AG2-062 Phase I Study Report

v1.00 released 2025-10-29 20:50

William 138 kV

21.609 MW Capacity / 147.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Catamount Wind LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is The Potomac Edison Company.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed a Wind generating facility located in the The Potomac Edison Company zone — Grant County, West Virginia. The installed facilities will have a total capability of 147.0 MW with 21.609 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-062
Project Name:
William 138 kV
Project Developer Name:
Catamount Wind LLC
State:
West Virginia
County:
Grant
Transmission Owner:
The Potomac Edison Company
MFO:
147.0
MWE:
147.0
MWC:
21.609
Fuel Type:
Wind
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AG2-062 will interconnect on the The Potomac Edison Company transmission system as a direct connect at the William 138 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AG2-062 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-062Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$4,374,112$0
Other Scope$59,600$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$4,433,712$0

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AG2-062

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AG2-062 Project due at DP1
ABA - B
AG2-062$0$588,000$0

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Interconnection Facilities
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Construct one span of 138 kV circuit from William substation to the Point of Change in Ownership outside the substation.$761,047 $761,047
(Pending)Expand the existing William substation, add one (1) new circuit breaker with SCADA controls.$3,550,485 $3,550,485
(Pending)Integrate Interconnection Facilities protection and controls to the transmission system.$62,580 $62,580
Physical Interconnection
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Install revenue metering on AG2-062 terminal at the existing William substation.$59,600 $59,600

Based on the scope of work for the Interconnection Facilities, it is expected to take 38 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

Transmission Owner Analysis

FE performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AG2-062 did not contribute to any overloads on the FE transmission <100 kV system.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The wind generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Wind speed (meters/second) - (Required)
  • Wind direction (decimal degrees from true north) - (Required)
  • Ambient air temperature (Fahrenheit) - (Required)
  • Air Pressure (Hectopascals) - (Required)
  • Humidity (Percent) - (Accepted, not required)
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-062 was evaluated as a 147.0 MW (21.609 MW Capacity) injection in the APS area.

AG2-062 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 147.0 MW (147.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AP
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line
AP_P7-1_PE-138-012A_SRT-A
TowerAC129.27 %206.0B266.293.79
GD2AP
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line
AP_P2-2_PE-138-066A_SRT-A
BusAC116.07 %206.0B239.13.51
GD2AP
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line
AP_P7-1_WPP-138-011_SRT-A
TowerAC106.66 %206.0B219.723.61
GD2AP
01BLACKO-01BLACKO 138.0/500.0 kV Ckt 3 transformer
AP_P2-3_PE-500-014_SRT-SL
BreakerAC108.3 %558.0B604.327.84
GD2AP
01BLACKO-01BLACKO 138.0/500.0 kV Ckt 3 transformer
AP_P2-3_WP-500-DRT19_SRT-SL
BreakerAC103.19 %558.0B575.87.85
GD2AP
01CROSSCHOOL-01BLACKO 138.0 kV Ckt 1 line
AP_P7-1_PE-138-012A_SRT-A
TowerAC108.85 %268.0B291.713.78
GD2AP
01MTZION-AG2-505 TP 138.0 kV Ckt 1 line
AP_P7-1_PE-138-012A_SRT-A
TowerAC110.51 %206.0B227.653.79
GD2AP
AG2-505 TP-01BERYL 138.0 kV Ckt 1 line
AP_P7-1_PE-138-012A_SRT-A
TowerAC114.9 %206.0B236.693.79
GD2AP
AG2-505 TP-01BERYL 138.0 kV Ckt 1 line
AP_P2-2_PE-138-066A_SRT-A
BusAC101.6 %206.0B209.33.51

Details for 01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line l/o AP_P7-1_PE-138-012A_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line
Contingency Name:
AP_P7-1_PE-138-012A_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:129.27 %
Rating:206.0 MVA
Rating Type:B
MVA to Mitigate:266.29
MW Contribution:3.79
Bus #Bus NameTypeMW Contribution
970697AG2-448 GEN
Solar/Wind Harmer
30.173
238185AF2-356 C
Solar/Wind Harmer
24.766
238193AE1-106 GEN
Solar/Wind Harmer
5.337
238120AE2-309 GEN
Solar/Wind Helper
0.281
970075AG2-062 GEN
Solar/Wind Harmer
3.787
970801AG2-505 GEN
50/50
8.819
23750701CROSSCHOOL
Solar/Wind Helper
3.048
238127S14_GEN_2
Solar/Wind Helper
0.523
238117U2-030
Solar/Wind Harmer
1.14
238126S14_GEN_1
Solar/Wind Helper
0.523
23751201ROTHROCK
Solar/Wind Harmer
1.038
971679AH1-340 GEN
Solar/Wind Harmer
3.675
23750501ELLIOTTS
Solar/Wind Harmer
1.151
238118U2-030_1
Solar/Wind Harmer
0.478
970995AG2-615 GEN
Solar/Wind Harmer
6.063
23562501BACKB
Solar/Wind Harmer
1.262
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.448
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.047
LAGNLTFEXP_LAGN->PJM
CLTF
0.218
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.84
LGEELTFEXP_LGEE->PJM
CLTF
0.123
TVALTFEXP_TVA->PJM
CLTF
0.106
NYPJM->LTFIMP_NY
CLTF
0.093
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.009
SIGELTFEXP_SIGE->PJM
CLTF
0.009
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.859
WECLTFEXP_WEC->PJM
CLTF
0.071
MECLTFEXP_MEC->PJM
CLTF
0.285

Details for 01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line l/o AP_P2-2_PE-138-066A_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line
Contingency Name:
AP_P2-2_PE-138-066A_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:116.07 %
Rating:206.0 MVA
Rating Type:B
MVA to Mitigate:239.1
MW Contribution:3.51
Bus #Bus NameTypeMW Contribution
970697AG2-448 GEN
Solar/Wind Harmer
30.369
238185AF2-356 C
Solar/Wind Harmer
24.837
238120AE2-309 GEN
Solar/Wind Helper
0.201
970075AG2-062 GEN
Solar/Wind Harmer
3.506
970801AG2-505 GEN
50/50
8.864
23750701CROSSCHOOL
Solar/Wind Helper
2.997
238127S14_GEN_2
Solar/Wind Helper
0.348
238126S14_GEN_1
Solar/Wind Helper
0.348
23751201ROTHROCK
Solar/Wind Harmer
0.962
971679AH1-340 GEN
Solar/Wind Harmer
3.381
23750501ELLIOTTS
Solar/Wind Harmer
1.054
970995AG2-615 GEN
Solar/Wind Harmer
5.643
23562501BACKB
Solar/Wind Harmer
1.169
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.382
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.04
LAGNLTFEXP_LAGN->PJM
CLTF
0.186
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.409
LGEELTFEXP_LGEE->PJM
CLTF
0.104
TVALTFEXP_TVA->PJM
CLTF
0.091
NYPJM->LTFIMP_NY
CLTF
0.083
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.007
SIGELTFEXP_SIGE->PJM
CLTF
0.008
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.584
WECLTFEXP_WEC->PJM
CLTF
0.06
MECLTFEXP_MEC->PJM
CLTF
0.243

Details for 01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line l/o AP_P7-1_WPP-138-011_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line
Contingency Name:
AP_P7-1_WPP-138-011_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:106.66 %
Rating:206.0 MVA
Rating Type:B
MVA to Mitigate:219.72
MW Contribution:3.61
Bus #Bus NameTypeMW Contribution
970697AG2-448 GEN
Solar/Wind Harmer
30.661
238185AF2-356 C
Solar/Wind Harmer
25.078
970075AG2-062 GEN
Solar/Wind Harmer
3.612
970801AG2-505 GEN
50/50
8.949
23750701CROSSCHOOL
Solar/Wind Helper
2.923
23751201ROTHROCK
Solar/Wind Harmer
0.987
23750501ELLIOTTS
Solar/Wind Harmer
1.649
971679AH1-340 GEN
Solar/Wind Harmer
3.431
23562501BACKB
Solar/Wind Harmer
1.204
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.398
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.019
SIGELTFEXP_SIGE->PJM
CLTF
0.007
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.236
LGEELTFEXP_LGEE->PJM
CLTF
0.101
MECLTFEXP_MEC->PJM
CLTF
0.233
NYPJM->LTFIMP_NY
CLTF
0.106
TVALTFEXP_TVA->PJM
CLTF
0.097
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.588
WECLTFEXP_WEC->PJM
CLTF
0.057
LAGNLTFEXP_LAGN->PJM
CLTF
0.197

Details for 01BLACKO-01BLACKO 138.0/500.0 kV Ckt 3 transformer l/o AP_P2-3_PE-500-014_SRT-SL


Base Case Flowgate

Area:AP
Facility Description:
01BLACKO-01BLACKO 138.0/500.0 kV Ckt 3 transformer
Contingency Name:
AP_P2-3_PE-500-014_SRT-SL
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:108.3 %
Rating:558.0 MVA
Rating Type:B
MVA to Mitigate:604.32
MW Contribution:7.84
Bus #Bus NameTypeMW Contribution
238109AE1-109 GEN2
Solar/Wind Harmer
0.395
238110AE1-109 GEN3
Solar/Wind Harmer
0.395
970697AG2-448 GEN
Solar/Wind Harmer
17.016
238185AF2-356 C
Solar/Wind Harmer
14.715
238193AE1-106 GEN
Solar/Wind Harmer
8.096
238120AE2-309 GEN
Solar/Wind Harmer
1.009
235048AD1-125 C1
Solar/Wind Harmer
4.411
970075AG2-062 GEN
Solar/Wind Harmer
7.838
970801AG2-505 GEN
50/50
5.078
23750701CROSSCHOOL
Solar/Wind Harmer
11.756
238127S14_GEN_2
Solar/Wind Harmer
2.086
202652Y1-033 WT C
Solar/Wind Harmer
0.622
20089026BF_G21_K23
Solar/Wind Harmer
0.318
238117U2-030
Solar/Wind Harmer
3.018
23585401KL_K28_T16
Solar/Wind Harmer
6.181
203955AF1-039 C O1
Solar/Wind Harmer
0.303
238126S14_GEN_1
Solar/Wind Harmer
2.086
23751201ROTHROCK
Solar/Wind Harmer
1.941
20089226LOOKOUT
Solar/Wind Harmer
0.391
20084026DEEPCRK1
50/50
0.068
942731AE2-289 GEN
Solar/Wind Harmer
7.516
944781AF1-143 GEN
Solar/Wind Harmer
1.377
235049AD1-125 C2
Solar/Wind Harmer
4.411
971679AH1-340 GEN
Solar/Wind Harmer
4.46
23750501ELLIOTTS
Solar/Wind Harmer
1.438
238118U2-030_1
Solar/Wind Harmer
1.267
20089126CSLMN_L13
Solar/Wind Harmer
0.402
235054AD2-180 GEN
Solar/Wind Harmer
7.425
238108AE1-109 GEN1
Solar/Wind Harmer
0.395
235531U2-073 GEN
Solar/Wind Harmer
8.001
970995AG2-615 GEN
Solar/Wind Harmer
14.008
23562501BACKB
Solar/Wind Harmer
2.612
23600101WARRIOR RN
50/50
39.966
20084126DEEPCRK2
50/50
0.068
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.451
WECLTFEXP_WEC->PJM
CLTF
0.208
LAGNLTFEXP_LAGN->PJM
CLTF
0.723
CBM West 1LTFEXP_CBM-W1->PJM
CBM
8.194
NYPJM->LTFIMP_NY
CLTF
0.307
TVALTFEXP_TVA->PJM
CLTF
0.356
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.035
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.051
SIGELTFEXP_SIGE->PJM
CLTF
0.027
CBM West 2LTFEXP_CBM-W2->PJM
CBM
5.787
LGEELTFEXP_LGEE->PJM
CLTF
0.362
MECLTFEXP_MEC->PJM
CLTF
0.849

Details for 01BLACKO-01BLACKO 138.0/500.0 kV Ckt 3 transformer l/o AP_P2-3_WP-500-DRT19_SRT-SL


Base Case Flowgate

Area:AP
Facility Description:
01BLACKO-01BLACKO 138.0/500.0 kV Ckt 3 transformer
Contingency Name:
AP_P2-3_WP-500-DRT19_SRT-SL
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:103.19 %
Rating:558.0 MVA
Rating Type:B
MVA to Mitigate:575.8
MW Contribution:7.85
Bus #Bus NameTypeMW Contribution
238109AE1-109 GEN2
Solar/Wind Harmer
0.395
238110AE1-109 GEN3
Solar/Wind Harmer
0.395
964991AG1-363 GEN
Solar/Wind Helper
6.213
970697AG2-448 GEN
Solar/Wind Harmer
17.025
238185AF2-356 C
Solar/Wind Harmer
14.725
238193AE1-106 GEN
Solar/Wind Harmer
8.114
238120AE2-309 GEN
Solar/Wind Harmer
1.01
235048AD1-125 C1
Solar/Wind Harmer
4.415
970075AG2-062 GEN
Solar/Wind Harmer
7.852
970801AG2-505 GEN
50/50
5.081
23750701CROSSCHOOL
Solar/Wind Harmer
11.762
238127S14_GEN_2
Solar/Wind Harmer
2.088
202652Y1-033 WT C
Solar/Wind Harmer
0.624
20089026BF_G21_K23
Solar/Wind Harmer
0.319
238117U2-030
Solar/Wind Harmer
3.022
23585401KL_K28_T16
Solar/Wind Harmer
6.188
203955AF1-039 C O1
Solar/Wind Harmer
0.304
238126S14_GEN_1
Solar/Wind Harmer
2.088
23751201ROTHROCK
Solar/Wind Harmer
1.945
20089226LOOKOUT
Solar/Wind Harmer
0.393
20084026DEEPCRK1
50/50
0.068
942731AE2-289 GEN
Solar/Wind Harmer
7.524
944781AF1-143 GEN
Solar/Wind Harmer
1.383
235049AD1-125 C2
Solar/Wind Harmer
4.415
971679AH1-340 GEN
Solar/Wind Harmer
4.469
23750501ELLIOTTS
Solar/Wind Harmer
1.442
238118U2-030_1
Solar/Wind Harmer
1.269
20089126CSLMN_L13
Solar/Wind Harmer
0.403
235054AD2-180 GEN
Solar/Wind Harmer
7.432
238108AE1-109 GEN1
Solar/Wind Harmer
0.395
235531U2-073 GEN
Solar/Wind Harmer
8.009
970995AG2-615 GEN
Solar/Wind Harmer
14.023
23562501BACKB
Solar/Wind Harmer
2.617
23600101WARRIOR RN
50/50
40.004
20084126DEEPCRK2
50/50
0.069
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.52
WECLTFEXP_WEC->PJM
CLTF
0.215
LAGNLTFEXP_LAGN->PJM
CLTF
0.76
CBM West 1LTFEXP_CBM-W1->PJM
CBM
8.46
NYPJM->LTFIMP_NY
CLTF
0.296
TVALTFEXP_TVA->PJM
CLTF
0.374
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.09
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.038
SIGELTFEXP_SIGE->PJM
CLTF
0.028
CBM West 2LTFEXP_CBM-W2->PJM
CBM
6.032
LGEELTFEXP_LGEE->PJM
CLTF
0.375
MECLTFEXP_MEC->PJM
CLTF
0.88

Details for 01CROSSCHOOL-01BLACKO 138.0 kV Ckt 1 line l/o AP_P7-1_PE-138-012A_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
01CROSSCHOOL-01BLACKO 138.0 kV Ckt 1 line
Contingency Name:
AP_P7-1_PE-138-012A_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:108.85 %
Rating:268.0 MVA
Rating Type:B
MVA to Mitigate:291.71
MW Contribution:3.78
Bus #Bus NameTypeMW Contribution
970697AG2-448 GEN
Solar/Wind Harmer
30.17
238185AF2-356 C
Solar/Wind Harmer
24.764
238193AE1-106 GEN
Solar/Wind Harmer
5.332
238120AE2-309 GEN
Solar/Wind Helper
0.282
970075AG2-062 GEN
Solar/Wind Harmer
3.782
970801AG2-505 GEN
50/50
8.818
23750701CROSSCHOOL
Solar/Wind Harmer
20.915
238127S14_GEN_2
Solar/Wind Helper
0.523
238117U2-030
Solar/Wind Harmer
1.139
238126S14_GEN_1
Solar/Wind Helper
0.523
23751201ROTHROCK
Solar/Wind Harmer
1.037
971679AH1-340 GEN
Solar/Wind Harmer
3.672
23750501ELLIOTTS
Solar/Wind Harmer
1.15
238118U2-030_1
Solar/Wind Harmer
0.478
970995AG2-615 GEN
Solar/Wind Harmer
6.058
23562501BACKB
Solar/Wind Harmer
1.261
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.427
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.05
LAGNLTFEXP_LAGN->PJM
CLTF
0.207
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.76
LGEELTFEXP_LGEE->PJM
CLTF
0.119
TVALTFEXP_TVA->PJM
CLTF
0.101
NYPJM->LTFIMP_NY
CLTF
0.096
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.011
SIGELTFEXP_SIGE->PJM
CLTF
0.009
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.786
WECLTFEXP_WEC->PJM
CLTF
0.069
MECLTFEXP_MEC->PJM
CLTF
0.276

Details for 01MTZION-AG2-505 TP 138.0 kV Ckt 1 line l/o AP_P7-1_PE-138-012A_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
01MTZION-AG2-505 TP 138.0 kV Ckt 1 line
Contingency Name:
AP_P7-1_PE-138-012A_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:110.51 %
Rating:206.0 MVA
Rating Type:B
MVA to Mitigate:227.65
MW Contribution:3.79
Bus #Bus NameTypeMW Contribution
238185AF2-356 C
Solar/Wind Harmer
24.766
238193AE1-106 GEN
Solar/Wind Harmer
5.337
238120AE2-309 GEN
Solar/Wind Helper
0.281
970075AG2-062 GEN
Solar/Wind Harmer
3.787
23750701CROSSCHOOL
Solar/Wind Helper
3.048
238127S14_GEN_2
Solar/Wind Helper
0.523
238117U2-030
Solar/Wind Harmer
1.14
238126S14_GEN_1
Solar/Wind Helper
0.523
23751201ROTHROCK
Solar/Wind Harmer
1.038
971679AH1-340 GEN
Solar/Wind Harmer
3.675
23750501ELLIOTTS
Solar/Wind Harmer
1.151
238118U2-030_1
Solar/Wind Harmer
0.478
970995AG2-615 GEN
Solar/Wind Harmer
6.063
23562501BACKB
Solar/Wind Harmer
1.262
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.448
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.047
LAGNLTFEXP_LAGN->PJM
CLTF
0.218
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.84
LGEELTFEXP_LGEE->PJM
CLTF
0.123
TVALTFEXP_TVA->PJM
CLTF
0.106
NYPJM->LTFIMP_NY
CLTF
0.093
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.009
SIGELTFEXP_SIGE->PJM
CLTF
0.009
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.859
WECLTFEXP_WEC->PJM
CLTF
0.071
MECLTFEXP_MEC->PJM
CLTF
0.285

Details for AG2-505 TP-01BERYL 138.0 kV Ckt 1 line l/o AP_P7-1_PE-138-012A_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
AG2-505 TP-01BERYL 138.0 kV Ckt 1 line
Contingency Name:
AP_P7-1_PE-138-012A_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:114.9 %
Rating:206.0 MVA
Rating Type:B
MVA to Mitigate:236.69
MW Contribution:3.79
Bus #Bus NameTypeMW Contribution
238185AF2-356 C
Solar/Wind Harmer
24.766
238193AE1-106 GEN
Solar/Wind Harmer
5.337
238120AE2-309 GEN
Solar/Wind Helper
0.281
970075AG2-062 GEN
Solar/Wind Harmer
3.787
970801AG2-505 GEN
50/50
8.819
23750701CROSSCHOOL
Solar/Wind Helper
3.048
238127S14_GEN_2
Solar/Wind Helper
0.523
238117U2-030
Solar/Wind Harmer
1.14
238126S14_GEN_1
Solar/Wind Helper
0.523
23751201ROTHROCK
Solar/Wind Harmer
1.038
971679AH1-340 GEN
Solar/Wind Harmer
3.675
23750501ELLIOTTS
Solar/Wind Harmer
1.151
238118U2-030_1
Solar/Wind Harmer
0.478
970995AG2-615 GEN
Solar/Wind Harmer
6.063
23562501BACKB
Solar/Wind Harmer
1.262
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.448
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.047
LAGNLTFEXP_LAGN->PJM
CLTF
0.218
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.84
LGEELTFEXP_LGEE->PJM
CLTF
0.123
TVALTFEXP_TVA->PJM
CLTF
0.106
NYPJM->LTFIMP_NY
CLTF
0.093
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.009
SIGELTFEXP_SIGE->PJM
CLTF
0.009
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.859
WECLTFEXP_WEC->PJM
CLTF
0.071
MECLTFEXP_MEC->PJM
CLTF
0.285

Details for AG2-505 TP-01BERYL 138.0 kV Ckt 1 line l/o AP_P2-2_PE-138-066A_SRT-A


Base Case Flowgate

Area:AP
Facility Description:
AG2-505 TP-01BERYL 138.0 kV Ckt 1 line
Contingency Name:
AP_P2-2_PE-138-066A_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:101.6 %
Rating:206.0 MVA
Rating Type:B
MVA to Mitigate:209.3
MW Contribution:3.51
Bus #Bus NameTypeMW Contribution
238185AF2-356 C
Solar/Wind Harmer
24.837
238120AE2-309 GEN
Solar/Wind Helper
0.201
970075AG2-062 GEN
Solar/Wind Harmer
3.506
970801AG2-505 GEN
50/50
8.864
23750701CROSSCHOOL
Solar/Wind Helper
2.997
238127S14_GEN_2
Solar/Wind Helper
0.348
238126S14_GEN_1
Solar/Wind Helper
0.348
23751201ROTHROCK
Solar/Wind Harmer
0.962
971679AH1-340 GEN
Solar/Wind Harmer
3.381
23750501ELLIOTTS
Solar/Wind Harmer
1.054
970995AG2-615 GEN
Solar/Wind Harmer
5.643
23562501BACKB
Solar/Wind Harmer
1.169
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.382
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.04
LAGNLTFEXP_LAGN->PJM
CLTF
0.186
CBM West 1LTFEXP_CBM-W1->PJM
CBM
2.409
LGEELTFEXP_LGEE->PJM
CLTF
0.104
TVALTFEXP_TVA->PJM
CLTF
0.091
NYPJM->LTFIMP_NY
CLTF
0.083
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.007
SIGELTFEXP_SIGE->PJM
CLTF
0.008
CBM West 2LTFEXP_CBM-W2->PJM
CBM
1.584
WECLTFEXP_WEC->PJM
CLTF
0.06
MECLTFEXP_MEC->PJM
CLTF
0.243
CONTINGENCY 'AP_P7-1_PE-138-012A_SRT-A'
 DISCONNECT BRANCH FROM BUS 235468 TO BUS 235504 CKT 1   /*01FROSTB     138.0 - 01RIDGLY     138.0
 DISCONNECT BRANCH FROM BUS 235468 TO BUS 237317 CKT 1   /*01FROSTB     138.0 - 01FINZEL     138.0
 DISCONNECT BUS 235449                                   /*01CARLOS     138.0
END
CONTINGENCY 'AP_P2-2_PE-138-066A_SRT-A'
 DISCONNECT BRANCH FROM BUS 235449 TO BUS 237310 CKT 1   /*01CARLOS     138.0 - 01DANSMTN    138.0
 DISCONNECT BRANCH FROM BUS 235449 TO BUS 970994 CKT 1   /*01CARLOS     138.0 - AG2-615 TP   138.0
 DISCONNECT BRANCH FROM BUS 237366 TO BUS 235449 CKT 1   /*01CARLOS      34.5 - 01CARLOS     138.0
END
CONTINGENCY 'AP_P7-1_WPP-138-011_SRT-A'
 DISCONNECT BRANCH FROM BUS 235143 TO BUS 235255 CKT 1   /*01BETHLB     138.0 - 01NU TP2     138.0
 DISCONNECT BRANCH FROM BUS 235143 TO BUS 235594 CKT 1   /*01BETHLB     138.0 - 01NU TP1     138.0
 DISCONNECT BRANCH FROM BUS 235223 TO BUS 235284 CKT 1   /*01NECEST     138.0 - 01TEX E5     138.0
 DISCONNECT BRANCH FROM BUS 235228 TO BUS 235255 CKT 1   /*01NU 62      138.0 - 01NU TP2     138.0
 DISCONNECT BRANCH FROM BUS 235254 TO BUS 235255 CKT 1   /*01SUNION     138.0 - 01NU TP2     138.0
 DISCONNECT BRANCH FROM BUS 235284 TO BUS 235594 CKT 1   /*01TEX E5     138.0 - 01NU TP1     138.0
 DISCONNECT BRANCH FROM BUS 235594 TO BUS 235595 CKT 1   /*01NU TP1     138.0 - 01NU 61      138.0
END
CONTINGENCY 'AP_P2-3_PE-500-014_SRT-SL'
 DISCONNECT BRANCH FROM BUS 235103 TO BUS 964990 CKT 1          /*01BLACKO     500.0 - AG1-363 TP   500.0
 REDUCE BUS 235103 SHUNT BY 50 PERCENT                          /*01BLACKO     500.0
 SET POSTCONTRATING 2771 BRANCH FROM BUS 235101 TO BUS 235103 CKT 1 /*01BEDNGT     500.0 - 01BLACKO     500.0
 SET PRECONTRATING 2707 BRANCH FROM BUS 235101 TO BUS 235103 CKT 1 /*01BEDNGT     500.0 - 01BLACKO     500.0
END
CONTINGENCY 'AP_P2-3_WP-500-DRT19_SRT-SL'
 OPEN BRANCH FROM BUS 235108 TO BUS 964990 CKT 1                /*01HATFLD     500.0 - AG1-363 TP   500.0
 SET POSTCONTRATING 3260 BRANCH FROM BUS 235108 TO BUS 235109 CKT 1 /*01HATFLD     500.0 - AB1-106 POI  500.0
 SET POSTCONTRATING 3260 BRANCH FROM BUS 235108 TO BUS 235774 CKT 1 /*01HATFLD     500.0 - 01RONCO      500.0
 SET PRECONTRATING 2707 BRANCH FROM BUS 235108 TO BUS 235109 CKT 1 /*01HATFLD     500.0 - AB1-106 POI  500.0
 SET PRECONTRATING 2707 BRANCH FROM BUS 235108 TO BUS 235774 CKT 1 /*01HATFLD     500.0 - 01RONCO      500.0
END
235550 to 237506 ckt 1
235446 to 235103 ckt 3
237506 to 235446 ckt 1
235492 to 970800 ckt 1
970800 to 235550 ckt 1

Winter Peak Analysis

The New Service Request AG2-062 was evaluated as a 147.0 MW (21.609 MW Capacity) injection in the APS area.

AG2-062 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 147.0 MW (147.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Light Load Analysis

The New Service Request AG2-062 was evaluated as a 147.0 MW injection

AG2-062 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 147.0 MW (147.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AD1-125Baker 138 kVSuspended
AD2-180Elk Garden-Parr Run 138kVIn Service
AE1-106Lake Lynn-Hazelton 138 kVSuspended
AE1-109Frenchs Mill 34 kVIn Service
AE2-289Frostburg 138 kVPending
AE2-309Carlos Junction-Lonaconing 34.5 kVIn Service
AF1-039Listonburg-Highpoint 24.9 kVIn Service
AF1-143Lick Run 115 kVEngineering & Procurement
AF2-356Albright-Mt. Zion 138 kVUnder Construction
AG1-363Black Oak-Hatfield 500 kVEngineering & Procurement
AG2-448Cross School - Westvaco 138 kVActive
AG2-505Westvaco - Mt Zion 138 kVActive
AG2-615Carlos Junction-Garrett 138 kVActive
AH1-340Cheat Lake-Ruthbelle 138 kVActive
U2-030Four Mile Ridge Wind 138kVIn Service
U2-073Frostburg 138kV IIIn Service
Y1-033Penn Mar-Rock Wood 115kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement
Type
Load Flow
TO
APS
RTEP ID / TO ID
(Pending) / TC2-PH1-023.a
Title
Upgrade 138 kV Disc Sw 1306_Q at Beryl
Description
Upgrade 138 kV Disc Sw 1306_Q at Beryl
Total Cost ($USD)
$432,790
Allocated Cost ($USD)
$0
Time Estimate
19 Months

Contingent

Note: Based on PJM cost allocation criteria, AG2-062 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-062 could receive cost allocation. Although AG2-062 may not presently have cost responsibility for this upgrade, AG2-062 may need this upgrade in-service to be deliverable to the PJM system. If AG2-062 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
01BERYL-01CROSSCHOOL 138.0 kV Ckt 1 line(Any)

System Reinforcement
Type
Load Flow
TO
APS
RTEP ID / TO ID
(Pending) / TC2-APS-002.a
Title
Upgrade Disc Switch at Beryl
Description
Upgrade (1) 138 kV Disc Switch at Beryl
Total Cost ($USD)
$432,791
Allocated Cost ($USD)
$0
Time Estimate
21 Months

Contingent

Note: Based on PJM cost allocation criteria, AG2-062 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-062 could receive cost allocation. Although AG2-062 may not presently have cost responsibility for this upgrade, AG2-062 may need this upgrade in-service to be deliverable to the PJM system. If AG2-062 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
01BERYL-AG2-505 TP 138.0 kV Ckt 1 line(Any)

System Reinforcement: s3713.1
Type
Load Flow
TO
APS
RTEP ID / TO ID
s3713.1 / APS-2025-018
Title
Terminal Equipment Upgrades at Black Oak & Cross School - Misoperation Relay Project (Supplemental - Projected ISD 12/31/2026)
Description
- At Black Oak, replace circuit breakers, disconnect switches, line trap, CCVT and line relaying. - At Cross School, replace line trap and line relaying. Presented at Jul 2025 SRRTEP: https://www.pjm.com/-/media/DotCom/committees-groups/committees/srrtep-w/2025/20250718/20250718-item-02---aps-supplemental-projects.pdf
Cost Information
Time Estimate
Dec 31 2026

Contingent

Note: Although AG2-062 may not presently have cost responsibility for this upgrade, AG2-062 may need this upgrade in-service to be deliverable to the PJM system. If AG2-062 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
01BLACKO-01CROSSCHOOL 138.0 kV Ckt 1 line(Any)

System Reinforcement
Type
Load Flow
TO
APS
RTEP ID / TO ID
(Pending) / TC2-APS-019.a
Title
Reconductor (Possible Rebuild) 8.6 miles of Black Oak - Cross School transmission line
Description
Reconductor (Possible Rebuild) 8.6 miles of Black Oak - Cross School transmission line
Total Cost ($USD)
$31,323,166
Allocated Cost ($USD)
$0
Time Estimate
41 Months

Contingent

Note: Based on PJM cost allocation criteria, AG2-062 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-062 could receive cost allocation. Although AG2-062 may not presently have cost responsibility for this upgrade, AG2-062 may need this upgrade in-service to be deliverable to the PJM system. If AG2-062 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
01BLACKO-01CROSSCHOOL 138.0 kV Ckt 1 line(Any)

System Reinforcement: b4000.11
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.11
Title
Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)
Description
Expand Black Oak Substation to accommodate the connection of the 502 Jct-Woodside 500 kV line and loop the 502 Jct-Woodside 500 kV line into the Black Oak substation by constructing ~0.85 miles of new 500 kV line into and out of Black Oak 500 kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AG2-062 may not presently have cost responsibility for this upgrade, AG2-062 may need this upgrade in-service to be deliverable to the PJM system. If AG2-062 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
01BLACKO-01BLACKO 500.0/138.0 kV Ckt 3 transformer(Any)

System Reinforcement
Type
Load Flow
TO
APS
RTEP ID / TO ID
(Pending) / TC2-APS-028
Title
Reconductor Mt Zion - AG2-505 138kV transmission line
Description
Reconductor (Possible Rebuild) ~2.8 miles of Mt Zion - AG2-505 138kV transmission line
Total Cost ($USD)
$12,297,524
Allocated Cost ($USD)
$0
Time Estimate
18 Months

Contingent

Note: Based on PJM cost allocation criteria, AG2-062 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-062 could receive cost allocation. Although AG2-062 may not presently have cost responsibility for this upgrade, AG2-062 may need this upgrade in-service to be deliverable to the PJM system. If AG2-062 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
01MTZION-AG2-505 TP 138.0 kV Ckt 1 line(Any)

Attachments

AG2-062 One Line Diagram

AG2-062 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.