AF2-335 Phase III Study Report
v1.00 released 2025-09-18 16:42
Delaware-Royerton 138 kV
60.0 MW Capacity / 100.0 MW Energy
Introduction
This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Royerton Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..
Preface
New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
- PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
- PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
- The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
- PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).
Decision Point III Requirements
At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.
As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:
- Increase overall by 35% or more
- Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Solar generating facility located in the American Electric Power zone — Delaware County, Indiana. The installed facilities will have a total capability of 100.0 MW with 60.0 MW of this output being recognized by PJM as Capacity.
Project Information
- New Service Request Number:
- AF2-335
- Project Name:
- Delaware-Royerton 138 kV
- Project Developer Name:
- Royerton Solar, LLC
- State:
- Indiana
- County:
- Delaware
- Transmission Owner:
- AEP Indiana Michigan Transmission Company, Inc.
- MFO:
- 100.0
- MWE:
- 100.0
- MWC:
- 60.0
- Fuel Type:
- Solar
- Basecase Study Year:
- 2027
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AF2-335 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system tapping the Delaware to Royerton 138 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).
Based on the Phase III SIS results, the AF2-335 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.
| Description | Cost Allocated to AF2-335 | Cost Subject to Security |
|---|---|---|
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 |
| Other Scope | $0 | $0 |
| Option to Build Oversight | $155,068 | $155,068 |
| Physical Interconnection Network Upgrades | ||
| Stand Alone Network Upgrades | $0 | $0 |
| Network Upgrades | $1,065,672 | $1,065,672 |
| System Reliability Network Upgrades | ||
| Steady State Thermal & Voltage (SP & LL) | $0 | $0 |
| Transient Stability | $0 | $0 |
| Short Circuit | $0 | $0 |
| Transmission Owner Analysis | ||
| SubRegional | $0 | $0 |
| Distribution | $0 | $0 |
| Affected System Study Reinforcements | ||
| AFS - PJM Violatons | $0 | $0 |
| AFS - Non-PJM Violations | $8,357 | $0 |
| Total | $1,229,098 | $1,220,741 |
* Contributes to calculation for Security. See Security Section of this report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Security Requirement
Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).
Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.
Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Security Due for AF2-335/AF2-370
Security has been calculated for the AF2-335/AF2-370 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.
Security Due for AF2-335/AF2-370
Transmission Owner Scope of Work
AF2-335 will interconnect with the AEP transmission system via a new station cut into the Delaware - Desoto 138 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Project Developer has elected the option Option to Build where they will assume responsibility for the design, procurement and construction of the Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades identified in this Phase III SIS report.
The Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.
The cost estimates for eligible facilities and Option to Build oversight are highlighted below:
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| n9478.0 |
Delaware - Royerton 138 kV: Interconnection Substation tie-in. Install two (2) new steel, single circuit, single pole dead end structures on concrete piers with anchor bolt cages along the existing West Del - Royerton 138 kV Circuit, one (1) additional steel, single circuit, single pole, running angle structure along the perimeter of the proposed AF2-335/AF2-370 138 kV station, and three (3) spans of ACSR 1033.5 (Curlew) transmission line conductor with 7#8 Alumoweld shield wire, cutting in the proposed AF2-335/AF2-370 138 kV station in an in-and-out arrangement. |
$801,197 | $613,378 | $107,527 | $82,320 | $1,604,422 | $802,211 (See Note 1) |
| n9477.0 |
Delaware 138 kV: • Reconfigure the existing ICON. • Install one (1) new small form-factor pluggable (SFP) transceiver. • Review and revise the protective relay settings. |
$13,877 | $7,750 | $7,932 | $4,430 | $33,989 | $16,994 (See Note 1) |
| n9476.0 |
Royerton 138 kV: • Reconfigure the existing ICON. • Install one (1) new SFP transceiver. • Review and revise the protective relay settings. |
$13,877 | $7,750 | $7,932 | $4,430 | $33,989 | $16,994 (See Note 1) |
| n9475.0 |
Proposed AF2-335/AF2-370, Delaware, and Royerton 138 kV Stations: Final Tie in for Fiber installation in new right of way (ROW). • Install one (1) ADLT fiber optic cable station exit transition and 0.5 miles of 96 ct ADLT fiber optic cable in new underground ROW terminating at a new splice on existing AEP fiber cable. • Install one (1) ADLT station exit transition, 0.3 miles of 96 ct ADLT cable installed in new underground ROW, and 0.3 miles of all dielectric loose tube fiber cable on existing distribution structures terminating at a new splice on an existing AEP fiber cable |
$317,761 | $83,233 | $45,910 | $12,041 | $458,945 | $229,472 (See Note 1) |
| Option to Build Oversight | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) |
New Interconnection Substation (Oversight) |
$137,553 | $48,951 | $91,184 | $32,449 | $310,137 | $155,068 (See Note 1) |
Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 22 to 26 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AF2-335 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.
Summer Peak Analysis
The New Service Request was evaluated as a 80.0 MW (60.0 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution |
|---|---|---|---|---|---|---|---|---|---|
| OVEC |
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1 |
DEOK_P2-3_1403_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A' OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1 /*08M.FORT 345.0 - 05TANNER 345.0 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7 /*08M.FORT 345.0 - 08M.FRT7 22.0 END |
Breaker | AC | 111.15 % | 971.0 | B | 1079.31 | 6.39 |
| OVEC |
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1 |
DEOK_P2-3_1401_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A' OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1 /*08M.FORT 345.0 - 05TANNER 345.0 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9 /*08M.FORT 345.0 - 08M.FORT 138.0 END |
Breaker | AC | 110.64 % | 971.0 | B | 1074.33 | 6.39 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
Summer Potential Congestion due to Local Energy Deliverability
PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.
Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution |
|---|---|---|---|---|---|---|---|---|---|
| AEP |
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
944540 to 243225 ckt 1 |
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C' OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2 /*AF1-118 TP 345.0 - 05SORENS 345.0 END |
OP | AC | 131.92 % | 897.0 | B | 1183.36 | 13.2 |
| AEP |
AF2-177 TP-AF1-118 TP 345.0 kV Ckt 2 line
958860 to 944530 ckt 2 |
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A' OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1 /*05KEYSTN 345.0 - 05SORENS 345.0 END |
OP | AC | 113.9 % | 971.0 | B | 1105.94 | 13.27 |
| AEP |
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1 |
Base Case | OP | AC | 108.31 % | 897.0 | A | 971.56 | 9.59 |
| AEP |
AF1-202 TP-AF1-119 TP 345.0 kV Ckt 1 line
945370 to 944540 ckt 1 |
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C' OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2 /*AF1-118 TP 345.0 - 05SORENS 345.0 END |
OP | AC | 103.54 % | 897.0 | B | 928.73 | 13.2 |
| AEP |
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1 |
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C' OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2 /*AF1-118 TP 345.0 - 05SORENS 345.0 END |
OP | AC | 103.3 % | 1318.0 | B | 1361.46 | 13.11 |
| AEP |
05DESOTO-AF2-177 TP 345.0 kV Ckt 2 line
243218 to 958860 ckt 2 |
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A' OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1 /*05KEYSTN 345.0 - 05SORENS 345.0 END |
OP | AC | 100.27 % | 971.0 | B | 973.65 | 13.27 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution |
|---|---|---|---|---|---|---|---|---|---|
| AEP |
AF1-118 TP-05SORENS 345.0 kV Ckt 2 line
944530 to 243232 ckt 2 |
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A' OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1 /*05KEYSTN 345.0 - 05SORENS 345.0 END |
OP | AC | 100.62 % | 1318.0 | B | 1326.14 | 13.34 |
Winter Peak Analysis
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Winter Potential Congestion due to Local Energy Deliverability
PJM will start performing Winter Peak analysis in Transition Cycle 2.
Light Load Analysis
Light Load Analysis is Not Required.
Light Load Potential Congestion due to Local Energy Deliverability
Light Load Analysis is Not Required.
Short Circuit Analysis
The Phase III Short circuit analysis was conducted for the following two study scenarios
- Scenario 1 - TC1 Projects Impact;
- Scenario 2 - TC1 Topology-Changing Upgrade Impacts;
The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1
Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests (projects) in PJM Transition Cycle 1, Cluster 59 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 59 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 59 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 59 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.01 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.
Cluster 59 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 40 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:
a) Steady-state operation (Category P0);
b) Three-phase faults with normal clearing time (Category P1);
c) Single-phase faults with stuck breaker (Category P4);
d) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).
e) Three-phase faults with normal clearing for common structure (Category P7).
Multiple-circuit tower line faults were identified for this study.
High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 59 projects.
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all of the fault contingencies tested on the 2027 peak load case:
a) Cluster 59 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 59 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
AF2-335 and AF2-370 meet the 0.95 leading and lagging PF requirement.
AE1-208 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.
No mitigations were found to be required for TC1 Cluster 59.
Table 1: TC1 Cluster 59 Projects
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
59 | AF2-335 | Solar | American Electric Power (AEP) | 100 MW | 100 MW | 60 MW | Delaware- Royerton 138 kV |
AF2-370 | Storage | American Electric Power (AEP) | 100 MW | 0 MW | 20 MW | Delaware- Royerton 138 kV |
Reactive Power Analysis
The reactive power capability of AF2-335 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AC1-174 | Losantville 345kV | In Service |
| AC1-175 | Losantville 345kV | In Service |
| AC2-090 | Losantville 345kV | In Service |
| AC2-111 | College Corner 138kV | Engineering & Procurement |
| AC2-176 | Jay 138 kV | In Service |
| AD1-043 | Makahoy 138 kV | Withdrawn |
| AD1-128 | Modoc-Delaware 138 kV | Under Construction |
| AD2-071 | Strawton-Deer Creek 138 kV | Suspended |
| AE1-207 | Mississinewa-Gaston 138 kV | Suspended |
| AE1-208 | Delaware-Van Buren 138 kV | Suspended |
| AE1-209 | Desoto 345 kV | Suspended |
| AE1-210 | Desoto 345 kV | Suspended |
| AE2-089 | Pennville-Adams 138 kV | Engineering & Procurement |
| AE2-169 | Delaware-Van Buren 138 kV | Suspended |
| AE2-172 | Mississinewa-Gaston 138 kV | Suspended |
| AE2-219 | Bluff Point-Randolph 138 kV | Suspended |
| AE2-220 | Losantville 345 kV | Engineering & Procurement |
| AE2-234 | Liberty Center-Buckeye Tap 69 kV | Engineering & Procurement |
| AE2-297 | Madison-Tanners Creek 138 kV | In Service |
| AF1-071 | College Corner 138 kV | Engineering & Procurement |
| AF1-118 | Sorenson-Desoto 345 kV | Engineering & Procurement |
| AF1-119 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF1-202 | Keystone-Desoto 345 kV | Under Construction |
| AF1-223 | Keystone-Desoto 345 kV | Under Construction |
| AF1-268 | Desoto-Jay 138 kV | Engineering & Procurement |
| AF2-068 | Jay 138 kV | Active |
| AF2-162 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-173 | Desoto 345 kV | Active |
| AF2-177 | Sorenson-DeSoto #2 345 kV | Active |
| AF2-370 | Delaware-Royerton 138 kV | Active |
| AF2-388 | Keystone-Desoto 345 kV | Active |
| AF2-407 | Fall Creek 345 kV | Active |
| AF2-408 | Fall Creek 138 kV | Engineering & Procurement |
| AG1-017 | Jay 138 kV | Under Construction |
| AG1-047 | Jay 138 kV | Engineering & Procurement |
| AG1-297 | Hanna-Tanners Creek 345 kV | Active |
| AG1-324 | Jay-Desoto 138 kV | Engineering & Procurement |
| AG1-367 | DeSoto 345 kV | Active |
| AG1-375 | Sorenson-Desoto 345 kV | Active |
| AG1-414 | Mississinewa 138 kV | Engineering & Procurement |
| AG1-433 | Keystone-DeSoto 345 kV | Active |
| V3-007 | Desoto-Tanners Creek #1 345kV | In Service |
| Z2-115 | Deer Creek 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.
If your project required an Affected System Study, the results are shown below from the Affected System Operator.
For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.
Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.
| Impacted Facility | Transmission Owner | Reinforcement | Cost | Cost Allocated to AF2-335 | Scenarios |
|---|---|---|---|---|---|
|
DEI |
Install 144 MVAR cap bank at Gallagher sub.
Install 144 MVAR cap bank at Gallagher sub. |
$3,000,000 | $8,357 |
|
System Reinforcements
No cost allocated system reinforcements were identified for this project in the Phase III System Impact Study load flow analysis.
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n7881
- Type
- Load Flow
- TO
- OVEC
- RTEP ID / TO ID
- n7881 / OVEC0001a
- Title
- Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F
- Description
- •Remove and replace sixteen (16) existing double circuit towers with taller double circuit custom steel poles. (Towers 11, 14, 45, 47, 52, 57, 59, 61, 63, 66, 67, 71, 77, 84, 91, and 96) •Remove and replace two (2) existing river crossing lattice towers with taller lattice structures. (Towers 2 and 140)
- Total Cost ($USD)
- $24,006,000
- Discounted Total Cost ($USD)
- $24,006,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 38 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AF2-335 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AF2-335 could receive cost allocation. Although AF2-335 may not presently have cost responsibility for this upgrade, AF2-335 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 06DEARB1-06PIERCE 345.0 kV Ckt 1 line | (Any) |
Attachments
AF2-335 One Line Diagram
[1]Winter load flow analysis will be performed starting in Transition Cycle 2.