AF2-376 Phase III Study Report

v1.00 released 2025-09-18 17:12

Timber Switch 138 kV

20.0 MW Capacity / 50.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Paulding Wind Farm II LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Ohio Power Company.

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $60,764 $0 = AND ( $60,764 - $0 ) 50.0 = $1,215 per MW

General

The Project Developer has proposed a Storage facility located in the American Electric Power zone — Paulding County, Ohio. The installed facilities will have a total capability of 149.0 MW with 20.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AF2-376
Project Name:
Timber Switch 138 kV
Project Developer Name:
Paulding Wind Farm II LLC
State:
Ohio
County:
Paulding
Transmission Owner:
Ohio Power Company
MFO:
149.0
MWE:
50.0
MWC:
20.0
Battery Storage Specification:
200.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AF2-376 will interconnect on the AEP Ohio Power Company transmission system at the Timber Switch 138 kV substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AF2-376 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AF2-376 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $193,802 $193,802
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $60,764 $60,764
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $0 $0
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $254,566 $254,566

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF2-376

Security has been calculated for the AF2-376 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF2-376
Project(s): AF2-376
Final Agreement Security (A): $254,566
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $254,566
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

AF2-376 will interconnect on the AEP transmission system at the Timber Switch 138 kV substation. The estimates provided in the report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9393.0

Timber Switch 138 kV: Review and revise the protective relay settings to account for the additional generation of AF2-376.

(Pending Facilities Study) $60,764 $60,764
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Install one (1) metering plate and one (1) ethernet switch in the AF2-376 Project Developer's collector station. Install one (1) connected grid router (CGR) in the Project Developer's originating project (Timber Road II) collector station.

(Pending Facilities Study) $193,802 $193,802

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 3 to 6 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 50.0 MW (20.0 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DAY 05ROLLER CRK-09ROCKFO 69.0 kV Ckt 1 line
290143 to 253202 ckt 1
AEP_P7-1_#11069___SRT-A
CONTINGENCY 'AEP_P7-1_#11069___SRT-A'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1   /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 243108 CKT 1   /*05E SIDE     138.0 - 05STERLING   138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 290024 CKT 1   /*05E SIDE     138.0 - 05GOMER      138.0
 OPEN BRANCH FROM BUS 243051 TO BUS 290024 CKT 1   /*05NDELPH     138.0 - 05GOMER      138.0
END
Tower AC 119.92 % 53.0 B 63.56 2.58
AEP 05TILLMA-05ALLEN 138.0 kV Ckt 1 line
243383 to 243242 ckt 1
AEP_P7-1_#11069___SRT-A
CONTINGENCY 'AEP_P7-1_#11069___SRT-A'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1   /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 243108 CKT 1   /*05E SIDE     138.0 - 05STERLING   138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 290024 CKT 1   /*05E SIDE     138.0 - 05GOMER      138.0
 OPEN BRANCH FROM BUS 243051 TO BUS 290024 CKT 1   /*05NDELPH     138.0 - 05GOMER      138.0
END
Tower AC 101.96 % 341.0 B 347.68 39.53
AEP 05TILLMA-05ALLEN 138.0 kV Ckt 1 line
243383 to 243242 ckt 1
AEP_P7-1_#16440_SRT-SL
CONTINGENCY 'AEP_P7-1_#16440_SRT-SL'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1                /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242989 TO BUS 243066 CKT 1                /*05E LIMA     138.0 - 05NW LIM     138.0
 OPEN BRANCH FROM BUS 243066 TO BUS 243157 CKT 1                /*05NW LIM     138.0 - 05WOODLA     138.0
 OPEN BRANCH FROM BUS 243136 TO BUS 243157 CKT 1                /*05W LIMA     138.0 - 05WOODLA     138.0
 SET POSTCONTRATING 368 BRANCH FROM BUS 242935 TO BUS 242989 CKT 2 /*05E LIMA     345.0 - 05E LIMA     138.0
 SET PRECONTRATING 285 BRANCH FROM BUS 242935 TO BUS 242989 CKT 2 /*05E LIMA     345.0 - 05E LIMA     138.0
END
Tower AC 100.66 % 341.0 B 343.25 39.38

Details for 05ROLLER CRK-09ROCKFO 69.0 kV Ckt 1 line l/o AEP_P7-1_#11069___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DAY
Facility Description:
05ROLLER CRK-09ROCKFO 69.0 kV Ckt 1 line
290143 to 253202 ckt 1
Contingency Name:
AEP_P7-1_#11069___SRT-A
CONTINGENCY 'AEP_P7-1_#11069___SRT-A'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1   /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 243108 CKT 1   /*05E SIDE     138.0 - 05STERLING   138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 290024 CKT 1   /*05E SIDE     138.0 - 05GOMER      138.0
 OPEN BRANCH FROM BUS 243051 TO BUS 290024 CKT 1   /*05NDELPH     138.0 - 05GOMER      138.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 119.92 %
Rating: 53.0 MVA
Rating Type: B
MVA to Mitigate: 63.56 MVA
MW Contribution: 2.58 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/DAY
Facility Description:
05ROLLER CRK-09ROCKFO 69.0 kV Ckt 1 line
290143 to 253202 ckt 1
Contingency Name:
AEP_P7-1_#11069___SRT-A
CONTINGENCY 'AEP_P7-1_#11069___SRT-A'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1   /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 243108 CKT 1   /*05E SIDE     138.0 - 05STERLING   138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 290024 CKT 1   /*05E SIDE     138.0 - 05GOMER      138.0
 OPEN BRANCH FROM BUS 243051 TO BUS 290024 CKT 1   /*05NDELPH     138.0 - 05GOMER      138.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 120.28 %
Rating: 53.0 MVA
Rating Type: B
MVA to Mitigate: 63.75 MVA
MW Contribution: 2.58 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247911 05TIMB G E Adder 3.93 MW 3.34 MW
942801 AE2-298 C 50/50 5.58 MW 5.58 MW
942802 AE2-298 E 50/50 3.73 MW 3.73 MW
960851 AF2-376 C Adder 1.03 MW 0.88 MW
960852 AF2-376 E Adder 1.55 MW 1.32 MW
940031 AE1-245 C Adder 1.52 MW 1.29 MW
940032 AE1-245 E Adder 10.17 MW 8.64 MW
958092 AF2-103 E Adder 0.14 MW 0.12 MW
247959 V1-011 E Adder 6.78 MW 5.76 MW
934906 AD1-119 E Adder 2.56 MW 2.18 MW
926812 AC1-167 E Adder 0.85 MW 0.73 MW
943182 AE2-322 E Adder 1.03 MW 0.88 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.29 MW 2.29 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.16 MW 0.16 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.03 MW 0.03 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.04 MW 0.04 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.02 MW 0.02 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.03 MW 0.03 MW
MEC LTFEXP_MEC->PJM CLTF 0.15 MW 0.15 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.08 MW 0.08 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.02 MW 0.02 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.19 MW 0.19 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.02 MW 0.02 MW

Details for 05TILLMA-05ALLEN 138.0 kV Ckt 1 line l/o AEP_P7-1_#11069___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05TILLMA-05ALLEN 138.0 kV Ckt 1 line
243383 to 243242 ckt 1
Contingency Name:
AEP_P7-1_#11069___SRT-A
CONTINGENCY 'AEP_P7-1_#11069___SRT-A'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1   /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 243108 CKT 1   /*05E SIDE     138.0 - 05STERLING   138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 290024 CKT 1   /*05E SIDE     138.0 - 05GOMER      138.0
 OPEN BRANCH FROM BUS 243051 TO BUS 290024 CKT 1   /*05NDELPH     138.0 - 05GOMER      138.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 101.96 %
Rating: 341.0 MVA
Rating Type: B
MVA to Mitigate: 347.68 MVA
MW Contribution: 39.53 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05TILLMA-05ALLEN 138.0 kV Ckt 1 line
243383 to 243242 ckt 1
Contingency Name:
AEP_P7-1_#11069___SRT-A
CONTINGENCY 'AEP_P7-1_#11069___SRT-A'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1   /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 243108 CKT 1   /*05E SIDE     138.0 - 05STERLING   138.0
 OPEN BRANCH FROM BUS 242991 TO BUS 290024 CKT 1   /*05E SIDE     138.0 - 05GOMER      138.0
 OPEN BRANCH FROM BUS 243051 TO BUS 290024 CKT 1   /*05NDELPH     138.0 - 05GOMER      138.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 101.69 %
Rating: 341.0 MVA
Rating Type: B
MVA to Mitigate: 346.75 MVA
MW Contribution: 39.53 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243017 05HAVILAND1 50/50 0.49 MW 0.49 MW
965041 AG1-368 C 50/50 52.32 MW 52.32 MW
965042 AG1-368 E 50/50 34.88 MW 34.88 MW
246953 05TIMB G C 50/50 2.96 MW 2.96 MW
247911 05TIMB G E 50/50 60.17 MW 60.17 MW
942801 AE2-298 C 50/50 13.83 MW 13.83 MW
942802 AE2-298 E 50/50 9.25 MW 9.25 MW
960851 AF2-376 C 50/50 15.81 MW 15.81 MW
960852 AF2-376 E 50/50 23.72 MW 23.72 MW
940031 AE1-245 C 50/50 13.12 MW 13.12 MW
940032 AE1-245 E 50/50 87.81 MW 87.81 MW
958091 AF2-103 C 50/50 0.14 MW 0.14 MW
958092 AF2-103 E 50/50 1.23 MW 1.23 MW
247607 V1-011 GEN 50/50 1.43 MW 1.43 MW
270258 AD1-119 C 50/50 0.97 MW 0.97 MW
270297 AD1-101 C 50/50 0.38 MW 0.38 MW
247959 V1-011 E 50/50 58.55 MW 58.55 MW
934742 AD1-101 E 50/50 3.79 MW 3.79 MW
934906 AD1-119 E 50/50 9.69 MW 9.69 MW
926811 AC1-167 C 50/50 1.16 MW 1.16 MW
926812 AC1-167 E 50/50 3.65 MW 3.65 MW
943181 AE2-322 C 50/50 1.37 MW 1.37 MW
943182 AE2-322 E 50/50 4.42 MW 4.42 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.03 MW 0.03 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.05 MW 0.05 MW
VTF LTFEXP_VFT->PJM CMTX 0.14 MW 0.14 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.25 MW 0.25 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.02 MW 0.02 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.44 MW 0.44 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.05 MW 0.05 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.16 MW 0.16 MW
MDU PJM->LTFIMP_MDU CLTF 0.02 MW 0.02 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.19 MW 0.19 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.02 MW 0.02 MW

Details for 05TILLMA-05ALLEN 138.0 kV Ckt 1 line l/o AEP_P7-1_#16440_SRT-SL


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05TILLMA-05ALLEN 138.0 kV Ckt 1 line
243383 to 243242 ckt 1
Contingency Name:
AEP_P7-1_#16440_SRT-SL
CONTINGENCY 'AEP_P7-1_#16440_SRT-SL'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1                /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242989 TO BUS 243066 CKT 1                /*05E LIMA     138.0 - 05NW LIM     138.0
 OPEN BRANCH FROM BUS 243066 TO BUS 243157 CKT 1                /*05NW LIM     138.0 - 05WOODLA     138.0
 OPEN BRANCH FROM BUS 243136 TO BUS 243157 CKT 1                /*05W LIMA     138.0 - 05WOODLA     138.0
 SET POSTCONTRATING 368 BRANCH FROM BUS 242935 TO BUS 242989 CKT 2 /*05E LIMA     345.0 - 05E LIMA     138.0
 SET PRECONTRATING 285 BRANCH FROM BUS 242935 TO BUS 242989 CKT 2 /*05E LIMA     345.0 - 05E LIMA     138.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 100.66 %
Rating: 341.0 MVA
Rating Type: B
MVA to Mitigate: 343.25 MVA
MW Contribution: 39.38 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05TILLMA-05ALLEN 138.0 kV Ckt 1 line
243383 to 243242 ckt 1
Contingency Name:
AEP_P7-1_#16440_SRT-SL
CONTINGENCY 'AEP_P7-1_#16440_SRT-SL'
 OPEN BRANCH FROM BUS 242989 TO BUS 243017 CKT 1                /*05E LIMA     138.0 - 05HAVILAND1  138.0
 OPEN BRANCH FROM BUS 242989 TO BUS 243066 CKT 1                /*05E LIMA     138.0 - 05NW LIM     138.0
 OPEN BRANCH FROM BUS 243066 TO BUS 243157 CKT 1                /*05NW LIM     138.0 - 05WOODLA     138.0
 OPEN BRANCH FROM BUS 243136 TO BUS 243157 CKT 1                /*05W LIMA     138.0 - 05WOODLA     138.0
 SET POSTCONTRATING 368 BRANCH FROM BUS 242935 TO BUS 242989 CKT 2 /*05E LIMA     345.0 - 05E LIMA     138.0
 SET PRECONTRATING 285 BRANCH FROM BUS 242935 TO BUS 242989 CKT 2 /*05E LIMA     345.0 - 05E LIMA     138.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 100.33 %
Rating: 341.0 MVA
Rating Type: B
MVA to Mitigate: 342.12 MVA
MW Contribution: 39.38 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243017 05HAVILAND1 50/50 0.49 MW 0.49 MW
965041 AG1-368 C 50/50 52.16 MW 52.16 MW
965042 AG1-368 E 50/50 34.77 MW 34.77 MW
246953 05TIMB G C 50/50 2.95 MW 2.95 MW
247911 05TIMB G E 50/50 59.94 MW 59.94 MW
942801 AE2-298 C 50/50 13.7 MW 13.7 MW
942802 AE2-298 E 50/50 9.16 MW 9.16 MW
960851 AF2-376 C 50/50 15.75 MW 15.75 MW
960852 AF2-376 E 50/50 23.63 MW 23.63 MW
940031 AE1-245 C 50/50 13.05 MW 13.05 MW
940032 AE1-245 E 50/50 87.33 MW 87.33 MW
958091 AF2-103 C 50/50 0.14 MW 0.14 MW
958092 AF2-103 E 50/50 1.23 MW 1.23 MW
247607 V1-011 GEN 50/50 1.42 MW 1.42 MW
270258 AD1-119 C 50/50 0.96 MW 0.96 MW
270297 AD1-101 C 50/50 0.36 MW 0.36 MW
247959 V1-011 E 50/50 58.24 MW 58.24 MW
934742 AD1-101 E 50/50 3.56 MW 3.56 MW
934906 AD1-119 E 50/50 9.56 MW 9.56 MW
926811 AC1-167 C 50/50 1.14 MW 1.14 MW
926812 AC1-167 E 50/50 3.6 MW 3.6 MW
943181 AE2-322 C 50/50 1.35 MW 1.35 MW
943182 AE2-322 E 50/50 4.34 MW 4.34 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.05 MW 0.05 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.07 MW 0.07 MW
VTF LTFEXP_VFT->PJM CMTX 0.2 MW 0.2 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.28 MW 0.28 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.02 MW 0.02 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.01 MW 0.01 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.49 MW 0.49 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.06 MW 0.06 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.18 MW 0.18 MW
MDU PJM->LTFIMP_MDU CLTF 0.03 MW 0.03 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.22 MW 0.22 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.02 MW 0.02 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line
243017 to 242989 ckt 1
AEP_P1-2_#7501_16678_SRT-A
CONTINGENCY 'AEP_P1-2_#7501_16678_SRT-A'
 OPEN BRANCH FROM BUS 243242 TO BUS 243383 CKT 1   /*05ALLEN      138.0 - 05TILLMA     138.0
 OPEN BRANCH FROM BUS 243383 TO BUS 246950 CKT 1   /*05TILLMA     138.0 - 05TIMBER SW  138.0
END
OP AC 118.41 % 205.0 B 242.74 28.1

Details for 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line l/o AEP_P1-2_#7501_16678_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line
243017 to 242989 ckt 1
Contingency Name:
AEP_P1-2_#7501_16678_SRT-A
CONTINGENCY 'AEP_P1-2_#7501_16678_SRT-A'
 OPEN BRANCH FROM BUS 243242 TO BUS 243383 CKT 1   /*05ALLEN      138.0 - 05TILLMA     138.0
 OPEN BRANCH FROM BUS 243383 TO BUS 246950 CKT 1   /*05TILLMA     138.0 - 05TIMBER SW  138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 118.41 %
Rating: 205.0 MVA
Rating Type: B
MVA to Mitigate: 242.74 MVA
MW Contribution: 28.1 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line
243017 to 242989 ckt 1
Contingency Name:
AEP_P1-2_#7501_16678_SRT-A
CONTINGENCY 'AEP_P1-2_#7501_16678_SRT-A'
 OPEN BRANCH FROM BUS 243242 TO BUS 243383 CKT 1   /*05ALLEN      138.0 - 05TILLMA     138.0
 OPEN BRANCH FROM BUS 243383 TO BUS 246950 CKT 1   /*05TILLMA     138.0 - 05TIMBER SW  138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 118.89 %
Rating: 205.0 MVA
Rating Type: B
MVA to Mitigate: 243.73 MVA
MW Contribution: 28.1 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
243017 05HAVILAND1 50/50 0.41 MW 0.41 MW
246953 05TIMB G C 50/50 2.1 MW 2.1 MW
247911 05TIMB G E 50/50 42.77 MW 42.77 MW
942801 AE2-298 C 50/50 11.49 MW 11.49 MW
942802 AE2-298 E 50/50 7.68 MW 7.68 MW
960851 AF2-376 C 50/50 11.24 MW 11.24 MW
960852 AF2-376 E 50/50 16.86 MW 16.86 MW
940031 AE1-245 C 50/50 10.96 MW 10.96 MW
940032 AE1-245 E 50/50 73.35 MW 73.35 MW
958091 AF2-103 C 50/50 0.12 MW 0.12 MW
958092 AF2-103 E 50/50 1.03 MW 1.03 MW
247607 V1-011 GEN 50/50 1.19 MW 1.19 MW
270258 AD1-119 C 50/50 0.81 MW 0.81 MW
247959 V1-011 E 50/50 48.89 MW 48.89 MW
934742 AD1-101 E Adder 2.73 MW 2.32 MW
934906 AD1-119 E 50/50 8.11 MW 8.11 MW
926811 AC1-167 C 50/50 0.97 MW 0.97 MW
926812 AC1-167 E 50/50 3.06 MW 3.06 MW
943181 AE2-322 C 50/50 1.15 MW 1.15 MW
943182 AE2-322 E 50/50 3.69 MW 3.69 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 2.28 MW 2.28 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.73 MW 0.73 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.1 MW 0.1 MW
NY PJM->LTFIMP_NY CLTF 0.05 MW 0.05 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.06 MW 0.06 MW
WEC LTFEXP_WEC->PJM CLTF 0.06 MW 0.06 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.01 MW 0.01 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.0 MW 0.0 MW
TVA LTFEXP_TVA->PJM CLTF 0.09 MW 0.09 MW
MEC LTFEXP_MEC->PJM CLTF 0.26 MW 0.26 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.14 MW 0.14 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.61 MW 0.61 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.02 MW 0.02 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request was evaluated as a 50.0 MW injection and 50.0 MW withdrawal in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Light Load Potential Congestion due to Local Energy Deliverability

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Request (project) in PJM Transition Cycle 1, AF2-376 is listed in Table 1 below. This report will cover the dynamic analysis of AF2-376 project.

 

This analysis is effectively a screening study to determine whether the addition of the AF2-376 project will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AF2-376 project has been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

AF2-376 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 92 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time,

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       f)       Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       AF2-376 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with AF2-376 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-376 meet the 0.95 leading and lagging PF requirement.

 

The AE2-298 unit tripped by an undervoltage relay for one contingency (P1.09). Contingency P1.09 involved a three-phase fault at Haviland 345 kV clearing in 6 cycles. As per NERC Standard PRC-024 requirements, this relay settings were found to meet the corresponding NERC PRC-024 LVRT. Additionally, this tripping event was observed in the AE2-298 Dynamic Study and with the pre-AF2-376 scenario, therefore is not attributed to AF2-376.

 

For contingencies P5.01, P5.02 and P5.04, it was observed that active power of Timber switch unit was not recovered to pre fault value. This will not cause any instability in the system and can be mitigated upon request.

 

The IPCMD and IQCMD states in the REGCAU model of AF2-376 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The CSCR results are summarized in Table 4 through Table 9 and revealed a minimum and maximum CSCR values of 1.85  for P4.25 and 4.91 for P1.04, respectively.

 

No mitigations were found to be required.

 

Table 1: TC1 AF2-376 Project

Queue

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AF2-376

AF2-376

BESS

AEP

50.0 MW

50.0 MW

20.0

MW

Timber Switch 138 kV

 

 

Reactive Power Analysis

The reactive power capability of AF2-376 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AC1-167 Mark Center 69kV Under Construction
AD1-101 Continental 69 kV In Service
AD1-119 Payne 69 kV In Service
AE1-245 Haviland 138 kV Under Construction
AE2-298 Cavett Switch - West Van Wert 69 kV Engineering & Procurement
AE2-322 Mark Center 69 kV Under Construction
AF2-103 Haviland 138 kV In Service
AG1-368 Tillman 138 kV Engineering & Procurement
V1-011 Haviland 138kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AF2-376 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
AEP n7679 Replace 1272 AAC Jumper at Allen station Contingent $0 N/A
Dayton b3904.1 Rebuild and reconductor 7.7 miles of 69kV line. Contingent $0 N/A
AEP s2793.5 Rebuild the T-line from West Van Wert to Roller Creek Contingent $0 N/A
Grand Total: $0

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n7679
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n7679 / AEPI0040a
Title
Replace 1272 AAC Jumper at Allen station
Description
Replace 1272 AAC Jumper at Allen station Cost updated to $76,051 from Facility Study.
Total Cost ($USD)
$76,051
Discounted Total Cost ($USD)
$76,051
Allocated Cost ($USD)
$0
Time Estimate
18 to 24 Months

Contingent

Note: Based on PJM cost allocation criteria, AF2-376 does not receive cost allocation towards this upgrade which has been securitized by a prior Queue/Cycle.. Although AF2-376 may not have cost responsibility for this upgrade, AF2-376 may need this upgrade in-service to be deliverable to the PJM system. If AF2-376 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
05ALLEN-05TILLMA 138.0 kV Ckt 1 line (Any)

System Reinforcement: b3904.1
Type
Load Flow
TO
Dayton
RTEP ID / TO ID
b3904.1
Title
Rebuild and reconductor 7.7 miles of 69kV line.
Description
Rebuild and reconductor 7.7 miles of 69kV line with our standard 1351 AAC conductor from Rockford substation to the POI. Ratings: 151/187/209/234 (SN/SE/WN/WE) MVA
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AF2-376 may not presently have cost responsibility for this upgrade, AF2-376 may need this upgrade in-service to be deliverable to the PJM system. If AF2-376 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
09ROCKFO-05ROLLER CRK 69.0 kV Ckt 1 line (Any)

System Reinforcement: s2793.5
Type
Load Flow
TO
AEP
RTEP ID / TO ID
s2793.5 / s2793
Title
Rebuild the T-line from West Van Wert to Roller Creek
Description
Rebuild the T-line from West Van Wert to Roller Creek & Roller Creek to POI 69kV line with ratings SN=102, SE=142 , WN= 129, & WE =160 (556.5 ACSR conductor).
Cost Information
Time Estimate
TBD

Contingent

Note: Although AF2-376 may not presently have cost responsibility for this upgrade, AF2-376 may need this upgrade in-service to be deliverable to the PJM system. If AF2-376 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Facility Contingency
09ROCKFO-05ROLLER CRK 69.0 kV Ckt 1 line (Any)

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AF2-376


AF2-376 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AF2-376 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AF2-376 One Line Diagram

AF2-376 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.