AF2-358 Phase III Study Report

v1.00 released 2025-09-18 16:44

Airey-Vienna 69 kV

60.0 MW Capacity / 100.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is RWE Solar Development, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Delmarva Power and Light Company.

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $59,241,848 $10,337,020 = 5.73 AND ( $59,241,848 - $10,337,020 ) 100.0 = $489,048 per MW

General

The Project Developer has proposed a Solar generating facility located in the Delmarva Power and Light Company zone — Dorchester County, Maryland. The installed facilities will have a total capability of 100.0 MW with 60.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-358
Project Name:
Airey-Vienna 69 kV
Project Developer Name:
RWE Solar Development, LLC
State:
Maryland
County:
Dorchester
Transmission Owner:
Delmarva Power and Light Company
MFO:
100.0
MWE:
100.0
MWC:
60.0
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF2-358 will interconnect on the Delmarva Power and Light Company transmission system by tapping the Airey - Vienna 69 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF2-358 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF2-358 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $0 $0
Other Scope $0 $0
Option to Build Oversight $1,500,000 $1,500,000
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $610,000 $610,000
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $57,529,731 $57,529,731
Transient Stability $1,102,116 $1,102,116
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $60,741,848 $60,741,848

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF2-358/AG1-450

Security has been calculated for the AF2-358/AG1-450 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF2-358/AG1-450
Project(s): AF2-358/AG1-450
Final Agreement Security (A): $78,611,927
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $78,611,927
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The total preliminary cost estimate is given in the table below. These costs do not include CIAC Tax Gross-up. Relay and Communication upgrades may require new fiber optic installation.

AF2-358 shares physical interconnection scope with AG1-450, which is also in Transition Cycle 1.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Project Developer has elected the option Option to Build where they will assume responsibility for the design, procurement and construction of the Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades identified in this Phase III SIS report.

The Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9604.0

Cut and loop the Vienna – West Cambridge 69 kV #6709 line into the new AF2-358/AG1-450 Interconnection Substation.

$465,000 $280,000 $155,000 $0 $900,000 $450,000 (See Note 1)
n9603.0

Replace existing 6709F-SEL421 relay with a new SEL-411L relay at Vienna 69 kV substation.

$89,886 $31,250 $28,864 $0 $150,000 $75,000 (See Note 1)
n9602.0

Replace existing 6709F-SEL321 relay with a new SEL-411L relay at West Cambridge 69 kV substation.

$89,886 $31,250 $28,864 $0 $150,000 $75,000 (See Note 1)
n9601.0

Install and splice optical ground wire (OPGW) fiber cable from the 6709 and 67YY transmission lines into the substation control house. Create fiber communications paths between new AF2-358/AG1-450 Interconnection Substation and Vienna and West Cambridge 69 kV substations for the purposes of end-to-end protective relay communications.

$14,192 $1,250 $4,558 $0 $20,000 $10,000 (See Note 1)
Option to Build Oversight
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Transmission Owner Interconnection Facilities (Oversight)

$75,173 $0 $25,058 $0 $100,231 $50,116 (See Note 1)
(Pending)

New Interconnection Substation (Oversight)

$2,147,318 $0 $715,773 $0 $2,863,091 $1,431,546 (See Note 1)
(Pending)

Fiber Installation in New ROW (Oversight)

$27,509 $0 $9,170 $0 $36,679 $18,340 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 48 to 60 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

Based on the scope of work for the interconnection facilities, it is expected to take a range of 48 to 60 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.


 
The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase III System Impact Studies. The estimated time to complete each of the required reinforcements is identified in the "System Reinforcements" section of the report.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. DPL interconnection requirements can be found here. Refer to AF2-358 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request was evaluated as a 100.0 MW (60.0 MW Capacity) injection in the DPL area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DP&L/PECO EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line
231001 to 214236 ckt 1
DPL_P4-2_DPEM231_SRT-A
CONTINGENCY 'DPL_P4-2_DPEM231_SRT-A'
 DISCONNECT BRANCH FROM BUS 231000 TO BUS 231001 CKT 1   /*CLAY_230     230.0 - EDGEMR 5     230.0
 DISCONNECT BRANCH FROM BUS 231001 TO BUS 231109 CKT 1   /*EDGEMR 5     230.0 - EDGEMR 4     138.0
END
Breaker AC 103.76 % 808.0 B 838.36 12.24

Details for EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line l/o DPL_P4-2_DPEM231_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L/PECO
Facility Description:
EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line
231001 to 214236 ckt 1
Contingency Name:
DPL_P4-2_DPEM231_SRT-A
CONTINGENCY 'DPL_P4-2_DPEM231_SRT-A'
 DISCONNECT BRANCH FROM BUS 231000 TO BUS 231001 CKT 1   /*CLAY_230     230.0 - EDGEMR 5     230.0
 DISCONNECT BRANCH FROM BUS 231001 TO BUS 231109 CKT 1   /*EDGEMR 5     230.0 - EDGEMR 4     138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 103.76 %
Rating: 808.0 MVA
Rating Type: B
MVA to Mitigate: 838.36 MVA
MW Contribution: 12.24 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L/PECO
Facility Description:
EDGEMR 5-LINWOOD85 230.0 kV Ckt 1 line
231001 to 214236 ckt 1
Contingency Name:
DPL_P4-2_DPEM231_SRT-A
CONTINGENCY 'DPL_P4-2_DPEM231_SRT-A'
 DISCONNECT BRANCH FROM BUS 231000 TO BUS 231001 CKT 1   /*CLAY_230     230.0 - EDGEMR 5     230.0
 DISCONNECT BRANCH FROM BUS 231001 TO BUS 231109 CKT 1   /*EDGEMR 5     230.0 - EDGEMR 4     138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 103.46 %
Rating: 808.0 MVA
Rating Type: B
MVA to Mitigate: 835.96 MVA
MW Contribution: 12.24 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
231505 HR4 50/50 16.52 MW 16.52 MW
231900 EM5 50/50 39.14 MW 39.14 MW
231908 HR1 50/50 2.1 MW 2.1 MW
231909 HR2 50/50 1.64 MW 1.64 MW
231910 HR3 50/50 2.1 MW 2.1 MW
232404 W1-003 C 50/50 0.26 MW 0.26 MW
232405 W1-003 E 50/50 1.48 MW 1.48 MW
232406 W1-004 C 50/50 0.26 MW 0.26 MW
232407 W1-004 E 50/50 1.48 MW 1.48 MW
232408 W1-005 C 50/50 0.26 MW 0.26 MW
232409 W1-005 E 50/50 1.48 MW 1.48 MW
232410 W1-006 C 50/50 0.26 MW 0.26 MW
232411 W1-006 E 50/50 1.48 MW 1.48 MW
232412 X1-032 E 50/50 0.48 MW 0.48 MW
232416 X2-083 50/50 0.08 MW 0.08 MW
232417 X3-008 C 50/50 0.15 MW 0.15 MW
232418 X3-008 E 50/50 1.53 MW 1.53 MW
232426 Y1-080 FULL 50/50 0.03 MW 0.03 MW
232427 Y1-080 E 50/50 0.26 MW 0.26 MW
232428 Y3-058 C 50/50 0.17 MW 0.17 MW
232429 Y3-058 E 50/50 1.12 MW 1.12 MW
232851 DUP-SFR1 Adder 1.17 MW 0.99 MW
232904 IR4 Adder 47.97 MW 40.77 MW
232907 VN8 50/50 3.01 MW 3.01 MW
232916 OH NUG5 50/50 0.88 MW 0.88 MW
232919 VN10 50/50 0.28 MW 0.28 MW
232921 TASLEY2G 50/50 0.58 MW 0.58 MW
232926 CRISFLD1 50/50 0.2 MW 0.2 MW
918835 AA1-102 E 50/50 11.16 MW 11.16 MW
926132 AC1-091 E Adder 1.26 MW 1.07 MW
926142 AC1-092 E Adder 1.26 MW 1.07 MW
926152 AC1-093 E Adder 1.2 MW 1.02 MW
926162 AC1-094 E Adder 1.02 MW 0.86 MW
927031 AC1-190 C 50/50 4.32 MW 4.32 MW
927032 AC1-190 E 50/50 1.85 MW 1.85 MW
943361 AF1-007 C Adder 0.22 MW 0.19 MW
943362 AF1-007 E Adder 0.63 MW 0.54 MW
943441 AF1-015 C 50/50 0.81 MW 0.81 MW
943442 AF1-015 E 50/50 1.11 MW 1.11 MW
943651 AF1-036 C 50/50 1.05 MW 1.05 MW
943652 AF1-036 E 50/50 1.45 MW 1.45 MW
959591 AF2-250 C 50/50 0.02 MW 0.02 MW
959592 AF2-250 E 50/50 0.1 MW 0.1 MW
960882 AF2-379 E 50/50 0.27 MW 0.27 MW
233915 AB1-141 C 50/50 0.27 MW 0.27 MW
233916 AB1-141 E 50/50 0.78 MW 0.78 MW
233918 AB1-142 C 50/50 0.27 MW 0.27 MW
233919 AB1-142 E 50/50 0.78 MW 0.78 MW
233923 AA1-102 C 50/50 1.0 MW 1.0 MW
923962 AB2-037 E 50/50 16.69 MW 16.69 MW
924832 AB2-136 E 50/50 3.23 MW 3.23 MW
930202 AB1-056 E Adder 21.36 MW 18.16 MW
932161 AC2-023 C 50/50 3.2 MW 3.2 MW
932162 AC2-023 E 50/50 2.33 MW 2.33 MW
941021 AE2-093 C 50/50 2.14 MW 2.14 MW
941022 AE2-093 E 50/50 3.5 MW 3.5 MW
941181 AE2-112 C 50/50 0.81 MW 0.81 MW
941182 AE2-112 E 50/50 1.32 MW 1.32 MW
964962 AG1-360 E 50/50 1.05 MW 1.05 MW
965321 AG1-397 C Adder 0.5 MW 0.42 MW
965322 AG1-397 E Adder 0.69 MW 0.58 MW
925254 AB2-179 E 50/50 1.49 MW 1.49 MW
933632 AC2-185 E Adder 2.55 MW 2.17 MW
232436 AB1-176 C 50/50 0.42 MW 0.42 MW
923603 AB1-176 E 50/50 0.69 MW 0.69 MW
923952 AB2-036 E 50/50 7.25 MW 7.25 MW
917082 Z2-012 E 50/50 1.48 MW 1.48 MW
924822 AB2-135 E 50/50 4.09 MW 4.09 MW
232424 Y1-079 C 50/50 0.08 MW 0.08 MW
232425 Y1-079 E 50/50 0.78 MW 0.78 MW
232433 Z2-076 E Adder 0.24 MW 0.2 MW
232435 Z2-077 E Adder 0.24 MW 0.2 MW
232905 CHERITON_25 50/50 0.24 MW 0.24 MW
936615 AD2-076_E 50/50 3.81 MW 3.81 MW
233900 O-025 C 50/50 0.12 MW 0.12 MW
233901 CHERRYDALE C 50/50 0.15 MW 0.15 MW
233906 AB1-056 C Adder 7.5 MW 6.38 MW
233939 AC1-091 C Adder 0.77 MW 0.66 MW
233940 AF2-379 C 50/50 0.03 MW 0.03 MW
233944 AB2-135 C 50/50 0.59 MW 0.59 MW
233946 AB2-136 C 50/50 0.5 MW 0.5 MW
233955 AB2-172 C OP 50/50 0.38 MW 0.38 MW
233968 AD2-076_C 50/50 2.33 MW 2.33 MW
233970 AC1-092 C Adder 0.77 MW 0.66 MW
233971 AC1-093 C Adder 0.73 MW 0.62 MW
233972 AC1-094 C Adder 0.62 MW 0.52 MW
233973 AC2-185 C Adder 1.56 MW 1.33 MW
233982 AB2-133 C 50/50 0.46 MW 0.46 MW
233984 AB2-036 C 50/50 4.43 MW 4.43 MW
233987 AB2-037 C 50/50 10.22 MW 10.22 MW
923925 AB2-153 E 50/50 1.54 MW 1.54 MW
923928 AB2-032 E 50/50 0.8 MW 0.8 MW
924802 AB2-133 E 50/50 3.81 MW 3.81 MW
925152 AB2-172 E OP 50/50 3.83 MW 3.83 MW
933645 AC2-186 E Adder 0.71 MW 0.6 MW
933655 AC2-187 E Adder 1.41 MW 1.2 MW
933665 AC2-188 E Adder 1.41 MW 1.2 MW
232422 X3-066 C 50/50 0.06 MW 0.06 MW
232423 X3-066 E 50/50 0.36 MW 0.36 MW
233964 AF2-378 C 50/50 0.14 MW 0.14 MW
960872 AF2-378 E 50/50 0.19 MW 0.19 MW
960341 AF2-325 C 50/50 0.52 MW 0.52 MW
960342 AF2-325 E 50/50 0.71 MW 0.71 MW
960671 AF2-358 C 50/50 7.34 MW 7.34 MW
960672 AF2-358 E 50/50 4.89 MW 4.89 MW
957661 AF2-060 C Adder 1.08 MW 0.91 MW
965821 AG1-450 C 50/50 3.06 MW 3.06 MW
233930 AB2-032 GEN 50/50 0.28 MW 0.28 MW
233933 AB2-153 GEN 50/50 0.15 MW 0.15 MW
233935 AB2-179 C 50/50 0.74 MW 0.74 MW
233985 AG1-318 E Adder 0.14 MW 0.12 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.99 MW 0.99 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.49 MW 0.49 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.14 MW 1.14 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.57 MW 1.57 MW
NY PJM->LTFIMP_NY CLTF 0.64 MW 0.64 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.04 MW 0.04 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 0.12 MW 0.12 MW
MEC LTFEXP_MEC->PJM CLTF 0.1 MW 0.1 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.14 MW 0.14 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 10.41 MW 10.41 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
DP&L VIENN_69-SHARPTWN 69.0 kV Ckt 1 line
232241 to 232239 ckt 1
Base Case OP AC 114.83 % 50.0 A 57.42 15.48
DP&L AB2-136 TAP-BAYLY 69.0 kV Ckt 1 line
233945 to 232292 ckt 1
Base Case OP AC 113.56 % 50.0 A 56.78 20.62
DP&L VIENN_69-MARDELA 69.0 kV Ckt 1 line
232241 to 232838 ckt 1
DPL_P1_2_CKT 6705_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6705_SRT-A'
 DISCONNECT BUS 232239   /*SHARPTWN      69.0
 DISCONNECT BUS 232607   /*SHRPTWN1      12.5
END
OP AC 113.25 % 64.0 B 72.48 21.57
DP&L/PECO CLAY_230-LINWOOD84 230.0 kV Ckt 1 line
231000 to 214235 ckt 1
PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A
CONTINGENCY 'PECO_P1-2_220-85
 TRIP BRANCH FROM BUS 214236 TO BUS 231001 CKT 1   /*LINWOOD85    230.0 - EDGEMR 5     230.0
END
OP AC 107.01 % 799.0 B 854.99 15.28
DP&L VIENN_69-SHARPTWN 69.0 kV Ckt 1 line
232241 to 232239 ckt 1
DPL_P1_2_CKT 6775_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6775_SRT-A'
 DISCONNECT BUS 232291   /*ROCKAWLKN     69.0
END
OP AC 106.4 % 71.0 B 75.55 19.64
DP&L EDGEMR 5-CLAY_230 230.0 kV Ckt 1 line
231001 to 231000 ckt 1
PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A
CONTINGENCY 'PECO_P1-2_220-85
 TRIP BRANCH FROM BUS 214236 TO BUS 231001 CKT 1   /*LINWOOD85    230.0 - EDGEMR 5     230.0
END
OP AC 105.35 % 808.0 B 851.25 13.53
DP&L MARDELA-HEBRON 69.0 kV Ckt 1 line
232838 to 232270 ckt 1
DPL_P1_2_CKT 6705_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6705_SRT-A'
 DISCONNECT BUS 232239   /*SHARPTWN      69.0
 DISCONNECT BUS 232607   /*SHRPTWN1      12.5
END
OP AC 104.5 % 64.0 B 66.88 21.57
DP&L BAYLY-CAMBRIDG 69.0 kV Ckt 1 line
232292 to 232237 ckt 1
Base Case OP AC 103.34 % 50.0 A 51.67 20.62
DP&L AF2-358 TP-VIENNALC 69.0 kV Ckt 1 line
960670 to 232242 ckt 1
DPL_P1_2_CKT 6715_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6715_SRT-A'
 DISCONNECT BUS 232817   /*ENMKTREA      69.0
END
OP AC 102.41 % 174.0 B 178.19 99.99
DP&L VIENNALC-VIENN_69 69.0 kV Ckt 1 line
232242 to 232241 ckt 1
DPL_P1_2_CKT 6715_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6715_SRT-A'
 DISCONNECT BUS 232817   /*ENMKTREA      69.0
END
OP AC 102.36 % 174.0 B 178.1 99.99

Details for VIENN_69-SHARPTWN 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
VIENN_69-SHARPTWN 69.0 kV Ckt 1 line
232241 to 232239 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 114.83 %
Rating: 50.0 MVA
Rating Type: A
MVA to Mitigate: 57.42 MVA
MW Contribution: 15.48 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L
Facility Description:
VIENN_69-SHARPTWN 69.0 kV Ckt 1 line
232241 to 232239 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 114.82 %
Rating: 50.0 MVA
Rating Type: A
MVA to Mitigate: 57.41 MVA
MW Contribution: 15.48 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232417 X3-008 C 50/50 0.16 MW 0.16 MW
232418 X3-008 E 50/50 1.57 MW 1.57 MW
232426 Y1-080 FULL 50/50 0.03 MW 0.03 MW
232427 Y1-080 E 50/50 0.32 MW 0.32 MW
232851 DUP-SFR1 Adder -1.18 MW -1.0 MW
232919 VN10 50/50 0.37 MW 0.37 MW
927031 AC1-190 C 50/50 4.55 MW 4.55 MW
927032 AC1-190 E 50/50 1.95 MW 1.95 MW
924832 AB2-136 E 50/50 3.81 MW 3.81 MW
932161 AC2-023 C Adder 1.81 MW 1.54 MW
932162 AC2-023 E Adder 1.32 MW 1.12 MW
233946 AB2-136 C 50/50 0.59 MW 0.59 MW
233955 AB2-172 C OP 50/50 0.39 MW 0.39 MW
925152 AB2-172 E OP 50/50 3.94 MW 3.94 MW
233964 AF2-378 C 50/50 0.16 MW 0.16 MW
960872 AF2-378 E 50/50 0.22 MW 0.22 MW
960341 AF2-325 C 50/50 0.58 MW 0.58 MW
960342 AF2-325 E 50/50 0.8 MW 0.8 MW
960671 AF2-358 C 50/50 9.29 MW 9.29 MW
960672 AF2-358 E 50/50 6.19 MW 6.19 MW
965821 AG1-450 C 50/50 3.87 MW 3.87 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.02 MW 0.02 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.02 MW 0.02 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.0 MW 0.0 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for AB2-136 TAP-BAYLY 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
AB2-136 TAP-BAYLY 69.0 kV Ckt 1 line
233945 to 232292 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.56 %
Rating: 50.0 MVA
Rating Type: A
MVA to Mitigate: 56.78 MVA
MW Contribution: 20.62 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DP&L
Facility Description:
AB2-136 TAP-BAYLY 69.0 kV Ckt 1 line
233945 to 232292 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.56 %
Rating: 50.0 MVA
Rating Type: A
MVA to Mitigate: 56.78 MVA
MW Contribution: 20.62 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232426 Y1-080 FULL 50/50 0.06 MW 0.06 MW
232427 Y1-080 E 50/50 0.56 MW 0.56 MW
927031 AC1-190 C Adder -7.39 MW -6.28 MW
924832 AB2-136 E 50/50 11.73 MW 11.73 MW
233946 AB2-136 C 50/50 1.81 MW 1.81 MW
233964 AF2-378 C Adder -0.54 MW -0.46 MW
960341 AF2-325 C Adder -1.7 MW -1.45 MW
960671 AF2-358 C 50/50 12.37 MW 12.37 MW
960672 AF2-358 E 50/50 8.25 MW 8.25 MW
965821 AG1-450 C 50/50 5.15 MW 5.15 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.02 MW 0.02 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.02 MW 0.02 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.0 MW 0.0 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.04 MW 0.04 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for VIENN_69-MARDELA 69.0 kV Ckt 1 line l/o DPL_P1_2_CKT 6705_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
VIENN_69-MARDELA 69.0 kV Ckt 1 line
232241 to 232838 ckt 1
Contingency Name:
DPL_P1_2_CKT 6705_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6705_SRT-A'
 DISCONNECT BUS 232239   /*SHARPTWN      69.0
 DISCONNECT BUS 232607   /*SHRPTWN1      12.5
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.25 %
Rating: 64.0 MVA
Rating Type: B
MVA to Mitigate: 72.48 MVA
MW Contribution: 21.57 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L
Facility Description:
VIENN_69-MARDELA 69.0 kV Ckt 1 line
232241 to 232838 ckt 1
Contingency Name:
DPL_P1_2_CKT 6705_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6705_SRT-A'
 DISCONNECT BUS 232239   /*SHARPTWN      69.0
 DISCONNECT BUS 232607   /*SHRPTWN1      12.5
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.21 %
Rating: 64.0 MVA
Rating Type: B
MVA to Mitigate: 72.46 MVA
MW Contribution: 21.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232417 X3-008 C 50/50 0.22 MW 0.22 MW
232418 X3-008 E 50/50 2.19 MW 2.19 MW
232426 Y1-080 FULL 50/50 0.04 MW 0.04 MW
232427 Y1-080 E 50/50 0.45 MW 0.45 MW
232919 VN10 50/50 0.51 MW 0.51 MW
927031 AC1-190 C 50/50 6.33 MW 6.33 MW
927032 AC1-190 E 50/50 2.71 MW 2.71 MW
924832 AB2-136 E 50/50 5.3 MW 5.3 MW
932161 AC2-023 C Adder -10.86 MW -9.23 MW
965321 AG1-397 C Adder -0.61 MW -0.52 MW
233946 AB2-136 C 50/50 0.82 MW 0.82 MW
233955 AB2-172 C OP 50/50 0.55 MW 0.55 MW
925152 AB2-172 E OP 50/50 5.47 MW 5.47 MW
233964 AF2-378 C 50/50 0.22 MW 0.22 MW
960872 AF2-378 E 50/50 0.3 MW 0.3 MW
960341 AF2-325 C 50/50 0.81 MW 0.81 MW
960342 AF2-325 E 50/50 1.12 MW 1.12 MW
960671 AF2-358 C 50/50 12.94 MW 12.94 MW
960672 AF2-358 E 50/50 8.63 MW 8.63 MW
965821 AG1-450 C 50/50 5.39 MW 5.39 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.0 MW 0.0 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.09 MW 0.09 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.04 MW 0.04 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.06 MW 0.06 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.0 MW 0.0 MW
WEC LTFEXP_WEC->PJM CLTF 0.0 MW 0.0 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.01 MW 0.01 MW
TVA LTFEXP_TVA->PJM CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.01 MW 0.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.01 MW 0.01 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.0 MW 0.0 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.0 MW 0.0 MW

Details for CLAY_230-LINWOOD84 230.0 kV Ckt 1 line l/o PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L/PECO
Facility Description:
CLAY_230-LINWOOD84 230.0 kV Ckt 1 line
231000 to 214235 ckt 1
Contingency Name:
PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A
CONTINGENCY 'PECO_P1-2_220-85
 TRIP BRANCH FROM BUS 214236 TO BUS 231001 CKT 1   /*LINWOOD85    230.0 - EDGEMR 5     230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 107.01 %
Rating: 799.0 MVA
Rating Type: B
MVA to Mitigate: 854.99 MVA
MW Contribution: 15.28 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L/PECO
Facility Description:
CLAY_230-LINWOOD84 230.0 kV Ckt 1 line
231000 to 214235 ckt 1
Contingency Name:
PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A
CONTINGENCY 'PECO_P1-2_220-85
 TRIP BRANCH FROM BUS 214236 TO BUS 231001 CKT 1   /*LINWOOD85    230.0 - EDGEMR 5     230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 106.63 %
Rating: 799.0 MVA
Rating Type: B
MVA to Mitigate: 851.94 MVA
MW Contribution: 15.29 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
231131 BLOOM ENRGY 50/50 0.73 MW 0.73 MW
231505 HR4 50/50 14.95 MW 14.95 MW
231900 EM5 50/50 35.41 MW 35.41 MW
231901 EM4 50/50 10.19 MW 10.19 MW
231908 HR1 50/50 7.32 MW 7.32 MW
231909 HR2 50/50 7.49 MW 7.49 MW
231910 HR3 50/50 7.32 MW 7.32 MW
231916 EM3 50/50 5.15 MW 5.15 MW
231917 EM10 50/50 0.72 MW 0.72 MW
231918 WEST 1 50/50 0.9 MW 0.9 MW
231919 CHRIST1 50/50 1.22 MW 1.22 MW
231920 CHRIST2 50/50 1.22 MW 1.22 MW
232405 W1-003 E Adder 1.85 MW 1.57 MW
232407 W1-004 E Adder 1.85 MW 1.57 MW
232409 W1-005 E Adder 1.85 MW 1.57 MW
232411 W1-006 E Adder 1.85 MW 1.57 MW
232412 X1-032 E Adder 0.6 MW 0.51 MW
232416 X2-083 50/50 0.11 MW 0.11 MW
232418 X3-008 E Adder 1.92 MW 1.63 MW
232427 Y1-080 E Adder 0.32 MW 0.27 MW
232429 Y3-058 E Adder 1.39 MW 1.19 MW
232851 DUP-SFR1 Adder 1.46 MW 1.24 MW
232904 IR4 Adder 59.85 MW 50.88 MW
918835 AA1-102 E Adder 13.9 MW 11.82 MW
926132 AC1-091 E Adder 1.6 MW 1.36 MW
926142 AC1-092 E Adder 1.6 MW 1.36 MW
926152 AC1-093 E Adder 1.52 MW 1.29 MW
926162 AC1-094 E Adder 1.28 MW 1.09 MW
927031 AC1-190 C Adder 5.4 MW 4.59 MW
927032 AC1-190 E Adder 2.32 MW 1.97 MW
943361 AF1-007 C Adder 0.28 MW 0.23 MW
943362 AF1-007 E Adder 0.78 MW 0.67 MW
943441 AF1-015 C Adder 1.02 MW 0.86 MW
943442 AF1-015 E Adder 1.4 MW 1.19 MW
943651 AF1-036 C Adder 1.38 MW 1.17 MW
943652 AF1-036 E Adder 1.9 MW 1.62 MW
959592 AF2-250 E Adder 0.13 MW 0.11 MW
960882 AF2-379 E Adder 0.34 MW 0.29 MW
233916 AB1-141 E Adder 1.04 MW 0.88 MW
233919 AB1-142 E Adder 1.04 MW 0.88 MW
923962 AB2-037 E Adder 20.47 MW 17.4 MW
924832 AB2-136 E Adder 4.04 MW 3.43 MW
930202 AB1-056 E Adder 26.65 MW 22.65 MW
932161 AC2-023 C Adder 3.99 MW 3.39 MW
932162 AC2-023 E Adder 2.9 MW 2.47 MW
941021 AE2-093 C Adder 2.69 MW 2.29 MW
941022 AE2-093 E Adder 4.4 MW 3.74 MW
941181 AE2-112 C Adder 1.06 MW 0.9 MW
941182 AE2-112 E Adder 1.73 MW 1.47 MW
964962 AG1-360 E Adder 1.31 MW 1.11 MW
965321 AG1-397 C Adder 0.62 MW 0.53 MW
965322 AG1-397 E Adder 0.86 MW 0.73 MW
925254 AB2-179 E Adder 2.16 MW 1.84 MW
933632 AC2-185 E Adder 3.22 MW 2.73 MW
232436 AB1-176 C Adder 0.56 MW 0.47 MW
923603 AB1-176 E Adder 0.92 MW 0.78 MW
923952 AB2-036 E Adder 9.32 MW 7.92 MW
917082 Z2-012 E Adder 1.85 MW 1.57 MW
924822 AB2-135 E Adder 5.44 MW 4.63 MW
232425 Y1-079 E Adder 1.01 MW 0.86 MW
232433 Z2-076 E Adder 0.29 MW 0.25 MW
232435 Z2-077 E Adder 0.29 MW 0.25 MW
936615 AD2-076_E Adder 4.99 MW 4.24 MW
233906 AB1-056 C Adder 9.36 MW 7.95 MW
233939 AC1-091 C Adder 0.97 MW 0.83 MW
233968 AD2-076_C Adder 3.06 MW 2.6 MW
233970 AC1-092 C Adder 0.97 MW 0.83 MW
233971 AC1-093 C Adder 0.92 MW 0.78 MW
233972 AC1-094 C Adder 0.78 MW 0.66 MW
233973 AC2-185 C Adder 1.97 MW 1.68 MW
233984 AB2-036 C Adder 5.69 MW 4.84 MW
233987 AB2-037 C Adder 12.53 MW 10.65 MW
923925 AB2-153 E Adder 2.05 MW 1.74 MW
923928 AB2-032 E Adder 1.06 MW 0.9 MW
924802 AB2-133 E Adder 5.13 MW 4.36 MW
925152 AB2-172 E OP Adder 4.79 MW 4.07 MW
933645 AC2-186 E Adder 0.89 MW 0.76 MW
933655 AC2-187 E Adder 1.78 MW 1.51 MW
933665 AC2-188 E Adder 1.78 MW 1.51 MW
232423 X3-066 E Adder 0.48 MW 0.41 MW
233964 AF2-378 C Adder 0.17 MW 0.14 MW
960872 AF2-378 E Adder 0.24 MW 0.2 MW
960341 AF2-325 C Adder 0.65 MW 0.55 MW
960342 AF2-325 E Adder 0.89 MW 0.76 MW
960671 AF2-358 C Adder 9.17 MW 7.79 MW
960672 AF2-358 E Adder 6.11 MW 5.19 MW
957661 AF2-060 C Adder 1.34 MW 1.14 MW
965821 AG1-450 C Adder 3.82 MW 3.25 MW
233985 AG1-318 E Adder 0.17 MW 0.15 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.63 MW 0.63 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.38 MW 0.38 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.07 MW 1.07 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 2.0 MW 2.0 MW
NY PJM->LTFIMP_NY CLTF 0.82 MW 0.82 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.03 MW 0.03 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.11 MW 0.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.1 MW 0.1 MW
MEC LTFEXP_MEC->PJM CLTF 0.07 MW 0.07 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.12 MW 0.12 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 13.26 MW 13.26 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for VIENN_69-SHARPTWN 69.0 kV Ckt 1 line l/o DPL_P1_2_CKT 6775_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
VIENN_69-SHARPTWN 69.0 kV Ckt 1 line
232241 to 232239 ckt 1
Contingency Name:
DPL_P1_2_CKT 6775_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6775_SRT-A'
 DISCONNECT BUS 232291   /*ROCKAWLKN     69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 106.4 %
Rating: 71.0 MVA
Rating Type: B
MVA to Mitigate: 75.55 MVA
MW Contribution: 19.64 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L
Facility Description:
VIENN_69-SHARPTWN 69.0 kV Ckt 1 line
232241 to 232239 ckt 1
Contingency Name:
DPL_P1_2_CKT 6775_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6775_SRT-A'
 DISCONNECT BUS 232291   /*ROCKAWLKN     69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 106.39 %
Rating: 71.0 MVA
Rating Type: B
MVA to Mitigate: 75.53 MVA
MW Contribution: 19.64 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232417 X3-008 C 50/50 0.2 MW 0.2 MW
232418 X3-008 E 50/50 2.0 MW 2.0 MW
232426 Y1-080 FULL 50/50 0.04 MW 0.04 MW
232427 Y1-080 E 50/50 0.41 MW 0.41 MW
232851 DUP-SFR1 Adder -1.19 MW -1.01 MW
232919 VN10 50/50 0.47 MW 0.47 MW
927031 AC1-190 C 50/50 5.77 MW 5.77 MW
927032 AC1-190 E 50/50 2.47 MW 2.47 MW
924832 AB2-136 E 50/50 4.82 MW 4.82 MW
932161 AC2-023 C 50/50 5.46 MW 5.46 MW
932162 AC2-023 E 50/50 3.97 MW 3.97 MW
233946 AB2-136 C 50/50 0.74 MW 0.74 MW
233955 AB2-172 C OP 50/50 0.5 MW 0.5 MW
925152 AB2-172 E OP 50/50 4.99 MW 4.99 MW
233964 AF2-378 C 50/50 0.2 MW 0.2 MW
960872 AF2-378 E 50/50 0.28 MW 0.28 MW
960341 AF2-325 C 50/50 0.74 MW 0.74 MW
960342 AF2-325 E 50/50 1.02 MW 1.02 MW
960671 AF2-358 C 50/50 11.78 MW 11.78 MW
960672 AF2-358 E 50/50 7.85 MW 7.85 MW
965821 AG1-450 C 50/50 4.91 MW 4.91 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.01 MW 0.01 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.0 MW 0.0 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.02 MW 0.02 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.0 MW 0.0 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for EDGEMR 5-CLAY_230 230.0 kV Ckt 1 line l/o PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
EDGEMR 5-CLAY_230 230.0 kV Ckt 1 line
231001 to 231000 ckt 1
Contingency Name:
PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A
CONTINGENCY 'PECO_P1-2_220-85
 TRIP BRANCH FROM BUS 214236 TO BUS 231001 CKT 1   /*LINWOOD85    230.0 - EDGEMR 5     230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.35 %
Rating: 808.0 MVA
Rating Type: B
MVA to Mitigate: 851.25 MVA
MW Contribution: 13.53 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L
Facility Description:
EDGEMR 5-CLAY_230 230.0 kV Ckt 1 line
231001 to 231000 ckt 1
Contingency Name:
PECO_P1-2_220-85/* $ DELCO $ 220-85 $ LC_SRT-A
CONTINGENCY 'PECO_P1-2_220-85
 TRIP BRANCH FROM BUS 214236 TO BUS 231001 CKT 1   /*LINWOOD85    230.0 - EDGEMR 5     230.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.02 %
Rating: 808.0 MVA
Rating Type: B
MVA to Mitigate: 848.58 MVA
MW Contribution: 13.53 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
231131 BLOOM ENRGY 50/50 0.6 MW 0.6 MW
231505 HR4 50/50 14.94 MW 14.94 MW
231900 EM5 50/50 35.39 MW 35.39 MW
231901 EM4 50/50 7.53 MW 7.53 MW
231908 HR1 50/50 5.41 MW 5.41 MW
231909 HR2 50/50 4.03 MW 4.03 MW
231910 HR3 50/50 5.41 MW 5.41 MW
231916 EM3 50/50 2.77 MW 2.77 MW
231917 EM10 50/50 0.39 MW 0.39 MW
231918 WEST 1 50/50 0.57 MW 0.57 MW
231919 CHRIST1 50/50 0.91 MW 0.91 MW
231920 CHRIST2 50/50 0.91 MW 0.91 MW
232405 W1-003 E Adder 1.64 MW 1.39 MW
232407 W1-004 E Adder 1.64 MW 1.39 MW
232409 W1-005 E Adder 1.64 MW 1.39 MW
232411 W1-006 E Adder 1.64 MW 1.39 MW
232412 X1-032 E Adder 0.53 MW 0.45 MW
232416 X2-083 50/50 0.09 MW 0.09 MW
232418 X3-008 E Adder 1.7 MW 1.44 MW
232427 Y1-080 E Adder 0.28 MW 0.24 MW
232429 Y3-058 E Adder 1.24 MW 1.05 MW
232851 DUP-SFR1 Adder 1.29 MW 1.1 MW
232904 IR4 Adder 53.02 MW 45.06 MW
918835 AA1-102 E Adder 12.32 MW 10.47 MW
926132 AC1-091 E Adder 1.41 MW 1.2 MW
926142 AC1-092 E Adder 1.41 MW 1.2 MW
926152 AC1-093 E Adder 1.34 MW 1.14 MW
926162 AC1-094 E Adder 1.13 MW 0.96 MW
927031 AC1-190 C Adder 4.78 MW 4.06 MW
927032 AC1-190 E Adder 2.05 MW 1.74 MW
943361 AF1-007 C Adder 0.24 MW 0.21 MW
943362 AF1-007 E Adder 0.7 MW 0.59 MW
943441 AF1-015 C Adder 0.9 MW 0.76 MW
943442 AF1-015 E Adder 1.24 MW 1.05 MW
943651 AF1-036 C Adder 1.2 MW 1.02 MW
943652 AF1-036 E Adder 1.66 MW 1.41 MW
959592 AF2-250 E Adder 0.11 MW 0.1 MW
960882 AF2-379 E Adder 0.3 MW 0.26 MW
233916 AB1-141 E Adder 0.9 MW 0.77 MW
233919 AB1-142 E Adder 0.9 MW 0.77 MW
923962 AB2-037 E Adder 18.23 MW 15.5 MW
924832 AB2-136 E Adder 3.57 MW 3.04 MW
930202 AB1-056 E Adder 23.61 MW 20.07 MW
932161 AC2-023 C Adder 3.53 MW 3.0 MW
932162 AC2-023 E Adder 2.57 MW 2.19 MW
941021 AE2-093 C Adder 2.38 MW 2.02 MW
941022 AE2-093 E Adder 3.88 MW 3.3 MW
941181 AE2-112 C Adder 0.92 MW 0.79 MW
941182 AE2-112 E Adder 1.51 MW 1.28 MW
964962 AG1-360 E Adder 1.16 MW 0.98 MW
965321 AG1-397 C Adder 0.55 MW 0.47 MW
965322 AG1-397 E Adder 0.76 MW 0.65 MW
925254 AB2-179 E Adder 1.82 MW 1.55 MW
933632 AC2-185 E Adder 2.84 MW 2.41 MW
232436 AB1-176 C Adder 0.48 MW 0.41 MW
923603 AB1-176 E Adder 0.8 MW 0.68 MW
923952 AB2-036 E Adder 8.17 MW 6.94 MW
917082 Z2-012 E Adder 1.64 MW 1.39 MW
924822 AB2-135 E Adder 4.72 MW 4.01 MW
232425 Y1-079 E Adder 0.88 MW 0.75 MW
232433 Z2-076 E Adder 0.26 MW 0.22 MW
232435 Z2-077 E Adder 0.26 MW 0.22 MW
936615 AD2-076_E Adder 4.34 MW 3.69 MW
233906 AB1-056 C Adder 8.29 MW 7.05 MW
233939 AC1-091 C Adder 0.86 MW 0.73 MW
233968 AD2-076_C Adder 2.66 MW 2.26 MW
233970 AC1-092 C Adder 0.86 MW 0.73 MW
233971 AC1-093 C Adder 0.81 MW 0.69 MW
233972 AC1-094 C Adder 0.69 MW 0.58 MW
233973 AC2-185 C Adder 1.74 MW 1.48 MW
233984 AB2-036 C Adder 4.99 MW 4.24 MW
233987 AB2-037 C Adder 11.16 MW 9.49 MW
923925 AB2-153 E Adder 1.78 MW 1.51 MW
923928 AB2-032 E Adder 0.92 MW 0.78 MW
924802 AB2-133 E Adder 4.43 MW 3.77 MW
925152 AB2-172 E OP Adder 4.24 MW 3.6 MW
933645 AC2-186 E Adder 0.79 MW 0.67 MW
933655 AC2-187 E Adder 1.57 MW 1.34 MW
933665 AC2-188 E Adder 1.57 MW 1.34 MW
232423 X3-066 E Adder 0.42 MW 0.35 MW
233964 AF2-378 C Adder 0.15 MW 0.13 MW
960872 AF2-378 E Adder 0.21 MW 0.18 MW
960341 AF2-325 C Adder 0.57 MW 0.49 MW
960342 AF2-325 E Adder 0.79 MW 0.67 MW
960671 AF2-358 C Adder 8.12 MW 6.9 MW
960672 AF2-358 E Adder 5.41 MW 4.6 MW
957661 AF2-060 C Adder 1.19 MW 1.01 MW
965821 AG1-450 C Adder 3.38 MW 2.87 MW
233985 AG1-318 E Adder 0.15 MW 0.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.76 MW 0.76 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.41 MW 0.41 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.07 MW 1.07 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.75 MW 1.75 MW
NY PJM->LTFIMP_NY CLTF 0.72 MW 0.72 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.03 MW 0.03 MW
WEC LTFEXP_WEC->PJM CLTF 0.02 MW 0.02 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.11 MW 0.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.1 MW 0.1 MW
MEC LTFEXP_MEC->PJM CLTF 0.09 MW 0.09 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.12 MW 0.12 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 11.64 MW 11.64 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for MARDELA-HEBRON 69.0 kV Ckt 1 line l/o DPL_P1_2_CKT 6705_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
MARDELA-HEBRON 69.0 kV Ckt 1 line
232838 to 232270 ckt 1
Contingency Name:
DPL_P1_2_CKT 6705_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6705_SRT-A'
 DISCONNECT BUS 232239   /*SHARPTWN      69.0
 DISCONNECT BUS 232607   /*SHRPTWN1      12.5
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.5 %
Rating: 64.0 MVA
Rating Type: B
MVA to Mitigate: 66.88 MVA
MW Contribution: 21.57 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: DP&L
Facility Description:
MARDELA-HEBRON 69.0 kV Ckt 1 line
232838 to 232270 ckt 1
Contingency Name:
DPL_P1_2_CKT 6705_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6705_SRT-A'
 DISCONNECT BUS 232239   /*SHARPTWN      69.0
 DISCONNECT BUS 232607   /*SHRPTWN1      12.5
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.46 %
Rating: 64.0 MVA
Rating Type: B
MVA to Mitigate: 66.86 MVA
MW Contribution: 21.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232417 X3-008 C 50/50 0.22 MW 0.22 MW
232418 X3-008 E 50/50 2.19 MW 2.19 MW
232426 Y1-080 FULL 50/50 0.04 MW 0.04 MW
232427 Y1-080 E 50/50 0.45 MW 0.45 MW
232919 VN10 50/50 0.51 MW 0.51 MW
927031 AC1-190 C 50/50 6.33 MW 6.33 MW
927032 AC1-190 E 50/50 2.71 MW 2.71 MW
924832 AB2-136 E 50/50 5.3 MW 5.3 MW
932161 AC2-023 C Adder -10.86 MW -9.23 MW
965321 AG1-397 C Adder -0.61 MW -0.52 MW
233946 AB2-136 C 50/50 0.82 MW 0.82 MW
233955 AB2-172 C OP 50/50 0.55 MW 0.55 MW
925152 AB2-172 E OP 50/50 5.47 MW 5.47 MW
233964 AF2-378 C 50/50 0.22 MW 0.22 MW
960872 AF2-378 E 50/50 0.3 MW 0.3 MW
960341 AF2-325 C 50/50 0.81 MW 0.81 MW
960342 AF2-325 E 50/50 1.12 MW 1.12 MW
960671 AF2-358 C 50/50 12.94 MW 12.94 MW
960672 AF2-358 E 50/50 8.63 MW 8.63 MW
965821 AG1-450 C 50/50 5.39 MW 5.39 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.0 MW 0.0 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.09 MW 0.09 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.04 MW 0.04 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.06 MW 0.06 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.0 MW 0.0 MW
WEC LTFEXP_WEC->PJM CLTF 0.0 MW 0.0 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.01 MW 0.01 MW
TVA LTFEXP_TVA->PJM CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.01 MW 0.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.01 MW 0.01 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.0 MW 0.0 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.0 MW 0.0 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.0 MW 0.0 MW

Details for BAYLY-CAMBRIDG 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
BAYLY-CAMBRIDG 69.0 kV Ckt 1 line
232292 to 232237 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.34 %
Rating: 50.0 MVA
Rating Type: A
MVA to Mitigate: 51.67 MVA
MW Contribution: 20.62 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DP&L
Facility Description:
BAYLY-CAMBRIDG 69.0 kV Ckt 1 line
232292 to 232237 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.34 %
Rating: 50.0 MVA
Rating Type: A
MVA to Mitigate: 51.67 MVA
MW Contribution: 20.62 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232426 Y1-080 FULL 50/50 0.06 MW 0.06 MW
232427 Y1-080 E 50/50 0.56 MW 0.56 MW
927031 AC1-190 C Adder -7.39 MW -6.28 MW
924832 AB2-136 E 50/50 11.73 MW 11.73 MW
233946 AB2-136 C 50/50 1.81 MW 1.81 MW
233964 AF2-378 C Adder -0.54 MW -0.46 MW
960341 AF2-325 C Adder -1.7 MW -1.45 MW
960671 AF2-358 C 50/50 12.37 MW 12.37 MW
960672 AF2-358 E 50/50 8.25 MW 8.25 MW
965821 AG1-450 C 50/50 5.15 MW 5.15 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.02 MW 0.02 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.02 MW 0.02 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.0 MW 0.0 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.04 MW 0.04 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for AF2-358 TP-VIENNALC 69.0 kV Ckt 1 line l/o DPL_P1_2_CKT 6715_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
AF2-358 TP-VIENNALC 69.0 kV Ckt 1 line
960670 to 232242 ckt 1
Contingency Name:
DPL_P1_2_CKT 6715_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6715_SRT-A'
 DISCONNECT BUS 232817   /*ENMKTREA      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.41 %
Rating: 174.0 MVA
Rating Type: B
MVA to Mitigate: 178.19 MVA
MW Contribution: 99.99 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DP&L
Facility Description:
AF2-358 TP-VIENNALC 69.0 kV Ckt 1 line
960670 to 232242 ckt 1
Contingency Name:
DPL_P1_2_CKT 6715_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6715_SRT-A'
 DISCONNECT BUS 232817   /*ENMKTREA      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.41 %
Rating: 174.0 MVA
Rating Type: B
MVA to Mitigate: 178.2 MVA
MW Contribution: 99.99 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232426 Y1-080 FULL 50/50 0.21 MW 0.21 MW
232427 Y1-080 E 50/50 2.1 MW 2.1 MW
927031 AC1-190 C 50/50 34.99 MW 34.99 MW
927032 AC1-190 E 50/50 15.0 MW 15.0 MW
924832 AB2-136 E 50/50 26.3 MW 26.3 MW
233946 AB2-136 C 50/50 4.05 MW 4.05 MW
233964 AF2-378 C 50/50 1.11 MW 1.11 MW
960872 AF2-378 E 50/50 1.54 MW 1.54 MW
960341 AF2-325 C 50/50 4.2 MW 4.2 MW
960342 AF2-325 E 50/50 5.8 MW 5.8 MW
960671 AF2-358 C 50/50 59.99 MW 59.99 MW
960672 AF2-358 E 50/50 39.99 MW 39.99 MW
965821 AG1-450 C 50/50 25.0 MW 25.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.03 MW 0.03 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.04 MW 0.04 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.02 MW 0.02 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

Details for VIENNALC-VIENN_69 69.0 kV Ckt 1 line l/o DPL_P1_2_CKT 6715_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: DP&L
Facility Description:
VIENNALC-VIENN_69 69.0 kV Ckt 1 line
232242 to 232241 ckt 1
Contingency Name:
DPL_P1_2_CKT 6715_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6715_SRT-A'
 DISCONNECT BUS 232817   /*ENMKTREA      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.36 %
Rating: 174.0 MVA
Rating Type: B
MVA to Mitigate: 178.1 MVA
MW Contribution: 99.99 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: DP&L
Facility Description:
VIENNALC-VIENN_69 69.0 kV Ckt 1 line
232242 to 232241 ckt 1
Contingency Name:
DPL_P1_2_CKT 6715_SRT-A
CONTINGENCY 'DPL_P1_2_CKT 6715_SRT-A'
 DISCONNECT BUS 232817   /*ENMKTREA      69.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 102.36 %
Rating: 174.0 MVA
Rating Type: B
MVA to Mitigate: 178.1 MVA
MW Contribution: 99.99 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
232426 Y1-080 FULL 50/50 0.21 MW 0.21 MW
232427 Y1-080 E 50/50 2.1 MW 2.1 MW
927031 AC1-190 C 50/50 34.99 MW 34.99 MW
927032 AC1-190 E 50/50 15.0 MW 15.0 MW
924832 AB2-136 E 50/50 26.3 MW 26.3 MW
233946 AB2-136 C 50/50 4.05 MW 4.05 MW
233964 AF2-378 C 50/50 1.11 MW 1.11 MW
960872 AF2-378 E 50/50 1.54 MW 1.54 MW
960341 AF2-325 C 50/50 4.2 MW 4.2 MW
960342 AF2-325 E 50/50 5.8 MW 5.8 MW
960671 AF2-358 C 50/50 59.99 MW 59.99 MW
960672 AF2-358 E 50/50 39.99 MW 39.99 MW
965821 AG1-450 C 50/50 25.0 MW 25.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.03 MW 0.03 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.04 MW 0.04 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.02 MW 0.02 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
MDU PJM->LTFIMP_MDU CLTF 0.0 MW 0.0 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.01 MW 0.01 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request was evaluated as a 100.0 MW injection in the DPL area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Light Load Potential Congestion due to Local Energy Deliverability

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - Issues Found

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 75 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 75 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 75 projects will meet the dynamics requirements of the NERC, Exelon/DPL, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 75 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.02 pu voltage at the POI buses.

Cluster 75 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 41 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No relevant multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 75 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For 36 out of 41 fault contingencies tested on the 2027 peak load case:

  1. Cluster 75 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 75 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-358 and AG1-450 meet the 0.95 leading and lagging PF requirement.

For P1.09, P4.11, P4.12, P4.13, and P5.02, when faults are close to Vienna 69 kV while losing circuit 6709 from Vienna to AF2-358 POI, the results show undamped oscillations indicating system instability. The CSCR assessment shows under these fault contingencies, the CSCR values would be below 1.15 which could be considered very weak grid conditions. System reinforcement would be needed. Also, the generic model might be not accurate at very low SC levels, so detailed models performed under EMT simulation would be required. Thus, mitigations were found to be required for TC1 Cluster 75. PSCAD/EMT analysis will also be performed.

 

Table 1: TC1 Cluster 75 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

75

AF2-358

Solar

DPL

100

100

60

Airey-Vienna 69 kV

AG1-450

Storage

DPL

125

25

25

Airey-Vienna 69 kV

 

 

PSCAD Analysis Executive Summary:

Introduction

This Weak Grid Assessment evaluates two projects from PJM Transition Cycle 1 (TC1) Cluster 75 for risk of voltage instability due to weak grid conditions in an EMT simulation environment. The two projects, AF2-358 and AG1-450, were identified in the Cluster Study [1] as having risk of undamped oscillations during a contingency condition and indicating system instability after dynamic simulation analysis in PSS/E. System reinforcement as a potential mitigation was recommended along with evaluation using detailed models in an EMT simulation.

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability and the impact of mitigations such as system reinforcement as concluded in the Cluster Study. A summary description of each project is listed below:

Table 1. Summary Description of TC1 Cluster 75 Projects

 

 

 

 

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AF2-358 Choptank Solar

PV

100

Airey-Vienna 69 kV

960670

AG1-450 Choptank BESS

BESS

125

Airey-Vienna 69 kV

960670

 

Conclusion:

First, the individual project PSCAD models were evaluated for data consistency and model performance

as part of the standard Model Quality Test in [2], with model updates being made where needed. INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual project models were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model.

 

A representative contingency case from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, was then simulated in the PSCAD detailed system model. For Cluster 75, the following contingency case was chosen.

  • Fault ID P1.03: 3LG Fault at AF2-358 POI 69 kV on Vienna circuit (6709) resulting in loss of AF2-358 POI - Vienna circuit (6709). Projects are operating at rated power pre-fault. [1]

Simulation results in PSCAD are summarized below. It can be observed that the base case with the PSCAD detailed system model results in weak grid oscillations similar to the Cluster Study and the projects are unable to recover to pre-fault conditions after the fault clears.

Table 2. Summary of cases tested in PSCAD system study

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 1.0

P1.03, Consider as the base case

Unstable

Unstable

Case 1.1a

P1.03, modified PPC tuning, P=1.0pu, Unity PF

-

Stable

Case 1.1b

P1.03, modified PPC tuning, P=1.0pu, Lag PF

-

Stable

Case 1.1c

P1.03, modified PPC tuning, P=1.0pu, Lead PF

-

Stable*

Case 1.2a

P1.03, modified PPC tuning, P=0.75pu, Unity PF

-

Stable

Case 1.2b

P1.03, modified PPC tuning, P=0.75pu, Lag PF

-

Stable

Case 1.2c

P1.03, modified PPC tuning, P=0.75pu, Lead PF

-

Stable

Case 1.3a

P1.03, modified PPC tuning, P=0.5pu, Unity PF

-

Stable

Case 1.3b

P1.03, modified PPC tuning, P=0.5pu, Lag PF

-

Stable

Case 1.3c

P1.03, modified PPC tuning, P=0.5pu, Lead PF

-

Stable

* Only able to recover to pre-fault conditions with additional 1.5MVAr cap bank, either on 69kV POI or 34.5kV side

 

PPC parameters were tuned to be more appropriate for weak grid conditions using a generic PPC model, and this configuration was evaluated in base case P1.03, resulting in stable recovery. Nine sensitivity cases were then tested to verify robustness of the modified tuning, with all showing stable recovery except for Case 1.1c. For Case 1.1c, it was observed that although oscillations were not present, low system voltage related to the new steady-state operating point prevented full recovery to pre-fault conditions. As a result, adding a small capacitor bank of 1.5 MVAr was evaluated. It was observed that the additional reactive power support from the capacitor bank was sufficient to increase the system voltage and allow the plant to recover stably.

 

Based on the simulation results described above, it is recommended that the PPC for the Cluster 75 projects is tuned for a similar response as the modified generic PPC model tuning in this study. The full set of parameter values is listed in [2]. In addition, a small capacitor bank rated at least 1.5 MVAr and connected at either 69kV POI or on the 34.5kV side can be considered to provide additional reactive power support under contingency conditions such as P1.03.

 

Reactive Power Analysis

The reactive power capability of AF2-358 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis complete, no voltage issues identified.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA1-102 Kings Creek-Loretto 138kV Partially in Service - Under Construction
AB1-056 Indian River 230kV I Suspended
AB1-141 Church-Wye Mills 138 kV I In Service
AB1-142 Church-Wye Mills 138 kV II In Service
AB1-176 Price 25kV II Engineering & Procurement
AB2-032 Church-Wye Mills 138 kV In Service
AB2-036 Church - Oil City 138kV Suspended
AB2-037 Keeney-Steele 230kV Under Construction
AB2-133 Chestertown 69kV Under Construction
AB2-135 Church-Kent 69kV In Service
AB2-136 Cambridge-West Cambridge 69kV Under Construction
AB2-153 Church-Wye Mills 138 kV In Service
AB2-172 Todd 69kV In Service
AB2-179 Townsend 138kV In Service
AC1-091 Cedar Creek 138kV I Engineering & Procurement
AC1-092 Cedar Creek 138kV II Engineering & Procurement
AC1-093 Cedar Creek 138kV III Engineering & Procurement
AC1-094 Cedar Creek 138kV IV Engineering & Procurement
AC1-190 East New Market 69kV Suspended
AC2-023 Hebron 69kV Engineering & Procurement
AC2-185 Cedar Creek 138kV II Engineering & Procurement
AC2-186 Harrington 25kV Under Construction
AC2-187 Harrington 69kV Under Construction
AC2-188 Harrington 69 kV Under Construction
AD2-076 Carville 138 kV Suspended
AE2-093 Easton-Steele 138 kV Withdrawn
AE2-112 Carville 138 kV II Suspended
AF1-007 Indian River 230 kV I Suspended
AF1-015 Easton-Steele 138 kV II Withdrawn
AF1-036 Carville 138 kV III Suspended
AF2-060 Wattsville 12 kV Engineering & Procurement
AF2-250 Edgewood 12 kV III In Service
AF2-325 Jacktown 12 kV Engineering & Procurement
AF2-378 Cambridge 12 kV Engineering & Procurement
AF2-379 Princess Anne 25 kV Under Construction
AG1-318 Ocean Bay 12 kV Withdrawn
AG1-360 Costen 25 kV In Service
AG1-397 Walston 12 kV Withdrawn
AG1-450 Airey-Vienna 69 kV II Active
W1-003 Oak Hall In Service
W1-004 Oak Hall In Service
W1-005 Oak Hall In Service
W1-006 Oak Hall In Service
X1-032 Costen 25kV In Service
X2-083 Newark 12kV In Service
X3-008 Todd 69kV In Service
X3-066 Church Hill 69kV In Service
Y1-079 Wye Mills 69kV In Service
Y1-080 Dorchester 12kV In Service
Y3-058 Rockawalkin 69kV In Service
Z2-012 Weirwood-Eastville 69kV In Service
Z2-076 Worcester South 25kV In Service
Z2-077 Worcester North 25kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF2-358 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
DPL n6925 Rebuild Edge Moor (DPL) - Linwood (PECO) 230 kV line. Cost Allocated $57,344,000
DPL n9645.0 Install 10 MVAR Cap Bank at new AF2-358 69kV Interconnection Swyd Cost Allocated $1,102,116
PECO n9371.0 Install OPGW on PECO portion of EDGEMR 5 230.0 kV to LINWOOD85 230.0 kV ckt 1 Cost Allocated $185,731
Grand Total: $58,631,847

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n9645.0
Type
Stability
TO
DPL
RTEP ID / TO ID
n9645.0 / (Pending)
Title
Install 10 MVAR Cap Bank at new AF2-358 69kV Interconnection Swyd
Description
Installation of the 1.5 MVAR capacitor bank can either be on the 69 kV network or 34.5 kV network around the AF2-358 POI. DPL will install 10MVAR, as this is the smallest size they install on their system.
Total Cost ($USD)
$2,479,762
Discounted Total Cost ($USD)
$2,479,762
Allocated Cost ($USD)
$1,102,116
Time Estimate
Jun 01 2027

Contributor

Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-358 100.0 MW 44.4% $1,102,116
AG1-450 125.0 MW 55.6% $1,377,646

System Reinforcement: n6925
Type
Load Flow
TO
DPL
RTEP ID / TO ID
n6925 / dt22085r0001
Title
Rebuild Edge Moor (DPL) - Linwood (PECO) 230 kV line.
Description
Rebuilt DPL portion (8.1 mi.) of EDGEMR 5 230.0 kV to LINWOOD85 230.0 kV ckt 1 and install OPGW. o DPL SUM Rate A/B/C: 712/885/1106 MVA o DPL WIN Rate A/B/C: 822/978/1217 MVA
Total Cost ($USD)
$71,680,000
Discounted Total Cost ($USD)
$71,680,000
Allocated Cost ($USD)
$57,344,000
Time Estimate
36 to 48 Months

Contributor

Facility Contingency
LINWOOD85-EDGEMR 5 230.0 kV Ckt 1 line (Any)
LINWOOD-EDGEMR 5 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-358 Airey-Vienna 69kV - DPL: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-358, AG1-450
12.2 MW 80.0% $57,344,000
AG1-450 Airey-Vienna 69kV - DPL: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-358, AG1-450
3.1 MW 20.0% $14,336,000

System Reinforcement: n9371.0
Type
Load Flow
TO
PECO
RTEP ID / TO ID
n9371.0 / PECO 220-85
Title
Install OPGW on PECO portion of EDGEMR 5 230.0 kV to LINWOOD85 230.0 kV ckt 1
Description
Install OPGW on PECO portion of EDGEMR 5 230.0 kV to LINWOOD85 230.0 kV ckt 1
Total Cost ($USD)
$232,164
Discounted Total Cost ($USD)
$232,164
Allocated Cost ($USD)
$185,731
Time Estimate
36 to 60 Months

Contributor

Facility Contingency
LINWOOD85-EDGEMR 5 230.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-358 Airey-Vienna 69kV - DPL: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-358, AG1-450
12.2 MW 80.0% $185,731
AG1-450 Airey-Vienna 69kV - DPL: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-358, AG1-450
3.1 MW 20.0% $46,433

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-358


AF2-358 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF2-358 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AF2-358 One Line Diagram

AF2-358 One Line Diagram.png

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.