AF2-126 Phase III Study Report

v1.00 released 2025-09-18 16:32

Weston 69 kV II

8.0 MW Capacity / 12.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Juliet Energy Project, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $235,091 $233,066 = 1.01 AND ( $235,091 - $233,066 ) 12.0 = $169 per MW

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the American Transmission Systems, Incorporated zone — Wood County, Ohio. This project is an increase to the developer’s AF1-064 project(s), which will share the same Point of Interconnection. The AF2-126 project is a 12.0 MW uprate (8.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 62.0 MW with 41.4 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-126
Project Name:
Weston 69 kV II
Project Developer Name:
Juliet Energy Project, LLC
State:
Ohio
County:
Wood
Transmission Owner:
American Transmission Systems, Incorporated
MFO:
62.0
MWE:
12.0
MWC:
8.0
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF2-126 will interconnect with the American Transmission Systems, Incorporated transmission system as an uprate to AF1-064 at the Weston 69 kV Substation.  The Project Developer will be responsible for acquiring all easements, properties, and permits that may be required.

Attached to this report is a one-line diagram of the proposed interconnection facilities for the AF2-126 generation project to connect to transmission system. 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF2-126 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF2-126 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $58,252 $58,252
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $233,066 $233,066
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $0 $0
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $2,025 $0
Total $293,343 $291,318

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF1-064/AF2-126

Security has been calculated for the AF1-064/AF2-126 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF1-064/AF2-126
Project(s): AF1-064/AF2-126
Final Agreement Security (A): $3,049,353
Portion of Costs Already Paid (B): $2,758,036
Net Security Due at DP3: A B = $291,317
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

AF2-126 will interconnect with the ATSI transmission system as an uprate to AF1-064 at the Sand Ridge 69 kV Substation. No additional interconnection facilities are required. The developer will be responsible for acquiring all easements, properties, and permits that may be required.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9621.0

Revise relay settings at Sand Ridge.

$49,250 $0 $9,002 $0 $58,252 $58,252
n9620.0

Revise relay settings at Bowling Green No. 2.

$49,299 $0 $9,011 $0 $58,310 $58,310
n9619.0

Revise relay settings Midway.

$49,250 $0 $9,002 $0 $58,252 $58,252
n9618.0

Revise relay settings Ayersville.

$49,250 $0 $9,002 $0 $58,252 $58,252
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Integrate Interconnection Facilities protection and controls to the transmission system.

$49,250 $0 $9,002 $0 $58,252 $58,252

Based on the scope of work for the Interconnection Facilities, it is expected to take 10 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

 

Transmission Owner Analysis

TO performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AF2-126 did not contribute to any overloads on the TO transmission <100 kV system.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ATSI interconnection requirements can be found here. Refer to AF2-126 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 12.0 MW (8.0 MW Capacity) injection in the ATSI area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

The New Service Request project in PJM Transition Cycle 1, Cluster 74 is listed in Table 1 below. The report covers the dynamic analysis of the Cluster 74 project.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 74 project meets the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include the applicable project. The Cluster 74 project was dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

 

The Cluster 74 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 87 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e) Single phase faults with normal clearing on common structure (Category P7)

High Speed Reclosing (HSR) facilities were found in the vicinity of the TC1 Cluster 74 project.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

a) The Cluster 74 project is able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with the Cluster 74 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-126 was tripped during the fault application close to the POI as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

No mitigation is required for TC1 Cluster 74.

 

Table 1: TC1 Cluster 74 Project 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

74

AF2-126

Solar

FirstEnergy (FE) transmission system, West Penn Power (“WPP” in ATSI) zone

62 MW

12 MW

8 MW

Weston substation

69 kV

 

 

Reactive Power Analysis

 Cluster 74 (PJM Queue project AF2-126) meets the PJM reactive power requirement, maintaining a 0.95 leading and lagging power factor at the high side of the Main Power Transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted Facility Transmission Owner Reinforcement Cost Cost Allocated to AF2-126 Scenarios
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
DEI DEI: Rebuild 1 mile of Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$1,500,000 $169
  • NIPSCO LPC
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS NIPSCO: Rebuild line (.3miles)Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M
NIPSCO: Rebuild line, NIPSCO owns 0.037 miles of
0.9 mile line. NIPSCO portion included in Argos to
Rochester tap mitigation/cost.
$0 $0
  • NIPSCO LPC
  • Argos 69.0 - Plymouth 69.0 CKT 1
NIPS Rebuild Argos - Plymouth 69 kV line
Rebuild line, approx 10 miles
$12,654,948 $1,398
  • NIPSCO LPC
  • Argos 69.0 - Rochester TP 69.0 CKT 1
NIPS Rebuild Argos - Rochester TP 69 kV
Rebuild line, approx 3.2 miles
$4,049,583 $458
  • NIPSCO LPC
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase III System Impact Study load flow analysis.

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-126


AF2-126 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF2-126 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AF2-126 One Line Diagram

AF2-126 One Line Diagram.png

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.