AG1-375 Phase III Study Report

v1.00 released 2025-09-18 17:04

Sorenson-Desoto 345 kV

60.0 MW Capacity / 100.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Blackford County Wind Farm LLC d/b/a Blackford County Solar Park LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $11,899,575 $11,515,338 = 1.03 AND ( $11,899,575 - $11,515,338 ) 100.0 = $3,842 per MW

General

The Project Developer has proposed an uprate to a planned/existing Wind facility located in the American Electric Power zone — Blackford County, Indiana. This project is an increase to the developer’s AF2-177 project(s), which will share the same Point of Interconnection. The AG1-375 project is a 100.0 MW uprate (60.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 300.0 MW with 86.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-375
Project Name:
Sorenson-Desoto 345 kV
Project Developer Name:
Blackford County Wind Farm LLC d/b/a Blackford County Solar Park LLC
State:
Indiana
County:
Blackford
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
300.0
MWE:
100.0
MWC:
60.0
Fuel Type:
Solar
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-375 will interconnect on the AEP Indiana Michigan Transmission Company, Inc. transmission system tapping the Sorenson to Desoto 345 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AG1-375 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AG1-375 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $1,199,530 $1,199,530
Other Scope $193,802 $193,802
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $8,649,190 $8,649,190
Network Upgrades $1,808,818 $1,808,818
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $1,426,881 $1,426,881
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $14,686 $0
Total $13,292,907 $13,278,221

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AF2-177/AG1-375

Security has been calculated for the AF2-177/AG1-375 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AF2-177/AG1-375
Project(s): AF2-177/AG1-375
Final Agreement Security (A): $27,728,756
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $27,728,756
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

AG1-375 will interconnect with the AEP transmission system as an uprate to a previous interconnection at the Sorenson - Desoto 345 kV Station. The estimates provided in this report are preliminary in nature, as they were determined without the benefit of detailed engineering studies. Final estimates will require an on-site review and coordination to determine final construction requirements.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9502.0

Proposed AF2-177 345 kV, 3M 345 kV, and Jay 345 kV Stations: Final tie in for fiber installation in new right of way.

$257,425 $67,268 $42,716 $11,162 $378,571 $189,286 (See Note 1)
n9501.0

3M 345 kV Station: • Reconfigure the existing ethernet switch, installing one (1) new Small Form-Factor Pluggable (SFP) transceiver.

$28,589 $11,817 $21,283 $8,424 $70,113 $35,056 (See Note 1)
n9500.0

Jay 345 kV Station: • Reconfigure the existing ethernet switch, installing one (1) new Small Form-Factor Pluggable (SFP) transceiver.

$28,589 $11,817 $21,283 $8,424 $70,113 $35,056 (See Note 1)
n9499.0

Desoto 345 kV Station: • Review and revise the protective relay settings.

$36,901 $7,080 $14,081 $2,702 $60,764 $30,382 (See Note 1)
n9498.0

Proposed AF1-148 345 kV Station: • Review and revise the protective relay settings.

$36,901 $7,080 $14,081 $2,702 $60,764 $30,382 (See Note 1)
n9497.0

Sorenson - Desoto #2 345 kV Circuit: Proposed AF2-177 345 kV Station tie-in. • Remove two (2) tower structures (#419 and #421) along with approximately 0.4 miles of existing wire. • Install two (2) new 150’ custom steel, single circuit, single pole dead end structures on concrete piers with anchor bolt cages along the existing Sorenson - Desoto #2 345 kV Circuit. • Install two (2) new 130’ custom steel, single circuit, single pole, running angle structures on concrete piers with anchor bolt cages along the perimeter of the Proposed AF2-177 345 kV station. • Install four (4) spans of double bundle aluminum conductor steel-reinforced (ACSR) 2156 (Bluebird) transmission line conductor with 12/7 Guinea shield wire.

$1,239,091 $1,185,343 $220,456 $210,893 $2,855,783 $1,427,892 (See Note 1)
n9489.0

Proposed AF2-177 345 kV Station: Review and revise the protective relay settings to account for the additional generation of AG1-375.

$36,901 $7,080 $14,081 $2,702 $60,764 $60,764
Other
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

• IMTCo will procure one (1) metering panel with two (2) primary meters and one (1) ethernet switch to be installed in the AG1-375 Project Developer's collector station. • IMTCo will procure one (1) connected grid router (CGR) to be installed in the Project Developer's originating project collector station (AF2-177).

$106,608 $51,442 $23,199 $12,553 $193,802 $193,802
Stand-Alone Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9496.0

Sorenson - Desoto #2 345 kV Circuit: Construct a new 345 kV breaker and a half station, initially populated with three (3) circuit breakers, expandable to six (6) circuit breakers. • Three (3) 5000A 63 kA circuit breakers with associated control relaying. • Nine (9) 3000A circuit breaker disconnect switches. • Two (2) single phase station service voltage transformers (SSVT). • One (1) 16' x 48' DICM. • Four (4) single phase wave traps, two (2) each on the line exits to the Desoto and Proposed AF1-148 345 kV Stations. • A directional comparison blocking (DCB) protective relaying scheme for the line to the Proposed AF1-148 345 kV Station. • A DCB protective relaying scheme for the line to the Desoto 345 kV Station. • Two (2) 3-phase coupling capacitor voltage transformers (CCVT), one each for the line exits to the Proposed AF1-148 and Desoto 345 kV Stations. • Two (2) A-Frame line exit structures, one each for the line exits to the Proposed AF1-148 and Desoto 345 kV Stations. • Associated conductors (buswork, ground grid, jumpers), telecom terminal equipment, insulators, arresters, foundations, and structures.

$8,041,121 $6,002,956 $501,890 $374,677 $14,920,644 $7,460,322 (See Note 1)
n9495.0

Proposed AF2-177 345 kV, 3M 345 kV, and Jay 345 kV Stations: Install two (2) all dielectric loose tube (ADLT) station exit transitions and two (2) new fiber optic cable paths consisting of a total 6.9 miles of 144 count ADLT cable installed underground in new right of way.

$1,555,334 $463,998 $276,051 $82,353 $2,377,736 $1,188,868 (See Note 1)
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

• Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage and one span of double bundle aluminum conductor steel-reinforced (ACSR) 954 (Cardinal) transmission line conductor with 12/7 Guinea shield wire for the generation lead circuit extending from the Proposed AF2-177 345 kV station. • Extension of two (2) underground 48 count all dielectric loose tube (ADLT) fiber optic cables from the Proposed AF2-177 345 kV station control house to fiber demarcation splice boxes to support direct fiber relaying between the Proposed AF2-177 345 kV and Project Developer's collector stations. The Project Developer will be responsible for the fiber extension from the splice boxes to the collector station. • Dual direct fiber current differential relays for the generation lead to the Proposed AF2-177 collector station. • Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase coupling capacitor voltage transformers (CCVT), associated structures and foundations, one (1) ethernet switch, and one (1) drop in control module (DICM)-installed metering panel, for the generation lead circuit at the Proposed AF2-177 345 kV station.

$1,271,405 $811,707 $190,689 $125,260 $2,399,061 $1,199,530 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 24 to 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

The minimum and maximum schedules reflect the amount of time (in months) that AEP projects their portion of the construction project scope elapsing from the time of agreement assuming commercial operation of the preceding project has been achieved. The minimum schedule assumes that the Transmission Owners only scope of work is review and revision of relay settings at the interconnection station. The maximum schedule assumes the need for additional work being required at the interconnection station.  Any material ordering or construction work done prior to Engineering and Procurement or Generation Interconnection Agreements is done solely at the Project Developers risk. There is a potential that any work done or materials ordered prior to agreements and the ensuing detailed engineering processes does not meet AEP specifications, resulting in rejection of the completed work.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here. Refer to AG1-375 Physical Interconnection Facilities Study for additional requirements found in the General Section of the report.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 100.0 MW (60.0 MW Capacity) injection in the AEP area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
OVEC 06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1
DEOK_P2-3_1403_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7   /*08M.FORT     345.0 - 08M.FRT7      22.0
END
Breaker AC 111.15 % 971.0 B 1079.31 7.49
OVEC 06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1
DEOK_P2-3_1401_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9   /*08M.FORT     345.0 - 08M.FORT     138.0
END
Breaker AC 110.64 % 971.0 B 1074.33 7.5
AEP 05DESOTO-05DESOTO 345.0/138.0 kV Ckt 2 transformer
243218 to 243278 ckt 2
AEP_P4_#2965_05DESOTO 345_A2_SRT-A
CONTINGENCY 'AEP_P4_#2965_05DESOTO 345_A2_SRT-A'
 OPEN BRANCH FROM BUS 243218 TO BUS 243222 CKT 1   /*05DESOTO     345.0 - 05FALL C     345.0
 OPEN BRANCH FROM BUS 243218 TO BUS 243278 CKT 1   /*05DESOTO     345.0 - 05DESOTO     138.0
END
Breaker AC 102.88 % 692.0 B 711.91 15.94

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1403_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7   /*08M.FORT     345.0 - 08M.FRT7      22.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 111.15 %
Rating: 971.0 MVA
Rating Type: B
MVA to Mitigate: 1079.31 MVA
MW Contribution: 7.49 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1
Contingency Name:
DEOK_P2-3_1403_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1403_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 251950 CKT 7   /*08M.FORT     345.0 - 08M.FRT7      22.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.94 %
Rating: 971.0 MVA
Rating Type: B
MVA to Mitigate: 1077.26 MVA
MW Contribution: 7.48 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C Adder 0.14 MW 0.12 MW
961762 AG1-017 E Adder 0.64 MW 0.54 MW
962031 AG1-047 C Adder 3.68 MW 3.13 MW
962032 AG1-047 E Adder 2.45 MW 2.08 MW
965031 AG1-367 C Adder 5.54 MW 4.71 MW
965032 AG1-367 E Adder 3.69 MW 3.14 MW
965101 AG1-375 C Adder 4.5 MW 3.82 MW
965102 AG1-375 E Adder 3.0 MW 2.55 MW
965651 AG1-433 C Adder 1.28 MW 1.09 MW
965652 AG1-433 E Adder 5.99 MW 5.09 MW
247264 05LAWG1A 50/50 6.8 MW 6.8 MW
247265 05LAWG1B 50/50 6.8 MW 6.8 MW
247266 05LAWG1S 50/50 10.87 MW 10.87 MW
247267 05LAWG2A 50/50 6.8 MW 6.8 MW
247268 05LAWG2B 50/50 6.32 MW 6.32 MW
247269 05LAWG2S 50/50 10.87 MW 10.87 MW
247543 V3-007 C 50/50 0.49 MW 0.49 MW
247929 S-071 E Adder 5.86 MW 4.98 MW
247935 V3-007 E 50/50 20.22 MW 20.22 MW
247958 05WLD G2 E Adder 12.56 MW 10.68 MW
247963 05HDWTR1G E 50/50 20.22 MW 20.22 MW
934962 AD1-128 E Adder 7.38 MW 6.27 MW
936561 AD2-071 C Adder 4.71 MW 4.0 MW
936562 AD2-071 E Adder 2.32 MW 1.97 MW
942081 AE2-220 C 50/50 6.1 MW 6.1 MW
942082 AE2-220 E 50/50 8.43 MW 8.43 MW
944031 AF1-071 C Adder 0.48 MW 0.4 MW
944032 AF1-071 E Adder 0.78 MW 0.66 MW
958711 AF2-162 C Adder 2.18 MW 1.85 MW
958712 AF2-162 E Adder 1.09 MW 0.93 MW
958821 AF2-173 C Adder 7.76 MW 6.59 MW
958822 AF2-173 E Adder 5.17 MW 4.39 MW
960441 AF2-335 C Adder 4.79 MW 4.07 MW
960442 AF2-335 E Adder 1.6 MW 1.36 MW
960971 AF2-388 C Adder 2.56 MW 2.18 MW
960972 AF2-388 E Adder 11.99 MW 10.19 MW
243795 05HDWTR1G C 50/50 0.49 MW 0.49 MW
251947 08EBND2 50/50 16.26 MW 16.26 MW
932681 AC2-090 C 50/50 0.72 MW 0.72 MW
932682 AC2-090 E 50/50 7.21 MW 7.21 MW
939761 AE1-207 C Adder 4.47 MW 3.8 MW
939762 AE1-207 E Adder 6.17 MW 5.24 MW
939771 AE1-208 C Adder 3.96 MW 3.37 MW
939772 AE1-208 E Adder 5.4 MW 4.59 MW
942071 AE2-219 C Adder 2.57 MW 2.19 MW
942072 AE2-219 E Adder 3.55 MW 3.02 MW
247968 Z2-115 E Adder 0.07 MW 0.06 MW
926874 AC1-174 E 50/50 7.21 MW 7.21 MW
926881 AC1-175 E 50/50 7.21 MW 7.21 MW
270209 AC1-174 C 50/50 0.72 MW 0.72 MW
270210 AC1-175 C 50/50 0.72 MW 0.72 MW
270222 AC2-111 C Adder 2.11 MW 1.79 MW
932844 AC2-111 E Adder 3.41 MW 2.9 MW
933596 AC2-176 E Adder 6.93 MW 5.89 MW
934161 AD1-043 C Adder 3.41 MW 2.9 MW
934162 AD1-043 E Adder 5.57 MW 4.73 MW
942221 AE2-234 C Adder 1.3 MW 1.1 MW
942222 AE2-234 E Adder 0.59 MW 0.5 MW
942791 AE2-297 C O1 50/50 1.58 MW 1.58 MW
942792 AE2-297 E O1 50/50 6.63 MW 6.63 MW
944531 AF1-118 C Adder 16.36 MW 13.91 MW
944532 AF1-118 E Adder 4.94 MW 4.2 MW
944541 AF1-119 C Adder 10.18 MW 8.65 MW
944542 AF1-119 E Adder 4.36 MW 3.71 MW
945371 AF1-202 C Adder 2.62 MW 2.22 MW
945372 AF1-202 E Adder 12.77 MW 10.86 MW
945581 AF1-223 C Adder 6.92 MW 5.88 MW
945582 AF1-223 E Adder 4.62 MW 3.92 MW
946032 AF1-268 E Adder 2.05 MW 1.74 MW
958861 AF2-177 C Adder 1.95 MW 1.66 MW
958862 AF2-177 E Adder 13.04 MW 11.08 MW
960791 AF2-370 C Adder 1.6 MW 1.36 MW
961161 AF2-407 C Adder 24.08 MW 20.47 MW
961171 AF2-408 C Adder 6.5 MW 5.53 MW
939781 AE1-209 C Adder 1.2 MW 1.02 MW
939782 AE1-209 E Adder 8.03 MW 6.83 MW
939791 AE1-210 C Adder 1.2 MW 1.02 MW
939792 AE1-210 E Adder 8.03 MW 6.83 MW
946031 AF1-268 C Adder 4.51 MW 3.83 MW
964351 AG1-297 C 50/50 9.34 MW 9.34 MW
964352 AG1-297 E 50/50 28.02 MW 28.02 MW
964611 AG1-324 C Adder 1.81 MW 1.54 MW
964612 AG1-324 E Adder 0.72 MW 0.61 MW
940981 AE2-089 C Adder 5.0 MW 4.25 MW
940982 AE2-089 E Adder 3.33 MW 2.83 MW
941691 AE2-169 C Adder 2.38 MW 2.02 MW
941721 AE2-172 C Adder 2.66 MW 2.26 MW
957741 AF2-068 C Adder 5.52 MW 4.69 MW
957742 AF2-068 E Adder 3.68 MW 3.13 MW
965461 AG1-414 C Adder 2.76 MW 2.34 MW
965462 AG1-414 E Adder 1.84 MW 1.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 36.42 MW 36.42 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 14.21 MW 14.21 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.92 MW 0.92 MW
NY PJM->LTFIMP_NY CLTF 0.47 MW 0.47 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.63 MW 0.63 MW
WEC LTFEXP_WEC->PJM CLTF 0.84 MW 0.84 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.26 MW 0.26 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.14 MW 0.14 MW
TVA LTFEXP_TVA->PJM CLTF 1.33 MW 1.33 MW
MEC LTFEXP_MEC->PJM CLTF 3.77 MW 3.77 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.09 MW 2.09 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.32 MW 0.32 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.9 MW 5.9 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.4 MW 0.4 MW

Details for 06DEARB1-06PIERCE 345.0 kV Ckt 1 line l/o DEOK_P2-3_1401_MIAMI FORT_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9   /*08M.FORT     345.0 - 08M.FORT     138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.64 %
Rating: 971.0 MVA
Rating Type: B
MVA to Mitigate: 1074.33 MVA
MW Contribution: 7.5 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: OVEC
Facility Description:
06DEARB1-06PIERCE 345.0 kV Ckt 1 line
248001 to 248013 ckt 1
Contingency Name:
DEOK_P2-3_1401_MIAMI FORT_SRT-A
CONTINGENCY 'DEOK_P2-3_1401_MIAMI FORT_SRT-A'
 OPEN BRANCH FROM BUS 249567 TO BUS 243233 CKT 1   /*08M.FORT     345.0 - 05TANNER     345.0
 OPEN BRANCH FROM BUS 249567 TO BUS 250057 CKT 9   /*08M.FORT     345.0 - 08M.FORT     138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 110.42 %
Rating: 971.0 MVA
Rating Type: B
MVA to Mitigate: 1072.22 MVA
MW Contribution: 7.48 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C Adder 0.14 MW 0.12 MW
961762 AG1-017 E Adder 0.64 MW 0.54 MW
962031 AG1-047 C Adder 3.68 MW 3.13 MW
962032 AG1-047 E Adder 2.45 MW 2.09 MW
965031 AG1-367 C Adder 5.54 MW 4.71 MW
965032 AG1-367 E Adder 3.69 MW 3.14 MW
965101 AG1-375 C Adder 4.5 MW 3.82 MW
965102 AG1-375 E Adder 3.0 MW 2.55 MW
965651 AG1-433 C Adder 1.28 MW 1.09 MW
965652 AG1-433 E Adder 6.0 MW 5.1 MW
247264 05LAWG1A 50/50 6.81 MW 6.81 MW
247265 05LAWG1B 50/50 6.81 MW 6.81 MW
247266 05LAWG1S 50/50 10.87 MW 10.87 MW
247267 05LAWG2A 50/50 6.81 MW 6.81 MW
247268 05LAWG2B 50/50 6.32 MW 6.32 MW
247269 05LAWG2S 50/50 10.87 MW 10.87 MW
247543 V3-007 C 50/50 0.49 MW 0.49 MW
247929 S-071 E Adder 5.86 MW 4.99 MW
247935 V3-007 E 50/50 20.23 MW 20.23 MW
247958 05WLD G2 E Adder 12.57 MW 10.68 MW
247963 05HDWTR1G E 50/50 20.23 MW 20.23 MW
934962 AD1-128 E Adder 7.38 MW 6.27 MW
936561 AD2-071 C Adder 4.71 MW 4.01 MW
936562 AD2-071 E Adder 2.32 MW 1.97 MW
942081 AE2-220 C 50/50 6.1 MW 6.1 MW
942082 AE2-220 E 50/50 8.43 MW 8.43 MW
944031 AF1-071 C Adder 0.48 MW 0.4 MW
944032 AF1-071 E Adder 0.78 MW 0.66 MW
958711 AF2-162 C Adder 2.18 MW 1.85 MW
958712 AF2-162 E Adder 1.09 MW 0.93 MW
958821 AF2-173 C Adder 7.76 MW 6.59 MW
958822 AF2-173 E Adder 5.17 MW 4.4 MW
960441 AF2-335 C Adder 4.79 MW 4.07 MW
960442 AF2-335 E Adder 1.6 MW 1.36 MW
960971 AF2-388 C Adder 2.56 MW 2.18 MW
960972 AF2-388 E Adder 11.99 MW 10.19 MW
243795 05HDWTR1G C 50/50 0.49 MW 0.49 MW
251947 08EBND2 50/50 16.26 MW 16.26 MW
932681 AC2-090 C 50/50 0.72 MW 0.72 MW
932682 AC2-090 E 50/50 7.21 MW 7.21 MW
939761 AE1-207 C Adder 4.47 MW 3.8 MW
939762 AE1-207 E Adder 6.17 MW 5.25 MW
939771 AE1-208 C Adder 3.96 MW 3.37 MW
939772 AE1-208 E Adder 5.4 MW 4.59 MW
942071 AE2-219 C Adder 2.57 MW 2.19 MW
942072 AE2-219 E Adder 3.55 MW 3.02 MW
247968 Z2-115 E Adder 0.07 MW 0.06 MW
926874 AC1-174 E 50/50 7.21 MW 7.21 MW
926881 AC1-175 E 50/50 7.21 MW 7.21 MW
270209 AC1-174 C 50/50 0.72 MW 0.72 MW
270210 AC1-175 C 50/50 0.72 MW 0.72 MW
270222 AC2-111 C Adder 2.11 MW 1.8 MW
932844 AC2-111 E Adder 3.41 MW 2.9 MW
933596 AC2-176 E Adder 6.94 MW 5.9 MW
934161 AD1-043 C Adder 3.41 MW 2.9 MW
934162 AD1-043 E Adder 5.57 MW 4.73 MW
942221 AE2-234 C Adder 1.3 MW 1.1 MW
942222 AE2-234 E Adder 0.59 MW 0.5 MW
942791 AE2-297 C O1 50/50 1.58 MW 1.58 MW
942792 AE2-297 E O1 50/50 6.63 MW 6.63 MW
944531 AF1-118 C Adder 16.37 MW 13.92 MW
944532 AF1-118 E Adder 4.94 MW 4.2 MW
944541 AF1-119 C Adder 10.19 MW 8.66 MW
944542 AF1-119 E Adder 4.37 MW 3.71 MW
945371 AF1-202 C Adder 2.62 MW 2.22 MW
945372 AF1-202 E Adder 12.77 MW 10.86 MW
945581 AF1-223 C Adder 6.93 MW 5.89 MW
945582 AF1-223 E Adder 4.62 MW 3.92 MW
946032 AF1-268 E Adder 2.05 MW 1.74 MW
958861 AF2-177 C Adder 1.95 MW 1.66 MW
958862 AF2-177 E Adder 13.04 MW 11.09 MW
960791 AF2-370 C Adder 1.6 MW 1.36 MW
961161 AF2-407 C Adder 24.08 MW 20.47 MW
961171 AF2-408 C Adder 6.5 MW 5.53 MW
939781 AE1-209 C Adder 1.2 MW 1.02 MW
939782 AE1-209 E Adder 8.04 MW 6.83 MW
939791 AE1-210 C Adder 1.2 MW 1.02 MW
939792 AE1-210 E Adder 8.04 MW 6.83 MW
946031 AF1-268 C Adder 4.51 MW 3.84 MW
964351 AG1-297 C 50/50 9.34 MW 9.34 MW
964352 AG1-297 E 50/50 28.02 MW 28.02 MW
964611 AG1-324 C Adder 1.81 MW 1.54 MW
964612 AG1-324 E Adder 0.72 MW 0.61 MW
940981 AE2-089 C Adder 5.0 MW 4.25 MW
940982 AE2-089 E Adder 3.33 MW 2.83 MW
941691 AE2-169 C Adder 2.38 MW 2.02 MW
941721 AE2-172 C Adder 2.66 MW 2.26 MW
957741 AF2-068 C Adder 5.52 MW 4.69 MW
957742 AF2-068 E Adder 3.68 MW 3.13 MW
965461 AG1-414 C Adder 2.76 MW 2.34 MW
965462 AG1-414 E Adder 1.84 MW 1.56 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 36.46 MW 36.46 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 14.22 MW 14.22 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.92 MW 0.92 MW
NY PJM->LTFIMP_NY CLTF 0.47 MW 0.47 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.63 MW 0.63 MW
WEC LTFEXP_WEC->PJM CLTF 0.84 MW 0.84 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.26 MW 0.26 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.13 MW 0.13 MW
TVA LTFEXP_TVA->PJM CLTF 1.33 MW 1.33 MW
MEC LTFEXP_MEC->PJM CLTF 3.77 MW 3.77 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.1 MW 2.1 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.32 MW 0.32 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 5.88 MW 5.88 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.4 MW 0.4 MW

Details for 05DESOTO-05DESOTO 345.0/138.0 kV Ckt 2 transformer l/o AEP_P4_#2965_05DESOTO 345_A2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05DESOTO-05DESOTO 345.0/138.0 kV Ckt 2 transformer
243218 to 243278 ckt 2
Contingency Name:
AEP_P4_#2965_05DESOTO 345_A2_SRT-A
CONTINGENCY 'AEP_P4_#2965_05DESOTO 345_A2_SRT-A'
 OPEN BRANCH FROM BUS 243218 TO BUS 243222 CKT 1   /*05DESOTO     345.0 - 05FALL C     345.0
 OPEN BRANCH FROM BUS 243218 TO BUS 243278 CKT 1   /*05DESOTO     345.0 - 05DESOTO     138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.88 %
Rating: 692.0 MVA
Rating Type: B
MVA to Mitigate: 711.91 MVA
MW Contribution: 15.94 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: AEP
Facility Description:
05DESOTO-05DESOTO 345.0/138.0 kV Ckt 2 transformer
243218 to 243278 ckt 2
Contingency Name:
AEP_P4_#2965_05DESOTO 345_A2_SRT-A
CONTINGENCY 'AEP_P4_#2965_05DESOTO 345_A2_SRT-A'
 OPEN BRANCH FROM BUS 243218 TO BUS 243222 CKT 1   /*05DESOTO     345.0 - 05FALL C     345.0
 OPEN BRANCH FROM BUS 243218 TO BUS 243278 CKT 1   /*05DESOTO     345.0 - 05DESOTO     138.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 102.26 %
Rating: 692.0 MVA
Rating Type: B
MVA to Mitigate: 707.63 MVA
MW Contribution: 15.94 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
962031 AG1-047 C Adder -17.4 MW -14.79 MW
965031 AG1-367 C 50/50 12.83 MW 12.83 MW
965032 AG1-367 E 50/50 8.56 MW 8.56 MW
965101 AG1-375 C 50/50 9.56 MW 9.56 MW
965102 AG1-375 E 50/50 6.38 MW 6.38 MW
965651 AG1-433 C 50/50 2.68 MW 2.68 MW
965652 AG1-433 E 50/50 12.57 MW 12.57 MW
247292 05KEY G1 50/50 1.2 MW 1.2 MW
247293 05KEY G2 50/50 1.21 MW 1.21 MW
247294 05KEY G3 50/50 1.23 MW 1.23 MW
247295 05KEY G4 50/50 1.24 MW 1.24 MW
247543 V3-007 C 50/50 0.77 MW 0.77 MW
247935 V3-007 E 50/50 31.64 MW 31.64 MW
247963 05HDWTR1G E 50/50 31.64 MW 31.64 MW
942081 AE2-220 C 50/50 9.55 MW 9.55 MW
942082 AE2-220 E 50/50 13.18 MW 13.18 MW
958711 AF2-162 C 50/50 4.58 MW 4.58 MW
958712 AF2-162 E 50/50 2.29 MW 2.29 MW
958821 AF2-173 C 50/50 17.97 MW 17.97 MW
958822 AF2-173 E 50/50 11.98 MW 11.98 MW
960971 AF2-388 C 50/50 5.37 MW 5.37 MW
960972 AF2-388 E 50/50 25.14 MW 25.14 MW
243795 05HDWTR1G C 50/50 0.77 MW 0.77 MW
932681 AC2-090 C 50/50 1.13 MW 1.13 MW
932682 AC2-090 E 50/50 11.27 MW 11.27 MW
942071 AE2-219 C Adder -10.64 MW -9.04 MW
926874 AC1-174 E 50/50 11.27 MW 11.27 MW
926881 AC1-175 E 50/50 11.27 MW 11.27 MW
270209 AC1-174 C 50/50 1.13 MW 1.13 MW
270210 AC1-175 C 50/50 1.13 MW 1.13 MW
944531 AF1-118 C 50/50 31.01 MW 31.01 MW
944532 AF1-118 E 50/50 9.35 MW 9.35 MW
944541 AF1-119 C 50/50 21.35 MW 21.35 MW
944542 AF1-119 E 50/50 9.15 MW 9.15 MW
945371 AF1-202 C 50/50 5.63 MW 5.63 MW
945372 AF1-202 E 50/50 27.5 MW 27.5 MW
945581 AF1-223 C 50/50 14.91 MW 14.91 MW
945582 AF1-223 E 50/50 9.94 MW 9.94 MW
958861 AF2-177 C 50/50 4.14 MW 4.14 MW
958862 AF2-177 E 50/50 27.74 MW 27.74 MW
939781 AE1-209 C 50/50 2.78 MW 2.78 MW
939782 AE1-209 E 50/50 18.61 MW 18.61 MW
939791 AE1-210 C 50/50 2.78 MW 2.78 MW
939792 AE1-210 E 50/50 18.61 MW 18.61 MW
940981 AE2-089 C Adder -19.94 MW -16.95 MW
CBM North LTFEXP_CBM-N->PJM CBM 0.1 MW 0.1 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 0.07 MW 0.07 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.15 MW 0.15 MW
VTF LTFEXP_VFT->PJM CMTX 0.4 MW 0.4 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 1.53 MW 1.53 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.15 MW 0.15 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.11 MW 0.11 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 2.78 MW 2.78 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.55 MW 0.55 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 1.84 MW 1.84 MW
MDU PJM->LTFIMP_MDU CLTF 0.04 MW 0.04 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 1.02 MW 1.02 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.17 MW 0.17 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
944540 to 243225 ckt 1
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
OP AC 131.92 % 897.0 B 1183.36 24.44
AEP AF2-177 TP-AF1-118 TP 345.0 kV Ckt 2 line
958860 to 944530 ckt 2
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A'
 OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1   /*05KEYSTN     345.0 - 05SORENS     345.0
END
OP AC 113.9 % 971.0 B 1105.94 44.59
AEP 05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1
Base Case OP AC 108.31 % 897.0 A 971.56 9.58
AEP AF1-202 TP-AF1-119 TP 345.0 kV Ckt 1 line
945370 to 944540 ckt 1
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
OP AC 103.54 % 897.0 B 928.73 24.44
AEP 05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
OP AC 103.3 % 1318.0 B 1361.46 24.32

Details for AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line l/o AEP_P1-2_#8702_2543_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
944540 to 243225 ckt 1
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 131.92 %
Rating: 897.0 MVA
Rating Type: B
MVA to Mitigate: 1183.36 MVA
MW Contribution: 24.44 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
AF1-119 TP-05KEYSTN 345.0 kV Ckt 1 line
944540 to 243225 ckt 1
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 132.86 %
Rating: 897.0 MVA
Rating Type: B
MVA to Mitigate: 1191.77 MVA
MW Contribution: 24.54 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C 50/50 0.24 MW 0.24 MW
961762 AG1-017 E 50/50 1.12 MW 1.12 MW
962031 AG1-047 C 50/50 6.47 MW 6.47 MW
962032 AG1-047 E 50/50 4.32 MW 4.32 MW
965031 AG1-367 C 50/50 14.67 MW 14.67 MW
965032 AG1-367 E 50/50 9.78 MW 9.78 MW
965101 AG1-375 C 50/50 14.67 MW 14.67 MW
965102 AG1-375 E 50/50 9.78 MW 9.78 MW
965651 AG1-433 C 50/50 8.29 MW 8.29 MW
965652 AG1-433 E 50/50 38.79 MW 38.79 MW
246991 05WLD G1 C 50/50 0.24 MW 0.24 MW
247255 05WLD G2 C 50/50 0.23 MW 0.23 MW
247285 05AND G1 50/50 0.58 MW 0.58 MW
247287 05AND G3 50/50 1.22 MW 1.22 MW
247288 05RICHG1 50/50 0.6 MW 0.6 MW
247289 05RICHG2 50/50 0.6 MW 0.6 MW
247536 05BLUFF P WF 50/50 0.41 MW 0.41 MW
247543 V3-007 C 50/50 0.92 MW 0.92 MW
247929 S-071 E 50/50 10.04 MW 10.04 MW
247935 V3-007 E 50/50 37.75 MW 37.75 MW
247958 05WLD G2 E 50/50 19.52 MW 19.52 MW
247963 05HDWTR1G E 50/50 37.75 MW 37.75 MW
934961 AD1-128 C 50/50 1.47 MW 1.47 MW
934962 AD1-128 E 50/50 15.68 MW 15.68 MW
936561 AD2-071 C 50/50 7.2 MW 7.2 MW
936562 AD2-071 E 50/50 3.55 MW 3.55 MW
942081 AE2-220 C 50/50 11.39 MW 11.39 MW
942082 AE2-220 E 50/50 15.73 MW 15.73 MW
944031 AF1-071 C Adder 0.64 MW 0.54 MW
944032 AF1-071 E Adder 1.04 MW 0.89 MW
958711 AF2-162 C 50/50 14.12 MW 14.12 MW
958712 AF2-162 E 50/50 7.06 MW 7.06 MW
958821 AF2-173 C 50/50 20.54 MW 20.54 MW
958822 AF2-173 E 50/50 13.69 MW 13.69 MW
960441 AF2-335 C 50/50 9.9 MW 9.9 MW
960442 AF2-335 E 50/50 3.3 MW 3.3 MW
960971 AF2-388 C 50/50 16.57 MW 16.57 MW
960972 AF2-388 E 50/50 77.58 MW 77.58 MW
243415 05WWVSTA 50/50 1.66 MW 1.66 MW
243795 05HDWTR1G C 50/50 0.92 MW 0.92 MW
932681 AC2-090 C 50/50 1.34 MW 1.34 MW
932682 AC2-090 E 50/50 13.45 MW 13.45 MW
939761 AE1-207 C 50/50 7.93 MW 7.93 MW
939762 AE1-207 E 50/50 10.96 MW 10.96 MW
939771 AE1-208 C 50/50 6.37 MW 6.37 MW
939772 AE1-208 E 50/50 8.68 MW 8.68 MW
942071 AE2-219 C 50/50 4.41 MW 4.41 MW
942072 AE2-219 E 50/50 6.08 MW 6.08 MW
926874 AC1-174 E 50/50 13.45 MW 13.45 MW
926881 AC1-175 E 50/50 13.45 MW 13.45 MW
270201 AC2-176 GEN 50/50 0.3 MW 0.3 MW
270209 AC1-174 C 50/50 1.35 MW 1.35 MW
270210 AC1-175 C 50/50 1.35 MW 1.35 MW
270222 AC2-111 C Adder 2.84 MW 2.41 MW
932844 AC2-111 E Adder 4.58 MW 3.89 MW
933596 AC2-176 E 50/50 12.2 MW 12.2 MW
934161 AD1-043 C 50/50 5.31 MW 5.31 MW
934162 AD1-043 E 50/50 8.66 MW 8.66 MW
942791 AE2-297 C O1 50/50 1.84 MW 1.84 MW
942792 AE2-297 E O1 50/50 7.71 MW 7.71 MW
944531 AF1-118 C 50/50 65.71 MW 65.71 MW
944532 AF1-118 E 50/50 19.82 MW 19.82 MW
944541 AF1-119 C 50/50 65.91 MW 65.91 MW
944542 AF1-119 E 50/50 28.25 MW 28.25 MW
945371 AF1-202 C 50/50 14.36 MW 14.36 MW
945372 AF1-202 E 50/50 70.11 MW 70.11 MW
945581 AF1-223 C 50/50 38.01 MW 38.01 MW
945582 AF1-223 E 50/50 25.34 MW 25.34 MW
946032 AF1-268 E 50/50 4.58 MW 4.58 MW
958861 AF2-177 C 50/50 6.36 MW 6.36 MW
958862 AF2-177 E 50/50 42.53 MW 42.53 MW
960791 AF2-370 C 50/50 3.3 MW 3.3 MW
961161 AF2-407 C 50/50 45.27 MW 45.27 MW
961171 AF2-408 C 50/50 11.16 MW 11.16 MW
243362 05RANDOLPH1 50/50 0.07 MW 0.07 MW
939781 AE1-209 C 50/50 3.18 MW 3.18 MW
939782 AE1-209 E 50/50 21.27 MW 21.27 MW
939791 AE1-210 C 50/50 3.18 MW 3.18 MW
939792 AE1-210 E 50/50 21.27 MW 21.27 MW
946031 AF1-268 C 50/50 10.11 MW 10.11 MW
964351 AG1-297 C Adder 6.15 MW 5.23 MW
964352 AG1-297 E Adder 18.45 MW 15.68 MW
964611 AG1-324 C 50/50 3.41 MW 3.41 MW
964612 AG1-324 E 50/50 1.36 MW 1.36 MW
941691 AE2-169 C 50/50 3.82 MW 3.82 MW
941721 AE2-172 C 50/50 4.72 MW 4.72 MW
957741 AF2-068 C 50/50 9.71 MW 9.71 MW
957742 AF2-068 E 50/50 6.47 MW 6.47 MW
965461 AG1-414 C Adder 4.25 MW 3.62 MW
965462 AG1-414 E Adder 2.84 MW 2.41 MW
955152 J993 G External Queue 18.15 MW 18.15 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 13.64 MW 13.64 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.68 MW 10.68 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.13 MW 0.13 MW
VTF LTFEXP_VFT->PJM CMTX 0.35 MW 0.35 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.29 MW 2.29 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.83 MW 0.83 MW
TVA LTFEXP_TVA->PJM CLTF 2.48 MW 2.48 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.53 MW 2.53 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.43 MW 0.43 MW
MDU PJM->LTFIMP_MDU CLTF 0.04 MW 0.04 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.41 MW 0.41 MW

Details for AF2-177 TP-AF1-118 TP 345.0 kV Ckt 2 line l/o AEP_P1-2_#4817_6341_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
AF2-177 TP-AF1-118 TP 345.0 kV Ckt 2 line
958860 to 944530 ckt 2
Contingency Name:
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A'
 OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1   /*05KEYSTN     345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 113.9 %
Rating: 971.0 MVA
Rating Type: B
MVA to Mitigate: 1105.94 MVA
MW Contribution: 44.59 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
AF2-177 TP-AF1-118 TP 345.0 kV Ckt 2 line
958860 to 944530 ckt 2
Contingency Name:
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A'
 OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1   /*05KEYSTN     345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 114.85 %
Rating: 971.0 MVA
Rating Type: B
MVA to Mitigate: 1115.15 MVA
MW Contribution: 44.66 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C 50/50 0.24 MW 0.24 MW
961762 AG1-017 E 50/50 1.12 MW 1.12 MW
962031 AG1-047 C 50/50 6.49 MW 6.49 MW
962032 AG1-047 E 50/50 4.33 MW 4.33 MW
965031 AG1-367 C 50/50 14.77 MW 14.77 MW
965032 AG1-367 E 50/50 9.85 MW 9.85 MW
965101 AG1-375 C 50/50 26.76 MW 26.76 MW
965102 AG1-375 E 50/50 17.84 MW 17.84 MW
965651 AG1-433 C 50/50 4.33 MW 4.33 MW
965652 AG1-433 E 50/50 20.28 MW 20.28 MW
246991 05WLD G1 C 50/50 0.24 MW 0.24 MW
247255 05WLD G2 C 50/50 0.23 MW 0.23 MW
247288 05RICHG1 50/50 0.6 MW 0.6 MW
247289 05RICHG2 50/50 0.6 MW 0.6 MW
247292 05KEY G1 50/50 2.32 MW 2.32 MW
247293 05KEY G2 50/50 2.34 MW 2.34 MW
247294 05KEY G3 50/50 2.38 MW 2.38 MW
247295 05KEY G4 50/50 2.41 MW 2.41 MW
247543 V3-007 C 50/50 0.93 MW 0.93 MW
247929 S-071 E Adder 10.07 MW 8.56 MW
247935 V3-007 E 50/50 38.0 MW 38.0 MW
247958 05WLD G2 E 50/50 19.58 MW 19.58 MW
247963 05HDWTR1G E 50/50 38.0 MW 38.0 MW
934961 AD1-128 C 50/50 1.48 MW 1.48 MW
934962 AD1-128 E 50/50 15.76 MW 15.76 MW
936561 AD2-071 C 50/50 7.22 MW 7.22 MW
936562 AD2-071 E 50/50 3.56 MW 3.56 MW
942081 AE2-220 C 50/50 11.47 MW 11.47 MW
942082 AE2-220 E 50/50 15.84 MW 15.84 MW
944031 AF1-071 C Adder 0.64 MW 0.54 MW
944032 AF1-071 E Adder 1.04 MW 0.89 MW
958711 AF2-162 C 50/50 7.38 MW 7.38 MW
958712 AF2-162 E 50/50 3.69 MW 3.69 MW
958821 AF2-173 C 50/50 20.68 MW 20.68 MW
958822 AF2-173 E 50/50 13.79 MW 13.79 MW
960441 AF2-335 C 50/50 9.96 MW 9.96 MW
960442 AF2-335 E 50/50 3.32 MW 3.32 MW
960971 AF2-388 C 50/50 8.66 MW 8.66 MW
960972 AF2-388 E 50/50 40.56 MW 40.56 MW
243795 05HDWTR1G C 50/50 0.93 MW 0.93 MW
932681 AC2-090 C 50/50 1.35 MW 1.35 MW
932682 AC2-090 E 50/50 13.54 MW 13.54 MW
939761 AE1-207 C 50/50 7.96 MW 7.96 MW
939762 AE1-207 E 50/50 10.99 MW 10.99 MW
939771 AE1-208 C 50/50 6.38 MW 6.38 MW
939772 AE1-208 E 50/50 8.71 MW 8.71 MW
942071 AE2-219 C Adder 4.42 MW 3.75 MW
942072 AE2-219 E Adder 6.1 MW 5.18 MW
247968 Z2-115 E Adder 0.09 MW 0.08 MW
926874 AC1-174 E 50/50 13.54 MW 13.54 MW
926881 AC1-175 E 50/50 13.54 MW 13.54 MW
270201 AC2-176 GEN 50/50 0.3 MW 0.3 MW
270209 AC1-174 C 50/50 1.36 MW 1.36 MW
270210 AC1-175 C 50/50 1.36 MW 1.36 MW
270222 AC2-111 C Adder 2.84 MW 2.41 MW
932844 AC2-111 E Adder 4.59 MW 3.9 MW
933596 AC2-176 E 50/50 12.24 MW 12.24 MW
934161 AD1-043 C 50/50 5.33 MW 5.33 MW
934162 AD1-043 E 50/50 8.69 MW 8.69 MW
942791 AE2-297 C O1 50/50 1.85 MW 1.85 MW
942792 AE2-297 E O1 50/50 7.74 MW 7.74 MW
944541 AF1-119 C 50/50 34.46 MW 34.46 MW
944542 AF1-119 E 50/50 14.77 MW 14.77 MW
945371 AF1-202 C 50/50 8.37 MW 8.37 MW
945372 AF1-202 E 50/50 40.86 MW 40.86 MW
945581 AF1-223 C 50/50 22.16 MW 22.16 MW
945582 AF1-223 E 50/50 14.77 MW 14.77 MW
946032 AF1-268 E 50/50 4.61 MW 4.61 MW
958861 AF2-177 C 50/50 11.6 MW 11.6 MW
958862 AF2-177 E 50/50 77.59 MW 77.59 MW
960791 AF2-370 C 50/50 3.32 MW 3.32 MW
961161 AF2-407 C 50/50 45.5 MW 45.5 MW
961171 AF2-408 C 50/50 11.21 MW 11.21 MW
939781 AE1-209 C 50/50 3.2 MW 3.2 MW
939782 AE1-209 E 50/50 21.42 MW 21.42 MW
939791 AE1-210 C 50/50 3.2 MW 3.2 MW
939792 AE1-210 E 50/50 21.42 MW 21.42 MW
946031 AF1-268 C 50/50 10.16 MW 10.16 MW
964351 AG1-297 C Adder 6.15 MW 5.23 MW
964352 AG1-297 E Adder 18.45 MW 15.69 MW
964611 AG1-324 C 50/50 3.42 MW 3.42 MW
964612 AG1-324 E 50/50 1.36 MW 1.36 MW
941691 AE2-169 C 50/50 3.83 MW 3.83 MW
941721 AE2-172 C 50/50 4.74 MW 4.74 MW
957741 AF2-068 C 50/50 9.74 MW 9.74 MW
957742 AF2-068 E 50/50 6.49 MW 6.49 MW
965461 AG1-414 C Adder 4.26 MW 3.62 MW
965462 AG1-414 E Adder 2.84 MW 2.41 MW
955152 J993 G External Queue 18.34 MW 18.34 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 13.23 MW 13.23 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 9.94 MW 9.94 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.03 MW 0.03 MW
NY PJM->LTFIMP_NY CLTF 0.06 MW 0.06 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.27 MW 2.27 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.76 MW 0.76 MW
TVA LTFEXP_TVA->PJM CLTF 2.39 MW 2.39 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.41 MW 2.41 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.43 MW 0.43 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.21 MW 0.21 MW
MDU PJM->LTFIMP_MDU CLTF 0.05 MW 0.05 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.37 MW 0.37 MW

Details for 05KEYSTN-05SORENS 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 108.31 %
Rating: 897.0 MVA
Rating Type: A
MVA to Mitigate: 971.56 MVA
MW Contribution: 9.58 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1
Contingency Name:
Base Case
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 108.89 %
Rating: 897.0 MVA
Rating Type: A
MVA to Mitigate: 976.73 MVA
MW Contribution: 9.62 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C Adder 0.18 MW 0.15 MW
961762 AG1-017 E Adder 0.81 MW 0.69 MW
962031 AG1-047 C Adder 4.68 MW 3.98 MW
962032 AG1-047 E Adder 3.12 MW 2.65 MW
965031 AG1-367 C 50/50 10.69 MW 10.69 MW
965032 AG1-367 E 50/50 7.13 MW 7.13 MW
965101 AG1-375 C Adder 5.75 MW 4.88 MW
965102 AG1-375 E Adder 3.83 MW 3.26 MW
965651 AG1-433 C 50/50 7.71 MW 7.71 MW
965652 AG1-433 E 50/50 36.11 MW 36.11 MW
247292 05KEY G1 50/50 5.16 MW 5.16 MW
247293 05KEY G2 50/50 5.19 MW 5.19 MW
247294 05KEY G3 50/50 5.28 MW 5.28 MW
247295 05KEY G4 50/50 5.35 MW 5.35 MW
247543 V3-007 C 50/50 0.67 MW 0.67 MW
247929 S-071 E Adder 7.26 MW 6.17 MW
247935 V3-007 E 50/50 27.48 MW 27.48 MW
247958 05WLD G2 E Adder 14.12 MW 12.0 MW
247963 05HDWTR1G E 50/50 27.48 MW 27.48 MW
934961 AD1-128 C 50/50 1.07 MW 1.07 MW
934962 AD1-128 E 50/50 11.39 MW 11.39 MW
936561 AD2-071 C Adder 5.21 MW 4.42 MW
936562 AD2-071 E Adder 2.56 MW 2.18 MW
942081 AE2-220 C 50/50 8.29 MW 8.29 MW
942082 AE2-220 E 50/50 11.45 MW 11.45 MW
958711 AF2-162 C 50/50 13.15 MW 13.15 MW
958712 AF2-162 E 50/50 6.57 MW 6.57 MW
958821 AF2-173 C 50/50 14.96 MW 14.96 MW
958822 AF2-173 E 50/50 9.98 MW 9.98 MW
960441 AF2-335 C 50/50 7.19 MW 7.19 MW
960442 AF2-335 E 50/50 2.4 MW 2.4 MW
960971 AF2-388 C 50/50 15.43 MW 15.43 MW
960972 AF2-388 E 50/50 72.22 MW 72.22 MW
243795 05HDWTR1G C 50/50 0.67 MW 0.67 MW
932681 AC2-090 C 50/50 0.98 MW 0.98 MW
932682 AC2-090 E 50/50 9.79 MW 9.79 MW
939761 AE1-207 C Adder 5.74 MW 4.88 MW
939762 AE1-207 E Adder 7.93 MW 6.74 MW
939771 AE1-208 C Adder 4.61 MW 3.92 MW
939772 AE1-208 E Adder 6.28 MW 5.34 MW
942071 AE2-219 C Adder 3.18 MW 2.71 MW
942072 AE2-219 E Adder 4.4 MW 3.74 MW
926874 AC1-174 E 50/50 9.79 MW 9.79 MW
926881 AC1-175 E 50/50 9.79 MW 9.79 MW
270209 AC1-174 C 50/50 0.98 MW 0.98 MW
270210 AC1-175 C 50/50 0.98 MW 0.98 MW
933596 AC2-176 E Adder 8.82 MW 7.5 MW
934161 AD1-043 C Adder 3.84 MW 3.27 MW
934162 AD1-043 E Adder 6.27 MW 5.33 MW
942792 AE2-297 E O1 Adder 5.59 MW 4.75 MW
944541 AF1-119 C 50/50 61.35 MW 61.35 MW
944542 AF1-119 E 50/50 26.29 MW 26.29 MW
945371 AF1-202 C 50/50 13.01 MW 13.01 MW
945372 AF1-202 E 50/50 63.51 MW 63.51 MW
945581 AF1-223 C 50/50 34.43 MW 34.43 MW
945582 AF1-223 E 50/50 22.95 MW 22.95 MW
946032 AF1-268 E 50/50 3.33 MW 3.33 MW
958861 AF2-177 C Adder 2.49 MW 2.12 MW
958862 AF2-177 E Adder 16.66 MW 14.16 MW
960791 AF2-370 C 50/50 2.4 MW 2.4 MW
961161 AF2-407 C 50/50 32.86 MW 32.86 MW
961171 AF2-408 C 50/50 8.1 MW 8.1 MW
939781 AE1-209 C 50/50 2.32 MW 2.32 MW
939782 AE1-209 E 50/50 15.5 MW 15.5 MW
939791 AE1-210 C 50/50 2.32 MW 2.32 MW
939792 AE1-210 E 50/50 15.5 MW 15.5 MW
946031 AF1-268 C 50/50 7.35 MW 7.35 MW
964611 AG1-324 C Adder 2.47 MW 2.1 MW
964612 AG1-324 E Adder 0.98 MW 0.83 MW
941691 AE2-169 C Adder 2.76 MW 2.35 MW
941721 AE2-172 C Adder 3.42 MW 2.91 MW
957741 AF2-068 C Adder 7.02 MW 5.97 MW
957742 AF2-068 E Adder 4.68 MW 3.98 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 9.3 MW 9.3 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 6.75 MW 6.75 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.07 MW 0.07 MW
NY PJM->LTFIMP_NY CLTF 0.07 MW 0.07 MW
LGEE LTFEXP_LGEE->PJM CLTF 1.62 MW 1.62 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.51 MW 0.51 MW
TVA LTFEXP_TVA->PJM CLTF 1.67 MW 1.67 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.67 MW 1.67 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.31 MW 0.31 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.46 MW 0.46 MW
MDU PJM->LTFIMP_MDU CLTF 0.04 MW 0.04 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.25 MW 0.25 MW

Details for AF1-202 TP-AF1-119 TP 345.0 kV Ckt 1 line l/o AEP_P1-2_#8702_2543_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
AF1-202 TP-AF1-119 TP 345.0 kV Ckt 1 line
945370 to 944540 ckt 1
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.54 %
Rating: 897.0 MVA
Rating Type: B
MVA to Mitigate: 928.73 MVA
MW Contribution: 24.44 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
AF1-202 TP-AF1-119 TP 345.0 kV Ckt 1 line
945370 to 944540 ckt 1
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 104.41 %
Rating: 897.0 MVA
Rating Type: B
MVA to Mitigate: 936.58 MVA
MW Contribution: 24.54 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C 50/50 0.24 MW 0.24 MW
961762 AG1-017 E 50/50 1.12 MW 1.12 MW
962031 AG1-047 C 50/50 6.47 MW 6.47 MW
962032 AG1-047 E 50/50 4.32 MW 4.32 MW
965031 AG1-367 C 50/50 14.67 MW 14.67 MW
965032 AG1-367 E 50/50 9.78 MW 9.78 MW
965101 AG1-375 C 50/50 14.67 MW 14.67 MW
965102 AG1-375 E 50/50 9.78 MW 9.78 MW
246991 05WLD G1 C 50/50 0.24 MW 0.24 MW
247255 05WLD G2 C 50/50 0.23 MW 0.23 MW
247285 05AND G1 50/50 0.58 MW 0.58 MW
247287 05AND G3 50/50 1.22 MW 1.22 MW
247288 05RICHG1 50/50 0.6 MW 0.6 MW
247289 05RICHG2 50/50 0.6 MW 0.6 MW
247536 05BLUFF P WF 50/50 0.41 MW 0.41 MW
247543 V3-007 C 50/50 0.92 MW 0.92 MW
247929 S-071 E 50/50 10.04 MW 10.04 MW
247935 V3-007 E 50/50 37.75 MW 37.75 MW
247958 05WLD G2 E 50/50 19.52 MW 19.52 MW
247963 05HDWTR1G E 50/50 37.75 MW 37.75 MW
934961 AD1-128 C 50/50 1.47 MW 1.47 MW
934962 AD1-128 E 50/50 15.68 MW 15.68 MW
936561 AD2-071 C 50/50 7.2 MW 7.2 MW
936562 AD2-071 E 50/50 3.55 MW 3.55 MW
942081 AE2-220 C 50/50 11.39 MW 11.39 MW
942082 AE2-220 E 50/50 15.73 MW 15.73 MW
944031 AF1-071 C Adder 0.64 MW 0.54 MW
944032 AF1-071 E Adder 1.04 MW 0.89 MW
958821 AF2-173 C 50/50 20.54 MW 20.54 MW
958822 AF2-173 E 50/50 13.69 MW 13.69 MW
960441 AF2-335 C 50/50 9.9 MW 9.9 MW
960442 AF2-335 E 50/50 3.3 MW 3.3 MW
243415 05WWVSTA 50/50 1.66 MW 1.66 MW
243795 05HDWTR1G C 50/50 0.92 MW 0.92 MW
932681 AC2-090 C 50/50 1.34 MW 1.34 MW
932682 AC2-090 E 50/50 13.45 MW 13.45 MW
939761 AE1-207 C 50/50 7.93 MW 7.93 MW
939762 AE1-207 E 50/50 10.96 MW 10.96 MW
939771 AE1-208 C 50/50 6.37 MW 6.37 MW
939772 AE1-208 E 50/50 8.68 MW 8.68 MW
942071 AE2-219 C 50/50 4.41 MW 4.41 MW
942072 AE2-219 E 50/50 6.08 MW 6.08 MW
926874 AC1-174 E 50/50 13.45 MW 13.45 MW
926881 AC1-175 E 50/50 13.45 MW 13.45 MW
270201 AC2-176 GEN 50/50 0.3 MW 0.3 MW
270209 AC1-174 C 50/50 1.35 MW 1.35 MW
270210 AC1-175 C 50/50 1.35 MW 1.35 MW
270222 AC2-111 C Adder 2.84 MW 2.41 MW
932844 AC2-111 E Adder 4.58 MW 3.89 MW
933596 AC2-176 E 50/50 12.2 MW 12.2 MW
934161 AD1-043 C 50/50 5.31 MW 5.31 MW
934162 AD1-043 E 50/50 8.66 MW 8.66 MW
942791 AE2-297 C O1 50/50 1.84 MW 1.84 MW
942792 AE2-297 E O1 50/50 7.71 MW 7.71 MW
944531 AF1-118 C 50/50 65.71 MW 65.71 MW
944532 AF1-118 E 50/50 19.82 MW 19.82 MW
945371 AF1-202 C 50/50 14.36 MW 14.36 MW
945372 AF1-202 E 50/50 70.11 MW 70.11 MW
945581 AF1-223 C 50/50 38.01 MW 38.01 MW
945582 AF1-223 E 50/50 25.34 MW 25.34 MW
946032 AF1-268 E 50/50 4.58 MW 4.58 MW
958861 AF2-177 C 50/50 6.36 MW 6.36 MW
958862 AF2-177 E 50/50 42.53 MW 42.53 MW
960791 AF2-370 C 50/50 3.3 MW 3.3 MW
961161 AF2-407 C 50/50 45.27 MW 45.27 MW
961171 AF2-408 C 50/50 11.16 MW 11.16 MW
243362 05RANDOLPH1 50/50 0.07 MW 0.07 MW
939781 AE1-209 C 50/50 3.18 MW 3.18 MW
939782 AE1-209 E 50/50 21.27 MW 21.27 MW
939791 AE1-210 C 50/50 3.18 MW 3.18 MW
939792 AE1-210 E 50/50 21.27 MW 21.27 MW
946031 AF1-268 C 50/50 10.11 MW 10.11 MW
964351 AG1-297 C Adder 6.15 MW 5.23 MW
964352 AG1-297 E Adder 18.45 MW 15.68 MW
964611 AG1-324 C 50/50 3.41 MW 3.41 MW
964612 AG1-324 E 50/50 1.36 MW 1.36 MW
941691 AE2-169 C 50/50 3.82 MW 3.82 MW
941721 AE2-172 C 50/50 4.72 MW 4.72 MW
957741 AF2-068 C 50/50 9.71 MW 9.71 MW
957742 AF2-068 E 50/50 6.47 MW 6.47 MW
965461 AG1-414 C Adder 4.25 MW 3.62 MW
965462 AG1-414 E Adder 2.84 MW 2.41 MW
955152 J993 G External Queue 18.15 MW 18.15 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 13.64 MW 13.64 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.68 MW 10.68 MW
G-007A LTFEXP_G-007A->PJM CMTX 0.13 MW 0.13 MW
VTF LTFEXP_VFT->PJM CMTX 0.35 MW 0.35 MW
NY PJM->LTFIMP_NY CLTF 0.01 MW 0.01 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.29 MW 2.29 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.83 MW 0.83 MW
TVA LTFEXP_TVA->PJM CLTF 2.48 MW 2.48 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.53 MW 2.53 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.43 MW 0.43 MW
MDU PJM->LTFIMP_MDU CLTF 0.04 MW 0.04 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.41 MW 0.41 MW

Details for 05KEYSTN-05SORENS 345.0 kV Ckt 1 line l/o AEP_P1-2_#8702_2543_SRT-A-C


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.3 %
Rating: 1318.0 MVA
Rating Type: B
MVA to Mitigate: 1361.46 MVA
MW Contribution: 24.32 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP
Facility Description:
05KEYSTN-05SORENS 345.0 kV Ckt 1 line
243225 to 243232 ckt 1
Contingency Name:
AEP_P1-2_#8702_2543_SRT-A-C
CONTINGENCY 'AEP_P1-2_#8702_2543_SRT-A-C'
 OPEN BRANCH FROM BUS 944530 TO BUS 243232 CKT 2   /*AF1-118 TP   345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 103.99 %
Rating: 1318.0 MVA
Rating Type: B
MVA to Mitigate: 1370.53 MVA
MW Contribution: 24.42 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C 50/50 0.24 MW 0.24 MW
961762 AG1-017 E 50/50 1.11 MW 1.11 MW
962031 AG1-047 C 50/50 6.4 MW 6.4 MW
962032 AG1-047 E 50/50 4.27 MW 4.27 MW
965031 AG1-367 C 50/50 14.6 MW 14.6 MW
965032 AG1-367 E 50/50 9.73 MW 9.73 MW
965101 AG1-375 C 50/50 14.59 MW 14.59 MW
965102 AG1-375 E 50/50 9.73 MW 9.73 MW
965651 AG1-433 C 50/50 8.26 MW 8.26 MW
965652 AG1-433 E 50/50 38.69 MW 38.69 MW
246991 05WLD G1 C 50/50 0.24 MW 0.24 MW
247255 05WLD G2 C 50/50 0.23 MW 0.23 MW
247288 05RICHG1 50/50 0.59 MW 0.59 MW
247289 05RICHG2 50/50 0.59 MW 0.59 MW
247292 05KEY G1 50/50 5.33 MW 5.33 MW
247293 05KEY G2 50/50 5.35 MW 5.35 MW
247294 05KEY G3 50/50 5.45 MW 5.45 MW
247295 05KEY G4 50/50 5.52 MW 5.52 MW
247543 V3-007 C 50/50 0.92 MW 0.92 MW
247929 S-071 E Adder 9.93 MW 8.44 MW
247935 V3-007 E 50/50 37.54 MW 37.54 MW
247958 05WLD G2 E 50/50 19.3 MW 19.3 MW
247963 05HDWTR1G E 50/50 37.54 MW 37.54 MW
934961 AD1-128 C 50/50 1.46 MW 1.46 MW
934962 AD1-128 E 50/50 15.56 MW 15.56 MW
936561 AD2-071 C 50/50 7.12 MW 7.12 MW
936562 AD2-071 E 50/50 3.51 MW 3.51 MW
942081 AE2-220 C 50/50 11.33 MW 11.33 MW
942082 AE2-220 E 50/50 15.64 MW 15.64 MW
944031 AF1-071 C Adder 0.63 MW 0.54 MW
944032 AF1-071 E Adder 1.03 MW 0.87 MW
958711 AF2-162 C 50/50 14.09 MW 14.09 MW
958712 AF2-162 E 50/50 7.04 MW 7.04 MW
958821 AF2-173 C 50/50 20.44 MW 20.44 MW
958822 AF2-173 E 50/50 13.62 MW 13.62 MW
960441 AF2-335 C 50/50 9.83 MW 9.83 MW
960442 AF2-335 E 50/50 3.28 MW 3.28 MW
960971 AF2-388 C 50/50 16.53 MW 16.53 MW
960972 AF2-388 E 50/50 77.38 MW 77.38 MW
243795 05HDWTR1G C 50/50 0.92 MW 0.92 MW
932681 AC2-090 C 50/50 1.34 MW 1.34 MW
932682 AC2-090 E 50/50 13.38 MW 13.38 MW
939761 AE1-207 C 50/50 7.85 MW 7.85 MW
939762 AE1-207 E 50/50 10.84 MW 10.84 MW
939771 AE1-208 C 50/50 6.3 MW 6.3 MW
939772 AE1-208 E 50/50 8.59 MW 8.59 MW
942071 AE2-219 C Adder 4.35 MW 3.7 MW
942072 AE2-219 E Adder 6.01 MW 5.11 MW
926874 AC1-174 E 50/50 13.38 MW 13.38 MW
926881 AC1-175 E 50/50 13.38 MW 13.38 MW
270201 AC2-176 GEN 50/50 0.29 MW 0.29 MW
270209 AC1-174 C 50/50 1.34 MW 1.34 MW
270210 AC1-175 C 50/50 1.34 MW 1.34 MW
270222 AC2-111 C Adder 2.8 MW 2.38 MW
932844 AC2-111 E Adder 4.52 MW 3.84 MW
933596 AC2-176 E 50/50 12.06 MW 12.06 MW
934161 AD1-043 C 50/50 5.25 MW 5.25 MW
934162 AD1-043 E 50/50 8.57 MW 8.57 MW
942791 AE2-297 C O1 50/50 1.82 MW 1.82 MW
942792 AE2-297 E O1 50/50 7.64 MW 7.64 MW
944531 AF1-118 C 50/50 65.38 MW 65.38 MW
944532 AF1-118 E 50/50 19.72 MW 19.72 MW
944541 AF1-119 C 50/50 65.73 MW 65.73 MW
944542 AF1-119 E 50/50 28.17 MW 28.17 MW
945371 AF1-202 C 50/50 14.32 MW 14.32 MW
945372 AF1-202 E 50/50 69.91 MW 69.91 MW
945581 AF1-223 C 50/50 37.9 MW 37.9 MW
945582 AF1-223 E 50/50 25.27 MW 25.27 MW
946032 AF1-268 E 50/50 4.55 MW 4.55 MW
958861 AF2-177 C 50/50 6.32 MW 6.32 MW
958862 AF2-177 E 50/50 42.32 MW 42.32 MW
960791 AF2-370 C 50/50 3.28 MW 3.28 MW
961161 AF2-407 C 50/50 44.91 MW 44.91 MW
961171 AF2-408 C 50/50 11.06 MW 11.06 MW
939781 AE1-209 C 50/50 3.16 MW 3.16 MW
939782 AE1-209 E 50/50 21.17 MW 21.17 MW
939791 AE1-210 C 50/50 3.16 MW 3.16 MW
939792 AE1-210 E 50/50 21.17 MW 21.17 MW
946031 AF1-268 C 50/50 10.04 MW 10.04 MW
964611 AG1-324 C 50/50 3.37 MW 3.37 MW
964612 AG1-324 E 50/50 1.34 MW 1.34 MW
941691 AE2-169 C 50/50 3.78 MW 3.78 MW
941721 AE2-172 C 50/50 4.67 MW 4.67 MW
957741 AF2-068 C 50/50 9.6 MW 9.6 MW
957742 AF2-068 E 50/50 6.4 MW 6.4 MW
965461 AG1-414 C Adder 4.2 MW 3.57 MW
965462 AG1-414 E Adder 2.8 MW 2.38 MW
955152 J993 G External Queue 18.15 MW 18.15 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 12.84 MW 12.84 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 9.43 MW 9.43 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.07 MW 0.07 MW
NY PJM->LTFIMP_NY CLTF 0.08 MW 0.08 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.22 MW 2.22 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.71 MW 0.71 MW
TVA LTFEXP_TVA->PJM CLTF 2.31 MW 2.31 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.31 MW 2.31 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.42 MW 0.42 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.47 MW 0.47 MW
MDU PJM->LTFIMP_MDU CLTF 0.05 MW 0.05 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.35 MW 0.35 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP AF1-118 TP-05SORENS 345.0 kV Ckt 2 line
944530 to 243232 ckt 2
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A'
 OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1   /*05KEYSTN     345.0 - 05SORENS     345.0
END
OP AC 100.62 % 1318.0 B 1326.14 44.66

Details for AF1-118 TP-05SORENS 345.0 kV Ckt 2 line l/o AEP_P1-2_#4817_6341_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: AEP
Facility Description:
AF1-118 TP-05SORENS 345.0 kV Ckt 2 line
944530 to 243232 ckt 2
Contingency Name:
AEP_P1-2_#4817_6341_SRT-A
CONTINGENCY 'AEP_P1-2_#4817_6341_SRT-A'
 OPEN BRANCH FROM BUS 243225 TO BUS 243232 CKT 1   /*05KEYSTN     345.0 - 05SORENS     345.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 100.62 %
Rating: 1318.0 MVA
Rating Type: B
MVA to Mitigate: 1326.14 MVA
MW Contribution: 44.66 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
961761 AG1-017 C 50/50 0.25 MW 0.25 MW
961762 AG1-017 E 50/50 1.13 MW 1.13 MW
962031 AG1-047 C 50/50 6.54 MW 6.54 MW
962032 AG1-047 E 50/50 4.36 MW 4.36 MW
965031 AG1-367 C 50/50 14.83 MW 14.83 MW
965032 AG1-367 E 50/50 9.89 MW 9.89 MW
965101 AG1-375 C 50/50 26.8 MW 26.8 MW
965102 AG1-375 E 50/50 17.87 MW 17.87 MW
965651 AG1-433 C 50/50 4.35 MW 4.35 MW
965652 AG1-433 E 50/50 20.36 MW 20.36 MW
246991 05WLD G1 C 50/50 0.24 MW 0.24 MW
247255 05WLD G2 C 50/50 0.24 MW 0.24 MW
247288 05RICHG1 50/50 0.61 MW 0.61 MW
247289 05RICHG2 50/50 0.61 MW 0.61 MW
247292 05KEY G1 50/50 2.33 MW 2.33 MW
247293 05KEY G2 50/50 2.34 MW 2.34 MW
247294 05KEY G3 50/50 2.38 MW 2.38 MW
247295 05KEY G4 50/50 2.41 MW 2.41 MW
247543 V3-007 C 50/50 0.93 MW 0.93 MW
247929 S-071 E Adder 10.16 MW 8.63 MW
247935 V3-007 E 50/50 38.21 MW 38.21 MW
247958 05WLD G2 E 50/50 19.68 MW 19.68 MW
247963 05HDWTR1G E 50/50 38.21 MW 38.21 MW
934961 AD1-128 C 50/50 1.48 MW 1.48 MW
934962 AD1-128 E 50/50 15.86 MW 15.86 MW
936561 AD2-071 C 50/50 7.26 MW 7.26 MW
936562 AD2-071 E 50/50 3.58 MW 3.58 MW
942081 AE2-220 C 50/50 11.53 MW 11.53 MW
942082 AE2-220 E 50/50 15.92 MW 15.92 MW
944031 AF1-071 C Adder 0.65 MW 0.55 MW
944032 AF1-071 E Adder 1.06 MW 0.9 MW
958711 AF2-162 C 50/50 7.41 MW 7.41 MW
958712 AF2-162 E 50/50 3.71 MW 3.71 MW
958821 AF2-173 C 50/50 20.77 MW 20.77 MW
958822 AF2-173 E 50/50 13.85 MW 13.85 MW
960441 AF2-335 C 50/50 10.01 MW 10.01 MW
960442 AF2-335 E 50/50 3.34 MW 3.34 MW
960971 AF2-388 C 50/50 8.7 MW 8.7 MW
960972 AF2-388 E 50/50 40.73 MW 40.73 MW
243795 05HDWTR1G C 50/50 0.93 MW 0.93 MW
932681 AC2-090 C 50/50 1.36 MW 1.36 MW
932682 AC2-090 E 50/50 13.61 MW 13.61 MW
939761 AE1-207 C 50/50 7.99 MW 7.99 MW
939762 AE1-207 E 50/50 11.04 MW 11.04 MW
939771 AE1-208 C 50/50 6.42 MW 6.42 MW
939772 AE1-208 E 50/50 8.76 MW 8.76 MW
942071 AE2-219 C Adder 4.46 MW 3.79 MW
942072 AE2-219 E Adder 6.16 MW 5.23 MW
247968 Z2-115 E Adder 0.09 MW 0.08 MW
926874 AC1-174 E 50/50 13.61 MW 13.61 MW
926881 AC1-175 E 50/50 13.61 MW 13.61 MW
270201 AC2-176 GEN 50/50 0.3 MW 0.3 MW
270209 AC1-174 C 50/50 1.36 MW 1.36 MW
270210 AC1-175 C 50/50 1.36 MW 1.36 MW
270222 AC2-111 C Adder 2.88 MW 2.45 MW
932844 AC2-111 E Adder 4.66 MW 3.96 MW
933596 AC2-176 E 50/50 12.33 MW 12.33 MW
934161 AD1-043 C 50/50 5.36 MW 5.36 MW
934162 AD1-043 E 50/50 8.74 MW 8.74 MW
942791 AE2-297 C O1 50/50 1.86 MW 1.86 MW
942792 AE2-297 E O1 50/50 7.81 MW 7.81 MW
944531 AF1-118 C 50/50 163.47 MW 163.47 MW
944532 AF1-118 E 50/50 49.3 MW 49.3 MW
944541 AF1-119 C 50/50 34.6 MW 34.6 MW
944542 AF1-119 E 50/50 14.83 MW 14.83 MW
945371 AF1-202 C 50/50 8.4 MW 8.4 MW
945372 AF1-202 E 50/50 41.03 MW 41.03 MW
945581 AF1-223 C 50/50 22.24 MW 22.24 MW
945582 AF1-223 E 50/50 14.83 MW 14.83 MW
946032 AF1-268 E 50/50 4.63 MW 4.63 MW
958861 AF2-177 C 50/50 11.61 MW 11.61 MW
958862 AF2-177 E 50/50 77.72 MW 77.72 MW
960791 AF2-370 C 50/50 3.34 MW 3.34 MW
961161 AF2-407 C 50/50 45.77 MW 45.77 MW
961171 AF2-408 C 50/50 11.28 MW 11.28 MW
939781 AE1-209 C 50/50 3.21 MW 3.21 MW
939782 AE1-209 E 50/50 21.51 MW 21.51 MW
939791 AE1-210 C 50/50 3.21 MW 3.21 MW
939792 AE1-210 E 50/50 21.51 MW 21.51 MW
946031 AF1-268 C 50/50 10.21 MW 10.21 MW
964351 AG1-297 C Adder 6.25 MW 5.31 MW
964352 AG1-297 E Adder 18.74 MW 15.93 MW
964611 AG1-324 C 50/50 3.44 MW 3.44 MW
964612 AG1-324 E 50/50 1.37 MW 1.37 MW
941691 AE2-169 C 50/50 3.85 MW 3.85 MW
941721 AE2-172 C 50/50 4.76 MW 4.76 MW
957741 AF2-068 C 50/50 9.81 MW 9.81 MW
957742 AF2-068 E 50/50 6.54 MW 6.54 MW
965461 AG1-414 C Adder 4.28 MW 3.63 MW
965462 AG1-414 E Adder 2.85 MW 2.42 MW
955152 J993 G External Queue 18.45 MW 18.45 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 13.59 MW 13.59 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 10.48 MW 10.48 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.06 MW 0.06 MW
NY PJM->LTFIMP_NY CLTF 0.07 MW 0.07 MW
LGEE LTFEXP_LGEE->PJM CLTF 2.42 MW 2.42 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.8 MW 0.8 MW
TVA LTFEXP_TVA->PJM CLTF 2.5 MW 2.5 MW
LAGN LTFEXP_LAGN->PJM CLTF 2.51 MW 2.51 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.44 MW 0.44 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.42 MW 0.42 MW
MDU PJM->LTFIMP_MDU CLTF 0.05 MW 0.05 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.39 MW 0.39 MW

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

Light Load Analysis is Not Required.

Light Load Potential Congestion due to Local Energy Deliverability

Light Load Analysis is Not Required.

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 62 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 199 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-173, AF2-177, AF2-407, AG1-367 and AG1-375 meet the 0.95 leading and lagging PF requirement.

 

AF2-173 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-173, setting Ki to 0.15 from its original value of 0.5.

 

AF2-177 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-177, setting Ki to 0.15 from its original value of 0.5.

 

AG1-367 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-367, setting Kc to 0.1 from its original value of 0.

 

AG1-375 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-375, setting Kc to 0.1 from its original value of 0.

 

AF2-407 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc, Ki and Kp parameters in the plant controller (REPCA1) for AF2-407, setting Kc to 0.15 from its original value of 0.04, setting Ki to 2 from its original value of 0.5, and setting Kp to 0.5 from its original value of 0.

 

Fictitious frequency response at AF2-407 generator bus tripped the queue project due to the action of instantaneous under-frequency and over-frequency relays when faults were applied at Fall Creek 345 kV (AF2-407 POI). Therefore, the relay pickup times for frequency relay instances 96116513 and 96116516 were set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 62 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

62

AF2-173

Solar

AEP

140

140

84

Desoto 345 kV Substation

AF2-177

Wind

AEP

200

200

26

Sorenson – Desoto #2 345 kV Line

AF2-407

Battery Storage

AEP

300

300

300

Fall Creek 345 kV Substation

AG1-367

Solar

AEP

100

100

60

DeSoto 345 kV Substation

AG1-375

Solar

AEP

100

100

100

Sorenson – Desoto #2 345 kV Line

 

Reactive Power Analysis

The reactive power capability of AG1-375 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AC1-174 Losantville 345kV In Service
AC1-175 Losantville 345kV In Service
AC2-090 Losantville 345kV In Service
AC2-111 College Corner 138kV Engineering & Procurement
AC2-176 Jay 138 kV In Service
AD1-043 Makahoy 138 kV Withdrawn
AD1-128 Modoc-Delaware 138 kV Under Construction
AD2-071 Strawton-Deer Creek 138 kV Suspended
AE1-207 Mississinewa-Gaston 138 kV Suspended
AE1-208 Delaware-Van Buren 138 kV Suspended
AE1-209 Desoto 345 kV Suspended
AE1-210 Desoto 345 kV Suspended
AE2-089 Pennville-Adams 138 kV Engineering & Procurement
AE2-169 Delaware-Van Buren 138 kV Suspended
AE2-172 Mississinewa-Gaston 138 kV Suspended
AE2-219 Bluff Point-Randolph 138 kV Suspended
AE2-220 Losantville 345 kV Engineering & Procurement
AE2-234 Liberty Center-Buckeye Tap 69 kV Engineering & Procurement
AE2-297 Madison-Tanners Creek 138 kV In Service
AF1-071 College Corner 138 kV Engineering & Procurement
AF1-118 Sorenson-Desoto 345 kV Engineering & Procurement
AF1-119 Keystone-Desoto 345 kV Engineering & Procurement
AF1-202 Keystone-Desoto 345 kV Under Construction
AF1-223 Keystone-Desoto 345 kV Under Construction
AF1-268 Desoto-Jay 138 kV Engineering & Procurement
AF2-068 Jay 138 kV Active
AF2-162 Keystone-Desoto 345 kV Engineering & Procurement
AF2-173 Desoto 345 kV Active
AF2-177 Sorenson-DeSoto #2 345 kV Active
AF2-335 Delaware-Royerton 138 kV Active
AF2-370 Delaware-Royerton 138 kV Active
AF2-388 Keystone-Desoto 345 kV Active
AF2-407 Fall Creek 345 kV Active
AF2-408 Fall Creek 138 kV Engineering & Procurement
AG1-017 Jay 138 kV Under Construction
AG1-047 Jay 138 kV Engineering & Procurement
AG1-297 Hanna-Tanners Creek 345 kV Active
AG1-324 Jay-Desoto 138 kV Engineering & Procurement
AG1-367 DeSoto 345 kV Active
AG1-414 Mississinewa 138 kV Engineering & Procurement
AG1-433 Keystone-DeSoto 345 kV Active
V3-007 Desoto-Tanners Creek #1 345kV In Service
Z2-115 Deer Creek 12.47kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) No Impact
Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted Facility Transmission Owner Reinforcement Cost Cost Allocated to AG1-375 Scenarios
  • CAP BANK 230.0 - Gallagher 230.0 CKT 0
DEI Install 144 MVAR cap bank at Gallagher sub.
Install 144 MVAR cap bank at Gallagher sub.
$3,000,000 $8,357
  • MISO Voltage
  • CAP BANK 138.0 - Shoals 138.0 CKT 0
DEI Install 28.8 MVAR cap bank at Shoals sub
Install 28.8 MVAR cap bank at Shoals sub
$3,000,000 $6,329
  • MISO Voltage
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

Based on the Phase III analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AG1-375 System Reinforcements:
TO RTEP ID Title Category Allocated Cost ($USD) Facilities Study
OVEC n7881 Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F Cost Allocated $1,406,420
AEP n7757 Replace Bus 1 at the Desoto 138 kV Station Cost Allocated $20,460
Grand Total: $1,426,880

PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements. For additional details, please click the icon below

Regional Topology Upgrade Conversion

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n7881
Type
Load Flow
TO
OVEC
RTEP ID / TO ID
n7881 / OVEC0001a
Title
Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F
Description
•Remove and replace sixteen (16) existing double circuit towers with taller double circuit custom steel poles. (Towers 11, 14, 45, 47, 52, 57, 59, 61, 63, 66, 67, 71, 77, 84, 91, and 96) •Remove and replace two (2) existing river crossing lattice towers with taller lattice structures. (Towers 2 and 140)
Total Cost ($USD)
$24,006,000
Discounted Total Cost ($USD)
$24,006,000
Allocated Cost ($USD)
$1,406,420
Time Estimate
38 Months

Contributor

Facility Contingency
06DEARB1-06PIERCE 345.0 kV Ckt 1 line (Any)
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-173 Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE1-209, AE1-210, AF2-173, AG1-367
12.9 MW 10.1% $2,426,183
AF2-177 Sorenson - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-177, AG1-375
15.0 MW 11.7% $2,812,841
AF2-388 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
14.5 MW 11.4% $2,730,442
AF2-407 24.1 MW 18.8% $4,519,578
AG1-297 37.4 MW 29.2% $7,012,206
AG1-367 Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE1-209, AE1-210, AF2-173, AG1-367
9.2 MW 7.2% $1,733,015
AG1-375 Sorenson - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-177, AG1-375
7.5 MW 5.9% $1,406,420
AG1-433 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
7.3 MW 5.7% $1,365,315

System Reinforcement: n7757
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n7757 / AEPI0063a
Title
Replace Bus 1 at the Desoto 138 kV Station
Description
Remove existing 3” bus #1 and replace with 5” SCH 40 IPS
Total Cost ($USD)
$186,000
Discounted Total Cost ($USD)
$186,000
Allocated Cost ($USD)
$20,460
Time Estimate
17 Months

Contributor

Facility Contingency
05DESOTO-05DESOTO 345.0/138.0 kV Ckt 2 transformer AEP_P4_#2965_05DESOTO 345_A2_SRT-A
Cost Allocation
Project MW Impact Percent Allocation Allocated Cost ($USD)
AF2-173 Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE1-209, AE1-210, AF2-173, AG1-367
29.9 MW 20.7% $38,435
AF2-177 Sorenson - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-177, AG1-375
31.9 MW 22.0% $40,919
AF2-388 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
30.5 MW 21.1% $39,154
AG1-367 Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AE1-209, AE1-210, AF2-173, AG1-367
21.4 MW 14.8% $27,454
AG1-375 Sorenson - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-177, AG1-375
15.9 MW 11.0% $20,460
AG1-433 Keystone - Desoto 345kV - AEP: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AF2-388, AG1-433
15.3 MW 10.5% $19,577

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-375


AG1-375 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AG1-375 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AG1-375 One Line Diagram

AG1-375 One Line Diagram.jpg

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.