AG1-071 Phase III Study Report

v1.00 released 2025-09-18 17:12

Bon Ayr 69 kV

37.5 MW Capacity / 55.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Wood Duck Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is East Kentucky Power Cooperative, Inc..

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $11,106,344 $0 = AND ( $11,106,344 - $0 ) 55.0 = $201,934 per MW

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the East Kentucky Power Cooperative, Inc. zone — Barren County, Kentucky. This project is an increase to the developer’s AG1-070 project(s), which will share the same Point of Interconnection. The AG1-071 project is a 55.0 MW uprate (37.5 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 100.0 MW with 70.2 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-071
Project Name:
Bon Ayr 69 kV
Project Developer Name:
Wood Duck Solar LLC
State:
Kentucky
County:
Barren
Transmission Owner:
East Kentucky Power Cooperative, Inc.
MFO:
100.0
MWE:
55.0
MWC:
37.5
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-071 will interconnect on the East Kentucky Power Cooperative, Inc. transmission system at the Bon Ayr 69 kV substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AG1-071 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AG1-071 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $953,500 $953,500
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $0 $0
Network Upgrades $6,189,500 $6,189,500
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $1,149,629 $1,149,629
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $3,767,215 $0
Total $12,059,844 $8,292,629

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AG1-070/AG1-071

Security has been calculated for the AG1-070/AG1-071 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AG1-070/AG1-071
Project(s): AG1-070/AG1-071
Final Agreement Security (A): $16,376,296
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $16,376,296
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The AG1-071 project is an uprate to AG1-070 and will share the same Point of Change of Ownership with AG1-070.

The scope for AG1-070/AG1-071 includes EKPC will expand its existing Bon Ayr 69 kV substation to accommodate the connection of the PD’s substation facilities to the EKPC transmission system.  EKPC will also construct a 69 kV disconnect switch structure which will be the POI interface.  

 

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9392.0

Expansion of the existing Bon Ayr Substation will include an additional 69 kV box structure, five (5) 69 kV circuit breakers, four (4) 69 kV switches, (1) station service transformer, (3) Bus PTs, (3) metering PTs, (3) Metering CTs, (6) arresters, and other misc equipment.

$3,180,000 $2,717,000 $1,128,000 $125,000 $7,150,000 $3,575,000 (See Note 1)
n9391.0

Revise relay settings at Barren County Substation

$55,000 $4,000 $6,000 $1,000 $66,000 $33,000 (See Note 1)
n9390.0

Revise relay settings at Fox Hollow Substation

$55,000 $4,000 $6,000 $1,000 $66,000 $33,000 (See Note 1)
n9389.0

Modify 69 kV transmission line facilities to re-terminate the existing Bon Ayer – Cave City 69 kV line section to the newly expanded Bon Ayr switching station. Two (2) replacement structures will need to be located near the Bon Ayr station.

$487,000 $223,000 $105,000 $12,000 $827,000 $413,500 (See Note 1)
n9388.0

Overhead Optical Ground Wire (OPGW) infrastructure on the Bon Ayr – Beckton – West Glasgow – Parkway 69kV line section (8.3 miles) will need to be installed for the new Bon Ayr 69 kV switching substation expansion.

$1,444,000 $336,000 $151,000 $15,000 $1,946,000 $973,000 (See Note 1)
n9387.0

OPGW infrastructure on the Bon Ayr – Cave City – Cav City Jct. – Barren County 69kV line section (14.6 miles) will also need to be installed for a redundant fiber path to the Bon Ayr 69kV switching substation expansion.

$1,700,000 $410,000 $191,000 $23,000 $2,324,000 $1,162,000 (See Note 1)
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

Install one (1) 69 kV monopole dead-end structure and foundation, 69 kV 3-pole disconnect switch attached to the new dead-end structure, line conductor from the dead-end structure to switching station bus position, interconnection metering and telecommunications facilities, 69 kV circuit breaker and associated line side 69 kV disconnect switch, and a relay panel.

$994,000 $593,000 $288,000 $32,000 $1,907,000 $953,500 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

EKPC anticipates that it will take 30 months after the signing of the Generator Interconnection Agreement and the project kickoff call is subsequently held to complete the physical interconnection project upgrades associated with AG1-070.

This assumes no delays due to permitting or environmental issues, and that all necessary outages can be taken as needed to maintain the schedule.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. EKPC interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request was evaluated as a 55.0 MW (37.5 MW Capacity) injection in the EKPC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 117.61 % 277.0 B 325.79 5.62
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1014_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1014_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Breaker AC 117.26 % 277.0 B 324.82 5.63
EKPC AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
EKPC_P2-3_SSHAD S11-1044_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1044_SRT-A-1'
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Breaker AC 110.42 % 63.0 B 69.56 5.13
EKPC AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
EKPC_P4-5_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P4-5_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Breaker AC 110.42 % 63.0 B 69.56 5.13
EKPC AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
EKPC_P2-3_SSHAD S11-1039_SRT-A
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1039_SRT-A'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Breaker AC 110.02 % 63.0 B 69.31 5.05
EKPC AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
EKPC_P4-2_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P4-2_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Breaker AC 110.02 % 63.0 B 69.31 5.05
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P2-2_LAUREL CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_LAUREL CO 161_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Bus AC 117.26 % 277.0 B 324.82 5.63
EKPC AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1
CONTINGENCY 'EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1'
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Bus AC 110.02 % 63.0 B 69.31 5.05
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 133.1 % 105.0 B 139.75 3.97
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 117.62 % 277.0 B 325.8 5.62

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1024_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 117.61 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 325.79 MVA
MW Contribution: 5.62 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 117.28 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.86 MVA
MW Contribution: 5.62 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.69 MW 10.69 MW
964902 AG1-354 E 50/50 7.13 MW 7.13 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.63 MW 6.63 MW
943702 AF1-038 E 50/50 4.42 MW 4.42 MW
943821 AF1-050 C 50/50 4.45 MW 4.45 MW
943822 AF1-050 E 50/50 2.96 MW 2.96 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.46 MW 20.46 MW
342945 1LAUREL 1G 50/50 6.36 MW 6.36 MW
939132 AE1-143 E 50/50 4.87 MW 4.87 MW
940831 AE2-071 C 50/50 0.4 MW 0.4 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.84 MW 9.84 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.56 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.33 MW 7.33 MW
964782 AG1-341 E 50/50 4.89 MW 4.89 MW
965411 AG1-406 C 50/50 2.57 MW 2.57 MW
966021 AG1-471 C 50/50 6.55 MW 6.55 MW
966022 AG1-471 E 50/50 4.0 MW 4.0 MW
950000 AG9-001 External Queue 7.4 MW 7.4 MW
950011 AG9-010 External Queue 13.44 MW 13.44 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.6 MW 3.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.12 MW 5.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.54 MW 2.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.92 MW 1.92 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1014_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P4-5_LAURL S50-1014_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1014_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 117.26 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.82 MVA
MW Contribution: 5.63 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.71 MW 10.71 MW
964902 AG1-354 E 50/50 7.14 MW 7.14 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.64 MW 6.64 MW
943702 AF1-038 E 50/50 4.43 MW 4.43 MW
943821 AF1-050 C 50/50 4.46 MW 4.46 MW
943822 AF1-050 E 50/50 2.97 MW 2.97 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.48 MW 20.48 MW
342945 1LAUREL 1G 50/50 6.37 MW 6.37 MW
939132 AE1-143 E 50/50 4.88 MW 4.88 MW
940831 AE2-071 C 50/50 0.41 MW 0.41 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.85 MW 9.85 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.57 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.34 MW 7.34 MW
964782 AG1-341 E 50/50 4.9 MW 4.9 MW
965411 AG1-406 C 50/50 2.58 MW 2.58 MW
966021 AG1-471 C 50/50 6.56 MW 6.56 MW
966022 AG1-471 E 50/50 4.01 MW 4.01 MW
950000 AG9-001 External Queue 7.42 MW 7.42 MW
950011 AG9-010 External Queue 13.46 MW 13.46 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.62 MW 3.62 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.15 MW 5.15 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.58 MW 2.58 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.93 MW 1.93 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.79 MW 1.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line l/o EKPC_P2-3_SSHAD S11-1044_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P2-3_SSHAD S11-1044_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1044_SRT-A-1'
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.42 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.56 MVA
MW Contribution: 5.13 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P2-3_SSHAD S11-1044_SRT-A-1
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1044_SRT-A-1'
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.58 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.67 MVA
MW Contribution: 5.13 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943701 AF1-038 C Adder -2.2 MW -1.87 MW
945381 AF1-203 C 50/50 1.24 MW 1.24 MW
945382 AF1-203 E 50/50 5.23 MW 5.23 MW
940831 AE2-071 C 50/50 2.2 MW 2.2 MW
940832 AE2-071 E 50/50 9.16 MW 9.16 MW
962241 AG1-070 C Adder 0.63 MW 0.54 MW
962242 AG1-070 E Adder 3.57 MW 3.03 MW
962251 AG1-071 C Adder 0.77 MW 0.65 MW
962252 AG1-071 E Adder 4.36 MW 3.71 MW
960741 AF2-365 C Adder 1.65 MW 1.41 MW
960742 AF2-365 E Adder 1.1 MW 0.94 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.67 MW 0.67 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.9 MW 0.9 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.52 MW 0.52 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.03 MW 0.03 MW
TVA LTFEXP_TVA->PJM CLTF 0.32 MW 0.32 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.03 MW 0.03 MW
MEC LTFEXP_MEC->PJM CLTF 0.14 MW 0.14 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.07 MW 0.07 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.32 MW 0.32 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.01 MW 0.01 MW

Details for AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line l/o EKPC_P4-5_SSHAD S11-1004_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P4-5_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P4-5_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.42 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.56 MVA
MW Contribution: 5.13 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P4-5_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P4-5_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
 OPEN BUS 361788                                   /*5SUM SHAD TP 161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.58 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.67 MVA
MW Contribution: 5.13 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943701 AF1-038 C Adder -2.2 MW -1.87 MW
945381 AF1-203 C 50/50 1.24 MW 1.24 MW
945382 AF1-203 E 50/50 5.23 MW 5.23 MW
940831 AE2-071 C 50/50 2.2 MW 2.2 MW
940832 AE2-071 E 50/50 9.16 MW 9.16 MW
962241 AG1-070 C Adder 0.63 MW 0.54 MW
962242 AG1-070 E Adder 3.57 MW 3.03 MW
962251 AG1-071 C Adder 0.77 MW 0.65 MW
962252 AG1-071 E Adder 4.36 MW 3.71 MW
960741 AF2-365 C Adder 1.65 MW 1.41 MW
960742 AF2-365 E Adder 1.1 MW 0.94 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.67 MW 0.67 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.9 MW 0.9 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.52 MW 0.52 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.03 MW 0.03 MW
TVA LTFEXP_TVA->PJM CLTF 0.32 MW 0.32 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.03 MW 0.03 MW
MEC LTFEXP_MEC->PJM CLTF 0.14 MW 0.14 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.07 MW 0.07 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.32 MW 0.32 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.01 MW 0.01 MW

Details for AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line l/o EKPC_P2-3_SSHAD S11-1039_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P2-3_SSHAD S11-1039_SRT-A
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1039_SRT-A'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.02 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.31 MVA
MW Contribution: 5.05 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P2-3_SSHAD S11-1039_SRT-A
CONTINGENCY 'EKPC_P2-3_SSHAD S11-1039_SRT-A'
 OPEN BRANCH FROM BUS 341059 TO BUS 342694 CKT 1   /*2BARREN CO    69.0 - 5BARREN CO   161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.06 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.34 MVA
MW Contribution: 5.05 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943701 AF1-038 C Adder -2.24 MW -1.9 MW
945381 AF1-203 C 50/50 1.24 MW 1.24 MW
945382 AF1-203 E 50/50 5.22 MW 5.22 MW
940831 AE2-071 C 50/50 2.19 MW 2.19 MW
940832 AE2-071 E 50/50 9.14 MW 9.14 MW
962241 AG1-070 C Adder 0.62 MW 0.53 MW
962242 AG1-070 E Adder 3.51 MW 2.99 MW
962251 AG1-071 C Adder 0.76 MW 0.64 MW
962252 AG1-071 E Adder 4.29 MW 3.65 MW
960741 AF2-365 C Adder 1.63 MW 1.38 MW
960742 AF2-365 E Adder 1.08 MW 0.92 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.67 MW 0.67 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.83 MW 0.83 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.39 MW 0.39 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.28 MW 0.28 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.13 MW 0.13 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.28 MW 0.28 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.01 MW 0.01 MW

Details for AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line l/o EKPC_P4-2_SSHAD S11-1004_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P4-2_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P4-2_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.02 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.31 MVA
MW Contribution: 5.05 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P4-2_SSHAD S11-1004_SRT-A-1
CONTINGENCY 'EKPC_P4-2_SSHAD S11-1004_SRT-A-1'
 OPEN BRANCH FROM BUS 361788 TO BUS 342814 CKT 1   /*5SUM SHAD TP 161.0 - 5SUMM SHADE  161.0
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.06 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.34 MVA
MW Contribution: 5.05 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943701 AF1-038 C Adder -2.24 MW -1.9 MW
945381 AF1-203 C 50/50 1.24 MW 1.24 MW
945382 AF1-203 E 50/50 5.22 MW 5.22 MW
940831 AE2-071 C 50/50 2.19 MW 2.19 MW
940832 AE2-071 E 50/50 9.14 MW 9.14 MW
962241 AG1-070 C Adder 0.62 MW 0.53 MW
962242 AG1-070 E Adder 3.51 MW 2.99 MW
962251 AG1-071 C Adder 0.76 MW 0.64 MW
962252 AG1-071 E Adder 4.29 MW 3.65 MW
960741 AF2-365 C Adder 1.63 MW 1.38 MW
960742 AF2-365 E Adder 1.08 MW 0.92 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.67 MW 0.67 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.83 MW 0.83 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.39 MW 0.39 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.28 MW 0.28 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.13 MW 0.13 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.28 MW 0.28 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.01 MW 0.01 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P2-2_LAUREL CO 161_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P2-2_LAUREL CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_LAUREL CO 161_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 117.26 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.82 MVA
MW Contribution: 5.63 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.71 MW 10.71 MW
964902 AG1-354 E 50/50 7.14 MW 7.14 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.64 MW 6.64 MW
943702 AF1-038 E 50/50 4.43 MW 4.43 MW
943821 AF1-050 C 50/50 4.46 MW 4.46 MW
943822 AF1-050 E 50/50 2.97 MW 2.97 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.48 MW 20.48 MW
342945 1LAUREL 1G 50/50 6.37 MW 6.37 MW
939132 AE1-143 E 50/50 4.88 MW 4.88 MW
940831 AE2-071 C 50/50 0.41 MW 0.41 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.85 MW 9.85 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.57 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.34 MW 7.34 MW
964782 AG1-341 E 50/50 4.9 MW 4.9 MW
965411 AG1-406 C 50/50 2.58 MW 2.58 MW
966021 AG1-471 C 50/50 6.56 MW 6.56 MW
966022 AG1-471 E 50/50 4.01 MW 4.01 MW
950000 AG9-001 External Queue 7.42 MW 7.42 MW
950011 AG9-010 External Queue 13.46 MW 13.46 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.62 MW 3.62 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.15 MW 5.15 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.58 MW 2.58 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.93 MW 1.93 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.79 MW 1.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line l/o EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1
CONTINGENCY 'EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1'
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 110.02 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.31 MVA
MW Contribution: 5.05 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1
CONTINGENCY 'EKPC_P2-2_SUMMSHADE 161 #2_SRT-A-1'
 OPEN BRANCH FROM BUS 964900 TO BUS 342814 CKT 1   /*AG1-354 TP   161.0 - 5SUMM SHADE  161.0
 OPEN BUS 342814                                   /*5SUMM SHADE  161.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 110.06 %
Rating: 63.0 MVA
Rating Type: B
MVA to Mitigate: 69.34 MVA
MW Contribution: 5.05 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943701 AF1-038 C Adder -2.24 MW -1.9 MW
945381 AF1-203 C 50/50 1.24 MW 1.24 MW
945382 AF1-203 E 50/50 5.22 MW 5.22 MW
940831 AE2-071 C 50/50 2.19 MW 2.19 MW
940832 AE2-071 E 50/50 9.14 MW 9.14 MW
962241 AG1-070 C Adder 0.62 MW 0.53 MW
962242 AG1-070 E Adder 3.51 MW 2.99 MW
962251 AG1-071 C Adder 0.76 MW 0.64 MW
962252 AG1-071 E Adder 4.29 MW 3.65 MW
960741 AF2-365 C Adder 1.63 MW 1.38 MW
960742 AF2-365 E Adder 1.08 MW 0.92 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.67 MW 0.67 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.83 MW 0.83 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.39 MW 0.39 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.02 MW 0.02 MW
TVA LTFEXP_TVA->PJM CLTF 0.28 MW 0.28 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.13 MW 0.13 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.01 MW 0.01 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.28 MW 0.28 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.09 MW 0.09 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.01 MW 0.01 MW

Details for 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
Contingency Name:
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 133.1 %
Rating: 105.0 MVA
Rating Type: B
MVA to Mitigate: 139.75 MVA
MW Contribution: 3.97 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC/LGEE
Facility Description:
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
Contingency Name:
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 132.18 %
Rating: 105.0 MVA
Rating Type: B
MVA to Mitigate: 138.79 MVA
MW Contribution: 3.96 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C Adder 7.27 MW 6.18 MW
964902 AG1-354 E Adder 4.85 MW 4.12 MW
965401 AG1-405 C 50/50 10.9 MW 10.9 MW
965402 AG1-405 E 50/50 7.27 MW 7.27 MW
943701 AF1-038 C 50/50 8.41 MW 8.41 MW
943702 AF1-038 E 50/50 5.61 MW 5.61 MW
943821 AF1-050 C Adder 2.98 MW 2.53 MW
943822 AF1-050 E Adder 1.99 MW 1.69 MW
945382 AF1-203 E Adder 0.72 MW 0.61 MW
342900 1COOPER1 G 50/50 5.11 MW 5.11 MW
342903 1COOPER2 G 50/50 9.91 MW 9.91 MW
939132 AE1-143 E Adder 3.13 MW 2.66 MW
940832 AE2-071 E Adder 1.26 MW 1.07 MW
339206 AE1-143 C Adder 6.31 MW 5.36 MW
962241 AG1-070 C Adder 0.49 MW 0.41 MW
962242 AG1-070 E Adder 2.76 MW 2.35 MW
962251 AG1-071 C Adder 0.6 MW 0.51 MW
962252 AG1-071 E Adder 3.37 MW 2.87 MW
944151 AF1-083 C Adder 2.92 MW 2.49 MW
944152 AF1-083 E Adder 1.95 MW 1.66 MW
960741 AF2-365 C Adder 1.77 MW 1.51 MW
960742 AF2-365 E Adder 1.18 MW 1.0 MW
964781 AG1-341 C Adder 5.04 MW 4.29 MW
964782 AG1-341 E Adder 3.36 MW 2.86 MW
965411 AG1-406 C 50/50 7.01 MW 7.01 MW
966021 AG1-471 C 50/50 4.64 MW 4.64 MW
966022 AG1-471 E 50/50 2.84 MW 2.84 MW
950011 AG9-010 External Queue 8.6 MW 8.6 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.1 MW 3.1 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.59 MW 3.59 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.67 MW 1.67 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.09 MW 0.09 MW
NY PJM->LTFIMP_NY CLTF 0.05 MW 0.05 MW
WEC LTFEXP_WEC->PJM CLTF 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.08 MW 0.08 MW
TVA LTFEXP_TVA->PJM CLTF 1.28 MW 1.28 MW
MEC LTFEXP_MEC->PJM CLTF 0.56 MW 0.56 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.21 MW 1.21 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.57 MW 0.57 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.04 MW 0.04 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P7-1_LAURL 161 DBL_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 117.62 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 325.8 MVA
MW Contribution: 5.62 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 117.27 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.84 MVA
MW Contribution: 5.62 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.69 MW 10.69 MW
964902 AG1-354 E 50/50 7.13 MW 7.13 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.63 MW 6.63 MW
943702 AF1-038 E 50/50 4.42 MW 4.42 MW
943821 AF1-050 C 50/50 4.45 MW 4.45 MW
943822 AF1-050 E 50/50 2.96 MW 2.96 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.46 MW 20.46 MW
342945 1LAUREL 1G 50/50 6.36 MW 6.36 MW
939132 AE1-143 E 50/50 4.87 MW 4.87 MW
940831 AE2-071 C 50/50 0.4 MW 0.4 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.84 MW 9.84 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.56 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.33 MW 7.33 MW
964782 AG1-341 E 50/50 4.89 MW 4.89 MW
965411 AG1-406 C 50/50 2.57 MW 2.57 MW
966021 AG1-471 C 50/50 6.55 MW 6.55 MW
966022 AG1-471 E 50/50 4.0 MW 4.0 MW
950000 AG9-001 External Queue 7.4 MW 7.4 MW
950011 AG9-010 External Queue 13.44 MW 13.44 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.6 MW 3.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.12 MW 5.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.54 MW 2.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.92 MW 1.92 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Base Case OP AC 100.9 % 57.0 A 57.51 5.85

Details for AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.9 %
Rating: 57.0 MVA
Rating Type: A
MVA to Mitigate: 57.51 MVA
MW Contribution: 5.85 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC
Facility Description:
AE2-071 TP-2SUMM SHAD J 69.0 kV Ckt 1 line
940830 to 342319 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.89 %
Rating: 57.0 MVA
Rating Type: A
MVA to Mitigate: 57.51 MVA
MW Contribution: 5.85 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
945381 AF1-203 C 50/50 1.52 MW 1.52 MW
945382 AF1-203 E 50/50 6.42 MW 6.42 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
940831 AE2-071 C 50/50 2.69 MW 2.69 MW
940832 AE2-071 E 50/50 11.23 MW 11.23 MW
962241 AG1-070 C 50/50 0.72 MW 0.72 MW
962242 AG1-070 E 50/50 4.07 MW 4.07 MW
962251 AG1-071 C 50/50 0.88 MW 0.88 MW
962252 AG1-071 E 50/50 4.97 MW 4.97 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.28 MW 0.28 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 0.41 MW 0.41 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 0.03 MW 0.03 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.02 MW 0.02 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
WEC LTFEXP_WEC->PJM CLTF 0.01 MW 0.01 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.0 MW 0.0 MW
TVA LTFEXP_TVA->PJM CLTF 0.12 MW 0.12 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
MEC LTFEXP_MEC->PJM CLTF 0.06 MW 0.06 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.04 MW 0.04 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.13 MW 0.13 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.01 MW 0.01 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.11 MW 0.11 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.0 MW 0.0 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

New Service Requests (projects) AG1-070 and AG1-071 in PJM Transition Cycle 1 are listed in Table 1 below. This report will cover the dynamic analysis of AG1-070 and AG1-071 projects.

This analysis is effectively a screening study to determine whether the addition of the AG1-071 and AG1-071 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-070 and AG1-071 have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

AG1-070 and AG1-071 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 121 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the AG1-070 and AG1-071 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AG1-070 and AG1-071 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AG1-070 and AG1-071 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-070 and AG1-071 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AG1-070 GEN and AG1-071 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

No mitigations were found to be required.

Table 1: TC1 AG1-070/AG1-071 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-070

Solar

EKPC

45

45

32.7

Bon Ayr 69 kV

AG1-071

Solar

EKPC

55

55

37.5

Bon Ayr 69 kV

 

 

Reactive Power Analysis

The reactive power capability of AG1-071 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AE1-143 Marion County 161 kV Engineering & Procurement
AE2-071 Patton Rd-Summer Shade 69 kV In Service
AF1-038 Sewellton Jct-Webbs Crossroads 69 kV Engineering & Procurement
AF1-050 Summer Shade - Green County 161 kV Engineering & Procurement
AF1-083 Green County-Saloma 161 kV Engineering & Procurement
AF1-203 Patton Rd-Summer Shade 69 kV In Service
AF2-365 Munfordville KU Tap-Horse Cave Jct. 69 kV Active
AG1-070 Bon Ayr 69 kV Active
AG1-341 Summer Shade 161 kV Active
AG1-354 Summershade-Green County 161 kV Active
AG1-405 Walnut Grove-Asahi 69 kV Active
AG1-406 Walnut Grove-Asahi 69 kV Active
AG1-471 Up Church-Wayne County 69 kV Active

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) Identified Impacts
AG1-071 System Reinforcements:
TO Trans Owner ID Title Category Allocated Cost ($USD)
LGEE LGEE_TC1_15519 Invalid - P7 contingency 69kV not monitored by LGEE Informational $0
LGEE LGEE_TC1_16266 LGEE AFS Analysis has determined reinforcements are not required on the Cooper - Elihu 161kV Line. Informational $0
LGEE None LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B Informational $0
Grand Total: $0

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_15519
Title
Invalid - P7 contingency 69kV not monitored by LGEE
Description
Invalid - P7 contingency 69kV not monitored by LGEE EKPC emergency rating is 143 MVA on the Somerset KU - Ferguston 69kV line.
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_16266
Title
LGEE AFS Analysis has determined reinforcements are not required on the Cooper - Elihu 161kV Line.
Description
LGEE Affected System Analysis has determined reinforcements are not required on the Cooper - Elihu 161kV Line. Thus EKPC existing 298 MVA Rate B is adequate as LGEE is the limiting element of the line. No reinforcements are required by EKPC.
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending)
Title
LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B
Description
LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)

Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted Facility Transmission Owner Reinforcement Cost Cost Allocated to AG1-071 Scenarios
  • 2CAMPBELVL 69.0 - 2TAYLOR CO 69.0 CKT 1
LGEE Campbellsville 2 Tap - Taylor County 69 kV Line Reconductor
Replace 0.38 miles of 266.8 MCM 26X7 ACSR
conductor in the Campbellsville 2 Tap to Taylor
County section of the Lebanon to Taylor County 69
kV line, using 556 MCM 26X7 ACSR or better
conductor.
$950,000 $47,634
  • 2LEBANON 69.0 - 2SPRINGFL KU 69.0 CKT 1
LGEE Lebanon - Springfield 69 kV Line Reconductor
Reconductor the 6.58 miles of 266.8 26x7 ACSR and
replace 266.8 26x7 ACSR line riser in the Lebanon
to Springfield 69 kV line with 397.5 MCM ACSR
$16,527,000 $873,725
  • 2MOREHEAD W 69.0 - 2MOREHEAD 69.0 CKT 1
LGEE Morehead W - Morehead 69 kV Line Reconductor
Reconductor the 0.19 miles of 2/0 7x CU in the
Morehead W to Morehead 69kV, to 266.8 MCM 26x7
ACSR.
$475,000 $11,003
  • 2SHELBY CO T 69.0 - 2SHELBYVIL S 69.0 CKT 1
LGEE Shelbyville South - Shelby Co Tap 69 kV Line MOT
Increase the maximum operating temperature of 1.96
miles of 397.5 ACSR in the Shelbyville South to
Shelby Co tap section of the Shelbyville to
Finchville 69 kV line from 150°F to a minimum of
170°F.
$682,500 $56,306
  • 2SPRINGFL KU 69.0 - 2N SPRINGFLD 69.0 CKT 1
LGEE Springfield - North Springfield 69 kV Line MOT
Increase the MOT of 3.24 miles of 266.8 26x7 ACSR
to 176/212F in the Springfield-North Springfield
69 kV line.
$1,134,000 $59,677
  • 4TYRONE 138.0 - 4BROWN N 1 138.0 CKT 1
LGEE Brown North - Tyrone 138 kV Line Reconductor
Reconductor the 556.5 MCM 26X7 ACSR 20.12 mi with
795 MCM 45X7 ACSR or better in the Brown North to
Tyrone 138 kV line.
$60,360,000 $2,718,870
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AG1-071 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
EKPC n7788.1 Rebuild the AE2-071-Summer Shade 69 kV line section using 795 MCM ACSR conductor at 212 degrees F (1.7 miles) Cost Allocated $1,149,629
Grand Total: $1,149,629

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n7788.1
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
n7788.1 / r0071
Title
Rebuild the AE2-071-Summer Shade 69 kV line section using 795 MCM ACSR conductor at 212 degrees F (1.7 miles)
Description
Rebuild the AE2-071-Summer Shade 69 kV line section using 795 MCM ACSR conductor at 212 degrees F (1.7 miles)
Total Cost ($USD)
$2,708,000
Discounted Total Cost ($USD)
$2,708,000
Allocated Cost ($USD)
$1,149,629
Time Estimate
8 to 12 Months

Contributor

Facility Contingency
2SUMM SHAD J-AE2-071 TAP 69.0 kV Ckt 1 line (Any)
2SUMM SHAD J-AE2-071 TP 69.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-365 2.8 MW 22.8% $617,704
AG1-070 4.2 MW 34.7% $940,667
AG1-071 5.1 MW 42.5% $1,149,629

System Reinforcement
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
(Pending) / EKPC-tc1-r0004a
Title
EKPC emergency rating is 143 MVA.
Description
EKPC emergency rating is 143 MVA. LG&E: SE rating is 105 MVA.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
(Pending) / EKPC-tc1-r0012a
Title
LGE/KU is limiting this facility. EKPC emergency rating is 298 MVA.
Description
LGE/KU is limiting this facility (LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B). EKPC emergency rating is 298 MVA. LGEE AFS for TC1 has determined they will not require an reinforcement and thus EKPC existing 298 MVA Rate B is adequate as LGEE is the limiting element of the line.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-071


AG1-071 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AG1-071 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AG1-071 One Line Diagram

AG1-071 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.