AG1-406 Phase III Study Report

v1.00 released 2025-09-18 17:14

Walnut Grove-Asahi 69 kV

22.0 MW Capacity / 22.0 MW Energy

Introduction

This Phase III System Impact Study Report (PH3) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 312 for New Service Requests (projects) in Transition Cycle 1. The Project Developer/Eligible Customer (developer) is Sunflower Prairie Solar Project, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is East Kentucky Power Cooperative, Inc..

Preface

New Service Requests meeting the requirements of Tariff, Part VII, Subpart D, Decision Point II, were included in the Phase III System Impact Study. The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
  1. PJM will retool load flow, short circuit and stability results based on decisions made by Project Developers or Eligible Customers during Decision Point II.
  2. PJM will coordinate with Affected System Operators to conduct any studies required to determine the final impact of a New Service Request on any Affected System and will include the final Affected System Study results in the Phase III System Impact Study, if available from the Affected System.
  3. The Phase III System Impact Study Results will be publicly available on PJM’s website; Project Developers and Eligible Customers must obtain the results from the website.
  4. PJM will tender draft final agreements to Project Developers or Eligible Customers.
The Transmission Owner takes the following actions during the Phase III System Impact Study:
  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase III System Impact Study phase will be for the System Reliability Network Upgrades. The Facilities Study requirements are outlined in Attachment C of PJM Manual 14H. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7).

Decision Point III Requirements

At the close of Phase III System Impact Study, PJM will initiate Decision Point III (DP3). During DP3, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 313.A. Additional information on these elements is available in PJM Manual 14H sections 4.8, 6, and 7.

As stated in PJM Tariff, Part VII, Subpart D, section 313.C, New Service Requests may not be changed or modified in any way for any reason during Decision Point III. A New Service Request must be withdrawn and resubmitted in a subsequent Cycle to the extent a Project Developer or Eligible Customer wants to make any changes to such New Service Request at this point in the Cycle process.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP3 with cumulative Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 313.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point III, the Network Upgrade cost from Phase II to Phase III must:

  1. Increase overall by 35% or more
  2. Increases by more than $25,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase, Decision Point I, and Decision Point II (RD1, and RD2 and RD3, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP3 Adverse Eligibility = DP3 Adverse Cost Alloc DP2 Adverse Cost Alloc > 1.35 AND ( DP3 Adverse Cost Alloc - DP2 Adverse Cost Alloc ) Project Size > $25,000 per MW
DP3 Adverse Eligibility = $5,035,000 $0 = AND ( $5,035,000 - $0 ) 22.0 = $228,864 per MW

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the East Kentucky Power Cooperative, Inc. zone — McLean County, Kentucky. This project is an increase to the developer’s AG1-405 project(s), which will share the same Point of Interconnection. The AG1-406 project is a 22.0 MW uprate (22.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 79.0 MW with 56.2 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG1-406
Project Name:
Walnut Grove-Asahi 69 kV
Project Developer Name:
Sunflower Prairie Solar Project, LLC
State:
Kentucky
County:
McLean
Transmission Owner:
East Kentucky Power Cooperative, Inc.
MFO:
79.0
MWE:
22.0
MWC:
22.0
Battery Storage Specification:
220.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2027

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG1-406 will interconnect on the East Kentucky Power Cooperative, Inc. transmission system as an uprate to AG1-405 tapping the Walnut Grove to Asahi Tap 69 kV line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase III SIS, the interconnected Transmission Owner has performed a facilities study for the required System Reliability Network Upgrades. The Facilities Studies for the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades were performed by the Transmission Owner in Phase II and are available for download on PJM.com (see General Section for document links).

Based on the Phase III SIS results, the AG1-406 project has the following allocation of costs for interconnection. The Security amount required at DP3 is also shown below.

Cost Summary
Description Cost Allocated to AG1-406 Cost Subject to Security
Transmission Owner Interconnection Facilities (TOIF) $1,225,000 $1,225,000
Other Scope $0 $0
Option to Build Oversight $0 $0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades $2,907,500 $2,907,500
Network Upgrades $2,127,500 $2,127,500
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL) $0 $0
Transient Stability $0 $0
Short Circuit $0 $0
Transmission Owner Analysis
SubRegional $0 $0
Distribution $0 $0
Affected System Study Reinforcements
AFS - PJM Violatons $0 $0
AFS - Non-PJM Violations $0 $0
Total $6,260,000 $6,260,000

* Contributes to calculation for Security. See Security Section of this report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Security Requirement

Per Tariff Part VII, Subpart D, section 313 (Decision Point III) A.1.a and PJM Manual 14H, section 8.6.1, Project Developers and Eligible Customers are required to provide Security in a form acceptable to PJM at Decision Point III which runs concurrently with the projects' Final Agreement Negotiation Phase. Security may be in the form of cash, letter of credit, or other form of Security acceptable to PJM (see PJM M14H, Section 6.4).

Security is calculated for a New Service Request based on the Network Upgrade costs allocated pursuant to the Phase III System Impact Study results.

Note 1: "Network Upgrades" referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Security Due for AG1-405/AG1-406

Security has been calculated for the AG1-405/AG1-406 project(s) based on the Phase III System Impact Study results and is shown in the table below. This Security must be provided at Decision Point III through either a wire transfer or letter of credit or other form of Security deemed acceptable by PJM per Manual 14H, Section 6.4.

Security Due for AG1-405/AG1-406
Project(s): AG1-405/AG1-406
Final Agreement Security (A): $12,520,000
Portion of Costs Already Paid (B): $0
Net Security Due at DP3: A B = $12,520,000
Note: Failure to provide an acceptable form of Security by the end of Decision Point III will result in withdrawal and termination of the New Service Request.

Transmission Owner Scope of Work

The AG1-406 project is an uprate to AG1-405 and will share the same Point of Change of Ownership with AG1-405.

The scope of work for AG1-405/AG1-406 includes: EKPC will construct a new 69 kV switching station and a new 69 kV loop-in tap from the EKPC Walnut Grove - Asahi Tap 69 kV line to accommodate the connection of the PD’s substation facilities to the EKPC transmission system. EKPC will also construct a 69 kV disconnect switch structure which will be the PCO interface. EKPC will also complete the required network upgrades at existing EKPC substations, which are system protection changes necessary at the Walnut Grove and Norwood substations to accommodate the addition of this new facility, and installation of OPGW on the Walnut Grove - East Pulaski and the East Pulaski - Shopville line sections (a total of 5.8 miles). Additionally to complete the redundant fiber path, new OPGW will need to be installed on the Walnut Grove – Woodstock and Floyd – Pulaski – South Floyd line sections (a total of 9.7 miles).

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9385.0

Revise relay settings at Walnut Grove Substation

$98,000 $7,000 $8,000 $1,000 $114,000 $57,000 (See Note 1)
n9384.0

Revise relay settings at Norwood JCT Substation

$98,000 $7,000 $8,000 $1,000 $114,000 $57,000 (See Note 1)
n9383.0

Loop existing Walnut Grove - Asahi Tap 69 kV line into new interconnection switching station

$485,000 $274,000 $93,000 $10,000 $862,000 $431,000 (See Note 1)
n9382.0

Install new overhead optical ground wire (OPGW) on the existing Walnut Grove - East Pulaski and East Pulaski - Shopville line sections for a total of 5.8 miles.

$881,000 $154,000 $100,000 $12,000 $1,147,000 $573,500 (See Note 1)
n9381.0

Install new overhead optical ground wire (OPGW) on the existing Walnut Grove - Woodstock and Floyd - Pulaski - South Floyd line sections for a total of 9.7 miles.

$1,406,000 $355,000 $232,000 $25,000 $2,018,000 $1,009,000 (See Note 1)
Stand-Alone Network Upgrades
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
n9386.0

East Pulaski Interconnection Substation: Construct new 69 kV switching station

$2,436,000 $2,570,000 $728,000 $81,000 $5,815,000 $2,907,500 (See Note 1)
Transmission Owner Interconnection Facilities
RTEP ID Description Direct Indirect Total Cost ($USD) Allocated Cost ($USD)
Labor Materials Labor Materials
(Pending)

One (1) 69 kV generator lead line including installation of a 69 kV line monopole dead-end structure and foundation, a 69 kV 3-pole disconnect switch mounted to the monopole, line conductor, and two (2) 48-strand fiber optic cables.

$1,512,000 $687,000 $226,000 $25,000 $2,450,000 $1,225,000 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase 2 of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

EKPC anticipates that it will take 30 months after the signing of the Generator Interconnection Agreement and the project kickoff call is subsequently held to complete the physical interconnection projects. This assumes no delays due to permitting or environmental issues, and that all necessary outages can be taken as needed to maintain this schedule.

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. EKPC interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards and in the Physical Interconnection Facilities Study.

Summer Peak Analysis

The New Service Request was evaluated as a 22.0 MW (22.0 MW Capacity) injection in the EKPC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential summer peak period network impacts were as follows:

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The full energy output of Generation Interconnection Requests are evaluated for multiple facility contingencies (double circuit tower line, fault with a stuck breaker, and bus fault).

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Breaker AC 117.61 % 277.0 B 325.79 2.57
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P4-5_LAURL S50-1014_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1014_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Breaker AC 117.26 % 277.0 B 324.82 2.58
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P2-2_LAUREL CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_LAUREL CO 161_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Bus AC 117.26 % 277.0 B 324.82 2.58
EKPC/LGEE 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Tower AC 133.1 % 105.0 B 139.75 7.01
EKPC/LGEE 5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Tower AC 117.62 % 277.0 B 325.8 2.57

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1024_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 117.61 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 325.79 MVA
MW Contribution: 2.57 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P4-5_LAURL S50-1024_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1024_SRT-A'
 OPEN BRANCH FROM BUS 324688 TO BUS 342781 CKT 1   /*2PITTSBRG KU  69.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
 OPEN BUS 342754                                   /*5LAUREL CO   161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 117.28 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.86 MVA
MW Contribution: 2.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.69 MW 10.69 MW
964902 AG1-354 E 50/50 7.13 MW 7.13 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.63 MW 6.63 MW
943702 AF1-038 E 50/50 4.42 MW 4.42 MW
943821 AF1-050 C 50/50 4.45 MW 4.45 MW
943822 AF1-050 E 50/50 2.96 MW 2.96 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.46 MW 20.46 MW
342945 1LAUREL 1G 50/50 6.36 MW 6.36 MW
939132 AE1-143 E 50/50 4.87 MW 4.87 MW
940831 AE2-071 C 50/50 0.4 MW 0.4 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.84 MW 9.84 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.56 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.33 MW 7.33 MW
964782 AG1-341 E 50/50 4.89 MW 4.89 MW
965411 AG1-406 C 50/50 2.57 MW 2.57 MW
966021 AG1-471 C 50/50 6.55 MW 6.55 MW
966022 AG1-471 E 50/50 4.0 MW 4.0 MW
950000 AG9-001 External Queue 7.4 MW 7.4 MW
950011 AG9-010 External Queue 13.44 MW 13.44 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.6 MW 3.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.12 MW 5.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.54 MW 2.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.92 MW 1.92 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P4-5_LAURL S50-1014_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P4-5_LAURL S50-1014_SRT-A
CONTINGENCY 'EKPC_P4-5_LAURL S50-1014_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 117.26 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.82 MVA
MW Contribution: 2.58 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.71 MW 10.71 MW
964902 AG1-354 E 50/50 7.14 MW 7.14 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.64 MW 6.64 MW
943702 AF1-038 E 50/50 4.43 MW 4.43 MW
943821 AF1-050 C 50/50 4.46 MW 4.46 MW
943822 AF1-050 E 50/50 2.97 MW 2.97 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.48 MW 20.48 MW
342945 1LAUREL 1G 50/50 6.37 MW 6.37 MW
939132 AE1-143 E 50/50 4.88 MW 4.88 MW
940831 AE2-071 C 50/50 0.41 MW 0.41 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.85 MW 9.85 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.57 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.34 MW 7.34 MW
964782 AG1-341 E 50/50 4.9 MW 4.9 MW
965411 AG1-406 C 50/50 2.58 MW 2.58 MW
966021 AG1-471 C 50/50 6.56 MW 6.56 MW
966022 AG1-471 E 50/50 4.01 MW 4.01 MW
950000 AG9-001 External Queue 7.42 MW 7.42 MW
950011 AG9-010 External Queue 13.46 MW 13.46 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.62 MW 3.62 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.15 MW 5.15 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.58 MW 2.58 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.93 MW 1.93 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.79 MW 1.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P2-2_LAUREL CO 161_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P2-2_LAUREL CO 161_SRT-A
CONTINGENCY 'EKPC_P2-2_LAUREL CO 161_SRT-A'
 OPEN BUS 342754   /*5LAUREL CO   161.0
END
Contingency Type: Bus
DC|AC: AC
Final Cycle Loading: 117.26 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.82 MVA
MW Contribution: 2.58 MW
Impact of Topology Modeling:
Increase
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.71 MW 10.71 MW
964902 AG1-354 E 50/50 7.14 MW 7.14 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.64 MW 6.64 MW
943702 AF1-038 E 50/50 4.43 MW 4.43 MW
943821 AF1-050 C 50/50 4.46 MW 4.46 MW
943822 AF1-050 E 50/50 2.97 MW 2.97 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.48 MW 20.48 MW
342945 1LAUREL 1G 50/50 6.37 MW 6.37 MW
939132 AE1-143 E 50/50 4.88 MW 4.88 MW
940831 AE2-071 C 50/50 0.41 MW 0.41 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.85 MW 9.85 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.57 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.34 MW 7.34 MW
964782 AG1-341 E 50/50 4.9 MW 4.9 MW
965411 AG1-406 C 50/50 2.58 MW 2.58 MW
966021 AG1-471 C 50/50 6.56 MW 6.56 MW
966022 AG1-471 E 50/50 4.01 MW 4.01 MW
950000 AG9-001 External Queue 7.42 MW 7.42 MW
950011 AG9-010 External Queue 13.46 MW 13.46 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.62 MW 3.62 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.15 MW 5.15 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.58 MW 2.58 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.93 MW 1.93 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.79 MW 1.79 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

Details for 2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line l/o EKPC_P7-1_COOP 161 DBL 2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
Contingency Name:
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 133.1 %
Rating: 105.0 MVA
Rating Type: B
MVA to Mitigate: 139.75 MVA
MW Contribution: 7.01 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC/LGEE
Facility Description:
2SOMERSET KU-2FERGUSON SO 69.0 kV Ckt 1 line
342287 to 324531 ckt 1
Contingency Name:
EKPC_P7-1_COOP 161 DBL 2_SRT-A
CONTINGENCY 'EKPC_P7-1_COOP 161 DBL 2_SRT-A'
 OPEN BRANCH FROM BUS 324141 TO BUS 342718 CKT 1   /*5ELIHU       161.0 - 5COOPER2     161.0
 OPEN BRANCH FROM BUS 342718 TO BUS 342757 CKT 1   /*5COOPER2     161.0 - 5LAUREL DAM  161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 132.18 %
Rating: 105.0 MVA
Rating Type: B
MVA to Mitigate: 138.79 MVA
MW Contribution: 7.01 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C Adder 7.27 MW 6.18 MW
964902 AG1-354 E Adder 4.85 MW 4.12 MW
965401 AG1-405 C 50/50 10.9 MW 10.9 MW
965402 AG1-405 E 50/50 7.27 MW 7.27 MW
943701 AF1-038 C 50/50 8.41 MW 8.41 MW
943702 AF1-038 E 50/50 5.61 MW 5.61 MW
943821 AF1-050 C Adder 2.98 MW 2.53 MW
943822 AF1-050 E Adder 1.99 MW 1.69 MW
945382 AF1-203 E Adder 0.72 MW 0.61 MW
342900 1COOPER1 G 50/50 5.11 MW 5.11 MW
342903 1COOPER2 G 50/50 9.91 MW 9.91 MW
939132 AE1-143 E Adder 3.13 MW 2.66 MW
940832 AE2-071 E Adder 1.26 MW 1.07 MW
339206 AE1-143 C Adder 6.31 MW 5.36 MW
962241 AG1-070 C Adder 0.49 MW 0.41 MW
962242 AG1-070 E Adder 2.76 MW 2.35 MW
962251 AG1-071 C Adder 0.6 MW 0.51 MW
962252 AG1-071 E Adder 3.37 MW 2.87 MW
944151 AF1-083 C Adder 2.92 MW 2.49 MW
944152 AF1-083 E Adder 1.95 MW 1.66 MW
960741 AF2-365 C Adder 1.77 MW 1.51 MW
960742 AF2-365 E Adder 1.18 MW 1.0 MW
964781 AG1-341 C Adder 5.04 MW 4.29 MW
964782 AG1-341 E Adder 3.36 MW 2.86 MW
965411 AG1-406 C 50/50 7.01 MW 7.01 MW
966021 AG1-471 C 50/50 4.64 MW 4.64 MW
966022 AG1-471 E 50/50 2.84 MW 2.84 MW
950011 AG9-010 External Queue 8.6 MW 8.6 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.1 MW 3.1 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 3.59 MW 3.59 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 1.67 MW 1.67 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.09 MW 0.09 MW
NY PJM->LTFIMP_NY CLTF 0.05 MW 0.05 MW
WEC LTFEXP_WEC->PJM CLTF 0.07 MW 0.07 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.08 MW 0.08 MW
TVA LTFEXP_TVA->PJM CLTF 1.28 MW 1.28 MW
MEC LTFEXP_MEC->PJM CLTF 0.56 MW 0.56 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.21 MW 1.21 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.57 MW 0.57 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.04 MW 0.04 MW

Details for 5COOPER2-5ELIHU 161.0 kV Ckt 1 line l/o EKPC_P7-1_LAURL 161 DBL_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 117.62 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 325.8 MVA
MW Contribution: 2.57 MW
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area: EKPC/LGEE
Facility Description:
5COOPER2-5ELIHU 161.0 kV Ckt 1 line
342718 to 324141 ckt 1
Contingency Name:
EKPC_P7-1_LAURL 161 DBL_SRT-A
CONTINGENCY 'EKPC_P7-1_LAURL 161 DBL_SRT-A'
 OPEN BRANCH FROM BUS 342754 TO BUS 342757 CKT 1   /*5LAUREL CO   161.0 - 5LAUREL DAM  161.0
 OPEN BRANCH FROM BUS 342754 TO BUS 342781 CKT 1   /*5LAUREL CO   161.0 - 5PITTSBURG   161.0
 OPEN BRANCH FROM BUS 342781 TO BUS 342820 CKT 1   /*5PITTSBURG   161.0 - 5TYNER       161.0
END
Contingency Type: Tower
DC|AC: AC
Final Cycle Loading: 117.27 %
Rating: 277.0 MVA
Rating Type: B
MVA to Mitigate: 324.84 MVA
MW Contribution: 2.57 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
964901 AG1-354 C 50/50 10.69 MW 10.69 MW
964902 AG1-354 E 50/50 7.13 MW 7.13 MW
965401 AG1-405 C 50/50 4.0 MW 4.0 MW
965402 AG1-405 E 50/50 2.67 MW 2.67 MW
943701 AF1-038 C 50/50 6.63 MW 6.63 MW
943702 AF1-038 E 50/50 4.42 MW 4.42 MW
943821 AF1-050 C 50/50 4.45 MW 4.45 MW
943822 AF1-050 E 50/50 2.96 MW 2.96 MW
945381 AF1-203 C 50/50 0.23 MW 0.23 MW
945382 AF1-203 E 50/50 0.96 MW 0.96 MW
342442 2W GLASGOW 50/50 0.02 MW 0.02 MW
342900 1COOPER1 G 50/50 10.52 MW 10.52 MW
342903 1COOPER2 G 50/50 20.46 MW 20.46 MW
342945 1LAUREL 1G 50/50 6.36 MW 6.36 MW
939132 AE1-143 E 50/50 4.87 MW 4.87 MW
940831 AE2-071 C 50/50 0.4 MW 0.4 MW
940832 AE2-071 E 50/50 1.69 MW 1.69 MW
339206 AE1-143 C 50/50 9.84 MW 9.84 MW
962241 AG1-070 C 50/50 0.69 MW 0.69 MW
962242 AG1-070 E 50/50 3.91 MW 3.91 MW
962251 AG1-071 C 50/50 0.84 MW 0.84 MW
962252 AG1-071 E 50/50 4.78 MW 4.78 MW
944151 AF1-083 C 50/50 4.47 MW 4.47 MW
944152 AF1-083 E 50/50 2.98 MW 2.98 MW
960741 AF2-365 C Adder 2.56 MW 2.18 MW
960742 AF2-365 E Adder 1.71 MW 1.45 MW
964781 AG1-341 C 50/50 7.33 MW 7.33 MW
964782 AG1-341 E 50/50 4.89 MW 4.89 MW
965411 AG1-406 C 50/50 2.57 MW 2.57 MW
966021 AG1-471 C 50/50 6.55 MW 6.55 MW
966022 AG1-471 E 50/50 4.0 MW 4.0 MW
950000 AG9-001 External Queue 7.4 MW 7.4 MW
950011 AG9-010 External Queue 13.44 MW 13.44 MW
CBM West 1 LTFEXP_CBM-W1->PJM CBM 3.6 MW 3.6 MW
CBM West 2 LTFEXP_CBM-W2->PJM CBM 5.12 MW 5.12 MW
CBM South 1 LTFEXP_CBM-S1->PJM CBM 0.0 MW 0.0 MW
CBM South 2 LTFEXP_CBM-S2->PJM CBM 2.54 MW 2.54 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.17 MW 0.17 MW
NY PJM->LTFIMP_NY CLTF 0.09 MW 0.09 MW
WEC LTFEXP_WEC->PJM CLTF 0.08 MW 0.08 MW
CPLE LTFEXP_CPLE->PJM CLTF 0.12 MW 0.12 MW
TVA LTFEXP_TVA->PJM CLTF 1.92 MW 1.92 MW
MEC LTFEXP_MEC->PJM CLTF 0.75 MW 0.75 MW
LAGN LTFEXP_LAGN->PJM CLTF 1.78 MW 1.78 MW
SIGE LTFEXP_SIGE->PJM CLTF 0.06 MW 0.06 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 1.11 MW 1.11 MW
LTFEXP_AA2-074 LTFEXP_AA2-074->LTFIMP_AA2-074 CLTF 0.06 MW 0.06 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
EKPC AG1-405 TP-2ASAHI M W T 69.0 kV Ckt 1 line
965400 to 341032 ckt 1
EKPC_P2-3_COOP S42-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_COOP S42-1014_SRT-A'
 OPEN BRANCH FROM BUS 342742 TO BUS 342745 CKT 1   /*5JABEZ       161.0 - 5JABEZ T     161.0
 OPEN BRANCH FROM BUS 342745 TO BUS 342751 CKT 1   /*5JABEZ T     161.0 - 5JAMESTOWN T 161.0
 OPEN BRANCH FROM BUS 342745 TO BUS 342799 CKT 1   /*5JABEZ T     161.0 - 5S OAKHILL   161.0
 OPEN BRANCH FROM BUS 342748 TO BUS 342751 CKT 1   /*5JAMESTOWN   161.0 - 5JAMESTOWN T 161.0
 OPEN BRANCH FROM BUS 342751 TO BUS 342796 CKT 1   /*5JAMESTOWN T 161.0 - 5RUSSEL CO J 161.0
 OPEN BRANCH FROM BUS 342793 TO BUS 342796 CKT 1   /*5RUSSEL CO   161.0 - 5RUSSEL CO J 161.0
 OPEN BRANCH FROM BUS 342796 TO BUS 360448 CKT 1   /*5RUSSEL CO J 161.0 - 5WOLF CRK HP 161.0
 OPEN BUS 342715                                   /*5COOPER1     161.0
 OPEN BUS 342900                                   /*1COOPER1 G    13.8
END
Breaker AC 100.41 % 57.0 B 57.24 15.0
EKPC AG1-405 TP-2ASAHI M W T 69.0 kV Ckt 1 line
965400 to 341032 ckt 1
EKPC_P2-3_COOP S42-1039_SRT-A
CONTINGENCY 'EKPC_P2-3_COOP S42-1039_SRT-A'
 OPEN BUS 342715   /*5COOPER1     161.0
 OPEN BUS 342718   /*5COOPER2     161.0
 OPEN BUS 342900   /*1COOPER1 G    13.8
 OPEN BUS 342903   /*1COOPER2 G    20.0
END
Breaker AC 100.3 % 57.0 B 57.17 15.04

Details for AG1-405 TP-2ASAHI M W T 69.0 kV Ckt 1 line l/o EKPC_P2-3_COOP S42-1014_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: EKPC
Facility Description:
AG1-405 TP-2ASAHI M W T 69.0 kV Ckt 1 line
965400 to 341032 ckt 1
Contingency Name:
EKPC_P2-3_COOP S42-1014_SRT-A
CONTINGENCY 'EKPC_P2-3_COOP S42-1014_SRT-A'
 OPEN BRANCH FROM BUS 342742 TO BUS 342745 CKT 1   /*5JABEZ       161.0 - 5JABEZ T     161.0
 OPEN BRANCH FROM BUS 342745 TO BUS 342751 CKT 1   /*5JABEZ T     161.0 - 5JAMESTOWN T 161.0
 OPEN BRANCH FROM BUS 342745 TO BUS 342799 CKT 1   /*5JABEZ T     161.0 - 5S OAKHILL   161.0
 OPEN BRANCH FROM BUS 342748 TO BUS 342751 CKT 1   /*5JAMESTOWN   161.0 - 5JAMESTOWN T 161.0
 OPEN BRANCH FROM BUS 342751 TO BUS 342796 CKT 1   /*5JAMESTOWN T 161.0 - 5RUSSEL CO J 161.0
 OPEN BRANCH FROM BUS 342793 TO BUS 342796 CKT 1   /*5RUSSEL CO   161.0 - 5RUSSEL CO J 161.0
 OPEN BRANCH FROM BUS 342796 TO BUS 360448 CKT 1   /*5RUSSEL CO J 161.0 - 5WOLF CRK HP 161.0
 OPEN BUS 342715                                   /*5COOPER1     161.0
 OPEN BUS 342900                                   /*1COOPER1 G    13.8
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 100.41 %
Rating: 57.0 MVA
Rating Type: B
MVA to Mitigate: 57.24 MVA
MW Contribution: 15.0 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965401 AG1-405 C 50/50 23.32 MW 23.32 MW
965402 AG1-405 E 50/50 15.55 MW 15.55 MW
965411 AG1-406 C 50/50 15.0 MW 15.0 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.0 MW 0.0 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.33 MW 0.33 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.05 MW 0.05 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.03 MW 0.03 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.23 MW 0.23 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.0 MW 0.0 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.04 MW 0.04 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.03 MW 0.03 MW
MDU PJM->LTFIMP_MDU CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.06 MW 0.06 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.06 MW 0.06 MW

Details for AG1-405 TP-2ASAHI M W T 69.0 kV Ckt 1 line l/o EKPC_P2-3_COOP S42-1039_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area: EKPC
Facility Description:
AG1-405 TP-2ASAHI M W T 69.0 kV Ckt 1 line
965400 to 341032 ckt 1
Contingency Name:
EKPC_P2-3_COOP S42-1039_SRT-A
CONTINGENCY 'EKPC_P2-3_COOP S42-1039_SRT-A'
 OPEN BUS 342715   /*5COOPER1     161.0
 OPEN BUS 342718   /*5COOPER2     161.0
 OPEN BUS 342900   /*1COOPER1 G    13.8
 OPEN BUS 342903   /*1COOPER2 G    20.0
END
Contingency Type: Breaker
DC|AC: AC
Final Cycle Loading: 100.3 %
Rating: 57.0 MVA
Rating Type: B
MVA to Mitigate: 57.17 MVA
MW Contribution: 15.04 MW
Impact of Topology Modeling:
Elimination
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
965401 AG1-405 C 50/50 23.38 MW 23.38 MW
965402 AG1-405 E 50/50 15.59 MW 15.59 MW
965411 AG1-406 C 50/50 15.04 MW 15.04 MW
G-007 PJM->LTFIMP_G-007 CMTX_NF 0.01 MW 0.01 MW
NY PJM->LTFIMP_NY CLTF 0.0 MW 0.0 MW
LGEE LTFEXP_LGEE->PJM CLTF 0.01 MW 0.01 MW
COTTONWOOD PJM->LTFIMP_COTTONWOOD CLTF 0.4 MW 0.4 MW
HAMLET PJM->LTFIMP_HAMLET CLTF 0.06 MW 0.06 MW
CATAWBA PJM->LTFIMP_CATAWBA CLTF 0.04 MW 0.04 MW
PRAIRIE PJM->LTFIMP_PRAIRIE CLTF 0.29 MW 0.29 MW
TRIMBLE PJM->LTFIMP_TRIMBLE CLTF 0.01 MW 0.01 MW
BlueGrass PJM->LTFIMP_BlueG CLTF 0.05 MW 0.05 MW
O66 PJM->LTFIMP_O-066 CMTX_NF 0.05 MW 0.05 MW
MDU PJM->LTFIMP_MDU CLTF 0.01 MW 0.01 MW
LTFEXP_AC1-056 LTFEXP_AC1-056->LTFIMP_AC1-056 CLTF 0.08 MW 0.08 MW
LTFEXP_AC1-131 LTFEXP_AC1-131->LTFIMP_AC1-131 CLTF 0.07 MW 0.07 MW

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request into the New Service Request process.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With an Upgrade Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Winter Peak Analysis

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Winter Potential Congestion due to Local Energy Deliverability

PJM will start performing Winter Peak analysis in Transition Cycle 2.

Light Load Analysis

The New Service Request was evaluated as a 22.0 MW injection and 22.0 MW withdrawal in the EKPC area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential light load period network impacts were as follows:

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Single AC 135.55 % 1180.0 B 1599.51 2.46
AEP/OVEC 06KYGER-05SPORN 345.0 kV Ckt 1 line
248005 to 242528 ckt 1
AEP_P1-2_#7441_100545_SRT-A
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
Single DC 105.64 % 1204.0 B 1271.86 1.3

Details for 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Contingency Type: Single
DC|AC: AC
Final Cycle Loading: 135.55 %
Rating: 1180.0 MVA
Rating Type: B
MVA to Mitigate: 1599.51 MVA
MW Contribution: 2.46 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943031 AE2-326 C 80/20 6.34 MW 6.34 MW
943032 AE2-326 E 80/20 4.23 MW 4.23 MW
242892 05AMG2 80/20 56.42 MW 56.42 MW
242893 05AMG3 80/20 92.58 MW 92.58 MW
243443 05RKG2 80/20 78.36 MW 78.36 MW
274675 JOLIET 29;7U Adder 30.54 MW 25.96 MW
274676 JOLIET 29;8U Adder 30.54 MW 25.96 MW
944971 AF1-162 C 80/20 7.93 MW 7.93 MW
944972 AF1-162 E 80/20 5.29 MW 5.29 MW
945382 AF1-203 E 80/20 2.17 MW 2.17 MW
964782 AG1-341 E 80/20 11.47 MW 11.47 MW
223403 AG1-063 C Adder -0.07 MW -0.06 MW
940351 AE2-019 C Adder -15.78 MW -13.41 MW
965411 AG1-406 C 80/20 2.46 MW 2.46 MW
966391 AG1-508 C 80/20 1.47 MW 1.47 MW
966392 AG1-508 E 80/20 8.51 MW 8.51 MW
242899 05CRG1H 80/20 8.49 MW 8.49 MW
242900 05CRG1L 80/20 7.11 MW 7.11 MW
242901 05CRG2H 80/20 8.55 MW 8.55 MW
242902 05CRG2L 80/20 7.17 MW 7.17 MW
243758 05MIDDLECR 80/20 0.26 MW 0.26 MW
270167 AD2-205 E 80/20 0.79 MW 0.79 MW
940353 AE2-019 BT 80/20 15.78 MW 15.78 MW
944201 AF1-088 FTIR Adder 115.8 MW 98.43 MW
957193 AF2-013 BT 80/20 11.36 MW 11.36 MW
962183 AG1-063 BAT 80/20 0.26 MW 0.26 MW
962553 AG1-104 BT 80/20 30.68 MW 30.68 MW
963033 AG1-152 BT 80/20 13.61 MW 13.61 MW
963053 AG1-154 BT 80/20 5.97 MW 5.97 MW
963693 AG1-221 BT 80/20 6.49 MW 6.49 MW
966143 AG1-483 BAT 80/20 55.8 MW 55.8 MW
966253 AG1-494 BT 80/20 12.02 MW 12.02 MW

Details for 06KYGER-05SPORN 345.0 kV Ckt 1 line l/o AEP_P1-2_#7441_100545_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
248005 to 242528 ckt 1
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
Contingency Type: Single
DC|AC: DC
Final Cycle Loading: 105.64 %
Rating: 1204.0 MVA
Rating Type: B
MVA to Mitigate: 1271.86 MVA
MW Contribution: 1.3 MW
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area: AEP/OVEC
Facility Description:
06KYGER-05SPORN 345.0 kV Ckt 1 line
248005 to 242528 ckt 1
Contingency Name:
AEP_P1-2_#7441_100545_SRT-A
CONTINGENCY 'AEP_P1-2_#7441_100545_SRT-A'
 OPEN BRANCH FROM BUS 242928 TO BUS 246999 CKT 1   /*05MARYSV     765.0 - 05SORENS     765.0
END
Contingency Type: Single
DC|AC: DC
Final Cycle Loading: 107.98 %
Rating: 1204.0 MVA
Rating Type: B
MVA to Mitigate: 1300.13 MVA
MW Contribution: 1.35 MW
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
247255 05WLD G2 C 80/20 0.23 MW 0.23 MW
243859 05FR-11G C 80/20 0.38 MW 0.38 MW
243862 05FR-12G C 80/20 0.18 MW 0.18 MW
243864 05FR-21G C 80/20 0.19 MW 0.19 MW
243866 05FR-22G C 80/20 0.19 MW 0.19 MW
243870 05FR-3G C 80/20 0.18 MW 0.18 MW
243873 05FR-4G C 80/20 0.43 MW 0.43 MW
247901 05FR-12G E 80/20 1.24 MW 1.24 MW
247902 05FR-21G E 80/20 1.32 MW 1.32 MW
247904 05FR-3G E 80/20 2.46 MW 2.46 MW
247905 05FR-4G E 80/20 1.95 MW 1.95 MW
247906 05MDL-1G E 80/20 2.56 MW 2.56 MW
247907 05MDL-2G E 80/20 1.23 MW 1.23 MW
247912 05MDL-3G E 80/20 1.23 MW 1.23 MW
247913 05MDL-4G E 80/20 1.28 MW 1.28 MW
247958 05WLD G2 E 80/20 3.06 MW 3.06 MW
274847 GR RIDGE ;BU 80/20 0.37 MW 0.37 MW
274853 TWINGROVE;U1 80/20 0.48 MW 0.48 MW
274854 TWINGROVE;U2 80/20 0.49 MW 0.49 MW
274861 TOP CROP ;1U 80/20 0.25 MW 0.25 MW
274862 TOP CROP ;2U 80/20 0.47 MW 0.47 MW
274863 CAYUGA RI;1U 80/20 0.31 MW 0.31 MW
274864 CAYUGA RI;2U 80/20 0.31 MW 0.31 MW
274871 GR RIDGE ;2U 80/20 0.14 MW 0.14 MW
274880 RADFORD R;1U 80/20 0.64 MW 0.64 MW
274887 PILOT HIL;1U 80/20 0.47 MW 0.47 MW
274888 KELLY CRK;1U 80/20 0.47 MW 0.47 MW
276615 W2-048 GEN 80/20 0.91 MW 0.91 MW
276621 X2-022 GEN 80/20 2.58 MW 2.58 MW
290261 S-027 E 80/20 2.26 MW 2.26 MW
290265 S-028 E 80/20 2.25 MW 2.25 MW
293061 N-015 E 80/20 1.62 MW 1.62 MW
293644 O22 E1 80/20 1.54 MW 1.54 MW
293645 O22 E2 80/20 1.77 MW 1.77 MW
294392 P-010 E 80/20 2.05 MW 2.05 MW
917502 Z2-087 E 80/20 2.4 MW 2.4 MW
918052 AA1-018 E OP 80/20 1.75 MW 1.75 MW
934721 AD1-100 C 80/20 1.95 MW 1.95 MW
934722 AD1-100 E 80/20 30.27 MW 30.27 MW
942111 AE2-223 C 80/20 0.86 MW 0.86 MW
942112 AE2-223 E 80/20 5.77 MW 5.77 MW
959351 AF2-226 C 80/20 1.07 MW 1.07 MW
959352 AF2-226 E 80/20 1.61 MW 1.61 MW
959611 AF2-252 C 80/20 1.11 MW 1.11 MW
959612 AF2-252 E 80/20 1.66 MW 1.66 MW
960281 AF2-319 C 80/20 1.07 MW 1.07 MW
960282 AF2-319 E 80/20 1.61 MW 1.61 MW
960611 AF2-352 C 80/20 1.11 MW 1.11 MW
960612 AF2-352 E 80/20 1.66 MW 1.66 MW
960971 AF2-388 C 80/20 1.88 MW 1.88 MW
960972 AF2-388 E 80/20 8.78 MW 8.78 MW
965651 AG1-433 C 80/20 0.94 MW 0.94 MW
965652 AG1-433 E 80/20 4.39 MW 4.39 MW
966091 AG1-478 C 80/20 0.21 MW 0.21 MW
966092 AG1-478 E 80/20 0.32 MW 0.32 MW
966431 AG1-512 C 80/20 0.86 MW 0.86 MW
966432 AG1-512 E 80/20 1.29 MW 1.29 MW
966842 AG1-555 E 80/20 5.22 MW 5.22 MW
243443 05RKG2 80/20 52.1 MW 52.1 MW
243795 05HDWTR1G C 80/20 0.51 MW 0.51 MW
246991 05WLD G1 C 80/20 0.23 MW 0.23 MW
247536 05BLUFF P WF 80/20 0.43 MW 0.43 MW
247543 V3-007 C 80/20 0.51 MW 0.51 MW
247929 S-071 E 80/20 1.71 MW 1.71 MW
247935 V3-007 E 80/20 3.4 MW 3.4 MW
247963 05HDWTR1G E 80/20 3.4 MW 3.4 MW
274674 JOLIET 9 ;6U 80/20 6.8 MW 6.8 MW
274676 JOLIET 29;8U 80/20 17.72 MW 17.72 MW
943771 AF1-045 C 80/20 3.67 MW 3.67 MW
943772 AF1-045 E 80/20 2.45 MW 2.45 MW
961761 AG1-017 C 80/20 0.15 MW 0.15 MW
961762 AG1-017 E 80/20 0.71 MW 0.71 MW
246909 05MDL-1G C 80/20 0.38 MW 0.38 MW
246910 05MDL-2G C 80/20 0.22 MW 0.22 MW
246976 05MDL-3G C 80/20 0.22 MW 0.22 MW
246979 05MDL-4G C 80/20 0.17 MW 0.17 MW
274890 CAYUG;1U E 80/20 1.64 MW 1.64 MW
274891 CAYUG;2U E 80/20 1.64 MW 1.64 MW
925771 AC1-053 C 80/20 0.58 MW 0.58 MW
925772 AC1-053 E 80/20 3.89 MW 3.89 MW
247900 05FR-11G E 80/20 1.26 MW 1.26 MW
247903 05FR-22G E 80/20 1.27 MW 1.27 MW
939401 AE1-172 C 80/20 1.96 MW 1.96 MW
939402 AE1-172 E 80/20 9.15 MW 9.15 MW
939781 AE1-209 C 80/20 0.76 MW 0.76 MW
939782 AE1-209 E 80/20 5.09 MW 5.09 MW
957382 AF2-032 E 80/20 0.11 MW 0.11 MW
247556 05MDL-5G 80/20 0.29 MW 0.29 MW
247943 T-127 E 80/20 1.16 MW 1.16 MW
251828 CLNTESP1 80/20 1.03 MW 1.03 MW
251968 08ZIMRHP 80/20 47.67 MW 47.67 MW
270180 AB1-006 W1 80/20 0.33 MW 0.33 MW
270181 AB1-006 W2 80/20 0.05 MW 0.05 MW
270681 BRIGHTSTK; R 80/20 0.36 MW 0.36 MW
270839 OTTER CRK; R 80/20 0.26 MW 0.26 MW
275149 KELLYCK ;1E 80/20 1.89 MW 1.89 MW
276174 W4-005 E 80/20 3.64 MW 3.64 MW
276655 AB2-047 C1 80/20 0.23 MW 0.23 MW
276656 AB2-047 C2 80/20 0.23 MW 0.23 MW
276668 AB2-070 C 80/20 0.36 MW 0.36 MW
293519 PILOT HIL;1E 80/20 1.89 MW 1.89 MW
924048 AB2-047 E1 80/20 1.49 MW 1.49 MW
924049 AB2-047 E2 80/20 1.51 MW 1.51 MW
924266 AB2-070 E 80/20 2.2 MW 2.2 MW
926821 AC1-168 C 80/20 0.44 MW 0.44 MW
926822 AC1-168 E 80/20 2.95 MW 2.95 MW
930041 AB1-006 E1 80/20 2.21 MW 2.21 MW
930042 AB1-006 E2 80/20 0.32 MW 0.32 MW
935141 AD1-148 C 80/20 0.81 MW 0.81 MW
936371 AD2-047 C 80/20 1.47 MW 1.47 MW
936372 AD2-047 E 80/20 7.16 MW 7.16 MW
939791 AE1-210 C 80/20 0.76 MW 0.76 MW
939792 AE1-210 E 80/20 5.09 MW 5.09 MW
941721 AE2-172 C 80/20 2.74 MW 2.74 MW
941731 AE2-173 C 80/20 2.76 MW 2.76 MW
942601 AE2-276 C 80/20 3.19 MW 3.19 MW
944221 AF1-090 C 80/20 1.58 MW 1.58 MW
944222 AF1-090 E 80/20 7.38 MW 7.38 MW
944242 AF1-092 E 80/20 6.5 MW 6.5 MW
944532 AF1-118 E 80/20 21.95 MW 21.95 MW
944542 AF1-119 E 80/20 12.99 MW 12.99 MW
945371 AF1-202 C 80/20 1.85 MW 1.85 MW
945372 AF1-202 E 80/20 9.03 MW 9.03 MW
945391 AF1-204 C 80/20 3.19 MW 3.19 MW
945392 AF1-204 E 80/20 9.56 MW 9.56 MW
957842 AF2-078 E 80/20 1.16 MW 1.16 MW
958861 AF2-177 C 80/20 1.4 MW 1.4 MW
958862 AF2-177 E 80/20 9.38 MW 9.38 MW
960261 AF2-317 C 80/20 0.35 MW 0.35 MW
960791 AF2-370 C 80/20 1.43 MW 1.43 MW
961161 AF2-407 C 80/20 21.89 MW 21.89 MW
961171 AF2-408 C 80/20 5.91 MW 5.91 MW
961501 AF2-441 C 80/20 4.3 MW 4.3 MW
961502 AF2-441 E 80/20 6.45 MW 6.45 MW
963581 AG1-207 C 80/20 6.56 MW 6.56 MW
963831 AG1-236 C 80/20 1.04 MW 1.04 MW
963832 AG1-236 E 80/20 6.99 MW 6.99 MW
963841 AG1-237 C 80/20 1.24 MW 1.24 MW
963842 AG1-237 E 80/20 8.31 MW 8.31 MW
964351 AG1-297 C 80/20 6.24 MW 6.24 MW
964352 AG1-297 E 80/20 18.7 MW 18.7 MW
964611 AG1-324 C 80/20 0.31 MW 0.31 MW
964612 AG1-324 E 80/20 0.47 MW 0.47 MW
965331 AG1-398 C 80/20 0.16 MW 0.16 MW
965411 AG1-406 C 80/20 1.3 MW 1.3 MW
965462 AG1-414 E 80/20 1.69 MW 1.69 MW
270201 AC2-176 GEN 80/20 0.29 MW 0.29 MW
933596 AC2-176 E 80/20 1.93 MW 1.93 MW
250164 08BKJDB1 80/20 0.26 MW 0.26 MW
251827 WILLYESP 80/20 0.67 MW 0.67 MW
944201 AF1-088 FTIR 80/20 63.79 MW 63.79 MW
957141 AF2-008 FTIR 80/20 31.89 MW 31.89 MW
965913 AG1-460 BT 80/20 0.01 MW 0.01 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Light Load Potential Congestion due to Local Energy Deliverability

The following flowgates remain after considering the topology reinforcements required by the cycle.

Area Facility Description Contingency Name Contingency Type DC|AC Final Cycle Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
AEP 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
OP AC 134.08 % 1180.0 B 1582.1 2.46

Details for 05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area: AEP
Facility Description:
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line
242512 to 242515 ckt 1
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
Contingency Type: OP
DC|AC: AC
Final Cycle Loading: 134.08 %
Rating: 1180.0 MVA
Rating Type: B
MVA to Mitigate: 1582.1 MVA
MW Contribution: 2.46 MW
Impact of Topology Modeling:
Addition
Bus # Bus Name Type Full MW Contribution GenDeliv MW Contribution
943031 AE2-326 C 50/50 6.34 MW 6.34 MW
943032 AE2-326 E 50/50 4.23 MW 4.23 MW
242892 05AMG2 50/50 56.42 MW 56.42 MW
242893 05AMG3 50/50 92.58 MW 92.58 MW
243443 05RKG2 Adder 78.36 MW 66.61 MW
274675 JOLIET 29;7U Adder 30.54 MW 25.96 MW
274676 JOLIET 29;8U Adder 30.54 MW 25.96 MW
944971 AF1-162 C 50/50 7.93 MW 7.93 MW
944972 AF1-162 E 50/50 5.29 MW 5.29 MW
945382 AF1-203 E 50/50 2.17 MW 2.17 MW
964782 AG1-341 E 50/50 11.47 MW 11.47 MW
223403 AG1-063 C Adder -0.07 MW -0.06 MW
940351 AE2-019 C Adder -15.78 MW -13.41 MW
965411 AG1-406 C 50/50 2.46 MW 2.46 MW
966391 AG1-508 C 50/50 1.47 MW 1.47 MW
966392 AG1-508 E 50/50 8.51 MW 8.51 MW
242899 05CRG1H 50/50 8.49 MW 8.49 MW
242900 05CRG1L 50/50 7.11 MW 7.11 MW
242901 05CRG2H 50/50 8.55 MW 8.55 MW
242902 05CRG2L 50/50 7.17 MW 7.17 MW
243758 05MIDDLECR 50/50 0.26 MW 0.26 MW
270167 AD2-205 E 50/50 0.79 MW 0.79 MW
940353 AE2-019 BT 50/50 15.78 MW 15.78 MW
944201 AF1-088 FTIR Adder 115.8 MW 98.43 MW
957193 AF2-013 BT 50/50 11.36 MW 11.36 MW
962183 AG1-063 BAT 50/50 0.26 MW 0.26 MW
962553 AG1-104 BT 50/50 30.68 MW 30.68 MW
963033 AG1-152 BT 50/50 13.61 MW 13.61 MW
963053 AG1-154 BT 50/50 5.97 MW 5.97 MW
963693 AG1-221 BT 50/50 6.49 MW 6.49 MW
966143 AG1-483 BAT 50/50 55.8 MW 55.8 MW
966253 AG1-494 BT 50/50 12.02 MW 12.02 MW

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

Short Circuit Analysis

The Phase III Short circuit analysis was conducted for the following two study scenarios

  • Scenario 1 - TC1 Projects Impact;
  • Scenario 2 - TC1 Topology-Changing Upgrade Impacts;

The starting TC1 Phase III short circuit case is an updated Phase II case that accounted for the DPII outcomes (project changes & withdrawals) and other pre-TC1 changes. The starting Phase III case was utilized for the Scenario 1 studies to determine the impact of TC1 projects without modeling any topology-changing upgrades required for TC1. To conduct the Scenario 2 studies, the required topology-changing upgrades from the latest Load Flow & Stability studies were incorporated into the Scenario 1 case and utilized for the Scenario 2 studies to determine the impact of the topology-changing upgrades on the short circuit results from Scenario 1

Based on PJM Short Circuit Analysis, this project did not contribute >1% fault duty to previously identified overduty breakers, nor did it cause any new overduty breakers.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

New Service Requests (projects) AG1-405 and AG1-406 in PJM Transition Cycle 1 are listed in Table 1 below. This report will cover the dynamic analysis of AG1-405 and AG1-406.

This analysis is effectively a screening study to determine whether the addition of the AG1-405 and AG1-406 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-405 and AG1-406 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

AG1-405 and AG1-406 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 240 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, AG1-405 and AG1-406 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AG1-405 and AG1-406 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AG1-405 and AG1-406 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-405 and AG1-406 projects meet the 0.95 leading and lagging PF requirement. Initial reactive power capability assessment showed the AG1-405/AG1-406 facility had a 7 MVAR reactive power deficiency due to reactive power losses between inverter terminals and the high side of the main transformer. The developer confirmed plans to install a 7 MVAR capacitor bank to resolve the deficiency (RE_ AG1-405 Model Inquiry.msg).

AG1-405 and AG1-406 exhibited slow reactive power recovery for several contingencies. This issue did not cause any instabilities in the AC system. However, to reduce reactive power settling time and to avoid potential interactions with the other plants in the AC system, a 5% reactive power droop was introduced to the Q/V controller in the power plant controller model (REPCA).

No mitigations were found to be required

 

Table 1: AG1-405/AG1-406 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-405

Solar

EKPC

57

57

34.2

Walnut Grove – Asahi 69 kV

AG1-406

BESS

EKPC

22

22

22

Walnut Grove – Asahi 69 kV

 

Reactive Power Analysis

The reactive power capability of AG1-406 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project ID Project Name Status
AA1-018 Powerton-Goodings Grove In Service
AB1-006 Meadow Lake 345kV In Service
AB2-047 Brokaw-Pontiac Midpoint In Service
AB2-070 Mt. Pulaski-Brokaw In Service
AC1-053 Lanesville-Brokaw Under Construction
AC1-168 Kewanee-Streator Suspended
AC2-176 Jay 138 kV In Service
AD1-100 Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV Under Construction
AD1-148 Brokaw-Lanesville In Service
AD2-047 Davis Creek 138 kV Suspended
AD2-205 Byllesby 69 kV In Service
AE1-143 Marion County 161 kV Engineering & Procurement
AE1-172 Loretto-Wilton Center Active
AE1-209 Desoto 345 kV Suspended
AE1-210 Desoto 345 kV Suspended
AE2-019 New Road 230 kV Engineering & Procurement
AE2-071 Patton Rd-Summer Shade 69 kV In Service
AE2-172 Mississinewa-Gaston 138 kV Suspended
AE2-173 McLean 345 kV Active
AE2-223 McLean 345 kV Active
AE2-276 Sullivan 345kV Engineering & Procurement
AE2-326 Jacksons Ferry 138 kV Engineering & Procurement
AF1-038 Sewellton Jct-Webbs Crossroads 69 kV Engineering & Procurement
AF1-045 Cedarville-Ford 138 kV Suspended
AF1-050 Summer Shade - Green County 161 kV Engineering & Procurement
AF1-083 Green County-Saloma 161 kV Engineering & Procurement
AF1-088 Sullivan 345 kV Active
AF1-090 Kincaid-Pana Engineering & Procurement
AF1-092 Huntington Jct. 138 kV Suspended
AF1-118 Sorenson-Desoto 345 kV Engineering & Procurement
AF1-119 Keystone-Desoto 345 kV Engineering & Procurement
AF1-162 Inez 138 kV Engineering & Procurement
AF1-202 Keystone-Desoto 345 kV Under Construction
AF1-203 Patton Rd-Summer Shade 69 kV In Service
AF1-204 Eugene 345 kV Active
AF2-008 Sullivan 345 kV Active
AF2-013 Arnold's Corner-Dahlgren 230 kV Engineering & Procurement
AF2-032 Kincaid 345 kV Engineering & Procurement
AF2-078 Reynolds-Olive #1 345 kV Engineering & Procurement
AF2-177 Sorenson-DeSoto #2 345 kV Active
AF2-226 Katydid Road 345 kV Active
AF2-252 Blue Mound 345 kV Engineering & Procurement
AF2-317 Hill Topper 345 kV In Service
AF2-319 Katydid Road 345 kV Active
AF2-352 Blue Mound 345 kV Engineering & Procurement
AF2-365 Munfordville KU Tap-Horse Cave Jct. 69 kV Active
AF2-370 Delaware-Royerton 138 kV Active
AF2-388 Keystone-Desoto 345 kV Active
AF2-407 Fall Creek 345 kV Active
AF2-408 Fall Creek 138 kV Engineering & Procurement
AF2-441 Burnham 138kV Active
AG1-017 Jay 138 kV Under Construction
AG1-063 Fairhaven 13,8 kV In Service
AG1-070 Bon Ayr 69 kV Active
AG1-071 Bon Ayr 69 kV Active
AG1-104 Waugh Chapel 230 kV Engineering & Procurement
AG1-152 Remington CT 230 kV Engineering & Procurement
AG1-154 Ladysmith CT 230 kV Active
AG1-207 Vandalia 69 kV Engineering & Procurement
AG1-221 Poland Rd-Runway DP 230 kV Under Construction
AG1-236 Lanesville-Brokaw 345 kV Active
AG1-237 Dequine-Eugene 345 kV Engineering & Procurement
AG1-297 Hanna-Tanners Creek 345 kV Active
AG1-324 Jay-Desoto 138 kV Engineering & Procurement
AG1-341 Summer Shade 161 kV Active
AG1-354 Summershade-Green County 161 kV Active
AG1-398 Brokaw-Lanesville 345 kV In Service
AG1-405 Walnut Grove-Asahi 69 kV Active
AG1-414 Mississinewa 138 kV Engineering & Procurement
AG1-433 Keystone-DeSoto 345 kV Active
AG1-460 Kincaid-Pana 345 kV Active
AG1-471 Up Church-Wayne County 69 kV Active
AG1-478 Wilmington 34.5 kV Engineering & Procurement
AG1-483 Dickerson 230 kV Engineering & Procurement
AG1-494 Boxwood-Riverville 138 kV Active
AG1-508 Point Lookout 69 kV Engineering & Procurement
AG1-512 University Park North 345 kV Withdrawn
AG1-555 Dequine 345 kV Engineering & Procurement
V3-007 Desoto-Tanners Creek #1 345kV In Service
W2-048 Brokaw-Lanesville In Service
W4-005 Blue Mound-Latham In Service
X2-022 Brokaw-Lanesville In Service
Z2-087 Pontiac MidPoint-Brokaw 345kV In Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO) No Impact
New York Independent System Operator (NYISO) No Impact
Tennessee Valley Authority (TVA) No Impact
Louisville Gas & Electric (LG&E) Identified Impacts
AG1-406 System Reinforcements:
TO Trans Owner ID Title Category Allocated Cost ($USD)
LGEE LGEE_TC1_15519 Invalid - P7 contingency 69kV not monitored by LGEE Informational $0
LGEE LGEE_TC1_16266 LGEE AFS Analysis has determined reinforcements are not required on the Cooper - Elihu 161kV Line. Informational $0
LGEE None LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B Informational $0
Grand Total: $0

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_15519
Title
Invalid - P7 contingency 69kV not monitored by LGEE
Description
Invalid - P7 contingency 69kV not monitored by LGEE EKPC emergency rating is 143 MVA on the Somerset KU - Ferguston 69kV line.
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending) / LGEE_TC1_16266
Title
LGEE AFS Analysis has determined reinforcements are not required on the Cooper - Elihu 161kV Line.
Description
LGEE Affected System Analysis has determined reinforcements are not required on the Cooper - Elihu 161kV Line. Thus EKPC existing 298 MVA Rate B is adequate as LGEE is the limiting element of the line. No reinforcements are required by EKPC.
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
LGEE
RTEP ID / TO ID
(Pending)
Title
LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B
Description
LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)

Duke Energy Carolinas (DUKE) No Impact
Duke Energy Progress – East (CPLE) No Impact
Duke Energy Progress – West (CPLW) No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 312.A.1.b and as outlined in PJM Manual 14H, Section 13, in Phase III of the Cycle, PJM coordinates with the Affected System Operators to conduct any studies required to determine the impact of the New Service Request on any Affected System and will include the Affected System Study results in Phase III System Impact Study, if available from the Affected System Operator.

If your project required an Affected System Study, the results are shown below from the Affected System Operator.

For more details, please refer to your Affected System Study report by the Affected System Operator. If the Affected System Operator identified the need for a system reinforcement on their system due to their planning criteria, Project Developer must follow the Affected System Operator Tariff for construction of the network upgrade. PJM will list any required network upgrades identified by the Affected System Operator in the PJM Project Developer’s GIA under Schedule F.

Affected System network upgrade costs are included in the Adverse Study Impact calculation for DP3. See the Adverse Test Eligibility section of this Phase III SIS report.

Midcontinent Independent System Operator, Inc. (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase III System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b4000.251
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.251
Title
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Description
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG1-406 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG1-406 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line (Any)

System Reinforcement: b4000.252
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.252
Title
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Description
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG1-406 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG1-406 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
05CLOVRD-05JOSHUA 765.0 kV Ckt 1 line (Any)

System Reinforcement: b3788.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b3788.1 / B3788.1
Title
Replace limiting station elements at Kyger Creek
Description
Upgrade existing 345 kV terminal equipment at Kyger Creek on the Kyger Creek-Sporn 345 kV line. Projected in-service date 6/1/2028 Replace AEP-owned station takeoff riser and breaker BB risers at OVEC-owned Kyger Creek station.
Cost Information
Time Estimate
Nov 18 2027

Not Contingent

Note: AG1-406 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG1-406 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
05SPORN-06KYGER 345.0 kV Ckt 1 line (Any)

System Reinforcement: b3788.2
Type
Load Flow
TO
OVEC
RTEP ID / TO ID
b3788.2 / B3788.2
Title
Replace limiting station elements at Kyger Creek
Description
Upgrade existing 345 kV terminal equipment at Kyger Creek on the Kyger Creek-Sporn 345 kV line. Projected in-service date 6/1/2028 Replace OVEC-owned breaker AA risers, bus work, and breaker AA disconnect switches at OVEC-owned Kyger Creek station.
Cost Information
Time Estimate
Jun 01 2028

Not Contingent

Note: AG1-406 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG1-406 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Facility Contingency
05SPORN-06KYGER 345.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
(Pending) / EKPC-tc1-r0004a
Title
EKPC emergency rating is 143 MVA.
Description
EKPC emergency rating is 143 MVA. LG&E: SE rating is 105 MVA.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
2FERGUSON SO-2SOMERSET KU 69.0 kV Ckt 1 line (Any)

System Reinforcement
Type
Load Flow
TO
EKPC
RTEP ID / TO ID
(Pending) / EKPC-tc1-r0012a
Title
LGE/KU is limiting this facility. EKPC emergency rating is 298 MVA.
Description
LGE/KU is limiting this facility (LGEE Summer 219/277 MVA & winter 335/335 MVA Rate A/Rate B). EKPC emergency rating is 298 MVA. LGEE AFS for TC1 has determined they will not require an reinforcement and thus EKPC existing 298 MVA Rate B is adequate as LGEE is the limiting element of the line.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

Facility Contingency
5ELIHU-5COOPER2 161.0 kV Ckt 1 line (Any)

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG1-406


AG1-406 Contributions into Topology or Eliminated Reinforcements:
Type TO RTEP ID / TO ID Title Topo or Elim MW Impact Percent Allocation Category Allocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total: $0
AG1-406 Contingent Region Topology Upgrades:
TO RTEP ID Title Category Allocated Cost ($USD)
Region Topology Upgrade Total: $0

Attachments

AG1-406 One Line Diagram

AG1-406 One Line Diagram.png

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.