 MW 3.18 MW
315063 1CHESTG8 80/20 6.82 MW 6.82 MW
315064 1CHESTS8 80/20 3.51 MW 3.51 MW
315065 1CHESTF6 Adder 34.49 MW 29.32 MW
315067 1DARBY 1 80/20 4.57 MW 4.57 MW
315068 1DARBY 2 80/20 4.58 MW 4.58 MW
315069 1DARBY 3 80/20 4.59 MW 4.59 MW
315070 1DARBY 4 80/20 4.6 MW 4.6 MW
315073 1STONECA 80/20 12.28 MW 12.28 MW
315076 1HOPPOLC 80/20 2.72 MW 2.72 MW
315077 1HOPHCF1 80/20 4.32 MW 4.32 MW
315078 1HOPHCF2 80/20 4.32 MW 4.32 MW
315079 1HOPHCF3 80/20 4.32 MW 4.32 MW
315080 1HOPHCF4 80/20 6.56 MW 6.56 MW
315083 1SPRUNCA Adder 15.79 MW 13.42 MW
315084 1SPRUNCB Adder 15.79 MW 13.42 MW
315092 1YORKTN3 80/20 239.44 MW 239.44 MW
936591 AD2-074 C Adder 8.71 MW 7.4 MW
942341 AE2-247 C Adder 2.6 MW 2.21 MW
943461 AF1-017 C Adder 2.35 MW 2.0 MW
943741 AF1-042 C Adder 4.56 MW 3.87 MW
961951 AG1-038 C Adder 5.04 MW 4.28 MW
966661 AG1-536 C Adder 8.21 MW 6.98 MW
966871 AG1-558 C Adder 4.08 MW 3.47 MW
315116 1SURRY 1 80/20 43.8 MW 43.8 MW
315119 1GRAVEL3 80/20 4.45 MW 4.45 MW
315120 1GRAVEL4 80/20 4.51 MW 4.51 MW
315122 1GRAVEL6 80/20 4.5 MW 4.5 MW
315233 1SURRY 2 80/20 45.83 MW 45.83 MW
315260 1GOSPORTA Adder 3.76 MW 3.2 MW
315261 1GOSPORTB Adder 4.81 MW 4.09 MW
315262 1GOSPORTC Adder 4.08 MW 3.47 MW
316075 AC2-137 C 80/20 0.69 MW 0.69 MW
316132 AB2-190 C 80/20 7.37 MW 7.37 MW
957601 AF2-054 C Adder 3.56 MW 3.03 MW
962861 AG1-135 C Adder 9.32 MW 7.92 MW
962971 AG1-146 C Adder 4.9 MW 4.16 MW
962981 AG1-147 C Adder 11.43 MW 9.72 MW
963611 AG1-210 C Adder 0.96 MW 0.81 MW
964211 AG1-282 C Adder 2.98 MW 2.54 MW
942001 AE2-212 C Adder 3.74 MW 3.18 MW
957871 AF2-081 C Adder 17.52 MW 14.89 MW
958161 AF2-110 C Adder 2.38 MW 2.03 MW
926071 AC1-086 C Adder 32.98 MW 28.04 MW
927021 AC1-189 C Adder 13.13 MW 11.16 MW
933291 AC2-141 C 80/20 54.36 MW 54.36 MW
934621 AD1-088 C Adder 18.12 MW 15.4 MW
939411 AE1-173 C Adder 145.79 MW 123.92 MW
934011 AD1-025 C 80/20 4.61 MW 4.61 MW
927041 AC1-191 C Adder 16.4 MW 13.94 MW
933981 AD1-022 C Adder 14.55 MW 12.37 MW
961681 AG1-008 C Adder 23.18 MW 19.71 MW
962571 AG1-106 C Adder 4.27 MW 3.63 MW
316004 AC1-112 C 80/20 0.6 MW 0.6 MW
316159 AE1-175 C 80/20 0.71 MW 0.71 MW
316169 AC1-164 GEN 80/20 73.92 MW 73.92 MW
316233 AE1-074 C Adder 4.09 MW 3.48 MW
316240 AF1-291 C Adder 3.78 MW 3.21 MW
316274 AC1-208 C Adder 14.05 MW 11.94 MW
316294 AC1-161 C 80/20 8.85 MW 8.85 MW
316312 AB1-027 C 80/20 0.96 MW 0.96 MW
316336 AC2-165 C Adder 13.93 MW 11.84 MW
316369 AC1-216 C 80/20 2.85 MW 2.85 MW
316382 AG1-145 C 80/20 0.64 MW 0.64 MW
316033 AB2-134 GEN 80/20 3.73 MW 3.73 MW
316311 AC2-079 C Adder 9.99 MW 8.49 MW
316349 AD2-085 C Adder 5.99 MW 5.09 MW
961611 AG1-000B C 80/20 28.36 MW 28.36 MW
941591 AE2-156 C Adder 31.66 MW 26.91 MW
944581 AF1-123 C Adder 80.24 MW 68.2 MW
944591 AF1-124 C Adder 80.52 MW 68.44 MW
944601 AF1-125 C Adder 79.0 MW 67.15 MW
944631 AF1-128 C 80/20 71.34 MW 71.34 MW
958261 AF2-120 C Adder 9.55 MW 8.12 MW
962491 AG1-098 C Adder 16.22 MW 13.79 MW
965281 AG1-393 C Adder 3.76 MW 3.19 MW
313764 3SOCKMAN Adder 1.11 MW 0.95 MW
934321 AD1-056 C Adder 9.66 MW 8.21 MW
934331 AD1-057 C Adder 5.39 MW 4.58 MW
934501 AD1-074 C Adder 56.23 MW 47.8 MW
934511 AD1-075 C Adder 14.06 MW 11.95 MW
935161 AD1-151 C 80/20 28.73 MW 28.73 MW
938531 AE1-072 C Adder 30.78 MW 26.16 MW
939191 AE1-149 C Adder 18.61 MW 15.82 MW
940431 AE2-027 C Adder 22.59 MW 19.2 MW
940481 AE2-033 C Adder 25.65 MW 21.8 MW
940541 AE2-040 C Adder 4.56 MW 3.87 MW
940551 AE2-041 C Adder 12.16 MW 10.34 MW
940641 AE2-051 C Adder 26.98 MW 22.94 MW
941101 AE2-104 C Adder 5.84 MW 4.97 MW
943471 AF1-018 C Adder 12.16 MW 10.34 MW
944641 AF1-129 C Adder 179.89 MW 152.91 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 84.24 MW 84.24 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 48.64 MW 48.64 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 156.7 MW 156.7 MW
NY PJM->LTFIMP_NY CLTF 4.13 MW 4.13 MW
LGEE LTFEXP_LGEE->PJM CLTF 3.35 MW 3.35 MW
WEC LTFEXP_WEC->PJM CLTF 1.73 MW 1.73 MW
CPLE LTFEXP_CPLE->PJM CLTF 17.61 MW 17.61 MW
TVA LTFEXP_TVA->PJM CLTF 12.4 MW 12.4 MW
MEC LTFEXP_MEC->PJM CLTF 9.56 MW 9.56 MW
LAGN LTFEXP_LAGN->PJM CLTF 15.45 MW 15.45 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.62 MW 0.62 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 8.41 MW 8.41 MW

Details for 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 573_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line
314918 to 314911 ckt 1
Contingency Name:
DVP_P1-2: LN 573_SRT-A
CONTINGENCY 'DVP_P1-2: LN 573_SRT-A'
 OPEN BRANCH FROM BUS 314918 TO BUS 314934 CKT 1   /*8NO ANNA     500.0 - 8SPOTSYL     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 111.16 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3579.93 MVA
MW Contribution: 5.98 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.74 MW 0.63 MW
961791 AG1-021 C 80/20 1.5 MW 1.5 MW
961941 AG1-037 C Adder 0.39 MW 0.34 MW
962331 AG1-082 C Adder 1.58 MW 1.34 MW
963041 AG1-153 C 80/20 5.39 MW 5.39 MW
963171 AG1-166 C 80/20 0.83 MW 0.83 MW
963181 AG1-167 C 80/20 0.63 MW 0.63 MW
963191 AG1-168 C 80/20 0.63 MW 0.63 MW
964791 AG1-342 C Adder 2.91 MW 2.48 MW
966801 AG1-551 C Adder 1.64 MW 1.39 MW
966811 AG1-552 C Adder 1.66 MW 1.41 MW
965291 AG1-394 C Adder 0.67 MW 0.57 MW
966621 AG1-532 C 80/20 1.15 MW 1.15 MW
313506 AB1-173 C OP 80/20 0.92 MW 0.92 MW
313853 3PONTONDP 80/20 0.56 MW 0.56 MW
314429 3JTRSVLE 80/20 0.34 MW 0.34 MW
314704 3LAWRENC 80/20 0.25 MW 0.25 MW
315131 1EDGECMA Adder 12.22 MW 10.39 MW
315153 1CLOVER1 80/20 11.36 MW 11.36 MW
315154 1CLOVER2 80/20 11.25 MW 11.25 MW
934521 AD1-076 C Adder 9.4 MW 7.99 MW
944011 AF1-069 C 80/20 12.72 MW 12.72 MW
959311 AF2-222 C 80/20 13.93 MW 13.93 MW
960061 AF2-297 C Adder 6.31 MW 5.37 MW
960081 AF2-299 C 80/20 1.54 MW 1.54 MW
316131 AB2-060 C 80/20 1.24 MW 1.24 MW
938371 AE1-056 C 80/20 5.4 MW 5.4 MW
939181 AE1-148 C 80/20 7.51 MW 7.51 MW
941031 AE2-094 C 80/20 38.93 MW 38.93 MW
946281 AF1-292 C 80/20 1.27 MW 1.27 MW
946301 AF1-294 C 80/20 3.09 MW 3.09 MW
957481 AF2-042 C 80/20 49.36 MW 49.36 MW
957521 AF2-046 C Adder 11.1 MW 9.44 MW
957861 AF2-080 C Adder 5.98 MW 5.08 MW
958211 AF2-115 C 80/20 1.88 MW 1.88 MW
938771 AE1-103 C Adder 2.23 MW 1.9 MW
314507 3THOMPSN Adder 1.49 MW 1.27 MW
315083 1SPRUNCA Adder 6.17 MW 5.24 MW
315084 1SPRUNCB Adder 6.17 MW 5.24 MW
942341 AE2-247 C Adder 1.11 MW 0.94 MW
943461 AF1-017 C Adder 1.0 MW 0.85 MW
315102 1BRUNSWICKG1 80/20 7.93 MW 7.93 MW
315103 1BRUNSWICKG2 80/20 7.93 MW 7.93 MW
315104 1BRUNSWICKG3 80/20 7.93 MW 7.93 MW
315105 1BRUNSWICKS1 80/20 16.47 MW 16.47 MW
315172 1LOISA A 80/20 3.08 MW 3.08 MW
315173 1LOISA B 80/20 3.1 MW 3.1 MW
315174 1LOISA C 80/20 3.1 MW 3.1 MW
315175 1LOISA D 80/20 3.1 MW 3.1 MW
315176 1LOISA E 80/20 6.31 MW 6.31 MW
315177 1S ANNAG1 80/20 3.04 MW 3.04 MW
315178 1S ANNAS1 80/20 1.56 MW 1.56 MW
315179 1S ANNAG2 80/20 3.04 MW 3.04 MW
315180 1S ANNAS2 80/20 1.56 MW 1.56 MW
315225 1N ANNA1 80/20 106.97 MW 106.97 MW
315226 1N ANNA2 80/20 107.01 MW 107.01 MW
315241 1Z1-086 GT1 80/20 10.17 MW 10.17 MW
315242 1Z1-086 GT2 80/20 10.17 MW 10.17 MW
315243 1Z1-086 GT3 80/20 10.17 MW 10.17 MW
315244 1Z1-086 ST 80/20 17.7 MW 17.7 MW
315260 1GOSPORTA Adder 1.58 MW 1.34 MW
315261 1GOSPORTB Adder 2.01 MW 1.71 MW
315262 1GOSPORTC Adder 1.71 MW 1.45 MW
966001 AG1-469 C 80/20 1.98 MW 1.98 MW
942001 AE2-212 C Adder 1.5 MW 1.27 MW
957871 AF2-081 C Adder 7.46 MW 6.34 MW
958161 AF2-110 C Adder 1.02 MW 0.87 MW
926071 AC1-086 C Adder 16.9 MW 14.37 MW
927021 AC1-189 C Adder 6.58 MW 5.59 MW
936261 AD2-033 C 80/20 10.87 MW 10.87 MW
933291 AC2-141 C Adder 22.43 MW 19.07 MW
934621 AD1-088 C 80/20 11.44 MW 11.44 MW
939411 AE1-173 C 80/20 82.31 MW 82.31 MW
933981 AD1-022 C Adder 6.75 MW 5.74 MW
961681 AG1-008 C Adder 11.1 MW 9.44 MW
962571 AG1-106 C Adder 2.19 MW 1.86 MW
208900 BRIS G1 80/20 -2.41 MW -2.41 MW
208901 BRIS G2 80/20 -2.86 MW -2.86 MW
316023 AB2-100 C2 80/20 0.79 MW 0.79 MW
316034 AC1-036 C 80/20 0.2 MW 0.2 MW
316192 AB2-158 C 80/20 4.28 MW 4.28 MW
316233 AE1-074 C 80/20 2.18 MW 2.18 MW
316237 AB2-079 C O1 80/20 0.27 MW 0.27 MW
316238 AB2-078 C O1 80/20 0.27 MW 0.27 MW
316239 AB2-077 C O1 80/20 0.27 MW 0.27 MW
316240 AF1-291 C Adder 1.38 MW 1.17 MW
316258 AE1-075 C 80/20 0.33 MW 0.33 MW
316263 AC1-034 C Adder 5.23 MW 4.45 MW
316274 AC1-208 C Adder 7.17 MW 6.09 MW
316313 AB2-026 C 80/20 0.36 MW 0.36 MW
316315 AB2-025 C 80/20 0.34 MW 0.34 MW
316336 AC2-165 C 80/20 9.25 MW 9.25 MW
316365 AB2-100 C1 80/20 0.79 MW 0.79 MW
316405 AF2-144 C 80/20 0.28 MW 0.28 MW
316181 AB2-040 GEN 80/20 1.03 MW 1.03 MW
313527 AB2-043 C 80/20 0.43 MW 0.43 MW
316087 AB2-174 C 80/20 0.96 MW 0.96 MW
316311 AC2-079 C Adder 4.26 MW 3.62 MW
316349 AD2-085 C Adder 2.55 MW 2.17 MW
961611 AG1-000B C Adder 10.32 MW 8.77 MW
941591 AE2-156 C Adder 13.25 MW 11.26 MW
944581 AF1-123 C Adder 34.12 MW 29.0 MW
944591 AF1-124 C Adder 34.24 MW 29.11 MW
944601 AF1-125 C Adder 33.6 MW 28.56 MW
962491 AG1-098 C 80/20 10.24 MW 10.24 MW
962561 AG1-105 C Adder 7.32 MW 6.22 MW
964241 AG1-285 C 80/20 10.46 MW 10.46 MW
965281 AG1-393 C Adder 1.42 MW 1.21 MW
313764 3SOCKMAN Adder 0.58 MW 0.49 MW
934321 AD1-056 C Adder 4.98 MW 4.23 MW
934331 AD1-057 C Adder 2.78 MW 2.36 MW
934501 AD1-074 C Adder 25.89 MW 22.0 MW
934511 AD1-075 C Adder 6.47 MW 5.5 MW
934611 AD1-087 C 80/20 1.12 MW 1.12 MW
935171 AD1-152 C 80/20 1.15 MW 1.15 MW
937481 AD2-202 C 80/20 0.33 MW 0.33 MW
938531 AE1-072 C Adder 13.13 MW 11.16 MW
939191 AE1-149 C Adder 7.78 MW 6.61 MW
940431 AE2-027 C Adder 8.32 MW 7.07 MW
940481 AE2-033 C 80/20 13.64 MW 13.64 MW
940541 AE2-040 C 80/20 2.43 MW 2.43 MW
940641 AE2-051 C 80/20 16.56 MW 16.56 MW
941101 AE2-104 C Adder 2.51 MW 2.13 MW
942461 AE2-259 C Adder 8.33 MW 7.08 MW
316303 AF2-085 80/20 4.06 MW 4.06 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 22.2 MW 22.2 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 17.64 MW 17.64 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 78.28 MW 78.28 MW
NY PJM->LTFIMP_NY CLTF 2.29 MW 2.29 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.95 MW 0.95 MW
WEC LTFEXP_WEC->PJM CLTF 0.47 MW 0.47 MW
CPLE LTFEXP_CPLE->PJM CLTF 9.36 MW 9.36 MW
TVA LTFEXP_TVA->PJM CLTF 4.89 MW 4.89 MW
MEC LTFEXP_MEC->PJM CLTF 2.98 MW 2.98 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.17 MW 6.17 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.19 MW 0.19 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 4.46 MW 4.46 MW

Details for 6SAPONY-6CARSON 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 108.58 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 736.88 MVA
MW Contribution: 6.82 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.9 MW 0.9 MW
961791 AG1-021 C 80/20 0.59 MW 0.59 MW
961941 AG1-037 C 80/20 0.48 MW 0.48 MW
962331 AG1-082 C 80/20 1.92 MW 1.92 MW
963171 AG1-166 C 80/20 0.33 MW 0.33 MW
963181 AG1-167 C 80/20 0.24 MW 0.24 MW
963191 AG1-168 C 80/20 0.24 MW 0.24 MW
964791 AG1-342 C 80/20 1.31 MW 1.31 MW
966801 AG1-551 C 80/20 1.62 MW 1.62 MW
966811 AG1-552 C 80/20 3.08 MW 3.08 MW
965291 AG1-394 C 80/20 0.78 MW 0.78 MW
966621 AG1-532 C 80/20 3.26 MW 3.26 MW
313506 AB1-173 C OP 80/20 2.19 MW 2.19 MW
313853 3PONTONDP 80/20 0.22 MW 0.22 MW
314429 3JTRSVLE 80/20 0.14 MW 0.14 MW
314704 3LAWRENC 80/20 0.56 MW 0.56 MW
315126 1ROARAP2 80/20 2.06 MW 2.06 MW
315128 1ROARAP4 80/20 1.95 MW 1.95 MW
315131 1EDGECMA 80/20 16.35 MW 16.35 MW
315136 1ROSEMG1 80/20 3.91 MW 3.91 MW
315137 1ROSEMS1 80/20 2.42 MW 2.42 MW
315138 1ROSEMG2 80/20 1.83 MW 1.83 MW
315139 1GASTONA 80/20 6.13 MW 6.13 MW
315158 1KERR 1 80/20 0.23 MW 0.23 MW
315159 1KERR 2 80/20 0.64 MW 0.64 MW
315160 1KERR 3 80/20 0.64 MW 0.64 MW
315161 1KERR 4 80/20 0.64 MW 0.64 MW
315162 1KERR 5 80/20 0.64 MW 0.64 MW
934521 AD1-076 C 80/20 7.21 MW 7.21 MW
943171 AE2-346 C 80/20 0.21 MW 0.21 MW
959311 AF2-222 C 80/20 7.01 MW 7.01 MW
960081 AF2-299 C 80/20 4.35 MW 4.35 MW
315163 1KERR 6 80/20 0.64 MW 0.64 MW
315164 1KERR 7 80/20 0.64 MW 0.64 MW
315601 1CONETOE2SOL 80/20 1.16 MW 1.16 MW
315606 3AA2-053SOLA 80/20 2.1 MW 2.1 MW
316129 AC1-054 C 80/20 1.19 MW 1.19 MW
316131 AB2-060 C 80/20 0.82 MW 0.82 MW
316140 AB2-099 C 80/20 0.09 MW 0.09 MW
939181 AE1-148 C 80/20 5.08 MW 5.08 MW
940491 AE2-034 C 80/20 0.54 MW 0.54 MW
946281 AF1-292 C 80/20 3.6 MW 3.6 MW
946301 AF1-294 C 80/20 1.21 MW 1.21 MW
957521 AF2-046 C 80/20 13.23 MW 13.23 MW
957861 AF2-080 C 80/20 6.82 MW 6.82 MW
958211 AF2-115 C 80/20 0.73 MW 0.73 MW
938771 AE1-103 C 80/20 1.28 MW 1.28 MW
315115 1S HAMPT1 80/20 0.96 MW 0.96 MW
315141 1GASTONB 80/20 6.13 MW 6.13 MW
315292 1DOMTR78 80/20 0.87 MW 0.87 MW
315607 3AA1-063SOLA 80/20 1.77 MW 1.77 MW
315608 3AA2-088SOLA 80/20 0.93 MW 0.93 MW
315611 6Z1-036WIND 80/20 0.2 MW 0.2 MW
926071 AC1-086 C 80/20 42.35 MW 42.35 MW
927021 AC1-189 C 80/20 7.5 MW 7.5 MW
936261 AD2-033 C 80/20 5.99 MW 5.99 MW
933981 AD1-022 C 80/20 5.79 MW 5.79 MW
961681 AG1-008 C 80/20 13.23 MW 13.23 MW
962571 AG1-106 C 80/20 5.48 MW 5.48 MW
316005 AA1-067 C 80/20 0.22 MW 0.22 MW
316011 AB1-132 C OP 80/20 4.68 MW 4.68 MW
316023 AB2-100 C2 80/20 2.77 MW 2.77 MW
316034 AC1-036 C 80/20 0.1 MW 0.1 MW
316049 AB1-081 C OP 80/20 1.47 MW 1.47 MW
316210 AC1-098 C 80/20 1.08 MW 1.08 MW
316212 AC1-099 C 80/20 0.36 MW 0.36 MW
316237 AB2-079 C O1 80/20 0.18 MW 0.18 MW
316238 AB2-078 C O1 80/20 0.18 MW 0.18 MW
316239 AB2-077 C O1 80/20 0.18 MW 0.18 MW
316263 AC1-034 C 80/20 6.88 MW 6.88 MW
316274 AC1-208 C 80/20 11.02 MW 11.02 MW
316315 AB2-025 C 80/20 1.66 MW 1.66 MW
316317 KELFORD C 80/20 0.37 MW 0.37 MW
316318 V4-068 C 80/20 0.07 MW 0.07 MW
316319 Z2-044 C 80/20 0.23 MW 0.23 MW
316365 AB2-100 C1 80/20 2.77 MW 2.77 MW
315602 1HOLLOMANSOL 80/20 1.59 MW 1.59 MW
316327 AA2-057 C 80/20 1.46 MW 1.46 MW
315614 AA2-178 C 80/20 0.73 MW 0.73 MW
316181 AB2-040 GEN 80/20 2.46 MW 2.46 MW
313527 AB2-043 C 80/20 0.29 MW 0.29 MW
316359 AB2-059 C OP 80/20 1.73 MW 1.73 MW
316174 AB2-169_C 80/20 0.72 MW 0.72 MW
316087 AB2-174 C 80/20 2.42 MW 2.42 MW
962561 AG1-105 C 80/20 3.57 MW 3.57 MW
964241 AG1-285 C 80/20 6.49 MW 6.49 MW
313764 3SOCKMAN 80/20 1.21 MW 1.21 MW
932631 AC2-084 C 80/20 1.15 MW 1.15 MW
934321 AD1-056 C 80/20 9.13 MW 9.13 MW
934331 AD1-057 C 80/20 5.1 MW 5.1 MW
934501 AD1-074 C 80/20 19.85 MW 19.85 MW
934511 AD1-075 C 80/20 4.96 MW 4.96 MW
940481 AE2-033 C 80/20 63.69 MW 63.69 MW
940541 AE2-040 C 80/20 11.75 MW 11.75 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.07 MW 12.07 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.77 MW 7.77 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 32.62 MW 32.62 MW
NY PJM->LTFIMP_NY CLTF 0.37 MW 0.37 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.47 MW 0.47 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.32 MW 4.32 MW
TVA LTFEXP_TVA->PJM CLTF 2.04 MW 2.04 MW
MEC LTFEXP_MEC->PJM CLTF 1.43 MW 1.43 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.6 MW 2.6 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.06 MW 2.06 MW

Details for 6FARMVIL-6BUCKING 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6FARMVIL-6BUCKING 230.0 kV Ckt 1 line
314692 to 314677 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 107.79 %
Rating: 559.3 MVA
Rating Type: B
MVA to Mitigate: 602.85 MVA
MW Contribution: 2.74 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.34 MW 0.34 MW
961791 AG1-021 C 80/20 3.55 MW 3.55 MW
961941 AG1-037 C 80/20 0.18 MW 0.18 MW
962331 AG1-082 C 80/20 0.72 MW 0.72 MW
963041 AG1-153 C 80/20 2.25 MW 2.25 MW
963171 AG1-166 C 80/20 1.97 MW 1.97 MW
963181 AG1-167 C 80/20 1.48 MW 1.48 MW
963191 AG1-168 C 80/20 1.48 MW 1.48 MW
964791 AG1-342 C 80/20 3.21 MW 3.21 MW
966811 AG1-552 C 80/20 0.94 MW 0.94 MW
965291 AG1-394 C 80/20 0.32 MW 0.32 MW
966621 AG1-532 C 80/20 0.67 MW 0.67 MW
313506 AB1-173 C OP 80/20 0.53 MW 0.53 MW
313853 3PONTONDP 80/20 1.31 MW 1.31 MW
314429 3JTRSVLE 80/20 0.81 MW 0.81 MW
314704 3LAWRENC 80/20 0.2 MW 0.2 MW
315126 1ROARAP2 80/20 0.63 MW 0.63 MW
315128 1ROARAP4 80/20 0.6 MW 0.6 MW
315131 1EDGECMA 80/20 5.86 MW 5.86 MW
315136 1ROSEMG1 80/20 0.76 MW 0.76 MW
315137 1ROSEMS1 80/20 0.47 MW 0.47 MW
315138 1ROSEMG2 80/20 0.36 MW 0.36 MW
315139 1GASTONA 80/20 1.14 MW 1.14 MW
315153 1CLOVER1 80/20 10.06 MW 10.06 MW
315154 1CLOVER2 80/20 9.97 MW 9.97 MW
315158 1KERR 1 80/20 0.34 MW 0.34 MW
315159 1KERR 2 80/20 0.94 MW 0.94 MW
315160 1KERR 3 80/20 0.94 MW 0.94 MW
315161 1KERR 4 80/20 0.94 MW 0.94 MW
315162 1KERR 5 80/20 0.94 MW 0.94 MW
942751 AE2-291 C 80/20 4.21 MW 4.21 MW
943171 AE2-346 C 80/20 0.08 MW 0.08 MW
944011 AF1-069 C 80/20 4.7 MW 4.7 MW
959311 AF2-222 C 80/20 27.3 MW 27.3 MW
960061 AF2-297 C 80/20 5.79 MW 5.79 MW
960081 AF2-299 C 80/20 0.9 MW 0.9 MW
315163 1KERR 6 80/20 0.94 MW 0.94 MW
315164 1KERR 7 80/20 0.94 MW 0.94 MW
315266 1PLYWOOD A 80/20 0.95 MW 0.95 MW
315601 1CONETOE2SOL 80/20 0.45 MW 0.45 MW
315606 3AA2-053SOLA 80/20 0.66 MW 0.66 MW
316118 AC1-105 C 80/20 0.76 MW 0.76 MW
316129 AC1-054 C 80/20 0.8 MW 0.8 MW
316131 AB2-060 C 80/20 1.71 MW 1.71 MW
316140 AB2-099 C 80/20 0.03 MW 0.03 MW
938371 AE1-056 C 80/20 13.65 MW 13.65 MW
939181 AE1-148 C 80/20 7.93 MW 7.93 MW
941011 AE2-092 C Adder -11.38 MW -9.67 MW
941031 AE2-094 C 80/20 14.38 MW 14.38 MW
946281 AF1-292 C 80/20 0.74 MW 0.74 MW
946301 AF1-294 C 80/20 7.3 MW 7.3 MW
957481 AF2-042 C 80/20 40.8 MW 40.8 MW
957521 AF2-046 C 80/20 5.13 MW 5.13 MW
957861 AF2-080 C 80/20 2.74 MW 2.74 MW
958211 AF2-115 C 80/20 4.44 MW 4.44 MW
315102 1BRUNSWICKG1 80/20 3.31 MW 3.31 MW
315103 1BRUNSWICKG2 80/20 3.31 MW 3.31 MW
315104 1BRUNSWICKG3 80/20 3.31 MW 3.31 MW
315105 1BRUNSWICKS1 80/20 6.89 MW 6.89 MW
315115 1S HAMPT1 80/20 0.49 MW 0.49 MW
315141 1GASTONB 80/20 1.14 MW 1.14 MW
315241 1Z1-086 GT1 80/20 4.1 MW 4.1 MW
315242 1Z1-086 GT2 80/20 4.1 MW 4.1 MW
315243 1Z1-086 GT3 80/20 4.1 MW 4.1 MW
315244 1Z1-086 ST 80/20 7.13 MW 7.13 MW
315607 3AA1-063SOLA 80/20 0.59 MW 0.59 MW
315608 3AA2-088SOLA 80/20 0.39 MW 0.39 MW
926071 AC1-086 C 80/20 7.87 MW 7.87 MW
927021 AC1-189 C 80/20 3.02 MW 3.02 MW
936261 AD2-033 C 80/20 19.43 MW 19.43 MW
934621 AD1-088 C 80/20 12.63 MW 12.63 MW
939411 AE1-173 C 80/20 27.14 MW 27.14 MW
961681 AG1-008 C 80/20 5.13 MW 5.13 MW
962571 AG1-106 C 80/20 1.02 MW 1.02 MW
316003 AC1-222 C 80/20 0.7 MW 0.7 MW
316011 AB1-132 C OP 80/20 0.87 MW 0.87 MW
316023 AB2-100 C2 80/20 0.35 MW 0.35 MW
316034 AC1-036 C 80/20 0.37 MW 0.37 MW
316049 AB1-081 C OP 80/20 0.54 MW 0.54 MW
316210 AC1-098 C 80/20 0.37 MW 0.37 MW
316212 AC1-099 C 80/20 0.12 MW 0.12 MW
316222 AC1-221 C 80/20 0.86 MW 0.86 MW
316237 AB2-079 C O1 80/20 0.36 MW 0.36 MW
316238 AB2-078 C O1 80/20 0.36 MW 0.36 MW
316239 AB2-077 C O1 80/20 0.36 MW 0.36 MW
316248 AF1-058 C 80/20 0.24 MW 0.24 MW
316263 AC1-034 C 80/20 2.54 MW 2.54 MW
316274 AC1-208 C 80/20 3.7 MW 3.7 MW
316283 AC2-100 C 80/20 0.68 MW 0.68 MW
316315 AB2-025 C 80/20 0.12 MW 0.12 MW
316317 KELFORD C 80/20 0.13 MW 0.13 MW
316318 V4-068 C 80/20 0.03 MW 0.03 MW
316319 Z2-044 C 80/20 0.08 MW 0.08 MW
316336 AC2-165 C Adder -7.12 MW -6.05 MW
316365 AB2-100 C1 80/20 0.35 MW 0.35 MW
316327 AA2-057 C 80/20 0.51 MW 0.51 MW
316181 AB2-040 GEN 80/20 0.59 MW 0.59 MW
313527 AB2-043 C 80/20 0.58 MW 0.58 MW
316359 AB2-059 C OP 80/20 0.64 MW 0.64 MW
316087 AB2-174 C 80/20 0.56 MW 0.56 MW
316123 AC1-075 C 80/20 0.49 MW 0.49 MW
316205 AC1-080 C 80/20 0.17 MW 0.17 MW
962491 AG1-098 C 80/20 11.94 MW 11.94 MW
962561 AG1-105 C 80/20 8.35 MW 8.35 MW
964241 AG1-285 C 80/20 16.08 MW 16.08 MW
313764 3SOCKMAN 80/20 0.33 MW 0.33 MW
932631 AC2-084 C 80/20 0.4 MW 0.4 MW
934321 AD1-056 C 80/20 2.36 MW 2.36 MW
934331 AD1-057 C 80/20 1.31 MW 1.31 MW
934611 AD1-087 C 80/20 0.99 MW 0.99 MW
935171 AD1-152 C 80/20 1.01 MW 1.01 MW
937481 AD2-202 C 80/20 0.29 MW 0.29 MW
938821 AE1-108 C Adder -12.57 MW -10.69 MW
940481 AE2-033 C 80/20 5.08 MW 5.08 MW
940641 AE2-051 C 80/20 5.44 MW 5.44 MW
942461 AE2-259 C 80/20 24.89 MW 24.89 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.4 MW 8.4 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.16 MW 7.16 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 37.0 MW 37.0 MW
NY PJM->LTFIMP_NY CLTF 0.4 MW 0.4 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.33 MW 0.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.65 MW 4.65 MW
TVA LTFEXP_TVA->PJM CLTF 2.01 MW 2.01 MW
MEC LTFEXP_MEC->PJM CLTF 1.16 MW 1.16 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.59 MW 2.59 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.21 MW 2.21 MW

Details for 6BUCKING-6BREMO 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6BUCKING-6BREMO 230.0 kV Ckt 1 line
314677 to 314747 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 106.88 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 610.86 MVA
MW Contribution: 2.74 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.34 MW 0.34 MW
961791 AG1-021 C 80/20 3.55 MW 3.55 MW
961941 AG1-037 C 80/20 0.18 MW 0.18 MW
962331 AG1-082 C 80/20 0.72 MW 0.72 MW
963041 AG1-153 C 80/20 2.25 MW 2.25 MW
963171 AG1-166 C 80/20 1.97 MW 1.97 MW
963181 AG1-167 C 80/20 1.48 MW 1.48 MW
963191 AG1-168 C 80/20 1.48 MW 1.48 MW
964791 AG1-342 C 80/20 3.2 MW 3.2 MW
966811 AG1-552 C 80/20 0.94 MW 0.94 MW
965291 AG1-394 C 80/20 0.31 MW 0.31 MW
966621 AG1-532 C 80/20 0.67 MW 0.67 MW
313506 AB1-173 C OP 80/20 0.53 MW 0.53 MW
313853 3PONTONDP 80/20 1.31 MW 1.31 MW
314429 3JTRSVLE 80/20 0.81 MW 0.81 MW
314704 3LAWRENC 80/20 0.2 MW 0.2 MW
315126 1ROARAP2 80/20 0.63 MW 0.63 MW
315128 1ROARAP4 80/20 0.6 MW 0.6 MW
315131 1EDGECMA 80/20 5.85 MW 5.85 MW
315136 1ROSEMG1 80/20 0.76 MW 0.76 MW
315137 1ROSEMS1 80/20 0.47 MW 0.47 MW
315138 1ROSEMG2 80/20 0.36 MW 0.36 MW
315139 1GASTONA 80/20 1.14 MW 1.14 MW
315153 1CLOVER1 80/20 10.06 MW 10.06 MW
315154 1CLOVER2 80/20 9.97 MW 9.97 MW
315158 1KERR 1 80/20 0.34 MW 0.34 MW
315159 1KERR 2 80/20 0.94 MW 0.94 MW
315160 1KERR 3 80/20 0.94 MW 0.94 MW
315161 1KERR 4 80/20 0.94 MW 0.94 MW
315162 1KERR 5 80/20 0.94 MW 0.94 MW
942751 AE2-291 C 80/20 4.21 MW 4.21 MW
943171 AE2-346 C 80/20 0.08 MW 0.08 MW
944011 AF1-069 C 80/20 4.7 MW 4.7 MW
959311 AF2-222 C 80/20 27.29 MW 27.29 MW
960061 AF2-297 C 80/20 5.79 MW 5.79 MW
960081 AF2-299 C 80/20 0.9 MW 0.9 MW
315163 1KERR 6 80/20 0.94 MW 0.94 MW
315164 1KERR 7 80/20 0.94 MW 0.94 MW
315266 1PLYWOOD A 80/20 0.95 MW 0.95 MW
315601 1CONETOE2SOL 80/20 0.45 MW 0.45 MW
315606 3AA2-053SOLA 80/20 0.66 MW 0.66 MW
316118 AC1-105 C 80/20 0.76 MW 0.76 MW
316129 AC1-054 C 80/20 0.8 MW 0.8 MW
316131 AB2-060 C 80/20 1.71 MW 1.71 MW
316140 AB2-099 C 80/20 0.03 MW 0.03 MW
938371 AE1-056 C 80/20 13.65 MW 13.65 MW
939181 AE1-148 C 80/20 7.92 MW 7.92 MW
941011 AE2-092 C Adder -11.38 MW -9.68 MW
941031 AE2-094 C 80/20 14.37 MW 14.37 MW
946281 AF1-292 C 80/20 0.74 MW 0.74 MW
946301 AF1-294 C 80/20 7.3 MW 7.3 MW
957481 AF2-042 C 80/20 40.78 MW 40.78 MW
957521 AF2-046 C 80/20 5.13 MW 5.13 MW
957861 AF2-080 C 80/20 2.74 MW 2.74 MW
958211 AF2-115 C 80/20 4.44 MW 4.44 MW
315102 1BRUNSWICKG1 80/20 3.31 MW 3.31 MW
315103 1BRUNSWICKG2 80/20 3.31 MW 3.31 MW
315104 1BRUNSWICKG3 80/20 3.31 MW 3.31 MW
315105 1BRUNSWICKS1 80/20 6.88 MW 6.88 MW
315115 1S HAMPT1 80/20 0.49 MW 0.49 MW
315141 1GASTONB 80/20 1.14 MW 1.14 MW
315241 1Z1-086 GT1 80/20 4.09 MW 4.09 MW
315242 1Z1-086 GT2 80/20 4.09 MW 4.09 MW
315243 1Z1-086 GT3 80/20 4.09 MW 4.09 MW
315244 1Z1-086 ST 80/20 7.12 MW 7.12 MW
315607 3AA1-063SOLA 80/20 0.59 MW 0.59 MW
315608 3AA2-088SOLA 80/20 0.38 MW 0.38 MW
926071 AC1-086 C 80/20 7.86 MW 7.86 MW
927021 AC1-189 C 80/20 3.01 MW 3.01 MW
936261 AD2-033 C 80/20 19.43 MW 19.43 MW
934621 AD1-088 C 80/20 12.62 MW 12.62 MW
939411 AE1-173 C 80/20 27.12 MW 27.12 MW
961681 AG1-008 C 80/20 5.13 MW 5.13 MW
962571 AG1-106 C 80/20 1.02 MW 1.02 MW
316003 AC1-222 C 80/20 0.7 MW 0.7 MW
316011 AB1-132 C OP 80/20 0.87 MW 0.87 MW
316023 AB2-100 C2 80/20 0.35 MW 0.35 MW
316034 AC1-036 C 80/20 0.37 MW 0.37 MW
316049 AB1-081 C OP 80/20 0.54 MW 0.54 MW
316210 AC1-098 C 80/20 0.37 MW 0.37 MW
316212 AC1-099 C 80/20 0.12 MW 0.12 MW
316222 AC1-221 C 80/20 0.86 MW 0.86 MW
316237 AB2-079 C O1 80/20 0.36 MW 0.36 MW
316238 AB2-078 C O1 80/20 0.36 MW 0.36 MW
316239 AB2-077 C O1 80/20 0.36 MW 0.36 MW
316248 AF1-058 C 80/20 0.24 MW 0.24 MW
316263 AC1-034 C 80/20 2.54 MW 2.54 MW
316274 AC1-208 C 80/20 3.7 MW 3.7 MW
316283 AC2-100 C 80/20 0.68 MW 0.68 MW
316315 AB2-025 C 80/20 0.12 MW 0.12 MW
316317 KELFORD C 80/20 0.13 MW 0.13 MW
316318 V4-068 C 80/20 0.03 MW 0.03 MW
316319 Z2-044 C 80/20 0.08 MW 0.08 MW
316322 AB2-045 C 80/20 1.15 MW 1.15 MW
316336 AC2-165 C Adder -7.13 MW -6.06 MW
316365 AB2-100 C1 80/20 0.35 MW 0.35 MW
316327 AA2-057 C 80/20 0.51 MW 0.51 MW
316181 AB2-040 GEN 80/20 0.59 MW 0.59 MW
313527 AB2-043 C 80/20 0.58 MW 0.58 MW
316359 AB2-059 C OP 80/20 0.64 MW 0.64 MW
316087 AB2-174 C 80/20 0.56 MW 0.56 MW
316123 AC1-075 C 80/20 0.49 MW 0.49 MW
316205 AC1-080 C 80/20 0.17 MW 0.17 MW
962491 AG1-098 C 80/20 11.94 MW 11.94 MW
962561 AG1-105 C 80/20 8.35 MW 8.35 MW
964241 AG1-285 C 80/20 16.07 MW 16.07 MW
313764 3SOCKMAN 80/20 0.33 MW 0.33 MW
932631 AC2-084 C 80/20 0.4 MW 0.4 MW
934321 AD1-056 C 80/20 2.35 MW 2.35 MW
934331 AD1-057 C 80/20 1.31 MW 1.31 MW
934611 AD1-087 C 80/20 0.99 MW 0.99 MW
935171 AD1-152 C 80/20 1.01 MW 1.01 MW
937481 AD2-202 C 80/20 0.29 MW 0.29 MW
938821 AE1-108 C Adder -12.58 MW -10.69 MW
940481 AE2-033 C 80/20 5.07 MW 5.07 MW
940641 AE2-051 C 80/20 5.44 MW 5.44 MW
942461 AE2-259 C 80/20 24.89 MW 24.89 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.3 MW 8.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.12 MW 7.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 36.94 MW 36.94 MW
NY PJM->LTFIMP_NY CLTF 0.4 MW 0.4 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.33 MW 0.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.17 MW 0.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.64 MW 4.64 MW
TVA LTFEXP_TVA->PJM CLTF 2.0 MW 2.0 MW
MEC LTFEXP_MEC->PJM CLTF 1.15 MW 1.15 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.58 MW 2.58 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.21 MW 2.21 MW

Details for AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
Base Case
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 105.77 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 717.82 MVA
MW Contribution: 6.82 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.91 MW 0.91 MW
961791 AG1-021 C 80/20 0.59 MW 0.59 MW
961941 AG1-037 C 80/20 0.48 MW 0.48 MW
962331 AG1-082 C 80/20 1.92 MW 1.92 MW
963171 AG1-166 C 80/20 0.33 MW 0.33 MW
963181 AG1-167 C 80/20 0.24 MW 0.24 MW
963191 AG1-168 C 80/20 0.24 MW 0.24 MW
964791 AG1-342 C 80/20 1.31 MW 1.31 MW
966801 AG1-551 C 80/20 1.62 MW 1.62 MW
966811 AG1-552 C 80/20 3.08 MW 3.08 MW
965291 AG1-394 C 80/20 0.78 MW 0.78 MW
966621 AG1-532 C 80/20 3.26 MW 3.26 MW
313506 AB1-173 C OP 80/20 2.19 MW 2.19 MW
313853 3PONTONDP 80/20 0.22 MW 0.22 MW
314429 3JTRSVLE 80/20 0.14 MW 0.14 MW
314704 3LAWRENC 80/20 0.56 MW 0.56 MW
315126 1ROARAP2 80/20 2.06 MW 2.06 MW
315128 1ROARAP4 80/20 1.95 MW 1.95 MW
315131 1EDGECMA 80/20 16.36 MW 16.36 MW
315136 1ROSEMG1 80/20 3.91 MW 3.91 MW
315137 1ROSEMS1 80/20 2.42 MW 2.42 MW
315138 1ROSEMG2 80/20 1.83 MW 1.83 MW
315139 1GASTONA 80/20 6.13 MW 6.13 MW
315158 1KERR 1 80/20 0.23 MW 0.23 MW
315159 1KERR 2 80/20 0.65 MW 0.65 MW
315160 1KERR 3 80/20 0.65 MW 0.65 MW
315161 1KERR 4 80/20 0.65 MW 0.65 MW
315162 1KERR 5 80/20 0.65 MW 0.65 MW
934521 AD1-076 C 80/20 7.21 MW 7.21 MW
943171 AE2-346 C 80/20 0.21 MW 0.21 MW
959311 AF2-222 C 80/20 7.02 MW 7.02 MW
960081 AF2-299 C 80/20 4.35 MW 4.35 MW
315163 1KERR 6 80/20 0.65 MW 0.65 MW
315164 1KERR 7 80/20 0.65 MW 0.65 MW
315601 1CONETOE2SOL 80/20 1.16 MW 1.16 MW
315606 3AA2-053SOLA 80/20 2.1 MW 2.1 MW
316129 AC1-054 C 80/20 1.19 MW 1.19 MW
316131 AB2-060 C 80/20 0.82 MW 0.82 MW
316140 AB2-099 C 80/20 0.09 MW 0.09 MW
939181 AE1-148 C 80/20 5.09 MW 5.09 MW
940491 AE2-034 C 80/20 0.54 MW 0.54 MW
946281 AF1-292 C 80/20 3.6 MW 3.6 MW
946301 AF1-294 C 80/20 1.21 MW 1.21 MW
957521 AF2-046 C 80/20 13.24 MW 13.24 MW
957861 AF2-080 C 80/20 6.82 MW 6.82 MW
958211 AF2-115 C 80/20 0.73 MW 0.73 MW
938771 AE1-103 C 80/20 1.28 MW 1.28 MW
315115 1S HAMPT1 80/20 0.96 MW 0.96 MW
315141 1GASTONB 80/20 6.13 MW 6.13 MW
315292 1DOMTR78 80/20 0.87 MW 0.87 MW
315607 3AA1-063SOLA 80/20 1.77 MW 1.77 MW
315608 3AA2-088SOLA 80/20 0.93 MW 0.93 MW
315611 6Z1-036WIND 80/20 0.2 MW 0.2 MW
926071 AC1-086 C 80/20 42.36 MW 42.36 MW
927021 AC1-189 C 80/20 7.51 MW 7.51 MW
936261 AD2-033 C 80/20 5.99 MW 5.99 MW
933981 AD1-022 C 80/20 5.8 MW 5.8 MW
961681 AG1-008 C 80/20 13.24 MW 13.24 MW
962571 AG1-106 C 80/20 5.48 MW 5.48 MW
316005 AA1-067 C 80/20 0.22 MW 0.22 MW
316011 AB1-132 C OP 80/20 4.68 MW 4.68 MW
316023 AB2-100 C2 80/20 2.77 MW 2.77 MW
316034 AC1-036 C 80/20 0.1 MW 0.1 MW
316049 AB1-081 C OP 80/20 1.47 MW 1.47 MW
316210 AC1-098 C 80/20 1.08 MW 1.08 MW
316212 AC1-099 C 80/20 0.36 MW 0.36 MW
316237 AB2-079 C O1 80/20 0.18 MW 0.18 MW
316238 AB2-078 C O1 80/20 0.18 MW 0.18 MW
316239 AB2-077 C O1 80/20 0.18 MW 0.18 MW
316263 AC1-034 C 80/20 6.89 MW 6.89 MW
316274 AC1-208 C 80/20 11.03 MW 11.03 MW
316317 KELFORD C 80/20 0.37 MW 0.37 MW
316318 V4-068 C 80/20 0.07 MW 0.07 MW
316319 Z2-044 C 80/20 0.23 MW 0.23 MW
316365 AB2-100 C1 80/20 2.77 MW 2.77 MW
315602 1HOLLOMANSOL 80/20 1.59 MW 1.59 MW
316327 AA2-057 C 80/20 1.46 MW 1.46 MW
315614 AA2-178 C 80/20 0.73 MW 0.73 MW
316181 AB2-040 GEN 80/20 2.46 MW 2.46 MW
313527 AB2-043 C 80/20 0.29 MW 0.29 MW
316359 AB2-059 C OP 80/20 1.73 MW 1.73 MW
316174 AB2-169_C 80/20 0.72 MW 0.72 MW
316087 AB2-174 C 80/20 2.42 MW 2.42 MW
962561 AG1-105 C 80/20 3.57 MW 3.57 MW
964241 AG1-285 C 80/20 6.5 MW 6.5 MW
313764 3SOCKMAN 80/20 1.21 MW 1.21 MW
932631 AC2-084 C 80/20 1.15 MW 1.15 MW
934321 AD1-056 C 80/20 9.14 MW 9.14 MW
934331 AD1-057 C 80/20 5.1 MW 5.1 MW
934501 AD1-074 C 80/20 19.87 MW 19.87 MW
934511 AD1-075 C 80/20 4.97 MW 4.97 MW
940481 AE2-033 C 80/20 63.7 MW 63.7 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.19 MW 12.19 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 7.81 MW 7.81 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 32.69 MW 32.69 MW
NY PJM->LTFIMP_NY CLTF 0.37 MW 0.37 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.47 MW 0.47 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.33 MW 4.33 MW
TVA LTFEXP_TVA->PJM CLTF 2.05 MW 2.05 MW
MEC LTFEXP_MEC->PJM CLTF 1.44 MW 1.44 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.61 MW 2.61 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.06 MW 2.06 MW

Details for 6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line
314282 to 314285 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 104.68 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1030.28 MVA
MW Contribution: 3.77 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.48 MW 0.48 MW
961791 AG1-021 C Adder 0.64 MW 0.54 MW
961941 AG1-037 C 80/20 0.24 MW 0.24 MW
962331 AG1-082 C 80/20 0.95 MW 0.95 MW
963041 AG1-153 C 80/20 3.04 MW 3.04 MW
963171 AG1-166 C Adder 0.36 MW 0.3 MW
963181 AG1-167 C Adder 0.27 MW 0.23 MW
963191 AG1-168 C Adder 0.27 MW 0.23 MW
964791 AG1-342 C 80/20 1.6 MW 1.6 MW
966801 AG1-551 C 80/20 0.96 MW 0.96 MW
966811 AG1-552 C 80/20 1.22 MW 1.22 MW
965291 AG1-394 C 80/20 0.39 MW 0.39 MW
966621 AG1-532 C 80/20 1.04 MW 1.04 MW
313506 AB1-173 C OP 80/20 0.76 MW 0.76 MW
313853 3PONTONDP Adder 0.24 MW 0.2 MW
314704 3LAWRENC 80/20 0.2 MW 0.2 MW
315126 1ROARAP2 80/20 0.82 MW 0.82 MW
315128 1ROARAP4 80/20 0.78 MW 0.78 MW
315131 1EDGECMA 80/20 8.34 MW 8.34 MW
315136 1ROSEMG1 80/20 1.35 MW 1.35 MW
315137 1ROSEMS1 80/20 0.84 MW 0.84 MW
315138 1ROSEMG2 80/20 0.63 MW 0.63 MW
315139 1GASTONA 80/20 2.07 MW 2.07 MW
315153 1CLOVER1 80/20 6.05 MW 6.05 MW
315154 1CLOVER2 80/20 5.99 MW 5.99 MW
315158 1KERR 1 80/20 0.2 MW 0.2 MW
315159 1KERR 2 80/20 0.55 MW 0.55 MW
315160 1KERR 3 80/20 0.55 MW 0.55 MW
315161 1KERR 4 80/20 0.55 MW 0.55 MW
315162 1KERR 5 80/20 0.55 MW 0.55 MW
934521 AD1-076 C 80/20 4.81 MW 4.81 MW
943171 AE2-346 C 80/20 0.1 MW 0.1 MW
944011 AF1-069 C 80/20 7.21 MW 7.21 MW
959311 AF2-222 C 80/20 6.65 MW 6.65 MW
960061 AF2-297 C 80/20 3.43 MW 3.43 MW
960081 AF2-299 C 80/20 1.39 MW 1.39 MW
315163 1KERR 6 80/20 0.55 MW 0.55 MW
315164 1KERR 7 80/20 0.55 MW 0.55 MW
315266 1PLYWOOD A 80/20 0.54 MW 0.54 MW
315601 1CONETOE2SOL 80/20 0.63 MW 0.63 MW
315606 3AA2-053SOLA 80/20 0.86 MW 0.86 MW
316118 AC1-105 C 80/20 0.41 MW 0.41 MW
316129 AC1-054 C 80/20 0.65 MW 0.65 MW
316131 AB2-060 C 80/20 0.68 MW 0.68 MW
316140 AB2-099 C 80/20 0.04 MW 0.04 MW
938371 AE1-056 C Adder 2.18 MW 1.86 MW
939181 AE1-148 C 80/20 4.34 MW 4.34 MW
940491 AE2-034 C 80/20 0.42 MW 0.42 MW
941031 AE2-094 C 80/20 22.07 MW 22.07 MW
946281 AF1-292 C 80/20 1.15 MW 1.15 MW
946301 AF1-294 C Adder 1.32 MW 1.12 MW
957481 AF2-042 C 80/20 26.39 MW 26.39 MW
957521 AF2-046 C 80/20 6.54 MW 6.54 MW
957861 AF2-080 C 80/20 3.77 MW 3.77 MW
958211 AF2-115 C Adder 0.8 MW 0.68 MW
938771 AE1-103 C Adder 0.97 MW 0.82 MW
315102 1BRUNSWICKG1 80/20 4.48 MW 4.48 MW
315103 1BRUNSWICKG2 80/20 4.48 MW 4.48 MW
315104 1BRUNSWICKG3 80/20 4.48 MW 4.48 MW
315105 1BRUNSWICKS1 80/20 9.3 MW 9.3 MW
315115 1S HAMPT1 80/20 0.57 MW 0.57 MW
315141 1GASTONB 80/20 2.07 MW 2.07 MW
315241 1Z1-086 GT1 80/20 5.75 MW 5.75 MW
315242 1Z1-086 GT2 80/20 5.75 MW 5.75 MW
315243 1Z1-086 GT3 80/20 5.75 MW 5.75 MW
315244 1Z1-086 ST 80/20 10.01 MW 10.01 MW
315292 1DOMTR78 80/20 0.56 MW 0.56 MW
315607 3AA1-063SOLA 80/20 0.75 MW 0.75 MW
315608 3AA2-088SOLA 80/20 0.47 MW 0.47 MW
942001 AE2-212 C Adder -3.93 MW -3.34 MW
926071 AC1-086 C 80/20 14.3 MW 14.3 MW
927021 AC1-189 C 80/20 4.15 MW 4.15 MW
936261 AD2-033 C 80/20 5.42 MW 5.42 MW
934621 AD1-088 C 80/20 5.84 MW 5.84 MW
939411 AE1-173 C 80/20 41.76 MW 41.76 MW
933981 AD1-022 C 80/20 3.58 MW 3.58 MW
961681 AG1-008 C 80/20 6.54 MW 6.54 MW
962571 AG1-106 C 80/20 1.85 MW 1.85 MW
316003 AC1-222 C 80/20 0.43 MW 0.43 MW
316005 AA1-067 C 80/20 0.13 MW 0.13 MW
316011 AB1-132 C OP 80/20 1.58 MW 1.58 MW
316023 AB2-100 C2 80/20 0.8 MW 0.8 MW
316034 AC1-036 C 80/20 0.1 MW 0.1 MW
316049 AB1-081 C OP 80/20 0.76 MW 0.76 MW
316210 AC1-098 C 80/20 0.5 MW 0.5 MW
316212 AC1-099 C 80/20 0.17 MW 0.17 MW
316222 AC1-221 C 80/20 0.63 MW 0.63 MW
316237 AB2-079 C O1 80/20 0.15 MW 0.15 MW
316238 AB2-078 C O1 80/20 0.15 MW 0.15 MW
316239 AB2-077 C O1 80/20 0.15 MW 0.15 MW
316240 AF1-291 C Adder -1.66 MW -1.41 MW
316248 AF1-058 C 80/20 0.14 MW 0.14 MW
316263 AC1-034 C 80/20 3.55 MW 3.55 MW
316274 AC1-208 C 80/20 4.96 MW 4.96 MW
316283 AC2-100 C 80/20 0.51 MW 0.51 MW
316315 AB2-025 C 80/20 0.42 MW 0.42 MW
316317 KELFORD C 80/20 0.18 MW 0.18 MW
316318 V4-068 C 80/20 0.04 MW 0.04 MW
316319 Z2-044 C 80/20 0.11 MW 0.11 MW
316365 AB2-100 C1 80/20 0.8 MW 0.8 MW
315602 1HOLLOMANSOL 80/20 0.83 MW 0.83 MW
316327 AA2-057 C 80/20 0.7 MW 0.7 MW
315614 AA2-178 C 80/20 0.57 MW 0.57 MW
316181 AB2-040 GEN 80/20 0.85 MW 0.85 MW
313527 AB2-043 C 80/20 0.24 MW 0.24 MW
316359 AB2-059 C OP 80/20 0.89 MW 0.89 MW
316174 AB2-169_C 80/20 0.45 MW 0.45 MW
316087 AB2-174 C 80/20 0.81 MW 0.81 MW
962491 AG1-098 C 80/20 5.17 MW 5.17 MW
962561 AG1-105 C 80/20 4.02 MW 4.02 MW
964241 AG1-285 C 80/20 5.55 MW 5.55 MW
313764 3SOCKMAN 80/20 0.45 MW 0.45 MW
932631 AC2-084 C 80/20 0.53 MW 0.53 MW
934321 AD1-056 C 80/20 3.74 MW 3.74 MW
934331 AD1-057 C 80/20 2.09 MW 2.09 MW
934501 AD1-074 C 80/20 13.23 MW 13.23 MW
934511 AD1-075 C 80/20 3.31 MW 3.31 MW
934611 AD1-087 C 80/20 0.6 MW 0.6 MW
935171 AD1-152 C 80/20 0.62 MW 0.62 MW
937481 AD2-202 C 80/20 0.17 MW 0.17 MW
940481 AE2-033 C 80/20 16.46 MW 16.46 MW
940541 AE2-040 C 80/20 3.0 MW 3.0 MW
940641 AE2-051 C 80/20 9.04 MW 9.04 MW
944641 AF1-129 C Adder -92.12 MW -78.3 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 17.95 MW 17.95 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 11.57 MW 11.57 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 46.16 MW 46.16 MW
NY PJM->LTFIMP_NY CLTF 0.58 MW 0.58 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.69 MW 0.69 MW
WEC LTFEXP_WEC->PJM CLTF 0.37 MW 0.37 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.54 MW 5.54 MW
TVA LTFEXP_TVA->PJM CLTF 3.05 MW 3.05 MW
MEC LTFEXP_MEC->PJM CLTF 2.13 MW 2.13 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.87 MW 3.87 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.13 MW 0.13 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.64 MW 2.64 MW

Details for 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 574_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
DVP_P1-2: LN 574_SRT-S
CONTINGENCY 'DVP_P1-2: LN 574_SRT-S'
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 103.22 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3324.19 MVA
MW Contribution: 10.17 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.25 MW 1.06 MW
961791 AG1-021 C Adder 1.83 MW 1.55 MW
961941 AG1-037 C Adder 0.67 MW 0.57 MW
962331 AG1-082 C Adder 2.69 MW 2.29 MW
963041 AG1-153 C 80/20 9.14 MW 9.14 MW
963171 AG1-166 C Adder 1.01 MW 0.86 MW
963181 AG1-167 C Adder 0.76 MW 0.65 MW
963191 AG1-168 C Adder 0.76 MW 0.65 MW
964791 AG1-342 C Adder 4.43 MW 3.77 MW
966801 AG1-551 C Adder 2.81 MW 2.39 MW
966811 AG1-552 C Adder 2.73 MW 2.32 MW
965291 AG1-394 C Adder 1.13 MW 0.96 MW
966621 AG1-532 C 80/20 1.86 MW 1.86 MW
313506 AB1-173 C OP 80/20 1.49 MW 1.49 MW
313853 3PONTONDP Adder 0.68 MW 0.57 MW
315131 1EDGECMA Adder 20.59 MW 17.5 MW
315153 1CLOVER1 80/20 17.95 MW 17.95 MW
315154 1CLOVER2 80/20 17.78 MW 17.78 MW
934521 AD1-076 C Adder 16.37 MW 13.92 MW
944011 AF1-069 C 80/20 21.71 MW 21.71 MW
959311 AF2-222 C Adder 18.29 MW 15.54 MW
960061 AF2-297 C Adder 9.89 MW 8.4 MW
960081 AF2-299 C 80/20 2.48 MW 2.48 MW
938371 AE1-056 C Adder 6.34 MW 5.39 MW
939181 AE1-148 C Adder 11.53 MW 9.8 MW
940491 AE2-034 C 80/20 1.54 MW 1.54 MW
941031 AE2-094 C 80/20 66.45 MW 66.45 MW
946281 AF1-292 C 80/20 2.06 MW 2.06 MW
946301 AF1-294 C Adder 3.75 MW 3.19 MW
957481 AF2-042 C 80/20 78.71 MW 78.71 MW
957521 AF2-046 C Adder 18.88 MW 16.04 MW
957861 AF2-080 C Adder 10.17 MW 8.64 MW
958211 AF2-115 C Adder 2.28 MW 1.94 MW
938771 AE1-103 C 80/20 3.87 MW 3.87 MW
313526 AB2-022 C 80/20 0.5 MW 0.5 MW
314507 3THOMPSN 80/20 2.68 MW 2.68 MW
315092 1YORKTN3 Adder 141.68 MW 120.43 MW
942341 AE2-247 C Adder 1.88 MW 1.6 MW
943461 AF1-017 C Adder 1.7 MW 1.45 MW
315098 1CHESPKA 80/20 0.58 MW 0.58 MW
315099 1CHESPKB 80/20 0.96 MW 0.96 MW
315102 1BRUNSWICKG1 80/20 13.45 MW 13.45 MW
315103 1BRUNSWICKG2 80/20 13.45 MW 13.45 MW
315104 1BRUNSWICKG3 80/20 13.45 MW 13.45 MW
315105 1BRUNSWICKS1 80/20 27.93 MW 27.93 MW
315108 1ELIZAR1 80/20 4.26 MW 4.26 MW
315109 1ELIZAR2 80/20 4.18 MW 4.18 MW
315110 1ELIZAR3 80/20 4.31 MW 4.31 MW
315115 1S HAMPT1 80/20 1.97 MW 1.97 MW
315241 1Z1-086 GT1 80/20 17.28 MW 17.28 MW
315242 1Z1-086 GT2 80/20 17.28 MW 17.28 MW
315243 1Z1-086 GT3 80/20 17.28 MW 17.28 MW
315244 1Z1-086 ST 80/20 30.08 MW 30.08 MW
315260 1GOSPORTA 80/20 2.83 MW 2.83 MW
315261 1GOSPORTB 80/20 3.62 MW 3.62 MW
315262 1GOSPORTC 80/20 3.07 MW 3.07 MW
315605 6W1-029WIND 80/20 1.04 MW 1.04 MW
315608 3AA2-088SOLA 80/20 1.41 MW 1.41 MW
315611 6Z1-036WIND 80/20 0.88 MW 0.88 MW
942001 AE2-212 C Adder 2.11 MW 1.8 MW
957871 AF2-081 C 80/20 13.43 MW 13.43 MW
958161 AF2-110 C 80/20 1.8 MW 1.8 MW
926071 AC1-086 C Adder 28.08 MW 23.86 MW
927021 AC1-189 C Adder 11.19 MW 9.52 MW
936261 AD2-033 C Adder 14.72 MW 12.52 MW
933291 AC2-141 C 80/20 41.9 MW 41.9 MW
934621 AD1-088 C 80/20 17.46 MW 17.46 MW
939411 AE1-173 C 80/20 144.1 MW 144.1 MW
916191 Z1-068 C 80/20 0.06 MW 0.06 MW
933981 AD1-022 C Adder 11.71 MW 9.96 MW
961681 AG1-008 C Adder 18.88 MW 16.04 MW
962571 AG1-106 C Adder 3.63 MW 3.09 MW
316023 AB2-100 C2 80/20 1.29 MW 1.29 MW
316036 AC1-147 C 80/20 0.49 MW 0.49 MW
316072 AD1-144 C 80/20 0.36 MW 0.36 MW
316185 AD1-033 C 80/20 1.65 MW 1.65 MW
316246 AF1-032 C 80/20 0.38 MW 0.38 MW
316263 AC1-034 C Adder 8.8 MW 7.48 MW
316274 AC1-208 C Adder 11.98 MW 10.19 MW
316294 AC1-161 C 80/20 6.82 MW 6.82 MW
316305 AF2-043 C 80/20 0.46 MW 0.46 MW
316315 AB2-025 C 80/20 0.56 MW 0.56 MW
316316 AC1-027 C 80/20 0.42 MW 0.42 MW
316320 Y1-086 C 80/20 0.29 MW 0.29 MW
316321 Z2-027 C 80/20 0.49 MW 0.49 MW
316365 AB2-100 C1 80/20 1.29 MW 1.29 MW
316017 AA1-139 ULT1 80/20 1.45 MW 1.45 MW
316018 AA1-139 ULT2 80/20 1.45 MW 1.45 MW
315614 AA2-178 C 80/20 2.09 MW 2.09 MW
316181 AB2-040 GEN 80/20 1.68 MW 1.68 MW
316087 AB2-174 C 80/20 1.56 MW 1.56 MW
316375 AC2-012 C 80/20 1.79 MW 1.79 MW
316311 AC2-079 C Adder 7.27 MW 6.18 MW
316349 AD2-085 C Adder 4.34 MW 3.69 MW
316388 AE2-253 GEN 80/20 2.63 MW 2.63 MW
961611 AG1-000B C Adder 17.07 MW 14.51 MW
941591 AE2-156 C 80/20 23.84 MW 23.84 MW
944581 AF1-123 C 80/20 61.95 MW 61.95 MW
944591 AF1-124 C 80/20 62.18 MW 62.18 MW
944601 AF1-125 C 80/20 61.0 MW 61.0 MW
962491 AG1-098 C 80/20 15.48 MW 15.48 MW
962561 AG1-105 C Adder 11.07 MW 9.41 MW
964241 AG1-285 C Adder 14.8 MW 12.58 MW
965281 AG1-393 C Adder 1.98 MW 1.68 MW
313764 3SOCKMAN Adder 0.95 MW 0.81 MW
934321 AD1-056 C Adder 8.33 MW 7.08 MW
934331 AD1-057 C Adder 4.65 MW 3.95 MW
934501 AD1-074 C Adder 45.08 MW 38.32 MW
934511 AD1-075 C Adder 11.27 MW 9.58 MW
934611 AD1-087 C 80/20 1.77 MW 1.77 MW
935161 AD1-151 C Adder 15.27 MW 12.98 MW
935171 AD1-152 C 80/20 1.83 MW 1.83 MW
937481 AD2-202 C 80/20 0.51 MW 0.51 MW
938531 AE1-072 C 80/20 23.61 MW 23.61 MW
939191 AE1-149 C Adder 11.99 MW 10.19 MW
940431 AE2-027 C Adder 11.4 MW 9.69 MW
940481 AE2-033 C 80/20 22.18 MW 22.18 MW
940541 AE2-040 C 80/20 3.94 MW 3.94 MW
940641 AE2-051 C 80/20 28.76 MW 28.76 MW
941101 AE2-104 C 80/20 4.41 MW 4.41 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 55.06 MW 55.06 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 35.38 MW 35.38 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 135.46 MW 135.46 MW
NY PJM->LTFIMP_NY CLTF 2.56 MW 2.56 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.18 MW 2.18 MW
WEC LTFEXP_WEC->PJM CLTF 1.13 MW 1.13 MW
CPLE LTFEXP_CPLE->PJM CLTF 15.91 MW 15.91 MW
TVA LTFEXP_TVA->PJM CLTF 9.31 MW 9.31 MW
MEC LTFEXP_MEC->PJM CLTF 6.56 MW 6.56 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.74 MW 11.74 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.41 MW 0.41 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.59 MW 7.59 MW

Details for 6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line
314285 to 314316 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 102.52 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1008.98 MVA
MW Contribution: 3.77 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 80/20 0.48 MW 0.48 MW
961791 AG1-021 C Adder 0.64 MW 0.54 MW
961941 AG1-037 C 80/20 0.24 MW 0.24 MW
962331 AG1-082 C 80/20 0.95 MW 0.95 MW
963041 AG1-153 C 80/20 3.04 MW 3.04 MW
963171 AG1-166 C Adder 0.36 MW 0.3 MW
963181 AG1-167 C Adder 0.27 MW 0.23 MW
963191 AG1-168 C Adder 0.27 MW 0.23 MW
964791 AG1-342 C 80/20 1.6 MW 1.6 MW
966801 AG1-551 C 80/20 0.96 MW 0.96 MW
966811 AG1-552 C 80/20 1.22 MW 1.22 MW
965291 AG1-394 C 80/20 0.39 MW 0.39 MW
966621 AG1-532 C 80/20 1.04 MW 1.04 MW
313506 AB1-173 C OP 80/20 0.76 MW 0.76 MW
313853 3PONTONDP Adder 0.24 MW 0.2 MW
314704 3LAWRENC 80/20 0.2 MW 0.2 MW
315126 1ROARAP2 80/20 0.82 MW 0.82 MW
315128 1ROARAP4 80/20 0.78 MW 0.78 MW
315131 1EDGECMA 80/20 8.34 MW 8.34 MW
315136 1ROSEMG1 80/20 1.35 MW 1.35 MW
315137 1ROSEMS1 80/20 0.84 MW 0.84 MW
315138 1ROSEMG2 80/20 0.63 MW 0.63 MW
315139 1GASTONA 80/20 2.07 MW 2.07 MW
315153 1CLOVER1 80/20 6.05 MW 6.05 MW
315154 1CLOVER2 80/20 5.99 MW 5.99 MW
315158 1KERR 1 80/20 0.2 MW 0.2 MW
315159 1KERR 2 80/20 0.55 MW 0.55 MW
315160 1KERR 3 80/20 0.55 MW 0.55 MW
315161 1KERR 4 80/20 0.55 MW 0.55 MW
315162 1KERR 5 80/20 0.55 MW 0.55 MW
934521 AD1-076 C 80/20 4.81 MW 4.81 MW
943171 AE2-346 C 80/20 0.1 MW 0.1 MW
944011 AF1-069 C 80/20 7.21 MW 7.21 MW
959311 AF2-222 C 80/20 6.65 MW 6.65 MW
960061 AF2-297 C 80/20 3.43 MW 3.43 MW
960081 AF2-299 C 80/20 1.39 MW 1.39 MW
315163 1KERR 6 80/20 0.55 MW 0.55 MW
315164 1KERR 7 80/20 0.55 MW 0.55 MW
315266 1PLYWOOD A 80/20 0.54 MW 0.54 MW
315601 1CONETOE2SOL 80/20 0.63 MW 0.63 MW
315606 3AA2-053SOLA 80/20 0.86 MW 0.86 MW
316118 AC1-105 C 80/20 0.41 MW 0.41 MW
316129 AC1-054 C 80/20 0.65 MW 0.65 MW
316131 AB2-060 C 80/20 0.68 MW 0.68 MW
316140 AB2-099 C 80/20 0.04 MW 0.04 MW
938371 AE1-056 C Adder 2.18 MW 1.86 MW
939181 AE1-148 C 80/20 4.34 MW 4.34 MW
940491 AE2-034 C 80/20 0.42 MW 0.42 MW
941031 AE2-094 C 80/20 22.07 MW 22.07 MW
946281 AF1-292 C 80/20 1.15 MW 1.15 MW
946301 AF1-294 C Adder 1.32 MW 1.12 MW
957481 AF2-042 C 80/20 26.39 MW 26.39 MW
957521 AF2-046 C 80/20 6.54 MW 6.54 MW
957861 AF2-080 C 80/20 3.77 MW 3.77 MW
958211 AF2-115 C Adder 0.8 MW 0.68 MW
938771 AE1-103 C Adder 0.97 MW 0.82 MW
315102 1BRUNSWICKG1 80/20 4.48 MW 4.48 MW
315103 1BRUNSWICKG2 80/20 4.48 MW 4.48 MW
315104 1BRUNSWICKG3 80/20 4.48 MW 4.48 MW
315105 1BRUNSWICKS1 80/20 9.3 MW 9.3 MW
315115 1S HAMPT1 80/20 0.57 MW 0.57 MW
315141 1GASTONB 80/20 2.07 MW 2.07 MW
315241 1Z1-086 GT1 80/20 5.75 MW 5.75 MW
315242 1Z1-086 GT2 80/20 5.75 MW 5.75 MW
315243 1Z1-086 GT3 80/20 5.75 MW 5.75 MW
315244 1Z1-086 ST 80/20 10.01 MW 10.01 MW
315292 1DOMTR78 80/20 0.56 MW 0.56 MW
315607 3AA1-063SOLA 80/20 0.75 MW 0.75 MW
315608 3AA2-088SOLA 80/20 0.47 MW 0.47 MW
942001 AE2-212 C Adder -3.93 MW -3.34 MW
926071 AC1-086 C 80/20 14.3 MW 14.3 MW
927021 AC1-189 C 80/20 4.15 MW 4.15 MW
936261 AD2-033 C 80/20 5.42 MW 5.42 MW
934621 AD1-088 C 80/20 5.84 MW 5.84 MW
939411 AE1-173 C 80/20 41.76 MW 41.76 MW
933981 AD1-022 C 80/20 3.58 MW 3.58 MW
961681 AG1-008 C 80/20 6.54 MW 6.54 MW
962571 AG1-106 C 80/20 1.85 MW 1.85 MW
316003 AC1-222 C 80/20 0.43 MW 0.43 MW
316005 AA1-067 C 80/20 0.13 MW 0.13 MW
316011 AB1-132 C OP 80/20 1.58 MW 1.58 MW
316023 AB2-100 C2 80/20 0.8 MW 0.8 MW
316034 AC1-036 C 80/20 0.1 MW 0.1 MW
316049 AB1-081 C OP 80/20 0.76 MW 0.76 MW
316210 AC1-098 C 80/20 0.5 MW 0.5 MW
316212 AC1-099 C 80/20 0.17 MW 0.17 MW
316222 AC1-221 C 80/20 0.63 MW 0.63 MW
316237 AB2-079 C O1 80/20 0.15 MW 0.15 MW
316238 AB2-078 C O1 80/20 0.15 MW 0.15 MW
316239 AB2-077 C O1 80/20 0.15 MW 0.15 MW
316240 AF1-291 C Adder -1.66 MW -1.41 MW
316248 AF1-058 C 80/20 0.14 MW 0.14 MW
316263 AC1-034 C 80/20 3.55 MW 3.55 MW
316274 AC1-208 C 80/20 4.96 MW 4.96 MW
316283 AC2-100 C 80/20 0.51 MW 0.51 MW
316315 AB2-025 C 80/20 0.42 MW 0.42 MW
316317 KELFORD C 80/20 0.18 MW 0.18 MW
316318 V4-068 C 80/20 0.04 MW 0.04 MW
316319 Z2-044 C 80/20 0.11 MW 0.11 MW
316365 AB2-100 C1 80/20 0.8 MW 0.8 MW
315602 1HOLLOMANSOL 80/20 0.83 MW 0.83 MW
316327 AA2-057 C 80/20 0.7 MW 0.7 MW
315614 AA2-178 C 80/20 0.57 MW 0.57 MW
316181 AB2-040 GEN 80/20 0.85 MW 0.85 MW
313527 AB2-043 C 80/20 0.24 MW 0.24 MW
316359 AB2-059 C OP 80/20 0.89 MW 0.89 MW
316174 AB2-169_C 80/20 0.45 MW 0.45 MW
316087 AB2-174 C 80/20 0.81 MW 0.81 MW
962491 AG1-098 C 80/20 5.17 MW 5.17 MW
962561 AG1-105 C 80/20 4.02 MW 4.02 MW
964241 AG1-285 C 80/20 5.55 MW 5.55 MW
313764 3SOCKMAN 80/20 0.45 MW 0.45 MW
932631 AC2-084 C 80/20 0.53 MW 0.53 MW
934321 AD1-056 C 80/20 3.74 MW 3.74 MW
934331 AD1-057 C 80/20 2.09 MW 2.09 MW
934501 AD1-074 C 80/20 13.23 MW 13.23 MW
934511 AD1-075 C 80/20 3.31 MW 3.31 MW
934611 AD1-087 C 80/20 0.6 MW 0.6 MW
935171 AD1-152 C 80/20 0.62 MW 0.62 MW
937481 AD2-202 C 80/20 0.17 MW 0.17 MW
940481 AE2-033 C 80/20 16.46 MW 16.46 MW
940541 AE2-040 C 80/20 3.0 MW 3.0 MW
940641 AE2-051 C 80/20 9.04 MW 9.04 MW
944641 AF1-129 C Adder -92.12 MW -78.3 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 17.95 MW 17.95 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 11.57 MW 11.57 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 46.16 MW 46.16 MW
NY PJM->LTFIMP_NY CLTF 0.58 MW 0.58 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.69 MW 0.69 MW
WEC LTFEXP_WEC->PJM CLTF 0.37 MW 0.37 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.54 MW 5.54 MW
TVA LTFEXP_TVA->PJM CLTF 3.05 MW 3.05 MW
MEC LTFEXP_MEC->PJM CLTF 2.13 MW 2.13 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.87 MW 3.87 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.13 MW 0.13 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.64 MW 2.64 MW

Details for 8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line
314908 to 314911 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 100.88 %
Rating: 4070.2 MVA
Rating Type: B
MVA to Mitigate: 4105.97 MVA
MW Contribution: 10.13 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.23 MW 1.04 MW
961941 AG1-037 C Adder 0.7 MW 0.59 MW
962331 AG1-082 C Adder 2.79 MW 2.37 MW
963041 AG1-153 C Adder 7.02 MW 5.97 MW
966801 AG1-551 C Adder 2.86 MW 2.43 MW
966811 AG1-552 C Adder 2.71 MW 2.3 MW
965291 AG1-394 C Adder 1.19 MW 1.01 MW
966621 AG1-532 C Adder 1.82 MW 1.54 MW
934521 AD1-076 C Adder 17.45 MW 14.83 MW
944011 AF1-069 C Adder 16.4 MW 13.94 MW
960081 AF2-299 C Adder 2.42 MW 2.06 MW
941031 AE2-094 C Adder 50.2 MW 42.67 MW
946281 AF1-292 C Adder 2.01 MW 1.71 MW
957481 AF2-042 C Adder 64.72 MW 55.02 MW
957521 AF2-046 C Adder 19.67 MW 16.72 MW
957861 AF2-080 C Adder 10.13 MW 8.61 MW
938771 AE1-103 C Adder 4.25 MW 3.61 MW
314229 6MT RD221 80/20 0.18 MW 0.18 MW
314421 6WINCHST 80/20 0.2 MW 0.2 MW
314507 3THOMPSN 80/20 3.07 MW 3.07 MW
315060 1CHESTF5 Adder 92.3 MW 78.45 MW
315065 1CHESTF6 Adder 27.54 MW 23.41 MW
315073 1STONECA Adder 9.99 MW 8.49 MW
315083 1SPRUNCA Adder 10.61 MW 9.02 MW
315084 1SPRUNCB Adder 10.61 MW 9.02 MW
315092 1YORKTN3 80/20 206.84 MW 206.84 MW
936591 AD2-074 C Adder 7.4 MW 6.29 MW
942341 AE2-247 C Adder 2.2 MW 1.87 MW
943461 AF1-017 C Adder 1.99 MW 1.69 MW
943741 AF1-042 C Adder 3.87 MW 3.29 MW
961951 AG1-038 C Adder 4.28 MW 3.64 MW
966661 AG1-536 C Adder 6.97 MW 5.92 MW
966871 AG1-558 C Adder 3.38 MW 2.88 MW
315098 1CHESPKA 80/20 0.66 MW 0.66 MW
315099 1CHESPKB 80/20 1.1 MW 1.1 MW
315108 1ELIZAR1 80/20 4.86 MW 4.86 MW
315109 1ELIZAR2 80/20 4.77 MW 4.77 MW
315110 1ELIZAR3 80/20 4.92 MW 4.92 MW
315116 1SURRY 1 80/20 36.99 MW 36.99 MW
315120 1GRAVEL4 80/20 3.81 MW 3.81 MW
315122 1GRAVEL6 80/20 3.8 MW 3.8 MW
315216 1CUNINGA 80/20 7.92 MW 7.92 MW
315217 1CUNINGB 80/20 7.92 MW 7.92 MW
315218 1CUNINGC 80/20 7.92 MW 7.92 MW
315219 1CUNINGD 80/20 17.71 MW 17.71 MW
315233 1SURRY 2 80/20 40.27 MW 40.27 MW
315260 1GOSPORTA 80/20 3.24 MW 3.24 MW
315261 1GOSPORTB 80/20 4.14 MW 4.14 MW
315262 1GOSPORTC 80/20 3.51 MW 3.51 MW
316075 AC2-137 C 80/20 0.57 MW 0.57 MW
957601 AF2-054 C Adder 3.04 MW 2.58 MW
962861 AG1-135 C Adder 7.91 MW 6.72 MW
962971 AG1-146 C Adder 4.16 MW 3.54 MW
962981 AG1-147 C Adder 9.72 MW 8.26 MW
963611 AG1-210 C Adder 0.81 MW 0.69 MW
964211 AG1-282 C Adder 2.53 MW 2.15 MW
942001 AE2-212 C Adder 3.02 MW 2.56 MW
957871 AF2-081 C 80/20 15.09 MW 15.09 MW
958161 AF2-110 C Adder 2.04 MW 1.73 MW
926071 AC1-086 C Adder 27.76 MW 23.6 MW
927021 AC1-189 C Adder 11.15 MW 9.48 MW
933291 AC2-141 C 80/20 47.33 MW 47.33 MW
934621 AD1-088 C Adder 14.9 MW 12.66 MW
939411 AE1-173 C Adder 124.69 MW 105.99 MW
916191 Z1-068 C 80/20 0.07 MW 0.07 MW
927041 AC1-191 C Adder 13.59 MW 11.55 MW
933981 AD1-022 C Adder 12.42 MW 10.55 MW
961681 AG1-008 C Adder 19.67 MW 16.72 MW
962571 AG1-106 C Adder 3.59 MW 3.05 MW
316004 AC1-112 C 80/20 0.51 MW 0.51 MW
316036 AC1-147 C 80/20 0.56 MW 0.56 MW
316159 AE1-175 C 80/20 0.61 MW 0.61 MW
316169 AC1-164 GEN 80/20 63.01 MW 63.01 MW
316185 AD1-033 C 80/20 1.86 MW 1.86 MW
316236 AE1-162 C 80/20 0.53 MW 0.53 MW
316240 AF1-291 C Adder 3.03 MW 2.57 MW
316274 AC1-208 C Adder 11.87 MW 10.09 MW
316294 AC1-161 C 80/20 7.71 MW 7.71 MW
316312 AB1-027 C 80/20 0.81 MW 0.81 MW
316316 AC1-027 C 80/20 0.48 MW 0.48 MW
316382 AG1-145 C 80/20 0.55 MW 0.55 MW
316017 AA1-139 ULT1 80/20 1.63 MW 1.63 MW
316018 AA1-139 ULT2 80/20 1.63 MW 1.63 MW
316375 AC2-012 C 80/20 2.05 MW 2.05 MW
316311 AC2-079 C Adder 8.47 MW 7.2 MW
316349 AD2-085 C Adder 5.08 MW 4.31 MW
316388 AE2-253 GEN 80/20 2.96 MW 2.96 MW
961611 AG1-000B C Adder 23.85 MW 20.27 MW
941591 AE2-156 C 80/20 27.26 MW 27.26 MW
944581 AF1-123 C 80/20 69.3 MW 69.3 MW
944591 AF1-124 C 80/20 69.54 MW 69.54 MW
944601 AF1-125 C 80/20 68.23 MW 68.23 MW
944631 AF1-128 C Adder 57.75 MW 49.09 MW
958261 AF2-120 C Adder 8.1 MW 6.88 MW
962491 AG1-098 C Adder 13.31 MW 11.31 MW
965281 AG1-393 C Adder 3.03 MW 2.58 MW
313764 3SOCKMAN Adder 0.93 MW 0.79 MW
934321 AD1-056 C Adder 8.15 MW 6.93 MW
934331 AD1-057 C Adder 4.55 MW 3.87 MW
934501 AD1-074 C Adder 48.04 MW 40.83 MW
934511 AD1-075 C Adder 12.01 MW 10.21 MW
935161 AD1-151 C Adder 23.76 MW 20.19 MW
938531 AE1-072 C Adder 26.5 MW 22.53 MW
939191 AE1-149 C Adder 15.33 MW 13.03 MW
940431 AE2-027 C Adder 18.18 MW 15.46 MW
940481 AE2-033 C Adder 21.38 MW 18.17 MW
940541 AE2-040 C Adder 3.79 MW 3.23 MW
940551 AE2-041 C Adder 10.37 MW 8.81 MW
940641 AE2-051 C Adder 23.01 MW 19.56 MW
941101 AE2-104 C Adder 5.0 MW 4.25 MW
943471 AF1-018 C Adder 10.37 MW 8.81 MW
944641 AF1-129 C Adder 143.62 MW 122.08 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 74.17 MW 74.17 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 42.32 MW 42.32 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 133.89 MW 133.89 MW
NY PJM->LTFIMP_NY CLTF 3.6 MW 3.6 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.95 MW 2.95 MW
WEC LTFEXP_WEC->PJM CLTF 1.52 MW 1.52 MW
CPLE LTFEXP_CPLE->PJM CLTF 14.97 MW 14.97 MW
TVA LTFEXP_TVA->PJM CLTF 10.75 MW 10.75 MW
MEC LTFEXP_MEC->PJM CLTF 8.37 MW 8.37 MW
LAGN LTFEXP_LAGN->PJM CLTF 13.39 MW 13.39 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.54 MW 0.54 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.15 MW 7.15 MW

Details for 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line l/o DVP_P4-2: H2T574_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
DVP_P4-2: H2T574_SRT-S
CONTINGENCY 'DVP_P4-2: H2T574_SRT-S'
 OPEN BRANCH FROM BUS 314196 TO BUS 314911 CKT 2                /*6LADYSMITH   230.0 - 8LADYSMITH   500.0
 OPEN BRANCH FROM BUS 314908 TO BUS 314911 CKT 1                /*8ELMONT      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314905 TO BUS 314911 CKT 1 /*8CHANCE      500.0 - 8LADYSMITH   500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314911 TO BUS 314922 CKT 1 /*8LADYSMITH   500.0 - 8POSSUM      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 115.67 %
Rating: 3940.0 MVA
Rating Type: C
MVA to Mitigate: 4557.54 MVA
MW Contribution: 14.76 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 1.25 MW 1.07 MW
961672 AG1-007 E Adder 0.71 MW 0.6 MW
961941 AG1-037 C Adder 0.68 MW 0.57 MW
961942 AG1-037 E Adder 0.45 MW 0.38 MW
962331 AG1-082 C Adder 2.71 MW 2.3 MW
962332 AG1-082 E Adder 1.8 MW 1.53 MW
963041 AG1-153 C 50/50 9.17 MW 9.17 MW
963042 AG1-153 E 50/50 13.76 MW 13.76 MW
964791 AG1-342 C Adder 4.45 MW 3.78 MW
964792 AG1-342 E Adder 2.97 MW 2.52 MW
966801 AG1-551 C Adder 2.82 MW 2.4 MW
966802 AG1-551 E Adder 1.48 MW 1.26 MW
966811 AG1-552 C Adder 2.75 MW 2.33 MW
966812 AG1-552 E Adder 1.31 MW 1.11 MW
965291 AG1-394 C Adder 1.14 MW 0.97 MW
965292 AG1-394 E Adder 2.1 MW 1.78 MW
966621 AG1-532 C Adder 1.87 MW 1.59 MW
966622 AG1-532 E Adder 1.25 MW 1.06 MW
314541 3WATKINS Adder 0.92 MW 0.78 MW
314572 3EMPORIA Adder 0.58 MW 0.49 MW
315131 1EDGECMA Adder 20.7 MW 17.59 MW
315153 1CLOVER1 50/50 18.02 MW 18.02 MW
315154 1CLOVER2 50/50 17.85 MW 17.85 MW
918492 AA1-063AE OP Adder 5.46 MW 4.64 MW
918532 AA1-067 E Adder 0.96 MW 0.81 MW
919692 AA2-053 E OP Adder 5.65 MW 4.8 MW
920042 AA2-088 E OP Adder 14.16 MW 12.04 MW
925785 AC1-054 E Adder 4.52 MW 3.84 MW
926274 AC1-105 E Adder 3.41 MW 2.9 MW
927146 AC1-208 E Adder 5.35 MW 4.55 MW
934521 AD1-076 C Adder 16.48 MW 14.0 MW
934522 AD1-076 E Adder 8.4 MW 7.14 MW
943172 AE2-346 E Adder 0.81 MW 0.69 MW
943902 AF1-058 E Adder 1.66 MW 1.41 MW
944011 AF1-069 C 50/50 21.79 MW 21.79 MW
944012 AF1-069 E 50/50 8.46 MW 8.46 MW
960061 AF2-297 C Adder 9.93 MW 8.44 MW
960062 AF2-297 E Adder 6.62 MW 5.63 MW
960081 AF2-299 C Adder 2.5 MW 2.12 MW
960082 AF2-299 E Adder 1.67 MW 1.42 MW
316141 AB2-099 E Adder 0.34 MW 0.29 MW
900672 V4-068 E Adder 0.48 MW 0.41 MW
917342 Z2-044 E Adder 0.8 MW 0.68 MW
922923 AB1-081 E OP Adder 4.97 MW 4.22 MW
923263 AB1-132 E OP Adder 8.22 MW 6.99 MW
923573 AB1-173 E OP Adder 4.39 MW 3.73 MW
924162 AB2-060 E OP Adder 5.21 MW 4.43 MW
924302 AB2-077 E O1 Adder 1.64 MW 1.4 MW
924312 AB2-078 E O1 Adder 1.64 MW 1.4 MW
924322 AB2-079 E O1 Adder 1.64 MW 1.4 MW
939181 AE1-148 C Adder 11.58 MW 9.84 MW
939182 AE1-148 E Adder 7.72 MW 6.56 MW
940492 AE2-034 E Adder 4.15 MW 3.53 MW
941031 AE2-094 C 50/50 66.68 MW 66.68 MW
941032 AE2-094 E 50/50 29.87 MW 29.87 MW
946281 AF1-292 C Adder 2.07 MW 1.76 MW
946282 AF1-292 E Adder 1.38 MW 1.17 MW
957481 AF2-042 C 50/50 79.02 MW 79.02 MW
957482 AF2-042 E 50/50 52.68 MW 52.68 MW
957521 AF2-046 C Adder 18.99 MW 16.14 MW
957522 AF2-046 E Adder 9.6 MW 8.16 MW
957861 AF2-080 C Adder 10.22 MW 8.69 MW
957862 AF2-080 E Adder 4.53 MW 3.85 MW
314539 3UNCAMP Adder 8.09 MW 6.88 MW
916042 Z1-036 E Adder 38.53 MW 32.75 MW
938771 AE1-103 C Adder 3.89 MW 3.31 MW
938772 AE1-103 E Adder 5.38 MW 4.57 MW
314331 6POE Adder 1.61 MW 1.37 MW
314507 3THOMPSN Adder 2.7 MW 2.3 MW
314525 6KINGFORK Adder 1.31 MW 1.11 MW
314550 6HICKORY 50/50 2.95 MW 2.95 MW
926662 AC1-147 E Adder 1.77 MW 1.51 MW
926755 AC1-161 E 50/50 18.01 MW 18.01 MW
935112 AD1-144 E Adder 1.21 MW 1.03 MW
942341 AE2-247 C Adder 1.89 MW 1.61 MW
942342 AE2-247 E Adder 2.62 MW 2.22 MW
943461 AF1-017 C Adder 1.71 MW 1.46 MW
943462 AF1-017 E Adder 2.8 MW 2.38 MW
943612 AF1-032 E Adder 1.24 MW 1.05 MW
315102 1BRUNSWICKG1 50/50 13.49 MW 13.49 MW
315103 1BRUNSWICKG2 50/50 13.49 MW 13.49 MW
315104 1BRUNSWICKG3 50/50 13.49 MW 13.49 MW
315105 1BRUNSWICKS1 50/50 28.03 MW 28.03 MW
315108 1ELIZAR1 50/50 4.29 MW 4.29 MW
315109 1ELIZAR2 50/50 4.21 MW 4.21 MW
315110 1ELIZAR3 50/50 4.34 MW 4.34 MW
315241 1Z1-086 GT1 50/50 17.34 MW 17.34 MW
315242 1Z1-086 GT2 50/50 17.34 MW 17.34 MW
315243 1Z1-086 GT3 50/50 17.34 MW 17.34 MW
315244 1Z1-086 ST 50/50 30.18 MW 30.18 MW
315260 1GOSPORTA Adder 2.85 MW 2.42 MW
315261 1GOSPORTB Adder 3.64 MW 3.1 MW
315262 1GOSPORTC Adder 3.09 MW 2.63 MW
913392 Y1-086 E Adder 2.97 MW 2.52 MW
916192 Z1-068 E 50/50 2.53 MW 2.53 MW
923832 AB2-022 E Adder 1.68 MW 1.42 MW
923852 AB2-025 E 50/50 1.6 MW 1.6 MW
939312 AE1-162 E Adder 1.72 MW 1.46 MW
957492 AF2-043 E Adder 1.91 MW 1.62 MW
901082 W1-029 E Adder 42.96 MW 36.51 MW
917122 Z2-027 E Adder 1.81 MW 1.54 MW
925522 AC1-027 E 50/50 1.64 MW 1.64 MW
957871 AF2-081 C 50/50 13.52 MW 13.52 MW
957872 AF2-081 E 50/50 5.79 MW 5.79 MW
958161 AF2-110 C Adder 1.81 MW 1.54 MW
958162 AF2-110 E Adder 2.88 MW 2.45 MW
917512 Z2-088 E OP1 Adder 6.55 MW 5.57 MW
926071 AC1-086 C Adder 28.24 MW 24.0 MW
926072 AC1-086 E Adder 12.85 MW 10.92 MW
927021 AC1-189 C Adder 11.26 MW 9.57 MW
927022 AC1-189 E Adder 5.61 MW 4.77 MW
933291 AC2-141 C 50/50 42.18 MW 42.18 MW
933292 AC2-141 E 50/50 18.01 MW 18.01 MW
934621 AD1-088 C 50/50 17.53 MW 17.53 MW
934622 AD1-088 E 50/50 8.25 MW 8.25 MW
939411 AE1-173 C 50/50 144.74 MW 144.74 MW
939412 AE1-173 E 50/50 96.49 MW 96.49 MW
916191 Z1-068 C 50/50 0.06 MW 0.06 MW
933981 AD1-022 C Adder 11.79 MW 10.02 MW
933982 AD1-022 E Adder 6.42 MW 5.46 MW
962572 AG1-106 E Adder 1.6 MW 1.36 MW
961681 AG1-008 C Adder 18.99 MW 16.14 MW
961682 AG1-008 E Adder 9.6 MW 8.16 MW
962571 AG1-106 C Adder 3.65 MW 3.1 MW
314594 6PLYMOUTH TP Adder 0.44 MW 0.37 MW
314632 6AYDLETT TAP 50/50 1.83 MW 1.83 MW
316185 AD1-033 C 50/50 1.66 MW 1.66 MW
316263 AC1-034 C Adder 8.85 MW 7.52 MW
316274 AC1-208 C Adder 12.05 MW 10.24 MW
316294 AC1-161 C 50/50 6.87 MW 6.87 MW
316315 AB2-025 C 50/50 0.56 MW 0.56 MW
316316 AC1-027 C 50/50 0.42 MW 0.42 MW
917332 KELFORD E Adder 2.2 MW 1.87 MW
924516 AB2-100 E1 Adder 3.93 MW 3.34 MW
924517 AB2-100 E2 Adder 3.93 MW 3.34 MW
925595 AC1-034 E Adder 6.68 MW 5.67 MW
926206 AC1-098 E Adder 4.88 MW 4.15 MW
926214 AC1-099 E Adder 1.61 MW 1.37 MW
927255 AC1-221 E Adder 4.85 MW 4.12 MW
932763 AC2-100 E Adder 2.91 MW 2.47 MW
934065 AD1-033 E 50/50 6.79 MW 6.79 MW
937226 AE2-253 E 50/50 7.91 MW 7.91 MW
918512 AA1-065 E OP Adder 7.43 MW 6.31 MW
316017 AA1-139 ULT1 50/50 1.46 MW 1.46 MW
316018 AA1-139 ULT2 50/50 1.46 MW 1.46 MW
919153 AA1-139 E2 50/50 5.53 MW 5.53 MW
919152 AA1-139 E1 50/50 5.53 MW 5.53 MW
919710 AA2-057 E Adder 5.3 MW 4.5 MW
920692 AA2-178 E Adder 5.54 MW 4.71 MW
923994 AB2-040_E Adder 8.22 MW 6.99 MW
924022 AB2-043 E O1 Adder 6.36 MW 5.4 MW
924152 AB2-059 E OP Adder 7.04 MW 5.98 MW
316084 AB2-161 E Adder 6.56 MW 5.57 MW
925122 AB2-169 E Adder 7.72 MW 6.56 MW
316088 AB2-174 E Adder 8.71 MW 7.41 MW
316375 AC2-012 C 50/50 1.8 MW 1.8 MW
932046 AC2-012 E 50/50 17.55 MW 17.55 MW
316311 AC2-079 C Adder 7.32 MW 6.22 MW
932596 AC2-079 E Adder 11.95 MW 10.15 MW
934576 AD1-082 E Adder 5.22 MW 4.44 MW
316349 AD2-085 C Adder 4.37 MW 3.71 MW
936666 AD2-085 E Adder 7.13 MW 6.06 MW
316388 AE2-253 GEN 50/50 2.65 MW 2.65 MW
941591 AE2-156 C 50/50 24.01 MW 24.01 MW
944581 AF1-123 C 50/50 62.37 MW 62.37 MW
944582 AF1-123 E 50/50 142.83 MW 142.83 MW
944591 AF1-124 C 50/50 62.6 MW 62.6 MW
944592 AF1-124 E 50/50 143.35 MW 143.35 MW
944601 AF1-125 C 50/50 61.41 MW 61.41 MW
944602 AF1-125 E 50/50 140.59 MW 140.59 MW
962491 AG1-098 C 50/50 15.55 MW 15.55 MW
962492 AG1-098 E 50/50 10.37 MW 10.37 MW
962561 AG1-105 C Adder 11.12 MW 9.45 MW
962562 AG1-105 E Adder 7.41 MW 6.3 MW
313764 3SOCKMAN Adder 0.95 MW 0.81 MW
932632 AC2-084 E Adder 4.32 MW 3.67 MW
934321 AD1-056 C Adder 8.38 MW 7.12 MW
934322 AD1-056 E Adder 4.54 MW 3.86 MW
934331 AD1-057 C Adder 4.67 MW 3.97 MW
934332 AD1-057 E Adder 2.43 MW 2.07 MW
934501 AD1-074 C Adder 45.36 MW 38.56 MW
934502 AD1-074 E Adder 23.09 MW 19.63 MW
934511 AD1-075 C Adder 11.34 MW 9.64 MW
934512 AD1-075 E Adder 5.77 MW 4.91 MW
934611 AD1-087 C 50/50 1.77 MW 1.77 MW
934612 AD1-087 E 50/50 5.14 MW 5.14 MW
935172 AD1-152 E Adder 7.57 MW 6.44 MW
937481 AD2-202 C 50/50 0.52 MW 0.52 MW
937482 AD2-202 E 50/50 1.5 MW 1.5 MW
938531 AE1-072 C 50/50 23.77 MW 23.77 MW
938532 AE1-072 E 50/50 12.39 MW 12.39 MW
939191 AE1-149 C Adder 12.1 MW 10.29 MW
939192 AE1-149 E Adder 8.07 MW 6.86 MW
940481 AE2-033 C 50/50 22.31 MW 22.31 MW
940482 AE2-033 E 50/50 15.04 MW 15.04 MW
940541 AE2-040 C 50/50 3.97 MW 3.97 MW
940641 AE2-051 C 50/50 28.87 MW 28.87 MW
940642 AE2-051 E 50/50 19.25 MW 19.25 MW
941101 AE2-104 C Adder 4.44 MW 3.77 MW
941102 AE2-104 E Adder 7.06 MW 6.0 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 55.26 MW 55.26 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 35.54 MW 35.54 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 136.08 MW 136.08 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 5.66 MW 5.66 MW
NY PJM->LTFIMP_NY CLTF 2.58 MW 2.58 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.19 MW 2.19 MW
WEC LTFEXP_WEC->PJM CLTF 1.14 MW 1.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 15.98 MW 15.98 MW
TVA LTFEXP_TVA->PJM CLTF 9.35 MW 9.35 MW
MEC LTFEXP_MEC->PJM CLTF 6.59 MW 6.59 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.8 MW 11.8 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.42 MW 0.42 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 36.0 MW 36.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 7.62 MW 7.62 MW

Details for 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line l/o DVP_P4-2: SPOTS H1T594_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line
314918 to 314911 ckt 1
Contingency Name:
DVP_P4-2: SPOTS H1T594_SRT-S
CONTINGENCY 'DVP_P4-2: SPOTS H1T594_SRT-S'
 OPEN BRANCH FROM BUS 314755 TO BUS 314934 CKT 1                /*3SPOTSYL     115.0 - 8SPOTSYL     500.0
 OPEN BRANCH FROM BUS 314916 TO BUS 314934 CKT 1                /*8MORRSVL     500.0 - 8SPOTSYL     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314900 TO BUS 314916 CKT 1 /*8BRISTER     500.0 - 8MORRSVL     500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 112.93 %
Rating: 3940.0 MVA
Rating Type: C
MVA to Mitigate: 4449.5 MVA
MW Contribution: 8.56 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.73 MW 0.62 MW
961672 AG1-007 E Adder 0.41 MW 0.35 MW
961791 AG1-021 C Adder 1.49 MW 1.27 MW
961792 AG1-021 E Adder 1.27 MW 1.08 MW
961941 AG1-037 C Adder 0.39 MW 0.33 MW
961942 AG1-037 E Adder 0.26 MW 0.22 MW
962331 AG1-082 C Adder 1.57 MW 1.33 MW
962332 AG1-082 E Adder 1.04 MW 0.89 MW
963041 AG1-153 C Adder 5.36 MW 4.56 MW
963042 AG1-153 E Adder 8.04 MW 6.84 MW
963171 AG1-166 C Adder 0.83 MW 0.7 MW
963172 AG1-166 E Adder 1.94 MW 1.65 MW
963181 AG1-167 C Adder 0.62 MW 0.53 MW
963182 AG1-167 E Adder 1.45 MW 1.23 MW
963191 AG1-168 C Adder 0.62 MW 0.53 MW
963192 AG1-168 E Adder 1.45 MW 1.23 MW
964791 AG1-342 C Adder 2.89 MW 2.46 MW
964792 AG1-342 E Adder 1.93 MW 1.64 MW
966801 AG1-551 C Adder 1.62 MW 1.38 MW
966802 AG1-551 E Adder 0.85 MW 0.73 MW
966811 AG1-552 C Adder 1.64 MW 1.4 MW
966812 AG1-552 E Adder 0.78 MW 0.67 MW
965291 AG1-394 C Adder 0.66 MW 0.56 MW
965292 AG1-394 E Adder 1.22 MW 1.04 MW
966621 AG1-532 C Adder 1.14 MW 0.97 MW
966622 AG1-532 E Adder 0.76 MW 0.65 MW
313853 3PONTONDP Adder 0.55 MW 0.47 MW
314541 3WATKINS Adder 0.53 MW 0.45 MW
314572 3EMPORIA Adder 0.35 MW 0.3 MW
314713 3PAMPLIN Adder 0.83 MW 0.7 MW
315131 1EDGECMA Adder 12.12 MW 10.3 MW
918492 AA1-063AE OP Adder 3.23 MW 2.75 MW
918532 AA1-067 E Adder 0.55 MW 0.47 MW
919692 AA2-053 E OP Adder 3.36 MW 2.86 MW
920042 AA2-088 E OP Adder 8.23 MW 6.99 MW
925785 AC1-054 E Adder 2.8 MW 2.38 MW
926274 AC1-105 E Adder 2.18 MW 1.85 MW
927146 AC1-208 E Adder 3.16 MW 2.69 MW
934521 AD1-076 C Adder 9.33 MW 7.93 MW
934522 AD1-076 E Adder 4.76 MW 4.04 MW
943172 AE2-346 E Adder 0.47 MW 0.4 MW
943902 AF1-058 E Adder 1.04 MW 0.89 MW
944011 AF1-069 C 50/50 12.66 MW 12.66 MW
944012 AF1-069 E 50/50 4.92 MW 4.92 MW
959311 AF2-222 C Adder 13.84 MW 11.76 MW
959312 AF2-222 E Adder 9.27 MW 7.88 MW
960061 AF2-297 C Adder 6.26 MW 5.33 MW
960062 AF2-297 E Adder 4.18 MW 3.55 MW
960081 AF2-299 C Adder 1.53 MW 1.3 MW
960082 AF2-299 E Adder 1.02 MW 0.86 MW
316141 AB2-099 E Adder 0.2 MW 0.17 MW
900672 V4-068 E Adder 0.28 MW 0.23 MW
917342 Z2-044 E Adder 0.47 MW 0.4 MW
922923 AB1-081 E OP Adder 2.91 MW 2.48 MW
923263 AB1-132 E OP Adder 4.88 MW 4.15 MW
923573 AB1-173 E OP Adder 2.66 MW 2.26 MW
924162 AB2-060 E OP Adder 3.55 MW 3.02 MW
924302 AB2-077 E O1 Adder 1.11 MW 0.94 MW
924312 AB2-078 E O1 Adder 1.11 MW 0.94 MW
924322 AB2-079 E O1 Adder 1.11 MW 0.94 MW
925612 AC1-036 E Adder 0.71 MW 0.61 MW
938371 AE1-056 C Adder 5.36 MW 4.56 MW
938372 AE1-056 E Adder 2.93 MW 2.49 MW
939181 AE1-148 C Adder 7.46 MW 6.34 MW
939182 AE1-148 E Adder 4.97 MW 4.22 MW
940492 AE2-034 E Adder 2.34 MW 1.99 MW
941031 AE2-094 C 50/50 38.74 MW 38.74 MW
941032 AE2-094 E 50/50 17.35 MW 17.35 MW
946281 AF1-292 C Adder 1.26 MW 1.07 MW
946282 AF1-292 E Adder 0.84 MW 0.72 MW
946301 AF1-294 C Adder 3.07 MW 2.61 MW
946302 AF1-294 E Adder 2.6 MW 2.21 MW
957481 AF2-042 C Adder 49.08 MW 41.72 MW
957482 AF2-042 E Adder 32.72 MW 27.81 MW
957521 AF2-046 C Adder 11.02 MW 9.37 MW
957522 AF2-046 E Adder 5.57 MW 4.73 MW
957861 AF2-080 C Adder 5.93 MW 5.04 MW
957862 AF2-080 E Adder 2.63 MW 2.23 MW
958211 AF2-115 C Adder 1.87 MW 1.59 MW
958212 AF2-115 E Adder 1.59 MW 1.35 MW
314539 3UNCAMP Adder 4.63 MW 3.93 MW
916042 Z1-036 E Adder 21.5 MW 18.27 MW
938771 AE1-103 C Adder 2.22 MW 1.89 MW
938772 AE1-103 E Adder 3.06 MW 2.6 MW
924032 AB2-045 E Adder 1.09 MW 0.93 MW
933502 AC2-165 E Adder 6.93 MW 5.89 MW
314331 6POE Adder 1.04 MW 0.89 MW
314507 3THOMPSN Adder 1.48 MW 1.26 MW
314525 6KINGFORK Adder 0.72 MW 0.62 MW
314550 6HICKORY Adder 1.62 MW 1.37 MW
315083 1SPRUNCA Adder 6.12 MW 5.21 MW
315084 1SPRUNCB Adder 6.12 MW 5.21 MW
926662 AC1-147 E Adder 0.97 MW 0.83 MW
926755 AC1-161 E Adder 9.51 MW 8.08 MW
935112 AD1-144 E Adder 0.67 MW 0.57 MW
942341 AE2-247 C Adder 1.1 MW 0.93 MW
942342 AE2-247 E Adder 1.52 MW 1.29 MW
943461 AF1-017 C Adder 0.99 MW 0.84 MW
943462 AF1-017 E Adder 1.62 MW 1.38 MW
943612 AF1-032 E Adder 0.68 MW 0.58 MW
958502 AF2-144 E Adder 1.16 MW 0.98 MW
315172 1LOISA A 50/50 3.09 MW 3.09 MW
315173 1LOISA B 50/50 3.11 MW 3.11 MW
315174 1LOISA C 50/50 3.11 MW 3.11 MW
315175 1LOISA D 50/50 3.11 MW 3.11 MW
315176 1LOISA E 50/50 6.33 MW 6.33 MW
315177 1S ANNAG1 50/50 3.05 MW 3.05 MW
315178 1S ANNAS1 50/50 1.57 MW 1.57 MW
315179 1S ANNAG2 50/50 3.05 MW 3.05 MW
315180 1S ANNAS2 50/50 1.57 MW 1.57 MW
315225 1N ANNA1 50/50 106.86 MW 106.86 MW
315226 1N ANNA2 50/50 106.89 MW 106.89 MW
315260 1GOSPORTA Adder 1.56 MW 1.33 MW
315261 1GOSPORTB Adder 2.0 MW 1.7 MW
315262 1GOSPORTC Adder 1.7 MW 1.44 MW
913392 Y1-086 E Adder 1.64 MW 1.39 MW
916192 Z1-068 E Adder 1.39 MW 1.18 MW
923832 AB2-022 E Adder 0.92 MW 0.79 MW
923852 AB2-025 E Adder 0.98 MW 0.83 MW
923862 AB2-026 E Adder 1.18 MW 1.0 MW
925022 AB2-158 E 50/50 11.37 MW 11.37 MW
938552 AE1-074 E Adder 1.09 MW 0.93 MW
938562 AE1-075 E Adder 1.0 MW 0.85 MW
939312 AE1-162 E Adder 0.98 MW 0.83 MW
957492 AF2-043 E Adder 1.05 MW 0.9 MW
966001 AG1-469 C 50/50 2.01 MW 2.01 MW
966002 AG1-469 E 50/50 1.0 MW 1.0 MW
901082 W1-029 E Adder 23.78 MW 20.22 MW
917122 Z2-027 E Adder 1.0 MW 0.85 MW
925522 AC1-027 E Adder 0.9 MW 0.76 MW
942001 AE2-212 C Adder 1.49 MW 1.26 MW
942002 AE2-212 E Adder 0.99 MW 0.84 MW
957871 AF2-081 C Adder 7.41 MW 6.3 MW
957872 AF2-081 E Adder 3.18 MW 2.7 MW
958161 AF2-110 C Adder 1.02 MW 0.86 MW
958162 AF2-110 E Adder 1.62 MW 1.37 MW
314722 3TWITTYS Adder 0.79 MW 0.67 MW
917512 Z2-088 E OP1 Adder 3.81 MW 3.23 MW
926071 AC1-086 C Adder 16.78 MW 14.27 MW
926072 AC1-086 E Adder 7.64 MW 6.49 MW
927021 AC1-189 C Adder 6.53 MW 5.55 MW
927022 AC1-189 E Adder 3.25 MW 2.76 MW
936261 AD2-033 C Adder 10.8 MW 9.18 MW
936262 AD2-033 E Adder 7.2 MW 6.12 MW
933291 AC2-141 C Adder 22.28 MW 18.93 MW
933292 AC2-141 E Adder 9.51 MW 8.08 MW
934621 AD1-088 C Adder 11.37 MW 9.66 MW
934622 AD1-088 E Adder 5.35 MW 4.55 MW
939411 AE1-173 C Adder 81.87 MW 69.59 MW
939412 AE1-173 E Adder 54.58 MW 46.4 MW
933981 AD1-022 C Adder 6.7 MW 5.69 MW
933982 AD1-022 E Adder 3.65 MW 3.1 MW
962572 AG1-106 E Adder 0.95 MW 0.81 MW
961681 AG1-008 C Adder 11.02 MW 9.37 MW
961682 AG1-008 E Adder 5.57 MW 4.73 MW
962571 AG1-106 C Adder 2.17 MW 1.84 MW
208900 BRIS G1 50/50 -2.49 MW -2.49 MW
208901 BRIS G2 50/50 -2.94 MW -2.94 MW
314594 6PLYMOUTH TP Adder 0.25 MW 0.21 MW
314632 6AYDLETT TAP Adder 1.01 MW 0.86 MW
316192 AB2-158 C 50/50 4.28 MW 4.28 MW
316233 AE1-074 C Adder 2.17 MW 1.85 MW
316263 AC1-034 C Adder 5.19 MW 4.41 MW
316274 AC1-208 C Adder 7.11 MW 6.05 MW
316336 AC2-165 C Adder 9.2 MW 7.82 MW
917332 KELFORD E Adder 1.28 MW 1.09 MW
924516 AB2-100 E1 Adder 2.37 MW 2.01 MW
924517 AB2-100 E2 Adder 2.37 MW 2.01 MW
925595 AC1-034 E Adder 3.91 MW 3.33 MW
926206 AC1-098 E Adder 2.87 MW 2.44 MW
926214 AC1-099 E Adder 0.95 MW 0.81 MW
927255 AC1-221 E Adder 2.96 MW 2.52 MW
927264 AC1-222 E Adder 3.21 MW 2.73 MW
932763 AC2-100 E Adder 2.01 MW 1.71 MW
934065 AD1-033 E Adder 3.71 MW 3.16 MW
937226 AE2-253 E Adder 4.33 MW 3.68 MW
918512 AA1-065 E OP Adder 4.26 MW 3.62 MW
919153 AA1-139 E2 Adder 3.03 MW 2.58 MW
919152 AA1-139 E1 Adder 3.03 MW 2.58 MW
919710 AA2-057 E Adder 3.11 MW 2.65 MW
920692 AA2-178 E Adder 3.12 MW 2.65 MW
923994 AB2-040_E Adder 4.98 MW 4.23 MW
924022 AB2-043 E O1 Adder 4.3 MW 3.65 MW
924152 AB2-059 E OP Adder 4.12 MW 3.51 MW
316084 AB2-161 E Adder 4.02 MW 3.42 MW
925122 AB2-169 E Adder 4.41 MW 3.75 MW
316088 AB2-174 E Adder 5.29 MW 4.5 MW
316044 AC1-158 C1 50/50 19.57 MW 19.57 MW
316045 AC1-158 C2 50/50 19.57 MW 19.57 MW
926739 AC1-158 E1 50/50 51.19 MW 51.19 MW
926740 AC1-158 E2 50/50 51.19 MW 51.19 MW
932046 AC2-012 E Adder 9.62 MW 8.18 MW
316311 AC2-079 C Adder 4.23 MW 3.59 MW
932596 AC2-079 E Adder 6.9 MW 5.86 MW
934576 AD1-082 E Adder 3.2 MW 2.72 MW
316349 AD2-085 C Adder 2.53 MW 2.15 MW
936666 AD2-085 E Adder 4.14 MW 3.52 MW
941591 AE2-156 C Adder 13.16 MW 11.18 MW
944581 AF1-123 C Adder 33.89 MW 28.81 MW
944582 AF1-123 E Adder 77.61 MW 65.97 MW
944591 AF1-124 C Adder 34.01 MW 28.91 MW
944592 AF1-124 E Adder 77.89 MW 66.2 MW
944601 AF1-125 C Adder 33.37 MW 28.36 MW
944602 AF1-125 E Adder 76.39 MW 64.93 MW
962491 AG1-098 C Adder 10.18 MW 8.66 MW
962492 AG1-098 E Adder 6.79 MW 5.77 MW
962561 AG1-105 C Adder 7.27 MW 6.18 MW
962562 AG1-105 E Adder 4.85 MW 4.12 MW
964241 AG1-285 C Adder 10.39 MW 8.83 MW
964242 AG1-285 E Adder 6.93 MW 5.89 MW
313764 3SOCKMAN Adder 0.57 MW 0.49 MW
932632 AC2-084 E Adder 2.54 MW 2.15 MW
934321 AD1-056 C Adder 4.94 MW 4.2 MW
934322 AD1-056 E Adder 2.68 MW 2.28 MW
934331 AD1-057 C Adder 2.75 MW 2.34 MW
934332 AD1-057 E Adder 1.43 MW 1.22 MW
934501 AD1-074 C Adder 25.7 MW 21.84 MW
934502 AD1-074 E Adder 13.08 MW 11.12 MW
934511 AD1-075 C Adder 6.42 MW 5.46 MW
934512 AD1-075 E Adder 3.27 MW 2.78 MW
934612 AD1-087 E Adder 3.22 MW 2.73 MW
935172 AD1-152 E Adder 4.73 MW 4.02 MW
937482 AD2-202 E Adder 0.94 MW 0.8 MW
938531 AE1-072 C Adder 13.04 MW 11.09 MW
938532 AE1-072 E Adder 6.8 MW 5.78 MW
939191 AE1-149 C Adder 7.73 MW 6.57 MW
939192 AE1-149 E Adder 5.15 MW 4.38 MW
940481 AE2-033 C Adder 13.56 MW 11.52 MW
940482 AE2-033 E Adder 9.14 MW 7.77 MW
940541 AE2-040 C Adder 2.41 MW 2.05 MW
940641 AE2-051 C 50/50 16.48 MW 16.48 MW
940642 AE2-051 E 50/50 10.99 MW 10.99 MW
941101 AE2-104 C Adder 2.49 MW 2.12 MW
941102 AE2-104 E Adder 3.96 MW 3.36 MW
942461 AE2-259 C Adder 8.28 MW 7.04 MW
942462 AE2-259 E Adder 5.52 MW 4.69 MW
316303 AF2-085 50/50 4.05 MW 4.05 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 20.0 MW 20.0 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 16.82 MW 16.82 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 77.12 MW 77.12 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 5.06 MW 5.06 MW
NY PJM->LTFIMP_NY CLTF 2.37 MW 2.37 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.87 MW 0.87 MW
WEC LTFEXP_WEC->PJM CLTF 0.43 MW 0.43 MW
CPLE LTFEXP_CPLE->PJM CLTF 9.25 MW 9.25 MW
TVA LTFEXP_TVA->PJM CLTF 4.72 MW 4.72 MW
MEC LTFEXP_MEC->PJM CLTF 2.78 MW 2.78 MW
LAGN LTFEXP_LAGN->PJM CLTF 5.96 MW 5.96 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.17 MW 0.17 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 32.2 MW 32.2 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 4.41 MW 4.41 MW

Details for 6CARSON-6POE 230.0 kV Ckt 1 line l/o DVP_P4-2: 562T563_SRT-S


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6CARSON-6POE 230.0 kV Ckt 1 line
314282 to 314331 ckt 1
Contingency Name:
DVP_P4-2: 562T563_SRT-S
CONTINGENCY 'DVP_P4-2: 562T563_SRT-S'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 OPEN BRANCH FROM BUS 314902 TO BUS 940640 CKT 1                /*8CARSON      500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
 SET PRECONTRATING 2650 BRANCH FROM BUS 314923 TO BUS 314927 CKT 1 /*8SEPTA       500.0 - 8YADKIN      500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.1 %
Rating: 830.0 MVA
Rating Type: C
MVA to Mitigate: 847.45 MVA
MW Contribution: 3.79 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.35 MW 0.29 MW
961672 AG1-007 E Adder 0.2 MW 0.17 MW
961791 AG1-021 C Adder 0.55 MW 0.47 MW
961792 AG1-021 E Adder 0.47 MW 0.4 MW
963041 AG1-153 C Adder 2.74 MW 2.33 MW
963042 AG1-153 E Adder 4.12 MW 3.5 MW
963171 AG1-166 C Adder 0.31 MW 0.26 MW
963172 AG1-166 E Adder 0.72 MW 0.61 MW
963181 AG1-167 C Adder 0.23 MW 0.2 MW
963182 AG1-167 E Adder 0.54 MW 0.46 MW
963191 AG1-168 C Adder 0.23 MW 0.2 MW
963192 AG1-168 E Adder 0.54 MW 0.46 MW
964791 AG1-342 C Adder 1.36 MW 1.15 MW
964792 AG1-342 E Adder 0.9 MW 0.77 MW
966811 AG1-552 C Adder 0.87 MW 0.74 MW
966812 AG1-552 E Adder 0.41 MW 0.35 MW
966621 AG1-532 C Adder 0.79 MW 0.67 MW
966622 AG1-532 E Adder 0.53 MW 0.45 MW
313853 3PONTONDP Adder 0.2 MW 0.17 MW
314572 3EMPORIA Adder 0.24 MW 0.2 MW
315131 1EDGECMA Adder 6.19 MW 5.26 MW
918492 AA1-063AE OP Adder 1.4 MW 1.19 MW
918532 AA1-067 E Adder 0.23 MW 0.19 MW
919692 AA2-053 E OP Adder 1.68 MW 1.43 MW
925785 AC1-054 E Adder 1.4 MW 1.19 MW
926274 AC1-105 E Adder 1.03 MW 0.87 MW
927146 AC1-208 E Adder 1.56 MW 1.33 MW
943902 AF1-058 E Adder 0.49 MW 0.42 MW
944011 AF1-069 C Adder 6.53 MW 5.55 MW
944012 AF1-069 E Adder 2.54 MW 2.16 MW
959311 AF2-222 C Adder 5.64 MW 4.79 MW
959312 AF2-222 E Adder 3.78 MW 3.21 MW
960061 AF2-297 C Adder 2.96 MW 2.52 MW
960062 AF2-297 E Adder 1.97 MW 1.68 MW
960081 AF2-299 C Adder 1.05 MW 0.89 MW
960082 AF2-299 E Adder 0.7 MW 0.6 MW
917342 Z2-044 E Adder 0.23 MW 0.2 MW
922923 AB1-081 E OP Adder 1.48 MW 1.26 MW
923263 AB1-132 E OP Adder 3.05 MW 2.59 MW
923573 AB1-173 E OP Adder 1.63 MW 1.39 MW
924162 AB2-060 E OP Adder 1.64 MW 1.39 MW
924302 AB2-077 E O1 Adder 0.52 MW 0.44 MW
924312 AB2-078 E O1 Adder 0.52 MW 0.44 MW
924322 AB2-079 E O1 Adder 0.52 MW 0.44 MW
925612 AC1-036 E Adder 0.3 MW 0.25 MW
939181 AE1-148 C Adder 3.56 MW 3.03 MW
939182 AE1-148 E Adder 2.37 MW 2.02 MW
941031 AE2-094 C Adder 19.98 MW 16.99 MW
941032 AE2-094 E Adder 8.95 MW 7.61 MW
946281 AF1-292 C Adder 0.87 MW 0.74 MW
946282 AF1-292 E Adder 0.58 MW 0.49 MW
946301 AF1-294 C Adder 1.13 MW 0.96 MW
946302 AF1-294 E Adder 0.96 MW 0.82 MW
957481 AF2-042 C Adder 23.55 MW 20.02 MW
957482 AF2-042 E Adder 15.7 MW 13.35 MW
957861 AF2-080 C Adder 2.62 MW 2.23 MW
957862 AF2-080 E Adder 1.16 MW 0.99 MW
958211 AF2-115 C Adder 0.69 MW 0.59 MW
958212 AF2-115 E Adder 0.59 MW 0.5 MW
923852 AB2-025 E 50/50 0.95 MW 0.95 MW
314722 3TWITTYS Adder 0.33 MW 0.28 MW
917512 Z2-088 E OP1 Adder 1.75 MW 1.49 MW
926071 AC1-086 C Adder 10.48 MW 8.91 MW
926072 AC1-086 E Adder 4.77 MW 4.05 MW
927021 AC1-189 C Adder 2.89 MW 2.46 MW
927022 AC1-189 E Adder 1.44 MW 1.22 MW
936261 AD2-033 C Adder 4.58 MW 3.89 MW
936262 AD2-033 E Adder 3.05 MW 2.59 MW
934621 AD1-088 C Adder 5.21 MW 4.43 MW
934622 AD1-088 E Adder 2.45 MW 2.08 MW
939411 AE1-173 C Adder 32.06 MW 27.25 MW
939412 AE1-173 E Adder 21.37 MW 18.17 MW
962572 AG1-106 E Adder 0.59 MW 0.5 MW
962571 AG1-106 C Adder 1.36 MW 1.15 MW
316023 AB2-100 C2 50/50 0.61 MW 0.61 MW
316240 AF1-291 C Adder -1.85 MW -1.57 MW
316263 AC1-034 C Adder 2.63 MW 2.24 MW
316274 AC1-208 C Adder 3.51 MW 2.99 MW
316315 AB2-025 C 50/50 0.33 MW 0.33 MW
316365 AB2-100 C1 50/50 0.61 MW 0.61 MW
917332 KELFORD E Adder 0.52 MW 0.44 MW
924516 AB2-100 E1 50/50 1.84 MW 1.84 MW
924517 AB2-100 E2 50/50 1.84 MW 1.84 MW
925595 AC1-034 E Adder 1.98 MW 1.69 MW
926206 AC1-098 E Adder 1.35 MW 1.15 MW
926214 AC1-099 E Adder 0.44 MW 0.38 MW
927255 AC1-221 E Adder 1.42 MW 1.21 MW
927264 AC1-222 E Adder 1.51 MW 1.28 MW
932763 AC2-100 E Adder 0.97 MW 0.82 MW
919710 AA2-057 E Adder 1.54 MW 1.31 MW
923994 AB2-040_E Adder 3.06 MW 2.6 MW
924022 AB2-043 E O1 Adder 2.0 MW 1.7 MW
924152 AB2-059 E OP Adder 2.09 MW 1.78 MW
316088 AB2-174 E Adder 3.38 MW 2.87 MW
962491 AG1-098 C Adder 4.61 MW 3.92 MW
962492 AG1-098 E Adder 3.08 MW 2.61 MW
962561 AG1-105 C Adder 3.41 MW 2.9 MW
962562 AG1-105 E Adder 2.27 MW 1.93 MW
964241 AG1-285 C Adder 4.65 MW 3.95 MW
964242 AG1-285 E Adder 3.1 MW 2.63 MW
313764 3SOCKMAN Adder 0.32 MW 0.28 MW
932632 AC2-084 E Adder 1.19 MW 1.01 MW
934321 AD1-056 C Adder 2.76 MW 2.35 MW
934322 AD1-056 E Adder 1.5 MW 1.27 MW
934331 AD1-057 C Adder 1.54 MW 1.31 MW
934332 AD1-057 E Adder 0.8 MW 0.68 MW
934612 AD1-087 E Adder 1.53 MW 1.3 MW
935172 AD1-152 E Adder 2.25 MW 1.91 MW
937482 AD2-202 E Adder 0.45 MW 0.38 MW
940481 AE2-033 C 50/50 12.83 MW 12.83 MW
940482 AE2-033 E 50/50 8.65 MW 8.65 MW
940541 AE2-040 C 50/50 2.34 MW 2.34 MW
944641 AF1-129 C Adder -63.64 MW -54.09 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.57 MW 15.57 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 9.85 MW 9.85 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 38.44 MW 38.44 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.02 MW 1.02 MW
NY PJM->LTFIMP_NY CLTF 0.46 MW 0.46 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.6 MW 0.6 MW
WEC LTFEXP_WEC->PJM CLTF 0.32 MW 0.32 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.56 MW 4.56 MW
TVA LTFEXP_TVA->PJM CLTF 2.58 MW 2.58 MW
MEC LTFEXP_MEC->PJM CLTF 1.83 MW 1.83 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.27 MW 3.27 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.12 MW 0.12 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 6.48 MW 6.48 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.17 MW 2.17 MW

Details for 3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line l/o DVP_P7-1: LN 2058-2181_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: CPLE/DVP
Facility Description:
3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
314554 to 304223 ckt 1
Contingency Name:
DVP_P7-1: LN 2058-2181_SRT-A
CONTINGENCY 'DVP_P7-1: LN 2058-2181_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 120.73 %
Rating: 313.0 MVA
Rating Type: B
MVA to Mitigate: 377.88 MVA
MW Contribution: 7.95 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.94 MW 0.94 MW
961672 AG1-007 E 50/50 0.53 MW 0.53 MW
961941 AG1-037 C Adder 0.26 MW 0.22 MW
961942 AG1-037 E Adder 0.18 MW 0.15 MW
962331 AG1-082 C Adder 1.06 MW 0.9 MW
962332 AG1-082 E Adder 0.7 MW 0.6 MW
966801 AG1-551 C Adder 0.81 MW 0.69 MW
966802 AG1-551 E Adder 0.43 MW 0.36 MW
966811 AG1-552 C 50/50 1.27 MW 1.27 MW
966812 AG1-552 E 50/50 0.6 MW 0.6 MW
965291 AG1-394 C Adder 0.39 MW 0.33 MW
965292 AG1-394 E Adder 0.71 MW 0.6 MW
966621 AG1-532 C Adder 0.6 MW 0.51 MW
966622 AG1-532 E Adder 0.4 MW 0.34 MW
314541 3WATKINS Adder 0.24 MW 0.21 MW
314572 3EMPORIA Adder 0.19 MW 0.17 MW
315126 1ROARAP2 50/50 0.85 MW 0.85 MW
315128 1ROARAP4 50/50 0.81 MW 0.81 MW
315131 1EDGECMA 50/50 21.15 MW 21.15 MW
315136 1ROSEMG1 50/50 1.4 MW 1.4 MW
315137 1ROSEMS1 50/50 0.87 MW 0.87 MW
315138 1ROSEMG2 50/50 0.65 MW 0.65 MW
315139 1GASTONA 50/50 1.87 MW 1.87 MW
918492 AA1-063AE OP Adder 2.25 MW 1.92 MW
918532 AA1-067 E Adder 0.28 MW 0.24 MW
919692 AA2-053 E OP 50/50 2.55 MW 2.55 MW
920042 AA2-088 E OP Adder 4.66 MW 3.96 MW
925785 AC1-054 E Adder 1.22 MW 1.03 MW
927146 AC1-208 E 50/50 6.05 MW 6.05 MW
934521 AD1-076 C Adder 3.96 MW 3.37 MW
934522 AD1-076 E Adder 2.02 MW 1.72 MW
943172 AE2-346 E Adder 0.32 MW 0.27 MW
960081 AF2-299 C Adder 0.8 MW 0.68 MW
960082 AF2-299 E Adder 0.53 MW 0.45 MW
315601 1CONETOE2SOL 50/50 1.1 MW 1.1 MW
315606 3AA2-053SOLA 50/50 0.91 MW 0.91 MW
316141 AB2-099 E Adder 0.13 MW 0.11 MW
900672 V4-068 E Adder 0.17 MW 0.14 MW
917342 Z2-044 E 50/50 1.49 MW 1.49 MW
922923 AB1-081 E OP 50/50 10.12 MW 10.12 MW
923263 AB1-132 E OP 50/50 3.76 MW 3.76 MW
923573 AB1-173 E OP Adder 1.69 MW 1.43 MW
946281 AF1-292 C Adder 0.66 MW 0.56 MW
946282 AF1-292 E Adder 0.44 MW 0.37 MW
957521 AF2-046 C Adder 6.92 MW 5.88 MW
957522 AF2-046 E Adder 3.5 MW 2.97 MW
957861 AF2-080 C 50/50 5.51 MW 5.51 MW
957862 AF2-080 E 50/50 2.44 MW 2.44 MW
314539 3UNCAMP Adder 1.92 MW 1.63 MW
315141 1GASTONB 50/50 1.87 MW 1.87 MW
917512 Z2-088 E OP1 50/50 4.3 MW 4.3 MW
926071 AC1-086 C 50/50 12.93 MW 12.93 MW
926072 AC1-086 E 50/50 5.88 MW 5.88 MW
927021 AC1-189 C 50/50 6.07 MW 6.07 MW
927022 AC1-189 E 50/50 3.02 MW 3.02 MW
933981 AD1-022 C Adder 3.04 MW 2.58 MW
933982 AD1-022 E Adder 1.65 MW 1.41 MW
962572 AG1-106 E 50/50 0.73 MW 0.73 MW
961681 AG1-008 C Adder 6.92 MW 5.88 MW
961682 AG1-008 E Adder 3.5 MW 2.97 MW
962571 AG1-106 C 50/50 1.67 MW 1.67 MW
316011 AB1-132 C OP 50/50 1.43 MW 1.43 MW
316049 AB1-081 C OP 50/50 3.85 MW 3.85 MW
316210 AC1-098 C 50/50 1.35 MW 1.35 MW
316212 AC1-099 C 50/50 0.45 MW 0.45 MW
316263 AC1-034 C 50/50 18.04 MW 18.04 MW
316274 AC1-208 C 50/50 13.63 MW 13.63 MW
316317 KELFORD C 50/50 0.3 MW 0.3 MW
316319 Z2-044 C 50/50 0.52 MW 0.52 MW
917332 KELFORD E 50/50 1.4 MW 1.4 MW
924516 AB2-100 E1 Adder 1.26 MW 1.07 MW
924517 AB2-100 E2 Adder 1.26 MW 1.07 MW
925595 AC1-034 E 50/50 13.61 MW 13.61 MW
926206 AC1-098 E 50/50 5.25 MW 5.25 MW
926214 AC1-099 E 50/50 1.73 MW 1.73 MW
918512 AA1-065 E OP Adder 2.28 MW 1.94 MW
316327 AA2-057 C 50/50 2.75 MW 2.75 MW
919710 AA2-057 E 50/50 8.42 MW 8.42 MW
923994 AB2-040_E Adder 3.16 MW 2.69 MW
316359 AB2-059 C OP 50/50 4.53 MW 4.53 MW
924152 AB2-059 E OP 50/50 14.34 MW 14.34 MW
925122 AB2-169 E Adder 2.07 MW 1.76 MW
316088 AB2-174 E Adder 3.18 MW 2.7 MW
313764 3SOCKMAN Adder 0.41 MW 0.34 MW
932631 AC2-084 C 50/50 1.44 MW 1.44 MW
932632 AC2-084 E 50/50 4.64 MW 4.64 MW
934321 AD1-056 C 50/50 6.63 MW 6.63 MW
934322 AD1-056 E 50/50 3.6 MW 3.6 MW
934331 AD1-057 C 50/50 3.7 MW 3.7 MW
934332 AD1-057 E 50/50 1.93 MW 1.93 MW
934501 AD1-074 C Adder 10.91 MW 9.27 MW
934502 AD1-074 E Adder 5.55 MW 4.72 MW
934511 AD1-075 C Adder 2.73 MW 2.32 MW
934512 AD1-075 E Adder 1.39 MW 1.18 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.18 MW 0.18 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.5 MW 0.5 MW
VTF LTFEXP_VFT->PJM CMTX 1.34 MW 1.34 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 2.74 MW 2.74 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 1.6 MW 1.6 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.8 MW 0.8 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 2.52 MW 2.52 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.45 MW 0.45 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 1.41 MW 1.41 MW
MDU PJM->LTFIMP_MDU CLTF 0.09 MW 0.09 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.9 MW 0.9 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 2.51 MW 2.51 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
OP AC 181.31 % 571.52 B 1036.21 14.68
DVP 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
OP AC 176.21 % 571.52 B 1007.06 14.68
DVP 6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Base Case OP AC 134.6 % 678.68 A 913.5 9.73
DVP AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Base Case OP AC 131.63 % 678.68 A 893.32 9.74
DVP 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
OP AC 132.32 % 1058.16 B 1400.18 4.8
DVP 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Base Case OP AC 123.93 % 571.52 A 708.28 11.48
DVP 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Base Case OP AC 116.78 % 678.68 A 792.59 9.74
DVP 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Base Case OP AC 118.96 % 571.52 A 679.89 11.48
DVP 8SEPTA-8SURRY 500.0 kV Ckt 1 line
314923 to 314924 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
OP AC 110.23 % 2442.12 B 2691.94 8.58
DVP 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line
314203 to 314637 ckt 1
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
OP AC 109.65 % 733.2 B 803.98 10.78
DVP 6CHOWAN-6PEMBROKE 230.0 kV Ckt 1 line
313015 to 313714 ckt 1
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
OP AC 108.94 % 733.2 B 798.78 10.78
DVP 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Base Case OP AC 105.73 % 3220.44 A 3404.98 12.45
DVP 6EDENTON-6CHOWAN 230.0 kV Ckt 1 line
314637 to 313015 ckt 1
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
OP AC 101.17 % 789.6 B 798.82 10.78
DVP 6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
OP AC 107.46 % 984.18 B 1057.62 3.88
DVP 6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
OP AC 107.41 % 984.18 B 1057.1 3.88
DVP 6CHARCTY-6LAKESIDE 230.0 kV Ckt 1 line
314225 to 314227 ckt 1
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
OP AC 103.84 % 984.18 B 1021.97 3.88
CPLE/DVP 6HATHAWAY-6ROCKYMT230T 230.0 kV Ckt 1 line
313845 to 304222 ckt 1
DVP_P1-2: LN 2181_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2181_SRT-A'
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
OP AC 108.56 % 478.0 B 518.89 16.98
CPLE/DVP 6NASH-6PA-RMOUNT#4 230.0 kV Ckt 1 line
314591 to 304226 ckt 1
DVP_P1-2: LN 2058_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2058_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
END
OP AC 108.45 % 478.0 B 518.4 16.57

Details for 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2092_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 181.31 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 1036.21 MVA
MW Contribution: 14.68 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 185.82 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 1062.0 MVA
MW Contribution: 15.05 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.01 MW 1.01 MW
961672 AG1-007 E 50/50 0.57 MW 0.57 MW
961941 AG1-037 C 50/50 0.91 MW 0.91 MW
961942 AG1-037 E 50/50 0.6 MW 0.6 MW
962331 AG1-082 C 50/50 3.62 MW 3.62 MW
962332 AG1-082 E 50/50 2.41 MW 2.41 MW
966801 AG1-551 C 50/50 3.46 MW 3.46 MW
966802 AG1-551 E 50/50 1.82 MW 1.82 MW
966811 AG1-552 C 50/50 1.92 MW 1.92 MW
966812 AG1-552 E 50/50 0.91 MW 0.91 MW
965291 AG1-394 C 50/50 0.61 MW 0.61 MW
965292 AG1-394 E 50/50 1.13 MW 1.13 MW
966621 AG1-532 C 50/50 0.86 MW 0.86 MW
966622 AG1-532 E 50/50 0.58 MW 0.58 MW
313506 AB1-173 C OP 50/50 0.86 MW 0.86 MW
314572 3EMPORIA 50/50 0.28 MW 0.28 MW
315126 1ROARAP2 50/50 1.29 MW 1.29 MW
315128 1ROARAP4 50/50 1.22 MW 1.22 MW
315131 1EDGECMA 50/50 14.36 MW 14.36 MW
315136 1ROSEMG1 50/50 2.0 MW 2.0 MW
315137 1ROSEMS1 50/50 1.24 MW 1.24 MW
315138 1ROSEMG2 50/50 0.94 MW 0.94 MW
315139 1GASTONA 50/50 3.02 MW 3.02 MW
918492 AA1-063AE OP 50/50 3.46 MW 3.46 MW
918532 AA1-067 E 50/50 1.11 MW 1.11 MW
919692 AA2-053 E OP 50/50 4.75 MW 4.75 MW
920042 AA2-088 E OP 50/50 7.01 MW 7.01 MW
925785 AC1-054 E Adder 2.01 MW 1.71 MW
927146 AC1-208 E 50/50 5.19 MW 5.19 MW
934521 AD1-076 C 50/50 24.97 MW 24.97 MW
934522 AD1-076 E 50/50 12.73 MW 12.73 MW
943171 AE2-346 C 50/50 0.4 MW 0.4 MW
943172 AE2-346 E 50/50 1.08 MW 1.08 MW
960081 AF2-299 C 50/50 1.15 MW 1.15 MW
960082 AF2-299 E 50/50 0.77 MW 0.77 MW
315601 1CONETOE2SOL 50/50 1.53 MW 1.53 MW
315606 3AA2-053SOLA 50/50 1.69 MW 1.69 MW
316140 AB2-099 C 50/50 0.17 MW 0.17 MW
316141 AB2-099 E 50/50 0.45 MW 0.45 MW
900672 V4-068 E 50/50 0.4 MW 0.4 MW
917342 Z2-044 E 50/50 0.83 MW 0.83 MW
922923 AB1-081 E OP 50/50 3.94 MW 3.94 MW
923263 AB1-132 E OP 50/50 6.05 MW 6.05 MW
923573 AB1-173 E OP 50/50 2.5 MW 2.5 MW
940491 AE2-034 C 50/50 2.33 MW 2.33 MW
940492 AE2-034 E 50/50 6.23 MW 6.23 MW
946281 AF1-292 C 50/50 0.95 MW 0.95 MW
946282 AF1-292 E 50/50 0.64 MW 0.64 MW
957521 AF2-046 C 50/50 17.77 MW 17.77 MW
957522 AF2-046 E 50/50 8.98 MW 8.98 MW
957861 AF2-080 C 50/50 10.17 MW 10.17 MW
957862 AF2-080 E 50/50 4.51 MW 4.51 MW
916042 Z1-036 E 50/50 56.9 MW 56.9 MW
315141 1GASTONB 50/50 3.02 MW 3.02 MW
315292 1DOMTR78 50/50 2.64 MW 2.64 MW
315607 3AA1-063SOLA 50/50 1.19 MW 1.19 MW
315608 3AA2-088SOLA 50/50 0.7 MW 0.7 MW
315611 6Z1-036WIND 50/50 1.31 MW 1.31 MW
917512 Z2-088 E OP1 50/50 5.99 MW 5.99 MW
926071 AC1-086 C 50/50 20.79 MW 20.79 MW
926072 AC1-086 E 50/50 9.46 MW 9.46 MW
927021 AC1-189 C 50/50 11.2 MW 11.2 MW
927022 AC1-189 E 50/50 5.58 MW 5.58 MW
933981 AD1-022 C 50/50 18.32 MW 18.32 MW
933982 AD1-022 E 50/50 9.97 MW 9.97 MW
962572 AG1-106 E 50/50 1.18 MW 1.18 MW
961681 AG1-008 C 50/50 17.77 MW 17.77 MW
961682 AG1-008 E 50/50 8.98 MW 8.98 MW
962571 AG1-106 C 50/50 2.69 MW 2.69 MW
314594 6PLYMOUTH TP 50/50 0.66 MW 0.66 MW
316005 AA1-067 C 50/50 0.42 MW 0.42 MW
316011 AB1-132 C OP 50/50 2.31 MW 2.31 MW
316023 AB2-100 C2 50/50 0.6 MW 0.6 MW
316049 AB1-081 C OP 50/50 1.5 MW 1.5 MW
316210 AC1-098 C 50/50 1.38 MW 1.38 MW
316212 AC1-099 C 50/50 0.46 MW 0.46 MW
316263 AC1-034 C 50/50 6.84 MW 6.84 MW
316274 AC1-208 C 50/50 11.68 MW 11.68 MW
316317 KELFORD C 50/50 0.65 MW 0.65 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.29 MW 0.29 MW
316365 AB2-100 C1 50/50 0.6 MW 0.6 MW
917332 KELFORD E 50/50 2.98 MW 2.98 MW
924516 AB2-100 E1 50/50 1.82 MW 1.82 MW
924517 AB2-100 E2 50/50 1.82 MW 1.82 MW
925595 AC1-034 E 50/50 5.16 MW 5.16 MW
926206 AC1-098 E 50/50 5.32 MW 5.32 MW
926214 AC1-099 E 50/50 1.76 MW 1.76 MW
315602 1HOLLOMANSOL 50/50 4.11 MW 4.11 MW
918512 AA1-065 E OP 50/50 12.36 MW 12.36 MW
316327 AA2-057 C 50/50 1.78 MW 1.78 MW
919710 AA2-057 E 50/50 5.42 MW 5.42 MW
315614 AA2-178 C 50/50 3.17 MW 3.17 MW
920692 AA2-178 E 50/50 8.3 MW 8.3 MW
316181 AB2-040 GEN 50/50 0.97 MW 0.97 MW
923994 AB2-040_E 50/50 4.69 MW 4.69 MW
316359 AB2-059 C OP 50/50 1.68 MW 1.68 MW
924152 AB2-059 E OP 50/50 5.31 MW 5.31 MW
316174 AB2-169_C 50/50 1.89 MW 1.89 MW
925122 AB2-169 E 50/50 10.4 MW 10.4 MW
316087 AB2-174 C 50/50 0.84 MW 0.84 MW
316088 AB2-174 E 50/50 4.68 MW 4.68 MW
313764 3SOCKMAN 50/50 0.61 MW 0.61 MW
932631 AC2-084 C 50/50 1.46 MW 1.46 MW
932632 AC2-084 E 50/50 4.7 MW 4.7 MW
934321 AD1-056 C 50/50 5.93 MW 5.93 MW
934322 AD1-056 E 50/50 3.22 MW 3.22 MW
934331 AD1-057 C 50/50 3.31 MW 3.31 MW
934332 AD1-057 E 50/50 1.72 MW 1.72 MW
934501 AD1-074 C 50/50 68.76 MW 68.76 MW
934502 AD1-074 E 50/50 35.01 MW 35.01 MW
934511 AD1-075 C 50/50 17.19 MW 17.19 MW
934512 AD1-075 E 50/50 8.75 MW 8.75 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.3 MW 12.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.06 MW 8.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 35.94 MW 35.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.59 MW 0.59 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.46 MW 0.46 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.94 MW 4.94 MW
TVA LTFEXP_TVA->PJM CLTF 2.13 MW 2.13 MW
MEC LTFEXP_MEC->PJM CLTF 1.47 MW 1.47 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.73 MW 2.73 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.76 MW 3.76 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.35 MW 2.35 MW

Details for 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2092_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 176.21 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 1007.06 MVA
MW Contribution: 14.68 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
DVP_P1-2: LN 2092_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2092_SRT-A'
 OPEN BRANCH FROM BUS 313714 TO BUS 313885 CKT 1   /*6PEMBROKE    230.0 - 6WALBMRL     230.0
 OPEN BRANCH FROM BUS 313885 TO BUS 314662 CKT 1   /*6WALBMRL     230.0 - 6S HERTFORD  230.0
 OPEN BRANCH FROM BUS 314651 TO BUS 314662 CKT 1   /*6WINFALL     230.0 - 6S HERTFORD  230.0
 OPEN BUS 313885                                   /*6WALBMRL     230.0
 OPEN BUS 314662                                   /*6S HERTFORD  230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 180.71 %
Rating: 571.52 MVA
Rating Type: B
MVA to Mitigate: 1032.82 MVA
MW Contribution: 15.05 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.01 MW 1.01 MW
961672 AG1-007 E 50/50 0.57 MW 0.57 MW
961941 AG1-037 C 50/50 0.91 MW 0.91 MW
961942 AG1-037 E 50/50 0.6 MW 0.6 MW
962331 AG1-082 C 50/50 3.62 MW 3.62 MW
962332 AG1-082 E 50/50 2.41 MW 2.41 MW
966801 AG1-551 C 50/50 3.46 MW 3.46 MW
966802 AG1-551 E 50/50 1.82 MW 1.82 MW
966811 AG1-552 C 50/50 1.92 MW 1.92 MW
966812 AG1-552 E 50/50 0.91 MW 0.91 MW
965291 AG1-394 C 50/50 0.61 MW 0.61 MW
965292 AG1-394 E 50/50 1.13 MW 1.13 MW
966621 AG1-532 C 50/50 0.86 MW 0.86 MW
966622 AG1-532 E 50/50 0.58 MW 0.58 MW
313506 AB1-173 C OP 50/50 0.86 MW 0.86 MW
314572 3EMPORIA 50/50 0.28 MW 0.28 MW
315126 1ROARAP2 50/50 1.29 MW 1.29 MW
315128 1ROARAP4 50/50 1.22 MW 1.22 MW
315131 1EDGECMA 50/50 14.36 MW 14.36 MW
315136 1ROSEMG1 50/50 2.0 MW 2.0 MW
315137 1ROSEMS1 50/50 1.24 MW 1.24 MW
315138 1ROSEMG2 50/50 0.94 MW 0.94 MW
315139 1GASTONA 50/50 3.02 MW 3.02 MW
918492 AA1-063AE OP 50/50 3.46 MW 3.46 MW
918532 AA1-067 E 50/50 1.11 MW 1.11 MW
919692 AA2-053 E OP 50/50 4.75 MW 4.75 MW
920042 AA2-088 E OP 50/50 7.01 MW 7.01 MW
925785 AC1-054 E Adder 2.01 MW 1.71 MW
927146 AC1-208 E 50/50 5.19 MW 5.19 MW
934521 AD1-076 C 50/50 24.97 MW 24.97 MW
934522 AD1-076 E 50/50 12.73 MW 12.73 MW
943171 AE2-346 C 50/50 0.4 MW 0.4 MW
943172 AE2-346 E 50/50 1.08 MW 1.08 MW
960081 AF2-299 C 50/50 1.15 MW 1.15 MW
960082 AF2-299 E 50/50 0.77 MW 0.77 MW
315601 1CONETOE2SOL 50/50 1.53 MW 1.53 MW
315606 3AA2-053SOLA 50/50 1.69 MW 1.69 MW
316140 AB2-099 C 50/50 0.17 MW 0.17 MW
316141 AB2-099 E 50/50 0.45 MW 0.45 MW
900672 V4-068 E 50/50 0.4 MW 0.4 MW
917342 Z2-044 E 50/50 0.83 MW 0.83 MW
922923 AB1-081 E OP 50/50 3.94 MW 3.94 MW
923263 AB1-132 E OP 50/50 6.05 MW 6.05 MW
923573 AB1-173 E OP 50/50 2.5 MW 2.5 MW
940491 AE2-034 C 50/50 2.33 MW 2.33 MW
940492 AE2-034 E 50/50 6.23 MW 6.23 MW
946281 AF1-292 C 50/50 0.95 MW 0.95 MW
946282 AF1-292 E 50/50 0.64 MW 0.64 MW
957521 AF2-046 C 50/50 17.77 MW 17.77 MW
957522 AF2-046 E 50/50 8.98 MW 8.98 MW
957861 AF2-080 C 50/50 10.17 MW 10.17 MW
957862 AF2-080 E 50/50 4.51 MW 4.51 MW
916042 Z1-036 E 50/50 56.9 MW 56.9 MW
315141 1GASTONB 50/50 3.02 MW 3.02 MW
315292 1DOMTR78 50/50 2.64 MW 2.64 MW
315607 3AA1-063SOLA 50/50 1.19 MW 1.19 MW
315608 3AA2-088SOLA 50/50 0.7 MW 0.7 MW
315611 6Z1-036WIND 50/50 1.31 MW 1.31 MW
917512 Z2-088 E OP1 50/50 5.99 MW 5.99 MW
926071 AC1-086 C 50/50 20.79 MW 20.79 MW
926072 AC1-086 E 50/50 9.46 MW 9.46 MW
927021 AC1-189 C 50/50 11.2 MW 11.2 MW
927022 AC1-189 E 50/50 5.58 MW 5.58 MW
933981 AD1-022 C 50/50 18.32 MW 18.32 MW
933982 AD1-022 E 50/50 9.97 MW 9.97 MW
962572 AG1-106 E 50/50 1.18 MW 1.18 MW
961681 AG1-008 C 50/50 17.77 MW 17.77 MW
961682 AG1-008 E 50/50 8.98 MW 8.98 MW
962571 AG1-106 C 50/50 2.69 MW 2.69 MW
314594 6PLYMOUTH TP 50/50 0.66 MW 0.66 MW
316005 AA1-067 C 50/50 0.42 MW 0.42 MW
316011 AB1-132 C OP 50/50 2.31 MW 2.31 MW
316023 AB2-100 C2 50/50 0.6 MW 0.6 MW
316049 AB1-081 C OP 50/50 1.5 MW 1.5 MW
316210 AC1-098 C 50/50 1.38 MW 1.38 MW
316212 AC1-099 C 50/50 0.46 MW 0.46 MW
316263 AC1-034 C 50/50 6.84 MW 6.84 MW
316274 AC1-208 C 50/50 11.68 MW 11.68 MW
316317 KELFORD C 50/50 0.65 MW 0.65 MW
316318 V4-068 C 50/50 0.09 MW 0.09 MW
316319 Z2-044 C 50/50 0.29 MW 0.29 MW
316365 AB2-100 C1 50/50 0.6 MW 0.6 MW
917332 KELFORD E 50/50 2.98 MW 2.98 MW
924516 AB2-100 E1 50/50 1.82 MW 1.82 MW
924517 AB2-100 E2 50/50 1.82 MW 1.82 MW
925595 AC1-034 E 50/50 5.16 MW 5.16 MW
926206 AC1-098 E 50/50 5.32 MW 5.32 MW
926214 AC1-099 E 50/50 1.76 MW 1.76 MW
315602 1HOLLOMANSOL 50/50 4.11 MW 4.11 MW
918512 AA1-065 E OP 50/50 12.36 MW 12.36 MW
316327 AA2-057 C 50/50 1.78 MW 1.78 MW
919710 AA2-057 E 50/50 5.42 MW 5.42 MW
315614 AA2-178 C 50/50 3.17 MW 3.17 MW
920692 AA2-178 E 50/50 8.3 MW 8.3 MW
316181 AB2-040 GEN 50/50 0.97 MW 0.97 MW
923994 AB2-040_E 50/50 4.69 MW 4.69 MW
316359 AB2-059 C OP 50/50 1.68 MW 1.68 MW
924152 AB2-059 E OP 50/50 5.31 MW 5.31 MW
316174 AB2-169_C 50/50 1.89 MW 1.89 MW
925122 AB2-169 E 50/50 10.4 MW 10.4 MW
316087 AB2-174 C 50/50 0.84 MW 0.84 MW
316088 AB2-174 E 50/50 4.68 MW 4.68 MW
313764 3SOCKMAN 50/50 0.61 MW 0.61 MW
932631 AC2-084 C 50/50 1.46 MW 1.46 MW
932632 AC2-084 E 50/50 4.7 MW 4.7 MW
934321 AD1-056 C 50/50 5.93 MW 5.93 MW
934322 AD1-056 E 50/50 3.22 MW 3.22 MW
934331 AD1-057 C 50/50 3.31 MW 3.31 MW
934332 AD1-057 E 50/50 1.72 MW 1.72 MW
934501 AD1-074 C 50/50 68.76 MW 68.76 MW
934502 AD1-074 E 50/50 35.01 MW 35.01 MW
934511 AD1-075 C 50/50 17.19 MW 17.19 MW
934512 AD1-075 E 50/50 8.75 MW 8.75 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 12.3 MW 12.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 8.06 MW 8.06 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 35.94 MW 35.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.59 MW 0.59 MW
NY PJM->LTFIMP_NY CLTF 0.26 MW 0.26 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.46 MW 0.46 MW
WEC LTFEXP_WEC->PJM CLTF 0.25 MW 0.25 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.94 MW 4.94 MW
TVA LTFEXP_TVA->PJM CLTF 2.13 MW 2.13 MW
MEC LTFEXP_MEC->PJM CLTF 1.47 MW 1.47 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.73 MW 2.73 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.76 MW 3.76 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.35 MW 2.35 MW

Details for 6SAPONY-6CARSON 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 134.6 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 913.5 MVA
MW Contribution: 9.73 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6SAPONY-6CARSON 230.0 kV Ckt 1 line
314435 to 314282 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 140.02 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 950.31 MVA
MW Contribution: 9.84 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.91 MW 0.91 MW
961672 AG1-007 E 50/50 0.51 MW 0.51 MW
961941 AG1-037 C 50/50 0.48 MW 0.48 MW
961942 AG1-037 E 50/50 0.32 MW 0.32 MW
962331 AG1-082 C 50/50 1.93 MW 1.93 MW
962332 AG1-082 E 50/50 1.28 MW 1.28 MW
966801 AG1-551 C 50/50 1.62 MW 1.62 MW
966802 AG1-551 E 50/50 0.85 MW 0.85 MW
966811 AG1-552 C 50/50 3.12 MW 3.12 MW
966812 AG1-552 E 50/50 1.48 MW 1.48 MW
965291 AG1-394 C 50/50 0.79 MW 0.79 MW
965292 AG1-394 E 50/50 1.46 MW 1.46 MW
966621 AG1-532 C 50/50 3.25 MW 3.25 MW
966622 AG1-532 E 50/50 2.17 MW 2.17 MW
313506 AB1-173 C OP 50/50 2.2 MW 2.2 MW
314541 3WATKINS 50/50 0.44 MW 0.44 MW
314572 3EMPORIA 50/50 0.96 MW 0.96 MW
314704 3LAWRENC 50/50 0.55 MW 0.55 MW
315126 1ROARAP2 50/50 2.1 MW 2.1 MW
315128 1ROARAP4 50/50 1.99 MW 1.99 MW
315131 1EDGECMA 50/50 15.81 MW 15.81 MW
315136 1ROSEMG1 50/50 3.92 MW 3.92 MW
315137 1ROSEMS1 50/50 2.43 MW 2.43 MW
315138 1ROSEMG2 50/50 1.84 MW 1.84 MW
315139 1GASTONA 50/50 6.17 MW 6.17 MW
918492 AA1-063AE OP 50/50 5.23 MW 5.23 MW
918532 AA1-067 E 50/50 0.58 MW 0.58 MW
919692 AA2-053 E OP 50/50 5.98 MW 5.98 MW
920042 AA2-088 E OP 50/50 9.43 MW 9.43 MW
925785 AC1-054 E 50/50 3.3 MW 3.3 MW
927146 AC1-208 E 50/50 5.58 MW 5.58 MW
934521 AD1-076 C Adder 7.38 MW 6.27 MW
934522 AD1-076 E Adder 3.76 MW 3.2 MW
943171 AE2-346 C 50/50 0.21 MW 0.21 MW
943172 AE2-346 E 50/50 0.58 MW 0.58 MW
960081 AF2-299 C 50/50 4.33 MW 4.33 MW
960082 AF2-299 E 50/50 2.89 MW 2.89 MW
315601 1CONETOE2SOL 50/50 1.15 MW 1.15 MW
315606 3AA2-053SOLA 50/50 2.13 MW 2.13 MW
316129 AC1-054 C 50/50 1.17 MW 1.17 MW
316140 AB2-099 C 50/50 0.09 MW 0.09 MW
316141 AB2-099 E 50/50 0.24 MW 0.24 MW
900672 V4-068 E 50/50 0.34 MW 0.34 MW
917342 Z2-044 E 50/50 0.85 MW 0.85 MW
922923 AB1-081 E OP 50/50 3.65 MW 3.65 MW
923263 AB1-132 E OP 50/50 12.35 MW 12.35 MW
923573 AB1-173 E OP 50/50 6.39 MW 6.39 MW
946281 AF1-292 C 50/50 3.58 MW 3.58 MW
946282 AF1-292 E 50/50 2.39 MW 2.39 MW
957521 AF2-046 C 50/50 13.35 MW 13.35 MW
957522 AF2-046 E 50/50 6.75 MW 6.75 MW
957861 AF2-080 C 50/50 6.74 MW 6.74 MW
957862 AF2-080 E 50/50 2.99 MW 2.99 MW
315115 1S HAMPT1 50/50 0.98 MW 0.98 MW
315141 1GASTONB 50/50 6.17 MW 6.17 MW
315607 3AA1-063SOLA 50/50 1.8 MW 1.8 MW
315608 3AA2-088SOLA 50/50 0.94 MW 0.94 MW
923852 AB2-025 E 50/50 4.77 MW 4.77 MW
917512 Z2-088 E OP1 50/50 4.5 MW 4.5 MW
926071 AC1-086 C 50/50 42.42 MW 42.42 MW
926072 AC1-086 E 50/50 19.31 MW 19.31 MW
927021 AC1-189 C 50/50 7.42 MW 7.42 MW
927022 AC1-189 E 50/50 3.7 MW 3.7 MW
933981 AD1-022 C 50/50 5.93 MW 5.93 MW
933982 AD1-022 E 50/50 3.23 MW 3.23 MW
962572 AG1-106 E 50/50 2.4 MW 2.4 MW
961681 AG1-008 C 50/50 13.35 MW 13.35 MW
961682 AG1-008 E 50/50 6.75 MW 6.75 MW
962571 AG1-106 C 50/50 5.49 MW 5.49 MW
316005 AA1-067 C 50/50 0.22 MW 0.22 MW
316011 AB1-132 C OP 50/50 4.71 MW 4.71 MW
316023 AB2-100 C2 50/50 2.78 MW 2.78 MW
316049 AB1-081 C OP 50/50 1.39 MW 1.39 MW
316210 AC1-098 C 50/50 1.23 MW 1.23 MW
316212 AC1-099 C 50/50 0.41 MW 0.41 MW
316263 AC1-034 C 50/50 6.56 MW 6.56 MW
316274 AC1-208 C 50/50 12.57 MW 12.57 MW
316315 AB2-025 C 50/50 1.67 MW 1.67 MW
316317 KELFORD C 50/50 0.39 MW 0.39 MW
316318 V4-068 C 50/50 0.07 MW 0.07 MW
316319 Z2-044 C 50/50 0.3 MW 0.3 MW
316365 AB2-100 C1 50/50 2.78 MW 2.78 MW
917332 KELFORD E 50/50 1.77 MW 1.77 MW
924516 AB2-100 E1 50/50 8.38 MW 8.38 MW
924517 AB2-100 E2 50/50 8.38 MW 8.38 MW
925595 AC1-034 E 50/50 4.95 MW 4.95 MW
926206 AC1-098 E 50/50 4.77 MW 4.77 MW
926214 AC1-099 E 50/50 1.57 MW 1.57 MW
315602 1HOLLOMANSOL 50/50 1.63 MW 1.63 MW
918512 AA1-065 E OP 50/50 4.9 MW 4.9 MW
316327 AA2-057 C 50/50 1.83 MW 1.83 MW
919710 AA2-057 E 50/50 5.57 MW 5.57 MW
316181 AB2-040 GEN 50/50 2.48 MW 2.48 MW
923994 AB2-040_E 50/50 11.99 MW 11.99 MW
316359 AB2-059 C OP 50/50 1.67 MW 1.67 MW
924152 AB2-059 E OP 50/50 5.25 MW 5.25 MW
316174 AB2-169_C 50/50 0.73 MW 0.73 MW
925122 AB2-169 E 50/50 4.03 MW 4.03 MW
316087 AB2-174 C 50/50 2.43 MW 2.43 MW
316088 AB2-174 E 50/50 13.45 MW 13.45 MW
313764 3SOCKMAN 50/50 1.22 MW 1.22 MW
932631 AC2-084 C 50/50 1.31 MW 1.31 MW
932632 AC2-084 E 50/50 4.21 MW 4.21 MW
934321 AD1-056 C 50/50 9.01 MW 9.01 MW
934322 AD1-056 E 50/50 4.89 MW 4.89 MW
934331 AD1-057 C 50/50 5.03 MW 5.03 MW
934332 AD1-057 E 50/50 2.62 MW 2.62 MW
934501 AD1-074 C Adder 20.32 MW 17.27 MW
934502 AD1-074 E Adder 10.34 MW 8.79 MW
934511 AD1-075 C Adder 5.08 MW 4.32 MW
934512 AD1-075 E Adder 2.59 MW 2.2 MW
940481 AE2-033 C 50/50 63.91 MW 63.91 MW
940482 AE2-033 E 50/50 43.09 MW 43.09 MW
940541 AE2-040 C 50/50 11.79 MW 11.79 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.88 MW 8.88 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.28 MW 6.28 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 29.69 MW 29.69 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.68 MW 0.68 MW
NY PJM->LTFIMP_NY CLTF 0.31 MW 0.31 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.34 MW 0.34 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.05 MW 4.05 MW
TVA LTFEXP_TVA->PJM CLTF 1.69 MW 1.69 MW
MEC LTFEXP_MEC->PJM CLTF 1.1 MW 1.1 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.17 MW 2.17 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.29 MW 4.29 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.93 MW 1.93 MW

Details for AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 131.63 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 893.32 MVA
MW Contribution: 9.74 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
AE2-033 TP-6SAPONY 230.0 kV Ckt 1 line
940480 to 314435 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 138.66 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 941.05 MVA
MW Contribution: 9.84 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.91 MW 0.91 MW
961672 AG1-007 E 50/50 0.51 MW 0.51 MW
961941 AG1-037 C 50/50 0.48 MW 0.48 MW
961942 AG1-037 E 50/50 0.32 MW 0.32 MW
962331 AG1-082 C 50/50 1.93 MW 1.93 MW
962332 AG1-082 E 50/50 1.28 MW 1.28 MW
966801 AG1-551 C 50/50 1.62 MW 1.62 MW
966802 AG1-551 E 50/50 0.85 MW 0.85 MW
966811 AG1-552 C 50/50 3.12 MW 3.12 MW
966812 AG1-552 E 50/50 1.48 MW 1.48 MW
965291 AG1-394 C 50/50 0.79 MW 0.79 MW
965292 AG1-394 E 50/50 1.46 MW 1.46 MW
966621 AG1-532 C 50/50 3.25 MW 3.25 MW
966622 AG1-532 E 50/50 2.17 MW 2.17 MW
313506 AB1-173 C OP 50/50 2.2 MW 2.2 MW
314541 3WATKINS 50/50 0.44 MW 0.44 MW
314572 3EMPORIA 50/50 0.96 MW 0.96 MW
314704 3LAWRENC 50/50 0.55 MW 0.55 MW
315126 1ROARAP2 50/50 2.1 MW 2.1 MW
315128 1ROARAP4 50/50 1.99 MW 1.99 MW
315131 1EDGECMA 50/50 15.82 MW 15.82 MW
315136 1ROSEMG1 50/50 3.92 MW 3.92 MW
315137 1ROSEMS1 50/50 2.43 MW 2.43 MW
315138 1ROSEMG2 50/50 1.84 MW 1.84 MW
315139 1GASTONA 50/50 6.17 MW 6.17 MW
918492 AA1-063AE OP 50/50 5.24 MW 5.24 MW
918532 AA1-067 E 50/50 0.58 MW 0.58 MW
919692 AA2-053 E OP 50/50 5.99 MW 5.99 MW
920042 AA2-088 E OP 50/50 9.43 MW 9.43 MW
925785 AC1-054 E 50/50 3.3 MW 3.3 MW
927146 AC1-208 E 50/50 5.59 MW 5.59 MW
934521 AD1-076 C Adder 7.38 MW 6.28 MW
934522 AD1-076 E Adder 3.76 MW 3.2 MW
943171 AE2-346 C 50/50 0.21 MW 0.21 MW
943172 AE2-346 E 50/50 0.58 MW 0.58 MW
960081 AF2-299 C 50/50 4.33 MW 4.33 MW
960082 AF2-299 E 50/50 2.89 MW 2.89 MW
315601 1CONETOE2SOL 50/50 1.15 MW 1.15 MW
315606 3AA2-053SOLA 50/50 2.13 MW 2.13 MW
316129 AC1-054 C 50/50 1.17 MW 1.17 MW
316140 AB2-099 C 50/50 0.09 MW 0.09 MW
316141 AB2-099 E 50/50 0.24 MW 0.24 MW
900672 V4-068 E 50/50 0.34 MW 0.34 MW
917342 Z2-044 E 50/50 0.85 MW 0.85 MW
922923 AB1-081 E OP 50/50 3.65 MW 3.65 MW
923263 AB1-132 E OP 50/50 12.35 MW 12.35 MW
923573 AB1-173 E OP 50/50 6.39 MW 6.39 MW
946281 AF1-292 C 50/50 3.59 MW 3.59 MW
946282 AF1-292 E 50/50 2.39 MW 2.39 MW
957521 AF2-046 C 50/50 13.36 MW 13.36 MW
957522 AF2-046 E 50/50 6.75 MW 6.75 MW
957861 AF2-080 C 50/50 6.75 MW 6.75 MW
957862 AF2-080 E 50/50 2.99 MW 2.99 MW
314539 3UNCAMP Adder 3.22 MW 2.73 MW
315115 1S HAMPT1 50/50 0.99 MW 0.99 MW
315141 1GASTONB 50/50 6.17 MW 6.17 MW
315607 3AA1-063SOLA 50/50 1.8 MW 1.8 MW
315608 3AA2-088SOLA 50/50 0.94 MW 0.94 MW
917512 Z2-088 E OP1 50/50 4.5 MW 4.5 MW
926071 AC1-086 C 50/50 42.43 MW 42.43 MW
926072 AC1-086 E 50/50 19.31 MW 19.31 MW
927021 AC1-189 C 50/50 7.43 MW 7.43 MW
927022 AC1-189 E 50/50 3.7 MW 3.7 MW
933981 AD1-022 C 50/50 5.93 MW 5.93 MW
933982 AD1-022 E 50/50 3.23 MW 3.23 MW
962572 AG1-106 E 50/50 2.4 MW 2.4 MW
961681 AG1-008 C 50/50 13.36 MW 13.36 MW
961682 AG1-008 E 50/50 6.75 MW 6.75 MW
962571 AG1-106 C 50/50 5.49 MW 5.49 MW
314594 6PLYMOUTH TP Adder 0.19 MW 0.16 MW
316005 AA1-067 C 50/50 0.22 MW 0.22 MW
316011 AB1-132 C OP 50/50 4.71 MW 4.71 MW
316023 AB2-100 C2 50/50 2.78 MW 2.78 MW
316049 AB1-081 C OP 50/50 1.39 MW 1.39 MW
316210 AC1-098 C 50/50 1.23 MW 1.23 MW
316212 AC1-099 C 50/50 0.41 MW 0.41 MW
316263 AC1-034 C 50/50 6.56 MW 6.56 MW
316274 AC1-208 C 50/50 12.58 MW 12.58 MW
316317 KELFORD C 50/50 0.39 MW 0.39 MW
316318 V4-068 C 50/50 0.07 MW 0.07 MW
316319 Z2-044 C 50/50 0.3 MW 0.3 MW
316365 AB2-100 C1 50/50 2.78 MW 2.78 MW
917332 KELFORD E 50/50 1.78 MW 1.78 MW
924516 AB2-100 E1 50/50 8.38 MW 8.38 MW
924517 AB2-100 E2 50/50 8.38 MW 8.38 MW
925595 AC1-034 E 50/50 4.95 MW 4.95 MW
926206 AC1-098 E 50/50 4.77 MW 4.77 MW
926214 AC1-099 E 50/50 1.58 MW 1.58 MW
315602 1HOLLOMANSOL 50/50 1.63 MW 1.63 MW
918512 AA1-065 E OP 50/50 4.9 MW 4.9 MW
316327 AA2-057 C 50/50 1.83 MW 1.83 MW
919710 AA2-057 E 50/50 5.57 MW 5.57 MW
316181 AB2-040 GEN 50/50 2.48 MW 2.48 MW
923994 AB2-040_E 50/50 11.99 MW 11.99 MW
316359 AB2-059 C OP 50/50 1.67 MW 1.67 MW
924152 AB2-059 E OP 50/50 5.25 MW 5.25 MW
316174 AB2-169_C 50/50 0.73 MW 0.73 MW
925122 AB2-169 E 50/50 4.03 MW 4.03 MW
316087 AB2-174 C 50/50 2.43 MW 2.43 MW
316088 AB2-174 E 50/50 13.45 MW 13.45 MW
313764 3SOCKMAN 50/50 1.22 MW 1.22 MW
932631 AC2-084 C 50/50 1.31 MW 1.31 MW
932632 AC2-084 E 50/50 4.22 MW 4.22 MW
934321 AD1-056 C 50/50 9.02 MW 9.02 MW
934322 AD1-056 E 50/50 4.89 MW 4.89 MW
934331 AD1-057 C 50/50 5.03 MW 5.03 MW
934332 AD1-057 E 50/50 2.62 MW 2.62 MW
934501 AD1-074 C Adder 20.33 MW 17.28 MW
934502 AD1-074 E Adder 10.35 MW 8.8 MW
934511 AD1-075 C Adder 5.08 MW 4.32 MW
934512 AD1-075 E Adder 2.59 MW 2.2 MW
940481 AE2-033 C 50/50 63.92 MW 63.92 MW
940482 AE2-033 E 50/50 43.09 MW 43.09 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 9.0 MW 9.0 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.33 MW 6.33 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 29.76 MW 29.76 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.67 MW 0.67 MW
NY PJM->LTFIMP_NY CLTF 0.31 MW 0.31 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.34 MW 0.34 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.06 MW 4.06 MW
TVA LTFEXP_TVA->PJM CLTF 1.7 MW 1.7 MW
MEC LTFEXP_MEC->PJM CLTF 1.11 MW 1.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.18 MW 2.18 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.25 MW 4.25 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.93 MW 1.93 MW

Details for 8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer l/o DVP_P1-2: LN 576_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
Contingency Name:
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 132.32 %
Rating: 1058.16 MVA
Rating Type: B
MVA to Mitigate: 1400.18 MVA
MW Contribution: 4.8 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
8MDLTHAN-6MDLTHAN 500.0/230.0 kV Ckt 1 transformer
314914 to 314322 ckt 1
Contingency Name:
DVP_P1-2: LN 576_SRT-A
CONTINGENCY 'DVP_P1-2: LN 576_SRT-A'
 OPEN BRANCH FROM BUS 314914 TO BUS 314918 CKT 1   /*8MDLTHAN     500.0 - 8NO ANNA     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 131.81 %
Rating: 1058.16 MVA
Rating Type: B
MVA to Mitigate: 1394.81 MVA
MW Contribution: 4.65 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.41 MW 0.35 MW
961672 AG1-007 E Adder 0.23 MW 0.2 MW
961941 AG1-037 C Adder 0.21 MW 0.18 MW
961942 AG1-037 E Adder 0.14 MW 0.12 MW
962331 AG1-082 C Adder 0.85 MW 0.72 MW
962332 AG1-082 E Adder 0.57 MW 0.48 MW
963041 AG1-153 C 50/50 3.75 MW 3.75 MW
963042 AG1-153 E 50/50 5.62 MW 5.62 MW
964791 AG1-342 C Adder 1.53 MW 1.3 MW
964792 AG1-342 E Adder 1.02 MW 0.87 MW
966801 AG1-551 C Adder 0.91 MW 0.77 MW
966802 AG1-551 E Adder 0.48 MW 0.41 MW
966811 AG1-552 C Adder 0.89 MW 0.75 MW
966812 AG1-552 E Adder 0.42 MW 0.36 MW
965291 AG1-394 C Adder 0.35 MW 0.3 MW
965292 AG1-394 E Adder 0.65 MW 0.55 MW
966621 AG1-532 C Adder 0.6 MW 0.51 MW
966622 AG1-532 E Adder 0.4 MW 0.34 MW
314541 3WATKINS Adder 0.28 MW 0.24 MW
314572 3EMPORIA Adder 0.19 MW 0.16 MW
315131 1EDGECMA Adder 6.83 MW 5.81 MW
918492 AA1-063AE OP Adder 1.73 MW 1.47 MW
918532 AA1-067 E Adder 0.31 MW 0.26 MW
919692 AA2-053 E OP Adder 1.82 MW 1.54 MW
920042 AA2-088 E OP Adder 4.38 MW 3.72 MW
925785 AC1-054 E Adder 1.5 MW 1.28 MW
926274 AC1-105 E Adder 1.17 MW 1.0 MW
927146 AC1-208 E Adder 1.78 MW 1.51 MW
934521 AD1-076 C Adder 5.13 MW 4.36 MW
934522 AD1-076 E Adder 2.62 MW 2.22 MW
943172 AE2-346 E Adder 0.26 MW 0.22 MW
943902 AF1-058 E Adder 0.57 MW 0.48 MW
944011 AF1-069 C 50/50 8.9 MW 8.9 MW
944012 AF1-069 E 50/50 3.46 MW 3.46 MW
959311 AF2-222 C Adder 5.8 MW 4.93 MW
959312 AF2-222 E Adder 3.89 MW 3.31 MW
960061 AF2-297 C Adder 3.42 MW 2.91 MW
960062 AF2-297 E Adder 2.28 MW 1.94 MW
960081 AF2-299 C Adder 0.8 MW 0.68 MW
960082 AF2-299 E Adder 0.54 MW 0.46 MW
316141 AB2-099 E Adder 0.11 MW 0.09 MW
900672 V4-068 E Adder 0.15 MW 0.13 MW
917342 Z2-044 E Adder 0.27 MW 0.23 MW
922923 AB1-081 E OP Adder 1.64 MW 1.4 MW
923263 AB1-132 E OP Adder 2.63 MW 2.23 MW
923573 AB1-173 E OP Adder 1.41 MW 1.2 MW
924162 AB2-060 E OP Adder 1.77 MW 1.51 MW
924302 AB2-077 E O1 Adder 0.57 MW 0.48 MW
924312 AB2-078 E O1 Adder 0.57 MW 0.48 MW
924322 AB2-079 E O1 Adder 0.57 MW 0.48 MW
925612 AC1-036 E Adder 0.31 MW 0.27 MW
939181 AE1-148 C Adder 3.96 MW 3.36 MW
939182 AE1-148 E Adder 2.64 MW 2.24 MW
940492 AE2-034 E Adder 1.28 MW 1.09 MW
941011 AE2-092 C Adder -4.44 MW -3.77 MW
941031 AE2-094 C 50/50 27.23 MW 27.23 MW
941032 AE2-094 E 50/50 12.2 MW 12.2 MW
946281 AF1-292 C Adder 0.66 MW 0.56 MW
946282 AF1-292 E Adder 0.44 MW 0.38 MW
957481 AF2-042 C Adder 29.33 MW 24.93 MW
957482 AF2-042 E Adder 19.55 MW 16.62 MW
957521 AF2-046 C Adder 5.93 MW 5.04 MW
957522 AF2-046 E Adder 3.0 MW 2.55 MW
957861 AF2-080 C Adder 3.33 MW 2.83 MW
957862 AF2-080 E Adder 1.48 MW 1.25 MW
314539 3UNCAMP Adder 2.43 MW 2.06 MW
916042 Z1-036 E Adder 11.81 MW 10.04 MW
938771 AE1-103 C Adder 1.16 MW 0.99 MW
938772 AE1-103 E Adder 1.6 MW 1.36 MW
314507 3THOMPSN Adder 0.8 MW 0.68 MW
314525 6KINGFORK Adder 0.36 MW 0.31 MW
314550 6HICKORY Adder 0.9 MW 0.77 MW
926662 AC1-147 E Adder 0.52 MW 0.45 MW
926755 AC1-161 E Adder 5.65 MW 4.8 MW
935112 AD1-144 E Adder 0.34 MW 0.28 MW
942341 AE2-247 C Adder 0.49 MW 0.42 MW
942342 AE2-247 E Adder 0.68 MW 0.58 MW
943461 AF1-017 C Adder 0.45 MW 0.38 MW
943462 AF1-017 E Adder 0.73 MW 0.62 MW
943612 AF1-032 E Adder 0.37 MW 0.31 MW
315102 1BRUNSWICKG1 50/50 5.53 MW 5.53 MW
315103 1BRUNSWICKG2 50/50 5.53 MW 5.53 MW
315104 1BRUNSWICKG3 50/50 5.53 MW 5.53 MW
315105 1BRUNSWICKS1 50/50 11.49 MW 11.49 MW
315241 1Z1-086 GT1 50/50 7.11 MW 7.11 MW
315242 1Z1-086 GT2 50/50 7.1 MW 7.1 MW
315243 1Z1-086 GT3 50/50 7.1 MW 7.1 MW
315244 1Z1-086 ST 50/50 12.37 MW 12.37 MW
315260 1GOSPORTA Adder 0.84 MW 0.71 MW
315261 1GOSPORTB Adder 1.08 MW 0.91 MW
315262 1GOSPORTC Adder 0.91 MW 0.78 MW
913392 Y1-086 E Adder 0.91 MW 0.77 MW
916192 Z1-068 E Adder 0.76 MW 0.65 MW
923832 AB2-022 E Adder 0.51 MW 0.43 MW
923852 AB2-025 E Adder 0.5 MW 0.43 MW
957492 AF2-043 E Adder 0.57 MW 0.48 MW
901082 W1-029 E Adder 13.03 MW 11.07 MW
917122 Z2-027 E Adder 0.55 MW 0.47 MW
925522 AC1-027 E Adder 0.49 MW 0.42 MW
957871 AF2-081 C Adder 4.13 MW 3.51 MW
957872 AF2-081 E Adder 1.77 MW 1.51 MW
958161 AF2-110 C Adder 0.52 MW 0.44 MW
958162 AF2-110 E Adder 0.83 MW 0.71 MW
314722 3TWITTYS Adder 0.35 MW 0.29 MW
917512 Z2-088 E OP1 Adder 2.14 MW 1.82 MW
926071 AC1-086 C Adder 9.03 MW 7.67 MW
926072 AC1-086 E Adder 4.11 MW 3.49 MW
927021 AC1-189 C Adder 3.67 MW 3.12 MW
927022 AC1-189 E Adder 1.83 MW 1.55 MW
936261 AD2-033 C Adder 4.4 MW 3.74 MW
936262 AD2-033 E Adder 2.93 MW 2.49 MW
933291 AC2-141 C Adder 13.23 MW 11.25 MW
933292 AC2-141 E Adder 5.65 MW 4.8 MW
934621 AD1-088 C Adder 5.98 MW 5.08 MW
934622 AD1-088 E Adder 2.81 MW 2.39 MW
939411 AE1-173 C 50/50 54.42 MW 54.42 MW
939412 AE1-173 E 50/50 36.28 MW 36.28 MW
933981 AD1-022 C Adder 3.68 MW 3.13 MW
933982 AD1-022 E Adder 2.0 MW 1.7 MW
962572 AG1-106 E Adder 0.51 MW 0.43 MW
961681 AG1-008 C Adder 5.93 MW 5.04 MW
961682 AG1-008 E Adder 3.0 MW 2.55 MW
962571 AG1-106 C Adder 1.17 MW 0.99 MW
314594 6PLYMOUTH TP Adder 0.14 MW 0.12 MW
314632 6AYDLETT TAP Adder 0.56 MW 0.48 MW
316263 AC1-034 C Adder 2.92 MW 2.48 MW
316274 AC1-208 C Adder 4.0 MW 3.4 MW
316336 AC2-165 C Adder -10.77 MW -9.16 MW
917332 KELFORD E Adder 0.71 MW 0.6 MW
924516 AB2-100 E1 Adder 1.24 MW 1.06 MW
924517 AB2-100 E2 Adder 1.24 MW 1.06 MW
925595 AC1-034 E Adder 2.21 MW 1.88 MW
926206 AC1-098 E Adder 1.61 MW 1.37 MW
926214 AC1-099 E Adder 0.53 MW 0.45 MW
927255 AC1-221 E Adder 1.7 MW 1.44 MW
927264 AC1-222 E Adder 1.72 MW 1.46 MW
932763 AC2-100 E Adder 1.15 MW 0.98 MW
934065 AD1-033 E Adder 2.07 MW 1.76 MW
937226 AE2-253 E Adder 2.42 MW 2.06 MW
918512 AA1-065 E OP Adder 2.33 MW 1.98 MW
919153 AA1-139 E2 Adder 1.69 MW 1.44 MW
919152 AA1-139 E1 Adder 1.69 MW 1.44 MW
919710 AA2-057 E Adder 1.8 MW 1.53 MW
920692 AA2-178 E Adder 1.71 MW 1.46 MW
923994 AB2-040_E Adder 2.65 MW 2.25 MW
924022 AB2-043 E O1 Adder 2.18 MW 1.86 MW
924152 AB2-059 E OP Adder 2.32 MW 1.98 MW
925122 AB2-169 E Adder 2.45 MW 2.08 MW
316088 AB2-174 E Adder 2.8 MW 2.38 MW
932046 AC2-012 E Adder 5.18 MW 4.4 MW
316311 AC2-079 C Adder 1.94 MW 1.65 MW
932596 AC2-079 E Adder 3.16 MW 2.69 MW
316349 AD2-085 C Adder 1.14 MW 0.97 MW
936666 AD2-085 E Adder 1.86 MW 1.58 MW
941591 AE2-156 C Adder 7.09 MW 6.02 MW
944581 AF1-123 C Adder 18.83 MW 16.0 MW
944582 AF1-123 E Adder 43.11 MW 36.65 MW
944591 AF1-124 C Adder 18.9 MW 16.06 MW
944592 AF1-124 E Adder 43.27 MW 36.78 MW
944601 AF1-125 C Adder 18.54 MW 15.76 MW
944602 AF1-125 E Adder 42.44 MW 36.07 MW
962491 AG1-098 C Adder 5.22 MW 4.44 MW
962492 AG1-098 E Adder 3.48 MW 2.96 MW
962561 AG1-105 C Adder 3.83 MW 3.25 MW
962562 AG1-105 E Adder 2.55 MW 2.17 MW
964241 AG1-285 C Adder 5.56 MW 4.72 MW
964242 AG1-285 E Adder 3.7 MW 3.15 MW
313764 3SOCKMAN Adder 0.31 MW 0.26 MW
932632 AC2-084 E Adder 1.42 MW 1.21 MW
934321 AD1-056 C Adder 2.73 MW 2.32 MW
934322 AD1-056 E Adder 1.48 MW 1.26 MW
934331 AD1-057 C Adder 1.52 MW 1.29 MW
934332 AD1-057 E Adder 0.79 MW 0.67 MW
934501 AD1-074 C Adder 14.13 MW 12.01 MW
934502 AD1-074 E Adder 7.19 MW 6.11 MW
934511 AD1-075 C Adder 3.53 MW 3.0 MW
934512 AD1-075 E Adder 1.8 MW 1.53 MW
934612 AD1-087 E Adder 1.86 MW 1.58 MW
935172 AD1-152 E Adder 2.71 MW 2.31 MW
936161 AD2-022 C Adder 3.15 MW 2.67 MW
936162 AD2-022 E Adder 1.89 MW 1.6 MW
936171 AD2-023 C Adder 1.84 MW 1.56 MW
936172 AD2-023 E Adder 1.0 MW 0.85 MW
937482 AD2-202 E Adder 0.54 MW 0.46 MW
938531 AE1-072 C Adder 7.26 MW 6.17 MW
938532 AE1-072 E Adder 3.79 MW 3.22 MW
938821 AE1-108 C Adder -4.69 MW -3.99 MW
940481 AE2-033 C Adder 6.99 MW 5.94 MW
940482 AE2-033 E Adder 4.71 MW 4.0 MW
940541 AE2-040 C Adder 1.24 MW 1.05 MW
940641 AE2-051 C 50/50 11.4 MW 11.4 MW
940642 AE2-051 E 50/50 7.6 MW 7.6 MW
941101 AE2-104 C Adder 1.28 MW 1.09 MW
941102 AE2-104 E Adder 2.04 MW 1.73 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 11.81 MW 11.81 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 9.22 MW 9.22 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 44.44 MW 44.44 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.11 MW 1.11 MW
NY PJM->LTFIMP_NY CLTF 0.52 MW 0.52 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.46 MW 0.46 MW
WEC LTFEXP_WEC->PJM CLTF 0.24 MW 0.24 MW
CPLE LTFEXP_CPLE->PJM CLTF 5.48 MW 5.48 MW
TVA LTFEXP_TVA->PJM CLTF 2.54 MW 2.54 MW
MEC LTFEXP_MEC->PJM CLTF 1.55 MW 1.55 MW
LAGN LTFEXP_LAGN->PJM CLTF 3.27 MW 3.27 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.09 MW 0.09 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 7.07 MW 7.07 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 2.61 MW 2.61 MW

Details for 6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 123.93 %
Rating: 571.52 MVA
Rating Type: A
MVA to Mitigate: 708.28 MVA
MW Contribution: 11.48 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line
314569 to 314575 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 126.9 %
Rating: 571.52 MVA
Rating Type: A
MVA to Mitigate: 725.24 MVA
MW Contribution: 11.77 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.8 MW 0.8 MW
961672 AG1-007 E 50/50 0.45 MW 0.45 MW
961941 AG1-037 C 50/50 0.76 MW 0.76 MW
961942 AG1-037 E 50/50 0.5 MW 0.5 MW
962331 AG1-082 C 50/50 3.02 MW 3.02 MW
962332 AG1-082 E 50/50 2.02 MW 2.02 MW
966801 AG1-551 C 50/50 2.48 MW 2.48 MW
966802 AG1-551 E 50/50 1.3 MW 1.3 MW
966811 AG1-552 C 50/50 1.59 MW 1.59 MW
966812 AG1-552 E 50/50 0.76 MW 0.76 MW
965291 AG1-394 C 50/50 0.51 MW 0.51 MW
965292 AG1-394 E 50/50 0.93 MW 0.93 MW
966621 AG1-532 C Adder 0.72 MW 0.61 MW
966622 AG1-532 E Adder 0.48 MW 0.41 MW
313506 AB1-173 C OP 50/50 0.71 MW 0.71 MW
314572 3EMPORIA Adder 0.24 MW 0.2 MW
315126 1ROARAP2 50/50 1.07 MW 1.07 MW
315128 1ROARAP4 50/50 1.02 MW 1.02 MW
315131 1EDGECMA 50/50 11.45 MW 11.45 MW
315136 1ROSEMG1 50/50 1.65 MW 1.65 MW
315137 1ROSEMS1 50/50 1.02 MW 1.02 MW
315138 1ROSEMG2 50/50 0.77 MW 0.77 MW
315139 1GASTONA 50/50 2.5 MW 2.5 MW
918492 AA1-063AE OP 50/50 2.87 MW 2.87 MW
918532 AA1-067 E 50/50 0.86 MW 0.86 MW
919692 AA2-053 E OP 50/50 3.95 MW 3.95 MW
920042 AA2-088 E OP Adder 5.77 MW 4.91 MW
925785 AC1-054 E Adder 1.67 MW 1.42 MW
927146 AC1-208 E 50/50 4.32 MW 4.32 MW
934521 AD1-076 C 50/50 12.91 MW 12.91 MW
934522 AD1-076 E 50/50 6.58 MW 6.58 MW
943171 AE2-346 C 50/50 0.34 MW 0.34 MW
943172 AE2-346 E 50/50 0.91 MW 0.91 MW
960081 AF2-299 C Adder 0.96 MW 0.81 MW
960082 AF2-299 E Adder 0.64 MW 0.54 MW
315601 1CONETOE2SOL 50/50 1.2 MW 1.2 MW
315606 3AA2-053SOLA 50/50 1.41 MW 1.41 MW
316140 AB2-099 C 50/50 0.14 MW 0.14 MW
316141 AB2-099 E 50/50 0.38 MW 0.38 MW
900672 V4-068 E 50/50 0.33 MW 0.33 MW
917342 Z2-044 E 50/50 0.69 MW 0.69 MW
922923 AB1-081 E OP 50/50 3.12 MW 3.12 MW
923263 AB1-132 E OP 50/50 5.01 MW 5.01 MW
923573 AB1-173 E OP 50/50 2.08 MW 2.08 MW
940491 AE2-034 C 50/50 0.86 MW 0.86 MW
940492 AE2-034 E 50/50 2.3 MW 2.3 MW
946281 AF1-292 C Adder 0.79 MW 0.67 MW
946282 AF1-292 E Adder 0.53 MW 0.45 MW
957521 AF2-046 C 50/50 14.8 MW 14.8 MW
957522 AF2-046 E 50/50 7.48 MW 7.48 MW
957861 AF2-080 C 50/50 7.95 MW 7.95 MW
957862 AF2-080 E 50/50 3.53 MW 3.53 MW
916042 Z1-036 E Adder 9.77 MW 8.3 MW
315141 1GASTONB 50/50 2.5 MW 2.5 MW
315292 1DOMTR78 50/50 1.48 MW 1.48 MW
315607 3AA1-063SOLA 50/50 0.99 MW 0.99 MW
917512 Z2-088 E OP1 50/50 4.7 MW 4.7 MW
926071 AC1-086 C 50/50 17.22 MW 17.22 MW
926072 AC1-086 E 50/50 7.84 MW 7.84 MW
927021 AC1-189 C 50/50 8.76 MW 8.76 MW
927022 AC1-189 E 50/50 4.36 MW 4.36 MW
933981 AD1-022 C 50/50 11.1 MW 11.1 MW
933982 AD1-022 E 50/50 6.04 MW 6.04 MW
962572 AG1-106 E 50/50 0.97 MW 0.97 MW
961681 AG1-008 C 50/50 14.8 MW 14.8 MW
961682 AG1-008 E 50/50 7.48 MW 7.48 MW
962571 AG1-106 C 50/50 2.23 MW 2.23 MW
314594 6PLYMOUTH TP 50/50 0.33 MW 0.33 MW
316005 AA1-067 C 50/50 0.33 MW 0.33 MW
316011 AB1-132 C OP 50/50 1.91 MW 1.91 MW
316049 AB1-081 C OP 50/50 1.19 MW 1.19 MW
316210 AC1-098 C 50/50 1.15 MW 1.15 MW
316212 AC1-099 C 50/50 0.38 MW 0.38 MW
316263 AC1-034 C 50/50 5.42 MW 5.42 MW
316274 AC1-208 C 50/50 9.74 MW 9.74 MW
316317 KELFORD C 50/50 0.54 MW 0.54 MW
316318 V4-068 C 50/50 0.07 MW 0.07 MW
316319 Z2-044 C 50/50 0.24 MW 0.24 MW
917332 KELFORD E 50/50 2.49 MW 2.49 MW
924516 AB2-100 E1 Adder 1.51 MW 1.29 MW
924517 AB2-100 E2 Adder 1.51 MW 1.29 MW
925595 AC1-034 E 50/50 4.09 MW 4.09 MW
926206 AC1-098 E 50/50 4.44 MW 4.44 MW
926214 AC1-099 E 50/50 1.47 MW 1.47 MW
315602 1HOLLOMANSOL 50/50 3.44 MW 3.44 MW
918512 AA1-065 E OP 50/50 10.35 MW 10.35 MW
316327 AA2-057 C 50/50 1.48 MW 1.48 MW
919710 AA2-057 E 50/50 4.52 MW 4.52 MW
315614 AA2-178 C 50/50 1.17 MW 1.17 MW
920692 AA2-178 E 50/50 3.07 MW 3.07 MW
316181 AB2-040 GEN 50/50 0.81 MW 0.81 MW
923994 AB2-040_E 50/50 3.9 MW 3.9 MW
316359 AB2-059 C OP 50/50 1.34 MW 1.34 MW
924152 AB2-059 E OP 50/50 4.21 MW 4.21 MW
316174 AB2-169_C 50/50 1.18 MW 1.18 MW
925122 AB2-169 E 50/50 6.48 MW 6.48 MW
316087 AB2-174 C 50/50 0.7 MW 0.7 MW
316088 AB2-174 E 50/50 3.88 MW 3.88 MW
313764 3SOCKMAN 50/50 0.51 MW 0.51 MW
932631 AC2-084 C 50/50 1.22 MW 1.22 MW
932632 AC2-084 E 50/50 3.92 MW 3.92 MW
934321 AD1-056 C 50/50 4.81 MW 4.81 MW
934322 AD1-056 E 50/50 2.61 MW 2.61 MW
934331 AD1-057 C 50/50 2.68 MW 2.68 MW
934332 AD1-057 E 50/50 1.4 MW 1.4 MW
934501 AD1-074 C 50/50 35.54 MW 35.54 MW
934502 AD1-074 E 50/50 18.09 MW 18.09 MW
934511 AD1-075 C 50/50 8.89 MW 8.89 MW
934512 AD1-075 E 50/50 4.52 MW 4.52 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 9.85 MW 9.85 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.42 MW 6.42 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 28.5 MW 28.5 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.46 MW 0.46 MW
NY PJM->LTFIMP_NY CLTF 0.21 MW 0.21 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.37 MW 0.37 MW
WEC LTFEXP_WEC->PJM CLTF 0.2 MW 0.2 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.91 MW 3.91 MW
TVA LTFEXP_TVA->PJM CLTF 1.69 MW 1.69 MW
MEC LTFEXP_MEC->PJM CLTF 1.17 MW 1.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.17 MW 2.17 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.95 MW 2.95 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.86 MW 1.86 MW

Details for 6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 116.78 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 792.59 MVA
MW Contribution: 9.74 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line
314563 to 940480 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 125.87 %
Rating: 678.68 MVA
Rating Type: A
MVA to Mitigate: 854.25 MVA
MW Contribution: 9.84 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.91 MW 0.91 MW
961672 AG1-007 E 50/50 0.51 MW 0.51 MW
961941 AG1-037 C 50/50 0.48 MW 0.48 MW
961942 AG1-037 E 50/50 0.32 MW 0.32 MW
962331 AG1-082 C 50/50 1.93 MW 1.93 MW
962332 AG1-082 E 50/50 1.28 MW 1.28 MW
966801 AG1-551 C 50/50 1.62 MW 1.62 MW
966802 AG1-551 E 50/50 0.85 MW 0.85 MW
966811 AG1-552 C 50/50 3.12 MW 3.12 MW
966812 AG1-552 E 50/50 1.48 MW 1.48 MW
965291 AG1-394 C 50/50 0.79 MW 0.79 MW
965292 AG1-394 E 50/50 1.46 MW 1.46 MW
966621 AG1-532 C 50/50 3.25 MW 3.25 MW
966622 AG1-532 E 50/50 2.17 MW 2.17 MW
313506 AB1-173 C OP 50/50 2.2 MW 2.2 MW
314541 3WATKINS 50/50 0.44 MW 0.44 MW
314572 3EMPORIA 50/50 0.96 MW 0.96 MW
314704 3LAWRENC 50/50 0.55 MW 0.55 MW
315126 1ROARAP2 50/50 2.1 MW 2.1 MW
315128 1ROARAP4 50/50 1.99 MW 1.99 MW
315131 1EDGECMA 50/50 15.82 MW 15.82 MW
315136 1ROSEMG1 50/50 3.92 MW 3.92 MW
315137 1ROSEMS1 50/50 2.43 MW 2.43 MW
315138 1ROSEMG2 50/50 1.84 MW 1.84 MW
315139 1GASTONA 50/50 6.17 MW 6.17 MW
918492 AA1-063AE OP 50/50 5.24 MW 5.24 MW
918532 AA1-067 E 50/50 0.58 MW 0.58 MW
919692 AA2-053 E OP 50/50 5.99 MW 5.99 MW
920042 AA2-088 E OP 50/50 9.43 MW 9.43 MW
925785 AC1-054 E 50/50 3.3 MW 3.3 MW
927146 AC1-208 E 50/50 5.59 MW 5.59 MW
934521 AD1-076 C Adder 7.38 MW 6.28 MW
934522 AD1-076 E Adder 3.76 MW 3.2 MW
943171 AE2-346 C 50/50 0.21 MW 0.21 MW
943172 AE2-346 E 50/50 0.58 MW 0.58 MW
960081 AF2-299 C 50/50 4.33 MW 4.33 MW
960082 AF2-299 E 50/50 2.89 MW 2.89 MW
315601 1CONETOE2SOL 50/50 1.15 MW 1.15 MW
315606 3AA2-053SOLA 50/50 2.13 MW 2.13 MW
316129 AC1-054 C 50/50 1.17 MW 1.17 MW
316140 AB2-099 C 50/50 0.09 MW 0.09 MW
316141 AB2-099 E 50/50 0.24 MW 0.24 MW
900672 V4-068 E 50/50 0.34 MW 0.34 MW
917342 Z2-044 E 50/50 0.85 MW 0.85 MW
922923 AB1-081 E OP 50/50 3.65 MW 3.65 MW
923263 AB1-132 E OP 50/50 12.35 MW 12.35 MW
923573 AB1-173 E OP 50/50 6.39 MW 6.39 MW
946281 AF1-292 C 50/50 3.59 MW 3.59 MW
946282 AF1-292 E 50/50 2.39 MW 2.39 MW
957521 AF2-046 C 50/50 13.36 MW 13.36 MW
957522 AF2-046 E 50/50 6.75 MW 6.75 MW
957861 AF2-080 C 50/50 6.75 MW 6.75 MW
957862 AF2-080 E 50/50 2.99 MW 2.99 MW
314539 3UNCAMP Adder 3.22 MW 2.73 MW
315115 1S HAMPT1 50/50 0.99 MW 0.99 MW
315141 1GASTONB 50/50 6.17 MW 6.17 MW
315607 3AA1-063SOLA 50/50 1.8 MW 1.8 MW
315608 3AA2-088SOLA 50/50 0.94 MW 0.94 MW
917512 Z2-088 E OP1 50/50 4.5 MW 4.5 MW
926071 AC1-086 C 50/50 42.43 MW 42.43 MW
926072 AC1-086 E 50/50 19.31 MW 19.31 MW
927021 AC1-189 C 50/50 7.43 MW 7.43 MW
927022 AC1-189 E 50/50 3.7 MW 3.7 MW
933981 AD1-022 C 50/50 5.93 MW 5.93 MW
933982 AD1-022 E 50/50 3.23 MW 3.23 MW
962572 AG1-106 E 50/50 2.4 MW 2.4 MW
961681 AG1-008 C 50/50 13.36 MW 13.36 MW
961682 AG1-008 E 50/50 6.75 MW 6.75 MW
962571 AG1-106 C 50/50 5.49 MW 5.49 MW
314594 6PLYMOUTH TP Adder 0.19 MW 0.16 MW
316005 AA1-067 C 50/50 0.22 MW 0.22 MW
316011 AB1-132 C OP 50/50 4.71 MW 4.71 MW
316023 AB2-100 C2 50/50 2.78 MW 2.78 MW
316049 AB1-081 C OP 50/50 1.39 MW 1.39 MW
316210 AC1-098 C 50/50 1.23 MW 1.23 MW
316212 AC1-099 C 50/50 0.41 MW 0.41 MW
316263 AC1-034 C 50/50 6.56 MW 6.56 MW
316274 AC1-208 C 50/50 12.58 MW 12.58 MW
316317 KELFORD C 50/50 0.39 MW 0.39 MW
316318 V4-068 C 50/50 0.07 MW 0.07 MW
316319 Z2-044 C 50/50 0.3 MW 0.3 MW
316365 AB2-100 C1 50/50 2.78 MW 2.78 MW
917332 KELFORD E 50/50 1.78 MW 1.78 MW
924516 AB2-100 E1 50/50 8.38 MW 8.38 MW
924517 AB2-100 E2 50/50 8.38 MW 8.38 MW
925595 AC1-034 E 50/50 4.95 MW 4.95 MW
926206 AC1-098 E 50/50 4.77 MW 4.77 MW
926214 AC1-099 E 50/50 1.58 MW 1.58 MW
315602 1HOLLOMANSOL 50/50 1.63 MW 1.63 MW
918512 AA1-065 E OP 50/50 4.9 MW 4.9 MW
316327 AA2-057 C 50/50 1.83 MW 1.83 MW
919710 AA2-057 E 50/50 5.57 MW 5.57 MW
316181 AB2-040 GEN 50/50 2.48 MW 2.48 MW
923994 AB2-040_E 50/50 11.99 MW 11.99 MW
316359 AB2-059 C OP 50/50 1.67 MW 1.67 MW
924152 AB2-059 E OP 50/50 5.25 MW 5.25 MW
316174 AB2-169_C 50/50 0.73 MW 0.73 MW
925122 AB2-169 E 50/50 4.03 MW 4.03 MW
316087 AB2-174 C 50/50 2.43 MW 2.43 MW
316088 AB2-174 E 50/50 13.45 MW 13.45 MW
313764 3SOCKMAN 50/50 1.22 MW 1.22 MW
932631 AC2-084 C 50/50 1.31 MW 1.31 MW
932632 AC2-084 E 50/50 4.22 MW 4.22 MW
934321 AD1-056 C 50/50 9.02 MW 9.02 MW
934322 AD1-056 E 50/50 4.89 MW 4.89 MW
934331 AD1-057 C 50/50 5.03 MW 5.03 MW
934332 AD1-057 E 50/50 2.62 MW 2.62 MW
934501 AD1-074 C Adder 20.33 MW 17.28 MW
934502 AD1-074 E Adder 10.35 MW 8.8 MW
934511 AD1-075 C Adder 5.08 MW 4.32 MW
934512 AD1-075 E Adder 2.59 MW 2.2 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 9.0 MW 9.0 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.33 MW 6.33 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 29.76 MW 29.76 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.67 MW 0.67 MW
NY PJM->LTFIMP_NY CLTF 0.31 MW 0.31 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.34 MW 0.34 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 4.06 MW 4.06 MW
TVA LTFEXP_TVA->PJM CLTF 1.7 MW 1.7 MW
MEC LTFEXP_MEC->PJM CLTF 1.11 MW 1.11 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.18 MW 2.18 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 4.25 MW 4.25 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.93 MW 1.93 MW

Details for 6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 118.96 %
Rating: 571.52 MVA
Rating Type: A
MVA to Mitigate: 679.89 MVA
MW Contribution: 11.48 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6NUCO TP-6SUFFOLK 230.0 kV Ckt 1 line
314575 to 314537 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 121.96 %
Rating: 571.52 MVA
Rating Type: A
MVA to Mitigate: 697.0 MVA
MW Contribution: 11.77 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.8 MW 0.8 MW
961672 AG1-007 E 50/50 0.45 MW 0.45 MW
961941 AG1-037 C 50/50 0.76 MW 0.76 MW
961942 AG1-037 E 50/50 0.5 MW 0.5 MW
962331 AG1-082 C 50/50 3.02 MW 3.02 MW
962332 AG1-082 E 50/50 2.02 MW 2.02 MW
966801 AG1-551 C 50/50 2.48 MW 2.48 MW
966802 AG1-551 E 50/50 1.3 MW 1.3 MW
966811 AG1-552 C 50/50 1.59 MW 1.59 MW
966812 AG1-552 E 50/50 0.76 MW 0.76 MW
965291 AG1-394 C 50/50 0.51 MW 0.51 MW
965292 AG1-394 E 50/50 0.93 MW 0.93 MW
966621 AG1-532 C Adder 0.72 MW 0.61 MW
966622 AG1-532 E Adder 0.48 MW 0.41 MW
313506 AB1-173 C OP 50/50 0.71 MW 0.71 MW
314572 3EMPORIA Adder 0.24 MW 0.2 MW
315126 1ROARAP2 50/50 1.07 MW 1.07 MW
315128 1ROARAP4 50/50 1.02 MW 1.02 MW
315131 1EDGECMA 50/50 11.45 MW 11.45 MW
315136 1ROSEMG1 50/50 1.65 MW 1.65 MW
315137 1ROSEMS1 50/50 1.02 MW 1.02 MW
315138 1ROSEMG2 50/50 0.77 MW 0.77 MW
315139 1GASTONA 50/50 2.5 MW 2.5 MW
918492 AA1-063AE OP 50/50 2.87 MW 2.87 MW
918532 AA1-067 E 50/50 0.86 MW 0.86 MW
919692 AA2-053 E OP 50/50 3.95 MW 3.95 MW
920042 AA2-088 E OP Adder 5.77 MW 4.91 MW
925785 AC1-054 E Adder 1.67 MW 1.42 MW
927146 AC1-208 E 50/50 4.32 MW 4.32 MW
934521 AD1-076 C 50/50 12.91 MW 12.91 MW
934522 AD1-076 E 50/50 6.58 MW 6.58 MW
943171 AE2-346 C 50/50 0.34 MW 0.34 MW
943172 AE2-346 E 50/50 0.91 MW 0.91 MW
960081 AF2-299 C Adder 0.96 MW 0.81 MW
960082 AF2-299 E Adder 0.64 MW 0.54 MW
315601 1CONETOE2SOL 50/50 1.2 MW 1.2 MW
315606 3AA2-053SOLA 50/50 1.41 MW 1.41 MW
316140 AB2-099 C 50/50 0.14 MW 0.14 MW
316141 AB2-099 E 50/50 0.38 MW 0.38 MW
900672 V4-068 E 50/50 0.33 MW 0.33 MW
917342 Z2-044 E 50/50 0.69 MW 0.69 MW
922923 AB1-081 E OP 50/50 3.12 MW 3.12 MW
923263 AB1-132 E OP 50/50 5.01 MW 5.01 MW
923573 AB1-173 E OP 50/50 2.08 MW 2.08 MW
940491 AE2-034 C 50/50 0.86 MW 0.86 MW
940492 AE2-034 E 50/50 2.3 MW 2.3 MW
946281 AF1-292 C Adder 0.79 MW 0.67 MW
946282 AF1-292 E Adder 0.53 MW 0.45 MW
957521 AF2-046 C 50/50 14.8 MW 14.8 MW
957522 AF2-046 E 50/50 7.48 MW 7.48 MW
957861 AF2-080 C 50/50 7.95 MW 7.95 MW
957862 AF2-080 E 50/50 3.53 MW 3.53 MW
916042 Z1-036 E Adder 9.77 MW 8.3 MW
315141 1GASTONB 50/50 2.5 MW 2.5 MW
315292 1DOMTR78 50/50 1.48 MW 1.48 MW
315607 3AA1-063SOLA 50/50 0.99 MW 0.99 MW
917512 Z2-088 E OP1 50/50 4.7 MW 4.7 MW
926071 AC1-086 C 50/50 17.22 MW 17.22 MW
926072 AC1-086 E 50/50 7.84 MW 7.84 MW
927021 AC1-189 C 50/50 8.76 MW 8.76 MW
927022 AC1-189 E 50/50 4.36 MW 4.36 MW
933981 AD1-022 C 50/50 11.1 MW 11.1 MW
933982 AD1-022 E 50/50 6.04 MW 6.04 MW
962572 AG1-106 E 50/50 0.97 MW 0.97 MW
961681 AG1-008 C 50/50 14.8 MW 14.8 MW
961682 AG1-008 E 50/50 7.48 MW 7.48 MW
962571 AG1-106 C 50/50 2.23 MW 2.23 MW
314594 6PLYMOUTH TP 50/50 0.33 MW 0.33 MW
316005 AA1-067 C 50/50 0.33 MW 0.33 MW
316011 AB1-132 C OP 50/50 1.91 MW 1.91 MW
316049 AB1-081 C OP 50/50 1.19 MW 1.19 MW
316210 AC1-098 C 50/50 1.15 MW 1.15 MW
316212 AC1-099 C 50/50 0.38 MW 0.38 MW
316263 AC1-034 C 50/50 5.42 MW 5.42 MW
316274 AC1-208 C 50/50 9.74 MW 9.74 MW
316317 KELFORD C 50/50 0.54 MW 0.54 MW
316318 V4-068 C 50/50 0.07 MW 0.07 MW
316319 Z2-044 C 50/50 0.24 MW 0.24 MW
917332 KELFORD E 50/50 2.49 MW 2.49 MW
924516 AB2-100 E1 Adder 1.51 MW 1.29 MW
924517 AB2-100 E2 Adder 1.51 MW 1.29 MW
925595 AC1-034 E 50/50 4.09 MW 4.09 MW
926206 AC1-098 E 50/50 4.44 MW 4.44 MW
926214 AC1-099 E 50/50 1.47 MW 1.47 MW
315602 1HOLLOMANSOL 50/50 3.44 MW 3.44 MW
918512 AA1-065 E OP 50/50 10.35 MW 10.35 MW
316327 AA2-057 C 50/50 1.48 MW 1.48 MW
919710 AA2-057 E 50/50 4.52 MW 4.52 MW
315614 AA2-178 C 50/50 1.17 MW 1.17 MW
920692 AA2-178 E 50/50 3.07 MW 3.07 MW
316181 AB2-040 GEN 50/50 0.81 MW 0.81 MW
923994 AB2-040_E 50/50 3.9 MW 3.9 MW
316359 AB2-059 C OP 50/50 1.34 MW 1.34 MW
924152 AB2-059 E OP 50/50 4.21 MW 4.21 MW
316174 AB2-169_C 50/50 1.18 MW 1.18 MW
925122 AB2-169 E 50/50 6.48 MW 6.48 MW
316087 AB2-174 C 50/50 0.7 MW 0.7 MW
316088 AB2-174 E 50/50 3.88 MW 3.88 MW
313764 3SOCKMAN 50/50 0.51 MW 0.51 MW
932631 AC2-084 C 50/50 1.22 MW 1.22 MW
932632 AC2-084 E 50/50 3.92 MW 3.92 MW
934321 AD1-056 C 50/50 4.81 MW 4.81 MW
934322 AD1-056 E 50/50 2.61 MW 2.61 MW
934331 AD1-057 C 50/50 2.68 MW 2.68 MW
934332 AD1-057 E 50/50 1.4 MW 1.4 MW
934501 AD1-074 C 50/50 35.54 MW 35.54 MW
934502 AD1-074 E 50/50 18.09 MW 18.09 MW
934511 AD1-075 C 50/50 8.89 MW 8.89 MW
934512 AD1-075 E 50/50 4.52 MW 4.52 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 9.85 MW 9.85 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.42 MW 6.42 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 28.5 MW 28.5 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.46 MW 0.46 MW
NY PJM->LTFIMP_NY CLTF 0.21 MW 0.21 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.37 MW 0.37 MW
WEC LTFEXP_WEC->PJM CLTF 0.2 MW 0.2 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.91 MW 3.91 MW
TVA LTFEXP_TVA->PJM CLTF 1.69 MW 1.69 MW
MEC LTFEXP_MEC->PJM CLTF 1.17 MW 1.17 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.17 MW 2.17 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.07 MW 0.07 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.95 MW 2.95 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.86 MW 1.86 MW

Details for 8SEPTA-8SURRY 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8SEPTA-8SURRY 500.0 kV Ckt 1 line
314923 to 314924 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 110.23 %
Rating: 2442.12 MVA
Rating Type: B
MVA to Mitigate: 2691.94 MVA
MW Contribution: 8.58 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
8SEPTA-8SURRY 500.0 kV Ckt 1 line
314923 to 314924 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 115.7 %
Rating: 2442.12 MVA
Rating Type: B
MVA to Mitigate: 2825.65 MVA
MW Contribution: 8.48 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.74 MW 0.63 MW
961672 AG1-007 E Adder 0.42 MW 0.36 MW
961791 AG1-021 C Adder 1.36 MW 1.16 MW
961792 AG1-021 E Adder 1.16 MW 0.98 MW
961941 AG1-037 C Adder 0.37 MW 0.31 MW
961942 AG1-037 E Adder 0.24 MW 0.21 MW
962331 AG1-082 C Adder 1.46 MW 1.24 MW
962332 AG1-082 E Adder 0.97 MW 0.83 MW
963041 AG1-153 C 50/50 6.65 MW 6.65 MW
963042 AG1-153 E 50/50 9.97 MW 9.97 MW
963171 AG1-166 C Adder 0.76 MW 0.64 MW
963172 AG1-166 E Adder 1.76 MW 1.5 MW
963181 AG1-167 C Adder 0.57 MW 0.48 MW
963182 AG1-167 E Adder 1.32 MW 1.12 MW
963191 AG1-168 C Adder 0.57 MW 0.48 MW
963192 AG1-168 E Adder 1.32 MW 1.12 MW
964791 AG1-342 C Adder 3.16 MW 2.69 MW
964792 AG1-342 E Adder 2.11 MW 1.79 MW
966801 AG1-551 C Adder 1.6 MW 1.36 MW
966802 AG1-551 E Adder 0.84 MW 0.72 MW
966811 AG1-552 C Adder 1.63 MW 1.39 MW
966812 AG1-552 E Adder 0.78 MW 0.66 MW
966621 AG1-532 C Adder 1.16 MW 0.98 MW
966622 AG1-532 E Adder 0.77 MW 0.66 MW
313853 3PONTONDP Adder 0.5 MW 0.43 MW
314572 3EMPORIA Adder 0.35 MW 0.3 MW
314713 3PAMPLIN Adder 0.76 MW 0.64 MW
315131 1EDGECMA Adder 12.42 MW 10.56 MW
315153 1CLOVER1 50/50 12.85 MW 12.85 MW
315154 1CLOVER2 50/50 12.73 MW 12.73 MW
918492 AA1-063AE OP Adder 3.09 MW 2.63 MW
918532 AA1-067 E Adder 0.55 MW 0.47 MW
919692 AA2-053 E OP Adder 3.31 MW 2.81 MW
925785 AC1-054 E Adder 2.91 MW 2.48 MW
926274 AC1-105 E Adder 2.39 MW 2.03 MW
927146 AC1-208 E Adder 3.21 MW 2.73 MW
934521 AD1-076 C Adder 9.07 MW 7.71 MW
934522 AD1-076 E Adder 4.62 MW 3.93 MW
943172 AE2-346 E Adder 0.44 MW 0.37 MW
943902 AF1-058 E Adder 1.14 MW 0.97 MW
944011 AF1-069 C 50/50 15.69 MW 15.69 MW
944012 AF1-069 E 50/50 6.09 MW 6.09 MW
959311 AF2-222 C Adder 14.6 MW 12.41 MW
959312 AF2-222 E Adder 9.78 MW 8.31 MW
960061 AF2-297 C Adder 6.85 MW 5.83 MW
960062 AF2-297 E Adder 4.57 MW 3.88 MW
960081 AF2-299 C Adder 1.54 MW 1.31 MW
960082 AF2-299 E Adder 1.03 MW 0.87 MW
316141 AB2-099 E Adder 0.18 MW 0.15 MW
917342 Z2-044 E Adder 0.49 MW 0.42 MW
922923 AB1-081 E OP Adder 2.97 MW 2.52 MW
923263 AB1-132 E OP Adder 4.84 MW 4.12 MW
923573 AB1-173 E OP Adder 2.66 MW 2.26 MW
924162 AB2-060 E OP Adder 3.86 MW 3.28 MW
924302 AB2-077 E O1 Adder 1.21 MW 1.03 MW
924312 AB2-078 E O1 Adder 1.21 MW 1.03 MW
924322 AB2-079 E O1 Adder 1.21 MW 1.03 MW
925612 AC1-036 E Adder 0.76 MW 0.65 MW
938371 AE1-056 C Adder 4.92 MW 4.18 MW
938372 AE1-056 E Adder 2.69 MW 2.28 MW
939181 AE1-148 C Adder 8.06 MW 6.85 MW
939182 AE1-148 E Adder 5.37 MW 4.57 MW
940492 AE2-034 E Adder 2.3 MW 1.95 MW
941031 AE2-094 C 50/50 48.01 MW 48.01 MW
941032 AE2-094 E 50/50 21.5 MW 21.5 MW
946281 AF1-292 C Adder 1.28 MW 1.08 MW
946282 AF1-292 E Adder 0.85 MW 0.72 MW
946301 AF1-294 C Adder 2.79 MW 2.38 MW
946302 AF1-294 E Adder 2.37 MW 2.01 MW
957481 AF2-042 C 50/50 56.62 MW 56.62 MW
957482 AF2-042 E 50/50 37.75 MW 37.75 MW
957521 AF2-046 C Adder 10.11 MW 8.59 MW
957522 AF2-046 E Adder 3.6 MW 3.06 MW
957861 AF2-080 C Adder 5.94 MW 5.05 MW
957862 AF2-080 E Adder 2.64 MW 2.24 MW
958211 AF2-115 C Adder 1.7 MW 1.44 MW
958212 AF2-115 E Adder 1.45 MW 1.23 MW
916042 Z1-036 E Adder 21.49 MW 18.26 MW
314507 3THOMPSN Adder 1.85 MW 1.57 MW
314550 6HICKORY 50/50 2.14 MW 2.14 MW
926662 AC1-147 E Adder 1.22 MW 1.03 MW
926755 AC1-161 E 50/50 37.0 MW 37.0 MW
315102 1BRUNSWICKG1 50/50 9.81 MW 9.81 MW
315103 1BRUNSWICKG2 50/50 9.81 MW 9.81 MW
315104 1BRUNSWICKG3 50/50 9.81 MW 9.81 MW
315105 1BRUNSWICKS1 50/50 20.39 MW 20.39 MW
315108 1ELIZAR1 50/50 3.0 MW 3.0 MW
315109 1ELIZAR2 50/50 2.95 MW 2.95 MW
315110 1ELIZAR3 50/50 3.04 MW 3.04 MW
315241 1Z1-086 GT1 50/50 12.59 MW 12.59 MW
315242 1Z1-086 GT2 50/50 12.58 MW 12.58 MW
315243 1Z1-086 GT3 50/50 12.58 MW 12.58 MW
315244 1Z1-086 ST 50/50 21.91 MW 21.91 MW
315260 1GOSPORTA Adder 1.95 MW 1.66 MW
315261 1GOSPORTB Adder 2.49 MW 2.12 MW
315262 1GOSPORTC Adder 2.12 MW 1.8 MW
913392 Y1-086 E Adder 1.87 MW 1.59 MW
916192 Z1-068 E 50/50 1.78 MW 1.78 MW
923832 AB2-022 E Adder 1.06 MW 0.9 MW
923852 AB2-025 E Adder 0.98 MW 0.83 MW
901082 W1-029 E Adder 23.29 MW 19.8 MW
917122 Z2-027 E Adder 1.1 MW 0.94 MW
925522 AC1-027 E 50/50 1.15 MW 1.15 MW
957871 AF2-081 C 50/50 9.4 MW 9.4 MW
957872 AF2-081 E 50/50 4.03 MW 4.03 MW
314722 3TWITTYS Adder 0.85 MW 0.72 MW
917512 Z2-088 E OP1 Adder 3.84 MW 3.26 MW
926071 AC1-086 C Adder 16.64 MW 14.14 MW
926072 AC1-086 E Adder 7.57 MW 6.44 MW
927021 AC1-189 C Adder 6.54 MW 5.56 MW
927022 AC1-189 E Adder 3.26 MW 2.77 MW
936261 AD2-033 C Adder 10.95 MW 9.31 MW
936262 AD2-033 E Adder 7.3 MW 6.21 MW
933291 AC2-141 C 50/50 86.68 MW 86.68 MW
933292 AC2-141 E 50/50 37.0 MW 37.0 MW
934621 AD1-088 C 50/50 12.4 MW 12.4 MW
934622 AD1-088 E 50/50 5.84 MW 5.84 MW
939411 AE1-173 C 50/50 85.83 MW 85.83 MW
939412 AE1-173 E 50/50 57.22 MW 57.22 MW
916191 Z1-068 C 50/50 0.04 MW 0.04 MW
933981 AD1-022 C Adder 6.44 MW 5.48 MW
933982 AD1-022 E Adder 3.51 MW 2.98 MW
962572 AG1-106 E Adder 0.94 MW 0.8 MW
961681 AG1-008 C Adder 10.11 MW 8.59 MW
962571 AG1-106 C Adder 2.15 MW 1.83 MW
314594 6PLYMOUTH TP Adder 0.24 MW 0.2 MW
314632 6AYDLETT TAP Adder 1.24 MW 1.06 MW
316185 AD1-033 C 50/50 1.21 MW 1.21 MW
316263 AC1-034 C Adder 5.29 MW 4.5 MW
316274 AC1-208 C Adder 7.23 MW 6.14 MW
316294 AC1-161 C 50/50 14.16 MW 14.16 MW
316316 AC1-027 C 50/50 0.3 MW 0.3 MW
917332 KELFORD E Adder 1.23 MW 1.05 MW
924516 AB2-100 E1 Adder 2.36 MW 2.01 MW
924517 AB2-100 E2 Adder 2.36 MW 2.01 MW
925595 AC1-034 E Adder 3.99 MW 3.39 MW
926206 AC1-098 E Adder 2.88 MW 2.45 MW
926214 AC1-099 E Adder 0.95 MW 0.81 MW
927255 AC1-221 E Adder 3.28 MW 2.79 MW
927264 AC1-222 E Adder 3.46 MW 2.94 MW
932763 AC2-100 E Adder 2.22 MW 1.89 MW
934065 AD1-033 E 50/50 4.96 MW 4.96 MW
937226 AE2-253 E 50/50 5.59 MW 5.59 MW
918512 AA1-065 E OP Adder 3.98 MW 3.38 MW
316017 AA1-139 ULT1 50/50 1.02 MW 1.02 MW
316018 AA1-139 ULT2 50/50 1.02 MW 1.02 MW
919153 AA1-139 E2 50/50 3.84 MW 3.84 MW
919152 AA1-139 E1 50/50 3.84 MW 3.84 MW
919710 AA2-057 E Adder 3.24 MW 2.75 MW
920692 AA2-178 E Adder 3.07 MW 2.61 MW
923994 AB2-040_E Adder 4.99 MW 4.24 MW
924022 AB2-043 E O1 Adder 4.7 MW 4.0 MW
924152 AB2-059 E OP Adder 4.21 MW 3.58 MW
925122 AB2-169 E Adder 4.33 MW 3.68 MW
316088 AB2-174 E Adder 5.31 MW 4.52 MW
316375 AC2-012 C 50/50 1.24 MW 1.24 MW
932046 AC2-012 E 50/50 12.04 MW 12.04 MW
316388 AE2-253 GEN 50/50 1.88 MW 1.88 MW
941591 AE2-156 C 50/50 16.58 MW 16.58 MW
944581 AF1-123 C 50/50 45.2 MW 45.2 MW
944582 AF1-123 E 50/50 103.51 MW 103.51 MW
944591 AF1-124 C 50/50 45.36 MW 45.36 MW
944592 AF1-124 E 50/50 103.88 MW 103.88 MW
944601 AF1-125 C 50/50 44.51 MW 44.51 MW
944602 AF1-125 E 50/50 101.88 MW 101.88 MW
962491 AG1-098 C 50/50 11.01 MW 11.01 MW
962492 AG1-098 E 50/50 7.34 MW 7.34 MW
962561 AG1-105 C Adder 7.95 MW 6.76 MW
962562 AG1-105 E Adder 5.3 MW 4.51 MW
964241 AG1-285 C Adder 12.02 MW 10.22 MW
964242 AG1-285 E Adder 8.01 MW 6.81 MW
313764 3SOCKMAN Adder 0.57 MW 0.49 MW
932632 AC2-084 E Adder 2.55 MW 2.17 MW
934321 AD1-056 C Adder 4.99 MW 4.24 MW
934322 AD1-056 E Adder 2.71 MW 2.3 MW
934331 AD1-057 C Adder 2.78 MW 2.37 MW
934332 AD1-057 E Adder 1.45 MW 1.23 MW
934501 AD1-074 C Adder 24.97 MW 21.22 MW
934502 AD1-074 E Adder 12.71 MW 10.8 MW
934511 AD1-075 C Adder 6.24 MW 5.31 MW
934512 AD1-075 E Adder 3.18 MW 2.7 MW
934611 AD1-087 C 50/50 1.26 MW 1.26 MW
934612 AD1-087 E 50/50 3.65 MW 3.65 MW
935171 AD1-152 C 50/50 1.29 MW 1.29 MW
935172 AD1-152 E 50/50 5.32 MW 5.32 MW
937481 AD2-202 C 50/50 0.37 MW 0.37 MW
937482 AD2-202 E 50/50 1.07 MW 1.07 MW
938531 AE1-072 C 50/50 16.24 MW 16.24 MW
938532 AE1-072 E 50/50 8.46 MW 8.46 MW
940481 AE2-033 C Adder 13.56 MW 11.53 MW
940482 AE2-033 E Adder 9.14 MW 7.77 MW
940541 AE2-040 C Adder 2.41 MW 2.05 MW
940641 AE2-051 C 50/50 26.25 MW 26.25 MW
940642 AE2-051 E 50/50 17.5 MW 17.5 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 24.91 MW 24.91 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 18.16 MW 18.16 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 82.64 MW 82.64 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.15 MW 2.15 MW
NY PJM->LTFIMP_NY CLTF 1.0 MW 1.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.96 MW 0.96 MW
WEC LTFEXP_WEC->PJM CLTF 0.51 MW 0.51 MW
CPLE LTFEXP_CPLE->PJM CLTF 10.09 MW 10.09 MW
TVA LTFEXP_TVA->PJM CLTF 4.93 MW 4.93 MW
MEC LTFEXP_MEC->PJM CLTF 3.15 MW 3.15 MW
LAGN LTFEXP_LAGN->PJM CLTF 6.32 MW 6.32 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.19 MW 0.19 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 13.68 MW 13.68 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 4.81 MW 4.81 MW

Details for 6MACKEYS-6EDENTON 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 246_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6MACKEYS-6EDENTON 230.0 kV Ckt 1 line
314203 to 314637 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 109.65 %
Rating: 733.2 MVA
Rating Type: B
MVA to Mitigate: 803.98 MVA
MW Contribution: 10.78 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6MACKEYS-6EDENTON 230.0 kV Ckt 1 line
314203 to 314637 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.12 %
Rating: 733.2 MVA
Rating Type: B
MVA to Mitigate: 829.39 MVA
MW Contribution: 11.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.73 MW 0.73 MW
961672 AG1-007 E 50/50 0.41 MW 0.41 MW
961941 AG1-037 C 50/50 0.56 MW 0.56 MW
961942 AG1-037 E 50/50 0.38 MW 0.38 MW
962331 AG1-082 C 50/50 2.26 MW 2.26 MW
962332 AG1-082 E 50/50 1.51 MW 1.51 MW
966801 AG1-551 C 50/50 3.0 MW 3.0 MW
966802 AG1-551 E 50/50 1.58 MW 1.58 MW
966811 AG1-552 C Adder 1.22 MW 1.04 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C Adder 0.4 MW 0.34 MW
965292 AG1-394 E Adder 0.73 MW 0.62 MW
314572 3EMPORIA Adder 0.18 MW 0.15 MW
315131 1EDGECMA 50/50 10.1 MW 10.1 MW
315136 1ROSEMG1 50/50 1.29 MW 1.29 MW
315137 1ROSEMS1 50/50 0.8 MW 0.8 MW
315138 1ROSEMG2 50/50 0.61 MW 0.61 MW
315139 1GASTONA 50/50 1.94 MW 1.94 MW
918492 AA1-063AE OP Adder 2.21 MW 1.88 MW
918532 AA1-067 E 50/50 0.82 MW 0.82 MW
919692 AA2-053 E OP 50/50 3.0 MW 3.0 MW
920042 AA2-088 E OP Adder 4.57 MW 3.88 MW
927146 AC1-208 E 50/50 3.27 MW 3.27 MW
934521 AD1-076 C 50/50 31.8 MW 31.8 MW
934522 AD1-076 E 50/50 16.21 MW 16.21 MW
943171 AE2-346 C 50/50 0.25 MW 0.25 MW
943172 AE2-346 E 50/50 0.68 MW 0.68 MW
315601 1CONETOE2SOL 50/50 1.11 MW 1.11 MW
315606 3AA2-053SOLA 50/50 1.07 MW 1.07 MW
316140 AB2-099 C 50/50 0.11 MW 0.11 MW
316141 AB2-099 E 50/50 0.28 MW 0.28 MW
900672 V4-068 E 50/50 0.25 MW 0.25 MW
917342 Z2-044 E 50/50 0.52 MW 0.52 MW
922923 AB1-081 E OP 50/50 2.82 MW 2.82 MW
923263 AB1-132 E OP 50/50 3.88 MW 3.88 MW
923573 AB1-173 E OP Adder 1.59 MW 1.35 MW
940491 AE2-034 C 50/50 3.66 MW 3.66 MW
940492 AE2-034 E 50/50 9.79 MW 9.79 MW
957521 AF2-046 C 50/50 11.22 MW 11.22 MW
957522 AF2-046 E 50/50 5.67 MW 5.67 MW
957861 AF2-080 C 50/50 7.47 MW 7.47 MW
957862 AF2-080 E 50/50 3.31 MW 3.31 MW
315141 1GASTONB 50/50 1.94 MW 1.94 MW
315292 1DOMTR78 50/50 3.12 MW 3.12 MW
917512 Z2-088 E OP1 50/50 4.36 MW 4.36 MW
926071 AC1-086 C 50/50 13.33 MW 13.33 MW
926072 AC1-086 E 50/50 6.07 MW 6.07 MW
927021 AC1-189 C 50/50 8.22 MW 8.22 MW
927022 AC1-189 E 50/50 4.09 MW 4.09 MW
933981 AD1-022 C 50/50 20.01 MW 20.01 MW
933982 AD1-022 E 50/50 10.89 MW 10.89 MW
962572 AG1-106 E 50/50 0.75 MW 0.75 MW
961681 AG1-008 C 50/50 11.22 MW 11.22 MW
961682 AG1-008 E 50/50 5.67 MW 5.67 MW
962571 AG1-106 C 50/50 1.72 MW 1.72 MW
314594 6PLYMOUTH TP 50/50 0.87 MW 0.87 MW
316005 AA1-067 C 50/50 0.32 MW 0.32 MW
316011 AB1-132 C OP 50/50 1.48 MW 1.48 MW
316049 AB1-081 C OP 50/50 1.08 MW 1.08 MW
316210 AC1-098 C 50/50 0.86 MW 0.86 MW
316212 AC1-099 C 50/50 0.29 MW 0.29 MW
316263 AC1-034 C 50/50 4.88 MW 4.88 MW
316274 AC1-208 C 50/50 7.36 MW 7.36 MW
316317 KELFORD C 50/50 0.41 MW 0.41 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.18 MW 0.18 MW
917332 KELFORD E 50/50 1.86 MW 1.86 MW
924516 AB2-100 E1 Adder 1.16 MW 0.99 MW
924517 AB2-100 E2 Adder 1.16 MW 0.99 MW
925595 AC1-034 E 50/50 3.68 MW 3.68 MW
926206 AC1-098 E 50/50 3.34 MW 3.34 MW
926214 AC1-099 E 50/50 1.1 MW 1.1 MW
315602 1HOLLOMANSOL 50/50 2.56 MW 2.56 MW
918512 AA1-065 E OP 50/50 7.68 MW 7.68 MW
316327 AA2-057 C 50/50 1.12 MW 1.12 MW
919710 AA2-057 E 50/50 3.41 MW 3.41 MW
315614 AA2-178 C 50/50 4.98 MW 4.98 MW
920692 AA2-178 E 50/50 13.05 MW 13.05 MW
923994 AB2-040_E Adder 2.98 MW 2.54 MW
316359 AB2-059 C OP 50/50 1.2 MW 1.2 MW
924152 AB2-059 E OP 50/50 3.78 MW 3.78 MW
316174 AB2-169_C 50/50 2.0 MW 2.0 MW
925122 AB2-169 E 50/50 11.01 MW 11.01 MW
316088 AB2-174 E Adder 2.97 MW 2.53 MW
313764 3SOCKMAN Adder 0.39 MW 0.33 MW
932631 AC2-084 C 50/50 0.92 MW 0.92 MW
932632 AC2-084 E 50/50 2.95 MW 2.95 MW
934321 AD1-056 C 50/50 4.01 MW 4.01 MW
934322 AD1-056 E 50/50 2.17 MW 2.17 MW
934331 AD1-057 C 50/50 2.23 MW 2.23 MW
934332 AD1-057 E 50/50 1.16 MW 1.16 MW
934501 AD1-074 C 50/50 87.56 MW 87.56 MW
934502 AD1-074 E 50/50 44.57 MW 44.57 MW
934511 AD1-075 C 50/50 21.89 MW 21.89 MW
934512 AD1-075 E 50/50 11.14 MW 11.14 MW
938531 AE1-072 C Adder -9.79 MW -8.32 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.78 MW 8.78 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.75 MW 5.75 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 25.69 MW 25.69 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.42 MW 0.42 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.33 MW 0.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.54 MW 3.54 MW
TVA LTFEXP_TVA->PJM CLTF 1.52 MW 1.52 MW
MEC LTFEXP_MEC->PJM CLTF 1.05 MW 1.05 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.95 MW 1.95 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.67 MW 2.67 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.69 MW 1.69 MW

Details for 6CHOWAN-6PEMBROKE 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 246_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHOWAN-6PEMBROKE 230.0 kV Ckt 1 line
313015 to 313714 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 108.94 %
Rating: 733.2 MVA
Rating Type: B
MVA to Mitigate: 798.78 MVA
MW Contribution: 10.78 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6CHOWAN-6PEMBROKE 230.0 kV Ckt 1 line
313015 to 313714 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 112.39 %
Rating: 733.2 MVA
Rating Type: B
MVA to Mitigate: 824.05 MVA
MW Contribution: 11.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.73 MW 0.73 MW
961672 AG1-007 E 50/50 0.41 MW 0.41 MW
961941 AG1-037 C 50/50 0.56 MW 0.56 MW
961942 AG1-037 E 50/50 0.38 MW 0.38 MW
962331 AG1-082 C 50/50 2.26 MW 2.26 MW
962332 AG1-082 E 50/50 1.51 MW 1.51 MW
966801 AG1-551 C 50/50 3.0 MW 3.0 MW
966802 AG1-551 E 50/50 1.58 MW 1.58 MW
966811 AG1-552 C Adder 1.22 MW 1.04 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C Adder 0.4 MW 0.34 MW
965292 AG1-394 E Adder 0.73 MW 0.62 MW
314572 3EMPORIA Adder 0.18 MW 0.15 MW
315131 1EDGECMA 50/50 10.1 MW 10.1 MW
315136 1ROSEMG1 50/50 1.29 MW 1.29 MW
315137 1ROSEMS1 50/50 0.8 MW 0.8 MW
315138 1ROSEMG2 50/50 0.61 MW 0.61 MW
315139 1GASTONA 50/50 1.94 MW 1.94 MW
918492 AA1-063AE OP Adder 2.21 MW 1.88 MW
918532 AA1-067 E 50/50 0.82 MW 0.82 MW
919692 AA2-053 E OP 50/50 3.0 MW 3.0 MW
920042 AA2-088 E OP Adder 4.57 MW 3.88 MW
927146 AC1-208 E 50/50 3.27 MW 3.27 MW
934521 AD1-076 C 50/50 31.8 MW 31.8 MW
934522 AD1-076 E 50/50 16.21 MW 16.21 MW
943171 AE2-346 C 50/50 0.25 MW 0.25 MW
943172 AE2-346 E 50/50 0.68 MW 0.68 MW
315601 1CONETOE2SOL 50/50 1.11 MW 1.11 MW
315606 3AA2-053SOLA 50/50 1.07 MW 1.07 MW
316140 AB2-099 C 50/50 0.11 MW 0.11 MW
316141 AB2-099 E 50/50 0.28 MW 0.28 MW
900672 V4-068 E 50/50 0.25 MW 0.25 MW
917342 Z2-044 E 50/50 0.52 MW 0.52 MW
922923 AB1-081 E OP 50/50 2.82 MW 2.82 MW
923263 AB1-132 E OP 50/50 3.88 MW 3.88 MW
923573 AB1-173 E OP Adder 1.59 MW 1.35 MW
940491 AE2-034 C 50/50 3.66 MW 3.66 MW
940492 AE2-034 E 50/50 9.79 MW 9.79 MW
957521 AF2-046 C 50/50 11.22 MW 11.22 MW
957522 AF2-046 E 50/50 5.67 MW 5.67 MW
957861 AF2-080 C 50/50 7.47 MW 7.47 MW
957862 AF2-080 E 50/50 3.31 MW 3.31 MW
315141 1GASTONB 50/50 1.94 MW 1.94 MW
315292 1DOMTR78 50/50 3.12 MW 3.12 MW
917512 Z2-088 E OP1 50/50 4.36 MW 4.36 MW
926071 AC1-086 C 50/50 13.33 MW 13.33 MW
926072 AC1-086 E 50/50 6.07 MW 6.07 MW
927021 AC1-189 C 50/50 8.22 MW 8.22 MW
927022 AC1-189 E 50/50 4.09 MW 4.09 MW
933981 AD1-022 C 50/50 20.01 MW 20.01 MW
933982 AD1-022 E 50/50 10.89 MW 10.89 MW
962572 AG1-106 E 50/50 0.75 MW 0.75 MW
961681 AG1-008 C 50/50 11.22 MW 11.22 MW
961682 AG1-008 E 50/50 5.67 MW 5.67 MW
962571 AG1-106 C 50/50 1.72 MW 1.72 MW
314594 6PLYMOUTH TP 50/50 0.87 MW 0.87 MW
316005 AA1-067 C 50/50 0.32 MW 0.32 MW
316011 AB1-132 C OP 50/50 1.48 MW 1.48 MW
316049 AB1-081 C OP 50/50 1.08 MW 1.08 MW
316210 AC1-098 C 50/50 0.86 MW 0.86 MW
316212 AC1-099 C 50/50 0.29 MW 0.29 MW
316263 AC1-034 C 50/50 4.88 MW 4.88 MW
316274 AC1-208 C 50/50 7.36 MW 7.36 MW
316317 KELFORD C 50/50 0.41 MW 0.41 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.18 MW 0.18 MW
917332 KELFORD E 50/50 1.86 MW 1.86 MW
924516 AB2-100 E1 Adder 1.16 MW 0.99 MW
924517 AB2-100 E2 Adder 1.16 MW 0.99 MW
925595 AC1-034 E 50/50 3.68 MW 3.68 MW
926206 AC1-098 E 50/50 3.34 MW 3.34 MW
926214 AC1-099 E 50/50 1.1 MW 1.1 MW
315602 1HOLLOMANSOL 50/50 2.56 MW 2.56 MW
918512 AA1-065 E OP 50/50 7.68 MW 7.68 MW
316327 AA2-057 C 50/50 1.12 MW 1.12 MW
919710 AA2-057 E 50/50 3.41 MW 3.41 MW
315614 AA2-178 C 50/50 4.98 MW 4.98 MW
920692 AA2-178 E 50/50 13.05 MW 13.05 MW
923994 AB2-040_E Adder 2.98 MW 2.54 MW
316359 AB2-059 C OP 50/50 1.2 MW 1.2 MW
924152 AB2-059 E OP 50/50 3.78 MW 3.78 MW
316174 AB2-169_C 50/50 2.0 MW 2.0 MW
925122 AB2-169 E 50/50 11.01 MW 11.01 MW
316088 AB2-174 E Adder 2.97 MW 2.53 MW
313764 3SOCKMAN Adder 0.39 MW 0.33 MW
932631 AC2-084 C 50/50 0.92 MW 0.92 MW
932632 AC2-084 E 50/50 2.95 MW 2.95 MW
934321 AD1-056 C 50/50 4.01 MW 4.01 MW
934322 AD1-056 E 50/50 2.17 MW 2.17 MW
934331 AD1-057 C 50/50 2.23 MW 2.23 MW
934332 AD1-057 E 50/50 1.16 MW 1.16 MW
934501 AD1-074 C 50/50 87.56 MW 87.56 MW
934502 AD1-074 E 50/50 44.57 MW 44.57 MW
934511 AD1-075 C 50/50 21.89 MW 21.89 MW
934512 AD1-075 E 50/50 11.14 MW 11.14 MW
938531 AE1-072 C Adder -9.79 MW -8.32 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.78 MW 8.78 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.75 MW 5.75 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 25.69 MW 25.69 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.42 MW 0.42 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.33 MW 0.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.54 MW 3.54 MW
TVA LTFEXP_TVA->PJM CLTF 1.52 MW 1.52 MW
MEC LTFEXP_MEC->PJM CLTF 1.05 MW 1.05 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.95 MW 1.95 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.67 MW 2.67 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.69 MW 1.69 MW

Details for 8CARSON-8MDLTHAN 500.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.73 %
Rating: 3220.44 MVA
Rating Type: A
MVA to Mitigate: 3404.98 MVA
MW Contribution: 12.45 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line
314902 to 314914 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 109.27 %
Rating: 3220.44 MVA
Rating Type: A
MVA to Mitigate: 3519.04 MVA
MW Contribution: 12.28 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961941 AG1-037 C Adder 0.57 MW 0.49 MW
961942 AG1-037 E Adder 0.38 MW 0.33 MW
962331 AG1-082 C Adder 2.3 MW 1.95 MW
962332 AG1-082 E Adder 1.53 MW 1.3 MW
963041 AG1-153 C 50/50 8.47 MW 8.47 MW
963042 AG1-153 E 50/50 12.7 MW 12.7 MW
964791 AG1-342 C Adder 4.06 MW 3.45 MW
964792 AG1-342 E Adder 2.7 MW 2.3 MW
966801 AG1-551 C Adder 2.38 MW 2.02 MW
966802 AG1-551 E Adder 1.25 MW 1.06 MW
966811 AG1-552 C Adder 2.39 MW 2.03 MW
966812 AG1-552 E Adder 1.13 MW 0.96 MW
965291 AG1-394 C Adder 0.97 MW 0.82 MW
965292 AG1-394 E Adder 1.78 MW 1.51 MW
966621 AG1-532 C 50/50 1.64 MW 1.64 MW
966622 AG1-532 E 50/50 1.09 MW 1.09 MW
313506 AB1-173 C OP 50/50 1.31 MW 1.31 MW
314541 3WATKINS Adder 0.77 MW 0.66 MW
314572 3EMPORIA 50/50 0.5 MW 0.5 MW
314704 3LAWRENC 50/50 0.36 MW 0.36 MW
315153 1CLOVER1 50/50 16.33 MW 16.33 MW
315154 1CLOVER2 50/50 16.18 MW 16.18 MW
918492 AA1-063AE OP Adder 4.7 MW 3.99 MW
918532 AA1-067 E Adder 0.81 MW 0.69 MW
919692 AA2-053 E OP Adder 4.89 MW 4.16 MW
920042 AA2-088 E OP Adder 12.0 MW 10.2 MW
925785 AC1-054 E Adder 4.01 MW 3.41 MW
926274 AC1-105 E Adder 3.06 MW 2.6 MW
927146 AC1-208 E Adder 4.78 MW 4.06 MW
934521 AD1-076 C Adder 13.79 MW 11.72 MW
934522 AD1-076 E Adder 7.03 MW 5.97 MW
943172 AE2-346 E Adder 0.69 MW 0.59 MW
943902 AF1-058 E Adder 1.46 MW 1.24 MW
944011 AF1-069 C 50/50 19.96 MW 19.96 MW
944012 AF1-069 E 50/50 7.75 MW 7.75 MW
959311 AF2-222 C Adder 18.25 MW 15.51 MW
959312 AF2-222 E Adder 12.23 MW 10.39 MW
960061 AF2-297 C Adder 8.78 MW 7.46 MW
960062 AF2-297 E Adder 5.85 MW 4.98 MW
960081 AF2-299 C 50/50 2.18 MW 2.18 MW
960082 AF2-299 E 50/50 1.46 MW 1.46 MW
316141 AB2-099 E Adder 0.29 MW 0.24 MW
900672 V4-068 E Adder 0.4 MW 0.34 MW
917342 Z2-044 E Adder 0.74 MW 0.63 MW
923263 AB1-132 E OP Adder 7.04 MW 5.99 MW
923573 AB1-173 E OP 50/50 3.82 MW 3.82 MW
924162 AB2-060 E OP Adder 4.95 MW 4.21 MW
924302 AB2-077 E O1 Adder 1.56 MW 1.32 MW
924312 AB2-078 E O1 Adder 1.56 MW 1.32 MW
924322 AB2-079 E O1 Adder 1.56 MW 1.32 MW
925612 AC1-036 E Adder 0.96 MW 0.81 MW
939181 AE1-148 C Adder 10.55 MW 8.96 MW
939182 AE1-148 E Adder 7.03 MW 5.98 MW
940492 AE2-034 E Adder 3.47 MW 2.95 MW
941031 AE2-094 C 50/50 61.09 MW 61.09 MW
941032 AE2-094 E 50/50 27.36 MW 27.36 MW
946281 AF1-292 C 50/50 1.81 MW 1.81 MW
946282 AF1-292 E 50/50 1.2 MW 1.2 MW
957481 AF2-042 C 50/50 71.85 MW 71.85 MW
957482 AF2-042 E 50/50 47.9 MW 47.9 MW
957521 AF2-046 C Adder 16.11 MW 13.7 MW
957522 AF2-046 E Adder 8.14 MW 6.92 MW
957861 AF2-080 C Adder 8.62 MW 7.33 MW
957862 AF2-080 E Adder 3.82 MW 3.25 MW
314539 3UNCAMP Adder 6.76 MW 5.75 MW
916042 Z1-036 E Adder 32.03 MW 27.22 MW
938771 AE1-103 C Adder 3.24 MW 2.76 MW
938772 AE1-103 E Adder 4.48 MW 3.81 MW
313526 AB2-022 C 50/50 0.42 MW 0.42 MW
314507 3THOMPSN Adder 2.22 MW 1.88 MW
314525 6KINGFORK Adder 1.06 MW 0.9 MW
314550 6HICKORY 50/50 2.45 MW 2.45 MW
926662 AC1-147 E Adder 1.45 MW 1.24 MW
926755 AC1-161 E 50/50 14.76 MW 14.76 MW
935112 AD1-144 E Adder 0.98 MW 0.83 MW
942341 AE2-247 C Adder 1.54 MW 1.31 MW
942342 AE2-247 E Adder 2.12 MW 1.81 MW
943461 AF1-017 C Adder 1.39 MW 1.18 MW
943462 AF1-017 E Adder 2.27 MW 1.93 MW
943612 AF1-032 E Adder 1.02 MW 0.87 MW
315102 1BRUNSWICKG1 50/50 12.5 MW 12.5 MW
315103 1BRUNSWICKG2 50/50 12.5 MW 12.5 MW
315104 1BRUNSWICKG3 50/50 12.5 MW 12.5 MW
315105 1BRUNSWICKS1 50/50 25.96 MW 25.96 MW
315108 1ELIZAR1 50/50 3.53 MW 3.53 MW
315109 1ELIZAR2 50/50 3.47 MW 3.47 MW
315110 1ELIZAR3 50/50 3.57 MW 3.57 MW
315241 1Z1-086 GT1 50/50 16.02 MW 16.02 MW
315242 1Z1-086 GT2 50/50 16.02 MW 16.02 MW
315243 1Z1-086 GT3 50/50 16.02 MW 16.02 MW
315244 1Z1-086 ST 50/50 27.89 MW 27.89 MW
315260 1GOSPORTA Adder 2.34 MW 1.99 MW
315261 1GOSPORTB Adder 2.99 MW 2.54 MW
315262 1GOSPORTC Adder 2.54 MW 2.15 MW
913392 Y1-086 E 50/50 2.46 MW 2.46 MW
916192 Z1-068 E 50/50 2.09 MW 2.09 MW
923832 AB2-022 E 50/50 1.39 MW 1.39 MW
923852 AB2-025 E 50/50 1.38 MW 1.38 MW
957492 AF2-043 E Adder 1.57 MW 1.33 MW
901082 W1-029 E Adder 35.56 MW 30.22 MW
917122 Z2-027 E 50/50 1.5 MW 1.5 MW
925522 AC1-027 E 50/50 1.35 MW 1.35 MW
957871 AF2-081 C 50/50 11.21 MW 11.21 MW
957872 AF2-081 E 50/50 4.8 MW 4.8 MW
958161 AF2-110 C Adder 1.49 MW 1.26 MW
958162 AF2-110 E Adder 2.37 MW 2.01 MW
314722 3TWITTYS Adder 1.06 MW 0.9 MW
926071 AC1-086 C Adder 24.19 MW 20.57 MW
926072 AC1-086 E Adder 11.01 MW 9.36 MW
927021 AC1-189 C Adder 9.5 MW 8.07 MW
927022 AC1-189 E Adder 4.73 MW 4.02 MW
936261 AD2-033 C Adder 11.55 MW 9.82 MW
933291 AC2-141 C 50/50 34.59 MW 34.59 MW
933292 AC2-141 E 50/50 14.76 MW 14.76 MW
934621 AD1-088 C 50/50 15.66 MW 15.66 MW
934622 AD1-088 E 50/50 7.37 MW 7.37 MW
939411 AE1-173 C 50/50 127.65 MW 127.65 MW
939412 AE1-173 E 50/50 85.1 MW 85.1 MW
916191 Z1-068 C 50/50 0.05 MW 0.05 MW
933981 AD1-022 C Adder 9.88 MW 8.4 MW
933982 AD1-022 E Adder 5.38 MW 4.57 MW
962572 AG1-106 E Adder 1.37 MW 1.16 MW
961681 AG1-008 C Adder 16.11 MW 13.7 MW
961682 AG1-008 E Adder 8.14 MW 6.92 MW
962571 AG1-106 C Adder 3.13 MW 2.66 MW
314594 6PLYMOUTH TP Adder 0.36 MW 0.31 MW
314632 6AYDLETT TAP 50/50 1.52 MW 1.52 MW
316023 AB2-100 C2 50/50 1.12 MW 1.12 MW
316185 AD1-033 C 50/50 1.38 MW 1.38 MW
316274 AC1-208 C Adder 10.76 MW 9.15 MW
316294 AC1-161 C 50/50 5.65 MW 5.65 MW
316315 AB2-025 C 50/50 0.48 MW 0.48 MW
316316 AC1-027 C 50/50 0.35 MW 0.35 MW
316320 Y1-086 C 50/50 0.25 MW 0.25 MW
316321 Z2-027 C 50/50 0.41 MW 0.41 MW
316365 AB2-100 C1 50/50 1.12 MW 1.12 MW
917332 KELFORD E Adder 1.9 MW 1.61 MW
924516 AB2-100 E1 50/50 3.38 MW 3.38 MW
924517 AB2-100 E2 50/50 3.38 MW 3.38 MW
926206 AC1-098 E Adder 4.34 MW 3.69 MW
926214 AC1-099 E Adder 1.43 MW 1.22 MW
934065 AD1-033 E 50/50 5.63 MW 5.63 MW
937226 AE2-253 E 50/50 6.55 MW 6.55 MW
918512 AA1-065 E OP Adder 6.26 MW 5.32 MW
316017 AA1-139 ULT1 50/50 1.21 MW 1.21 MW
316018 AA1-139 ULT2 50/50 1.21 MW 1.21 MW
919153 AA1-139 E2 50/50 4.58 MW 4.58 MW
919152 AA1-139 E1 50/50 4.58 MW 4.58 MW
919710 AA2-057 E Adder 4.83 MW 4.11 MW
920692 AA2-178 E Adder 4.62 MW 3.93 MW
316181 AB2-040 GEN 50/50 1.48 MW 1.48 MW
923994 AB2-040_E 50/50 7.17 MW 7.17 MW
924022 AB2-043 E O1 Adder 6.04 MW 5.13 MW
925122 AB2-169 E Adder 6.49 MW 5.51 MW
316087 AB2-174 C 50/50 1.37 MW 1.37 MW
316088 AB2-174 E 50/50 7.6 MW 7.6 MW
932046 AC2-012 E Adder 14.38 MW 12.23 MW
316311 AC2-079 C Adder 5.96 MW 5.06 MW
932596 AC2-079 E Adder 9.72 MW 8.26 MW
316349 AD2-085 C Adder 3.55 MW 3.02 MW
936666 AD2-085 E Adder 5.79 MW 4.92 MW
316388 AE2-253 GEN 50/50 2.21 MW 2.21 MW
941591 AE2-156 C 50/50 19.67 MW 19.67 MW
944581 AF1-123 C 50/50 50.97 MW 50.97 MW
944582 AF1-123 E 50/50 116.7 MW 116.7 MW
944591 AF1-124 C 50/50 51.15 MW 51.15 MW
944592 AF1-124 E 50/50 117.13 MW 117.13 MW
944601 AF1-125 C 50/50 50.18 MW 50.18 MW
944602 AF1-125 E 50/50 114.87 MW 114.87 MW
962491 AG1-098 C 50/50 13.88 MW 13.88 MW
962492 AG1-098 E 50/50 9.25 MW 9.25 MW
962561 AG1-105 C Adder 10.2 MW 8.67 MW
962562 AG1-105 E Adder 6.8 MW 5.78 MW
964241 AG1-285 C 50/50 15.25 MW 15.25 MW
964242 AG1-285 E 50/50 10.17 MW 10.17 MW
313764 3SOCKMAN 50/50 0.83 MW 0.83 MW
932632 AC2-084 E Adder 3.83 MW 3.26 MW
934321 AD1-056 C Adder 7.12 MW 6.05 MW
934322 AD1-056 E Adder 3.86 MW 3.28 MW
934331 AD1-057 C Adder 3.97 MW 3.38 MW
934332 AD1-057 E Adder 2.07 MW 1.76 MW
934501 AD1-074 C Adder 37.98 MW 32.28 MW
934502 AD1-074 E Adder 19.33 MW 16.43 MW
934511 AD1-075 C Adder 9.49 MW 8.07 MW
934512 AD1-075 E Adder 4.83 MW 4.11 MW
934611 AD1-087 C 50/50 1.61 MW 1.61 MW
934612 AD1-087 E 50/50 4.64 MW 4.64 MW
935171 AD1-152 C 50/50 1.65 MW 1.65 MW
935172 AD1-152 E 50/50 6.79 MW 6.79 MW
937481 AD2-202 C 50/50 0.47 MW 0.47 MW
937482 AD2-202 E 50/50 1.36 MW 1.36 MW
938531 AE1-072 C 50/50 19.7 MW 19.7 MW
938532 AE1-072 E 50/50 10.27 MW 10.27 MW
940481 AE2-033 C 50/50 19.22 MW 19.22 MW
940482 AE2-033 E 50/50 12.96 MW 12.96 MW
940541 AE2-040 C 50/50 3.42 MW 3.42 MW
940641 AE2-051 C 50/50 25.91 MW 25.91 MW
940642 AE2-051 E 50/50 17.27 MW 17.27 MW
941101 AE2-104 C Adder 3.64 MW 3.1 MW
941102 AE2-104 E Adder 5.79 MW 4.92 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 29.97 MW 29.97 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 23.14 MW 23.14 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 108.88 MW 108.88 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 3.59 MW 3.59 MW
NY PJM->LTFIMP_NY CLTF 1.68 MW 1.68 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.18 MW 1.18 MW
WEC LTFEXP_WEC->PJM CLTF 0.62 MW 0.62 MW
CPLE LTFEXP_CPLE->PJM CLTF 13.38 MW 13.38 MW
TVA LTFEXP_TVA->PJM CLTF 6.37 MW 6.37 MW
MEC LTFEXP_MEC->PJM CLTF 3.92 MW 3.92 MW
LAGN LTFEXP_LAGN->PJM CLTF 8.15 MW 8.15 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.24 MW 0.24 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 22.86 MW 22.86 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 6.38 MW 6.38 MW

Details for 6EDENTON-6CHOWAN 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 246_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6EDENTON-6CHOWAN 230.0 kV Ckt 1 line
314637 to 313015 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 101.17 %
Rating: 789.6 MVA
Rating Type: B
MVA to Mitigate: 798.82 MVA
MW Contribution: 10.78 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DVP
Facility Description:
6EDENTON-6CHOWAN 230.0 kV Ckt 1 line
314637 to 313015 ckt 1
Contingency Name:
DVP_P1-2: LN 246_SRT-A
CONTINGENCY 'DVP_P1-2: LN 246_SRT-A'
 OPEN BRANCH FROM BUS 314537 TO BUS 314575 CKT 1   /*6SUFFOLK     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314569 TO BUS 314575 CKT 1   /*6EARLEYS     230.0 - 6NUCO TP     230.0
 OPEN BRANCH FROM BUS 314575 TO BUS 314590 CKT 1   /*6NUCO TP     230.0 - 6NUCOR       230.0
 OPEN BUS 314575                                   /*6NUCO TP     230.0
 OPEN BUS 314590                                   /*6NUCOR       230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.37 %
Rating: 789.6 MVA
Rating Type: B
MVA to Mitigate: 824.08 MVA
MW Contribution: 11.0 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 0.73 MW 0.73 MW
961672 AG1-007 E 50/50 0.41 MW 0.41 MW
961941 AG1-037 C 50/50 0.56 MW 0.56 MW
961942 AG1-037 E 50/50 0.38 MW 0.38 MW
962331 AG1-082 C 50/50 2.26 MW 2.26 MW
962332 AG1-082 E 50/50 1.51 MW 1.51 MW
966801 AG1-551 C 50/50 3.0 MW 3.0 MW
966802 AG1-551 E 50/50 1.58 MW 1.58 MW
966811 AG1-552 C Adder 1.22 MW 1.04 MW
966812 AG1-552 E Adder 0.58 MW 0.49 MW
965291 AG1-394 C Adder 0.4 MW 0.34 MW
965292 AG1-394 E Adder 0.73 MW 0.62 MW
314572 3EMPORIA Adder 0.18 MW 0.15 MW
315131 1EDGECMA 50/50 10.1 MW 10.1 MW
315136 1ROSEMG1 50/50 1.29 MW 1.29 MW
315137 1ROSEMS1 50/50 0.8 MW 0.8 MW
315138 1ROSEMG2 50/50 0.61 MW 0.61 MW
315139 1GASTONA 50/50 1.94 MW 1.94 MW
918492 AA1-063AE OP Adder 2.21 MW 1.88 MW
918532 AA1-067 E 50/50 0.82 MW 0.82 MW
919692 AA2-053 E OP 50/50 3.0 MW 3.0 MW
920042 AA2-088 E OP Adder 4.57 MW 3.88 MW
927146 AC1-208 E 50/50 3.27 MW 3.27 MW
934521 AD1-076 C 50/50 31.8 MW 31.8 MW
934522 AD1-076 E 50/50 16.21 MW 16.21 MW
943171 AE2-346 C 50/50 0.25 MW 0.25 MW
943172 AE2-346 E 50/50 0.68 MW 0.68 MW
315601 1CONETOE2SOL 50/50 1.11 MW 1.11 MW
315606 3AA2-053SOLA 50/50 1.07 MW 1.07 MW
316140 AB2-099 C 50/50 0.11 MW 0.11 MW
316141 AB2-099 E 50/50 0.28 MW 0.28 MW
900672 V4-068 E 50/50 0.25 MW 0.25 MW
917342 Z2-044 E 50/50 0.52 MW 0.52 MW
922923 AB1-081 E OP 50/50 2.82 MW 2.82 MW
923263 AB1-132 E OP 50/50 3.88 MW 3.88 MW
923573 AB1-173 E OP Adder 1.59 MW 1.35 MW
940491 AE2-034 C 50/50 3.66 MW 3.66 MW
940492 AE2-034 E 50/50 9.79 MW 9.79 MW
957521 AF2-046 C 50/50 11.22 MW 11.22 MW
957522 AF2-046 E 50/50 5.67 MW 5.67 MW
957861 AF2-080 C 50/50 7.47 MW 7.47 MW
957862 AF2-080 E 50/50 3.31 MW 3.31 MW
315141 1GASTONB 50/50 1.94 MW 1.94 MW
315292 1DOMTR78 50/50 3.12 MW 3.12 MW
917512 Z2-088 E OP1 50/50 4.36 MW 4.36 MW
926071 AC1-086 C 50/50 13.33 MW 13.33 MW
926072 AC1-086 E 50/50 6.07 MW 6.07 MW
927021 AC1-189 C 50/50 8.22 MW 8.22 MW
927022 AC1-189 E 50/50 4.09 MW 4.09 MW
933981 AD1-022 C 50/50 20.01 MW 20.01 MW
933982 AD1-022 E 50/50 10.89 MW 10.89 MW
962572 AG1-106 E 50/50 0.75 MW 0.75 MW
961681 AG1-008 C 50/50 11.22 MW 11.22 MW
961682 AG1-008 E 50/50 5.67 MW 5.67 MW
962571 AG1-106 C 50/50 1.72 MW 1.72 MW
314594 6PLYMOUTH TP 50/50 0.87 MW 0.87 MW
316005 AA1-067 C 50/50 0.32 MW 0.32 MW
316011 AB1-132 C OP 50/50 1.48 MW 1.48 MW
316049 AB1-081 C OP 50/50 1.08 MW 1.08 MW
316210 AC1-098 C 50/50 0.86 MW 0.86 MW
316212 AC1-099 C 50/50 0.29 MW 0.29 MW
316263 AC1-034 C 50/50 4.88 MW 4.88 MW
316274 AC1-208 C 50/50 7.36 MW 7.36 MW
316317 KELFORD C 50/50 0.41 MW 0.41 MW
316318 V4-068 C 50/50 0.06 MW 0.06 MW
316319 Z2-044 C 50/50 0.18 MW 0.18 MW
917332 KELFORD E 50/50 1.86 MW 1.86 MW
924516 AB2-100 E1 Adder 1.16 MW 0.99 MW
924517 AB2-100 E2 Adder 1.16 MW 0.99 MW
925595 AC1-034 E 50/50 3.68 MW 3.68 MW
926206 AC1-098 E 50/50 3.34 MW 3.34 MW
926214 AC1-099 E 50/50 1.1 MW 1.1 MW
315602 1HOLLOMANSOL 50/50 2.56 MW 2.56 MW
918512 AA1-065 E OP 50/50 7.68 MW 7.68 MW
316327 AA2-057 C 50/50 1.12 MW 1.12 MW
919710 AA2-057 E 50/50 3.41 MW 3.41 MW
315614 AA2-178 C 50/50 4.98 MW 4.98 MW
920692 AA2-178 E 50/50 13.05 MW 13.05 MW
923994 AB2-040_E Adder 2.98 MW 2.54 MW
316359 AB2-059 C OP 50/50 1.2 MW 1.2 MW
924152 AB2-059 E OP 50/50 3.78 MW 3.78 MW
316174 AB2-169_C 50/50 2.0 MW 2.0 MW
925122 AB2-169 E 50/50 11.01 MW 11.01 MW
316088 AB2-174 E Adder 2.97 MW 2.53 MW
313764 3SOCKMAN Adder 0.39 MW 0.33 MW
932631 AC2-084 C 50/50 0.92 MW 0.92 MW
932632 AC2-084 E 50/50 2.95 MW 2.95 MW
934321 AD1-056 C 50/50 4.01 MW 4.01 MW
934322 AD1-056 E 50/50 2.17 MW 2.17 MW
934331 AD1-057 C 50/50 2.23 MW 2.23 MW
934332 AD1-057 E 50/50 1.16 MW 1.16 MW
934501 AD1-074 C 50/50 87.56 MW 87.56 MW
934502 AD1-074 E 50/50 44.57 MW 44.57 MW
934511 AD1-075 C 50/50 21.89 MW 21.89 MW
934512 AD1-075 E 50/50 11.14 MW 11.14 MW
938531 AE1-072 C Adder -9.79 MW -8.32 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.78 MW 8.78 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.75 MW 5.75 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 25.69 MW 25.69 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.42 MW 0.42 MW
NY PJM->LTFIMP_NY CLTF 0.19 MW 0.19 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.33 MW 0.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.18 MW 0.18 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.54 MW 3.54 MW
TVA LTFEXP_TVA->PJM CLTF 1.52 MW 1.52 MW
MEC LTFEXP_MEC->PJM CLTF 1.05 MW 1.05 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.95 MW 1.95 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 2.67 MW 2.67 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.69 MW 1.69 MW

Details for 6CHESTF B-6VARINA 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 107.46 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1057.62 MVA
MW Contribution: 3.88 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6CHESTF B-6VARINA 230.0 kV Ckt 1 line
314287 to 314260 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.86 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1022.21 MVA
MW Contribution: 3.75 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.33 MW 0.28 MW
961672 AG1-007 E Adder 0.19 MW 0.16 MW
961941 AG1-037 C Adder 0.19 MW 0.16 MW
961942 AG1-037 E Adder 0.13 MW 0.11 MW
962331 AG1-082 C Adder 0.76 MW 0.65 MW
962332 AG1-082 E Adder 0.51 MW 0.43 MW
963041 AG1-153 C Adder 1.97 MW 1.68 MW
963042 AG1-153 E Adder 2.96 MW 2.52 MW
966801 AG1-551 C Adder 0.74 MW 0.63 MW
966802 AG1-551 E Adder 0.39 MW 0.33 MW
966811 AG1-552 C Adder 0.82 MW 0.7 MW
966812 AG1-552 E Adder 0.39 MW 0.33 MW
965291 AG1-394 C Adder 0.33 MW 0.28 MW
965292 AG1-394 E Adder 0.61 MW 0.52 MW
966621 AG1-532 C Adder 0.62 MW 0.52 MW
966622 AG1-532 E Adder 0.41 MW 0.35 MW
314541 3WATKINS Adder 0.27 MW 0.23 MW
314572 3EMPORIA Adder 0.19 MW 0.16 MW
315131 1EDGECMA Adder 5.45 MW 4.63 MW
918492 AA1-063AE OP Adder 1.61 MW 1.37 MW
918532 AA1-067 E Adder 0.25 MW 0.21 MW
919692 AA2-053 E OP Adder 1.67 MW 1.42 MW
920042 AA2-088 E OP Adder 4.11 MW 3.49 MW
925785 AC1-054 E Adder 1.23 MW 1.04 MW
927146 AC1-208 E Adder 1.63 MW 1.38 MW
934521 AD1-076 C Adder 4.38 MW 3.72 MW
934522 AD1-076 E Adder 2.23 MW 1.9 MW
943172 AE2-346 E Adder 0.23 MW 0.2 MW
944011 AF1-069 C Adder 4.62 MW 3.93 MW
944012 AF1-069 E Adder 1.8 MW 1.53 MW
960081 AF2-299 C Adder 0.82 MW 0.7 MW
960082 AF2-299 E Adder 0.55 MW 0.47 MW
316141 AB2-099 E Adder 0.1 MW 0.08 MW
900672 V4-068 E Adder 0.14 MW 0.12 MW
917342 Z2-044 E Adder 0.25 MW 0.21 MW
922923 AB1-081 E OP Adder 1.32 MW 1.12 MW
923263 AB1-132 E OP Adder 2.58 MW 2.2 MW
923573 AB1-173 E OP Adder 1.38 MW 1.18 MW
924162 AB2-060 E OP Adder 1.33 MW 1.13 MW
924302 AB2-077 E O1 Adder 0.42 MW 0.36 MW
924312 AB2-078 E O1 Adder 0.42 MW 0.36 MW
924322 AB2-079 E O1 Adder 0.42 MW 0.36 MW
939181 AE1-148 C Adder 2.9 MW 2.46 MW
939182 AE1-148 E Adder 1.93 MW 1.64 MW
940492 AE2-034 E Adder 1.09 MW 0.93 MW
941031 AE2-094 C Adder 14.14 MW 12.02 MW
941032 AE2-094 E Adder 6.33 MW 5.38 MW
946281 AF1-292 C Adder 0.68 MW 0.58 MW
946282 AF1-292 E Adder 0.45 MW 0.39 MW
957481 AF2-042 C Adder 17.36 MW 14.76 MW
957482 AF2-042 E Adder 11.57 MW 9.84 MW
957521 AF2-046 C Adder 5.44 MW 4.62 MW
957522 AF2-046 E Adder 2.75 MW 2.33 MW
957861 AF2-080 C Adder 2.69 MW 2.29 MW
957862 AF2-080 E Adder 1.19 MW 1.01 MW
314539 3UNCAMP Adder 2.33 MW 1.98 MW
916042 Z1-036 E Adder 9.94 MW 8.45 MW
938771 AE1-103 C Adder 1.12 MW 0.95 MW
938772 AE1-103 E Adder 1.55 MW 1.31 MW
314331 6POE 50/50 1.08 MW 1.08 MW
314507 3THOMPSN Adder 0.69 MW 0.58 MW
314525 6KINGFORK Adder 0.36 MW 0.3 MW
314550 6HICKORY Adder 0.72 MW 0.61 MW
315065 1CHESTF6 50/50 23.03 MW 23.03 MW
315073 1STONECA 50/50 4.5 MW 4.5 MW
315076 1HOPPOLC 50/50 1.0 MW 1.0 MW
315077 1HOPHCF1 50/50 1.59 MW 1.59 MW
315078 1HOPHCF2 50/50 1.59 MW 1.59 MW
315079 1HOPHCF3 50/50 1.59 MW 1.59 MW
315080 1HOPHCF4 50/50 2.41 MW 2.41 MW
315083 1SPRUNCA Adder 2.67 MW 2.27 MW
315084 1SPRUNCB Adder 2.67 MW 2.27 MW
926662 AC1-147 E Adder 0.45 MW 0.38 MW
926755 AC1-161 E Adder 3.76 MW 3.19 MW
927226 AC1-216 E Adder 4.11 MW 3.49 MW
935112 AD1-144 E Adder 0.33 MW 0.28 MW
942341 AE2-247 C Adder 0.68 MW 0.58 MW
942342 AE2-247 E Adder 0.94 MW 0.8 MW
943461 AF1-017 C Adder 0.62 MW 0.53 MW
943462 AF1-017 E Adder 1.01 MW 0.86 MW
943612 AF1-032 E Adder 0.32 MW 0.27 MW
315260 1GOSPORTA Adder 0.72 MW 0.62 MW
315261 1GOSPORTB Adder 0.93 MW 0.79 MW
315262 1GOSPORTC Adder 0.79 MW 0.67 MW
316132 AB2-190 C 50/50 2.4 MW 2.4 MW
913392 Y1-086 E Adder 0.74 MW 0.63 MW
916192 Z1-068 E Adder 0.63 MW 0.54 MW
923832 AB2-022 E Adder 0.42 MW 0.36 MW
923852 AB2-025 E Adder 0.63 MW 0.54 MW
939312 AE1-162 E Adder 0.57 MW 0.48 MW
946262 AF1-291 E 50/50 1.63 MW 1.63 MW
957492 AF2-043 E Adder 0.49 MW 0.42 MW
901082 W1-029 E Adder 10.95 MW 9.3 MW
917122 Z2-027 E Adder 0.46 MW 0.39 MW
925332 AB2-190 E 50/50 4.68 MW 4.68 MW
925522 AC1-027 E Adder 0.41 MW 0.35 MW
942001 AE2-212 C 50/50 2.11 MW 2.11 MW
942002 AE2-212 E 50/50 1.41 MW 1.41 MW
957871 AF2-081 C Adder 3.32 MW 2.83 MW
957872 AF2-081 E Adder 1.42 MW 1.21 MW
958161 AF2-110 C Adder 0.52 MW 0.44 MW
958162 AF2-110 E Adder 0.82 MW 0.7 MW
917512 Z2-088 E OP1 Adder 1.72 MW 1.46 MW
926071 AC1-086 C Adder 8.88 MW 7.55 MW
926072 AC1-086 E Adder 4.04 MW 3.44 MW
927021 AC1-189 C Adder 2.96 MW 2.52 MW
927022 AC1-189 E Adder 1.47 MW 1.25 MW
933291 AC2-141 C Adder 8.8 MW 7.48 MW
933292 AC2-141 E Adder 3.76 MW 3.19 MW
934621 AD1-088 C Adder 3.87 MW 3.29 MW
934622 AD1-088 E Adder 1.82 MW 1.55 MW
939411 AE1-173 C Adder 31.3 MW 26.61 MW
939412 AE1-173 E Adder 20.87 MW 17.74 MW
934012 AD1-025 E Adder 5.32 MW 4.52 MW
933981 AD1-022 C Adder 3.16 MW 2.69 MW
933982 AD1-022 E Adder 1.72 MW 1.46 MW
962572 AG1-106 E Adder 0.5 MW 0.43 MW
961681 AG1-008 C Adder 5.44 MW 4.62 MW
961682 AG1-008 E Adder 2.75 MW 2.33 MW
962571 AG1-106 C Adder 1.15 MW 0.98 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
314632 6AYDLETT TAP Adder 0.45 MW 0.39 MW
316240 AF1-291 C 50/50 2.44 MW 2.44 MW
316263 AC1-034 C Adder 2.34 MW 1.99 MW
316274 AC1-208 C Adder 3.66 MW 3.12 MW
917332 KELFORD E Adder 0.63 MW 0.54 MW
924516 AB2-100 E1 Adder 1.37 MW 1.16 MW
924517 AB2-100 E2 Adder 1.37 MW 1.16 MW
925595 AC1-034 E Adder 1.77 MW 1.5 MW
926206 AC1-098 E Adder 1.47 MW 1.25 MW
926214 AC1-099 E Adder 0.48 MW 0.41 MW
934065 AD1-033 E Adder 1.66 MW 1.41 MW
937226 AE2-253 E Adder 1.94 MW 1.65 MW
918512 AA1-065 E OP Adder 2.05 MW 1.74 MW
919153 AA1-139 E2 Adder 1.36 MW 1.16 MW
919152 AA1-139 E1 Adder 1.36 MW 1.16 MW
919710 AA2-057 E Adder 1.64 MW 1.4 MW
920692 AA2-178 E Adder 1.45 MW 1.24 MW
923994 AB2-040_E Adder 2.59 MW 2.2 MW
924022 AB2-043 E O1 Adder 1.63 MW 1.38 MW
924152 AB2-059 E OP Adder 1.86 MW 1.58 MW
924814 AB2-134 E Adder 6.73 MW 5.72 MW
316083 AB2-161 C 50/50 0.32 MW 0.32 MW
316084 AB2-161 E 50/50 3.2 MW 3.2 MW
925122 AB2-169 E Adder 2.04 MW 1.74 MW
316088 AB2-174 E Adder 2.78 MW 2.37 MW
932046 AC2-012 E Adder 4.46 MW 3.79 MW
316311 AC2-079 C Adder 2.56 MW 2.18 MW
932596 AC2-079 E Adder 4.18 MW 3.56 MW
316381 AD1-082 C 50/50 0.73 MW 0.73 MW
934576 AD1-082 E 50/50 2.55 MW 2.55 MW
316349 AD2-085 C Adder 1.57 MW 1.34 MW
936666 AD2-085 E Adder 2.57 MW 2.18 MW
961611 AG1-000B C Adder 7.32 MW 6.22 MW
941591 AE2-156 C Adder 6.08 MW 5.17 MW
944581 AF1-123 C Adder 14.95 MW 12.71 MW
944582 AF1-123 E Adder 34.23 MW 29.09 MW
944591 AF1-124 C Adder 15.0 MW 12.75 MW
944592 AF1-124 E Adder 34.35 MW 29.2 MW
944601 AF1-125 C Adder 14.72 MW 12.51 MW
944602 AF1-125 E Adder 33.69 MW 28.64 MW
962491 AG1-098 C Adder 3.44 MW 2.92 MW
962492 AG1-098 E Adder 2.29 MW 1.95 MW
964241 AG1-285 C Adder 3.93 MW 3.34 MW
964242 AG1-285 E Adder 2.62 MW 2.23 MW
965281 AG1-393 C 50/50 1.26 MW 1.26 MW
965282 AG1-393 E 50/50 0.84 MW 0.84 MW
313764 3SOCKMAN Adder 0.29 MW 0.25 MW
932632 AC2-084 E Adder 1.3 MW 1.1 MW
934321 AD1-056 C Adder 2.39 MW 2.03 MW
934322 AD1-056 E Adder 1.3 MW 1.1 MW
934331 AD1-057 C Adder 1.33 MW 1.13 MW
934332 AD1-057 E Adder 0.69 MW 0.59 MW
934501 AD1-074 C Adder 12.06 MW 10.25 MW
934502 AD1-074 E Adder 6.14 MW 5.22 MW
934511 AD1-075 C Adder 3.01 MW 2.56 MW
934512 AD1-075 E Adder 1.53 MW 1.3 MW
934612 AD1-087 E Adder 1.13 MW 0.96 MW
935161 AD1-151 C Adder 9.0 MW 7.65 MW
935162 AD1-151 E Adder 6.0 MW 5.1 MW
935172 AD1-152 E Adder 1.67 MW 1.42 MW
937482 AD2-202 E Adder 0.33 MW 0.28 MW
938531 AE1-072 C Adder 5.86 MW 4.98 MW
938532 AE1-072 E Adder 3.06 MW 2.6 MW
939191 AE1-149 C 50/50 7.12 MW 7.12 MW
939192 AE1-149 E 50/50 4.75 MW 4.75 MW
940431 AE2-027 C Adder 7.02 MW 5.97 MW
940432 AE2-027 E Adder 4.68 MW 3.98 MW
940481 AE2-033 C Adder 8.64 MW 7.34 MW
940482 AE2-033 E Adder 5.82 MW 4.95 MW
940541 AE2-040 C Adder 1.56 MW 1.32 MW
940641 AE2-051 C Adder 6.05 MW 5.14 MW
940642 AE2-051 E Adder 4.03 MW 3.43 MW
941101 AE2-104 C Adder 1.27 MW 1.08 MW
941102 AE2-104 E Adder 2.01 MW 1.71 MW
944641 AF1-129 C 50/50 120.11 MW 120.11 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.73 MW 6.73 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.61 MW 5.61 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 28.02 MW 28.02 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.93 MW 0.93 MW
NY PJM->LTFIMP_NY CLTF 0.44 MW 0.44 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.27 MW 0.27 MW
WEC LTFEXP_WEC->PJM CLTF 0.14 MW 0.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.51 MW 3.51 MW
TVA LTFEXP_TVA->PJM CLTF 1.57 MW 1.57 MW
MEC LTFEXP_MEC->PJM CLTF 0.92 MW 0.92 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.01 MW 2.01 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.92 MW 5.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.67 MW 1.67 MW

Details for 6VARINA-6CHARCTY 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 107.41 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1057.1 MVA
MW Contribution: 3.88 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6VARINA-6CHARCTY 230.0 kV Ckt 1 line
314260 to 314225 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.82 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1021.73 MVA
MW Contribution: 3.75 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.33 MW 0.28 MW
961672 AG1-007 E Adder 0.19 MW 0.16 MW
961941 AG1-037 C Adder 0.19 MW 0.16 MW
961942 AG1-037 E Adder 0.13 MW 0.11 MW
962331 AG1-082 C Adder 0.76 MW 0.65 MW
962332 AG1-082 E Adder 0.51 MW 0.43 MW
963041 AG1-153 C Adder 1.97 MW 1.68 MW
963042 AG1-153 E Adder 2.96 MW 2.52 MW
966801 AG1-551 C Adder 0.74 MW 0.63 MW
966802 AG1-551 E Adder 0.39 MW 0.33 MW
966811 AG1-552 C Adder 0.82 MW 0.7 MW
966812 AG1-552 E Adder 0.39 MW 0.33 MW
965291 AG1-394 C Adder 0.33 MW 0.28 MW
965292 AG1-394 E Adder 0.61 MW 0.52 MW
966621 AG1-532 C Adder 0.62 MW 0.52 MW
966622 AG1-532 E Adder 0.41 MW 0.35 MW
314541 3WATKINS Adder 0.27 MW 0.23 MW
314572 3EMPORIA Adder 0.19 MW 0.16 MW
315131 1EDGECMA Adder 5.45 MW 4.63 MW
918492 AA1-063AE OP Adder 1.61 MW 1.37 MW
918532 AA1-067 E Adder 0.25 MW 0.21 MW
919692 AA2-053 E OP Adder 1.67 MW 1.42 MW
920042 AA2-088 E OP Adder 4.11 MW 3.49 MW
925785 AC1-054 E Adder 1.23 MW 1.04 MW
927146 AC1-208 E Adder 1.63 MW 1.38 MW
934521 AD1-076 C Adder 4.38 MW 3.72 MW
934522 AD1-076 E Adder 2.23 MW 1.9 MW
943172 AE2-346 E Adder 0.23 MW 0.2 MW
944011 AF1-069 C Adder 4.62 MW 3.93 MW
944012 AF1-069 E Adder 1.8 MW 1.53 MW
960081 AF2-299 C Adder 0.82 MW 0.7 MW
960082 AF2-299 E Adder 0.55 MW 0.47 MW
316141 AB2-099 E Adder 0.1 MW 0.08 MW
900672 V4-068 E Adder 0.14 MW 0.12 MW
917342 Z2-044 E Adder 0.25 MW 0.21 MW
922923 AB1-081 E OP Adder 1.32 MW 1.12 MW
923263 AB1-132 E OP Adder 2.58 MW 2.2 MW
923573 AB1-173 E OP Adder 1.38 MW 1.18 MW
924162 AB2-060 E OP Adder 1.33 MW 1.13 MW
924302 AB2-077 E O1 Adder 0.42 MW 0.36 MW
924312 AB2-078 E O1 Adder 0.42 MW 0.36 MW
924322 AB2-079 E O1 Adder 0.42 MW 0.36 MW
939181 AE1-148 C Adder 2.9 MW 2.46 MW
939182 AE1-148 E Adder 1.93 MW 1.64 MW
940492 AE2-034 E Adder 1.09 MW 0.93 MW
941031 AE2-094 C Adder 14.14 MW 12.02 MW
941032 AE2-094 E Adder 6.33 MW 5.38 MW
946281 AF1-292 C Adder 0.68 MW 0.58 MW
946282 AF1-292 E Adder 0.45 MW 0.39 MW
957481 AF2-042 C Adder 17.36 MW 14.76 MW
957482 AF2-042 E Adder 11.57 MW 9.84 MW
957521 AF2-046 C Adder 5.44 MW 4.62 MW
957522 AF2-046 E Adder 2.75 MW 2.33 MW
957861 AF2-080 C Adder 2.69 MW 2.29 MW
957862 AF2-080 E Adder 1.19 MW 1.01 MW
314539 3UNCAMP Adder 2.33 MW 1.98 MW
916042 Z1-036 E Adder 9.94 MW 8.45 MW
938771 AE1-103 C Adder 1.12 MW 0.95 MW
938772 AE1-103 E Adder 1.55 MW 1.31 MW
314331 6POE 50/50 1.08 MW 1.08 MW
314507 3THOMPSN Adder 0.69 MW 0.58 MW
314525 6KINGFORK Adder 0.36 MW 0.3 MW
314550 6HICKORY Adder 0.72 MW 0.61 MW
315065 1CHESTF6 50/50 23.03 MW 23.03 MW
315073 1STONECA 50/50 4.5 MW 4.5 MW
315076 1HOPPOLC 50/50 1.0 MW 1.0 MW
315077 1HOPHCF1 50/50 1.59 MW 1.59 MW
315078 1HOPHCF2 50/50 1.59 MW 1.59 MW
315079 1HOPHCF3 50/50 1.59 MW 1.59 MW
315080 1HOPHCF4 50/50 2.41 MW 2.41 MW
315083 1SPRUNCA Adder 2.67 MW 2.27 MW
315084 1SPRUNCB Adder 2.67 MW 2.27 MW
926662 AC1-147 E Adder 0.45 MW 0.38 MW
926755 AC1-161 E Adder 3.76 MW 3.19 MW
927226 AC1-216 E Adder 4.11 MW 3.49 MW
935112 AD1-144 E Adder 0.33 MW 0.28 MW
942341 AE2-247 C Adder 0.68 MW 0.58 MW
942342 AE2-247 E Adder 0.94 MW 0.8 MW
943461 AF1-017 C Adder 0.62 MW 0.53 MW
943462 AF1-017 E Adder 1.01 MW 0.86 MW
943612 AF1-032 E Adder 0.32 MW 0.27 MW
315260 1GOSPORTA Adder 0.72 MW 0.62 MW
315261 1GOSPORTB Adder 0.93 MW 0.79 MW
315262 1GOSPORTC Adder 0.79 MW 0.67 MW
316132 AB2-190 C 50/50 2.4 MW 2.4 MW
913392 Y1-086 E Adder 0.74 MW 0.63 MW
916192 Z1-068 E Adder 0.63 MW 0.54 MW
923832 AB2-022 E Adder 0.42 MW 0.36 MW
923852 AB2-025 E Adder 0.63 MW 0.54 MW
939312 AE1-162 E Adder 0.57 MW 0.48 MW
946262 AF1-291 E 50/50 1.63 MW 1.63 MW
957492 AF2-043 E Adder 0.49 MW 0.42 MW
901082 W1-029 E Adder 10.95 MW 9.3 MW
917122 Z2-027 E Adder 0.46 MW 0.39 MW
925332 AB2-190 E 50/50 4.68 MW 4.68 MW
925522 AC1-027 E Adder 0.41 MW 0.35 MW
942001 AE2-212 C 50/50 2.11 MW 2.11 MW
942002 AE2-212 E 50/50 1.41 MW 1.41 MW
957871 AF2-081 C Adder 3.32 MW 2.83 MW
957872 AF2-081 E Adder 1.42 MW 1.21 MW
958161 AF2-110 C Adder 0.52 MW 0.44 MW
958162 AF2-110 E Adder 0.82 MW 0.7 MW
917512 Z2-088 E OP1 Adder 1.72 MW 1.46 MW
926071 AC1-086 C Adder 8.88 MW 7.55 MW
926072 AC1-086 E Adder 4.04 MW 3.44 MW
927021 AC1-189 C Adder 2.96 MW 2.52 MW
927022 AC1-189 E Adder 1.47 MW 1.25 MW
933291 AC2-141 C Adder 8.8 MW 7.48 MW
933292 AC2-141 E Adder 3.76 MW 3.19 MW
934621 AD1-088 C Adder 3.87 MW 3.29 MW
934622 AD1-088 E Adder 1.82 MW 1.55 MW
939411 AE1-173 C Adder 31.3 MW 26.61 MW
939412 AE1-173 E Adder 20.87 MW 17.74 MW
934012 AD1-025 E Adder 5.32 MW 4.52 MW
933981 AD1-022 C Adder 3.16 MW 2.69 MW
933982 AD1-022 E Adder 1.72 MW 1.46 MW
962572 AG1-106 E Adder 0.5 MW 0.43 MW
961681 AG1-008 C Adder 5.44 MW 4.62 MW
961682 AG1-008 E Adder 2.75 MW 2.33 MW
962571 AG1-106 C Adder 1.15 MW 0.98 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
314632 6AYDLETT TAP Adder 0.45 MW 0.39 MW
316240 AF1-291 C 50/50 2.44 MW 2.44 MW
316263 AC1-034 C Adder 2.34 MW 1.99 MW
316274 AC1-208 C Adder 3.66 MW 3.12 MW
917332 KELFORD E Adder 0.63 MW 0.54 MW
924516 AB2-100 E1 Adder 1.37 MW 1.16 MW
924517 AB2-100 E2 Adder 1.37 MW 1.16 MW
925595 AC1-034 E Adder 1.77 MW 1.5 MW
926206 AC1-098 E Adder 1.47 MW 1.25 MW
926214 AC1-099 E Adder 0.48 MW 0.41 MW
934065 AD1-033 E Adder 1.66 MW 1.41 MW
937226 AE2-253 E Adder 1.94 MW 1.65 MW
918512 AA1-065 E OP Adder 2.05 MW 1.74 MW
919153 AA1-139 E2 Adder 1.36 MW 1.16 MW
919152 AA1-139 E1 Adder 1.36 MW 1.16 MW
919710 AA2-057 E Adder 1.64 MW 1.4 MW
920692 AA2-178 E Adder 1.45 MW 1.24 MW
923994 AB2-040_E Adder 2.59 MW 2.2 MW
924022 AB2-043 E O1 Adder 1.63 MW 1.38 MW
924152 AB2-059 E OP Adder 1.86 MW 1.58 MW
924814 AB2-134 E Adder 6.73 MW 5.72 MW
316083 AB2-161 C 50/50 0.32 MW 0.32 MW
316084 AB2-161 E 50/50 3.2 MW 3.2 MW
925122 AB2-169 E Adder 2.04 MW 1.74 MW
316088 AB2-174 E Adder 2.78 MW 2.37 MW
932046 AC2-012 E Adder 4.46 MW 3.79 MW
316311 AC2-079 C Adder 2.56 MW 2.18 MW
932596 AC2-079 E Adder 4.18 MW 3.56 MW
316381 AD1-082 C 50/50 0.73 MW 0.73 MW
934576 AD1-082 E 50/50 2.55 MW 2.55 MW
316349 AD2-085 C Adder 1.57 MW 1.34 MW
936666 AD2-085 E Adder 2.57 MW 2.18 MW
961611 AG1-000B C Adder 7.32 MW 6.22 MW
941591 AE2-156 C Adder 6.08 MW 5.17 MW
944581 AF1-123 C Adder 14.95 MW 12.71 MW
944582 AF1-123 E Adder 34.23 MW 29.09 MW
944591 AF1-124 C Adder 15.0 MW 12.75 MW
944592 AF1-124 E Adder 34.35 MW 29.2 MW
944601 AF1-125 C Adder 14.72 MW 12.51 MW
944602 AF1-125 E Adder 33.69 MW 28.64 MW
962491 AG1-098 C Adder 3.44 MW 2.92 MW
962492 AG1-098 E Adder 2.29 MW 1.95 MW
964241 AG1-285 C Adder 3.93 MW 3.34 MW
964242 AG1-285 E Adder 2.62 MW 2.23 MW
965281 AG1-393 C 50/50 1.26 MW 1.26 MW
965282 AG1-393 E 50/50 0.84 MW 0.84 MW
313764 3SOCKMAN Adder 0.29 MW 0.25 MW
932632 AC2-084 E Adder 1.3 MW 1.1 MW
934321 AD1-056 C Adder 2.39 MW 2.03 MW
934322 AD1-056 E Adder 1.3 MW 1.1 MW
934331 AD1-057 C Adder 1.33 MW 1.13 MW
934332 AD1-057 E Adder 0.69 MW 0.59 MW
934501 AD1-074 C Adder 12.06 MW 10.25 MW
934502 AD1-074 E Adder 6.14 MW 5.22 MW
934511 AD1-075 C Adder 3.01 MW 2.56 MW
934512 AD1-075 E Adder 1.53 MW 1.3 MW
934612 AD1-087 E Adder 1.13 MW 0.96 MW
935161 AD1-151 C Adder 9.0 MW 7.65 MW
935162 AD1-151 E Adder 6.0 MW 5.1 MW
935172 AD1-152 E Adder 1.67 MW 1.42 MW
937482 AD2-202 E Adder 0.33 MW 0.28 MW
938531 AE1-072 C Adder 5.86 MW 4.98 MW
938532 AE1-072 E Adder 3.06 MW 2.6 MW
939191 AE1-149 C 50/50 7.12 MW 7.12 MW
939192 AE1-149 E 50/50 4.75 MW 4.75 MW
940431 AE2-027 C Adder 7.02 MW 5.97 MW
940432 AE2-027 E Adder 4.68 MW 3.98 MW
940481 AE2-033 C Adder 8.64 MW 7.34 MW
940482 AE2-033 E Adder 5.82 MW 4.95 MW
940541 AE2-040 C Adder 1.56 MW 1.32 MW
940641 AE2-051 C Adder 6.05 MW 5.14 MW
940642 AE2-051 E Adder 4.03 MW 3.43 MW
941101 AE2-104 C Adder 1.27 MW 1.08 MW
941102 AE2-104 E Adder 2.01 MW 1.71 MW
944641 AF1-129 C 50/50 120.11 MW 120.11 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.73 MW 6.73 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.61 MW 5.61 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 28.02 MW 28.02 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.93 MW 0.93 MW
NY PJM->LTFIMP_NY CLTF 0.44 MW 0.44 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.27 MW 0.27 MW
WEC LTFEXP_WEC->PJM CLTF 0.14 MW 0.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.51 MW 3.51 MW
TVA LTFEXP_TVA->PJM CLTF 1.57 MW 1.57 MW
MEC LTFEXP_MEC->PJM CLTF 0.92 MW 0.92 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.01 MW 2.01 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.92 MW 5.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.67 MW 1.67 MW

Details for 6CHARCTY-6LAKESIDE 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 563_SRT-S-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DVP
Facility Description:
6CHARCTY-6LAKESIDE 230.0 kV Ckt 1 line
314225 to 314227 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.84 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 1021.97 MVA
MW Contribution: 3.88 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DVP
Facility Description:
6CHARCTY-6LAKESIDE 230.0 kV Ckt 1 line
314225 to 314227 ckt 1
Contingency Name:
DVP_P1-2: LN 563_SRT-S-1
CONTINGENCY 'DVP_P1-2: LN 563_SRT-S-1'
 OPEN BRANCH FROM BUS 314902 TO BUS 314914 CKT 1                /*8CARSON      500.0 - 8MDLTHAN     500.0
 SET POSTCONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
 SET POSTCONTRATING 3118 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314902 TO BUS 940640 CKT 1 /*8CARSON      500.0 - AE2-051 TP   500.0
 SET PRECONTRATING 2858 BRANCH FROM BUS 314923 TO BUS 940640 CKT 1 /*8SEPTA       500.0 - AE2-051 TP   500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.23 %
Rating: 984.18 MVA
Rating Type: B
MVA to Mitigate: 986.44 MVA
MW Contribution: 3.75 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C Adder 0.33 MW 0.28 MW
961672 AG1-007 E Adder 0.19 MW 0.16 MW
961941 AG1-037 C Adder 0.19 MW 0.16 MW
961942 AG1-037 E Adder 0.13 MW 0.11 MW
962331 AG1-082 C Adder 0.76 MW 0.65 MW
962332 AG1-082 E Adder 0.51 MW 0.43 MW
963041 AG1-153 C Adder 1.97 MW 1.68 MW
963042 AG1-153 E Adder 2.96 MW 2.52 MW
966801 AG1-551 C Adder 0.74 MW 0.63 MW
966802 AG1-551 E Adder 0.39 MW 0.33 MW
966811 AG1-552 C Adder 0.82 MW 0.7 MW
966812 AG1-552 E Adder 0.39 MW 0.33 MW
965291 AG1-394 C Adder 0.33 MW 0.28 MW
965292 AG1-394 E Adder 0.61 MW 0.52 MW
966621 AG1-532 C Adder 0.62 MW 0.52 MW
966622 AG1-532 E Adder 0.41 MW 0.35 MW
314541 3WATKINS Adder 0.27 MW 0.23 MW
314572 3EMPORIA Adder 0.19 MW 0.16 MW
315131 1EDGECMA Adder 5.45 MW 4.63 MW
918492 AA1-063AE OP Adder 1.61 MW 1.37 MW
918532 AA1-067 E Adder 0.25 MW 0.21 MW
919692 AA2-053 E OP Adder 1.67 MW 1.42 MW
920042 AA2-088 E OP Adder 4.11 MW 3.49 MW
925785 AC1-054 E Adder 1.23 MW 1.04 MW
927146 AC1-208 E Adder 1.63 MW 1.38 MW
934521 AD1-076 C Adder 4.38 MW 3.72 MW
934522 AD1-076 E Adder 2.23 MW 1.9 MW
943172 AE2-346 E Adder 0.23 MW 0.2 MW
944011 AF1-069 C Adder 4.62 MW 3.93 MW
944012 AF1-069 E Adder 1.8 MW 1.53 MW
960081 AF2-299 C Adder 0.82 MW 0.7 MW
960082 AF2-299 E Adder 0.55 MW 0.47 MW
316141 AB2-099 E Adder 0.1 MW 0.08 MW
900672 V4-068 E Adder 0.14 MW 0.12 MW
917342 Z2-044 E Adder 0.25 MW 0.21 MW
922923 AB1-081 E OP Adder 1.32 MW 1.12 MW
923263 AB1-132 E OP Adder 2.58 MW 2.2 MW
923573 AB1-173 E OP Adder 1.38 MW 1.18 MW
924162 AB2-060 E OP Adder 1.33 MW 1.13 MW
924302 AB2-077 E O1 Adder 0.42 MW 0.36 MW
924312 AB2-078 E O1 Adder 0.42 MW 0.36 MW
924322 AB2-079 E O1 Adder 0.42 MW 0.36 MW
939181 AE1-148 C Adder 2.9 MW 2.46 MW
939182 AE1-148 E Adder 1.93 MW 1.64 MW
940492 AE2-034 E Adder 1.09 MW 0.93 MW
941031 AE2-094 C Adder 14.14 MW 12.02 MW
941032 AE2-094 E Adder 6.33 MW 5.38 MW
946281 AF1-292 C Adder 0.68 MW 0.58 MW
946282 AF1-292 E Adder 0.45 MW 0.39 MW
957481 AF2-042 C Adder 17.36 MW 14.76 MW
957482 AF2-042 E Adder 11.57 MW 9.84 MW
957521 AF2-046 C Adder 5.44 MW 4.62 MW
957522 AF2-046 E Adder 2.75 MW 2.33 MW
957861 AF2-080 C Adder 2.69 MW 2.29 MW
957862 AF2-080 E Adder 1.19 MW 1.01 MW
314539 3UNCAMP Adder 2.33 MW 1.98 MW
916042 Z1-036 E Adder 9.94 MW 8.45 MW
938771 AE1-103 C Adder 1.12 MW 0.95 MW
938772 AE1-103 E Adder 1.55 MW 1.31 MW
314331 6POE 50/50 1.08 MW 1.08 MW
314507 3THOMPSN Adder 0.69 MW 0.58 MW
314525 6KINGFORK Adder 0.36 MW 0.3 MW
314550 6HICKORY Adder 0.72 MW 0.61 MW
315065 1CHESTF6 50/50 23.03 MW 23.03 MW
315073 1STONECA 50/50 4.5 MW 4.5 MW
315076 1HOPPOLC 50/50 1.0 MW 1.0 MW
315077 1HOPHCF1 50/50 1.59 MW 1.59 MW
315078 1HOPHCF2 50/50 1.59 MW 1.59 MW
315079 1HOPHCF3 50/50 1.59 MW 1.59 MW
315080 1HOPHCF4 50/50 2.41 MW 2.41 MW
315083 1SPRUNCA Adder 2.67 MW 2.27 MW
315084 1SPRUNCB Adder 2.67 MW 2.27 MW
926662 AC1-147 E Adder 0.45 MW 0.38 MW
926755 AC1-161 E Adder 3.76 MW 3.19 MW
927226 AC1-216 E Adder 4.11 MW 3.49 MW
935112 AD1-144 E Adder 0.33 MW 0.28 MW
942341 AE2-247 C Adder 0.68 MW 0.58 MW
942342 AE2-247 E Adder 0.94 MW 0.8 MW
943461 AF1-017 C Adder 0.62 MW 0.53 MW
943462 AF1-017 E Adder 1.01 MW 0.86 MW
943612 AF1-032 E Adder 0.32 MW 0.27 MW
315260 1GOSPORTA Adder 0.72 MW 0.62 MW
315261 1GOSPORTB Adder 0.93 MW 0.79 MW
315262 1GOSPORTC Adder 0.79 MW 0.67 MW
316132 AB2-190 C 50/50 2.4 MW 2.4 MW
913392 Y1-086 E Adder 0.74 MW 0.63 MW
916192 Z1-068 E Adder 0.63 MW 0.54 MW
923832 AB2-022 E Adder 0.42 MW 0.36 MW
923852 AB2-025 E Adder 0.63 MW 0.54 MW
939312 AE1-162 E Adder 0.57 MW 0.48 MW
946262 AF1-291 E 50/50 1.63 MW 1.63 MW
957492 AF2-043 E Adder 0.49 MW 0.42 MW
901082 W1-029 E Adder 10.95 MW 9.3 MW
917122 Z2-027 E Adder 0.46 MW 0.39 MW
925332 AB2-190 E 50/50 4.68 MW 4.68 MW
925522 AC1-027 E Adder 0.41 MW 0.35 MW
942001 AE2-212 C 50/50 2.11 MW 2.11 MW
942002 AE2-212 E 50/50 1.41 MW 1.41 MW
957871 AF2-081 C Adder 3.32 MW 2.83 MW
957872 AF2-081 E Adder 1.42 MW 1.21 MW
958161 AF2-110 C Adder 0.52 MW 0.44 MW
958162 AF2-110 E Adder 0.82 MW 0.7 MW
917512 Z2-088 E OP1 Adder 1.72 MW 1.46 MW
926071 AC1-086 C Adder 8.88 MW 7.55 MW
926072 AC1-086 E Adder 4.04 MW 3.44 MW
927021 AC1-189 C Adder 2.96 MW 2.52 MW
927022 AC1-189 E Adder 1.47 MW 1.25 MW
933291 AC2-141 C Adder 8.8 MW 7.48 MW
933292 AC2-141 E Adder 3.76 MW 3.19 MW
934621 AD1-088 C Adder 3.87 MW 3.29 MW
934622 AD1-088 E Adder 1.82 MW 1.55 MW
939411 AE1-173 C Adder 31.3 MW 26.61 MW
939412 AE1-173 E Adder 20.87 MW 17.74 MW
934012 AD1-025 E Adder 5.32 MW 4.52 MW
933981 AD1-022 C Adder 3.16 MW 2.69 MW
933982 AD1-022 E Adder 1.72 MW 1.46 MW
962572 AG1-106 E Adder 0.5 MW 0.43 MW
961681 AG1-008 C Adder 5.44 MW 4.62 MW
961682 AG1-008 E Adder 2.75 MW 2.33 MW
962571 AG1-106 C Adder 1.15 MW 0.98 MW
314594 6PLYMOUTH TP Adder 0.12 MW 0.1 MW
314632 6AYDLETT TAP Adder 0.45 MW 0.39 MW
316240 AF1-291 C 50/50 2.44 MW 2.44 MW
316263 AC1-034 C Adder 2.34 MW 1.99 MW
316274 AC1-208 C Adder 3.66 MW 3.12 MW
917332 KELFORD E Adder 0.63 MW 0.54 MW
924516 AB2-100 E1 Adder 1.37 MW 1.16 MW
924517 AB2-100 E2 Adder 1.37 MW 1.16 MW
925595 AC1-034 E Adder 1.77 MW 1.5 MW
926206 AC1-098 E Adder 1.47 MW 1.25 MW
926214 AC1-099 E Adder 0.48 MW 0.41 MW
934065 AD1-033 E Adder 1.66 MW 1.41 MW
937226 AE2-253 E Adder 1.94 MW 1.65 MW
918512 AA1-065 E OP Adder 2.05 MW 1.74 MW
919153 AA1-139 E2 Adder 1.36 MW 1.16 MW
919152 AA1-139 E1 Adder 1.36 MW 1.16 MW
919710 AA2-057 E Adder 1.64 MW 1.4 MW
920692 AA2-178 E Adder 1.45 MW 1.24 MW
923994 AB2-040_E Adder 2.59 MW 2.2 MW
924022 AB2-043 E O1 Adder 1.63 MW 1.38 MW
924152 AB2-059 E OP Adder 1.86 MW 1.58 MW
924814 AB2-134 E Adder 6.73 MW 5.72 MW
316083 AB2-161 C 50/50 0.32 MW 0.32 MW
316084 AB2-161 E 50/50 3.2 MW 3.2 MW
925122 AB2-169 E Adder 2.04 MW 1.74 MW
316088 AB2-174 E Adder 2.78 MW 2.37 MW
932046 AC2-012 E Adder 4.46 MW 3.79 MW
316311 AC2-079 C Adder 2.56 MW 2.18 MW
932596 AC2-079 E Adder 4.18 MW 3.56 MW
316381 AD1-082 C 50/50 0.73 MW 0.73 MW
934576 AD1-082 E 50/50 2.55 MW 2.55 MW
316349 AD2-085 C Adder 1.57 MW 1.34 MW
936666 AD2-085 E Adder 2.57 MW 2.18 MW
961611 AG1-000B C Adder 7.32 MW 6.22 MW
941591 AE2-156 C Adder 6.08 MW 5.17 MW
944581 AF1-123 C Adder 14.95 MW 12.71 MW
944582 AF1-123 E Adder 34.23 MW 29.09 MW
944591 AF1-124 C Adder 15.0 MW 12.75 MW
944592 AF1-124 E Adder 34.35 MW 29.2 MW
944601 AF1-125 C Adder 14.72 MW 12.51 MW
944602 AF1-125 E Adder 33.69 MW 28.64 MW
962491 AG1-098 C Adder 3.44 MW 2.92 MW
962492 AG1-098 E Adder 2.29 MW 1.95 MW
964241 AG1-285 C Adder 3.93 MW 3.34 MW
964242 AG1-285 E Adder 2.62 MW 2.23 MW
965281 AG1-393 C 50/50 1.26 MW 1.26 MW
965282 AG1-393 E 50/50 0.84 MW 0.84 MW
313764 3SOCKMAN Adder 0.29 MW 0.25 MW
932632 AC2-084 E Adder 1.3 MW 1.1 MW
934321 AD1-056 C Adder 2.39 MW 2.03 MW
934322 AD1-056 E Adder 1.3 MW 1.1 MW
934331 AD1-057 C Adder 1.33 MW 1.13 MW
934332 AD1-057 E Adder 0.69 MW 0.59 MW
934501 AD1-074 C Adder 12.06 MW 10.25 MW
934502 AD1-074 E Adder 6.14 MW 5.22 MW
934511 AD1-075 C Adder 3.01 MW 2.56 MW
934512 AD1-075 E Adder 1.53 MW 1.3 MW
934612 AD1-087 E Adder 1.13 MW 0.96 MW
935161 AD1-151 C Adder 9.0 MW 7.65 MW
935162 AD1-151 E Adder 6.0 MW 5.1 MW
935172 AD1-152 E Adder 1.67 MW 1.42 MW
937482 AD2-202 E Adder 0.33 MW 0.28 MW
938531 AE1-072 C Adder 5.86 MW 4.98 MW
938532 AE1-072 E Adder 3.06 MW 2.6 MW
939191 AE1-149 C 50/50 7.12 MW 7.12 MW
939192 AE1-149 E 50/50 4.75 MW 4.75 MW
940431 AE2-027 C Adder 7.02 MW 5.97 MW
940432 AE2-027 E Adder 4.68 MW 3.98 MW
940481 AE2-033 C Adder 8.64 MW 7.34 MW
940482 AE2-033 E Adder 5.82 MW 4.95 MW
940541 AE2-040 C Adder 1.56 MW 1.32 MW
940641 AE2-051 C Adder 6.05 MW 5.14 MW
940642 AE2-051 E Adder 4.03 MW 3.43 MW
941101 AE2-104 C Adder 1.27 MW 1.08 MW
941102 AE2-104 E Adder 2.01 MW 1.71 MW
944641 AF1-129 C 50/50 120.11 MW 120.11 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.73 MW 6.73 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.61 MW 5.61 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 28.02 MW 28.02 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.93 MW 0.93 MW
NY PJM->LTFIMP_NY CLTF 0.44 MW 0.44 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.27 MW 0.27 MW
WEC LTFEXP_WEC->PJM CLTF 0.14 MW 0.14 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.51 MW 3.51 MW
TVA LTFEXP_TVA->PJM CLTF 1.57 MW 1.57 MW
MEC LTFEXP_MEC->PJM CLTF 0.92 MW 0.92 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.01 MW 2.01 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.92 MW 5.92 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.67 MW 1.67 MW

Details for 6HATHAWAY-6ROCKYMT230T 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2181_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CPLE/DVP
Facility Description:
6HATHAWAY-6ROCKYMT230T 230.0 kV Ckt 1 line
313845 to 304222 ckt 1
Contingency Name:
DVP_P1-2: LN 2181_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2181_SRT-A'
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 108.56 %
Rating: 478.0 MVA
Rating Type: B
MVA to Mitigate: 518.89 MVA
MW Contribution: 16.98 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 2.21 MW 2.21 MW
961672 AG1-007 E 50/50 1.25 MW 1.25 MW
961941 AG1-037 C 50/50 0.32 MW 0.32 MW
961942 AG1-037 E 50/50 0.22 MW 0.22 MW
962331 AG1-082 C 50/50 1.29 MW 1.29 MW
962332 AG1-082 E 50/50 0.86 MW 0.86 MW
966801 AG1-551 C 50/50 1.6 MW 1.6 MW
966802 AG1-551 E 50/50 0.84 MW 0.84 MW
966811 AG1-552 C 50/50 1.48 MW 1.48 MW
966812 AG1-552 E 50/50 0.7 MW 0.7 MW
965291 AG1-394 C Adder 0.47 MW 0.4 MW
965292 AG1-394 E Adder 0.87 MW 0.74 MW
966621 AG1-532 C 50/50 0.88 MW 0.88 MW
966622 AG1-532 E 50/50 0.59 MW 0.59 MW
313506 AB1-173 C OP 50/50 0.76 MW 0.76 MW
314541 3WATKINS Adder 0.31 MW 0.26 MW
314572 3EMPORIA 50/50 0.28 MW 0.28 MW
315126 1ROARAP2 50/50 1.0 MW 1.0 MW
315128 1ROARAP4 50/50 0.94 MW 0.94 MW
315131 1EDGECMA 50/50 44.69 MW 44.69 MW
315136 1ROSEMG1 50/50 2.54 MW 2.54 MW
315137 1ROSEMS1 50/50 1.57 MW 1.57 MW
315138 1ROSEMG2 50/50 1.19 MW 1.19 MW
315139 1GASTONA 50/50 3.27 MW 3.27 MW
918492 AA1-063AE OP 50/50 2.67 MW 2.67 MW
918532 AA1-067 E 50/50 0.58 MW 0.58 MW
919692 AA2-053 E OP 50/50 3.0 MW 3.0 MW
920042 AA2-088 E OP Adder 5.7 MW 4.85 MW
925785 AC1-054 E Adder 1.41 MW 1.2 MW
927146 AC1-208 E 50/50 2.91 MW 2.91 MW
934521 AD1-076 C Adder 6.58 MW 5.59 MW
934522 AD1-076 E Adder 3.35 MW 2.85 MW
943171 AE2-346 C 50/50 0.14 MW 0.14 MW
943172 AE2-346 E 50/50 0.39 MW 0.39 MW
960081 AF2-299 C 50/50 1.18 MW 1.18 MW
960082 AF2-299 E 50/50 0.78 MW 0.78 MW
315601 1CONETOE2SOL 50/50 2.37 MW 2.37 MW
315606 3AA2-053SOLA 50/50 1.07 MW 1.07 MW
316140 AB2-099 C 50/50 0.06 MW 0.06 MW
316141 AB2-099 E 50/50 0.16 MW 0.16 MW
900672 V4-068 E Adder 0.21 MW 0.18 MW
917342 Z2-044 E 50/50 0.45 MW 0.45 MW
922923 AB1-081 E OP 50/50 9.19 MW 9.19 MW
923263 AB1-132 E OP 50/50 6.54 MW 6.54 MW
923573 AB1-173 E OP 50/50 2.2 MW 2.2 MW
940492 AE2-034 E Adder 1.44 MW 1.22 MW
946281 AF1-292 C 50/50 0.97 MW 0.97 MW
946282 AF1-292 E 50/50 0.65 MW 0.65 MW
957521 AF2-046 C 50/50 8.47 MW 8.47 MW
957522 AF2-046 E 50/50 4.28 MW 4.28 MW
957861 AF2-080 C 50/50 11.76 MW 11.76 MW
957862 AF2-080 E 50/50 5.21 MW 5.21 MW
314539 3UNCAMP Adder 2.46 MW 2.09 MW
916042 Z1-036 E Adder 10.67 MW 9.07 MW
938771 AE1-103 C Adder 1.1 MW 0.94 MW
938772 AE1-103 E Adder 1.53 MW 1.3 MW
315141 1GASTONB 50/50 3.27 MW 3.27 MW
315607 3AA1-063SOLA 50/50 0.92 MW 0.92 MW
923852 AB2-025 E Adder 0.45 MW 0.39 MW
917512 Z2-088 E OP1 50/50 9.28 MW 9.28 MW
926071 AC1-086 C 50/50 22.49 MW 22.49 MW
926072 AC1-086 E 50/50 10.24 MW 10.24 MW
927021 AC1-189 C 50/50 12.95 MW 12.95 MW
927022 AC1-189 E 50/50 6.45 MW 6.45 MW
933981 AD1-022 C Adder 4.98 MW 4.23 MW
933982 AD1-022 E Adder 2.71 MW 2.3 MW
962572 AG1-106 E 50/50 1.27 MW 1.27 MW
961681 AG1-008 C 50/50 8.47 MW 8.47 MW
961682 AG1-008 E 50/50 4.28 MW 4.28 MW
962571 AG1-106 C 50/50 2.91 MW 2.91 MW
314594 6PLYMOUTH TP Adder 0.17 MW 0.14 MW
316005 AA1-067 C 50/50 0.22 MW 0.22 MW
316011 AB1-132 C OP 50/50 2.5 MW 2.5 MW
316023 AB2-100 C2 50/50 0.7 MW 0.7 MW
316049 AB1-081 C OP 50/50 3.5 MW 3.5 MW
316210 AC1-098 C 50/50 0.68 MW 0.68 MW
316212 AC1-099 C 50/50 0.23 MW 0.23 MW
316263 AC1-034 C 50/50 16.93 MW 16.93 MW
316274 AC1-208 C 50/50 6.55 MW 6.55 MW
316317 KELFORD C 50/50 0.24 MW 0.24 MW
316319 Z2-044 C 50/50 0.16 MW 0.16 MW
316365 AB2-100 C1 50/50 0.7 MW 0.7 MW
917332 KELFORD E 50/50 1.12 MW 1.12 MW
924516 AB2-100 E1 50/50 2.12 MW 2.12 MW
924517 AB2-100 E2 50/50 2.12 MW 2.12 MW
925595 AC1-034 E 50/50 12.77 MW 12.77 MW
926206 AC1-098 E 50/50 2.61 MW 2.61 MW
926214 AC1-099 E 50/50 0.86 MW 0.86 MW
315602 1HOLLOMANSOL 50/50 1.21 MW 1.21 MW
918512 AA1-065 E OP 50/50 3.63 MW 3.63 MW
316327 AA2-057 C 50/50 0.96 MW 0.96 MW
919710 AA2-057 E 50/50 2.93 MW 2.93 MW
920692 AA2-178 E Adder 1.92 MW 1.63 MW
316181 AB2-040 GEN 50/50 0.85 MW 0.85 MW
923994 AB2-040_E 50/50 4.13 MW 4.13 MW
316359 AB2-059 C OP 50/50 4.4 MW 4.4 MW
924152 AB2-059 E OP 50/50 13.87 MW 13.87 MW
316174 AB2-169_C 50/50 0.7 MW 0.7 MW
925122 AB2-169 E 50/50 3.83 MW 3.83 MW
316087 AB2-174 C 50/50 0.78 MW 0.78 MW
316088 AB2-174 E 50/50 4.29 MW 4.29 MW
313764 3SOCKMAN 50/50 0.5 MW 0.5 MW
932631 AC2-084 C 50/50 0.72 MW 0.72 MW
932632 AC2-084 E 50/50 2.31 MW 2.31 MW
934321 AD1-056 C 50/50 13.39 MW 13.39 MW
934322 AD1-056 E 50/50 7.26 MW 7.26 MW
934331 AD1-057 C 50/50 7.47 MW 7.47 MW
934332 AD1-057 E 50/50 3.89 MW 3.89 MW
934501 AD1-074 C Adder 18.11 MW 15.39 MW
934502 AD1-074 E Adder 9.22 MW 7.83 MW
934511 AD1-075 C Adder 4.53 MW 3.85 MW
934512 AD1-075 E Adder 2.3 MW 1.96 MW
940481 AE2-033 C Adder 7.02 MW 5.97 MW
940482 AE2-033 E Adder 4.74 MW 4.03 MW
940541 AE2-040 C Adder 1.12 MW 0.95 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.23 MW 0.23 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.64 MW 0.64 MW
VTF LTFEXP_VFT->PJM CMTX 1.7 MW 1.7 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 3.86 MW 3.86 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 2.39 MW 2.39 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 1.18 MW 1.18 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 3.44 MW 3.44 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.59 MW 0.59 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 1.87 MW 1.87 MW
MDU PJM->LTFIMP_MDU CLTF 0.12 MW 0.12 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 1.22 MW 1.22 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 3.75 MW 3.75 MW

Details for 6NASH-6PA-RMOUNT#4 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2058_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: CPLE/DVP
Facility Description:
6NASH-6PA-RMOUNT#4 230.0 kV Ckt 1 line
314591 to 304226 ckt 1
Contingency Name:
DVP_P1-2: LN 2058_SRT-A
CONTINGENCY 'DVP_P1-2: LN 2058_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 108.45 %
Rating: 478.0 MVA
Rating Type: B
MVA to Mitigate: 518.4 MVA
MW Contribution: 16.57 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961671 AG1-007 C 50/50 1.99 MW 1.99 MW
961672 AG1-007 E 50/50 1.13 MW 1.13 MW
961941 AG1-037 C 50/50 0.32 MW 0.32 MW
961942 AG1-037 E 50/50 0.21 MW 0.21 MW
962331 AG1-082 C 50/50 1.29 MW 1.29 MW
962332 AG1-082 E 50/50 0.86 MW 0.86 MW
966801 AG1-551 C 50/50 1.57 MW 1.57 MW
966802 AG1-551 E 50/50 0.82 MW 0.82 MW
966811 AG1-552 C 50/50 1.49 MW 1.49 MW
966812 AG1-552 E 50/50 0.71 MW 0.71 MW
965291 AG1-394 C Adder 0.47 MW 0.4 MW
965292 AG1-394 E Adder 0.87 MW 0.74 MW
966621 AG1-532 C 50/50 0.89 MW 0.89 MW
966622 AG1-532 E 50/50 0.59 MW 0.59 MW
313506 AB1-173 C OP 50/50 0.76 MW 0.76 MW
314541 3WATKINS Adder 0.31 MW 0.26 MW
314572 3EMPORIA 50/50 0.28 MW 0.28 MW
315126 1ROARAP2 50/50 1.0 MW 1.0 MW
315128 1ROARAP4 50/50 0.95 MW 0.95 MW
315131 1EDGECMA 50/50 45.23 MW 45.23 MW
315136 1ROSEMG1 50/50 2.57 MW 2.57 MW
315137 1ROSEMS1 50/50 1.59 MW 1.59 MW
315138 1ROSEMG2 50/50 1.2 MW 1.2 MW
315139 1GASTONA 50/50 3.3 MW 3.3 MW
918492 AA1-063AE OP 50/50 2.69 MW 2.69 MW
918532 AA1-067 E 50/50 0.57 MW 0.57 MW
919692 AA2-053 E OP 50/50 3.02 MW 3.02 MW
920042 AA2-088 E OP Adder 5.72 MW 4.86 MW
925785 AC1-054 E Adder 1.42 MW 1.21 MW
927146 AC1-208 E 50/50 2.92 MW 2.92 MW
934521 AD1-076 C Adder 6.52 MW 5.54 MW
934522 AD1-076 E Adder 3.32 MW 2.82 MW
943171 AE2-346 C 50/50 0.14 MW 0.14 MW
943172 AE2-346 E 50/50 0.39 MW 0.39 MW
960081 AF2-299 C 50/50 1.19 MW 1.19 MW
960082 AF2-299 E 50/50 0.79 MW 0.79 MW
315601 1CONETOE2SOL 50/50 2.31 MW 2.31 MW
315606 3AA2-053SOLA 50/50 1.08 MW 1.08 MW
316140 AB2-099 C 50/50 0.06 MW 0.06 MW
316141 AB2-099 E 50/50 0.16 MW 0.16 MW
900672 V4-068 E Adder 0.21 MW 0.18 MW
917342 Z2-044 E 50/50 0.45 MW 0.45 MW
922923 AB1-081 E OP 50/50 7.97 MW 7.97 MW
923263 AB1-132 E OP 50/50 6.6 MW 6.6 MW
923573 AB1-173 E OP 50/50 2.22 MW 2.22 MW
940492 AE2-034 E Adder 1.43 MW 1.21 MW
946281 AF1-292 C 50/50 0.98 MW 0.98 MW
946282 AF1-292 E 50/50 0.65 MW 0.65 MW
957521 AF2-046 C 50/50 8.47 MW 8.47 MW
957522 AF2-046 E 50/50 4.28 MW 4.28 MW
957861 AF2-080 C 50/50 11.48 MW 11.48 MW
957862 AF2-080 E 50/50 5.09 MW 5.09 MW
314539 3UNCAMP Adder 2.46 MW 2.1 MW
916042 Z1-036 E Adder 10.6 MW 9.01 MW
938771 AE1-103 C Adder 1.11 MW 0.94 MW
938772 AE1-103 E Adder 1.53 MW 1.3 MW
315141 1GASTONB 50/50 3.3 MW 3.3 MW
315607 3AA1-063SOLA 50/50 0.93 MW 0.93 MW
923852 AB2-025 E Adder 0.46 MW 0.39 MW
917512 Z2-088 E OP1 50/50 9.06 MW 9.06 MW
926071 AC1-086 C 50/50 22.69 MW 22.69 MW
926072 AC1-086 E 50/50 10.33 MW 10.33 MW
927021 AC1-189 C 50/50 12.64 MW 12.64 MW
927022 AC1-189 E 50/50 6.3 MW 6.3 MW
933981 AD1-022 C Adder 4.94 MW 4.2 MW
933982 AD1-022 E Adder 2.69 MW 2.29 MW
962572 AG1-106 E 50/50 1.28 MW 1.28 MW
961681 AG1-008 C 50/50 8.47 MW 8.47 MW
961682 AG1-008 E 50/50 4.28 MW 4.28 MW
962571 AG1-106 C 50/50 2.94 MW 2.94 MW
314594 6PLYMOUTH TP Adder 0.17 MW 0.14 MW
316005 AA1-067 C 50/50 0.22 MW 0.22 MW
316011 AB1-132 C OP 50/50 2.52 MW 2.52 MW
316023 AB2-100 C2 50/50 0.71 MW 0.71 MW
316049 AB1-081 C OP 50/50 3.04 MW 3.04 MW
316210 AC1-098 C 50/50 0.68 MW 0.68 MW
316212 AC1-099 C 50/50 0.23 MW 0.23 MW
316263 AC1-034 C 50/50 14.2 MW 14.2 MW
316274 AC1-208 C 50/50 6.57 MW 6.57 MW
316317 KELFORD C 50/50 0.24 MW 0.24 MW
316319 Z2-044 C 50/50 0.16 MW 0.16 MW
316365 AB2-100 C1 50/50 0.71 MW 0.71 MW
917332 KELFORD E 50/50 1.11 MW 1.11 MW
924516 AB2-100 E1 50/50 2.14 MW 2.14 MW
924517 AB2-100 E2 50/50 2.14 MW 2.14 MW
925595 AC1-034 E 50/50 10.71 MW 10.71 MW
926206 AC1-098 E 50/50 2.62 MW 2.62 MW
926214 AC1-099 E 50/50 0.86 MW 0.86 MW
315602 1HOLLOMANSOL 50/50 1.2 MW 1.2 MW
918512 AA1-065 E OP 50/50 3.61 MW 3.61 MW
316327 AA2-057 C 50/50 0.97 MW 0.97 MW
919710 AA2-057 E 50/50 2.94 MW 2.94 MW
920692 AA2-178 E Adder 1.9 MW 1.62 MW
316181 AB2-040 GEN 50/50 0.86 MW 0.86 MW
923994 AB2-040_E 50/50 4.16 MW 4.16 MW
316359 AB2-059 C OP 50/50 3.58 MW 3.58 MW
924152 AB2-059 E OP 50/50 11.29 MW 11.29 MW
316174 AB2-169_C 50/50 0.69 MW 0.69 MW
925122 AB2-169 E 50/50 3.77 MW 3.77 MW
316087 AB2-174 C 50/50 0.78 MW 0.78 MW
316088 AB2-174 E 50/50 4.33 MW 4.33 MW
313764 3SOCKMAN 50/50 0.5 MW 0.5 MW
932631 AC2-084 C 50/50 0.72 MW 0.72 MW
932632 AC2-084 E 50/50 2.31 MW 2.31 MW
934321 AD1-056 C 50/50 13.56 MW 13.56 MW
934322 AD1-056 E 50/50 7.36 MW 7.36 MW
934331 AD1-057 C 50/50 7.57 MW 7.57 MW
934332 AD1-057 E 50/50 3.94 MW 3.94 MW
934501 AD1-074 C Adder 17.94 MW 15.25 MW
934502 AD1-074 E Adder 9.13 MW 7.76 MW
934511 AD1-075 C Adder 4.49 MW 3.81 MW
934512 AD1-075 E Adder 2.28 MW 1.94 MW
940481 AE2-033 C Adder 7.08 MW 6.02 MW
940482 AE2-033 E Adder 4.77 MW 4.06 MW
940541 AE2-040 C Adder 1.13 MW 0.96 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.24 MW 0.24 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.65 MW 0.65 MW
VTF LTFEXP_VFT->PJM CMTX 1.73 MW 1.73 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 3.86 MW 3.86 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 2.39 MW 2.39 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 1.18 MW 1.18 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 3.44 MW 3.44 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.59 MW 0.59 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 1.87 MW 1.87 MW
MDU PJM->LTFIMP_MDU CLTF 0.12 MW 0.12 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 1.21 MW 1.21 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 3.76 MW 3.76 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 39 are listed in Table 1 below. This report will cover the TC1 Phase 3 dynamic analysis of Cluster 39 projects.

 

 

Table 1: Transition Cycle 1 Cluster 39 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

39

AF2-080

Solar

Dominion

150

70

48.5

Chinquapin - Everetts 230 kV

AG1-106

Solar

Dominion

323

23

16

Thelma 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 39 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 39 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 39 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 39 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 39 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 211 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 39 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 39 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Oscillations were observed at the Gaston units for contingencies P4.43, P4.48, P4.52, P4.57, and P4.58. These oscillations did not met Dominion’s 4% damping criteria for local area and were observed to be pre-existing but was exacerbated by dispatched generation at Thelma.  The damping angle with changes to the generation dispatched at Thelma. The results indicate that reducing generation in the surrounding area leads to improved damping performance at Gaston and it is concluded that the oscillations at Gaston were not caused by the TC1 Cluster 39 projects.

 

The Transmission Owner has elected to upgrade the Hathaway 115 kV substation by splitting the existing 115 kV bus into two separate buses with a 115 kV line on each bus and the tie switch between line 55 and 80 was closed. Additionally, Line #1001 was opened at Battleboro, resulting in it becoming a radial line from Chestnut Substation. Contingency definitions at the Hathaway 115 kV substation were updated based on topology change, and the analysis was performed. Oscillations at Gaston continue to persist and were unaffected by the topology changes. No other violations occurred.

 

AF2-080 queue project did not meet the 0.95 lagging power factor measured at high side of the main transformer. When the facility was tested at its maximum lagging reactive capability, voltages above 1.10 p.u. were observed at the inverter terminal. To ensure that the facility can provide its lagging power factor without high voltages at the inverter terminal, it is recommended that the tap on the high side of the main transformer be adjusted from 1.0 to 1.025. An additional 5.42 Mvar is required to meet the 0.95 lagging power factor. The AF2-080 queue project met the 0.95 leading power factor measured at high side of the main transformer.

 

AG1-106 is an uprate of AB1-132 and AC1-086. The measurement point for the power factor requirements per the Interconnection Service Agreement (ISA) is at the generator terminals for AB1-132 and AC1-086.  AG1-106’s power factor requirements is measured at the high side of the station transformer.  Due to this three power factor assessments were included to bound the lagging deficiencies observed.  The following lagging deficiencies were observed for AG1-106 depending on the measurement’s points enforced for each test.

 

  • With AG1-106 online, and AB1-132 and AC1-086 offline to ensure the losses created by the AB1-132 and AC1-086 generators are not counted against AG1-106. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer.
  • With AG1-106 and AB1-132 online, AC1-086 offline to consider the shared high side of main station transformer. AB1-132’s measurement point in the ISA is not enforced in this test. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer. However, voltage violation were observed at the generator terminals with the voltage of 1.196 p.u. at AB1-132 and 1.147 p.u. at AG1-106.
  • AG1-106, AB1-132, and AC1-086 online to consider the shared high side of main station transformer. AB1-132 and AC1-086 measurement point in the ISA are not enforced in this test. The lagging power factor deficiency is 49.38 Mvar.

 

No mitigation was required.

Reactive Power Analysis

AF2-080 queue project did not meet the 0.95 lagging power factor measured at high side of the main transformer. When the facility was tested at its maximum lagging reactive capability, voltages above 1.10 p.u. were observed at the inverter terminal. To ensure that the facility can provide its lagging power factor without high voltages at the inverter terminal, it is recommended that the tap on the high side of the main transformer be adjusted from 1.0 to 1.025.. An additional 5.42 Mvar is required to meet the 0.95 lagging power factor. The AF2-080 queue project met the 0.95 leading power factor measured at high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA1-063A Carolina–Seaboard 115kV In Service
AA1-065 Earleys 230kV In Service
AA1-067 Everetts 34.5kV In Service
AA1-139 Hickory-Shawboro 230kV In Service
AA2-053 Carolina-Jackson 115kV In Service
AA2-057 Hornertown-Whitakers 115kV In Service
AA2-088 Boykins-Handsome 115kV In Service
AA2-178 Mackeys 230kV In Service
AB1-081 Anaconda-Mayo Dunbar 115kV In Service
AB1-132 Thelma 230kV In Service
AB1-173 Brink-Trego 115kV In Service
AB2-022 Elizabeth City 34.5kV In Service
AB2-025 Sapony 34.5kV In Service
AB2-026 Powhatan 34.5kV In Service
AB2-040 Brink 115kV In Service
AB2-043 Chase City 115kV In Service
AB2-059 Benson-Dunbar 115kV In Service
AB2-060 Chase City-Lunenburg 115kV In Service
AB2-077 Buggs Island-Chase City 115kV In Service
AB2-078 Buggs Island-Chase City 115kV In Service
AB2-079 Buggs Island-Chase City 115kV In Service
AB2-099 Ahoskie 34.5kV In Service
AB2-100 Clubhouse-Lakeview 230kV In Service
AB2-134 Hopewell-Surry 230kV In Service
AB2-161 Waverly #2 DP 115kV In Service
AB2-169 Pantago-Five Points 115kV In Service
AB2-174 Emporia-Trego 115kV In Service
AB2-190 Hopewell-Surry 230kV In Service
AC1-027 Pendleton 34.5kV In Service
AC1-034 Heartsease DP - Mayo Dunbar 115kV Suspended
AC1-036 Twittys Creek 34.5kV In Service
AC1-054 Kerr Dam–Eatons Ferry 115 kV In Service
AC1-075 Perth-Hickory Grove 115kV In Service
AC1-080 Perth-Hickory Grove 115kV In Service
AC1-086 Thelma 230kV Suspended
AC1-098 Dawson-South Justice 115kV Under Construction
AC1-099 Dawson-South Justice 115kV Under Construction
AC1-105 Halifax-Mt. Laurel 115kV In Service
AC1-147 Grassfield 34.5kV In Service
AC1-161 Septa 500kV In Service
AC1-164 Chickahominy 230kV Partially in Service - Under Construction
AC1-189 Chinquapin-Everetts 230kV Engineering & Procurement
AC1-208 Cox-Whitakers 115kV Under Construction
AC1-216 Hopewell-Surry 230kV In Service
AC1-221 Halifax-Person 230kV In Service
AC1-222 Crystal Hill-Halifax 115kV In Service
AC2-012 Grassfield-Great Bridge 115kV In Service
AC2-079 Ivor-Oak Ridge 115kV Suspended
AC2-084 Dawson-South Justice 115kV Under Construction
AC2-100 Halifax-Person 230kV In Service
AC2-141 Septa 500kV Engineering & Procurement
AC2-165 Bremo-Powhatan 230kV Suspended
AD1-022 Cashie-Trowbridge 230 kV Engineering & Procurement
AD1-025 Hopewell-Surry 230 kV Under Construction
AD1-033 Fentress-Landstown 230 kV In Service
AD1-056 Hornertown-Hathaway 230 kV Suspended
AD1-057 Hornertown-Hathaway 230 kV Suspended
AD1-074 Trowbridge 230 kV Engineering & Procurement
AD1-075 Trowbridge 230 kV Engineering & Procurement
AD1-076 Trowbridge 230 kV Engineering & Procurement
AD1-082 Bakers Pond-Ivor 115kV In Service
AD1-087 Clover-Sedge Hill 230 kV In Service
AD1-088 Briery-Clover 230 kV Suspended
AD1-144 Kings Fork 34.5 kV In Service
AD1-151 Hopewell-Surry 230 kV Suspended
AD1-152 Clover-Sedge Hill 230 kV In Service
AD2-022 East Danville - Roxborough 230 kV Engineering & Procurement
AD2-023 East Danville - Roxborough 230 kV Engineering & Procurement
AD2-033 Chase City-Lunenburg 115 kV Engineering & Procurement
AD2-085 Myrtle-Windsor DP 115kV Engineering & Procurement
AD2-202 Clover-Sedge Hill 230kV In Service
AE1-056 Red House-South Creek 115 kV Suspended
AE1-072 Shawboro-Sligo 230 kV Engineering & Procurement
AE1-074 Winterpock 34.5 kV Under Construction
AE1-075 Powhatan 34.5 kV In Service
AE1-103 Holland-Union Camp 115 kV Under Construction
AE1-108 Bremo-Scottsville 138 kV Engineering & Procurement
AE1-148 Kerr Dam-Ridge Rd 115 kV Active
AE1-149 Disputanta-Poe 115 kV Suspended
AE1-162 Smithfield 34.5 kV In Service
AE1-173 Carson-Suffolk 500 kV Under Construction
AE1-175 Light Foot 34.5 kV In Service
AE2-027 Harrowgate-Locks 115kV Suspended
AE2-033 Clubhouse-Sapony 230 kV Suspended
AE2-034 Mackeys 230 kV Partially in Service - Under Construction
AE2-040 Sapony 34.5 kV Under Construction
AE2-041 Harmony Village 230 kV Engineering & Procurement
AE2-051 Carson-Septa 500 kV Engineering & Procurement
AE2-092 Kidds Store-Sherwood 115 kV Engineering & Procurement
AE2-094 Carson-Rogers Road 500 kV Engineering & Procurement
AE2-104 Suffolk 115 kV Suspended
AE2-156 Yadkin 115 kV Active
AE2-212 Harrowgate 34 kV Engineering & Procurement
AE2-247 Myrtle-Windsor 115 kV Engineering & Procurement
AE2-253 Hickory-Moyock 230 kV In Service
AE2-259 Curdsville-Willis Mtn 115 kV Engineering & Procurement
AE2-346 Ahoskie 34.5 kV In Service
AF1-017 Myrtle-Windsor 115 kV Engineering & Procurement
AF1-018 Harmony Village 230 kV Engineering & Procurement
AF1-032 Suffolk 34.5 kV In Service
AF1-058 Welco 34.5 kV In Service
AF1-069 Carson-Rogers Rd 500 kV Engineering & Procurement
AF1-123 Oceana 230 kV Active
AF1-124 Oceana 230 kV Active
AF1-125 Oceana 230 kV Active
AF1-128 Chesterfield 230 kV Active
AF1-129 Chesterfield 230 kV Engineering & Procurement
AF1-291 Tyler 34.5 kV Engineering & Procurement
AF1-292 Fields 34.5kV Engineering & Procurement
AF1-294 Jetersville-Ponton 115 kV Active
AF2-042 Clover-Rawlings 500 kV Active
AF2-043 Suffolk 34.5 kV In Service
AF2-046 Tunis-Mapleton 115 kV Active
AF2-054 Wan 34.5 kV In Service
AF2-077 White Marsh 34.5 kV In Service
AF2-081 Moyock 230 kV Active
AF2-085 Midlothian 34.5 kV In Service
AF2-110 Suffolk 115 kV Suspended
AF2-115 Jetersville-Ponton 115 kV Active
AF2-144 Powhatan 34.5 kV In Service
AF2-222 Madisonville DP-Twitty's Creek 115 kV Active
AF2-297 Sedge Hill 115 kV Active
AF2-299 Fields 34.5 kV Active
AG1-007 Tar River 12.5 kV Engineering & Procurement
AG1-008 Tunis-Mapleton 115 kV Active
AG1-021 Jetersville-Ponton 115 kV Active
AG1-037 Ahoskie 34.5 kV Engineering & Procurement
AG1-082 Ahoskie 34.5 kV Active
AG1-098 Briery-Clover 230 kV Active
AG1-105 Mount Laurel-Barnes Junction 115 kV Active
AG1-106 Thelma 230 kV Active
AG1-145 Lightfoot 34.5 kV In Service
AG1-146 Garner DP-Lancaster 115 kV Active
AG1-147 Garner DP-Lancaster 115 kV Active
AG1-153 Heritage 500 kV Active
AG1-166 Lone Pine 115 kV Active
AG1-167 Lone Pine 115 kV Active
AG1-168 Lone Pine 115 kV Active
AG1-285 Chase City-Central 115 kV Active
AG1-342 Dryburg 115 kV Active
AG1-393 Fort Pickett DP 34.5 kV Active
AG1-394 Boykins 34.5 kV Active
AG1-532 Fields 34.5 kV Engineering & Procurement
AG1-551 Parmele 34.5 kV Active
AG1-552 Carolina 34.5 kV Active
V4-068 Murphy's 34.5kV In Service
W1-029 Winfall 230kV In Service
Y1-086 Morgans Corner In Service
Z1-036 WinFall-Chowan 230kV In Service
Z1-068 Birdneck 34.5kV In Service
Z2-027 Pasquotank 34.5kV In Service
Z2-044 Whitakers 34.5kV In Service
Z2-088 Tarboro-Everetts 230kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) Identified Impacts
AF2-080 System Reinforcements:
TO Trans Owner ID Title Category Allocated Cost ($USD)
CPLE dep0003-1 Rebuild aging double circuit 230kV towers of Everets to Greenvile Line Informational $0
CPLE dep0003-2 Reconductor one side of Everets to Greenvile 230 kV Line. Informational $0
Grand Total: $0

System Reinforcement
Type
Load Flow
TO
CPLE
RTEP ID / TO ID
(Pending) / dep0003-1
Title
Rebuild aging double circuit 230kV towers of Everets to Greenvile Line
Description
Rebuild 1.87 miles of aging double circuit 230kV towers of Everets to Greenvile Line. Projected ISD: 6/1/2027 Note: This project is similar to supplimental upgrade from Duke Energy. Queue project will not cost allocated for this reinforcement project.
Total Cost ($USD)
$19,000,000
Allocated Cost ($USD)
$0
Time Estimate
TBD

Info

Note: AF2-080 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.

Facility Contingency
6GREENVILE T-6EVERETS 230.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
CPLE
RTEP ID / TO ID
(Pending) / dep0003-2
Title
Reconductor one side of Everets to Greenvile 230 kV Line.
Description
Reconductor one side of Everets to Greenvile 230 kV Line. Upgrade the terminal equipment.
Total Cost ($USD)
$150,000
Allocated Cost ($USD)
$0
Time Estimate
30 to 36 Months

Info

Note: AF2-080 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.

Facility Contingency
6GREENVILE T-6EVERETS 230.0 kV Ckt 1 line (Any)

Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted Facility Transmission Owner Reinforcement Cost Cost Allocated to AF2-080 Scenarios
  • Rocky Mount 230.0 - Nash 230.0 CKT 1
  • Rocky Mount 230.0 - Hathaway 230.0 CKT 1
CPLE Reconductor 4.73 miles with bundled 795 ACSS and replace substation components to get 3000A (City of Rocky Mount – Nash 230 kV)
Reconductor 4.73 miles with bundled 795 ACSS and
replace substation components to get 3000A (City
of Rocky Mount – Nash 230 kV)
$14,033,000 $3,559,000
  • Rocky Mount 230.0 - Rocky Mount 115.0 CKT 1
CPLE Replace transformer protection panel, uprate CT ratios, and revise relay settings
Replace transformer protection panel, uprate CT
ratios, and revise relay settings
$619,000 $167,000
  • Greenville 230.0 - Everetts 230.0 CKT 1
CPLE Reconductor one side of Everetts to Greenville 230 kV Line. Upgrade the terminal equipment.
Reconductor one side of Everetts to Greenville 230
kV Line. Upgrade the terminal equipment.
$150,000 $0
  • Contingent
  • Greenville 230.0 - Everetts 230.0 CKT 1
CPLE Rebuild aging double circuit 230kV towers of Everetts to Greenville Line
Rebuild aging double circuit 230kV towers of
Everetts to Greenville Line
$19,000,000 $0
  • Contingent
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF2-080 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
Dominion n6872 Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C. Cost Allocated $6,723,564
Dominion n9200.0 Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductors. Cost Allocated $4,367,336
Dominion n9646.0 Upgrade 7.94 miles of 230 kV line 2092 between West Albemarle DP and South Hertford with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. Upgrade line leads at South Hertford. Cost Allocated $3,569,693
Dominion n9252.0 Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. Cost Allocated $3,038,213
Dominion n9111.0 Wreck and rebuild 3.3 miles of 230 kV transmission line 2092 between S. Hertford and Winfall with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C and replace line lead at S. Herftord and Winfall Cost Allocated $1,776,711
Dominion n9204.0 Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor. Cost Allocated $763,434
Dominion n9377.0 Upgrade 0.18 miles of 230 kV line 2092 between Pembroke Creek and West Albemarle DP with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. Cost Allocated $641,771
Dominion n9201.0 Replace wave trap at Carson 230 kV (Carson - Sapony). Cost Allocated $42,911
Dominion n6618.1 Split the 115 kV Bus at Hathaway into two separate buses with a 115 kV Line on each bus and close the tie switch between Line 55 & 80. Contingent $0 N/A
Dominion s3222.1 Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA. Contingent $0 N/A
Dominion n6144 Rebuild DEV portion 20.5 miles 2-636 ACSR and Rebuild 17.5 miles 2-636 ACSR between 6GREENVILE T - 6EVERETS 230.0 kV substations. Rating after the upgrade: 1047/1047/1204 Contingent $0 N/A
Dominion n8492.2 Expand Yadkin Substation to accommodate the new 500 kV line. Non-Contingent $0 N/A
Dominion n9259.0 Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. Non-Contingent $0 N/A
Dominion n9267.0 Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. Non-Contingent $0 N/A
Dominion n9630.0 Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. Non-Contingent $0 N/A
Dominion b4000.357 Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. Non-Contingent $0 N/A
Dominion b4000.356 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). Non-Contingent $0 N/A
Dominion b4000.355 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). Non-Contingent $0 N/A
Dominion b4000.352 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. Non-Contingent $0 N/A
Dominion b4000.351 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. Non-Contingent $0 N/A
Dominion b4000.350 Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. Non-Contingent $0 N/A
Dominion b4000.349 Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. Non-Contingent $0 N/A
Dominion b4000.348 Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. Non-Contingent $0 N/A
Dominion b4000.346 Cut-in 500kV line from Kraken substation into Yeat substation Non-Contingent $0 N/A
Dominion b4000.345 Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. Non-Contingent $0 N/A
Dominion b4000.344 Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. Non-Contingent $0 N/A
Dominion b4000.342 Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. Non-Contingent $0 N/A
Dominion b4000.341 Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. Non-Contingent $0 N/A
Dominion b4000.325 Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. Non-Contingent $0 N/A
Dominion b3689.2 Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA Non-Contingent $0 N/A
Dominion b4000.103 Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA Non-Contingent $0 N/A
Dominion b3800.405 Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. Non-Contingent $0 N/A
Dominion b3854.1 Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA Non-Contingent $0 N/A
Dominion b4000.108 Carson Sub 230kV - replace 40kA breaker 23872 with 63kA Non-Contingent $0 N/A
Dominion b4000.326 At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. Non-Contingent $0 N/A
Dominion n9138.0 Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. Non-Contingent $0 N/A
Dominion b4000.327 Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. Non-Contingent $0 N/A
Dominion b3800.406 Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. Non-Contingent $0 N/A
Dominion b4000.115 Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA Non-Contingent $0 N/A
Dominion b4000.354 Ladysmith substation breakers replacement: 574T575 and 568T581 Non-Contingent $0 N/A
Dominion b3853.1 Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA Non-Contingent $0 N/A
Dominion b4000.114 Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA Non-Contingent $0 N/A
Dominion b3800.235 Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers Non-Contingent $0 N/A
Dominion b3800.334 Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. Non-Contingent $0 N/A
Dominion b3800.407 Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. Non-Contingent $0 N/A
Dominion b4000.119 Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. Non-Contingent $0 N/A
Dominion b4000.128 North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. Non-Contingent $0 N/A
Dominion b3800.408 Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. Non-Contingent $0 N/A
Dominion s2609.6 Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. Non-Contingent $0 N/A
Dominion s2609.9 Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. Non-Contingent $0 N/A
Dominion b4000.134 Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. Non-Contingent $0 N/A
Dominion b1696 Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 Non-Contingent $0 N/A
Dominion n9250.0 Construct a new 22.59 mile line between Carson and Rawlings Substations. Non-Contingent $0 N/A
Dominion b3800.236 Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. Non-Contingent $0 N/A
Dominion s3047.2 Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. Non-Contingent $0 N/A
Dominion b3800.312 Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. Non-Contingent $0 N/A
Dominion b3800.313 Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. Non-Contingent $0 N/A
Dominion b3800.356 Build a new 500 kV line from Vint Hill to Wishing Star. Non-Contingent $0 N/A
Dominion b3800.357 Build a new 500 kV line from Morrisville to Vint Hill. Non-Contingent $0 N/A
Dominion b3800.354 Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. Non-Contingent $0 N/A
Dominion b3800.335 Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker Non-Contingent $0 N/A
Dominion n7541 Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. Non-Contingent $0 N/A
Dominion n8492 Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. Non-Contingent $0 N/A
Dominion n8492.1 Two Breaker Additions at Fentress Substation. Non-Contingent $0 N/A
Grand Total: $20,923,633

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n6872
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n6872 / dom-047
Title
Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C.
Description
Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C
Total Cost ($USD)
$59,572,939
Discounted Total Cost ($USD)
$59,572,939
Allocated Cost ($USD)
$6,723,564
Time Estimate
Dec 31 2029

Contributor

Facility Contingency
6CLUBHSE-AE2-033 TAP 230.0 kV Ckt 1 line (Any)
6CLUBHSE-AE2-033 TP 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-042 24.4 MW 21.5% $12,812,988
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
25.8 MW 22.7% $13,541,094
AF2-080 12.8 MW 11.3% $6,723,564
AF2-222 8.7 MW 7.7% $4,561,293
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
25.8 MW 22.7% $13,541,094
AG1-106 8.7 MW 7.7% $4,578,092
AG1-285 7.3 MW 6.4% $3,814,814

System Reinforcement: n9200.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9200.0 / TC1-PH2-DOM-005
Title
Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductors.
Description
Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" @ 250C
Total Cost ($USD)
$38,691,326
Discounted Total Cost ($USD)
$38,691,326
Allocated Cost ($USD)
$4,367,336
Time Estimate
45 to 46 Months

Contributor

Facility Contingency
6CARSON-6SAPONY 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-042 24.4 MW 21.5% $8,318,848
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
25.8 MW 22.7% $8,796,073
AF2-080 12.8 MW 11.3% $4,367,336
AF2-222 8.7 MW 7.7% $2,961,588
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
25.8 MW 22.7% $8,796,073
AG1-106 8.7 MW 7.7% $2,974,209
AG1-285 7.3 MW 6.4% $2,477,200

System Reinforcement: n9646.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9646.0 / TC1-PH3-DOM-005
Title
Upgrade 7.94 miles of 230 kV line 2092 between West Albemarle DP and South Hertford with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. Upgrade line leads at South Hertford.
Description
Upgrade 7.94 miles of 230 kV line 2092 between West Albemarle DP and South Hertford with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor at 250 degrees C. Upgrade line leads at South Hertford.
Total Cost ($USD)
$14,749,563
Discounted Total Cost ($USD)
$14,749,563
Allocated Cost ($USD)
$3,569,693
Time Estimate
Mar 31 2029

Contributor

Facility Contingency
6WALBMRL-6S HERTFORD 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
16.8 MW 37.9% $5,589,935
AF2-080 10.7 MW 24.2% $3,569,693
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
16.8 MW 37.9% $5,589,935

System Reinforcement: n9252.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9252.0 / TC1-PH2-DOM-047
Title
Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor.
Description
Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro, specifically, between structures 2021/31 and 2021/62, with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor at 250 degrees C.
Total Cost ($USD)
$12,801,638
Discounted Total Cost ($USD)
$12,801,638
Allocated Cost ($USD)
$3,038,213
Time Estimate
15 to 16 Months

Contributor

Facility Contingency
6ELIZ CT-6SHAWBRO 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
14.8 MW 38.1% $4,881,712
AF2-080 9.2 MW 23.7% $3,038,213
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
14.8 MW 38.1% $4,881,712

System Reinforcement: n9111.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9111.0 / dom-094
Title
Wreck and rebuild 3.3 miles of 230 kV transmission line 2092 between S. Hertford and Winfall with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C and replace line lead at S. Herftord and Winfall
Description
Wreck and rebuild 3.3 miles of 230 kV transmission line 2092 between S. Hertford and Winfall with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C and replace line lead at S. Hertford and Winfall
Total Cost ($USD)
$7,341,167
Discounted Total Cost ($USD)
$7,341,167
Allocated Cost ($USD)
$1,776,711
Time Estimate
42 to 43 Months

Contributor

Facility Contingency
6WINFALL-6S HERTFORD 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
16.8 MW 37.9% $2,782,228
AF2-080 10.7 MW 24.2% $1,776,711
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
16.8 MW 37.9% $2,782,228

System Reinforcement: n9204.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9204.0 / TC1-PH2-DOM-014
Title
Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C
Total Cost ($USD)
$6,764,273
Discounted Total Cost ($USD)
$6,764,273
Allocated Cost ($USD)
$763,434
Time Estimate
42 to 43 Months

Contributor

Facility Contingency
6SAPONY-AE2-033 TP 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-042 24.4 MW 21.5% $1,454,864
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
25.8 MW 22.7% $1,537,538
AF2-080 12.8 MW 11.3% $763,434
AF2-222 8.7 MW 7.7% $517,917
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
25.8 MW 22.7% $1,537,538
AG1-106 8.7 MW 7.7% $519,824
AG1-285 7.3 MW 6.4% $433,157

System Reinforcement: n9377.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9377.0 / TC1-PH3-DOM-004
Title
Upgrade 0.18 miles of 230 kV line 2092 between Pembroke Creek and West Albemarle DP with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor.
Description
Upgrade 0.18 miles of 230 kV Line 2092 between Pembroke Creek and West Albemarle DP with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor at 250 degrees C.
Total Cost ($USD)
$2,651,724
Discounted Total Cost ($USD)
$2,651,724
Allocated Cost ($USD)
$641,771
Time Estimate
Dec 31 2029

Contributor

Facility Contingency
6PEMBROKE-6WALBMRL 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
16.8 MW 37.9% $1,004,977
AF2-080 10.7 MW 24.2% $641,771
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
16.8 MW 37.9% $1,004,977

System Reinforcement: n9201.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9201.0 / TC1-PH2-DOM-006
Title
Replace wave trap at Carson 230 kV (Carson - Sapony).
Description
Replace wave trap at Carson 230 kV (Carson - Sapony).
Total Cost ($USD)
$521,941
Discounted Total Cost ($USD)
$521,941
Allocated Cost ($USD)
$42,911
Time Estimate
14 to 15 Months

Contributor

Facility Contingency
6CARSON-6SAPONY 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-042 24.4 MW 29.5% $153,825
AF2-046 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
13.4 MW 16.3% $84,819
AF2-080 6.8 MW 8.2% $42,911
AF2-222 8.7 MW 10.5% $54,763
AG1-008 AF2-046 115 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-046, AG1-008
13.4 MW 16.3% $84,819
AG1-106 8.7 MW 10.5% $54,997
AG1-285 7.3 MW 8.8% $45,806

System Reinforcement: n6618.1
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n6618.1
Title
Split the 115 kV Bus at Hathaway into two separate buses with a 115 kV Line on each bus and close the tie switch between Line 55 & 80.
Description
Split the 115 kV Bus at Hathaway into two separate buses with a 115 kV Line on each bus and close the tie switch between Line 55 & 80. Line #1001 is opened at Battleboro thus making Line #1001 radial from Chestnut Substation.
Total Cost ($USD)
$20,749
Discounted Total Cost ($USD)
$20,749
Allocated Cost ($USD)
$0
Time Estimate
30 to 36 Months

Contingent

Note: Based on PJM cost allocation criteria, AF2-080 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AF2-080 may not have cost responsibility for this upgrade, AF2-080 may need this upgrade in-service to be deliverable to the PJM system. If AF2-080 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
3ROCKYMT115T-3BTLEBRO 115.0 kV Ckt 1 line (Any)

System Reinforcement: n9112.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9112.0 / TC1-PH2-DOM-063
Title
Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield.
Description
Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield.
Total Cost ($USD)
$87,030,447
Discounted Total Cost ($USD)
$87,030,447
Allocated Cost ($USD)
$0
Time Estimate
46 to 47 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
6BASIN-6CHESTF B 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9265.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9265.0 / TC1-PH2-DOM-064
Title
Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B).
Description
Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B).
Total Cost ($USD)
$396,021
Discounted Total Cost ($USD)
$396,021
Allocated Cost ($USD)
$0
Time Estimate
14 to 15 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
6BASIN-6CHESTF B 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9266.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9266.0 / TC1-PH2-DOM-065
Title
Replace switches 25944 and 25945 at Basin 230 kV (Basin - Chesterfield B).
Description
Replace switches 25944 and 25945 at Basin 230 kV (Basin - Chesterfield B).
Total Cost ($USD)
$701,120
Discounted Total Cost ($USD)
$701,120
Allocated Cost ($USD)
$0
Time Estimate
38 to 39 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
6BASIN-6CHESTF B 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9220.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9220.0 / TC1-PH2-DOM-033
Title
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Total Cost ($USD)
$44,465,922
Discounted Total Cost ($USD)
$44,465,922
Allocated Cost ($USD)
$0
Time Estimate
42 to 48 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
6BUCKING-6BREMO 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9217.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9217.0 / TC1-PH2-DOM-028
Title
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.
Total Cost ($USD)
$40,414,822
Discounted Total Cost ($USD)
$40,414,822
Allocated Cost ($USD)
$0
Time Estimate
45 to 46 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
6BUCKING-6FARMVIL 230.0 kV Ckt 1 line (Any)

System Reinforcement: b3694.8
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3694.8
Title
Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1572 MVA.
Description
Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1572 MVA. Upgrade terminal equipment at Carson and Locks to not limit the new conductor rating.
Cost Information
Time Estimate
May 03 2025

Not Contingent

Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it is already in-service.

Facility Contingency
6CARSON-6CHRL249 230.0 kV Ckt 1 line (Any)
6CHRL249-6LOCKS 230.0 kV Ckt 1 line (Any)
6CARSON-6CHAPARRAL T 230.0 kV Ckt 1 line (Any)
6CHAPARRAL T-6LOCKS 230.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.319
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.319
Title
Reconductor 230kV Line #2002 Carson – Poe. New conductor has a summer rating of 1573 MVA.
Description
Reconductor 230kV Line #2002 Carson – Poe. New conductor has a summer rating of 1573 MVA.
Cost Information
Time Estimate
Mar 20 2030

Not Contingent

Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
6CARSON-6POE 230.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.320
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.320
Title
At Carson substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.
Description
At Carson substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.
Cost Information
Time Estimate
Mar 20 2030

Not Contingent

Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
6CARSON-6POE 230.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.321
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.321
Title
At Poe substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.
Description
At Poe substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.
Cost Information
Time Estimate
Mar 20 2030

Not Contingent

Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
6CARSON-6POE 230.0 kV Ckt 1 line (Any)

System Reinforcement: s3222.1
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
s3222.1
Title
Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA.
Description
Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA.
Cost Information
Time Estimate
Dec 31 2028

Contingent

Note: Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 may need this upgrade in-service to be deliverable to the PJM system. If AF2-080 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
6EARLEYS-6NUCO TP 230.0 kV Ckt 1 line (Any)
6SUFFOLK-6NUCO TP 230.0 kV Ckt 1 line (Any)

System Reinforcement: n6144
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n6144 / dom-173
Title
Rebuild DEV portion 20.5 miles 2-636 ACSR and Rebuild 17.5 miles 2-636 ACSR between 6GREENVILE T - 6EVERETS 230.0 kV substations. Rating after the upgrade: 1047/1047/1204
Description
Rebuild DEV portion 20.5 miles 2-636 ACSR and Rebuild 17.5 miles 2-636 ACSR between 6GREENVILE T - 6EVERETS 230.0 kV substations. Rating after the upgrade: 1047/1047/1204
Total Cost ($USD)
$39,923,299
Discounted Total Cost ($USD)
$39,923,299
Allocated Cost ($USD)
$0
Time Estimate
Nov 25 2026

Contingent

Note: Based on PJM cost allocation criteria, AF2-080 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AF2-080 may not have cost responsibility for this upgrade, AF2-080 may need this upgrade in-service to be deliverable to the PJM system. If AF2-080 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
6GREENVILE T-6EVERETS 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9379.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9379.0 / TC1-PH3-DOM-011
Title
Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase transformers.
Description
Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase 500/230 kV transformers.
Total Cost ($USD)
$37,836,293
Discounted Total Cost ($USD)
$37,836,293
Allocated Cost ($USD)
$0
Time Estimate
Dec 31 2029

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer (Any)

System Reinforcement: b4000.315
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.315
Title
Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.
Description
Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.
Cost Information
Time Estimate
Apr 22 2030

Not Contingent

Note: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
6TYLER1-6POE 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9139.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9139.0 / TC1-PH1-DOM-073
Title
Wreck and rebuild 37.41 miles of 500kV line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" and associated substation work.
Description
Wreck and rebuild 37.41 miles of 500kV transmission line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA. Remove wave traps.
Total Cost ($USD)
$245,455,768
Discounted Total Cost ($USD)
$245,455,768
Allocated Cost ($USD)
$0
Time Estimate
69 to 70 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
8CARSON-8MDLTHAN 500.0 kV Ckt 1 line (Any)

System Reinforcement: n9264.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9264.0 / TC1-PH1-DOM-080
Title
Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1.
Description
Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1.
Total Cost ($USD)
$582,006
Discounted Total Cost ($USD)
$582,006
Allocated Cost ($USD)
$0
Time Estimate
12 to 13 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
8CHCKAHM-8SURRY 500.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.357
Title
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Description
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.357
Title
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Description
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Cost Information
Time Estimate
Jun 01 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.352
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.352
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.352
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.352
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Cost Information
Time Estimate
Sep 16 2030
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.351
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.351
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.351
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.351
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Cost Information
Time Estimate
Sep 16 2030
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.350
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.350
Title
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Description
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.350
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.350
Title
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Description
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Cost Information
Time Estimate
Sep 16 2030
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.344
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.344
Title
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.344
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.344
Title
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Time Estimate
Sep 16 2030
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.346
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.346
Title
Cut-in 500kV line from Kraken substation into Yeat substation
Description
Cut-in 500kV line from Kraken substation into Yeat substation
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.346
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.346
Title
Cut-in 500kV line from Kraken substation into Yeat substation
Description
Cut-in 500kV line from Kraken substation into Yeat substation
Cost Information
Time Estimate
Jun 01 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.345
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.345
Title
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.345
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.345
Title
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Time Estimate
Sep 16 2030
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.348
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.348
Title
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Description
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.348
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.348
Title
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Description
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
Cost Information
Time Estimate
Jun 01 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.349
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.349
Title
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Description
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Cost Information
Time Estimate
Sep 16 2030

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.349
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.349
Title
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Description
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Cost Information
Time Estimate
Sep 16 2030
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.325
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.325
Title
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Description
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Cost Information
Time Estimate
Feb 24 2029

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.325
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.325
Title
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Description
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Cost Information
Time Estimate
Feb 24 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.326
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.326
Title
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Description
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Cost Information
Time Estimate
Feb 24 2029

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.326
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.326
Title
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Description
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Cost Information
Time Estimate
Feb 24 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.327
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.327
Title
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Description
Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
Cost Information
Time Estimate
Feb 24 2029

Not ContingentTopology Changing

Note 1: AF2-080 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AF2-080 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

Facility Contingency
8ELMONT-8LADYSMITH 500.0 kV Ckt 1 line (Any)
System Reinforcement: b4000.327
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.327
Title
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Description
Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
Cost Information
Time Estimate
Feb 24 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: n9191.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9191.0 / TC1-PH1-DOM-090
Title
Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor and associated substation work.
Description
Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA.
Total Cost ($USD)
$256,706,175
Discounted Total Cost ($USD)
$256,706,175
Allocated Cost ($USD)
$0
Time Estimate
74 to 75 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Facility Contingency
8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line (Any)

System Reinforcement: n9246.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9246.0 / TC1-PH2-DOM-040
Title
Wreck and rebuild 18.75 miles of Line 594 btwn Morrisville and Spotsylvania with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and assoc substation work to achieve new rating of 4356/4356/5009 MVA.
Description
Wreck and rebuild 18.75 miles of Line 594 between Morrisville and Spotsylvania with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA.
Total Cost ($USD)
$128,018,212
Discounted Total Cost ($USD)
$128,018,212
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months

Potential Aggregate ContributorEliminated

Note 1: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line (Any)

System Reinforcement: n9247.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9247.0 / TC1-PH2-DOM-041
Title
Wreck and rebuild 14.02 miles of Line 573 btwn Spotsylvania and North Anna with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and assoc substation work to achieve new rating of 4356/4356/5009 MVA.
Description
Wreck and rebuild 14.02 miles of Line 573 between Spotsylvania and North Anna with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and associated substation work to achieve new rating of 4356/4356/5009 MVA
Total Cost ($USD)
$99,636,684
Discounted Total Cost ($USD)
$99,636,684
Allocated Cost ($USD)
$0
Time Estimate
48 Months

Potential Aggregate ContributorEliminated

Note 1: Based on PJM cost allocation criteria, AF2-080 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-080 could receive cost allocation. Although AF2-080 may not presently have cost responsibility for this upgrade, AF2-080 is a potential Aggregate Pool Contributor.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line (Any)

System Reinforcement: n8492.2

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492.2
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.2
Title
Expand Yadkin Substation to accommodate the new 500 kV line.
Description
Expansion of yadkins 500 kV switchyard to accommodate the new 500 kV line which includes addition of 5000 amp GIS breakers and relocation of the existing suffolk -yadkin 500 kV line#565
Total Cost ($USD)
$16,207,123
Allocated Cost ($USD)
$0
Time Estimate
15 to 16 Months
Cost Alloc Type
Non-Contingent

System Reinforcement: n9259.0

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9259.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9259.0
Title
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Description
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Total Cost ($USD)
$25,304,902
Allocated Cost ($USD)
$0
Time Estimate
38 to 39 Months
Cost Alloc Type
Non-Contingent

System Reinforcement: n9267.0

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9267.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9267.0 / TC1-PH2-DOM-067
Title
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
Description
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner substations with single (1) 768.2 ACSS/TW “Maumee” at 250 degrees C. This new line will be on separate transmission towers from the existing Northern Neck and Moon Corner line 1059. Station expansion is required at Northern Neck and Moon Corner to accommodate the new line.
Total Cost ($USD)
$45,730,074
Allocated Cost ($USD)
$0
Time Estimate
45 to 46 Months
Cost Alloc Type
Non-Contingent

System Reinforcement: n9630.0

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9630.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9630.0 / TC1-PH3-DOM-013
Title
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
Description
n9630.0 addresses both stability and load flow violations. Construct a new 230 kV Line from the AG1-285 substation to the 230 kV Finneywood substation following the Line 1012 ROW for approximately 1.0 miles, then following the Line 556 ROW for approximately 3.5 miles to terminate at Finneywood. Expand the AG1-285 115 kV substation to accommodate two (2) new 115/230 kV transformers. Build a 230 kV substation at AG1-285 to connect the 115/230 kV transformers and the new 230 kV line to Finneywood. Expand the Finneywood 230 kV substation to accommodate the new line. The existing 1.0 miles of 115 kV from AG1-285 to Chase City does not need to be rebuilt to accommodate a new structure in the same right of way and therefore will be unchanged. The existing 3.5 miles of 500 kV towers from Structure 556/46 to Finneywood substation will need to be rebuilt as a double circuit tower to accommodate the new 230 kV line.
Total Cost ($USD)
$89,468,616
Allocated Cost ($USD)
$0
Time Estimate
Dec 31 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.356

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.356
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.355

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.355
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.355
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.342

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.342
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.342
Title
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Description
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.341

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.341
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.341
Title
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Description
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3689.2

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3689.2
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3689.2
Title
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA
Description
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 4000A 80 kA breakers and associated equipment including breaker leads as necessary to address breaker duty issues identified in short circuit analysis.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.103

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.103
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.103
Title
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Description
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.405

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.405
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.405
Title
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Description
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3854.1

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3854.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3854.1
Title
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Description
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.108

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.108
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.108
Title
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Description
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: n9138.0

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9138.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9138.0 / TC1-PH1-DOM-070
Title
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Description
Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
Total Cost ($USD)
$111,130,292
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.406

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.406
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.406
Title
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Description
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.115

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.115
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.115
Title
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Description
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.354

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.354
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.354
Title
Ladysmith substation breakers replacement: 574T575 and 568T581
Description
Expand Ladysmith substation to a add redundant circuit breakers to the middle breakers on both 500kV strings (574T575 and 568T581). The equipment including switches 57518, 57515, H115 will be replaced with 5000A equipment.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3853.1

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3853.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3853.1 / (Pending)
Title
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Description
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.114

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.114
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.114
Title
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Description
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.235

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.235
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.235
Title
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers
Description
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers: 212352, 2123T2173, 2030T2117, 211752, and 2008T2045
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.334

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.334
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.334
Title
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.
Description
Replace 4 overdutied 230kV breakers at Loudoun Substation with 80kA breakers: 2094T2140, 214052, 200852 and 203052.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.407

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.407
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.407
Title
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.
Description
Replace Loudoun 230 kV breakers 204552, 217352 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.119

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.119
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.119
Title
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.
Description
Loudoun Cap Sub 230kV - replace 50kA breaker SC352 with 63kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.128

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.128
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.128
Title
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.
Description
North Anna Sub 500kV - replace 40kA breakers 57502, G102-1, G102-2, G202, G2T575, XT573 with 63kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.408

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.408
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.408
Title
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.
Description
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, H342 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: s2609.6

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s2609.6
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.6
Title
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Description
Upgrade (2) 230 kV breakers 201342 & L142 from 50kA to 63kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: s2609.9

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s2609.9
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.9
Title
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.
Description
Upgrade 230kV Pleasant View breakers L3T203 and L3T2180 from 50kA to 80kA.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b4000.134

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.134
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.134
Title
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.
Description
Remington Sub 230kV - replace 40kA and 50kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, H9T299 with 63kA
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b1696

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b1696
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b1696
Title
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Description
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: n9250.0

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9250.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9250.0 / TC1-PH2-DOM-044
Title
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Description
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Total Cost ($USD)
$108,728,086
Allocated Cost ($USD)
$0
Time Estimate
60 to 61 Months
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.236

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.236
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.236
Title
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.
Description
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers: H1T539 and H2T539
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: s3047.2

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s3047.2
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
s3047.2
Title
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
Description
Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV line #535 Loudoun – Meadowbrook and #569 Loudoun - Morrisville as the 500 kV sources into the proposed 500 kV ring bus Vint Hill Substation will be expanded to the north of the existing site to accommodate the 500 kV ring required for the addition of the new transformers Existing terminations for 230 kV line #2174 Wheeler – Vint Hill, line #2101 Bristers – Vint Hill, and line #2163 Liberty – Vint Hill will be rearranged to terminate into the expanded Vint Hill Substation 230 kV line #2114 Remington CT – Rollins Ford will also be cut and looped into the expanded Vint Hill Substation due to spatial constraints along the existing right-of-way.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.312

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.312
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.312
Title
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
Description
Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.313

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.313
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.313
Title
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Description
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.356

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.356
Title
Build a new 500 kV line from Vint Hill to Wishing Star.
Description
Build a new 500kV line from Vint Hill to Wishing Star. The line will be supported on single circuit monopoles. New conductor to have a summer rating of 4357 MVA. Line length is approximately 16.59 miles
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.357

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.357
Title
Build a new 500 kV line from Morrisville to Vint Hill.
Description
Build a new 500kV line from Morrisville to Vint Hill. New conductor to have a summer rating of 4357 MVA. Line length is approximately 19.71 miles.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.354

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.354
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.354
Title
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
Description
Install terminal equipment at Wishing Star substation to support a 5000A line to Vint Hill. Update relay settings for 500kV Lines #546 and #590.
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: b3800.335

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.335
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.335
Title
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker
Description
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker: 56142
Cost Information
Cost Alloc Type
Non-Contingent

System Reinforcement: n7541

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n7541
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7541 / dom-016
Title
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Description
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Total Cost ($USD)
$22,779,395
Allocated Cost ($USD)
$0
Time Estimate
Dec 31 2029
Cost Alloc Type
Non-Contingent

System Reinforcement: n8492

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492
Title
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
Description
Wreck and rebuild one (1) overhead 500kV transmission line that will start at the existing Fentress 500 kV Substation and terminate at the existing Yadkin 500 kV Substation, located approximately 13.5 miles away.
Total Cost ($USD)
$80,172,278
Allocated Cost ($USD)
$0
Time Estimate
26 to 27 Months
Cost Alloc Type
Non-Contingent

System Reinforcement: n8492.1

AF2-080 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492.1
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.1
Title
Two Breaker Additions at Fentress Substation.
Description
Install Two 5000 amp GIS Breakers at Fentress Substation to connect the new 500 kV line 5005.
Total Cost ($USD)
$19,945,879
Allocated Cost ($USD)
$0
Time Estimate
30 to 36 Months
Cost Alloc Type
Non-Contingent

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-080


AF2-080 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF2-080 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Dominion n8492.2 Expand Yadkin Substation to accommodate the new 500 kV line. Non-Contingent $0
Dominion n9259.0 Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. Non-Contingent $0
Dominion n9267.0 Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. Non-Contingent $0
Dominion n9630.0 Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. Non-Contingent $0
Dominion b4000.357 Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. Non-Contingent $0
Dominion b4000.356 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). Non-Contingent $0
Dominion b4000.355 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). Non-Contingent $0
Dominion b4000.352 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. Non-Contingent $0
Dominion b4000.351 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. Non-Contingent $0
Dominion b4000.350 Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. Non-Contingent $0
Dominion b4000.349 Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. Non-Contingent $0
Dominion b4000.348 Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. Non-Contingent $0
Dominion b4000.346 Cut-in 500kV line from Kraken substation into Yeat substation Non-Contingent $0
Dominion b4000.345 Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. Non-Contingent $0
Dominion b4000.344 Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. Non-Contingent $0
Dominion b4000.342 Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. Non-Contingent $0
Dominion b4000.341 Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. Non-Contingent $0
Dominion b4000.325 Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. Non-Contingent $0
Dominion b3689.2 Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA Non-Contingent $0
Dominion b4000.103 Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA Non-Contingent $0
Dominion b3800.405 Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. Non-Contingent $0
Dominion b3854.1 Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA Non-Contingent $0
Dominion b4000.108 Carson Sub 230kV - replace 40kA breaker 23872 with 63kA Non-Contingent $0
Dominion b4000.326 At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. Non-Contingent $0
Dominion n9138.0 Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. Non-Contingent $0
Dominion b4000.327 Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. Non-Contingent $0
Dominion b3800.406 Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. Non-Contingent $0
Dominion b4000.115 Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA Non-Contingent $0
Dominion b4000.354 Ladysmith substation breakers replacement: 574T575 and 568T581 Non-Contingent $0
Dominion b3853.1 Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA Non-Contingent $0
Dominion b4000.114 Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA Non-Contingent $0
Dominion b3800.235 Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers Non-Contingent $0
Dominion b3800.334 Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. Non-Contingent $0
Dominion b3800.407 Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. Non-Contingent $0
Dominion b4000.119 Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. Non-Contingent $0
Dominion b4000.128 North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. Non-Contingent $0
Dominion b3800.408 Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. Non-Contingent $0
Dominion s2609.6 Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. Non-Contingent $0
Dominion s2609.9 Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. Non-Contingent $0
Dominion b4000.134 Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. Non-Contingent $0
Dominion b1696 Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 Non-Contingent $0
Dominion n9250.0 Construct a new 22.59 mile line between Carson and Rawlings Substations. Non-Contingent $0
Dominion b3800.236 Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. Non-Contingent $0
Dominion s3047.2 Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. Non-Contingent $0
Dominion b3800.312 Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. Non-Contingent $0
Dominion b3800.313 Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. Non-Contingent $0
Dominion b3800.356 Build a new 500 kV line from Vint Hill to Wishing Star. Non-Contingent $0
Dominion b3800.357 Build a new 500 kV line from Morrisville to Vint Hill. Non-Contingent $0
Dominion b3800.354 Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. Non-Contingent $0
Dominion b3800.335 Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker Non-Contingent $0
Dominion n7541 Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. Non-Contingent $0
Dominion n8492 Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. Non-Contingent $0
Dominion n8492.1 Two Breaker Additions at Fentress Substation. Non-Contingent $0
Region Topology Upgrade Total: $0

Attachments

AF2-080 One Line Diagram

AF2-080 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.