AG2-061 Phase I Study Report

v1.00 released 2025-10-29 21:49

Dana 345 kV

20.0 MW Capacity / 50.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Aurora Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed an uprate to a planned/existing Solar/Wind facility located in the Commonwealth Edison Company zone — Lasalle County, Illinois. This project is an increase to the developer’s AD2-038/AF2-143 project(s), which will share the same Point of Interconnection. The AG2-061 project is a 50.0 MW uprate (20.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 200.0 MW with 136.4 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-061
Project Name:
Dana 345 kV
Project Developer Name:
Aurora Solar LLC
State:
Illinois
County:
Lasalle
Transmission Owner:
Commonwealth Edison Company
MFO:
200.0
MWE:
50.0
MWC:
20.0
Battery Storage Specification:
200.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AG2-061 will interconnect on the Commonwealth Edison Company  transmission system via a Direct connection into the Dana 345 kV substation. .

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AG2-061 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-061Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$0$0
Other Scope$350,000$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$350,000$0

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AG2-061

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AG2-061 Project due at DP1
ABA - B
AG2-061$0$200,000$0

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project, unless the Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or applicable Network Upgrades have been securitized in an ISA/GIA. 

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Physical Interconnection
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)SCADA, Relay and Comm' review/updates.$350,000 $350,000

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 12 to 15 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

Notes on Cost Estimate:

  1. These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
  2. There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
  3. These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
  4. The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.

 

 

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-061 was evaluated as a 50.0 MW (20.0 MW Capacity) injection in the ComEd area.

AG2-061 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 200.0 MW (50.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2CE
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
COMED_P4_012-45-BT11-12_SRT-A
BreakerAC144.26 %1568.0STE2261.982.97
GD2CE
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
COMED_P1-2_345-L1227__R-S_SRT-A
SingleAC127.67 %1568.0STE2001.83.04
GD2CE
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
COMED_P4_939_45-BT2-3___SRT-A
BreakerAC112.0 %1568.0STE1756.173.1
IPDCE
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
COMED_P4_012-45-BT11-12_SRT-A
BreakerAC111.35 %1568.0STE1745.957.43
IPDCE
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
COMED_P1-2_345-L1227__R-S_SRT-A
SingleAC110.68 %1568.0STE1735.517.59
GD2CE
MULBERRY ; R-DRESDEN ; R 345.0 kV Ckt 1 line
COMED_P4_012-45-BT4-5___SRT-A
BreakerAC119.78 %1837.0STE2200.383.16
GD2CE
MULBERRY ; R-DRESDEN ; R 345.0 kV Ckt 1 line
COMED_P1-2_345-L1202__B-S_SRT-A
SingleAC107.43 %1837.0STE1973.493.23
GD2AMIL/CE
POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A
TowerAC119.4 %1656.0B1977.3314.77

Details for MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line l/o COMED_P4_012-45-BT11-12_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_012-45-BT11-12_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:144.26 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:2261.98
MW Contribution:2.97
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
11.715
274678POWERTON ;6U
50/50
11.774
274848CAMPGROVE;RU
Solar/Wind Harmer
5.836
274851PROVIDENC;RU
Solar/Wind Harmer
1.906
274861TOP CROP ;1U
Solar/Wind Harmer
4.798
274862TOP CROP ;2U
Solar/Wind Harmer
4.006
274877BISHOP HL;1U
Solar/Wind Harmer
2.611
274878BISHOP HL;2U
Solar/Wind Harmer
2.611
274879MINONK ;1U
Solar/Wind Harmer
30.396
274849CRESCENT ;1U
Solar/Wind Harmer
1.238
276691AA1-018 GEN1
Solar/Wind Harmer
0.374
276694AA1-018 GEN2
Solar/Wind Harmer
5.063
276782AC1-033 GEN
Solar/Wind Harmer
3.082
276646AC1-214 GEN2
Solar/Wind Harmer
0.897
276645AC1-214 GEN1
Solar/Wind Harmer
0.897
926823AC1-168 GEN
Solar/Wind Harmer
2.068
276893AG1-478 C
Solar/Wind Helper
0.308
276658THREERVRS;U1
50/50
28.268
276660THREERVRS;U2
50/50
28.305
276889AE2-281 GEN
Solar/Wind Harmer
3.72
276872AE1-163_GEN1
Solar/Wind Harmer
13.021
276876AE1-163_GEN2
Solar/Wind Harmer
13.021
276882AE2-255 GEN
Solar/Wind Harmer
15.198
276868AE1-113 GEN
Solar/Wind Harmer
45.59
276805AD2-038 GEN
Solar/Wind Harmer
6.559
958481AF2-142 GEN
Solar/Wind Harmer
12.035
958491AF2-143 GEN
Solar/Wind Harmer
19.179
970569AG2-363 GEN
Solar/Wind Harmer
71.763
970571AG2-364 GEN
Solar/Wind Harmer
47.842
957751AF2-069 GEN
Solar/Wind Harmer
0.307
971997AH1-543 GEN
Solar/Wind Harmer
80.052
970073AG2-061 GEN
50/50
2.973
990353J1289
External Queue
5.49595308303833
990752J1383
External Queue
16.262409210205078
991278J1725 G
External Queue
5.79633092880249
991303J1755 G
External Queue
5.005650043487549
NYPJM->LTFIMP_NY
CLTF
0.359
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.05
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.007
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.116
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.293
LAGNLTFEXP_LAGN->PJM
CLTF
2.487
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.095
CBM West 2LTFEXP_CBM-W2->PJM
CBM
20.525
CBM South 1LTFEXP_CBM-S1->PJM
CBM
2.346
TVALTFEXP_TVA->PJM
CLTF
0.784
MECLTFEXP_MEC->PJM
CLTF
5.043
SIGELTFEXP_SIGE->PJM
CLTF
0.017

Details for MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L1227__R-S_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L1227__R-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:127.67 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:2001.8
MW Contribution:3.04
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
11.832
274678POWERTON ;6U
50/50
11.891
274848CAMPGROVE;RU
Solar/Wind Harmer
0.001
274851PROVIDENC;RU
Solar/Wind Harmer
0.001
274861TOP CROP ;1U
Solar/Wind Harmer
0.002
274862TOP CROP ;2U
Solar/Wind Harmer
0.776
274877BISHOP HL;1U
Solar/Wind Harmer
0.183
274878BISHOP HL;2U
Solar/Wind Harmer
0.183
274879MINONK ;1U
Solar/Wind Harmer
1.336
274849CRESCENT ;1U
Solar/Wind Harmer
0.001
276691AA1-018 GEN1
Solar/Wind Harmer
0.702
276694AA1-018 GEN2
Solar/Wind Harmer
0.001
276782AC1-033 GEN
Solar/Wind Harmer
0.001
276646AC1-214 GEN2
Solar/Wind Harmer
0.185
276645AC1-214 GEN1
Solar/Wind Harmer
0.185
926823AC1-168 GEN
Solar/Wind Harmer
0.572
276893AG1-478 C
Solar/Wind Helper
0.3
276658THREERVRS;U1
50/50
28.459
276660THREERVRS;U2
50/50
28.496
276889AE2-281 GEN
Solar/Wind Harmer
0.001
276872AE1-163_GEN1
Solar/Wind Harmer
0.004
276876AE1-163_GEN2
Solar/Wind Harmer
0.004
276882AE2-255 GEN
Solar/Wind Harmer
3.703
276868AE1-113 GEN
Solar/Wind Harmer
6.355
276805AD2-038 GEN
Solar/Wind Harmer
0.003
958481AF2-142 GEN
Solar/Wind Harmer
8.695
958491AF2-143 GEN
Solar/Wind Harmer
13.665
970569AG2-363 GEN
Solar/Wind Harmer
50.57
970571AG2-364 GEN
Solar/Wind Harmer
33.713
957751AF2-069 GEN
Solar/Wind Harmer
0.155
971997AH1-543 GEN
Solar/Wind Harmer
18.75
959351AF2-226 GEN
50/50
1.912
960281AF2-319 GEN
50/50
1.912
970073AG2-061 GEN
50/50
3.037
990353J1289
External Queue
5.426510334014893
990752J1383
External Queue
16.331815719604492
991278J1725 G
External Queue
5.802485942840576
991303J1755 G
External Queue
5.045654296875
NYPJM->LTFIMP_NY
CLTF
0.365
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.06
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.014
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.13
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.337
LAGNLTFEXP_LAGN->PJM
CLTF
2.441
CBM West 1LTFEXP_CBM-W1->PJM
CBM
3.264
CBM West 2LTFEXP_CBM-W2->PJM
CBM
20.076
CBM South 1LTFEXP_CBM-S1->PJM
CBM
2.255
TVALTFEXP_TVA->PJM
CLTF
0.759
MECLTFEXP_MEC->PJM
CLTF
5.053
SIGELTFEXP_SIGE->PJM
CLTF
0.015

Details for MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line l/o COMED_P4_939_45-BT2-3___SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_939_45-BT2-3___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:112.0 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1756.17
MW Contribution:3.1
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
11.955
274678POWERTON ;6U
50/50
12.013
274848CAMPGROVE;RU
Solar/Wind Harmer
6.032
274851PROVIDENC;RU
Solar/Wind Harmer
1.99
274861TOP CROP ;1U
Solar/Wind Harmer
5.135
274862TOP CROP ;2U
Solar/Wind Harmer
4.287
274877BISHOP HL;1U
Solar/Wind Harmer
2.712
274878BISHOP HL;2U
Solar/Wind Harmer
2.712
274879MINONK ;1U
Solar/Wind Harmer
30.799
274849CRESCENT ;1U
Solar/Wind Harmer
1.292
276691AA1-018 GEN1
Solar/Wind Harmer
0.398
276694AA1-018 GEN2
Solar/Wind Harmer
5.401
276782AC1-033 GEN
Solar/Wind Harmer
3.201
276646AC1-214 GEN2
Solar/Wind Harmer
0.936
276645AC1-214 GEN1
Solar/Wind Harmer
0.936
926823AC1-168 GEN
Solar/Wind Harmer
2.182
276893AG1-478 C
Solar/Wind Helper
0.289
276660THREERVRS;U2
50/50
28.595
276889AE2-281 GEN
Solar/Wind Harmer
3.817
276872AE1-163_GEN1
Solar/Wind Harmer
13.359
276876AE1-163_GEN2
Solar/Wind Harmer
13.359
276882AE2-255 GEN
Solar/Wind Harmer
15.399
276868AE1-113 GEN
Solar/Wind Harmer
46.194
276805AD2-038 GEN
Solar/Wind Harmer
6.827
958481AF2-142 GEN
Solar/Wind Harmer
12.838
958491AF2-143 GEN
Solar/Wind Harmer
19.961
970569AG2-363 GEN
Solar/Wind Harmer
73.233
970571AG2-364 GEN
Solar/Wind Harmer
48.822
957751AF2-069 GEN
Solar/Wind Harmer
0.321
971997AH1-543 GEN
Solar/Wind Harmer
81.016
970073AG2-061 GEN
50/50
3.095
990353J1289
External Queue
5.426510334014893
990752J1383
External Queue
16.331815719604492
991278J1725 G
External Queue
5.802485942840576
991303J1755 G
External Queue
5.045654296875
NYPJM->LTFIMP_NY
CLTF
0.204
LGEELTFEXP_LGEE->PJM
CLTF
0.089
CPLELTFEXP_CPLE->PJM
CLTF
0.12
LAGNLTFEXP_LAGN->PJM
CLTF
2.949
CBM West 1LTFEXP_CBM-W1->PJM
CBM
6.922
CBM West 2LTFEXP_CBM-W2->PJM
CBM
23.452
CBM South 1LTFEXP_CBM-S1->PJM
CBM
3.208
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.702
TVALTFEXP_TVA->PJM
CLTF
1.014
MECLTFEXP_MEC->PJM
CLTF
5.474
SIGELTFEXP_SIGE->PJM
CLTF
0.028

Details for [AG2-061] MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line l/o COMED_P4_012-45-BT11-12_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_012-45-BT11-12_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:111.35 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1745.95
MW Contribution:7.43
IPD Plant:AG2-061
Bus #Bus NameTypeMW Contribution
970073AG2-061 GEN
PJM_IPD_GROUP
7.434

Details for [AG2-061] MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L1227__R-S_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; B-DRESDEN ; B 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L1227__R-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:110.68 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1735.51
MW Contribution:7.59
IPD Plant:AG2-061
Bus #Bus NameTypeMW Contribution
970073AG2-061 GEN
PJM_IPD_GROUP
7.592

Details for MULBERRY ; R-DRESDEN ; R 345.0 kV Ckt 1 line l/o COMED_P4_012-45-BT4-5___SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; R-DRESDEN ; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_012-45-BT4-5___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:119.78 %
Rating:1837.0 MVA
Rating Type:STE
MVA to Mitigate:2200.38
MW Contribution:3.16
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
12.175
274678POWERTON ;6U
50/50
12.233
274848CAMPGROVE;RU
Solar/Wind Harmer
6.294
274851PROVIDENC;RU
Solar/Wind Harmer
2.162
274861TOP CROP ;1U
Solar/Wind Harmer
5.793
274862TOP CROP ;2U
Solar/Wind Harmer
4.837
274877BISHOP HL;1U
Solar/Wind Harmer
2.879
274878BISHOP HL;2U
Solar/Wind Harmer
2.879
274879MINONK ;1U
Solar/Wind Harmer
31.177
274849CRESCENT ;1U
Solar/Wind Harmer
1.404
276691AA1-018 GEN1
Solar/Wind Harmer
0.409
276694AA1-018 GEN2
Solar/Wind Harmer
5.544
276782AC1-033 GEN
Solar/Wind Harmer
3.399
276646AC1-214 GEN2
Solar/Wind Harmer
1.017
276645AC1-214 GEN1
Solar/Wind Harmer
1.017
926823AC1-168 GEN
Solar/Wind Harmer
2.373
276658THREERVRS;U1
50/50
28.907
276660THREERVRS;U2
50/50
28.871
276889AE2-281 GEN
Solar/Wind Harmer
3.891
276872AE1-163_GEN1
Solar/Wind Harmer
13.618
276876AE1-163_GEN2
Solar/Wind Harmer
13.618
276882AE2-255 GEN
Solar/Wind Harmer
15.588
276868AE1-113 GEN
Solar/Wind Harmer
46.76
276805AD2-038 GEN
Solar/Wind Harmer
6.977
958481AF2-142 GEN
Solar/Wind Harmer
13.177
958491AF2-143 GEN
Solar/Wind Harmer
20.401
970569AG2-363 GEN
Solar/Wind Harmer
74.584
970571AG2-364 GEN
Solar/Wind Harmer
49.723
957751AF2-069 GEN
Solar/Wind Harmer
0.349
971997AH1-543 GEN
Solar/Wind Harmer
82.056
959351AF2-226 GEN
50/50
2.223
960281AF2-319 GEN
50/50
2.223
970073AG2-061 GEN
50/50
3.163
990353J1289
External Queue
4.809133529663086
990752J1383
External Queue
16.256980895996094
991278J1725 G
External Queue
5.6570892333984375
991303J1755 G
External Queue
5.535541534423828
NYPJM->LTFIMP_NY
CLTF
0.437
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.137
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.061
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.235
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.669
LAGNLTFEXP_LAGN->PJM
CLTF
2.336
CBM West 1LTFEXP_CBM-W1->PJM
CBM
9.029
CBM West 2LTFEXP_CBM-W2->PJM
CBM
18.224
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.794
TVALTFEXP_TVA->PJM
CLTF
0.646
MECLTFEXP_MEC->PJM
CLTF
5.836
SIGELTFEXP_SIGE->PJM
CLTF
0.004

Details for MULBERRY ; R-DRESDEN ; R 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L1202__B-S_SRT-A


Base Case Flowgate

Area:CE
Facility Description:
MULBERRY ; R-DRESDEN ; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L1202__B-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:107.43 %
Rating:1837.0 MVA
Rating Type:STE
MVA to Mitigate:1973.49
MW Contribution:3.23
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
12.296
274678POWERTON ;6U
50/50
12.355
274848CAMPGROVE;RU
Solar/Wind Harmer
0.001
274851PROVIDENC;RU
Solar/Wind Harmer
0.001
274861TOP CROP ;1U
Solar/Wind Harmer
0.002
274862TOP CROP ;2U
Solar/Wind Harmer
0.869
274877BISHOP HL;1U
Solar/Wind Harmer
0.201
274878BISHOP HL;2U
Solar/Wind Harmer
0.201
274879MINONK ;1U
Solar/Wind Harmer
1.376
274849CRESCENT ;1U
Solar/Wind Harmer
0.001
276691AA1-018 GEN1
Solar/Wind Harmer
0.767
276694AA1-018 GEN2
Solar/Wind Harmer
0.001
276782AC1-033 GEN
Solar/Wind Harmer
0.001
276646AC1-214 GEN2
Solar/Wind Harmer
0.208
276645AC1-214 GEN1
Solar/Wind Harmer
0.208
926823AC1-168 GEN
Solar/Wind Harmer
0.654
276658THREERVRS;U1
50/50
29.27
276660THREERVRS;U2
50/50
29.234
276889AE2-281 GEN
Solar/Wind Harmer
0.001
276872AE1-163_GEN1
Solar/Wind Harmer
0.004
276876AE1-163_GEN2
Solar/Wind Harmer
0.004
276882AE2-255 GEN
Solar/Wind Harmer
3.813
276868AE1-113 GEN
Solar/Wind Harmer
6.544
276805AD2-038 GEN
Solar/Wind Harmer
0.003
958481AF2-142 GEN
Solar/Wind Harmer
9.5
958491AF2-143 GEN
Solar/Wind Harmer
14.526
970569AG2-363 GEN
Solar/Wind Harmer
52.553
970571AG2-364 GEN
Solar/Wind Harmer
35.035
957751AF2-069 GEN
Solar/Wind Harmer
0.175
971997AH1-543 GEN
Solar/Wind Harmer
19.315
959351AF2-226 GEN
50/50
2.14
960281AF2-319 GEN
50/50
2.14
970073AG2-061 GEN
50/50
3.228
990353J1289
External Queue
4.970827579498291
990752J1383
External Queue
16.503253936767578
991278J1725 G
External Queue
5.760590553283691
991303J1755 G
External Queue
5.556852340698242
NYPJM->LTFIMP_NY
CLTF
0.434
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.129
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.055
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.224
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.633
LAGNLTFEXP_LAGN->PJM
CLTF
2.391
CBM West 1LTFEXP_CBM-W1->PJM
CBM
8.404
CBM West 2LTFEXP_CBM-W2->PJM
CBM
18.797
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.891
TVALTFEXP_TVA->PJM
CLTF
0.673
MECLTFEXP_MEC->PJM
CLTF
5.826
SIGELTFEXP_SIGE->PJM
CLTF
0.006

Details for POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line l/o COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A


Base Case Flowgate

Area:AMIL/CE
Facility Description:
POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
Contingency Name:
COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:119.4 %
Rating:1656.0 MVA
Rating Type:B
MVA to Mitigate:1977.33
MW Contribution:14.77
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
31.102
274678POWERTON ;6U
50/50
31.102
274848CAMPGROVE;RU
Solar/Wind Helper
1.304
274851PROVIDENC;RU
Solar/Wind Helper
0.71
274861TOP CROP ;1U
Solar/Wind Harmer
38.493
274862TOP CROP ;2U
Solar/Wind Harmer
32.143
274877BISHOP HL;1U
Solar/Wind Helper
1.383
274878BISHOP HL;2U
Solar/Wind Helper
1.383
274879MINONK ;1U
Solar/Wind Harmer
26.017
274849CRESCENT ;1U
Solar/Wind Helper
0.668
276691AA1-018 GEN1
Solar/Wind Harmer
2.957
276694AA1-018 GEN2
Solar/Wind Harmer
40.086
276782AC1-033 GEN
Solar/Wind Helper
1.006
276646AC1-214 GEN2
Solar/Wind Helper
0.492
276645AC1-214 GEN1
Solar/Wind Helper
0.492
276889AE2-281 GEN
Solar/Wind Harmer
12.189
276872AE1-163_GEN1
Solar/Wind Harmer
42.661
276876AE1-163_GEN2
Solar/Wind Harmer
42.661
276882AE2-255 GEN
Solar/Wind Harmer
13.008
276868AE1-113 GEN
Solar/Wind Harmer
39.023
276805AD2-038 GEN
Solar/Wind Harmer
32.584
958481AF2-142 GEN
Solar/Wind Harmer
95.281
958491AF2-143 GEN
Solar/Wind Harmer
95.276
970569AG2-363 GEN
Solar/Wind Harmer
190.528
970571AG2-364 GEN
Solar/Wind Harmer
127.018
959351AF2-226 GEN
50/50
14.772
960281AF2-319 GEN
50/50
14.772
970073AG2-061 GEN
50/50
14.771
NYPJM->LTFIMP_NY
CLTF
0.488
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.741
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.465
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
7.878
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.666
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.12
GibsonPJM->LTFIMP_GIBSON
CLTF
0
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
MDUPJM->LTFIMP_MDU
CLTF
0
CONTINGENCY 'COMED_P4_012-45-BT11-12_SRT-A'
 CLOSE BRANCH FROM BUS 270824 TO BUS 270825 CKT Z1   /*MULBERRY ; B 345.0 - MULBERRY ; R 345.0
 TRIP BRANCH FROM BUS 270717 TO BUS 270737 CKT 1     /*DRESDEN  ; R 345.0 - ELWOOD   ; R 345.0
 TRIP BRANCH FROM BUS 270717 TO BUS 270825 CKT 1     /*DRESDEN  ; R 345.0 - MULBERRY ; R 345.0
END
CONTINGENCY 'COMED_P1-2_345-L1227__R-S_SRT-A'
 CLOSE BRANCH FROM BUS 270824 TO BUS 270825 CKT Z1   /*MULBERRY ; B 345.0 - MULBERRY ; R 345.0
 TRIP BRANCH FROM BUS 270717 TO BUS 270825 CKT 1     /*DRESDEN  ; R 345.0 - MULBERRY ; R 345.0
END
CONTINGENCY 'COMED_P4_939_45-BT2-3___SRT-A'
 CLOSE BRANCH FROM BUS 270824 TO BUS 270825 CKT Z1   /*MULBERRY ; B 345.0 - MULBERRY ; R 345.0
 DISCONNECT BUS 276658                               /*THREERVRS;U1  22.5
 REMOVE UNIT 1 FROM BUS 276658                       /*THREERVRS;U1  22.5
 TRIP BRANCH FROM BUS 270717 TO BUS 270825 CKT 1     /*DRESDEN  ; R 345.0 - MULBERRY ; R 345.0
END
CONTINGENCY 'COMED_P4_012-45-BT4-5___SRT-A'
 CLOSE BRANCH FROM BUS 270824 TO BUS 270825 CKT Z1   /*MULBERRY ; B 345.0 - MULBERRY ; R 345.0
 TRIP BRANCH FROM BUS 270716 TO BUS 270736 CKT 1     /*DRESDEN  ; B 345.0 - ELWOOD   ; B 345.0
 TRIP BRANCH FROM BUS 270716 TO BUS 270824 CKT 1     /*DRESDEN  ; B 345.0 - MULBERRY ; B 345.0
 TRIP BRANCH FROM BUS 270736 TO BUS 270737 CKT Z1    /*ELWOOD   ; B 345.0 - ELWOOD   ; R 345.0
END
CONTINGENCY 'COMED_P1-2_345-L1202__B-S_SRT-A'
 CLOSE BRANCH FROM BUS 270824 TO BUS 270825 CKT Z1   /*MULBERRY ; B 345.0 - MULBERRY ; R 345.0
 TRIP BRANCH FROM BUS 270716 TO BUS 270824 CKT 1     /*DRESDEN  ; B 345.0 - MULBERRY ; B 345.0
END
CONTINGENCY 'COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A'
 TRIP BRANCH FROM BUS 270790 TO BUS 270770 CKT 1   /*KATYDID  ; B 345.0 - GOODINGS ;4B 345.0
 TRIP BRANCH FROM BUS 270827 TO BUS 270769 CKT 1   /*NEVADA   ; R 345.0 - GOODINGS ;2R 345.0
END
270824 to 270716 ckt 1
270825 to 270717 ckt 1
270855 to 349662 ckt 1

Winter Peak Analysis

The New Service Request AG2-061 was evaluated as a 50.0 MW (20.0 MW Capacity) injection in the ComEd area.

AG2-061 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 200.0 MW (50.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AMIL/CE
POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A
TowerAC109.24 %1656.0B1809.014.75

Details for POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line l/o COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A


Base Case Flowgate

Area:AMIL/CE
Facility Description:
POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line
Contingency Name:
COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:109.24 %
Rating:1656.0 MVA
Rating Type:B
MVA to Mitigate:1809.0
MW Contribution:14.75
Bus #Bus NameTypeMW Contribution
274677POWERTON ;5U
50/50
31.579
274678POWERTON ;6U
50/50
31.494
274848CAMPGROVE;RU
Solar/Wind Helper
0.842
274851PROVIDENC;RU
Solar/Wind Helper
0.154
274861TOP CROP ;1U
Solar/Wind Harmer
72.714
274862TOP CROP ;2U
Solar/Wind Harmer
60.398
274877BISHOP HL;1U
Solar/Wind Helper
0.708
274878BISHOP HL;2U
Solar/Wind Helper
0.708
274879MINONK ;1U
Solar/Wind Harmer
52.552
274849CRESCENT ;1U
Solar/Wind Helper
0.264
276691AA1-018 GEN1
Solar/Wind Harmer
3.971
276694AA1-018 GEN2
Solar/Wind Harmer
71.156
276646AC1-214 GEN2
Solar/Wind Helper
0.365
276645AC1-214 GEN1
Solar/Wind Helper
0.365
276889AE2-281 GEN
Solar/Wind Harmer
23.596
276872AE1-163_GEN1
Solar/Wind Harmer
82.586
276876AE1-163_GEN2
Solar/Wind Harmer
82.586
276882AE2-255 GEN
Solar/Wind Harmer
23.705
276868AE1-113 GEN
Solar/Wind Harmer
75.138
276805AD2-038 GEN
Solar/Wind Harmer
66.812
958481AF2-142 GEN
Solar/Wind Harmer
5.531
958491AF2-143 GEN
Solar/Wind Harmer
5.531
970569AG2-363 GEN
Solar/Wind Harmer
11.06
970571AG2-364 GEN
Solar/Wind Harmer
7.373
959351AF2-226 GEN
50/50
14.749
960281AF2-319 GEN
50/50
14.749
970073AG2-061 GEN
50/50
14.749
276782AC1-033 GEN
Solar/Wind Helper
0.158
NYPJM->LTFIMP_NY
CLTF
0.556
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.814
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.51
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
8.204
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.734
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.332
MDUPJM->LTFIMP_MDU
CLTF
0
CONTINGENCY 'COMED_P7-1_345-L9806__R-S_+_345-L19601_B-S_SRT-A'
 TRIP BRANCH FROM BUS 270790 TO BUS 270770 CKT 1   /*KATYDID  ; B 345.0 - GOODINGS ;4B 345.0
 TRIP BRANCH FROM BUS 270827 TO BUS 270769 CKT 1   /*NEVADA   ; R 345.0 - GOODINGS ;2R 345.0
END
270855 to 349662 ckt 1

Light Load Analysis

The New Service Request AG2-061 was evaluated as a 50.0 MW injection and 50.0 MW withdrawal in the ComEd area.

AG2-061 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 200.0 MW (50.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AA1-018Powerton-Goodings GroveIn Service
AC1-033Kewanee 138 kVIn Service
AC1-168Kewanee-StreatorSuspended
AC1-214Crescent RidgeIn Service
AD2-038Powerton-Nevada 345 kVUnder Construction
AE1-113Mole Creek 345 kVEngineering & Procurement
AE1-163Powerton-Nevada 345 kVEngineering & Procurement
AE2-255Molecreek 345 kVEngineering & Procurement
AE2-281Powerton-Nevada 345 kVEngineering & Procurement
AF2-069Crescent Ridge 138 kVActive
AF2-142Nevada 345 kVActive
AF2-143Powerton-Nevada 345 kVActive
AF2-226Katydid Road 345 kVActive
AF2-319Katydid Road 345 kVActive
AG1-478Wilmington 34.5 kVEngineering & Procurement
AG2-363Powerton 345 kVActive
AG2-364Powerton 345 kVActive
AH1-543Mulberry – Tazewell 345 kVActive

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts

No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.


System Reinforcement: n9135.0
Type
Load Flow
TO
AMIL
RTEP ID / TO ID
n9135.0 / AMIL_TC1_13300
Title
Ameren - Powerton - Tazewell 345 kV Line Reconductoring & Upgrade Station Equipment
Description
AMIL limit is 1512 MVA 0.64 miles. (PWRT-TAZW-0304). Need to rebuild to be 4000 A/2390 MVA SE, upgrade the Powerton-Tazewell 345 kV circuit 1 terminal equipment and breaker and a half leg at Tazewell from 3000A to 4000A. Rebuild 0.6 miles of the Powerton-Tazewell 345 kV transmission line to increase the ampacity to 4000A
Total Cost ($USD)
$2,760,000
Allocated Cost ($USD)
$0
Time Estimate
Dec 01 2025

Not Contingent

Note: AG2-061 contributes to the loading of an overloaded facility that is being mitigated by a network upgrade that was securitized by a prior Queue/Cycle. AG2-061 is not contingent on this network upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line(Any)
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Study Pending
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b3915.2
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3915.2
Title
Equipment upgrades at Dresden 345 kV Substation
Description
Install 345 kV circuit breaker on line 1202 (Dresden-Mulberry 345 kV) and upgrade disconnects and associated equipment at Dresden 345 kV substation.
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG2-061 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-061 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DRESDEN ; B-MULBERRY ; B 345.0 kV Ckt 1 line(Any)
DRESDEN ; R-MULBERRY ; R 345.0 kV Ckt 1 line(Any)

System Reinforcement: b3915.3
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3915.3
Title
Equipment upgrades at Mulberry 345 kV Substation
Description
Upgrade disconnects and associated equipment at Mulberry 345 kV substation.
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG2-061 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-061 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DRESDEN ; B-MULBERRY ; B 345.0 kV Ckt 1 line(Any)
DRESDEN ; R-MULBERRY ; R 345.0 kV Ckt 1 line(Any)

System Reinforcement: b3915.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
b3915.1
Title
Reconductor 345 kV lines 1202 and 1227 from Dresden to Mulberry
Description
Reconductor 1.5 miles of 345 kV lines 1202 and 1227 from Dresden to Mulberry with two conductor bundled 1033.5 ACSS conductor. Modify and replace towers as necessary to accommodate the higher mechanical loads of the bundled conductor.
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG2-061 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-061 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
DRESDEN ; B-MULBERRY ; B 345.0 kV Ckt 1 line(Any)
DRESDEN ; R-MULBERRY ; R 345.0 kV Ckt 1 line(Any)

System Reinforcement: n6280
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n6280 / ce-005
Title
Mitigate the sag on the ComEd Powerton - Tazewell L0304 345 kV line.
Description
ComEd 345kV L0304 ratings ,SSTE: 1512 MVA and ALDR: 1739 MVA. The post contingency flow for this event exceeds the rating therefore an upgrade is required. The upgarde will be to mitigate the sag on the line. A preliminary estimate for this work is $9.1M with a estimated construction timeline of 30 months. Upon completion of this upgrade the new ratings will be 1461/1656/1909/1912/2198 MVA (SN/SLTE/SSTE/SLD/ALDR).
Total Cost ($USD)
$2,470,000
Allocated Cost ($USD)
$0
Time Estimate
Nov 01 2026

Not Contingent

Note: AG2-061 contributes to the loading of an overloaded facility that is being mitigated by a network upgrade that was securitized by a prior Queue/Cycle. AG2-061 is not contingent on this network upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
POWERTON ; R-7TAZEWELL 345.0 kV Ckt 1 line(Any)

Attachments

AG2-061 One Line Diagram

AG2-061 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.