AG1-124 Phase III Study Report

v1.00 released 2025-09-18 16:51

Gladstone 138 kV

53.01 MW Capacity / 90.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Wild Rose Solar Project, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Appalachian Power Company.

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $21,235,914 $13,005,587 = 1.63 AND ( $21,235,914 - $13,005,587 ) 90.0 = $91,448 per MW

General

The Project Developer has proposed a Solar generating facility located in the American Electric Power zone — Nelson County, Virginia. The installed facilities will have a total capability of 90.0 MW with 53.01 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-124
Project Name:
Gladstone 138 kV
Project Developer Name:
Wild Rose Solar Project, LLC
State:
Virginia
County:
Nelson
Transmission Owner:
Appalachian Power Company
MFO:
90.0
MWE:
90.0
MWC:
53.01
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-124 will interconnect on the AEP Appalachian Power Company transmission system via a newly constructed 138 kV station tapping the Riverville - Gladstone 138 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AG1-124 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AG1-124 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $1,838,092 $1,838,092
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $7,960,528 $7,960,528
Network Upgrades $2,115,949 $2,115,949
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $11,141,119 $11,141,119
Transient Stability $0 $0
Short Circuit $18,318 $18,318
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $23,074,006 $23,074,006

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AG1-124

Security has been calculated for the AG1-124 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AG1-124
Project(s): AG1-124
Final Agreement Security (A): $23,074,006
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $23,074,006
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

AG1-124 will interconnect with the AEP transmission system via a new station cut into the Riverville - Gladstone 138 kV Circuit. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9536.0

Riverville - Gladstone 138 kV Circuit: Proposed AG1-124 138 kV Switching Station tie-in. Install two (2) new steel, 75', double circuit, two-pole dead-end structures on concrete piers with anchor bolt cages, and three (3) spans of ACSR 795 26/7 (Drake) transmission line conductor with 7#8 Alumoweld shield wire in the existing Riverville - Gladstone 138 kV Right of Way, cutting in the proposed AG1-124 138 kV Station in an in-and-out arrangement from an existing structure.

$1,180,398 $271,140 $246,708 $56,669 $1,754,915 $1,754,915
n9534.0

Riverville - Gladstone 138 kV and Proposed AG1-124 138 kV Switching Station: Final Tie in for Fiber installation.

$274,711 $34,898 $45,211 $6,214 $361,034 $361,034
Stand-Alone Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9537.0

Riverville - Gladstone 138 kV Circuit: Construct a new 138 kV ring bus station; initially populated with three (3) circuit breakers, expandable to four (4) breakers. • Three (3) 138 kV 40 kA circuit breakers with associated control relaying. • One (1) 16' x 27' DICM. • Six (6) breaker disconnect switches. • Three (3) line disconnect motor operated air breaker (MOAB) switches with associated control relaying, one (1) each on the line exits to the AG1-124 collector, Gladstone 138 kV, and Riverville 138 kV stations. • Six (6) single phase CCVTs, three (3) each on the line exits to the Riverville and Gladstone 138 kV Stations. • Two (2) single phase station service voltage transformers (SSVT). • Two (2) Monopole dead-end take off structures, one (1) each for the line exits to Riverville and Gladstone 138 kV Stations. • A direct fiber current differential line protection relay scheme for the line to the Riverville 138 kV Station. • A direct fiber current differential line protection relay scheme for the line to the Gladstone 138 kV Station. • Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures.

$4,206,032 $2,521,702 $503,150 $301,661 $7,532,545 $7,532,545
n9535.0

Proposed AG1-124 138 kV Switching Station: Install two (2) station exit transitions and two (2) new fiber optic cable paths, one (1) consisting of 0.3 miles of underground 144 count ADLT cable and the other consisting of 0.1 miles of optical ground wire (OPGW) fiber optic shield wire.

$322,644 $51,611 $46,319 $7,409 $427,983 $427,983
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

• Installation of one (1) new steel, 85’, single circuit, single pole dead end structure and one span of aluminum conductor steel-reinforced (ACSR) 795 26/7 (Drake) transmission line conductor with 7#8 Alumoweld shield wire for the generation lead circuit extending from the Proposed AG1-124 138 kV Switching Station. • Extension of two (2) underground 96 count all dielectric loose tube (ADLT) fiber optic cables from the Proposed AG1-124 138 kV Switching Station control house to fiber demarcation splice boxes to support direct fiber relaying between the Proposed AG1-124 138 kV and Project Developer's collector stations. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station. • Installation of one (1) Monopole dead-end take off structure for the generation lead circuit line exit. • Installation of three (3) single phase coupling capacitor voltage transformers (CCVTs) on the generation lead circuit. • Installation of a dual, direct-fiber, current differential protection scheme for the generation lead circuit. • Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase voltage transformers (VT), associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module (DICM)-installed metering panel, for the generation lead circuit at the Proposed AG1-124 138 kV Switching Station.

$1,086,495 $487,514 $185,291 $78,792 $1,838,092 $1,838,092

Based on the scope of work for the Interconnection Facilities, it is expected to take 26 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

The minimum and maximum schedules reflect the amount of time, in months, that AEP projects their portion of the construction project scope elapsing from the time of agreement. Final agreements will reflect an "on or before" date, allowing all parties to c, including remote end work, considering the Project Developer selection of the Option To Build, allocating the long lead material ordering as part of the Project Developer scope. The maximum schedule is based off of AEP assumed long lead material ordering not considering allocation of existing material production slots, advanced progress enabled by Engineering and Procurement Agreements, or other schedule expediting methods. AEP may be able to allocate material production slots for long lead time materials to expedite this schedule. Final agreements will reflect an "on or before" date, allowing all parties to complete their scope of work prior to the agreement date, should there be means to expedite. Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to these agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AG1-124 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 90.0 MW (53.01 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Single AC 119.75 % 167.0 B 199.99 6.52
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
DVP_P4-2: 547T566_SRT-A
CONTINGENCY 'DVP_P4-2: 547T566_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314901 TO BUS 314987 CKT 1   /*8BATH CO     500.0 - 8LEXINGTN SC 500.0
 OPEN BRANCH FROM BUS 314912 TO BUS 314987 CKT 1   /*8LEXNGTN     500.0 - 8LEXINGTN SC 500.0
 OPEN BUS 314987                                   /*8LEXINGTN SC 500.0
END
Breaker AC 153.22 % 167.0 B 255.88 11.07
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
DVP_P4-2: 56602_SRT-A
CONTINGENCY 'DVP_P4-2: 56602_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314856 TO BUS 314912 CKT 1   /*6LEXNGT2     230.0 - 8LEXNGTN     500.0
END
Breaker AC 151.88 % 167.0 B 253.63 11.07
DVP 6FORK UNION-6CUNNING 230.0 kV Ckt 1 line
313707 to 313373 ckt 1
DVP_P1-2: LN 2027_SRT-A-2
CONTINGENCY 'DVP_P1-2: LN 2027_SRT-A-2'
 OPEN BRANCH FROM BUS 314322 TO BUS 314333 CKT 1   /*6MDLTHAN     230.0 - 6POWHATN     230.0
 OPEN BRANCH FROM BUS 314333 TO BUS 316335 CKT 1   /*6POWHATN     230.0 - AC2-165 TAP  230.0
 OPEN BUS 314333                                   /*6POWHATN     230.0
 OPEN BUS 316258                                   /*AE1-075 C    230.0
 OPEN BUS 316313                                   /*AB2-026 C    230.0
 OPEN BUS 316405                                   /*AF2-144 C    230.0
 OPEN BUS 923862                                   /*AB2-026 E    230.0
 OPEN BUS 938562                                   /*AE1-075 E    230.0
 OPEN BUS 958502                                   /*AF2-144 E    230.0
END
Single AC 103.11 % 661.76 B 682.37 3.06
DVP 6CUNNING-6MTEAGLE 230.0 kV Ckt 1 line
313373 to 314765 ckt 1
DVP_P1-2: LN 2027_SRT-A-2
CONTINGENCY 'DVP_P1-2: LN 2027_SRT-A-2'
 OPEN BRANCH FROM BUS 314322 TO BUS 314333 CKT 1   /*6MDLTHAN     230.0 - 6POWHATN     230.0
 OPEN BRANCH FROM BUS 314333 TO BUS 316335 CKT 1   /*6POWHATN     230.0 - AC2-165 TAP  230.0
 OPEN BUS 314333                                   /*6POWHATN     230.0
 OPEN BUS 316258                                   /*AE1-075 C    230.0
 OPEN BUS 316313                                   /*AB2-026 C    230.0
 OPEN BUS 316405                                   /*AF2-144 C    230.0
 OPEN BUS 923862                                   /*AB2-026 E    230.0
 OPEN BUS 938562                                   /*AE1-075 E    230.0
 OPEN BUS 958502                                   /*AF2-144 E    230.0
END
Single AC 100.45 % 661.76 B 664.72 3.06
DVP 3BREMO-3FORK UNION 115.0 kV Ckt 2 line
314744 to 313708 ckt 2
DVP_P4-3: SX32_SRT-A
CONTINGENCY 'DVP_P4-3: SX32_SRT-A'
 OPEN BRANCH FROM BUS 313708 TO BUS 314744 CKT 1   /*3FORK UNION  115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 313874 CKT 1   /*3COBBS CREEK 115.0 - 3DUNCAN STOR 115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 314762 CKT 1   /*3COBBS CREEK 115.0 - 3JAMES R     115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 313875 CKT 1   /*3DUNCAN STOR 115.0 - 3TRICESLK    115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 314744 CKT 1   /*3DUNCAN STOR 115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BUS 313871                                   /*3COBBS CREEK 115.0
 OPEN BUS 313874                                   /*3DUNCAN STOR 115.0
 OPEN BUS 313875                                   /*3TRICESLK    115.0
 OPEN BUS 314762                                   /*3JAMES R     115.0
END
Breaker AC 104.02 % 165.0 C 171.64 9.39
DVP 3BREMO-3FORK UNION 115.0 kV Ckt 2 line
314744 to 313708 ckt 2
DVP_P2-2: BREMO B4_SRT-A
CONTINGENCY 'DVP_P2-2: BREMO B4_SRT-A'
 OPEN BRANCH FROM BUS 313708 TO BUS 314744 CKT 1   /*3FORK UNION  115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 313874 CKT 1   /*3COBBS CREEK 115.0 - 3DUNCAN STOR 115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 314762 CKT 1   /*3COBBS CREEK 115.0 - 3JAMES R     115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 313875 CKT 1   /*3DUNCAN STOR 115.0 - 3TRICESLK    115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 314744 CKT 1   /*3DUNCAN STOR 115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BUS 313871                                   /*3COBBS CREEK 115.0
 OPEN BUS 313874                                   /*3DUNCAN STOR 115.0
 OPEN BUS 313875                                   /*3TRICESLK    115.0
 OPEN BUS 314762                                   /*3JAMES R     115.0
END
Bus AC 104.03 % 165.0 C 171.65 9.39

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 119.75 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 199.99 MVA
MW Contribution: 6.52 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 80/20 3.41 MW 3.41 MW
942671 AE2-283 C 80/20 1.41 MW 1.41 MW
242889 05REUSENS 80/20 0.05 MW 0.05 MW
941011 AE2-092 C Adder -6.94 MW -5.9 MW
941801 AE2-185 C 80/20 1.81 MW 1.81 MW
941821 AE2-187 C 80/20 1.81 MW 1.81 MW
958131 AF2-107 C 80/20 9.27 MW 9.27 MW
962751 AG1-124 C 80/20 6.52 MW 6.52 MW
316217 AC1-145 C 80/20 0.16 MW 0.16 MW
270173 AC1-122 C 80/20 0.46 MW 0.46 MW
316197 AC1-042 C 80/20 0.13 MW 0.13 MW
938821 AE1-108 C 80/20 62.13 MW 62.13 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.24 MW 15.24 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.56 MW 6.56 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.75 MW 7.75 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.61 MW 0.61 MW
WEC LTFEXP_WEC->PJM CLTF 0.31 MW 0.31 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.36 MW 0.36 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.53 MW 1.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.18 MW 0.18 MW

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o DVP_P4-2: 547T566_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
DVP_P4-2: 547T566_SRT-A
CONTINGENCY 'DVP_P4-2: 547T566_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314901 TO BUS 314987 CKT 1   /*8BATH CO     500.0 - 8LEXINGTN SC 500.0
 OPEN BRANCH FROM BUS 314912 TO BUS 314987 CKT 1   /*8LEXNGTN     500.0 - 8LEXINGTN SC 500.0
 OPEN BUS 314987                                   /*8LEXINGTN SC 500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 153.22 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 255.88 MVA
MW Contribution: 11.07 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.41 MW 3.41 MW
966252 AG1-494 E 50/50 5.11 MW 5.11 MW
926646 AC1-145 E Adder 0.86 MW 0.73 MW
942671 AE2-283 C Adder 1.41 MW 1.2 MW
942672 AE2-283 E Adder 1.26 MW 1.07 MW
941011 AE2-092 C Adder -6.96 MW -5.91 MW
941801 AE2-185 C Adder 1.81 MW 1.54 MW
941802 AE2-185 E Adder 1.21 MW 1.03 MW
941821 AE2-187 C Adder 1.81 MW 1.54 MW
941822 AE2-187 E Adder 0.8 MW 0.68 MW
958131 AF2-107 C 50/50 9.27 MW 9.27 MW
958132 AF2-107 E 50/50 5.08 MW 5.08 MW
962751 AG1-124 C 50/50 6.52 MW 6.52 MW
962752 AG1-124 E 50/50 4.55 MW 4.55 MW
926516 AC1-122_E Adder 1.33 MW 1.13 MW
925665 AC1-042 E Adder 1.31 MW 1.11 MW
938821 AE1-108 C 50/50 62.12 MW 62.12 MW
938822 AE1-108 E 50/50 29.64 MW 29.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.22 MW 15.22 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.55 MW 6.55 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.71 MW 7.71 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.57 MW 0.57 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.61 MW 0.61 MW
WEC LTFEXP_WEC->PJM CLTF 0.31 MW 0.31 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.36 MW 0.36 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.53 MW 1.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.64 MW 3.64 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.17 MW 0.17 MW

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o DVP_P4-2: 56602_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
DVP_P4-2: 56602_SRT-A
CONTINGENCY 'DVP_P4-2: 56602_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314856 TO BUS 314912 CKT 1   /*6LEXNGT2     230.0 - 8LEXNGTN     500.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 151.88 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 253.63 MVA
MW Contribution: 11.07 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.41 MW 3.41 MW
966252 AG1-494 E 50/50 5.11 MW 5.11 MW
926646 AC1-145 E Adder 0.86 MW 0.73 MW
942671 AE2-283 C Adder 1.41 MW 1.2 MW
942672 AE2-283 E Adder 1.26 MW 1.07 MW
941011 AE2-092 C Adder -6.95 MW -5.91 MW
941801 AE2-185 C Adder 1.81 MW 1.54 MW
941802 AE2-185 E Adder 1.21 MW 1.03 MW
941821 AE2-187 C Adder 1.81 MW 1.54 MW
941822 AE2-187 E Adder 0.81 MW 0.69 MW
958131 AF2-107 C 50/50 9.27 MW 9.27 MW
958132 AF2-107 E 50/50 5.08 MW 5.08 MW
962751 AG1-124 C 50/50 6.52 MW 6.52 MW
962752 AG1-124 E 50/50 4.55 MW 4.55 MW
926516 AC1-122_E Adder 1.33 MW 1.13 MW
925665 AC1-042 E Adder 1.31 MW 1.11 MW
938821 AE1-108 C 50/50 62.13 MW 62.13 MW
938822 AE1-108 E 50/50 29.64 MW 29.64 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 15.24 MW 15.24 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 6.56 MW 6.56 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 7.74 MW 7.74 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.57 MW 0.57 MW
NY PJM->LTFIMP_NY CLTF 0.24 MW 0.24 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.61 MW 0.61 MW
WEC LTFEXP_WEC->PJM CLTF 0.31 MW 0.31 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.36 MW 0.36 MW
TVA LTFEXP_TVA->PJM CLTF 1.5 MW 1.5 MW
MEC LTFEXP_MEC->PJM CLTF 1.53 MW 1.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.1 MW 0.1 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 3.63 MW 3.63 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.18 MW 0.18 MW

Details for 6FORK UNION-6CUNNING 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2027_SRT-A-2


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6FORK UNION-6CUNNING 230.0 kV Ckt 1 line
313707 to 313373 ckt 1
Contingency Name:
DVP_P1-2: LN 2027_SRT-A-2
CONTINGENCY 'DVP_P1-2: LN 2027_SRT-A-2'
 OPEN BRANCH FROM BUS 314322 TO BUS 314333 CKT 1   /*6MDLTHAN     230.0 - 6POWHATN     230.0
 OPEN BRANCH FROM BUS 314333 TO BUS 316335 CKT 1   /*6POWHATN     230.0 - AC2-165 TAP  230.0
 OPEN BUS 314333                                   /*6POWHATN     230.0
 OPEN BUS 316258                                   /*AE1-075 C    230.0
 OPEN BUS 316313                                   /*AB2-026 C    230.0
 OPEN BUS 316405                                   /*AF2-144 C    230.0
 OPEN BUS 923862                                   /*AB2-026 E    230.0
 OPEN BUS 938562                                   /*AE1-075 E    230.0
 OPEN BUS 958502                                   /*AF2-144 E    230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 103.11 %
Rating: 661.76 MVA
Rating Type: B
MVA to Mitigate: 682.37 MVA
MW Contribution: 3.06 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 2.4 MW 2.4 MW
963171 AG1-166 C 80/20 1.33 MW 1.33 MW
963181 AG1-167 C 80/20 1.0 MW 1.0 MW
963191 AG1-168 C 80/20 1.0 MW 1.0 MW
964791 AG1-342 C 80/20 2.15 MW 2.15 MW
966251 AG1-494 C 80/20 1.66 MW 1.66 MW
966621 AG1-532 C 80/20 0.42 MW 0.42 MW
313853 3PONTONDP 80/20 0.89 MW 0.89 MW
314429 3JTRSVLE 80/20 0.55 MW 0.55 MW
314704 3LAWRENC 80/20 0.13 MW 0.13 MW
315153 1CLOVER1 80/20 6.44 MW 6.44 MW
315154 1CLOVER2 80/20 6.38 MW 6.38 MW
315158 1KERR 1 80/20 0.22 MW 0.22 MW
315159 1KERR 2 80/20 0.61 MW 0.61 MW
315160 1KERR 3 80/20 0.61 MW 0.61 MW
315161 1KERR 4 80/20 0.61 MW 0.61 MW
315162 1KERR 5 80/20 0.61 MW 0.61 MW
942751 AE2-291 C 80/20 3.58 MW 3.58 MW
959311 AF2-222 C 80/20 18.39 MW 18.39 MW
960061 AF2-297 C 80/20 3.9 MW 3.9 MW
960081 AF2-299 C 80/20 0.56 MW 0.56 MW
315163 1KERR 6 80/20 0.61 MW 0.61 MW
315164 1KERR 7 80/20 0.61 MW 0.61 MW
315266 1PLYWOOD A 80/20 0.64 MW 0.64 MW
316118 AC1-105 C 80/20 0.51 MW 0.51 MW
316129 AC1-054 C 80/20 0.52 MW 0.52 MW
316131 AB2-060 C 80/20 1.14 MW 1.14 MW
938371 AE1-056 C 80/20 9.25 MW 9.25 MW
939181 AE1-148 C 80/20 5.2 MW 5.2 MW
941011 AE2-092 C 80/20 22.97 MW 22.97 MW
946281 AF1-292 C 80/20 0.46 MW 0.46 MW
946301 AF1-294 C 80/20 4.94 MW 4.94 MW
957481 AF2-042 C 80/20 25.79 MW 25.79 MW
958131 AF2-107 C 80/20 4.63 MW 4.63 MW
958211 AF2-115 C 80/20 3.0 MW 3.0 MW
315191 1BEARGRDN G1 80/20 16.68 MW 16.68 MW
315192 1BEARGRDN G2 80/20 16.68 MW 16.68 MW
936261 AD2-033 C 80/20 13.05 MW 13.05 MW
934621 AD1-088 C 80/20 8.19 MW 8.19 MW
315193 1BEARGRDN S1 80/20 21.59 MW 21.59 MW
316003 AC1-222 C 80/20 0.49 MW 0.49 MW
316034 AC1-036 C 80/20 0.25 MW 0.25 MW
316222 AC1-221 C 80/20 0.56 MW 0.56 MW
316237 AB2-079 C O1 80/20 0.24 MW 0.24 MW
316238 AB2-078 C O1 80/20 0.24 MW 0.24 MW
316239 AB2-077 C O1 80/20 0.24 MW 0.24 MW
316248 AF1-058 C 80/20 0.16 MW 0.16 MW
316283 AC2-100 C 80/20 0.44 MW 0.44 MW
316322 AB2-045 C 80/20 0.79 MW 0.79 MW
316336 AC2-165 C 80/20 30.63 MW 30.63 MW
962751 AG1-124 C 80/20 3.06 MW 3.06 MW
313527 AB2-043 C 80/20 0.38 MW 0.38 MW
316087 AB2-174 C 80/20 0.35 MW 0.35 MW
316123 AC1-075 C 80/20 0.39 MW 0.39 MW
316205 AC1-080 C 80/20 0.13 MW 0.13 MW
962491 AG1-098 C 80/20 7.77 MW 7.77 MW
962561 AG1-105 C 80/20 5.58 MW 5.58 MW
964241 AG1-285 C 80/20 10.76 MW 10.76 MW
934611 AD1-087 C 80/20 0.63 MW 0.63 MW
935171 AD1-152 C 80/20 0.65 MW 0.65 MW
937481 AD2-202 C 80/20 0.18 MW 0.18 MW
938821 AE1-108 C 80/20 31.7 MW 31.7 MW
942461 AE2-259 C 80/20 16.91 MW 16.91 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.19 MW 3.19 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.95 MW 3.95 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 22.9 MW 22.9 MW
NY PJM->LTFIMP_NY CLTF 0.41 MW 0.41 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.15 MW 0.15 MW
WEC LTFEXP_WEC->PJM CLTF 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 2.87 MW 2.87 MW
TVA LTFEXP_TVA->PJM CLTF 1.18 MW 1.18 MW
MEC LTFEXP_MEC->PJM CLTF 0.56 MW 0.56 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.51 MW 1.51 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.37 MW 1.37 MW

Details for 6CUNNING-6MTEAGLE 230.0 kV Ckt 1 line l/o DVP_P1-2: LN 2027_SRT-A-2


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
6CUNNING-6MTEAGLE 230.0 kV Ckt 1 line
313373 to 314765 ckt 1
Contingency Name:
DVP_P1-2: LN 2027_SRT-A-2
CONTINGENCY 'DVP_P1-2: LN 2027_SRT-A-2'
 OPEN BRANCH FROM BUS 314322 TO BUS 314333 CKT 1   /*6MDLTHAN     230.0 - 6POWHATN     230.0
 OPEN BRANCH FROM BUS 314333 TO BUS 316335 CKT 1   /*6POWHATN     230.0 - AC2-165 TAP  230.0
 OPEN BUS 314333                                   /*6POWHATN     230.0
 OPEN BUS 316258                                   /*AE1-075 C    230.0
 OPEN BUS 316313                                   /*AB2-026 C    230.0
 OPEN BUS 316405                                   /*AF2-144 C    230.0
 OPEN BUS 923862                                   /*AB2-026 E    230.0
 OPEN BUS 938562                                   /*AE1-075 E    230.0
 OPEN BUS 958502                                   /*AF2-144 E    230.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 100.45 %
Rating: 661.76 MVA
Rating Type: B
MVA to Mitigate: 664.72 MVA
MW Contribution: 3.06 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961791 AG1-021 C 80/20 2.4 MW 2.4 MW
963171 AG1-166 C 80/20 1.33 MW 1.33 MW
963181 AG1-167 C 80/20 1.0 MW 1.0 MW
963191 AG1-168 C 80/20 1.0 MW 1.0 MW
964791 AG1-342 C 80/20 2.15 MW 2.15 MW
966251 AG1-494 C 80/20 1.66 MW 1.66 MW
966621 AG1-532 C 80/20 0.42 MW 0.42 MW
313853 3PONTONDP 80/20 0.89 MW 0.89 MW
314429 3JTRSVLE 80/20 0.55 MW 0.55 MW
314704 3LAWRENC 80/20 0.13 MW 0.13 MW
315153 1CLOVER1 80/20 6.44 MW 6.44 MW
315154 1CLOVER2 80/20 6.38 MW 6.38 MW
315158 1KERR 1 80/20 0.22 MW 0.22 MW
315159 1KERR 2 80/20 0.61 MW 0.61 MW
315160 1KERR 3 80/20 0.61 MW 0.61 MW
315161 1KERR 4 80/20 0.61 MW 0.61 MW
315162 1KERR 5 80/20 0.61 MW 0.61 MW
942751 AE2-291 C 80/20 3.58 MW 3.58 MW
959311 AF2-222 C 80/20 18.39 MW 18.39 MW
960061 AF2-297 C 80/20 3.9 MW 3.9 MW
960081 AF2-299 C 80/20 0.56 MW 0.56 MW
315163 1KERR 6 80/20 0.61 MW 0.61 MW
315164 1KERR 7 80/20 0.61 MW 0.61 MW
315266 1PLYWOOD A 80/20 0.64 MW 0.64 MW
316118 AC1-105 C 80/20 0.51 MW 0.51 MW
316129 AC1-054 C 80/20 0.52 MW 0.52 MW
316131 AB2-060 C 80/20 1.14 MW 1.14 MW
938371 AE1-056 C 80/20 9.25 MW 9.25 MW
939181 AE1-148 C 80/20 5.2 MW 5.2 MW
941011 AE2-092 C 80/20 22.97 MW 22.97 MW
946281 AF1-292 C 80/20 0.46 MW 0.46 MW
946301 AF1-294 C 80/20 4.94 MW 4.94 MW
957481 AF2-042 C 80/20 25.79 MW 25.79 MW
958131 AF2-107 C 80/20 4.63 MW 4.63 MW
958211 AF2-115 C 80/20 3.0 MW 3.0 MW
315191 1BEARGRDN G1 80/20 16.68 MW 16.68 MW
315192 1BEARGRDN G2 80/20 16.68 MW 16.68 MW
936261 AD2-033 C 80/20 13.05 MW 13.05 MW
934621 AD1-088 C 80/20 8.19 MW 8.19 MW
315193 1BEARGRDN S1 80/20 21.59 MW 21.59 MW
316003 AC1-222 C 80/20 0.49 MW 0.49 MW
316034 AC1-036 C 80/20 0.25 MW 0.25 MW
316222 AC1-221 C 80/20 0.56 MW 0.56 MW
316237 AB2-079 C O1 80/20 0.24 MW 0.24 MW
316238 AB2-078 C O1 80/20 0.24 MW 0.24 MW
316239 AB2-077 C O1 80/20 0.24 MW 0.24 MW
316248 AF1-058 C 80/20 0.16 MW 0.16 MW
316283 AC2-100 C 80/20 0.44 MW 0.44 MW
316322 AB2-045 C 80/20 0.79 MW 0.79 MW
316336 AC2-165 C 80/20 30.63 MW 30.63 MW
962751 AG1-124 C 80/20 3.06 MW 3.06 MW
313527 AB2-043 C 80/20 0.38 MW 0.38 MW
316087 AB2-174 C 80/20 0.35 MW 0.35 MW
316123 AC1-075 C 80/20 0.39 MW 0.39 MW
316205 AC1-080 C 80/20 0.13 MW 0.13 MW
962491 AG1-098 C 80/20 7.77 MW 7.77 MW
962561 AG1-105 C 80/20 5.58 MW 5.58 MW
964241 AG1-285 C 80/20 10.76 MW 10.76 MW
934611 AD1-087 C 80/20 0.63 MW 0.63 MW
935171 AD1-152 C 80/20 0.65 MW 0.65 MW
937481 AD2-202 C 80/20 0.18 MW 0.18 MW
938821 AE1-108 C 80/20 31.7 MW 31.7 MW
942461 AE2-259 C 80/20 16.91 MW 16.91 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.19 MW 3.19 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.95 MW 3.95 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 22.9 MW 22.9 MW
NY PJM->LTFIMP_NY CLTF 0.41 MW 0.41 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.15 MW 0.15 MW
WEC LTFEXP_WEC->PJM CLTF 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 2.87 MW 2.87 MW
TVA LTFEXP_TVA->PJM CLTF 1.18 MW 1.18 MW
MEC LTFEXP_MEC->PJM CLTF 0.56 MW 0.56 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.51 MW 1.51 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.03 MW 0.03 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.37 MW 1.37 MW

Details for 3BREMO-3FORK UNION 115.0 kV Ckt 2 line l/o DVP_P4-3: SX32_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3BREMO-3FORK UNION 115.0 kV Ckt 2 line
314744 to 313708 ckt 2
Contingency Name:
DVP_P4-3: SX32_SRT-A
CONTINGENCY 'DVP_P4-3: SX32_SRT-A'
 OPEN BRANCH FROM BUS 313708 TO BUS 314744 CKT 1   /*3FORK UNION  115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 313874 CKT 1   /*3COBBS CREEK 115.0 - 3DUNCAN STOR 115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 314762 CKT 1   /*3COBBS CREEK 115.0 - 3JAMES R     115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 313875 CKT 1   /*3DUNCAN STOR 115.0 - 3TRICESLK    115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 314744 CKT 1   /*3DUNCAN STOR 115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BUS 313871                                   /*3COBBS CREEK 115.0
 OPEN BUS 313874                                   /*3DUNCAN STOR 115.0
 OPEN BUS 313875                                   /*3TRICESLK    115.0
 OPEN BUS 314762                                   /*3JAMES R     115.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 104.02 %
Rating: 165.0 MVA
Rating Type: C
MVA to Mitigate: 171.64 MVA
MW Contribution: 9.39 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.0 MW 3.0 MW
966252 AG1-494 E 50/50 4.49 MW 4.49 MW
941011 AE2-092 C Adder -8.37 MW -7.11 MW
958131 AF2-107 C 50/50 8.45 MW 8.45 MW
958132 AF2-107 E 50/50 4.63 MW 4.63 MW
962751 AG1-124 C 50/50 5.53 MW 5.53 MW
962752 AG1-124 E 50/50 3.86 MW 3.86 MW
938821 AE1-108 C 50/50 58.27 MW 58.27 MW
938822 AE1-108 E 50/50 27.8 MW 27.8 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 7.39 MW 7.39 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.12 MW 3.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.33 MW 3.33 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.28 MW 0.28 MW
NY PJM->LTFIMP_NY CLTF 0.11 MW 0.11 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.29 MW 0.29 MW
WEC LTFEXP_WEC->PJM CLTF 0.15 MW 0.15 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 0.7 MW 0.7 MW
MEC LTFEXP_MEC->PJM CLTF 0.73 MW 0.73 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.84 MW 0.84 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.75 MW 1.75 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for 3BREMO-3FORK UNION 115.0 kV Ckt 2 line l/o DVP_P2-2: BREMO B4_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3BREMO-3FORK UNION 115.0 kV Ckt 2 line
314744 to 313708 ckt 2
Contingency Name:
DVP_P2-2: BREMO B4_SRT-A
CONTINGENCY 'DVP_P2-2: BREMO B4_SRT-A'
 OPEN BRANCH FROM BUS 313708 TO BUS 314744 CKT 1   /*3FORK UNION  115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 313874 CKT 1   /*3COBBS CREEK 115.0 - 3DUNCAN STOR 115.0
 OPEN BRANCH FROM BUS 313871 TO BUS 314762 CKT 1   /*3COBBS CREEK 115.0 - 3JAMES R     115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 313875 CKT 1   /*3DUNCAN STOR 115.0 - 3TRICESLK    115.0
 OPEN BRANCH FROM BUS 313874 TO BUS 314744 CKT 1   /*3DUNCAN STOR 115.0 - 3BREMO       115.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BUS 313871                                   /*3COBBS CREEK 115.0
 OPEN BUS 313874                                   /*3DUNCAN STOR 115.0
 OPEN BUS 313875                                   /*3TRICESLK    115.0
 OPEN BUS 314762                                   /*3JAMES R     115.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 104.03 %
Rating: 165.0 MVA
Rating Type: C
MVA to Mitigate: 171.65 MVA
MW Contribution: 9.39 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.0 MW 3.0 MW
966252 AG1-494 E 50/50 4.49 MW 4.49 MW
941011 AE2-092 C Adder -8.37 MW -7.11 MW
958131 AF2-107 C 50/50 8.45 MW 8.45 MW
958132 AF2-107 E 50/50 4.63 MW 4.63 MW
962751 AG1-124 C 50/50 5.53 MW 5.53 MW
962752 AG1-124 E 50/50 3.86 MW 3.86 MW
938821 AE1-108 C 50/50 58.27 MW 58.27 MW
938822 AE1-108 E 50/50 27.8 MW 27.8 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 7.39 MW 7.39 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.12 MW 3.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.33 MW 3.33 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.28 MW 0.28 MW
NY PJM->LTFIMP_NY CLTF 0.11 MW 0.11 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.29 MW 0.29 MW
WEC LTFEXP_WEC->PJM CLTF 0.15 MW 0.15 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 0.7 MW 0.7 MW
MEC LTFEXP_MEC->PJM CLTF 0.73 MW 0.73 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.84 MW 0.84 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.75 MW 1.75 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
AEP_P1-2_242515_248184_SRT-A
CONTINGENCY 'AEP_P1-2_242515_248184_SRT-A'
 OPEN BRANCH FROM BUS 242515 TO BUS 248184 CKT 1   /*05JOSHUA     765.0 - 05YEAT7      765.0
END
OP AC 112.94 % 167.0 B 188.61 10.24
AEP 05JOSHUA-05JOSHUA_XFL 138.0 kV Ckt 1 line
242688 to 247670 ckt 1
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
OP AC 100.49 % 747.0 B 750.68 44.86

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o AEP_P1-2_242515_248184_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
AEP_P1-2_242515_248184_SRT-A
CONTINGENCY 'AEP_P1-2_242515_248184_SRT-A'
 OPEN BRANCH FROM BUS 242515 TO BUS 248184 CKT 1   /*05JOSHUA     765.0 - 05YEAT7      765.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 112.94 %
Rating: 167.0 MVA
Rating Type: B
MVA to Mitigate: 188.61 MVA
MW Contribution: 10.24 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.27 MW 3.27 MW
966252 AG1-494 E 50/50 4.9 MW 4.9 MW
941011 AE2-092 C Adder -5.43 MW -4.62 MW
958131 AF2-107 C 50/50 9.2 MW 9.2 MW
958132 AF2-107 E 50/50 5.04 MW 5.04 MW
962751 AG1-124 C 50/50 6.03 MW 6.03 MW
962752 AG1-124 E 50/50 4.21 MW 4.21 MW
938821 AE1-108 C 50/50 63.45 MW 63.45 MW
938822 AE1-108 E 50/50 30.27 MW 30.27 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.2 MW 8.2 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.44 MW 3.44 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.5 MW 3.5 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.3 MW 0.3 MW
NY PJM->LTFIMP_NY CLTF 0.12 MW 0.12 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.33 MW 0.33 MW
WEC LTFEXP_WEC->PJM CLTF 0.17 MW 0.17 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.11 MW 0.11 MW
TVA LTFEXP_TVA->PJM CLTF 0.77 MW 0.77 MW
MEC LTFEXP_MEC->PJM CLTF 0.81 MW 0.81 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.92 MW 0.92 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.93 MW 1.93 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for 05JOSHUA-05JOSHUA_XFL 138.0 kV Ckt 1 line l/o AEP_P1-2_#3174_6_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05JOSHUA-05JOSHUA_XFL 138.0 kV Ckt 1 line
242688 to 247670 ckt 1
Contingency Name:
AEP_P1-2_#3174_6_SRT-A
CONTINGENCY 'AEP_P1-2_#3174_6_SRT-A'
 OPEN BRANCH FROM BUS 242512 TO BUS 242515 CKT 1   /*05CLOVRD     765.0 - 05JOSHUA     765.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.49 %
Rating: 747.0 MVA
Rating Type: B
MVA to Mitigate: 750.68 MVA
MW Contribution: 44.86 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 8.97 MW 8.97 MW
966252 AG1-494 E 50/50 13.45 MW 13.45 MW
247284 05LEESVG 50/50 1.98 MW 1.98 MW
315156 1HALLBR1 50/50 2.39 MW 2.39 MW
926646 AC1-145 E 50/50 4.93 MW 4.93 MW
942671 AE2-283 C 50/50 8.1 MW 8.1 MW
942672 AE2-283 E 50/50 7.23 MW 7.23 MW
942751 AE2-291 C 50/50 11.6 MW 11.6 MW
942752 AE2-291 E 50/50 7.73 MW 7.73 MW
242889 05REUSENS 50/50 0.3 MW 0.3 MW
940081 AE1-250 C 50/50 11.28 MW 11.28 MW
940082 AE1-250 E 50/50 7.52 MW 7.52 MW
941801 AE2-185 C 50/50 10.41 MW 10.41 MW
941802 AE2-185 E 50/50 6.94 MW 6.94 MW
941821 AE2-187 C 50/50 10.41 MW 10.41 MW
941822 AE2-187 E 50/50 4.63 MW 4.63 MW
958131 AF2-107 C 50/50 12.29 MW 12.29 MW
958132 AF2-107 E 50/50 6.74 MW 6.74 MW
246843 05SMG1 50/50 2.19 MW 2.19 MW
246844 05SMG2 50/50 6.03 MW 6.03 MW
246845 05SMG3 50/50 3.7 MW 3.7 MW
246846 05SMG4 50/50 6.03 MW 6.03 MW
246847 05SMG5 50/50 2.29 MW 2.29 MW
926055 AC1-083 E 50/50 11.9 MW 11.9 MW
927264 AC1-222 E Adder 2.17 MW 1.84 MW
962751 AG1-124 C 50/50 26.42 MW 26.42 MW
962752 AG1-124 E 50/50 18.44 MW 18.44 MW
316217 AC1-145 C 50/50 0.9 MW 0.9 MW
270197 AC1-083 C 50/50 1.19 MW 1.19 MW
270173 AC1-122 C 50/50 2.77 MW 2.77 MW
926516 AC1-122_E 50/50 7.96 MW 7.96 MW
316197 AC1-042 C 50/50 0.75 MW 0.75 MW
925665 AC1-042 E 50/50 7.53 MW 7.53 MW
316123 AC1-075 C 50/50 1.02 MW 1.02 MW
925997 AC1-075 E 50/50 3.55 MW 3.55 MW
316205 AC1-080 C 50/50 0.34 MW 0.34 MW
926024 AC1-080 E 50/50 1.18 MW 1.18 MW
938821 AE1-108 C 50/50 13.78 MW 13.78 MW
938822 AE1-108 E 50/50 6.58 MW 6.58 MW
940601 AE2-047 C Adder 2.13 MW 1.81 MW
940602 AE2-047 E Adder 1.16 MW 0.98 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 30.12 MW 30.12 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 14.44 MW 14.44 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 29.54 MW 29.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 1.95 MW 1.95 MW
NY PJM->LTFIMP_NY CLTF 0.85 MW 0.85 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.2 MW 1.2 MW
WEC LTFEXP_WEC->PJM CLTF 0.61 MW 0.61 MW
CPLE LTFEXP_CPLE->PJM CLTF 2.67 MW 2.67 MW
TVA LTFEXP_TVA->PJM CLTF 3.45 MW 3.45 MW
MEC LTFEXP_MEC->PJM CLTF 3.15 MW 3.15 MW
LAGN LTFEXP_LAGN->PJM CLTF 4.19 MW 4.19 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.21 MW 0.21 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 12.4 MW 12.4 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.28 MW 1.28 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP/DVP AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Base Case OP AC 110.74 % 167.0 A 184.94 10.05
DVP AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line
316000 to 313168 ckt 1
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
OP AC 105.86 % 285.76 B 302.51 5.94
DVP 3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line
313168 to 314696 ckt 1
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
OP AC 105.68 % 285.76 B 302.0 5.94
DVP 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line
314901 to 314991 ckt 1
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
OP AC 104.77 % 3220.44 B 3374.15 15.23
DVP 8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line
314991 to 314926 ckt 1
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
OP AC 104.55 % 3220.44 B 3366.96 15.23

Details for AE1-108 TP-4BREMO 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP/DVP
Facility Description:
AE1-108 TP-4BREMO 138.0 kV Ckt 1 line
938820 to 314746 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 110.74 %
Rating: 167.0 MVA
Rating Type: A
MVA to Mitigate: 184.94 MVA
MW Contribution: 10.05 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C 50/50 3.2 MW 3.2 MW
966252 AG1-494 E 50/50 4.8 MW 4.8 MW
941011 AE2-092 C Adder -6.27 MW -5.33 MW
958131 AF2-107 C 50/50 9.03 MW 9.03 MW
958132 AF2-107 E 50/50 4.95 MW 4.95 MW
962751 AG1-124 C 50/50 5.92 MW 5.92 MW
962752 AG1-124 E 50/50 4.13 MW 4.13 MW
938821 AE1-108 C 50/50 62.27 MW 62.27 MW
938822 AE1-108 E 50/50 29.71 MW 29.71 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 8.0 MW 8.0 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.34 MW 3.34 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 3.34 MW 3.34 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.29 MW 0.29 MW
NY PJM->LTFIMP_NY CLTF 0.12 MW 0.12 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.32 MW 0.32 MW
WEC LTFEXP_WEC->PJM CLTF 0.16 MW 0.16 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.1 MW 0.1 MW
TVA LTFEXP_TVA->PJM CLTF 0.75 MW 0.75 MW
MEC LTFEXP_MEC->PJM CLTF 0.79 MW 0.79 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.89 MW 0.89 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.85 MW 1.85 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.05 MW 0.05 MW

Details for AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line l/o AEP_P1-2_#5366_42_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
AC1-222 TAP-3HUBER DP 115.0 kV Ckt 1 line
316000 to 313168 ckt 1
Contingency Name:
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.86 %
Rating: 285.76 MVA
Rating Type: B
MVA to Mitigate: 302.51 MVA
MW Contribution: 5.94 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 1.3 MW 1.11 MW
966252 AG1-494 E Adder 1.96 MW 1.66 MW
247284 05LEESVG 50/50 1.33 MW 1.33 MW
315156 1HALLBR1 50/50 2.24 MW 2.24 MW
926646 AC1-145 E 50/50 3.8 MW 3.8 MW
942671 AE2-283 C 50/50 6.24 MW 6.24 MW
942672 AE2-283 E 50/50 5.57 MW 5.57 MW
942751 AE2-291 C 50/50 30.94 MW 30.94 MW
942752 AE2-291 E 50/50 20.63 MW 20.63 MW
940081 AE1-250 C 50/50 10.19 MW 10.19 MW
940082 AE1-250 E 50/50 6.79 MW 6.79 MW
941801 AE2-185 C 50/50 8.02 MW 8.02 MW
941802 AE2-185 E 50/50 5.35 MW 5.35 MW
941821 AE2-187 C 50/50 8.02 MW 8.02 MW
941822 AE2-187 E 50/50 3.56 MW 3.56 MW
246843 05SMG1 50/50 1.2 MW 1.2 MW
246844 05SMG2 50/50 3.3 MW 3.3 MW
246845 05SMG3 50/50 2.03 MW 2.03 MW
246846 05SMG4 50/50 3.3 MW 3.3 MW
246847 05SMG5 50/50 1.25 MW 1.25 MW
316003 AC1-222 C 50/50 5.01 MW 5.01 MW
926055 AC1-083 E 50/50 8.42 MW 8.42 MW
927264 AC1-222 E 50/50 20.52 MW 20.52 MW
962751 AG1-124 C Adder 3.5 MW 2.98 MW
962752 AG1-124 E Adder 2.44 MW 2.08 MW
316217 AC1-145 C 50/50 0.69 MW 0.69 MW
270197 AC1-083 C 50/50 0.84 MW 0.84 MW
270173 AC1-122 C 50/50 0.89 MW 0.89 MW
926516 AC1-122_E 50/50 2.58 MW 2.58 MW
316197 AC1-042 C 50/50 0.58 MW 0.58 MW
925665 AC1-042 E 50/50 5.8 MW 5.8 MW
316123 AC1-075 C 50/50 3.59 MW 3.59 MW
925997 AC1-075 E 50/50 12.49 MW 12.49 MW
316205 AC1-080 C 50/50 1.2 MW 1.2 MW
926024 AC1-080 E 50/50 4.14 MW 4.14 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.37 MW 6.37 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.46 MW 1.46 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.26 MW 0.26 MW
NY PJM->LTFIMP_NY CLTF 0.1 MW 0.1 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 0.13 MW 0.13 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.72 MW 0.72 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.25 MW 0.25 MW
TVA LTFEXP_TVA->PJM CLTF 0.19 MW 0.19 MW
MEC LTFEXP_MEC->PJM CLTF 0.53 MW 0.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.15 MW 0.15 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.61 MW 1.61 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.26 MW 1.26 MW

Details for 3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line l/o AEP_P1-2_#5366_42_SRT-A-1


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
3HUBER DP-3SEDGE HILL 115.0 kV Ckt 1 line
313168 to 314696 ckt 1
Contingency Name:
AEP_P1-2_#5366_42_SRT-A-1
CONTINGENCY 'AEP_P1-2_#5366_42_SRT-A-1'
 OPEN BRANCH FROM BUS 242549 TO BUS 242632 CKT 1    /*05BANSTR     138.0 - 05EDAN 2     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 314668 CKT Z1   /*05BANSTR     138.0 - 4BANISTR     138.0
 OPEN BRANCH FROM BUS 242549 TO BUS 940080 CKT 1    /*05BANSTR     138.0 - AE1-250 TP   138.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 105.68 %
Rating: 285.76 MVA
Rating Type: B
MVA to Mitigate: 302.0 MVA
MW Contribution: 5.94 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 1.3 MW 1.11 MW
966252 AG1-494 E Adder 1.96 MW 1.66 MW
247284 05LEESVG 50/50 1.33 MW 1.33 MW
315156 1HALLBR1 50/50 2.24 MW 2.24 MW
926646 AC1-145 E 50/50 3.8 MW 3.8 MW
942671 AE2-283 C 50/50 6.24 MW 6.24 MW
942672 AE2-283 E 50/50 5.57 MW 5.57 MW
942751 AE2-291 C 50/50 30.94 MW 30.94 MW
942752 AE2-291 E 50/50 20.63 MW 20.63 MW
940081 AE1-250 C 50/50 10.19 MW 10.19 MW
940082 AE1-250 E 50/50 6.79 MW 6.79 MW
941801 AE2-185 C 50/50 8.02 MW 8.02 MW
941802 AE2-185 E 50/50 5.35 MW 5.35 MW
941821 AE2-187 C 50/50 8.02 MW 8.02 MW
941822 AE2-187 E 50/50 3.56 MW 3.56 MW
246843 05SMG1 50/50 1.2 MW 1.2 MW
246844 05SMG2 50/50 3.3 MW 3.3 MW
246845 05SMG3 50/50 2.03 MW 2.03 MW
246846 05SMG4 50/50 3.3 MW 3.3 MW
246847 05SMG5 50/50 1.25 MW 1.25 MW
316003 AC1-222 C 50/50 5.01 MW 5.01 MW
926055 AC1-083 E 50/50 8.42 MW 8.42 MW
927264 AC1-222 E 50/50 20.52 MW 20.52 MW
962751 AG1-124 C Adder 3.5 MW 2.98 MW
962752 AG1-124 E Adder 2.44 MW 2.08 MW
316217 AC1-145 C 50/50 0.69 MW 0.69 MW
270197 AC1-083 C 50/50 0.84 MW 0.84 MW
270173 AC1-122 C 50/50 0.89 MW 0.89 MW
926516 AC1-122_E 50/50 2.58 MW 2.58 MW
316197 AC1-042 C 50/50 0.58 MW 0.58 MW
925665 AC1-042 E 50/50 5.8 MW 5.8 MW
316123 AC1-075 C 50/50 3.59 MW 3.59 MW
925997 AC1-075 E 50/50 12.49 MW 12.49 MW
316205 AC1-080 C 50/50 1.2 MW 1.2 MW
926024 AC1-080 E 50/50 4.14 MW 4.14 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 6.37 MW 6.37 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 1.46 MW 1.46 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.26 MW 0.26 MW
NY PJM->LTFIMP_NY CLTF 0.1 MW 0.1 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.26 MW 0.26 MW
WEC LTFEXP_WEC->PJM CLTF 0.13 MW 0.13 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.72 MW 0.72 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.25 MW 0.25 MW
TVA LTFEXP_TVA->PJM CLTF 0.19 MW 0.19 MW
MEC LTFEXP_MEC->PJM CLTF 0.53 MW 0.53 MW
LAGN LTFEXP_LAGN->PJM CLTF 0.15 MW 0.15 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.61 MW 1.61 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 1.26 MW 1.26 MW

Details for 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 555_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line
314901 to 314991 ckt 1
Contingency Name:
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.77 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3374.15 MVA
MW Contribution: 15.23 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 3.06 MW 2.6 MW
966252 AG1-494 E Adder 4.6 MW 3.91 MW
926646 AC1-145 E Adder 2.4 MW 2.04 MW
942671 AE2-283 C Adder 3.93 MW 3.34 MW
942672 AE2-283 E Adder 3.51 MW 2.99 MW
943031 AE2-326 C Adder 4.43 MW 3.77 MW
943032 AE2-326 E Adder 2.95 MW 2.51 MW
242889 05REUSENS 50/50 0.12 MW 0.12 MW
244165 05FRIES Adder 0.72 MW 0.61 MW
941801 AE2-185 C Adder 5.06 MW 4.3 MW
941802 AE2-185 E Adder 3.37 MW 2.87 MW
941821 AE2-187 C Adder 5.06 MW 4.3 MW
941822 AE2-187 E Adder 2.25 MW 1.91 MW
958121 AF2-106 C Adder 14.69 MW 12.48 MW
958122 AF2-106 E Adder 9.79 MW 8.32 MW
958131 AF2-107 C Adder 3.77 MW 3.21 MW
958132 AF2-107 E Adder 2.07 MW 1.76 MW
940451 AE2-029 C Adder -4.93 MW -4.19 MW
313738 3CUSHAW 50/50 0.28 MW 0.28 MW
314860 4E MILL 50/50 15.81 MW 15.81 MW
315186 1LOWMORA 50/50 1.29 MW 1.29 MW
315188 1LOWMORC 50/50 1.3 MW 1.3 MW
315201 1BATH 1A 50/50 47.86 MW 47.86 MW
315202 1BATH 2B 50/50 47.86 MW 47.86 MW
315203 1BATH 3C 50/50 47.89 MW 47.89 MW
315204 1BATH 4D 50/50 47.88 MW 47.88 MW
315205 1BATH 5E 50/50 47.94 MW 47.94 MW
315206 1BATH 6F 50/50 48.03 MW 48.03 MW
941671 AE2-166 C Adder 7.02 MW 5.96 MW
941672 AE2-166 E Adder 4.68 MW 3.98 MW
316370 X2-060 E 50/50 9.49 MW 9.49 MW
918234 AA1-038_E 50/50 21.54 MW 21.54 MW
926055 AC1-083 E Adder 9.77 MW 8.3 MW
932996 AC2-123 E Adder 4.3 MW 3.66 MW
962751 AG1-124 C 50/50 8.97 MW 8.97 MW
962752 AG1-124 E 50/50 6.26 MW 6.26 MW
270205 AE1-176 50/50 0.08 MW 0.08 MW
926516 AC1-122_E Adder 4.22 MW 3.59 MW
925665 AC1-042 E Adder 3.66 MW 3.11 MW
937351 AD2-179 C Adder 9.78 MW 8.32 MW
937352 AD2-179 E Adder 6.52 MW 5.54 MW
938742 AE1-100 E Adder 3.01 MW 2.56 MW
941431 AE2-140 C Adder 14.41 MW 12.25 MW
941432 AE2-140 E Adder 9.61 MW 8.16 MW
966391 AG1-508 C Adder 1.29 MW 1.1 MW
966392 AG1-508 E Adder 7.5 MW 6.37 MW
940601 AE2-047 C Adder 3.82 MW 3.24 MW
940602 AE2-047 E Adder 2.07 MW 1.76 MW
315616 AA1-038_C 50/50 3.19 MW 3.19 MW
270167 AD2-205 E Adder 0.65 MW 0.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 88.3 MW 88.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 41.42 MW 41.42 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 58.94 MW 58.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 5.88 MW 5.88 MW
NY PJM->LTFIMP_NY CLTF 2.7 MW 2.7 MW
LGEE LTFEXP_LGEE->PJM CLTF 3.69 MW 3.69 MW
WEC LTFEXP_WEC->PJM CLTF 1.81 MW 1.81 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.38 MW 3.38 MW
TVA LTFEXP_TVA->PJM CLTF 9.84 MW 9.84 MW
MEC LTFEXP_MEC->PJM CLTF 9.24 MW 9.24 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.64 MW 11.64 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.64 MW 0.64 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 37.45 MW 37.45 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.64 MW 1.64 MW

Details for 8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line l/o DVP_P1-2: LN 555_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: DVP
Facility Description:
8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line
314991 to 314926 ckt 1
Contingency Name:
DVP_P1-2: LN 555_SRT-A
CONTINGENCY 'DVP_P1-2: LN 555_SRT-A'
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.55 %
Rating: 3220.44 MVA
Rating Type: B
MVA to Mitigate: 3366.96 MVA
MW Contribution: 15.23 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
966251 AG1-494 C Adder 3.06 MW 2.6 MW
966252 AG1-494 E Adder 4.6 MW 3.91 MW
926646 AC1-145 E Adder 2.4 MW 2.04 MW
942671 AE2-283 C Adder 3.93 MW 3.34 MW
942672 AE2-283 E Adder 3.51 MW 2.99 MW
943031 AE2-326 C Adder 4.43 MW 3.77 MW
943032 AE2-326 E Adder 2.95 MW 2.51 MW
242889 05REUSENS 50/50 0.12 MW 0.12 MW
244165 05FRIES Adder 0.72 MW 0.61 MW
941801 AE2-185 C Adder 5.06 MW 4.3 MW
941802 AE2-185 E Adder 3.37 MW 2.87 MW
941821 AE2-187 C Adder 5.06 MW 4.3 MW
941822 AE2-187 E Adder 2.25 MW 1.91 MW
958121 AF2-106 C Adder 14.69 MW 12.48 MW
958122 AF2-106 E Adder 9.79 MW 8.32 MW
958131 AF2-107 C Adder 3.77 MW 3.21 MW
958132 AF2-107 E Adder 2.07 MW 1.76 MW
940451 AE2-029 C Adder -4.93 MW -4.19 MW
313738 3CUSHAW 50/50 0.28 MW 0.28 MW
314860 4E MILL 50/50 15.81 MW 15.81 MW
315186 1LOWMORA 50/50 1.29 MW 1.29 MW
315188 1LOWMORC 50/50 1.3 MW 1.3 MW
315201 1BATH 1A 50/50 47.86 MW 47.86 MW
315202 1BATH 2B 50/50 47.86 MW 47.86 MW
315203 1BATH 3C 50/50 47.89 MW 47.89 MW
315204 1BATH 4D 50/50 47.88 MW 47.88 MW
315205 1BATH 5E 50/50 47.94 MW 47.94 MW
315206 1BATH 6F 50/50 48.03 MW 48.03 MW
941671 AE2-166 C Adder 7.02 MW 5.96 MW
941672 AE2-166 E Adder 4.68 MW 3.98 MW
316370 X2-060 E 50/50 9.49 MW 9.49 MW
918234 AA1-038_E 50/50 21.54 MW 21.54 MW
926055 AC1-083 E Adder 9.77 MW 8.3 MW
932996 AC2-123 E Adder 4.3 MW 3.66 MW
962751 AG1-124 C 50/50 8.97 MW 8.97 MW
962752 AG1-124 E 50/50 6.26 MW 6.26 MW
270205 AE1-176 50/50 0.08 MW 0.08 MW
926516 AC1-122_E Adder 4.22 MW 3.59 MW
925665 AC1-042 E Adder 3.66 MW 3.11 MW
937351 AD2-179 C Adder 9.78 MW 8.32 MW
937352 AD2-179 E Adder 6.52 MW 5.54 MW
938742 AE1-100 E Adder 3.01 MW 2.56 MW
941431 AE2-140 C Adder 14.41 MW 12.25 MW
941432 AE2-140 E Adder 9.61 MW 8.16 MW
966391 AG1-508 C Adder 1.29 MW 1.1 MW
966392 AG1-508 E Adder 7.5 MW 6.37 MW
940601 AE2-047 C Adder 3.82 MW 3.24 MW
940602 AE2-047 E Adder 2.07 MW 1.76 MW
315616 AA1-038_C 50/50 3.19 MW 3.19 MW
270167 AD2-205 E Adder 0.65 MW 0.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 88.3 MW 88.3 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 41.42 MW 41.42 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 58.94 MW 58.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 5.88 MW 5.88 MW
NY PJM->LTFIMP_NY CLTF 2.7 MW 2.7 MW
LGEE LTFEXP_LGEE->PJM CLTF 3.69 MW 3.69 MW
WEC LTFEXP_WEC->PJM CLTF 1.81 MW 1.81 MW
CPLE LTFEXP_CPLE->PJM CLTF 3.38 MW 3.38 MW
TVA LTFEXP_TVA->PJM CLTF 9.84 MW 9.84 MW
MEC LTFEXP_MEC->PJM CLTF 9.24 MW 9.24 MW
LAGN LTFEXP_LAGN->PJM CLTF 11.64 MW 11.64 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.64 MW 0.64 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 37.45 MW 37.45 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 1.64 MW 1.64 MW

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios:

 

  • Scenario 1 - TC1 Project Impacts;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

 

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1. The result is detailed in the following table:

Short Circuit Analysis

 

 

 

 

 

 

 

Bus Name

Breaker

Interrupting Capability (Amps)

Duty Percent TC1 Phase 3 - Scenario 2 Topology Upgrades (%)

Duty Percent TC1 Phase 3 - Scenario 2 No Topology Upgrades (%)

Duty Percent Difference (%)

Reinforcement

Projected In Service Date (ISD)

GOODING 345 kV

270769

57267

100.77%

98.71%

2.06%

s3011

12/31/2028

 

 

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests AG1-124 and AG1-494 in PJM Transition Cycle 1, Cluster 54 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 54 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 54 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 54 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 54 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 111 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 54 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 54 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-124 and AG1-494 meet the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed forinverter-based renewable generation units which are within one (1) substation away AG1-124 and AG1-494. CSCR results are summarized in Table 4 to Table 9 and revealed a minimum and maximum CSCR values of 3.99 for P1.16 and 6.08 for P4.21 & P4.22, respectively.

 

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e. fault where spike is observed]). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.” 

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-494 GEN, and AG1-124 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

Non-queue project AE1-108:

 

In the previous phase (phase 2) of the dynamic simulation analysis for Cluster 54, the relay pick-up time of AE1-108, instance 93882501 (VTGTPAT) was adjusted to 0.25 seconds to prevent tripping under one contingency. For this phase of the study (phase 3) the relay pick-up time for 93882501 (VTGTPAT) of AE1-108 was restored to original setting 0.0 seconds. No trippings of this unit were observed in this study.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 54 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

54

AG1-124

Solar

AEP

90

90

53.01

Gladstone 138 kV

AG1-494

Battery

AEP

50

50

20

Boxwood-Amherst 138 kV

 

 

 

Reactive Power Analysis

The reactive power capability of AG1-124 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AG1-124 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
AEP n9243.0 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Cost Allocated $3,239,436
Dominion n9146.0 Wreck and rebuild 1.51 miles of 115 kV Line No. 5 between Bremo and Fork Union with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees Celsius. Replace line lead at Bremo. Cost Allocated $2,331,168
Dominion n9138.0 Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. Cost Allocated $1,180,088
Dominion n9250.0 Construct a new 22.59 mile line between Carson and Rawlings Substations. Cost Allocated $1,154,579
Dominion n9630.0 Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. Cost Allocated $950,063
Dominion n8492 Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. Cost Allocated $851,346
Dominion n9267.0 Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. Cost Allocated $485,606
Dominion n9259.0 Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. Cost Allocated $268,712
Dominion n7541 Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. Cost Allocated $241,893
Dominion n8492.1 Two Breaker Additions at Fentress Substation. Cost Allocated $211,804
Dominion n8492.2 Expand Yadkin Substation to accommodate the new 500 kV line. Cost Allocated $172,103
ComEd n9195.0 Install a new 345 kV circuit breaker at Station 12 Dresden. Cost Allocated $54,319
Dominion n6588 Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker. Cost Allocated $18,318
ComEd b3811.1 Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. Contingent $0 N/A
ComEd s3011 Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. Contingent $0 N/A
ComEd b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line Contingent $0 N/A
Dominion b4000.357 Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. Contingent $0 N/A
Dominion b4000.356 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). Contingent $0 N/A
Dominion b4000.355 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). Contingent $0 N/A
Dominion b4000.352 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. Contingent $0 N/A
Dominion b4000.351 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. Contingent $0 N/A
Dominion b4000.350 Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. Contingent $0 N/A
Dominion b4000.349 Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. Contingent $0 N/A
Dominion b4000.348 Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. Contingent $0 N/A
Dominion b4000.346 Cut-in 500kV line from Kraken substation into Yeat substation Contingent $0 N/A
Dominion b4000.345 Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0 N/A
Dominion b4000.344 Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0 N/A
Dominion b4000.342 Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. Contingent $0 N/A
Dominion b4000.341 Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. Contingent $0 N/A
Dominion b4000.325 Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. Contingent $0 N/A
Dominion b3689.2 Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA Contingent $0 N/A
Dominion b4000.103 Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA Contingent $0 N/A
Dominion b3800.405 Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. Contingent $0 N/A
Dominion b3854.1 Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA Contingent $0 N/A
Dominion b4000.108 Carson Sub 230kV - replace 40kA breaker 23872 with 63kA Contingent $0 N/A
Dominion b4000.326 At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. Contingent $0 N/A
Dominion b4000.327 Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. Contingent $0 N/A
Dominion b3800.406 Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. Contingent $0 N/A
Dominion b4000.115 Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA Contingent $0 N/A
Dominion b4000.354 Ladysmith substation breakers replacement: 574T575 and 568T581 Contingent $0 N/A
Dominion b3853.1 Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA Contingent $0 N/A
Dominion b4000.114 Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA Contingent $0 N/A
Dominion b3800.235 Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers Contingent $0 N/A
Dominion b3800.334 Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. Contingent $0 N/A
Dominion b3800.407 Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. Contingent $0 N/A
Dominion b4000.119 Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. Contingent $0 N/A
Dominion b4000.128 North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. Contingent $0 N/A
Dominion b3800.408 Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. Contingent $0 N/A
Dominion s2609.6 Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. Contingent $0 N/A
Dominion s2609.9 Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. Contingent $0 N/A
Dominion b4000.134 Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. Contingent $0 N/A
Dominion b1696 Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 Contingent $0 N/A
Dominion b3800.236 Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. Contingent $0 N/A
Dominion s3047.2 Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. Contingent $0 N/A
Dominion b3800.312 Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. Contingent $0 N/A
Dominion b3800.313 Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. Contingent $0 N/A
Dominion b3800.356 Build a new 500 kV line from Vint Hill to Wishing Star. Contingent $0 N/A
Dominion b3800.357 Build a new 500 kV line from Morrisville to Vint Hill. Contingent $0 N/A
Dominion b3800.354 Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. Contingent $0 N/A
Dominion b3800.335 Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker Contingent $0 N/A
Grand Total: $11,159,435

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n6588
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
n6588 / TC1-PH2-DOM-034
Title
Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Description
Replace 230kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.
Total Cost ($USD)
$1,725,040
Discounted Total Cost ($USD)
$1,725,040
Allocated Cost ($USD)
$18,318
Time Estimate
Dec 01 2028

Contributor

Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $9,757
AE2-185 0.03% $597
AE2-187 0.03% $518
AE2-283 0.03% $526
AE2-291 0.54% $9,277
AF1-123 10.21% $176,104
AF1-124 10.25% $176,739
AF1-125 10.05% $173,379
AF1-294 0.41% $7,047
AF2-035 0.26% $4,527
AF2-042 28.18% $486,093
AF2-046 2.88% $49,766
AF2-115 0.25% $4,292
AF2-120 4.50% $77,663
AF2-222 3.88% $66,923
AF2-297 0.72% $12,360
AG1-008 2.88% $49,766
AG1-021 0.20% $3,433
AG1-082 0.19% $3,231
AG1-098 1.60% $27,651
AG1-105 0.68% $11,763
AG1-124 1.06% $18,318
AG1-135 4.42% $76,186
AG1-146 2.12% $36,633
AG1-147 4.96% $85,476
AG1-154 0.14% $2,384
AG1-166 0.13% $2,249
AG1-167 0.10% $1,687
AG1-168 0.10% $1,687
AG1-285 2.80% $48,263
AG1-342 0.06% $1,087
AG1-494 0.82% $14,097
AG1-536 4.96% $85,562

System Reinforcement: n7812
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7812 / dom-397
Title
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.
Description
Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C.
Total Cost ($USD)
$23,887,052
Discounted Total Cost ($USD)
$9,761,491
Allocated Cost ($USD)
$5,516,195
Time Estimate
43 to 44 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Facility Contingency
4BREMO-AE1-108 TAP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-124 11.1 MW 56.5% $5,516,195
AG1-494 8.5 MW 43.5% $4,245,297

System Reinforcement: n9178.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9178.0 / AEPAPRJV007
Title
Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.
Description
•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design. •Replace 3 structures and 1 floating dead ends along the Reusens – Scottsville – Bremo Bluff line determined in preliminary engineering study.
Total Cost ($USD)
$4,759,000
Discounted Total Cost ($USD)
$4,620,011
Allocated Cost ($USD)
$2,610,757
Time Estimate
29 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Facility Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-124 11.1 MW 56.5% $2,610,757
AG1-494 8.5 MW 43.5% $2,009,254

System Reinforcement: n9146.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9146.0 / TC1-PH1-DOM-004
Title
Wreck and rebuild 1.51 miles of 115 kV Line No. 5 between Bremo and Fork Union with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees Celsius. Replace line lead at Bremo.
Description
Wreck and rebuild 1.51 miles of 115 kV Line No. 5 between Bremo and Fork Union with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees Celsius. Replace line lead at Bremo.
Total Cost ($USD)
$7,535,533
Discounted Total Cost ($USD)
$7,535,533
Allocated Cost ($USD)
$2,331,168
Time Estimate
42 to 43 Months

Contributor

Facility Contingency
3FORK UNION-3BREMO 115.0 kV Ckt 2 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF1-123 CVOW Harpers 230 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-123, AF1-124, AF1-125
6.7 MW 22.2% $1,670,261
AF1-124 CVOW Harpers 230 kV - Dominion: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF1-123, AF1-124, AF1-125
6.8 MW 22.2% $1,675,225
AG1-124 9.4 MW 30.9% $2,331,168
AG1-494 7.5 MW 24.7% $1,858,879

System Reinforcement: n9179.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9179.0 / AEPAPRJV008
Title
Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.
Description
"•Acquire LiDAR data for Scottsville Station to STR 268 of the Reusens – Scottsville - Bremo Bluff line needed for detailed line design. •Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line by installing one floating deadend and replacing one structure"
Total Cost ($USD)
$1,245,000
Discounted Total Cost ($USD)
$1,208,639
Allocated Cost ($USD)
$682,999
Time Estimate
15 Months

ContributorEliminated

Note: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle. However, this project is receiving cost allocation based on its MW contribution to this eliminated reinforcement to fund the topology reinforcements which together alleviated the need for this reinforcement. This project's cost allocation is based on the pro rata share of the MW impacts from all cost allocated contributors multiplied by the relevant regional discount factor listed in the executive summary report.

Since this project contributed to a violation with a reinforcement that was eliminated by the topology changing reinforcements, this project is contingent on all of the topology changing reinforcements within the region in which the eliminated reinforcement belongs.

Facility Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AG1-124 11.1 MW 56.5% $682,999
AG1-494 8.5 MW 43.5% $525,640

System Reinforcement
Type
Load Flow
TO
AEP
RTEP ID / TO ID
(Pending) / NONAEPRJV01
Title
Reinforcement for AE1-108 TP 138 KV to 4BREMO 138 KV ckt 1: Non-AEP Limiting Element.
Description
Non-AEP Limiting Element
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
0 to 1 Months

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
4BREMO-AE1-108 TP 138.0 kV Ckt 1 line (Any)
4BREMO-AE1-108 POI 138.0 kV Ckt 1 line (Any)

System Reinforcement: n9203.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9203.0 / TC1-PH2-DOM-008
Title
Wreck and rebuild 10.74 miles of line 2028 between Fork Union and Cunningham (Grape Vine) with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C.
Description
Wreck and rebuild 10.74 miles of line 2028 between Fork Union and Cunningham (Grape Vine) with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C.
Total Cost ($USD)
$29,539,973
Discounted Total Cost ($USD)
$29,539,973
Allocated Cost ($USD)
$0
Time Estimate
45 to 46 Months

Potential Aggregate ContributorEliminated

Note 1: Based on PJM cost allocation criteria, AG1-124 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-124 could receive cost allocation. Although AG1-124 may not presently have cost responsibility for this upgrade, AG1-124 is a potential Aggregate Pool Contributor.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
6CUNNING-6FORK UNION 230.0 kV Ckt 1 line (Any)
6GRAPEVINE-6FORK UNION 230.0 kV Ckt 1 line (Any)

System Reinforcement: n7569
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7569 / dom-490
Title
Upgrade a 3.78 mile segment of 230kV transmission line 2028 between Mt. Eagle and Grape Vine Substations at structure 2080/73.
Description
Uograde 3.78 miles of transmission line 2028 between Mt. Eagle and Grape Vine with (2) 768.2 ACSS/TW (20/7) "MAUMEE". The segment runs from Mt Eagle to structure 2080/73.
Total Cost ($USD)
$13,360,242
Discounted Total Cost ($USD)
$13,360,242
Allocated Cost ($USD)
$0
Time Estimate
43 to 44 Months

Potential Aggregate ContributorEliminated

Note 1: Based on PJM cost allocation criteria, AG1-124 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG1-124 could receive cost allocation. Although AG1-124 may not presently have cost responsibility for this upgrade, AG1-124 is a potential Aggregate Pool Contributor.

Note 2: The topology changing reinforcements listed in the Cycle executive summary report eliminated the need for this reinforcement and it is no longer required by the Cycle.

Facility Contingency
6CUNNING-6MTEAGLE 230.0 kV Ckt 1 line (Any)
6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line (Any)

System Reinforcement: n9243.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9243.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9243.0 / AEPSERG13
Title
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.
Description
At the Jefferson Station: • Expand the northeast corner of the station • Remove Circuit breaker C1 • Install one (1) new 765/345 kV transformer and associated equipment • Install one (1) new 765 kV circuit breaker with associated control relaying and breaker disconnect switches • Install one (1) new 345 kV circuit breaker with associated control relaying and breaker disconnect switches • Install a new station service center At the Clifty Creek Station: • Extend 345 kV bus 1 and 2 to make room for a new breaker string • Move a section of the 138 kV bus underground to make room for the new breaker string • Relocate circuit breaker S to the new string • Install two (2) new 345 kV circuit breakers on the new string •Remove the existing Jefferson – Clifty Creek 345 kV line •Construct a new Jefferson – Clifty Creek 345 kV double circuit line •Evaluate line settings for all appropriate lines •Install direct fiber relaying between the Jefferson and Clifty Creek station •Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures
Total Cost ($USD)
$200,238,000
Allocated Cost ($USD)
$3,239,436
Time Estimate
55 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 0.2057 % $411,890
AE2-173 0.0788 % $157,788
AE2-223 0.2363 % $473,162
AE2-261 2.3717 % $4,749,045
AF1-088 42.0284 % $84,156,828
AF1-204 2.2821 % $4,569,631
AF2-008 42.0284 % $84,156,828
AF2-225 0.2363 % $473,162
AG1-124 1.6178 % $3,239,450
AG1-226 6.8230 % $13,662,239
AG1-236 0.1693 % $339,003
AG1-374 0.4391 % $879,245
AG1-460 0.2380 % $476,566
AG1-494 1.2451 % $2,493,163

System Reinforcement: n9138.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9138.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9138.0 / TC1-PH1-DOM-070
Title
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.
Description
Wreck and rebuild 22.59 miles of Line 511 between Carson and Rawlings with three (3) 1351 ACSS/TW and associated substation work.
Total Cost ($USD)
$111,130,292
Allocated Cost ($USD)
$1,180,088
Time Estimate
60 to 61 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $628,553
AE2-185 0.0346 % $38,451
AE2-187 0.0300 % $33,339
AE2-283 0.0305 % $33,895
AE2-291 0.5378 % $597,659
AF1-123 10.2087 % $11,344,958
AF1-124 10.2455 % $11,385,854
AF1-125 10.0507 % $11,169,372
AF1-294 0.4085 % $453,967
AF2-035 0.2624 % $291,606
AF2-042 28.1786 % $31,314,960
AF2-046 2.8849 % $3,205,998
AF2-115 0.2488 % $276,492
AF2-120 4.5021 % $5,003,197
AF2-222 3.8795 % $4,311,300
AF2-297 0.7165 % $796,249
AG1-008 2.8849 % $3,205,998
AG1-021 0.1990 % $221,149
AG1-082 0.1873 % $208,147
AG1-098 1.6029 % $1,781,307
AG1-105 0.6819 % $757,797
AG1-124 1.0619 % $1,180,093
AG1-135 4.4165 % $4,908,069
AG1-146 2.1236 % $2,359,963
AG1-147 4.9550 % $5,506,506
AG1-154 0.1382 % $153,582
AG1-166 0.1304 % $144,914
AG1-167 0.0978 % $108,685
AG1-168 0.0978 % $108,685
AG1-285 2.7978 % $3,109,203
AG1-342 0.0630 % $70,012
AG1-494 0.8172 % $908,157
AG1-536 4.9600 % $5,512,062

System Reinforcement: n9250.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9250.0
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n9250.0 / TC1-PH2-DOM-044
Title
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Description
Construct a new 22.59 mile line between Carson and Rawlings Substations.
Total Cost ($USD)
$108,728,086
Allocated Cost ($USD)
$1,154,579
Time Estimate
60 to 61 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $614,966
AE2-185 0.0346 % $37,620
AE2-187 0.0300 % $32,618
AE2-283 0.0305 % $33,162
AE2-291 0.5378 % $584,740
AF1-123 10.2087 % $11,099,724
AF1-124 10.2455 % $11,139,736
AF1-125 10.0507 % $10,927,934
AF1-294 0.4085 % $444,154
AF2-035 0.2624 % $285,302
AF2-042 28.1786 % $30,638,052
AF2-046 2.8849 % $3,136,697
AF2-115 0.2488 % $270,515
AF2-120 4.5021 % $4,895,047
AF2-222 3.8795 % $4,218,106
AF2-297 0.7165 % $779,037
AG1-008 2.8849 % $3,136,697
AG1-021 0.1990 % $216,369
AG1-082 0.1873 % $203,648
AG1-098 1.6029 % $1,742,802
AG1-105 0.6819 % $741,417
AG1-124 1.0619 % $1,154,584
AG1-135 4.4165 % $4,801,976
AG1-146 2.1236 % $2,308,950
AG1-147 4.9550 % $5,387,477
AG1-154 0.1382 % $150,262
AG1-166 0.1304 % $141,781
AG1-167 0.0978 % $106,336
AG1-168 0.0978 % $106,336
AG1-285 2.7978 % $3,041,994
AG1-342 0.0630 % $68,499
AG1-494 0.8172 % $888,526
AG1-536 4.9600 % $5,392,913

System Reinforcement: n9630.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9630.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9630.0 / TC1-PH3-DOM-013
Title
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.
Description
n9630.0 addresses both stability and load flow violations. Construct a new 230 kV Line from the AG1-285 substation to the 230 kV Finneywood substation following the Line 1012 ROW for approximately 1.0 miles, then following the Line 556 ROW for approximately 3.5 miles to terminate at Finneywood. Expand the AG1-285 115 kV substation to accommodate two (2) new 115/230 kV transformers. Build a 230 kV substation at AG1-285 to connect the 115/230 kV transformers and the new 230 kV line to Finneywood. Expand the Finneywood 230 kV substation to accommodate the new line. The existing 1.0 miles of 115 kV from AG1-285 to Chase City does not need to be rebuilt to accommodate a new structure in the same right of way and therefore will be unchanged. The existing 3.5 miles of 500 kV towers from Structure 556/46 to Finneywood substation will need to be rebuilt as a double circuit tower to accommodate the new 230 kV line.
Total Cost ($USD)
$89,468,616
Allocated Cost ($USD)
$950,063
Time Estimate
Dec 31 2029
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $506,034
AE2-185 0.0346 % $30,956
AE2-187 0.0300 % $26,841
AE2-283 0.0305 % $27,288
AE2-291 0.5378 % $481,162
AF1-123 10.2087 % $9,133,583
AF1-124 10.2455 % $9,166,507
AF1-125 10.0507 % $8,992,222
AF1-294 0.4085 % $365,479
AF2-035 0.2624 % $234,766
AF2-042 28.1786 % $25,211,003
AF2-046 2.8849 % $2,581,080
AF2-115 0.2488 % $222,598
AF2-120 4.5021 % $4,027,967
AF2-222 3.8795 % $3,470,935
AF2-297 0.7165 % $641,043
AG1-008 2.8849 % $2,581,080
AG1-021 0.1990 % $178,043
AG1-082 0.1873 % $167,575
AG1-098 1.6029 % $1,434,092
AG1-105 0.6819 % $610,086
AG1-124 1.0619 % $950,067
AG1-135 4.4165 % $3,951,381
AG1-146 2.1236 % $1,899,956
AG1-147 4.9550 % $4,433,170
AG1-154 0.1382 % $123,646
AG1-166 0.1304 % $116,667
AG1-167 0.0978 % $87,500
AG1-168 0.0978 % $87,500
AG1-285 2.7978 % $2,503,153
AG1-342 0.0630 % $56,365
AG1-494 0.8172 % $731,138
AG1-536 4.9600 % $4,437,643

System Reinforcement: n8492

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492
Title
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.
Description
Wreck and rebuild one (1) overhead 500kV transmission line that will start at the existing Fentress 500 kV Substation and terminate at the existing Yadkin 500 kV Substation, located approximately 13.5 miles away.
Total Cost ($USD)
$80,172,278
Allocated Cost ($USD)
$851,346
Time Estimate
26 to 27 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $453,454
AE2-185 0.0346 % $27,740
AE2-187 0.0300 % $24,052
AE2-283 0.0305 % $24,453
AE2-291 0.5378 % $431,167
AF1-123 10.2087 % $8,184,547
AF1-124 10.2455 % $8,214,051
AF1-125 10.0507 % $8,057,875
AF1-294 0.4085 % $327,504
AF2-035 0.2624 % $210,372
AF2-042 28.1786 % $22,591,426
AF2-046 2.8849 % $2,312,890
AF2-115 0.2488 % $199,469
AF2-120 4.5021 % $3,609,436
AF2-222 3.8795 % $3,110,284
AF2-297 0.7165 % $574,434
AG1-008 2.8849 % $2,312,890
AG1-021 0.1990 % $159,543
AG1-082 0.1873 % $150,163
AG1-098 1.6029 % $1,285,081
AG1-105 0.6819 % $546,695
AG1-124 1.0619 % $851,349
AG1-135 4.4165 % $3,540,809
AG1-146 2.1236 % $1,702,538
AG1-147 4.9550 % $3,972,536
AG1-154 0.1382 % $110,798
AG1-166 0.1304 % $104,545
AG1-167 0.0978 % $78,408
AG1-168 0.0978 % $78,408
AG1-285 2.7978 % $2,243,060
AG1-342 0.0630 % $50,509
AG1-494 0.8172 % $655,168
AG1-536 4.9600 % $3,976,545

System Reinforcement: n9267.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9267.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9267.0 / TC1-PH2-DOM-067
Title
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.
Description
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner substations with single (1) 768.2 ACSS/TW “Maumee” at 250 degrees C. This new line will be on separate transmission towers from the existing Northern Neck and Moon Corner line 1059. Station expansion is required at Northern Neck and Moon Corner to accommodate the new line.
Total Cost ($USD)
$45,730,074
Allocated Cost ($USD)
$485,606
Time Estimate
45 to 46 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $258,649
AE2-185 0.0346 % $15,823
AE2-187 0.0300 % $13,719
AE2-283 0.0305 % $13,948
AE2-291 0.5378 % $245,936
AF1-123 10.2087 % $4,668,446
AF1-124 10.2455 % $4,685,275
AF1-125 10.0507 % $4,596,193
AF1-294 0.4085 % $186,807
AF2-035 0.2624 % $119,996
AF2-042 28.1786 % $12,886,095
AF2-046 2.8849 % $1,319,267
AF2-115 0.2488 % $113,776
AF2-120 4.5021 % $2,058,814
AF2-222 3.8795 % $1,774,098
AF2-297 0.7165 % $327,656
AG1-008 2.8849 % $1,319,267
AG1-021 0.1990 % $91,003
AG1-082 0.1873 % $85,652
AG1-098 1.6029 % $733,007
AG1-105 0.6819 % $311,833
AG1-124 1.0619 % $485,608
AG1-135 4.4165 % $2,019,669
AG1-146 2.1236 % $971,124
AG1-147 4.9550 % $2,265,925
AG1-154 0.1382 % $63,199
AG1-166 0.1304 % $59,632
AG1-167 0.0978 % $44,724
AG1-168 0.0978 % $44,724
AG1-285 2.7978 % $1,279,436
AG1-342 0.0630 % $28,810
AG1-494 0.8172 % $373,706
AG1-536 4.9600 % $2,268,212

System Reinforcement: n9259.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9259.0
Type
Stability
TO
Dominion
RTEP ID / TO ID
n9259.0
Title
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Description
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.
Total Cost ($USD)
$25,304,902
Allocated Cost ($USD)
$268,712
Time Estimate
38 to 39 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $143,125
AE2-185 0.0346 % $8,755
AE2-187 0.0300 % $7,591
AE2-283 0.0305 % $7,718
AE2-291 0.5378 % $136,090
AF1-123 10.2087 % $2,583,302
AF1-124 10.2455 % $2,592,614
AF1-125 10.0507 % $2,543,320
AF1-294 0.4085 % $103,371
AF2-035 0.2624 % $66,400
AF2-042 28.1786 % $7,130,567
AF2-046 2.8849 % $730,021
AF2-115 0.2488 % $62,959
AF2-120 4.5021 % $1,139,252
AF2-222 3.8795 % $981,704
AF2-297 0.7165 % $181,310
AG1-008 2.8849 % $730,021
AG1-021 0.1990 % $50,357
AG1-082 0.1873 % $47,396
AG1-098 1.6029 % $405,612
AG1-105 0.6819 % $172,554
AG1-124 1.0619 % $268,713
AG1-135 4.4165 % $1,117,591
AG1-146 2.1236 % $537,375
AG1-147 4.9550 % $1,253,858
AG1-154 0.1382 % $34,971
AG1-166 0.1304 % $32,998
AG1-167 0.0978 % $24,748
AG1-168 0.0978 % $24,748
AG1-285 2.7978 % $707,981
AG1-342 0.0630 % $15,942
AG1-494 0.8172 % $206,792
AG1-536 4.9600 % $1,255,123

System Reinforcement: n7541

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n7541
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
n7541 / dom-016
Title
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Description
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.
Total Cost ($USD)
$22,779,395
Allocated Cost ($USD)
$241,893
Time Estimate
Dec 31 2029
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $128,840
AE2-185 0.0346 % $7,882
AE2-187 0.0300 % $6,834
AE2-283 0.0305 % $6,948
AE2-291 0.5378 % $122,508
AF1-123 10.2087 % $2,325,480
AF1-124 10.2455 % $2,333,863
AF1-125 10.0507 % $2,289,489
AF1-294 0.4085 % $93,054
AF2-035 0.2624 % $59,773
AF2-042 28.1786 % $6,418,915
AF2-046 2.8849 % $657,163
AF2-115 0.2488 % $56,675
AF2-120 4.5021 % $1,025,551
AF2-222 3.8795 % $883,727
AF2-297 0.7165 % $163,214
AG1-008 2.8849 % $657,163
AG1-021 0.1990 % $45,331
AG1-082 0.1873 % $42,666
AG1-098 1.6029 % $365,131
AG1-105 0.6819 % $155,333
AG1-124 1.0619 % $241,894
AG1-135 4.4165 % $1,006,052
AG1-146 2.1236 % $483,743
AG1-147 4.9550 % $1,128,719
AG1-154 0.1382 % $31,481
AG1-166 0.1304 % $29,704
AG1-167 0.0978 % $22,278
AG1-168 0.0978 % $22,278
AG1-285 2.7978 % $637,322
AG1-342 0.0630 % $14,351
AG1-494 0.8172 % $186,153
AG1-536 4.9600 % $1,129,858

System Reinforcement: n8492.1

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492.1
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.1
Title
Two Breaker Additions at Fentress Substation.
Description
Install Two 5000 amp GIS Breakers at Fentress Substation to connect the new 500 kV line 5005.
Total Cost ($USD)
$19,945,879
Allocated Cost ($USD)
$211,804
Time Estimate
30 to 36 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $112,814
AE2-185 0.0346 % $6,901
AE2-187 0.0300 % $5,984
AE2-283 0.0305 % $6,083
AE2-291 0.5378 % $107,269
AF1-123 10.2087 % $2,036,215
AF1-124 10.2455 % $2,043,555
AF1-125 10.0507 % $2,004,700
AF1-294 0.4085 % $81,479
AF2-035 0.2624 % $52,338
AF2-042 28.1786 % $5,620,469
AF2-046 2.8849 % $575,419
AF2-115 0.2488 % $49,625
AF2-120 4.5021 % $897,983
AF2-222 3.8795 % $773,800
AF2-297 0.7165 % $142,912
AG1-008 2.8849 % $575,419
AG1-021 0.1990 % $39,692
AG1-082 0.1873 % $37,359
AG1-098 1.6029 % $319,712
AG1-105 0.6819 % $136,011
AG1-124 1.0619 % $211,805
AG1-135 4.4165 % $880,910
AG1-146 2.1236 % $423,571
AG1-147 4.9550 % $988,318
AG1-154 0.1382 % $27,565
AG1-166 0.1304 % $26,009
AG1-167 0.0978 % $19,507
AG1-168 0.0978 % $19,507
AG1-285 2.7978 % $558,046
AG1-342 0.0630 % $12,566
AG1-494 0.8172 % $162,998
AG1-536 4.9600 % $989,316

System Reinforcement: n8492.2

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n8492.2
Type
Stability
TO
Dominion
RTEP ID / TO ID
n8492.2
Title
Expand Yadkin Substation to accommodate the new 500 kV line.
Description
Expansion of yadkins 500 kV switchyard to accommodate the new 500 kV line which includes addition of 5000 amp GIS breakers and relocation of the existing suffolk -yadkin 500 kV line#565
Total Cost ($USD)
$16,207,123
Allocated Cost ($USD)
$172,103
Time Estimate
15 to 16 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.5656 % $91,667
AE2-185 0.0346 % $5,608
AE2-187 0.0300 % $4,862
AE2-283 0.0305 % $4,943
AE2-291 0.5378 % $87,162
AF1-123 10.2087 % $1,654,537
AF1-124 10.2455 % $1,660,501
AF1-125 10.0507 % $1,628,929
AF1-294 0.4085 % $66,206
AF2-035 0.2624 % $42,527
AF2-042 28.1786 % $4,566,940
AF2-046 2.8849 % $467,559
AF2-115 0.2488 % $40,323
AF2-120 4.5021 % $729,661
AF2-222 3.8795 % $628,755
AF2-297 0.7165 % $116,124
AG1-008 2.8849 % $467,559
AG1-021 0.1990 % $32,252
AG1-082 0.1873 % $30,356
AG1-098 1.6029 % $259,784
AG1-105 0.6819 % $110,516
AG1-124 1.0619 % $172,103
AG1-135 4.4165 % $715,788
AG1-146 2.1236 % $344,174
AG1-147 4.9550 % $803,063
AG1-154 0.1382 % $22,398
AG1-166 0.1304 % $21,134
AG1-167 0.0978 % $15,851
AG1-168 0.0978 % $15,851
AG1-285 2.7978 % $453,443
AG1-342 0.0630 % $10,210
AG1-494 0.8172 % $132,445
AG1-536 4.9600 % $803,873

System Reinforcement: n9195.0

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: n9195.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9195.0 / CE_NUN_STA12_345 NEW CB
Title
Install a new 345 kV circuit breaker at Station 12 Dresden.
Description
• Upgrade the existing substation STA 12 Dresden by adding 345kV BT 14-15 circuit breaker and associated disconnect switches. • Upgrade relay & protection at 345kV substation STA 12 Dresden to support installation of 345kV BT 14-15
Total Cost ($USD)
$3,357,627
Allocated Cost ($USD)
$54,319
Time Estimate
45 Months
Cost Alloc Type
Cost Allocated
Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 0.2057 % $6,907
AE2-173 0.0788 % $2,646
AE2-223 0.2363 % $7,934
AE2-261 2.3717 % $79,633
AF1-088 42.0284 % $1,411,157
AF1-204 2.2821 % $76,624
AF2-008 42.0284 % $1,411,157
AF2-225 0.2363 % $7,934
AG1-124 1.6178 % $54,320
AG1-226 6.8230 % $229,091
AG1-236 0.1693 % $5,684
AG1-374 0.4391 % $14,743
AG1-460 0.2380 % $7,991
AG1-494 1.2451 % $41,806

System Reinforcement: b3811.1

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3811.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3811.1 / CE_PJM B3811_L11323
Title
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Description
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s3011

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s3011
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
s3011 / CE_S3011
Title
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.
Description
Replace 345 kV open air straight bus with GIS in a breaker and half configuration (34 Circuit Breakers) at Goodings Grove with 80kA capability.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3775.1

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3775.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3775.1
Title
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line
Description
Outside of the Green Acres substation, swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line to the University Park N-Olive 345 kV line to create a University Park N-Green Acres-Olive and St. John-Olive 345 kV lines.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.357

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.357
Title
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Description
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.356

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.356
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.355

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.355
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.355
Title
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Description
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.352

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.352
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.352
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.351

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.351
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.351
Title
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Description
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.350

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.350
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.350
Title
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Description
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.349

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.349
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.349
Title
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Description
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.348

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.348
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.348
Title
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
Description
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.346

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.346
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.346
Title
Cut-in 500kV line from Kraken substation into Yeat substation
Description
Cut-in 500kV line from Kraken substation into Yeat substation
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.345

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.345
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.345
Title
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.344

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.344
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.344
Title
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Description
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.342

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.342
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.342
Title
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Description
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.341

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.341
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.341
Title
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
Description
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.325

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.325
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.325
Title
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Description
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3689.2

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3689.2
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3689.2
Title
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA
Description
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 4000A 80 kA breakers and associated equipment including breaker leads as necessary to address breaker duty issues identified in short circuit analysis.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.103

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.103
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.103
Title
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Description
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.405

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.405
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.405
Title
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Description
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3854.1

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3854.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3854.1
Title
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Description
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.108

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.108
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.108
Title
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Description
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.326

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.326
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.326
Title
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Description
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.327

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.327
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b4000.327
Title
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
Description
Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.406

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.406
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.406
Title
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Description
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.115

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.115
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.115
Title
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Description
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.354

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.354
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.354
Title
Ladysmith substation breakers replacement: 574T575 and 568T581
Description
Expand Ladysmith substation to a add redundant circuit breakers to the middle breakers on both 500kV strings (574T575 and 568T581). The equipment including switches 57518, 57515, H115 will be replaced with 5000A equipment.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3853.1

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3853.1
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3853.1 / (Pending)
Title
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Description
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.114

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.114
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.114
Title
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Description
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.235

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.235
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.235
Title
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers
Description
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers: 212352, 2123T2173, 2030T2117, 211752, and 2008T2045
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.334

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.334
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.334
Title
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.
Description
Replace 4 overdutied 230kV breakers at Loudoun Substation with 80kA breakers: 2094T2140, 214052, 200852 and 203052.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.407

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.407
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.407
Title
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.
Description
Replace Loudoun 230 kV breakers 204552, 217352 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.119

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.119
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.119
Title
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.
Description
Loudoun Cap Sub 230kV - replace 50kA breaker SC352 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.128

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.128
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.128
Title
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.
Description
North Anna Sub 500kV - replace 40kA breakers 57502, G102-1, G102-2, G202, G2T575, XT573 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.408

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.408
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.408
Title
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.
Description
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, H342 with breakers rated 80 kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s2609.6

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s2609.6
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.6
Title
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Description
Upgrade (2) 230 kV breakers 201342 & L142 from 50kA to 63kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s2609.9

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s2609.9
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
s2609.9
Title
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.
Description
Upgrade 230kV Pleasant View breakers L3T203 and L3T2180 from 50kA to 80kA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b4000.134

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b4000.134
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b4000.134
Title
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.
Description
Remington Sub 230kV - replace 40kA and 50kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, H9T299 with 63kA
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b1696

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b1696
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b1696
Title
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Description
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.236

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.236
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.236
Title
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.
Description
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers: H1T539 and H2T539
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: s3047.2

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: s3047.2
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
s3047.2
Title
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.
Description
Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV line #535 Loudoun – Meadowbrook and #569 Loudoun - Morrisville as the 500 kV sources into the proposed 500 kV ring bus Vint Hill Substation will be expanded to the north of the existing site to accommodate the 500 kV ring required for the addition of the new transformers Existing terminations for 230 kV line #2174 Wheeler – Vint Hill, line #2101 Bristers – Vint Hill, and line #2163 Liberty – Vint Hill will be rearranged to terminate into the expanded Vint Hill Substation 230 kV line #2114 Remington CT – Rollins Ford will also be cut and looped into the expanded Vint Hill Substation due to spatial constraints along the existing right-of-way.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.312

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.312
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.312
Title
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.
Description
Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.313

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.313
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.313
Title
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Description
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.356

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.356
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.356
Title
Build a new 500 kV line from Vint Hill to Wishing Star.
Description
Build a new 500kV line from Vint Hill to Wishing Star. The line will be supported on single circuit monopoles. New conductor to have a summer rating of 4357 MVA. Line length is approximately 16.59 miles
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.357

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.357
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.357
Title
Build a new 500 kV line from Morrisville to Vint Hill.
Description
Build a new 500kV line from Morrisville to Vint Hill. New conductor to have a summer rating of 4357 MVA. Line length is approximately 19.71 miles.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.354

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.354
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
b3800.354
Title
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.
Description
Install terminal equipment at Wishing Star substation to support a 5000A line to Vint Hill. Update relay settings for 500kV Lines #546 and #590.
Cost Information
Cost Alloc Type
Contingent

System Reinforcement: b3800.335

AG1-124 did not load into this reinforcement directly however this project contributed to an topology or eliminated upgrade and therefore this project is responsible for relevant regional upgrades.

System Reinforcement: b3800.335
Type
Short Circuit
TO
Dominion
RTEP ID / TO ID
b3800.335
Title
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker
Description
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker: 56142
Cost Information
Cost Alloc Type
Contingent

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-124


AG1-124 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Load Flow Dominion n7812 / dom-397 Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor. Eliminated 11.1 MW 56.5% Cost Allocated $5,516,195
Load Flow AEP n9178.0 / AEPAPRJV007 Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station. Eliminated 11.1 MW 56.5% Cost Allocated $2,610,757
Load Flow AEP n9179.0 / AEPAPRJV008 Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line. Eliminated 11.1 MW 56.5% Cost Allocated $682,999
Contributions into Topology or Eliminated Reinforcement Total: $8,809,951
AG1-124 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
AEP n9243.0 Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. Cost Allocated $3,239,436
Dominion n9138.0 Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. Cost Allocated $1,180,088
Dominion n9250.0 Construct a new 22.59 mile line between Carson and Rawlings Substations. Cost Allocated $1,154,579
Dominion n9630.0 Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. Cost Allocated $950,063
Dominion n8492 Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. Cost Allocated $851,346
Dominion n9267.0 Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. Cost Allocated $485,606
Dominion n9259.0 Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. Cost Allocated $268,712
Dominion n7541 Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. Cost Allocated $241,893
Dominion n8492.1 Two Breaker Additions at Fentress Substation. Cost Allocated $211,804
Dominion n8492.2 Expand Yadkin Substation to accommodate the new 500 kV line. Cost Allocated $172,103
ComEd n9195.0 Install a new 345 kV circuit breaker at Station 12 Dresden. Cost Allocated $54,319
ComEd b3811.1 Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. Contingent $0
ComEd s3011 Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. Contingent $0
ComEd b3775.1 Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line Contingent $0
Dominion b4000.357 Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. Contingent $0
Dominion b4000.356 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). Contingent $0
Dominion b4000.355 Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). Contingent $0
Dominion b4000.352 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. Contingent $0
Dominion b4000.351 Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. Contingent $0
Dominion b4000.350 Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. Contingent $0
Dominion b4000.349 Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. Contingent $0
Dominion b4000.348 Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. Contingent $0
Dominion b4000.346 Cut-in 500kV line from Kraken substation into Yeat substation Contingent $0
Dominion b4000.345 Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0
Dominion b4000.344 Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. Contingent $0
Dominion b4000.342 Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. Contingent $0
Dominion b4000.341 Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. Contingent $0
Dominion b4000.325 Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. Contingent $0
Dominion b3689.2 Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA Contingent $0
Dominion b4000.103 Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA Contingent $0
Dominion b3800.405 Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. Contingent $0
Dominion b3854.1 Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA Contingent $0
Dominion b4000.108 Carson Sub 230kV - replace 40kA breaker 23872 with 63kA Contingent $0
Dominion b4000.326 At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. Contingent $0
Dominion b4000.327 Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. Contingent $0
Dominion b3800.406 Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. Contingent $0
Dominion b4000.115 Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA Contingent $0
Dominion b4000.354 Ladysmith substation breakers replacement: 574T575 and 568T581 Contingent $0
Dominion b3853.1 Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA Contingent $0
Dominion b4000.114 Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA Contingent $0
Dominion b3800.235 Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers Contingent $0
Dominion b3800.334 Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. Contingent $0
Dominion b3800.407 Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. Contingent $0
Dominion b4000.119 Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. Contingent $0
Dominion b4000.128 North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. Contingent $0
Dominion b3800.408 Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. Contingent $0
Dominion s2609.6 Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. Contingent $0
Dominion s2609.9 Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. Contingent $0
Dominion b4000.134 Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. Contingent $0
Dominion b1696 Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 Contingent $0
Dominion b3800.236 Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. Contingent $0
Dominion s3047.2 Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. Contingent $0
Dominion b3800.312 Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. Contingent $0
Dominion b3800.313 Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. Contingent $0
Dominion b3800.356 Build a new 500 kV line from Vint Hill to Wishing Star. Contingent $0
Dominion b3800.357 Build a new 500 kV line from Morrisville to Vint Hill. Contingent $0
Dominion b3800.354 Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. Contingent $0
Dominion b3800.335 Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker Contingent $0
Region Topology Upgrade Total: $8,809,949

Attachments

AG1-124 One Line Diagram

AG1-124 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.